Subdivision and Development Servicing Bylaw No. 4353, 2017 (Consolidated)

Dawson Creek, British Columbia · adopted 2017-07-17

This is the exact embedded text of the captured official document. Snapshot b6a8f1bc634c · verified 2026-08-23 · original document · archived snapshot · unofficial consolidation, the official version is held by the municipal clerk.

CONSOLIDATED VERSION CITY OF DAWSON CREEK SUBDIVISION AND DEVELOPMENT SERVICING BYLAW NO. 4353, 2017 CONSOLIDATED FOR CONVENIENCE ONLY This is a consolidation of the parent bylaw and the bylaws listed below. Amendments have been incorporated with the parent bylaw for convenience only. This consolidation is not a legal document. Certified copies of the original bylaws should be consulted for all interpretations and applications of the subject bylaw. Amendment Bylaw 4491, 2021 City of Dawson Creek Subdivision and Development Servicing Bylaw TABLE OF CONTENTS PART 1 REPEAL ....................................................................................................................... 1 PART 2 CITATION ................................................................................................................... 1 PART 3 ADMINISTRATION ...................................................................................................... 1 PART 4 INTERPRETATION ...................................................................................................... 2 PART 5 CONNECTION TO COMMUNITY SYSTEMS .................................................................. 4 PART 6 SERVICING REQUIREMENTS FOR SUBDIVISIONS AND DEVELOPMENTS ................. 5 PART 7 FEES AND SECURITY .................................................................................................. 8 PART 8 GENERAL PROVISIONS ............................................................................................10 PART 9 ENFORCEMENT .........................................................................................................11 PART 10 EFFECTIVE DATE .......................................................................................................12 SCHEDULES SCHEDULE A WORKS AND SERVICES REQUIREMENTS SCHEDULE B WATER DISTRIBUTION SCHEDULE C SANITARY SEWER SCHEDULE D STORMWATER SCHEDULE E ROADS SCHEDULE F STREET LIGHTING SCHEDULE G LANDSCAPING SCHEDULE H SITE GRADING SCHEDULE I QUALITY CONTROL SCHEDULE J STANDARDS FOR SUBMISSION BY DEVELOPER SCHEDULE K SUPPLEMENTARY DETAIL DRAWINGS 1 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw CITY OF DAWSON CREEK SUBDIVISION AND DEVELOPMENT SERVICING BYLAW NO. 4353, 2017 A bylaw to regulate and require the provision of services in respect of subdivision and development within the City of Dawson Creek. WHEREAS pursuant to the Local Government Act, a local government may, by bylaw, regulate and require the provision of works and services in respect of the subdivision and development of land. NOW THEREFORE the Council of the City of Dawson Creek, in open meeting assembled, HEREBY ENACTS as follows: PART 1 REPEAL 1.1 Subdivision and Development Servicing Bylaw No. 4176, 2013 and all of its amendments are hereby repealed. PART 2 CITATION 2.1 This Bylaw may be cited for all purposes as "Subdivision and Development Servicing Bylaw No. 4353, 2017". PART 3 ADMINISTRATION Application 3.1 This bylaw applies to all land within the boundaries of the City of Dawson Creek. 3.2 Schedules A-K, attached hereto, form an integral part of this bylaw. Minimum Parcel Highway Frontage 3.3 Council hereby delegates to the Approving Officer the power to exempt a Parcel from the statutory or bylaw minimum frontage provided for in the Local Government Act. Standards of Measure 3.4 Any equivalent imperial units of measure shown, in parentheses, after metric units in any schedule to this bylaw are for information purposes only and do not form part of this bylaw. 2 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Severance 3.5 If any section, subsection, sentence, clause or phrase of this bylaw is for any reason held to be invalid by the decision of any court of competent jurisdiction, the invalid portion must be severed and the decision that it is invalid does not affect the validity of the remainder of this bylaw. Master Municipal Construction Document (MMCD) 3.6 All Works and Services must be completed in accordance with the current Master Municipal Construction Document (MMCD), Volume II, along with this bylaw. Where there are conflicts between this bylaw and the MMCD, this bylaw takes precedence. Approved Products 3.7 Materials used for Works and Services must be those listed in the City of Dawson Creek Approved Products List, as amended from time to time, unless otherwise approved by the Director of Development Services. PART 4 INTERPRETATION 4.1 Definitions All-Weather Vehicle Access has the meaning of a Temporary Road. Approved Design means the detailed drawings and specifications for Works and Services prepared on behalf of the Owner and accepted by the Director of Development Services. Approving Officer means the person appointed by Council as such under the Land Title Act. Asbuilt Security means an amount equal to fifteen percent (15%) of the total cost of the Works and Services as originally estimated by the Professional Engineer, and as approved by the Director of Development Services in the form of cash or an irrevocable and unconditional letter of credit in a form acceptable to the Director of Development Services. Certificate of Provisional Completion of All Works means a certificate issued by the Owner's Professional Engineer stating that: 3 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw a) Works and Services are ready to be used for their intended purpose; b) The total cost of addressing incomplete, defective and deficient Works and Services, as estimated by the Professional Engineer and verified by the City, is not more than 2% of the total cost of the Works and Services; and c) Fire protection has been approved to the satisfaction of the Fire Chief. A description of the Works and Services that remain to be completed must be included as part of this certificate. Certificate of Provisional Completion of Deep Utilities means a certificate issued by the Owner's Professional Engineer stating that deep utility Works and Services including water, sanitary sewer, and storm sewer mains, are ready to be used for their intended purpose. City means the City of Dawson Creek. Community Drainage System means a community drainage system operated by or on behalf of the City. Community Sewer System means a community sanitary sewage collection system operated by or on behalf of the City. Community Water System means a community water supply system operated by or on behalf of the City. Council means the Municipal Council of the City. Development means any construction to which the Building Regulation Bylaw applies. Director of Development Services means the person appointed as such by Council, or successor in function. Excess or Extended Services has the same meaning as under the Local Government Act. Professional Geotechnical Engineer means a person who is registered or duly licensed as a Professional Engineer in British Columbia under the provisions of the Engineers and Geoscientists Act with expertise in the field of geotechnical engineering. Highway has the same meaning as under the Community Charter. Owner has the same meaning under the Community Charter. 4 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Parcel has the same meaning as under the Community Charter. Performance Security means an amount, as approved by the Director of Development Services, in the form of cash or an irrevocable and unconditional letter of credit in a form acceptable to the Director of Development Services, given to the City when the Owner would like to obtain Subdivision approval or a building permit prior to the installation of on-site and off-site Works and Services. Professional Engineer means a person who is registered or duly licensed as a Professional Engineer in British Columbia under the provisions of the Engineers and Geoscientists Act. Subdivision means and includes a Subdivision as defined in the Land Title Act and a Subdivision under the Strata Property Act. Sustainable Neighbourhood - Special Policy Area means the area as shown in Figure 1 of Schedule A - Works and Services Requirements that is designated to be developed as a sustainable and environmentally- friendly neighbourhood, as outlined in the City of Dawson Creek's Official Community Plan. Temporary Road means a road as required in Schedule E - Roads with the exception of any permanent surfacing such as asphalt. Warranty Security means the security to be provided under Section 7.5.f, which shall be in the form of cash or an irrevocable and unconditional letter of credit in a form acceptable to the Director of Development Services. Works and Services means Works and Services that may be required under this bylaw, including but are not limited to: highways, curbs, gutters, sidewalks, boulevards, boulevard crossings, transit bays, street lighting, underground wiring, overhead wiring, water distribution systems, fire hydrant systems, sewage collection systems, sewage disposal systems, drainage collection systems, drainage disposal systems, and natural gas, power, telephone, and cable services. Works and Services Agreement means a written agreement between the City and the Owner for the provision of Works and Services under this bylaw. PART 5 CONNECTION TO COMMUNITY SYSTEMS Community Water System 5.1 All water distribution systems and fire hydrant systems in those areas identified in Schedule A must be connected, in accordance with the standards established under this bylaw, to the Community Water System. 5 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 5.2 Prior to connecting a water distribution systems to the Community Water System, existing water sources providing water to Parcels to be serviced by the Community Water System must be abandoned in such a way as to prevent cross-connection with the Community Water System, in accordance with applicable City bylaws requirements. Community Sewer System 5.3 All sanitary sewage collection systems and sewage disposal systems in those areas identified in Schedule A must be connected, in accordance with the standards established under this bylaw, to the Community Sewer System. Community Drainage System 5.4 All drainage collection systems and drainage disposal systems in those areas identified in Schedule A must be connected, in accordance with the standards established under this bylaw, to the Community Drainage System. PART 6 SERVICING REQUIREMENTS FOR SUBDIVISIONS AND DEVELOPMENTS Works and Services within a Subdivision 6.1 The Owner of every Parcel being Subdivided must, as a condition of approval of the Subdivision by the Approving Officer, provide Works and Services within the Subdivision in accordance with the standards established in this bylaw. 6.2 The requirements under Section 6.1 do not apply in respect of a Subdivision under the Strata Property Act. Works and Services up to the Centre Line of Adjacent Highways 6.3 The Owner of every Parcel being Subdivided or developed must, as a condition of the approval of a Subdivision by the Approving Officer or the issuance of a building permit by the City, provide Works and Services, in accordance with the standards established in this bylaw, on that portion of every Highway immediately adjacent to the Parcel being Subdivided or developed up to the centre line of the Highway and Council hereby delegates to the Director of Development Services the power to impose such requirements in respect of a Parcel being Subdivided or developed. Works and Services on Site to be Developed 6.4 The Owner of every Parcel being developed must, as a condition of issuance of a building permit by the City, provide Works and Services on the site being developed, in accordance with the standards established under this bylaw and Council hereby delegates to the Director of Development Services the power to impose such requirements in respect of a Parcel being developed. 6 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Excess and Extended Services 6.5 Council hereby delegates to the Director of Development Services the power under the Local Government Act to: a) require Excess or Extended Services in accordance with the Local Government Act. b) determine whether the cost to the City of an Excess or Extended Service is excessive such that the Owner of the Parcel being Subdivided or developed must pay such costs; c) determine the proportion of the cost of providing the Works and Services that constitutes an Excess or Extended Service; d) identify the Parcels that will be served by an Excess or Extended Service; e) determine which part of the Excess or Extended Service will benefit each of the Parcels that will be served by an Excess or Extended Service; and f) enter into an agreement with the Owner of the Parcel being Subdivided or developed to establish the period during which charges may be collected in accordance with the Local Government Act. 6.6 Latecomer charges imposed by the City under the Local Government Act must include interest calculated annually at a rate established by the City by bylaw. Works and Services and Standards 6.7 All Works and Services to be provided under this bylaw must be provided in accordance with and to the standards set out in the Schedules to this bylaw. Timing of Completion of Works and Services 6.8 Every Owner of a Parcel being Subdivided or developed must, at the Owner's expense, complete the construction and installation all Works and Services required to be provided by the Owner under this bylaw or by the Director of Development Services before the Approving Officer approves of the Subdivision or the City issues the building permit for the Development. 6.9 For the purposes of Section 6.8, the construction and installation of Works and Services are not considered to be complete until and unless the Director of Development Services has issued a Certification of Provisional Completion for all of the Works and Services required to be constructed and installed with respect to the Subdivision or Development. 7 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 6.10 Notwithstanding Section 6.9, a Subdivision approval may be given or the building permit may be issued if the Owner of the Parcel being Subdivided or Developed: a) deposits with the City security in an amount equal to 125% of the cost of the required Works and Services, as estimated by a Professional Engineer and approved by the Director of Development Services pursuant to Section 7.6, in the form of cash or an irrevocable and unconditional letter of credit in a form acceptable to the Director of Development Services; b) enters into an agreement with the City to construct and install the required Works and Services by a specified date or forfeit to the District the security provided under paragraph (a) of this section; and c) detailed drawings and specifications for the required Works and Services have been prepared in accordance with Section 6.12 and approved by the Director of Development Services in accordance with that section and the Owner has satisfied the other requirements of that section. 6.11 The Director of Development Services is hereby delegated the power to enter into agreements on behalf of the City under Section 6.10.b on such terms and conditions as may be determined by the Director of Development Services. Design of Works and Services 6.12 Prior to commencing the construction and installation of any required Works or Services, the Owner of a Parcel being Subdivided or Developed must cause a Professional Engineer and a Professional Geotechnical Engineer to prepare, under seal, detailed drawings and specifications for all Works and Services required under this bylaw or by the Director of Development Services with respect to the Subdivision or Development and an estimate of the cost to construct and install such Works and Services and the Owner must submit such drawings and specifications and cost estimate to the Director of Development Services for approval and the Owner must cause such drawings and specifications and cost estimate to be revised as may be necessary in order to obtain the approval of the Director of Development Services. Without limiting the foregoing, the Owner must cause such drawings and specification to be prepared in accordance with the requirements of the Schedules to this bylaw and to be submitted to the Director of Development Services accompanied by the following: a) a letter from the Owner confirming the relationship between the Owner and the Professional Engineer; 8 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw b) a letter from the Professional Engineer confirming their engagement by the Owner and that they will be providing professional services to the Owner to ensure that the Works and Services are designed and constructed in accordance with this bylaw and the detailed drawings and specification; and c) if the required Works and Services include a water supply system, a permission to construct such system from the regional health authority. Exemptions 6.13 The requirements under Section 6.1 do not apply if: a) The Subdivision creates only natural areas; b) The Subdivision or Development creates a Parcel for the installation of utilities and related structures and equipment; and c) A covenant restricting the use of the Parcel to one of those uses has been registered on title under the Land Title Act in favour of the City. PART 7 FEES AND SECURITY Application Fees 7.1 An Owner applying for subdivision approval or a building permit must submit with the application the fees set out in the City of Dawson Creek Fees and Charges Bylaw as amended or replaced from time to time. Inspection Fees 7.2 An Owner, prior to making application for final approval of a Subdivision or a building permit must submit with the application the following fees: a) Charges for inspection of Works and Services in the amount equal to one percent (1%) of the Owner's Professional Engineer's cost estimate for constructing Works and Services required by the new Subdivision or Development, or actual City cost, whichever is greater. The Goods and Services Tax (GST) must be additional to the inspection charges. The Owner's Professional Engineer's estimate must include the GST. Performance Security Confirmation 7.3 The City may, at the Owner's expense, confirm the cost estimate of the Works and Services by consulting with a Professional Engineer chosen by the City. The Director of Development Services may choose which estimate to use. 9 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 7.4 If the required Works and Services have not been completely installed in accordance with the approved design drawings within the time specified in the Works and Services Agreement, the City may draw on the Performance Security in order to complete the required Works and Services. If the cost of installation exceeds the amount of the Performance Security, the balance must be a debt due from the Owner to the City, recoverable in any court of competent jurisdiction or by any other means available to the City. Provisional Completion of All Works 7.5 Notwithstanding Section 6.9, a Subdivision approval may be given or the building permit may be issued if the City has received the following from the Owner: a) A statutory declaration confirming that all Works and Services completed to date have been paid for in full; b) A Certificate of Provisional Completion of All Works, issued by the Owner's Professional Engineer, together with the supporting documentation upon which it is based, including relevant:  Quality assurance test results signed and sealed by a Professional Geotechnical Engineer; and  Inspection reports; c) Record drawings of all Works and Services, prepared by the Owner's Professional Engineer or Asbuilt Security in lieu of record drawings; d) A list of defects and deficiencies in the work, as identified during an inspection of the Works and Services with the City, together with a cost estimate sealed by the Owner's Professional Engineer of the cost required to rectify these defects and deficiencies. If record drawings are not provided at this point, they must be considered as a deficiency to be rectified; e) Receipt of a schedule of quantities and prices of completed work to date, prepared by the Owner's Professional Engineer; and f) Warranty Security, as set out in Section 7.6; And the Director of Development Services confirms in writing that he or she has received the items to be provided under this section and is satisfied with the validity of the Certificate of Provisional Completion of All Works and with the list of defects and deficiencies. 10 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Warranty Security 7.6 Pursuant to Section 7.5.f the Owner must provide to the City Warranty Security in an amount equal to ten percent (10%) of the cost estimate for the Works and Services accepted under Section 6.12 plus two times the estimated value of defects and deficiencies remaining to be rectified. 7.7 If the Owner fails to repair or replace any defect in the Works identified before or during the three year period commencing on the date of Provisional Completion of All Warranty Period or any failure of the Works to operate normally during that period, the City may repair or replace any defective work and may deduct from the Warranty Security the City's costs of doing so and the amount of any resulting damages suffered by the City as a result of such defect. 7.8 The Owner is responsible for the actual cost of repairing or replacing any defective Works and Services and correcting any deficiencies in the Works and Services regardless of the adequacy of the Warranty Security deposited with the City. If the cost of repairing or replacing any defective Works and Services and correcting any deficiencies exceeds the amount of the Warranty Security, the balance will be a debt due from the Owner to the City, recoverable in any court of competent jurisdiction or by any other means available to the City. 7.9 Following completion of the three year period and the repair or replacement of all defects to the satisfaction of the Director of Development Services, the City will return any unused portions of the Warranty Security to the Owner. PART 8 GENERAL PROVISIONS Owner's Expense 8.1 An Owner who is subject to any of the requirements and regulations under this bylaw is responsible for all costs of complying with such requirements and regulations, including all costs of designing, constructing and install all Works and Services required to be provided by the Owner under this bylaw and all the costs of retaining a Professional Engineer as and when required under this bylaw. Professional Engineer 8.2 Where the services of a Professional Engineer or Professional Geotechnical Engineer are required in connection with any provision of this bylaw, the Owner of the Parcel being subdivided or developed must, at its expense, engage the qualified Professional Engineer or Professional Geotechnical Engineer for the required purposes. 11 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Cost of Services 8.3 All Works and Services required by this bylaw must be designed, reviewed, constructed and inspected at the expense of the Owner. Project Supervision and Certification 8.4 Within thirty (30) days of the Works and Services being operational, the Owner's Professional Engineer must submit a report to the City in a format acceptable to the City and prior to the commencement of the warranty period. The report must briefly describe the work and any material changes during construction and certify that the Works and Services have been constructed in compliance with this bylaw and the approved plans, drawings and supporting documents. The report must contain copies of all inspection reports and test results upon which the certification is based. Statutory Rights-of-Way 8.5 All Works and Services required by this bylaw must be located in highways, unless the Director of Development Services has approved the location of the Works and Services in an area that will be within a statutory right-of-way in favour of the City under the Land Title Act. Where the Director of Development Services permits the location of Works and Services within a statutory right of way area, the Owner providing such Works and Services must, at its expense, cause a statutory right of way in favour of the City together with a statutory right of way plan, to be prepared in a form and on terms determined by the Director of Development Services, and must cause the statutory right of way to be registered and the right of way plan deposited with the Land Title Office, with priority over all financial liens, charges and encumbrances, including any leases, rights of first refusal or options to purchase, prior to the commencement of the construction and installation of such Works and Services. Third Party Review 8.6 Where the review of any document, report or analysis related to servicing that the Owner has submitted to the City is required, at the sole discretion of the Approving Officer, the City may engage a third party Professional Engineer chosen by the City to review the document, report or analysis. The Owner may be responsible for the full costs of any required third party review. Subdivision approval may not be granted until these costs are paid by the Owner. PART 9 ENFORCEMENT 9.1 Any person designated as a Bylaw Enforcement Officer pursuant to the City of Dawson Creek's Bylaw Enforcement Notice Bylaw or Dawson Creek's Municipal Ticket Information Bylaw is hereby authorized and empowered to enforce the provisions of this Bylaw by the Bylaw Notice Enforcement Bylaw No. 4277, 2016 as amended from time to time, or by the Municipal Ticket Information System Bylaw No. 4278, 2016 as amended from time to time. 12 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 9.2 No person shall do any act or suffer or permit and act to be done in contravention of this bylaw. 9.3 No person shall obstruct or impede a Bylaw Enforcement Officer in lawful performance on any property, at all reasonable times, in order to ascertain whether such regulations are being observed. 9.4 Each day that an offence against this bylaw continues shall be deemed a separate and distinct offence. 9.5 A person who contravenes any provision of this bylaw is liable to a fine of not more than $10,000.00 and not less than $100.00 for each offence. 9.6 Any penalty imposed pursuant to this bylaw shall be in addition to, and not in substitute for, any other penalty or remedy imposed pursuant to any other applicable statue, law, or legislation. PART 10 EFFECTIVE DATE 10.1 This bylaw comes into full force and effect upon its adoption. READ a first time this 26th day of June , 2017. READ a second time this 26th day of June , 2017. READ a third time this 26th day of June , 2017. ADOPTED this 17th day of July , 2017. CERTIFIED A TRUE AND CORRECT COPY of Bylaw No. 4353 cited as "SUBDIVISION AND SERVICING BYLAW NO. 4353, 2017". The Corporate Seal of THE CORPORATION OF THE CITY OF DAWSON CREEK was affixed in the presence of: ORIGINAL SIGNED BY ORIGINAL SIGNED BY Brenda Ginter Director of Corporate Administration Dale Bumstead - Mayor ORIGINAL SIGNED BY Brenda Ginter - Director of Corporate Administration City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULES City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE A WORKS AND SERVICES REQUIREMENTS Schedule A - Works and Services Requirements 1 of 3 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE A - WORKS AND SERVICES REQUIREMENTS 1.0 Works and Services Requirements ........................................................................................... 2 1.1 Establishment of Service Levels .............................................................................................. 2 1.2 Sustainable Neighbourhood ................................................................................................... 3 1.3 Accessibility ....................................................................................................................... 3 List of Tables Table A1 - Level of Service Schedule A - Works and Services Requirements 2 of 3 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 WORKS AND SERVICES REQUIREMENTS 1.1 Establishment of Service Levels The minimum level of Works and Services to be constructed by an Owner prior to approval of Subdivision or Development is set out in Table A1 and Figure 1. While Table A1 sets out the minimum level of Works and Services required, the Director of Development Services retains the right to require a higher level of Works and Services or standard due to the conditions affecting a specific Subdivision or Development. Table A1 - Level of Service Service Level of Service Urban Subdivision Rural Subdivision Sustainable Neighbourhood For Parcels identified as Urban in Figure 1 For Industrial Parcels identified as Rural in Figure 1 Parcels within the area identified in Figure 1 Roads Urban Roads Rural Roads Alternate Urban Roads Sewer Community Sewer System Community Sewer System Community Sewer System Water Community Water System Community Water System Community Water System Drainage Community Drainage System Ditch Alternate Community Drainage System Wiring Underground Overhead Underground Lighting Thru Subdivision Thru Subdivision Thru Subdivision Landscaping Public N/A Public For the purposes of Table A1:  Urban Subdivision means a Subdivision or Development where the Parcels have been identified as Urban in Figure 1.  Rural Subdivision means an Industrial Subdivision or Development where the Parcels have been identified as Rural in Figure 1.  Sustainable Neighbourhood means a Subdivision or Development where the Parcels are part of the Special Policy Area as shown in Figure 1 and the City's Official Community Plan Land Use Map.  Urban Roads means roads that meet the requirements for urban roads as set out in Schedule A - Works and Services Requirements 3 of 3 City of Dawson Creek Subdivision and Development Servicing Bylaw Schedule E - Roads.  Rural Roads means roads that meet the requirements for rural roads as set out in Schedule E - Roads.  Alternate Urban Roads means roads that meet the requirements for Alternate Urban Roads as set out in Schedule E - Roads.  Ditch means a drainage collection and disposal system of open ditches and culverts.  Alternate Community Drainage System means a community drainage system that meets the requirements outlined in Schedule D - Stormwater.  Underground means a system of underground electrical and communications wiring.  Overhead means a system of overhead electrical and communications wiring.  Thru Subdivision means street lighting that is provided throughout the Subdivision (rather than only at intersections).  Public means landscaping required on public lands as set out in Schedule G - Landscaping. 1.2 Sustainable Neighbourhood - Special Policy Area Servicing requirements for any Subdivisions or Developments in this area must conform to Table A1. 1.3 Accessibility The Owner's Professional Engineer must consider the accessibility of people with disabilities when designing all roads, sidewalks, pathways, curb let downs and driveway crossings. CITY OF DAWSON CREEK LEVEL OF SERVICE AREAS 1 FIGURE ° 1:40,000 Legend Municipal Boundary Level of Service Rural Urban Sustainable Neighbourhood - Special Policy Area Parcels Alaska Avenue 8th Street Highway 2 Highway 97 Highway 97 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE B WATER DISTRIBUTION Schedule B - Water Distribution 1 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE B - WATER DISTRIBUTION 1.0 WATER DISTRIBUTION .......................................................................................................... 2 1.1 Water Distribution ............................................................................................................... 2 1.2 Per Capita Demand .............................................................................................................. 2 1.3 Non-Residential Demand ...................................................................................................... 2 1.4 Fire Flows .......................................................................................................................... 5 1.5 Design Flows ...................................................................................................................... 5 1.6 Water Pressure ................................................................................................................... 5 1.7 Hydraulic Design ................................................................................................................. 6 1.8 Minimum Pipe Diameter ....................................................................................................... 6 1.9 Dead Ends .......................................................................................................................... 6 1.10 Minimum Depth of Cover ...................................................................................................... 7 1.11 Grade ............................................................................................................................... 7 1.12 Corrosion Protection ............................................................................................................ 7 1.13 Valves ............................................................................................................................... 8 1.14 Hydrants ............................................................................................................................ 8 1.15 Air Valves ........................................................................................................................... 8 1.16 Thrust Restraint .................................................................................................................. 9 1.17 Chambers ........................................................................................................................ 10 1.18 Service Connections ........................................................................................................... 10 1.19 Utility Separation .............................................................................................................. 10 1.20 Alignment ........................................................................................................................ 11 1.21 Rights-Of-Way (R.O.W.) ...................................................................................................... 11 1.22 Connection to Existing Watermains ....................................................................................... 12 1.23 Testing and Disinfection ...................................................................................................... 12 List of Tables Table B1: Population/Hectares per Land Use Table B2: Average Annual Daily Water Demands Table B3: Minimum Fire Flow Requirements Table B4: Water Pressure Table B5: Minimum Pipe Diameter Table B6: Air Valve Sizing Schedule B - Water Distribution 2 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 WATER DISTRIBUTION 1.1 Water Distribution Water distribution systems must be designed in accordance with the requirements of this bylaw, and must be constructed in accordance with the appropriate American Water Works Association (AWWA) standards. Drawings completed by a Professional Engineer showing all works to be constructed must be submitted to the Director of Development Services for approval prior to construction. No construction will be allowed prior to obtaining approval from the Director of Development Services. The Owner must submit an approved Water Works Construction Permit from the Northern Health Authority (Public Health Authority) to the Director of Development Services prior to construction. 1.2 Per Capita Demand To determine the required water demand for residential areas, use the following per capita demands and population densities:  (ADD) Average Annual Daily Demand (A): 600 litres per capita per day (L/c/d)  (MDD) Maximum Day Demand (D): 1,200 litres per capita per day (L/c/d)  (PHD) Peak Hour Demand (H): 1,800 litres per capita per day (L/c/d) Population densities:  Single Family = 3 persons/unit  Multi Family = 2 persons/unit 1.3 Non-Residential Demand Commercial, industrial and institutional demands should be determined using specific data related to the specific zoning designation of the property. In the absence of such data, use the residential per capita demands as listed in Section 1.2 - Per Capita Demand and the equivalent population values listed in Table B1 with the following factors: Schedule B - Water Distribution 3 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Average Daily Demand (A): Values listed in Table B1 Max Daily Demand (D): D = 2.0 x A Peak Hour Demand (H): H = 1.5 x D Table B1: Population/Hectares per Land Use Land Use Equivalent Population/Hectare (gross) Commercial: 90 people/ha Institutional: 50 people/ha Industrial: 90 people/ha For identified commercial and institutional facilities, (A), the average annual daily water demands must be as per Table B2. Schedule B - Water Distribution 4 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw Table B2: Average Annual Daily Water Demands Facility Unit Typical Average Annual Daily Water Demand L/(person or unit)/d Assembly hall Seat 8 Automobile dealer/renter Hectare 30,000 Automobile service station Set of pumps 2,000 Car wash Vehicle served 5,000 Bed and breakfast Patron 150 Bowling alley Lane 800 Camp: Children's, central toilet & bath Person 180 Day, no meals Person 50 Campground Site 600 Curling club Lane 8,500 Golf course Hectare 1,500 Greenhouse Hectare 27,000 Hospital Bed 1,000 Hotel Patron 300 Ice arena Rink 85,000 Motel Patron 500 Office Employee 50 Picnic park, with flush toilets Visitor 30 Restaurant: Conventional Seat 150 24 hour Seat 200 Tavern Seat 80 School: Day, with cafeteria or lunchroom Student 60 Day, with cafeteria & showers Student 70 Boarding Student 400 Self-service laundry Machine 2,000 Schedule B - Water Distribution 5 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.4 Fire Flows Fire flows are determined in accordance with the requirements of the current edition of "Water Supply for Public Fire Protection - A Guide to Recommended Practice", published by Fire Underwriters Survey. Fire flows are subject to minimum requirements as summarized in Table B3. Where it is not feasible to achieve these fire flows, the Director of Development Services may accept lower requirements. Table B3: Minimum Fire Flow Requirements Developments (without sprinklers) Minimum Fire Flow Single Family Residential 60 L/s Apartments, Townhouses, Duplex, Mobile Home Park 90 L/s Commercial 150 L/s Institutional 150 L/s Industrial 225 L/s 1.5 Design Flows Total design flows (Qdesign) are to be the greater of the following: Qdesign = D+F Maximum Day Demand for the population or equivalent population plus the Fire Flow, or Qdesign = H Peak Hour Demand for the population or equivalent population 1.6 Water Pressure Table B4: Water Pressure Maximum allowable pressure 850 kPa (123.3 psi) Minimum pressure at Peak Hour Demand (H) 300 kPa (43.5 psi) Minimum pressure in system during design Maximum Day and Fire Flow Demand (D+F) 150 kPa (21.8 psi) Determination of pressure limits should include consideration of property elevations relative to street level. Schedule B - Water Distribution 6 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.7 Hydraulic Design For hydraulic design, the following parameters are established:  Use a proven network analysis computer model based on the Hazen-Williams formula: Q = CD2.63S0.54 Where: Q = Rate of flow in L/s 278780 D = Internal pipe diameter in mm S = Slope of hydraulic grade line in m/m C = Roughness coefficient = 130 for all pipes  The maximum allowable design velocity under fire flow conditions should be 4.0 m/s. At Peak Hour Demand the maximum flow velocity should be 2.0 m/s. 1.8 Minimum Pipe Diameter Table B5: Minimum Pipe Diameter Distribution mains:  Residential  Commercial, Industrial 150 mm 200 mm Fire hydrant connections: 150 mm Residential service connections: 19 mm Duplex service before wye: 25 mm Duplex service after wye: 19 mm Commercial service connections: 50 mm Industrial service connections: 50 mm Service with fire sprinklers: 50 mm* *May be reduced if Professional Engineer through modeling confirms acceptability of a smaller service. 1.9 Dead Ends Watermains must be looped wherever possible. Where dead ends are unavoidable hydrants may be used as blow-offs. Schedule B - Water Distribution 7 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.10 Minimum Depth of Cover Depth of cover is be determined as the distance from finished ground surface to top of pipe. Watermains and services must be of sufficient depth to:  Prevent freezing  Clear other underground utilities  Provide mechanical protection from external loads  Clear other underground utilities The minimum depth of cover is 2.75 metres. In cases where minimum depths cannot be attained, the Owner must provide special consideration for frost and mechanical protection, which must be approved by the Director of Development Services, for example at bridge crossings and in chambers. The City may accept watermains with less than 2.75 meters cover providing that the Owner's Professional Engineer has designed insulation adequate to prevent watermain freezing. 1.11 Grade Grades must be straight lines between defined deflection points. Elevations must be recorded. The minimum grade of watermains must be 0.1%, unless approved otherwise by the Director of Development Services. Grading must be designed to minimize the number of high points. When the slope equals or exceeds 10%, the Owner must provide anchorage, joint restraints, trench dams and trench drainage. The Director of Development Services may require a geotechnical engineering report where appropriate. 1.12 Corrosion Protection Each metal fitting must be provided with corrosion protection as shown in the Supplementary Detail Drawings. Metal fittings must be epoxy coated and attached with a 7.7 kg magnesium anode. Anodes must be embedded into trench wall, at pipe depth, with a minimum of 50 mm of native soil completely surrounding the anode. Anodes must be attached to fittings by fusing methods. Schedule B - Water Distribution 8 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw If epoxy coating is chipped, use touch up epoxy paint to repair the damage. Denso tape must not be used on bolts, fittings, or hydrant barrel unless gaps are smoothed out with mastic to prevent any air or water from sitting in gaps. Hydrant barrel and boot to each have their own anode. 1.13 Valves In general, valves should be located as follows:  In intersections either in a cluster at the pipe intersection or at projected property lines to avoid conflicts with curbs and sidewalks:  3 valves at "X" intersection  2 valves at "T" intersection  Not more than 300 m apart  Not more than 1 hydrant isolated  Not more than 20 service connections isolated Gate valves are required on all mains up to 300 mm diameter. Mechanically assisted groundhog butterfly valves may be installed in mains 350 mm and larger. On mains 600 mm and larger, valves may be one size smaller than the mains (with suitable reducers). 1.14 Hydrants Fire hydrants must be located, in general, at street intersections and as follows:  Not more than 150 m apart in single family residential zones and not or more than 90 m apart in higher density residential, industrial, commercial, and institutional zones  In accordance with "Water Supply for Public Fire Protection - A Guide to Recommended Practice" published by Fire Underwriters Survey  1.0 m back from property line  Minimum 1.0 m clear of any other utility structure  At property lines in mid-block locations 1.15 Air Valves Combination air valves must be installed at the summits of all mains 200 mm diameter and larger, except as follows: Schedule B - Water Distribution 9 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw  Where the difference in elevation between the summit and valley is less than 600 mm  Where it can be shown that air pockets will be carried by typical flows  Where active service connections are suitably located to dissipate entrapped air Typical air valve sizes, subject to design analysis, are summarized in Table B6. Table B6: Air Valve Sizing Watermain Size Valve Size 200 mm to 300 mm 25 mm 350 mm to 600 mm 50 mm Larger than 600 mm Special design Air valves must be vented to an appropriate above-grade location to eliminate any potential for cross connection in a flooded or contaminated chamber. 1.16 Thrust Restraint Concrete thrust blocking and/or adequate joint restraining devices must be provided at bends, tees, wyes, reducers, plugs, caps, valves, hydrants and blow-offs. The restraint system must take into account potential future excavations in the vicinity of the watermain. Design calculations must be based on fitting type, water and test pressure and soil conditions. Schedule B - Water Distribution 10 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.17 Chambers Chambers or manholes containing valves, blow-offs, meters, or other appurtenances must allow adequate room for maintenance, including headroom and side room. Access openings must be suitable for removing valves and equipment. The chamber must be provided with a drain to storm sewer or ditch, complete with backflow prevention, to prevent flooding of the chamber. Rock pits may be considered, subject to suitable soil and groundwater conditions. A pumping system may be required for drainage. Adequate venting must be provided. Access and ventilation details must comply with WCB requirements. Insulation to prevent freezing must be provided where necessary. 1.18 Service Connections Service connections size must be calculated on the basis of the designated land use including sprinkler systems and/or on-site hydrants, where applicable. The minimum sizes are listed in Table B5. Each property must have an independent service located at the centre of each lot. Duplexes are to be serviced using a wye connection as per the Supplementary Detail Drawings. Each service must have a shut-off located within 300 mm of the property line within the City right-of way. 1.19 Utility Separation Requirements for separation of sanitary/storm sewers from water mains are as follows, unless otherwise indicated by the local public health authority:  Horizontal Separation: At least 3 m horizontal separation must be maintained between a water main and a sanitary/storm sewer. In special circumstances, specifically in rock or where the soils are determined to be impermeable, lesser separation than 3 m may be permitted provided that:  Approval has been granted by the Provincial Health Authority; or Schedule B - Water Distribution 11 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw  Any potential conflicts are constructed in accordance to Provincial/Local Health Authority Guidelines.  Vertical Separation: Where a sanitary/storm sewer crosses a water main, the sewer must be below the water main with a minimum clearance of 0.45 m. Where clearance is less than 0.45 m or the watermain crosses below the sanitary/storm sewer, protective measures approved by the local public health authority must be applied. Large diameter services must be separated 3 m horizontally from sewer services in separate trenches. Small diameter services may be installed in a common trench. 1.20 Alignment Except as noted in Section 1.21 - Right-Of-Way (R.O.W.), watermains must have straight alignments with uniform offsets between intersections. Mains must be located such that each property served has at least one side facing the watermain. Joint deflections and bending of mains are permitted within the manufacturer's specifications. If this is not possible, any required vertical or horizontal alignment changes must be made using appropriate bends or at fitting joints. 1.21 Rights-Of-Way (R.O.W.) Right-of-way locations should be selected to avoid environmentally sensitive areas such as watercourses, wetlands and wildlife migration corridors, and forested areas. In all cases, the R.O.W. width must be sufficient to permit an open excavation with side slopes in accordance with the WorkSafe BC regulations, without impacting on, or endangering, adjacent structures. The minimum R.O.W. width is 6.0 m. Where required, water feeder mains should have the R.O.W. wide enough for future twinning. The width of the R.O.W. should be the required separation between pipe centerlines plus three (3) times the depth to the crown of the deeper watermain. Where a utility is located within a R.O.W., and valves, valve chambers, manholes, or other appurtenances which require maintenance are located within the R.O.W., road access must be provided from a public road. The maintenance access must be sufficiently wide and structurally Schedule B - Water Distribution 12 of 12 City of Dawson Creek Subdivision and Development Servicing Bylaw adequate to support the maintenance vehicles for which the access is intended. Maximum allowable grade of the maintenance access is 12%. 1.22 Connection to Existing Watermains Connection to an existing watermain must be undertaken by the Owner at the Owner's expense under the supervision of City staff. The Owner must provide no less than 72 hours notice to City staff of the intent to connect to an existing watermain. City staff must operate existing valves. Provide 24 hours notice to City staff if operation of valves is required. 1.23 Testing and Disinfection Testing and disinfection must be done as per MMCD requirements and in accordance with applicable AWWA standards. Existing City hydrants must not be used for testing. The Owner must provide no less than 48 hours notice to City staff of the intent to test a watermain. Testing and disinfection must be completed under the supervision of City staff. Any work requiring the supervision or assistance of City staff must be completed during regular City business hours, Monday to Friday. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE C SANITARY SEWER Schedule C - Sanitary Sewer 1 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE C - SANITARY SEWER 1.0 Sanitary Sewer .................................................................................................................... 2 1.1 Sanitary Sewer .................................................................................................................... 2 1.2 Per Capita Flow ................................................................................................................... 2 1.3 Non-Residential Flows .......................................................................................................... 2 1.4 Peaking Factor .................................................................................................................... 4 1.5 Infiltration/Inflow ................................................................................................................ 4 1.6 Design Flow ........................................................................................................................ 4 1.7 Pipe Flow Formulas .............................................................................................................. 4 1.8 Flow Velocities .................................................................................................................... 5 1.9 Minimum Grades ................................................................................................................. 5 1.10 Minimum Pipe Diameter ....................................................................................................... 5 1.11 Alignment .......................................................................................................................... 5 1.12 Curved Sewers .................................................................................................................... 6 1.13 Manholes .......................................................................................................................... 6 1.14 Depth and Cover ................................................................................................................. 7 1.15 Right-Of-Way (R.O.W.) .......................................................................................................... 8 1.16 Utility Separation ................................................................................................................ 8 1.17 Service Connections ............................................................................................................. 9 1.18 Connection to Existing Sanitary Mains .................................................................................... 10 1.19 Corrosion and Odour Criteria ............................................................................................... 10 1.20 Testing ............................................................................................................................ 10 List of Tables: Table C1: Land Use Densities per Population Table C2: Commercial and Industrial ADWF Table C3: Pump Control Panel Schedule C - Sanitary Sewer 2 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 SANITARY SEWER 1.1 Sanitary Sewer Sanitary sewer systems must be designed in accordance with the requirements of this bylaw. 1.2 Per Capita Flow Sanitary sewer system design must be based on an average daily dry weather flow (ADWF) of 250 litres per day per capita (L/d/c). Population densities must be as follows:  Single Family = 3 persons/unit  Multi Family = 2 persons/unit 1.3 Non-Residential Flows Average dry weather flows (ADWF) for non-residential areas must be based on specific data related to the development or zoning. In the absence of such data, use the above residential per capita flow and the equivalent population factors as summarized in Table C1. Table C1: Land Use Densities per Population Land Use Equivalent Population/Hectare (gross) Commercial 120 people/ha Institutional 200 people/ha Industrial 200 people/ha Special consideration must be given to the design of the sanitary sewers for heavy users of water or generators of sanitary sewage. For identified commercial and institutional facilities, the ADWF must be as per Table C2. Schedule C - Sanitary Sewer 3 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw Table C2: Commercial and Industrial ADWF FACILITY UNIT TYPICAL ADWF L/(person or unit)/d Assembly hall Seat 8 Automobile dealer/renter Hectare 30,000 Automobile service station Set of pumps 2,000 Car wash Vehicle served 5,000 Bed and breakfast Patron 150 Bowling alley Lane 800 Camp: Children's, central toilet and bath Person 180 Day, no meals Person 50 Campground Site 600 Curling club Lane 8,500 Hospital Bed 1,000 Hotel Patron 300 Motel Patron 500 Office Employee 50 Picnic park, with flush toilets Visitor 30 Restaurant: Conventional Seat 150 24 hour Seat 200 Tavern Seat 80 School: Day, with cafeteria or lunchroom Student 60 Day, with cafeteria and showers Student 70 Boarding Student 400 Self-service laundry Machine 2000 Shopping centre m² 0.10 Swimming pool, with toilet and shower Patron 50 Theatre Seat 15 Schedule C - Sanitary Sewer 4 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.4 Peaking Factor The peaking factor is the ratio of Peak Dry Weather Flow (PDWF) to the Average Dry Weather Flow (ADWF). The peaking factor must be calculated using the design residential population and non-residential equivalent population with the following formula: PF = __3.2___ Where: PF = peaking factor (P) 0.105 P = residential population plus non-residential equivalent population in thousands 1.5 Infiltration/Inflow Design flows must include an Infiltration and Inflow (I/I) allowance of 15,000 L/d/ha 1.6 Design Flow Design flow, Q (= Peak Wet Weather Flow (PWWF)) = population and equivalent x per capita flow x peaking factor + infiltration/inflow allowance. Q = PWWF = (P) x (ADWF) x (PF) + I/I 1.7 Pipe Flow Formulas  Gravity Sewers Use Manning's formula: Q = AR0.667 S0.5 n Where: Q = Design flow in m³/s A = Cross sectional area in m² R = Hydraulic radius (area/wetted perimeter) in m S = Slope of hydraulic grade line in m/m n = Roughness coefficient → concrete = 0.013 → PVC = 0.011  Sewage Force Mains Use Hazen-Williams formula: Q = CD2.63S0.54 Where: Q = Rate of flow in L/s 278780 D = Internal pipe dia. in mm S = Slope of hydraulic grade line in m/m C = Friction coefficient → PVC or HDPE = 130 Schedule C - Sanitary Sewer 5 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.8 Flow Velocities Gravity Mains: The minimum full pipe velocity must be 0.6 m/s. There is no maximum velocity. However, consideration must be given to scour problems and the dynamic loading on manholes where flow exceeds 3.0 m/s. Anchoring must be incorporated where the grade(s) of the sewer are 15% or greater. Force Mains: At the lowest pump delivery rate anticipated to occur at least once per day, a minimum cleansing velocity of 1.0 m/s must be maintained. Maximum velocity should not exceed 3.5 m/s. 1.9 Minimum Grades Gravity Mains: The grade of any sewer is governed by the minimum required full pipe velocity of 0.6 m/s. Forcemains: Forcemains must be graded at a minimum of 0.5%. Grading must be designed to minimize high points. Provide air release valves at high points 1.10 Minimum Pipe Diameter Gravity Mains:  200 mm Forcemains:  100 mm Service Connections:  Single family residential - 100 mm  Duplex residential - One 100 mm service per side  Multi-family/commercial/institutional/industrial - 150 mm 1.11 Alignment Except as noted in Schedule C Section 1.12 - Curved Sewers, horizontal and vertical alignments must be straight lines between manholes. Schedule C - Sanitary Sewer 6 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.12 Curved Sewers Horizontal curves may be formed using pipe joint deflections as follows:  Minimum radius = 60 m  Constant radius throughout curve  Minimum design velocity = 0.9 m/s  Curvature limited to half of maximum curvature specified by pipe manufacturer  Deflection to be at pipe joints only, no bending of the sewermain will be allowed  Radius and curvature not less than 60 m  Curve locations to be recorded at ¼ points and midpoint  Constant offset from property line or road centerline 1.13 Manholes Manholes are required at:  Every change in grade  Every change in direction, except as permitted for curved sewers  Every change in pipe size  Downstream end of curved sewers  Every pipe intersection except for 100 mm and 150 mm service connections and junctions with trunk sewers 900 mm and larger  120 m maximum spacing for all pipe sizes  Every future pipe intersection  Every terminal end (upstream end of every sewer main)  Temporary clean-outs may be provided at terminal section of a main provided that:  Future extension of the main is proposed or anticipated  The length of sewer to the downstream manhole does not exceed 45.0 m  The depth of the pipe does not exceed 2.4 m at the terminal point  Clean-outs are not to be considered a permanent structure  Sanitary manhole rim elevations outside of paved roadways must be designed to be:  Above the adjacent storm manhole rim elevation and Schedule C - Sanitary Sewer 7 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw  Above the surrounding ground so that infiltration from ponding will not occur Hydraulic Details:  Crown elevations of inlet sewers must not be lower than the crown elevation of the outlet sewer  Minimum slopes across manholes:  Straight run: 5 mm  Deflections up to 45°: 20 mm  Deflections 45° to 90°: 30 mm  The maximum deflection angle in a junction is 90°  Drop manhole and ramp structures must be avoided where possible by steepening inlet sewers. Where necessary, provide ramp and drop structures as follows: Invert Difference Structure Up to 0.25 m Inside Ramp 0.25 m to 1.0 m Inside Drop Greater than 1.0 m Outside Drop  Force main discharges must be directed into the receiving manhole outlet pipe. Manhole benching must be extended a minimum 200 mm above the force main crown. If a manhole drop cannot be avoided, an outside drop structure is required. 1.14 Depth and Cover Depth is defined as the distance from the finished ground surface to the top of pipe. Sewers must be of sufficient depth to:  Permit gravity sewer service to the basements of properties adjacent to the roadway or sewer right-of-way  Prevent freezing  Meet the minimum depth requirements of 2.4 m  Clear other underground utilities  Prevent damage from surface loading Schedule C - Sanitary Sewer 8 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw  Allow for future extension of the sanitary sewer system to service upstream tributary lands at ultimate development, as required by the Director of Development Services Minimum cover on sewer connections at property lines must be 2.4 m. The City may accept sewer mains and services with less than 2.4 m cover providing that the Owner's Professional Engineer has designed insulation adequate to prevent sanitary freezing. 1.15 Right-Of-Way (R.O.W.) Right-of-way locations must be selected to avoid environmentally sensitive areas such as watercourses, wetlands and wildlife migration corridors and forested areas. Rear yard sewers are discouraged and will only be allowed with appropriate easements, access and the permission of the Director of Development Services. Where location of a municipal utility in a statutory right-of-way is permitted by the Director of Development Services, the minimum right-of-way width is 6.0 m. In all cases, the width of rights-of-way must be sufficient to permit an open excavation with side slopes in accordance with the WorkSafe BC regulations, without impacting on, or endangering, adjacent structures. Where a utility is located within a right-of-way, and valves, valve chambers, manholes, or other appurtenances which require maintenance are located within the right-of-way, access from a public road must be provided. The maintenance access must be sufficiently wide and structurally adequate to support the maintenance vehicles for which the access is intended. Maximum allowable grade of the maintenance access is 12%. 1.16 Utility Separation Requirements for separation of sanitary sewers from water mains are as follows, unless otherwise indicated by the local public health authority.  Horizontal Separation: At least 3 m horizontal separation must be maintained between a water main and a sanitary sewer. In special circumstances, specifically in rock or where the soils are determined to be impermeable, lesser separation than 3 m may be permitted provided that:  Approval has been granted by the Provincial Health Authority, or  Any potential conflicts are constructed in accordance to Provincial/Local Health Authority Guidelines. Schedule C - Sanitary Sewer 9 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw  Vertical Separation: Where a sanitary sewer crosses a water main, the sewer must be below the water main with a minimum clearance of 0.45 m. Where clearance is less than 0.45 m or the sewer main crosses above the water, protective measures approved by the local public health authority must be applied.  Sewers in Common Trench: Sanitary and storm sewers may be installed in a common trench, provided that the design has taken into account:  Interference with service connections  Stability of the benched portion of the trench  Conflicts with manholes and appurtenances The horizontal clearance between sewer pipes must be no less than 1.0 m and the horizontal clearance between manholes must be no less than 0.3 m. 1.17 Service Connections Connections are to serve all plumbing by gravity. Building elevations should be established accordingly. Service connections must be provided to each lot fronting the main. Service connections must be installed perpendicular to the main, and in no case must a service connection be placed so that it extends in front of any property other than the one being serviced. Each property is permitted only one service connection. In special circumstances, where servicing of all buildings on existing industrial or commercial properties is not feasible, two services may be allowed if permitted by the Director of Development Services. Each unit of a residential duplex must be provided with a separate service connection. The minimum grade from the main to the property line must be 2.0% for 100 mm services and 1% for 150 mm services. Service connections may be permitted into manholes provided that:  The connection is not in an adverse direction to the flow in the sewer main  The connection enters the manhole so the service crown is no lower than the sewer main crown Schedule C - Sanitary Sewer 10 of 10 City of Dawson Creek Subdivision and Development Servicing Bylaw Manholes are required on service connections larger than 150 mm diameter. For residential developments, service connections must be located at the centre of each lot and as noted on the Supplementary Detail Drawings. The maximum length of any service connection is 30 m. Services exceeding 30 m in length will be considered mains. 1.18 Connection to Existing Sanitary Mains Connection to an existing sanitary main must be undertaken by the Owner at the Owner's expense under the supervision of City staff. The Owner must provide no less than 72 hours notice to City staff of the intent to connect to an existing watermain. 1.19 Corrosion and Odour Criteria  Dissolved sulphide maximum limit at any point in the system is to be 0.5 mg/l  Odour Criteria:  At 10 m from any gravity main, force main, manhole and lift station or other sewer facility (summer conditions, winds between 2-10 km/h), 1.0 odour units  Where sewer facilities are close to houses, parks or walkways, 0.0 odour units  Analysis for odour and sulphides may be required 1.20 Testing Testing of installed pipes depends on the height of existing ground water and must consist of low pressure air testing and video inspection as outlined in the MMCD. The Owner must provide no less than 48 hours notice to City staff of the intent to test a sanitary main. Testing must be completed under the supervision of City staff. Any work requiring the supervision or assistance of City staff must be completed during regular City business hours, Monday to Friday. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE D STORMWATER Schedule D - Stormwater 1 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE D - STORMWATER 1.0 Stormwater Management ..................................................................................................... 2 1.1 General ........................................................................................................................... 2 1.2 Stormwater Management ................................................................................................... 2 1.3 Integrated Stormwater Management Plan .............................................................................. 3 1.4 Minor and Major Systems .................................................................................................... 4 1.5 Runoff Analysis ................................................................................................................. 4 1.6 Design Frequencies ............................................................................................................ 4 1.7 Rational Method ............................................................................................................... 6 1.8 Computer Modelling Method ............................................................................................... 9 1.9 Minor System Design ........................................................................................................ 11 1.10 Major System Design ........................................................................................................ 17 1.11 Runoff Controls ............................................................................................................... 20 1.12 Environmental Protection .................................................................................................. 24 1.13 Testing .......................................................................................................................... 25 List of Tables: Table D1: Drainage and Stormwater Return Frequencies Table D2: Runoff Coefficients Table D3: Inlet Times Table D4: Common Impervious Fractions Table D5: Critical Storm Events Table D6: Permissible Depths for Submerged Objects Schedule D - Stormwater 2 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 STORMWATER MANAGEMENT 1.1 General These standards are not intended to be a substitute for sound engineering knowledge and experience. Drainage designs must be prepared under the direction of a Professional Engineer with the appropriate experience and knowledge. These standards are intended to cover only minimum requirements. Drainage designs must conform to all pertinent City bylaws, regulations, guidelines and policies as well as federal and provincial statutes and guidelines. 1.2 Stormwater Management Stormwater management involves the planning and design necessary to avoid and/or mitigate the negative hydrological impacts of land development or land use changes on adjacent and downstream lands and watercourses. Adverse hydrological impacts include such issues as increased runoff (peak stormwater flows and volume), erosion, sedimentation, flooding, property damage and injury or loss of life, reduced surface infiltration, reduced minimum groundwater levels and stream flows, water quality deterioration and degradation of aquatic and wildlife habitats. Mitigation measures include but are not limited to the following:  Appropriate sizing and routing of pipes and channels  Major flow path routing  Detention storage  Removal of sediment and other pollutants  Landscaping  Source control  Erosion protection  Groundwater infiltration  Subsurface disposal  Lot grading Schedule D - Stormwater 3 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.3 Integrated Stormwater Management Plan An Integrated Stormwater Management Plan (ISMP) is required for any Subdivision or Development larger than 0.4 ha (1 acre) and must be submitted for the full extents of the Subdivision or Development and not by phase. The ISMP must include the following:  Catchment plan for the subject site which includes all upstream lands that drain into or through the site  Description of the existing and proposed land uses  Details indicating how the ISMP integrates with the City's drainage planning  Major contours at 1.0 m and minor contours at 0.2 m elevation intervals (existing and proposed)  Alignment and limits of existing watercourses and wetlands located in existing and proposed, or within 30 m of, the subject site, complete with environmental classifications and/or fish presence information  Layout of existing and proposed drainage systems  Proposed point and method of stormwater discharge from the site (e.g., pipe connection to the City's Community Drainage System, open discharge to ditch or natural watercourse)  Existing and proposed major surface flow paths  Proposed site grading plan in accordance with Schedule H - Site Grading  Proposed source quality treatment systems, where required  Locations and sizes of proposed conveyance and other management facilities for both minor and major systems  Proposed building elevations and their relationship to the 1:100 year major flow path hydraulic grade line  Temporary (construction) and permanent erosion and sediment control plan  Pre and post-development flows, with the impact mitigation measures  Downstream capacity for the system to which the subject site is proposed to discharge  Pre-development flows for all areas draining to or through the subject site Subdivision or Developments less than 0.4 ha (1 acre) are required to submit a lot grading plan to ensure proper routing of surface flow. Building locations and elevations must be checked relative to major surface flow paths. Schedule D - Stormwater 4 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.4 Minor and Major Systems Each drainage system consists of the components that relate to either major or minor stormwater systems. The minor system comprises of the following:  Minor conveyance system comprising the gutters, inlets, storm sewers, driveway culverts, low flow channels and watercourses  Storage Facilities  Water Quality Treatment Systems The major system comprises of the following:  Surface flow paths, roadways, storage facility overflows, and watercourses  Culverts, bridges, and other crossing structures 1.5 Runoff Analysis Storm drainage systems must be designed to accommodate the post-development flows using the Rational Method or an approved hydrologic/hydraulic computer model. The final hydraulic report must be signed and sealed by a Professional Engineer. For Subdivision or Developments where the total tributary area is 25 hectares or less, the Rational Method may be used to compute the peak runoffs. An approved hydrologic/hydraulic computer model must be used for analyzing larger catchments and for the design of all storage facilities. Regardless of the analytical method being used, the tributary area used for the design of the storm drainage system must be consistent with the actual contours of the land. It is the Professional Engineer's responsibility to confirm the extent of the drainage area with the Director of Development Services prior to final design. 1.6 Design Frequencies Schedule D - Stormwater 5 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw In general, the design of stormwater management system components is required to accommodate a number of variable stormwater runoff rates and volumes generated by storms of certain recurrence intervals. Table D1 summarizes the return frequencies to be used for the design of the drainage and stormwater management system components. Table D1: Drainage and Stormwater Return Frequencies Drainage System Component Hydraulic Variables Hydrologic Design Basis Minor conveyance system comprising the storm sewers, driveway culverts, low flow channels and watercourses. Peak flow rate, flow depth, duration of storm events and base flow rates. 1:5 year design storm with winter condition antecedent moisture condition. Storage facility Runoff volume, depth, freeboard, peak inflow rate, control discharge rate, time to empty, base flow rates. Storage capacity to reduce the post- development flow rates to below their respective pre-development levels of the 1:10 year event. This may be increased to 1:100 year if inadequate downstream major flow paths exist. Major system comprising the surface flow paths, roadways, storage facility overflows and watercourses Peak flow rate, flow depth, duration, storage outflow and overflow rates, runoff volumes, and velocity. 1:100 year design storm with winter condition antecedent moisture condition. Sufficient freeboard above the maximum hydraulic grade line must be provided to protect buildings. Culverts, bridges, and other crossing structures Peak flow rates, depth and freeboard, backwater effect, fish passage. 1:100 year design storm and/or with safe overflow to protect City infrastructure and private property. 1:200 year for natural streams with catchments exceeding 10 sq. km or for structures crossing arterial or collector roads. Water Quality Treatment Systems Peak flow, base flow Oil and grit separators required for treatment of flows up to the 5 year post- development peak rate for parking lots and industrial properties. Schedule D - Stormwater 6 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.7 Rational Method The Rational Method calculates the peak flow using the formula: Q = RAIN Where: R = Runoff Coefficient A = Drainage area in ha. I = Rainfall intensity in mm/hr. N = 0.00278 Q = Flow in m³/s 1.7.1 Runoff Coefficients Zone designations selected for design purposes must be based on the highest and best use of the properties in the design catchment area based on the most current version of the City's Zoning Bylaw. Future land designations, as defined in the City's Official Community Plan (OCP), must be used if such land use designations will result in a higher runoff coefficient. Table D2: Runoff Coefficients Type of Area Coefficient 1:5 year 1:100 year Woodlot 0.10 0.20 Agricultural (cultivated) 0.10 0.15 Rural Residential 0.35 0.40 Single Family Residential 0.50 0.55 Low Density Multi-Family Residential 0.60 0.65 Apartment 0.70 0.75 Commercial 0.80 0.85 Industrial 0.80 0.85 Institutional 0.75 0.80 Roofs or Pavement 0.95 1.00 Parks/Cemeteries 0.15 0.20 Natural Grass 0.10 0.15 Schedule D - Stormwater 7 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.7.2 Time of Concentration The time of concentration is the time required for runoff to flow from the most remote part of the catchment area under consideration to the design node. For both urban and rural areas, the time of concentration consists of the following formula: Tc = Ti + Tt Where: Tc = time of concentration (minutes) Ti = inlet or overland flow time (minutes) Tt = travel time in sewers, ditches, channels or watercourses (minutes)  Inlet or Overland Flow Time (Ti):  Inlet times for various land use conditions are given to ensure uniformity in runoff computations Table D3: Inlet Times Lot Type Inlet time (minutes) 5 year 100 year Single Family 15 10 Multi Family 10 5 Commercial/Industrial/Institutional 10 5  The inlet time in rural areas must be calculated using the Airport Method: Ti = 3.26(1.1 - C) L0.5 S0.33 Where: Ti = inlet (minutes), minimum time = 15 minutes C = runoff coefficient L = travel distance (m), maximum length = 300 m S = slope of travel path (%)  Travel Time (Tt)  The travel time in sewers, ditches, channels or watercourses must be estimated using the following formula: Tt = Ct Ln 12 s 0.5 Schedule D - Stormwater 8 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw Ct = Concentration coefficient depending on the type of flow = 0.5 for natural watercourses or ditches = 1.4 for overland flow = 0.5 for storm sewer flow L = Length of watercourse, conduit or overland flow in metres, along the drainage path from the furthest point in the basin to the outlet. n = Channel friction factor = 0.050 for natural channels = 0.030 for excavated ditches = 0.016 for overland flow on smooth paving = 0.400 for overland flow on natural areas = 0.013 for concrete pipe = 0.011 for PVC pipe s = Basin slope in meter/meter The above equation provides an approximate travel time which must be corrected with the actual time of flow calculated from the hydraulic properties of the selected pipe/channel. A composite value for Tt must be calculated in cases where the type of flow along the longest path varies or the slope changes. 1.7.3 Rainfall Intensity The Intensity-Duration-Frequency (IDF) curve established for Dawson Creek is based on rainfall records collected from the weather station at the Dawson Creek Airport. See the Supplementary Detail Drawing S17 for the IDF Curve. Intensities corresponding to the 0.5, 1, 2, 6, 12, & 24 hour storms must be calculated to determine the design peak flow rate. 1.7.4 Mean Annual Rainfall (MAR) Statistically, the Mean Annual Rainfall (MAR) is defined to be the 24 hour rainfall volume with a return period of 2.33 years. For practical purposes, the 2 year 24 hour rainfall volume is used as the MAR and is calculated to be 36.3 mm. 1.7.5 Presentation of Rational Calculations The Professional Engineer is required to tabulate the Rational Method calculations for submission along with the appropriate plans and other relevant information. Schedule D - Stormwater 9 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.8 Computer Modelling Method 1.8.1 Selection of Modelling Program For basins larger than 25 hectares, hydrologic programs must be used for runoff analyses. Hydrologic/hydraulic programs must also be used for the design of all stormwater detention facilities. Software programs must be run with an EPA SWMM engine. 1.8.2 Catchment Data Data preparation for planning areas or proposed Subdivisions or Developments must be based on the best available information as per the City's Official Community Plan (OCP), Zoning Bylaw, adjacent Subdivision or Development proposals and other pertinent land use information. The Professional Engineer must determine both pre-development and post-development flows with appropriate parameters chosen to be reflective of the type of soils, ground cover and typical antecedent moisture condition (AMC) prevalent during the winter season. Where information is not specifically available through applicable documents, future impervious fractions for common land uses, as shown in Table D4 must be used for analysis. These are intended as a guide only. In existing developed areas or where more detailed information is available, the Professional Engineer must verify that the values shown are representative of the true conditions. Table D4: Common Impervious Fractions Common Land Use Total Impervious Fraction Woodlot 0.05 Agricultural 0.10 Sub-Urban Residential 0.35 Single Family Residential 0.45 Low Density Multi-Family Residential 0.65 Apartment 0.75 Commercial 0.90 Industrial 0.90 Institutional 0.80 1.8.3 Storm Events In order to determine the critical storm event for designing drainage works, analysis must be conducted using design storms with the appropriate return period and the durations included in Table D5. Developing design flows for both existing and proposed conditions are required. Schedule D - Stormwater 10 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw Table D5: Critical Storm Events Infrastructure Component Storm Return Period Storm Durations to Model Minor conveyance system 1:5 year 0.5, 1, 2, 6, 12, & 24 hour storms to determine design peak flow rate Major conveyance system 1:100 year 0.5, 1, 2, 6, 12, & 24 hour storms to determine design peak flow rate Detention Storage Facilities 1:10 year 1:100 year (if necessary) 0.5, 1, 2, 6, 12, & 24 hour storms to determine maximum storage volume and peak overflow rate. The storm duration which generates the highest peak runoff rate is not necessarily the event which results in the largest storage volume requirement for peak flow attenuation. The Professional Engineer must review all design storm events and select the critical design values for each component of the drainage system. 1.8.4 Presentation of Modeling Results To document the design rationale used to develop the hydrologic model and to standardize the presentation of model results, the design reports must include an appropriate section which must indicate the following:  Type and version of computer model used  Summary of all parameters and specific simulation assumptions used  Design storms with clear documentation and plotted  A summary of peak flows for each system component  Inflow and outflow hydrographs for storage facilities  A plan showing sub-catchment areas, watershed boundary (including upstream catchments) and the drainage system  A plan identifying the specific land uses modeled for each development condition analyzed  For detention ponds, stage-area and storage-discharge curves and the layout (including sizing) of pond control devices  The functional layout and sizing of any flow control/diversion structure and the tabular/graphical plots of inflow and outflow hydrographs Schedule D - Stormwater 11 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Tables summarizing the above described performance related parameters 1.9 Minor System Design 1.9.1 Level of Service The minor drainage system consists of pipes and appurtenances sized to convey peak runoff by gravity (non-surcharged) flow conditions for storms having the return period specified in Schedule D - Table D1. 1.9.2 Pipe and Channel Capacity Apply the Manning Formula under free flow (non-surcharged) condition. The Manning Formula is: Q = A R 0.667 S 0.5 n Where: Q = flow capacity (m/s) A = cross sectional area (m²) R = hydraulic radius (m) S = slope of hydraulic grade line (m/m) n = roughness coefficient Pipes must be designed to carry the required quantity when flowing ¾ full. 1.9.3 Flow Velocities Minimum design velocity for pipes flowing full: 0.6 m/s. Where steep grades result in pipe velocities exceeding 6 m/s, consider measures to prevent pipe erosion and movement. Anchoring must be incorporated where the grade(s) of the sewer are 15% or greater. Provide riprap bank protection and, if necessary, energy dissipation facilities in accordance to Section 1.12.3 - Channel Erosion Protection. Schedule D - Stormwater 12 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.9.4 Minimum Pipe Diameter Storm Sewers 300 mm Culverts:  Crossing Roads 600 mm  Crossing Driveways 400 mm Catchbasin Leads Storm Services BC Hydro sump drain 200 mm for single catchbasin 250 mm for double catchbasin 300 mm 75 mm Downstream pipe sizes are not to be reduced unless the proposed downstream pipe is 600 mm diameter or larger and increased grade provides adequate capacity. Detailed hydraulic analysis is required. The maximum reduction is two pipe sizes. 1.9.5 Alignment Horizontal and vertical alignments as straight lines between manholes are preferred. Horizontal and vertical curves may be formed using pipe joint deflections as follows:  Minimum radius = 60 m  Constant radius throughout curve  Minimum design velocity = 0.9 m/s  Curve locations to be recorded at ¼ points and midpoint  Radius and curvature not less than 60 m  Deflection to be at pipe joints only, no bending of the watermain will be allowed  Curvature limited to half of maximum curvature specified by pipe manufacturer  Constant offset from property line or road centerline 1.9.6 Manholes Manholes are to have precast bases. Manholes are required at:  Every change in grade  Every change in direction, except as permitted for curved sewers  Every change in pipe size Schedule D - Stormwater 13 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Upstream and downstream end of curved sewers  Every pipe intersection  120 m maximum spacing for all main sizes  Every future pipe intersection  Upstream end of every sewer main Hydraulic Details:  Crown elevations of inlet sewers must not be lower than crown elevation of outlet sewer  Minimum slopes across manholes: o Straight run: 5 mm o Deflections up to 45 degrees: 20 mm o Deflections 45 to 90 degrees: 30 mm  Drop manhole and ramp structures must generally be avoided by steepening inlet sewers. Where necessary, provide drop structures as follows: Invert Difference Structure Up to 0.25 m Inside Ramp 0.25 m to 1.0 m Inside Drop Greater than 1.0 m Outside Drop  Hydraulic losses must be calculated for manholes with significant changes in alignment (>45º). For high velocity flows (>3m/s) or large pipes (>600 mm Ø), detailed analysis is required. For low velocities and smaller pipes, use the following formula: HL = k V2 Where: HL = head loss (m) 2g V = outlet flow velocity (m/s) g = gravitational acceleration (9.81m/s2) k = head loss coefficient (1.0 for channeled 90° bends and tees, to 1.5 without channelized benching) 1.9.7 Depth and Cover Depth must be defined as the distance from the finished ground surface to the top of the pipe. Storm sewers must be of sufficient depth to: Schedule D - Stormwater 14 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Meet the minimum depth of cover requirements of 2.1 m  Clear other underground utilities  Prevent damage from surface loading  Allow for future extension of the minor system to service upstream tributary lands at ultimate development 1.9.8 Right-of-Way (R.O.W.) Right-of-way locations must be selected to avoid environmentally sensitive areas such as watercourses, wetlands and wildlife migration corridors and forested areas. Rear yard sewers are discouraged. Where location of a municipal utility is in a statutory right-of-way the minimum right-of-way width is 6.0 m. In all cases, the width of rights-of-way must be sufficient to permit an open excavation with side slopes in accordance with the Worksafe BC regulations, without impacting on or endangering adjacent structures. Where required, trunk and interceptor sewers should have rights-of-way wide enough for future widening and/or twinning. Where a utility is located within a right-of-way, and valves, valve chambers, manholes, or other appurtenances which require maintenance are located within the right-of-way, provide road access from a public road. The maintenance access must be sufficiently wide and structurally adequate to support the maintenance vehicles for which the access is intended. Maximum allowable grade of the maintenance access is 12%. 1.9.9 Utility Separation Requirements for separation of storm sewers from water mains are as follows, unless otherwise indicated by the local public health authority.  Horizontal Separation: At least 3 m horizontal separation must be maintained between a water main and a storm sewer. In special circumstances, specifically in rock or where the soils are determined to be impermeable, lesser separation than 3 m may be permitted provided that:  Approval has been granted by the Provincial Health Authority, or  Any potential conflicts are constructed in accordance to Provincial/Local Health Authority Guidelines. Schedule D - Stormwater 15 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Vertical Separation: Where a storm sewer crosses a water main, the sewer must be below the water main with a minimum clearance of 0.45 m. Where clearance is less than 0.45 m or the sewer main crosses above the water, protective measures approved by the local public health authority must be applied.  Sewers in Common Trench: Storm and sanitary sewers may be installed in a common trench, provided that the design has taken into account:  Interference with service connections  Stability of the benched portion of the trench  Conflicts with manholes and appurtenances The horizontal clearance between sewer pipes must be no less than 1.0 m and the horizontal clearance between manholes must be no less than 0.3 m. 1.9.10 Service Connections, Roof Drainage and Building Perimeter Foundation Drainage Direct storm connections from building roof drains or foundation drains are not permitted. Roof drainage for all buildings must be discharged to the ground and dispersed via splash pads at the downspouts, provided that the site is graded away from the building, or to an approved sub- surface soak-away system. Building perimeter foundation drains must drain by gravity to the surface if grades permit or into a sump pump that discharges water onto the surface. Roof leaders and foundations drains must not discharge at the top of bank of a natural watercourse or other open channel. A roof leader or building perimeter foundation drain must not be connected to a sanitary sewer. On site surface runoff collection systems, through the use of catchbasins or other inlet devices, are permitted to connect to the storm system. For multifamily residential, commercial and urban industrial lots, storm services must be installed to property line for connection of future on-site surface runoff collection systems only. 1.9.11 Catchbasin Spacing Catchbasins are required at regular intervals along roadways, at intersections and at low points. Catchbasin spacing is to provide sufficient inlet capacity to collect the entire minor flow or major flow, if required, into the pipe system. Schedule D - Stormwater 16 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw The capacity of a single catchbasin (in sump conditions) can be calculated using the orifice formula: gh kCA Q 2  Where: Q = inlet capacity (m3/s) k = clogging factor (0.6) C = orifice coefficient A = open area (m²) g = gravitational acceleration (9.81m/s2) h = depth of ponding (m) Space catchbasins to drain maximum paved areas of:  500 m² on roads with grades up to 4%  400 m² on roads with grades greater than 4% Other spacing requirements include:  Prevent overflows to driveways, boulevards, sidewalks and private property  Avoid interference with crosswalks  Catchbasin leads to discharge into manholes wherever possible  Maximum lead length: 30 m  Maximum spacing: 110 m Minimum grade of catchbasin leads: 2.0%. Lawn basins are required on boulevards and private properties where necessary to prevent ponding or flooding of sidewalks, boulevards, driveways, buildings and yards. Double catchbasins must be provided at all vertical points of intersections on road sag curves. 1.9.12 Pipe Joints Use watertight joints except where storm sewers are part of a subsurface disposal system. 1.9.13 Tie In Procedures Connection to the City's existing storm infrastructure must be undertaken by the Owner at the Owner's expense. Schedule D - Stormwater 17 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.9.14 Culverts Driveway culverts that form part of the minor system must have capacity for the runoff from the 1:5 year storm. The Professional Engineer must determine whether the culvert will operate under the inlet or outlet control at design conditions. The minimum depth of cover for a culvert must be 0.3 m, subject to the correct pipe loading criteria. 1.9.15 BC Hydro Utility Drainage Where BC Hydro requires drainage for their infrastructure, the drain pipe will be a minimum of 75 mm diameter PVC line. BC Hydro Utility Drainage requirements:  Prevent overflows to driveways, boulevards, sidewalks and private property  Avoid interference with crosswalks  Drainage line to discharge into manholes wherever possible  Minimum grade of drainage line: 2.0% 1.10 Major System Design 1.10.1 Surface Flow Routing All surface flows must have specially designed routes that are preserved and protected by easements or right-of-ways and are accessible for maintenance. Design criteria include:  In accordance to Schedule D Section 1.6 - Design Frequencies  One lane, or a 3.5 m width at the crown of each arterial road, is to be free from flooding  Where a road is used as a major flow path, the road grades are to be designed to accommodate and control the flow at intersections and driveways  Overflow routes are required at all sags and low points in roads and other surface flow routes  Major flood routes are required at down-slope cul-de-sacs  Maximum flow depths on roadways are subject to the design velocities as per Table D6. Schedule D - Stormwater 18 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw Table D6: Permissible Depths for Submerged Objects Water Velocity (m/s) Permissible Depth (m) 0.5 0.80 1.0 0.32 2.0 0.21 3.0 0.09 1.10.2 Surface Flow Capacity Flow capacity of road surfaces and swales must be calculated using the Manning formula, which is presented in Schedule D Section 1.9.2 - Pipe and Channel Capacity. Typical values of the Manning Roughness Coefficient "n" are:  0.018 for paved roadways  0.030 for grassed boulevards and swales  0.040 to 0.10 for irregular or treed channels 1.10.3 Site Grading The establishment of a site grading plan is one of the principal means for establishing a critical component of the major drainage system. A detailed site grading plan is required to be developed in accordance with Schedule H - Site Grading. All lots are to be graded to include provision of protection against surface flooding and property damage for the 1:100 year return frequency design storm. Through control of surface elevations, designs should be such that maximum flow or ponding surface elevations are 300 mm below the lowest anticipated finished ground elevations at buildings. 1.10.4 Piped System The minor drainage system may be enlarged or supplemented to accommodate major flows. Design considerations include:  Provision of adequate inlets to accommodate major flows  The requirement for surface overflow routes at potential surface ponding locations  Design in accordance with minor drainage system guidelines  Adequate capacity of the existing downstream storm sewer  Culverts located in watercourses or culverts crossing roads must be designed for the 1:100 year event Schedule D - Stormwater 19 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.10.5 Inlet and Outlet Structures Pipes larger than 1,200 mm in diameter, and non-circular culverts require specially designed inlet and outlet structures. Outlets may require rip rap protection and/or energy dissipating structures for erosion control. The Professional Engineer must apply Best Management Practices to reduce erosion at all inlet/outlet structures. Ditch inlets to storm sewers must include sedimentation basins, safety grillage and hinged trash racks for all pipes that are 450 mm and larger. 1.10.6 Ditches Ditches must only be provided if in accordance with the applicable road classification and design standards. Ditches adjacent to roads must conform to the following criteria:  Maximum depth 1.0 m  Minimum bottom width 0.5 m  Maximum side slope 2.0(H):1(V) Confirmed by Owner's Professional Geotechnical Engineer  Minimum grade 0.5%  Maximum velocity (Unlined ditch)  Temporary (construction) and Permanent Erosion and Sediment Control Determined such that ditch materials do not become erodible As designed by the Owner's Professional Engineer The minimum right-of-way width for a ditch through private property must be 5 m or the width of the ditch plus 3 m, whichever is greater. The ditch must be offset in the right-of-way to permit a 3 m wide access for maintenance vehicles. Additional right-of-way may be required to facilitate ditch construction and access. The top of the ditch must be a minimum 0.5 m from any property line. Schedule D - Stormwater 20 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.11 Runoff Controls 1.11.1 Stormwater Storage Facilities Stormwater dry detention must be provided in accordance with the criteria herein:  Capacity Requirements: The storage capacity requirement must be determined by evaluating the performance under a number of storm events as listed in Table D1. Sufficient live storage capacity must be sized to such that post-development flows are equal to pre-development flows. Storm events exceeding the 1:10 year level are generally considered an overflow condition and part of the major system. The facility must be designed to permit the controlled overflow release of flows up to the peak 1:100 year level to an approved major flow path. If a sufficient major flow path does not exist, or if the proposed release rate will increase the risk of downstream impacts to an unacceptable level, then storage may be required to ensure that the post-development 1:100 year flows do not exceed the 1:100 year pre- development levels or other erosion control measures may be required. 1:100 year flows and volumes are to be determined by the Professional Engineer as required to suit downstream conditions The performance of the storage facility must be evaluated under the selection of storm events listed in Table D5. The facility must be sized and designed for the criteria which results in the largest storage volume. Storage facilities must be designed and evaluated using an approved modelling program as discussed in Schedule D Section 1.7 - Rational Method. This criteria is applicable to all service areas 0.4 hectares or greater.  Geometrical Requirements: To minimize short circuiting dry detention facilities must have a minimum length to width ratio of 3:1. For slope stability, ease of maintenance, and safety, maximum side slopes are 3:1. A freeboard of 0.3 m is required for all detention facilities.  Small Lot Criteria: For service areas smaller than 0.4 hectares, the requirement for a detailed analysis of the storage facility is not required. 1:100 year flows and volumes are to be determined by the Professional Engineer as required to suit downstream conditions.  Control Structures: Schedule D - Stormwater 21 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw The release rate from detention facilities must be regulated using a control structure. The outlet control for storage facilities must be designed using standard orifice or weir equations. Storage facility must include provisions for discharge rates greater than the design release rate. Designs must also provide means for rapid drawdown, such as an emergency drain. Design of inlet/outlet structures must consider flow energy dissipation and erosion control. Safety railings are required over all inlet/outlet openings larger than 450 mm in diameter. Locks for access hatches are required to prevent unauthorized entrance to the structure.  Emergency Overflow: Whether the facility is sized to control the 1:100 year event or not, an emergency overflow with the capacity for the peak 1:100 year flow rate must be provided for all storage facilities. The overflow surface must be finished with erosion resistant material such as concrete, asphalt, paving stone, or an approved equivalent. The design of the spillway and/or overflow must consider the possibility of blockages in the outlet structure. The overflow must provide safe discharge to an accepted major flow path. If the stormwater storage facility is an underground storage facility, overflow piping must be installed and must have the capacity to safely convey the 100 year event.  Operation and Maintenance Requirements: A minimum 4 m wide All-Weather Vehicle Access must be constructed from a public road right-of-way to the control structure and other works requiring maintenance. The maximum grade on the access is to be 12%. A maintenance access of the same type must also be provided to a sediment sump or forebay at the inlet end of an open pond. For facilities servicing multiple lots, and where the City agrees to assume responsibility for operation and maintenance of the facility, six copies of the operation and maintenance manual must be provided when the facility is completed and prior to the City assuming ownership. The manual must include:  Record drawings of the constructed facility  Brief description of the facility operation including design flows, design depths, and schematic diagrams of the inlet and outlet structures, connections, controls, valves, bypasses, overflows, etc  List of manufacturer's operation, service and repair instructions and parts lists (where applicable)  Stage-storage-discharge relationship of all controls  General maintenance requirements and emergency procedures Schedule D - Stormwater 22 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Public Safety and Signage: All above ground storage facilities must be designed to maximize public safety. Interior side slopes must be 4:1 within the limits of the live storage volume. Side slopes above the live storage zone may be a maximum of 3:1. The design of storage facilities must include adequate provisions for installation of standard signage to warn of anticipated water level fluctuations, with demarcation of the expected maximum water levels for design conditions.  Performance Monitoring: Prior to final approval of all stormwater facilities, the Owner must prepare and submit to the City a written monitoring program to be conducted by the Owner for a period of 12 months following construction. Monitoring results are to be submitted to the City on a monthly basis for review. Adjustments to the control device must be required as necessary prior to the expiry of the 1-year warranty period. 1.11.2 Erosion and Sediment Control for Construction An erosion and sediment control plan must be provided by the Owner's Engineer prior to construction. The purpose of this plan is to prevent the release of silt, raw concrete, concrete leachate and other deleterious substances into any ditch, storm sewer, watercourse or ravine. Construction materials, excavation wastes, overburden soils, or other deleterious substances must be disposed of or placed in such a manner as to prevent their entry into any watercourse, ravine, Community Drainage System, or restrictive covenant area. All siltation control devices must be situated to allow for ready access for cleaning and maintenance. Siltation control structures must be maintained throughout the course of construction and to the end of the maintenance period (final acceptance). Changes in the design of the structure are required if the proposed structure is found to perform inadequately. At minimum, the control plan must provide the following:  Section I: Narrative:  Project description: A brief description of the nature and purpose of the land- disturbing activity and the amount of grading involved  Existing site conditions: A description of the existing topography, vegetation, and drainage  Adjacent areas: A description of neighbouring areas, such as streams, lakes, residential areas, and roads that might be affected by the land disturbance Schedule D - Stormwater 23 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw  Soils: A brief description of the soils on the site including erodibility and particle size distribution (texture)  Critical areas: A description of areas within the developed site that have potential for serious erosion or sediment problems  Erosion and sediment control measures: A description of the methods that will be used to control erosion and sediment on the site including, temporary erosion control and temporary sediment control measures  Permanent stabilization: A brief description of how the site will be stabilized after construction is completed  Maintenance: A schedule of regular inspections and repairs of erosion and sediment control structures, and the person responsible for maintenance  Section II: Details:  Detailed drawings: Enlarged dimensioned drawings of key facilities such as sediment basin risers, energy dissipaters, waterway cross-sections, and sediment barriers  Seeding and mulching specifications: Seeding dates, seeding, fertilizing, and mulching rates, and application procedures  Maintenance program: Inspection schedules, spare materials needed, stockpile locations, and instructions for sediment removal and disposal and for repair of damaged structures  Section III: Calculations:  Calculations and assumptions: Data for design storm used to size pipes and channels and sediment basins and traps (e.g., 5-year, 6-hour storm = 75 mm; intensity peak = 60 mm/hr), design particle size for sediment trap efficiencies, basin discharge rates, size and strength characteristics for filter fabric, wire mesh, fence posts, etc. and other calculations necessary to support drainage, erosion, and sediment control systems  Attachments: The erosion control plan must be accompanied by a grading plan 1.11.3 Rain Gardens All apartment developments in the Sustainable Neighbourhood - Special Policy Area must provide a rain garden. Design of the rain garden is the responsibly of the Landscape Architect hired by the Developer. Schedule D - Stormwater 24 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.12 Environmental Protection 1.12.1 Water Quality Protection Oil and grit separators must be installed for all storm connections from industrial parcels and in all parking lots. The separators must be sized to treat peak runoff flows from a 5-year rain event. 1.12.2 Slope Stabilization The implementation of stormwater management measures, combined with controls on land development adjacent to watercourses, is intended to minimize the impact on the receiving watercourses.  Setbacks: Disturbance too close to a slope bank can destabilize the bank material and contribute to bank failures. In addition to the environmental restrictions to working within the streamside protection area of a natural watercourse, no disruption to the native ground is permitted within a setback zone established by a 4:1 slope measured from the bottom of the slope. Detailed site investigations by a qualified Professional Geotechnical Engineer are required prior to the approval of any Subdivision or Development of disturbance within this setback zone.  Retention of Bank Vegetation: Existing vegetation along stream channel banks and within the established riparian setback must be retained, and the disposal of debris within this setback is prohibited. The working limits for the protection of the riparian setback must be clearly identified and flagged or fenced for the duration of construction.  Storm Outfalls: The number of storm outfalls into natural watercourses are to be minimized. All storm drains from private properties must connect to a Community Drainage System. Individual drains to natural watercourses are not permitted. 1.12.3 Channel Erosion Protection Bank protection must be constructed along existing and new open watercourses to provide adequate erosion protection in the form of bank armouring, soil stabilization, flow deflection and other methods applicable for the specific site conditions Schedule D - Stormwater 25 of 25 City of Dawson Creek Subdivision and Development Servicing Bylaw It is noted that any proposed works within the streamside protection area of an existing watercourse falls under the jurisdiction of the Provincial or Federal governments, and as such, is subject to their approval. 1.13 Testing Testing of installed pipes must consist of video inspection as outlined in the MMCD. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE D STORMWATER SCHEDULE E ROADS Schedule E - Roads 1 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE E - ROADS 1.0 ROADS .............................................................................................................................. 2 1.1 General ................................................................................................................................ 2 1.2 Road Classification ................................................................................................................. 2 1.3 Road Cross-Section Details ....................................................................................................... 3 1.4 Road Design Criteria ............................................................................................................... 4 1.5 Vertical Alignment .................................................................................................................. 5 1.6 Horizontal Alignment .............................................................................................................. 6 1.7 Cul-de-Sacs ........................................................................................................................... 6 1.8 Intersections ......................................................................................................................... 6 1.9 Sidewalks, Walkways, Multi-Use Pathways, Bicycle Facilities and Wheelchair Ramps .......................... 7 1.10 Curb Returns ......................................................................................................................... 8 1.11 Curb and Gutter ..................................................................................................................... 8 1.12 Driveways/Crossovers ............................................................................................................. 9 1.13 Regulatory and Information Signs ............................................................................................ 10 1.14 Appurtenances .................................................................................................................... 10 1.15 Pavement Structure .............................................................................................................. 11 1.16 Onsite Traffic Loaded Areas .................................................................................................... 15 1.17 Testing ............................................................................................................................... 15 List of Tables Table E1: Roadway Cross Section Details Table E2: Road Design Criteria Table E3: K Values Table E4: Curb Returns Table E5: Corner Clearance Table E6: Driveway Widths Table E7: Equivalent Single Axel Loads Table E8: Minimum Pavement Structures Table E9: 40mm Granular Subbase Gradation Schedule E - Roads 2 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 ROADS 1.1 General The Director of Development Services will consider the sufficiency and suitability of the proposed road system, the arrangement, width, grade and location of all roads in relation to existing and planned roads, to topographic features, to public convenience and safety, and to the proposed uses of the land to be served by such roads. The arrangement of roads in a Subdivision or Development must either:  provide for the continuation or appropriate projection of existing roads in surrounding areas; or  where topographic or other conditions make continuation or projection of existing roads impractical, provide an adequate and suitable roadway system having regard to the uses of the land to be served. The dimensions, locations and standard of all roads in a proposed Subdivision or Development must conform substantially to the Official Community Plan. The design parameters of all roads within the City must be in accordance with the Transportation Association of Canada's (TAC) most current edition of "Geometric Guide for Canadian Roads." Local residential roads must be aligned so that their use by through traffic will be discouraged. 1.2 Road Classification The existing roadway classifications within the City are described as follows:  Arterial Roadway - An arterial road has the primary function of carrying through traffic from one area to another with as little interference as possible from adjacent land uses. An arterial road may provide direct access to properties as a secondary function when alternate access is not available; however, this secondary function is discouraged  Collector Roadway - A collector road has the primary function of distributing traffic between arterial, other collector and local roads within an area. A collector road may also provide direct access to properties  Local Roadway - A local road has the primary function of providing direct access to properties. Local roads normally connect to other local roads or to collector roads Schedule E - Roads 3 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw  Alternate Urban Roadway - Alternate Urban Roadways are to be used in the Sustainable Neighbourhood - Special Policy Area as shown in Figure 1 of Schedule A - Works and Services Requirements. Some roadway classifications have been further divided into urban and rural classifications within this bylaw. Other road network components include:  Walkways and Pathways - Walkways and pathways are paths which follow routes independent from motor vehicle roadways, sidewalks and bike lanes. 1.3 Road Cross-Section Details The standard roadway cross-sections must be as shown in the Supplementary Detail Drawings and detailed in Table E1. The standard road cross-sections detailed in Table E1 and the Supplementary Detail Drawings applies to all roadways within the City. Where ambient conditions, (standards in existing and substantially "built-up" areas, steep topography, etc.) are not amenable to accommodate the required roadway standards a variance to these standards may be considered by the Director of Development Services. Schedule E - Roads 4 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw Table E1: Roadway Cross-section Details Facility Classification Detail Drawing # Right-of- Way (metres) Road Width (metres) Lane Width (metres) Parking Shoulder Curb Type Sidewalks (metres) Bicycle Facilities WALKWAYS AND PATHWAYS Multi-Use Path A15 N/A 3.0 N/A N/A N/A N/A N/A N/A LOCAL ROADWAYS Urban A1 20.0 10.0 2 - 5.0 Allowed N/A Rollover 1.5 one side Shared Asphalt Cul-de-Sac (Urban) A2 20.0 10.0 2 - 5.0 Allowed N/A Rollover 1.5 one side Shared Asphalt COLLECTOR ROADWAYS Urban A4 22.0 12.0 2 - 6.0 Allowed N/A Barrier 1.5 one side Shared Asphalt Commercial Urban A5 22.0 12.0 4 - 3.0 Allowed N/A Barrier 1.5 both sides N/A Industrial (Urban) A6 20.0 12.0 2 - 6.0 Allowed N/A Barrier 1.5 one side N/A Industrial (Rural) A7 25.0 8.5 2 - 4.25 N/A 1.5 Gravel N/A N/A N/A ARTERIAL ROADWAYS Arterial A3 27.0 14.0 2 - 7.0 N/A N/A Barrier 2.0 both sides side Shared Asphalt LANES Lane A13 6.0 6.0 N/A N/A N/A N/A N/A N/A ALTERNATE URBAN ROADWAYS (SUSTAINABLE NEIGHBOURHOOD) Neighbourhood Arterial A8 20.0 11.0 2 - 5.5 Allowed N/A Barrier 2.5 one side Shared Sidewalk Residential (Local) A9 20.0 10.0 2 - 5 Allowed N/A Rollover 1.5 one side Shared Asphalt Village Centre Road (Collector) A10 22.0 11.0 2 - 5.5 Allowed N/A Rollover 1.5 one side, 2.0 other side N/A Neighbourhood Arterial Stormwater A11 22.0 10.0 2 - 5.0 Allowed N/A Barrier & Rollover 2.0 one side 2.4 one side Residential (Local) Stormwater A12 20.0 9.0 2 - 4.5 Allowed N/A Rollover 1.5 N/A Where roadway cuts or fill sections extend beyond the right-of-way widths noted in Table E1, the right-of way must be widened accordingly. 1.4 Road Design Criteria All road classifications and designations for vertical and horizontal alignment elements must be designed utilizing the designated design speeds contained in Table E2, and in compliance with the most current edition of the Transportation Association of Canada - Geometric Design Guide Schedule E - Roads 5 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw for Canadian Roads. Road design criteria to be referenced from this document include superelevation, centreline radius, maximum grade, vertical curvature and sight distance. Table E2: Road Design Criteria Facility Classification Design Speed (km/h) Maximum Grade Desirable (%) Absolute (%) Asphalt Walkway N/A 10 15 Local Roadway 50 6 12 Collector Roadway 70 6 8 Arterial Roadway 70 5 8 1.5 Vertical Alignment The following must be considered when establishing the vertical alignment of a roadway:  The vertical alignment of roads must be set so the grades of the driveway to adjacent properties will conform to Section 1.12  The draining grade around the outside curb of a cul-de-sac must not be less than 0.5% and not greater than 5.0%. Longitudinal gradients of cul-de-sac bulbs must not exceed 5.0%  When a cul-de-sac is at the bottom of a hill, the longitudinal gradient of the first 50 m of roadway uphill from the cul-de-sac bulb must not exceed 5.0%. The maximum longitudinal gradient for the rest of the hill must not exceed 8.0%  When a cul-de-sac is at the top of a hill, the longitudinal gradient for the roadway downhill from the cul-de-sac must not exceed 12.0%  All changes in gradient over 1.0% on arterial and collector roads and over 2.0% on all other road classifications must be connected by vertical curves  Standard cross slopes (normal crown) must be 2% for local roads; standard cross slopes must be 3% for all other road classifications. Design road elevations must give due consideration to flood proofing requirements of adjacent properties. Full road crossfall (reverse crown) may be considered in special circumstances, as a means of more closely matching property grade on either side of the roadway  The length of a transition from a normal cross-sectioned road to a section of road where there is super-elevation or crossfall must, in no case, be less than 70 m for a 50 km/h designed road. In selecting the length of the transition, care and consideration must be given to draining all of the pavement. Typically, if no horizontal spiral curve is used, 60% of the super-elevation is introduced prior to the beginning of the curve, and the balance is developed in the curve Schedule E - Roads 6 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw  Gutter elevations on curb returns and cul-de-sacs must be shown on the drawings at the beginning, one-quarter points and end of curb returns and at 7.5 m intervals around cul-de- sacs 1.6 Horizontal Alignment The following must be considered when establishing the horizontal alignment of a roadway:  The horizontal centreline alignment of the road must be in accordance to the Supplementary Detail Drawings.  Typical locations of works and utilities in roads are shown on the Supplementary Detail Drawings.  Centreline chainage stations must be fully referenced and dimensioned from property lines.  Horizontal curves must be fully described showing internal angle, radius, tangent length and arc.  If reversed curves are required in a roadway alignment they must be separated by means of tangents of sufficient length  Where angular deflections occur in a roadway alignment, the angle must be replaced by a curve of suitable radius 1.7 Cul-de-Sacs Cul-de-sac bulbs must be used to terminate "no exit" roads. The following applies:  A maximum cul-de-sac length of 250 m is allowed, unless a secondary emergency vehicle access is provided at least halfway to the end of the cul-de-sac, in which case the length specification is not prescribed.  Cul-de-sac roads, designed to be permanent, must be provided at the closed end with an area designed to permit safe and adequate space for the turning of motor vehicles. The end treatment must be a cul-de-sac bulb. 1.8 Intersections 90º intersections are preferred by the City. Intersections that cannot conform to a 90º angle may be designed and located within the range of angles between 70º and 110º at the discretion of the Director of the Infrastructure. Schedule E - Roads 7 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw The minimum spacing between intersections must be designed as per TAC standards. Local Street Intersecting Arterials - Intersecting local streets must have a minimum width of 11 m for a distance of 20 m from the end of the curb return of the major street. Thereafter the road must taper at 30:1 to the design width of the local street. In the design of all street intersections, including those with lanes and walkways, the Professional Engineer must give consideration to providing adequate decision sight and stopping distances for conflicting traffic streams involving pedestrians, bicycles and/or vehicles. Line of sight at stop signs must consider all landscaping and utility installations. Vertical Curvature at Intersections - Providing the minor intersecting street is subjected to a "Stop" condition, the following K values, indicated in Table E3 may be used for the minor street. Table E3: K Values Classification Crest Sag Minimum Preferred Minimum Preferred Collector 4 6 4 6 Local 2 4 2 4 1.9 Sidewalks, Walkways, Multi-Use Pathways, Bicycle Facilities and Wheelchair Ramps Concrete sidewalks must be provided on roads in or adjacent to Subdivisions or Developments in accordance with Table E1 and the Supplementary Detail Drawings. The maximum grade for sidewalks must not exceed the maximum road grades. Concrete sidewalks must be 150mm thick with 150mm of 19mm crushed granular base at vehicle crossings and letdowns, and 100mm thick with 100mm of 19mm crushed granular base at all other locations. All base material to be compacted to 98% Standard Proctor Maximum Dry Density. Asphalt walkways must be provided for access through Subdivisions or Developments to schools, playgrounds, shopping centres, transit, and other community facilities. The dimensions, locations and standard of all trails in a proposed Subdivision or Development must conform substantially to the Official Community Plan. Schedule E - Roads 8 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw The maximum grade for walkways must not exceed 15%. Where walkways would otherwise exceed 15%, concrete stairs must be installed. Prior to the authorization of concrete stairs, alternate walk routes must be submitted for City review and approval. Only where other acceptable walk routes are not available will the installation of stairs be considered. Walkways must be designed as per the Supplementary Detail Drawings and must contain the following design parameters:  Minimum 300 mm depth of 19 mm crush gravel base compacted to 98% Standard Proctor Dry Density;  Minimum 150 mm concrete thickness at driveway letdowns  Minimum 100 mm concrete thickness at all other locations. Wheelchair ramps must be provided at all intersection curb returns as an integral part of the sidewalk or to link walkways and crosswalks. Design at the midpoint of the curb return. Bicycle facilities must be designed in accordance with the Transportation Association of Canada Geometric Design Guide. In the Sustainable Neighbourhood - Special Policy Area, a 3.0 m (minimum 1.5 m) wide perimeter trail must be provided along the Northern and Eastern edges of the site. Native trees and shrub species are required for the vegetated buffer. This trail must meet all Agriculture Land Reserve vegetated buffer requirements and/or guidelines. 1.10 Curb Returns The minimum radius of curb return at intersections must meet the requirements listed in Table E4. Curb returns located on roads within industrial and commercial areas may require a larger radius to facilitate truck and/or bus traffic. Table E4: Curb Returns Roadway Classification Curb Return Radii Arterial 11 m Collector 11 m Local 9 m When a new road with curbs intersects an existing road without curbs, full curb returns must be constructed. 1.11 Curb and Gutter Schedule E - Roads 9 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw Curb and gutters must be provided as specified in Table E1 and the Supplementary Detail Drawings. Minimum gutter grade must be 0.5% for all street classifications. 1.12 Driveways/Crossovers Each single family residential property must only have one driveway access per road frontage. Multi-family residential, commercial, and industrial properties must only have one driveway access per road frontage, unless there is a demonstrated need and approval is obtained from the Director of Development Services. Where a lot abuts a lane or road of different classification, the driveway must be located to access the lane or road of the lower classification. Driveway letdowns must be provided for each lot. At the discretion of the Director of Development Services, access to large parking areas must be by curb returns rather than a driveway letdown. The Director of Development Services may require deceleration and acceleration lanes for access off major roads for safety reasons and to minimize disruption to traffic flows. Driveway access grades must be designed to permit the appropriate vehicular access for the zone, without "bottoming-out" or "hanging-up". From edge of pavement to property line, the driveway grade must match the boulevard slope to encourage drainage towards the road. For the first 10 m on private property, the maximum allowable driveway grade is limited to 10%. Driveways must be located a minimum of 1 m from hydrants, poles, street lights, street signs, and property lines. Residential driveway access onto an arterial road is not permitted unless alternate access is impractical. Wherever physically possible, alternate local road access must be dedicated to preclude residential driveways accessing directly onto major roads. Driveway accesses serving corner lots must be in accordance to Table E5. Table E5: Corner Clearance* Schedule E - Roads 10 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw Road Classification Signalized Intersection (m) Unsignalized Intersection (m) Arterial 70 35 Collector 55 25 Local 5 5 *Clearance is measured from the intersection of the property lines at the corner. All driveway accesses must be in accordance to Table E6 and the Supplementary Detail Drawings. Table E6: Driveway Widths Zone Driveway widths Single family residential Minimum - 4.5m Maximum - 45% of lot frontage to a maximum of 9m Multi-family residential Minimum - 4.5m Maximum - 9m Commercial/Industrial Urban As approved by Director of Development Services Industrial Rural 4m - 10m (max culvert length - 12m) or as approved by Director of Development Services * see stormwater schedule for minimum culvert sizing 1.13 Regulatory and Information Signs Road name signs and traffic signs for new or improved roads must be provided and installed by the Owner to match the City's standard signage and naming convention. Sign details and locations are to be provided on the submitted drawings. 1.14 Appurtenances All proposed traffic islands, retaining walls, guard-rails, and permanent barricades must be designed in keeping with good engineering practices. Traffic control devices must be designed and installed in accordance with applicable and current City requirements. Schedule E - Roads 11 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw For all utility poles and anchors which require re-locating prior to road construction, the utility must confirm the feasibility of their re-location prior to design completion. All rock cuts, escarpments or retaining structures greater than 1 m high must be equipped with protective railings or fencing. 1.15 Pavement Structure 1.15.1 General Requirements: 1.15.1.1 Hot-Mix Asphalt or Reclaimed Asphalt Pavement (RAP) Pavement structures for Hot-Mix or Reclaimed Asphalt Pavement (RAP) must be designed by a qualified Professional Engineer in accordance with a commonly accepted design method (AASHTO, Asphalt Institute, etc.). The pavement must be designed to provide a 20-year design life. The parameters used for design must be based on site specific information which includes, but is not limited to the following:  Existing pavement surface conditions  Subsoil conditions  Groundwater & drainage conditions  Climate  Traffic Volumes Pavement structure designs must be submitted to the Director of Development Services for approval. 1.15.1.2 Warm-Mix Asphalt (WMA) Warm-Mix Asphalt (WMA) Pavement is a generic term used to describe the reduction of the production, paving, and compaction temperatures achieved through the application of one of several WMA technologies. WMA may be achieved by one or a combination of several technologies involving HMA plant foaming and equipment, mineral additives, or chemicals that allow the reduction of mix production temperatures to within 85°C to 130°C. Pavement structures for WMA must be designed by a qualified Professional Engineer in accordance with a commonly accepted design method (AASHTO, Asphalt Institute, etc.). The pavement must be designed to provide a 20-year design life. Schedule E - Roads 12 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw The parameters used for design must be based on site specific information which includes, but is not limited to the following:  Existing pavement surface conditions  Subsoil conditions  Groundwater & drainage conditions  Climate  Traffic Volumes Pavement structure designs must be submitted to the Director of Development Services for approval and must contain the following information:  WMA technology and/or WMA additives information  WMA technology manufacture's established recommendations for usage  WMA technology manufacturer's established target rate for water and additives, the acceptable variation for production, and documentation showing the impact of excessive production variation  Temperature range for mixing  Temperature range for compacting  Asphalt binder performance grade test data over the range of WMA additive percentages proposed for use During installation, the temperature of mix upon placement must not be less than the effective spreading and compaction temperature of the warm mix asphalt mix. 1.15.2 Field and Laboratory Investigations: A subsurface exploration program must be completed to a depth of at least 3.0 m below existing and proposed finished roadway surface grades. At least one exploratory borehole and/or test pit must be made at intervals of no more than 150 m along the proposed horizontal alignment. Insitu testing must be completed, representative soil samples collected, and laboratory testing carried out as necessary to determine the engineering properties and characteristics of the subgrade materials. The minimum laboratory testing requirements include natural moisture content determinations and grain-size analyses and/or Atterberg limit determinations as appropriate to characterize the site subsoils for design purposes. Schedule E - Roads 13 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw Groundwater levels that may influence the roadway performance must be determined at the time of the investigation and seasonal fluctuations should be estimated. 1.15.3 Design Parameters: On the basis of the gathered information, a soaked California Bearing Ratio (CBR) value must be determined or estimated for use in design of the pavement structure. A Resilient Modulus may be approximated from the CBR value using the relationship: MR (Mpa) = 10.3*CBR The plasticity of the subgrade soils determined in the laboratory must be reported (swelling/shrinking potential). The frost susceptibility of the soils must be considered in the design. 1.15.4 Minimum Pavement Design: In the absence of traffic volume data, the roads must be classified, as indicated in Table E7, with the associated Equivalent Single Axle Loads (ESAL) for the purposes of pavement structure design: Table E7: Equivalent Single Axle Loads Road Classification Design Traffic (ESAL) Arterial 1.0 x 106 Collector 2.8 x 105 Industrial 1.0 x 106 Local 2.0 x 105 In the event that the CBR value soaked CBR value is less than 3, the subgrade must be enhanced to provide a CBR value of 3 to be used for the pavement structure design calculations. Irrespective of calculated requirements, the Table E8 indicates the minimum values for pavement structure component thicknesses for all roadways where:  the subgrade CBR value is greater than or equal to 6; and Schedule E - Roads 14 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw  the subgrade soils are not frost susceptible within 1500 mm of the finished paved surface or groundwater is at least 1.5 m below the proposed subgrade surface. Table E8: Minimum Pavement Structures Road Classification Subbase 1 40mm (minus) (mm) Base 2 19 mm (minus) (mm) Hot and Warm Mix Asphalt Surface Course 3 (mm) Arterial 500 75 100 (2 lifts) Collector 450 75 75 Industrial 450 75 75 Local 350 75 75 Lanes 350 75 75 Asphalt Walkways 150 75 50 (1) 40mm Granular Subbase as per Table E9 gradation (2) MMCD Granular Base (3) MMCD Upper Course #1 for hot mix Table E9: 40mm Granular Subbase Gradation Sieve Designation Percent Passing 37.5 mm 100 25 mm 70 - 94 19 mm 58 - 88 12.5 mm 44 - 77 9.5 mm 35 - 74 4.75 mm 25 - 62 1.18 mm 14 - 43 0.600 mm 8 - 34 0.300 mm 5 - 26 0.150 mm 2 - 18 0.075mm 2 - 10 Road subgrades must be compacted to 95% Standard Proctor Maximum Dry Density. For sugbrade fills due to over-excavation compaction requirement must be 98% Standard Proctor Maximum Dry Density. Subgrade fill lifts must be no larger than 150mm thickness unless approved by a Professional Engineer. Non-woven geotextile and geogrid must be placed on the Schedule E - Roads 15 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw prepared subgrade. Subgrade drainage must be provided using perforated drain piping wrapped in a geotextile sock. The granular subbase must be placed and compacted to 98% Standard Proctor Maximum Dry Density. The granular base must be placed and compacted to 100% Standard Proctor Maximum Dry Density and must be placed in lifts no larger than 300mm thickness or as approved by a Professional Engineer. A Geotechnical Professional Engineer must be retained by the Owner to provide a geotechnical design, provide geotechnical testing recommendations and approve all geotechnical testing performed on the Works & Services. Pavement structure designs must be submitted to the Director of Development Services for approval. Trenches and excavations made within existing roadways and under existing sidewalks and curb and gutter must be backfilled to top of existing asphalt with a non-shrink fill, such as fillcrete. The excavation is to be capped shortly thereafter with an asphalt patch of thickness conforming to Table E8 of this section and the cap is to be made a smooth transition to the existing road surface with no reduction in the quality of the ride of the road. The non-shrink fill must have a compressive strength between 0.5MPa and 2MPa and must be allowed to cure for 24 hours prior to allowing traffic loading. The excavation may be backfilled to top of existing asphalt less the thickness of the asphalt patch if the excavation is to be capped with asphalt within 36 hours of the non-shrink fill being installed or if approved by the Director of Development Services. 1.15.5 Construction Recommendations: Recommendations related to roadway construction must be provided by the Owners Professional Engineer. The recommendations should address:  Subgrade preparation and enhancement  Long-term drainage and erosion and sediment control  Road structure materials requirements  Construction methods and procedures 1.16 Onsite Traffic Loaded Areas This Schedule applies to all onsite roads infrastructure including but not limited to parking areas, sidewalks, walkways, driveways and permanent and temporary vehicle accesses. 1.17 Testing Schedule E - Roads 16 of 16 City of Dawson Creek Subdivision and Development Servicing Bylaw Compaction testing must be completed by the Owner, at the Owner's cost, to ensure compliance with this bylaw and MMCD specifications. Prior to paving or placement of concrete curb, gutter and sidewalk, copies of test results must be provided to the City. In addition to compaction testing, proof rolls of the prepared base and subbase must be completed as per MMCD specifications, prior to paving or placement of concrete curb, gutter and sidewalk. Proof rolls must be witnessed by City staff. The Owner must provide no less than 24 hours notice to City staff of the intent to complete a proof roll. Any work requiring the supervision or assistance of City staff must be completed during regular City business hours, Monday to Friday. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE F STREET LIGHTING Schedule F - Street Lighting 1 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE F - STREET LIGHTING 1.0 STREET LIGHTING ................................................................................................................. 2 1.1 General ............................................................................................................................. 2 1.2 Luminance Levels ................................................................................................................ 2 1.3 Light Pole Spacing ................................................................................................................ 2 1.4 Luminaires, Poles and Light Source .......................................................................................... 3 1.5 Lighting Calculations ............................................................................................................ 4 1.6 Traffic Signals ..................................................................................................................... 5 1.7 Conduit ............................................................................................................................. 5 1.8 Junction Boxes .................................................................................................................... 6 1.9 Conductors ........................................................................................................................ 6 1.10 Service Equipment ............................................................................................................... 7 1.11 Bases ................................................................................................................................ 7 List of Tables Table F1: Streetlight Pole Locations Table F2: Luminaire Lighting Table F3: Total Light Loss Factor Schedule F - Street Lighting 2 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 STREET LIGHTING 1.1 General Design of street lighting systems must be prepared by a qualified Professional Engineer, fully knowledgeable with the current Transportation Association of Canada (TAC) "Guide for the Design of Roadway Lighting" and the MMCD Volume II. Obtrusive light, light trespass, light pollution and environmental zones are key project design issues that will be considered by the City. The Professional Engineer will utilize luminaires and design techniques that will mitigate these issues. All light fixtures must have full cutoff optics. 1.2 Luminance Levels Roadways will be illuminated to produce accurate and comfortable night time visibility and safety. Pedestrian walkways and bikeways may require illumination if requested by the Director of Development Services. The recommended minimum average maintained horizontal luminance levels; uniformity ratios and veiling luminance ratios used by the City are listed in the current TAC "Guide for the Design of Roadway Lighting". Illuminance method can be used for pedestrian walkways and bikeways and where a specific circumstance warrants its use such as curved roadways. Prior to starting a project, the Professional Engineer will verify the road classification (i.e.; arterial, collector, local etc) and the pedestrian activity classification with the Director of Development Services. Definitions of these terms may be found in the current TAC "Guide for the Design of Roadway Lighting". The road classifications, luminance levels, ratios, road and pedestrian activity areas proposed will be listed in a table format on the design drawings. The Professional Engineer will calculate all luminance levels and ratios as noted under Section 1.5 - Lighting Calculations. For calculations where the roadway surface is asphalt, R3, Road Surface Classification will be used. 1.3 Light Pole Spacing Spacing and location of poles will be governed by road width, road configuration, intersecting property lines, luminaire photometrics, mounting heights and recommended lumination levels. Maintain clearances to overhead and underground utilities in accordance with MMCD specifications and standards. The Canadian Electrical Code, Work Safe BC and the BC Electrical Safety Act will also govern pole spacing and height. Schedule F - Street Lighting 3 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw Poles will be generally arranged in a one sided, staggered or opposite spacing based on the road classifications listed in Table F1 in this Section. In circumstances where overhead lines are in conflict with street light poles, one sided spacing may be considered if the required illumination levels and ratios can be achieved. Alternative pole spacing to those listed in Table F1 must be acceptable to the Director of Development Services. Where possible, poles will be located close to property lines and will avoid being placed in front of residential windows. Where sidewalks are present, street light poles will be offset 0.3 m behind back of sidewalk. Where sidewalks are not present, street light poles will be offset 0.5 m behind back of curb. Alternative offsets require the acceptance of the Director of Development Services. On existing roadways where the standard offsets cannot be maintained due to underground utility conflicts, the Professional Engineer will make recommendations for alternate locations to the Director of Development Services and obtain acceptance prior to proceeding. Luminaires will be installed on all signal poles to maximize intersection illumination. The pole spacing at intersections will therefore be governed by the signal pole locations. Additional street light poles may be required to meet the required lighting levels. Table F1: Streetlight Pole Locations Road Type Pole Location / Spacing Arterial Opposite or Staggered Collector Spaced on One Side of Road Industrial Urban Spaced on One Side of Road Local Spaced on One Side of Road Walkways & Pathways Entrance & Exit Points 1.4 Luminaires, Poles and Light Source Luminaire type and pole type are as listed in Table F2. When expanding an existing street lighting system, the wattage and mounting height should match those previously installed, if the road classification and pedestrian conflict area are identical; unless otherwise accepted by the Director of Development Services. New luminaires must have full cut-off optics. Luminaire wattage, distribution type and voltage will be noted on the engineering drawings. The preferred operating voltage for the street lighting system is 120/240V. Schedule F - Street Lighting 4 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw Alternative voltages will require acceptance by the Director of Development Services. Streetlighting poles in residential areas must be decorative type as noted on the City's Approved Products List. All luminaires will be flat glass, IESNA full cutoff type. Alternative cutoff classifications must be acceptable to the Director of Development Services. The Professional Engineer will select the most effective IESNA luminaire distribution type (i.e. Type 2, Type 3 etc.) to suit the roadway geometrics. Cobra head luminaires will be used for all roadway lighting as noted on the City's Approved Products List. Exact luminaire used in lighting calculations must be shown on design drawings. The light source for luminaires must be light-emitting diode (LED). For development projects requiring pedestrian walkway/bikeway lighting, the cost for the supply and installation of luminaires, mounting arms and lamps will be borne by the Owner. The Professional Engineer will consult with the Director of Development Services for specific fixture type, colour and model number information. Table F2: Luminaire Lighting Pole Height & Type 11.0 m Davit Pole Cobra Head Luminaire 9.0 m Davit Pole* Cobra Head Luminaire 9.0 m Decorative Pole Cobra Head Luminaire 6.0 m Decorative Pole Cobra Head Luminaire Road Classification Arterial Roads Arterial Roads Collector Roads Industrial Urban Roads Local Roads Walkways & Pathways (*) Shorter 7.5m Davit Poles may be used to avoid conflicts with overhead lines if accepted by the Director of Development Services. For rural standard roads, coordinate with the local hydroelectric company to arrange for streetlighting on utility poles. 1.5 Lighting Calculations Lighting calculations will be carried out as follows:  Lighting calculations are based on the luminance methods described in the current TAC "Guide for the Design of Roadway Lighting". Lighting calculations will be completed using Schedule F - Street Lighting 5 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw suitable computer lighting design software designed to carry out the required calculations by inputting the luminaire manufacturers IESNA formatted photometrics. The IESNA photometric files for the City accepted luminaires are available in electronic format through the specific luminaire manufacturer(s) web sites or local supplier.  Computer lighting calculations for walkways and bikeways (where required) will be undertaken as described in the current TAC "Guide for the Design of Roadway Lighting".  Lighting calculations will be based on maintained levels using initial rated lamp lumens and the total light loss factor (TLLF) of 0.72. Refer to Table F3 for the factors included in the TLLF. The TLLF will be considered as the total maintenance factor.  The Director of Development Services may require a printed copy of the computer lighting calculations from the Professional Engineer. Table F3: Total Light Loss Factor Lamp Lumen Depreciation (LLD) (1) Lamp Dirt Depreciation (LDD)(1) Lamp Component Depreciation (LCD)(2) Equipment Factor (EF)(3) Total Light Loss Factor (TLLF)(4) 0.82 0.94 0.98 0.95 0.72 Notes: (1) Based on a 5 year maintenance schedule (2) Degradation of the reflector and refractor (3) Effect of ambient temperature on the lamp including the ballast and lamp factors (4) TLLF = LLD x LLD x LCD x EF 1.6 Traffic Signals Traffic signal designs are highly specialized and, if traffic signals are required for a Subdivision or Development, will therefore be prepared by a Professional Engineer qualified in this area of expertise. Traffic signals will be designed in general accordance with Sections 402.6 of the Ministry of Transportation Electrical and Traffic Engineering Manual. Traffic signal designs will also conform to the British Columbia Motor Vehicle Act and the Manual of Uniform Traffic Control Devices for Canada. Traffic engineering and timing/coordination plans will be provided by the Owner and prepared by a qualified traffic Consulting Engineer with PTOE certification. 1.7 Conduit Conduit design for street lighting and traffic signals will conform to the following criteria: Schedule F - Street Lighting 6 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw  Conduits will generally be parallel or perpendicular to the roadway, and routed to run in a direct line between adjacent poles or junction boxes. The exception would be where existing or proposed trees conflict with the conduit run.  There will be a maximum four (4) 90° bends in a conduit run. Where this cannot be avoided junction boxes will be used as noted under Section 1.8 - Junction Boxes.  Street lighting conduits will be minimum 30mm diameter rigid polyvinyl chloride (RPVC). Signal conduits will be minimum 50mm RPVC and minimum 25mm RPVC for loop stub-outs.  Where conduits cross an existing road, they will be installed by a suitable trenchless technology to avoid cutting pavement and interrupting traffic. Prior to specifying trenchless technology, confirm that the site specific soil conditions are suitable. Open cutting of existing roadways is only permitted at the discretion of the Director of Development Services. 1.8 Junction Boxes The design of junction boxes for street lighting and traffic signals will conform to the following criteria:  Large round plastic junction boxes (2 sections deep) with galvanized steel lids will generally be used: where the maximum number of 90° bends in a conduit run is exceeded, where branch conduit runs are required, in conduit runs over 100 metres in length, and at service panels.  Concrete junction boxes with galvanized steel lids can be used for installations in sidewalks or hard landscape areas.  Large concrete junction boxes with galvanized steel lids will be used for traffic signal installations only in the quadrant where the traffic controller is to be installed. 1.9 Conductors The design of conductors for street lighting and traffic signals will conform to the following criteria:  For the purpose of standardization and to accommodate future expansion, street lighting feeder conductors will be No. 6 RW90. The use of alternate conductor sizes will require the acceptance of the Director of Development Services.  For traffic signal installations, multi-conductor cable will be used. The cable will run continuously from the traffic controller to each pole with no splices.  All conductors must be stranded copper. Schedule F - Street Lighting 7 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.10 Service Equipment Street lighting and traffic signal service equipment will be designed with the following items being taken into consideration:  The Professional Engineer will confirm service locations with the local hydroelectric utility company.  Street lighting systems are controlled with a lighting contactor and photocell. The photocell will be located on the luminaire nearest the service panel.  Service panels for street lighting systems will have a 40 Amp - 2 Pole breaker, contactor and photocell bypass switch and will be mounted in a service base as shown on the MMCD Standard Detail Drawings. Smaller size service panels must be accepted by the City and must be detailed on the drawings in the form of a "Wiring Diagram" or "One Line" Diagram.  Where possible, traffic signal and street lighting systems will be fed from the same service panel. The combination street lighting and traffic signal service panel will have a 100 Amp -2 Pole main breaker, sub-breakers, contactor and photocell by-pass switch. The service panel will be mounted in a service base or on the side of a street light pole or post located near the traffic controller. No other signal equipment will be mounted on the same pole as the service panel. Refer to the MMCD Standard Detail Drawings.  All services will be 120/240V single phase, 3 wire. Alternative service voltage must be accepted by the Director of Development Services. 1.11 Bases The design of bases for street lighting and traffic signal pole installations will take the following items into consideration:  When selecting pole base locations, search out proposed or existing utility locations and identify sensitive tree root zones to avoid conflicts. The pole base will be positioned outside the drip line of trees proposed for retention. The Professional Engineer will coordinate the design with a Landscape Architect where applicable.  For traffic signal poles, the Professional Engineer will select a concrete base to suit the required pole from those shown in the MMCD Standard Detail Drawings. Where a customized base is required to accommodate unusual soils conditions, or to avoid underground utilities and sensitive tree root zones, the customized base design will be prepared by a qualified Professional Engineer. The design must also be acceptable to the Director of Development Services. Schedule F - Street Lighting 8 of 8 City of Dawson Creek Subdivision and Development Servicing Bylaw  All pole height and type indicated in Table F2, as well as all other styles of lamp standards will be installed on screw pile or concrete bases. The base design will be prepared by a qualified Professional Engineer and must be acceptable to the Director of Development Services.  Avoid running more than two conduits into a street light pole base. Where this situation cannot be avoided, a junction box will be used. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE G LANDSCAPING Schedule G - Landscaping 1 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE G - LANDSCAPING 1.0 LANDSCAPING ..................................................................................................................... 2 1.1 Objectives .......................................................................................................................... 2 1.2 Related Standards ............................................................................................................... 2 1.3 Application of Standard ........................................................................................................ 2 1.4 Landscape Consultant ........................................................................................................... 2 1.5 Landscape Plan ................................................................................................................... 2 1.6 Landscape Requirements ...................................................................................................... 3 1.7 Retaining Walls ................................................................................................................... 4 1.8 Stormwater Management Facilities ......................................................................................... 4 1.9 Erosion Control ................................................................................................................... 5 List of Tables Table G1: Sustainable Neighbourhood Tree Requirements Table G2: Rates of Application of Hydraulic Mulch with Tackifier Additive Table G3: Stormwater Management Requirements Schedule G - Landscaping 2 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 LANDSCAPING 1.1 Objectives These design standards are intended to enhance the safety, aesthetics and sustainability of public lands and to ensure efficiency and effectiveness of maintenance and operations of these lands. 1.2 Related Standards This standard must be referenced to and integrated with, at minimum, the following:  BC Landscape Standard, Current Edition  National Guide to Sustainable Municipal Infrastructure (Canada)  Irrigation Association - Turf and Landscape Irrigation Best Management Practices 1.3 Application of Standard These standards apply to the following areas:  Boulevards  Public walkways and access routes  Stormwater management facilities  Parks 1.4 Landscape Consultant The Owner must retain a Landscape Consultant to be directly supervised by a Landscape Architect or a Registered Irrigation Designer. All landscape drawings and specifications must be sealed by a professional Landscape Architect. 1.5 Landscape Plan The Landscape Designer must consider, at minimum, the following criteria:  The functional relationship of the landscape design to existing and proposed land uses, utilities, flood patterns, drainage facilities, roads, driveways and pedestrian facilities Schedule G - Landscaping 3 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw  Accessibility as it relates to pedestrians, cyclists and people with limited physical or visual abilities  Horticultural use of plant material, including plant suitability, survival rate, growth habit, size, disease resistance and water demand  Appearance of the proposed plant material and site landscape, including appropriateness, aesthetics, visual screening and sight lines  Protection of existing trees  Protection of the natural environment and restoration or enhancement of natural habitat  Site drainage, water levels, ponding and overland flow  Minimization of the opportunity for crime and undesirable behaviour  Weed control  Erosion control  Fire hazard reduction  The estimated costs and efficiency of maintenance practices that will be required for the public land  Restoration of disturbed areas 1.6 Landscape Requirements In boulevards within urban public road right of ways, the area from the back of curb or back of sidewalk to the front property line must be graded as per the site grading plan. Minimum landscaping by the Owner must consist of 100 mm of topsoil to property line. For rural road right of ways, minimum landscaping by the Owner must consist of 100 mm of topsoil to property line and seed. Trees must be installed on private property as per the Supplementary Detail Drawings and meet the list of approved species. The landscape plan must identify the proposed location for each tree to avoid conflict with any utilities, appurtenances, or driveways. Developments in the Sustainable Neighbourhood - Special Policy Area must provide trees as detailed in Table G1. Approved species, planting sizes and best practices are outlined in Supplementary Detail Drawing G10. Table G1: Sustainable Neighbourhood Tree Requirements Schedule G - Landscaping 4 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw Road Classification Requirement Neighbourhood Arterial One Side Residential (local) Roads not within one block of the reserve site At least one side Residential (local) Roads within one block of the reserve site Both sides Grass seed must be a mixture of 60% creeping red fescue, 20% perennial ryegrass and 20% Kentucky bluegrass or approved equivalent. All seed to meet requirements of Canada Seed Act for Canada No. 1 seed. Mechanical and hand application rates for this mixture are a minimum 240 kg/ha. Hydraulic mulch material to consist of approved grass seed, mulch and tackifier with application rates as detailed in Table G2. Sod is an approved equivalent to mechanical or hydraulic seeding. Table G2: Rates of Application of Hydraulic Mulch with Tackifier Additive Grass Seed Mulch Tackifier 55 kg/ha 2500 kg/ha 7 kg/ha For public access routes, walkways and parks, minimum landscaping by the Owner must consist of:  100 mm of topsoil and hydroseed  Perimeter fencing where required by the Director of Development Services  Lighting where required by the Director of Development Services 1.7 Retaining Walls Retaining walls on all residential lots, except those required as a condition of subdivision approval, must not exceed a height of 1.2 m measured from grade on the lower side, and must be constructed so that any retaining walls are spaced to provide at least a 1.2 m horizontal separation between them and setback 1.2m from the parallel property line. 1.8 Stormwater Management Facilities Landscape requirements for dry detention stormwater facilities must consist of the following:  The bottom of dry ponds and infiltration basins must be turf on 50 mm depth smooth growing medium  Side slopes with a 4 (horizontal) to 1 (vertical) or shallower slope must have a turf surface on 50 mm minimum depth smooth growing medium. Side slopes steeper than 4 (horizontal) to 1 (vertical) slope must be naturalized with low maintenance riparian plantings in 100 mm minimum depth growing medium. Schedule G - Landscaping 5 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw  Above the design high water level the ground surface must be turf on 50 mm depth smooth growing medium, with a maximum slope of 4 (horizontal) to 1 (vertical), except as required for vehicle access and pedestrian surfaces  Shrubs and trees must be selected, planted and maintained to provide screening, habitat, shade and aesthetics as required  Residential land uses in the Sustainable Neighbourhood - Special Policy Area are subject to the stormwater management design requirements as per Table G3. Table G3: Stormwater Management Requirements Designation Required Stormwater Management Country Residential absorptive topsoil (457 mm) Single Family Village Residential absorptive topsoil (457 mm) Multi Family Village Residential absorptive topsoil (457 mm) extra area allowed for rain gardens on lots that are across the street and down slope from single family lots absorptive topsoil (457 mm) absorptive topsoil (457 mm) Apartment Residential absorptive topsoil (457 mm) Site drains to rain garden for 6 month storm (31 mm) 1.9 Erosion Control Land proposed as public land where there is evidence of active or historic erosion that may have maintenance or liability implications for the City will not be accepted by the City as public land. The Owner is responsible for undertaking erosion control and restoration works on proposed public land as necessary for the long-term prevention and control of erosion. The Owner must develop an erosion and sediment control plan for construction in accordance to Schedule D - Stormwater. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE G LANDSCAPING SCHEDULE H SITE GRADING Schedule H - Site Grading 1 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE H - SITE GRADING 1.0 SITE GRADING ..................................................................................................................... 2 1.1 General ............................................................................................................................. 2 1.2 Site Grading Plans ................................................................................................................ 2 1.3 Geotechnical Evaluation ........................................................................................................ 3 1.4 Design Criteria - Lot Grading .................................................................................................. 4 1.5 Design Criteria - Swales ........................................................................................................ 4 1.6 Siltation Abatement and Erosion Control .................................................................................. 5 1.7 Site Preparation .................................................................................................................. 6 1.8 Compaction ........................................................................................................................ 6 1.9 Detailed Site Surveys ............................................................................................................ 6 Schedule H - Site Grading 2 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 SITE GRADING 1.1 General The Owner must execute site grading work in accordance with the regulations, standards and specifications set out in this Schedule. Site grading must ensure proper drainage of individual properties and establish an effective surface drainage system for the whole Subdivision or Development area as part of the major drainage system. Supplemental to the requirements for drainage systems outlined in Schedule D of this bylaw, the Owner must design site grading and drainage works to:  Accommodate drainage from adjacent areas (including off-site areas) through the site  Accommodate drainage generated on-site  Avoid drainage from one lot to another  Mitigate groundwater problems  Mitigate soil erosion potential  Produce buildable lots that provide:  access from fronting roadways  drainage from each lot and into drainage infrastructure  structural competence of undisturbed and embanked soils to support building loads 1.2 Site Grading Plans Prior to commencement of construction, site grading plans prepared by the Owner's Professional Engineer must be submitted to the Director of Development Services for approval. These site grading plans are to include the following information:  Clearing and grubbing boundaries  Fill and excavation areas (by shading) including structural fill areas and any required retaining walls  Locations of required siltation abatement and control measures  Predevelopment topography - Showing existing contours within the Subdivision or Development and extending into the adjacent lands, at a maximum 0.5 m interval as well as arrows showing natural flow paths. Schedule H - Site Grading 3 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw  Post development topography - Showing proposed contours within the Subdivision or Development and extending into adjacent lands, at a maximum 0.5 m interval as well as arrows showing natural flow paths  Representation of the major conveyance system - The nature and detail of the major conveyance system is to be shown, including all major drainage flow directions, ponding areas and the extent and maximum depth of ponding anticipated for a 1 in 100 year return frequency rainfall event. The overall major drainage flow route is to be clearly defined and designated with prominent arrows. Include the direction of surface flows on all surfaces and elevations of overflow points from local depressions, details of channel cross sections etc.  Surface slopes of roadways and other surfaces with arrows indicating the direction of flow.  Proposed or existing elevations along the boundaries of the Subdivision or Development and design elevations at all lot corners and changes of surface slope along property boundaries.  Lot drainage pattern - The direction of surface drainage for each lot is to be identified, to indicate whether split drainage or through drainage is contemplated. Proposed surface drainage for abutting future lands is to be shown to the extent that it will impact on the subject lands.  Lot grading details - Typical detail diagrams of the various types of lot grading arrangements, which will normally conform to the figures provided in the Supplementary Detail Drawings G11 & G12, are to be used, identifying for each lot which typical detail applies.  Minimum finished ground elevations (adjacent to future building foundations) must be specified for each lot.  Swale details including locations, easement requirements, slopes, cross sections and construction details for the swales.  Easements and restrictive covenants - Requirements and locations for all easements and restrictive covenants related to drainage provisions and development restrictions associated with the drainage of the property. 1.3 Geotechnical Evaluation The Owner must engage the services of a qualified Professional Geotechnical Engineer to investigate surface soil and sub-surface conditions with respect to site grading within the proposed subdivisions. The Professional Geotechnical Engineer must prepare a report outlining his findings and must provide clear, definitive recommendations on the geometry and placement of fill sections, compaction requirements for structural and non-structural fills, cut and fill slope geometry handling of topsoil and any other geotechnical issues affecting site grading construction within the proposed subdivision or development. A copy of the geotechnical evaluation must be submitted to the Director of Development Services at the time the engineering drawings are submitted for approval. Schedule H - Site Grading 4 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.4 Design Criteria - Lot Grading Refer to Supplementary Detail Drawings G11, G12 and G13 for typical lot grading details. Wherever possible, lots must be graded from rear to front, towards roadways. Split drainage or front to rear drainage will be permitted only where site topography prohibits drainage to roadways. In this situation, portions of lots may be graded to a drainage swale that is then graded to convey drainage to a public right of way. See Section 1.5 for detailed swale design criteria. Property line elevations must be established such that lots have maximum overall slopes of 15% and minimum overall slopes of 2%. Areas around buildings (or proposed building sites) must be graded away from the (proposed) foundations to prevent flooding. Finished building elevations must be established such that the ground will slope away from the building at a minimum of 10% for a distance of 2.0 m (or to the property line), on all sides, with the slope directing drainage away from the building. The lot grading must then provide for minimum slopes in the order of 1.5% to 2.0% from all points within the property to the property boundaries, from which the drainage may escape. Finished ground elevations adjacent to (proposed) foundations must be located a minimum of 300 mm above the maximum flow or ponding surface elevations for the 1:100 year major storm event. The Owner must ensure that builders are informed of any potential problems or restrictions respecting building design and lot grading. The site grading plan and covenants will be used as the principle means by which this information is communicated. 1.5 Design Criteria - Swales A swale is a shallow sloped linear depression for conveyance of surface runoff. Drainage swales must be located in an easement and protected by registration of a covenant on the lot title. For grassed swales serving lots on one side only:  Location: Rear of upstream lot in a 3.0 m easement  Cross Section: V-shape, 150 mm minimum depth and 4H:1V maximum side slope  Longitudinal slope: 1.5% minimum For grassed swales serving lots on both sides:  Location: Common rear property line as centre of a 6.0 m easement. Schedule H - Site Grading 5 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw  Cross-section: Trapezoidal with 1.0 m bottom, 150 mm minimum depth and 4H:1V maximum slope.  Longitudinal slope: 1.5% minimum Concrete swales or alternate configurations may be considered where minimum slope requirements for grassed swales cannot be achieved or when swales are located within existing developments or at locations where infill development is proposed. Additional swale design criteria include:  Swales must have capacity to contain the 1:100 year storm major flow within the easement  Where swales intersect walkways, provide a catchbasin upstream of walkways to intercept the 1:5 year storm flow.  The number of lots draining to swale is dependent on the swale capacities and the catchbasin's 1:5 year storm flow inlet capacity.  Avoid bends greater that 45 degrees in swale alignments where possible.  Swales that convey flows from more than two lots must not be routed along the side yard of a single family or duplex residential lot.  Future swale extensions must be identified and evaluated to ensure that anticipated constraints and capacities are addressed. Calculations for the swale's minor and major flow capacities must be submitted with the Professional Engineer's drawings. 1.6 Siltation Abatement and Erosion Control Siltation abatement and erosion control works must be designed and implemented during construction in accordance with the requirements specified in Schedule D - Stormwater. Schedule H - Site Grading 6 of 6 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.7 Site Preparation All areas of the site where excavations or embankments are to be constructed must be cleared of trees, structures and debris; grubbed; and stripped of organic topsoil. 1.8 Compaction Unless specified otherwise by the Professional Geotechnical Engineer all non structural embankments must be compacted to a minimum 95% Standard Proctor maximum dry density. Compaction requirements for structural embankments are to be specified by the Owner's Professional Geotechnical Engineer. 1.9 Detailed Site Surveys Detailed site surveys are required throughout the site and of relevant areas beyond the site to ensure grading meets requirements. The Owner must rough grade all lots to within 150 mm of the proposed grading plan elevations along the perimeter of lots and construct all swales to within 150 mm of the proposed grade. Final lot grading and landscaping will be enforced through the building permit process. An as-built plan showing lot and swale elevations surveyed after rough grading must be submitted as a prerequisite to the issuance of the Certificate of Provisional Completion of All Works. City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE I QUALITY CONTROL Schedule I - Quality Control 1 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE I - QUALITY CONTROL 1.0 QUALITY CONTROL AND ASSURANCE ....................................................................................... 2 1.1 Engineering Requirements .................................................................................................... 2 1.2 Construction Requirements ................................................................................................... 3 1.3 Quality Control and Assurance Plans ........................................................................................ 3 Schedule I - Quality Control 2 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 QUALITY CONTROL AND ASSURANCE This Schedule sets out the City's minimum standards for quality in design, quality in construction and quality in record-keeping for the Works and Services to be designed and constructed in accordance with this bylaw. 1.1 Engineering Requirements The Owner must demonstrate to the satisfaction of the Director of Development Services that the Owner has retained or will retain the services of a Professional Engineer to undertake the design, inspection, testing and record-keeping for the Works and Services. The Owner must complete and provide the Director of Development Services with the following information in an Owner/Professional Engineering confirmation letter to demonstrate that the Professional Engineer is qualified to undertake the Works and Services and more particularly, has successfully undertaken projects similar in scope, nature and value to the Works and Services:  The name and address of the Professional Engineer and a summary of the projects that the Professional Engineer has undertaken that are similar in scope, nature and value to the Works and Services.  The names of the individuals assigned to various aspects of the project by the Professional Engineer together with a summary of the projects that the individual Professional Engineers have undertaken that are similar in scope, nature and value to the Works and Services.  The names and the curriculum vitae for the person(s) that the Professional Engineer proposes/has retained to undertake the inspections and testing on its behalf during the construction of the Works and Services together with a summary of the projects that the person(s) has completed that are similar in scope, nature and value to the Works and Services.  The names and addresses of all sub-consultants that the Professional Engineer has/proposes to retain and a summary of the projects that the sub-consultants have completed that are similar in scope, nature and value to the Works and Services.  The Owner must ensure the Professional Engineer designs all Works and Services in accordance with this bylaw.  The Owner must also confirm that the Professional Engineer will provide the Design, Construction and Record-keeping Quality Control and Assurance Plans described herein. A copy of the agreement must be filed with the Director of Development Services. Schedule I - Quality Control 3 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.2 Construction Requirements The Owner must demonstrate to the satisfaction of the Director of Development Services that the Owner has or will retain the services of one or more qualified contractors to undertake the construction of the Works and Services. The Owner must provide the City with the name and address of its contractor(s) together with a summary of the projects that the contractor(s) has undertaken that are similar in scope, nature and value to the Works and Services prior to awarding the contract(s) to the contractor. In the case where the contractor has not performed similar Works and Services in the City, the Director of Development Services may require that the Owner provide a list of projects and references from other municipalities that demonstrates that the contractor(s) is qualified to undertake the Works and Services. The Owner must ensure that its contractor(s) constructs the Works and Services in accordance with the design, drawings, plans and specifications approved for construction by the Director of Development Services. 1.3 Quality Control and Assurance Plans Requirements regarding the Design Quality Control and Assurance Plan is as follows:  The Owner must submit or cause the Professional Engineer to submit a Design Quality Control and Assurance Plan to the City for approval coincident with submission of the first design drawings.  The Owner's proposed Design Quality Control and Assurance Plan must detail the procedures that will be used to ensure and verify that the design for the Works and Services, including all plans, drawings and specifications, must be completed in accordance with the minimum design standards set out in this bylaw.  In the case of design items related to pump stations, structures, structural fills, geotechnical or hydro-geotechnical items or any item not described in other Schedules, the Design Quality Control and Assurance Plan must show such specialist and/or sub-consultants with suitable experience in these works. Schedule I - Quality Control 4 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw Construction Quality Control and Assurance Plan is as follows:  The Owner must submit or cause the Professional Engineer to submit a Construction Quality Control and Assurance Plan to the Director of Development Services coincident with submission of the first design drawings to the City.  The Owner's proposed Construction Quality Control and Assurance Plan must detail the procedures that will be used to ensure and verify that the Works and Services must be constructed in accordance with the Professional Engineer's design, plans, drawings and specifications. The Construction Quality Control and Assurance Plan must include:  A proposed construction schedule showing milestone dates and the dates of Provisional Completion of the Works and Services.  The nature and frequency (periodic or full-time resident) of the proposed site inspections during construction to ensure that all Works and Services constructed satisfy the intent of the design and conform to the drawings, plans and specifications.  The nature and frequency of the proposed field and laboratory testing requirements for the Works and Services including what materials and equipment are to be tested, what types of tests will be performed and when these tests are to take place.  Such information as the Director of Development Services may stipulate from time to time. Record-keeping Quality Control and Assurance Plan is as follows:  The Owner must submit or cause its Professional Engineer to submit a Record-keeping Quality Control and Assurance Plan to the Director of Development Services coincident with submission of the first design drawings.  The Owner's proposed Record-keeping Quality Control and Assurance Plan must detail the procedures that will be used to ensure and verify that proper records will be kept and maintained throughout the design, construction and warranty phases of the Works and Services. The Record-keeping Quality and Assurance Control Plan must ensure that the following records are kept as a minimum:  Quality manual and standards.  Details of any field design or construction changes to the drawings, plans and specifications to which changes are approved in writing by the City.  Deficiency identification forms (Items of the work that are either not supplied or constructed in accordance with the design (drawings, plans and specifications) or that require remedial or corrective action). Schedule I - Quality Control 5 of 5 City of Dawson Creek Subdivision and Development Servicing Bylaw  Deficiency disposition/verification Forms (List of the foregoing items of the work that have been corrected).  Inspection and test records.  Field measurement records of completed Works and Services that have been used by the Professional Engineer to accurately prepare reproducible record drawings that are filed with the City. Notwithstanding the generality of the foregoing, the Owner must ensure that its Professional Engineer provides the City with the following at the times and in the manner set out below:  Certification prior to paving that it has inspected those items of the Works and Services that are below areas to be paved such as roads, walkways, driveways and parking lots, have been inspected and that same comply with the design (drawings, plans and specifications). Such certification must be accompanied by all test and inspection reports and by video tapes and reports on pipe lines.  Certification prior to acceptance by the City that surface works including paving, drainage, curbs and gutters, sidewalks, street lights, etc. have been constructed in accordance with the design (drawings, plans and specifications). City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE J STANDARDS FOR SUBMISSION BY DEVELOPER Schedule J - Standards for Submission by Developer 1 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE J - STANDARDS FOR SUBMISSION BY DEVELOPER 1.0 GENERAL ........................................................................................................................... 3 1.1 Introduction ....................................................................................................................... 3 1.2 General Requirements .......................................................................................................... 3 1.3 Abbreviations ..................................................................................................................... 3 2.0 DRAFTING STANDARDS ......................................................................................................... 4 2.1 Sheet Layout ...................................................................................................................... 4 2.2 Dimensions and Units ........................................................................................................... 4 2.3 Lettering ............................................................................................................................ 4 2.4 Scales................................................................................................................................ 5 3.0 DRAWING STANDARDS - DIGITAL ............................................................................................ 5 3.1 CAD Creation Guidelines ....................................................................................................... 5 3.2 Layer Naming Convention ..................................................................................................... 6 3.3 SPECIAL LAYERS................................................................................................................... 7 3.4 STANDARD LAYERS .............................................................................................................. 8 3.5 STANDARD OBJECT PROPERTIES ........................................................................................... 15 3.6 SYMBOLS ......................................................................................................................... 16 4.0 REQUIRED DRAWINGS ........................................................................................................ 16 4.1 Cover Sheet (Title Page) ...................................................................................................... 16 4.2 Key Plan(s) ....................................................................................................................... 16 4.3 Building Envelope Plan (if applicable) ..................................................................................... 17 4.4 Composite Plan(s) (as required) ............................................................................................ 17 4.5 Plan / Profile Drawings ....................................................................................................... 18 4.6 Grading Plan(s) ................................................................................................................. 20 4.7 Landscape Plan(s) .............................................................................................................. 22 4.8 Integrated Stormwater Management Plan (ISMP) ..................................................................... 22 4.9 Erosion and Sediment Control Plan(s) .................................................................................... 23 4.10 Street Lighting Plan(s) ......................................................................................................... 23 4.11 Street Sign, Paint Marking, and Traffic Control Device Plans ....................................................... 23 4.12 Traffic Management Plan(s) ................................................................................................. 24 4.13 Road Cross Section Plan(s) ................................................................................................... 24 4.14 Construction Details ........................................................................................................... 24 4.15 Electrical, Gas, and Communication Utilities ............................................................................ 24 5.0 DRAWING SUBMISSIONS ..................................................................................................... 24 5.1 Design Submissions ............................................................................................................ 24 5.2 Record Drawings ............................................................................................................... 25 5.3 Electronic Drawings ........................................................................................................... 25 5.4 Digital Hard Copies ............................................................................................................ 26 Schedule J - Standards for Submission by Developer 2 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw List of Tables Table J1: Layer Naming Conventions Table J2: Special Layers Table J3: Details Table J4: Grading Table J5: Landscaping Table J6: Legal/Cadastral Table J7: Planning Table J8: Roads Table J9: Sanitary Sewer Table J10: Storm Sewer Table J11: Stormwater Management Table J12: Structures and Surface Features Table J13: Survey Table J14: Topography Table J15: Shallow Utilities Table J16: Water Table J17: Titleblock Table J18: Point Group Types Schedule J - Standards for Submission by Developer 3 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 1.0 GENERAL 1.1 Introduction This Schedule outlines the minimum standards and requirements for design and record drawing submissions for Works and Services. Where a City or MMCD detail drawing exists, it is sufficient to refer to the appropriate drawing by reference number and date of issue. Where a detail drawing does not exist, or is unsuitable for a particular case, detail drawings must be prepared to accurately portray the various elements of the installation. Where no standard is defined in this Schedule for the preparation of a drawing to portray a particular service, structure, or other item, instructions and requirements may be obtained by discussion with City staff. 1.2 General Requirements Drawings must clearly show existing and proposed locations of all utilities using offsets from property lines or boundaries of rights-of-way. All drawings must be signed and sealed by a Professional Engineer registered in the Province of British Columbia. Elevations must be relative to geodetic datum. Horizontal coordinates must be referenced to UTM coordinate system NAD83. Vertical datum is CGVD 1928 - BC. 1.3 Abbreviations UTM Universal Transverse Mercator NAD83 1983 North American Datum BOC Back of Curb EC End of Curve BC Beginning of Curve PI Point of Intersection Schedule J - Standards for Submission by Developer 4 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 2.0 DRAFTING STANDARDS 2.1 Sheet Layout Drawing sheet layout(s) must conform to and include the following:  Sheet size to be ANSI D 22 x 34 in (558.8 x 863.6 mm).  A north arrow must be placed close to the top right side of each plan view on the sheet.  A title block that describes the contents of the drawing (eg. Key plan, road, etc.) and clearly indicates the location of the works by road name(s) and/or legal description.  Drawing scale, date, revision history block, and a detailed legend must also be included on each sheet layout. 2.2 Dimensions and Units The following conventions must be used:  Dimensions and units must be shown in metric. No imperial units are permitted.  All distances, elevations, and coordinates must be given in metres to accuracy of 3 decimal places.  Grades must be given as a percentage to accuracy of 2 decimal places.  Areas must be in square meters rounded to the nearest square meter.  All pipe sizes must be given in millimeters as per ASTM specifications using: 1 inch = 25 mm  Existing imperial dimensions, except for pipe sizes, are to be soft converted using the factors: 1 inch = 25.4 millimetres 1 foot = 0.3048 metres. 2.3 Lettering  Lettering is to be an open style of Vertical Gothic (eg. CG Omega or AutoCAD - 'romans').  All lettering to maintain a 1:10 ratio between plotted text height and plotted pen thickness.  The minimum plotted text height must be 1.5 mm.  The maximum plotted text height must be 5.0 mm.  The standard lettering height is 2.0 mm. Schedule J - Standards for Submission by Developer 5 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 2.4 Scales The following are acceptable scales to be used:  Location and Key Plans - 1:1000; 1:2500; 1:5000; 1:10000  Composite Plans - 1:500; 1:1000; 1:2500  Plan/Profile Drawings - Horizontal 1:500 or 1:250 Vertical 1:50 or 1:25  Cross Sections - Horizontal 1:100 Vertical 1:50  Details - 1:100; 1:20; 1:10 3.0 DRAWING STANDARDS - DIGITAL 3.1 CAD Creation Guidelines 3.1.1 Software Guidelines  All drawings must be in standard AutoCAD Version 2004 or later with no extensions. All drawing objects must be standard AutoCAD entities. In order for this to occur, set the AutoCAD system variable PROXYGRAPHICS to 1.  The use of third party software for AutoCAD will be at the discretion of the contractor/consultant. As these packages typically generate proprietary layers, linetypes and blocks, the contractors/consultant must ensure these items conform to the specifications as outlined in this document.  All linetypes, fonts, font styles, dimensioning styles, symbols, blocks and layers not deemed as project critical must be purged. Please note that these items may be needed for future project work.  Drawings are to be submitted in .PDF format.  All AutoCAD drawing entities must be on modelspace for the final drawings with title block only in paperspace. 3.1.2 Layers and Symbology A base drawing containing all the standard blocks and layering will be provided by the as part of these specifications. 3.1.3 Colour and Pen Assignments A .ctb file with colour and layer specifications will be provided by the City. Schedule J - Standards for Submission by Developer 6 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 3.1.4 Fonts and Text Sizes Only standard text fonts supplied with AutoCAD will be used. 3.1.5 Base Drawings The layer "BMBASE" must be used as the staging layer for inserting and referencing external drawings. The XREF drawings will be inserted as symbols (blocks) at the coordinates (0,0) with a scale factor of 1. 3.1.6 File Storage and Transfer All files transferred back to the City must be in the standard AutoCAD DWG format. Any AutoCAD blocks and XREF's must also be included. 3.2 Layer Naming Convention The following is the standard for layering name conventions to be used on all drawings being submitted: 3.2.1 Naming Convention:  X-<TYPE>-DESC  X = Prefix  TYPE = Types (see Table K1)  DESC = Description of the layer or layer name (see Section 3.4)  Example: E-SAN-MH = Existing Sanitary Manhole 3.2.2 Prefixes: The following are to be used as the prefix 'X' in the naming convention:  E - Existing  D - Detail  P - Proposed  F - Future  T - Titleblock 3.2.3 Types: The following Table J1 shows the 'TYPE' to be used in the naming convention. Schedule J - Standards for Submission by Developer 7 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J1: Layer Naming Conventions LAYER CATEGORY CATEGORY DESCRIPTION ELEC Electrical Diagrams (Not Shallow Utilities) GRADE Grading LAND Landscaping LGL Legal/Cadastral MECH Mechanical Diagrams PLAN Planning ROAD Roads SAN Sanitary STM Storm SWM Stormwater Management STRUC Structures and Surface Features SURV Survey TOPO Topography UTIL Shallow Utilities WAT Water NOTE: When 'T' or 'D' is the prefix, go directly to 'DESC' (i.e. T-border) 3.2.4 Suffixes: Suffixes may be used to describe in more detail the layer or to further separate objects of a similar type. For example, instead of placing all sanitary sewer mains on a layer called 'E-SAN- MAIN', you could place them on layers 'E-SAN-MAIN-150-DR35' and 'E-SAN-MAIN-200-DR35'. 3.3 SPECIAL LAYERS The following list of layers are pre-set layers contained in the City's Standard Drawing Template file (DC_CITY_BASE.dwt). Table J2 describes a few special layers that do not follow the layer convention set out in Section 3.2 Schedule J - Standards for Submission by Developer 8 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J2: Special Layers LAYER NAME PEN # LINE TYPE TYPE OF DATA _MVIEW 7 Continuous Viewports _IMAGE 7 Continuous Images (i.e. Aerial, etc.) _TEMP 7 Continuous Temporary Lines, Notes, Etc _XREF 7 Continuous General Cross References _XREF-DES 7 Continuous Design Dwg Cross Reference _XREF-LAN 7 Continuous Landscape Dwg Cross Reference _XREF-LGL 7 Continuous Legal Dwg Cross Reference _XREF-UTL 7 Continuous Utility Dwg Cross Reference 3.4 STANDARD LAYERS The following layers are defined in the City's Standard Drawing Template file (DC_CITY_ BASE.dwt). Each of these layers will use the prefixes defined in Section 3.2. Table J3: Details LAYER NAME PEN # LINE TYPE TYPE OF DATA LINE-LGT 26 Continuous Linework Lgt Penweight LINE-MED 24 Continuous Linework Med Penweight LINE-HVY 20 Continuous Linework Hvy Penweight PAT 27 Continuous Hatch Patterns TEXT-LGT 26 Continuous Text Lgt Penweight TEXT-MED 24 Continuous Text Med Penweight TEXT-HVY 20 Continuous Text Hvy Penweight Table J4: Grading LAYER NAME E P F LINE TYPE TYPE OF DATA GRADE-ARROW 65 64 252 Continuous Grading Arrows GRADE-ELEV 63 62 252 Continuous Spot Elevations GRADE-PAT 253 252 254 Continuous Hatch Patterns GRADE-TEXT 65 64 252 Continuous Grading Text Schedule J - Standards for Submission by Developer 9 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J5: Landscaping LAYER NAME E P F LINE TYPE TYPE OF DATA LAND-BOLLARD 73 72 252 Continuous Bollards LAND-BORDER 73 72 252 Continuous Borders LAND-CONC 73 72 252 Continuous Concrete Features LAND-FIXTURES 73 72 252 Continuous Fixtures/Furniture LAND-HEDGE 73 72 252 Continuous Hedges LAND-PATH 73 72 252 Continuous Pathways LAND-PLANTER 73 72 252 Continuous Planters LAND-RETWALL 73 72 252 Continuous Retaining Walls LAND-SHRUB 71 70 252 Continuous Shrubs LAND-TREE 71 70 252 Continuous Trees LAND-TREELINE 73 72 252 Continuous Edge Of Treeline LAND-TEXT 75 74 252 Continuous Landscaping Text Table J6: Legal/Cadastral LAYER NAME E P F LINE TYPE TYPE OF DATA LGL-ADRS-TEXT 145 144 252 Continuous Address Text LGL-BLOCK-TEXT 145 144 252 Continuous Block Text LGL-BLOCK 141 140 252 Continuous Block Linework LGL-DIM-TEXT 145 144 252 Continuous Dimension Text LGL-EASE 141 140 252 Hidden Easement Linework LGL-EASE-TEXT 145 144 252 Continuous Easement Text LGL-LOT 141 140 252 Continuous Lot Linework LGL-LOT-TEXT 145 144 252 Continuous Lot Text LGL-PLAN-TEXT 145 144 252 Continuous Plan Of Subd. Text LGL-SEC-TEXT 145 144 252 Continuous Section/Range/Tp. LGL-STRNAME 141 140 252 Continuous Street Names LGL-RW-ROADS 141 140 252 Continuous Road Right Of Way LGL-RW-ROADS-TEXT 145 144 252 Continuous Road Row Text LGL-RW-UTIL 141 140 252 Dashed Utility Right Of Way LGL-RW-UTIL-TEXT 145 144 252 Continuous Utility Row Text Schedule J - Standards for Submission by Developer 10 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table K7: Planning LAYER NAME E P F LINE TYPE TYPE OF DATA PLAN-AREA 41 40 254 Continuous Areas Of Measurement PLAN-BDY 48 10 254 Dashdot Boundaries PLAN-PAT 49 47 254 Continuous Hatch Patterns PLAN-LU 43 42 254 Continuous Land Use PLAN-MET 43 42 254 Continuous Planimetrics PLAN-SAN 91 90 254 Continuous Sanitary PLAN-STM 211 210 254 Continuous Storm PLAN-WAT 151 150 254 Continuous Water PLAN-TEXT 45 44 254 Continuous Text PLAN-ZON 43 42 254 Continuous Zoning Schedule J - Standards for Submission by Developer 11 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J8: Roads LAYER NAME E P F LINE TYPE TYPE OF DATA ROAD-CL 25 24 252 Center Road Centreline ROAD-CURB-ASP 23 22 252 Continuous Asphalt Curb ROAD-CURB-BACK 21 20 252 Continuous Back Of Curb ROAD-CURB-CONC 23 22 252 Continuous Concrete Curb ROAD-CURB-FACE 21 20 252 Continuous Face Of Curb ROAD-CURB-LIP 23 22 252 Continuous Lip Of Curb ROAD-CURB-TEXT 25 24 252 Continuous Curb Text ROAD-DRIVE-ASP 23 22 252 Continuous Asphalt Driveway ROAD-DRIVE-CONC 23 22 252 Continuous Concrete Driveway ROAD-DRIVE-GRAVEL 23 22 252 Continuous Gravel Driveway ROAD-DRIVE-PSTONE 23 22 252 Continuous Paving Stone Driveway ROAD-DRIVE-TEXT 25 24 252 Continuous Driveway Text ROAD-EOG 23 22 252 Continuous Edge Of Gravel ROAD-EOP 23 22 252 Continuous Edge Of Pavement ROAD-MARK 25 24 252 Continuous Pavement Markings ROAD-SHLD 23 22 252 Dashed Edge Of Shoulder ROAD-SIGN 23 22 252 Continuous Road Sign ROAD-TEXT 25 24 252 Continuous Text ROAD-WALK 23 22 252 Continuous Misc. Sidewalk ROAD-WALK-ASP 23 22 252 Continuous Asphalt Sidewalk ROAD-WALK-CONC 23 22 252 Continuous Concrete Sidewalk ROAD-WALK-TEXT 25 24 252 Continuous Sidewalk Text Schedule J - Standards for Submission by Developer 12 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J9: Sanitary Sewer LAYER NAME E P F LINE TYPE TYPE OF DATA SAN-MAIN 91 90 252 Center Gravity Lines SAN-CASING 93 92 252 Continuous Casing Pipe SAN-FM 91 90 252 Center Forcemains SAN-LS 93 92 252 Continuous Lift Stations SAN-MH 93 92 252 Continuous Manholes SAN-SEPTIC 93 92 252 Continuous Septic Lines/Fields/Tanks SAN-SERV 91 90 252 Center Service Hookups SAN-SERV-IC 93 92 252 Continuous Cleanout/Insp. Chamber SAN-STRUC 93 92 252 Continuous Structures SAN-TEXT 95 94 252 Continuous Text Table J10: Storm Sewer LAYER NAME E P F LINE TYPE TYPE OF DATA STM-MAIN 211 210 252 Phantom Gravity Lines STM-CASING 213 212 252 Continuous Casing Pipe STM-CB 213 212 252 Continuous Catch Basins STM-CBLEAD 215 214 252 Phantom Catch Basin Lead STM-CBMH 213 212 252 Continuous Catch Basin / Manholes STM-CULVERT 213 212 252 Continuous Culverts STM-DITCH 213 212 252 Arrow Ditch STM-DITCH-TEXT 215 214 252 Continuous Ditch Text STM-MH 213 212 252 Continuous Manholes STM-SERV 211 210 252 Continuous Service Hookups STM-STRUC 213 212 252 Continuous Structures STM-SWALE 213 212 252 Arrow Swales STM-SWALE-TEXT 215 214 252 Continuous Swale Text STM-TEXT 215 214 252 Continuous Text Schedule J - Standards for Submission by Developer 13 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J11: Stormwater Management LAYER NAME E P F LINE TYPE TYPE OF DATA SWM-BDY 253 251 254 Continuous Swm Boundary SWM-PAT 253 251 254 Continuous Swm Hatch/Pattern SWM-POND 95 94 252 Continuous Swm Ponding SWM-POND-TEXT 95 94 252 Continuous Swm Pond Text SWM-TEXT 95 94 254 Continuous Swm Text Table J12: Structures and Surface Features LAYER NAME E P F LINE TYPE TYPE OF DATA STRUC-BLDG 243 242 252 Continuous Buildings STRUC-BLDG-TEXT 245 244 252 Continuous Building Text STRUC-BRIDGE 243 242 252 Continuous Bridges STRUC-FNC 243 242 252 Fence Generic Fenceline STRUC-FNC-CLINK 243 242 252 Fence Chainlink Fenceline STRUC-FNC-POST 243 242 252 Fence Post & Cable Fenceline STRUC-FNC-TEXT 243 242 252 Continuous Fence Text STRUC-FNC-WOOD 243 242 252 Fence Wood Fenceline STRUC-RETWALL 243 242 252 Continuous Retaining Walls STRUC-TEXT 245 244 252 Continuous Structures Text Table K13: Survey LAYER NAME E P LINE TYPE TYPE OF DATA SURV-CONTROL 45 44 Continuous Control/ASCM's SURV-FIP 45 44 Continuous Found Iron Pins SURV-GEOTECH 45 44 Continuous Mon. Well, Test Pit, BH, PZ SURV-TRAV 45 44 Phantom Traverse Lines Schedule J - Standards for Submission by Developer 14 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J14: Topography LAYER NAME E P F LINE TYPE TYPE OF DATA TOPO-CONT-MAJ 67 64 252 Continuous Major Contours TOPO-CONT-MIN 69 66 252 Continuous Minor Contours TOPO-CONT-TEXT 65 66 252 Continuous Contour Text TOPO-SPOTELEV 63 62 252 Continuous Spot Elevation TOPO-TOE 63 62 252 Continuous Toe Of Slope TOPO-TOP 63 62 252 Continuous Top Of Slope TOPO-TEXT 65 64 252 Continuous Slope Text TOPO-TREELINE 63 62 252 Continuous Treeline TOPO-WATER-CL 63 62 252 Continuous Single Line Wat Feature TOPO-WATER-EDGE 63 62 252 Continuous Double Line Wat Feature Table J15: Shallow Utilities LAYER NAME E P F LINE TYPE TYPE OF DATA UTIL-CABLE 191 190 252 Cable Tv Cable UTIL-CABLE-TEXT 195 194 252 Continuous Tv Cable Text UTIL-ELEC 191 190 252 Elec Line, Box, Mh, Trans. UTIL-ELEC-LIGHT 193 192 252 Continuous Light Std UTIL-ELEC-PP 193 192 252 Continuous Power Pole UTIL-ELEC-SERV 191 190 252 Elec Electricity Service UTIL-ELEC-TEXT 195 194 252 Continuous Electricity Text UTIL-GAS 191 190 252 Gas Gas UTIL-GAS-SERV 191 190 252 Gas Gas Service UTIL-GAS-TEXT 195 194 252 Continuous Gas Text UTIL-TEL 191 190 252 Tel Telephone Line UTIL-TEL-MH 193 192 252 Continuous Telephone Manhole UTIL-TEL-SERV 191 190 252 Tel Telephone Service UTIL-TEL-TEXT 195 194 252 Continuous Telephone Text UTIL-CON1 191 190 252 Con1 1 Use Conduit UTIL-CON2 191 190 252 Con2 2 Joint Use Conduit UTIL-CON3 191 190 252 Con3 3 Joint Use Conduit UTIL-CON-TEXT 195 194 252 Continuous Conduit Text Schedule J - Standards for Submission by Developer 15 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Table J16: Water LAYER NAME E P F LINE TYPE TYPE OF DATA WAT-MAIN 151 150 252 Dashed Watermains WAT-CASING 155 154 252 Continuous Casing Pipe WAT-CHAMB 153 152 252 Continuous Chambers WAT-SERV-CS 153 152 252 Continuous Curb Stops WAT-FTG 153 152 252 Continuous Fittings WAT-HYD 153 152 252 Continuous Hydrants WAT-IRRIG 151 150 252 Dashed Irrigation WAT-SERV 151 150 252 Dashed Water Service WAT-STRUC 153 152 252 Continuous Lift Sta, Reservoirs WAT-TEXT 155 154 252 Continuous Water Text WAT-VALVE 153 152 252 Continuous Valves Table J17: Titleblock LAYER NAME PEN # LINE TYPE TYPE OF DATA T-BDR 180 Continuous Border Linework T-BLK-TEXT-LGT 184 Continuous Titleblock Info Text T-BLK-TEXT-MED 182 Continuous Titleblock Info Text T-BLK-TEXT-HVY 180 Continuous Titleblock Info Text T-GRID-MAJ 185 Continuous Major Grid Line T-GRID-MIN 187 Continuous Minor Grid Line T-GRID-TEXT 180 Continuous Grid Text T-LEGEND 184 Continuous Legend T-NORTH 184 Continuous North Arrow T-STAMP-DISCLAIMER 184 Continuous Disclaimer Stamp T-STAMP-FORISSUE 184 Continuous For Issue Stamp T-STAMP-PERMIT 184 Continuous Permit To Practice Stamp T-STAMP-PLOT 184 Continuous Plot/Date Stamp 3.5 STANDARD OBJECT PROPERTIES All objects colour and linetype properties should be set to "bylayer". This ensures the greatest amount of control over the entire drawing and enables changes to be made quickly and easily. Schedule J - Standards for Submission by Developer 16 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 3.5.1 Point Groups  Naming Convention: <TYPE>-<SOURCE>-<DATE>  Type = See Table J18  Source = Data source, surveyor, etc...  Date = Current date in the format yyyy-mm-dd Table J18: Point Group Types Name Description SURV Field Surveys UTIL Record Utility Information (not for surface use) CTRL Survey Control Points INTP Interpolated Points 3.6 SYMBOLS Submitted drawings must include symbols provided in the City's Standard Drawing Template file. Symbols must be inserted using the specified insertion point, which is to be centre point of the symbol unless otherwise indicated. Where possible, symbols are to be inserted at the end or mid points of line segments. 4.0 REQUIRED DRAWINGS 4.1 Cover Sheet (Title Page) The cover sheet must show the following information:  Name of Development or Subdivision  Name and address of Owner and Professional Engineer.  Site location plan of Development or Subdivision.  Legal description of subject properties.  File numbers of approving authorities. (i.e. City and/or Ministry).  Complete drawing index of all sheets belonging to the set.  Other pertinent information 4.2 Key Plan(s) Schedule J - Standards for Submission by Developer 17 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw Key Plans must show the following information:  Lot numbers, plan numbers, and road names of the subject Development or Subdivision and adjoining properties.  Cross reference of the drawings by outlining the area contained in each drawing and referencing that drawing by drawing number.  General construction notes.  Other pertinent information. 4.3 Building Envelope Plan (if applicable) Building Envelope Plans must show the following information:  Overall plan of current phase  Lot numbers  Roads, curbs, gutters and sidewalks  Rights of way and easements  Offset lines from all property boundaries indicating required building setbacks  10 metre by 10 metre square on each parcel indicating the required minimum building envelope  Notes that indicate the required setbacks from all property boundaries pursuant to the Zoning Bylaw  Other pertinent information 4.4 Composite Plan(s) (as required) Composite Plans must show the following information:  All existing and proposed utilities, roads, walkways, and sidewalks.  All rights of way and easements including widths.  Control monuments with identification number.  All legal information, including bearings, dimensions, lot numbers, block numbers, legal plan numbers, and street names. All lots must be numbered.  Show legal lot line dimensions. Schedule J - Standards for Submission by Developer 18 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw  All roadway dimensions including width of right of way, BOC to BOC and BOC to edge of right of way.  Area of each parcel.  Other pertinent information. 4.5 Plan / Profile Drawings Plan/Profile drawings must show the following information: 4.5.1 General The following criteria applies to all drawings:  Both plan and profile stationing must be tied to a property line or road boundary.  The profile must be shown at true centerline length and projected below the plan in as close a horizontal relationship as possible.  The top half of a plan/profile sheet must show the plan view and must show the legal layout with legal descriptions of all properties, the location of all sidewalks, catch basins, underground utilities such as sewer, water, telephone, television power, manholes, valves, hydrants, and all survey monuments, etc.  Drawings must also show existing dwellings, fences, trees, hedges, unusual ground features, existing roads and driveways including the type such as asphalt, concrete or gravel.  Plan/profile drawings for various services may be combined on one plan providing the plans are clear and readable. Plan/profile drawings may combine the following services:  Roads & Storm Drains  Sanitary Sewers & Water  Roads, Storm Drains, Sanitary Sewers and Water may be included on one drawing depending on the complexity of the design and at the discretion of the Director of Development Services. 4.5.2 Road Plan/Profile Drawings (may be combined with Storm Drains) Road plan views must show the following information:  Drawings must show width of road, width of shoulders, and the offset of curb from property line. Schedule J - Standards for Submission by Developer 19 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw  Chainages of the B.C. and E.C. of horizontal curves must be shown together with the delta angle, centerline radius, tangent length, and centerline arc length. Curb radii are not required if the centerline radius and road width are shown, except on curb returns at intersections and at the end of cul-de-sacs. Road profile views must show the following information:  The design gutter and/or centerline grade (%).  Vertical curve chainage and elevations of B.C., E.C. and P.I.:  the external value, e;  the length of vertical curve;  the chainage and elevation of the low spot of sag curves; and  K value of vertical curvature (crest on sag).  Existing ground elevation along the centerline of the proposed roadway and/or the edge of existing asphalt. 4.5.3 Water Plan/Profile Drawings (may be combined with Sanitary Sewer) Water plan views must show the following information:  Offset of pipelines from property lines.  Length and size of pipe.  Offset of connections from property lines.  The locations of hydrants, valves, services, end-of-main, or other appurtenances referenced to the nearest property line.  Information on any curves or pipe deflections.  Easements (existing and/or required). Water profile views must show the following information:  Surface profiles (existing and design, if applicable) over proposed main.  Length, size, grade, type, and material of pipe.  Profiles of invert and crown of pipes.  Location, type and invert elevation of all crossing utilities. Schedule J - Standards for Submission by Developer 20 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 4.5.4 Storm Drains and Sanitary Sewer Plan/Profile Drawings Storm and Sanitary plan views must show the following information:  The structural details of all manholes and chambers, etc. not covered by standard drawings.  Offset of pipelines from property lines.  The size of pipe.  Offset of connections from property lines.  The locations of manholes, clean-outs and services relating to property lines.  Information on any curves or pipe deflections.  Easements (existing and/or required).  Future curb and gutter lines (if applicable).  Manhole identification numbers.  Inverts of service connections at property line (if applicable).  For storm drainage, features such as ditches, culverts, streams, channels, etc. Storm and sanitary profile views must show the following information:  Surface profiles (existing and design, if applicable) over proposed main.  Length, size, grade, type, and material of pipe.  Profiles of invert and crown of pipes.  Location, type and invert elevation of all crossing utilities.  Invert elevations of manholes.  Alignment station of manholes.  Manhole identification number.  Rim elevations of proposed or adjusted manholes. 4.6 Grading Plan(s) In addition to any other requirements presented, grading plans must show the following information: Schedule J - Standards for Submission by Developer 21 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 4.6.1 General  Clearing and grubbing boundaries  Fill and excavation areas (by shading) including structural fill areas  Locations of required temporary (during construction) and permanent siltation abatement and erosion control measures,  Pre-development contour lines at a maximum 0.5 m interval. The topographic information must extend a minimum 30.0 m outside the development site  Proposed contours, slopes, grades, and spot elevations including surface slopes of roadways and other surfaces with arrows indicating the direction of flow.  Proposed or existing elevations along the boundaries of the subdivision and design elevations at all lot corners and changes of surface slope along property boundaries.  The minor (5 year return) storm sewer system with the flows calculated per section and the accumulated flows from all upstream sections. Provision must be made for upstream development potential where applicable;  The major (100-year return) system. The nature and detail of the major conveyance system is to be shown, including all major drainage flow directions, ponding areas and the extent and maximum depth of ponding anticipated for a 1 in 100 year return frequency rainfall event along with the maximum hydraulic grade line. The overall major drainage flow route is to be clearly defined and designated with prominent arrows. Include the direction of surface flows on all surfaces and elevations of overflow points from local depressions and details of channel cross sections.  Swale details including locations, easement requirements, slopes, cross sections and construction details for the swales.  Easement and restrictive covenants - Requirements and locations for all easements and restrictive covenants related to drainage provisions and development restrictions associated with the drainage of the property. 4.6.2 Lot Grading  All existing corner lot elevations  All proposed corner lot elevations  Lot drainage pattern - The direction of surface drainage for each lot is to be identified, to indicate whether split drainage or through drainage is contemplated. Proposed surface drainage for abutting future development lands is to be shown to the extent that it will impact on the subject lands. Schedule J - Standards for Submission by Developer 22 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw  Lot grading details - Typical detail diagrams of the various types of lot grading arrangements, which will normally conform to the figures provided in the Supplementary Detail Drawings, are to be used, identifying for each lot which typical detail applies.  The proposed building envelope with the minimum finished ground elevation adjacent to the proposed building noted for each lot. 4.7 Landscape Plan(s) Landscape plans must show the following information:  Extent of proposed landscape works and services  Existing and proposed property information, including lot lines, easements, right of ways, legal descriptions, addresses and dimensions  Existing and proposed contours, slopes, grades and spot elevations for landscaped areas (if not already shown on grading plan)  Existing and proposed buildings, structures, roads, curbs, sidewalks, walls, fences, signs, site features and other appurtenances  Existing vegetation proposed to be removed, relocated or retained  Areas of proposed preservation, naturalization, restoration, lawn and landscaping, including soil types, depths and amendments  Proposed plant species name (botanical and common), size and planting condition  Existing and proposed irrigation systems (if required)  Construction details and specifications or other pertinent information as required. 4.8 Integrated Stormwater Management Plan (ISMP) In addition to any other requirements presented, Integrated Stormwater Management Plans must show the following information:  Site and surrounding area (400 m minimum outside development) showing roads and major features. A small location plan of the watershed is also to be included.  Major contours at 1.0 m and minor contours at 0.2 m elevation intervals (existing and proposed)  Existing and proposed major surface flow paths. Schedule J - Standards for Submission by Developer 23 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw  Detention pond details, if applicable.  Area, in hectares, of development and the total area of drainage basin.  Directional arrows of flow within the site and on surrounding areas.  Sub-catchment boundaries, coefficients and areas.  Pipe system including size, grade, and minor and major flows (a table may be utilized).  The subject development is to be highlighted.  Other pertinent information (see Schedule D) 4.9 Erosion and Sediment Control Plan(s) In addition to any other requirements presented in this bylaw, Erosion and Sediment Control Plans must show the following information:  Existing contours of the site at an interval sufficient to determine drainage patterns.  Final contours if the existing contours are to be significantly changed.  Final drainage patterns/boundaries.  Existing vegetation such as significant trees, shrubs, grass, and unique vegetation.  Limits of clearing and grading.  Erosion and sediment control measures (temporary and permanent) including locations, names and details, in accordance with "Land Development Guidelines for the Protection of Aquatic Habitat".  Storm Drainage systems including drain inlets, outlets, pipes, and other permanent drainage facilities (swales, waterways, etc.). 4.10 Street Lighting Plan(s) A plan view of the street lighting must be provided. General notes on the plan must reference municipal standards, specifications and appropriate design criteria. 4.11 Street Sign, Paint Marking, and Traffic Control Device Plans A drawing identifying signs, markings, and required control devices must be provided. Detailed drawings may be required for traffic control devices. These plans can be added to road plan drawings if the plan is clear and readable. Schedule J - Standards for Submission by Developer 24 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 4.12 Traffic Management Plan(s) Detail routes for construction traffic and traffic controls for traffic on existing roads affected by construction may be required if requested by the Director of Development Services. 4.13 Road Cross Section Plan(s) Must be scaled at 1:100 horizontal and 1:50 vertical and must note the existing ground elevation, the proposed elevations of the road centreline, the curb and gutter (or road edge) and property lines. Cross-sections are required at critical locations as required by the Director of Development Services. 4.14 Construction Details Show all proposals for construction which are not covered or specifically detailed in the City's standards. Where there is a City or MMCD standard, it is expected to refer to the detail drawing number. 4.15 Electrical, Gas, and Communication Utilities The Owner's Professional Engineer must obtain and submit engineering drawings from each utility drawing showing detailed design and construction requirements for any necessary Works and Services. The Professional Engineer must assemble all drawings and superimpose them onto an overall subdivision compilation drawing(s) to ensure that there are no conflicts between any of the municipal services and the shallow utilities both underground and above ground. The Owner's Professional Engineer must also provide sealed Shop Drawings of the screw piling design for all lamp standards as part of their Electrical design drawings. 5.0 DRAWING SUBMISSIONS 5.1 Design Submissions 3 full size paper copies of all design drawings are required for design submissions. The Owner must also submit to the City a complete set of electronic design drawings of the subdivision or development in a digital hard copy in Adobe PDF format in accordance with this Schedule. Schedule J - Standards for Submission by Developer 25 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw 5.2 Record Drawings Record drawings must be submitted prior to issuance of a Certificate of Provisional Completion of All Works. Record drawings must be delivered in both paper and electronic format(s) to the City. Record drawings must include all drawings in approved design submission or as requested by Director of Development Services. The Owner must submit to the City a complete set of electronic drawings of the subdivision or development in a digital hard copy in Adobe PDF format in accordance with this Schedule. In conjunction with the record drawings, service connection records must be provided for each lot. The service connection records must be submitted in Adobe PDF format, 8.5" x 11" letter size, using the City's service connection record AutoCAD template form. The service connection record must include the following record information:  Lot, Block & Plan number  Civic address  Water & sanitary service invert and depth at main and at property line  Water & sanitary service and main sizes, materials and dates of install (both in the City boulevard and on-lot)  Date service connection record was created (date plotted)  A plan drawing (location map) showing:  Lot relative to road and other lots, clearly identified  North arrow  Lot services and all other underground services maintained by the City (water, sanitary sewer, storm sewer , and street lighting)  Any lot features like swales, easements or right of ways  Perpendicular distance from closest adjacent property line to water shutoff  Lot grading information 5.3 Electronic Drawings 5.3.1 General Requirements The Owner must submit to the City a complete set of electronic drawings of the Subdivision or Development in AutoCAD .dwg format. Schedule J - Standards for Submission by Developer 26 of 26 City of Dawson Creek Subdivision and Development Servicing Bylaw The electronic drawing must be prepared in accordance with Section 3. All external files associated with the electronic drawing (e.g. special fonts, line types, and/or images) must be supplied with the electronic drawing submission. No drawing is to be submitted that contains any external references (xrefs). All externally referenced drawings must be bound prior to submittal. 5.4 Digital Hard Copies A digital hard copy is any digital file that is reproducible without the ability to modify the drawings contents or appearance. 5.4.1 General Requirements Adobe's Portable Document Format (*.pdf) is the preferred file type. Drawing sets submitted as a digital hard copy must be electronically sealed by the Professional Engineer. 5.4.2 Device/Document Settings for Plotting Adobe Portable Document Format Ensure all text is legible and the shading and hatching ordered so as not to block or hide other line work and/or text. The following settings must be used when plotting the drawings to Adobe PDF:  paper size to be ANSI D 22" x 34"  layout to be "landscape"  graphic print quality to be no less than "600 dpi" City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE K SUPPLEMENTARY DETAIL DRAWINGS Schedule K - Supplementary Detail Drawings 1 of 2 City of Dawson Creek Subdivision and Development Servicing Bylaw SCHEDULE K - SUPPLEMENTARY DETAIL DRAWINGS Naming of Supplementary Detail Drawings follows MMCD Standard Detail Drawings naming convention. Supplementary drawings that replace an existing MMCD Standard Detail Drawing are denoted with an "S" in front of the MMCD Standard Detail Drawing number. Drawing Number Drawing Title A Roads A1 Local Road - Typical Section A2 Local Road (Cul-De-Sac) - Typical Section A3 Arterial Road - Typical Section A4 Collector - Typical Section A5 Commercial Urban - Typical Section A6 Industrial Urban Standard - Typical Section A7 Industrial Rural Standard - Typical Section A8 Neighbourhood Arterial - Typical Section A9 Residential (Local) Road - Typical Section A10 Village Centre Road - Typical Section A11 Neighbourhood Arterial Stormwater Street - Typical Section A12 Residential (Local) Stormwater Street - Typical Section A13 Paved Lane - Typical Section A14 Road Widths and Underground Utility Locations A15 Multi-Use Path - Typical Section A16 Approved Driveway Configuration Examples for Duplex Lots G General SG4 Typical Utility Trench Section and Pipe Bedding Detail SG8 Pipe Anchor Blocks G9 Water and Sewer Crossings G10 Landscaping and Approved Tree Species G11 Lot Grading Typical Detail - Rear to Front Drainage G12 Lot Grading Typical Detail - Split Drainage G13 Lot Grading Typical Detail - Front to Rear Drainage G14 Corrosion Protection in Native Soil at Steel or Iron Fittings S Storm and Sanitary S16 Large Diameter Water and Sewer Services S17 Rainfall Intensity-Duration-Frequency Curve S18 Driveway Culvert Placement W Water SW4 Typical Hydrant Assembly Schedule K - Supplementary Detail Drawings 2 of 2 City of Dawson Creek Subdivision and Development Servicing Bylaw SW6/SW7 Standard Air Valve Assembly SW8 Buried Standpipe Detail W11 Pressure Main Thrust Blocks W12 Double Water Service Connection x x x x