Policy No. 9 "Policy Governing Administration and Enforcement of the Building By-law,
Building Code Act, Municipal Government Act and Land Use By-law"
POLICY NO. 9
POLICY GOVERNING ADMINISTRATIION AND ENFORCEMENT OF THE
BUILDING BY-LAW, BUILDING CODE ACT, MUNICIPAL GOVERNMENT ACT AND
LAND USE BY-LAW
________________________________________________________________________________
1.
All applications shall be checked to ensure that adequate information has been provided
to identify applicant/owner, location of lot, location of structures to be placed upon the
lot and other requirements as contained in the Land Use By-law.
2.
Where work commences on the development of a lot where no development permit has
been issued or the commencement of construction of a structure or the location of a
mobile home where no permit has been issued under the Building By-law then the
following procedure shall be followed:
(a)
Immediate personal contact with the owner(s) agent/constructor and By-law
requirements explained. Required application forms are to be provided during time
of visit.
(b)
If there is personal contact with the owner(s) agent/constructor then it is to be
followed up by a letter at which time confirmation of the discussion is to be made
along with the requirement that completed applications are to be returned and that
no work is to be proceeded with.
(c)
If personal contact is not possible, then an attempt shall be made to contact the
property owner and/or constructor by telephone and to be followed up by
notification by letter and required application forms are to be provided. The
owner(s) agent/constructor shall be instructed to complete the required forms and
that work on the project is to cease until such time as the required permits have been
issued.
(d)
The Building Inspector shall have the authority to issue a "Stop Work Order"
where circumstances warrant it. The "Stop Work Order" shall be personally
served on the owner and constructor or mailed to each by registered or certified
mail and a copy shall be posted on the property.
(e)
If the required documentation is not forthcoming, the Inspector shall monitor the
situation and no later than ten (10) days from the date of the letter shall further visit
2
Policy No. 9 "Policy Governing Administration and Enforcement of the Building By-law,
Building Code Act, Municipal Government Act and Land Use By-law"
the site to determine whether work has progressed.
(f)
If development continues without a Development and/or Building Permit having
been issued, then a detailed report and recommendation shall be made to the
Chief Administrative Officer for the action of Council.
(g)
The Inspector shall document all proceedings, especially proof of mailing of
notices and posting of orders and take photographs.
(h)
If work continues after the issue of the "Stop Work Order", then that fact shall be
immediately reported to the Chief Administrative Officer and the matter shall be
dealt with by the Municipal Council at the earliest possible date.
3.
The Development Officer/Building Inspector shall follow all required procedures
as contained in the Land Use By-law, Building Code Act, Municipal Government Act
and Building By-law.
4.
It shall be the responsibility of the Council to determine whether legal action is to be
taken to enforce the requirements of the Land Use By-law, Building Code Act, Municipal
Government Act and Building By-law.
Approved April 27, 1994
Amended May 28, 2003
Amended December 11, 2017