Updated Asset Management Plan - Chapple 2022 Section 1

Chapple, Ontario

This is the exact embedded text of the captured official document. Snapshot 5767069ed4a2 · verified 2026-06-09 · original document · archived snapshot · unofficial consolidation, the official version is held by the municipal clerk.

Township of Chapple Asset Management Plan Prepared By: June 14, 2017 Updated June 2022 Saulteaux Consulting and Engineering - www.sceinc.ca 2 Saulteaux Consulting and Engineering would like to thank Crupi Consulting Group for their assistance in the preparation of this Asset Management Plan: 3 Contents 1.0 Executive Summary ..................................................................................................... 5 2.0 Introduction ................................................................................................................ 6 2.1 Asset Listing ...................................................................................................................... 7 3.0 State of Local Infrastructure ...................................................................................... 10 3.1 Asset Types ..................................................................................................................... 10 3.2 Total Maintenance, Remediation, Rehabilitation, and Replacement Costs .................. 11 3.3 Asset Condition, Asset Age Distribution ........................................................................ 15 4.0 Desired Levels of Service ........................................................................................... 19 4.1 Assumptions & Performance Measures ......................................................................... 19 4.2 State of Local Infrastructure and Levels of Service (2022) ................................................ 22 4.3 Levels of Service - Roads & Related (2022) ........................................................................ 22 4.4 Levels of Service - Bridges & Culverts (2022) ..................................................................... 27 4.5 Levels of Service - Water & Wastewater (2022) ................................................................ 31 5.0 Asset Management Strategy ..................................................................................... 33 5.1 Non-Infrastructure Solutions ......................................................................................... 33 5.2 Maintenance Activities ................................................................................................... 34 5.3 Renewal / Rehabilitation Activities ................................................................................ 35 5.4 Replacement Activities ................................................................................................... 35 5.5 Disposal Activities ........................................................................................................... 36 5.6 Expansion Activities ........................................................................................................ 36 6.0 Financial Plan ............................................................................................................ 37 6.1 General overview of financial plan requirements .............................................................. 37 6.2 Financial information relating to the Township of Chapple's AMP .................................... 39 6.2.1 Funding objective ......................................................................................................... 39 6.2.2 Tax funded assets ......................................................................................................... 39 6.2.2.1 Current funding position ........................................................................................... 39 6.3 Use of Reserves ................................................................................................................... 43 6.3.1 Available Reserves ....................................................................................................... 43 6.4 Summary of financial Plan .................................................................................................. 44 7.0 Lifecycle Management Strategy ..................................................................................... 46 7.1 Introduction (2022) ............................................................................................................. 46 7.2 Roads & Roads Related (2022) ................................................................................................... 47 4 7.3 Bridges & Culverts (2022) ............................................................................................................49 7.4 Water & Wastewater (2022) ...................................................................................................... 50 5 1.0 Executive Summary Saulteaux Consulting and Engineering (SCE) has prepared this Asset Management Plan (AMP) for the Township of Chapple. In preparing the plan, SCE worked with Crupi Consulting Group (CCG). SCE undertook the inspections of Municipal Buildings, Recreation, Water, Waste Water, Electrical, Roads, Bridges, and Vehicle inspections. CCG undertook the financial analysis, and life cycle costing process. This AMP provides an overview of the estimated future expenditures related to municipal assets over the period of the next ten (10) years. This document will help the Township to undertake an ongoing process to budget for the expenditures necessary to maintain the service levels that have been outlined in the Township's Official Plan. Additionally, the plan identifies assets which require urgent attention in order to bring them to standard, and further identifies a recommended timeframe to undertake necessary maintenance, rehabilitation, and in some cases replacement of assets. The financial plan (Section 6.0) of this plan, outlines a recommended strategy for the Township to finance the necessary work while limiting the tax burden, and maintaining a fiscally responsible, sustainable approach to asset management. Included in the plan are recommendations regarding the maintenance of each asset. If identified maintenance is completed, and ongoing maintenance is undertaken, this will extend the lifecycle of assets, giving the Township a much more manageable budgeting process. All assumptions regarding levels of service are listed within the plan, the financial plan is developed with the understanding that the Township intends to maintain existing levels of service, and that any future development would be undertaken as per the Official Plan. 6 2.0 Introduction This asset management plan has been developed for the Township of Chapple to assist the Township in making informed choices regarding future investment. This plan helps to define priorities for future spending, identifies estimated maintenance costs for existing assets, and defines a financing strategy. The goal of this process is to provide the Township with the information required to ensure that it can develop a financing strategy to maintain satisfactory levels of service, and undertake required investments in the future. Additionally, this process reviews the lifecycle cost of each asset including construction, ongoing maintenance, and disposal. Consideration has been given to ensuring that services are maintained in an environmentally sustainable manner, as per the Township's Official Plan. A key feature of this plan is that it will provide the Township with a prioritized listing of infrastructure needs. This listing of priorities will help the Township to identify projects to undertake in the coming years, with a clear focus on the most urgent priorities, projects that will require investment within the next three years. This plan is designed to cover the lifecycle of each asset, and is intended as a living document to be amended, as required, or when new tangible assets are added to the Asset Listing. For the purposes of completing this project, Saulteaux Consulting and Engineering (SCE) has worked with Crupi Consulting Group (CCG). SCE undertook the inspections of Municipal Buildings, Recreation, Water, Waste Water, Electrical, Roads, Bridges, and Vehicle inspections. CCG undertook the financial analysis, and life cycle costing process. 7 2.1 Asset Listing The following assets are included in the plan: Table 2.1 - Asset Listing Asset Name Asset No. Ext. No. Asset Code Quantity Units Municipal Office 100000 01 A1A 235.52 SQ. M Public Works Building 100000 01 A2B 503.57 SQ. M Small Garage 100100 01 A2B 170.20 SQ. M Mortuary 100200 01 A3Z 30.88 SQ. M Museum 100300 01 A3F 596.52 SQ. M Recreation Centre/Hall 100400 01 A6A 1383.30 SQ. M Shed Single Stall 100500 01 A2B 29.58 SQ. M Deck 100600 01 A6Z 17.54 SQ. M Pavilion 100700 01 A6H 29.04 SQ. M Riverview Park Pavilion 100800 01 A6H 38.44 SQ. M Rink 100900 01 A6H 822.16 SQ. M Rink Shack 101000 01 A6E 18.12 SQ. M Rink Shack Pumphouse 101100 01 A5A 5.01 SQ. M Lighthouse 101200 01 A6Z 14.52 SQ. M Fire Hall 101300 01 A3H 192.18 SQ. M Sports field Canteen 101400 01 A6G 109.00 SQ. M Covered Picnic Area 101500 01 A6H 63.42 SQ. M Landfill Building 101600 01 A5D 18.76 SQ. M Equipment Storage 101700 01 A6H 27.54 SQ. M St. Paul's Heritage Place Church 101800 01 A3I 93.56 SQ. M North Rink 101900 01 A6H 822.16 SQ. M North Rink Shack 102000 01 A6E 18.12 SQ. M North Fire Hall 102100 01 A3H 95.50 SQ. M Water Treatment Plant Building 102200 01 A5A 199.8 SQ. M Playground 200000 01 C5D 468.00 SQ. M Sport field Recreation Area 200100 01 A6H 27000 SQ. M 5 Stall RV Park 200400 01 A6Z 1150 SQ. M Docks 200500 01 C0C 157.17 SQ. M Boat Launch 200600 01 C0C 40 SQ. M Water Treatment System 400000 01 B1C 1 EA Well #1 400000 01 B1F 1 EA Well #2 400200 01 B1F 1 EA Well #3 400300 01 B1F 1 EA Well #4 400400 01 B1F 1 EA Well #5 400500 01 B1F 1 EA Well #6 400600 01 B1F 1 EA 200mmø Watermain 400700 01 B1B 937.5 M 150mmø Watermain 400800 01 B1B 1890 M Shenston Dum 450000 01 B4B 1 EA Lagoon 450200 01 B2E 1 EA Sewage Life Station 450300 01 B2H 1 EA 200mmø Sanitary Sewer 450400 01 B2A 1824 M Street Lights 500000 01 B3C 27 EA Brigham Road North 600100 01 D1B 0.8 KM Brigham Road South 600200 01 D1B 0.4 KM Westover Road 600300 01 D1B 5.2 KM 8 Asset Name Asset No. Ext. No. Asset Code Quantity Units Westover Road 600300 02 D1B 3.2 KM Playford Road 600400 01 D1B 1.5 KM J. Wilson Road 600500 01 D1B 1.3 KM Sturgeon Creek Road 600600 01 D1B 5.0 KM Angus Road South 600700 01 D1B 3.4 KM Angus Road North 600800 01 D1B 4.9 KM Gibson Road 600900 01 D1B 1.6 KM Irvine Road 601000 01 D1B 1.6 KM Moulton Road 601100 01 D1B 2.9 KM Hart Road 601200 01 D1B 2.8 KM Mather Road West 601400 01 D1B 9.9 KM Mather Road East 601500 01 D1B 9.9 KM Olson Road 601600 01 D1B 2.6 KM Hunsperger Road 601700 01 D1B 1.6 KM McNally Road 601800 01 D1B 2.4 KM Elliot Road 601900 01 D1B 1.6 KM R. Wilson Road 602000 01 D1B 2.6 KM Cates Road 602100 01 D1B 4.3 KM French Road 602200 01 D1B 0.8 KM Korpi Road 602300 01 D1B 6.9 KM Curtis Pit Road 602400 01 D1B 0.6 KM Lampi Road 602500 01 D1B 4.8 KM Boundary Lake Road 602600 01 D1B 3.8 KM Maki Road 602700 01 D1B 2.0 KM Heatwole Road 602800 01 D1B 1.8 KM Gallinger Road 602900 01 D1B 4.1 KM Marrs Road 603100 01 D1B 6.0 KM Teeple Road 603200 01 D1B 5.1 KM Hayes Road 603300 01 D1B 2.6 KM Church Road 603400 01 D1B 2.4 KM Barwick Road 603500 01 D1D 0.3 KM Barwick Road 603500 02 D1B 3.3 KM Barwick Road 603500 03 D1C 1.1 KM Barwick Road 603500 04 D1B 19.1 KM Atkinson Road 603600 01 D1B 1.4 KM Vanheyst Road 603700 01 D1B 1.8 KM Tait Road 603800 01 D1B 11.4 KM Huziak Road 603900 01 D1B 4.8 KM Woolsey Road 604000 01 D1B 3.2 KM Development Road 604100 01 D1B 9.6 KM Oien Road 604200 01 D1B 1.3 KM Hele Road 604300 01 D1B 6.5 KM McCulloch Road 604400 01 D1B 1.8 KM Fehr Road 604500 01 D1B 4.9 KM Bolen Road North 604600 01 D1B 6.9 KM Bolen Road South 604600 02 D1B 0.6 KM Steiner Road 604700 01 D1B 2.4 KM Taylor Road 604800 01 D1B 2.0 KM Clink Road 604900 01 D1B 0.8 KM Caul Road 605000 01 D1A 0.8 KM Morley-Chapple Road 605100 01 D1B 8.9 KM Prison Farm Road 605200 01 D1B 1.1 KM Ceder Yard Road 605300 01 D1B 0.4 KM Ceder Yard Road 605300 02 D1D 0.1 KM 9 Asset Name Asset No. Ext. No. Asset Code Quantity Units Morley-Chapple Road 605100 01 D1B 8.9 KM Prison Farm Road 605200 01 D1B 1.1 KM Ceder Yard Road 605300 01 D1B 0.4 KM Ceder Yard Road 605300 02 D1D 0.1 KM Queen Street 605400 01 D1D 0.8 KM Mill Road 605500 01 D1B 0.3 KM Agnes Street 605600 01 D1D 0.4 KM Alley Way 605700 01 D1D 0.3 KM Cawston Avenue 605800 01 D1D 0.2 KM Nighswander Road 605900 01 D1B 1.0 KM Main Street 606000 01 D1D 0.7 KM Hillbilly Road 606100 01 D1B 1.8 KM Walking Bridge 800000 01 D2B 20.79 SQ. M Barwick Rd Bridge (Barron Bridge) 800100 01 D2A 204.43 SQ. M McCulloch Road Bridge 800200 01 D2A 181.90 SQ. M Hele Road Bridge (Woolsley Bridge) 800300 01 D2A 151.46 SQ. M Mather Rd Bridge #1 (Hilliard Bridge) 800400 01 D2A 80.41 SQ. M Mather Rd Bridge #2 (Hickey Bridge) 800500 01 D2A 67.55 SQ. M Angus Bridge #1 (Nanson Bridge) 800600 01 D2A 79.52 SQ. M Angus Bridge #2 (Zimmerman Bridge) 800700 01 D2A 78.69 SQ. M Sturgeon Creek Bridge (Ahrens Bridge) 800800 01 D2A 186.84 SQ. M Angus Rd N Bridge #1 (Hart Bridge) 800900 01 D2A 80.84 SQ. M Angus Rd N Bridge #2 (Irvine Bridge) 801000 01 D2A 79.9 SQ. M Fire Rescue Vehicle 5-6 901000 01 E1Z 1 EA Fire Truck 5-3 901100 01 E1A 1 EA Fire Truck 5-4 901200 01 E1A 1 EA Fire Truck 5-2 901300 01 E1B 1 EA Link-Belt Backhoe 902000 01 E8B 1 EA Volvo Strongco Grader 902100 01 E8K 1 EA Dodge Ram 3500 Flatbed 902200 01 E6C 1 EA John Deere F915 902300 01 E8L 1 EA Case 721F 902400 01 E8L 1 EA Cat 140M Grader 902500 01 E8K 1 EA John Deere 2350 Tractor 902600 01 E8L 1 EA Peterbuilt Tandem Truck 902700 01 E8B 1 EA Midland Belly Dump Trailer 902800 01 E8N 1 EA Ford F150 XLT 902900 01 E6C 1 EA Chapple Tandem Dump Truck 903000 01 E8Q 1 EA John Deere 644B Loader 903100 01 E8I 1 EA John Deere 450 Dozer 903200 01 E7E 1 EA 10 3.0 State of Local Infrastructure This section outlines the following: - Asset types (Roads, Buildings, Equipment, Bridges, Water, Waste Water, Solid Waste and Vehicles). - Identification of maintenance, repair, remediation, and replacement costs for assets. - Age of assets, including age of assets as a portion of expected life. - Condition of assets, as per standard engineering practices. Roads, vehicles, buildings, and recreation equipment were inspected for this process, and the most recent bridge inspection reports were analyzed by a Professional Engineer. As the asset management planning process is intended to be ongoing, and the condition of assets, especially those requiring immediate repair, can impact the budget process, it is recommended that the tables included herein be updated with current information, as it becomes available. Data will be updated as identified in Municipal policy which complies with Provincial requirements (i.e. as required inspections are undertaken, at regular intervals). 3.1 Asset Types Table 3.1 - Listing of Asset Codes in Township of Chapple MUNICIPAL ASSET MANAGEMENT PLAN ASSET CODES Category Class Subclass Asset Code Units Buildings Administrative Office A1A SQ.M Buildings Operative Garage (Municipal) A2B SQ.M Building Institutional Museum A3F SQ.M Buildings Institutional Fire Station A3H SQ.M Building Institutional Church/Chapel A3I SQ.M Building Institutional Other A3Z SQ.M Building Utility Water Supply/Treatment A5A SQ.M Building Utility Solid Waste Disposal A5D SQ.M Building Recreational Community Centre/Hall/Culture Centre A6A SQ.M Building Recreational Club House/Youth Centre/Senior Centre/Drop-In Centre A6E SQ.M Building Recreational Kitchen Shelter A5G SQ.M Buildings Recreational Shelter/Hut A6H SQ.M Building Recreational Other A6Z SQ.M Utility Water Supply & Distribution System Water Mains B1B M Utility Water Supply & Distribution System Water Treatment System B1C EA Utility Water Supply & Distribution System Community Wells B1F EA Utility Waste Collection & Disposal System Sanitary Main B2A M Utility Waste Collection & Disposal System Lagoon B2E EA Utility Waste Collection & Disposal System Liftstation B2H EA Utility Electrical Power Supply & Dist. Sys Street Lights B3C EA Utility Solid Waste Collection & Disposal Landfill Site B4B EA 11 MUNICIPAL ASSET MANAGEMENT PLAN ASSET CODES Category Class Subclass Asset Code Units Grounds Ports WHARF - Rec C0C SQ.M Grounds Playgrounds Outdoor Hockey C5D SQ.M Transportation Roads Earth Roads D1A KM Transportation Roads Gravel Roads D1B KM Transportation Roads Surface Treated Roads D1C KM Transportation Roads Paved Roads D1D KM Transportation Bridges Vehicular Bridges D2A SQ.M Transportation Bridges Pedestrian Bridge D2B SQ.M Vehicles Fire Mini-Pumper E1A EA. Vehicles Fire Triple Combination Pumper E1B EA. Vehicles Fire Other E1Z EA. Vehicles Municipal Truck 1/2 Ton E6C EA. Vehicles Commercial Bulldozer Other E7E EA. Vehicles Commercial Bulldozer E8B EA. Vehicles Commercial Front End Loader E8I EA. Vehicles Commercial Grader E8K EA. Vehicles Commercial Miscellaneous E8L EA. Vehicles Commercial Trailer E8N EA. Vehicles Commercial Truck, Dump E8Q EA. Note: Quantity and extent of assets are identified in Table 2.1. 3.2 Total Maintenance, Remediation, Rehabilitation, and Replacement Costs Asset Name Asset Number Asset Ext. Year of Construction Totals ($) Municipal Office 100000 01 1980 13,500 Public Works Building 100000 01 1980 11,100 Small Garage 100100 01 2000 350 Mortuary 100200 01 1994 1,300 Museum 100300 01 2000 8,750 Recreation Centre/Hall 100400 01 1940 37,000 Shed Single Stall 100500 01 1980 6,400 Deck 100600 01 1994 3,800 Pavilion 100700 01 1999 2,600 Riverview Park Pavilion 100800 01 1970 2,250 Rink 100900 01 2008 - Rink Shack 101000 01 1970 3,100 Rink Shack Pumphouse 101100 01 1970 525 Lighthouse 101200 01 1999 2,050 Fire Hall 101300 01 1990 3,400 Sports field Canteen 101400 01 1995 5,550 Covered Picnic Area 101500 01 1997 1,000 Landfill Building 101600 01 1997 200 Equipment Storage 101700 01 1970 400 St. Paul's Heritage Place Church 101800 01 1901 16,800 North Rink 101900 01 2003 500 North Rink Shack 102000 01 1970 6,800 North Fire Hall 102100 01 1990 1,400 12 Asset Name Asset Number Asset Ext. Year of Construction Totals ($) Water Treatment Plant Building 102200 01 1993 15,100 Playground 200000 01 2003 100 Sport field Recreation Area 200100 01 1950 14,250 5 Stall RV Park 200400 01 1986 - Docks 200500 01 2013 - Boat Launch 200600 01 1994 - Water Treatment System 400000 01 1993 93,500 Well #1 400000 01 1993 - Well #2 400200 01 1993 - Well #3 400300 01 1993 - Well #4 400400 01 1993 500 Well #5 400500 01 1993 - Well #6 400600 01 1993 3,500 200mmø Watermain 400700 01 1993 - 150mmø Watermain 400800 01 1993 - Shenston Dump 450000 01 1989 - Lagoon 450200 01 1989 124,000 Sewage Life Station 450300 01 1989 12,000 200mmø Sanitary Sewer 450400 01 1989 - Street Lights 500000 01 2008 - Brigham Road North 600100 01 Township to advise 2,000 Brigham Road South 600200 01 Township to advise 1,000 Westover Road 600300 01 Township to advise 5,000 Westover Road 600300 02 Township to advise 3,000 Playford Road 600400 01 Township to advise 2,000 J. Wilson Road 600500 01 Township to advise 3,000 Sturgeon Creek Road 600600 01 Township to advise 2,000 Angus Road South 600700 01 Township to advise 2,000 Angus Road North 600800 01 Township to advise 8,000 Gibson Road 600900 01 Township to advise 2,000 Irvine Road 601000 01 Township to advise 3,000 Moulton Road 601100 01 Township to advise 3,000 Hart Road 601200 01 Township to advise 5,000 Mather Road West 601400 01 Township to advise 6,000 Mather Road East 601500 01 Township to advise 8,000 Olson Road 601600 01 Township to advise 2,000 Hunsperger Road 601700 01 Township to advise 4,000 McNally Road 601800 01 Township to advise 2,000 Elliot Road 601900 01 Township to advise 2,000 R. Wilson Road 602000 01 Township to advise 7,000 Cates Road 602100 01 Township to advise 2,000 French Road 602200 01 Township to advise 2,000 Korpi Road 602300 01 Township to advise 508,000 Curtis Pit Road 602400 01 Township to advise 2,000 Lampi Road 602500 01 Township to advise 5,000 Boundary Lake Road 602600 01 Township to advise 20,000 Maki Road 602700 01 Township to advise 5,000 13 Asset Name Asset Number Asset Ext. Year of Construction Totals ($) Heatwole Road 602800 01 Township to advise 6,000 Gallinger Road 602900 01 Township to advise 14,000 Marrs Road 603100 01 Township to advise 26,000 Teeple Road 603200 01 Township to advise 2,000 Hayes Road 603300 01 Township to advise 2,000 Church Road 603400 01 Township to advise 3,000 Barwick Road 603500 01 Township to advise 2,000 Barwick Road 603500 02 Township to advise 2,000 Barwick Road 603500 03 Township to advise 3,000 Barwick Road 603500 04 Township to advise 5,000 Atkinson Road 603600 01 Township to advise 1,000 Vanheyst Road 603700 01 Township to advise 2,000 Tait Road 603800 01 Township to advise 17,000 Huziak Road 603900 01 Township to advise 3,000 Woolsey Road 604000 01 Township to advise 3,000 Development Road 604100 01 Township to advise 5,000 Oien Road 604200 01 Township to advise 1,000 Hele Road 604300 01 Township to advise 5,000 McCulloch Road 604400 01 Township to advise 3,000 Fehr Road 604500 01 Township to advise 6,000 Bolen Road North 604600 01 Township to advise 5,000 Bolen Road South 604600 02 Township to advise 1,000 Steiner Road 604700 01 Township to advise 2,000 Taylor Road 604800 01 Township to advise 2,000 Clink Road 604900 01 Township to advise 1,000 Caul Road 605000 01 Township to advise 1,000 Morley-Chapple Road 605100 01 Township to advise 6,000 Prison Farm Road 605200 01 Township to advise 8,000 Ceder Yard Road 605300 01 Township to advise 1,000 Ceder Yard Road 605300 02 Township to advise 9,000 Queen Street 605400 01 Township to advise 11,000 Mill Road 605500 01 Township to advise 1,000 Agnes Street 605600 01 Township to advise 2,000 Alley Way 605700 01 Township to advise 2,000 Cawston Avenue 605800 01 Township to advise 1,000 Nighswander Road 605900 01 Township to advise 2,000 Main Street 606000 01 Township to advise 3,000 Hillbilly Road 606100 01 Township to advise 1,000 Walking Bridge 800000 01 2008 850 Barwick Road Bridge 800100 01 2010 20,000 McCulloch Road Bridge 800200 01 1966 1,000,800 Hele Road Bridge 800300 01 1960 1,041,800 Mather Road East Bridge #1 800400 01 1969 78,000 Mather Road East Bridge #2 800500 01 1967 371,200 Angus Road Bridge #1 800600 01 1968 16,500 Angus Road Bridge #2 800700 01 1974 25,600 Sturgeon Creek Bridge 800800 01 1955 888,200 14 Asset Name Asset Number Asset Ext. Year of Construction Totals ($) Angus Road North Bridge #1 800900 01 1970 36,000 Angus Road North Bridge #2 801000 01 1970 90,000 Fire Rescue Vehicle 5-6 901000 01 2006 - Fire Truck 5-3 901100 01 1989 - Fire Truck 5-4 901200 01 1995 - Fire Truck 5-2 901300 01 2000 - Link-Belt Backhoe 902000 01 1999 - Volvo Strongco Grader 902100 01 1999 - Dodge Ram 3500 Flatbed 902200 01 1995 - John Deere F915 902300 01 2007 - Case 721F 902400 01 2015 - Cat 140M Grader 902500 01 2008 - John Deere 2350 Tractor 902600 01 1986 700 Peterbuilt Tandem Truck 902700 01 2017 - Midland Belly Dump Trailer 902800 01 2014 - Ford F150 XLT 902900 01 2013 - Chapple Tandem Dump Truck 903000 01 2005 - John Deere 644B Loader 903100 01 1981 2,550 John Deere 450 Dozer 903200 01 1993 50 Totals: 4,741,375 The above table reflects maintenance, remediation, rehabilitation, and replacement costs. Ongoing maintenance items are not reflected beyond their initial occurrence; however they are listed in the financial plan, under Section 6.0 of the Asset Management Plan. 15 3.3 Asset Condition, Asset Age Distribution Table 3.3.1 Buildings & Recreation Asset Name General Condition Year Constructed Estimated Remaining Life (Years) Municipal Office 7 1980 22 Public Works Building 7 1980 22 Small Garage 8 2000 30 Mortuary 7 1994 26 Museum 7 2000 28 Recreation Centre/Hall 7 1940 25 Shed Single Stall 6 1980 20 Deck 6 1994 15 Pavilion 7 1999 23 Riverview Park Pavilion 8 1970 20 Rink 8 2008 22 Rink Shack 6 1970 15 Rink Shack Pumphouse 7 1970 22 Lighthouse 8 1999 22 Fire Hall 7 1990 25 Sports field Canteen 7 1995 22 Covered Picnic Area 6 1997 20 Landfill Building 7 1997 25 Equipment Storage 7 1970 20 St. Paul's Heritage Place Church 7 1901 22 North Rink 6 2003 20 North Rink Shack 5 1970 15 North Fire Hall 7 1990 22 Water Treatment Plant Building 7 1993 25 Playground 9 2003 22 Sport field Recreation Area 7 1950 40 5 Stall RV Park 9 1986 40 Docks 8 2013 15 Boat Launch 8 1994 22 Table 3.3.2 Water, Sewer, Solid Waste & Electrical Asset Name General Condition Year Constructed Estimated Remaining Life (Years) Water Treatment System 7 1993 10 Well #1 7 1993 10 Well #2 7 1993 10 Well #3 7 1993 10 Well #4 7 1993 10 Well #5 7 1993 10 Well #6 0 1993 10 200mmø Watermain 7 1993 30 150mmø Watermain 7 1993 30 Shenston Dump 4 1989 17 Lagoon 7 1989 17 Sewage Life Station 7 1989 17 200mmø Sanitary Sewer 7 1989 30 Street Lights 9 2008 22 16 Table 3.3.3 Roads Asset Name Pavement Condition Rating Estimated Surface Age Possible Remedial Treatments Brigham Road North 70 10 Grading, brushing, signage. Brigham Road South 72 10 Install speed limit sign. Westover Road 68 10 Grading, brushing, signage. Westover Road 72 10 Signage, brushing. Playford Road 88 10 Grading, brushing, signage. J. Wilson Road 62 10 Grading, brushing, signage. Sturgeon Creek Road 85 10 Grading, brushing, signage. Angus Road South 86 10 Grading, brushing, signage. Angus Road North 74 10 Grading, brushing, signage. Gibson Road 72 10 Grading, signage, brushing. Irvine Road 84 10 Grading, brushing, signage. Moulton Road 85 10 Grading, signage, brushing. Hart Road 67 10 Grading, signage, brushing. Mather Road West 89 10 Shaping, signage, brushing. Mather Road East 86 10 Grading, signage, brushing. Olson Road 63 10 Grading, signage, brushing. Hunsperger Road 70 10 Grading, signage, brushing. McNally Road 71 10 Signage, brushing. Elliot Road 75 10 Signage, brushing. R. Wilson Road 70 10 Signage, brushing, Allowance for spot improvement. Cates Road 77 10 Signage, brushing. French Road 74 10 Signage, brushing, ditching Korpi Road 80 10 Crash protection, ditching, embankments, guardrails Curtis Pit Road 70 10 Grading, signage. Lampi Road 68 10 Grading, signage Boundary Lake Road 58 10 Grading, shaping, signage, brushing & ditching Maki Road 50 10 Shaping, signage brushing, ditching. Heatwole Road 82 10 Shaping signage, brushing Gallinger Road South 63 10 Shaping, signage. Marrs Road 60 10 Brushing, signage, & ditching. Teeple Road 78 10 Brushing. Hayes Road 79 10 Shaping, signage, brushing. Church Road 74 10 Shaping, signage, brushing. Barwick Road 81 10 Seal cracks Barwick Road 80 10 Shaping, brushing Barwick Road 79 10 Surface patching, brushing Barwick Road 77 10 Shaping, brushing Atkinson Road 85 10 Brushing Vanheyst Road 73 10 Shaping, signage, brushing. Tait Road 57 10 Allowance for major spot improvement, shaping, signage, brushing. Huziak Road 72 10 Shaping, signage, brushing. Woolsey Road 79 10 Shaping, signage, brushing. Development Road 82 10 Shaping, signage, brushing. Oien Road 65 10 Grading, shaping, signage, brushing. Hele Road 69 10 Shaping, signage, brushing. McCulloch Road 67 10 Shaping, signage, brushing Fehr Road East 60 10 Shaping, signage, brushing. Bolen Road North 68 10 Spot repair, shaping signage, & brushing. Bolen Road South 57 10 Shaping & brushing Steiner Road 66 10 Shaping, signage & brushing 17 Asset Name Pavement Condition Rating Estimated Surface Age Possible Remedial Treatments Taylor Road 64 10 Shaping, signage & brushing Clink Road 63 10 Shaping, signage & brushing Caul Road N/A 10 Proper signage Morley-Chapple Road 72 10 Signage & brushing Prison Farm Road 70 10 Shaping, signage, brushing & ditching. Ceder Yard Road 75 10 Signage Ceder Yard Road 60 10 Patching Queen Street 77 10 Patching, signage Mill Road 63 10 Shaping, signage & brushing Agnes Street 80 10 Patch & seal Alley Way 79 10 Patching & signage Cawston Avenue 77 10 Patch & seal Nighswander Road 70 10 Patch & seal, signage and brushing Main Street 80 10 Patch & seal Hillbilly Road 66 10 Shaping Table 3.3.4 Bridges Asset Name Useful Life (Years) Year of Construction Action Walking Bridge 22 2008 Barwick Road Bridge 35 2010 McCulloch Road Bridge 15 1966 Hele Road Bridge 10 1960 Mather Road East Bridge #1 20 1969 Mather Road East Bridge #2 5 1967 Angus Road Bridge #1 20 1968 Angus Road Bridge #2 20 1974 Sturgeon Creek Bridge 5 1955 Angus Road North Bridge #1 20 1970 Angus Road North Bridge #2 10 1970 Table 3.3.5 Vehicles Asset Name General Condition Year Constructed Estimated Remaining Life (Years) Fire Rescue Vehicle 5-6 9 2006 15 Fire Truck 5-3 7 1989 5 Fire Truck 5-4 8 1995 8 Fire Truck 5-2 9 2000 15 Link-Belt Backhoe 7 1999 10 Volvo Strongco Grader 7 1999 10 Dodge Ram 3500 Flatbed 7 1995 10 John Deere F915 7 2007 5 Case 721F 8 2015 30 Cat 140M Grader 7 2008 20 John Deere 2350 Tractor 7 1986 5 Peterbuilt Tandem Truck 9 2017 25 Midland Belly Dump Trailer 9 2014 20 Ford F150 XLT 8 2013 15 Chapple Tandem Dump Truck 7 2005 10 John Deere 644B Loader 7 1981 6 18 Asset Name General Condition Year Constructed Estimated Remaining Life (Years) John Deere 450 Dozer 7 1993 10 Fire Truck 5-1 10 2021 20 Ford F150 Truck 10 2018 10 Notes and Assumptions: 1. Estimated life value assumes that identified maintenance is completed, and regular ongoing maintenance is performed. Estimated remaining life for vehicles in good condition is assumed to be ten (10) years. 2. Building Condition rating scale is as follows: 0 = Closed 1 - 3 = Poor 4 - 6 = Fair 7 - 9 = Good 10 = New 3. Roads use Pavement Condition Rating value from 0-100. 19 4.0 Desired Levels of Service For the purposes of this AMP, it is assumed that all assets owned by the municipality will continue to be used for their existing purpose, at the existing level of service. All defined maintenance items are indicated based upon this assumption. This assumption was developed based upon the following from the Township's Official Plan document, adopted September 2013: "The Township is committed to actively seeking and encouraging new development that maintains and improves the quality of life, the health of existing businesses and diversifies the economy. " Furthermore, The Township of Chapple Official Plan document has outlined levels of service regarding roads in Section 6.1: "Safe and efficient movement of people and goods within the Township and to and from adjacent municipalities is encouraged by this Plan. The road system should safely serve the Township but should not be developed to a standard or extended beyond which would result in a burden to the residents and taxpayers of the Township. The roads in the Township as shown on all schedules to this Plan include provincial highways and Township roads." Regarding reported speed limits. Please note the speed limits reported on our inspection sheets is the speed limit either posted or specified by the Township staff. It is not an endorsement of the limit as this would involve geometric, sight line, road width, etc. considerations which are beyond the scope of the AMP. 4.1 Assumptions & Performance Measures 1. It is assumed that all roads will be maintained and rehabilitated as required to continue to offer the existing level of service. It is further assumed that the Official Plan will apply when an increase to a level of service is warranted, and that any increase in level of service will be offset by a corresponding increase in tax revenue. Our inspections include some deferred estimated cost such as road widening for roads which are only currently used as agricultural access which have been termed as a "deferred improvement" only justifiable should additional residential development occur to warrant the works. Our inspections also include recommendations to post signs on roads, or in some cases trails, advising "road is un- 20 maintained and to be used at own risk". Estimated annual daily traffic ranges are appended to this report. It is important to note that the surface age is unknown and is assumed to be 10 years, this is used to calculate the estimated surface value of roads. While the Township can control development within its boundaries, activities occurring in surrounding areas can impact levels of use. If an increase in traffic volume creates increased maintenance costs that cannot be offset by tax revenue, the Township should re-visit its financial plan to: - Determine the best means to cover the cost to maintain the existing level of service during the period of increased use, using the options outlined in the financial plan. Or - If it is not feasible to cover the cost to maintain the existing level of service, the Township could consider reducing the level of service. By reducing the level of service, the Township may deter the factors leading to increased use of the asset. 2. It is assumed that all bridges will continue to serve the same function as they currently do. Therefore, it is assumed that they will be maintained, rehabilitated, and replaced to perform the same function, and handle the same traffic volumes and loads as they are currently designed to do. It is further assumed that the Official Plan will apply when an increase to a level of service occurs, and that any increase in level of service will be offset by a corresponding increase in tax revenue. Estimated annual daily traffic ranges are appended to this report (see traffic numbers for associated road). While the Township can control development within its boundaries, activities occurring in surrounding areas can impact levels of use. If an increase in traffic volume creates increased maintenance costs that cannot be offset by tax revenue, the Township should re-visit its financial plan to: - Determine the best means to cover the cost to maintain the existing level of service during the period of increased use, using the options outlined in the financial plan. Or - If it is not feasible to cover the cost to maintain the existing level of service, the Township could consider reducing the level of service. By reducing the level of service, the Township may deter the factors leading to increased use of the asset. 21 3. It is assumed that all buildings will continue to be used for their current purpose for the duration of the plan. If a change in service is required, it is assumed that any increase in level of service, or operating requirements will be offset by a corresponding increase in tax revenue. It is recommended that the Township follow up on all maintenance items identified in the inspection reports appended to the plan to ensure that all buildings can operate at their present level of service, and conform to code requirements. See the asset reports for a detailed listing of maintenance needs, and a description of the building. If new buildings are required, it is assumed that the costs to construct new structures would be offset by a corresponding increase in tax revenue, or by using a debt financing solution, as outlined in the Financial Plan. 4. Given the relatively static population trends in the Township, it is assumed that all recreation equipment will continue to be used for its current purpose, at a similar level of use, for the duration of the plan. If a change in service is required, it is assumed that any increase in level of service, or operating requirements will be offset by a corresponding increase in tax revenue. It is recommended that the Township continue to undertake regular maintenance to ensure that the equipment remains in good working order, and is safe to use. 5. It is assumed that all vehicles will continue to be used for their current purpose for the duration of the plan. It is recommended that the Township follow up on all maintenance items identified in the inspection reports appended to the plan to ensure that all vehicles can operate at their present level of service. It should be noted that while many of the vehicles are older, they are in good condition, and it is anticipated that with proper maintenance, the vehicles should last for the duration of the plan. Note: Detailed inspection reports regarding each asset are appended to this report. Descriptions of each asset are available under the General Description heading contained within each asset report. 22 4.2 State of Local Infrastructure and Levels of Service This section provides an analysis of the Municipality's assets and the current service levels provided by those assets. O. Reg 588/17 requires that for each asset category included in the asset management plan, the following information must be identified: - Summary of the assets; - Replacement cost of the assets; - Average age of the assets (it is noted that the Regulation specifically requires average age to be determined by assessing the age of asset components); - Information available on condition of assets; and - Approach to condition assessments (based on recognized and generally accepted good engineering practices where appropriate). Asset management plans must identify the current levels of service being provided for each asset category. For core municipal infrastructure assets, both the qualitative descriptions pertaining to community levels of service, and metrics pertaining to technical levels or service, are prescribed by O. Reg 588/17. For all other infrastructure assets, each municipality will need to establish its own measures for levels of service. Asset management plans must also include a 10-year forecast identifying the proposed levels of service for each asset category. The proposed levels of service will be defined using the qualitative descriptions and technical metrics that the municipality uses to define current levels of service. The rest of Section 4 addresses the requirements identified above, with a focus on each individual asset category. 4.3 Roads & Related 4.3.1 State of Local Infrastructure The Township of Chapple currently owns and manages 469.94 total kilometres of roads with a 2021 replacement cost totalling approximately $160,337,200.00. The replacement cost has been estimated based on the unit costs identified in the Lifecycle Management Strategy section of this report (Section 7.0). The road network consists of roads with various surface types, including gravel, pavement, and earth. These assets reside in urban and rural roadside environments. 90% of the road network length is gravel. The next most common surface type is earth roads at 9% of the road network length - these roads have very minimal traffic and are not accessed regularly. Asphalt roads only account 23 for 1% of the road network length and exist solely in the Barwick Village area. In the context of roadside environment, over 95% of the network is rural. Figure 4-1 provides an illustration of Chapple's road network, showing surface type with corresponding repair and replacement costs. Table 4-1 Road Network Replacement Value (2021) Surface Type Quantity (kms) Per/km Replacement Cost Full Replacement Cost Asphalt 6.6 $ 225,000.00 $ 1,485,000.00 Earth 41.4 $ 160,000.00 $ 6,624,000.00 Gravel 421.9 $ 380,000.00 $ 160,337,200.00 Road Network Repair Value (2021) Surface Type Quantity (kms) Per/km Repair Cost Full Repair Cost Asphalt 6.6 $ 2,500.00 $ 16,500.00 Earth 41.4 $ 1,500.00 $ 62,100.00 Gravel 421.9 $ 18,000.00 $ 7,594,920.00 *Repair and replacement costs do not include curbs, gutters, culverts, bridges, brushing/trimming, or any other necessary environmental or infrastructure 4.3.2 Condition Assessed physical condition, rather than age provides a more accurate estimate of an asset's remaining service life. 90% of the Township of Chapple's road network consists of gravel roads. The condition of gravel roads can deteriorate rapidly and is less costly to improve through lifecycle activities such as routine grading and re-gravelling every few years. Because of this, lifecycle activities for gravel roads are currently funded through the operating budget. The condition of the asphalt and gravel roads was assessed by the Public Works Department in 2021. The department used a Pavement Condition Index (PCI) as the measure of condition. PCI is measured on a scale of 0-100, with 100 being a perfect condition and 0 indicating an asset that has failed. To better communicate the condition of the road network, these numeric condition ratings have been segmented into qualitative condition states. Table 4-2 summarizes the various physical condition ratings and the condition state they represent for road assets. 24 4-2: Road Conditions Assessment Calculator Measurement Condition Rating PCI 1 Very Poor 0-29 2 Poor 30-49 3 Fair 50-69 4 Good 70-89 5 Very Good 90-100 4-3: Roads Summary Surface Type Length (lane-km) Average Condition (PCI) Condition Rating Gravel 421.9 74 Good Asphalt 6.6 77 Good Earth 41.4 46 Poor TOTAL 469.9 65.67 Fair *Roads have two lanes with the exception of Off-Lake Road and Barwick Townline Road Table 4-3 examines the average condition of the road network by surface type. The average condition is weighted based on kilometres. The PCI ratings used in this plan are from 2021. The Municipality should develop a strategy to update the road condition values annually to reflect expected deterioration and any improvements that have been made that year. Every three to five years, a road needs study should be completed where the condition of roads is assessed directly and evaluated to identify short- and medium-term needs. As illustrated in Table 4-3, Gravel and Asphalt roads are in a Good condition state. The overall average PCI for the entire road network is currently 65.67 - Fair condition state. 25 Table 4-4: Road Condition State with Respect to Pavement Condition Index Condition (PCI) Condition Description Picture 90-100 Very Good 70-89 Good 50-69 Fair 30-49 Poor 0-29 Very poor N/A 4.3.3 Current Levels of Service - Roads & Related The levels of service currently provided by the Township of Chapple's road network are, in part, a result of the state of local infrastructure identified above. A levels of service analysis defines the current levels of service and enables the Municipality to periodically evaluate these service level objectives. Road assets have prescribed levels of service reporting requirements under O. Reg. 588/17. These requirements include levels of service reporting at two different levels, i.e., community levels of service and technical levels of service. Community levels of service objectives describe service levels in terms that customers understand and reflect customers' expectations with respect to the scope and quality of the road network. Technical levels of service describe the scope and quality of the Municipality's roads through performance measures that can be quantified 26 and evaluated. These performance measures can be used to assess how effectively a municipality is achieving its established targets. Road users are often particularly concerned with roads that are in Poor and Very Poor condition. To address these concerns, the information on condition conveyed through the average PCI performance measure required by O. Reg. 588/17 will be supplemented by reporting the total kilometre length of roads in Poor condition or worse. Table 4-5 presents the current level of service for roads. It includes the requirements mandated by O. Reg 588/17. Figure 4-4 and Figure 4-5 provide a spatial illustration of the condition of the Municipality's road network. 4-5: Community Levels of Service - Roads & Related Service Attribute Community Levels of Service Scope Table 4-1 depicts the road network by surface type Quality Table 4-4 details how road PCI is separated into qualitative condition states 4.3.4 Proposed Levels of Service - Roads & Related Table 4-6 presents the proposed technical levels of service for the Township of Chapple's road network, identified through consultation with the municipality's Public Works Department. 4-6: Roads Summary Surface Type Length (lane-km) Current Performance (Average Condition PCI) Proposed Performance (Average Condition PCI) Gravel 421.9 74 75 Asphalt 6.6 77 80 Earth 41.4 46 50 TOTAL 469.9 65.67 68.33 *Roads have two lanes except for Off-Lake Road and Barwick Townline Road 27 4.4 Bridges and Culverts 4.4.1 State of Local Infrastructure The Municipality currently owns and manages 10 bridges and 1 major culvert, with an estimated replacement cost of $10,436,300.00. Table 4-7 provides a summary of the number, age, and replacement cost for the current bridge and major culvert inventory. The average age of the municipality's bridges and culverts is almost 41 years, with bridges averaging 44.7 years. The municipality's major culvert was completed in 2021. Table 4-7: Bridge and Culvert Infrastructure Summary Type Quantity Average Age Replacement Cost Bridges 10 44.7 $10,190,000.00 Culverts 1 1 $276,300.00 TOTAL 11 40.73 $10,436,300.00 *Replacement costs are calculated based on $6,500/m2 * Span* 8.2 (assumed deck width) * 1.3 unless the actual construction cost is known 4.4.2 Condition The Township of Chapple's 2021 Structure Inspection Appraisal Report, completed by K. Smart & Associates Ltd, assessed the condition of the bridge and culvert inventory, assigning a Bridge Condition Index (BCI) to each asset. A BCI score is provided on a numeric scale of 0-100 and is a measure of the overall condition of the structure based on an evaluation of individual components. Like road assets, to better communicate the condition of the bridge and culvert inventory, the numeric condition ratings have been segmented into qualitative condition states, as summarized in Table 4-8. 28 Table 4-8: Bridge and Culvert Condition States Defined with Respect to the Bridge Construction Index Condition (BCI) Condition Description Picture 93-100 Excellent 70-92 Good 65-70 Fair 30-49 Poor 0-29 Very poor N/A 29 Table 4-9 indicates bridges and culverts are both, on average, in a Good to Excellent condition state. The overall average BCI for the entire bridge and culvert inventory is 85.24 representing a Good to Excellent condition state. Two bridges are in Poor condition, meaning their BCI are less than 80. The 2021 Structure Inspection Appraisal Report has recommendations for rehabilitation or replacement projects for these structures. Table 4-9: Bridge and Culvert Condition Analysis Type Quantity Average BCI Number in Poor Condition Average Condition State Bridge 10 83.76 2 Good to Excellent Culvert 1 100 0 Excellent TOTAL 11 2 4.4.3 Current and Proposed Levels of Service - Bridges & Culverts The level of service currently provided by the Municipality's bridge and culvert inventory is, in part a result of the state of local infrastructure identified above. A levels of service analysis defines the current levels of service and enables the Municipality to periodically evaluate these service level objectives. Bridge and culvert assets have prescribed levels of service reporting requirements under O. Reg 588/17. These requirements include levels of service reporting at two levels - community levels of service and technical levels of service. Community levels of service objectives describe service levels in terms that customers understand and reflect customers' expectations with respect to the scope and quality of the bridge and culvert inventory. Technical levels of service describe the scope and quality of the Municipality's bridges and culverts through performance measures that can be quantified and evaluated. These performance measures can be used to assess how effectively a municipality is achieving its established targets. Table 4-10 provides a summary of this information for all major bridge and culvert assets, completed by K. Smart Associates Ltd. in the Township's 2021 Structure Inspection Appraisal Report. The Municipality plans to address the identified renewal needs over time, gradually increasing the overall condition of the inventory and following the proposed recommendations in the report. 30 Table 4-10: Current and Proposed Levels of Service - Bridges & Culverts Structure Name Approx. Year of Construction Estimated Replacement Cost Estimated Remaining Lifespan (Years) BCI Condition Ahrens Bridge 2019 $1,621,600.00 73 100.0 Excellent Barron Bridge 2010 $1,348,400.00 64 98.6 Excellent Hart Bridge 1970 $660,000.00 24 69.5 Fair Hickey Bridge 1967 $550,000.00 21 67.9 Poor Hilliard Bridge 1969 $675,000.00 23 87.0 Fair to Poor Irvine Bridge 1970 $675,000.00 24 79.7 Poor McCulloch Bridge 1966 $1,500,000.00 20 77.1 Fair Nanson Bridge 1968 $660,000.00 22 92.6 Good to Fair Off Lake Culvert 2021 $276,300.00 35 100.0 Excellent Woolsey Bridge 1960 $1,650,000.00 14 92.0 Fair Zimmerman Bridge 1974 $850,000.00 28 73.2 Good to Fair *Replacement costs are calculated based on $6,500/m2 *Span* 8.2 (assumed deck width) * 1.3 unless the actual construction cost is known. *Remaining lifespan assumes that a bridge has an expected lifespan of 75 years, and a culvert has an expected lifespan of 35 years. 31 4.5 Water and Wastewater Network 4.5.1 State of Local Infrastructure The Municipality currently owns and manages a water treatment and distribution system comprised of a water and wastewater treatment facility, sewers and watermains. The 2022 replacement cost of the system is approximately $9,090,000.00. Table 4-11 provides the current performance and replacement cost of the various types of assets. Table 4-11 Water Network Infrastructure Summary System/Type Good (No Deficiencies) Fair (Has Deficiencies) Poor (Requires Treatment/Spending) Replacement Cost (2022$) Water Treatment $1,101,000.000 $238,000.00 $1,541,000.00 $2,880,000.00 Wastewater Treatment $175,000.00 $515,000.00 $200,000.00 $890,000.00 Sewers $1,440,000.00 $860,000.00 $0.00 $2,300,000.00 Watermains $2,220,000.00 $800,000.00 $0.00 $3,020,000.00 Total $4,936,000.00 $2,413,000.00 $1,741,000.00 $9,090,000.00 4.5.2 Condition The Township of Chapple's water and wastewater network was assessed in 2022 by the Ontario Clean Water Agency (OCWA), assigning a Performance Rating to each asset. Table 4-12 provides a description of the performance ratings as provided by OCWA. Table 4-12 Asset Performance Rating Descriptions Performance Category Description State of Asset Good Asset performance meets or exceeds its objectives/requirements No deficiencies Fair Asset performance is nearing the point where it will not meet its objectives/requirements Has deficiencies Poor Asset performance is not meeting its objectives/requirements Requires treatment (spending) 32 Table 4-13 Current Asset Performance Category Table 4-13 indicates that Chapple's water network is, on average, in a Good to Fair condition state. The 2022 Asset Management Plan for Water and Wastewater Systems, developed by the Ontario Clean Water Agency for the Township of Chapple, contains recommendations for rehabilitation or replacement projects for these assets. 4.5.3 Current and Proposed Levels of Service - Water and Wastewater Network The level of service currently provided by the Municipality's water and wastewater network is, in part a result of the state of local infrastructure identified above. A levels of service analysis defines the current levels of service and enables the Municipality to periodically evaluate these service level objectives. Water and wastewater networks have prescribed levels of service reporting requirements under O. Reg 588/17. These requirements include levels of service reporting at two levels - community levels of service and technical levels of service. Community levels of service objectives describe service levels in terms that customers understand and reflect customers' expectations with respect to the scope and quality of the water and wastewater systems. Technical levels of service describe the scope and quality of the Municipality's water and wastewater network through performance measures that can be quantified and evaluated. These performance measures can be used to assess how effectively a municipality is achieving its established targets. The 2022 Asset Management Plan for Water and Wastewater Systems provides detailed summaries of this information for water and wastewater assets. The Municipality plans to address the identified renewal needs over time, gradually increasing the overall condition of the inventory and following the proposed recommendations provided by OCWA. 33 5.0 Asset Management Strategy The asset management strategy is a set of planned actions that will allow the Township of Chapple to ensure that its assets offer the desired levels of service, for a sustainable cost, while managing risk. This section summarizes the following: - Non-infrastructure solutions. - Maintenance activities. - Renewal / Rehabilitation activities. - Replacement activities. - Disposal activities. - Expansion activities. 5.1 Non-Infrastructure Solutions Non-infrastructure solutions are actions or policies that can lower costs or extend asset life. The Township of Chapple has identified many of these solutions in their official plan which was approved in 2013, and is intended to last for a period of 20 years. Included in the Basis for the plan is the following: - The Township of Chapple is characterized primarily by rural residential development and agriculturally based activities. The rural character of the Township will be maintained over the lifetime of this Plan. - Private water and sewage will continue to be the primary source of lot servicing in the Township. As a result, developments that require communal or full municipal services will be considered only with an amendment to this Plan. Any application to extend services from an adjacent municipality will be considered only with an amendment to the Official Plan. - Much of the Township's existing non-residential development occurs along Highway 11/71. This Plan recognizes the Highway 11/71 corridor as the continued focus of primary economic development in the Township. - The municipality presently provides an adequate level of services to allow for sufficient growth over the lifetime of this Plan. Development in the Township will occur on the basis of the existing level of municipal services. 34 Additionally, Section 6.0 of the plan indicates a mechanism for demand management, and a mechanism for directing development to limit the burden on existing road assets. It is recommended that the Township of Chapple continue to undertake land use planning, undertake development in accordance with the Official Plan, and continue with the fiscally sound methodology outlined in the Official Plan. Doing so will help manage demand, and ensure that the Township develops in such a way that has a sustainable plan to cover the costs needed to maintain levels of service. 5.2 Maintenance Activities A detailed list of maintenance activities for each asset is appended to this report. It is recommended that the Township undertake the identified maintenance within the timeframe identified in each asset report. Some significant maintenance activities that were identified during the inspection process include (these include critical health and safety issues and building code issues): 1. Install rated door, and closer at mechanical room in Municipal Office. 2. Provide second exit from second floor in Municipal Office. 3. Install fire dampers in ductwork at mechanical room in Municipal Office. 4. Install rate drywall on underside stairs at storage room in the Public Works Building. 5. Provide gas detection system in garage in the Public Works Building. 6. Re-set several floor boards in main level open area in the Museum. 7. Provide emergency exit signs in the Museum. 8. Cut off exposed guardrail anchor bolts and cap on the Lighthouse. 9. Finish off drywall in mechanical room in the Fire Hall. 10. Install rated door complete with closer to mechanical room in Fire Hall. 11. Relocate combustible material away from wood stove in Landfill Building. 12. Install door to electrical room in North Rink Shack. 13. Reattach grounding wire conduit to building in North Fire Hall. 14. Provide Epoxy seal on floor at generator and fuel tank in Water Treatment Plant Building. 15. Remove stored materials from diesel generator room in Water Treatment Plant Building. 16. Provide stop and speed limit signs to roads as required. 17. Install blind hill sign on Playford Road, Tait Road 35 18. Install Curve Signs on Woolsey Road, Cedar Yard Road. 19. Provide and install "Use road at own Risk sign" on Caul Road. 5.3 Renewal / Rehabilitation Activities A detailed list of maintenance activities for each asset is appended to this report. It is recommended that the Township undertake the identified maintenance within the timeframe identified in each asset report. Renewal / Rehabilitation costs are identified within each asset report. It should be noted that it is recommended that all roads be rehabilitated as described in the individual asset reports within a period of ten (10) years, as identified. It is recommended to: - Add an additional four inches of granular "A" to the entire length of Marr Road. - Add an additional four inches of granular "A" (0.8km to end) on Vanheyst Road. - Add an additional four inches of granular "A" to the entire length of Bolen Road South. - Resurface road (0-0.6km) on Nighswander Road. - Repair east retaining wall (wing wall) on Angus Road North Bridge #2. 5.4 Replacement Activities A detailed list of maintenance activities for each asset is appended to this report. It is recommended that the Township undertake the identified maintenance within the timeframe identified in each asset report. When required, replacement costs are identified within each asset report. It is recommended that the Township replace the following assets as identified in the asset reports. - Replace 20 meters of pavement (West of Main Street) on Ceder Yard Road - Replace 20 meters of pavement (in two locations) on Queen Street. - Replace 5 meter section of curb on Hele Road Bridge - Replace bent steel upright posts on Mather Road East Bridge #1 - Replace rotted retaining wall/abutment pile/post on Mather Road East Bridge #1 - Replace one 10x8 creosote-treated timber curb member on Mather Road East Bridge #2 - Replace and relevel one 12x12 creosote-treated support on Mather Road East Bridge #2 - Replace all retaining wall end piles (4) on Angus Road Bridge #2. - Replace curb supports (timbers) on Sturgeon Creek Bridge. - Replace two (2) guard rail boards on Sturgeon Creek Bridge. 36 5.5 Disposal Activities It is recommended that the Township dispose of assets in accordance with their procurement policy, if the asset has potential value (e.g. used vehicle, building). Otherwise, the Township should dispose of assets in accordance with environmental regulations as required. Disposal of assets should occur in accordance with the Official Plan. 5.6 Expansion Activities Expansion activities should occur in accordance with the Official Plan, which utilizes a fiscally responsible approach to development focussed on the Highway 11/71 corridor, which limits financial exposure. 37 6.0 Financial Plan 6.1 General overview of financial plan requirements In order for an AMP to be effectively put into action, it must be integrated with financial planning and long-term budgeting. The development of a comprehensive financial plan will allow the Township of Chapple to identify the financial resources required for sustainable asset management based on existing asset inventories, desired levels of service and projected growth requirements. The following pyramid depicts the various cost elements and resulting funding levels that should be incorporated into AMP's that are based on best practices. This report develops such a financial plan by presenting several scenarios for consideration and culminating with final recommendations. As outlined below, the scenarios presented model different combinations of the following components: a) The financial requirements for: - Existing assets - Existing service levels 38 - Requirements of contemplated changes in service levels (none identified for this plan) - Requirements of anticipated growth (none identified for this plan) b) Use of traditional sources of municipal funds: - Tax levies - User fees - Reserves - Debt - Development charges (not applicable) c) Use of non-traditional sources of municipal funds: - Reallocated budgets (not required for this AMP) - Partnerships (not applicable) - Procurement methods (no changes recommended) d) Use of other orders of government funds: - Federal gas tax - Grants If the financial plan component of an AMP results in a funding shortfall, the Province requires the inclusion of a specific plan as to how the impact of the shortfall will be managed. In determining the legitimacy of a funding shortfall, the Province may evaluate a municipality's approach to the following: a) In order to reduce financial requirements, consideration has been given to revising service levels downward. b) All asset management and financial strategies have been considered. For example: - If a zero debt policy is in place, is it warranted? If not, the use of debt should be considered. - Do user fees reflect the cost of the applicable service? If not, increased user fees should be considered. - Our organization recently attended the Ontario Good Roads Association meeting in which both the Premier and Minister of Infrastructure encouraged the carrying of a maximum of 11% debt load by municipalities. This is now considered prudent as it multi-generational. Thus a 10-year plan to finance a bridge would be viewed quite favourably by both Provincial and Federal funding agencies. 39 This AMP includes recommendations that avoid long-term funding deficits 6.2 Financial information relating to the Township of Chapple's AMP 6.2.1 Funding objective We have developed scenarios that would enable the Township of Chapple to achieve full funding within 10 years for the following assets: a) Tax funded assets - Road network, Bridges & Culverts, Facilities, Water & Wastewater, Equipment, Other For each scenario developed we have included strategies, where applicable, regarding the use of tax revenues, grant revenues, reserves and debt financing. It should be noted that in developing these scenarios it was projected that the percentage of total taxation revenue allocated to capital projects will remain consistent with prior year's allocations. In years prior to 2016 approximately 32% of total taxation revenue was allocated to capital projects and this was the percentage that was used for all projected taxation revenue dedicated to capital throughout this financial plan. It should be noted that the level of taxation revenue that the Township is able to dedicate to capital is quite exceptional as, for example, the City of Thunder Bay is only able to allocate approximately 10% of its budget to capital. 6.2.2 Tax funded assets 6.2.2.1 Current funding position Tables 1 and 2 outline, by asset category, the Township of Chapple's annual asset investment requirements, projected funding positions and funding changes projected and required to achieve full funding on assets funded by taxes. 40 Table 1: Summaries of Projected Annual Infrastructure Requirements and Projected Annual Funding 2016 Summary of Projected Annual Infrastructure Requirements and Projected Annual Funding Asset Category Projected 2013 Investment Required Taxes Gas Tax Other Total 2013 Projected Annual Surplus Roads $101,100 $238,234 $42,912 $ - $281,146 $180,046 Bridges & Culverts $11,000 $11,000 $ - $ - $11,000 $ - Facilities $53,900 $53,900 $ - $ - $53,900 $ - Water & Wastewater $6,000 $6,000 $ - $ - $6,000 $ - Equipment $7,500 $7,500 $ - $ - $7,500 $ - Other $2,000 $2,000 $ - $ - $2,000 $ - Total $181,500 $318,634 $42,912 $ - $361,546 $180,046 Years 1 to 5 Summary of Projected Annual Infrastructure Requirements and Projected Annual Funding Asset Category Projected Year 1 - 5 Investment Required Taxes Gas Tax Other Total Year 1 - 5 Projected Annual Deficit Roads $256,029 $214,945 $42,912 $ - $257,857 $1,828 Bridges & Culverts $31,850 $31,850 $ - $ - $31,850 $ - Facilities $35,630 $35,630 $ - $ - $35,630 $ - Water & Wastewater $51,700 $51,700 $ - $ - $51,700 $ - Equipment $7,500 $7,500 $ - $ - $7,500 $ - Other $2,000 $2,000 $ - $ - $2,000 $ - Total $382,709 $343,625 $42,912 $ - $307,546 $1,828 41 Years 6 to 10 Summary of Projected Annual Infrastructure Requirements and Projected Annual Funding Asset Category Projected Year 6 - 10 Investment Required Taxes Gas Tax Other Total Year 6 - 10 Projected Annual Surplus Roads $68,000 $334,363 $42,912 $ - $377,275 $309,275 Bridges & Culverts $11,000 $11,000 $ - $ - $11,000 $ - Facilities $14,000 $14,000 $ - $ - $14,000 $ - Water & Wastewater $6,000 $6,000 $ - $ - $6,000 $ - Equipment $7,500 $7,500 $ - $ - $7,500 $ - Other $2,000 $2,000 $ - $ - $2,000 $ - Total $106,500 $374,863 $42,912 $ - $417,775 $309,275 6.2.2.2 Recommendations for full funding The annual investment requirement for roads, bridges/culverts, facilities, water and wastewater, equipment, other deferred maintenance and ongoing maintenance, and the annual revenue allocated to these assets are: Table 2: Summary of Annual Investment Requirements and Annual Revenue Allocated Annual Investment Requirement Annual Revenue Allocated Annual Surplus (Deficit) 2016 $181,500 $361,546 $180,046 Years 1 to 5 $382,709 $386,537 $1,828 Years 6 to 10 $106,500 $417,775 $309,275 Therefore, the cumulative annual surplus for capital investments is projected to be $1,735,561. These infrastructure categories are projected to be funded via taxation revenue and Gas Tax at 100% of the townships long-term requirements assuming no additional capital spending other than the maintenance costs projected. The Township of Chapple budgeted for annual tax revenues of $955,086 in 2015. Planned funding would require an increase in tax revenue corresponding to the projected annual inflation rate. 42 We recommend that over the next 10 years an annual tax increase corresponding to the annual inflation rate be implemented in order to achieve the required total tax revenue. This involves full funding being achieved over 10 years by: a) Increasing tax revenues by the annual inflation rate each year for the next 10 years solely for the purpose of full funding to the 6 asset categories covered by this AMP. b) Allocating 100% of the gas tax revenue (currently $42,912) to the roads category. c) Applying for grant funding as required. It should be noted that several major capital outlays will be required in the next 5 years in order to achieve all of the requirements outlined in the AMP. These major capital items consist of: a) The Water Treatment System requires $93,500 in improvements which include a new backup pump, new Scada system, and new confined space equipment. b) The Lagoon requires $124,000 in improvements which include a new discharge line. c) Tait Road will require $203,450 in repairs and improvements including widening, additional gravel, and rock blasting d) Marr Road will require $102,300 in repairs and improvements including widening and ditching. In performing our projections these expenditures were not assigned to any particular year within the next 5 years. Instead these expenditures were projected in equal annual amounts throughout the next 5 years as it was not possible for us to project specifically which year the Township will perform these major repairs. This method ensures that all the expenditures are recorded within the projections. However, it does fail to indicate that these large expenditures will not be incurred in smaller annual amounts but will instead be incurred in larger less reliable expenditure amounts. The overall affect by the end of the 5 year and 10 year projections will be the same, however the actual expenditures will not be incurred as smoothly as these projections indicate. Although this option achieves full funding on an annual basis in 10 years and provides financial sustainability over the period modeled (to 2050), the recommendations do require prioritizing capital projects to fit the resulting annual funding available. Prioritizing these and future projects will require the age based data to be replaced by condition based data. 43 6.3 Use of Reserves 6.3.1 Available Reserves Reserves play a critical role in long-term financial planning. The benefits of having reserves available for infrastructure planning include: - The ability to stabilize tax rates when dealing with variable and sometimes uncontrollable factors. - Financing one-time or short-term investments. - Accumulating the funding for significant future infrastructure investments. - Managing the use of debt. - Normalizing infrastructure funding requirements. By reserve type, table 7 outlines the details of the reserves available to the Township of Chapple per the 2015 financial statements Table 7: Summary of Reserves Available Reserve Type Balance Reserve Funds Capital $463,005 Deferred Revenue Gas Tax $138,407 There is considerable debate in the municipal sector as to the appropriate level of reserves that a municipality should have on hand. There is no clear guideline that has gained wide acceptance. Factors that municipalities should take into account when determining their capital reserve requirements include: - Breadth of services provided - Age and condition of infrastructure - Use and level of debt - Economic conditions and outlook - Internal reserve and debt policies 44 6.4 Summary of financial Plan Table 10 illustrates the expected annual capital investments, revenues, reserve allocations and debt financing required under the recommended financial plan. Table 10: Summary of Annual Capital Transactions Under the Financial Plan Summary of 2016 Capital Transactions Under the Financial Plan Summary of Year 1 to 5 Annual Capital Transactions Under the Financial Plan Asset Category Year 1 - 5 Annual Investment Required Year 1 - 5 Projected Annual Taxation Revenue Year 1 - 5 Projected Annual Gas Tax Year 1 - 5 Projected Annual Grant Revenue Year 1 - 5 Annual Surplus (Deficit) Year 1 - 5 Projected Annual Reserve Allocations Year 1 - 5 Annual Debt Financing Year 1 - 5 Adjusted Annual Surplus (Deficit) Roads $256,029 $214,945 $42,912 $ - $1,828 $ - $ - $ 1,828 Bridges & Culverts $31,850 $31,850 $ - $ - $ - $ - $ - $ - Facilities $35,630 $35,630 $ - $ - $ - $ - $ - $ - Water & Wastewater $51,700 $51,700 $ - $ - $ - $ - $ - $ - Equipment $7,500 $7,500 $ - $ - $ - $ - $ - $ - Other $2,000 $2,000 $ - $ - $ - $ - $ - $ - Total $508,649 $343,625 $42,912 $ - $1,828 $ - $ - $1,828 Asset Category 2016 Annual Investment Required 2016 Projected Taxation Revenue 2016 Projected Gas Tax 2016 Projected Grant Revenue 2016 Surplus (Deficit) 2016 Projected Reserve Allocations 2016 Debt Financing 2016 Adjusted Surplus (Deficit) Roads $101,100 $238,234 $42,912 $ - $180,046 $ - $ - $180,046 Bridges & Culverts $11,000 $ 11,000 $ - $ - $ - $ - $ - $ - Facilities $53,900 $53,900 $ - $ - $ - $ - $ - $ - Water & Wastewater $6,000 $6,000 $ - $ - $ - $ - $ - $ - Equipment $7,500 $7,500 $ - $ - $ - $ - $ - $ - Other $2,000 $2,000 $ - $ - $ - $ - $ - $ - Total $181,500 $318,634 $42,912 $ - $180,046 $ - $ - $180,046 45 Summary of Year 6 to 10 Annual Capital Transactions Under the Financial Plan Asset Category Year 6 - 10 Annual Investment Required Year 6 - 10 Projected Annual Taxation Revenue Year 6 - 10 Projected Annual Gas Tax Year 6 - 10 Projected Annual Grant Revenue Year 6 - 10 Annual Surplus (Deficit) Year 6 - 10 Projected Annual Reserve Allocations Year 6 - 10 Annual Debt Financing Year 6 - 10 Adjusted Annual Surplus (Deficit) Roads $68,000 $334,363 $42,912 $ - $309,275 $ - $ - $309,275 Bridges & Culverts $11,000 $11,000 $ - $ - $ - $ - $ - $ - Facilities $14,000 $14,000 $ - $ - $ - $ - $ - $ - Water & Wastewater $6,000 $6,000 $ - $ - $ - $ - $ - $ - Equipment $7,500 $7,500 $ - $ - $ - $ - $ - $ - Other $2,000 $2,000 $ - $ - $ - $ - $ - $ - Total $106,500 $374,863 $42,912 $ - $309,275 $ - $ - $309,275 The recommended plan will result in the Township of Chapple being able to complete all recommended investments in the capital assets as outlined by the AMP. The financial plan will result in the township annually increasing its tax rate by the annual inflation rate over the next 10 years. It is assumed that Gas Tax revenue will remain constant at $42,912 over the next 10 years as there is no indication from the information reviewed that these revenues will significantly increase. It should be noted that in preparing this financial plan several projections and estimates were required and it is possible that actual future results could differ materially from the projections and estimates that were utilized in preparing the above financial plan. 46 7.0 Lifecycle Management Strategy 7.1 Introduction This section details the lifecycle management strategies required to achieve the proposed levels of service outlined in Section 4.0. A lifecycle management strategy identifies the recommended lifecycle activities required to achieve the levels of service discussed in Section 4.0. Within the context of this Asset Management Plan, lifecycle activities are the specified actions that can be performed on an asset to ensure it is performing at an appropriate level and/or to extend its service life. These actions can be carried out on a planned schedule in a prescriptive manner, or through a dynamic approach where the lifecycle activities are only carried out when specified conditions are met. O. Reg 588/17 requires that all potential lifecycle activity options be presented, with the aim of analyzing these options in search of identifying the set of lifecycle activities that can be undertaken at the lowest cost to maintain current levels of service or to provide proposed levels of service. Asset management plans must include a 10-year capital plan that forecasts the lifecycle activities resulting from the lifecycle management strategy. What follows are the lifecycle management strategies for all assets contained within this Asset Management Plan, with each section focusing on an individual asset class. 7.1.1 Population and Economic Activity - Impact on Lifecycle Management As of the 2021 Census, the Municipality had a population of 763. This represents a change of 18.7% from its 2016 population of 643. This population growth, though minimal, may result in incremental service demands that could impact levels of service in the future. Climate change and severe weather events, including flooding and drought conditions experienced in 2021 and 2022, may have negative impacts on specific core assets, putting them under more stress, and likely shortening their service lives. As a result, assets may need more frequent repair, maintenance, and replacement in the future, which could impact the lifecycle activities detailed in Section 7. 47 7.2 Roads and Roads Related 7.2.1 Lifecycle Activities This section will detail the lifecycle activities as identified through discussions with the municipality's Public Works department. The lifecycle activities that the Municipality currently employs in the management of its roads include patching, grading, gravel resurfacing, surface treatment, dust layer, ditching and brushing. Table 7-1 details the maintenance treatments associated with undertaking these lifecycle activities, by road surface type. Table 7-1 Road Lifecycle Activity Costs by Surface Type (per km) Surface Type Quantity (kms) Maintenance Treatment Reconstruction Treatment Asphalt 6.6 Patching -Fill potholes with cold mix, add asphalt on paved and surface treated areas Earth 41.4 Gravel Resurfacing -Haul 'A' Gravel onto roads and grade Gravel 421.9 Gravel Resurfacing/Dust Layer/Grading/Ditching/Brushing/Surface Treatment -Haul 'A' gravel onto roads and grade -Add layer of calcium chloride onto gravel roads -Maintain ditches to allow for water to flow away from roads -Brushing/cutting overgrown vegetation around roads to keep visual clearance and maintain ditches *Assets like sidewalks, streetlights, and signs have a simple lifecycle - they are simply replaced if they are found not to be delivering the desired level of service. Figure 7-2 provides a 10-year forecast of expenditures for lifecycle activities and costs for all the municipality's roads, based on lifecycle costs from 2021. As stated in Section 4, 90% of Chapple's road network consists of gravel roads. The condition of gravel roads can deteriorate rapidly and is less costly to improve through these lifecycle activities, such as routine grading and gravelling. As a result, most lifecycle activities for roads are funded through the municipality's operating budget, rather than the capital budget. The forecast illustrates the average annual expenditures, and the projected 10-year costs. 48 Table 7-2 Annual Average Lifecycle Cost (per km) Surface Type/ Lifecycle Activity Quantity (kms) Average Annual Lifecycle Cost ($2021) 10-year Forecast Asphalt Patching 6.6 $3,650.00 $36,500.00 Gravel Gravel Resurfacing 421.9 $172,375.00 $1,723,750.00 Dust Layer 421.9 $85, 075.00 $850,750.00 Grading 421.9 $47,200.00 $472,000.00 Ditching 421.9 $11,765.00 $117,650.00 Brushing 421.9 $18,150.00 $181,500.00 Surface Treatment 421.9 $5,150.00 $51,500.00 TOTAL $343,365.00 $3,433,650.00 *Lifecycle costs and forecasted costs are represented in 2021 dollars and do not account for inflation or price changes over time 49 7.3 Bridges and Culverts 7.3.1 Managing Bridges and Culverts O. Reg 104/97 requires that structural bridges and culverts be inspected every two years by professional engineers. The Township of Chapple plans to manage bridges and culverts by completing the work recommended in the inspection reports. By following the engineering recommendations, the municipality believes it can continue to operate the bridges safely on an ongoing basis. 7.3.2 Lifecycle Activities This section identifies a generalized lifecycle model for bridges and culverts. Minor rehabilitation, major rehabilitation, and reconstruction have been included in the general lifecycle model. In the 2021 OSIM report, lifecycle activities with a total cost of $7,350,500.00 were identified that needed to be done over the next ten years. Table 7-3 shows the distribution of the costs of the projects over the ten-year forecast period as recommended in the report. Table 7-3 List of Repair and Rehabilitation Work Recommended in 2021 OSIM Report Timeframe Total Cost Urgent $0.00 Years 1 - 5 $1,978,000.00 Years 6 - 10 $5,372,500.00 Total $7,350,500.00 50 7.4 Water and Wastewater Network 7.4.1 Managing the Network By-Law 1675, dated July 24, 2018, authorized the Township of Chapple to enter into a 10-year agreement with the Ontario Clean Water Agency (OCWA). OCWA provides management, operation, and maintenance services in respect to the Municipality's water and wastewater treatment and lagoon facilities. O. Reg. 170/03 made under the Safe Drinking Water Act (2002), requires that the owner of a drinking water system prepare an annual report on the operation of the system and quality of its water. The Township of Chapple manages its water network by completing the work recommended in these annual and monthly reports provided by OCWA and made publicly available on the municipality's website. In 2022, OCWA developed an Asset Management Plan for Water and Wastewater Systems for the Township of Chapple. By following the recommendations provided by OCWA, the municipality believes it can continue to operate the water network safely on an ongoing basis. 7.4.2 Lifecycle Activities This section will detail the lifecycle activities for Chapple's Water and Wastewater Network as identified by the Ontario Clean Water Agency. The lifecycle activities that the Municipality currently employs in the management of its water network is detailed in the publicly available monthly and annual reports submitted by the Ontario Clean Water Agency, as well as the 2022 Asset Management Plan for Water and Wastewater Systems. These reports also provide details of all non-routine maintenance, capital project forecasting and estimated costs. In the most recent report provided by OCWA, lifecycle activities with a total cost of approximately $325,000.00 per year are needed over the next 20 years to achieve asset performance expectations for the water and wastewater systems. This average annual spending needs include an estimated $5,500,000.00 for a large project associated with the new well supply. The average annual spending need is approximately $80,000.00 per year for the water and wastewater systems when the $5,500,000.00 is isolated from the analysis. In the 2022 Asset Management Plan for Water and Wastewater Systems, lifecycle activities were identified that needed to be completed over a 20-year period. Table 7-4 provides a summary of the anticipated annual spending for these lifecycle activities. 51 Table 7-4 Annual Spending Forecast/Lifecycle Costs - Water and Wastewater Systems CHAPPLE Maintenance and Upgrade Summary Asset Name Asset Number Asset Ext. Year of Construction Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Totals Municipal Office 100000 01 1980 $ 11,350.00 $ 2,150.00 $ 13,500.00 Public Works Building 100000 02 1980 $ 10,300.00 $ 800.00 $ 11,100.00 Small Garage 100100 01 2000 $ 350.00 $ 350.00 Mortuary 100200 01 1994 $ 1,300.00 $ 1,300.00 Museum 100300 01 2000 $ 1,500.00 $ 750.00 $ 6,500.00 $ 8,750.00 Recreation Centre/Hall 100400 01 1940 $ 12,000.00 $ 25,000.00 $ 37,000.00 Shed Single Stall 100500 01 1980 $ 6,400.00 $ 6,400.00 Deck 100600 01 1994 $ 800.00 $ 3,000.00 $ 3,800.00 Pavilion 100700 01 1999 $ 800.00 $ 1,800.00 $ 2,600.00 Riverview Park Pavilion 100800 01 1970 $ 2,250.00 $ 2,250.00 Rink 100900 01 2008 $ - Rink Shack 101000 01 1970 $ 1,300.00 $ 1,800.00 $ 3,100.00 Rink Shack Pumphouse 101100 01 1970 $ 525.00 $ 525.00 Lighthouse 101200 01 1999 $ 500.00 $ 1,550.00 $ 2,050.00 Fire Hall 101300 01 1990 $ 1,400.00 $ 2,000.00 $ 3,400.00 Sports field Canteen 101400 01 1995 $ 550.00 $ 5,000.00 $ 5,550.00 Covered Picnic Area 101500 01 1997 $ 1,000.00 $ 1,000.00 Landfill Building 101600 01 1997 $ - $ 200.00 $ 200.00 Equipment Storage 101700 01 1970 $ 400.00 $ 400.00 St. Paul's Heritage Place Church 101800 01 1901 $ 8,800.00 $ 8,000.00 $ 16,800.00 North Rink 101900 01 2003 $ 500.00 $ 500.00 North Rink Shack 102000 01 1970 $ 350.00 $ 6,450.00 $ 6,800.00 North Fire Hall 102100 01 1990 $ 50.00 $ 1,350.00 $ 1,400.00 Water Treatment Plant Building 102200 01 1993 $ 5,100.00 $ 10,000.00 $ 15,100.00 Playground 200000 01 2003 $ 100.00 $ 100.00 Sport field Recreation Area 200100 01 1950 $ 10,000.00 $ 4,250.00 $ 14,250.00 5 Stall RV Park 200400 01 1986 $ - Docks 200500 01 2013 $ - Boat Launch 200600 01 1994 $ - WATER TREATMENT SYSTEM 400000 01 1993 $ 93,500.00 $ 93,500.00 WELL #1 400000 01 1993 $ - WELL #2 400200 01 1993 $ - WELL #3 400300 01 1993 $ - WELL #4 400400 01 1993 $ 500.00 $ 500.00 WELL #5 400500 01 1993 $ - WELL #6 400600 01 1993 $ 3,500.00 $ 3,500.00 200mmø WATERMAIN 400700 01 1993 $ - $ - 150mmø WATERMAIN 400800 01 1993 $ - $ - SHENSTON DUMP 450000 01 1989 $ - LAGOON 450200 01 1989 $ 124,000.00 $ 124,000.00 SEWAGE LIFT STATION 450300 01 1989 $ 12,000.00 $ 12,000.00 200mmø SANITARY SEWER 450400 01 1989 $ - STREET LIGHTS 500000 01 2008 $ - Brigham Road North 600100 01 10 $ 300.00 $ 10,950.00 $ 11,250.00 Brigham Road South 600200 01 10 $ 300.00 $ 1,920.00 $ 2,220.00 Westover Road 600300 01 10 $ 900.00 $ 28,420.00 $ 29,320.00 Westover Road 600300 02 10 $ 1,200.00 $ 1,200.00 $ 2,400.00 Playford Road 600400 01 10 $ 300.00 $ 850.00 $ 1,150.00 Wilson Road 600500 01 10 $ 300.00 $ 2,550.00 $ 2,850.00 Sturgeon Creek Road 600600 01 10 $ 300.00 $ 1,700.00 $ 2,000.00 Angus Road South 600700 01 10 $ 600.00 $ 1,335.00 $ 1,935.00 Angus Road North 600800 01 10 $ 600.00 $ 7,100.00 $ 7,700.00 Gibson Road 600900 01 10 $ 600.00 $ 1,265.00 $ 1,865.00 Irvine Road 601000 01 10 $ 600.00 $ 2,100.00 $ 2,700.00 Moulton Road 601100 01 10 $ 600.00 $ 1,700.00 $ 2,300.00 Hart Road 601200 01 10 $ 900.00 $ 23,400.00 $ 24,300.00 Mather Road West 601400 01 10 $ 1,800.00 $ 3,900.00 $ 5,700.00 Mather Road East 601500 01 10 $ 1,200.00 $ 6,500.00 $ 7,700.00 Olson Road 601600 01 10 $ 300.00 $ 20,100.00 $ 20,400.00 Hunsperger Road 601700 01 10 $ 300.00 $ 3,470.00 $ 3,770.00 CHAPPLE Maintenance and Upgrade Summary Asset Name Asset Number Asset Year of Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Totals Ext. Construction McNally Road 601800 01 10 $ 900.00 $ 1,300.00 $ 2,200.00 Elliot Road 601900 01 10 $ 600.00 $ 500.00 $ 1,100.00 R. Wilson Road 602000 01 10 $ 600.00 $ 24,520.00 $ 25,120.00 Cates Road 602100 01 10 $ 300.00 $ 1,250.00 $ 1,550.00 Frenches Road 602200 01 10 $ 300.00 $ 7,020.00 $ 7,320.00 Korpi Road 602300 01 10 $ 5,000.00 $ 502,500.00 $ 155,000.00 $ 662,500.00 Curtis Pit Road 602400 01 10 $ 300.00 $ 800.00 $ 1,100.00 Lampi Road 602500 01 10 $ 1,800.00 $ 47,020.00 $ 48,820.00 Boundary Lake Road 602600 01 10 $ 900.00 $ 19,095.00 $ 19,995.00 Maki Road 602700 01 10 $ 34,880.00 $ 34,880.00 Heatwole Road 602800 01 10 $ 600.00 $ 4,970.00 $ 5,570.00 Gallinger Road 602900 01 10 $ 300.00 $ 18,800.00 $ 19,100.00 Marrs Road 603100 01 10 $ 300.00 $ 102,000.00 $ 102,300.00 Teeple Road 603200 01 10 $ 1,400.00 $ 1,400.00 Hayes Road 603300 01 10 $ 900.00 $ 1,100.00 $ 2,000.00 Church Road 603400 01 10 $ 900.00 $ 1,400.00 $ 2,300.00 Barwick Road 603500 01 10 $ 1,200.00 $ 1,200.00 Barwick Road 603500 02 10 $ 1,550.00 $ 1,550.00 Barwick Road 603500 03 10 $ 2,350.00 $ 2,350.00 Barwick Road 603500 04 10 $ 5,000.00 $ 5,000.00 Atkinson Road 603600 01 10 $ 4,250.00 $ 4,250.00 Vanheyst Road 603700 01 10 $ 300.00 $ 34,880.00 $ 35,180.00 Tait Road 603800 01 10 $ 2,700.00 $ 200,750.00 $ 203,450.00 Huziak Road 603900 01 10 $ 300.00 $ 12,950.00 $ 13,250.00 Woolsey Road 604000 01 10 $ 1,200.00 $ 1,300.00 $ 2,500.00 Development Road 604100 01 10 $ 900.00 $ 3,250.00 $ 4,150.00 OIEN ROAD 604200 01 10 $ 300.00 $ 6,940.00 $ 7,240.00 HELE ROAD 604300 01 10 $ 300.00 $ 23,650.00 $ 23,950.00 MCCULLOCH ROAD 604400 01 10 $ 300.00 $ 2,050.00 $ 2,350.00 FEHER ROAD 604500 01 10 $ 1,200.00 $ 4,150.00 $ 5,350.00 BOLEN ROAD NORTH 604600 01 10 $ 1,000.00 $ 19,600.00 $ 20,600.00 BOLEN ROAD SOUTH 604600 02 10 $ 8,550.00 $ 8,550.00 STEINER ROAD 604700 01 10 $ 600.00 $ 1,000.00 $ 1,600.00 TAYLOR ROAD 604800 01 10 $ 300.00 $ 800.00 $ 1,100.00 CLINK ROAD 604900 01 10 $ 300.00 $ 500.00 $ 800.00 CAUL ROAD 605000 01 10 $ 300.00 $ 300.00 MORLEY-CHAPPLE ROAD 605100 01 10 $ 1,200.00 $ 60,400.00 $ 61,600.00 PRISON FARM ROAD 605200 01 10 $ 300.00 $ 7,300.00 $ 7,600.00 CEDER YARD ROAD 605300 01 10 $ 300.00 $ 300.00 CEDER YARD ROAD 605300 02 10 $ 9,000.00 $ 9,000.00 QUEEN STREET 605400 01 10 $ 600.00 $ 9,500.00 $ 10,100.00 MILL ROAD 605500 01 10 $ 300.00 $ 250.00 $ 550.00 AGNES STREET 605600 01 10 $ 1,500.00 $ 1,500.00 ALLEY WAY 605700 01 10 $ 900.00 $ 500.00 $ 1,400.00 CAWSTON AVENUE 605800 01 10 $ 1,000.00 $ 1,000.00 NIGHSWANDER ROAD 605900 01 10 $ 600.00 $ 9,750.00 $ 10,350.00 MAIN STREET 606000 01 10 $ 3,000.00 $ 3,000.00 HILLBILLY ROAD 606100 01 10 $ 3,500.00 $ 3,500.00 Walking Bridge 800000 01 2008 $ 850.00 $ 850.00 Barwick Rd Bridge (Barron Bridge) 800100 01 2010 $ 20,000.00 $ 20,000.00 MCCULLOCH ROAD BRIDGE 800200 01 1966 $ 800.00 $ 100,000.00 $ 900,000.00 $ 1,000,800.00 HELE ROAD BRIDGE (Woosley Bridge) 800300 01 1960 $ 41,800.00 $ 1,000,000.00 $ 1,041,800.00 MATHER RD E BRIDGE #1 (Hilliard Bridge) 800400 01 1969 $ 78,000.00 $ 78,000.00 MATHER RD E BRIDGE #2 (Hickey Bridge) 800500 01 1967 $ 21,200.00 $ 350,000.00 $ 371,200.00 ANGUS RD BRIDGE #1 (Nanson Bridge) 800600 01 1968 $ 16,500.00 $ 16,500.00 ANGUS RD BRIDGE #2 (Zimmerman Bridge) 800700 01 1974 $ 25,600.00 $ 25,600.00 STURGEON CREEK BRIDGE (Ahrens Bridge) 800800 01 1955 $ 888,200.00 $ 888,200.00 ANGUS RD N BRIDGE #1 (Hart Bridge) 800900 01 1970 $ 36,000.00 $ 36,000.00 ANGUS RD N BRIDGE #2 (Irvine Bridge) 801000 01 1970 $ 90,000.00 $ 90,000.00 FIRE RESCUE VEHICLE 5-6 901000 01 2006 $ - CHAPPLE Maintenance and Upgrade Summary Asset Name Asset Number Asset Year of Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Totals Ext. Construction FIRE TRUCK 5-3 901100 01 1989 $ - FIRE TRUCK 5-4 901200 01 1995 $ - FIRE TRUCK 5-2 901300 01 2000 $ - LINK-BELT BACKHOE 902000 01 1999 $ - VOLVO STRONGCO GRADER 902100 01 1999 $ - DODGE RAM 3500 FLATBED 902200 01 1995 $ - JOHN DEERE F915 902300 01 2007 $ - Case 721F 902400 01 2015 $ - Cat 140M Grader 902500 01 2008 $ - JOHN DEERE 2350 TRACTOR 902600 01 1986 $ 700.00 $ 700.00 PETERBUILT TANDEM TRUCK 902700 01 2017 $ - MIDLAND BELLY DUMP TRAILER 902800 01 2014 $ - FORD F150 XLT 902900 01 2013 $ - CHAPPLE TANDEM DUMP TRUCK 903000 01 2005 $ - John Deere 644B Loader 903100 01 1981 $ 50.00 $ 2,500.00 $ 2,550.00 John Deere 450 Dozer 903200 01 1993 $ 50.00 $ 50.00 Totals: $ 80,350.00 $ 2,946,360.00 $ 46,100.00 $ 5,000.00 $ - $ 505,000.00 $ - $ - $ - $ - $ 1,900,000.00 $ 5,485,410.00 i TOWNSHIP OF CHAPPLE COMMUNITY LAYOUT FRENCHRO(lm200-01) .....,..,,.,..,\. iiI -------l=J I i i 0 KOl'iPIR0 (602:»>-01) 7 TEE PI..EI.D (!liX.'200-01) 0 GIBSON f..D(tU»»01). MGU Sfi O,.O NQfilH - - BhlDOEIQ(N1i»J-01) ANGUS ROAD NORTH"' BRt DOEr 1 ) i MATHER EAST (6)15'»01) ANGUS,:.O,.OBf-lJGE.IQ.(!007'00-01)/ _ ANGUS r.o,,.o llf-lOGE 11 r.o.»J()-01)"' TAYlOfl'-0 1)1 ! 8 TURGEONCf;EE K1 BF;IDGE(eooeoo.l1) STURGEONCREEK R0 (600600-01) ACCULLOCH F.OBF.I00£( 1) I 700.QI) T WESTClVERI.Otro,}300-01) PROJECT: TOWNSHIP OF CHAPPLE - MUNICIPAL ASSET MANAGEMENT PLAN PREPARED BY: SAULTEAUX CONSULTING & ENGINEERING SITE 206-207 RR#2 FORT FRANCES, ONTARIO P9A3M3 1-807-274-7114 1\ "'"' " "\ i TOWNSHIP OF CHAPPLE MAIN TOWNSITE WELL #1 (401000-01) MUNICIPAL OFFICE (100000-01) PUBLIC WORKS BUILDING (100000-02) WELL #2 (402000-01) SHED SINGLE STALL (100500-01) WATER TREATMENT PLANT BUILDING (102200-01) WATER TREATMENT SYSTEM (400000-01) SMALL GARAGE (100100-01) WELL #6 (406000-01) WELL #3 (403000-01) WELL #5 (405000-01) WELL #4 (404000-01) HIGHWAY 11 HIGHWAY 11 0 ' SPORTFIELD RECREATION AREA (200100-01) EQUIPMENT STORAGE (101700-01) COVERED PICNIC AREA (101500-01) SPORTSFIELD CANTEEN (101400-01) FIREHALL (101300-01) PLAYGROUND (200300-01) WALKING BRIDGE (800000-01) DECK (100600-01) RIVERVIEW PARK RECREATION CENTRE/HALL (100400-01) 5 STALL RV PARK (200400-01) PAVILLION (100700-01) RINK (100900-01) RINK SHACK (101000 -01) SEWAGE LIFT STATION (450300-01) LAGOON (450200-01) NORTH FIRE HALL PROPERTY ( MILL ROAD (605500-01) RINK SHACK PUMPHOUSE (101100-01) DOCKS (200500-01) BOAT LAUNCH (200600-01) / LIGHTHOUSE (101200-01) "- SH ,::: I (!) :i: NORTH RINK (101900-01) NORTH RINK SHACK (102000-01) NORTH FIRE HALL (102100-01) PROJECT : TO WNSHIP OF CHAPPLE - MUNICIPAL ASSET MANAGEMENT PLAN PREPARED BY: SAULTEAUX CONSU LTING & ENGINEERING SITE 206-207 RR#2 FORT FRANCES, ONTARIO P9A 3M3 1-807-274-7114