Township of Emo
Asset Management Plan
Prepared By:
June 14, 2017
2
Saulteaux Consulting and Engineering would like to thank Crupi Consulting Group
for their assistance in the preparation of this Asset Management Plan:
3
Contents
1.0
Executive Summary .......................................................................................................................... 4
2.0
Introduction ...................................................................................................................................... 5
2.1
Asset Listing .................................................................................................................................. 5
3.0
State of Local Infrastructure ............................................................................................................ 9
3.1
Asset Types ................................................................................................................................... 9
3.2
Total Maintenance, Remediation, Rehabilitation, and Replacement Costs ............................... 11
3.3
Asset Condition, Asset Age Distribution ..................................................................................... 13
4.0
Desired Levels of Service ................................................................................................................ 18
4.1
Assumptions & Performance Measures ..................................................................................... 18
5.0
Asset Management Strategy ......................................................................................................... 21
5.1
Non-Infrastructure Solutions ...................................................................................................... 21
5.2
Maintenance Activities ............................................................................................................... 22
5.3
Renewal / Rehabilitation Activities ............................................................................................. 23
5.4
Replacement Activities................................................................................................................ 23
5.5
Disposal Activities ....................................................................................................................... 24
5.6
Expansion Activities .................................................................................................................... 24
6.0
Financial Strategy ........................................................................................................................... 25
6.1 General overview of financial plan requirements ............................................................................ 25
6.2 Financial information relating to the Township of Emo's AMP ........................................................ 27
6.2.1 Funding objective ...................................................................................................................... 27
6.3 Tax funded assets ............................................................................................................................. 27
6.3.1 Current funding position ........................................................................................................... 27
6.3.2. Recommendations for full funding .......................................................................................... 29
6.4 Use of Grant Funding ........................................................................................................................ 30
6.4.1 Grant funding ............................................................................................................................ 30
6.4.2 Recommendation ...................................................................................................................... 31
6.5 Use of debt ....................................................................................................................................... 32
6.5.1 Use of debt ................................................................................................................................ 32
6.5.2 Recommendation ...................................................................................................................... 34
6.6 Use of Reserves ................................................................................................................................ 34
6.6.1 Available reserves ..................................................................................................................... 34
6.6.4 Recommendation ...................................................................................................................... 35
6.7 Summary of Financial Plan ............................................................................................................... 36
4
1.0 Executive Summary
Saulteaux Consulting and Engineering (SCE) has prepared this Asset Management Plan
(AMP) for the Township of Emo. In preparing the plan, SCE worked with Crupi Consulting Group
(CCG). SCE undertook the inspections of Municipal Buildings, Recreation, Water, Waste Water,
Electrical, Roads, and Vehicle inspections. CCG undertook the financial analysis, and life cycle
costing process.
This AMP provides an overview of the estimated future expenditures related to
municipal assets over the period of the next ten (10) years. This document will help the
Township to undertake an ongoing process to budget for the expenditures necessary to
maintain the service levels that have been outlined in the Township's Official Plan. Additionally,
the plan identifies assets which require urgent attention in order to bring them to standard,
and further identifies a recommended timeframe to undertake necessary maintenance,
rehabilitation, and in some cases replacement of assets. The financial plan (Section 6.0) of this
plan, outlines a recommended strategy for the Township to finance the necessary work while
limiting the tax burden, and maintaining a fiscally responsible, sustainable approach to asset
management.
Included in the plan are recommendations regarding the maintenance of each asset. If
identified maintenance is completed, and ongoing maintenance is undertaken, this will extend
the lifecycle of assets, giving the Township a much more manageable budgeting process.
All assumptions regarding levels of service are listed within the plan, the financial plan is
developed with the understanding that the Township intends to maintain existing levels of
service, and that any future development would be undertaken as per the Official Plan.
5
2.0 Introduction
This asset management plan has been developed for the Township of Emo to assist the
Township in making informed choices regarding future investment. This plan helps to define
priorities for future spending, identifies estimated maintenance costs for existing assets, and
defines a financing strategy. The goal of this process is to provide the Township with the
information required to ensure that it can develop a financing strategy to maintain satisfactory
levels of service, and undertake required investments in the future.
Additionally, this process reviews the lifecycle cost of each asset including construction,
ongoing maintenance, and disposal. Consideration has been given to ensuring that services are
maintained in an environmentally sustainable manner, as per the Township's Official Plan. A
key feature of this plan is that it will provide the Township with a prioritized listing of
infrastructure needs. This listing of priorities will help the Township to identify projects to
undertake in the coming years, with a clear focus on the most urgent priorities, projects that
will require investment within the next three years.
This plan is designed to cover the lifecycle of each asset, and is intended as a living
document to be amended, as required, or when new tangible assets are added to the Asset
Listing.
For the purposes of completing this project, Saulteaux Consulting and Engineering (SCE)
has worked with Crupi Consulting Group (CCG). SCE undertook the inspections of Municipal
Buildings, Recreation, Water, Waste Water, Electrical, Roads, and Vehicle inspections. CCG
undertook the financial analysis, and life cycle costing process.
2.1 Asset Listing
The following assets are included in the plan:
Table 2.1 - Asset Listing
Asset Name
Asset No.
Ext. No.
Asset
Code
Quantity
Units
Municipal Office
100000
01
A1A
194.43
SQ. M
Curling Club Building
100100
01
A6A
1065.95
SQ. M
Public Library
100200
01
A3E
164.73
SQ. M
Toy Library
100200
02
A3E
141.93
SQ. M
Library Storage
100300
01
A2C
9.86
SQ. M
Pavilion
100400
01
A6H
80.63
SQ. M
Splash Pad Building
100500
01
A5A
27.55
SQ. M
6
Asset Name
Asset No.
Ext. No.
Asset
Code
Quantity
Units
Washrooms
100600
01
A6H
45.33
SQ. M
Deck #1
100700
01
A6Z
36.86
SQ. M
Deck #2
100800
01
A6Z
36.86
SQ. M
Deck #3
100900
01
A6Z
107.99
SQ. M
Sportsfield Building
101000
01
A6H
121.57
SQ. M
Sportsfield Canopy
101100
01
A6H
127.58
SQ. M
Mortuary
101200
01
A3I
22.76
SQ. M
Snowmobile Club Building
101300
01
A6E
130.43
SQ. M
Storage and Recycling Building
101400
01
B4Z
235.26
SQ. M
Maintenance Garage/Fire Hall
101500
01
A2B/A3H
877.26
SQ. M
OPP Generator Building
101600
01
A5C
19.5
SQ. M
OPP Residence #21
101700
01
A4A
192.72
SQ. M
OPP Residence #25
101800
01
A4A
192.72
SQ. M
OPP Residence #31
101900
01
A4A
192.72
SQ. M
Arena
102000
01
A6B
3089.24
SQ. M
Emo OPP Building
102100
01
A1A
333.78
SQ. M
RR Futures Development Corporation
102200
01
A1A
197.37
SQ. M
Water Treatment Plant
102300
01
A5A
353.25
SQ. M
Water Treatment Storage Garage
102400
01
A2B
59.2
SQ. M
Little House
102500
01
A6H
7.87
SQ. M
Playground
200000
01
C5D
434
SQ. M
Tennis Court
200100
01
C5D
1247.8
SQ. M
Sportfield Area
200200
01
C5D
94700
SQ. M
Splash Park
200300
01
C5D
85
SQ. M
Water Treatment System
400000
01
B1C
1
EA
150mmø Watermain PVC
400100
01
B1B
7050
M
200mmø Watermain PVC
400200
01
B1B
930.5
M
300mmø Watermain PVC
400300
01
B1B
1445.22
M
150mmø Watermain DI
400400
01
B1B
3949.25
M
200mmø Watermain HDPE
400500
01
B1B
63.68
M
300mmø Watermain HDPE
400600
01
B1B
70.41
M
450mmø Watermain HDPE
400700
01
B1B
343.49
M
Sewage Lagoon
450000
01
B2E
1
EA
200mmø Sanitary Main
450100
01
B2A
5827.98
M
250mmø Sanitary Main
450200
01
B2A
3658.96
M
300mmø Sanitary Main
450300
01
B2A
498.64
M
100mmø Sanitary Forcemain
450400
01
B2J
1350.21
M
150mmø Sanitary Forcemain
450500
01
B2J
1413.89
M
Unknown ø Sanitary Main
450600
01
B2A
659.69
M
Roy Street Lift Station
450800
01
B2H
1
EA
Kaemingh Lift Station
450900
01
B2H
1
EA
HWY 11/71 Lift Station
451000
01
B2H
1
EA
Street Lights
500000
01
B3C
35
EA
Meadow Street
600000
01
D1D
0.42
KM
Maple Place
600100
01
D1D
0.1
KM
Birch Place
600200
01
D1D
0.1
KM
Turrell Street
600300
01
D1B
0.22
KM
Colonization Road
600400
01
D1C
0.7
KM
Kitchener Street
600500
01
D1C
0.2
KM
Byng Street - Surface Treated
600600
01
D1C
0.15
KM
Byng Street - Gravel
600700
01
D1B
0.3
KM
Adelaide Street
600800
01
D1C
0.38
KM
Mitchell Street
600900
01
D1B
0.1
KM
Union Street
601000
01
D1B
0.2
KM
7
Judson Street
601100
01
D1B
0.3
KM
Maple Crescent
601200
01
D1B
0.4
KM
Marion Street
601300
01
D1B
0.2
KM
Canning Lane - Paved
601400
01
D1D
0.7
KM
Canning Lane - Gravel
601500
01
D1B
0.3
KM
Jessie Street West
601600
01
D1C
0.12
KM
Queen Street
601700
01
D1D
0.38
KM
Florence Street - Surface Treated
601800
01
D1C
0.1
KM
Florence Street - Paved
601800
02
D1D
0.3
KM
Roy Street - Surface Treated
601900
01
D1C
0.15
KM
Roy Street - Paved
601900
02
D1D
0.2
KM
Young Lane
602000
01
D1B
0.28
KM
Robert Street - Surface Treated
602100
01
D1C
0.05
KM
Robert Street - Paved
602100
02
D1D
0.1
KM
Station Street
602200
01
D1D
0.15
KM
Strachan Drive
602300
01
D1C
0.3
KM
Front Street
602400
01
D1D
1.6
KM
Walker Street - Surface Treated
602500
01
D1C
0.2
KM
Walker Street - Gravel
602500
02
D1B
0.1
KM
Hannah Street
602600
01
D1C
0.28
KM
River Street
602700
01
D1C
0.2
KM
King Street
602800
01
D1C
0.4
KM
Jessie Street East
602900
01
D1C
0.15
KM
Charles Street East
603000
01
D1C
0.15
KM
Charles Street West
603100
01
D1B
0.2
KM
Hornal Road
603200
01
D1B
2.6
KM
Emo Road - Gravel
603300
01
D1B
6.3
KM
Emo Road - Paved
603400
01
D1D
0.3
KM
Allan Road
603500
01
D1B
4.8
KM
Reid Road
603600
01
D1B
5
KM
Cooper Road South
603700
01
D1B
1.6
KM
Cooper Road North
603800
01
D1B
1.7
KM
Meyers Road
603900
01
D1B
4.7
KM
Everett Road
604000
01
D1B
1.8
KM
Howse Road
604100
01
D1B
3.3
KM
Dunbar Road
604200
01
D1B
1
KM
Mather Road
604300
01
D1B
0.1
KM
Off Lake Road
604400
01
D1B
5.6
KM
Vandrunen Road South
604500
01
D1B
4.8
KM
Carpenter Road
604700
01
D1B
8.1
KM
McDiarmid Road
604800
01
D1B
4.4
KM
Stewart Road
604900
01
D1B
4.8
KM
Alexander Road
605000
01
D1B
1.6
KM
Barnhardt Road
605100
01
D1B
6.6
KM
Carlson Road
605200
01
D1B
3.4
KM
George Road
605300
01
D1B
4
KM
Redford Road
605400
01
D1B
5.7
KM
Plaskett Road
605500
01
D1B
0.8
KM
Ellis Road
605600
01
D1B
0.8
KM
Locking Creek Road
605700
01
D1B
1.6
KM
Fisher Road
605800
01
D1B
9.5
KM
Alysworth Road
605900
01
D1B
6
KM
O'Neil Road
606000
01
D1A
0.9
KM
Jewell Road
606100
01
D1B
0.8
KM
McDonald Road
606200
01
D1A
1
KM
Ogden Road
606300
01
D1B
1.1
KM
8
Peterson Road
606400
01
D1B
0.4
KM
Larson Road
606500
01
D1B
0.5
KM
Cherlen Bay
606600
01
D1C
0.15
KM
Fire Tanker
901000
01
E1B
1
EA
Superior Unit #1 Fire Truck
901100
01
E1A
1
EA
Rescue 1
902000
01
E6C
1
EA
Truck 107
902100
01
E8L
1
EA
Chevy Silverado 4X4
902200
01
E6C
1
EA
Street Sweeper
902300
01
E8L
1
EA
Dump Truck
902400
01
E7U
1
EA
Zamboni
902500
01
E8L
1
EA
John Deere Tractor
902600
01
E8L
1
EA
Dodge Ram 2004
902700
01
E6C
1
EA
GMC Sierra Extended Cab
902800
01
E6C
1
EA
John Deere Loader
902900
01
E8L
1
EA
Dodge Ram 2001
903000
01
E6C
1
EA
Handicapped Van
903100
01
E6C
1
EA
Volvo Excavator
903200
01
E6C
1
EA
GMC Sierra Extended Cab
903300
01
E6C
1
EA
Volvo Grader
903400
01
E8K
1
EA
9
3.0 State of Local Infrastructure
This section outlines the following:
Asset types (Roads, Buildings, Equipment, Water, Waste Water, and Vehicles).
Identification of maintenance, repair, remediation, and replacement costs for assets.
Age of assets, including age of assets as a portion of expected life.
Condition of assets, as per standard engineering practices. Roads, vehicles, buildings,
and recreation equipment were inspected for this process.
As the asset management planning process is intended to be ongoing, and the condition of
assets, especially those requiring immediate repair, can impact the budget process, it is
recommended that the tables included herein be updated with current information, as it
becomes available. Data will be updated as identified in Municipal policy which complies with
Provincial requirements (i.e. as required inspections are undertaken, at regular intervals).
3.1 Asset Types
Table 3.1 - Listing of Asset Codes in Township of Emo
MUNICIPAL ASSET MANAGEMENT PLAN
ASSET CODES
Category
Class
Subclass
Asset Code
Units
Building
Administrative
Office
A1A
SQ. M
Building
Operative
Garage (Municipal)
A2B
SQ. M
Building
Operative
Warehouse
A2C
SQ. M
Building
Institutional
Library
A3E
SQ. M
Building
Institutional
Church/Chapel
A3I
SQ. M
Building
Residential
Single Family House
A4A
SQ. M
Building
Utility
Water Supply/Treatment
A5A
SQ. M
Building
Utility
Electric Power Generation
A5C
SQ. M
Building
Recreational
City Rec Center/Hall/Cultural
Center
A6A
SQ. M
Building
Recreational
Arena
A6B
SQ. M
Building
Recreational
Club HS/Youth Center/SR
CIT/Drop-in
A6E
SQ. M
Building
Recreational
Shelter/Hut/Skate/Ball/Play
A6H
SQ. M
Building
Recreational
Other
A6Z
SQ. M
Utility
Water supply and distribution
system
Water mains
B1B
M
Utility
Water supply and distribution
system
Water Treatment System
B1C
EA
Utility
Waste Collection and Disposal
System
Sanitary Main
B2A
M
10
MUNICIPAL ASSET MANAGEMENT PLAN
ASSET CODES
Category
Class
Subclass
Asset Code
Units
Utility
Waste Collection and Disposal
System
Lagoon
B2E
EA
Utility
Waste Collection and Disposal
System
Lift Station
B2H
EA
Utility
Waste Collection and Disposal
System
Forcemain
B2J
M
Utility
Electrical Power and Dist. Sys.
Street Lights
B3C
EA
Utility
Solid Waste Collection and
Disposal Sys.
Other
B4Z
-
Grounds
Playgrounds
Outdoor Hockey
C5D
EA
Transportation
Roads
Earth Road
D1A
KM
Transportation
Roads
Gravel Road
D1B
KM
Transportation
Roads
Surface Treated Roads
D1C
KM
Transportation
Roads
Paved Roads
D1D
KM
Vehicles
Fire
Mini-Pumper
E1A
EA
Vehicles
Fire
Triple Combination Pumper
E1B
EA
Vehicles
Administrative
Truck 1/2 Ton
E6C
EA
Vehicles
Construction
Truck, dump other
E7U
EA
Vehicles
Commercial
Grader
E8K
EA
Vehicles
Commercial
Miscellaneous
E8L
EA
Note: Quantity and extent of assets are identified in Table 2.1.
11
3.2
Total Maintenance, Remediation, Rehabilitation, and Replacement Costs
Asset Name
Asset
Number
Asset
Ext.
Year of
Construction
Totals ($)
Municipal Office
100000
01
1978
10,450.00
Curling Club Building
100100
01
1964
29,775.00
Public Library
100200
01
1986
425.00
Toy Library
100200
02
1986
1,600.00
Library Storage
100300
01
2012
150.00
Pavilion
100400
01
1988
12,850.00
Splash Pad Building
100500
01
2010
5,050.00
Washrooms
100600
01
1988
1,925.00
Deck #1
100700
01
1988
1,500.00
Deck #2
100800
01
1988
1,250.00
Deck #3
100900
01
1988
550.00
Sportsfield Building
101000
01
2008
1,100.00
Sportsfield Canopy
101100
01
2007
500.00
Mortuary
101200
01
1984
600.00
Snowmobile Club Building
101300
01
1992
4,700.00
Storage and Recycling Building
101400
01
1992
650.00
Maintenance Garage/Fire Hall
101500
01
1992
11,750.00
OPP Generator Building
101600
01
2003
1,200.00
OPP Residence #21
101700
01
2003
3,410.00
OPP Residence #25
101800
01
2003
3,525.00
OPP Residence #31
101900
01
2003
4,680.00
Arena
102000
01
1979
43,950.00
Emo OPP Building
102100
01
2003
25,950.00
RR Futures Development Corporation
102200
01
2003
2,350.00
Water Treatment Plant
102300
01
1969
39,400.00
Water Treatment Storage Garage
102400
01
1969
150.00
Little House
102500
01
1999
900.00
Playground
200000
01
2006
1,000.00
Tennis Court
200100
01
1988
23,250.00
Sportfield Area
200200
01
2007
14,100.00
Splash Park
200300
01
2010
-
Water Treatment System
400000
01
1969
628,100.00
150mmø Watermain PVC
400100
01
1969
-
200mmø Watermain PVC
400200
01
1969
2,500
300mmø Watermain PVC
400300
01
1969
-
150mmø Watermain DI
400400
01
1969
802,500
200mmø Watermain HDPE
400500
01
1969
-
300mmø Watermain HDPE
400600
01
1969
-
450mmø Watermain HDPE
400700
01
2015
-
Sewage Lagoon
450000
01
2014
18,000.00
200mmø Sanitary Main
450100
01
1969
-
250mmø Sanitary Main
450200
01
1969
-
300mmø Sanitary Main
450300
01
1969
-
100mmø Sanitary Forcemain
450400
01
1987
-
150mmø Sanitary Forcemain
450500
01
1987
-
Unknown ø Sanitary Main
450600
01
1969
-
Roy Street Lift Station
450800
01
1969
56,500.00
Kaemingh Lift Station
450900
01
1995
5,700.00
HWY 11/71 Lift Station
451000
01
1969
18,500.00
Street Lights
500000
01
2008
-
Meadow Street
600000
01
Township to advise
103,000.00
12
Maple Place
600100
01
Township to advise
21,000.00
Asset Name
Asset
Number
Asset
Ext.
Year of
Construction
Totals ($)
Birch Place
600200
01
Township to advise
103,000
Turrell Street
600300
01
Township to advise
21,000
Colonization Road
600400
01
Township to advise
23,000
Kitchener Street
600500
01
Township to advise
1,000
Byng Street - Surface Treated
600600
01
Township to advise
5,000
Byng Street - Gravel
600700
01
Township to advise
3,000
Adelaide Street
600800
01
Township to advise
0
Mitchell Street
600900
01
Township to advise
0
Union Street
601000
01
Township to advise
3,000
Judson Street
601100
01
Township to advise
1,000
Maple Crescent
601200
01
Township to advise
0
Marion Street
601300
01
Township to advise
0
Canning Lane - Paved
601400
01
Township to advise
0
Canning Lane - Gravel
601500
01
Township to advise
0
Jessie Street West
601600
01
Township to advise
67,000
Queen Street
601700
01
Township to advise
1,000
Florence Street - Surface Treated
601800
01
Township to advise
0
Florence Street - Paved
601800
02
Township to advise
8,000
Roy Street - Surface Treated
601900
01
Township to advise
5,000
Roy Street - Paved
601900
02
Township to advise
52,000
Young Lane
602000
01
Township to advise
0
Robert Street - Surface Treated
602100
01
Township to advise
37,000
Robert Street - Paved
602100
02
Township to advise
2,000
Station Street
602200
01
Township to advise
0
Strachan Drive
602300
01
Township to advise
13,000
Front Street
602400
01
Township to advise
25,000
Walker Street - Surface Treated
602500
01
Township to advise
16,000
Walker Street - Gravel
602500
02
Township to advise
10,000
Hannah Street
602600
01
Township to advise
1,000
River Street
602700
01
Township to advise
1,000
King Street
602800
01
Township to advise
0
Jessie Street East
602900
01
Township to advise
2,000
Charles Street East
603000
01
Township to advise
4,000
Charles Street West
603100
01
Township to advise
0
Hornal Road
603200
01
Township to advise
2,000
Emo Road - Gravel
603300
01
Township to advise
1,000
Emo Road - Paved
603400
01
Township to advise
2,000
Allan Road
603500
01
Township to advise
13,000
Reid Road
603600
01
Township to advise
4,000
Cooper Road South
603700
01
Township to advise
8,000
Cooper Road North
603800
01
Township to advise
2,000
Meyers Road
603900
01
Township to advise
16,000
Everett Road
604000
01
Township to advise
4,000
Howse Road
604100
01
Township to advise
25,000
Dunbar Road
604200
01
Township to advise
3,000
Mather Road
604300
01
Township to advise
1,000
Off Lake Road
604400
01
Township to advise
3,000
Vandrunen Road South
604500
01
Township to advise
24,000.00
Carpenter Road
604700
01
Township to advise
19,000
McDiarmid Road
604800
01
Township to advise
12,000
Stewart Road
604900
01
Township to advise
6,000
Alexander Road
605000
01
Township to advise
2,000
13
Asset Name
Asset
Number
Asset
Ext.
Year of
Construction
Totals ($)
Barnhardt Road
605100
01
Township to advise
10,000
Carlson Road
605200
01
Township to advise
4,000
George Road
605300
01
Township to advise
2,000
Redford Road
605400
01
Township to advise
8,000
Plaskett Road
605500
01
Township to advise
1,000
Ellis Road
605600
01
Township to advise
6,000
Locking Creek Road
605700
01
Township to advise
3,000
Fisher Road
605800
01
Township to advise
12,000
Alysworth Road
605900
01
Township to advise
12,000
O'Neil Road
606000
01
Township to advise
1,000
Jewell Road
606100
01
Township to advise
2,000
McDonald Road
606200
01
Township to advise
1,000
Ogden Road
606300
01
Township to advise
2,000
Peterson Road
606400
01
Township to advise
1,000
Larson Road
606500
01
Township to advise
1,000
Cherlen Bay
606600
01
Township to advise
1,000
Fire Tanker
901000
01
1992
-
Superior Unit #1 Fire Truck
901100
01
2004
-
Rescue 1
902000
01
2010
-
Truck 107
902100
01
1982
-
Chevy Silverado 4X4
902200
01
2009
-
Street Sweeper
902300
01
1973
1,500.00
Dump Truck
902400
01
2015
-
Zamboni
902500
01
2012
-
John Deere Tractor
902600
01
1995
500.00
Dodge Ram 2004
902700
01
2004
500.00
GMC Sierra Extended Cab
902800
01
2011
-
John Deere Loader
902900
01
2005
-
Dodge Ram 2001
903000
01
2001
2,700.00
Handicapped Van
903100
01
2005
2,500.00
Volvo Excavator
903200
01
2015
150.00
GMC Sierra Extended Cab
903300
01
2011
350.00
Volvo Grader
903400
01
2005
850.00
Totals:
2,531,540.00
The above table reflects maintenance, remediation, rehabilitation, and replacement costs.
Ongoing maintenance items are not reflected beyond their initial occurrence; however they are
listed in the financial plan, under Section 6.0 of the Asset Management Plan.
3.3 Asset Condition, Asset Age Distribution
Table 3.3.1
Buildings, Grounds
Asset Name
General
Year
Estimated Remaining
Condition
Constructed
Life (Years)
Municipal Office
7
1978
30
Curling Club Building
7
1964
22
Public Library
8
1986
25
Toy Library
8
1986
25
Library Storage
7
2012
22
Pavilion
8
1988
25
14
Asset Name
General
Year
Estimated Remaining
Condition
Constructed
Life (Years)
Splash Pad Building
7
2010
30
Washrooms
8
1988
25
Deck #1
9
1988
25
Deck #2
8
1988
25
Deck #3
8
1988
25
Sportsfield Building
8
2008
30
Sportsfield Canopy
9
2007
25
Mortuary
7
1984
20
Snowmobile Club Building
7
1992
30
Storage and Recycling Building
8
1992
22
Maintenance Garage/Fire Hall
8
1992
25
OPP Generator Building
8
2003
25
OPP Residence #21
8
2003
25
OPP Residence #25
8
2003
25
OPP Residence #31
8
2003
25
Arena
7
1979
22
Emo OPP Building
7
2003
25
RR Futures Development
Corporation
8
2003
25
Water Treatment Plant
7
1969
20
Water Treatment Storage Garage
9
1969
30
Little House
7
1999
20
Playground
8
2006
20
Tennis Court
6
1988
20
Sportfield Area
7
2007
22
Splash Park
9
2010
20
Table 3.3.2
Roads
Asset Name
Pavement
Condition Rating
Estimated
Surface Age
Possible Remedial Treatments
Meadow Street
67
10
N/A
Maple Place
73
10
crack routing and sealing
Birch Place
80
10
crack routing and sealing/ 3 lm curb and gutter
replacement
Turrell Street
72
10
Grade and shape shoulder
Colonization Road
73
10
Complete spot repairs for potholes and shoulder
deterioration
Kitchener Street
81
10
Complete spot repairs for potholes and around
manhole.
Byng Street -
Surface Treated
85
10
None Required
Byng Street - Gravel
83
10
None Required
Adelaide Street
80
10
Complete surface patching to mitigate deterioration
Mitchell Street
86
10
None required for road and drainage - need a street
name sign
Union Street
84
10
None required
Judson Street
85
10
None required
Maple Crescent
83
10
None required
Marion Street
86
10
None required
Canning Lane -
Paved
59
10
1-5 years - design followed by upgrades and resurfacing
Canning Lane -
Gravel
76
10
None required for road and drainage - need brushing
and 3 X stop signs
15
Jessie Street West
78
10
None required
Asset Name
Pavement
Condition Rating
Estimated
Surface Age
Possible Remedial Treatments
Queen Street
92
4
Minor sidewalk paving and ashalt pavement edge
granular filling req'd
Florence Street -
Surface Treated
66
10
Complete spot repairs
Florence Street -
Paved
76
10
Minor sidewalk and pvmt spot repairs
Roy Street - Surface
Treated
78
10
None required
Roy Street - Paved
73
10
Minor sidealk and pvmt spot repairs
Young Lane
72
10
Require 50 mm Gran 'A' west of Robert St.
Robert Street -
Surface Treated
73
10
None required
Robert Street -
Paved
68
10
None required
Station Street
64
10
Complete spot repairs
Strachan Drive
63
10
4 patches and last 50 meters repave + signage
Front Street
80
10
Crack routing/sealing and shoulder repairs
Walker Street -
Surface Treated
77
10
None required for road and drainage - curve signs
recommended
Walker Street -
Gravel
75
10
Grade and shape shoulder to permit good water
shedding.
Hannah Street
84
10
None required for road and drainage.
River Street
79
10
Repair potholes
King Street
81
10
Minor sidewalk and pvmt spot repairs
Jessie Street East
82
10
N/A
Charles Street East
78
10
Minor pvmt edge/shoulder repairs
Charles Street West
80
10
Grade the road to take out and fill low areas.
Hornal Road
70 to 20
10
grade and shape shoulder first 0.1 km of road, install
speed limit signs, install "enter at own risk sign" at km
1.7
Emo Road - Gravel
80
10
Install speed limit and stop signs, as well as complete
minor brushing
Emo Road - Paved
57
10
Surface patching and shoulder graveling.
Allan Road
78
10
Grade surface, crown & pull shoulders, install speed &
stop signs, brushing
Reid Road
77
10
Grade & shape shoulders (1000m total), Install speed
limit sign, mild brushing (1000m)
Cooper Road South
73
10
Grade & shape shoulders, Install speed limit sign, minor
brushing
Cooper Road North
63
10
Install stop & curve signs, brushing in ditch, addition
granular over culvert
Meyers Road
65
10
Grade, shaping, ditching signage, & brushing.
Everett Road
85
10
Install stop & speed limit signs, mild brushing
Howse Road
88
10
Install curve & railway crossing signs
Dunbar Road
55
10
Install speed limit and stop signs, reshape
embankment, remove beaver dam
Mather Road
84
10
Install stop & dead end signs.
Off Lake Road
90
10
Install speed limit signs & minor brushing
Vandrunen Road
South
67
10
Grade road, major spot repairs requiring fill, shoulders,
signage, crown road, ditching/brushing
Carpenter Road
82
10
Grade & shape shoulders, install speed limit signs,
brushing, spot improvement.
16
Asset Name
Pavement
Condition Rating
Estimated
Surface Age
Possible Remedial Treatments
McDiarmid Road
62
10
Apply granular, grade and shape shoulder, signage,
ditching, brushing, drainage, major spot repair.
Stewart Road
63
10
Grade & shape road/shoulders, install stop, speed limit
and curve signs, install rip rap on culvert.
Alexander Road
70
10
Grade & Shape shoulders, install speed limit and bend
signs, minor brushing
Barnhardt Road
79
10
Grade road & Shoulders, Install stop, speed limit, and
keep right signs, brushing and drainage.
Carlson Road
72
10
grading, stop, signage, brusing
George Road
76
10
Install speed limit, corner & stop signs, cut brush in
ditch.
Redford Road
73
10
Install stop signs, speed limit signs, keep right signs &
cut brush in ditch
Plaskett Road
68
10
Grading, Install speed limit and stop sign.
Ellis Road
55
10
Grading, signage, shape embankment, allowance for
spot improvement
Locking Creek Road
60
10
Spot improvement, Stop & speed limit signs.
Fisher Road
86
10
Install speed limit signs X6, cut brush in ditches
Alysworth Road
82
10
Install Speed limit signs x6, stop sign, Keep right at
outcrop x2, brush cutting.
O'Neil Road
N/A
10
Install "Enter at own risk" sign
Jewell Road
50
10
spot repair, signage
McDonald Road
N/A
N/A
"Enter at own risk" sign
Ogden Road
53
10
Grading, speed limit, dead end & brushing required.
Peterson Road
80
10
Grading, Speed limit & dead end sign
Larson Road
N/A
N/A
Install Enter at own risk
Cherlen Bay
75
10
Patch around manholes, shoulders and misc. spots
Table 3.3.3
Utility
Asset Name
General
Year
Estimated Remaining
Condition
Constructed
Life (Years)
Water Treatment System
7
1969
20
150mmø Watermain PVC
7
1969
30
200mmø Watermain PVC
7
1969
30
300mmø Watermain PVC
7
1969
30
150mmø Watermain DI
7
1969
10
200mmø Watermain HDPE
7
1969
30
300mmø Watermain HDPE
7
1969
30
450mmø Watermain HDPE
8
2015
40
Sewage Lagoon
8
2014
20
200mmø Sanitary Main
7
1969
40
250mmø Sanitary Main
7
1969
40
300mmø Sanitary Main
7
1969
60
100mmø Sanitary Forcemain
7
1987
40
150mmø Sanitary Forcemain
7
1987
40
Unknown ø Sanitary Main
7
1969
40
Roy Street Lift Station
5
1969
10
Kaemingh Lift Station
7
1995
15
HWY 11/71 Lift Station
7
1969
15
Street Lights
9
2008
22
17
Table 3.3.4
Vehicles
Asset Name
General
Year
Estimated Remaining
Condition
Constructed
Life (Years)
Fire Tanker
7
1992
17
Superior Unit #1 Fire Truck
8
2004
20
Rescue 1
8
2010
20
Truck 107
8
1982
10
Chevy Silverado 4X4
8
2009
8
Street Sweeper
7
1973
8
Dump Truck
8
2015
20
Zamboni
8
2012
10
John Deere Tractor
7
1995
8
Dodge Ram 2004
7
2004
7
GMC Sierra Extended Cab
8
2011
15
John Deere Loader
7
2005
15
Dodge Ram 2001
6
2001
5
Handicapped Van
8
2005
15
Volvo Excavator
9
2015
20
GMC Sierra Extended Cab
8
2011
15
Volvo Grader
8
2005
15
Notes and Assumptions:
1. Estimated life value assumes that identified maintenance is completed, and regular
ongoing maintenance is performed. Estimated remaining life for vehicles in good
condition is assumed to be ten (10) years.
2. Building Condition rating scale is as follows:
0 = Closed
1 - 3 = Poor
4 - 6 = Fair
7 - 9 = Good
10 = New
3. Roads use Pavement Condition Rating value from 0-100.
18
4.0 Desired Levels of Service
For the purposes of this AMP, it is assumed that all assets owned by the municipality will
continue to be used for their existing purpose, at the existing level of service. All defined
maintenance items are indicated based upon this assumption.
This assumption was developed based upon the following from the Township's Official
Plan document, adopted September 2013:
"The Township is committed to actively seeking and encouraging new development that
maintains and improves the quality of life, the health of existing businesses and diversifies the
economy. "
Furthermore, The Township of Emo Official Plan document has outlined levels of service
regarding roads in Section 6.1:
"Safe and efficient movement of people and goods within the Township and to and from
adjacent municipalities is encouraged by this Plan. The road system should safely serve the
Township but should not be developed to a standard or extended beyond which would result in
a burden to the residents and taxpayers of the Township. The roads in the Township as shown
on all schedules to this Plan include provincial highways and Township roads."
Regarding reported speed limits. Please note the speed limits reported on our inspection sheets
is the speed limit either posted or specified by the Township staff. It is not an endorsement of
the limit as this would involve geometric, sight line, road width, etc. considerations which are
beyond the scope of the AMP.
4.1 Assumptions & Performance Measures
1. It is assumed that all roads will be maintained, and rehabilitated as required to continue to
offer the existing level of service. It is further assumed that the Official Plan will apply when
an increase to a level of service is warranted, and that any increase in level of service will be
offset by a corresponding increase in tax revenue. Our inspections include some deferred
estimated cost such as road widening for roads which are only currently used as agricultural
access which have been termed as a "deferred improvement" only justifiable should
additional residential development occur to warrant the works. Our inspections also include
recommendations to post signs on roads, or in some cases trails, advising "road is un-
maintained and to be used at own risk". Estimated annual daily traffic ranges are appended
19
to this report. It is important to note that the surface age is unknown and is assumed to be
10 years, this is used to calculate the estimated surface value of roads.
While the Township can control development within its boundaries, activities occurring in
surrounding areas can impact levels of use. If an increase in traffic volume creates increased
maintenance costs that cannot be offset by tax revenue, the Township should re-visit its
financial plan to:
Determine the best means to cover the cost to maintain the existing level of service
during the period of increased use, using the options outlined in the financial plan.
Or
If it is not feasible to cover the cost to maintain the existing level of service, the
Township could consider reducing the level of service. By reducing the level of
service, the Township may deter the factors leading to increased use of the asset.
2. It is assumed that all buildings will continue to be used for their current purpose for the
duration of the plan. If a change in service is required, it is assumed that any increase in
level of service, or operating requirements will be offset by a corresponding increase in tax
revenue. It is recommended that the Township follow up on all maintenance items
identified in the inspection reports appended to the plan to ensure that all buildings can
operate at their present level of service, and conform to code requirements. See the asset
reports for a detailed listing of maintenance needs, and a description of the building.
If new buildings are required, it is assumed that the costs to construct new structures would
be offset by a corresponding increase in tax revenue, or by using a debt financing solution,
as outlined in the Financial Plan.
3. Given the relatively static population trends in the Township, it is assumed that all
recreation equipment will continue to be used for its current purpose, at a similar level of
use, for the duration of the plan. If a change in service is required, it is assumed that any
increase in level of service, or operating requirements will be offset by a corresponding
increase in tax revenue. It is recommended that the Township continue to undertake
regular maintenance to ensure that the equipment remains in good working order, and is
safe to use.
20
4. It is assumed that all vehicles will continue to be used for their current purpose for the
duration of the plan. It is recommended that the Township follow up on all maintenance
items identified in the inspection reports appended to the plan to ensure that all vehicles
can operate at their present level of service. It should be noted that while many of the
vehicles are older, they are in good condition, and it is anticipated that with proper
maintenance, the vehicles should last for the duration of the plan. Unless vehicles are
identified for replacement in our estimates.
Note: Detailed inspection reports regarding each asset are appended to this report.
Descriptions of each asset are available under the General Description heading contained
within each asset report.
21
5.0 Asset Management Strategy
The asset management strategy is a set of planned actions that will allow the Township
of Emo to ensure that its assets offer the desired levels of service, for a sustainable cost, while
managing risk.
This section summarizes the following:
Non-infrastructure solutions.
Maintenance activities.
Renewal / Rehabilitation activities.
Replacement activities.
Disposal activities.
Expansion activities.
5.1 Non-Infrastructure Solutions
Non-infrastructure solutions are actions or policies that can lower costs or extend asset life. The
Township of Emo has identified many of these solutions in their official plan which was
approved in 2013, and is intended to last for a period of 20 years.
Included in the Basis for the plan is the following:
The Township of Emo is characterized primarily by rural residential development and
agriculturally based activities. The rural character of the Township will be maintained
over the lifetime of this Plan.
Private water and sewage will continue to be the primary source of lot servicing in areas
beyond the Village of Emo Settlement Area. As a result, developments that require
communal or full municipal services will be only be considered only if the lands are
within the Village of Emo Settlement Area and meet the criteria laid out in the official
plan. Any application to extend services from an adjacent municipality will be
considered only with an amendment to the Official Plan.
Much of the Township's existing non-residential development occurs in The Village of
Emo Settlement Area. This Plan recognizes The Village of Emo Settlement Area as the
continued focus of primary economic development in the Township.
It is assumed that if a development proceeds requiring affected services to be
upgraded/improved that needs and associated costs will be included in the approvals
required to advance the project and are beyond the scope of this plan.
22
Additionally, Section 5.1 of the plan indicates a mechanism for demand management, and a
mechanism for directing development to limit the burden on existing road assets.
It is recommended that the Township of Emo continue to undertake land use planning,
undertake development in accordance with the Official Plan, and continue with the fiscally
sound methodology outlined in the Official Plan. Doing so will help manage demand, and
ensure that the Township develops in such a way that has a sustainable plan to cover the costs
needed to maintain levels of service.
5.2 Maintenance Activities
A detailed list of maintenance activities for each asset is appended to this report. It is
recommended that the Township undertake the identified maintenance within the timeframe
identified in each asset report.
Some significant maintenance activities that were identified during the inspection process
include (these include critical health and safety issues and building code issues):
1. Install rated door and closer in mechanical room, remove stored material in mechanical
room & replace battery for emergency lighting in Municipal Office.
2. Install additional guard on entrance stair rail, Provide 1hr f.r.r. at mech. Room, Upgrade
door to compressor room, Install handrails on stairs, and remove stored materials from
mechanical room at the Curling Club Building.
3. Install rated door & closer for furnace room, Drywall at underside of stairs in storage
room & Install smoke/CO detector in furnace /HRV room (Toy Library).
4. Install grab bars in Sports field Building.
5. Install carbon monoxide detector in OPP Residence #21.
6. Install emergency exit signs & carbon monoxide detector in OPP Residence #25.
7. Mount fire extinguisher, install exit and carbon monoxide detector in OPP Residence
#31
8. Lower concrete curb at main entrance of Arena.
9. Install door closer on mechanical room door, label electrical panel in hallway near
washrooms and install smoke/CO detector in mech. room in OPP building.
10. Install handrails on stairs in Little House.
11. Replace ladder & tighten hand grab at Water Treatment System lift station.
23
5.3 Renewal / Rehabilitation Activities
A detailed list of maintenance activities for each asset is appended to this report. It is
recommended that the Township undertake the identified maintenance within the timeframe
identified in each asset report. Renewal / Rehabilitation costs are identified within each asset
report.
It should be noted that it is recommended that all roads be rehabilitated as described in the
individual asset reports within a period of ten (10) years, as identified. It is recommended that
the following roads should be rehabilitated in the present year.
1. George Road
2. O'Neil Road
3. Jewell Road
4. Larson Road
In addition to the above recommendations roads requiring signage such as stop signs, speed
limit signs, approaching curve signs, dead end signs etc. should be installed in the present year.
5.4 Replacement Activities
A detailed list of maintenance activities for each asset is appended to this report. It is
recommended that the Township undertake the identified maintenance within the timeframe
identified in each asset report. When required, replacement costs are identified within each
asset report. It is recommended that the Township replace the following assets as identified in
the asset reports.
1. Replace wood siding at curling club.
2. Replace wood shakes on pavilion roof.
3. Replace loading dock doors with rollup door at water treatment plant.
4. Replace asphalt surface of tennis court.
5. Replace various fencing posts at sewage lagoon.
6. Replace magnesium meter, pipes and valves, and guide rails at Roy Street Lift Station.
7. Replace switch on pump #1 control panel.
8. Re surface portions of Meadow Street.
9. Replace curb and gutters on Birch Place road.
10. Resurface Canning Lane - Paved.
11. Resurface Jessie Street West.
24
12. Resurface road on Florence Street - Surface Treated.
13. Replace various sections of sidewalk located on Roy Street - Paved.
14. Re-pave asphalt on Robert Street - Paved.
15. Re-pave Station Street.
16. Re-surface Strachan Drive.
17. Replace 150mmø Watermain DI with new PVC watermain.
5.5 Disposal Activities
It is recommended that the Township dispose of assets in accordance with their procurement
policy, if the asset has potential value (e.g. used vehicle, building). Otherwise, the Township
should dispose of assets in accordance with environmental regulations as required. Disposal of
assets should occur in accordance with the Official Plan.
5.6 Expansion Activities
Expansion activities should occur in accordance with the Official Plan, which utilizes a fiscally
responsible approach to development focussed on The Village of Emo Settlement Area, which
limits financial exposure.
25
6.0 Financial Strategy
6.1 General overview of financial plan requirements
In order for an AMP to be effectively put into action, it must be integrated with financial
planning and long-term budgeting. The development of a comprehensive financial plan will
allow the Township of Emo to identify the financial resources required for sustainable asset
management based on existing asset inventories, desired levels of service and projected growth
requirements.
The following pyramid depicts the various cost elements and resulting funding levels that
should be incorporated into AMP's that are based on best practices.
This report develops such a financial plan by presenting several scenarios for consideration and
culminating with final recommendations. As outlined below, the scenarios presented model
different combinations of the following components:
a)
The financial requirements for:
existing assets
existing service levels
requirements of contemplated changes in service levels (none identified for
this plan)
26
requirements of anticipated growth (none identified for this plan)
b)
Use of traditional sources of municipal funds:
tax levies
user fees
reserves
debt
development charges (not applicable)
c)
Use of non-traditional sources of municipal funds:
reallocated budgets (not required for this AMP)
partnerships (not applicable)
procurement methods (no changes recommended)
d)
Use of other orders of government funds:
Federal gas tax
grants
If the financial plan component of an AMP results in a funding shortfall, the Province requires
the inclusion of a specific plan as to how the impact of the shortfall will be managed. In
determining the legitimacy of a funding shortfall, the Province may evaluate a municipality's
approach to the following:
a) In order to reduce financial requirements, consideration has been given to revising
service levels downward.
b) All asset management and financial strategies have been considered. For example:
If a zero debt policy is in place, is it warranted? If not, the use of debt should
be considered.
Do user fees reflect the cost of the applicable service? If not, increased user
fees should be considered.
Our organization recently attended the Ontario Good Roads Association
meeting in which both the Premier and Minister of Infrastructure encouraged
the carrying of a maximum of 11% debt load by municipalities. This is now
considered prudent as it multi-generations. Thus a 10-year plan to finance a
bridge would be viewed quite favourably by both Provincial and Federal
funding agencies.
This AMP includes recommendations that avoid long-term funding deficits.
27
6.2 Financial information relating to the Township of Emo's AMP
6.2.1 Funding objective
We have developed scenarios that would enable the Township of Emo to achieve full funding
within 10 years for the following assets:
a) Tax funded assets - Road network; Water and Wastewater; Facilities; Equipment and
Other
For each scenario developed we have included strategies, where applicable, regarding the use
of tax revenues, grant revenues, reserves and debt financing. It should be noted that in
developing these scenarios it was projected that the percentage of total taxation revenue
allocated to capital projects will remain consistent with prior year's allocations. In years prior to
2016 approximately 28% of total taxation revenue was allocated to capital projects and this was
the percentage that was used for all projected taxation revenue dedicated to capital
throughout this financial plan. It should be noted that the level of taxation revenue that the
Township is able to dedicate to capital is quite exceptional as, for example, the City of Thunder
Bay is only able to allocate approximately 10% of its budget to capital.
6.3 Tax funded assets
6.3.1 Current funding position
Tables 1 and 2 outline, by asset category, the Township of Emo's annual asset investment
requirements, projected funding positions and funding changes projected and required to
achieve full funding on assets funded by taxes.
28
Table 1: Summaries of Projected Annual Infrastructure Requirements and Projected Annual
Funding
2016 Summary of Projected Annual Infrastructure Requirements and Projected Annual
Funding
2016 Projected Annual Funding Available
Asset Category
Projected
2016
Investment
Required
Taxes
Gas Tax
Other
Total
2016
Projected
Annual
Surplus
Roads
$579,517
$132,926
$72,504
$ -
$209,430
$(370,087)
Water &
Wastewater
$126,100
$126,100
$ -
$ -
$126,100
$ -
Facilities
$89,905
$89,905
$ -
$ -
$89,905
$ -
Equipment
$34,250
$34,250
$ -
$ -
$34,250
$ -
Other
$15,000
$15,000
$ -
$ -
$15,000
$ -
Total
$844,772
$402,181
$72,504
$ -
$474,685
$(370,087)
Years 1 to 5 Summary of Projected Annual Infrastructure Requirements and Projected Annual
Funding
Year 1 to 5 Projected Annual Funding Available
Asset Category
Projected
Year 1 - 5
Investment
Required
Taxes
Gas Tax
Other
Total
Year 1 - 5
Projected
Annual
Deficit
Roads
$107,387
$144,727
$72,504
$ -
$217,231
$109,844
Water &
Wastewater
$250,000
$130,000
$ -
$ 60,000
$190,000
$ (60,000)
Facilities
$118,998
$118,998
$ -
$ -
$118,998
$ -
Equipment
$25,000
$25,000
$ -
$ -
$25,000
$ -
Other
$15,000
$15,000
$ -
$ -
$15,000
$ -
Total
$516,385
$433,725
$72,504
$ 60,000
$566,229
$49,844
29
Years 6 to 10 Summary of Projected Annual Infrastructure Requirements and Projected
Annual Funding
Year 6 to 10 Projected Annual Funding Available
Asset Category
Projected
Year 6 - 10
Investment
Required
Taxes
Gas Tax
Other
Total
Year 6 - 10
Projected
Annual
Surplus
Roads
$204,334
$354,671
$72,504
$ -
$298,658
$94,324
Water &
Wastewater
$122,000
$122,000
$ -
$ -
$122,000
$ -
Facilities
$85,000
$85,000
$ -
$ -
$85,000
$ -
Equipment
$25,000
$25,000
$ -
$ -
$25,000
$ -
Other
$15,000
$15,000
$ -
$ -
$15,000
$ -
Total
$451,334
$473,154
$72,504
$ -
$545,658
$94,324
6.3.2. Recommendations for full funding
The annual investment requirement for roads, water/wastewater facilities and equipment and
the annual revenue allocated to these assets are:
Table 2: Summary of Annual Investment Requirements and Annual Revenue Allocated
Annual Investment
Requirement
Annual Revenue
Allocated
Annual Surplus
(Deficit)
2016
$844,772
$474,685
$(370,087)
Years 1 to 5
$516,385
$566,229
$49,844
Years 6 to 10
$451,334
$545,658
$94,324
Therefore, the cumulative annual surplus for capital investments is projected to be $350,753
over the next 10 years. These infrastructure categories are projected to be funded via taxation
revenue and Gas Tax funding at 75% of the townships long-term requirements assuming no
additional capital spending other than the maintenance costs projected.
The Township of Emo budgeted for annual tax revenues of $1,398,403 in 2015. Planned funding
would require an increase in tax revenue corresponding to the projected annual inflation rate.
We recommend that over the next 10 years an annual tax increase corresponding to the annual
inflation rate be implemented in order to achieve the required total tax revenue.
This involves full funding being achieved over 10 years by:
a)
Increasing tax revenues by the annual inflation rate each year for the next 10 years
solely for the purpose of full funding to the 5 asset categories covered by this AMP.
b) Allocating 100% of the gas tax revenue (currently $72,504) to the roads category.
30
c)
Applying for grant funding as required.
d)
Allocating reserve funds to the five asset categories as outlined below.
e)
Utilizing debt financing as required as outlined below.
It should be noted that several major capital outlays will be required in the next 5 years in order
to achieve all of the requirements outlined in the AMP. These major capital items consist of:
a)
The Water Treatment System requires $628,100 in improvements which include a
new line and utility locator.
b)
Canning Lake Road will require repaving of $66,150
c)
Emo Road will require repaving of $125,000
d)
Jewell Road will require upgrading of $160,000
e)
Meadow Street will require upgrading of $103,000
f)
O'Neill Road will require upgrading of $200,900
In performing our projections these expenditures were not assigned to any particular year
within the next 5 years. Instead these expenditures were projected in equal annual amounts
throughout the next 5 years as it was not possible for us to project specifically which year the
Township will perform these major repairs. This method ensures that all of the expenditures
are recorded within the projections however it does fail to indicate that these large
expenditures will not be incurred in smaller annual amounts but will instead be incurred in
larger less reliable expenditure amounts The overall affect by the end of the 5 year and 10 year
projections will be the same however the actual expenditures will not be incurred as smoothly
as these projections indicate.
Although this option achieves full funding on an annual basis in 10 years and provides financial
sustainability over the period modeled (to 2050), the recommendations do require prioritizing
capital projects to fit the resulting annual funding available. Prioritizing these and future
projects will require the age based data to be replaced by condition based data.
6.4 Use of Grant Funding
6.4.1 Grant funding
For the purposes of the Township's financial plan we have accounted for three possible
scenarios pertaining to possible grant funding for the Water Treatment Plant improvements. As
indicated in the report a new line and utility locator is recommended to be installed in the
Water Treatment Facility within the next 5 years at an estimated total cost of $600,000. Given
the costs projected for rehabilitation of the Township's various other assets over the 1 to 5 year
period we project that the township would be able to fund the Water Treatment Plant
upgrades through taxation revenue and reserves alone however these costs could cause a
strain on the financial wellbeing of the Township in the next 5 to 10 years. Table 3 indicates
scenarios regarding grant funding for the improvements to the Water Treatment Plant.
31
Table 3: Years 1 to 5 Grant Funding Scenarios
Primarily Grant Funded Scenario
Investment
Required
Grant
Funding
Debt
Financing
Taxation
Revenue
Surplus
(Deficit)
Water Treatment Plant
Upgrades
$600,000
$600,000
$ -
$ -
$ -
Primarily Debt Financed Scenario
Investment
Required
Grant
Funding
Debt
Financing
Taxation
Revenue
Surplus
(Deficit)
Water Treatment Plant
Upgrades
$600,000
$ -
$600,000
$ -
$ -
Grant Funded and Debt Financed Scenario
Investment
Required
Grant
Funding
Debt
Financing
Taxation
Revenue
Surplus
(Deficit)
Water Treatment Plant
Upgrades
$600,000
$300,000
$300,000
$ -
$ -
It should be noted that if the Township is unable to receive grant funding for 100% of the Water
Treatment Plant upgrades debt financing could be required to complete the funding of the
project. In the "Use of Debt" section below we outline potential financing costs related to any
debt financing required as part of this financial plan.
6.4.2 Recommendation
In our opinion, the most beneficial scenario for the Township would be to have the Water
Treatment Plant upgrades be 100% grant funded, however we also believe this is the least likely
scenario given the provincial and federal government's history of requiring municipalities to
participate as partners in major capital projects.
In our opinion the most likely scenario would be that the Township is able to find grant funding
for a portion of the bridge replacement project sometime within the 1 to 5 year period, in this
case we assume the project is 50% grant funded and 50% debt financed obviously the portions
grant funded as compared to financed may vary from these estimates. Possible funding sources
for the project would be Canada-Ontario Municipal Rural Infrastructure Fund (COMRIF) or the
Small Rural & Northern Municipal Infrastructure Fund.
There is also the possibility that the Township is unable to locate grant funding for the Water
Treatment Plant upgrades and is required to 100% finance the project. We believe that the
32
Township would have minimal trouble 100% financing the project given the Township's strong
historical financial data and the data included indicating that tax revenues will be earned to
repay any debt incurred within the next 10 years. Obviously, the negative consequences of fully
financing the project would be that the Township would incur significantly more financing costs
than if the project was partially or fully grant funded.
6.5 Use of debt
6.5.1 Use of debt
For reference purposes, table 4 outlines the premium paid on a project if financed by debt. For
example, a $1M project financed at 3.0% over 15 years would result in a 26% premium or
$260,000 of increased costs due to interest payments. For simplicity, the table does not take
into account the time value of money or the effect of inflation on delayed projects.
Table 4: Total Interest Paid as a % of Project Costs
Interest
Rate
Number of Years Financed
5
10
15
20
25
30
7.0%
22%
42%
65%
89%
115%
142%
6.5%
20%
39%
60%
82%
105%
130%
6.0%
19%
36%
54%
74%
96%
118%
5.5%
17%
33%
49%
67%
86%
106%
5.0%
15%
30%
45%
60%
77%
95%
4.5%
14%
26%
40%
54%
69%
84%
4.0%
12%
23%
35%
47%
60%
73%
3.5%
11%
20%
30%
41%
52%
63%
3.0%
9%
17%
26%
34%
44%
53%
2.5%
8%
14%
21%
28%
36%
43%
2.0%
6%
11%
17%
22%
28%
34%
1.5%
5%
8%
12%
16%
21%
25%
1.0%
3%
6%
8%
11%
14%
16%
0.5%
2%
3%
4%
5%
7%
8%
0.0%
0%
0%
0%
0%
0%
0%
It should be noted that current interest rates are near all-time lows. Sustainable funding models
that include debt need to incorporate the risk of rising interest rates. The following graph
shows where historical lending rates have been:
33
Table 5: Historical Prime Lending Rates
As illustrated in table 4, a change in 15 year rates from 3% to 6% would change the premium
from 26% to 54%. Such a change would have a significant impact on a financial plan.
Historically, the Township of Emo has used debt financing minimally for capital projects and as
of the 2015 fiscal year the Township has minimal outstanding debt. As illustrated in this plan
Emo could be required to finance a portion of the investment requirements under the asset
management plan. Table 6 outlines projected financing costs resulting from various funding
scenarios related to financing of the Water Treatment Plant upgrades:
Table 6: Planned Debt Financing
Principal
Term
Interest
Rate
Monthly
Payment
Financing
Costs
$300,000
10 years
3%
$2,897
$47,619
$300,000
10 years
6%
$3,331
$99,674
$300,000
20 years
3%
$1,664
$99,310
$300,000
20 years
6%
$2,149
$215,830
$600,000
10 years
3%
$5,794
$95,237
$600,000
10 years
6%
$6,661
$199,349
$600,000
20 years
3%
$3,328
$198,621
$600,000
20 years
6%
$4,299
$431,661
As indicated above ideally Emo should be able to receive grant funding for at least 50% of the
Water Treatment Plant upgrades and could then finance only 50% of the project. If this were
the case the financing costs for the project would be kept to a minimum. The financing for the
project could be kept to shorter term and the monthly payments would not be overly
cumbersome under the Township's budget.
34
6.5.2 Recommendation
Our recommendation is that if the project is grant funded approximately 50% that Emo obtain
financing for at most a 10 year term in order to minimize the debt financing costs. Should Emo
be required to fully finance the project it would be overall most beneficial to the Township to
try to keep the term loan at a maximum of 10 years in order to minimize financing costs
however given how cumbersome to the annual budget the size of the monthly payment might
become we would suggest that the Township review its budget to ensure that the monthly
financing payments are not overly cumbersome.
By utilizing debt funding for this project the Township will be able to avoid a massive reduction
to the Township's reserve funds over the next 10 years and will be able to better manage its
cash flows.
Given the fact that the other orders or government are supporting the practice of municipalities
using debt to finance major capital projects, as outlined earlier, this use of debt by Emo would
likely assist with future funding applications.
6.6 Use of Reserves
6.6.1 Available reserves
Reserves play a critical role in long-term financial planning. The benefits of having reserves
available for infrastructure planning include:
the ability to stabilize tax rates when dealing with variable and sometimes uncontrollable
factors
financing one-time or short-term investments
accumulating the funding for significant future infrastructure investments
managing the use of debt
normalizing infrastructure funding requirements
By reserve type, table 7 outlines the details of the reserves available to the Township of Emo
budgeted for 2015.
35
Table 7: Summary of Reserves Available
Reserve Type
Balance
Reserve Funds
Capital
$1,014,609
Deferred Revenue
Gas Tax
$45,479
There is considerable debate in the municipal sector as to the appropriate level of reserves that
a municipality should have on hand. There is no clear guideline that has gained wide
acceptance. Factors that municipalities should take into account when determining their capital
reserve requirements include:
breadth of services provided
age and condition of infrastructure
use and level of debt
economic conditions and outlook
internal reserve and debt policies
We are projecting that in order to fund the major capital expenditures in the roads sector the
Township will be required to utilize $370,087 of its capital reserves in 2016 in order to ensure
that the roads maintenance deficit is properly funded.
6.6.4 Recommendation
Under the plan the Township of Emo will be required to use and contribute to reserve funds as
necessary in order to implement the financial plan required to fund the AMP outlined. It is
possible the Township of Emo could utilize reserves instead of debt to fund the Water
Treatment Plant upgrades required by the AMP however this might result in a significant
reduction of the Township of Emo's reserves for a 5 to 10 year period a tax revenues are
collected to replenish the reserve funds. If possible it would be most beneficial to avoid such a
reduction of reserves and to utilize grant funding a debt options to fund the Water Treatment
Plant upgrades.
36
6.7 Summary of Financial Plan
Table 10 illustrates the expected annual capital investments, revenues, reserve allocations and
debt financing required under the recommended financial plan.
Table 10: Summary of Annual Capital Transactions Under the Financial Plan
Summary of 2016 Capital Transactions Under the Financial Plan
Asset
Category
2016
Annual
Investment
Required
2016
Projected
Taxation
Revenue
2016
Projected
Gas Tax
2016
Projected
Grant
Revenue
2016
Surplus
(Deficit)
2016
Projected
Reserve
Allocations
2016 Debt
Financing
2016
Adjusted
Surplus
(Deficit)
Roads
$579,517
$136,926
$72,504
$ -
$(370,087)
$(370,087)
$ -
$-
Water &
Wastewater
$126,100
$126,100
$ -
$ -
$ -
$-
$ -
$ -
Facilities
$89,905
$89,905
$ -
$ -
$ -
$ -
$ -
$ -
Equipment
$34,250
$34,250
$ -
$ -
$ -
$ -
$ -
$ -
Other
$15,000
$15,000
Total
$844,772
$402,181
$72,504
$ -
$(370,087)
$370,087
$ -
$-
Summary of Year 1 to 5 Annual Capital Transactions Under the Financial Plan
Asset
Category
Year 1 - 5
Annual
Investment
Required
Year 1 - 5
Projected
Annual
Taxation
Revenue
Year 1 - 5
Projected
Annual
Gas Tax
Year 1 - 5
Projected
Annual
Grant
Revenue
Year 1 - 5
Annual
Surplus
(Deficit)
Year 1 - 5
Projected
Annual
Reserve
Allocations
Year 1 - 5
Annual
Debt
Financing
Year 1 - 5
Adjusted
Annual
Surplus
(Deficit)
Roads
$107,387
$144,727
$72,504
$ -
$109,844
$109,844
$ -
$ -
Water &
Wastewater
$250,000
$130,000
$ -
$60,000
$(60,000)
$ -
$60,000
$ -
Facilities
$118,998
$118,998
$ -
$ -
$ -
$ -
$ -
$ -
Equipment
$25,000
$25,000
$ -
$ -
$ -
$ -
$ -
$ -
Other
$15,000
$15,000
$ -
$ -
Total
$516,385
$433,725
$72,504
$60,000
$49,844
$109,844
$60,000
$ -
37
Summary of Year 6 to 10 Annual Capital Transactions Under the Financial Plan
Asset
Category
Year 6 - 10
Annual
Investment
Required
Year 6 - 10
Projected
Annual
Taxation
Revenue
Year 6 - 10
Projected
Annual
Gas Tax
Year 6 - 10
Projected
Annual
Grant
Revenue
Year 6 -
10 Annual
Surplus
(Deficit)
Year 6 - 10
Projected
Annual
Reserve
Allocations
Year 6 - 10
Annual
Debt
Financing
Year 6 - 10
Adjusted
Annual
Surplus
(Deficit)
Roads
$204,334
$226,154
$72,504
$ -
$94,324
$94,324
$ -
$ -
Water &
Wastewater
$122,000
$122,000
$ -
$ -
$ -
$ -
$ -
$ -
Facilities
$85,000
$85,500
$ -
$ -
$ -
$ -
$ -
$ -
Equipment
$25,000
$25,000
$ -
$ -
$ -
$ -
$ -
$ -
Other
$15,000
$15,000
$ -
$ -
$ -
$ -
$ -
$ -
Total
$451,334
$473,154
$72,504
$ -
$94,324
$94,324
$ -
$ -
The financial plan will result in the Township of Emo annually increasing its tax rate at a rate
equal to the annual inflation rate. It is assumed that Gas Tax revenue will remain constant at
$72,504 over the next 10 years as there is no indication from the information reviewed that
these revenues will significantly increase. We are assuming that the Township of Emo will be
able to qualify for grant revenue in the amount of $300,000 during the years 1 to 5 periods to
assist in financing a Water Treatment Facility upgrade. We are also recommending debt
financing be utilized to make up the difference between the grant funding received and the
investment required for the recommended Water Treatment Plant upgrade. Finally, we are
recommending the usage of reserve funds as necessary and the buildup of reserves where
possible. Of course, it is possible that the township could use some of the funds that the plan
has designated to increase reserve balances in order to assist in payments of the debt
financing's principal.
It should be noted that in preparing this financial plan several projections and estimates were
required and it is possible that actual future results could differ materially from the projections
and estimates that were utilized in preparing the above financial plan.