Project Management Methodology policy
Page 1 of 16
THE CORPORATION OF THE CITY OF WINDSOR
POLICY
Service Area: Office of the Chief Administrative Officer Policy No.:
CR252/2014
Department:
Approval Date: October 6, 2014
Division:
Corporate Initiatives
Approved By:
CR252/2014
Effective Date:
October 6, 2014
Subject:
Project Management Methodology Procedure Ref.: N/A
Review Date: October 6, 2017
Pages:
Replaces: M249/2011
Prepared By: Mel Douglas
Date: September 19, 2011
1 POLICY
1.1
The Project Management Methodology Policy governs the execution of projects as
defined within this Policy. Projects governed by this Policy will be managed and
overseen using a methodology appropriate to their scope, timeline, visibility, budget
and risk
2 PURPOSE
2.1
The objective of this policy is to enable the Corporation to deliver successful projects
on time, on budget and in compliance with policies and directives of City Council and
applicable legislation. Experience has shown that the most important factors in
delivering successful projects on time and on budget is to ensure projects are well
defined up front and minimize scope changes once a project is underway. Therefore
this Policy specifically:
⮚ Defines those activities deemed to be Projects; and
⮚ Establishes an adequate and effective project management methodology that
provides standard methods and guidelines to ensure that Projects are conducted
in a disciplined, well-managed and consistent manner.
3 SCOPE
3.1
This Policy applies to ALL City of Windsor projects as defined herein that fall under
the mandate of the CAO.
3.2
Where a Project involves external stakeholders and/or funders with a separate project
management methodology or project requirements, a review will be done by the
Project Manager to determine whose methodology or requirements apply. If this
project is managed by the City of Windsor, the Project Manager will be required to
maintain records created by the external methodology (if applicable) as if this Policy
applied.
Project Management Methodology policy
Page 2 of 16
4 RESPONSIBILITY
4.1
The Chief Administrative Officer is responsible for the implementation of the
policy. The Manager of Corporate Initiatives is responsible for any revisions to the
policy and providing training, as required.
4.2
The responsibilities related to use of this policy are:
4.2..1 The Mayor and City Council are responsible for:
⮚ Approving and supporting the Project Management Methodology
Policy;
⮚ Ensuring that the Project Management Methodology Policy is supported
through approval of the appropriate allocation of resources;
4.2..2 The Chief Administrative Officer is responsible for:
⮚ Enforcing and supporting the Project Management Methodology Policy;
4.2..3 The Corporate Leadership Team is responsible for:
⮚ Enforcing the Project Management Methodology Policy;
⮚ Ensuring that the Project Management Methodology Policy is supported
through recommendation of appropriate allocation of resources;
4.2..4 The Executive Directors and their Subordinates are responsible for:
⮚ Ensuring that proper Project Management Methodology is used in the
managing of projects within their respective departments;
⮚ Identifying when training is needed for employees
4.2..5 The Corporate Initiatives division is responsible for:
⮚ Monitoring compliance with this policy for projects categorized as
'Major'
⮚ Maintaining an inventory of Projects as defined herein;
⮚ Providing training as requested;
⮚ Reviewing this policy at least once every three years;
⮚ Updating this policy as required;
4.3
All Project Management documents are the responsibility of the Project Manager and
shall be organized in a responsible fashion and retained for audit purposes.
5 GOVERNING RULES AND REGULATIONS
5.1
The following process is part of the Project Management Methodology policy:
Project Management Methodology policy
Page 3 of 16
5.1..1 Corporate activities and initiatives must be reviewed using the Project
Determination Protocol set out in Schedule A to determine whether they are
correctly defined as Operations or Projects.
5.1..2 Activities or initiatives that are determined to be Projects using Schedule A,
must be further assessed for size using the Project Assessment Protocol set out
in Schedule B.
5.1..3 Projects designated Major using Schedule B must comply with all Project
Methodology requirements of Schedule C.
5.1..4 Small and Medium Projects are encouraged to comply with those elements of
the Project Methodology in Schedule C appropriate to the budget, scope,
visibility and risk of the Project.
5.1..5 In the case where the City assumes the management of a project initiated by a
third party, at any point of the life-cycle of the project, and it is designated a
Major Project under this policy, the required documents must be completed
as soon as reasonably possible.
5.2
Additional rules for the policy are:
5.2..1 Any current practices should remain in place provided that they meet the
outlined components in this policy.
5.2..2 Amendments to any Schedules, Procedures, Protocols or Processes created
under this Policy may be made by the CAO without further approval by City
Council.
5.2..3 Where there are multiple phases to a project or sub-projects within a project,
each phase can also be deemed a project and tracked as such.
5.2..4 Any exceptions to this Policy must be approved in advance by City Council.
5.3
The following definitions apply to this policy:
5.3..1 Operations are defined as an "organizational function performing the
ongoing execution of activities that provide a repetitive service and/or
produce the same product." Examples of Operations may include:
⮚ Annual road, sewer and bridge rehabilitation
⮚ Annual parks and facilities rehabilitation
⮚ Repetitive yearly works
5.3..2 Project is defined as "a temporary endeavour undertaken to create a unique
result, service or product." Examples of projects may include:
⮚ Developing a new product or service
⮚ Effecting change in the structure, or staffing of an organization
⮚ Developing or acquiring a new or modified information system
⮚ Constructing a building
⮚ Implementing a new business process or procedure.
⮚ Master, Community or Official Plan development
Project Management Methodology policy
Page 4 of 16
5.3..3 Major Project is defined as a Project that typically meets at minimum two or
more criteria in the MAJOR column on the Project Assessment Worksheet
provided in Schedule A. If only one criterion falls within the Major column,
the classification remains at the discretion of the Project Sponsor.
5.3..4 Medium Project is defined as a Project that typically meets at minimum two
or more criteria in the MEDIUM column on the Project Assessment
Worksheet provided in Schedule A.
5.3..5 Small Project is defined as a Project that has most of the criteria in the Small
column on the Project Assessment Worksheet provided in Schedule A.
5.3..6 Scope is defined as the statement of work to be undertaken by the Project
including all objectives and deliverables the Project is expected to achieve;
and it includes a statement of what will not be achieved (i.e. out of scope), so
to manage stakeholder expectations.
5.3..7 Budget is defined as the total gross amount of financial resources required to
complete the project, which may include procurement and or development
costs, interest charges during the life of the project needed to finance the
unfunded expenditures, appropriate salaries and benefits (as defined in the
Capital Tangible Assets Policy) necessary to deliver the project in scope.
Project budgets are to be presented in the format set out in the Finance
Checklist for Council Reports and Delegation of Authority Reports document.
5.3..8 Project Charter (aka Scope Document) is an initiating document that defines
the project's scope and all the parameters of the project that the Project
Manager will manage the project through. The document should adequately
represent the stakeholder's expectations of what the project will produce.
5.3..9 Project Management Plan is a more detailed plan of the project as defined in
the Project Charter, created by the Project Manager and their team, to
successfully achieve the project's objectives and success factors. Components
of the plan can include project management of: scope, time, cost, human
resourcing, quality assurance & control, communications, risk, and
procurement.
5.3..10 Project Change Order is the document that clearly identifies approved
changes in the Scope, Budget or Timeline of a Project.
5.3..11 Timeline is defined as the estimated amount of time required from the
approval of the Project by Council or other approving authority until the final
deliverables and objectives have been deemed complete.
5.3..12 Project Sponsor is the City of Windsor manager assigned as the lead
executive for the Project. They should be the Project's champion for success.
Typically they Chair the Project Executive Committee.
Project Management Methodology policy
Page 5 of 16
5.3..13 Project Manager is the City of Windsor employee, or employee of an ABC
who has adopted this policy and is overseeing a city council approved budget,
with the appropriate skills and experience for the project, assigned as the lead
manager for the Project and charged with delivering the Project in Scope, on
Budget and within the Timeline.
5.3..14 Project Team is the group of key individuals with specific skill sets who:
participate in the success of the project, report to the Project Manager, and are
assigned work on the Project whether full-time or otherwise.
5.3..15 Project Executive Committee is a senior body to the project made up of key
stakeholders (consisting of representative(s) of City of Windsor management
and/or external groups) who have a direct benefit or are directly affected by
the outcome of the project who provide advice, direction and decision making
on the Project.
5.3..16 Steering Committee is an advisory committee made up of high level
stakeholders and/or experts (example: City Standing Committee) who provide
guidance on key issues, direction and decision making on the Project.
5.3..17 Project Management Methodology is the set of practices, tools and
techniques used by Project Managers on any size project that ensure that the
Scope, Budget, Change Orders and Timelines are clearly approved,
understood and managed throughout the lifecycle of the Project.
5.3..18 Risk Level is the indicator of the degree of risk a Project faces in achieving its
objectives.
5.3..19 Visibility is the degree to which a Project is exposed to impacts from external
stakeholders or the general public.
5.4
All Projects must follow all applicable City of Windsor policies including, but not
limited to:
⮚ Purchasing By-Law
⮚ General Council Report Requirements
⮚ Delegation of Authority Report Requirements
⮚ Annual Capital Budget Process
⮚ Municipal Act
⮚ Records Retention Bylaw
⮚ All applicable Legislation
6 RECORDS, FORMS AND ATTACHMENTS
6.1
All Project Management documents are the responsibility of the Project Manager and
shall be organized in a responsible fashion and retained for audit purposes. All
records will be kept in accordance with City of Windsor Records Retention Bylaw.
The copies of the following records & notifications should be sent to the Corporate
Initiatives division under the following conditions:
Project Management Methodology policy
Page 6 of 16
6.1..1 All projects (SMALL, MEDIUM and MAJOR) designated in Schedule A
must be reported to the Corporate Initiatives division by:
⮚ Providing a copy of the results from the Schedule B to the Corporate
Initiatives division.
⮚ Providing written notification of project completion to the Corporate
Initiatives division once the project has been completed and closed.
6.1..2 Projects designated as MAJOR must provide the following additional
information to the Corporate Initiatives division as approved by the Project's
governing body:
⮚ Project Charter
⮚ Periodic project status reports
⮚ Project Close Summary
⮚ Request for Change, as applicable
⮚ Any additional project information indicated in the MAJOR Project
Management Methodology as requested by Corporate Initiatives
division.
6.2
The relevant forms can be obtained from Dashboard at Office of the CAO-Project
Management page:
⮚ Schedule A
⮚ Schedule B
⮚ Periodic project status report
⮚ Request for Change
⮚ Project Close Summary
6.3
Included attachments to the policy are:
⮚ Schedule A
⮚ Schedule B
⮚ Schedule C
Project Management Methodology policy
Page 7 of 16
SCHEDULE A
Project Determination Protocol
The following short checklist must be used to determine whether a particular initiative is a
Project for purposes of the Project Management Methodology Policy. To determine, rate each
characteristic in the ‗Rating' column below representing the result that is most appropriate. At
a minimum, if 2 out of the 3 characteristics are rated as a ‗Project, the initiative is considered a
Project under this Policy.
Is this a Project? Operational vs. Project
Narrative
descriptive of
Initiative:
To determine if an initiative is "Operational" or a "Project", please rate each
characteristic below (in white drop down boxes):
Characteristics of
Initiative
Operational
Rating
Project
Length
On going
Temporary
Results
Repetitive
Unique
Value
Maintenance
Growth
Initiative is considered:
At a minimum, if 2 out of the 3 characteristics are rated to those of a 'Project, the initiative is
considered a Project under this Policy.
The Executive Director of the Department undertaking the initiative must agree as to the
designation of Project or Operational.
Characteristics Definitions
Length - The length of time for a project is classified as "temporary" if a definitive start and
stop date can be defined. If the initiative is one that is continuously "on-going" then it can be
classified more as operational.
Example 1: An annual business plan that revises management's strategy is a repetitive function and
considered operational; however a strategy on a particular topic that has a definitive completion date
would be considered a project.
Example 2: Annual park beautification would be considered operational; however constructing a new
park or playground equipment / sporting facilities would be considered a project.
Project Management Methodology policy
Page 8 of 16
Results - The results or outputs of a project is classified as "unique" if the results (or similar to)
have never been duplicated before. If the initiative is one that produces "repetitive" results
then it can be classified more as operational management.
Example 1: An annual business plan that revises management's strategy is a repetitive function and
considered operational; however a case study on a particular topic that has not been produced before is
unique and would be considered a project.
Example 2: Repetitive road or bridge repair that takes place each day of the season (regardless of the
location) would be considered operational; however constructing a new structure or infrastructure with
new technology never or rarely used at the city would be considered a project.
Value - A project is classified as providing "growth" if the project results are adding to the
City's assets (either tangible or intangible). If the initiative is one that "maintains" the City's
assets (either tangible or intangible) then it can be classified more as operational
management.
Example 1: Revisions to a current staff development strategy & its implementation is a maintenance
function and considered operational; however a new strategy & its implementation for developing staff
reflects growth and would be considered a project.
Example 2: Maintenance on City assets would be considered operational; however constructing a new
structure or infrastructure would be considered a project.
Next Step:
If this initiative is deemed:
Operational - this policy does not apply as individual departments already have processes in
place.
Project - your task requires some level of project management. The next step is to assess the
appropriate level of project management required under this policy.
Project Management Methodology policy
Page 9 of 16
SCHEDULE B
Project Assessment Worksheet
Description:
1. The project description information is contained within the white text boxes
located at the top of the Project Assessment Worksheet. This is a brief
summary of the proposed work which reflects the project's information known
at the time of the assessment. Any subsequent changes to project description
information should be communicated to Corporate Initiatives' office so to
update the Corporation's project list.
Classification:
1. The project classification is based on the ‗most appropriate' response for each
characteristic noted in the left column on the Project Assessment Worksheet.
2. To determine, rate each characteristic by indicating ‗Major', ‗Medium' or ‗Small'
in the ‗Rating' column representing the result that is most appropriate. For
clarify, the characteristics are defines as follows;
Scope is defined as the statement of work to be undertaken by the Project
including all objectives and deliverables the Project is expected to achieve.
Timeline is defined as the estimated amount of time required from the
approval of the Project by Council or other approving authority until the final
deliverables and objectives have been deemed complete.
Budget is defined as the total gross amount of financial resources required to
complete the project, which may include procurement and or development
costs, interest charges during the life of the project needed to finance the
unfunded expenditures, appropriate salaries and benefits (as defined in the
Capital Tangible Assets Policy) necessary to deliver the project in scope.
Risk Level is the indicator of the degree of risk a Project faces in achieving its
objectives.
Visibility is the degree to which a Project is exposed to impacts from external
stakeholders or the general public.
3. The result of the rating is based on a minimum of two or more criteria that falls
under the higher classification. For example;
Major Project is defined as a Project that typically meets at minimum two
or more criteria in the MAJOR column. If only one criterion falls within the
Project Management Methodology policy
Page 10 of 16
Major column, the classification remains at the discretion of the Project
Sponsor.
Medium Project is defined as a Project that typically meets at minimum
two or more criteria in the MEDIUM column.
Small Project is defined as a Project that has most of the criteria in the
Small column.
4. The Project Sponsor and Executive Director of the Department undertaking the
initiative must agree as to the classification of a Project.
Project Management Methodology policy
Page 11 of 16
Project Assessment Worksheet
Schedule B: Project Assessment Worksheet
Project Name:
Project Description:
Lead Department:
Project Sponsor:
Project Manager:
Date of Assessment:
Targeted Start Date:
Targeted End Date:
Total Budgeted Estimate: $
-
If the initiative is considered to be a project, then please rate the level of project for each characteristic in the white drop down text
boxes below to determine the overall size of the project.
Characteristics
of a Project
Rating
Small
Medium
Major
Scope
- Straight forward project that has
minimal dependencies within the
project or with other projects.
- Project's objective has been achieve
before.
- Limited number of internal key
stakeholders
- Somewhat complex project that has
significant dependencies within the
project or with other projects.
- Project's objective has been
achieved before but can face difficult
challenges to achieve.
- Limited number of internal &
external key stakeholders
- Very complex project that includes
many task dependencies within the
project or with other projects.
- Project's objective has never been
achieved in the City before, or is
rarely accomplished.
- Many internal/external key
stakeholders
Timeline
- No or minor impacts for missing
deadlines.
- Funding and/or legislation
requirements and/or political
commitments are dependent upon a
deadline that have a moderate impact
for missing deadlines.
- Funding and/or legislation
requirements and/or political
commitments are dependent upon a
deadlines that have a significant
impact for missing deadlines.
Budget
- Up to $5 million
- $5 million - $10 million
- $10 million +
Visibility
- The project has a limited profile in
the City and is not likely to be
impacted by outside sources (i.e.
Public, Media, Agencies, other Govt.
Bodies, etc.)
- The project has a medium profile in
the City and can be somewhat
impacted by inside & outside
sources (I.e. City Administration,
ABC's, Council, Media, other Govt.
Bodies, etc.)
- The project has a high profile in and
outside the City and can be
significantly impacted by outside
sources (I.e. Council, Media, other
Govt. Bodies, etc.)
Risk Level
- An initial risk assessment for the
project indicates a low to medium
risk level.
- The likely impact of the project's
risks is minimal.
- An initial risk assessment for the
project indicates a high risk level.
- The likely impact of the project's
risks is moderate to high if not
managed.
- An initial risk assessment for the
project indicates a high / critical risk
level
- The likely impact of the project's
risks is very significant if not carefully
managed.
Recommended
Project Type:
Approved By:
Project Sponsor:
Date:
Project Management Methodology policy
Page 12 of 16
SCHEDULE C
Project Management Methodology
Projects assessed as MAJOR under this assessment must follow this methodology.
The tools outlined under this Policy are based on the Project Management Institutes
(PMI) best practices and guidelines. They follow the principle project management &
auditing concept: an initiation document (i.e. project brief, project charter, or scope
document) indicates what the project intended to accomplish and how, a closing
document indicates what the project actually accomplished and how, and a process
and/or documentation explaining the deviation between the two.
1. Governance Structure
Project Governance is the planning, implementation, and ongoing management of
roles, responsibility and decision-making processes involved in project planning and
delivery. The following project organization structure is a sample of the hierarchy of
a MAJOR project. In some instances, it may be warranted to have the Steering
Committee and the Project Executive Committee operate as one. The governance
structure should fit the project and as such there is flexibility of governance provided
the roles and responsibilities are distinct and clear. The change would be outlined
in the project Charter to be approved by City Council.
As per Council Resolution #271/2011, all Major Projects as defined in this policy
must include the City Solicitor or designated lawyer as a member of the Project
Executive Committee, or combined Executive & Steering Committees depending on
the project governance structure.
Project Management Methodology policy
Page 13 of 16
2. Documents*
The following documents are to be completed for MAJOR projects with the
expectation that the project will be audited, and should maintain consistency
throughout the life of the project:
a. Project Charter, that contains at least the following components:
o scope & deliverables
o roles & responsibilities
o high level project timeline
o resource management plan for staffing & funding
o risk
o procurement
o communication management plan
b. Project risk assessment.
c. Responsibility matrix.
d. Periodic project status reports.
e. Project meeting minutes identifying key project related decisions.
f. Project issues list.
g. Project Close Summary including;
o deliverables completed/not completed
o success factors achieved
o variance summary
o lessons learned
h. Change control process and documentation explaining scope, budget and
timeline changes.
i. Project Management Plan (optional)**, that builds upon the Project Charter
with greater detail as required which addresses project management for:
o scope
o time
o cost
o human resourcing
o quality assurance & control
o communications
o risk
o procurement
*Typical documents used in project management can be found on the Corporate Initiatives'
website. These documents are only samples and are not comprehensive of all forms required
under this policy. These are samples used in past projects and must be tailored to meet
individual project needs
**The Project Management Plan is considered optional to the Project Manager's discretion
which is dependent upon whether the level of detail provided in the Project Charter is
adequate enough to successfully obtain the project's objectives and achieve the project
success criteria. Select areas within the Project Management Plan may require more detail
than others depending on what's needed to successfully complete the project.
Project Management Methodology policy
Page 14 of 16
3. Roles and Responsibilities:
Project related responsibilities must be clearly defined for each role. Defining the
responsibilities of each role and communicating this will help maximize the use of
resources, increase efficiency, and ensure the quality of the completed project. For
each role in the organization structure above, the typical project responsibilities
have been listed below:
Project Sponsor - The role of the Project Sponsor is to be the champion of the
project, who is accountable for the benefits and short comings of the project. As
such, they play a role in navigating the project through the political climate and help
the project be successful by providing adequate resources (staff & budget) and
ensuring the scope is attainable and fits the strategic direction of the Corporation.
The Project Sponsor has the following responsibilities:
- Provides overall project direction and guidance, including setting attainable
expectations and scope of work.
- Champion/Promote/Support the project at senior levels
- Empower the project manager to manage the project.
- Provide the Project Manager with adequate staffing and budget for the project
to be successful.
- Accountable for realizing the benefits and short comings of the projects.
- Hold the Project Manager accountable for the status of the project (I.e. on
budget, on time, within scope), and be available to help the Project Manager
address issues/constraints outside their control.
- Provide the Project Manager with a go / no go decision at various stages of the
project. In rare circumstances, the Project Sponsor could assume some or all of
the responsibilities of the Project Executive Committee, with the approval of
Council or the CAO.
Project Steering Committee - The role of the Project Steering Committee is to
support the project, and assist them in navigating the project through the political
climate and help the project be successful by providing adequate resources (staff &
budget) and ensuring the scope is attainable and fits the strategic direction of the
Corporation.
Project Executive Committee - The role of the Project Executive Committee is to
support the Project Sponsor of the project, and assist them in navigating the project
through the political climate and help the project be successful by providing
adequate resources (staff & budget) and ensuring the scope is attainable and fits
the strategic direction of the Corporation.
Depending on the project governance structure some of the responsibilities can be
transferred to a superior Steering Committee or the Project Sponsor. Typically the
Project Executive Committee has the following responsibilities:
- Provides overall project direction and guidance.
- Promote/Support the project at senior levels
Project Management Methodology policy
Page 15 of 16
- Provides stakeholder's engagement.
- Provides cross-functional resources to the project (I.e. staff, funding,
technology, etc.)
- Ensures the project stays aligned with the corporate goals; advises the Project
Manager where changes to strategy might impact the project
- Approve success criteria and performance measurements
- Hold the Project Manager accountable for the status of the project (I.e. on
budget, on time, within scope), and be available to help the Project Manager
address issues/constraints outside their control.
- Provide the Project Manager with go / no go decision at various stages of the
project, and authorize key project milestones (I.e. pass through gating, entering
into contracts, deliverable completion, etc.)
- Authorizes or declines scope change requests
- Monitors the overall project progress, through consistent monitoring mediums
such as, regular Committee meetings, reviewing project status reporting, risk
management, etc.
- Authorizes the project completion
Project Manager - The role of the Project Manager with the appropriate skills and
experience for the project, is to be the leader of the project, who orchestrates a plan
and leads a project team to meet the project's goals and objectives set by the
Project Sponsor and Project Executive Committee. The Project Manager has the
following responsibilities:
- Has overall leadership and responsibility of the Project Team to meet the
project success criteria.
- Is the person responsible for accomplishing the project objectives within the
parameters of the Project Charter.
- Elevates risks/issues, change requests, and direction for approval to the Project
Executive Committee.
- Is involved with the planning, implementation and monitoring of the project plan,
including managing and directing the assigned project resources to best meet
project objectives.
- Controls and monitors --triple constraints‖--project scope, time and cost (quality
also)--in managing competing project requirements.
- Collects metrics data (such as baseline, actual values for costs, schedule, work
in progress, and work completed) & reports on project progress and other
project specific information to the Project Executive Committee and
stakeholders.
- Responsible to the project stakeholders for delivering a project's objectives
within scope, schedule, cost, and quality.
- Responsible for constructing and implementing a project plan, including all 4
remaining phases of a project (planning, implementation, monitoring, & closing),
to achieve the objectives within the Project Charter.
Project Management Methodology policy
Page 16 of 16
Project Team - The role of the Project Team is to complete the work assigned in
the project plan to meet the project's goals and objectives set by the Project
Sponsor and Project Executive Committee. The Project Team has the following
responsibilities:
- Does the work as allocated in the project plan.
- Assists in building the details of the project plan.
- Assists in resolving issues at the project level and refers to the Executive
Committee if required.
- Provide input to process improvements.
- Report to the Project Manager the status of the assigned tasks, issues or risks
relating the project, or process changes that may impact the project.
3rd Party Responsibilities - Consultants, vendors, and contractors typically report
to the Project Manager, providing services through the project life-cycle. The
services will vary depending on the nature of the project and are based on the
formal agreement between the Consultant and the City. The responsibilities of the
3rd party are to:
- Be aware of the Project Management Policy and report appropriately to the
Project Manager for compliance.
- Complete an acceptable level of work as identified in the binding document
between the 3rd party and the City (I.e. tender contract, statement of work, etc.)