BUILDING PERMIT FEE SCHEDULE
Residential Installations
New Dwellings, Additions, Renovations, $6.50 per $1000 of Project Value **
Decks, Accessory Buildings, Reconstruction $150.00 minimum permit fee
Manufactured / Mobile Home $150.00
(on blocking or piles)
Relocation of a Building $0.35 per square foot of main floor
(on crawlspace or basement) $150.00 minimum permit fee
Roof Mounted Solar Installations $175.00
Solid Fuel Burning Appliances, Hot Tubs,
oe «a: $150.00
Swimming Pools, Demolition
Multi-Family, Commercial, Industrial, Institutional Installations
Description of Work Permit fee ("SCC Levy not included)
New, Addition, Renovation, . +
Alteration, Demolition $6.50 per $1000 of Project Value
Minimum Building Permit Fee $300.00
Project Value is based on the actual cost of material and labour.
Use the Project Value Calculator to ensure fair market value.
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
ELECTRICAL PERMIT FEE SCHEDULE
Residential Installations
Single Family Dwellings, Additions
Up to 1000 $165.00 $6.60 $171.60
1001 -- 1200 $190.00 $7.60 $197.60
1201 --- 1500 $215.00 $8.60 $223.60
1501 -- 2000 $240.00 $9.60 $249.60
2001 -- 2500 $265.00 $10.60 $275.60
Over 2500 $265.00 plus $0.10 per square foot plus SCC Levy
Residential Connections
Permanent Service Connection Only $165.00 $6.60 $171.60
Temporary Power/Underground $165.00 $6.60 $171.60
Service
Alternative Energy (Solar, Wind) $225.00 $9.00 $234.00
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
ELECTRICAL PERMIT FEE SCHEDULE
Other than New Single Family Dwellings and Additions and Residential Connections
$0.00 - $2,500.00 $165.00 $6.60 $171.60
$2,501.00 - $5,000.00 $200.00 $208.00
$5,001.00 - $7,500.00 $265.00 $10.60 $275.60
$7,501.00 - $10,000.00 s350.00 | si400 | $364.00
$10,001.00 - $20,000.00 $450.00 $18.00 $468.00
$20,001.00 - $30,000.00 $575.00 $23.00 $598.00
$30,001.00 - $40,000.00 $700.00 $28.00 $728.00
$40,001.00 - $50,000.00 $825.00 $858.00
$350,001.00 - $500,000.00 $1,750.00 $70.00 $1,820.00
$500,001.00 - $750,000.00 $2,250.00 $90.00 $2,340.00
$750,001.00 - $1,000,000.00 $2,750.00 $110.00 $2,860.00
For projects over $1,000,000 divide the total installation cost by
Greater than $1,000,000.00 $1,000 and then multiply by 3.000 plus SC Levy
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
ELECTRICAL PERMIT FEE SCHEDULE
Annual Electrical Permits
Annual Electrical Maintenance $375.00 $15.00 $390.00
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
GAS PERMIT FEE SCHEDULE
Residential Installations
16 - 20 $325.00 $13.00 $338.00
Over 20 Outlets $325.00 plus $10.00 per outlet over 20
Propane Tank Set (if
doing a connection, also add the $165.00 $6.60 $171.60
permit fee for the number of outlets)
Temporary Heat $165.00 $6.60 $171.60
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
GAS PERMIT FEE SCHEDULE
Multi-Family, Commercial, Industrial, Institutional, Oil & Gas
New and Replacement Installations
0 - 400,000 $165.00 $6.60 $171.60
400,001 - 750,000 $215.00 $223.60
750,001 - 1,000,000 $265.00 $10.60 $275.60
1,000,001 - 2,000,000 $315.00 $12.60 $327.60
$315.00 plus $6.50 per 100,000
Over 2,000,000 (or portion of) over 2,000,000 BTU
Propane Installations
Tank Set Only
(if doing a connection, also add the $165.00 $6.60 $171.60
permit fee for the BTU Input)
Propane Cylinder Refill Centre $250.00 $10.00 $260.00
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
PLUMBING PERMIT FEE SCHEDULE
Residential & Non-Residential Installations
16 - 20 $270.00 $10.80 $280.80
$270.00 plus $6.50 per fixture over 20
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
PRIVATE SEWAGE PERMIT FEE SCHEDULE
Holding Tanks and Septic Tanks Only $275.00 $11.00 $286.00
Open Discharge, Fields, Mounds,
Lagoons, Treatment Plants $450.00 $18.00 $468.00
* SCC Levy is 4% of the permit fee with a minimum of $4.50 and a maximum of $560
MD of Bighorn
MISCELLANEOUS FEE SCHEDULE
Additional Inspections $125.00 / inspection
(beyond QMP requirements (SCO Discretion) subject to 4% SC Levy
6 months -- no charge
Another 6 months -- 10% of permit fee
Request for Extension minimum $125.00
subject to 4% SC Levy
New permit required beyond one year
Altemative Solutions / Variances $150.00/hour minimum 2-hour charge
- . . Double Permit Fee
Additional work found during inspection $75.00
not on the onginal permit subject to 4% SC Levy
Building & Private Sewage Issued Permits $150.00
Change to Drawings or Design subject to 4% SC Levy
Private Sewage Inspection for $150.00/hour minimum 2-hour charge
Subdivision Approval plus GST