# Get a Building Permit
Apply for building permits, check requirements, and track your application status all in one place.
###
Rocky View County advises that STANDATA 23-BCI-015R1 (Design of Wood Trusses for Roof Assemblies in Part 9 Buildings) will apply to all Part 9 buildings effective March 1, 2026.
### Building Permit Application Requirements
* All Part 9 buildings must include authenticated (P. Eng.-stamped) wood truss designs for roof assemblies
* This requirement includes one- and two-family dwellings
* STANDATA 23-BCB-002R1 -- *Roof Trusses for One- and Two-Family Dwellings* will be archived as of February 28, 2026
### Authentication Requirements
All wood roof truss assemblies must be authenticated and address the following:
* Truss profiles
* Member sizes
* Authentication does not have to occur on the roof truss layout plan provided the information of how trusses are interconnected is provided in a separate authenticated document
* Joint and plate connections
* Bracing requirements
* Truss connections
All truss profiles and layouts require authentication (P. Eng. stamps) unless the complete required design information is provided and authenticated through other documentation.
### Background
Alberta Municipal Affairs has provided industry guidance over the past year to support this transition. The implementation timeline has allowed manufacturers, suppliers, and builders time to prepare for the updated authentication requirements for roof trusses.
### Questions or Feedback
Applicants with questions or comments may contact:
* [email protected] -- Alberta Municipal Affairs
* [email protected] -- Rocky View County Building Services
A Building Permit is formal permission from Rocky View County to begin construction, demolition, addition, or renovation to a property. Building Services staff review plans to ensure they comply with all application local and provincial regulations.
The building permit process protects both the owner's interest and those of the community at large. It also helps to ensure that any structural change is safe. Failure to get the proper permits before starting construction can result in costly delays, legal action or the removal of work you have already completed.
## When to Get a Building Permit
Building permits are required for demolition or construction for any building over 107 square feet (10 m²). This includes relocation, alterations/renovations, and changing the use of a building (e.g. yoga studio changing to a retail store). They are also required for:
* Deck construction (where the deck is greater than 0.6 m (2 feet) from ground level at any point)
* Wood burning appliance installation
* Swimming pools
* Hot tubs
* Kitchen renovations (when replacing/installing cabinets or replacing/installing a hood fan)
Building permits are not required for minor repairs and replacements that do not affect the structural integrity of a building. Some of the projects that do not require a building permit include:
* Re-insulating or adding insulation
* Window or door replacement, providing the opening is not enlarged
* Re-roofing, except where structural work is involved
* Minor exterior repairs and siding
Although your project may not require a building permit, permits for other disciplines may still be needed (e.g. gas, electrical, plumbing, private sewage, or sewer connections). Some of the projects that do not require a subtrade permit include:
* Furnace and hot water tank replacements, providing no design change is required to any gas piping or venting system
* Repair or replacement of plumbing fixtures, providing no design change is required to the piping system
## How to Apply for a Building Permit
###
Building and subtrade permit applications can be submitted online through *my*Build.
* *my*Build Guide [PDF/316KB]
###
In person applications can be accepted Monday to Friday, 8 a.m. to 4:30 p.m., on a first-come, first-served basis at:
County Hall
Building Services Counter
262075 Rocky View Point
Rocky View County, AB, T4A 0X2
(map and hours)
If submitting applications in person, plans and documents must be submitted in electronic format, such as a flash drive or memory stick.
## Permitting Process
1. 1
### Pre-application consultation
Applicants may arrange a meeting for a fee to discuss their proposed project by scheduling a pre-application meeting with Building Services.
2. 2
### Application submission
When submitting your application, all forms and required documentation are to be submitted to ensure timely review of your permit applications. Refer to the relevant checklist to assist in completing your application.All forms must be filled out in their entirety, including signatures where applicable.
All contact information (names, phone numbers, and email addresses) for all owners, contractors and applicants must be provided.When submitting applications in person, plans and documents must be submitted in electronic format, such as a flash drive or memory stick.
3. 3
### Evaluation of application
The application will undergo an administrative review and processing, which may take 35 days. The application is not considered complete until all required information and documents have been submitted.
4. 4
### Fees
Permit fees will be calculated as part of the administrative review and must be paid before your application proceeds to a technical review. Learn more about payment options and fee schedules.
5. 5
### Technical Review
The application will be reviewed for all technical and building code requirements.
6. 6
### Permit issuance
Depending on the complexity of the project, applications may have a permit issued within three to five days, or up to 25 business days. Three to five is typical for basement development, decks, fireplace/wood stove, swimming pool/hot tub, kitchen/home renovation, farm building exemption, simple accessory building, simple tent/air-supported structures.
Ten to 25 business days is typical for single family dwelling, move-on dwelling/manufactured home, additions, detached garage and other accessory buildings, accessory dwelling unit/secondary suite, tent/air-supported structure, tenant bay development, commercial/industrial/institutional building.
Once a permit is issued, the County must be notified of any changes. All permits expire one year from the date of issuance.
7. 7
### Inspections
Safety Codes Officers for all trades and subtrades perform inspections at major phases of construction. It is the responsibility of all property owners and/or agents to be aware of inspection requirements and to schedule inspections at the specified stages of construction. The permit and a current copy of building and relevant subtrade plans must be kept on site and be made available for the inspection.
8. 8
### Completion
A Permit Services Report stating the closed status of the permit(s) will be sent to the property owner within 30 days of all final inspections being passed.
9. 9
### Permit renewals (if required)
All permits expire one year from the date of issuance. If a permit expires before work has been started, or before all required inspections have been performed and passed, the applicant will be required to renew or reapply for a permit.
## Project-Specific Information
Building projects require different applications and processes depending on what is being built. The following list of building projects provides details and instructions specific to each task. Please refer to the Rocky View County Building Permit Checklists and the Safety Codes Council Safety Tips brochures specific to your project.
## Links
* Alberta New Home Warranty
* Alberta Wall and Ceiling Association
* Canadian Homebuilders Association
* Canada Mortgage and Housing Corporation
* National Research Council
* Private Sewage Systems Design Tools and Forms
* Safety Codes Council - Safety Tips Brochures
**Was this page helpful?**
No
### We want to hear your feedback
Feedback
Cancel
Your submissions are used by our web team to help improve the experience on rockyview.ca.