TOWN OF SIDNEY
BYLAW NO. 1440
A BYLAW OF THE MUNICIPALITY TO IMPOSE DEVELOPMENT COST CHARGES.
WHEREAS pursuant to Section 932 through 937 of the Municipal Act, the Council may, by
bylaw, impose development cost charges under terms and conditions of the Section;
AND WHEREAS the development cost charges may be imposed for the sole purpose of
providing funds to assist the Municipality to pay the capital costs of providing, constructing,
altering or expanding sewage, water, drainage and highway facilities, to provide park land, to
service, directly or indirectly, the development for which the charge is being imposed:
AND WHEREAS no development cost charges shall be required to be paid:
(a) if a development cost charge has previously been paid with respect to the same
development, unless, as a result of a further development, new capital cost
burdens will be imposed on the Municipality; or
(b) where the development does not impose new capital cost burdens on the
Municipality.
AND WHEREAS Council has taken in consideration future land use patterns and development,
the phasing of works and services, and the provision of park land described in an Official
Community Plan;
AND WHEREAS in the consideration of Council the charges imposed by this bylaw:
(a) are not excessive in relation to the capital cost of prevailing standards of service;
(b) will not deter development;
(c) nor will discourage the construction of reasonably priced housing or the provision
of reasonably price serviced land in the Municipality.
AND WHEREAS in the opinion of Council the charges imposed by this bylaw are:
(a) related to capital costs attributable to projects involved in the capital budget of the
Municipality;
(b) related to capital projects consistent with the Official Community Plan of the
Municipality.
Bylaw 1440
Development Cost Charges / page 2
NOW THEREFORE the Municipal Council of the Town of Sidney in open meeting assembled
enacts as follows:
1. This bylaw may be cited for all purposes as ''Development Cost Charge Bylaw 1440,
1998".
2. For the purpose of calculating units in this bylaw:
(a) a unit shall mean a self-contained dwelling unit in a Multiple Family Residence,
each 230 square meters of Commercial space and each 1850 square metres of
Industrial land for Building Permit Applications; and,
(b) a unit shall mean each new lot created during a subdivision or strata development
under the Strata Title Act.
3. (a) Every person who obtains a building permit authorizing the construction,
alteration or extension of a building that will, after the construction, alteration or
extension that:
i. contains 4 or more self-contained dwelling units; and,
i. be put to other uses other than the residential use in the dwelling unit; or,
ili. the value of the work authorized by the permit exceeds $50,000.
(b) Every person who obtains approval of the subdivision of a parcel of land under
the Land Registry Act or the Strata Titles Act for any purpose other than the
creation of four (4) or more lots to provide sites for a total of four (4) or more self-
contained dwelling units shall pay, prior to the approval of the subdivision or the
issue of the building permit, as the case may be, to the Town, the applicable
development cost charges as indicated in Schedule "A" attached hereto is subject
to the charges payable in this bylaw if the real property is within the area shown
on Schedule "B" of this bylaw.
4, A charge is payable in respect of every event under Tables 1(A), 1(B), 1(C), 1(D) and
1(E) provided that:
a) a charge is not payable under this section where a charge under this bylaw has
been paid previously for the same event in respect of the same development;
b) a credit shall be deducted from the amount that would otherwise have been
imposed under this Section in respect of a parcel for the amount of development
cost charges previously paid to the Town for the same development on the same
parcel under this bylaw;
5. Under no circumstances shall any charges collected under this bylaw be refunded. When
an approved subdivision plan is not deposited or not construction is commenced pursuant
to an approved building permit, charges collected shall be credit toward charges payable
in respect of a future charging under Table 1.
Bylaw 1440
Development Cost Charges / page 3
6. Exemptions:
No charge is payable under this bylaw where the:
a) building permit authorizes the construction, alteration or extension of a building
or part of a building that is, or will be, after the construction, alteration or
extension, exempt from taxation under Section 339 (1)(g) of the Municipal Act;
b) building permit authorizes the construction, alteration or extension of a building
that will, after the construction, alteration or extension:
(1) contain less than four (4) self contained dwelling units; and
(ii) be put to no other use than the residential use in those dwellings; and
c) value of the work authorized by the permit does not exceed $50,000 or any other
amount prescribed by regulation under section 933 (4)(c) of the Municipal Act.
7. This bylaw hereby repeals Development Cost Charge Bylaw No. 1259, 1995.
Read a first time this 22"! day of June, 1998.
Read a second time this 22" day of June, 1998.
Read a third time this 29" day of June, 1998.
Approved by the Inspector of Municipalities on the under the provisions of Section 937 of the
Municipal Act on the 8" day of September, 1998.
Reconsidered and finally adopted on this 28" -- day of September, 1998.
MAYOR CLERK
Bylaw 1440
Development Cost Charges / page 4
SCHEDULE "A"
DEVELOPMENT COST CHARGES
* Charges to be levied and paid are specified in Column "C"'.
TABLE 1 (A) - SEWER (See Schedule "B" for breakdown)
AREA NO. OF UNITS TOTAL UNIT COST
TABLE 1(B) - WATER (See Schedule "C" for breakdown)
AREA NO. OF UNITS TOTAL UNIT COST
TABLE 1 (C) - STORM DRAIN (See Schedule "D" for breakdown)
AREA NO. OF UNITS TOTAL UNIT COST
TABLE NO. 1 (D) - PARKS AND PUBLIC OPEN SPACE (See Schedule "E" for breakdown)
AREA NO. OF UNITS TOTAL UNIT COST
. A
' | °
a ) | =
PE] [2 SCHEDULE Bes
| 2 |e | DEVELOPMENT COST CHARGE :
Ls | Por | AREA ( VIEW ENLARGED )
io Ile] ff Te] [2 oy
: nt Alc
a] ; z .
evan ee | 3 |
4) ae
5 ? 22 | "
| 5 | 22 | 54]
a
, SALTHOUR ROO 20 7
1] flee |e [= | Gee i
| 2 | pa otane | |, . : .
7 | 8) s Bl 1s 5 5
aa 15 ras |
Ls | 2 z aad
g ie ce a 17 Jur. Baer AVENUE ; 5 ;
a Pa tn | C. Pede
~ tt? | a | J n | 2] ee a
eK + | 2, 8 x3 to |e{s Feels [io | .
<] on ee ee: i ee Plots.
borg BOULEVARD SIONEY AVENUE .,
; m7 >7]7) fs le |] fteq -. ..
' 15 15 ; om
A
Te fw | fe te | deal
Pl) Pieters bePery bee} -
BEACAN AVENUE .
, rade
| i WEE] PEREEE) RET
te Aa ast
"boots Ve} 2 : an :
a fs | fe
Pets
pa fe | Ce Pe } Ge
| sein iene
| [+ Te]
P+ | pe] fs pe .
1 | 3 | 4 A
t 2 Ji¢4 5 6 1 2 J 4
: mam 6 tz]
OAKVILLE AVENUE
| Bele) Eelek) PPIRARPE IE:
| be org PE) 5 a, TG ET '
erie] [rll] Pier] mole b] bli] EPIEE
. ORCHARD AVENUE P
x ~
e Lede [lle eCeLe [lee] ef] fe [ode et le ee tee ed lel
; 3 12 _3 12 ! 12 im J 12 Sit 3 12 .
Pos | SCHEDULE "Cc"
CALCULATION DATA |
UNITS
AREA 1
: A. Residential - Based on Official Community Plan:
1. Residential 2 AO units per net hectare
2. Residential 4 30 units per net hectare .
3. Residential 5 38 units per net hectare oe
4. Residential 7 65 units per net hectare ;
5. Residential 8 75 units per net hectare .
6. Residential 9 75 units per net hectare
7. Residential 10 75 units per net hectare
B. Institutional:
Based on maximum density of 75 units per net hectare
AREA 2 ; ;
Cc. Commercial:
Commercial 1 and 2 - based on 223 square metres which is the minimum parcel
size for Commercial Zone in the Subdivision Bylaw.
TOTAL AREAS:
1. Residential 2 0.73 hectares x 40 units = 29 units
2. Residential 4 0.4666 hectares x 30 units = 13 units
3. Residential 5 2.6599 hectares x 38 units = 101 units
4. Residential 7 0.228 hectares x 65 units = 14 units
5. Residential 8 0.1486 hectares x 75 units = 11 units -
6. -Residential 9 1.682 hectares x 75 units = 126 units - ,
7. Residential 10 4.2987 hectares x 75 units = 97 units
8. Institutional 0.4061 hectares x 75 units = 30 units
9. Commercial 1 & 2 5.284 hectares + 0.0223 units = 234 units
Total 655 units-_
Pipe History:
a Existing pipe 250mm constructed in 1954
o Life expectancy - 50 years
o Life remaining - 10 years
a 4994 Construction Cost - $130,000. less contribution (Infrastructure Grant)
$33,000. = $97,000.
o Assist factor 10/50 of $97,000. = $19,000.
o Estimated cost of Sewer Upgrading - $97,000.
a Less Assist Factor of (20%) = $19,000.
o $97,000. - $19,000. = $78,000. + 655 units = $119. per unit
/ 7 ; ; SCHEDULE "me |
Oe re ae mae oe re Ee Ds teded
[LS CESHEEEA EERE EERE A CEE Perce ee Pee
PELE] (EEE. []/PROPOSED DEVELOPMENT COST CHARGE|-----|-----} |
Hell] [PPE -[ E> [LAREA'S FOR WATER MAIN UPGRADING a,
TFOOUCCECCUCTCT GEINsaccraeen cze@o=s Ua
PERE Bete a |]. cry |
PEE) CEECHEGH GEREEEPEPEES TE HSerE LL + TITIES * (i =o.
mnee ces : oar
Hie PTTL) ERECTA eur TE A es
PEEPS EEHOPREaUb Perot | EL] <4 | EAGT:
PEEL) GELEPEDEL] FEEEEL ET TERA a | eres OO on RAE pce
FEBEE) EEEGEPIEY ESEEEPPREEES Feb | Srey
lessen Ce [See |
Po Ee >
pe eA eT ANY | pREK2) - |----
7] ="
cane ates PL EE
BREAN | NTT es
EEL TET opt |
PEEL} EET Pepe DEERE TT) ta |
SSUES TEE ae FE EE
mem eaDertiaa ert OE ee
See |) Cre ELS | [meses
= : [ «| [3
BO050)es meee aah] aS cl
), NaH Ee BE mele PERC a
FA XPEE Foye ae LT FS LNB 7]
PA Xie SG" oes Ee ea
Vv Bojalerlaaltclanih
ph Eee Gree anes GEA Llc
. AL) CL) Cy a eg a
re Sheet1
CALCULATION DATA FOR WATER
AREA 1 HENRY AVENUE FROM SEVENTH STREET TO RESTHAVEN DRIVE :
JAMES WHITE BOULEVARD FROM SEVENTH STREET TO BESSREDGE PLACE -
RESTHAVEN DRIVE FROM JAMES WHITE BOULEVARD TO HENRY AVENUE
SEVENTH STREET FROM JAMES WHITE BOULEVARD TO HENRY AVENUE
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1. RESIDENTIAL 1 20 UNITS PER NET HECTARE
2. RESIDENTIAL 4 30 UNITS PER NET HECTARE
3. RESIDENTIAL 5 38 UNITS PER NET HECTARE . °
4. RESIDENTIAL 7.1 65 UNITS PER NET HECTARE
5. RESIDENTIAL 7.2 73 UNITS PER NET HECTARE .,
6. RESIDENTIAL 10 75 UNITS PER NET HECTARE
7. RESIDENTIAL 11 40 UNITS
B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
C. COMMERCIAL - BASED ON THE ZONING BYLAW 1300:
1. COMMERCIAL 1 - BASED ON THE MINIMUM LOT AREA OF NOT LESS
THAN 220 SQUARE METERS. a
2. COMMERCIAL 2 - BASED ON MAXIMUM DENSITY OF 75 UNITS PER
NET HECTARE.
3. COMMERCIAL 5 - BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN
600 SQUARE METERS AND NOT MORE THAN 1800 SQUARE METERS.
TOTAL AREAS:
1. RESIDENTIAL 1 0.206 HECTARES X 20 UNITS = 4 UNITS
2. RESIDENTIAL 4 1.518 HECTARES X 30 UNITS = 46 UNITS
3. RESIDENTIAL 5 4.001 HECTARES X 38 UNITS = 152 UNITS
4. RESIDENTIAL 7.1 1.078 HECTARES X 65 UNITS = 70 UNITS
5. RESIDENTIAL 7.2 1,224 HECTARES X 73 UNITS = 89 UNITS
6. RESIDENTIAL 10 0.583 HECTARES X 75 UNITS = 43 UNITS
7, RESIDENTIAL 11 = 40 UNITS
8. INSTITUTIONAL 4.14] HECTARES/ 0.2 HECTARES = 21 UNITS
9. COMMERCIAL 1 1.073 HECTARES/0.022 HECTARES = 48 UNITS
10. COMMERCIAL 2 1.413 HECTARES X 75 UNITS = 105 UNITS
11, COMMERCIAL 5 0.053 HECTARES / 0.06 HECTARES = 1 UNIT.
TOTAL = 619 UNITS ;
PIPE HISTORY:
REASON WATERMAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN PROJECTIONS,
FIRE FLOW, AGE AND THE CAPACITY OF THE EXISTING SYSTEM.
PROPOSED PIPES -- 200 mm PVC
EXISTING PIPES 6" AC CONSTRUCTED IN 1957
4" PVC CONSTRUCTED IN 1977
6" PVC CONSTRUCTED IN 1980
1997 ESTIMATED CONSTRUCTION COST OF WATER UPGRADING - $560,500.
ASSIST FACTOR ( 60%) OF $560,500 = $336,300.
$560,500. - $336,300. = $224,200. /619 UNITS = $362.20 PER UNIT
Page 1
so Sheet
CALCULATION DATA FOR WATER
AREA 2 FIFTH STREET FROM BEACON AVENUE TO MILLS ROAD
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1. RESIDENTIAL 1 20 UNITS PER NET HECTARE
2. RESIDENTIAL 4 30 UNITS PER NET HECTARE .
. 3. RESIDENTIAL 5 38 UNITS PER NET HECTARE
4. RESIDENTIAL 8 75 UNITS PER NET HECTARE
5. RESIDENTIAL 9 75 UNITS PER NET HECTARE
6. RESIDENTIAL 10 75 UNITS PER NET HECTARE ;
B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 1000 SOUARE METERS.
C. COMMERCIAL - BASED ON THE ZONING BYLAW 1300:
1. COMMERCIAL 1 - BASED ON THE MINIMUM LOT AREA OF NOT LESS
THAN 220 SQUARE METERS.
2. COMMERCIAL 2 - BASED ON MAXIMUM DENSITY OF 75 UNITS PER
NET HECTARE. ;
TOTAL AREAS: ,
1. RESIDENTIAL 1 0.146 HECTARES X 20 UNITS = 2 UNITS
2. RESIDENTIAL 4 0.212 HECTARES X 30 UNITS = 6 UNITS
3. RESIDENTIAL § 4.132 HECTARES X 38 UNITS = 157 UNITS
4. RESIDENTIAL 8 0.180 HECTARES X 75 UNITS = 13 UNITS
5. RESIDENTIAL 9 1.662 HECTARES X 75 UNITS = 124 UNITS
6. RESIDENTIAL 10 0.822 HECTARES X 75 UNITS = 61 UNITS
7. INSTITUTIONAL 0.629 HECTARES / 0.1 HECTARES) = 6 UNITS
8. COMMERCIAL 1 0.795 HECTARES/0.022 HECTARES = 36 UNITS
9. COMMERCIAL 2 0.455 HECTARES X 75 UNITS = 34 UNITS
TOTAL = 439 UNITS
PIPE HISTORY:
REASON WATERMAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN PROJECTIONS,
FIRE FLOW, AGE AND THE CAPACITY OF THE EXISTING SYSTEM.
PROPOSED PIPE 200 mm PVC
EXISTING PIPES 6" AC CONSTRUCTED IN 1962
6" AC CONSTRUCTED IN 1972
1997 ESTIMATED CONSTRUCTION COST OF WATER UPGRADING - $340,300. °
ASSIST FACTOR ( 60%) OF $340,300 = $204,180.
$340,300. - $204,180. = $136,120. / 439 UNITS = $310.07 PER UNIT
Page 2 -
oO , Sheet1
CALCULATION DATA FOR WATER
AREA 3 FOURTH STREET FROM SIDNEY AVENUE TO HENRY AVENUE
A RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
]. RESIDENTIAL 8 75 UNITS PER NET HECTARE
2. RESIDENTIAL 9 75 UNITS PER NET HECTARE .
B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
TOTAL AREAS: .
1. RESIDENTIAL 8 2.055 HECTARES X 75 UNITS = 154 UNITS
2. RESIDENTIAL 9 0.502 HECTARES X 75 UNITS = 37 UNITS
3. INSTITUTIONAL 0.753 HECTARES /0.2 HECTARES = 4 UNITS
TOTAL = 195 UNITS
PIPE HISTORY:
REASON WATERMAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN PROJECTIONS, -
FIRE FLOW, AGE AND THE CAPACITY OF THE EXISTING SYSTEM.
PROPOSED PIPES 200mm PYC
EXISTING PIPES 4" AC CONSTRUCTED IN 1965
1997 ESTIMATED CONSTRUCTION COST OF WATER UPGRADING - $169,200.
ASSIST FACTOR ( 60%) OF $169,200. = $101,520.
$169,200. - $101,520. = $67,6800. / 195 UNITS = $347.08 PER UNIT
Page 3
a 'Sheet! |
CALCULATION DATA FOR WATER
AREA 4 MALAVIEW AVENUE FROM THIRD STREET TO RESTHAVEN DRIVE .
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1. RESIDENTIAL 4 30 UNITS PER NET HECTARE
2. RESIDENTIAL 10 75 UNITS PER'NET HECTARE °
. B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
C. COMMERCIAL - BASED ON THE ZONING BYLAW 1300: .
1. COMMERCIAL 5 - BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN .
600 SQUARE METERS AND NOT MORE THAN 1800 SQUARE METERS.
TOTAL ARFAS: .
1. RESIDENTIAL 4 3.059 HECTARES X 30 UNITS = 92 UNITS
2. RESIDENTIAL 10 0.902 HECTARES X 75 UNITS ~ 67 UNITS
3. INSTITUTIONAL 0.501 HECTARES /0.2 HECTARES = 3 UNITS . |
4. COMMERCIAL 5 0.102 HECTARES / 0.06 HECTARES = 2 UNITS
TOTAL = 164 UNITS ;
PIPE HISTORY:
REASON WATERMAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN PROJECTIONS,
| FIRE FLOW, AGE AND THE CAPACITY OF THE EXISTING SYSTEM.
PROPOSED PIPE 200 mm PVC
EXISTING PIPES 6" AC CONSTRUCTED IN 1973
1997 ESTIMATED CONSTRUCTION COST OF WATER UPGRADING - $185,600.
ASSIST FACTOR (60%) OF $185,600. = $111,360.
$185,600. - $111,360. = $74,240. / 164 UNITS = $452.68 PER UNIT
Page 4 .
- a Schedule "D"
}
=n. Roe
| _\ ieee he
Vee \\ ai
AURNRI Tlie, PARQUE". i
EN ee LOOKS
Bazan cen ,
SSS OS ULE ER RIO rts
SES Serf EOS
Bo ROTI) SE ARP
ARV iT ees SEA
j CEST PT | RATE
! TEST ASE iz =\-- LIQ .
oe seca eas V fe EE §
| OREN BO aa aS AS
| \ \COREAGHISAS <caeeset nn SS
iA \CEATnTE TD Cnc =p- 5 fi Bayh
i" 3 roe dm nore
Ve == ticity
yy AO ETT ec a
eS See i |
Ts BIT TILT & Uo"
yyy | Bhs LYE .
ee MUNA (IO yg) | FR
an FIGS, ee Pemmes Te A
ES UU Veo Se SH
Os
BSN AS SO pes
= SEE pemmn gens, al s,Q eZ TOWN OF
DSN EEE ag) SSE SIDNEY
Hea 8 [aap BERD aa, AND DISTRICT V1
DAL CTP SS SS gl TY A add
=o | SSS DEVELOPMENT COST CHARGE
SSeS | BEES! AREA'S FOR STORM SEWER UPGRADING
ee Sheet |
CALCULATION DATA FOR STORM DRAIN
AREAI MT BAKER AVENUE FROM THIRD STREET TO SECOND STREET OUTFALL
THIRD STREET FROM MT BAKER AVENUE TO SHOREACRES ROAD
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN: .
1, RESIDENTIAL 1 20 UNITS PER NET HECTARE
- 2. RESIDENTIAL 4 30 UNITS PER NET HECTARE
3. RESIDENTIAL 5 38 UNITS PER NET HECTARE
4. RESIDENTIAL 8 75 UNITS PER NET HECTARE . .
5. RESIDENTIAL 10 75 UNITS PER NET HECTARE °
B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300: "
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
TOTAL AREAS:
1, RESIDENTIAL ! 0.126 HECTARES X 20 UNITS = 3 UNITS
2. RESIDENTIAL 4 2.311 HECTARES X 30 UNITS = 69 UNITS ;
3. RESIDENTIAL 5 3.404 HECTARES X 38 UNITS = 129 UNITS
4, RESIDENTIAL 8 1.036 HECTARES X 75 UNITS = 78 UNITS
5. RESIDENTIAL 10 0.455 HECTARES X 75 UNITS = 34 UNITS '
6. INSTITUTIONAL 0.456 HECTARES / 0.2 HECTARES = 2 UNITS
TOTAL = 315 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS .
PROPOSED PIPES 300 mm PVC
375 mm PVC
450 mm PVC
EXISTING PIPES 8" CONCRETE
10" CONCRETE
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $192,000.
ASSIST FACTOR (60%) OF $192,000 = $115,200.
$192,000. - $115,200. = $76,800. /315 UNITS = $243.81 PER UNIT
Page 1 ve
pS Sheet1
CALCULATION DATA FOR STORM DRAIN
AREA2 MILLS ROAD FROM McDONALD PARK ROAD TO GALARAN ROAD
A, INDUSTRIAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
TOTAL AREAS:
1, INDUSTRIAL 4.548 HECTARES / 0.2 HECTARES = 23 UNITS
TOTAL = 23 UNITS 2
PIPE HISTORY: ;
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS
PROPOSED PIPES -- 525mm PVC
EXISTING PIPES 14" AC
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $30,000.
ASSIST FACTOR ( 60%) OF $30,000. = $18,000.
$30,000. - $18,000. = $12,000. /23 UNITS = $521.74 PER UNIT °
Page 2
ee Sheet1 .
CALCULATION DATA FOR STORM DRAIN
AREA 3 AMELIA AVENUE FROM McDONALD PARK ROAD TO THE PAT BAY HWY
. A. INDUSTRIAL - BASED ON THE ZONING BYLAW 1300:
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
. TOTAL AREAS:
1. INDUSTRIAL 2.745 HECTARES / 0.2 HECTARES = 14 UNITS :
TOTAL = 14 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS
ASSIST FACTOR DETERMINED BY THE DIFFERENCE IN COST OF INSTALLING THE
EXISTING PIPE SIZE AND THE PROPOSED PIPE SIZE
PROPOSED PIPES 525mm PYC
EXISTING PIPES 18" CONCRETE .
18" PYC
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $34,500.
ASSIST FACTOR (60%) OF $34,500. = $20,700.
$34,500 - $20,700. = $13,800. / 14 UNITS = $985.7] PER UNIT
Page 3 .
ss , Sheeti
CALCULATION DATA FOR STORM DRAIN
AREA 4 FIFTH STREET FROM SIDNEY AVENUE TO MT BAKER AVENUE
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
I. RESIDENTIAL 9 75 UNITS PER NET HECTARE
2. RESIDENTIAL 10 75 UNITS PER NET HECTARE .
B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300: .
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 1000 SQUARE METERS.
TOTAL AREAS:
I. RESIDENTIAL 9 0.708 HECTARES X 75 UNITS = 53 UNITS
2. RESIDENTIAL 10 0.374 HECTARES X 75 UNITS = 28 UNITS
3. INSTITUTIONAL 0.448 HECTARES /0.1 HECTARES = 4 UNITS
TOTAL = 85 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN ~
PROJECTIONS .
PROPOSED PIPES 375 mm PYC .
EXISTING PIPES 10" CONCRETE
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $36,000.
ASSIST FACTOR ( 60%) OF $36,000 = $21,600.
$36,000. - $21,600. = $14,400. /85 UNITS = $169.41 PER UNIT
Page 4
re Sheeti
CALCULATION DATA FOR STORM DRAIN .
AREAS MALAVIEW AVENUE FROM McDONALD PARK ROAD TO PAT BAY HWY
A. INDUSTRIAL - BASED ON THE ZONING BYLAW 1300: o
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS.
- TOTAL AREAS:
1, INDUSTRIAL 2.303 HECTARES /0.2 HECTARES = 12 UNITS .
TOTAL = 12 UNITS °
PIPE HISTORY: .
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS
PROPOSED PIPES 450mm PVC
EXISTING PIPES 10" CONCRETE
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $75,000.
ASSIST FACTOR ( 60%) OF $75,000. = $45,000. .
$75,000. - $45,000. = $30,000. /12 UNITS = $2,500.00 PER UNIT
Page 5 -
CO Sheett
CALCULATION DATA FOR STORM DRAIN
AREA 6 RESTHAVEN DRIVE FROM BRETHOUR ROAD TO HENRY AVENUE
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1, RESIDENTIAL 5 38 UNITS PER NET HECTARE
2. RESIDENTIAL 7.1 65 UNITS PER NET HECTARE °
3. RESIDENTIAL 10 75 UNITS PER NET HECTARE
B. COMMERCIAL - BASED ON THE ZONING BYLAW 1300: .
COMMERCIAL 5 - BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN .
600 SQUARE METERS AND NOT MORE THAN 1800 SQUARE METERS.
TOTAL AREAS:
I. RESIDENTIAL $5 0.312 HECTARES X 38 UNITS = 12 UNITS
2, RESIDENTIAL 7.1 0.325 HECTARES X 65 UNITS = 21 UNITS
3. RESIDENTIAL 10 0.391 HECTARES X 75 UNITS = 29 UNITS
1. COMMERCIAL 5 0.053 HECTARES / 0.06 HECTARES = 1 UNIT
TOTAL = 63 UNITS
PIPE HISTORY: ,
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS
PROPOSED PIPES -- 375mm PVC
EXISTING PIPES 10" AC
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $32,000.
ASSIST FACTOR ( 60%) OF $32,000. = $19,200.
$32,000 - $19,200. = $12,800. / 63 UNITS = $203.18 PER UNIT
Page 6
PO Sheet
CALCULATION DATA FOR STORM DRAIN
AREA 7 SEVENTH STREET/BEVAN AVENUE FROM SAANCHA HALL TO DRAIN EASEMENT
A. COMMERCIAL - BASED ON THE ZONING BYLAW 1300:
1. COMMERCIAL | - BASED ON THE MINIMUM LOT AREA OF NOT LESS
THAN 220 SQUARE METERS. .
TOTAL AREAS: |
J. COMMERCIAL 1 2.821 HECTARES / 0.022 HECTARES = 128 UNITS -
TOTAL = 128 UNITS
PIPE HISTORY: 7
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS.
PROPOSED PIPE --. 375mm PVC
EXISTING PIPES 200mm PYC.
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $29,000. _
ASSIST FACTOR ( 60%) OF $29,000. = $17,400.
$29,000. - $17,400. = $11,600. / 128 UNITS = $90.63 PER UNIT
Page 7 oo
ee Sheet
CALCULATION DATA FOR STORM DRAIN
AREA 8 JAMES WHITE BOULEVARD FROM SEVENTH TO CORNER
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1. RESIDENTIAL 4 30 UNITS PER NET HECTARE
2. RESIDENTIAL 7.1 65 UNITS PER NET HECTARE .
3. RESIDENTIAL 7.2 73 UNITS PER NET HECTARE
B. COMMERCIAL - BASED ON THE ZONING BYLAW 1300:
1. COMMERCIAL | - BASED ON THE MINIMUM LOT AREA OF NOT LESS) :
THAN 220 SQUARE METERS. .
2. COMMERCIAL 2 - BASED ON MAXIMUM DENSITY OF 75 UNITS PER *
NET HECTARE.
TOTAL AREAS:
1. RESIDENTIAL 4 0.094 HECTARES X 30 UNITS = 2 UNITS
2. RESIDENTIAL 7.1 0.330 HECTARES X 65 UNITS = 21 UNITS
3. RESIDENTIAL 7.2 . 0.854 HECTARES X 73 UNITS = 62 UNITS ;
4. COMMERCIAL 1 1.073 HECTARES/ 0.022 UNITS = 48 UNITS
5. COMMERCIAL 2 1.403 HECTARES X 75 UNITS = 105 UNITS
TOTAL 2 238 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS.
PROPOSED PIPE 600 mm PVC
EXISTING PIPES 18" CONCRETE
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $63,000.
ASSIST FACTOR (60%) OF $63,000 = $37,800.
$63,000. - $37,800. = $25,200. / 238 UNITS = $105.88 PER UNIT
Page 8 : .
. tote Sheett
CALCULATION DATA FOR STORM DRAIN
AREA 9 WHITE BIRCH ROAD FROM MCDONALD PARK ROAD TO END
A. RESIDENTIAL - BASED ON OFFICIAL COMMUNITY PLAN:
1. RESIDENTIAL 5 38 UNITS PER NET HECTARE .
2. RESIDENTIAL 9 75 UNITS PER NET HECTARE
: B. INSTITUTIONAL - BASED ON THE ZONING BYLAW 1300: ;
BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN 2000 SQUARE METERS. 7
TOTAL AREAS:
1. RESIDENTIAL 5 0.443 HECTARES X 38 UNITS = 17 UNITS
2. RESIDENTIAL 9 0.217 HECTARES X 75 UNITS = 16 UNITS
3. INSTITUTIONAL 2.105 HECTARES / 0.2 HECTARES = Jl UNITS
TOTAL = 44 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY PLAN
PROJECTIONS
PROPOSED PIPES 250mm PVC '
300mm PVC
EXISTING PIPES 6"AC
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $47,000. -
ASSIST FACTOR ( 60%) OF $47,000. = $28,200.
$47,000. - $28,200. = $18,800. / 44 UNITS = $427.27 PER UNIT
Page 9 Lo
ee Sheet
CALCULATION DATA FOR STORM DRAIN |
AREA 10 HARBOUR ROAD FROM RESTHAVEN DRIVE TO TSEHUM ROAD
A. COMMERCIAL - BASED ON THE ZONING BYLAW 1300: .
1. COMMERCIAL 5 - BASED ON THE MINIMUM LOT AREA OF NOT LESS THAN
600 SQUARE METERS AND NOT MORE THAN 1800 SQUARE METERS. ~
. 2. COMMERCIAL 5 - BASED ON THE MINIMUM LOT AREA OF
NOT LESS THAN 1000 SQUARE METERS.
B. HARBOUR ROAD MARINE - BASED ON OFFICIAL COMMUNITY PLAN: a
1. HRM 38 UNITS PER NET HECTARE
TOTAL AREAS:
1. COMMERCIAL 5 0.12] HECTARES /0.06 HECTARES = 2 UNITS
2. COMMERCIAL § 0.224 HECTARES /0.1 HECTARES) = 2 UNITS
3. HRM 1.150 HECTARES X 38 UNITS = 44 UNITS
TOTAL = 48 UNITS
PIPE HISTORY:
REASON STORM DRAIN UPGRADING FOR OFFICIAL COMMUNITY, PLAN
PROJECTIONS.
PROPOSED PIPES 300mm PYC
EXISTING PIPES 8"AC
1997 ESTIMATED CONSTRUCTION COST OF STORM DRAIN UPGRADING - $15,000.
ASSIST FACTOR ( 60%) OF $15,000 = $9,000.
$15,000. - $9,000. = $6,000. / 48 UNITS = $125.00 PER UNIT
Page 10 :
ee _ Schedule 'E"
TABLE NO. (D) - Parks and Public Open spaces ( See Schedule "E" for breakdown)
Column A Column B . Column C
. - Total Unit Cost
Area No. of Units .
Commercial Sub Area 1 611 units $245.00 .
All Residential Multi Family
low, medium and high
densit
Residential - Based on Official Community Plan: ;
1. Residential 5 40 units per hectare
2. Residential 6 50 units per hectare '
3. Residential 7.1 65 units per hectare
4. Residential 8 75 units per hectare
5.Residential 9 75 units per hectare
6.Residential 10 75 units per hectare
7. Commercial Sub-Commercial 75 units per hectare
TOTAL AREAS (Within the OCP not already developed as a condo)
Residential 5 2.32 hectares times 40 units = 92 units
Residential 6 .27 hectares times 50 units = 13 units
Residential 7.1 .24 hectares times 65 units = 15 units
Residential 8 .80 hectares times 75 units = 60 units
Residential 9 .60 hectares times 75 units = 51 units
Commercial Sub-area 1 4.80 hectares times 75 units = 360 units
Total 611 units
Waterfront improvements including both Capital Improvements and land acquisition of
property for a linear walkway, park improvements and other capital expenditures as
required for amenities . $1,000,000.00
Less Assist factor of (85%) $ 850,000.00
$1,000,000.00 - $850,000.00 = $150,000.00 divided by 611= $245.00 per unit