| single detached charge | $9,196 per unit in infill areas; $12,376 (Area 2) and $15,538 (Area 3) per unit in upland areas (Schedule A1, effective 1994 March 1) | Schedule "A1" row 5 and note (b); Schedule "A" row 5 and note (b) |
| apartment charge | $9,196 per unit (infill areas; Schedule A1, effective 1994 March 1) | Schedule "A1" row 5 and note (b); Schedule "A" row 5 and note (b) |
| non residential charge | $9,196 per 186 m² (approx. 2,000 ft²) of gross floor area or portion (infill areas; Schedule A1, effective 1994 March 1) | Schedule "A1" row 5 and note (b); Schedule "A" row 5 and note (b) |
| services covered | Highway facilities (water, drainage, neighbourhood/community highways, underground wiring) and public open spaces (Ambleside Waterfront, major/local parks). | Schedule "A" column headings |
| exemptions | Exempt: tax-exempt buildings; <4 self-contained dwelling units with no other use; work ≤ $50,000; no new capital cost burden; prior DCC paid; registered land use contract. | s. 3; s. 4; s. 7 |
| payment timing | At subdivision approval or building permit issuance. | s. 2 |
scout note
DCC bylaw for water, drainage, highway facilities and open space, charged by area at subdivision or building permit. Consolidation through amendment effective 2024-11-25.