Building permits — Fundy Shores, New Brunswick

Do I need a building permit? What does it cost?

In the Rural community of Fundy Shores, New Brunswick, building permit rules are set by By-Law C-4-2026: Building By-Law, verified 2026-10-18. Permit required for: Construction work, demolition work, and change of use affecting occupancy classifications. Permit fees: Building permit: $25 plus $5 per $1,000 of estimated construction cost; demolition permit: $25; doubled for unauthorized work after order. Administered by: building inspector.

By-Law C-4-2026: Building By-Law adopted bylaw
permit required for Construction work, demolition work, and change of use affecting occupancy classifications. s. 2(a)(i), s. 2(b)
exemptions Accessory buildings ≤55 m2 not for overnight accommodation; construction-site buildings; buildings ≤58.06 m2 for overnight accommodation; temporary buildings ≤28 days. s. 3(a)(i)-(iv)
fee basis Building permit: $25 plus $5 per $1,000 of estimated construction cost; demolition permit: $25; doubled for unauthorized work after order. s. 12(a)-(c)
authority building inspector s. 8(b), s. 13, s. 14
scout note

Fundy Shores Building By-Law (C-4-2026) under the Building Code Administration Act; read third time February 4, 2026. Sets construction and inspection standards for the rural community.

Machine-readable: building-permits.json · Official website: https://www.fundyshores.ca/ · Last verified 2026-10-18 · Building permits across New Brunswick · Building permits in other municipalities