Township of Huron-Kinloss
2012-41
Consolidated
Building By-Law
The amending by-laws have been combined with the original
by-law for convenience only. This consolidation is not a legal
document. Certified copies of the original by-laws should be
consulted for interpretations and applications of the by-laws
on this subject.
The by-law numbers referenced in this consolidation refer to
the by-laws that amended the principal by-law number
2012-41
By-Law No.
Date
Amendment
2019-16
February 19, 2019
Schedules A, B, C, D
Amended
Office Consolidation
1.0
CITATION AND DEFINITIONS
1.1
Short Title
This by-law may be cited as the "Building By-law"
1.2
Definitions
In this by-law;
a) "Act" means the Building Code Act, S.O. 1992, c.23, as amended;
b) "As constructed plans" means as constructed plans as defined in the Building Code, as
amended;
c) "Architect" means a holder of a license, a certificate of practice, or a temporary license
under the Architect's Act as defined by the Building Code, as amended;
d) "Building" means a building as defined in the Act;
e) "Building Code, as amended" means regulations made under Section 34 of the Act;
f)
"Chief Building Official" means the Chief Building Official appointed by the by-law of the
Corporation of the Township of Huron-Kinloss for the purpose of enforcement of the Act;
g) "Complete" means a building permit application in accordance with Article 2.4.1.1.A of
the Building Code, as amended submitted with all required approvals appended in order
to comply with the building permit timelines as noted in Article 2.4.1.1.B of the Building
Code, as amended;
h) "Corporation" mean the Corporation of the Township of Huron-Kinloss;
i)
"Demolish" means demolish as defined in the Building Code, as amended;
j)
"Farm Building" means a farm building as defined in the Building Code, as amended,
k) "Final Occupancy" means when all outstanding items on a partial Occupancy including
grading have been completed;
l) "Owner" means the registered owner of the land and includes a lessee, mortgagee in
possession and the person in charge of the property, acting as the authorized agent of
the owner;
m) "Partial Occupancy" means a permit issued to allow occupancy of a building prior to its
completion in accordance with Article 1.3.3.1.or 1.3.3.2, Division C of the Building Code,
as amended;
n) "Permit" means written permission or written authorization from the Chief Building
Official to perform work regulated by this by-law and the Act, or the change the use of a
building or part of a building or parts thereof or, in the case of an occupancy permit, to
occupy a building or part of a building or parts thereof;
o) "Plumbing" means plumbing as defined in Section 1(1) of the Act;
p) "Residential construction site" means any construction site in respect of which a building
permit has been issued for the construction of a new building consisting of a single
dwelling unit where such evacuation is within 2 m. of another occupied dwelling unit
except where the site is within a registered plan of subdivision which subdivision is being
developed for the first time;
q) "Sewage System" means a sewage system as defined in Section 1(1) of the
Regulations;
r)
Other terms which may be used in the by-law and which are defined in the Building
Code Ac, 1992, including "change certificate"; "construct"; "demolish"; "director"; "final
certificate"; "inspector"; "Minister"; "municipality"; "officer"; "planning board"; "plans
review certificate"; "principal authority"; "registered code agency'; and "regulations".
2.0
PERMITS
2.1
Classes of Permits (Ontario Building Code Act, Section 7(a))
Classes of permits required for any stage of construction, demolition, change of use,
occupancy of a partially complete building, conditional permits and other classes as set
forth in Schedule "A" appended to forming part of this by-law.
2.2
Application for Permit (Ontario Building Code Act, Section 7(b))
2.2.1 To obtain a permit an applicant shall file a "complete" application in writing on forms
regulated by the Chief Building Official.
2.2.2 Every application for a permit shall be submitted to the Chief Building Official, and
contain the following information:
(a)
Where application is made for a Construction Permit under Subsection 8(1) of
the Act, the application shall:
i.
Use the provincial application form, "Application for a Permit to Construct
or Demolish";
ii.
Include plans, specifications, forms, documents, and other information as
may be required by Clause 1.3.1.3.(5)(e), Division C of the Building Code,
as amended and as prescribed in this by-law for the work to be covered
by the permit;
iii.
Include the proposed or existing occupancy of all parts of the building;
and
iv.
Include the required fees as prescribed by Building Fees By-Law as
amended.
(b)
Where application is made for a Demolition Permit under Subsection 8(1) of the
Act, the application shall:
i.
Use the provincial application form, Application for a Permit to Construct
or Demolish";
ii.
Include plans, specifications, forms, documents, and other information as
may be required by Clause 1.3.1.3.(5)(e) and 1.3.1.1.(3), Division C of the
Building Code, as amended and as prescribed in this by-law for the work
to be covered by the permit;
iii.
Include the existing occupancy of all parts of the building; and
iv.
Include the required fees as prescribed by the Building Fees By-Law as
amended.
(c)
Where application is made for a Conditional Permit under Subsection 8(3) of the
Act, the application shall:
i.
Use the provincial application form, Application for a Permit to Construct
or Demolish";
ii.
Include plans, specifications, forms, documents, and other information as
may be required by Clause 1.3.1.3.(5)(e) of the Building Code, as
amended and as prescribed in this by-law for the work to be covered by
the permit;
iii.
Include the proposed or existing occupancy of all parts of the building;
iv.
Include the required fees as prescribed by the Building Fees By-Law as
amended;
v.
State the reasons why the applicant believes that unreasonable delays in
construction would occur if a conditional permit is not granted;
vi.
State the necessary approvals, which must be obtained in respect of the
proposed building and the time in which such approvals will be obtained;
vii.
Include an agreement in writing by the applicant and such other person
as the Chief Building Official determines with the Corporation dealing with
the matters required pursuant to Section 8(3)(c) of the Building Code Act;
and
viii.
State the time in which plans and specifications of the complete building
will be filed with the Chief Building Official.
(d)
Where application is made for a Change of Use permit issued under Subsection
10(1) of the Act, the application shall be submitted to the Chief Building Official
and shall:
i.
Use the provincial application form, Application for a Permit to Construct
or Demolish";
ii.
Describe the building in which the occupancy is to be changed, by a
description that will readily identify and locate the building;
iii.
Identify and describe as required by the Chief Building Official, the current
and proposed occupancies of the building or part of the building for which
the application is being made;
iv.
Include, as may be required by the Chief Building Official, plans and
specifications which show the current and proposed occupancy of all
parts of the building and which contain sufficient information to establish
compliance with the requirements of the Building Code, as amended,
including floor plans, details of walls, ceiling and roof assemblies
identifying required fire resistance ratings and load bearing capacities and
details of the existing sewage system, if any;
v.
Include the required fees as prescribed by the Building Fees By-Law as
amended;
vi.
State the name, address and telephone number of the owner; and
vii.
Be signed by the owner or his or her authorized agent who shall certify
the truth of the contents of the application
(e)
Where application is made for a Plumbing Permit under Subsection (8)(1) of the
Act, the application shall:
i.
Use the provincial application form, Application for a Permit to Construct
or Demolish";
ii.
Include the required fees as prescribed by the Building Fees By-Law as
amended;
iii.
Include such other information, methods and specification concerning the
complete project as the Chief Building Official may require.
(f)
Every application for a Sewage Permit shall be submitted to the Chief Building
Official and contain the following information:
i.
Use the provincial application form, Application for a Permit to Construct
or Demolish";
ii.
Include plans, specifications, forms, documents, and other information as
may be required by Clause 1.3.1.3.(5)(e), Division C of the Building Code,
as amended and as prescribed in this by-law for the work to be covered
by the permit;
iii.
Include the required fees as prescribed by Building Fees By-Law as
amended;
iv.
A site evaluation, which shall include all of the following items, unless
otherwise specified by the Chief Building Official:
a) The date the evaluation was done;
b) Name, address, telephone number and signature of the person who
prepared the evaluation;
c) A scaled map of the site showing:
a. The legal description, lot size, property dimensions, existing
rights-of-way, easements or municipal corridors;
b. The location and clearance of items listed in Article 8.2.1.5 and
8.2.1.6. of the Building Code, as amended;
c. The location of the proposed sewage system;
d. The location of any unsuitable, disturbed or compacted areas;
e. Proposed access routes for system maintenance;
f. Depth of bedrock;
g. Depth to zones of soil saturation
h. Soil properties, including soil permeability; and
i. Soil conditions, including potential of flooding
(g)
Every application for a Partial Occupancy Permit shall be submitted to the Chief
Building Official and contain the following information:
i. Use the prescribed form;
ii. Include plans, specifications, forms, documents, and other information as
may be required by Article 1.3.3.1.or 1.3.3.2, Division C of the Building
Code, as amended and as prescribed in this by-law for the work to be
covered by the permit;
iii. Include a statement indicating the expected occupancy dates, and the
portions of the building to be occupied; and
iv. Include the required fees as prescribed by Building Fees By-Law as
amended.
2.3
Revision to Permit
2.3.1 Every person who makes revision(s) shall notify the Chief Building Official and shall
submit the following information:
Where under Subsection 8(12) of the Act, notification is given for a material change to
the plans, specifications, documents or other information on the basis of which a permit
was issued, the owner or authorized agent shall:
a) Use the prescribed form;
b) Submit revised plans and specifications illustrating the changes and any supporting
documentation as may be requested by the Chief Building Official; and
c) Remit the additional fee to the Chief Building Official where applicable.
2.4
Plans and specifications (Ontario Building Code Act, Section 7(b))
2.4.1 Sufficient information shall be submitted with each application for a permit to enable the
Chief Building Official to determine whether or not the proposed construction, demolition,
change of use, etc. will conform with the Act, the Building Code as amended and any
other applicable law.
2.4.2 Each application shall, unless otherwise specified by the Chief Building Official, be
accompanied by two complete sets of the plans and specifications required under this
by-law.
2.4.3 Plans shall be drawn to scale on the paper or other durable material, shall be legible
and, without limiting the generality of the foregoing, shall include such working drawings
as set out in Schedule "C" to this By-law unless otherwise specified by the Chief Building
Official.
2.4.4 Site plans shall be referenced to an up-to-date survey and, when required by the Chief
Building Official to demonstrate compliance with the Act, the Building Code, as amended
or other applicable law, a copy of the survey shall be submitted to the Chief Building
Official. Site Plans shall show:
a) Lot Size and the dimension of property lines and setbacks to any existing or
proposed buildings;
b) Existing and finished ground levels or grades;
c) Existing rights-of-way, easements, municipal services and fencing; and
d) Proposed fire access routes and existing fire hydrant locations.
2.4.5 The granting of a permit, the review of the drawing and specifications or inspections
made by the Chief Building Official or an inspector shall not in any way relieve the owner
of the building from full responsibility for carrying out the work or having the work carried
out in accordance with the requirements of this by-law, the Act and the Building Code, as
amended, including ensuring that the occupancy of the building, or any part thereof, is in
accordance with the terms of this by-law and the Building Code, as amended.
2.4.6 The Chief Building Official may require that a set of plans of a building or any class of
buildings as constructed be filed with the Chief Building Official on completion of the
construction under such conditions as may be prescribed in the Ontario Building Code
Act, Section 7(g), as amended.
2.4.7 The Chief Building Official may deem an application for permit to have been abandoned
and cancelled six months after the date of filing, unless such application is being
seriously proceeded with.
2.5
Authorization of Equivalents (Alternative Solutions)
2.5.1 Where an application for a permit contains materials, systems or building design for
which authorization under Section 9 of the Act is required the applicant shall submit:
a. Supporting documentation demonstrating the proposed materials,
systems or building design will provide the required level of performance
according to Article 1.2.1.1. Division A of the Building Code, as amended.
b. Supporting documentation and test methods providing information
according to Section 2.1. Division C of the Building Code, as amended.
2.5.2 The Chief Building Official may accept or reject any proposed equivalents or may
impose conditions or limitations on their use.
2.5.3 Equivalents which are accepted under this Section shall be applicable only to the
location to which the approval was given and are not transferable to any other
construction permit.
3.0
FEES (Ontario Building Code Act, Section 7(c))
3.1
Fees for a required permit shall be as prescribed bythe Building Fees By-Law as
amended, known as the "Building Fees By-law" passed by the Council of the Township
of Huron-Kinloss.
3.2
Where application is made for a conditional permit, the conditional application fee shall
be payable at application for permit and in addition to this fee prior to issuance of the
conditional permit the applicable construction permit fee shall be paid for the complete
project.
3.3
Where the fees payable in respect of an application issued under Subsection 8(1) or 8(3)
of the Act are based on a floor area, floor area shall mean the total floor space of all
storeys below the first storey (except the unfinished floor area below the first storey in
single family dwellings) measured as the horizontal area between the exterior walls of
the building.
3.4
With respect to an application for a change of use permit issued under Subsection 10(1)
of the Act the change of use permit fee shall be utilized when no construction is
proposed or required, When construction is proposed or required and will result in a
change of use the appropriate construction permit fee shall be utilized.
3.5
The Chief Building Official shall determine permit fees not described or included in the
Building Fees By-law, as amended.
3.6
Refund of Fees (Ontario Building Code Act, Section (d))
3.6.1 In the case of withdrawal of an application or the abandonment of all or a portion of the
work or the non-commencement of any project, the Chief Building Official shall
determine the amount of paid permit fees that may be refunded to the applicant, if any,
in accordance with Schedule "B" attached to and forming part of this by-law.
3.6.2 Notwithstanding Schedule "B", no refund shall be made in an amount less then $10.00
3.6.3 No refund shall be made unless a written application for such refund is made by the
Owner or his agent and unless the permit is returned for cancellation.
4.0
NOTICE REQUIREMENTS FOR INSPECTIONS (Ontario Building Code Act, Section
7(e))
4.1
The permit holder shall notify the Chief Building Official of each stage of construction
listed in Schedule "D". In addition, the permit holder shall provide the notice of
completion as prescribed in Section 11 of the Act, or where occupancy is required prior
to completion, notice of inspection to ensure that the requirements of Section 11 of the
Act and Subsection 1.3.3., Division C of the Building Code, as amended are complied
with.
4.2
A notice pursuant to this part of the by-law is not effective until notice is actually received
by the Chief Building Official
__________________
4.3
Upon receipt of proper notice, the inspector shall undertake a site inspection of the
building to which the notices relate in accordance with the time periods stated in Article
1.3.5.3., Division C of the Building Code, as amended and Section 11 of the Act.
5.0
TRANSFER OF PERMIT (Ontario Building Code Act, Section 7(h))
5.1
Permits are non-transferable without written consent of the Chief Building Official and a
Transfer of Permit being issued.
6.0
PRESCRIBED FORMS (Ontario Building Code Act, Section 7(f))
6.1
The forms prescribed for use shall be registered by the Province of Ontario and the
Chief Building Official.
7.0
PENALTY CLAUSE
7.1
Section 36 of the Building Code Act provides that a person is guilty of an offence under
the Building Code Act if a person contravenes the Building Code Act, the regulations or
this by-law.
8.0
REPEAL CLAUSE
8.1
By-law 99-19 as amended for the Corporation of the Township of Huron-Kinloss is
hereby repealed.
9.0
This By-Law shall come into full force and effect upon its final passage.
10.0 This By-Law may be cited as "The Township of Huron-Kinloss Building By-Law".
READ a FIRST, SECOND and THIRD TIME and FINALLY PASSED this 16th
day of April, 2012.
Original signed by Mitch Twolan
Original signed by Sonya Watson
Mayor
Clerk
Schedule 'A' to By-Law No. 2019-16
Class of Permits
1. Building Permits (Building Code Act, Section 8(1)) may be issued for all types of
construction governed by the Building Code, as amended and may include plumbing,
farm building, change of use, sewage system, heating ventilating and air conditioning
systems, moving a building a building, etc.
2. Partial Building Permit (Building Code Act, Section 8(1)) may be issued when, in order to
expedite work, approval of a portion of the building or project is desired prior to the
issuance of a permit for the complete building or project and where the construction
authorized by the permit complies with the Act, Building Code, as amended and other
applicable law. Application shall be made, fees paid and complete plans and
specifications covering the portion of the work for which the immediate approval is
desired shall be filed with the Chief Building Official. Where a permit is issued for part of
a building or project, such permit shall not be construed to authorize construction beyond
the plans for which approval was given nor that approval will necessarily be granted for
the entire building or project.
3. Conditional permits may be issued by the Chief Building Official in accordance with
Section 2.2.2.(c) of this by-law.
4. Change of Use Permit may be issued where a change in use of a building or part of a
building would result in an increase in hazard as determined under Section 1.3.1.4 (1),
Division C of the Building Code, as amended even though no construction is proposed.
5. Sewage System Permit is required for all Classes of Systems as defined in Section
8.1.2.1.(a),(b),(c),(d) and (e), Classification of systems in the regulation.
6. Sign Permits may be issued in respect of the structural requirements for signs as
described in Section 3.15, Division B of the Building Code, as amended.
7. Special Building Permit may be issued for all types of construction governed by the
Building Code, as amended and may include plumbing, farm buildings, sewage system,
signs, change of use and heating, ventilating and air conditioning systems at the
discretion of the Chief Building Official where construction or change of use has
commenced prior to the issuance of the permit.
Schedule 'B' to By-Law No. 2019-16
Building Permits and Fees
Refunds
Pursuant to Section 3.5 of the Building By-law, the fees that may be refunded shall be a
percentage of the fees payable under Section 3.1, calculated by the Chief Building Official as
follows:
a) 80% if the application is received but no processing or review of plans submitted has
commenced;
b) 50% if the application is received, plans reviewed and permit issued;
c) 10% additional deduction for each field inspection that has been performed; and
d) No refund shall be in the amount less than $50.00.
Interpretation
The following explanatory notes are to be observed in the calculation of permit fees:
- Floor area of the proposed work is to be measured to the outer face of exterior walls and
to the centerline of any party walls or demising walls (excluding residential garages).
- In the case of interior alterations of renovations, area of proposed work is the actual
space receiving the work (e.g. tenant space).
- Mechanical penthouses and floors, mezzanines, lofts, habitable attics, and interior
balconies are to be included in all floor area calculations.
- Except for interconnected floor spaces, deductions are made for opening within the floor
area (e.g. stairs, elevators, escalators, shafts, ducts, etc.)
- Unfinished basements for single detached dwellings (including semis, duplexes, and
townhouses, etc.) are not included in floor area.
- Attached garages and fireplaces are in the permit fee for single detached dwellings,
attached dwellings, semis, duplexes and townhouses.
- Where interior alterations and renovations require relocation of sprinkler heads or fire
alarm components, no addition charge is applicable.
- Ceilings are included in both new shell and finished (partitioned) buildings. The Service
Index for ceilings applies only when alterations occur in existing buildings. Minor
alterations to existing ceilings to accommodate lighting or HVAC improvements are not
chargeable.
-
Where demolition of partitions or alteration to existing ceilings is part of an alteration or
renovation permit, no additional charge is applicable.
-
Corridors, lobbies, washrooms, lounges, etc. are to be included and classified according
to the major classification for the floor area on which they are located.
-
The occupancy categories in the Schedule correspond with the major occupancy
classification in the Ontario Building Code, as amended. For mixed occupancy floor
areas, the Service Index for each of the applicable occupancy categories may be used,
except where an occupancy category is less than 10% of the floor area.
SCHEDULE 'C' to By-Law No. 2019-16
Schedule of Documents, Drawings and Specifications
Required for Construction, Demolition and Change of Use
Permits
A minimum of 2 sets of the following types of drawings, specifications and documents at
a legible scale are required to be submitted in order for the various types of Building
Permit Applications listed to be considered a complete application pursuant to section
2.4 of the Building Code Act , 1992 as amended and the Building By-law. Depending
upon the nature, scope and scale of a project other additional supporting drawings,
specification and documents maybe be required to demonstrate Ontario Building Code
compliance at the discretion of the Chief Building Official.
Where required by the Chief Building Official the plans and specifications shall be
submitted in a digital PDF or ACAD format compatible with the municipality's software
system.
REQUIRED DOCUMENTATION
Where applicable the following supporting documentation shall accompany applications
for a permit unless otherwise waived by the Chief Building Official:
a) Proof/Confirmation of Approval of all Applicable Law pursuant to Section G
of an application to Construct or Demolish
b) Owner / engineer/architect's letter of commitment and general review form Real
Property Report (Survey Plan) prepared by an Ontario Land Surveyor,
c) Driveway access permit approved by the authority having jurisdiction as
may be applicable,
d) Where required approval by the Ministry of the Environment for the
design and construction of a private sewage disposal and water supply systems,
e) Commitment of Undertaking that a termite control program shall be undertaken
to resist termite infestation of the building.
f) OMAFRA Nutrient Management Strategy and/or Plan Sign-Off Form.
g) Heritage Permit pursuant to the Ontario Heritage Act.
h) Confirmation of Compliance with OMAFRA Minimum Distance Separation 1 or 2
Optional:
i.
Zoning Compliance Certificate / Pre-consultation Letter
ii.
Approved Lot Grading and Drainage Plan
iii.
Geotechnical Soils Report.
iv.
Structural Engineering Report.
REQUIRED DRAWINGS BY TYPICAL PROJECT TYPE
1. Demolitions
a) Description of the structural design characteristics of the building and a
method of demolition prepared by a Professional Engineer where
deemed necessary by the Chief Building Official
b) Site Grading and Rehabilitation Plan
c) Confirmation that arrangements have been made with the proper
authorities for the cutting off and plugging of all water, sewer, gas,
electric, and telephone or other utilities and services.
d) Proof of liability insurance coverage to not less than $1,000,000.00, that
relates to the proposed demolition,
e) Where a building is designated under the Heritage Act, approval of the
Township Council to de-designate the building and permit demolition.
f) Where the building is located within an area of known termite infestation,
the owner/contractor's undertaking confirming that all waste wood and
cellulose materials shall be destroyed or disposed at a provincially
licensed waste disposal site.
2. Private Septic Disposal System
a)
Site Evaluation Report prepared by a Professional Engineer
including soil permeability, and soil conditions, including the
potential for flooding
b)
Plot / Site Plan and or Approved Lot Grading and Drainage Plan
c)
Septic system design and drawings (prepared by a Professional
Engineer where the lot is less than 2 acres in area and / or located
within a plan of subdivision.)
d)
In the case of Class 4 sewage systems, a copy of the required annual
service and maintenance agreement.
e)
Where applicable, a construction permit from the Saugeen Valley
Conservation Authority or Maitland Valley Conservation Authority.
3. Residential Decks and Porches
a)
Plot / Site Plan
b)
Foundation Plan
c)
Framing plan and guard details
d)
Where applicable, either confirmation that the final lot grading and
drainage is in accordance with the overall subdivision lot grading and
drainage plans or a waiver signed by the homebuilder who posted the
lot grading and drainage deposit permitting the construction.
4. Residential Accessory Buildings (Less Than 50 m2 in building area)
a)
Plot / Site Plan
b)
Real Property Report (Survey Plan) prepared by an Ontario Land Surveyor if
building is to be within a distance 1.25 times that of the required setback from
the property boundary.
c)
Foundation plan / Eng. Floor Slab
d)
Floor Plans
e)
Floor and Roof Framing Plans
f)
Building Elevations
g)
Building Section
h)
Where applicable, either confirmation that the final lot grading and
drainage is in accordance with the overall subdivision lot grading
and drainage plans or a waiver signed by the homebuilder who
posted the lot grading and drainage deposit permitting the
construction
5. Residential Accessory Buildings (Greater Than 50 m2 in building area)
a) Plot / Site Plan
b) Real Property Report (Survey Plan) prepared by an Ontario Land
Surveyor if building is to be within a distance 1.25 times that of the
required setback from the property boundary.
c) Where applicable, either confirmation that the final lot grading and
drainage is in accordance with the overall subdivision lot grading
and drainage plans or a waiver signed by the home builder who
posted the lot grading and drainage deposit permitting the
construction
d) The following architectural plans
i.
Foundation plan
ii.
Floor Plans
iii.
Floor and Roof Framing Plans
iv.
Building Elevations
v.
Building Section
6. Residential Additions and Renovations Permits
a)
Plot / Site Plan
b)
The following architectural plans prepared by a Provincially
Registered Designer or the home owner
vi. Foundation plan
vii. Floor Plans
viii. Floor and Roof Framing Plans
ix.
Building Elevations
x.
Building Section
xi.
Private Septic System Evaluation where applicable
7. New Residential Houses and Semi Detached
a)
Plot / Site Plan
b)
Approved Lot Grading and Drainage Plan
c)
Tarion Home Warranty Program Registration Form
d)
Where applicable a complete Private Septic System Permit Application
e)
The following architectural plans prepared by a Provincially
Registered Designer or a Homebuilder registered with the Tarion
Warranty Corporation of the homeowner
xii.Foundation plan
xiii.Floor Plans
xiv. Floor and Roof Framing Plans
xv. Building Elevations
xvi.Building Section
vi. Energy Efficiency Design Summary Matrix
8. New Residential Townhouses, Triplex, Quad-plex
a)
Approved Site Development Plan and Agreement
b)
The following architectural plans prepared by a Provincially Registered
Designer or a Home builder registered with the Tarion Home
Warranty Program
i.
Foundation Plan
ii.
Floor Plans
iii.
Floor and Roof Framing Plans
iv.
Building Elevations
v.
Building Section
vi. Energy Efficiency Design Summary Matrix
9. New Residential Apartment Buildings
a)
Approved Site Development Plan and Agreement
b)
Professional Field Review Commitment forms from the Design
Professionals
c)
The following architectural plans prepared and stamped by an
Architect and Professional Engineer by a Provincially Registered
Designer
a) Foundation Plan
a) Floor Plans
b) Floor and Roof Structural Plans
c) Building Elevations
d) Building Section
e) Energy Efficiency Design Summary Matrix
f) Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Automatic Sprinkler and Standpipe Drawings
iii.
Fire Alarm system
10. Small Commercial and Industrial Interior Renovations (Part 9 Buildings)
The following architectural plans prepared and stamped by a Provincially
Registered Designer or the Building Owner
a)
Floor Layout and Framing Plans
b)
Building Section
c)
Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Automatic Sprinkler and Standpipe Drawings
iii. A complete Private Septic System Permit Application
11. Small Commercial and Industrial Additions (Part 9 Buildings)
a) Approved Site Development Plan and Agreement
b) The following architectural plans prepared and stamped by a
Provincially Registered Designer or the Building Owner
i.
Foundation Plan
ii.
Floor Plans
iii. Roof Plans
iv. Building Elevations
v.
Building Section
c) Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Energy Efficiency Design Summary Matrix
iii. Automatic Sprinkler and Standpipe Drawings
iv. Fire Alarm system
v.
Structural Drawings stamped by a Professional Engineer
vi. Complete Private Septic System Permit Application
12. New Small Commercial and Industrial Buildings (Part 9 Buildings)
a)
Approved Site Development Plan and Agreement
b)
The following architectural plans
i. Foundation Plan
ii. Floor Plans
iii. Floor and Roof Structural Plans
iv. Building Elevations
v. Building Section
c) Where applicable
i. HVCA, Electrical and Plumbing System Drawings
ii. Energy Efficiency Design Summary Matrix
iii. Automatic Sprinkler and Standpipe Drawings
iv. Fire Alarm system
v. Complete Private Septic System Permit Application
13. Small Assembly / Institutional Building Additions and Renovations (Part 3
Buildings)
a)
The following architectural plans prepared and stamped by an
Architect and Professional Engineer
ii.
Foundation Plan
iii. Floor Plans
iv. Floor and Roof Structural Plans
v.
Building Elevations
vi. Building Section
b) Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Automatic Sprinkler and Standpipe Drawings
iii.
Fire Alarm system
iv.
Professional Field Review Commitment forms from the Design
Professionals
v.
Complete Private Septic System Permit Application
14. New Small Assembly / Institutional Buildings (Part 3 Buildings)
a)
Approved Site Development Plan and Agreement
b)
Professional Field Review Commitment forms from the Design
Professionals
c)
The following architectural plans prepared and stamped by an
Architect and Professional Engineer
i. Foundation Plan
ii. Floor Plans
iii. Floor and Roof Structural Plans
iv. Building Elevations
v. Building Section
d)
Where applicable
i. HVCA, Electrical and Plumbing System Drawings
ii. Energy Efficiency Design Summary Matrix
iii. Automatic Sprinkler and Standpipe Drawings
iv. Fire Alarm system
15. Industrial / Commercial / Institutional Buildings Additions and Renovations (Part 3
Buildings)
a)
Approved Site Development Plan and Agreement
b)
Professional Field Review Commitment forms from the Design Professionals
c)
The following architectural plans prepared and stamped by an Architect
and Professional Engineer
i.
Foundation Plan
ii.
Floor Plans
iii.
Floor and Roof Structural Plans
iv.
Building Elevations
v.
Building Section
d) Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Energy Efficiency Design Summary Matrix
iii.
Automatic Sprinkler and Standpipe Drawings
iv.
Fire Alarm system
16. New Industrial / Commercial / Institutional Buildings ( Part 3 Buildings)
a)
Approved Site Development Plan and Agreement
b)
Professional Field Review Commitment forms from the Design Professionals
c)
The following architectural plans prepared and stamped by an Architect
and Professional Engineer by a Provincially Registered Designer
i.
Foundation Plan
ii.
Floor Plans
iii.
Floor and Roof Structural Plans
iv.
Building Elevations
v.
Building Section
d)
Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Energy Efficiency Design Summary Matrix
ii.
Automatic Sprinkler and Standpipe Drawings
iii.
Fire Alarm system
17. Specially Designated Structures
a) The following plans prepared and stamped by a Professional Engineer by
a Provincially Registered Designer
i.
Site Plan
ii.
Foundation Plan
iii.
Floor and Roof Plans
iv.
Floor and Roof Structural Plans
v.
Sections
18. Use of an Equivalent / Alternated Solution
a)
The following plans and reports prepared and stamped by a
Professional Engineer:
i.
Description of the proposed equivalent / Alternate solution
ii.
Demonstration of Compliance with SA-1 Objectives and Functional
Statements Matrix
iii.
Supporting documentation (past performance, tests and other evaluations)
19. Change of Use Permit
a) Description of the proposed change of use
b) Reduction in performance matrix
c) Description of Compensating measures or alternate measures
d) The following plans and where applicable prepared and stamped by a
Professional Engineer
i.
Foundation Plan
ii.
Floor Plans
iii.
Floor and Roof Structural Plans
iv.
Building Elevations
v.
Building Section
e). Where applicable
i.
HVCA, Electrical and Plumbing System Drawings
ii.
Energy Design Summary
iii.
Automatic Sprinkler and Standpipe Drawings
iv.
Fire Alarm system
DRAWING COMPLETENESS
Unless otherwise specified by the Chief Building Official the following Information shall
be shown on plans or working drawings that accompany applications for permits.
Depending upon the nature, scope and scale of a project other additional information
may be required to demonstrate Ontario Building Code compliance at the discretion of
the Chief Building Official.
1.
The Plot / Site Plan shall show:
a)
The location, use, height and dimensions of any existing and
proposed buildings including front, side, and rear yard dimensions
and relationships to adjoining property lines, condominium
corporation lines and buildings,
b)
Existing and proposed elevation contours of the building site and
adjacent properties,
c)
Relation of buildings and finished grade to existing elevations and
storm water drainage control plan on site where applicable,
d)
All existing and proposed site services, parking layout, retaining
walls, swimming pools accessory buildings and any other such
physical additions necessary to the site,
e)
Parking and GFA calculations, location and size of typical parking,
loading and accessible spaces including aisle widths serving the
parking spaces.
f)
Site statistics that may be relevant to what is being proposed, such
as but not limited to: number of residential units, gross floor area,
amenity area, proposed height etc.
g)
Elevation drawings clearly indicating compliance with height
regulations including various calculations such as average grade
calculations where required.
2.
The Architectural Drawings shall show:
a)
Designers and/or Firms Building Code Identification Number
including statement of responsibility for the building design,
b)
Architects/designer's Ontario Building Code data matrix,
c)
Foundation plans and grade details,
d)
Each floor plan with exact dimensions of the layout of all proposed
areas and their use,
e)
All wall thicknesses and type of construction, window and door
openings and schedules elevator, sections and details of all walls,
stairs and exits, firewalls, fire separations, shaft and duct openings
sand other related pertinent information,
f)
Building elevations, cross sections and wall sections showing all
floor-to-floor heights, materials and thickness etc.
g)
Spatial separation table and calculations,
h)
Energy Efficiency Design Summary Matrix
3.
Structural Drawings shall show:
a)
All foundation, floor, roof and wall structural elements
indicting
sizes shapes and proper location and all dead and live design loads
and condition of loading,
b)
All reinforced concrete work indicting thickness and strength of
concrete, size spacing minimum cover and type of reinforcing steel,
c)
All lintel locations and sizes,
d)
Where applicable Engineered Roof and Floor Truss drawings
4.
The Mechanical Electrical and Plumbing Plans shall show:
a)
For buildings defined in Part 9 of the Building Code, provisions for
heating, ventilation and air conditioning, electrical and plumbing
systems may be shown and indicated on the architectural drawings,
b)
For Buildings defined in Part 3 of the Building Code, a separate set
of drawings for heating ventilation air conditioning, electrical and
plumbing systems,
c)
The location of all fire protection equipment such as early warning,
detection and suppression systems,
d)
Energy Efficiency Design Summary Matrix (ASHREA 90.1),
e)
Where the primary heat source is provided by heat/hot water
combination unit, a solar or geothermal system the all design
drawings and documents must be prepared by a Professional
Engineer
Optional:
i.
Heat loss / heat gain calculations,
ii.
HVAC duct layout and sizing calculations,
iii.
Plumbing DWV and water supply piping layout drawings
5.
The Private Sewage system plans shall show:
a)
A site evaluation conducted by a Professional Engineer identifying
the soil percolation time and anticipated high ground water level
elevation,
b)
The private sewage system design and construction drawing
including all components and a calculation of the total daily design
sanitary sewage flow of the system prepared and stamped by a
Professional Engineer,
c)
The location, use, height and dimensions of any existing and
proposed buildings including front, side, and rear yard dimensions
and relationships to adjoining property lines, condominium
corporation lines and buildings,
d)
Existing and proposed elevation contours of the building site and
adjacent properties,
e)
Relation of buildings and finished grade to existing elevations and
storm water drainage control plan on site where applicable,
f)
All existing and proposed site services, parking layout, retaining
walls, swimming pools accessory buildings and any other such
physical additions necessary to the site
Such other approvals as may be required by the Chief Building Official to demonstrate
compliance with applicable law.
Schedule 'D'
Stage of Construction Requiring Notification
The person to whom a permit under Section 8 of the Act is issued shall notify the Chief
Building Official of:
a) Readiness to construct footings,
b) Substantial completion of footings and foundations prior to
commencement of backfilling,
c) Substantial completion of structural framing and ductwork and piping
for heating and air-conditioning systems, if the building is within the
scope of Part 9, Division B,
d) Substantial completion of structural framing and roughing-in of
heating, ventilation, air-conditioning and air-contaminant extraction
equipment, if the building is not a building to which Clause (c)
applies,
e) Substantial completion of insulation, vapor barriers and air barriers,
f) Substantial completion of all required fire separations and closures
and all fire protection systems including standpipe, sprinkler, fire
alarm and emergency lighting systems,
g) Substantial completion of fire access routes,
h) Readiness for inspection and testing of:
i.
Building sewers and building drains,
ii.
Water service pipes,
iii.
Fire service mains,
iv.
Drainage systems and venting systems,
v.
The water distribution system, and
vi.
Plumbing fixtures and plumbing appliances.
i) Readiness for inspection of suction and gravity outlets, covers and
suction piping servicing outlets, of an outdoor pool described in
Clause 1.3.1.1.(1)(j) of Division A, a public pool or a public spa,
j) Substantial completion of the circulation/recirculation system of an
outdoor pool described in Clause 1.3.1.1.(1)(j) of Division A, a
public pool or public spa and substantial completion of the pool
before it is filled with water,
k) Readiness to construct the sewage system,
l) Substantial completion of the installation of the sewage system
before the commencement of backfilling,
m) Substantial completion of installation of plumbing not located in a
structure, before the commencement of backfilling,
n) Completion of construction and installation of components required
to permit the issuance of an occupancy permit under Sentence
1.3.3.1.(2), Division C or to permit occupancy under Sentence
1.3.3.2.(1), Division C if the building or part of the building to be
occupied is not fully completed,
o) Completion of a building or part thereof for which an occupancy
permit is required under Article 1.3.3.4, Division C, and
p) Substantial completion of site grading.