| permit required for | Construction, demolition or change of use of a building or part thereof. | s. 2.0 |
| fee basis | Schedule 'A' sets fees by class; Permit to Construct: 2022 - $15.96 per $1,000 of construction value for the first $1,000,000 in construction value, with a minimum charge of $100; plus $10.00 per plumbing fixture, with a minimum charge for plumbing of $100.00; 40% of yearly calculated rate per $1,000 of construction value for amounts between $1,000,000 and$6,000,000 of construction value; 25% of yearly calculated rate per $1,000 of construction value for amounts in excess of $6,000,000. | Schedule "A" |
| fees location | by-law 2018-039 | s. 8.4 |
| authority | Chief Building Official and inspectors | s. 1.1 |
scout note
Under Building Code Act 1992 s.3/s.7; appoints Chief Building Official, requires permits for construction/demolition/change of use, sets classes of permit, fees, and inspection requirements. Consolidated to 2026.