| permit required for | Building Permit under Act s.8(1); Demolition Permit; Change of Use Permit for increased hazard; Occupancy Permit where building occupied. | s. 830.3.1.1, s. 830.3.1.2, s. 830.3.1.4, s. 830.3.1.5 |
| fee basis | Permit Fee = SI x A (SI = Service Index multiplier; A = total floor area in ft2); minimum fee $150.00. | Schedule "A", s. 1.1 and s. 2 |
| authority | Chief Building Official and Inspectors | s. 830.2.7, s. 830.2.16 |
scout note
Orillia's Building chapter: classes of permits (building, demolition, conditional, change of use, occupancy), application/plan requirements, alternative solutions, and fees (Schedule A). Repealed/replaced by By-law 2023-024; last amended by By-law 2025-108 (Dec 8, 2025), current to December 2025.