| permit required for | Construction governed by the Building Code, including structural, plumbing, sewage, HVAC, demolition, and change of use; sewage and plumbing permits for systems/alterations. | Schedule "B" |
| exemptions | Demolition of a building located on a farm pursuant to Div. C Part 1 clause 1.3.1.1.(1)(a). | Schedule "B", item 6 |
| fee basis | Based on floor area or cost of valuation of proposed work; set out in Fees and Charges By-Law. | s. 5.1, 5.3, 5.6 |
| fees location | Fees and Charges By-Law | s. 5.1 |
| authority | Chief Building Official (CBO) and inspectors | s. 1.2.6, s. 7.1 |
| fine range | Up to $5,000 additional fee for commencing without permit; fees doubled for work before permit. | s. 5.9, s. 14.2 |
scout note
Municipality of South Huron's building by-law respecting construction, demolition, change of use and inspection under the Building Code Act, 1992; appoints the Chief Building Official and sets permit requirements.