Building permits — Strong, Ontario

Do I need a building permit? What does it cost?

In the Township of Strong, Ontario, building permit rules are set by Building By-law 2024-017, Schedule B — Permit Fee Schedule and 1 other bylaw, verified 2026-09-25. Permit required for: Construction of a building, including erection, installation, extension, material alteration or repair; demolition; change of use; conditional permits. Exemptions: Re-shingling a roof; storage shed ancillary to principal building, <=15 m2 (161 sq ft), one storey, not attached, no plumbing. Permit fees: $100.00 + $15.00 per Thousand; construction cost guidelines cost per square foot of floor area.

Building By-law 2024-017, Schedule B — Permit Fee Schedule adopted bylaw
exemptions Re-shingling a roof; storage shed ancillary to principal building, <=15 m2 (161 sq ft), one storey, not attached, no plumbing. No permit is required for re-shingling a roof; No permit is required for a shed intended for storage purposes only
fee basis $100.00 + $15.00 per Thousand; construction cost guidelines cost per square foot of floor area. Cost Guidelines $100.00 + $15.00 per Thousand; CONSTRUCTION COST GUIDELINES - cost per square foot of floor area
authority Chief Building Official Chief Building Official
fine range FEES ARE DOUBLED FEES ARE DOUBLED
scout note

Schedule B to Strong's Building By-law 2024-017: permit fee cost guidelines (per-$1,000 of value and per-square-foot rates by building type), re-inspection/transfer/compliance-letter fees, annual permit-maintenance fees; fees doubled if construction starts without a permit.

Building By-law No. 2024-017 adopted bylaw
permit required for Construction of a building, including erection, installation, extension, material alteration or repair; demolition; change of use; conditional permits. Schedule "A"
exemptions Re-shingling a roof; storage shed ancillary to principal building, not more than 15 m2, one storey, detached, no plumbing. Schedule "B"
fee basis $100.00 + $15.00 per thousand; construction cost guidelines per square foot; fees doubled if construction started without permit. Schedule "B"
authority Chief Building Official; Building Inspector s. 2.1.6, s. 2.1.12
scout note

Township of Strong's Building By-law under the Building Code Act, 1992: requires permits for construction, demolition, change of use and conditional permits; defines Chief Building Official/Inspector roles and inspections. Permits administered jointly with 6 area municipalities via the Joint Building Committee (Burk's Falls, Joly, Machar, Ryerson, South River, Sundridge).

Machine-readable: building-permits.json · Official website: http://www.strongtownship.com/ · Last verified 2026-09-25 · Building permits across Ontario · Building permits in other municipalities