Town of Albion Development Review Regulation
page 1
Town of Albion
Regulation Pertaining to Subdivision and Commercial
Development Review
Revised 2/16
Part 1: Administrative Provisions
Part 2: Procedural Guidelines
Part 3: Submission Requirements
Part 1: Administrative Provisions
1.
Authority
This Regulation is adopted pursuant to the instruction and authority of the planning board
in Article IV, Section 3.B of the Town of Albion Land Use Ordinance.
2.
Purpose
The purpose of this Regulation is to establish a clear set of administrative practices and
standards for the review of development applications under the aforementioned ordinance.
Development applications include both subdivision applications and application for review
of major commercial developments.
3.
Administration
The Town of Albion Planning Board is responsible for administering this regulation.
Amendment
The Town of Albion Planning Board may amend this Regulation only after holding a
public hearing. The planning board shall provide at least fourteen (14) days' notice of the
public hearing. The planning board shall amend this regulation only upon majority vote.
5.
Effective Date
The effective date of this regulation shall be the date of adoption by the planning board.
The same shall apply to any amendment adopted except that the amendment shall not apply
to any application already submitted for review by the board.
Town of Albion Development Review Regulation
page 2
Part 2: Procedural Guidelines
1.
Introduction
This Part provides detailed procedures by which development applications are to be
received and reviewed by the planning board.
2.
Pre-applications (Sketch Plan)
A.
Purpose
The purpose of the pre-application process is for the prospective applicant to
present general information regarding the proposal to the planning board for
comment before investing substantial time and money developing the application.
This meeting provides the applicant information on procedures and requirements
for submitting an application. The applicant may also use this opportunity to ask
questions and schedule a site inspection with the Code Enforcement Officer.
B.
Procedure
The prospective applicant shall contact the Chair or Secretary of the planning board
to request to be placed on the board's agenda at least seven (7) days before the next
regular scheduled meeting. The pre-application will be placed on the next agenda,
provided that the agenda has not already been posted.
Prior to or at the meeting, the prospective applicant will provide an inked sketch
plan of the proposed development indicating the proposed layout of roads and lot
lines, anticipated location of proposed structures, and locations of existing features
such as roads, easements, wetlands, and water bodies.
The planning board, at the review meeting, will provide guidance to the prospective
applicant as follows:
-
A determination of the scope of the application, for example whether it
contains roads or other improvements which may require detailed
information, or whether the proposed development may need permits or
review by state or federal agencies and the proposed timeline for approval;
-
A determination of whether additional submittals, for example traffic study,
erosion control plan, or analysis of special historic or ecological resources,
should be included;
-
An opinion concerning any waivers to submission requirements to be
proposed by the applicant.
C.
Rights not vested
Town of Albion Development Review Regulation
page 3
The pre-application meeting shall not be considered the initiation of the review
process for the purposes of bringing the plan under protection of Title 1, MRSA, §
302.
3.
Submitting an Application
A.
Establishment of a File
After the pre-application meeting, the planning board shall establish a file for the
proposed development. All information and submittals regarding the development
shall be maintained in the file.
B.
Code Enforcement Inspection of the Site
The Code Enforcement Officer will arrange with the applicant to perform an on-site
inspection of the proposed site prior to the submission of the application to the
planning board. The CEO will inform the planning board of the site inspection.
Members of the planning board may accompany the CEO if the date and time of the
inspection is posted at the town office.
The Code Enforcement Officer will verify information provided on the sketch plan
and answer any questions the developer may have with regard to the site. The CEO
will suggest a contour interval for the plan. The suggested contour interval will be
forwarded to the planning board.
C.
Application Forms and Submittal
An applicant will submit seven (7) copies of application materials as required in
Part 3 of this regulation. The application must be accompanied by the Town's
Application Form, available from the Code Enforcement Officer or Town website,
and the Application Fee as calculated using the Town's Fee Schedule.
The applicant will submit the application directly to the Town Clerk or Town Office
Staff. The Town Clerk or Town Office Staff will issue the applicant a dated receipt
showing that the application has been received and fee paid, and will notify the
Secretary of the planning board of his (her) action.
4.
Development Review Process
A.
Review for Completeness
Within thirty (30) days after receiving notification of the application, the planning
board will meet to determine whether the application is complete. The applicant is
not required to attend this meeting, but is advised that questions regarding adequacy
of the contents may come up in the course of the meeting.
Town of Albion Development Review Regulation
page 4
The board will notify the applicant in writing that either the application is complete
or, if the application is incomplete, the specific material the applicant should submit
to complete the application.
1.
The planning board will act on any waivers requested for items not included.
2.
The planning board will not begin the review of the application on its merits
until it determines that the application is complete.
3.
If the application is incomplete, the applicant shall submit the required
material to the board before it commences review. After the board receives
the materials from the applicant, it has thirty (30) additional days to review
this material before notifying the applicant whether the application is
complete.
4.
The board may notify the applicant of additional studies needed to
supplement the application or of the need to hire additional expertise for
review.
B.
Professional Review and Assistance
1.
At the time it deems the application to be complete, the planning board may
identify portions of the development proposal that, due to their complexity,
require an expertise in review that is not ordinarily available to the board.
Examples include traffic analysis, noise, light, or radio frequency
propagation, or archeological analysis. The planning board is authorized to
retain impartial professional assistance to advise it on these elements of the
application.
2.
The cost of retaining professional assistance shall be borne by the applicant.
The cost shall be estimated prior to commencement of the assistance. The
applicant may set aside an amount equal to the estimated cost in advance, to
be retained by the Town in an escrow account, or may choose to reimburse
the Town directly for costs incurred. In either case, no application will
receive final approval until the costs of professional assistance are paid.
3.
The scope of services of the expert retained for this purpose shall be strictly
limited to study and report on the application in hand.
C.
Scheduling and Notification
1.
Upon determining that the application is complete, the planning board will
place it on the agenda for the next regularly-scheduled meeting of the board.
2.
Abutters shall be notified by certified mail that an application has been filed.
The notification shall identify the property to be developed, include a brief
description of the type of development proposed, and provide the date, time,
and place at which the board review will take place. Notification to abutters
shall be mailed no less than fourteen (14) days before the scheduled date of
review.
Town of Albion Development Review Regulation
page 5
3.
Notice of the date, time, and place of the pending review shall be published
at least two (2) times in the local newspaper. The date of the first publication
must be at least fourteen (14) days before the scheduled date of review.
4.
Notice shall also be provided to the Board of Selectmen, to the Fire Chief,
and to the Road Commissioner, with an invitation to provide comments on
the application.
5.
If any portion of the property to be developed crosses town boundaries,
notice shall be sent to the clerk and planning board of the affected town,
providing the date, time, and place of review. The board shall offer to
conduct a joint review with the planning board of the affected town.
6.
A copy of the application shall be available for public viewing during
regular hours of the town office.
D.
Review Meeting Procedure
1.
Board review of the application shall be conducted in open, public session.
The conduct of the meeting shall be as follows:
-
The applicant or his/her representative is required to attend. He or she
shall give an oral presentation concerning the application;
-
Members of the public who wish to may speak for, against, or
concerning the application. Written comment will also be accepted.
The applicant may respond to questions if permitted by the Chairman of
the board;
-
As provided in Article IV, section 3.F of the Ordinance, the board will
act on any request by the applicant to modify performance standards;
-
The board will engage in deliberations concerning the application. The
applicant and members of the public may participate during this period
only at the discretion of the Chairman of the board.
-
The board will make findings of fact and conclusions of law and shall
vote to approve or deny the application.
2.
The board is not required to complete review of the application in one
meeting. The board may defer any portion of the decision-making process
to a subsequent meeting. The vote to approve or deny the application will
take place no more than thirty-five (35) days from the date of the initial
meeting for board review, unless a delay is mutually agreed upon by the
applicant and the board.
3.
The board shall, within sixty (60) days of determining it has received a
complete application or within any other time limit that is otherwise
mutually agreed to by the applicant and the board, issue a written decision to
Town of Albion Development Review Regulation
page 6
either approve the application; approve the application with conditions; or
deny the application.
The board shall base its decision on the following:
For subdivisions, compliance with the review criteria contained in Title
30-A MRSA § 4404;
For commercial development, compliance with the criteria and standards
of Articles V, VI, and VII of the Land Use Ordinance.
4.
Provision for Two-stage Review
A.
Conditional Preliminary Approval
The planning board is authorized to grant approval of a development application
conditional on provision by the applicant of additional information. The form of
information is generally, but not exclusively, of two types:
Engineering information, such as final road or stormwater design or the
survey and setting of lot boundary markers;
Administrative information, such as pending permit approvals from State or
Federal regulatory authorities.
The board will state in writing as part of its conditional approval the elements that
must be added to the application package in order to receive final approval.
B.
Final Approval and Signing
The applicant shall provide the elements required as part of the conditional approval
within ninety (90) days of the date of conditional approval, or a date otherwise
mutually agreed upon.
Final approval shall be scheduled for the first regularly-scheduled meeting after the
Code Enforcement Officer has certified that the elements required as part of the
conditional approval have been submitted. The public is not required to be notified
except through the standard posting of the agenda.
The applicant shall submit for signature at least two mylar copies and one paper
copy of the final plan. One paper copy and one mylar copy will be retained by the
Town of Albion.
Planning board members in attendance at the final review shall sign the approved
plan if they find as follows:
All changes, modifications and amendments required by the board have
been placed on the Plan.
Any permits required from Maine DEP, Maine DOT, US Army Corps of
Engineers, or other state or federal agency are in hand.
All waivers approved by the board are listed on the Plan.
Town of Albion Development Review Regulation
page 7
Any conditions imposed by the board that have not been met at the time of
final approval are listed on the Plan.
The Plan contains a signature block and is titled as the "Final Plan."
Costs for professional assistance, if any, are paid in full.
5.
Amendments and Revisions
A.
Amendments to a Subdivision Plan
The planning board shall review any amendments or revisions to an approved
subdivision plan. If the amendment or revision involves the creation of new lots or
units, or a significant change in road alignment or design, the notice and meeting
requirements for a new subdivision shall be followed.
B.
Amendments to a Commercial Development Plan
The planning board shall review any change to a commercial development plan
which involves any of the following conditions. The board may follow notice and
meeting requirements if it determines the change to be significant.
An increase in the number or footprint area of buildings on the site;
An increase in the area of impervious surface on the site;
A change of use of the property to a use which will generate a higher traffic
demand; or
A change in location or design of any infrastructure that will be used by the
general public, including but not limited to parking areas, streetlights, roads,
or sidewalks.
Town of Albion Development Review Regulation
page 8
Part 3: Submission Requirements
1.
Application Package
All applications shall be covered by a Town of Albion Application Form.
All applications shall be submitted with sufficient fees, as calculated under the Town of
Albion Fee Schedule. No application shall be processed until fees are paid.
All applications shall include sufficient and legible copies for review. These shall include:
Seven (7) copies of all required submissions, including plan drawings reduced to fit on
11 x 17 pages.
One (1) copy of all plan drawings at a size of 24 x 36 inches. Subdivision plats shall
be drawn at a scale of no smaller than one hundred feet (100') to the inch. Design
plans for roads and other infrastructure shall include plans, profiles, and cross-
sections, as appropriate.
For the final plan only, the page for planning board signature shall be 24 x 36 inches
in size and shall be presented on a reproducible, stable based transparent "mylar"
original. Two (2) mylar copies shall be provided, one to be retained by the Town and
one to be filed in the Kennebec County Registry of Deeds. One paper copy shall be
provided, to be retained by the Town.
2.
Submittals Required for all Applications
A.
Application Form
A completed application form with all information included, shall be submitted. The
form shall be signed by the applicant and by the owner of the property, if different.
B.
Plan Drawing
The plan drawing shall contain the listed elements. In order to maintain clarity, the
drawing may consist of two or more pages, individually numbered and labelled with
the name of the development.
i)
Proposed name of the development and municipality(ies) in which it is located,
together with assessor's map and lot number(s) and street address if available.
ii)
Name and address of the landowner, applicant, his/her agent, and the person(s)
who prepared the application.
iii)
Contour lines at the interval specified, showing elevations in relation to Mean
Sea Level. (Most common contour interval is five feet (5').
iv)
The date the Plan was prepared, magnetic north point, declination, and graphic
map scale.
Town of Albion Development Review Regulation
page 9
v)
The boundary lines of the tract and any proposed new lot lines with
approximate dimensions and lot areas, including any proposed open space or
land to be dedicated for public use.
vi)
The boundaries of all water bodies, wetlands, significant vernal pools or unique
natural areas as identified on Beginning with Habitat maps or known historic
or archeological sites located on the tract.
vii) The location of any shoreland zoning or land use district boundaries affecting
the tract.
viii) If any portion of the development is in a flood prone area, the boundaries of
any flood hazard areas with the 100 year flood elevation delineated.
ix)
The approximate location and dimensions of any structures proposed to be
erected in the development, including but not limited to buildings, signs,
lighting structures, and auxiliary and accessory structures.
x)
The approximate alignment and dimensions (profile and cross-section) of any
road(s), access points, commercial driveways, or parking areas proposed to be
constructed or improved to serve the development.
xi)
The location, dimensions, and description of any buffers or landscaping
proposed for the development.
xii) The size, type, and location of any water lines, sewer lines, hydrants, fire
ponds, drainage facilities, electric or telephone lines and other utilities
designed to service the subdivision.
xiii) The boundaries of any farmland within the tract.
xiv) A location map insert showing an outline of the development area at a scale
sufficient to show adjacent roads, water bodies, municipal boundaries and
other significant features in the vicinity.
C.
Attachments to the Application
The following materials will be included with the application package.
i)
Verification of applicant's right, title, or interest in the property by means of a
deed, lease, signed purchase and sales agreement or similar document.
ii)
A copy of the deed for the parent tract together with copies of all covenants or
deed restrictions, easements, rights of way, or other encumbrances currently
affecting the property.
Town of Albion Development Review Regulation
page 10
iii)
A copy of any lease terms, covenants, or deed restrictions proposed to cover all
or part of the development.
iv)
Indication of the type of sewage disposal to be used in the development. When
sewage disposal is to be accomplished by subsurface sewage disposal system,
test pit analyses, prepared by a Licensed Site Evaluator shall be provided. A
map showing the location of all test pits on the site shall be submitted. (Form
HHE 200 - Page 2 of 3)
v)
Indication of the type of water supply to be used in the development. When
water is to be supplied by a public water supply, certification that the water
supply has been designed by a registered professional engineer. When water is
to be supplied by private wells, evidence of adequate ground water supply and
quality, in the form of test wells or a written statement from either a well driller
or a geologist familiar with the area.
vi)
A description of fire protection measures to be available. Proposed sources of
water must be reviewed by the fire chief prior to submittal of the application.
vii) The names and addresses of owners of record of all property abutting the
parcel to be developed, including any property directly across an existing
public street.
viii) A medium intensity soil survey covering the development. When the medium
intensity soil survey shows soils which are generally unsuitable for the uses
proposed, the applicant shall provide a high intensity soil survey or a report by
a registered soil scientist or registered professional engineer experienced in
geotechnics, indicating the suitability of soil conditions for those uses.
ix)
An estimate of the costs required to construct the infrastructure required for the
development, including but not limited to public and private roads, sidewalks,
parking areas, utility installations, and lighting fixtures, together with a
proposed mechanism for financing the construction.
3.
Conditional Requirements for Certain Applications
A.
Due to their size or potential impact on resources or facilities in the Town of
Albion, developments with certain aspects must submit additional application
information:
i)
If the development is a subdivision, include an affidavit that no timber
harvesting has occurred on the tract within the preceding five (5) years, or if it
has, that it has not been conducted in violation of rules adopted pursuant to 12
M.R.S.A. §8869(14). The affidavit may be signed by a licensed forester or an
agent of the Maine Bureau of Forestry.
Town of Albion Development Review Regulation
page 11
ii)
If the development is a subdivision of ten lots/units or more, or a commercial
building of greater than 2,000 square feet, include an estimate of the traffic
volume to be produced.
iii)
If the development will generate traffic of more than 400 vehicles per day,
include a traffic impact analysis, prepared by a Registered Professional
Engineer with experience in traffic modeling. The Traffic Impact Analysis
shall indicate recommended improvements to maintain the desired level of
service on affected streets. If the development is large enough to require a
Traffic Movement Permit from the Maine DOT, the applicant may substitute
data and analysis necessary for that permit.
iv)
If the development involves any grading or construction, include a grading
plan and an erosion control plan meeting the requirements of Maine Erosion
and Sedimentation Control BMP's (DEP, March 2003 or as revised.)
v)
If the development will create more than 10,000 square feet of impervious
surface, include a Stormwater Management Plan prepared by a registered
professional engineer.
vi)
If the development is within the direct watershed of Lovejoy Pond, evidence
that it will comply with the standard for phosphorous export in the ordinance,
consistent with Phosphorous Control in Lake Watersheds: A Technical Guide
to Evaluating New Development (DEP, May, 1992 or as revised.)
vii) If the development proposes the establishment of an association for
maintenance of a private road, central sewer system or water supply, open
space or parkland, include proposed articles of incorporation and bylaws for
the association.
viii) If the development will result in the extraction of more than 2,000 gallons per
day of water or if it is located over a mapped aquifer, include a groundwater
impact analysis, prepared by a groundwater hydrologist.
ix)
If a commercial development will utilize or handle hazardous or toxic
chemicals in the course of its operation, include a description of the chemicals
to be used and a Spill Prevention, Control, and Cleanup Plan in accordance
with 38 MRSA §1318-C.
B.
Additional submission requirements may apply for specific forms of development,
e.g. groundwater extraction, wireless telecommunication towers. Consult
respective sections of Article VII of the ordinance for requirements.
C.
Nothing in this regulation shall be construed as limiting the authority of the
planning board to require the applicant to perform additional studies or hire a
consultant to review any or all portions of an application. The cost to perform
Town of Albion Development Review Regulation
page 12
additional studies or hire a consultant shall be borne by the applicant in accordance
with Article IV, section 1.C(3) of the ordinance.
4.
Final Plan Submission
The final plan intended for signature by the planning board shall include on its face
the following items:
i)
The plan must show the name and signature, registration number, and seal
of the surveyor or engineer who prepared it.
ii)
All waivers to performance standards approved by the board shall be listed
on the Plan.
iii)
Any conditions imposed by the board that have not been met at the time of
final approval shall be listed on the Plan.
iv)
If any roads within the development are to be privately-owned, the
following sentence must appear: "[Name of Roads] shall remain private, to
be maintained by [Name of developer or homeowners' association], and
shall not be offered for acceptance or maintained by the Town until they
meet applicable public road design standards."
v)
A signature block shall appear with the words "Approved, Town of Albion
Planning Board" together with seven signature lines and a date line.