STATE OF MAINE
DEPARTMENT OF ENVIRONMENTAL PROTECTION
17 STATE HOUSE STATION
AUGUSTA, MAINE 04333-0017
DEPARTMENT ORDER
IN THE MATTER OF
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE )
ORDER #48-2025
) CONDITIONAL APPROVAL
Pursuant to the provisions of 38 M.R.S. §§ 435-448, the Mandatory Shoreland Zoning Act
("Act"), and the Maine Department of Environmental Protection's Guidelines for Municipal
Shoreland Zoning Ordinances, 06-096 C.M.R. ch. 1000 (amended January 26, 2015)
("Guidelines"), the Department of Environmental Protection has considered the request for
approval of the Town of Athens Shoreland Zoning Ordinance (Ordinance), as amended on July
15, 2025, and FINDS THE FOLLOWING FACTS:
1.
The Act requires municipalities to establish zoning controls in areas within 250 feet of
the normal high-water line of great ponds and rivers; within 250 feet of the upland edge
of freshwater and coastal wetlands; and within 75 feet of the normal high-water line of
streams. Such zoning standards must be consistent with or no less restrictive than those in
the Guidelines. 38 M.R.S. §§435 & 438-A.
2.
The Act specifies that before a locally adopted shoreland zoning ordinance, or
amendment to that ordinance, is effective, it must be approved by the Commissioner of
the Department of Environmental Protection ("Commissioner"). The Commissioner may
approve, approve with conditions, or deny the ordinance or amendment. If denied, or
approved with conditions, such action must be preceded by notice to the municipality. If
the Commissioner fails to act within 45 days of receipt of the ordinance or amendment,
then the ordinance or amendment is automatically approved. 38 M.R.S. § 438-A.
3.
On August 12, 2025, the Town of Athens submitted the following amendments to its
Ordinance as adopted on July 15, 2025 to the Department for review:
A.
The Town of Athens has chosen to pursue Option 2 for timber harvesting,1 joint
administration and regulation of all forestry activities within the municipality
between the Bureau of Forestry (also commonly referred to as the Maine Forest
Service) and the municipality by adopting the Option 2 minimum requirements of
the Chapter 1000 Guidelines.
1 Title 38, section 438-A provides that, notwithstanding other provisions in the Mandatory Shoreland Zoning Act, the
regulation of timber harvesting and timber harvesting activities in shoreland areas must be in accordance with section
438-B and rules adopted by the Bureau of Forestry. Section 438-B establishes three options from which each
municipality may choose. The options are further identified in a Note Relating to Timber Harvesting Standards, located
in the Guidelines between Ch. 1000, § 15(N) and § 15(O-1).
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
B.
The amendments make extensive revisions throughout the Ordinance, including
minor corrections and clarifications, as well as substantive changes in standards
including, but not limited to, expansion of nonconforming structures and
associated definitions.
4.
The Department's review of the Ordinance has revealed the following significant
deficiencies:
A. Section 4 Effective Date and Repeal of Formerly Adopted Ordinance, fails to identify
the effective date.
B. Section 9.A Districts and Zoning Map, fails to accurately represent applicable
Shoreland Zoning districts identified on the Shoreland Zoning map.
C. Section 12.C Non-conforming Structures, omits language for expansion standards.
D. Section 12.C.3 Contiguous Lots - Vacant of Partially Built, fails to identify the
applicable effective date.
E. Section 13.C Establishment of Districts, fails to accurately represent applicable
Shoreland Zoning districts identified on the Shoreland Zoning map.
F. Section 14 Table of Land Uses, fails to accurately represent applicable Shoreland
Zoning districts identified on the Shoreland Zoning map.
G. Section 15.B Principal and Accessory Structures, omits language on retaining walls.
H. Section 15. C Piers, Docks, Wharves, Bridges, and Other Structures and uses
Extending Over or Beyond the Normal High-Water Line of a Water Body or Within a
Wetland, omits the standard for pier, dock, or wharf quantity, permanent piers, and
the standards for shoreline stabilizations.
I. Section 15.E Individual Private Campsites, omits applicable standards for individual
private campsites.
J. Section 15.O Timber Harvesting, fails to accurately represent timber harvesting
standards.
K. Section 15.P Clearing of Vegetation for Development fails to accurately represent
vegetation removal standards.
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
L. Section 16.C Permit Application omits contractor requirements for working in the
shoreland zone.
M. Sections on Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal,
Exemptions to Clearing and Vegetation Removal Requirements, and Revegetation
Requirements, are missing from the document.
5.
On September 3, 2025, the Town of Athens was notified by the Department of the above
deficiencies, and the proposed conditional approval of the Ordinance.
BASED on the above Findings of Fact, the Commissioner makes the following CONCLUSION:
1.
The deficiencies noted in paragraph 4 above can be addressed by the Commissioner
approving the Ordinance with conditions. This will result in the Ordinance being
substantially consistent with the requirements of the Mandatory Shoreland Zoning Act,
38 M.R.S., Section 438-A, and the minimum Guidelines.
THEREFORE, the Commissioner APPROVES the Ordinance, as amended on July 15, 2025,
SUBJECT TO THE ATTACHED CONDITIONS:
1.
Section 4 Effective Date and Repeal of Formerly Adopted Ordinance, shall be amended
in part to add the highlighted language:
This Ordinance, which was adopted by the municipal legislative body on July 15,
2025, shall not be effective unless approved by the Commissioner of the
Department of Environmental Protection. A certified copy of the Ordinance,
attested and signed by the Municipal Clerk, shall be forwarded to the
Commissioner for approval. If the Commissioner fails to act on this Ordinance or
Ordinance Amendment, within forty-five (45) days of his/her receipt of the
Ordinance, or Ordinance Amendment, it shall be automatically approved.
2.
Section 9.A Districts and Zoning Map, shall be amended in part to remove the
strikethrough language:
9. Districts and Zoning Map
A. Official Shoreland Zoning Map. The areas to which this Ordinance is
applicable are hereby divided into the following districts as shown on the Official
Shoreland Zoning Map(s) which is (are) made a part of this Ordinance:
(1)
Resource Protection
(2)
Limited Residential
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(3)
Limited Commercial
(4) General Development
(5) Commercial Fisheries/Maritime Activities
(6)
Stream Protection
3.
Section 12.C Non-conforming Structures, shall be amended in part to include the
following language:
When it is necessary to remove vegetation within the water or wetland setback
area in order to relocate a structure, the Planning Board shall require replanting of
native vegetation to compensate for the destroyed vegetation in accordance with
Section 15(S). In addition, the area from which the relocated structure was
removed must be replanted with vegetation. Replanting shall be required as
follows:
(a) Trees removed in order to relocate a structure must be replanted with at least one
native tree, three (3) feet in height, for every tree removed. If more than five trees
are planted, no one species of tree shall make up more than 50% of the number of
trees planted. Replaced trees must be planted no further from the water or wetland
than the trees that were removed.
Other woody and herbaceous vegetation, and ground cover, that are removed or
destroyed in order to relocate a structure must be re-established. An area at least
the same size as the area where vegetation and/or ground cover was disturbed,
damaged, or removed must be reestablished within the setback area. The
vegetation and/or ground cover must consist of similar native vegetation and/or
ground cover that was disturbed, destroyed or removed.
(b) Where feasible, when a structure is relocated on a parcel the original location of
the structure shall be replanted with vegetation which may consist of grasses,
shrubs, trees, or a combination thereof.
If the reconstructed or replacement structure is less than the required setback it
shall not be any larger than the original structure, except as allowed pursuant to
Section 12(C)(1) above, as determined by the non-conforming footprint of the
reconstructed or replaced structure at its new location. If the total footprint of the
original structure can be relocated or reconstructed beyond the required setback
area, no portion of the relocated or reconstructed structure shall be replaced or
constructed at less than the setback requirement for a new structure. When it is
necessary to remove vegetation in order to replace or reconstruct a structure,
vegetation shall be replanted in accordance with Section 12(C)(3) above.
4.
Section 12.C.3 Contiguous Lots - Vacant of Partially Built, shall be amended in part to
remove the strikethrough language and add the highlighted language:
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
Contiguous Lots - Vacant of Partially Built: If two or more contiguous lots or
parcels are in single or joint ownership of record at the time of this Ordinance, if
any of these lots do not individually meet the dimensional requirements of this
Ordinance or subsequent amendments, and if one or more of the lots are vacant or
contain no principal structure the lots shall be combined to the extent necessary to
meet the dimensional requirements.
This provision shall not apply to 2 or more contiguous lots, at least one of which
is non-conforming, owned by the same person or persons on July 28, 1993 the
effective date of this Ordinance and recorded in the registry of deeds if the lot is
served by a public sewer or can accommodate a subsurface sewage disposal
system in conformance with the State of Maine Subsurface Wastewater Disposal
Rules; and
(a) Each lot contains at least 100 feet of shore frontage and at least 20,000 square
feet of lot area; or
(b) Any lots that do not meet the frontage and lot size requirements of Section
12(E)(3)(a) are reconfigured or combined so that each new lot contains at least
100 feet of shore frontage and 20,000 square feet of lot area.
5.
Section 13.C Establishment of Districts, shall be amended to remove the General
Development District.
6.
Section 14 Table of Land Uses, shall be amended to remove the General Development
District and Commercial Fisheries/Maritime Activities District.
7.
Section 15.B Principal and Accessory Structures, shall be amended in part to include the
following language:
Retaining walls that are not necessary for erosion control shall meet the structure
setback requirement, except for low retaining walls and associated fill provided
all of the following conditions are met:
(a) The site has been previously altered and an effective vegetated buffer does not
exist;
(b) The wall(s) is(are) at least 25 feet, horizontal distance, from the normal high-
water line of a water body, tributary stream, or upland edge of a wetland;
(c) The site where the retaining wall will be constructed is legally existing lawn or is
a site eroding from lack of naturally occurring vegetation, and which cannot be
stabilized with vegetative plantings;
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(d) The total height of the wall(s), in the aggregate, are no more than 24 inches;
(e) Retaining walls are located outside of the 100-year floodplain on rivers, streams,
coastal wetlands, and tributary streams, as designated on the Federal Emergency
Management Agency's (FEMA) Flood Insurance Rate Maps or Flood Hazard
Boundary Maps, or the flood of record, or in the absence of these, by soil types
identified as recent flood plain soils.
(f) The area behind the wall is revegetated with grass, shrubs, trees, or a combination
thereof, and no further structural development will occur within the setback area,
including patios and decks; and
(g) A vegetated buffer area is established within 25 feet, horizontal distance, of the
normal high-water line of a water body, tributary stream, or upland edge of a
wetland when a natural buffer area does not exist. The buffer area must meet the
following characteristics:
(i) The buffer must include shrubs and other woody and herbaceous vegetation.
Where natural ground cover is lacking the area must be supplemented with leaf
or bark mulch;
(ii) Vegetation plantings must be in quantities sufficient to retard erosion and
provide for effective infiltration of stormwater runoff;
(iii)
Only native species may be used to establish the buffer area;
(iv) A minimum buffer width of 15 feet, horizontal distance, is required,
measured perpendicularly to the normal high-water line or upland edge of a
wetland;
(v) A footpath not to exceed the standards in Section 15(P)(2)(a), may traverse the
buffer;
8.
Section 15.C Piers, Docks, Wharves, Bridges, and Other Structures and uses Extending
Over or Beyond the Normal High-Water Line of a Water Body or Within a Wetland, shall
be amended in part to include the following language:
No more than one pier, dock, wharf or similar structure extending or located
below the normal high-water line of a water body or within a wetland is allowed
on a single lot; except that when a single lot contains at least twice the minimum
shore frontage as specified in Section 15(A), a second structure may be allowed
and may remain as long as the lot is not further divided.
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
New permanent piers and docks on non-tidal waters shall not be permitted unless
it is clearly demonstrated to the Planning Board that a temporary pier or dock is
not feasible, and a permit has been obtained from the Department of
Environmental Protection, pursuant to the Natural Resources Protection Act.
Vegetation may be removed in excess of the standards in Section 15(P) of this
ordinance in order to conduct shoreline stabilization of an eroding shoreline,
provided that a permit is obtained from the Planning Board. Construction
equipment must access the shoreline by barge when feasible as determined by the
Planning Board.
(a) When necessary, the removal of trees and other vegetation to allow for
construction equipment access to the stabilization site via land must be limited to
no more than 12 feet in width. When the stabilization project is complete the
construction equipment accessway must be restored.
(b) Revegetation must occur in accordance with revegetation standards.
9.
Section 15.E Individual Private Campsites, shall be amended in part to include the
following language:
When an individual private campsite is proposed on a lot that contains another
principal use and/or structure, the lot must contain the minimum lot dimensional
requirements for the principal structure and/or use, and the individual private
campsite separately.
Only one recreational vehicle shall be allowed on a campsite.
10.
Section 15.O Timber Harvesting, will be amended to replace the current standards with
the updated Chapter 21 - Statewide Standards. Section 15.0 Timber Harvesting will be
amended to add the highlighted language:
Timber Harvesting - Statewide Standards Option 2 - please see Appendix A for
regulatory information.
11.
Section 15.P Clearing of Vegetation for Development shall be amended in part to remove
the strikethrough language and add the highlighted language:
(a) There shall be no cleared opening greater than 250 square feet in the forest
canopy (or other existing woody vegetation if a forested canopy is not present) as
measured from the outer limits of the tree or shrub crown. However, a single
footpath not to exceed ten (10) six (6) feet in width as measured between tree
trunks and/or shrub stems is permitted provided that a cleared line of sight
through the buffer strip is not created. Adjacent to a great pond classified GPA,
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
or river flowing to a great pond classified GOA, the width of the foot path shall be
limited to six (6) feet.
12.
Section 16.C Permit Application shall be amended in part to include the following
language:
When an excavation contractor will perform an activity that requires or results in
more than one (1) cubic yard of soil disturbance, the person responsible for
management of erosion and sedimentation control practices at the site must be
certified in erosion control practices by the Maine Department of Environmental
Protection. This person must be present at the site each day earthmoving activity
occurs for a duration that is sufficient to ensure that proper erosion and
sedimentation control practices are followed. This is required until erosion and
sedimentation control measures have been installed, which will either stay in
place permanently or stay in place until the area is sufficiently covered with
vegetation necessary to prevent soil erosion. The name and certification number
of the person who will oversee the activity causing or resulting in soil disturbance
shall be included on the permit application. This requirement does not apply to a
person or firm engaged in agriculture or timber harvesting if best management
practices for erosion and sedimentation control are used; and municipal, state and
federal employees engaged in projects associated with that employment.
13.
Section 17 Definitions shall be amended in part to remove the strikethrough language and
add the highlighted language:
Expansion of a structure - an increase in the floor area or volume footprint or
height of a structure, including all extensions such as, but not limited to attached:
decks, garages, porches and greenhouses.
14.
Section 17 Definitions shall be amended in part to include the following language:
Increase in nonconformity of a structure - any change in a structure or property
which causes further deviation from the dimensional standard(s) creating the
nonconformity such as, but not limited to, reduction in water body, tributary
stream or wetland setback distance, increase in lot coverage, or increase in height
of a structure. Property changes or structure expansions which either meet the
dimensional standard or which cause no further increase in the linear extent of
nonconformance of the existing structure shall not be considered to increase
nonconformity. For example, there is no increase in nonconformity with the
setback requirement for water bodies, wetlands, or tributary streams if the
expansion extends no further into the required setback area than does any portion
of the existing nonconforming structure. Hence, a structure may be expanded
laterally provided that the expansion extends no closer to the water body, tributary
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
stream, or wetland than the closest portion of the existing structure from that
water body, tributary stream, or wetland. Included in this allowance are
expansions which in-fill irregularly shaped structures.
Stream - a free-flowing body of water from the outlet of a great pond or the
confluence of two (2) perennial streams as depicted on the most recent , highest
resolution version of the national hydrography dataset available from the United
States Geological Survey on the website of the United States Geological Survey
or the national map to the point where the stream becomes a river or where the
stream meets the shoreland zone of another water body or wetland. When a
stream meets the shoreland zone of a water body or wetland and a channel forms
downstream of the water body or wetland as an outlet, that channel is also a
stream.
15.
The following sections shall be added as follows (added language in Italics):
Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal
(1) Hazard trees in the shoreland zone may be removed without a permit after
consultation with the Code Enforcement Officer if the following requirements are
met:
(a) Within the shoreline buffer, if the removal of a hazard tree results in a cleared
opening in the tree canopy greater than two hundred and fifty (250) square feet,
replacement with native tree species is required, unless there is new tree growth
already present. New tree growth must be as near as practicable to where the
hazard tree was removed and be at least two (2) inches in diameter, measured at
four and one half (4.5) feet above the ground level. If new growth is not present,
then replacement trees shall consist of native species and be at least four (4) feet
in height and be no less than two (2) inches in diameter. Stumps may not be
removed.
(b) Outside of the shoreline buffer, when the removal of hazard trees exceeds forty
(40) percent of the volume of trees four (4) inches or more in diameter, measured
at four and one half (4.5) feet above ground level in any ten (10) year period,
and/or results in cleared openings exceeding twenty-five (25) percent of the lot
area within the shoreland zone, or ten thousand (10,000) square feet, whichever
is greater, replacement with native tree species is required, unless there is new
tree growth already present. New tree growth must be as near as practicable to
where the hazard tree was removed and be at least two (2) inches in diameter,
measured at four and one half (4.5) feet above the ground level. If new growth is
not present, then replacement trees shall consist of native species and be at least
two (2) inches in diameter, measured at four and one half (4.5) feet above the
ground level.
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(c) The removal of standing dead trees, resulting from natural causes, is permissible
without the need for replanting or a permit, as long as the removal does not result
in the creation of new lawn areas, or other permanently cleared areas, and
stumps are not removed. For the purposes of this provision dead trees are those
trees that contain no foliage during the growing season.
(d) The Code Enforcement Officer may require the property owner to submit an
evaluation from a licensed forester or arborist before any hazard tree can be
removed within the shoreland zone.
(e) The Code Enforcement Officer may require more than a one-for-one replacement
for hazard trees removed that exceed eight (8) inches in diameter measured at
four and one half (4.5) feet above the ground level.
(2) Storm-damaged trees in the shoreland zone may be removed without a permit after
consultation with the Code Enforcement Officer if the following requirements are
met:
(a) Within the shoreline buffer, when the removal of storm-damaged trees results in a
cleared opening in the tree canopy greater than two hundred and fifty (250)
square feet, replanting is not required, but the area shall be required to naturally
revegetate, and the following requirements must be met:
(i) The area from which a storm-damaged tree is removed does not result in new
lawn areas, or other permanently cleared areas;
(ii) Stumps from the storm-damaged trees may not be removed;
(iii)Limbs damaged from a storm event may be pruned even if they extend beyond
the bottom one-third (1/3) of the tree; and
(iv) If after one growing season, no natural regeneration or regrowth is present,
replanting of native tree seedlings or saplings is required at a density of one
seedling per every eighty (80) square feet of lost canopy.
(b) Outside of the shoreline buffer, if the removal of storm damaged trees exceeds
40% of the volume of trees four (4) inches or more in diameter, measured at four
and one half (4.5) feet above the ground level in any ten (10) year period, or
results, in the aggregate, in cleared openings exceeding 25% of the lot area
within the shoreland zone or ten thousand (10,000) square feet, whichever is
greater, and no natural regeneration occurs within one growing season, then
native tree seedlings or saplings shall be replanted on a one-for-one basis.
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
Q. Exemptions to Clearing and Vegetation Removal Requirements
The following activities are exempt from the clearing and vegetation removal standards
set forth in Section 15(P), provided that all other applicable requirements of this chapter
are complied with, and the removal of vegetation is limited to that which is necessary:
(1) The removal of vegetation that occurs at least once every two (2) years for the
maintenance of legally existing areas that do not comply with the vegetation
standards in this chapter, such as but not limited to cleared openings in the canopy or
fields. Such areas shall not be enlarged, except as allowed by this section. If any of
these areas, due to lack of removal of vegetation every two (2) years, reverts back to
primarily woody vegetation, the requirements of Section 15(P) apply;
(2) The removal of vegetation from the location of allowed structures or allowed uses,
when the shoreline setback requirements of section 15(B) are not applicable;
(3) The removal of vegetation from the location of public swimming areas associated
with an allowed public recreational facility;
(4) The removal of vegetation associated with allowed agricultural uses, provided best
management practices are utilized, and provided all requirements of section 15(N)
are complied with.
(5) The removal of vegetation associated with brownfields or voluntary response action
program (VRAP) projects provided that the removal of vegetation is necessary for
remediation activities to clean-up contamination on a site in a general development
district, commercial fisheries and maritime activities district or other equivalent
zoning district approved by the Commissioner that is part of a state or federal
brownfields program or a voluntary response action program pursuant 38 M.R.S.A
section 343-E, and that is located along:
(a) A coastal wetland; or
(b) A river that does not flow to a great pond classified as GPA pursuant to
38 M.R.S.A section 465-A.
(6) The removal of non-native invasive vegetation species, provided the following
minimum requirements are met:
(a) If removal of vegetation occurs via wheeled or tracked motorized equipment, the
wheeled or tracked motorized equipment is operated and stored at least twenty-
five (25) feet, horizontal distance, from the shoreline, except that wheeled or
tracked equipment may be operated or stored on existing structural surfaces, such
as pavement or gravel.
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(b) Removal of vegetation within twenty-five (25) feet, horizontal distance, from the
shoreline occurs via hand tools; and
(c) If applicable clearing and vegetation removal standards are exceeded due to the
removal of non-native invasive species vegetation, the area shall be revegetated
with native species to achieve compliance.
(7) The removal of vegetation associated with emergency response activities conducted
by the Department, the U.S. Environmental Protection Agency, the U.S. Coast Guard,
and their agents.
R. Revegetation Requirements
When revegetation is required in response to violations of the vegetation standards set
forth in Section 15(P), to address the removal of non- native invasive species of
vegetation, or as a mechanism to allow for development that may otherwise not be
permissible due to the vegetation standards, including removal of vegetation in
conjunction with a shoreline stabilization project, the revegetation must comply with the
following requirements.
(1) The property owner must submit a revegetation plan, prepared with and signed by a
qualified professional, that describes revegetation activities and maintenance. The
plan must include a scaled site plan, depicting where vegetation was, or is to be
removed, where existing vegetation is to remain, and where vegetation is to be
planted, including a list of all vegetation to be planted.
(2) Revegetation must occur along the same segment of shoreline and in the same area
where vegetation was removed and at a density comparable to the pre-existing
vegetation, except where a shoreline stabilization activity does not allow revegetation
to occur in the same area and at a density comparable to the pre-existing vegetation,
in which case revegetation must occur along the same segment of shoreline and as
close as possible to the area where vegetation was removed:
(3) If part of a permitted activity, revegetation shall occur before the expiration of the
permit. If the activity or revegetation is not completed before the expiration of the
permit, a new revegetation plan shall be submitted with any renewal or new permit
application.
(4) Revegetation activities must meet the following requirements for trees and saplings:
(a) All trees and saplings removed must be replaced with native noninvasive species;
(b) Replacement vegetation must at a minimum consist of saplings;
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(c) If more than three (3) trees or saplings are planted, then at least three (3)
different species shall be used;
(d) No one species shall make up 50% or more of the number of trees and saplings
planted;
(e) If revegetation is required for a shoreline stabilization project, and it is not
possible to plant trees and saplings in the same area where trees or saplings were
removed, then trees or sapling must be planted in a location that effectively
reestablishes the screening between the shoreline and structures; and
(f) A survival rate of at least eighty (80) percent of planted trees or saplings is
required for a minimum five (5) years period.
(5) Revegetation activities must meet the following requirements for woody vegetation
and other vegetation under three (3) feet in height:
(a) All woody vegetation and vegetation under three (3) feet in height must be
replaced with native noninvasive species of woody vegetation and vegetation
under three (3) feet in height as applicable;
(b) Woody vegetation and vegetation under three (3) feet in height shall be planted in
quantities and variety sufficient to prevent erosion and provide for effective
infiltration of stormwater;
(c) If more than three (3) woody vegetation plants are to be planted, then at least
three (3) different species shall be planted;
(d) No one species shall make up 50% or more of the number of planted woody
vegetation plants; and
(e) Survival of planted woody vegetation and vegetation under three feet in height
must be sufficient to remain in compliance with the standards contained within
this chapter for minimum of five (5) years
(6) Revegetation activities must meet the following requirements for ground vegetation
and ground cover:
(a) All ground vegetation and ground cover removed must be replaced with native
herbaceous vegetation, in quantities and variety sufficient to prevent erosion and
provide for effective infiltration of stormwater;
(b) Where necessary due to a lack of sufficient ground cover, an area must be
covered with mulch to prevent erosion and provide for effective infiltration of
stormwater; and
TOWN OF ATHENS
) MANDATORY SHORELAND ZONING ACT
SOMERSET COUNTY
)
SHORELAND ZONING ORDINANCE
)
ORDER # 48-2025
) CONDITIONAL APPROVAL
(c) Survival and functionality of ground vegetation and ground cover must be
sufficient to remain in compliance with the standards contained within this
chapter for minimum of five (5) years.
DONE AND DATED AT AUGUSTA, MAINE, THIS 12TH DAY OF SEPTEMBER, 2025.
DEPARTMENT OF ENVIRONMENTAL PROTECTION
BY:
For: Melanie Loyzim, Commissioner
PLEASE NOTE ATTACHED SHEET FOR GUIDANCE ON APPEAL PROCEDURES.
DEPLW-1249/r21/r25
DEP INFORMATION SHEET
Appealing a Commissioner's Decision on a
Shoreland Zoning Ordinance
Date: April 2025 Contact: [email protected] or (207) 314-1458
SUMMARY
This document provides information regarding a municipality's rights and obligations in filing an
administrative or judicial appeal of a shoreland zoning ordinance decision made by the Commissioner
of the Department of Environmental Protection ("DEP").
There are two methods available to a municipality seeking to appeal a shoreland zoning ordinance
decision made by the DEP Commissioner: (1) an administrative process before the Board of
Environmental Protection ("Board"), or (2) a judicial appeal before Maine's Superior Court.
I. ADMINISTRATIVE APPEALS TO THE BOARD
LEGAL REFERENCES
A municipality filing an appeal with the Board should review the applicable rules and statutes,
including the DEP's Chapter 2 rule, Processing of Applications and Other Administrative Matters (06-
096 C.M.R. ch. 2); Organization and Powers, 38 M.R.S. §§ 341-D(4) and 346; and the
the Mandatory Shoreland Zoning laws 38 M.R.S. § 438-A(3).
DEADLINE TO SUBMIT AN APPEAL TO THE BOARD
Within 30 calendar days of the date of a final license decision of the Commissioner; a municipality
may appeal to the Board for review of that decision. "Aggrieved person" means any person whom the
Board determines may suffer a particularized injury as a result of a Commissioner's license decision. A
complete appeal must be received by the Board no later than 5:00 p.m. on the 30th calendar day of the
decision being appealed. With limited exception, untimely appeals will be dismissed.
HOW TO SUBMIT AN APPEAL TO THE BOARD
An appeal to the Board may be submitted via postal mail or via electronic mail (e-mail) and must
contain all signatures and the required appeal contents. An electronic filing must contain the scanned
original signature of the appellant(s). The appeal documents must be sent to the following address.
Chair, Board of Environmental Protection
c/o Board Clerk
17 State House Station
Augusta, ME 04333-0017
[email protected]
The DEP may also request the submittal of the original signed paper appeal documents when the
appeal is filed electronically. The risk of material not being received in a timely manner is on the
sender, regardless of the method used.
Appealing a Commissioner's Decision on a Shoreland Zoning Ordinance
April 2025
DEPLW-1249/r21/r25
At the time an appeal is filed with the Board, the appellant must send a copy of the appeal to the
Commissioner of the DEP (Maine Department of Environmental Protection, 17 State House Station,
Augusta, Maine 04333-0017). Please contact the Board Clerk at [email protected] or DEP
staff at 207-287-7688 with questions or for contact information regarding a specific license.
REQUIRED APPEAL CONTENTS
A written appeal must contain the information specified in Chapter 2, section 23(B) or section 24(B),
as applicable, at the time the appeal is submitted. Please carefully review these sections of Chapter
2, which is available online at https://www.maine.gov/sos/cec/rules/06/chaps06.htm, or contact the
Board Clerk to obtain a copy of the rule. Failure to comply with the content of appeal requirements
may result in the appeal being dismissed pursuant to Chapter 2, section 23(C) or section 24(C).
OTHER CONSIDERATIONS IN APPEALING A DECISION TO THE BOARD
1. Be familiar with the administrative record. Generally, the record on which the Board decides an
appeal is limited to the record prepared by the agency in its review of the application, any
supplemental evidence admitted to the record by the Board Chair and, if a hearing is held on the
appeal, additional evidence admitted during the hearing. A municipality that seeks to appeal a
decision to the Board is encouraged to contact the DEP to inspect the record before filing an appeal.
2. Be familiar with the applicable rules and laws. An appellant is required to identify the licensing
criterion or standard the appellant believes was not satisfied in issuing the decision, the bases of the
objections or challenges, and the remedy sought. Prior to filing an appeal, review the decision being
appealed to identify the rules and laws that are applicable to the decision. An appellant may contact
the DEP or Board staff with any questions regarding the applicable rules and laws or the appeal
procedure generally.
3. The filing of an appeal does not operate as a stay to any decision. If a license has been granted and
it has been appealed, the license normally remains in effect pending the processing of the appeal.
Unless a separate stay of the decision is requested and granted (see Chapter 2, section 23(M)), the
licensee may proceed with an approved project pending the outcome of the appeal. Any activity
initiated in accordance with the approved license during the pendency of the appeal comes with the
risk of not knowing the outcome of the appeal, including the possibility that the decision may be
reversed or modified by the Board.
4. Alternative dispute resolution. If the municipality agree to use mediation or another form of
alternative dispute resolution ("ADR") to resolve the appeal and so notify the Board, the Board will
not hear the matter until the conclusion of that effort, provided the participants engaged in the
alternative dispute resolution demonstrate satisfactory progress toward resolving the issues. See
Chapter 2, section 23(H) or contact the Board Executive Analyst (contact information below) for
more information on the ADR provision.
WHAT TO EXPECT ONCE YOU FILE A TIMELY APPEAL WITH THE BOARD
The Board will acknowledge receipt of each appeal and develop a service list of appeal participants and any
interested persons for use in the appeal proceeding. Electronic mail (e-mail) is the preferred method of
communication during an appeal proceeding; however, the Board reserves the right to require paper copies
of all filings. Once the Board Chair rules on the admissibility of all proposed supplemental evidence, the
licensee (if the licensee is not the appellant) may respond to the merits of the appeal. Instructions specific to
each appeal will be provided in correspondence from the Board Executive Analyst or Board Chair.
Generally, once all filings in an appeal proceeding are complete, the DEP staff will assemble a packet of
materials for the Board (Board packet), including a staff recommendation in the form of a proposed Board
Order. Once available, appeal participants will receive a copy of the Board packet and an agenda with the
meeting location and start time. Once finalized, the meeting agenda will be posted on the Board's webpage
Appealing a Commissioner's Decision on a Shoreland Zoning Ordinance
April 2025
DEPLW-1249/r21/r25
https://www.maine.gov/dep/bep/index.html. Appeals will be considered based on the administrative record
on appeal and oral argument at a regular meeting of the Board. See Chapter 2, Section 23(I). The Board may
affirm all or part of the decision under appeal; affirm all or part of the decision under appeal with
modifications, or new or additional conditions; order a hearing to be held as expeditiously as possible;
reverse the decision under appeal; or remand the decision to the Commissioner or State Fire Marshal, as
applicable, for further proceedings.
II. APPEALS TO MAINE SUPERIOR COURT
The filing of an appeal with the Board is not a prerequisite for the filing of a judicial appeal. Maine law
generally allows aggrieved persons to appeal final license decisions to Maine's Superior Court (see 38 M.R.S. §
346(1); Chapter 2; 5 M.R.S. § 11001; and M.R. Civ. P. 80C). A judicial appeal by a party to the underlying
proceeding must be filed with the Superior Court within 30 days of receipt of notice of the Board's or the
Commissioner's decision.
ADDITIONAL INFORMATION
If you have questions or need additional information on the appeal process, for administrative appeals
contact the Board Clerk at [email protected] or 207-287-2811 or the Board Executive Analyst at
[email protected], or 207-314-1458 or for judicial appeals contact the court clerk's office in
which the appeal will be filed.
Note: This information sheet, in conjunction with a review of the statutory and rule provisions referred to
herein, is provided to help a person to understand their rights and obligations in filing an administrative
or judicial appeal, and to comply with the notice requirements of the Maine Administrative Procedure
Act, 5 M.R.S. § 9061. This information sheet is not intended to supplant the parties' obligations to
review and comply with all statutes and rules applicable to an appeal and insofar as there is any
inconsistency between the information in this document and the applicable statutes and rules, the
relevant statutes and rules apply.