Blue Hill Commercial Site Plan Review Ordinance
- i -
Section 1. General Provisions ................................................................................................. 1
A.
Title .................................................................................................................................................. 1
B.
Authority .......................................................................................................................................... 1
C.
Purposes ........................................................................................................................................... 1
D.
Conflict with Other Laws .................................................................................................................. 1
E.
Severability....................................................................................................................................... 1
F.
Effective Date ................................................................................................................................... 1
Section 2. Definitions ............................................................................................................. 3
Section 3. Site Plan Review Required ..................................................................................... 8
A.
Permit Required ............................................................................................................................... 8
B.
Table of Land Uses ........................................................................................................................... 8
C.
Prohibited Uses ................................................................................................................................ 9
Section 4. Application Procedures ........................................................................................ 10
A.
Classification of Projects ................................................................................................................ 10
B.
Major Developments ..................................................................................................................... 10
C.
Minor Developments ..................................................................................................................... 11
D.
Submission Requirements ............................................................................................................. 11
E.
Requirements for All Applications ................................................................................................. 12
F.
Additional Reports for Specific Project Types ................................................................................ 15
Section 5. Site Plan Review Process...................................................................................... 17
A.
Purpose .......................................................................................................................................... 17
B.
Prohibition ..................................................................................................................................... 17
C.
Review Procedures ........................................................................................................................ 17
D.
Public Hearing Procedures ............................................................................................................. 19
E.
Professional Review of Major Developments ................................................................................ 20
F.
Failure to Act .................................................................................................................................. 20
G.
Appeals........................................................................................................................................... 21
H.
Expiration of Approvals .................................................................................................................. 21
I.
Other Permits ................................................................................................................................. 21
J.
Access to Site and Records ............................................................................................................ 21
Section 6. Site Plan Review Criteria ...................................................................................... 22
A.
Parking and Loading ....................................................................................................................... 22
B.
Traffic Movement, Congestion and Safety .................................................................................... 22
Blue Hill Commercial Site Plan Review Ordinance
- ii -
C.
Soil Types, Erosion, Contamination, Drainage, etc. ....................................................................... 23
D.
Outdoor Displays and Storage Areas ............................................................................................. 25
E.
Hazards and Nuisances .................................................................................................................. 25
F.
Buffers, Screening, Landscaping, Natural Features ....................................................................... 26
G.
Avoidance of adverse effects, generally ........................................................................................ 26
H.
Avoidance of Adverse Effects on Nearby Properties ..................................................................... 26
I.
Municipal Services ......................................................................................................................... 27
J.
Provision for Proper Operation ...................................................................................................... 28
K.
Campgrounds ................................................................................................................................. 28
L.
Signs ............................................................................................................................................... 29
M.
Site Conditions ............................................................................................................................... 29
N.
Permissible Solar Farms ................................................................................................................. 30
O.
Ordinance Conformity ................................................................................................................... 31
Section 7. Enforcement ........................................................................................................ 32
A.
Enforcement Authority .................................................................................................................. 32
B.
Violations ....................................................................................................................................... 32
Blue Hill Commercial Site Plan Review Ordinance
Section 1. General Provisions
- 1 -
Section 1. General Provisions
A. Title
This ordinance shall be known as the "Blue Hill Commercial Site Plan Review Ordinance" or, herein,
as the "Ordinance."
B. Authority
This Ordinance is adopted pursuant to the enabling provisions of Article VIII, Part 2 of the Maine
Constitution (Municipal Home Rule), the provisions of 30-A M.R.S. § 3001 (Home Rule) and the
provisions of the Planning and Land Use Regulation Act 30-A M.R.S. Chapter 187 (Comprehensive
Planning and Regulation or "Growth Management Act") and 30-A M.R.S. § 4452 (Enforcement of
Land Use Laws and Ordinances).
C. Purposes
1. To assure the safety, health, and welfare of the people of the Town of Blue Hill.
2. To promote an economically sound and stable community.
3. To lessen the danger and congestion of traffic on public roads.
4. To protect and preserve the natural environment of the Town of Blue Hill.
5. To establish orderly and uniform procedures whereby the Town may review high impact
projects to ensure that the other purposes of this Ordinance are met.
6. To affirmatively further the purpose of the Federal Fair Housing Act, 42 U.S.C. ch 45, as
amended, and the Maine Human Rights Act to achieve the applicable statewide or regional
housing production goal established by the Maine Department of Economic and Community
Development.
D. Conflict with Other Laws
Whenever the requirements of this Ordinance are in conflict with the requirements of any other
lawfully adopted rule, regulation, ordinance or statute which also applies to the proposed project,
the requirement imposing the more restrictive or higher standard shall govern.
E. Severability
In the event that any section, subsection or provision of this Ordinance shall be declared by any
court of competent jurisdiction to be invalid for any reason, that declaration shall not be deemed to
affect the validity of any other section, subsection or provision of this Ordinance. To this end, the
provisions of this Ordinance are hereby declared to be severable.
F. Effective Date; Date of Applicability
The effective date of this Ordinance or any amendments hereto is the date of its adoption at a Town
Meeting.
Notwithstanding 1 M.R.S.A. § 302 or any other law to the contrary, and regardless of the effective
date, this Ordinance, as amended at a Town Meeting held on April 8, 2023, shall apply to all
proceedings and applications that were or are pending before any permitting authority on or any
time after February 14, 2023 (the "Date of Applicability") and, to the extent allowed by 30-A
Blue Hill Commercial Site Plan Review Ordinance
Section 1. General Provisions
- 2 -
M.R.S.A. § 3007(6), shall nullify the issuance of any final approval of a permitting authority made on
or any time after the Date of Applicability.
Blue Hill Commercial Site Plan Review Ordinance
Section 2. Definitions
- 3 -
Section 2. Definitions
As used in this Ordinance, unless the context otherwise indicates, the following terms have the
following meanings.
NOTE: For convenience only, defined terms are marked in bold italics where they appear in the
text.
Abutting lot: A lot which abuts, is contiguous to, or joins at a border or boundary, including lots
across a road, the lot(s) subject to the Site Plan Review requirement and any contiguous lots under
common ownership.
Aggrieved party: An owner of land whose property is directly or indirectly affected by the granting
or denial of a permit or variance under this Ordinance; a person who owns an abutting lot to that
lot for which a Site Plan Review Permit or variance has been granted; or any other person who has
suffered particularized injury as a result of the granting or denial of such Site Plan Review Permit or
variance.
Accessory structure or use: A use or structure which is incidental and subordinate to the principal
use or structure. Accessory uses, when aggregated, shall not subordinate the principal use of the
lot.
Accessory Dwelling Unit (ADU): A self-contained dwelling unit located within, attached to, or
detached from a single-family dwelling that complies with 30-A M.R.S.A §4364-B, as amended. As
used in this Ordinance, an ADU is an accessory structure or use to a single-family dwelling.
Affordable Housing Development: A development of single-family dwellings, duplex dwellings,
multi-family dwellings, or any combination thereof, in which a household whose income does not
exceed 80% (for rental housing) or 120% (for owned housing) of the area median income can afford
51% or more of the units in the development without spending more than 30% of the household's
monthly income on housing costs. "Housing costs" means (a) for a rental unit, the cost of rent and
any utilities (electric, heat, water, sewer, and/or trash) that the household pays separately from the
rent; and (b) for an ownership unit, the cost of mortgage principal and interest, real estate taxes
(including assessments), private mortgage insurance, homeowner's insurance, condominium fees,
and homeowners' association fees. "Area median income" means the midpoint of income distribution
in the HUD-designated metropolitan area that includes the Town of Blue Hill, as calculated on an
annual basis by the U.S. Department of Housing and Urban Development ("HUD").
Agricultural activities: The production, keeping or maintenance for sale or lease, of plants and/or
animals, including but not limited to forages and sod crops, grains and seed crops, dairy animals and
dairy products, poultry and poultry products, livestock, fruits and vegetables, and ornamentals and
greenhouse products. Agricultural activities do not include the processing of agricultural products
for market or consumption such as slaughterhouses, packing plants or canneries.
Attic: That part of a structure immediately below and wholly or partly within the roof framing.
Basement: Any portion of a structure with a floor to ceiling height of six (6) feet or more and having
more than fifty per cent (50%) of its volume below the existing ground level.
Building: Any structure designed to shelter people, animals, or property.
Blue Hill Commercial Site Plan Review Ordinance
Section 2. Definitions
- 4 -
Campground: Any premises established for camping, including recreational vehicle parks, for which
a fee is charged.
Campsite: An area in a campground designed for use by a single recreational vehicle, tent, or
shelter.
CEO (Code Enforcement Officer): A person appointed by the municipal officers to administer and
enforce this Ordinance.
Commercial: An activity the intent or result of which is to generate revenue from the buying and
selling of goods and/or services, including the short-term and long-term rental of single-family or
duplex dwellings. This definition includes non-profit organizations and activities.
Commercial recreation facility: Any commercial enterprise that provides recreational activities
including, but not limited to, racquet ball clubs, health clubs, amusement parks and golf courses.
Commercial use: The use of lands or structures, other than for a "home occupation," for
commercial purposes.
Duplex dwelling: A detached or semi-detached building consisting of two (2) dwelling units.
Dwelling unit: A room or group of rooms designed and equipped exclusively for use as living
quarters for only one (1) family, including provisions for living, sleeping, cooking, and eating and, if
present, a home occupation).
Expansion (of a structure): An increase in the height, floor area or volume of a structure, including
increases in all extensions such as, but not limited to, attached decks, garages, porches, and
greenhouses.
Expansion (of use): Any intensification of use in time, volume, or function, whether or not resulting
from an increase in the footprint, height, floor area, land area or cubic volume occupied by a
particular use. Increases which are required in order to meet the requirements of the Americans
with Disabilities Act and/or the State Fire Code are not considered to be expansions of use.
Family: One or more persons occupying a premises and living as a single housekeeping unit.
Floor area: The sum of the horizontal surface areas of a structure enclosed by exterior walls
(including the gross habitable portions of any attic or basement), plus the horizontal surface area of
any unenclosed portions of a structure such as porches and decks.
Footprint: The area enclosed by the outside perimeter of a structure at ground level.
Forest management activities: Timber cruising and other forest resources evaluation activities,
management planning activities, insect and disease control, timber stand improvement, pruning,
timber harvesting and other similar associated silvicultural activities.
Height (of a structure): The vertical distance between the mean original (prior to construction)
grade at the downhill side of the structure and the highest point of the structure, excluding roof-
mounted solar photovoltaic (PV) panels, chimneys, steeples, antennas, and similar appurtenances
that have no floor area. For ground-mounted solar photovoltaic (PV) panels, the vertical distance
between the mean original (prior to construction) grade at the point where a panel is fixed to the
ground and the highest point of the panel.
Blue Hill Commercial Site Plan Review Ordinance
Section 2. Definitions
- 5 -
High intensity soil survey: A "high intensity soil survey" as defined by the Maine Association of
Professional Soil Scientists.
Home occupation: An occupation or profession which is customarily conducted on or in a residential
structure or property and which is 1) clearly incidental to and compatible with the residential use of
the property and surrounding residential uses; and 2) which employs no more than two (2) persons
other than family members.
Impervious surface: Surfaces which do not absorb water, including, without limitation, all buildings,
parking areas, driveways, roads, sidewalks and any areas of concrete or asphalt. In the case of
lumberyards, areas of stored lumber constitute impervious surfaces.
Loading area: An off-street space or berth on the same lot with a building or contiguous to a group
of buildings for the temporary parking of a commercial vehicle while loading or unloading
merchandise or materials, and which abuts upon a street, alley, or other appropriate means of
access.
Lot: A parcel of land undivided by any public road.
Lot coverage: The maximum combined footprints of all structures on a lot, divided by the area of
such lot, the result expressed as a percentage. In shoreland areas, lot coverage also includes all un-
revegetated areas.
Lot line: A line bounding a lot that divides one lot from another, or from a public road.
Major Development: A project which has been classified as such under the provisions of Section
4(B) (or reclassified under Section 4(C)) of this Ordinance.
Minor Development: All projects not classified as a Major Development.
Multi-family Dwelling: A structure containing three (3) or more dwelling units.
Non-conforming (building or structure): A building or structure which 1) was in commercial use as
of the date of adoption of Section 6(H)(3) and 2) did not conform to the setback provisions of that
section as of such date.
Owner: The person having the right of legal title to, beneficial interest in, or a contractual right to
purchase a lot.
Permitting authority: The person (CEO) or entity (Planning Board) responsible for issuing a
particular permit or approval under this Ordinance.
Person: An individual, corporation, governmental agency, municipality, trust, estate, partnership,
association, two or more individuals having a joint or common interest, or other legal entity.
Principal structure: A building other than one that is used for purposes wholly incidental or
accessory to the use of another building or use on the same premises. A deck or similar extension of
the principal structure or a garage attached to the principal structure by a roof or a common wall is
considered part of the principal structure.
Principal use: A use other than one that is wholly incidental or accessory to another use on the
same premises.
Blue Hill Commercial Site Plan Review Ordinance
Section 2. Definitions
- 6 -
Public road: A road designated for public use; typically maintained by a governmental body such as
a town, county, state, or the Federal government.
Recreational vehicle: A vehicle or vehicular attachment designed for temporary sleeping or living
quarters for one or more persons, including, without limitation, a pickup camper, travel trailer, tent
trailer, motor home, or converted van or truck.
Road: A thoroughfare, way or easement permanently constructed for or created by the repeated
passage of vehicles.
Site Plan Approval: A decision by the permitting authority to approve a project as a result of Site
Plan Review.
Site Plan Review: The process of evaluating an application for a project under this Ordinance.
Site Plan Review Permit: A written order granting Site Plan Approval.
Shore frontage: The horizontal distance, measured in a straight line, between the intersections of
the lot lines with the shoreline at the normal high water line or the upland edge of a coastal
wetland. The terms "normal high water line" and "coastal wetland" shall have the meanings set
forth in 38 M.R.S. § 480-B.
Shoreland area: All areas to which the Shoreland Zoning Ordinance for the Municipality of Blue Hill,
as it may be amended from time to time, is applicable.
Sign: Any structure, display, logo, device, or representation which is designed or used to advertise or
call attention to any thing, person, business, activity, or place, and which is visible to the public. A
sign does not include any flag, pennant or insignia of a nation, state, town, or other political entity.
Whenever dimensions of a sign are specified they shall include frames. Each visible sign face shall
constitute a separate sign, except that a sign with two (2) faces shall be considered one (1) sign so
long as the distance between the faces does not exceed twelve (12) inches. The area of both faces
shall be combined in determining the total area of the sign.
Single-family dwelling: A detached or semi-detached building consisting of one (1) dwelling unit.
Solar energy system: A complete assembly of solar collectors and associated mounting hardware,
electricity storage equipment, transmission and distribution lines, and related infrastructure that
uses solar photovoltaic (PV) technology (including solar panels) to collect, convert, store, and deliver
electricity for on-site or remote consumption. A solar energy system may be roof-mounted or
ground-mounted.
Solar energy system, accessory: A solar energy system, other than a solar microgrid, that is (i) roof-
mounted; or (ii) ground-mounted, whose solar land area does not exceed 0.5 acres, and whose
nameplate capacity is 125 kW (DC) or less.
Solar farm, local-scale: A ground-mounted solar energy system, other than an accessory solar
energy system, whose solar land area is less than 3.0 acres.
Solar farm, large-scale: A ground-mounted solar energy system, other than an accessory solar
energy system, whose solar land area is 3.0 acres or more.
Solar farm, permissible: Any solar energy system that is listed under Section 3(B) (the Table of Land
Uses) as an allowed land use activity requiring a site plan review permit.
Blue Hill Commercial Site Plan Review Ordinance
Section 2. Definitions
- 7 -
Solar land area: The aggregate area of land occupied by a ground-mounted solar energy system,
including but not limited to: (i) solar panels and associated mounting hardware and equipment, (ii)
all inter-panel space, and (iii) all impervious surfaces. Solar land area does not include parking lots,
driveways, or roadways used to access the solar energy system or any areas adjacent to the solar
energy system that are vegetated by grasses and must, by virtue of a legal instrument, be kept free
of structures, trees, or shrubs in order for the system to capture sunlight.
Solar microgrid: A solar energy system of any size or nameplate capacity that shall operate
independently of the electric grid to generate, store, and deliver electricity primarily for on-site
consumption by multiple principal uses or structures located on one or more parcels of land within
a geographically defined area that does not extend beyond the geographic scope of the Town of
Blue Hill.
Street: A public road.
Structure: Anything built for the support, shelter or enclosure of persons, animals, goods, or
property of any kind, together with anything constructed or erected with a fixed location on or in
the ground, exclusive of fences, poles, signs, sidewalks, driveways, or parking lots. The term includes
structures temporarily or permanently located, such as tents, decks, raised walkways, handicapped
access ramps, external stairways, and satellite dishes.
Substantial commencement: Completion of thirty percent (30%) of a permitted structure or use
measured as a percentage of estimated total cost.
Vegetation: All live trees, shrubs, ground cover, and other plants.
Yard: The area of land not occupied by buildings.
Blue Hill Commercial Site Plan Review Ordinance
Section 3. Site Plan Review Required
- 8 -
Section 3. Site Plan Review Required
A. Permit Required
No person shall commence or undertake any land use activity within the Town of Blue Hill
without first obtaining a Site Plan Review Permit as indicated by the following Table of Land
Uses.
B. Table of Land Uses
Land Use Activity
Site Plan Review
Permit
Required?
1. One or two single-family dwellings on a single lot.
No
2. Duplex dwelling on a single lot.
No
3. Conversion of a single-family dwelling on a single lot to a duplex dwelling.
No
4. Any structure or activity that is an accessory structure or use to items 1
through 3, above.
No
5. Multi-family dwelling or affordable housing development
Yes
6. All agricultural activities.
No
7. Forest management activities.
No
8. The construction of any new structure not otherwise exempted by this table.
Yes
9. Any new commercial use of land not otherwise exempted by this table.
Yes
10. Any expansion of an existing commercial use that results in:
A. lot coverage greater than fifty percent (50%);
B. a structure with a footprint greater than two thousand (2,000) sq. ft. in
area; or
C. total impervious surfaces on the lot in excess of four thousand (4,000)
sq. ft. or seventy five percent (75%) of lot area.
Yes
11. Any use that will result in substantial wastewater discharge as described in
Section 4(B)(1) of this Ordinance.
Yes
12. The interior expansion of any commercial use structure that increases the
floor area used for commercial purposes by fifty percent (50%) or more.
Yes
13. Any use that will result in substantial groundwater extraction as described in
Section 4(B)(2) of this Ordinance.
Yes
14. Any accessory solar energy system.
No
15. Any local-scale solar farm.
Yes
16. Any solar microgrid.
Yes
Blue Hill Commercial Site Plan Review Ordinance
Section 3. Site Plan Review Required
- 9 -
C. Prohibited Uses
The following land use activities within the Town of Blue Hill, and any structures associated with
such activities, are prohibited:
1. Any large-scale solar farm.
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 10 -
Section 4. Application Procedures
A. Classification of Projects
Each project subject to Site Plan Review shall be classified by the CEO as a Major Development
or a Minor Development.
B. Major Developments
Any project involving any of the following shall be classified by the CEO as a Major
Development. Any project initially classified as a Major Development may be reclassified as a
Minor Development upon a finding by the Planning Board that the project does not meet any of
the requirements for classification as a Major Development. After such reclassification all
further review shall be conducted by the CEO.
1. Projects with substantial wastewater discharge
Projects that are not served by a public sewer, which will generate a daily average discharge
of more than two thousand (2,000) gallons of wastewater, and which will meet any one of
the following three conditions:
a. The project is located within three hundred (300) feet of a sand and gravel aquifer, as
shown on the relevant map of Significant Sand and Gravel Aquifers published by Maine
Geological Survey;
b. Any part of the project is located in an area to which the Shoreland Zoning Ordinance
for the Municipality of Blue Hill is applicable; or
c. Any part of the project is located in the watershed of the Blue Hill Water District.
2. Projects with substantial groundwater extraction
Projects extracting one thousand (1,000) gallons or more of groundwater per day.
3. Projects involving hazardous materials, oil, or radioactive substances.
Hazardous activities involving the consumption, generation, or handling of:
a. Hazardous wastes as defined in 38 M.R.S. § 1303-C;
b. Hazardous matter as defined in 38 M.R.S. § 1317;
c. Oil, as defined in 38 M.R.S. § 542; and
d. Low-level radioactive wastes, as defined in 38 M.R.S. § 1451.
4. Building footprint in excess of ten thousand (10,000) sq. ft.
Any building or buildings on a single lot constructed or erected with a fixed location on or in
the ground or attached to something on or in the ground which occupies a footprint in
excess of ten thousand (10,000) square feet.
5. Impervious surfaces in excess of sixty thousand (60,000) sq. ft.
Any project in which total impervious surface(s) will occupy a ground area in excess of sixty
thousand (60,000) square feet.
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 11 -
6. Conversion or Expansion of a Major Development
Any project which is a conversion or expansion of an existing project meeting the
description of a Major Development.
7. CEO Determination of Potential Significant Impact
Any project which the CEO determines a) may have significant impact to the physical, social,
economic, or the environmental welfare of the Town or b) has characteristics that make it
reasonable and necessary to conduct a professional review (as described in Section 5(E))
prior to considering the application for Site Plan Approval.
8. Permissible Solar Farms
Any project that meets the definition of a permissible solar farm.
C. Minor Developments
A project not classified by the CEO as a Major Development shall be considered a Minor
Development under this Ordinance. Any project initially classified as a Minor Development may
be reclassified as a Major Development upon a finding by the CEO that the project meets the
requirements for classification as a Major Development. After reclassification, all further review
shall be conducted by the Planning Board.
D. Submission Requirements
1. Major and Minor Developments
All projects requiring Site Plan Review shall submit the information specified in Section 4(E).
Major Developments meeting the criteria in Section 4(B)(1) (Projects with substantial
wastewater discharge) and Section 4(B)(2) (Projects with substantial groundwater
extraction) shall submit additional information as provided in Section 4(F).
2. Waiver
The permitting authority may waive any of the submission requirements upon the written
request of an applicant for good cause shown. The permitting authority must state the facts
constituting good cause in writing. No waiver may be granted if it will unduly restrict the
review process. The permitting authority may condition such a waiver on the applicant's
compliance with alternative requirements. Good cause may include the permitting
authority's finding that particular submissions are inapplicable, unnecessary, or
inappropriate for a complete review. Notwithstanding the waiver of a submission
requirement, the permitting authority may, at any later point in the review process, rescind
such waiver if it appears that any submission requirement previously waived is necessary for
an adequate review. A request for submission previously waived shall not affect the pending
status of an application.
3. Procedures
Applications for Site Plan Review shall be submitted on forms provided by the Town. The
complete application form, required fees, and the required plans and related information
shall be submitted to the CEO who shall, for Major Developments, forward these materials
to the Planning Board.
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 12 -
4. Optional pre-application review
Prospective applicants may submit a sketch plan of the site and proposed project to the CEO
for informal review and comment. There is no fee for pre-application review; any review or
comment by the CEO is not binding upon either the CEO or Planning Board.
E. Requirements for All Applications
The following materials and items are required of all applications.
1. Application form
A fully executed and signed copy of the application form.
2. Review and advertising fees
Fees associated with applications for permits under this Ordinance shall be as indicated on
the Town fee schedule, as determined by the Select Board, in effect at the time the
application is deemed complete by the permitting authority.
3. Technical review fee
Technical review fees, if applicable, shall be as indicated on the Town fee schedule, as
determined by the Select Board, in effect at the time the application is deemed complete by
the permitting authority.
Upon request of the Planning Board and the approval of the Municipal Officers of the Town,
all or any portion of the technical review fee may be expended for technical services by
independent consultants, to be conducted as described in Section 5(E). Any moneys
remaining at the end of the review shall be returned to the applicant.
4. Copies
a. Applications for Minor Developments shall include two (2) copies of written materials
plus two (2) sets of maps or drawings containing the information listed below.
b. Applications for Major Developments shall include two (2) copies of written materials
plus two (2) sets of maps or drawings containing the information listed below and a
complete electronic copy of the application.
c. All maps or drawings shall be at a scale sufficient to allow review of the items listed
under the criteria for approval.
5. General information
The following general information is required:
a. Name and address of owner of record and the facility operator's name and address if
different;
b. Applicant's name and address if different;
c. The name of the proposed project;
d. Table of contents organizing the following required materials;
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 13 -
e. The applicant shall provide a list of the names and addresses of all current abutting
landowners of the proposed project with the application. The applicant shall be
responsible for sending a notice (provided by the Town) of the proposed project and
application via certified mail, return receipt requested, to all abutting landowners and
shall provide the CEO with copies of the completed return receipts and an affidavit
stating the terms of this condition have been met.
f.
Sketch map showing general location of the site within the Town;
g. Location map showing the relationship of the proposed project to adjacent properties
and to the general surrounding area within three thousand (3,000) feet of any property
line of the site, and the location of any identified sand and gravel aquifers within three
hundred (300) feet of the project. The scale shall not be smaller than 1" = 400'; reduced
tax maps showing owner's names and other required information may be acceptable;
h. The tax map(s) and lot number(s) of the lot where the project is located and of abutting
lots;
i.
A copy of the current deed to the lot, option to purchase the lot or other
documentation to demonstrate right, title, or interest in the lot on the part of the
applicant; and
j.
The name(s), registration number(s), and seal(s) of the land surveyor, architect,
engineer, and/or similar professionals assisting with the preparation of the plan.
6. Site information
The following information regarding the proposed project and existing conditions is
required. This information must accompany, or be submitted on, a map using the following
scale and showing the date of the map, magnetic north, the scale, and the identity of the
draftsman:
Acres
Scale
1 to 10
1"=10' to 1"=50'
10+ to 50
1"=50' to 1"=100'
50+(lots <=4 acres)
1"=100'
50+(lots >4 acres)
1"=200'
a. Zoning classification(s) of the lot and the location of zoning district boundaries if the lot
is wholly or partially located in a shoreland area.
b. The bearings and distance of all lot lines of the lot on which the project is located and
the source of this information.
c. Location and size of all existing and proposed wells, sewer and water mains, culverts,
drains, above or below ground utilities and wastewater disposal systems on the lot on
which the project is located, and of any of these items that currently serves or will serve
the project from abutting lots or public roads.
d. Location, names and widths of all existing and proposed roads and rights-of-way
adjacent to the proposed project.
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 14 -
e. The location, dimensions and ground floor elevations of all existing and proposed
buildings on the lot.
f.
The location and dimensions of all existing and proposed driveways, roads, parking and
loading areas and walkways on the lot.
g. The existing and proposed topography of the site at an appropriate contour interval (not
greater than 5') depending on the nature of the use and character of the lot.
h. Major natural features on the site and including, within two hundred fifty (250) feet of
the lot lines, wetlands, streams, ponds, floodplains, groundwater aquifers, significant
wildlife habitats including bird nesting, staging and feeding areas and deer yards (as
identified in the Town's 1999 Comprehensive Plan), archaeological resources or other
important natural features.
i.
The direction and amount of pre-development and proposed surface water drainage
flow across and from the site, based upon 24-hour, 2-, 10- and 25-year storms. Where
proposed flows exceed pre-development flows by ten percent (10%) or more, the
applicant shall submit a storm water management plan, showing the steps taken to
minimize the impact of storm water runoff. The storm water management plan shall be
based upon 24-hour, 2-, 10- and 25-year storms.
j.
The location and type of all existing and proposed exterior signs.
k. A copy of such covenants or deed restrictions, if any, as are intended to cover all or part
of the lot. Such covenants or deed restrictions shall be referenced on the plan.
l.
The location of all existing and proposed building setbacks, yards and buffers required
by this Ordinance.
m. Elevation view of the building and signs, showing heights and materials.
n. Landscaping plan showing the building(s), existing and proposed vegetation, walkways
and exterior lighting. Drawings to be at the scale designated in Section 4(E)(6).
o. For any project that will dispose of wastewater through any subsurface wastewater
system, a completed Maine Department of Health and Human Services (Maine DHHS)
Health Engineering site evaluation and subsurface wastewater disposal system
application showing adequate soils, and adequate system design and capacity. For any
project that will dispose of wastewater through the municipal sewer system, evidence
that all criteria of the Sewer Use Ordinance for Town of Blue Hill, Maine, as it may be
amended from time to time, can be met.
p. A schedule of construction, including anticipated beginning and completion dates, and
the estimated total cost of the project.
q. The permitting authority may, at its discretion, require the applicant to provide a visual
impact assessment which may include photo simulations of the proposed facility taken
from perspectives determined by the permitting authority, or its designee.
r. Projects involving the storing, generating, or handling of hazardous wastes or materials,
oil, or radioactive wastes shall specify the exact amount and nature of all such
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 15 -
substances that will be on the site, and the specific method of handling and containing
those substances that will be used.
s. An erosion control and sedimentation control plan setting forth the measures to be
taken to comply with Section 6(C)(1).
7. Waivers sought by applicant
A list of the submission requirements for which the applicant seeks a waiver under Section
4(D)(2), and a written explanation of the reasons that the waiver is sought.
F. Additional Reports for Specific Project Types
1. Projects with substantial wastewater discharge (Section 4(B)(1)) must submit a high
intensity soil survey and a hydrogeologic assessment, which shall include, at a minimum, the
following information:
a. A map showing basic soil types on the lot.
b. The depth of the water table at representative points throughout the lot.
c. Drainage conditions throughout the lot.
d. Data regarding the existing ground water quality, either from test wells on the lot or
from existing wells on the lot or on abutting lots.
e. An analysis and evaluation of the impact of the project on ground water resources,
including a projection of nitrate-nitrogen concentrations associated with the project.
Projects within the watershed of a lake or pond shall include phosphate impact
calculations.
f.
The location of any existing or proposed subsurface wastewater disposal systems and
wells on the lot and within two hundred (200) feet of the lot lines.
g. Projections of post-development water quality at any wells within the lot or within five
hundred (500) feet from the point of contamination, whichever is the shorter distance.
These projections shall be based upon a drought condition assumption of sixty per cent
(60%) of annual average recharge from precipitation.
h. The signature and seal of the Certified Geologist who prepared the assessment.
The Planning Board may require additional information where necessary to evaluate the
project's compliance with this Ordinance.
2. Projects with substantial groundwater extraction (Section 4(B)(2)) shall submit a
groundwater extraction impact assessment which shall include, at a minimum, the following
information:
a. A statement from the applicant specifying the quantity of ground water to be extracted
expressed as the annual total, the maximum monthly rate by calendar month, and the
maximum daily rate. These rates shall be maximum rates, which rates shall not be
exceeded without further Site Plan Approval by the Planning Board.
Blue Hill Commercial Site Plan Review Ordinance
Section 4. Application Procedures
- 16 -
b. For projects coming under the jurisdiction of the Maine DHHS, a letter from that agency
containing its review comments.
c. A report prepared by a Certified Geologist showing:
i.
A map of the aquifer tributary to the spring(s), well(s) or excavation(s) from which
the water is to be extracted. The map shall include sufficient detail to support a
calculation of sustained yield during a ten (10) year drought, as well as an estimate
of any potential interaction between or among this and adjacent aquifers.
ii. Calculations based upon the investigation showing the aquifer characteristics, the
rates of draw-down and rebound, the sustainable yearly, monthly (by calendar
month) and daily extraction rates, the cone of depression that may develop about
the project and impacts upon the water table in the tributary aquifer and other
private or public wells within one thousand (1,000) feet of the proposed extraction
facilities.
3. Proposals for a permissible solar farm shall submit the following additional materials:
a. Evidence that the owner and operator of the proposal has adequate technical and
financial capacity to adequately construct, operate, and decommission the permissible
solar farm, including a statement or other documentation from a lending institution that
the owner has secured financing to cover the cost of construction.
b. A statement prepared by a licensed professional engineer certifying that the permissible
solar farm design is safe in terms of strength, stability, security, and grounding.
c. Plans prepared by a professional engineer or surveyor showing the location of all solar
energy system components, existing and proposed structures, existing and proposed
impervious surfaces, areas proposed to be cleared of vegetation, and their physical
dimensions, including a calculation of the solar land area.
d. An operations and maintenance plan for the permissible solar farm, which must include
the manufacturer-identified useful life of the facility and documentation of the entity
that will be legally responsible for operating, maintaining, and repairing the facility for
the term of its useful life.
e. If applicable, any Decommissioning Plan (and associated Approval Letter) required by
Maine Department of Environmental Protection (MDEP) for the removal of the
permissible solar farm and stabilization of the site. The approval authority may require,
as a condition of approval, a decommissioning bond naming the Town of Blue Hill as the
beneficiary, in addition to any bond issued to MDEP.
Blue Hill Commercial Site Plan Review Ordinance
Section 5. Site Plan Review Process
- 17 -
Section 5. Site Plan Review Process
A. Purpose
The purpose of Site Plan Review is to promote the public health, safety, and general welfare by
requiring CEO or Planning Board review of plans for certain uses or structures which have a
significant potential impact on the neighborhood or the environment and which, when properly
designed with respect to their surroundings, can become uses or structures that are compatible
with the neighborhood and environment.
B. Prohibition
No activity or use requiring a Site Plan Review Permit shall commence until the applicant has
been granted the requisite Site Plan Approval from the applicable permitting authority and
complied with all other applicable provisions of this Ordinance.
C. Review Procedures
The procedures for Site Plan Review are as follows:
1. Submission of completed application to the CEO.
The applicant shall submit the requisite number of copies of the application and supporting
information required by this Ordinance, as described in Section 4.
2. CEO classification and review
a. Dated receipt
The CEO shall issue the applicant a dated receipt and will date-stamp the application.
b. Classification
The CEO shall review the application and classify it as either a Major or Minor
Development in accordance with the provisions of this Ordinance.
c. Fees submitted
After classification, the applicant shall provide the CEO with the applicable review fees.
d. Review for completeness
The CEO shall initially review the application and determine whether or not it is
complete.
e. Notice of incomplete application
If the application is found to be incomplete, the CEO shall, within ten (10) days, notify
the applicant in writing of the information needed to complete the application. Upon
the applicant's submission of such additional information, the process above shall be
repeated.
3. Complete applications
Upon finding an application to be complete, the CEO shall take the following action with
regard to that application.
Blue Hill Commercial Site Plan Review Ordinance
Section 5. Site Plan Review Process
- 18 -
a. Minor Developments
Applications determined to be Minor Developments will be reviewed and acted upon by
the CEO in accordance with the procedures set forth below, and the other requirements
of this Ordinance.
b. Major Developments forwarded to the Planning Board
The CEO shall forward copies of a complete application and supporting documents
determined to be Major Developments to the members of the Planning Board and place
the project on the agenda of the next regular Planning Board meeting occurring not
more than forty (40) days after the CEO determines the application is complete.
c. Notice of public hearing to abutting lot owners
In the event that a public hearing will be held in connection with the project, the CEO
shall notify abutting lot owners of the date, time and place of such hearing by certified
mail when the hearing date has been determined.
4. Planning Board Review
For Major Developments, the Planning Board shall meet to review the project as follows.
The Planning Board shall:
a. CEO report
Hear any report of the CEO and, if the Town has retained the services of a professional
adviser, the report of the adviser regarding the proposed project;
b. Applicant's response
Hear any comments of the applicant regarding the CEO and professional advisor reports;
c. Request for waivers
Hear any requests from the applicant for waivers;
d. Determination of completeness
Determine whether or not the application is complete;
e. Notice of incompleteness
If the application is determined to be incomplete, the Planning Board shall inform the
CEO of the information required to make the application complete. The CEO shall,
within ten (10) days, inform the applicant, in writing, of the additional information
required by the Planning Board. Upon the applicant's submission of such additional
material, previous steps in Sections 5(C)(2 through 4) shall be repeated; and
f. Public hearing determination
If the application is determined to be complete, the Planning Board shall set the matter
for a public hearing conducted by the Planning Board. The public hearing shall take place
within forty (40) days of the Planning Board's determination that the application is
Blue Hill Commercial Site Plan Review Ordinance
Section 5. Site Plan Review Process
- 19 -
complete. This deadline may be extended by mutual agreement of the Planning Board
and the applicant, either in writing or orally, on the record, at a public meeting.
5. Public hearing for Minor Developments
At the CEO's discretion, a public hearing may also be required for Minor Developments, in
which case such public hearing shall be conducted by the CEO within forty (40) days of the
CEO's determination that the application is complete. This deadline may be extended by
mutual agreement, in writing, of the CEO and the applicant.
6. Deliberation and decision
a. Deliberation
Within forty (40) days after the public hearing on an application or, if no hearing is held,
within forty (40) days of a determination of completeness by the CEO, the permitting
authority shall decide the matter. For Major Developments, the Planning Board shall
deliberate the matter at a public meeting. Site Plan Approval shall be granted if the
proposed project complies with all applicable criteria and minimum standards set forth
in Section 6. This deadline may be extended by mutual agreement of the permitting
authority and the applicant in writing, or (in the case of Major Developments) either in
writing or orally, on the record, at a public meeting.
b. Decision
If the permitting authority finds that the proposed project complies with all criteria and
minimum standards of this Ordinance, it shall issue an order granting Site Plan Approval
subject to such terms and conditions as the permitting authority finds are reasonably
necessary to ensure conformity with the criteria and minimum standards of this
Ordinance.
If the permitting authority finds that the proposed project does not comply with all
applicable review criteria and minimum standards, it shall issue an order denying Site
Plan Approval.
In either case the permitting authority shall, within fifteen (15) days after the
completion of its deliberations, issue specific written findings of fact supporting its
decision.
The decision shall state any conditions of approval that apply to the project and the
reason for the imposition of those conditions. A copy of the decision shall be sent to the
applicant at the address provided on the application. Decisions by the CEO shall also be
sent to any abutting lot owner who responded, in writing, to the notice sent by the
CEO.
D. Public Hearing Procedures
Site Plan Review public hearings and notice thereof shall comply with the following procedures:
1. Published notice
Notice of the hearing shall be published in a newspaper of general circulation in the Town of
Blue Hill at least ten (10) days prior to the hearing date.
Blue Hill Commercial Site Plan Review Ordinance
Section 5. Site Plan Review Process
- 20 -
2. Content of notice
Such notice shall identify the applicant and the lot involved, describe the specific nature of
the proposal, state the date, time, and place of the hearing.
3. Rules
Hearings shall be conducted according to rules adopted by the Planning Board.
4. Representation
At any hearing a party may be represented by an agent or attorney, provided, however, that
if any party is not present, any person acting as that party's agent or attorney shall provide
evidence of such authority.
5. Continuation
Any hearing may be continued or recessed to another time for good cause, or upon written
or recorded agreement of the permitting authority conducting the hearing and the
applicant.
E. Professional Review of Major Developments
1. Additional studies
The Planning Board may require the applicant to undertake any additional studies which it
deems reasonable and necessary to ensure that the requirements of the Ordinance are met.
The cost of all such studies shall be borne by the applicant.
2. Independent technical review
The Planning Board may require that an independent consultant(s) review one (1) or more
submissions of an application. The independent consultant(s) shall report to the Planning
Board as to the project's compliance or non-compliance with the applicable provisions of
this Ordinance and recommend, if appropriate, those actions which will result in
compliance. Such consultants shall be fully qualified to provide the required information,
and may include, but not be limited to:
An Attorney;
A Community Planner;
A Registered Professional Engineer;
A Registered Architect;
A Registered Landscape Architect;
A Registered Geologist;
A Licensed Soil Scientist;
A Registered Land Surveyor;
or
Any other Registered/Licensed Professional or Independent Expert
Witness deemed fully qualified by the Planning Board.
The consultant(s) selected shall estimate the cost of such review and the applicant shall
deposit with the Town the full estimated cost to the extent it exceeds the amount paid as a
technical review fee (Section 4(E)(3).
F. Failure to Act
Failure of the permitting authority to act within any of the time requirements set forth herein
shall constitute a denial of the application.
Blue Hill Commercial Site Plan Review Ordinance
Section 5. Site Plan Review Process
- 21 -
G. Appeals
Any aggrieved party may appeal a decision to grant or deny a permit under this Ordinance, or
the imposition of conditions of approval, to the Blue Hill Board of Appeals.
H. Expiration of Approvals
Unless specifically authorized by the permitting authority at the time Site Plan Approval is
granted, all Site Plan Approvals shall expire unless work on the project is substantially
commenced within twelve (12) months from the date Site Plan Approval is granted. If work is
not substantially completed within twenty-four (24) months from the date Site Plan Approval is
granted, a new application and Site Plan Approval shall be required prior to the commencement
of any project activity or use.
I.
Other Permits
The granting of Site Plan Approval does not relieve the applicant from the need to obtain any
other permits or approvals required prior to the commencement of any activity or use. Such
other required permits or approvals may include, but are not limited to, building and plumbing
permits, permits required under other ordinances of the Town of Blue Hill, licenses granted
pursuant to 38 M.R.S. § 1022, Maine Department of Environmental Protection and United States
Army Corps of Engineers' approvals, subsurface wastewater disposal permits, sewer connection
permits, and Maine Department of Transportation approvals. The fact that the applicant may
have obtained or may have been granted such permits or approvals prior to Site Plan Review
may be considered by the Planning Board as evidence as to the project's compliance with
applicable review standards, but shall not be deemed conclusive evidence as to compliance. The
written order granting Site Plan Approval constitutes the Site Plan Review Permit for the
project.
J. Access to Site and Records
The CEO shall have reasonable access to the site at all times to review the progress of the work
and shall have the authority to review all records and documents related to the project. The
applicant, by accepting Site Plan Approval, waives any objection to the CEO having access to the
site to review the progress of the work or to review all records and documents related to the
project.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 22 -
Section 6. Site Plan Review Criteria
The permitting authority, in reviewing projects requiring Site Plan Approval under this Ordinance,
shall make positive written conclusions and factual findings as to whether the applicant has
submitted adequate evidence showing that the following criteria have been met.
In addition, the minimum standards listed in this Section shall govern all permits and approvals
issued under this Ordinance. In reviewing applications submitted pursuant to this Ordinance, the
permitting authority shall consider these minimum standards prior to issuing final approval. In all
instances, the burden of proof shall be upon the applicant.
A. Parking and Loading
Criterion: Adequate provision has been made for off-street parking and loading.
Minimum Standards:
1. All commercial recreation facilities shall have adequate off-street parking for the
anticipated maximum attendance at any event.
B. Traffic Movement, Congestion and Safety
Criterion: Adequate provision has been made for traffic movement of all types, including
pedestrian, into, out of and within the proposed project and any traffic increase attributable to
the project will not result in unreasonable congestion or unsafe conditions on a road in the
vicinity of the project. The permitting authority shall consider traffic movement both on-site
and off-site in making its determination under this criterion.
Minimum Standards:
1. Vehicular circulation
The layout of the site shall provide for the safe movement of passenger, service, and
emergency vehicles through the site.
a. Clear routes of access shall be provided and maintained for emergency vehicles to all
portions of the site and shall be posted with appropriate language.
b. The layout and design of access ways and parking areas shall provide for safe and
convenient circulation of vehicles, including delivery vehicles, and prevent their backing
out onto a street.
c. All roads shall be designed to harmonize with the topographic and natural features of
the site. The road network shall provide for vehicular and pedestrian safety, all season
emergency access, snow storage, and delivery and collection services.
2. Pedestrian circulation
The project shall provide for a system of pedestrian circulation within the site. This system
shall connect with existing sidewalks if they exist in the vicinity of the project.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 23 -
C. Soil Types, Erosion, Contamination, Drainage, etc.
Criterion: The project will be built on soil types which are suitable to the nature of the project
and adequate provision has been made to avoid erosion, contamination of ground or surface
waters, interference with adjacent land, over-burdening of natural or artificial drainage systems
and/or any other adverse effects of inadequate drainage.
Minimum Standards:
1. Conservation, erosion, and sediment control
a. The procedures outlined in the erosion and sedimentation control plan prepared and
submitted by the applicant shall be implemented during the site preparation,
construction, and cleanup stages.
b. Erosion of soil and sedimentation of watercourses and water bodies shall be minimized
by employing the Maine Erosion and Sediment Control Best Management Practices
(BMPs). To the extent the applicant cannot employ all of the BMPs, the application shall
identify all BMPs from which relief is sought, together with the reason the BMP cannot
be employed and any alternative measures proposed by the applicant. The permitting
authority will determine whether to waive full compliance with the BMPs as part of its
Site Plan Review.
c. In addition:
i.
The project shall preserve outstanding natural features, keep cut-fill operations to a
minimum and ensure conformity with topography so as to create the least erosion
potential and adequately handle the volume and velocity of surface water runoff;
ii. Whenever feasible, natural vegetation shall be retained, protected and
supplemented;
iii. The disturbed area and the duration of exposure shall be kept to a practical
minimum;
iv. Permanent (final) vegetation and mechanical erosion control measures shall be
installed as soon as practicable;
v. The top of a cut or the bottom of a fill section shall not be closer than ten (10) feet
to an abutting lot, unless specifically permitted by the permitting authority.
vi. Extraction operations (gravel pits, etc.) shall not be permitted within one hundred
(100) feet of any lot line unless specifically permitted by the permitting authority
and upon the prior written agreement of the owner of such abutting lot;
vii. Whenever sedimentation is caused by stripping vegetation, re-grading or other
development, it shall be the responsibility of the applicant to remove it from all
adjoining surfaces, drainage systems, and watercourses and to repair any damage at
his expense as quickly as possible; and
viii. Maintenance of drainage facilities or watercourses originating completely on private
property is the responsibility of the applicant to the point of open discharge at the
lot line or at a communal watercourse on the lot.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 24 -
2. Groundwater protection
a. The quantity of water to be taken from groundwater shall not substantially lower the
water table, cause salt water intrusion into any existing well, cause unreasonable
changes in groundwater flow, or unreasonable ground subsidence, based upon ten (10)-
year drought water levels.
b. The project shall not cause pollution or unreasonable diminution of the aquifer from
which it is extracted.
c. Any project located in a defined public water supply aquifer recharge area shall not have
an unreasonable adverse effect upon that public water supply.
d. Any pollutant introduced into soil on the site shall not exceed a concentration in the
ground water that is greater than the guideline established for it in the Maine CDC
Maximum Exposure Guidelines (MEGs) for Drinking Water. Any violation of this standard
shall be cause to order the immediate cessation of the use or activity responsible for the
contamination.
e. The project shall not increase any contaminant concentration in ground water to more
than one-half of the Primary Drinking Water Standards, nor more than the Secondary
Drinking Water Standards (however, where existing ground water pollution already
exceeds the Secondary Drinking Water Standards, the project shall not cause the
concentration of the parameters in question to exceed one hundred fifty percent (150%)
of the ambient concentration).
f.
All projects shall be designed to minimize any increase in storm water runoff from the
site from the natural predevelopment conditions. Storm water runoff systems should be
designed to facilitate aquifer recharge where it is advantageous to compensate for
groundwater withdrawals and infiltration, but should avoid recharge where the
groundwater effects may be harmful.
g. Where possible, existing natural runoff control features such as berms, swales, terraces,
and wooded areas shall be retained in order to reduce runoff. The use of enclosed
components (such as pipes, etc.) should be minimized where natural systems are able to
accommodate runoff.
h. Design of permanent runoff storage facilities should consider safety, appearances,
recreational use, and the cost and effectiveness of maintenance operations in addition
to the primary storage function.
i.
Energy dissipaters and other forms of outfall protection shall be employed where
enclosed drains discharge into soils subject to erosion.
j.
Storm water management systems shall be maintained as necessary to ensure that they
function properly.
k. If the project will result an increased total flow of runoff that will be discharged into the
municipal storm sewer system, the applicant shall pay for the cost of improvements to
the municipal system so that it will have the capacity to handle one hundred twenty five
percent (125%) of the projected total flow. Payment shall be made within thirty (30)
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 25 -
days of the date Site Plan Approval is granted. No construction may commence on the
project before this payment is made.
D. Outdoor Displays and Storage Areas
Criterion: Adequate provision has been made to locate and design proposed outdoor display
and/or storage areas so as to avoid any safety hazard to vehicular and pedestrian traffic on and
off the site.
E. Hazards and Nuisances
Criterion: Adequate provision has been made to avoid any hazard to travel on public or private
ways, or any glare or other nuisance to the use of adjoining public or private property.
Minimum Standards:
1. Emissions
a. Emissions of dust, dirt, fly ash, fumes, vapors or gases which pose an unreasonable risk
of harm to human health or the environment shall be prohibited.
b. No land use activity shall be permitted to produce unreasonable, offensive, or harmful
odors perceptible beyond the lot lines, measured either at ground or habitable
elevations.
2. Lighting
a. No land use activity shall be permitted to produce unreasonable glare or brightness
beyond the lot lines.
b. Lighting fixtures shall be shielded or hooded so that the lighting elements are not
exposed to normal view of motorists, pedestrians, or buildings on abutting lots.
c. Direct or indirect illumination shall not exceed 0.5 foot-candles upon residences on
abutting lots.
d. All exterior lighting shall be designed to ensure safe movement of people and vehicles,
and to minimize adverse impact on abutting lots and public roads. Adverse impact is to
be judged in terms of hours of use, hazards to people and vehicular traffic and potential
damage to the value of abutting lots. Lighting shall be arranged to minimize glare and
reflection on abutting lots and the traveling public.
3. Hazardous materials
a. No highly flammable or explosive liquids, solids or gases shall be stored in bulk above
ground, unless they are stored in compliance with the requirements of the rules and
regulations adopted by the State of Maine.
b. All storage of petroleum or liquid petroleum products shall be in conformance with the
provisions to 38 M.R.S. §§ 541-560 which, among other things, establishes a ten-year
compliance schedule for the discontinuance and removal of non-conforming
underground storage facilities and requires qualified personnel to oversee the removal
of certain underground facilities.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 26 -
c. Oil and chemical storage shall be in conformance with rules and regulations adopted by
the State of Maine applicable to the stored substance.
4. The applicant shall have the burden of proof to assure the Planning Board or CEO that all
provisions of the above statutes have been met before Site Plan Approval may be granted.
F. Buffers, Screening, Landscaping, Natural Features
Criterion: Adequate provision has been made with regard to buffers, screening, landscaping and
the preservation and enhancement of significant natural features.
G. Avoidance of adverse effects, generally
Criterion: Adequate provision has been made to avoid unreasonable adverse effects on the
scenic or natural beauty of the area or the community in general, including scenic areas
designated in the most recent Comprehensive Plan adopted by the Town, historic sites,
archaeological resources, rare and irreplaceable natural areas, wildlife habitats including
identified deer wintering areas, existing uses, air quality, water quality, or other natural
resources within the Town or in neighboring towns.
Minimum Standards:
1. Any proposed land use activity that may disturb an archaeological site as determined by the
Maine Historic Preservation Commission, or historic site which is listed on or eligible to be
listed on the National Register of Historic Places, shall require the applicant to submit
comments in writing from the Maine Historic Preservation Commission concerning the
proposed project. These comments shall be considered by the permitting authority in
deciding whether to grant the permit.
H. Avoidance of Adverse Effects on Nearby Properties
Criterion: Adequate provision has been made to prevent any undue adverse effect upon
abutting or nearby lots.
Minimum Standards:
1. Wastewater disposal
a. Projects served by subsurface wastewater systems
All projects served by subsurface wastewater systems shall construct and use such
systems and the overall project in accordance with the design, specifications and terms
of the subsurface wastewater disposal system application and permit.
b. Subsurface wastewater systems in common ownership
Where two (2) or more buildings or lots in different ownership share a common
subsurface wastewater disposal system, the system shall be owned and maintained in
common by an owners' association. Covenants shall be made in the deeds for each lot
requiring membership in the association and providing adequate funding of the
association to assure proper maintenance of the system.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 27 -
2. Water Supply
a. The project shall be provided with a system of water supply that provides an adequate
supply of water meeting the standards of the State of Maine for drinking water. Where
groundwater pollution exceeds the Primary Drinking Water Standards and the project is
to be served by on-site ground water supplies, the applicant shall provide adequate
evidence of the manner in which the water quality will be adequately improved or
treated.
b. For Major Developments the applicant shall construct ponds and dry hydrants to
provide for adequate water storage for firefighting purposes. An easement shall be
granted to the Town granting access to the dry hydrants where necessary. The Planning
Board may waive the requirement for dry hydrants or ponds only with the written
concurrence of the Blue Hill Fire Chief.
3. Lot line setback
a. Except as provided in Section 6(N)(1) and Section 6(H)(3)(c
b. ) below, all structures must be set back at least ten (10) feet from all lot lines and must
be set back at least ten (10) feet from the edge of the traveled way of any road.
c. Original non-conforming structures are not subject to the setback requirements above;
however, replacements or significant repairs to such structures shall be subject to such
requirements except as provided in Section 6(H)(3)(c) below.
d. In the event a non-conforming structure is removed, damaged, or destroyed, such
structure may be repaired or replaced, subject to the following provisions:
i.
Any such reconstruction or replacement may not increase the footprint of the
previous structure within the setback area. Furthermore, reconstructed or replaced
buildings may not be sited within the footprint of a previous non-building structure.
ii. A permit for the project must be obtained within eighteen (18) months of the date
of the damage, destruction, or removal of the non-conforming structure.
iii. The provisions of Section 6(A) and Section 6(B) will only apply to the same extent
that they applied to the non-conforming structure and its commercial use.
iv. An existing commercial use of a non-conforming structure may be changed to
another commercial use provided that the proposed use has no greater adverse
impact on the subject and adjacent properties and resources than the former use as
determined by the permitting authority.
v. A permit for the repair or replacement of a non-conforming structure shall only be
granted in the event no reasonable alternative is available. The historic appearance
and context of the non-conforming structure shall be a factor in making the
determination of reasonableness.
I.
Municipal Services
Criterion: Adequate provision has been made to avoid any undue burden on municipal services
including, but not limited to, water, fire, sewer, and police services.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 28 -
Minimum Standards:
1. Municipal sewer system
a. Any project that will dispose of its wastewater through the municipal sewer system, and
that will use more than thirty-three and one third percent (33 1/3%) of the excess
capacity of any portion of the sewer collection system, treatment facility and/or its
discharge permits, shall be approved only if the applicant pays the cost of replacing the
excess capacity needed for the project. Payment shall be made within thirty (30) days of
the date Site Plan Approval is granted. No construction may commence on the project
before this payment is made.
b. All discharges into the system shall be in accordance with the Sewer Use Ordinance for
Town of Blue Hill, Maine, as it may be amended from time to time.
J. Provision for Proper Operation
Criterion: Adequate provision has been made to assure the proper operation of the proposed
business(es) or activity(ies) on the site through the provision of adequate and appropriate safety
measures, utilities, drainage, water supply, sewage disposal, solid waste disposal, access,
parking and loading, and other necessary site improvements.
Minimum Standards:
1. For Major Developments, the project owner and operator of record shall have adequate
technical and financial capacity to construct, operate, and decommission, as needed, the
proposed development or land use activities on the site.
K. Campgrounds
Criterion: Campgrounds shall meet the following requirements, in addition to the other
requirements of this Ordinance.
Minimum Requirements:
1. Campsites and all structures shall be located at least fifty (50) feet from any lot line, and at
least one hundred (100) feet from any residence on an abutting lot.
2. Campsites shall be laid out and screened in such a manner that they are not visible from
abutting public roads, residences or approved subdivision lots.
3. No recreational vehicle shall be exhibited for sale on the lot.
4. Stored recreational vehicles shall be screened in such a manner that they are not visible
from abutting public roads, residences or approved subdivision lots.
5. Site density shall not exceed twenty (20) tent sites or sixteen (16) recreational vehicle sites
per acre (excluding circulation roads).
6. Campsites located in a shoreland area, shall have a minimum shore frontage of seventy-five
(75) feet.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 29 -
7. A minimum of three hundred (300) square feet of off-street parking plus maneuvering space
shall be provided for each recreational vehicle, tent or shelter site.
8. There shall be a minimum of twenty-five (25) feet between recreational vehicles.
9. There shall be a minimum of seventy-five (75) feet between recreational vehicles and tent
sites.
10. Each recreational vehicle, tent site or covered shelter site shall include at least one picnic
table per site, and at least one (1) covered trash receptacle for every three (3) sites. Trash
receptacles shall be emptied at least once per day.
11. There shall be one toilet and lavatory for each five (5) campsites. Water and sewage
systems shall conform to state regulation.
12. Each campsite shall be equipped with a masonry or metal fireplace, the construction of
which is approved by the Blue Hill Fire Chief.
L. Signs
Criterion: Adequate provision has been made to ensure that any signs associated with the
project do not create a safety hazard.
Minimum standards:
1. Where vision may be obscured entering a public road the whole of a sign board or display
elements of any free-standing sign shall be either below three (3) feet or above seven (7)
feet in height above street level.
2. Any free-standing sign located in any yard space abutting a public road shall be set back at
least ten (10) feet from the edge of the traveled way of such public road and at least twelve
(12) feet from all other lot lines. Where an existing principal structure is located within
fifteen (15) feet of the edge of the traveled way of a public road, a free-standing sign may
be located no closer than five (5) feet to the edge of the traveled way.
3. These sign design and placement standards shall not apply to the following:
a. Legal notices, identification, informational or directional control signs erected or
required by a governmental entity; and
b. Signs that guide or direct traffic and parking on private property, but bear no advertising
or commercial identification.
M. Site Conditions
Criterion: Adequate provision has been made to ensure that, during construction, the site and
surrounding area is safe.
Minimum standards:
1. During construction, the site shall be maintained and left each day in a safe and sanitary
manner, and any condition that could lead to personal injury or property damage, shall be
immediately corrected by the applicant upon an order by the CEO or other authorized
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 30 -
person. The applicant shall make provision for disposal of oil and grease from equipment,
and the site area should be regularly treated to control dust from construction activity; and
2. Developed areas shall be cleared of all stumps, litter, rubbish, brush, weeds, dead and dying
trees, roots, and debris. Excess or scrap building materials shall be removed or destroyed
immediately upon the request of and to the satisfaction of the CEO.
N. Permissible Solar Farms
Criterion: Permissible solar farms shall meet the following minimum standards, in addition to
the other requirements of this Ordinance.
Minimum Standards:
1. Minimum Setbacks. Permissible solar farms and all structures shall meet the following
minimum setbacks:
Minimum setback from any
lot line
Minimum setback from any
residence on an abutting
lot
Local-scale solar farm
50 feet
150 feet
Solar microgrid
As the permitting authority determines is necessary to
satisfy any other applicable requirements of this Ordinance
2. The height of any ground-mounted solar photovoltaic (PV) panel associated with a
permissible solar farm shall not exceed twenty-five (25) feet.
3. Decommissioning and Removal; Abandonment. The owner or operator of record of a
permissible solar farm shall, at its expense, be responsible for the decommissioning and
removal of the permissible solar farm, in compliance with a decommissioning plan
approved by the permitting authority, within twelve (12) months of the end of the
manufacturer-identified useful life of the solar photovoltaic (PV) technology, or 90 days of
the receipt of a notice to the owner or operator of record of a determination by the CEO
that the permissible solar farm has been abandoned. A permissible solar farm shall be
considered abandoned if it ceases to generate electricity for a consecutive period of twelve
(12) months. The permitting authority may extend the 12-month decommissioning deadline
if the owner or operator of record demonstrates that the solar photovoltaic (PV) technology
is likely to remain economically feasible for its intended use for longer than twelve (12)
months after the end of its manufacturer-identified useful life
4. Performance Guarantee. The permitting authority may, as a condition of approval, require
the owner of a permissible solar farm to provide a performance guarantee in the form of an
escrow account, irrevocable letter of credit, or other form satisfactory to the Town in an
amount equal to the anticipated total cost of decommissioning. The amount of the
performance guarantee may be reviewed and adjusted by the permitting authority from
time to time during the manufacturer-identified useful life of the solar photovoltaic (PV)
technology if the anticipated cost of decommissioning materially changes.
Blue Hill Commercial Site Plan Review Ordinance
Section 6. Site Plan Review Criteria
- 31 -
O. Affordable Housing Development
Criterion: An affordable housing development shall meet the following minimum standards, in
addition to the other requirements of this Ordinance.
Minimum Standards:
1. More than half of the total dwelling units in the affordable housing development must be
designated as affordable rental units or affordable homeownership units.
2. Prior to the sale or occupancy of any unit within an affordable housing development, the
owner of the affordable housing development must execute a restrictive covenant, recorded
in the Hancock County Registry of Deeds and enforceable by a third party acceptable to the
Planning Board, ensuring that, for at least thirty (30) years after completion of construction,
occupancy of all of the units designated affordable in the development will remain limited to
households at or below 80% (for rental housing) or 120% (for owned housing) of the local
area median income at the time of initial occupancy. The restrictive covenant must run with
the land and encumber the affordable housing development, be binding upon the developer
(for rental housing) or the unit owners (for owned housing) and their successors and assigns,
and inure to the benefit of and be enforceable by the Town of Blue Hill and a third party
acceptable to the Planning Board.
3. The developer of an affordable housing development must make adequate provision for the
long-term maintenance, repair, and improvement of any septic systems and drinking water
supplies proposed to serve the units within the affordable housing development, including a
process of collection and enforcement to obtain capital improvement funds from the
developer (for rental housing) or the unit owners (for owned housing).
4. Nothing in this section exempts an affordable housing development from any other
requirements of this Ordinance or any other municipal ordinances or regulations, including
any subdivision or shoreland zoning requirements.
P. Ordinance Conformity
Criterion: Adequate provision has been made to ensure that the proposed project conforms in
all respects with the provisions of this Ordinance.
Blue Hill Commercial Site Plan Review Ordinance
Section 7. Enforcement
- 32 -
Section 7. Enforcement
A. Enforcement Authority
The CEO is authorized to enforce the provisions of this Ordinance, and to take legal action for
enforcement at the direction of the Municipal Officers of the Town.
B. Violations
1. Any person who undertakes any land use activity listed in Section 3 as requiring a Site Plan
Review Permit, without first obtaining such permit, violates this Ordinance. Each day that
such use continues shall constitute a separate violation of this Ordinance.
2. Any person who, having received a Site Plan Review Permit, thereafter conducts the land
use activity in such a manner contrary to any condition set forth in the Site Plan Review
Permit, or to the provisions of this Ordinance, violates this Ordinance. Each day that such
use continues shall constitute a separate violation of this Ordinance.
3. Every violation of this Ordinance may be prosecuted pursuant to 30-A M.R.S. § 4452.