Chapter 4
Shoreland Zoning
Ordinance
AN ORDINANCE AMENDING
THE SHORELAND ZONING ORDINANCE
THE TOWN OF BRADLEY
ENACTED AND ORDAINED, Councilors into an ordinance this 17" day of December 2017 of the Town of Bradley
County of Penobscot County in lawful session duly assembled.
Councilors of the Town of Bradley A True Copy:
Council Chair, Mark Ketch Attest: Town Clerk Melissa L. Doane
vcaue 4 ; s er
Duane Lugdon
- Richard . :
Sally Lith
Harley Carmichael
a | t dedi
<-- -- -- A
se S 3 | 2 bi valan
c = = i r 8 Sfeseye
o2% © Q EReteete satis
gee 3 S| 5) PRR
CT itt ta) vo O KI g8 tae 2 ve:
293a6 2 2] Re EE bie
z 83,27
ae oe! ony 2 Hanne
waosEec "aw Hi S . i Hy ate
Geronss6 Ss oo . i |
FEseERONL Ee § fi :
BPs e€angagz cf
Sse esi lll
-- WY oS | did i
ee a
Bi Se nem Oe ef. ae
Ge ot St ao AS OS™
| ee FP ape SG OS = Ff
5 x oP @ ss ae
8 'ie EN
9 = » RW, Sore
° > D. % 8 Ft
Town of Bradley -
Shoreland Zoning Ordinance
C TOWN OF BRADLEY :
SHORELAND ZONING ORDINANCE
TABLE OF CONTENTS
1. PULPOSES 00... .eceeceesscecceeserecsseneneveessessessesssseseesesaesuesneaeseeneessaassssscsesesessensesecatenesacsecneerenseesssesestessees L
2. AUthOrity.... cc cscssssssccseecnesecscsessensesesesssssessesenseescseseeesseesesessscessassssssessssesscsesssesesssecsasstescease
3. Applicability ......c..ceccccscscssssssssesesssseccsessesversecsessesesesseseesesesscsusseseeseessesseancarsesscavarcarsecsearsasseersanseeel
4. Effective Date of Ordinance and Ordinance Amendment ...........c:cccccccsceeesesseseesesenseeesesecseseeeal
5. Availability 0... ce cseecssessssseccececenessessecsessecssessessesssseesscseessesscussassessesssassesaussacasssassasssessesseseeeel
6. Severability cee seeecsesessesesseecsceecscceseseesesusesseesassesessssessessesssessaasceseescecseseescescersesseecseesesesseel
7. Conflicts with Other Ordinances 0.0.0... cee ccsecsessesseseesesescescescseesetaseesssencatessesssetsessesessssceesscencen
8. Amendment wee seeseeseseseessessesesscseescscescescesesscsassessesncasssescsasessansatsacsesncsecsacsecsessesessensssceavesseed,
9. Districts and Zoning Map .0......eceesssesssseesssssscssessescescaecaessccessenessesecaesecancessassessseseensessatsacenecnseed
A. Official Shoreland Zoning Map .....cccccccscecscesssessescsesessescsensesesseecsesseseaseessessnscaeesseaesneeteed, _
B. Scale Of Map ou... ce scccsesseescssscsessecnscsenscsscssssaeseesaesseesessessssscsacoecacensnscescascnecescescnesseesseasesesd
C. Certification of Official Shoreland Zoning Map .........cscccssscssscssseessecsesceressescsesessssesesesesene,
D. Changes to the Official Shoreland Zoning Map ...........cccccsscesessecsesscssesscseesascarseccensssesseesenee
10. Interpretation of District Boundaries ........c.ccccccssescsseseceesceneceesesscsecsecscansateassasstcsecsteesstsscssseeveeal
11. Land Use Requirements... ecesssseccssescescsersssesesesesenssnesenssscsseaesessacsessssessescascessneseecseessensesd
12. Nonconformannce........ceceecssescssesssssssescesceseesenescesessevecsesacsecsceseaecaesaseacasssessessasssscesceesserssessecsacsned
C A. PULPOSE 000... ec eeseeeceseeeceeseesescnsseccesesasnseseesnesscsnsaassassesssessesecaseaseatensesscoacaeeseestentesteeteatenesened
B. Gomera... eceecescsssessesssssscesecsessesesessesaecaneaecsussssssssssssssseascascaeesuenseseeeseeeteaeeateateanseesssseecaeed
C. Nonconforming Structures... ceeeseseeseesecescesessesesceeesceneessnecsessesscatsaseassecsscseesesseseerenesd
D. Nonconforming USES ..0..... cc cccsssseessessessencescesscssessecsessesscseestestesnecnseassaseasessessessesssesesssesceeseas
EB, Nonconforming Lots... cccssssscsssssscssecensesessestessccssseessesseatcasessssssessessssssssssssssersesseesenssnsssee®
13. Establishment of Districts 00... ccc cecesssscesessssssessessessessessesscsscssessecaesasccessesescescesesesssessseassessncanes
A. Resource Protection District 0.0... ce cceccsssesssesseseecssersessesseessecescseseeseanesseessecsesensesssenseenesesD
B. Limited Residential District....0..ccccccsessessesseessssscereseescsecsesseseesesscsseacsecssseccaseserscsssreesssessenad
C. Stream Protection District... cseccesssessssessseessestecsescsoesssssessesseeseeseeaeeecseesesensensensensesceeseD
14, Table of Land Uses... eeeceseessessecsseesecssesensenccssenesssacsecseeassesseesensesseassasssessessessaesorseeseeserae O
15. Land Use Standards oc eeccssscessccsscscesesssessesecenencssesescssesesssseseeassessescseessatssesensvecseseescessese] 2
A. Minimum Lot Standards «0.0... ccscssssesssssesssssscsscesesenesenesersessaessssesseassenenesavecsesseesetsesterse LD
B. Principal and Accessory Structures ........cccccssscsesssscsesssscsessescseesssessccsesessesesseaeeesseereesseesseeel 3
C. Piers, Docks, Wharves, Bridges and Other Structures and Uses Extending or Located .
Below the Normal High-Water Line of a Water Body or Within a Wetland, and Shoreline
Stabilization 2... ese ssseecsscecesessesceecseessesssseseseesessscaesenscsessascaseeseesteceesesscsesstsasssssenseresesee LO
D. Campground 0.00... ee ceeeeesseessecsetsecssessessesseseessesscsscsessecessssesassasssseasesseasessensenrestesresseeseseD 7
E. Individual Private Campsites 0.0... .cccccscssssesssseecesecsceeesecesseesseesessesseassseesessescssscsaseaseaceseael 7
F. Commercial and Industrial Uses... ccccssssssescesscsssceessessescesseseeecseceesecsecseestersensetearsseee LS
G. Parking Areas... cess csesesseseesessesessesescescaecessecnssssseesasscesessscencasseescssesessestacessacsesseneescrensel &
H. Roads and Driveways ......cccsscsseceecsessessesseeeeseesesseaseacssessssesecsecsesseseesearestssesareessessteatseesseeens Ll
- J. Storm Water Runoff oo... eee ccsseecssceseessssssecssssseeseseasesecessesseseesssesaeseteessecsecsesesssereeseeeesD lL
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" Tev. 2017
Town of Bradley
Shoreland Zoning Ordinance
( K. Septic Waste Disposal 00.0... cceccccsecesseeesesessseeresceecneseeassesesssesesnseeseesseecsesscsesessssestsassessens 2d
: L. Essential Services .0.....cccccccsssssssssssscecsecccessecassarsessecsessesesssetsevecsecescssescassusscescasssessessssvesenee 22,
M. Mineral Exploration and Extraction 0.0... ccccccsesssssssesssescsessecssscscsnscseessssesesesssescensvessssseenes la
N. Agriculture... csesesseeseessesseeseseesessesecessesasscssessenssassassscasesssevsesssescecessecsecessessscssessessseeee23
O. Timber Harvesting ~ Repealed as of January 1, 2013 vce icccccescsessessssscsssescsesesscsseesseel4
P. Clearing or Removal of Vegetation for Activities Other Than Timber Harvesting..........24
Q. Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal...........cccsccsessssesesseseseseen 27
R. Exemptions to Clearing and Vegetation Removal Requirements ...........:ccccsessseseesseee 28
S. Revegetation Requirements ..........cccceecesscsessssesessescsessssessescaesecsesesersesesessessssssvscasestsesseseseees SO
T. Erosion and Sedimentation Control ........ccscecsesessesseseesesseseesessessescsscstescsessesseesssssseassaseseed
WU. SOUS see eeccseseseeseseseeeenesesssassnesseceneseesseessevsnesssussessessscsusavsneneseersacsueasssueereacaneassusasetseeaeeneee D3
Vi. Water Quality... ceccssssssscsscsessescesessesesessesseseesesecsessessessessssssscsscsesseecsesssessasensensaseaseaensd
W. Archaeological Site... ccc cssscsessesessesssssssssessessescsecscssessersesessesassasssanssessssssacansseesencvesseensd
16. AAMAIMIStrAatiON ..... ec seteeeeeneceeesceccsecsessesescesesccnesaesterscatsassessscaesaseassnsscaecaeseeecsssessessavseesasseessd 9
A. Administering Bodies and Agents .........cccccccsssssssssesssssssscssesescecsesscsesseassessssesssssscacssssvscrenne G3
B. Permits Required oo... ee sescecceseseesesessesceecsscsscsesnesseseesesscsusassassssessesscseseeecsessenscnessesseseeesG4
C. Permit Application... cc cccsccsssseesesecseseeseesssesscsnsessacsassecssesssacessenscnccscssssessssssassassesssseee 4
D. Procedure for Administering Permits ............ccccccsscsscsscsscescsseescessesseesssecnssssssessessssseseesseseees dD
E. Special Exceptions... ccctsccccsesesesesesetsesceecsecssacseeecsecesessasasseescassesacssessseasseseeessesseseseeees dO
F. Expiration of Permit .0.......ccccccccsscssssssscsssssesceseesseseeceecscsncesscsessessscssesacscsessaesaesaseaseaseaseaeeeedO
G. Installation of Public Utility Service oo... eseseseeseesessessessssechessescescseescecssvsecessscsscsseseseesed 7
HL, Appeals «00.0... cccccccsssssessescssesssscsscseseescesesenscsessenaesseasessnessecsessesessesaussesseassesseesssessaccssesssscsensd P
C I. Emforcement....... cece ssssssesesseseseseseeseseseessseesesessesenscacesseseseassecscessseessassssesssssevsessesveesee4 0
17, Defimitions oe eee cceseecsceseesensesesesceasseseecesssesssssssescsscecseseesenscessetscassavscstssesssssssssecessaveseesseree4
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev, 2017
06-96 Bradley Shoreland Zoning Ordinance
C 1. Purposes. The purposes of this Ordinance are to further the maintenance of safe and-
healthful conditions; to prevent and control water pollution; to protect fish spawning
grounds, aquatic life, bird and other wildlife habitat; to protect buildings and lands from
flooding and accelerated erosion; to protect archaeological and historic resources; to protect
commercial fishing and maritime industries; to protect freshwater and coastal wetlands; to
control building sites, placement of structures and land uses; to conserve shore cover, and
visual as well as actual points of access to inland and coastal waters; to conserve natural
beauty and open space; and to anticipate and respond to the impacts of development in
shoreland areas.
2. Authority. This Ordinance has been prepared in accordance with the provisions of Title 38
sections 435-448 of the Maine Revised Statutes Annotated (M.R.S.A.).
3. Applicability. This Ordinance applies to all land areas within 250 feet, horizontal distance,
of the normal high-water line of great ponds; within 250 feet, horizontal distance, of the
normal high-water line of rivers; within 250 feet, horizontal distance, of the upland edge of a
coastal wetland, including all areas affected by tidal action; within 250 feet, horizontal
distance, of the upland edge of a freshwater wetland; and within 75 feet, horizontal distance,
. of the normal high-water line of a stream. This Ordinance also applies to any structure built
on, over or abutting a dock, wharf or pier, or other structure extending or located below the
normal high-water line of a water body or within a wetland.
4 4. Effective Date of Ordinance and Ordinance Amendments
This Ordinance, which was adopted by the municipal legislative body on December 12,
2017, shall not be effective unless approved by the Commissioner of the Department of
Environmental Protection. A certified copy of the Ordinance, or Ordinance Amendment,
attested and signed by the Municipal Clerk, shall be forwarded to the Commissioner for
approval. If the Commissioner fails to act on this Ordinance or Ordinance Amendment,
within forty-five (45) days of his/her receipt of the Ordinance, or Ordinance Amendment, it
shall be automatically approved. Any application for a permit submitted to the municipality
within the forty-five (45) day period shall be governed by the terms of this Ordinance, or
Ordinance Amendment, if the Ordinance, or Ordinance Amendment, is approved by the
Comunissioner.
5. Availability. A certified copy of this Ordinance shall be filed with the Municipal Clerk and
shall be accessible to any member of the public. Copies shall be made available to the public
at reasonable cost at the expense of the person making the request. Notice of availability of
this Ordinance shall be posted.
6. Severability. Should any section or provision of this Ordinance be declared by the courts to
be invalid, such decision shall not invalidate any other section or provision of the Ordinance.
7. Conflicts with Other Ordinances. Whenever a provision of this Ordinance conflicts with or
; is inconsistent with another provision of this Ordinance or of any other ordinance, regulation
< or statute administered by the municipality, the more restrictive provision shall control.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-l-
06-96 Bradley Shoreland Zoning Ordinance
- 8. Amendments. This Ordinance may be amended by majority vote of the legislative body.
Copies of amendments, attested and signed by the Municipal Clerk, shall be submitted to the
Commissioner of the Department of Environmental Protection following adoption by the
municipal legislative body and shall not be effective unless approved by the Commissioner.
If the Commissioner fails to act on any amendment within forty-five (45) days of his/her
receipt of the amendment, the amendment is automatically approved. Any application for a
permit submitted to the municipality within the forty-five (45) day period shall be governed
by the terms of the amendment, if such amendment is approved by the Commissioner.
9, Districts and Zoning Map
A. Official Shoreland Zoning Map. The areas to which this Ordinance is applicable are
hereby divided into the following districts as shown on the Official Shoreland Zoning
Map(s) which is (are) made a part of this Ordinance:
(1) Resource Protection
(2) Limited Residential
(3) Stream Protection
B. Scale of Map. The Official Shoreland Zoning Map shall be drawn at a scale of not less
than: 1 inch = 2000 feet. District boundaries shall be clearly delineated and a legend
4 indicating the symbols for each district shall be placed on the map.
C. Certification of Official Shoreland Zoning Map. The Official Shoreland Zoning Map
shall be certified by the attested signature of the Municipal Clerk and shall be located in
the municipal office. In the event the municipality does not have a municipal office, the
Municipal Clerk shall be the custodian of the map.
D. Changes to the Official Shoreland Zoning Map. If amendments, in accordance with
Section 8, are made in the district boundaries or other matter portrayed on the Official
Shoreland Zoning Map, such changes shall be made on the Official Shoreland Zoning
Map within thirty (30) days after the amendment has been approved by the
Commissioner of the Department of Environmental Protection.
10. Interpretation of District Boundaries. Unless otherwise set forth on the Official Shoreland
Zoning Map, district boundary lines are property lines, the centerlines of streets, roads and
rights of way, and the boundaries of the shoreland area as defined herein. Where uncertainty
exists as to the exact location of district boundary lines, the Board of Appeals shall be the
final authority as to location.
11. Land Use Requirements. Except as hereinafter specified, no building, structure or land shall
hereafter be used or occupied, and no building or structure or part thereof shall hereafter be
erected, constructed, expanded, moved, or altered and no new lot shall be created except in
conformity with all of the regulations herein specified for the district in which it is located,
C unless a variance is granted.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
~2-
06-96 Bradley Shoreland Zoning Ordinance
C 12. Nonconformance
A. Purpose. It is the intent of this Ordinance to promote land use conformities, except that
nonconforming conditions that existed before the effective date of this Ordinance or
amendments thereto shall be allowed to continue, subject to the requirements set forth in
Section 12. Except as otherwise provided in this Ordinance, a nonconforming condition
shall not be permitted to become more nonconforming.
B. General
(1) Transfer of Ownership. Nonconforming structures, lots, and uses may be
transferred, and the new owner may continue the nonconforming use or continue to
use the nonconforming structure or lot, subject to the provisions of this Ordinance.
(2) Repair and Maintenance. This Ordinance allows, without a permit, the normal
upkeep and maintenance of nonconforming uses and structures including repairs or
renovations that do not involve expansion of the nonconforming use or structure, and
such other changes in a nonconforming use or structure as federal, state, or local
building and safety codes may require.
C. Nonconforming Structures
C (1) Expansions. All new principal and accessory structures, excluding functionally
water-dependent uses, must meet the water body, tributary stream, or wetland setback
requirements contained in Section 15(B)(1). A nonconforming structure may be
added to or expanded after obtaining a permit from the same permitting authority as
that for a new structure, if such addition or expansion does not increase the
nonconformity of the structure and is in accordance with Section 12(C)(1), sub
sections (a), (b); and (c) below.
(a) Expansion of an accessory structure that is located closer to the normal high-water
line of a water body, tributary stream, or upland edge of a wetland than the
principal structure is prohibited, even if the expansion will not increase
nonconformity with the water body, tributary stream or wetland setback
requirement.
(b) Expansion of any portion of a structure within 25 feet of the normal high-water
line of a water body, tributary stream or upland edge of a wetland is prohibited,
even if the expansion will not increase nonconformity with the water body,
tributary stream or wetland setback requirement.
(c) Notwithstanding Sections 12(C)(1)(b), ifa legally existing nonconforming
principal structure is entirely located less than 25 feet from the normal high-water
( line of a water body, tributary stream or upland edge of a wetland, that structure
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-3-
06-96 Bradley Shoreland Zoning Ordinance
< : . may be expanded as follows, as long as all other applicable standards of this
Ordinance are met and the expansion is not prohibited by Section 12(C)(1) above:
(i) The maximum total footprint of the principal structure may not be expanded
to an area greater than 800 square feet or 30% larger than the footprint that
existed on January 1, 1989, whichever is greater.
(ii) The maximum height of the principal structure may not be made greater than
15 feet or the height of the existing structure, whichever is greater.
(d) All other legally existing nonconforming principal and accessory structures that
do not meet the water body, tributary stream or wetland setback requirements may
be expanded or altered as follows, as long as other applicable land use standards
of this Ordinance are met and the expansion is not prohibited by Section 12(C)(1)
and subsections (a), (b) or (c) above:
(i) For structures located less than 75 feet from the normal high-water line of a
water body, tributary stream or upland edge of a wetland, the maximum
combined total footprint of all structures may not be expanded to an area
greater than 1,000 square feet or 30% larger than the footprint that existed on
January 1, 1989, whichever is greater.
( ; (ii) For structures located less than 75 feet from the normal high-water line of a
~ water body, tributary stream or upland edge of a wetland, the maximum height
of any structure may not be made greater than 20 feet or the height of the,
existing structure, whichever is greater.
(iii)For structures located less than 100 feet from the normal high-water line of
Chemo Pond, the maximum combined total footprint of all structures may not
be expanded to an area greater than 1,500 square feet or 30% larger than the
footprint that existed on January 1, 1989, whichever is greater.
(iv) For structures located less than 100 feet from the normal high-water line of
Chemo Pond, the maximum height of any structure may not be made greater
than 25 feet or the height of the existing structure, whichever is greater.
(v) For structures located less than 100 feet from the normal high-water line of
Chemo Pond, any portion of those structures located less than 75 feet from the
normal high-water line of a water body, tributary stream or upland edge of a
wetland must meet the footprint and height requirements of Sections
12(C)(1)(d)G@) and (ii).
(e) In addition to the limitations in Section 12(C)(1) and subsections (a), (b) and (c)
above, structures that are nonconforming due to their location within the Resource
( Protection District and are located at less than 250 feet from the normal high-
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-4-
06-96 Bradley Shoreland Zoning Ordinance
C : water line of a water body or the upland edge of a wetland may be expanded or
altered as follows, as long as other applicable standards of this Ordinance are met:
(i) The maximum combined total footprint of all structures may not be expanded
to an area greater than 1,500 square feet or 30% larger than the footprint that
existed at the time the Resource Protection District was established on the lot,
whichever is greater.
(ii) The maximum height of any structure may not be made greater than 25 feet or
the height of the existing structure, whichever is greater.
(iii)Any portion of the structures located less than 100 feet from the normal high-
water line of Chemo Pond, must meet the footprint and height requirements of
Sections 12(C)(1)(d)(iit) and (iv).
(iv) Any portion of the structures located less than 75 feet from the normal high-
water line of a water body, tributary stream or upland edge of a wetland must
meet the footprint and height requirements of Sections 12(C)(1)(d)(i) and (ii).
(f) The applicant must have plan(s) that are approved by the municipality for
expansions under Section 12(C)(1) filed in the registry of deeds of the county in
which the property is located within 90 days of approval. The recorded plan(s)
( must show the existing and proposed footprint of the non-conforming structure,
- the existing and proposed structure height, the footprint of any other structures on
the parcel, and the shoreland zone boundary.
(2) Foundations. Whenever a new, expanded or replacement foundation is constructed
under a nonconforming structure, the structure and new foundation must be placed
such that the shoreline setback requirement is met to the greatest practical extent as
determined by the Planning Board or its designee, basing its decision on the criteria
specified in Section 12(C)(3) below.
(3) Relocation. A nonconforming structure may be relocated within the boundaries of the
parcel on which the structure is located provided that the site of relocation conforms
to all setback requirements to the greatest practical extent as determined by the
. Planning Board or its designee, and provided that the applicant demonstrates that the
present subsurface sewage disposal system meets the requirements of State law and
the State of Maine Subsurface Wastewater Disposal Rules (Rules), or that a new
system can be installed in compliance with the law and said Rules. In no case shall a
structure be relocated in a manner that causes the structure to be more
nonconforming.
In determining whether the building relocation meets the setback to the greatest
practical extent, the Planning Board or its designee shall consider the size of the lot,
- the slope of the land, the potential for soil erosion, the location of other structures on
C the property and on adjacent properties, the location of the septic system and other
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-5-
06-96 Bradley Shoreland Zoning Ordinance
( " on-site soils suitable for septic systems, and the type and-amount of vegetation to be
removed to accomplish the relocation.
When it is necessary to remove vegetation within the water or wetland setback area in
order to relocate a structure, the Planning Board shall require replanting of native
vegetation to compensate for the destroyed vegetation. in accordance with Section
15(S). In addition, the area from which the relocated structure was removed must be
replanted with vegetation. Replanting shall be required as follows:
Trees removed in order to relocate a structure must be replanted with at least one
native tree, three (3) feet in height, for every tree removed. If more than five trees are
planted, no one species of tree shall make up more than 50% of the number of trees
planted. Replaced trees must be planted no further from the water or wetland than the
trees that were removed.
Other woody and herbaceous vegetation, and ground cover, that are removed or
destroyed in order to relocate a structure must be re-established. An area at least the
same size as the area where vegetation and/or ground cover was disturbed, damaged,
or removed must be reestablished within the setback area. The vegetation and/or
ground cover must consist of similar native vegetation and/or ground cover that was
; disturbed, destroyed or removed.
C Where feasible, when a structure is relocated on a parcel the original location of the
. structure shall be replanted with vegetation which may consist of grasses, shrubs,
trees, or a combination thereof.
(4) Reconstruction or Replacement. Any nonconforming structure which is located less
than the required setback from a water body, tributary stream, or wetland and which
is removed, or damaged or destroyed, regardless of the cause, by more than 50% of
the market value of the structure before such damage, destruction or removal, may be
reconstructed or replaced provided that a permit is obtained within eighteen (18)
months of the date of said damage, destruction, or removal, and provided that such
reconstruction or replacement is in compliance with the water body, tributary stream
or wetland setback requirement to the greatest practical extent as determined by the
Planning Board or its designee in accordance with Section 12(C)(3) above. In no case
shall a structure be reconstructed or replaced so as to increase its nonconformity.
If the reconstructed or replacement structure is less than the required setback it shall
not be any larger than the original structure, except as allowed pursuant to Section
12(C)(1) above, as determined by the nonconforming footprint of the reconstructed or
replaced structure at its new location. If the total amount of footprint of the original
structure can be relocated or reconstructed beyond the required setback area, no
portion of the relocated or reconstructed structure shall be replaced or constructed at
less than the setback requirement for a new structure.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-6-
06-96 Bradley Shoreland Zoning Ordinance
C - When it is necessary to remove vegetation in order to replace or reconstruct a
structure, vegetation shall be replanted in accordance with Section 12(C)(3) above.
Any nonconforming structure which is located less than the required setback from a
water body, tributary stream, or wetland and which is removed by 50% or less of the
market value, or damaged or destroyed by 50% or less of the market value of the
structure, excluding normal maintenance and repair, may be reconstructed in place if
a permit is obtained from the Code Enforcement Officer within one year of such
damage, destruction, or removal.
In determining whether the building reconstruction or replacement meets the setback
to the greatest practical extent the Planning Board or its designee shall consider, in
addition to the criteria in Section 12(C)(3) above, the physical condition and type of
foundation present, if any.
(5) Change of Use of a Nonconforming Structure. The use of a nonconforming
structure may not be changed to another use unless the Planning Board, after
receiving a written application, determines that the new use will have no greater
adverse impact on the water body, tributary stream, or wetland, or on the subject or
adjacent properties and resources than the existing use.
In determining that no greater adverse impact will occur, the Planning Board shall
C require written documentation from the applicant, regarding the probable effects on
. public health and safety, erosion and sedimentation, water quality, fish and wildlife
habitat, vegetative cover, visual and actual points of public access to waters, natural
beauty, floodplain management, archaeological and historic resources, and
commercial fishing and maritime activities, and other functionally water-dependent
uses.
D. Nonconforming Uses
(1) Expansions. Expansions of nonconforming uses are prohibited, except that
nonconforming residential uses may, after obtaining a permit from the Planning
Board, be expanded within existing residential structures or within expansions of such
structures as allowed in Section 12(C)(1) above.
(2) Resumption Prohibited. A lot, building or structure in or on which a nonconforming
use is discontinued for a period exceeding one year, or which is superseded by a
conforming use, may not again be devoted to a nonconforming use except that the
Planning Board may, for good cause shown by the applicant, grant up to a one year
extension to that time period. This provision shall not apply to the resumption of a use
of a residential structure provided that the structure has been used or maintained for
residential purposes during the preceding five (5) year period.
- (3) Change of Use. An existing nonconforming use may be changed to another
C nonconforming use provided that the proposed use has no greater adverse impact on
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-7-
06-96 Bradley Shoreland Zoning Ordinance
( i the subject and adjacent properties and resources, including water dependent uses,
- than the former use, as determined by the Planning Board. The determination of no
greater adverse impact shall be made according to criteria listed in Section 12(C)(5)
above.
EK. Nonconforming Lots
(1) Nonconforming Lots: A nonconforming lot of record as of the effective date of this
Ordinance or amendment thereto may be built upon, without the need for a variance, -
provided that such lot is in separate ownership and not contiguous with any other lot
in the same ownership, and that all provisions of this Ordinance except lot area, lot
width and shore frontage can be met. Variances relating to setback or other
requirements not involving lot area, lot width or shore frontage shall be obtained by
action of the Board of Appeals.
(2) Contiguous Built Lots: If two or more contiguous lots or parcels are in a single or
joint ownership of record at the time of adoption of this Ordinance, if all or part of the
lots do not meet the dimensional requirements of this Ordinance, and if a principal
use or structure exists on each lot, the nonconforming lots may be conveyed
separately or together, provided that the State Minimum Lot Size Law (12 M.R.S.A.
sections 4807-A through 4807-D) and the State of Maine Subsurface Wastewater
Disposal Rules are complied with.
C If two or more principal uses or structures existed on a single lot of record on the
effective date of this ordinance, each may be sold on a separate lot provided that the
above referenced law and rules are complied with. When such lots are divided each
lot thus created must be as conforming as possible to the dimensional requirements of
this Ordinance.
(3) Contiguous Lots - Vacant or Partially Built: If two or more contiguous lots or
parcels are in single or joint ownership of record at the time of or since adoption or
amendment of this Ordinance, if any of these lots do not individually meet the
dimensional requirements of this Ordinance or subsequent amendments, and if one or
more of the lots are vacant or contain no principal structure the lots shall be combined
to the extent necessary to meet the dimensional requirements.
This provision shall not apply to 2 or more contiguous lots, at least one of which is
nonconforming, owned by the same person or persons on March 27, 1992, and
recorded in the registry of deeds if the lot is served by a public sewer or can
accommodate a subsurface sewage disposal system in conformance with the State of
Maine Subsurface Wastewater Disposal Rules; and
(a) Each lot contains at least 100 feet of shore frontage and at least 20,000 square feet
of lot area; or
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-8-
06-96 Bradley Shoreland Zoning Ordinance
C ; (b) Any lots that do not meet the frontage and lot size requirements of Section
12(E)(3)(a) are reconfigured or combined so that each new lot contains at least
100 feet of shore frontage and 20,000 square feet of lot area.
13. Establishment of Districts
A. Resource Protection District. The Resource Protection District includes areas in which
development would adversely affect water quality, productive habitat, biological
ecosystems, or scenic and natural values. This district shall include the following areas
when they occur within the limits of the shoreland zone, exclusive of the Stream
Protection District.
(1) Floodplains along rivers and floodplains along artificially formed great ponds along
rivers, defined by the 100 year floodplain as designated on the Federal Emergency
Management Agency's (FEMA) Flood Insurance Rate Maps or Flood Hazard
Boundary Maps, or the flood of record, or in the absence of these, by soil types
identified as recent floodplain soils. This district shall also include 100 year
floodplains adjacent to tidal waters as shown on FEMA's Flood Insurance Rate Maps
or Flood Hazard Boundary Maps.
(2) Areas of two or more contiguous acres with sustained slopes of 20% or greater.
a (3) Areas of two (2) or more contiguous acres supporting wetland vegetation and hydric
NX soils, which are not part of a freshwater or coastal wetland as defined, and which are
not surficially connected to a water body during the period of normal high water.
NOTE: These areas usually consist of forested wetlands abutting water bodies and non-
forested wetlands.
(4) Land areas along rivers subject to severe bank erosion, undercutting, or river bed
movement, and lands adjacent to tidal waters which are subject to severe erosion or
mass movement, such as steep coastal bluffs.
B. Limited Residential District. The Limited Residential District includes those areas
suitable for residential and recreational development. It includes areas other than those in
the Resource Protection District, or Stream Protection District.
C. Stream Protection District. The Stream Protection District includes all land areas within
seventy-five (75) feet, horizontal distance, of the normal high-water line of a stream,
exclusive of those areas within two-hundred and fifty (250) feet, horizontal distance, of
the normal high-water line of Chemo Pond, or a river, or within two hundred and fifty
(250) feet, horizontal distance, of the upland edge of a freshwater or coastal wetland.
Where a stream and its associated shoreland area are located within two-hundred and
fifty (250) feet, horizontal distance, of the above water bodies or wetlands, that land area
C shall be regulated under the terms of the shoreland district associated with that water
body or wetland.
. Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-9.
06-96 Bradley Shoreland Zoning Ordinance
C 14. Table of Land Uses. All land use activities, as indicated in Table 1, Land Uses in the
Shoreland Zone, shall conform with all of the applicable land use standards in Section 15.
The district designation for a particular site shall be determined from the Official Shoreland
Zoning Map.
Key to Table 1:
Yes - Allowed (no permit required but the use must comply with all applicable land use
standards)
No- Prohibited
PB- Allowed with permit issued by the Planning Board. |
CEO - Allowed with permit issued by the Code Enforcement Officer
LPI- Allowed with permit issued by the Local Plumbing Inspector
Abbreviations:
RP- Resource Protection
C LR- Limited Residential
SP- Stream Protection
C
fase on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
06-96 Bradley Shoreland Zoning Ordinance
C TABLE 1. LAND USES IN THE SHORELAND ZONE .
~ LAND USES ; DISTRICT
SP RP LR
1. Non-intensive recreational uses not requiring structures such as hunting, fishing and yes yes yes
hiking
2.___ Motorized vehicular traffic on existing roads and trails yes yes yes
3.__ Clearing or removal of vegetation for activities other than timber harvesting CEO CEO! yes
4. __ Fire prevention activities yes yes yes
5.__ Wildlife management practices yes yes yes
6,___ Soil and water conservation practices ' yes yes yes
7. Mineral exploration no yes? yes?
8__ Mineral extraction including sand and gravel extraction no PB? PB
9, ___ Surveying and resource analysis yes yes yes
10. Emergency operations yes yes yes
li. Agriculture yes PB yes
12. Aquaculture PB PB PB
13. Principal structures and uses
A. Once and two family residential. including driveways PB' PBS CEO
B. _ Mutti-unit residential no no PB
C. _ Commercial No? No' No?
D. _ Industrial no no no
E. _ Governmental and institutional no no PB
. F. Small non-residential facilities for educational, scientific, or nature interpretation PBt PB CEO
purposes
14. Structures accessory to allowed uses . PB PB CEO
15. Piers, docks, wharfs, bridges and other structures and uses extending or located
, below the normal high-water line or within a wetland
a. Temporary CEO" CEO" CEO"
b. Permanent PB PB PB
16, _Conversions of seasonal residences to year-round residences LPI LPI LPI
17, Home occupations PB PB PB
18.__ Private sewage disposal systems for allowed uses LPI LPI LPI
19, Essential services
; A. Roadside distribution lines (34.5kV and lower) CEO® CEO® yes!t
C B. Non-roadside or cross-country distribution lines involving ten poles or less in the PBS PB* CEO
shoreland zone
€. Non-roadside or cross-country distribution lines involving eleven or more poles in PBS PBS PB
the shoreland zone
D. _ Other essential services PBS PB* PB
20. Service drops, as defined, to allowed uses yes yes yes
21, Public and private recreational areas involving minimal structural development PB PB PB
22.__ Individual private campsites CEO CEO CEO
23. Campgrounds no Nof PB
24. Road construction PB No? PB
25. Parking facilities no No® PB
27.__ Filling and earth moving of <10 cubic yards CEO CEO yes
28, Filling and earth moving of >10 cubic yards PB PB CEO
29. __ Signs yes yes yes
30. Uses similar to allowed uses CEO CEO CEO
31. Uses similar to uses requiring a CEO permit CEO CEO CEO
32. Uses similar to uses requiring a PB permit PB PB PB
1In RP not allowed within 75 feet horizontal distance, of the normal high-water line of Chemo Pond, except to remove safety hazards.
Requires permit from the Code Enforcement Officer if more than 100 square feet of surface areca, in total, is disturbed.
3In RP not allowed in areas so designated because of wildlife value.
'Provided that a variance from the setback requirement is obtained from the Board of Appeals.
5Sce further restrictions in Section 15(L).
'Except when area is zoned for resource protection duc to floodplain criteria in which case a permit is required from the PB.
Except as provided in Section 15(H).
®Single family residential structures may be allowed by special exception only according to the provisions of Section 16(E), Special Exceptions. Two-family
residential structures are prohibited.
Except for commercial uses otherwise listed in this Table, such as marinas and campgrounds, that are allowed in the respective district.
"Excluding bridges and other crossings not involving earthwork, in which case no permit is required.
"Permit not required: but must file a written "notice of intent to construct" with CEO.
NOTE; A person performing any of the following activities shall require a permit from the Department of Environmental Protection, pursuant to 38
MLR.S.A. section 480-C, if the activity occurs in, on, over or adjacent to any freshwater or coastal wetland, great pond, river, stream or brook and
operates in such a manner that material or soil may be washed into them:
A. Dredging, bulldozing, removing or displacing soil, sand, vegetation or other materials;
B. Draining or otherwise dewatering;
( C. Filling, including adding sand or other material to a sand dune; or
~ D. Any construction or alteration of any permanent structure.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-ll-
06-96 Bradley Shoreland Zoning Ordinance
< 15. Land Use Standards. All land use activities within the shoreland zone shall conform with
the following provisions, if applicable.
A. Minimum Lot Standards
(1) Minimum Lot Minimum
Area (sq. ft.) Shore
Frontage (ft.)
(a) Residential per dwelling unit
(1) Within the Shoreland Zone
Adjacent to Tidal Areas 43,560 150
(i) Within the Shoreland Zone
Adjacent to Non-Tidal Areas 43,560 _ 200
(b) Governmental, Institutional, Commercial or Industrial per principal structure
(i) Within the Shoreland Zone
Adjacent to Tidal Areas 43,560 200
(ii) Within the Shoreland Zone
C Adjacent to Non-tidal Areas 60,000 300
o
(c) Public and Private Recreational Facilities
(i) Within the Shoreland Zone Adjacent
to Tidal and Non-Tidal Areas 43,560 200
(2) Land below the normal high-water line of a water body or upland edge of a wetland
and land beneath roads serving more than two (2) lots shall not be included toward
calculating minimum lot area.
(3) Lots located on opposite sides of a public or private road shall be considered each a
separate tract or parcel of land unless such road was established by the owner of land
on both sides thereof after September 22, 1971.
(4) The minimum width of any portion of any lot within one hundred (100) feet, horizontal
distance, of the normal high-water line of a water body or upland edge of a wetland
shall be equal to or greater than the shore frontage requirement for a lot with the
proposed use.
(5) If more than one residential dwelling unit, principal governmental, institutional,
commercial or industrial structure or use, or combination thereof, is constructed or
established on a single parcel, all dimensional requirements shall be met for each
C additional dwelling unit, principal structure, or use.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-12-
06-96 Bradley Shoreland Zoning Ordinance
( B. Principal and Accessory Structures
(1) All new principal and accessory structures shall be set back at least one hundred (100)
feet, horizontal distance, from the normal high-water line of Chemo Pond, and seventy-
five (75) feet, horizontal distance, from the normal high-water line of other water
bodies, tributary streams, or the upland edge of a wetland. In the Resource Protection
District the setback requirement shall be 250 feet, horizontal distance, except for
structures, roads, parking spaces or other regulated objects specifically allowed in that
district in which case the setback requirements specified above shall apply.
NOTE: The Natural Resources Protection Act, 38 M.S.R.A. sections 480-A through 480-HH,
requires the Department of Environmental Protection to designate areas of "significant
wildlife habitat".
Permitting under the Natural Resources Protection Act for activities adjacent to
significant wildlife habitat areas may require greater setbacks. Contact your local
Department of Environmental Protection office to see if additional permitting is
required.
In addition: .
C (a) The water body, tributary stream, or wetland setback provision shall neither apply
to structures which require direct access to the water body or wetland as an
operational necessity, such as piers, docks and retaining walls, nor to other
functionally water-dependent uses.
(b) For principal structures, water and wetland setback measurements shall be taken
from the top of a coastal bluff that has been identified on Coastal Bluff maps as
being "highly unstable" or "unstable" by the Maine Geological Survey pursuant to
its "Classification of Coastal Bluffs" and published on the most recent Coastal Bluff
map. If the applicant and the permitting official(s) are in disagreement as to the
specific location of a "highly unstable" or "unstable" bluff, or where the top of the
bluff is located, the applicant may at his or her expense, employ a Maine Registered
Professional Engineer, a Maine Certified Soil Scientist, a Maine State Geologist, or
other qualified individual to make a determination. If agreement is still not reached,
the applicant may appeal the matter to the board of appeals.
(c) On a nonconforming lot of record on which only a residential structure exists, and it
is not possible to place an accessory structure meeting the required water body,
tributary stream or wetland setbacks, the code enforcement officer may issue a
permit to place a single accessory structure, with no utilities, for the storage of yard
tools and similar equipment. Such accessory structure shall not exceed eighty (80)
( square feet in area nor eight (8) feet in height, and shall be located as far from the
~ shoreline or tributary stream as practical and shall meet all other applicable
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
- 13 - .
06-96 Bradley Shoreland Zoning Ordinance
C - standards, including lot coverage and vegetation clearing limitations. In no case
shall the structure be located closer to the shoreline or tributary stream than the
principal structure.
NOTE:Refer to Section 17 for definitions of coastal wetland and tributary stream.
(2) Principal or accessory structures and expansions of existing structures which are
permitted in the Resource Protection, Limited Residential, and Stream Protection
Districts, shall not exceed thirty-five (35) feet in height.
(a) This provision shall not apply to structures such as transmission towers, windmills,
antennas, and similar structures having no floor area.
(b) The height of a structure shall exclude a nonhabitable feature mounted on a
structure roof for observation purposes, such as a cupola, a dome or a widow's
walk, provided the following conditions are met:
(i) the feature is being added to, or is part of, a conforming structure,
(11) the structure is not located in a Resource Protection or Stream Protection
District,
(ii)the feature does not extend beyond the exterior walls of the structure,
(iv) the feature has a floor area of fifty-three (53) square feet or less, and
( (v) the feature does not increase the height of the structure, as defined, more than
~ seven (7) feet.
(3) The lowest floor elevation or openings of all buildings and structures, including
basements, shall be elevated at least one foot above the elevation of the 100 year
flood, the flood of record, or in the absence of these, the flood as defined by soil types
identified as recent floodplain soils. Accessory structures may be placed in
accordance with the standards of the Floodplain Management Ordinance that is
consistent with the April 2005 or later version under the National Flood Insurance
Program.
(4) Non-vegetated surfaces shall not exceed twenty (20) percent of the portion of the lot
located within the shoreland zone. Non-vegetated surfaces include, but are not
limimted to the following: structures, driveways, parking areas, patios, decks,
retaining walls and access paths. Ledge and rock outcroppings are not counted as
non-vegetated surfaces.
(5) Retaining walls that are not necessary for erosion control shall meet the structure
setback requirement, except for low retaining walls and associated fill provided all of
the following conditions are met:
(a) The site has been previously altered and an effective vegetated buffer does not
( exist;
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-14-
06-96 Bradley Shoreland Zoning Ordinance
4 ~ (b) The wali(s) is(are) at least 25 feet, horizontal distance, from the normal high-
water line of a water body, tributary stream, or upland edge of a wetland;
(c) The site where the retaining wall will be constructed is legally existing lawn or is
a site eroding from lack of naturally occurring vegetation, and which cannot be
stabilized with vegetative plantings;
(d) The total height of the wall(s), in the aggregate, is no more than 24 inches;
(e) Retaining walls are located outside of the 100-year floodplain on rivers, streams,
coastal wetlands, and tributary streams, as designated on the Federal Emergency
Management Agency's (FEMA) Flood Insurance Rate Maps or Flood Hazard
Boundary Maps, or the flood of record, or in the absence of these, by soil types
identified as recent floodplain soils.
(f) The area behind the wall is revegetated with grass, shrubs, trees, or a combination
thereof, and no further structural development will occur within the setback area,
including patios and decks; and
(g) A vegetated buffer area is established within 25 feet, horizontal distance, of the
normal high-water line of a water body, tributary stream, or upland edge of a
wetland when a natural buffer area does not exist. The buffer area must meet the
( following characteristics:
(i) The buffer must include shrubs and other woody and herbaceous vegetation.
Where natural ground cover is lacking the area must be supplemented with
leaf or bark mulch;
(ii) Vegetation plantings must be in quantities sufficient to retard erosion and
provide for effective infiltration of stormwater runoff,
(iii)Only native species may be used to establish the buffer area;
(iv)A minimum buffer width of 15 feet, horizontal distance, is required, measured
perpendicularly to the normal high-water line or upland edge of a wetland;
(v) A footpath not to exceed the standards in Section 15(P)(2)(a), may traverse
the buffer.
NOTE: If the wall and associated soil disturbance occurs within 75 feet, horizontal
distance, of a water body, tributary stream or coastal wetland, a permit pursuant to
the Natural Resource Protection Act is required from the Department of
Environmental Protection.
( (6) Notwithstanding the requirements stated above, stairways or similar structures may be
~. allowed with a permit from the Code Enforcement. Officer, to provide shoreline access
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-15- ,
06-96 Bradley Shoreland Zoning Ordinance ;
( in areas of steep slopes or unstable soils provided: that the structure is limited to a
. maximum of four (4) feet in width; that the structure does not extend below or over the
normal high-water line of a water body or upland edge of a wetland, (unless permitted
by the Department of Environmental Protection pursuant to the Natural Resources
Protection Act, 38 M.R.S.A. section 480-C); and that the applicant demonstrates that no
reasonable access alternative exists on the property.
C. Piers, Docks, Wharves, Bridges and Other Structures and Uses Extending or
Located Below the Normal High-Water Line of a Water Body or Within a Wetland.,
and Shoreline Stabilization
(1) No more than one pier, dock, wharf or similar structure extending or located below the
normal high-water line of a water body or within a wetland is allowed on a single lot;
except that when a single lot contains at least twice the minimum shore frontage as
specified in Section 15(A), a second structure may be allowed and may remain as long
as the lot is not further divided.
(2) Access from shore shall be developed on soils appropriate for such use and constructed
so as to control erosion.
(3) The location shall not interfere with existing developed or natural beach areas.
C (4) The facility shall be located so as to minimize adverse effects on fisheries. -
(5) The facility shall be no larger in dimension than necessary to carry on the activity and
be consistent with the surrounding character and uses of the area. A temporary pier,
dock or wharf in non-tidal waters shall not be wider than six feet for non-commercial
uses.
(6) No new structure shall be built on, over or abutting a pier, wharf, dock or other
structure extending or located below the normal high-water line of a water body or
within a wetland unless the structure requires direct access to the water body or
wetland as an operational necessity. .
(7) New permanent piers and docks on non-tidal waters shall not be permitted unless it is
clearly demonstrated to the Planning Board that a temporary pier or dock is not
feasible, and a permit has been obtained from the Department of Environmental
Protection, pursuant to the Natural Resources Protection Act.
(8) No existing structures built on, over or abutting a pier, dock, wharf or other structure
extending or located below the normal high-water line of a water body or within a
wetland shall be converted to residential dwelling units in any district.
(9) Structures built on, over or abutting a pier, wharf, dock or other structure extending or
located below the normal high-water line of a water body or within a wetland shall
C not exceed twenty (20) feet in height above the pier, wharf, dock or other structure.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-16-
06-96 Bradley Shoreland Zoning Ordinance
C NOTE: New permanent structures, and expansions thereof, projecting into or over water
bodies shall require a permit from the Department of Environmental Protection
pursuant to the Natural Resources Protection Act, 38 M.R.S.A. section 480-C.
Permits may also be required from the Army Corps of Engineers if located in
navigable waters.
D. Campgrounds. Campgrounds shall conform to the minimum requirements imposed
under State licensing procedures and the following:
(1) Campgrounds shall contain a minimum of five thousand (5,000) square feet of land,
not including roads and driveways, for each site. Land supporting wetland vegetation,
and land below the normal high-water line of a water body shall not be included in
calculating land area per site.
(2) The areas intended for placement of a recreational vehicle, tent or shelter, and utility
and service buildings shall be set back a minimum of one hundred (100) feet,
horizontal distance, from the normal high-water line of Chemo Pond, and seventy-
five (75) feet, horizontal distance, from the normal high-water line of other water
bodies, tributary streams, or the upland edge of a wetland.
E. Individual Private Campsites. Individual private campsites not associated with
( campgrounds are allowed provided the following conditions are met:
(1) One campsite per lot existing on the effective date of this Ordinance, or thirty
thousand (30,000) square feet of lot area within the shoreland zone, whichever is less,
may be permitted.
When an individual private campsite is proposed on a lot that contains another principal
use and/or structure, the lot must contain the minimum lot dimensional requirements
for the principal structure and/or use, and the individual private campsite separately.
(2) Campsite placement on any lot, including the area intended for a recreational vehicle
or tent platform, shall be set back one hundred (100) feet, horizontal distance, from
the normal high-water line of Chemo Pond, and seventy-five (75) feet, horizontal
distance, from the normal high-water line of other water bodies, tributary streams, or
the upland edge of a wetland.
(3) Only one recreational vehicle shall be allowed on a campsite. The recreational vehicle
shall not be located on any type of permanent foundation except for a gravel pad, and
. no structure except a canopy shall be attached to the recreational vehicle.
(4) The clearing of vegetation for the siting of the recreational vehicle, tent or similar
C shelter in a Resource Protection District shall be limited to one thousand (1000)
square feet.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-17-
06-96 Bradley Shoreland Zoning Ordinance
C (5) A written sewage disposal plan describing the proposed method and location of
sewage disposal shall be required for each campsite and shall be approved by the
Local Plumbing Inspector. Where disposal is off-site, written authorization from the
receiving facility or land owner is required.
(6) When a recreational vehicle, tent or similar shelter is placed on-site for more than one
hundred and twenty (120) days per year, all requirements for residential structures
shall be met, including the installation of a subsurface sewage disposal system in
compliance with the State of Maine Subsurface Wastewater Disposal Rules unless
served by public sewage facilities.
F. Commercial and Industrial Uses. New commercial and industrial uses are prohibited
within the shoreland zone in the Town of Bradley, except for campgrounds and marinas.
G. Parking Areas
(1) Parking areas shall meet the shoreline and tributary stream setback requirements for
structures for the district in which such areas are located. The setback requirement for .
parking areas serving public boat launching facilities shall be no less than fifty (50)
feet, horizontal distance, from the shoreline or tributary stream if the Planning Board
finds that no other reasonable alternative exists further from the shoreline or tributary
4 stream.
(2) Parking areas shall be adequately sized for the proposed use and shall be designed to
prevent stormwater runoff from flowing directly into a water body, tributary stream
or wetland and where feasible, to retain all runoff on-site.
(3) In determining the appropriate size of proposed parking facilities, the following shall
apply:
(a) Typical parking space: Approximately ten (10) feet wide and twenty (20) feet
long, except that parking spaces for a vehicle and boat trailer shall be forty (40)
feet long.
(b) Internal travel aisles: Approximately twenty (20) feet wide.
H. Roads and Driveways. The following standards shall apply to the construction of roads
and/or driveways and drainage systems, culverts and other related features.
(1) Roads and driveways shall be set back at least one-hundred (100) feet, horizontal
distance, from the normal high-water line of Chemo Pond, and seventy-five (75) feet,
horizontal distance from the normal high-water line of other water bodies, tributary
streams, or the upland edge of a wetland unless no reasonable alternative exists as
- determined by the Planning Board. If no other reasonable alternative exists, the road
C and/or driveway setback requirement shall be no less than fifty (50) feet, horizontal
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-18- .
06-96 Bradley Shoreland Zoning Ordinance
C . distance, upon clear showing by the applicant that appropriate techniques will be used
to prevent sedimentation of the water body, tributary stream, or wetland. Such
techniques may include, but are not limited to, the installation of settling basins,
and/or the effective use of additional ditch relief culverts and turnouts placed so as to
avoid sedimentation of the water body, tributary stream, or wetland.
On slopes of greater than twenty (20) percent the road and/or driveway setback shall
be increased by ten (10) feet, horizontal distance, for each five (5) percent increase in
slope above twenty (20) percent.
Section 15 (H)(1) does not apply to approaches to water crossings or to roads or
driveways that provide access to permitted structures and facilities located nearer to
the shoreline or tributary stream due to an operational necessity, excluding temporary
_ docks for recreational uses. Roads and driveways providing access to permitted
structures within the setback area shall comply fully with the requirements of Section
15(H)(1) except for that portion of the road or driveway necessary for direct access to
the structure.
(2) Existing public roads may be expanded within the legal road right of way regardless
of their setback from a water body, tributary stream or wetland.
(3) New roads and driveways are prohibited in a Resource Protection District except that
: the Planning Board may grant a permit to construct a road or driveway to provide
« access to permitted uses within the district. A road or driveway may also be approved
by the Planning Board in a Resource Protection District, upon a finding that no
reasonable alternative route or location is available outside the district. When a road
or driveway is permitted in a Resource Protection District the road and/or driveway
shall be set back as far as practicable from the normal high-water line of a water
body, tributary stream, or upland edge of a wetland.
(4) Road and driveway banks shall be no steeper than a slope of two (2) horizontal to one
(1) vertical, and shall be graded and stabilized in accordance with the provisions for
erosion and sedimentation control contained in Section 15(Q).
(5) Road and driveway grades shall be no greater than ten (10) percent except for
segments of less than two hundred (200) feet.
(6) In order to prevent road and driveway surface drainage from directly entering water
bodies, tributary streams or wetlands, roads and driveways shall be designed,
constructed, and maintained to empty onto an unscarified buffer strip at least (50) feet
plus two times the average slope, in width between the outflow point of the ditch or
culvert and the normal high-water line of a water body, tributary stream, or upland
edge of a wetland. Surface drainage which is directed to an unscarified buffer strip
shall be diffused or spread out to promote infiltration of the runoff and to minimize
( channelized flow of the drainage through the buffer strip.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-19-
06-96 Bradley Shoreland Zoning Ordinance
C , (7) Ditch relief (cross drainage) culverts, drainage dips and water turnouts shall be
. installed in a manner effective in directing drainage onto unscarified buffer strips
before the flow gains sufficient volume or head to erode the road, driveway, or ditch.
To accomplish this, the following shall apply:
(a) Ditch relief culverts, drainage dips and associated water turnouts shall be spaced
along the road, or driveway at intervals no greater than indicated in the following
table:
Grade Spacing
(Percent) . (Feet)
0-2 ~ 250
3-5 200-135
6-10 100-80
11-15 80-60
16-20 60-45
21+ 40
(b) Drainage dips may be used in place of ditch relief culverts only where the grade is
ten (10) percent or less.
C (c) On sections having slopes greater than ten (10) percent, ditch relief culverts shall
. be placed at approximately a thirty (30) degree angle downslope from a line
perpendicular to the centerline of the road or driveway.
(d) Ditch relief culverts shall be sufficiently sized and properly installed in order to
allow for effective functioning, and their inlet and outlet ends shall be stabilized
with appropriate materials.
(8) Ditches, culverts, bridges, dips, water turnouts and other storm water runoff control
installations associated with roads and driveways shall be maintained on a regular
basis to assure effective functioning.
I Signs. The following provisions shall govern the use of signs in the Resource Protection,
Limited Residential, and Stream Protection Districts:
(1) Signs relating to goods and services sold on the premises shall be allowed, provided
that such signs shall not exceed six (6) square feet in area and shall not exceed two
(2) signs per premises. Signs relating to goods or services not sold or rendered on the
premises shall be prohibited.
(2) Name signs are allowed, provided such signs shall not exceed two (2) signs per
premises, and shall not exceed twelve (12) square feet in the aggregate.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-20 -
06-96 Bradley Shoreland Zoning Ordinance
C (3) Residential users may display a single, one- or two-sided sign not over three (3)
square feet in area relating to the sale, rental, or lease of the premises.
_ (A) Signs relating to trespassing and hunting shall be allowed without restriction as to
number provided that no such sign shall exceed two (2) square feet in area.
(5) Signs relating to public safety shall be allowed without restriction.
(6) No sign shall extend higher than twenty (20) feet above the ground.
(7) Signs may be illuminated only by shielded, non-flashing lights.
Please also see Section V. A. 30. Signs of the Town of Bradley Land Use Ordinance.
J. Storm Water Runoff
(1) All new construction and development shall be designed to minimize storm water
runoff from the site in excess of the natural predevelopment conditions. Where
possible, existing natural runoff control features, such as berms, swales, terraces and
wooded areas, shall be retained in order to reduce runoff and encourage infiltration of
stormwaters.
C (2) Storm water runoff control systems shall be maintained as necessary to ensure proper
. functioning.
NOTE: The Stormwater Management Law (38 M.R.S.A. section 420-D) requires a full
permit to be obtained from the DEP prior to construction of a project consisting of
20,000 square feet or more of impervious area or 5 acres or more of a developed
area in an urban impaired stream watershed or most-at-risk lake watershed, or a
project with 1 acre or more of developed area in any other stream, coastal or
wetland watershed. A permit-by-rule is necessary for a project with one acre or
more of disturbed area but less than 1 acre impervious area (20,000 square feet for
most-at-risk lakes and urban impaired streams) and less than 5 acres of developed
area. Furthermore, a Maine Construction General Permit is required if the
construction will result in one acre or more of disturbed area.
K. Septic Waste Disposal
(1) All subsurface sewage disposal systems shall be installed in conformance with the
State of Maine Subsurface Wastewater Disposal Rules, and the following:
(a) clearing or removal of woody vegetation necessary to site a new system and any
associated fill extensions, shall not extend closer than seventy-five (75) feet,
horizontal distance, from a the normal high-water line of a water body or the upland
< edge of a wetland and
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-21-
06-96 Bradley Shoreland Zoning Ordinance
C (b) a holding tank is not allowed for a first-time residential use in the shoreland zone.
NOTE: The Maine Subsurface Wastewater Disposal Rules require new systems, excluding
fill extensions, to be constructed no less than one hundred (100) horizontal feet from
the normal high-water line of a perennial water body. The minimum setback distance
for a new subsurface disposal system may not be reduced by variance.
L. Essential Services
(1) Where feasible, the installation of essential services shall be limited to existing public
ways and existing service corridors.
(2) The installation of essential services, other than road-side distribution lines, is not
allowed in a Resource Protection or Stream Protection District, except to provide
services to a permitted use within said district, or except where the applicant
demonstrates that no reasonable alternative exists. Where allowed, such structures
and facilities shall be located so as to minimize any adverse impacts on surrounding
uses and resources, including visual impacts.
(3) Damaged or destroyed public utility transmission and distribution lines, towers and
related equipment may be replaced or reconstructed without a permit.
C M. Mineral Exploration and Extraction. Mineral exploration to determine the nature or
extent of mineral resources shall be accomplished by hand sampling, test boring, or other
methods which create minimal disturbance of less than one hundred (100) square feet of
ground surface. A permit from the Code Enforcement Officer shall be required for
mineral exploration which exceeds the above limitation. All excavations, including test
pits and holes, shall be immediately capped, filled or secured by other equally effective
measures to restore disturbed areas and to- protect the public health and safety.
Mineral extraction may be permitted under the following conditions:
(1) A reclamation plan shall be filed with, and approved, by the Planning Board before a
; permit is granted. Such plan shall describe in detail procedures to be undertaken to
fulfill the requirements of Section 15 (M)(3) below.
(2) No part of any extraction operation, including drainage and runoff control features,
shall be permitted within one hundred (100) feet, horizontal distance, of the normal
high-water line of Chemo Pond, and within seventy-five (75) feet, horizontal
distance, of the normal high-water line of any other water body, tributary stream, or
the upland edge of a wetland. Extraction operations shall not be permitted within fifty
(50) feet, horizontal distance, of any property line without written permission of the
owner of such adjacent property.
oO (3) Within twelve (12) months following the completion of extraction operations at any
C 7 extraction site, which operations shall be deemed complete when less than one
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-22 »
06-96 Bradley Shoreland Zoning Ordinance
4 hundred (100) cubic yards of materials are removed in any consecutive twelve (12)
month period, ground levels and grades shall be established in accordance with the
following: .
(a) All debris, stumps, and similar material shall be removed for disposal in an
approved location, or shall be buried on-site. Only materials generated on-site
may: be buried or covered on-site. .
NOTE: The State of Maine Solid Waste Laws, 38 M.R.S.A., section 1301 and the solid waste
management rules, Chapters 400-419 of the Department of Environmental
Protection's regulations may contain other applicable provisions regarding disposal of
such materials. ;
(b) The final graded slope shall be two and one-half to one (2 1/2:1) slope or flatter.
(c) Top soil or loam shall be retained to cover all disturbed land areas, which shall be
reseeded and stabilized with vegetation native to the area. Additional topsoil or
loam shall be obtained from off-site sources if necessary to complete the
stabilization project.
(4) In keeping with the purposes of this Ordinance, the Planning Board may impose such
conditions as are necessary to minimize the adverse impacts associated with mineral
C extraction operations on surrounding uses and resources.
N. Agriculture
(1) All spreading of manure shall be accomplished in conformance with the Manure
Utilization Guidelines published by the Maine Department of Agriculture on
November 1, 2001, and the Nutrient Management Law (7 M.R.S.A. sections 4201-
4209).
(2) Manure shall not be stored or stockpiled within one hundred (100) feet, horizontal
distance, of Chemo Pond, or within seventy-five (75) feet horizontal distance, of
other water bodies, tributary streams, or wetlands. All manure storage areas within
the shoreland zone must be constructed or modified such that the facility produces no
discharge of effluent or contaminated storm water.
(3) Agricultural activities involving tillage of soil greater than forty thousand (40,000)
square feet in surface area, within the shoreland zone shall require a Conservation
Plan to be filed with the Planning Board. Nonconformance with the provisions of said
plan shall be considered to be a violation of this Ordinance.
NOTE: Assistance in preparing a Conservation Plan may be available through the
. Penobscot County Soil and Water Conservation District office.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-~23-
06-96 Bradley Shoreland Zoning Ordinance
C ; (4) There shall be no new tilling of soil within one-hundred (100) feet, horizontal
~ distance, of the normal high-water line of Chemo Pond; within seventy-five (75) feet,
horizontal distance, from other water bodies and coastal wetlands; nor within twenty-
five (25) feet, horizontal distance, of tributary streams and freshwater wetlands.
Operations in existence on the effective date of this ordinance and not in conformance
with this provision may be maintained.
(5) Newly established livestock grazing areas shall not be permitted within one hundred
(100) feet, horizontal distance, of the normal high-water line of Chemo Pond; within
seventy-five (75) feet, horizontal distance, of other water bodies and coastal wetlands,
nor; within twenty-five (25) feet, horizontal distance, of tributary streams and
freshwater wetlands. Livestock grazing associated with ongoing farm activities, and
which are not in conformance with the above setback provisions may continue,
provided that such grazing is conducted in accordance with a Conservation Plan that
has been filed with the Planning Board.
OQ. Timber Harvesting -- Repealed as of January 1, 2013
P. Clearing or Removal of Vegetation for Activities Other Than Timber Harvesting
(1) In a Resource Protection District abutting Chemo Pond, there shall be no cutting of
vegetation within the strip of land extending 75 feet, horizontal distance, inland from
C the normal high-water line, except to remove safety hazards as described in Section
Q, below.
Elsewhere, in any Resource Protection District the cutting or removal of vegetation
shall be limited to that which is necessary for uses expressly authorized in that
district.
(2) Except in areas as described in Section P(1), above, and except to allow for the
development of permitted uses, within a strip of land extending one-hundred (100)
feet, horizontal distance, inland from the normal high-water line of Chemo Pond,
and/or within a strip extending seventy-five (75) feet, horizontal distance, from any
other water body, tributary stream, or the upland edge of a wetland, a buffer strip of
vegetation shall be preserved as follows:
(a) There shall be no cleared opening greater than 250 square feet in the forest
canopy (or other existing woody vegetation if a forested canopy is not present) as
measured from the outer limits of the tree or shrub crown. However, a footpath
not to exceed six (6) feet in width as measured between tree trunks and/or shrub
stems is allowed provided that a cleared line of sight to the water through the
buffer strip is not created.
' (b) Selective cutting of trees within the buffer strip is allowed provided that a well-
- distributed stand of trees and other natural vegetation is maintained. For the
C purposes of Section 15(P)(2)(b) a "well-distributed stand of trees" adjacent to
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" tev.7-3 1-06
-24-
06-96 Bradley Shoreland Zoning Ordinance
C Chemo Pond shall be defined as maintaining a rating score of 24 or more in each
25-foot by 50-foot rectangular (1250 square feet) area as determined by the
following rating system.
Diameter of Tree at 4-1/2 feet Above Points
Ground Level (inches)
2<4in. 1
4<8 in. 2
8 < 12 in. 4
12 in. or greater 8
Adjacent to other water bodies, tributary streams, and wetlands, a "well-
distributed stand of trees" is defined as maintaining a minimum rating score of 16
per 25-foot by 50-foot rectangular area.
NOTE:As an example, adjacent to Chemo Pond, if a 25-foot x 50-foot plot contains
four (4) trees between 2 and 4 inches in diameter, two trees between 4 and 8
inches in diameter, three trees between 8 and 12 inches in diameter, and two
trees over 12 inches in diameter, the rating score is:
(4x1)+(2x2) + (3x4) + (2x8) = 36 points
C Thus, the 25-foot by 50-foot plot contains trees worth 36 points. Trees totaling
~ 12 points (36- 24 =12) may be removed from the plot provided that no cleared
openings are created.
The following shall govern in applying this point system:
(i) The 25-foot by 50-foot rectangular plots must be established where the
landowner or lessee proposes clearing within the required buffer;
(ii) Each successive plot must be adjacent to, but not overlap a previous plot;
(1i)Any plot not containing the required points must have no vegetation
removed except as otherwise allowed by this Ordinance;
(iv) Any plot containing the required points may have vegetation removed
down to the minimum points required or as otherwise allowed by is
Ordinance;
(v) Where conditions permit, no more than 50% of the points on any 25-foot
by 50-foot rectangular area may consist of trees greater than 12 inches in
diameter.
For the purposes of Section 15(P)(2)(b) "other natural vegetation" is defined as
retaining existing vegetation under three (3) feet in height and other ground cover
and retaining at least five (5) saplings less than two (2) inches in diameter at four
and one half (4 4) feet above ground level for each 25-foot by 50-foot rectangle
C area. If five saplings do not exist, no woody stems less than two (2) inches in
diameter can be removed until 5 saplings have been recruited into the plot.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
~25-
06-96 Bradley Shoreland Zoning Ordinance
L. Notwithstanding the above provisions, no more than 40% of the total volume of
- trees four (4) inches or more in diameter, measured at 4 1/2 feet above ground
level may be removed in any ten (10) year period.
(c) In order to protect water quality and wildlife habitat, existing vegetation under
three (3) feet in height and other ground cover, including leaf litter and the forest
duff layer, shall not be cut, covered, or removed, except to provide for a footpath
or other permitted uses as described in Section 15(P) paragraphs (2) and (2)(a)
above.
(d) Pruning of tree branches, on the bottom 1/3 of the tree is allowed.
(e) In order to maintain a buffer strip of vegetation, when the removal of storm-
damaged, diseased, unsafe, or dead trees results in the creation of cleared
openings, these openings shall be replanted with native tree species unless
existing new tree growth is present.
(f) In order to maintain the vegetation in the shoreline buffer, clearing or removal of
vegetation for allowed activities, including associated construction and related
equipment operation, within or outside the shoreline buffer, must comply with the
requirements of Section 15.P(2).
Section 15(P)(2) does not apply to the following:
Those portions of public recreational facilities adjacent to public swimming areas as
long as clearing or removal of vegetation is limited to the minimum area necessary.
Cleanup and removal of petroleum contamination or other hazardous waste, if the
activity is deemed necessary by the Department's Division of Response Services.
(3) At distances greater than one hundred (100) feet, horizontal distance, from Chemo
Pond, and seventy-five (75) feet, horizontal distance, from the normal high-water line
of any other water body, tributary stream, or the upland edge of a wetland, there shall
be allowed on any lot, in any ten (10) year period, selective cutting of not more than
forty (40) percent of the volume of trees four (4) inches or more in diameter,
measured 4 1/2 feet above ground level. Tree removal in conjunction with the
development of permitted uses shall be included in the forty (40) percent calculation.
For the purposes of these standards volume may be considered to be equivalent to
basal area.
In no event shall cleared openings for any purpose, including but not limited to,
principal and accessory structures, driveways, lawns and sewage disposal areas,
exceed in the aggregate, 25% of the lot area within the shoreland zone or ten thousand
(10,000) square feet, whichever is greater, including land previously cleared.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-26-
06-96 Bradley Shoreland Zoning Ordinance
C : (4) Legally existing nonconforming cleared openings may be maintained, but shall not be
enlarged, except as allowed by this Ordinance.
(5) Fields and other cleared openings which have reverted to primarily shrubs, trees, or
other woody vegetation shall be regulated under the provisions of Section 15(P).
Q. Q. Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal
(1) Hazard trees in the shoreland zone may be removed without a permit after
consultation with the Code Enforcement Officer if the following requirements are
met:
(a) Within the shoreline buffer, if the removal of a hazard tree results in a cleared
opening in the tree canopy greater than two hundred and fifty (250) square feet,
replacement with native tree species is required, unless there is new tree growth
already present. New tree growth must be as near as practicable to where the
hazard tree was removed and be at least two (2) inches in diameter, measured at
four and one half (4.5) feet above the ground level. If new growth is not present,
then replacement trees shall consist of native species and be at least four (4) feet
in height, and be no less than two (2) inches in diameter. Stumps may not be
removed.
C (b) Outside of the shoreline buffer, when the removal of hazard trees exceeds forty
(40) percent of the volume of trees four (4) inches or more in diameter, measured
at four and one half (4.5) feet above ground level in any ten (10) year period,
and/or results in cleared openings exceeding twenty-five (25) percent of the lot
area within the shoreland zone, or ten thousand (10,000) square feet, whichever is
greater, replacement with native tree species is required, unless there is new tree
growth already present. New tree growth must be as near as practicable to where
the hazard tree was removed and be at least two (2) inches in diameter, measured
at four and one half (4.5) feet above the ground level. If new growth is not
present, then replacement trees shall consist of native species and be at least two
(2) inches in diameter, measured at four and one half (4.5) feet above the ground
- level.
(c) The removal of standing dead trees, resulting from natural causes, is permissible
without the need for replanting or a permit, as long as the removal does not result
in the creation of new lawn areas, or other permanently cleared areas, and stumps
are not removed. For the purposes of this provision dead trees are those trees that
contain no foliage during the growing season.
(d) The Code Enforcement Officer may require the property owner to submit an
evaluation from a licensed forester or arborist before any hazard tree can be
( removed within the shoreland zone.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-27-
06-96 Bradley Shoreland Zoning Ordinance
4 " (e) The Code Enforcement Officer may require more than a one--for-one replacement
for hazard trees removed that exceed eight (8) inches in diameter measured at four
and one half (4.5) feet above the ground level.
(2) Storm-damaged trees in the shoreland zone may be removed without a permit after
consultation with the Code Enforcement Officer if the following requirements are
met:
(a) Within the shoreline buffer, when the removal of storm-damaged trees results in a
cleared opening in the tree canopy greater than two hundred and fifty (250) square
feet, replanting is not required, but the area shall be required to naturally
revegetate, and the following requirements must be met:
(i) The area from which a storm-damaged tree is removed does not result in new
lawn areas, or other permanently cleared areas;
(i) Stumps from the storm-damaged trees may not be removed;
(ii1)Limbs damaged from a storm event may be pruned even if they extend
beyond the bottom one-third (1/3) of the tree; and
(iv) If after one growing season, no natural regeneration or regrowth is present,
C replanting of native tree seedlings or saplings is required at a density of one
seedling per every eighty (80) square feet of lost canopy.
(b) Outside of the shoreline buffer, if the removal of storm damaged trees exceeds
40% of the volume of trees four (4) inches or more in diameter, measured at four
and one half (4.5) feet above the ground level in any ten (10) year period, or
results, in the aggregate, in cleared openings exceeding 25% of the lot area within
the shoreland zone or ten thousand (10,000) square feet, whichever is greater, and
no natural regeneration occurs within one growing season, then native tree
seedlings or saplings shall be replanted on a one-for-one basis.
R. Exemptions to Clearing and Vegetation Removal Requirements
The following activities are exempt from the clearing and vegetation removal standards
set forth in Section 15(P), provided that all other applicable requirements of this chapter
are complied with, and the removal of vegetation is limited to that which is necessary:
(1) The removal of vegetation that occurs at least once every two (2) years for the
maintenance of legally existing areas that do not comply with the vegetation
standards in this chapter, such as but not limited to cleared openings in the canopy or
fields. Such areas shall not be enlarged, except as allowed by this section. If any of
these areas, due to lack of removal of vegetation every two (2) years, reverts back to
C primarily woody vegetation, the requirements of Section 15(P) apply;
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
~28 -
06-96 Bradley Shoreland Zoning Ordinance
C (2) The removal of vegetation from the location of allowed structures or allowed uses, -
when the shoreline setback requirements of section 15(B) are not applicable;
(3) The removal of vegetation from the location of public swimming areas associated
with an allowed public recreational facility;
(4) The removal of vegetation associated with allowed agricultural uses, provided best
management practices are utilized, and provided all requirements of section 15(N) are
~ complied with;
(5) The removal of vegetation associated with brownfields or voluntary response action
. program (VRAP) projects provided that the removal of vegetation is necessary for
remediation activities to clean-up contamination on a site in a general development
district, commercial fisheries and maritime activities district or other equivalent
zoning district approved by the Commissioner that is part of a state or federal
brownfields program or a voluntary response action program pursuant 38 M.R.S.A
section 343-E, and that is located along:
(a) A coastal wetland; or
(b) A river that does not flow to a great pond classified as GPA pursuant to
38 M.R.S.A section 465-A.
C (6) The removal of non-native invasive vegetation species, provided the following
minimum requirements are met:
(a) Ifremoval of vegetation occurs via wheeled or tracked motorized equipment, the
wheeled or tracked motorized equipment is operated and stored at least twenty-
five (25) feet, horizontal distance, from the shoreline, except that wheeled or
tracked equipment may be operated or stored on existing structural surfaces, such
as pavement or gravel;
(b) Removal of vegetation within twenty-five (25) feet, horizontal distance, from the
shoreline occurs via hand tools; and
(c) If applicable clearing and vegetation removal standards are exceeded due to the
removal of non-native invasive species vegetation, the area shall be revegetated
. with native species to achieve compliance.
NOTE: An updated list of non-native invasive vegetation is maintained by the
Department of Agriculture, Conservation and Forestry's Natural Areas Program:
http://www.maine.gov/dacf/mnap/features/invasive_plants/invasives.htm
(7) The removal of vegetation associated with emergency response activities conducted
( by the Department, the U.S. Environmental Protection Agency, the U.S. Coast Guard,
" and their agents.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-29.
06-96 Bradley Shoreland Zoning Ordinance
S. Revegetation Requirements
When revegetation is required in response to violations of the vegetation standards set
forth in Section 15(P), to address the removal of non- native invasive species of
vegetation, or as a mechanism to allow for development that may otherwise not be
permissible due to the vegetation standards, including removal of vegetation in
; conjunction with a shoreline stabilization project, the revegation must comply with the
following requirements.
(1) The property owner must submit a revegetation plan, prepared with and signed by a
qualified professional, that describes revegetation activities and maintenance. The
plan must include a scaled site plan, depicting where vegetation was, or is to be
removed, where existing vegetation is to remain, and where vegetation is to be
planted, including a list of all vegetation to be planted.
(2) Revegetation must occur along the same segment of shoreline and in the same area
where vegetation was removed and at a density comparable to the pre-existing .
vegetation, except where a shoreline stabilization activity does not allow revegetation
to occur in the same area and at a density comparable to the pre-existing vegetation,
in which case revegetation must occur along the same segment of shoreline and as
C close as possible to the area where vegetation was removed:
(3) If part of a permitted activity, revegetation shall occur before the expiration of the
permit. If the activity or revegetation is not completed before the expiration of the
permit, a new revegetation plan shall be submitted with any renewal or new permit
application.
(4) Revegetation activities must meet the following requirements for trees and saplings:
(a) All trees and saplings removed must be replaced with native noninvasive species;
(b) Replacement vegetation must at a minimum consist of saplings;
(c) If more than three (3) trees or saplings are planted, then at least three (3) different
species shall be used;
(d) No one species shall make up 50% or more of the number of trees and saplings
planted;
(ce) If revegetation is required for a shoreline stabilization project, and it is not
possible to plant trees and saplings in the same area where trees or saplings were
removed, then trees or sapling must be planted in a location that effectively
( reestablishes the screening between the shoreline and structures; and
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-30-
06-96 Bradley Shoreland Zoning Ordinance
C , (f) A survival rate of at least eighty (80) percent of planted trees or saplings is
IN. required for a minimum five (5) years period.
(5S) Revegetation activities must meet the following requirements for woody vegetation
and other vegetation under three (3) feet in height:
(a) All woody vegetation and vegetation under three (3) feet in height must be
replaced with native noninvasive species of woody vegetation and vegetation
under three (3) feet in height as applicable;
(b) Woody vegetation and vegetation under three (3) feet in height shall be planted in
quantities and variety sufficient to prevent erosion and provide for effective
infiltration of stormwater;
(c) If more than three (3) woody vegetation plants are to be planted, then at least
three (3) different species shall be planted;
. _(d) No one species shall make up 50% or more of the number of planted woody
vegetation plants; and
(e) Survival of planted woody vegetation and vegetation under three feet in height
must be sufficient to remain in compliance with the standards contained within
this chapter for minimum of five (5) years
(6) Revegetation activities must meet the following requirements for ground vegetation
C and ground cover:
(a) All ground vegetation and ground cover removed must be replaced with native
herbaceous vegetation, in quantities and variety sufficient to prevent erosion and
provide for effective infiltration of stormwater;
(b) Where necessary due to a lack of sufficient ground cover, an area must be
supplemented with a minimum four (4) inch depth of leaf mulch and/or bark
mulch to prevent erosion and provide for effective infiltration of stormwater; and
(c) Survival and functionality of ground vegetation and ground cover must be
sufficient to remain in compliance with the standards contained within this
chapter for minimum of five (5) years.
T. Erosion and Sedimentation Control
(1) All activities which involve filling, grading, excavation or other similar activities
which result in unstabilized soil conditions and which require a permit shall also
require a written soil erosion and sedimentation control plan. The plan shall be
submitted to the permitting authority for approval and shall include, where applicable,
provisions for:
( (a) Mulching and revegetation of disturbed soil.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-31-
06-96 Bradley Shoreland Zoning Ordinance
{ ' (b) Temporary runoff control features such as hay bales, silt fencing or diversion
wo ditches.
(c) Permanent stabilization structures such as retaining walls or riprap.
(2) In order to create the least potential for erosion, development shall be designed to fit
with the topography and soils of the site. Areas of steep slopes where high cuts and
fills may be required shall be avoided wherever possible, and natural contours shall
be followed as closely as possible.
(3) Erosion and sedimentation control measures shall apply to all aspects of the proposed
project involving land disturbance, and shall be in operation during all stages of the
activity. The amount of exposed soil at every phase of construction shall be
minimized to reduce the potential for erosion.
(4) Any exposed ground area shall be temporarily or permanently stabilized within one |
(1) week from the time it was last actively worked, by use of riprap, sod, seed, and
mulch, or other effective measures. In all cases permanent stabilization shall occur
within nine (9) months of the initial date of exposure. In addition:
(a) Where mulch is used, it shall be applied at a rate of at least one (1) bale per five
hundred (500) square feet and shall be maintained until a catch of vegetation is
C established.
(b) Anchoring the mulch with netting, peg and twine or other suitable method may be
required to maintain the mulch cover.
(c) Additional measures shall be taken where necessary in order to avoid siltation into
the water. Such measures may include the use of staked hay bales and/or silt
fences.
(5) Natural and man-made drainage ways and drainage outlets shall be protected from
erosion from water flowing through them. Drainageways shall be designed and
constructed in order to carry water from a twenty five (25) year storm or greater, and
shall be stabilized with vegetation or lined with riprap.
$e
(6) When an excavation contractor will perform an activity that requires or results in
more than one (1) cubic yard of soil disturbance, the person responsible for
_ management of erosion and sedimentation control practices at the site must be certified
in erosion control practices by the Maine Department of Environmental Protection.
This person must be present at the site each day earthmoving activity occurs for a
duration that is sufficient to ensure that proper erosion and sedimentation control
practices are followed. This is required until erosion and sedimentation control
( measures have been installed, which will either stay in place permanently or stay in
Ne place until the area is sufficiently covered with vegetation necessary to prevent soil
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-32-
06-96 Bradley Shoreland Zoning Ordinance
( } erosion. The name and certification number of the person who will oversee the activity
.- causing or resulting in soil disturbance shall be included on the permit application. This
requirement does not apply to a person or firm engaged in agriculture or timber
harvesting if best management practices for erosion and sedimentation control are used;
and municipal, state and federal employees engaged in projects associated with that
employment.
U. Soils. All land uses shall be located on soils in or upon which the proposed uses or
structures can be established or maintained without causing adverse environmental
impacts, including severe erosion, mass soil movement, improper drainage, and water
pollution, whether during or after construction. Proposed uses requiring subsurface waste
disposal, and commercial or industrial development and other similar intensive land uses,
shall require a soils report based on an on-site investigation and be prepared by state-
certified professionals. Certified persons may include Maine Certified Soil Scientists,
Maine Registered Professional Engineers, Maine State Certified Geologists and other
persons who have training and experience in the recognition and evaluation of soil
properties. The report shall be based upon the analysis of the characteristics of the soil
and surrounding land and water areas, maximum ground water elevation, presence of
ledge, drainage conditions, and other pertinent data which the evaluator deems
appropriate. The soils report shall include recommendations for a proposed use to
C ' counteract soil limitations where they exist.
V. Water Quality. No activity shall deposit on or into the ground or discharge to the waters
of the State any pollutant that, by itself or in combination with other activities or
substances, will impair designated uses or the water classification of the water body,
tributary stream or wetland.
W. Archaeological Site. Any proposed land use activity involving structural development or
soil disturbance on or adjacent to sites listed on, or eligible to be listed on the National
Register of Historic Places, as determined by the permitting authority, shall be submitted
by the applicant to the Maine Historic Preservation Commission for review and
comment, at least twenty (20) days prior to action being taken by the permitting
authority. The permitting authority shall consider comments received from the
Commission prior to rendering a decision on the application.
NOTE: Municipal officials should contact the Maine Historic Preservation Commission for
the listing and location of Historic Places in their community.
16. Administration
A. Administering Bodies and Agents
( (1) Code Enforcement Officer. A Code Enforcement Officer shall be appointed or
- reappointed annually by July ist.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-33-
06-96 Bradley Shoreland Zoning Ordinance
- (2) Board of Appeals. A Board of Appeals shall be created in accordance with the
provisions of 30-A M.R.S.A. section 2691.
(3) Planning Board. A Planning Board shall be created in accordance with the
provisions of State law.
B. Permits Required. After the effective date of this Ordinance no person shall, without
first obtaining a permit, engage in any activity or use of land or structure requiring a
permit in the district in which such activity or use would occur; or expand, change, or
replace an existing use or structure; or renew a discontinued nonconforming use. A
person who is issued a permit pursuant to this Ordinance shall have a copy of the permit
on site while the work authorized by the permit is performed.
(1) A permit is not required for the replacement of an existing road culvert as long as:
(a) The replacement culvert is not more than 25% longer than the culvert being
replaced;
(b) The replacement culvert is not longer than 75 feet; and
(c) Adequate erosion control measures are taken to prevent sedimentation of the
C water, and the crossing does not block fish passage in the watercourse.
(2) A permit is not required for an archaeological excavation as long as the excavation is
conducted by an archaeologist listed on the State Historic Preservation Officer's level
1 or level 2 approved list, and unreasonable erosion and sedimentation is prevented
by means of adequate and timely temporary and permanent stabilization measures.
(3) Any permit required by this Ordinance shall be in addition to any other permit
required by other law or ordinance.
C, Permit Application
(1) Every applicant for a permit shall submit a written application, including a scaled site
plan, on a form provided by the municipality, to the appropriate official as indicated
in Section 14.
(2) All applications shall be signed by an owner or individual who can show evidence of
right, title or interest in the property or by an agent, representative, tenant, or
contractor of the owner with authorization from the owner to apply for a permit
hereunder, certifying that the information in the application is complete and correct.
(3) All applications shall be dated, and the Code Enforcement Officer or Planning Board,
( as appropriate, shall note upon each application the date and time of its receipt.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-34-
06-96 Bradley Shoreland Zoning Ordinance
C - (4) If the property is not served by a public sewer, a valid plumbing permit or a
completed application for a plumbing permit, including the site evaluation approved
by the Plumbing Inspector, shall be submitted whenever the nature of the proposed
structure or use would require the installation of a subsurface sewage disposal system.
D. Procedure for Administering Permits. Within 35 days of the date of receiving a written
application, the Planning Board or Code Enforcement Officer, as indicated in Section 14,
shall notify the applicant in writing either that the application is a complete application,
or, if the application is incomplete, that specified additional material is needed to make
the application complete. The Planning Board or the Code Enforcement Officer, as
appropriate, shall approve, approve with conditions, or deny all permit applications in
writing within 35 days of receiving a completed application. However, if the Planning
Board has a waiting list of applications, a decision on the application shall occur within
35 days after the first available date on the Planning Board's agenda following receipt of
the completed application, or within 35 days of the public hearing, if the proposed use or
structure is found to be in conformance with the purposes and provisions of this
Ordinance.
The applicant shall have the burden of proving that the proposed land use activity is in
conformity with the purposes and provisions of this Ordinance.
After the submission of a complete application to the Planning Board, the Board shall
C approve an application or approve it with conditions if it makes a positive finding based
; on the information presented that the proposed use:
(1) Will maintain safe and healthful conditions;
(2) Will not result in water pollution, erosion, or sedimentation to surface waters;
(3) Will adequately provide for the disposal of all wastewater;
(4) Will not have an adverse impact on spawning grounds, fish, aquatic life, bird or other
wildlife habitat;
(5) Will conserve shore cover and visual, as well as actual, points of access to inland and
coastal waters;
(6) Will protect archaeological and historic resources as designated in the comprehensive
plan;
(7) Will not adversely affect existing commercial fishing or maritime activities;
(8) Will avoid problems associated with floodplain development and use; and
C (9) Is in conformance with the provisions of Section 15, Land Use Standards.
. Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-35-
06-96 Bradley Shoreland Zoning Ordinance
C ' If a permit is either denied or approved with conditions, the reasons as well as conditions
shall be stated in writing. No approval shall be granted for an application involving a
structure if the structure would be located in an unapproved subdivision or would violate
, any other local ordinance, or regulation or statute administered by the municipality.
E. Special Exceptions. In addition to the criteria specified in Section 16(D) above,
excepting structure setback requirements, the Planning Board may approve a permit for a
single family residential structure in a Resource Protection District provided that the
applicant demonstrates that all of the following conditions are met:
(1) There is no location on the property, other than a location within the Resource
Protection District, where the structure can be built.
(2) The lot on which the structure is proposed is undeveloped and was established and
recorded in the registry of deeds of the county in which the lot is located before the
adoption of the Resource Protection District.
(3) All proposed buildings, sewage disposal systems and other improvements are:
(a) Located on natural ground slopes of less than 20%; and
(b) Located outside the floodway of the 100-year floodplain along rivers and
4 artificially formed great ponds along rivers and outside the velocity zone in areas
. subject to tides, based on detailed flood insurance studies and as delineated on the
Federal Emergency Management Agency's Flood Boundary and Floodway Maps
and Flood Insurance Rate Maps; all buildings, including basements, are elevated
at least one foot above the 100-year floodplain elevation; and the development is
otherwise in compliance with any applicable municipal floodplain ordinance. If
the floodway is not shown on the Federal Emergency Management Agency Maps,
it is deemed to be 1/2 the width of the 100-year floodplain.
(4) The total footprint, as defined, is limited to a maximum of 1,500 square feet. This
limitation shall not be altered by variance.
(5) All structures, except functionally water-dependent structures, are set back from the
normal high-water line of a water body, tributary stream or upland edge of a wetland
to the greatest practical extent, but not less than 75 feet, horizontal distance. In
determining the greatest practical extent, the Planning Board shall consider the depth
of the lot, the slope of the land, the potential for soil erosion, the type and amount of
vegetation to be removed, the proposed building site's elevation in regard to the
floodplain, and its proximity to moderate-value and high-value wetlands.
F, Expiration of Permit. Permits shall expire one year from the date of issuance if a
substantial start is not made in construction or in the use of the property during that
( period. Ifa substantial start is made within one year of the issuance of the permit, the
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
~ 36 - ,
06-96 Bradley Shoreland Zoning Ordinance
C . applicant shall have one additional year to complete the project, at which time the permit
: shall expire.
G. Installation of Public Utility Service. A public utility, water district, sanitary district or
any utility company of any kind may not install services to any new structure located in
the shoreland zone unless written authorization attesting to the validity and currency of
all local permits required under this or any previous Ordinance has been issued by the
appropriate municipal officials or other written arrangements have been made between
the municipal officials and the utility.
H. Appeals
(1) Powers and Duties of the Board of Appeals. The Board of Appeals shall have the
following powers:
(a) Administrative Appeals: To hear and decide administrative appeals, on an
appellate basis, where it is alleged by an aggrieved party that there is an error in any
order, requirement, decision, or determination made by, or failure to act by, the
Planning Board in the administration of this Ordinance; and to hear and decide
administrative appeals on a de novo basis where it is alleged by an aggrieved party
that there is an error in any order, requirement, decision or determination made by,
or failure to act by, the Code Enforcement Officer in his or her review of and action
4 on a permit application under this Ordinance. Any order, requirement, decision or
_ determination made, or failure to act, in the enforcement of this ordinance is not
appealable to the Board of Appeals.
(b) Variance Appeals: To authorize variances upon appeal, within the limitations set
forth in this Ordinance.
(2) Variance Appeals. Variances may be granted only under the following conditions:
(a) Variances may be granted only from dimensional requirements including, but not
. limited to, lot width, structure height, percent of lot coverage, and setback
requirements.
(b) Variances shall not be granted for establishment of any uses otherwise prohibited
by this Ordinance.
(c) The Board shall not grant a variance unless it finds that: ;
(i) The proposed structure or use would meet the provisions of Section 15 except
for the specific provision which has created the nonconformity and from which
relief is sought; and
(ii) The strict application of the terms of this Ordinance would result in undue
C hardship. The term "undue hardship" shall mean:
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
-37-
06+96 Bradley Shoreland Zoning Ordinance
< a. That the land in question cannot yield a reasonable return unless a variance
is granted;
b. That the need for a variance is due to the unique circumstances of the
property and not to the general conditions in the neighborhood;
c. That the granting of a variance will not alter the essential character of the
locality; and
d. That the hardship is not the result of action taken by the applicant or a prior
owner.
(d) Notwithstanding Section 16(H)(2)(c)(ii) above, the Code Enforcement Officer if
authorized in accordance with 30-A MRSA §4353-A, may approve a permit to the
owner of a residential dwelling unit for the purpose of making that dwelling
accessible to a person with a disability who resides in or regularly uses that
dwelling. The permit is deemed to include the variance, which shall be solely for
installation of equipment or the construction of structures necessary for access to or
egress from the dwelling by the person with the disability. The Code Enforcement
Officer may impose conditions on the permit, including limiting the permit to the
duration of the disability or to the time that the person with the disability lives in the
4 : dwelling. The term "structures necessary for access to or egress from the dwelling"
- shall include ramps and associated railing, and wall or roof systems necessary for
the safety or effectiveness of the structure. Such permitting is subject to Sections
16(H)(2)(f) and 16(H)(4)(b)(iv) below.
(e) The Board of Appeals shall limit any variances granted as strictly as possible in
order to ensure conformance with the purposes and provisions of this Ordinance to
the greatest extent possible, and in doing so may impose such conditions to a
variance as it deems necessary. The party receiving the variance shall comply with
any conditions imposed.
(f) A copy of each variance request, including the application and all supporting
information supplied by the applicant, shall be forwarded by the municipal officials
to the Commissioner of the Department of Environmental Protection at least twenty
(20) days prior to action by the Board of Appeals. Any comments received from the
Commissioner prior to the action by the Board of Appeals shall be made part of the
record and shall be taken into consideration by the Board of Appeals.
(3) Administrative Appeals
When the Board of Appeals reviews a decision of the Code Enforcement Officer the
Board of Appeals shall hold a "de novo" hearing. At this time the Board may receive
- and consider new evidence and testimony, be it oral or written. When acting in a "de
C novo" capacity the Board of Appeals shall hear and decide the matter afresh,
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
- 38 -
06-96 Bradley Shoreland Zoning Ordinance
C ~ undertaking its own independent analysis of evidence and the law, and reaching its own
. decision.
When the Board of Appeals hears a decision of the Planning Board, it shall hold an
appellate hearing, and may reverse the decision of the Planning Board only upon
finding that the decision was contrary to specific provisions of the Ordinance or
contrary to the facts presented to the Planning Board. The Board of Appeals may only
review the record of the proceedings before the Planning Board. The Board Appeals
shall not receive or consider any evidence which was not presented to the Planning
Board, but the Board of Appeals may receive and consider written or oral arguments. If
the Board of Appeals determines that the record of the Planning Board proceedings are
inadequate, the Board of Appeals may remand the matter to the Planning Board for
additional fact finding.
(4) Appeal Procedure
(a) Making an Appeal
(i) An administrative or variance appeal may be taken to the Board of Appeals by
an aggrieved party from any decision of the Code Enforcement Officer or the
Planning Board, except for enforcement-related matters as described in Section
16(H)(1)(a) above. Such an appeal shall be taken within thirty (30) days of the
C date of the official, written decision appealed from, and not otherwise, except
~ that the Board, upon a showing of good cause, may waive the thirty (30) day
requirement.
(ii) Applications for appeals shall be made by filing with the Board of Appeals a
written notice of appeal which includes:
a. A concise written statement indicating what relief is requested and why the
appeal or variance should be granted.
b. A sketch drawn to scale showing lot lines, location of existing buildings and
structures and other physical features of the lot pertinent to the relief sought.
(i1i)Upon receiving an application for an administrative appeal or a variance, the
Code Enforcement Officer or Planning Board, as appropriate, shall transmit to
the Board of Appeals all of the papers constituting the record of the decision
appealed from.
(iv) The Board of Appeals shall hold a public hearing on an administrative appeal or
a request for a variance within thirty-five (35) days of its receipt of a complete
written application, unless this time period is extended by the parties.
( | (b) Decision by Board of Appeals
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
~39-
06-96 Bradley Shoreland Zoning Ordinance
( (i) A majority of the full voting membership of the Board shall constitute a
quorum for the purpose of deciding an appeal.
(ii) The person filing the appeal shall have the burden of proof.
(iii)The Board shall decide all administrative appeals and variance appeals
within thirty five (35) days after the close of the hearing, and shall issue a
written decision on all appeals.
(iv)The Board of Appeals shall state the reasons and basis for its decision,
including a statement of the facts found and conclusions reached by the
Board. The Board shall cause written notice of its decision to be mailed or
hand-delivered to the applicant and to the Department of Environmental
Protection within seven (7) days of the Board's decision. Copies of written
decisions of the Board of Appeals shall be given to the Planning Board,
Code Enforcement Officer, and the municipal officers.
(5) Appeal to Superior Court. Except as provided by 30-A MLR.S.A. section 2691(3)(F),
any aggrieved party who participated as a party during the proceedings before the
Board of Appeals may take an appeal to Superior Court in accordance with State laws
within forty-five (45) days from the date of any decision of the Board of Appeals.
{
NL (6) Reconsideration. In accordance with 30-A M.R.S.A. section 2691(3)(F), the Board of
Appeals may reconsider any decision within forty-five (45) days of its prior decision. A
request to the Board to reconsider a decision must be filed within ten (10) days of the
decision that is being reconsidered. A vote to reconsider and the action taken on that
reconsideration must occur and be completed within forty-five (45) days of the date of
the vote on the original decision. Reconsideration of a decision shall require a positive
vote of the majority of the Board members originally voting on the decision, and proper
notification to the landowner, petitioner, planning board, code enforcement officer, and
other parties of interest, including abutters and those who testified at the original
hearing(s). The Board may conduct additional hearings and receive additional evidence
and testimony.
Appeal of a reconsidered decision to Superior Court must be made within fifteen (15)
days after the decision on reconsideration.
I. Enforcement
(1) Nuisances. Any violation of this Ordinance shall be deemed to be a nuisance.
(2) Code Enforcement Officer ,
° (a) It shall be the duty of the Code Enforcement Officer to enforce the provisions of
C this Ordinance. If the Code Enforcement Officer shall find that any provision of
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
- 40 -
06-96 Bradley Shoreland Zoning Ordinance
C this Ordinance is being violated, he or she shall notify in writing the person -
- responsible for such violation, indicating the nature of the violation and ordering
the action necessary to correct it, including discontinuance of illegal use of land,
buildings or structures, or work being done, removal of illegal buildings or
structures, and abatement of nuisance conditions. A copy of such notices shall be
submitted to the municipal officers and be maintained as a permanent record.
(b) The Code Enforcement Officer shall conduct on-site inspections to ensure
compliance with all applicable laws and conditions attached to permit approvals.
The Code Enforcement Officer shall also investigate all complaints of alleged
violations of this Ordinance.
(c) The Code Enforcement Officer shall keep a complete record of all essential
transactions of the office, including applications submitted, permits granted or
denied, variances granted or denied, revocation actions, revocation of permits,
appeals, court actions, violations investigated, violations found, and fees collected.
(3) Legal Actions. When the above action does not result in the correction or abatement of
the violation or nuisance condition, the Municipal Officers, upon notice from the Code
Enforcement Officer, are hereby directed to institute any and all actions and
proceedings, either legal or equitable, including seeking injunctions of violations and
the imposition of fines, that may be appropriate or necessary to enforce the provisions
C of this Ordinance in the name of the municipality. The municipal officers, or their
. authorized agent, are hereby authorized to enter into administrative consent agreements
for the purpose of eliminating violations of this Ordinance and recovering fines without
Court action. Such agreements shall not allow an illegal structure or use to continue
unless there is clear and convincing evidence that the illegal structure or use was
constructed or conducted as a direct result of erroneous advice given by an authorized
municipal official and there is no evidence that the owner acted in bad faith, or unless
the removal of the structure or use will result in a threat or hazard to public health and
safety or will result in substantial environmental damage.
(4) Fines. Any person, including but not limited to a landowner, a landowner's agent or a
contractor, who violates any provision or requirement of this Ordinance shall be
penalized in accordance with 30-A, M.R.S.A. section 4452.
NOTE: Current penalties include fines of not less than $100 nor more than $2500 per
violation for each day that the violation continues. However, in a resource
protection district the maximum penalty is increased to $5000 (38 M.R.S.A. section
4452).
17. Definitions.
Accessory structure or use - a use or structure which is incidental and subordinate to the
( principal use or structure. Accessory uses, when aggregated, shall not subordinate the principal
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-4]-
06-96 Bradley Shoreland Zoning Ordinance
C - use of the lot. A deck or similar extension of the principal structure or a garage attached to the
: principal structure by a roof or a common wall is considered part of the principal structure.
Aggrieved party - an owner of land whose property is directly or indirectly affected by the
granting or denial of a permit or variance under this Ordinance; a person whose land abuts land
for which a permit or variance has been granted; or any other person or group of persons who
have suffered particularized injury as a result of the granting or denial of such permit or
variance.
Agriculture - the production, keeping or maintenance for sale or lease, of plants and/or
animals, including but not limited to: forages and sod crops; grains and seed crops; dairy
animals and dairy products; poultry and poultry products; livestock; fruits and vegetables; and
ornamental and green-house products. Agriculture does not include forest management and
timber harvesting activities.
Aquaculture - the growing or propagation of harvestable freshwater, estuarine, or marine plant
or animal species.
Basal Area - the area of cross-section of a tree stem at 4 1/2 feet above ground level and
inclusive of bark.
Basement - any portion of a structure with a floor-to-ceiling height of 6 feet or more and
( : having more than 50% of its volume below the existing ground level.
Boat Launching Facility - a facility designed primarily for the launching and landing of
watercraft, and which may include an access ramp, docking area, and parking spaces for
vehicles and trailers.
Campground - any area or tract of land to accommodate two (2) or more parties in temporary
living quarters, including, but not limited to tents, recreational vehicles or other shelters.
Canopy -- the more or less continuous cover formed by tree crowns in a wooded area.
Chemo Pond -- a great pond as defined.
Coastal wetland - all tidal and subtidal lands; all lands with vegetation present that is tolerant
of salt water and occurs primarily in a salt water or estuarine habitat; and any swamp, marsh,
bog, beach, flat or other contiguous low land that is subject to tidal action during the highest
tide level for the year in which an activity is proposed as identified in tide tables published by
' the National Ocean Service. Coastal wetlands may include portions of coastal sand dunes.
NOTE: All areas below the highest annual tide level are coastal wetlands. These areas may
consist of rocky ledges, sand and cobble beaches, mud flats, etc., in addition to salt marshes
C and salt meadows.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-42-
06-96 Bradley Shoreland Zoning Ordinance
C 7 Commercial use - the use of lands, buildings, or structures, other than a "home occupation,"
~ defined below, the intent and result of which activity is the production of income from the
buying and selling of goods and/or services, exclusive of rental of residential buildings and/or
dwelling units.
DBH --- the diameter of a standing tree measured 4.5 feet from ground level.
Development -- a change in land use involving alteration of the land, water or vegetation, or
the addition or alteration of structures or other construction not naturally occurring.
Dimensional requirements - numerical standards relating to spatial relationships including
but not limited to setback, lot area, shore frontage and height.
Disability - any disability, infirmity, malformation, disfigurement, congenital defect or
mental condition caused by bodily injury, accident, disease, birth defect, environmental
conditions or illness; and also includes the physical or mental condition of a person which
constitutes a substantial handicap as determined by a physician or in the case of mental
handicap, by a psychiatrist or psychologist, as well as any other health or sensory impairment
which requires special education, vocational rehabilitation or related services.
Disruption of shoreline integrity - the alteration of the physical shape, properties, or
C condition of a shoreline at any location by timber harvesting and related activities. A
- shoreline where shoreline integrity has been disrupted is recognized by compacted, scarified
and/or rutted soil, an abnormal channel or shoreline cross-section, and in the case of flowing
waters, a profile and character altered from natural conditions.
Driveway - a vehicular access-way less than five hundred (500) feet in length serving two
single-family dwellings or one two-family dwelling, or less.
Emergency operations - operations conducted for the public health, safety or general
welfare, such as protection of resources from immediate destruction or loss, law
enforcement, and operations to rescue human beings, property and livestock from the threat
of destruction or injury.
Essential services - gas, electrical or communication facilities; steam, fuel, electric power or
water transmission or distribution lines, towers and related equipment; telephone cables or
lines, poles and related equipment; gas, oil, water, slurry or other similar pipelines; municipal
sewage lines, collection or supply systems; and associated storage tanks. Such systems may
include towers, poles, wires, mains, drains, pipes, conduits, cables, fire alarms and police call
boxes, traffic signals, hydrants and similar accessories, but shall not include service drops or
buildings which are necessary for the furnishing of such services.
Excavation contractor - an individual or firm that either is engaged in a business that causes
the disturbance of one or more cubic yards of soil, or is in a business in which the
C . disturbance of one or more cubic yards of soil results from an activity that the individual or
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev, 7-31-06
- 43 -
06-96 Bradley Shoreland Zoning Ordinance
C " firm is retained to perform. Disturbance includes: grading, filling, and removal. A person or
me firm engaged in agriculture or timber harvesting activities is not considered an excavation
contractor as long as best management practices for erosion and sedimentation control are
used. Municipal, state and federal employees engaged in projects associated with that
employment are not considered excavation contractors.
Expansion of a structure - an increase in the footprint of a structure, including all
extensions such as, but not limited to: attached decks, garages, porches and greenhouses.
Expansion of use - the addition of one or more months to a use's operating season; or the use
of more footprint or ground area devoted to a particular use.
Family - one or more persons occupying a premises and living as a single housekeeping unit.
Floodway - the channel of a river or other watercourse and adjacent land areas that must be
reserved in order to discharge the 100-year flood without cumulatively increasing the water
surface elevation by more than one foot in height.
Floor area - the sum of the horizontal areas of the floor(s) of a structure enclosed by exterior
walls, plus the horizontal area of any unenclosed portions of a structure such as porches and
decks.
C Footprint - the entire area of ground covered by the structure(s) on a lot, including but not
. limited to: cantilevered or similar overhanging extensions, as well as unenclosed structures
such as patios and decks.
Forested wetland - a freshwater wetland dominated by woody vegetation that is six (6)
meters tall (approximately twenty (20) feet) or taller.
Foundation - the supporting substructure of a building or other structure, excluding wooden
sills and post supports, but including basements, slabs, frostwalls, or other base consisting of
concrete, block, brick or similar material.
Freshwater wetland - freshwater swamps, marshes, bogs and similar areas, other than
forested wetlands, which are:
1. Of ten or more contiguous acres; or of less than 10 contiguous acres and adjacent
to a surface water body, excluding any river, stream or brook, such that in a
natural state, the combined surface area is in excess of 10 acres; and
2. Inundated or saturated by surface or ground water at a frequency and for a
duration sufficient to support, and which under normal circumstances do support,
a prevalence of wetland vegetation typically adapted for life in saturated soils.
- Freshwater wetlands may contain small stream channels or inclusions of land that do not
C conform to the criteria of this definition.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-44.
06-96 Bradley Shoreland Zoning Ordinance
C Functionally water-dependent uses - those uses that require, for their primary purpose,
location on submerged lands or that require direct access to, or location in, coastal or inland
waters and that can not be located away from these waters. The uses include, but are not
limited to commercial and recreational fishing and boating facilities, excluding recreational
boat storage buildings, finfish and shellfish processing, fish storage and retail and wholesale
fish marketing facilities, waterfront dock and port facilities, shipyards and boat building
facilities, marinas, navigation aids, basins and channels, retaining walls, industrial uses
dependent upon water-bome transportation or requiring large volumes of cooling or
processing water that can not reasonably be located or operated at an inland site, and uses
that primarily provide general public access to coastal or inland waters.
Great pond - any inland body of water which in a natural state has a surface area in excess
of ten acres, and any inland body of water artificially formed or increased which has a
surface area in excess of thirty (30) acres except for the purposes of this Ordinance, where
the artificially formed or increased inland body of water is completely surrounded by land
held by a single owner,. Chemo Pond is a great pond.
Ground cover -- small plants, fallen leaves, needles and twigs, and the partially decayed
organic matter of the forest floor.
Hazard tree - a tree with a structural defect, combination of defects, or disease resulting in a
C structural defect that under the normal range of environmental conditions at the site exhibits a
- high probability of failure and loss of a major structural component of the tree in a manner
that will strike a target. A normal range of environmental conditions does not include
_ meteorological anomalies, such as, but not limited to: hurricanes; hurricane-force winds;
tornados; microbursts; or significant ice storm events. Hazard trees also include those trees
that pose a serious and imminent risk to bank stability. A target is the area where personal
injury or property damage could occur if the tree or a portion of the tree fails. Targets include
roads, driveways, parking areas, structures, campsites, and any other developed area where
people frequently gather and linger.
Height of a structure - the vertical distance between the mean original (prior to
construction) grade at the downhill side of the structure and the highest point of the structure,
excluding chimneys, steeples, antennas, and similar appurtenances that have no floor area.
. Home occupation - an occupation or profession which is customarily conducted on or in a
residential structure or property and which is 1) clearly incidental to and compatible with the
residential use of the property and surrounding residential uses; and 2) which employs no
more than two (2) persons other than family members residing in the home.
Increase in nonconformity of a structure - any change in a structure or property which
causes further deviation from the dimensional standard(s) creating the nonconformity such -- .
as, but not limited to, reduction in water body, tributary stream or wetland setback distance,
" increase in lot coverage, or increase in height of a structure. Property changes or structure
(-- expansions which either meet the dimensional standard or which cause no further increase in
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-45-
0 6-96 Bradley Shoreland Zoning Ordinance
( ~ the linear extent of nonconformance of the existing structure shall not be considered to
- increase nonconformity. For example, there is no increase in nonconformity with the setback
requirement for water bodies, wetlands, or tributary streams if the expansion extends no
further into the required setback area than does any portion of the existing nonconforming
structure. Hence, a structure may be expanded laterally provided that the expansion extends
no closer to the water body, tributary stream, or wetland than the closest portion of the
existing structure from that water body, tributary stream, or wetland. Included in this
allowance are expansions which in-fill irregularly shaped structures.
Individual private campsite - an area of land which is not associated with a campground,
but which is developed for repeated camping by only one group not to exceed ten (10)
individuals and which involves site improvements which may include but not be limited to a
gravel pad, parking area, fire place, or tent platform.
Industrial - The assembling, fabrication, finishing, manufacturing, packaging or processing
of goods, or the extraction of minerals.
Institutional - a non-profit or quasi-public use, or institution such as a church, library,
_ public or private school, hospital, or municipally owned or operated building, structure or
land used for public purposes.
Licensed Forester - a forester licensed under 32 M.R.S.A. Chapter 76.
< Lot area - The area of land enclosed within the boundary lines of a Jot, minus land below the
normal high-water line of a water body or upland edge of a wetland and areas beneath roads
serving more than two lots.
Marina - a business establishment having frontage on navigable water and, as its principal
use, providing for hire offshore moorings or docking facilities for boats, and which may also
provide accessory services such as boat and related sales, boat repair and construction, indoor
and outdoor storage of boats and marine equipment, bait and tackle shops and marine fuel
service facilities.
Market value - the estimated price a property will bring in the open market and under
prevailing market conditions in a sale between a willing seller and a willing buyer, both
conversant with the property and with prevailing general price levels.
Mineral exploration - hand sampling, test boring, or other methods of determining the
nature or extent of mineral resources which create minimal disturbance to the land and which
include reasonable measures to restore the land to its original condition.
Mineral extraction - any operation within any twelve (12) month period which removes
more than one hundred (100) cubic yards of soil, topsoil, loam, sand, gravel, clay, rock, peat,
or other like material from its natural location and to transport the product removed, away
( from the extraction site.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
- 46 -
06-96 Bradley Shoreland Zoning Ordinance .
C ° Minimum lot width - the closest distance between the side lot lines of a lot. When only two
~ lot lines extend into the shoreland zone, both lot lines shall be considered to be side lot lines.
Multi-unit residential - a residential structure containing three (3) or more residential
dwelling units.
Native -- indigenous to the local forests.
Nonconforming condition -- nonconforming lot, structure or use which is allowed solely
because it was in lawful existence at the time this Ordinance or subsequent amendment took
effect.
Nonconforming lot - a single lot of record which, at the effective date of adoption or
amendment of this Ordinance, does not meet the area, frontage, or width requirements of the
district in which it is located.
Nonconforming structure - a structure which does not meet any one or more of the
following dimensional requirements; setback, height, lot coverage or footprint, but which is
allowed solely because it was in lawful existence at the time this Ordinance or subsequent
amendments took effect.
Nonconforming use - use of buildings, structures, premises, land or parts thereof which is
C not allowed in the district in which it is situated, but which is allowed to remain solely
. because it was in lawful existence at the time this Ordinance or subsequent amendments took
effect.
Non-native invasive species of vegetation - species of vegetation listed by the Maine
Department of Agriculture, Conservation and Forestry as being invasive in Maine
ecosystems and not native to Maine ecosystems.
Normal high-water line (non-tidal waters) - that line which is apparent from visible
markings, changes in the character of soils due to prolonged action of the water or changes in
vegetation, and which distinguishes between predominantly aquatic and predominantly
terrestrial land. Areas contiguous with rivers and great ponds that support non-forested
wetland vegetation and hydric soils and that are at the same or lower elevation as the water
level of the river or great pond during the period of normal high-water are considered part of
the river or great pond.
NOTE: Adjacent to tidal waters, setbacks are measured from the upland edge of the "coastal
wetland."
Person - an individual, corporation, governmental agency, municipality, trust, estate,
partnership, association, two or more individuals having a joint or common interest, or other
legal entity.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-47-
06-96 Bradley Shoreland Zoning Ordinance
( Se Piers, docks, wharves, bridges and other structures and uses extending or located below
the normal high-water line or within a wetland.
Temporary: Structures which remain in or over the water for less than seven (7)
months in any period of twelve (12) consecutive months.
Permanent: Structures which remain in or over the water for seven (7) months or more
in any period of twelve (12) consecutive months.
Principal structure - a building other than one which is used for purposes wholly incidental
or accessory to the use of another building or use on the same lot.
Principal use - a use other than one which is wholly incidental or accessory to another use
on the same lot.
Public facility - any facility, including, but not limited to, buildings, property, recreation
areas, and roads, which are owned, leased, or otherwise operated, or funded by a
governmental body or public entity.
Recent floodplain soils - the following soil series as described and identified by the National
Cooperative Soil Survey:
Fryeburg Hadley Limerick
C Lovewell Medomak Ondawa
; Alluvial Cornish Charles
Podunk Rumney Saco
Suncook Sunday Winooski
Recreational facility - a place designed and equipped for the conduct of sports, leisure time
activities, and other customary and usual recreational activities, excluding boat launching
facilities.
Recreational vehicle - a vehicle or an attachment to a vehicle designed to be towed, and
designed for temporary sleeping or living quarters for one or more persons, and which may
include a pick-up camper, travel trailer, tent trailer, camp trailer, and motor home. In order to
be considered as a vehicle and not as a structure, the unit must remain with its tires on the
ground, and must be registered with the State Division of Motor Vehicles.
Replacement system - a system intended to replace: 1.) an existing system which is either
malfunctioning or being upgraded with no significant change of design flow or use of the
structure, or 2.) any existing overboard wastewater discharge.
Residential dwelling unit - a room or group of rooms designed and equipped exclusively for
use as permanent, seasonal, or temporary living quarters for only one family at a time, and
containing cooking, sleeping and toilet facilities. The term shall include mobile homes and
rental units that contain cooking, sleeping, and toilet facilities regardless of the time-period
( rented. Recreational vehicles are not residential dwelling units.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
- 48 -
06-96 Bradley Shoreland Zoning Ordinance
( " Riprap - rocks, irregularly shaped, and at least six (6) inches in diameter, used for erosion
control and soil stabilization, typically used on ground slopes of two (2) units horizontal to
one (1) unit vertical or less.
River - a free-flowing body of water including its associated floodplain wetlands from that
point at which it provides drainage for a watershed of twenty five (25) square miles to its
mouth.
NOTE: The portion of a river that is subject to tidal action is a coastal wetland.
Road - a route or track consisting of a bed of exposed mineral soil, gravel, asphalt, or other
surfacing material constructed for or created by the repeated passage of motorized vehicles,
excluding a driveway as defined.
Salt marsh - Areas of coastal wetland (most often along coastal bays) that support salt
tolerant species, and where at average high tide during the growing season, the soil is
irregularly inundated by tidal waters. The predominant species is saltmarsh cordgrass
(Spartina alterniflora). More open areas often support widgeon grass, eelgrass, and Sago
pondweed.
Salt meadow - Areas of a coastal wetland that support salt tolerant plant species bordering
the landward side of salt marshes or open coastal water, where the soil is saturated during the
C growing season but which is rarely inundated by tidal water. Indigenous plant species include
~ salt meadow cordgrass (Spartina patens) and black rush; common threesquare occurs in
fresher areas.
Sapling - a tree species that is less than two (2) inches in diameter at four and one half (4.5)
feet above ground level.
Seedling - a young tree species that is less than four and one half (4.5) feet in height above
ground level.
Service drop - any utility line extension which does not cross or run beneath any portion of a
water body provided that:
1. in the case of electric service
a. the placement of wires and/or the installation of utility poles is located entirely upon
the premises of the customer requesting service or upon a roadway right-of-way; and
b. the total length of the extension is less than one thousand (1,000) feet.
2. in the case of telephone service
( a. the extension, regardless of length, will be made by the installation of telephone wires
_ to existing utility poles, or
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-31-06
- 49 -
06-96 Bradley Shoreland Zoning Ordinance
C b. the extension requiring the installation of new utility poles or placement underground
is less than one thousand (1,000) feet in length.
Setback - the nearest horizontal distance from the normal high-water line of a water body or
tributary stream, or upland edge of a wetland, to the nearest part of a structure, road, parking
space or other regulated object or area.
Shore frontage - the length of a lot bordering on a water body or wetland measured in a
straight line between the intersections of the lot lines with the shoreline.
Shoreland zone - the land area located within two hundred and fifty (250) feet, horizontal
distance, of the normal high-water line of any great pond or river; within 250 feet, horizontal
distance, of the upland edge of a coastal wetland, including all areas affected by tidal action;
within 250 feet of the upland edge of a freshwater wetland; or within seventy-five (75) feet,
horizontal distance, of the normal high-water line of a stream.
Shoreline -- the normal high-water line, or upland edge of a freshwater or coastal wetland.
Significant River Segments - See 38 M.R.S.A. section 437.
Storm-damaged tree - a tree that has been uprooted, blown down, is lying on the ground, or
- that remains standing and is damaged beyond the point of recovery as the result of a storm
C event.
Stream - a free-flowing body of water from the outlet of a great pond or the confluence of
two (2) perennial streams as depicted on the most recent, highest resolution version of the
national hydrography dataset available from the United States Geological Survey, on the
website of the United States Geological Survey or the national map, to point where the
stream becomes a river or where the stream meets the shoreland zone of another water body
or wetland. When a stream meets the shoreland zone of a water body or wetland and a
channel forms downstream of the water body or wetland as an outlet, that channel is also a
stream.
Structure - whether temporary or permanent: anything located, built, constructed or erected
for the support, shelter or enclosure of persons, animals, goods or property of any kind;
anything built, constructed or erected on or in the ground. The term structure includes decks,
patios, and satellite dishes. Structure does not include fences; poles; wiring, guy wires, guy
anchors and other aerial equipment normally associated with service drops; subsurface waste
water disposal systems as defined in Title 30-A, section 4201, subsection 5; geothermal heat
exchange wells as defined in Title 32, section 4700-E, subsection 3-C; and wells or water
wells as defined in Title 32, section 4700-E, subsection 8.
Substantial start - completion of thirty (30) percent of a permitted structure or use measured
( as a percentage of estimated total cost.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
- 50-
06-96 Bradley Shoreland Zoning Ordinance
C Subsurface sewage disposal system -- any system designed to dispose of waste or waste
water on or beneath the surface of the earth; includes, but is not limited to: septic tanks;
disposal fields; grandfathered cesspools; holding tanks; pretreatment filter, piping, or any
other fixture, mechanism, or apparatus used for those purposes; does not include any
discharge system licensed under 38 M.R.S.A. section 414, any surface waste water disposal
system, or any municipal or quasi-municipal sewer or waste water treatment system..
Sustained slope - a change in elevation where the referenced percent grade is substantially
maintained or exceeded throughout the measured area.
Tidal waters -- all waters affected by tidal action during the highest annual tide.
Tree - a woody perennial plant with a well-defined trunk(s) at least two (2) inches in
diameter at four and one half (4.5) feet above the ground, with a more or less definite crown,
and reaching a height of at least ten (10) feet at maturity.
Tributary stream -- means a channel between defined banks created by the action of surface
water, which is characterized by the lack of terrestrial vegetation or by the presence of a bed,
devoid of topsoil, containing waterborne deposits or exposed soil, parent material or bedrock;
and which is connected hydrologically with other water bodies. "Tributary stream" does not
include rills or gullies forming because of accelerated erosion in disturbed soils where the
- natural vegetation cover has been removed by human activity. This definition does not
C include the term "stream" as defined elsewhere in this Ordinance, and only applies to that
portion of the tributary stream located within the shoreland zone of the receiving water body
or wetland.
NOTE: Water setback requirements apply to tributary streams within the shoreland zone.
Upland edge of a wetland - the boundary between upland and wetland. For purposes of a
coastal wetland, this boundary is the line formed by the landward limits of the salt tolerant
vegetation and/or the highest annual tide level, including all areas affected by tidal action.
For purposes of a freshwater wetland, the upland edge is formed where the soils are not
saturated for a duration sufficient to support wetland vegetation; or where the soils support
the growth of wetland vegetation, but such vegetation is dominated by woody stems that are
six (6) meters (approximately twenty (20) feet) tall or taller.
Vegetation - all live trees, shrubs, and other plants including without limitation, trees both
over and under 4 inches in diameter, measured at 4 1/2 feet above ground level.
Velocity zone - an area of special flood hazard extending from offshore to the inland limit of
the primary frontal dune along an open coast and any other area subject to high velocity wave
action from storms or seismic sources.
Volume of a structure - the volume of all portions of a structure enclosed by roof and fixed
C exterior walls as measured from the exterior faces of these walls and roof.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" rev.7-3 1-06
-51-
06-96 Bradley Shoreland Zoning Ordinance
C Water body - any great pond, river or stream.
Water crossing - any project extending from one bank to the opposite bank of a river,
stream, tributary stream, or wetland whether under, through, or over the water or wetland.
Such projects include but may not be limited to roads, fords, bridges, culverts, water lines,
sewer lines, and cables as well as maintenance work on these crossings. This definition
includes crossings for timber harvesting equipment and related activities.
Wetland - a Freshwater Wetland or Coastal Wetland, as defined herein
Woody Vegetation - live trees or woody, non-herbaceous shrubs.
Based on "Chapter 1000: Guidelines for Municipal Shoreland Zoning Ordinances" ; rev.7-3 1-06