Brooklin Maine Site Plan Review Ordinance
Effective Date: 9/19/1995
Amended: 4/6/2024
Certified:
Certified:
Certified:
Select Board
Attest: A True Copy:
4/11/2024
Town Clerk
1
TABLE OF CONTENTS
Section 1.
Purpose
2
Section 2.
Authority
2
Section 3.
Applicability
2
Section 4.
Availability
3
Section 5.
Severability
3
Section 6.
Conflicts
4
Section 7.
Amendments
4
Section 8.
Administration and Enforcement
4
Section 9.
Standards and Review Criteria
5
9.1
Utilization of the Site
5
9.2
Adequacy of the Road System
6
9.3
Access into the Site
6
9.4
Internal Vehicular Circulation
8
9.5
Parking Layout and Design
8
9.6
Pedestrian Circulation
8
9.7
Stormwater Management
8
9.8
Erosion Control
9
9.9
Water Supply
9
9.10
Sewage Disposal
10
9.11
Utilities
10
9.12
Natural Features
11
9.13
Water Quality Protection
11
9.14
Hazardous, Special and Radioactive Materials
11
9.15
Shoreland Relationship
12
9.16
Technical and Financial Capacity
12
9.17
Solid Waste Disposal
12
9.18
Historic and Archaeological Resources
12
9.19
Floodplain Management
13
9.20
Air Pollution
13
9.21
Town Services
13
9.22
Exterior Lighting
13
9.23
Noise
14
9.24
Campgrounds
14
9.25
Mineral Exploration and Extraction
14
9.26
Signage
15
Section 10.
Submission Requirements
15
10.1
General Information
16
10.2
Existing Conditions
17
10.3
Proposed Development Activity
18
Section 11.
Review Procedures
18
Section 12.
Post Approval Activities
22
Section 13.
Appeals and Variances
24
Section 14.
Definitions (terms in bold found in text)
27
Appendix I.
Trip Generation Manuel of the Institute of Traffic Engineers
28
2
Section 1. Purpose
The site plan review provisions set forth in this Ordinance are intended to protect the public health
and safety, promote the general welfare of the community, and conserve the environment by
assuring that commercial and multifamily uses are designed and developed in a manner which
assures that adequate provisions are made for traffic safety and access; emergency access; water
supply; sewage disposal; management of stormwater, erosion, and sedimentation; protection of the
groundwater; protection of the environment, wildlife habitat, fisheries, and protection of historic
and archaeological resources avoiding clear adverse affects on health, safety or valuation of
abutting property.
This Ordinance is being adopted pursuant to Article VIII, Part 2, Section 1 of the Maine
Constitution and pursuant to the authority granted in Title 30-A M.R.S.A. Section 3001.
Section 2. Review and Approval Authority
The Planning Board is authorized to review and act on all applications for development requiring
site plan review as defined above.
In considering an application under this provision, the Planning Board may act to approve,
disapprove, or approve the project with conditions as are authorized by these provisions in
accordance with the standards provided.
Upon inquiry by an applicant or another party, the Town Code Enforcement Officer shall provide
a brief written decision as to whether or not this Ordinance is applicable to a specific use and,
therefore, Planning Board approval is required within 30 days. This decision is purely advisory
and may not be appealed to the Board of Appeals. If the CEO has any doubt as to the applicability
of this Ordinance, the CEO may require the applicant to submit an applicant to the Planning Board,
which shall determine the applicability of the Ordinance, and may do so before requiring an
applicant submit a full Brooklin Site Plan Review application.
Section 3. Applicability of Brooklin Site Plan Review
A person who has right, title, or interest in a parcel of land must obtain site plan approval prior
to commencing any of the following activities on the parcel, or undertaking any alteration or
improvement of the site including grubbing or grading:
1. The construction or placement of any new building or structure for a nonresidential
use, including accessory buildings and structures.
2. The expansion of an existing nonresidential building or structure including accessory
buildings that increases the total floor area by two hundred fifty (250) square feet.
3. The conversion of an existing building, in whole or in part, from a residential use to a
new nonresidential use.
3
4. The establishment of a nonresidential use even if no buildings or structures are
proposed, including uses such as gravel pits, cemeteries, golf courses, and other
nonstructural nonresidential uses.
5. The conversion of an existing nonresidential use, in whole or in part, to new
nonresidential use.
6. The construction of a residential building containing three (3) or more dwelling units.
7. The modification or expansion of an existing residential structure that increases the
number of dwelling units in the structure by three (3) or more.
8. The conversion of an existing nonresidential building or structure, in whole or in part,
into three (3) or more dwelling units.
9. The construction or expansion of paved areas or other impervious surfaces, including
roof surfaces, walkways, access drives, and parking lots involving an area of more than
two thousand five hundred (2,500) square feet.
The following activities shall not require site plan approval. Certain of these activities will,
however, require the owner to obtain a plumbing permit or other state or local approvals:
1. The construction, alteration, or enlargement of a single family or two-family dwelling,
including accessory buildings and structures.
2. The placement, alteration, or enlargement of a single manufactured home or mobile
home dwelling, including accessory buildings and structures on individually owned
lots.
3. Agricultural activities, including agricultural buildings and structures.
4. Timber harvesting and forest management activities pursuant to Title 12 M.R.S.A
§8868.
5. The establishment and modification of home occupations that do not result in changes
to the site or exterior of the building and do not require on-street parking or storage of
large equipment.
6. Flea markets, yard sales, and similar intermittent or occasional activities where the total
activity area is less than 10,000 f² to be held not more than six (6) times per year.
7. Any structure or use lawfully existing as of the date of this amended Ordinance, unless
such structure or use has been discontinued for a period of at least 12 months, is to be
changed to a different use, or is altered or enlarged.
4
Section 4. Availability
A certified copy of this Ordinance shall be filed with the Town Clerk and shall be accessible to
any member of the public. Copies shall be made available to the public, at reasonable cost, at the
expense of the person making the request. Notice of availability of this Ordinance shall be posted.
Section 5. Severability
The invalidity of any section or provision of this Ordinance shall not be held to invalidate any
other section or provision of this Ordinance.
Section 6. Conflicts
Whenever a provision of this Ordinance conflicts with or is inconsistent with another provision of
this Ordinance or of any other ordinance, regulation or statute administered by the Town, the more
restrictive provision shall control.
Section 7. Amendments
Amendments of this Ordinance may be initiated by the Select Board, or the Planning Board.
No proposed amendments to this Ordinance shall be referred to the Town Meeting until the Select
Board has held a public hearing with Planning Board members in attendance on the proposal,
notice of which shall be posted at least fourteen (14) days prior to such hearing and advertised in
a newspaper of general circulation in the town at least two (2) times with the date of first
publication being at least fourteen (14) days prior to the hearing and the second at least seven (7)
days prior to the hearing.
The proposed amendments shall be adopted by a simple majority vote of the Town Meeting and
upon approval be certified to by the Town Clerk who shall maintain copies in accordance with the
law.
Section 8. Administration and Enforcement
This Ordinance shall be administered and enforced by the Code Enforcement Officer (CEO)
appointed by the Select Board.
It shall be the duty of the CEO to enforce the provisions of this Ordinance. If the CEO shall find
that any provision of this Ordinance is being violated, he/she shall notify in writing that the person
responsible for such violation, indicating the nature of the violation and ordering the action
necessary to correct it. The CEO shall order discontinuance of illegal use of buildings, structures,
additions, or work being done, or shall take any other action authorized by this Ordinance to insure
compliance with or to prevent violation of its provisions.
The Select Board is hereby authorized to institute or cause to be instituted, in the name of the
Town, any and all actions, legal or equitable, that may be appropriate or necessary for the
enforcement of this Ordinance; provided, however, that this section shall not prevent any person
entitled to equitable relieve from enjoining any act contrary to the provisions of this Ordinance.
5
Any person, firm, or corporation being the owner of or having control or use of any building or
premises who violates any of the provisions of this Ordinance, shall be fined, enjoined, or
otherwise penalized all in accordance with Title 30-A §4452. Each day such a violation is
permitted to exist after notification shall constitute a separate offense. The Select Board, or its
authorized agent, is hereby authorized to enter into administrative consent agreements for the
purpose of eliminating violations of this Ordinance and recovering fines without court action. Such
agreements shall not allow an illegal structure or use to continue unless the removal of the
structure or use will result in a threat or hazard to public health and safety or will result in
substantial environmental damage.
Section 9. Standards and Review Criteria
The following criteria shall be used by the Planning Board in reviewing applications for site plan
review and shall serve as standards with minimum requirements for approval of the application.
The application shall be approved unless the Planning Board determines that the applicant has
failed to meet one or more of the standards. In all instances, the burden of proof shall be on the
applicant who must produce evidence sufficient to warrant a finding that all applicable standards
have been met. The Planning Board may waive any of the application standards or requirements
when the Board determines that because of special circumstances such application standards or
requirements would be either (1) burdensome or (2) not be applicable and that the waiver will not
adversely affect the Town or the abutting properties' landowners' or public health, safety and
welfare or intent of this Ordinance. The Planning Board may also utilize as guidelines in meeting
specific standards expert opinion and such related provisions as may be found in the Shoreland
Zoning Ordinance.
The Planning Board shall determine by recorded vote that each of the following listed standards
either:
A. Applies and either (1) has been met by the applicant or (2) has been or will be met by the
applicant subject to stated conditions;
B. Applies and has NOT been met by the applicant for stated reason(s);
C. Does not apply for stated reason(s);
OR
D. Applies but has been waived for stated reason(s).
As a preliminary matter, before considering the following criteria, the Planning Board shall
determine whether the proposed use requires a site plan under this Ordinance.
9.1. Utilization of the Site
6
Standard: The planned development makes proper utilization of the site.
Minimum Requirements:
A. The plan for the development must reflect the natural capabilities of the site to support
development.
B. Buildings, lots, and support facilities must be clustered in those portions of the site that
have the most suitable conditions for development consistent with the criteria of this
Ordinance.
C. Buildings must be set back at least twenty-five (25) feet from the edge of traveled portions
of existing town ways and fifty (50) feet from the edge of traveled portions of a state
highway, and must have a minimum side and rear lot setbacks of fifteen (15) feet.
D. Buildings shall not exceed thirty-five (35) feet in height.
E. Environmentally sensitive areas, including but not limited to, wetlands, steep slopes,
floodplains, significant wildlife habitats, fisheries, scenic areas, habitat for rare and
endangered plants and animals, unique natural communities and natural areas, and sand
and gravel aquifers must be maintained and preserved to the maximum extent.
F. Natural drainage areas must also be preserved to the maximum extent. The development
must include appropriate measures for protecting these resources, including but not limited
to, modification of the proposed design of the site, timing of construction, and limiting the
extent of excavation.
9.2. Adequacy of Road System
Standard: The road system accessing the site is adequate and safe.
Minimum Requirements: Vehicular access to the site must be on roads which have adequate
capacity to accommodate the additional traffic generated by the development.
Guidelines: For developments which generate one hundred (100) or more peak hour trips based on
the Trip Generation Manual of the Institute of Traffic Engineers (see Appendix I), the project must
not reduce the current level of service on any major access route or intersection within one mile of
any entrance road.
Waiver: This requirement may be waived by the Planning Board if the project is located within a
growth area designated in the Town's adopted Comprehensive Plan and the Board determines that
the project will not have an unnecessary adverse impact on traffic flow or safety.
Alternative guideline: A development not meeting this standard may be approved if the applicant
demonstrates that:
7
A. A public agency has committed funds to construct the improvements necessary to bring
the level of access to this standard, or
B. The applicant will assume financial responsibility for the improvements necessary to bring
the level of service to this standard and will assure the completion of the improvements
with a financial guarantee acceptable to the Town (see Section 12.C).
9.3. Access into the Site
Standard: Vehicular access to and from the development must be safe and convenient.
Minimum Requirements:
A. The applicant must have a letter from the Brooklin Fire Chief stating that the development
meets the needs of the Fire Department.
B. Any driveway or proposed street must be designed so as to provide the minimum sight
distance according to the Maine Department of Transportation (DOT) standards, to the
maximum extent possible and a DOT entrance permit must be obtained for new curb cuts.
C. Points of access and egress must be located to avoid hazardous conflicts with existing
turning movements and traffic flows.
D. The grade of any proposed drive or street must be not more than ±3% for a minimum of
two (2) car lengths, or forty (40) feet, from the intersection.
E. Where a lot has frontage on two (2) or more streets, the primary access to and egress from
the lot must be provided from the street where there is less potential for traffic congestion
and for traffic and pedestrians hazards. Access from other streets may be allowed if it is
safe and does not promote shortcutting through the site.
F. Where is it necessary to safeguard against hazards to traffic and pedestrians and/or to avoid
traffic congestion, the applicant shall be responsible for providing turning lanes, traffic
directional islands, and traffic controls within public streets.
G. Accessways must be designed and have sufficient capacity to avoid queuing of entering
vehicles on any public street. Private entrances/exits must be located at least fifty (50) feet
from the closest intersection as measured from the point of tangency for the corner to the
point of tangency for the accessway. This requirement may be reduced if the shape of the
site does not allow conformance with this standard.
H. Private accessways in or out of a development must be separated by a minimum of seventy-
five (75) feet where possible.
8
I. The following criteria must be used to limit the number of driveways serving a proposed
project:
1. No use which generates less than one hundred (100) vehicle trips per day and has less
than 500 feet of roadway frontage shall have more than one (1) two-way driveway onto
a single roadway. Such driveway must be no greater than thirty (30) feet wide.
2. No use which generates one hundred (100) or more vehicle trips per day and has less
than 1,000 feet of roadway frontage shall have more than two (2) points of entry from
and two (2) points of egress to a single roadway. The combined width of all accessways
must not exceed sixty (60) feet.
3. Shared access points to an existing roadway shall be used whenever possible.
9.4. Internal Vehicular Circulation
Standard: The layout of the site provides for the safe movement of passenger, service and
emergency vehicles through the site.
9.5. Parking Layout and Design
Standard: Off-street parking is properly located and sufficient for proposed use.
Minimum Requirements:
A. Parking areas with more than two (2) parking spaces must be arranged so that it is not
necessary for vehicles to back into the street.
B. Parking areas for nonresidential uses must be designed to permit each motor vehicle to
proceed to and from the parking space provided for it without requiring the moving of any
other motor vehicles.
C. Provisions must be made to ensure that parked vehicles do not restrict traffic flow on
adjacent through roads, restrict pedestrian or bicycle movement on adjacent walkways, or
damage landscape materials.
9.6. Pedestrian Circulation
Standard: The site plan provides for a system of pedestrian ways within the development
appropriate to the type and scale of development.
9.7. Stormwater Management
9
Standard: Adequate provisions have been made for the collection and disposal of all stormwater.
Minimum Requirements:
A. The stormwater drainage system and maintenance plan must not have adverse impacts on
abutting or downstream properties.
B. To the extent possible, the plan must retain stormwater on the site using the natural features
of the site.
C. Stormwater runoff systems must detain or retain water such that the rate of flow from the
site after development does not exceed the predevelopment rate.
D. The applicant must demonstrate that on and off-site downstream channel or system
capacity is sufficient to carry the flow without adverse effects, including but not limited to
flooding and erosion of shoreland areas, or that he/she will be responsible for whatever
improvements are needed to provide the required increase in capacity and/or mitigation.
E. All natural drainage ways must be preserved at their natural gradients and must not be filled
or converted to a closed system unless approved as part of the site plan review.
F. The design of the stormwater drainage system must provide for the disposal of stormwater
without damage to streets, adjacent properties, downstream properties, soils, and
vegetation.
G. The design of the storm drainage systems must be fully cognizant of upstream runoff which
must pass over or through the site to be developed and provide for this movement.
H. The biological and chemical properties of the receiving waters must not be degraded by
the stormwater runoff from the development site.
Guideline: The use of oil and grease traps in manholes, the use of on-site vegetated waterways,
and vegetated buffer strips along waterways and drainage swales, and the reduction in use of
deicing salts and fertilizers may be required, especially where the development stormwater
discharges into a gravel aquifer area or other water supply source.
9.8. Erosion Control
Standard: All building, site, and roadway designs and layouts harmonize with existing topography
and conserve desirable natural surroundings to the fullest extent possible.
Minimum requirements:
A. Filling, excavation and earth moving activity must be kept to a minimum.
10
B. Parking lots on sloped sites must be terraced to avoid undue cut and fill, and/or the need
for retaining walls.
C. Natural vegetation must be preserved and protected wherever possible.
D. Soil erosion and sedimentation of watercourses and water bodies must be minimized by an
active program meeting the requirements of the Maine Erosion and Sediment Control
Handbook for Construction: Best Management Practices, dated March 1991.
9.9. Water Supply
Standard: The development is provided with a system of water supply that provides each use with
an adequate supply of water and does not infringe on use by neighboring properties.
Minimum Requirements:
Uses that require extraction of more than 1,000 gallons daily of groundwater must provide
additional information:
A. A complete copy of any application and/or permit for such extraction filed with any agency
or department of the State of Maine.
B. A written report of a hydrologic investigation conducted and prepared by a licensed
professional hydrogeologist, geologist, hydrologist or other appropriately licensed
professional describing the rates of draw down and recharge of any aquifer or other
groundwater source as may have been established by a pumping or "stress test" or other
similar testing regime in accordance with accepted professional standards; the
characteristics of the groundwater source including rates of draw down and recharge,
sustainable extraction rates, aquifer boundaries, recharge areas, impacts on the water
table, and impacts on all existing water bodies including and not limited to streams,
wetlands and private wells or other existing extraction locations within the zone of
contribution; the possible effects on other groundwater resources which might result in
the disturbance of existing minerals and any health hazards raised by such a disturbance or
other impacts including issues such as turbidity and aroma of water extracted within the
zone of contribution.
9.10. Sewage Disposal
Standard: The development is provided with a method of disposing of sewage which is in
compliance with the State Plumbing Code.
Minimum Requirements:
11
A. Applicant must show proof of a subsurface waste water permit for the proposed
development.
B. When four (4) or more lots or buildings in different ownership share the use of a common
subsurface disposal system, the system must be owned and maintained in common by an
owners' association. Covenants in the deeds for each lot must require mandatory
membership in the association and provide for adequate funding of the association to assure
proper maintenance of the system.
9.11. Utilities
Standard: The development is provided with electrical, telephone, and telecommunication service,
adequate to meet the anticipated use of the project.
Minimum Requirements:
A. New utility lines and facilities must be screened from view to the extent feasible.
B. If the service in the street or on adjoining lots is underground, the new service must be
placed underground.
9.12. Natural Features
Standard: The landscape is preserved in its natural state as much as is practical.
Minimum Requirements:
A. Minimize tree removal, disturbance and compaction of soil.
B. Retain existing vegetation in so far as practical during construction.
C. Extensive grading and filling must be avoided as far as possible.
9.13. Water Quality Protection
Standard: The proposed site development and use does not adversely impact either the quality or
quantity of groundwater available to abutting properties or to public water supply systems.
Minimum Requirements:
A. Applicants whose projects involve on-site water supply or sewage disposal systems with a
capacity of two thousand (2,000) gallons per day or greater must demonstrate that the
groundwater at the property line will comply, following development, with the standards
for safe drinking water as established by the State of Maine.
B. All aspects of the project must be designed so that:
1. No person shall locate, store, discharge, or permit the discharge of any treated,
untreated, or inadequately treated liquid, gaseous, or solid materials of such nature,
12
quantity, obnoxiousness, toxicity, or temperature that may run off, seep, percolate, or
wash into surface or groundwaters so as to contaminate, pollute, or harm such waters
or cause nuisances, such as objectionable shore deposits, floating or submerged debris,
oil or scum, color, odor, taste, or unsightliness or be harmful to human, animal, plant,
or aquatic life.
2. All storage facilities for fuel, chemicals, chemical or industrial wastes, and
biodegradable raw materials, must meet the standards of the Maine Department of
Environmental Protection and the State Fire Marshall's Office.
9.14. Hazardous, Special and Radioactive Materials
Standard: The handling, storage, and use of all materials identified by the standards of a federal or
state agency as hazardous, special or radioactive is done in accordance with the standards of these
agencies.
Minimum Requirements:
A. No flammable or explosive liquids, solids or gases shall be stored in bulk above ground
unless they are located at least seventy-five (75) feet from any lot line, or forty (40) feet in
the case of underground storage.
B. All materials must be stored in a manner and location which is in compliance with
appropriate rules and regulations of the Maine Department of Public Safety and other
appropriate federal, state, and local regulations.
9.15. Shoreland Relationship
Standard: The development does not adversely affect the water quality or shoreline of any adjacent
water body.
Minimum Requirements:
A. Portions of the project within the Shoreland Zone must be approved under the Town of
Brooklin Shoreland Zoning Ordinance.
B. The development plan must provide for access to abutting navigable water bodies for the
use of the occupants of the development as appropriate.
9.16. Technical and Financial Capacity
Standard: The applicant demonstrates that he/she has the financial and technical capacity to carry
out the project in accordance with this Ordinance and the approved plan.
Guideline: Financial capacity may be evidenced by a letter of credit from a state or national
financial institution or improvement guarantee as provided in Section 12. Technical capacity may
be evidenced by expert opinion or past successful performance of similar development.
13
9.17. Solid Waste Disposal
Standard: The proposed development provides for adequate disposal of solid wastes.
Minimum Requirements: All solid waste must be disposed of at a licensed disposal facility having
adequate capacity to accept the project's wastes.
9.18. Historic and Archaeological Resources
Standard: If any portion of the site has been identified as containing historic or archaeological
resources, the development includes appropriate measures for protecting these resources,
including but not limited to, modification of the proposed design of the site, timing of construction,
and limiting the extent of excavation.
Guideline: Consult the Maine Historic Preservation Commission regarding the possibility of
historic or archaeological resources on the site.
9.19. Floodplain Management
Standard: If any portion of the site is located within a special flood hazard area as identified by the
Federal Emergency Management Agency, all use and development of that portion of the site is to
be consistent with the Town's Floodplain management provisions.
Guideline: Consult the CEO regarding Floodplain management provisions.
9.20. Air Pollution
Standard: The proposed use does not result in undue air pollution.
Note: The Planning Board shall consult federal and state authorities it determines applicable
regarding air quality laws and regulations.
Minimum Requirements:
A. Emissions of dust, dirt, fly ash, fumes, vapors or gases which pose an unreasonable risk of
harm to human health or the environment shall be prohibited.
B. No land use or establishment shall be permitted to produce unreasonable, offensive or
harmful odors perceptible beyond their lot lines, measured either at ground or habitable
elevations.
9.21. Town Services
Standard: The development does not have an unreasonable adverse impact on Town services
including Town road systems, fire department, police department, solid waste program, schools,
open spaces, recreational programs and facilities, and any other Town services and facilities.
9.22. Exterior Lighting
14
Standard: All exterior lighting is designed to increase night time safety and minimize adverse
impact on neighboring properties.
Minimum Requirements:
A. Any land use or establishment must have adequate exterior lighting to provide for its safe
use during nighttime hours if such use is contemplated. All exterior lighting shall be
designed to avoid undue glare, adverse impact on neighboring properties and rights-of-
way, and the unnecessary lighting of the night sky.
B. Lighting fixtures shall be shielded or hooded so that the lighting elements are not exposed
to normal view of motorist, pedestrians or buildings on abutting properties.
C. Direct or indirect illumination shall not exceed 0.5 foot-candles at the lot line.
9.23. Noise
Standard: Land uses involving noise in excess of that which is normal for the area are designed
and landscaped to minimize noise interference with neighboring uses.
Minimum Requirements:
Noise emanating from the proposed use shall not exceed the standards set forth in Appendix B
"Noise Control" of the Town of Brooklin Wind Energy Facility Ordinance.
9.24. Campgrounds
Standard: Campgrounds shall conform to the minimum requirements imposed under State
licensing procedures.
Minimum Requirements:
A. Campgrounds shall contain a minimum of five thousand (5,000) square feet of land, not
including roads and driveways for each site. Land supporting wetland vegetation, and land
below the normal high-water line of a water body shall not be included in calculating land
area per site.
B. The areas intended for placement of a recreational vehicle, tent or shelter, and utility and
service buildings shall be set back seventy-five (75) feet, horizontal distance, from the
normal high water line of water bodies, tributary streams, or the upland edge of a wetland.
9.25. Mineral Exploration and Extraction
Standard: Mineral exploration and extraction activities not regulated by the State including
extraction of sand, gravel and fill, of less than five acres in size satisfies each of the minimum
requirements of this Section 9.25.
15
Minimum Requirements:
A. Mineral exploration to determine the nature or extent of mineral resources shall be
accomplished by hand sampling, test boring, or other methods which create minimal
disturbance of less than 100 square feet of land surface. A permit from the CEO shall be
required for mineral exploration which exceeds the above limitation. All excavations,
including test pits and holes, shall be immediately capped, filled or secured by other equally
effective measures to restore disturbed areas and to protect the public health and safety.
B. Prior to mineral extraction, a reclamation plan shall be filed with and approved by the
Planning Board before a permit is granted. Such plan shall describe in detail procedures
to be undertaken to fulfill the requirements of this Section.
C. No part of any extraction operation, including drainage and runoff control features, shall
be permitted within 100 feet, horizontal distance, of the normal high-water line of a river,
and within 75 feet, horizontal distance, of the normal high-water line of any other water
body, tributary stream, or the upland edge of a wetland. Extraction operations shall not be
permitted within 50 feet, horizontal distance, of any property line without written
permission of the owner of such adjacent property.
D. Within 12 months following the completion of extraction operations at any extraction site,
which operations shall be deemed complete when less than 100 cubic yards of materials
are removed in any consecutive 12 month period, ground levels and grades shall be
established in accordance with the following:
1. All debris, stumps and similar material shall be removed for disposal in an approved
location, or shall be buried on-site. Only materials generated on-site may be buried or
covered on-site.
2. The final graded slope shall be two and one half to one (2½:1) slope or flatter.
3. Top soil or loam shall be retained to cover all disturbed land areas, which shall be
reseeded and stabilized with vegetation native to the area. Additional topsoil or loam
shall be obtained from off-site sources if necessary to complete the stabilization project.
E. In keeping with the purposes of this Article, the Planning Board may impose such
conditions as are necessary to minimize the adverse impacts associated with mineral
extraction operations on surrounding uses and resources.
9.26. Signage
Standard: Signs relating to goods and services being sold on the premises are properly placed,
sized and illuminated.
Minimum Requirements:
16
A. Freestanding commercial signs shall be placed at right angles to the street, so as to be
viewed from both directions, and shall be set back at least ten (10) feet from the edge of
the traveled way and fifteen (15) feet from the side lot lines.
B. Signs shall be no larger than sixteen (16) square feet in area, shall not exceed two (2) signs
per premises, and shall not extend more than fifteen (15) feet above the ground.
C. Signs shall be illuminated only by shielded, non-flashing lights and shall conform with
Section 9.22.
Section 10. Submission Requirements
Applications for site plan review must be submitted on application forms provided by the Town.
The complete application form, evidence of payment of the required fees, and the required plans
and related information must be submitted to the CEO. The submission must contain at least the
following exhibits and information unless specifically waived in writing. The Planning Board may
waive any of the submission requirements based upon a written request of the applicant and a
finding that the requirement is not necessary for the Board's consideration of the application as
proposed. Such request must be made at the time of the preapplication conference or at the initial
review of the application if no preapplication conference is held. A waiver of any submission
requirement may be granted only if the Board makes a written finding that the information is not
required to determine compliance with the standards.
All applications for site plan review must contain the following information:
A. A fully executed and signed copy of the application for site plan review.
B. Evidence of payment of the application fee, and agreement to pay the professional review
fees.
C. Seven (7) copies of written materials plus seven (7) sets of maps or drawings containing
the information listed below. The written materials must be presented as a report. The
maps or drawings must be at a scale sufficient to allow review of the items listed under the
approval standards and criteria, but in no case shall be more than one hundred (100) feet to
the inch for that portion of the tract of land being proposed for development.
10.1. General information
A. Record owner's name, address, and phone number and applicant's name, address and
phone number if different.
B. The location of all required building setbacks, yards, and buffers.
C. Names and addresses of all property owners within five hundred (500) feet of any and all
property boundaries.
17
D. Sketch map showing general location of the site within the town based upon a reduction of
the tax maps.
E. Boundaries of all contiguous property under the total or partial control of the owner or
applicant regardless of whether all or part is being developed at this time.
F. The tax map and lot number of the parcel or parcels on which the project is located.
G. A copy of the deed to the property, an option to purchase the property or other
documentation to demonstrate right, title or interest in the property on the part of the
applicant.
H. The name, registration number, and seal of the person who prepared the plan, if applicable.
I. Evidence of the applicant's technical and financial capability to carry out the project as
proposed.
10.2. Existing Conditions
A. Zoning classification(s) of the property and the location of Shoreland Zoning district
boundaries if the property is located in two (2) or more zoning districts or abuts a different
district.
B. The bearings and length of all property lines of the property to be developed and the source
of this information. The Planning Board may waive this requirement of a boundary survey
when sufficient information is available to establish, on the ground, all property
boundaries.
C. Location and size of any existing sewer and water mains, culverts and drains, on-site
sewage disposal systems, wells, underground tanks or installations, and power and
telephone lines and poles on the property to be developed, on adjacent streets, or land that
may serve the development, and an assessment of their adequacy and condition to meet the
needs of the proposed use. Appropriate contours must be provided as necessary to
determine the direction of surface water flow.
D. Location, names and present widths of existing public and/or private streets and rights-of-
way within or adjacent to the proposed development.
E. The location, dimensions and ground floor elevation of all existing buildings on the site.
F. The location and dimensions of existing driveways, parking and loading areas, walkways,
and sidewalks on or immediately adjacent to the site.
18
G. Location of intersecting roads or driveways within two hundred (200) feet of the site.
H. The location of open drainage courses, wetlands, stonewalls, graveyards, fences, stands of
trees, and other important or unique natural areas and site features, including but not
limited to, floodplains, deer wintering areas, significant wildlife habitats, scenic areas,
habitat for rare and endangered plants and animals, unique natural communities and
natural areas, sand and gravel aquifers, and historic and/or archaeological resources,
together with a description of such features.
I. The direction of existing surface water drainage across the site.
J. The location, front view, dimensions, and lighting of existing signs.
K. Location and dimensions of any existing easements and copies of existing covenants or
deed restrictions.
L. The location of the nearest water supply for fire protection.
10.3. Proposed Development Activity
A. Estimated demand for water supply and sewage disposal together with the location and
dimensions of all provisions for water supply and wastewater disposal, and evidence of
their adequacy for the proposed use, including soils test pit data if on-site sewage disposal
is proposed and plumbing permit.
B. The direction of proposed surface water drainage across the site and from the site, with an
assessment of impacts on downstream properties.
C. Provisions for handling all solid wastes, including hazardous and special wastes and the
location and proposed screening of any on-site collection or storage facilities.
D. The location, dimensions, and materials to be used in the construction of proposed
driveways, parking and loading areas, and walkways and any changes in traffic flow onto
or off-site.
E. Proposed landscaping and buffering.
F. The location, dimensions, and ground floor elevation of all proposed buildings or building
expansion proposed on the site. Plan and elevation views of all proposed buildings or
building expansion proposed on the site.
G. Location, front view, materials, and dimensions of proposed signs together with the method
for securing sign.
19
H. Location and type of exterior lighting.
I. The location of all utilities, including fire protection systems.
J. A general description of the proposed use or activity.
K. An estimate of the peak hours and daily traffic to be generated by the project.
Section 11. Review Procedures
The Planning Board shall use the following procedures in reviewing applications for site plan
review.
A. Preapplication
Prior to submitting a formal application, the applicant or his/her representative may request
a preapplication conference with the Planning Board. A preapplication conference is
strongly advised. The preapplication conference shall be informal and informational in
nature. There shall be no fee for a preapplication review, and such review shall not cause
the plan to be a pending application or proceeding under Title 1 M.R.S.A. §302. No
decision on the substance on the plan shall be made at the preapplication conference, except
that a Planning Board may issue a final decision that the Ordinance is not applicable.
1. Purpose
The purposes of the preapplication conference are to:
a. Allow the Planning Board to understand the nature of the proposed use and the
issues involved in the proposal,
b. Allow the applicant to understand the development review process and required
submissions,
c. Identify issues that need to be addressed in future submissions, and
d. Make the applicant aware of any opportunities for coordinating the development
with community policies, programs, or facilities.
e. To determine whether the Planning Board will waive certain submission
requirements.
2. Information Required
20
There are no formal submission requirements for a preapplication conference.
However, the applicant should be prepared to discuss the following with the Board:
a. The proposed site, including its location, size, and general characteristics,
b. The nature of the proposed use and potential development,
c. Any issues or questions about existing town regulations and their applicability to
the project, and
d. Any requests for waivers from the submission requirements.
B. Application Submission and Review Procedures
The applicant must prepare and submit a site plan review application, including the
development plan and supporting documentation, that meets the submission requirements
set forth in Section 10 and below. This material must be submitted to the CEO two weeks
prior to the next regular monthly meeting.
1. The applicant shall notify by first-class mail all property owners within five hundred
(500) feet of the parcel on which the proposed development is located. Written notice
of the pending application shall be mailed to the CEO, Fire Chief, Road Commissioner,
and Plumbing Inspector.
2. Within thirty-five (35) days of the receipt of a formal site plan review application, the
Planning Board shall review the material and determine whether or not the submission
is complete. If the application is determined to be incomplete, the Board shall notify
the applicant of this finding, shall specify the additional materials required to make the
application complete and shall advise the applicant that the application will not be
considered by the Board until the additional information is submitted to the Board.
These steps, except the notification requirements, shall be repeated until the application
is found to be complete.
3. As soon as the Board determines that the application is complete and the Board has
received payment of any professional service fees as determined in subsection D.2
below, the Board shall; notify the applicant of this finding, meet the notification
requirements of subsection 4 below, and place the item on the agenda for substantive
review within thirty-five (35) days of this finding.
4. The Planning Board shall hold a public hearing on any complete application if so
requested by the applicant by a landowner within 500 feet of the proposed site, by a
majority vote of the Board of Selectman, or by a petition of 15% of the votes cast in
the last gubernatorial election in town. Upon receipt of any completed application the
21
Board shall publish a notice as soon as possible in a newspaper of area-wide circulation
describing the application and notifying the public that a hearing will be held. The
deadline for receipt by the Planning Board of requests or petitions for a public hearing
shall be the next regular Planning Board meeting that occurs within thirty-five (35)
days after the application is deemed complete. Public hearings by the Planning Board
shall be conducted according to the procedures outlined in Title 30, M.R.S.A Section
2691.
5. The Planning Board may hold an on-site inspection of the site to review the existing
conditions, field verify the information submitted and investigate the development
proposal. The Board may schedule this visit either before or after the first meeting at
which the application is considered. The Board may decide not to hold an on-site
inspection when the site is snow covered. If an application is pending during a period
when there is snow cover, the deadline by which the Planning Board shall take final
action on the application as specified in subsection 4 above may be extended, which
extensions shall not exceed thirty-five (35) days after the Board is able to conduct an
on-site inspection. Written notice of the on-site inspection shall be provided to all
parties entitled to notice under subsection 1 above or by publication of notice as soon
as possible in a newspaper of area-wide circulation describing the application and
notifying the public that an on-site inspection will be held. Any site inspection made
by the Board shall be with notice as provided by law for the holding of a public meeting,
however, no deliberations may then be conducted nor evidence taken, with the
exception that photographs may be made for later presentation at hearing or Board
meeting.
6. The Planning Board shall take final action on said application within thirty-five (35)
days of determining that the application is complete. The Board shall act to deny, to
approve, or to approve the application with conditions. The Board may impose such
conditions as are deemed advisable to assure compliance with the standards of
approval.
In issuing its decision, the Planning Board shall make written findings of fact establishing that the
proposed development does or does not meet the standards of approval and other requirements of
the Town. The Board shall notify the applicant of the findings of fact and any conditions of
approval.
All time limits provided for in this section may be extended by mutual agreement of the applicant
and Planning Board.
C. Final Approval and Filing
Upon completion of the requirements of this Section and an approval vote by the majority of
the Planning Board members, the application shall be deemed to have final approval and the
22
permit shall be signed by the voting members of the Board and must be filed with the Code
Enforcement Officer.
D. Fees
1. Fees associated with applications for permits under this Ordinance shall be as indicated
on the Town fee schedule, as determined by the Select Board, in effect at the time the
application is deemed complete by the permitting authority.
2. The applicant will be responsible for all professional fees incurred by the Planning
Board in evaluating an application. In reviewing the application for compliance with
this Ordinance, the Planning Board may retain professional services, including, but not
limited to, those of an attorney or consultant, to verify information presented by the
Applicant. The attorney or consultant shall first estimate the reasonable cost of such
review and the Applicant shall deposit with the Town of Brooklin the full estimated
cost, which the Town shall place in an escrow account. The Town shall pay the attorney
or consultant from the escrow account and shall provide an accounting and refund, if
due, within forty-five (45) days of a request from the applicant. The commencement
of such professional services shall not be required until the requested deposit is made
and the time lapsed from request to payment shall be added to the time allowed for
Board consideration of the application. If an appeal of a Planning Board decision
issued pursuant to this Ordinance is filed, any funds remaining is the escrow account
may be retained any used for any professional fees incurred by the Board of Appeals
in considering such appeal, except that applicant is not required to replenish such fees
if depleted in the course of the appeal, except as otherwise provided by the Board of
Appeals Ordinance.
Section 12. Post Approval Activities
A. Limitation of Approval
Construction of the approved, permitted project must be substantially commenced within
twelve (12) months and substantially completed within eighteen (18) months of the date
upon which the approval was granted. If construction has not been substantially
commenced or substantially completed within the specified period, the approval shall be
null and void and the CEO shall issue a stop work order until the applicant appears before
the Board at a regularly scheduled meeting to review the prior approval. The applicant
may request an extension of either deadline prior to the expiration of the period. Such
request must be in writing and must be made to the Planning Board. The Planning Board
may grant extensions to the periods if the approved plan conforms to the ordinances in
effect at the time the extension is granted and any and all federal and state approvals and
permits are current.
B. Incorporation of Approved Plan
23
All construction activities must conform to the approved plan, including any conditions of
approval and minor changes approved by the CEO to address field conditions.
C. Improvement Guarantees
1. Application
a. Improvement Guarantee - The Planning Board may require the posting of an
improvement guarantee in such amount and form as specified in subsection 2 below
as is reasonably necessary to ensure the proper installation of all off-site
improvements required as conditions of approval. The nature and duration of the
guarantee shall be structured to achieve this goal without adding unnecessary costs
to the applicant.
b. Upon substantial completion of all required improvements, the developer must
notify the Planning Board of the completion or substantial completion of
improvements, and must send a copy of such notice to the CEO. The CEO shall
inspect all improvements and must file a report indicating either approval, partial
approval, or rejection or such improvements with a statement of reasons for any
rejection.
c. The Planning Board shall either approve, partially approve, or reject the
improvements on the basis of the report of the CEO.
d. If the improvements are approved the guarantee shall be released upon receipt by
the Board of a contractor's certificate with accompanying lien waivers evidencing
that all contractors, subcontractors and suppliers have been paid in full. Where
partial approval is granted, the developer shall be released from liability only for
that portion of the improvements approved.
2. Form of Guarantee
Performance guarantees may be provided by a variety of means including, but not limited
to, the following which must be approved as to form and enforceability by the Board of
Selectmen.
a. Security Bond - The applicant may obtain a security bond from a surety bonding
company authorized to do business in the state.
b. Letter of Credit - The applicant may provide an irrevocable letter of credit from a
bank or other reputable lending institution.
c. Escrow Account - The applicant may deposit cash, or other instruments readily
convertible into cash at face value, either with the town, or in escrow with a bank.
Any such account must require Town approval for withdrawal and must stipulate
24
that the Town can withdraw the money upon forty-eight (48) hour advance notice
to the applicant to complete the guaranteed improvements.
D. Submission of As-Built Plans
Any project involving the construction of more than ten thousand (10,000) square feet of
gross floor area or twenty thousand (20,000) square feet of impervious surface, must
provide the CEO with a set of construction plans showing the building(s) and site
improvements as actually constructed on the site. These "as-built" plans must be submitted
within thirty (30) days of completion of construction or upon request of the CEO.
E. Minor Changes to Approved Plans
Minor changes in approved plans necessary to address field conditions may be approved
by the CEO provided that any such change does not affect compliance with the standards
or alter the essential nature of the proposal. Any such change must be endorsed in writing
on the approved plan by the CEO.
F. Amendments to Approved Plans
Approvals of site plans are dependent upon and limited to the proposals and plans
contained in the application and supporting documents submitted and affirmed by the
applicant. Any variation from the plans, proposals, and supporting documents, except
minor changes that do not affect approval standards, is subject to review and approval by
the Board at a regular or special meeting following public notification procedures outlined
in Section 11.B above.
Section 13. Appeals and Variances
A. Powers and Duties of the Board of Appeals. The Board of Appeals shall have the following
powers:
1. Administrative appeals in accordance with section 13.C.
2. Variance Appeals in accordance with section 13.B.
B. Variance Appeals: Variances may be granted only under the following conditions:
1. Variances may be granted only from dimensional requirements including, but not
limited to, lot width, structure height, and setback requirements.
2. Variances shall not be granted for establishment of any uses otherwise prohibited by
this Ordinance.
3. The Board of Appeals shall not grant a variance unless it finds that:
25
a. The variance is necessary for access by handicapped or disabled persons in
accordance with Title 30-A M.R.S.A. Section 4353 (4)(A-C);
OR
b. The proposed structure of or use would meet the provisions of Section 9 except for
the specific provision which has created the nonconformity and from which relief
is sought; and
c. The strict application of the terms of this Ordinance would result in undue hardship.
The term "undue hardship" shall mean:
i.
That the land in question cannot yield a reasonable return unless a variance
is granted;
ii.
That the need for a variance is due to the unique circumstances of the
property and not the general conditions in the neighborhood;
iii.
The granting of a variance will not alter the essential character of the
locality; and
iv.
That the hardship is not the result of action taken by the applicant or prior
owner.
4. The Board of Appeals shall limit any variances granted as strictly as possible in order
to ensure conformance with the purposes and provisions of this Ordinance to the
greatest extent possible, and in doing so may impose such conditions to a variance as
it deems necessary. The party receiving the variance shall comply with any conditions
imposed.
C. Administrative Appeals
1. When the Board of Appeals hears a decision of the Planning Board, it shall hold an
appellate hearing, and may reverse the decision of the Planning Board only upon
finding that the decision was contrary to specific provisions of the Ordinance or
contrary to the facts presented to the Planning Board. The Board of Appeals shall not
receive or consider any evidence which was not presented to the Planning Board, but
the Board of Appeals may receive and consider written or oral arguments. If the Board
of Appeals determines that the record of the Planning Board proceedings are
inadequate, the Board of Appeals may remand the matter to the Planning Board for
additional finding of fact.
26
D. Appeal Procedure
1. Making an appeal.
a. An administrative or variance appeal may be taken to the Board of Appeals by an
aggrieved party who is either an abutter or who had participated in the
proceedings before the Planning Board from any decision of the Planning Board.
Such an appeal shall be taken within thirty (30) days of the date of the official,
written decision appealed from, and not otherwise, except that the Board of
Appeals, upon a showing of good cause, may waive the thirty (30) day
requirement.
b. Applications for appeals shall be made by filing with the Board of Appeals a written
notice of appeal which includes:
i.
A concise written statement indicating what relief is requested and why the
appeal or variance should be granted.
ii.
A sketch drawn to scale showing lot lines, location of existing buildings,
structures and other physical features of the lot pertinent to the relief sought.
c. Upon receiving an application for an administrative appeal or a variance, the CEO
or Planning Board shall transmit to the Board of Appeals all of the papers
constituting the record of the decision appealed from.
d. The Board of Appeals shall govern the appeal in accordance with the Board of
Appeals Ordinance.
E. Appeal to Superior Court
Except as provided by Title 30-A M.R.S.A. Section 2691(3)(F) or the Board of Appeals
Ordinance, any aggrieved party who participated as a party during the proceedings before the
Board of Appeals may take an appeal to Superior Court in accordance with the State laws
within forty-five (45) days from the date of any decision of the Board of Appeals.
F. Reconsideration
In accordance with Title 30-A M.R.S.A Section 2691(3)(F), the Board of Appeals may
reconsider any decision within forty-five (45) days of its prior decision.
Section 14. Definitions
A. Meaning of Words
27
All words not defined herein shall carry their customary and usual meanings. Words used
in the present tense shall include the future. Words used in the singular shall include the
plural.
B. Definitions
Abutting property: Any lot which is physically contiguous with the subject lot even if
only at a point and any lot which is located directly across a street or right-of-way from the
subject lot such that the extension of the side lot lines of the subject lot would touch or
enclose the abutting property.
Accessory building: A detached, subordinate building, the use of which is clearly
incidental and related to that of the principal structure or use of the land, and which is
located on the same lot as that of the principal structure or use.
Aggrieved party: An owner of land whose property is directly or indirectly affected by
the granting or denial of an approval under this Ordinance; a person whose land abuts land
for which approval has been granted; or any other person or group of persons who have
suffered particularized injury as a result of the granting or denial of such approval.
Agricultural Activities: The production, keeping or maintenance for sale or lease, of
plants and/or animals, including but not limited to forages and sod crops, grains and seed
crops, dairy animals and dairy products, poultry and poultry products, livestock, fruits and
vegetables, cannabis (to the extent permitted by local and state law) and ornamentals and
greenhouse products. Agricultural activities do not include the processing of agricultural
products for market or consumption such as slaughterhouses, packing plants or canneries.
Except, however, commercial uses on properties otherwise used for agricultural activities,
such as restaurants, wedding venues, and stores selling products other than those grown or
raised on site, shall be considered Commercial Uses and not Agricultural Activities.
Arterial: A controlled access road or a street or road with stop signs on side streets or
which is functionally classified by the Maine Department of Transportation as an arterial.
Building: Any permanent structure having one or more floors and a roof, which is used
for the housing or enclosure or persons, animals or property. When any portion thereof is
separated by a division wall without opening, then each such portion shall be deemed a
separate building.
Building footprint: The area covered by a building measured from the exterior surface of
the exterior walls at grade level exclusive of cantilevered portions (including roof
overhangs) of the building. Where the building is elevated above grade level on posts or
similar devices, the building footprint is the area the building would cover if it were located
at ground level.
Commercial use: An activity the intent or result of which is to generate revenue from the
buying and selling of goods and/or services, exclusive of rental of single-family or duplex
28
dwellings, agricultural activities, industrial use, and home occupations. This definition
includes non-profit organizations and activities.
Curb cut: The opening along the curb line or street right-of-way line at which point
vehicles may enter or leave the street.
Enlargement or expansion of a structure: An increase of the building footprint and/or
increase in the height of the structure beyond its present highest point. Alterations of
existing buildings which are required in order to meet the requirements of the Americans
with Disabilities Act (ADA) and/or the State Fire Code are not considered to be
enlargements or expansions of a structure and are not required to meet otherwise
applicable setback requirements, provided the alterations are the minimum necessary to
satisfy the ADA and/or State Fire Code.
Enlargement or expansion of use: Any intensification of use in time, volume, or function,
whether or not resulting from an increase in the footprint, height, floor area, land area or
cubic volume occupied by a particular use. Increases which are required in order to meet
the requirements of the American with Disabilities Act and/or the State Fire Code are not
considered to be enlargements or expansions of use.
Fisheries, significant fisheries: Areas identified by a governmental agency such as the
Maine Department of Inland Fisheries and Wildlife, Atlantic Salmon Authority, or Maine
Department of Marine Resources as having significant value as fisheries and any areas so
identified in the Town's Comprehensive Plan.
Floor area: The sum of the horizontal areas of the floor(s) of a structure enclosed by
exterior walls as measured from the inside of exterior walls.
Groundwater: All of the water found beneath the surface of the ground. For purposes of
aquifer protection, this term refers to the subsurface water present in aquifers and recharge
areas.
Historic or archaeological resource: Areas identified by a governmental agency such as
the Maine Historic Preservation Commission as having significant value as a historic or
archaeological resource and any areas identified in the Town's Comprehensive Plan.
Home occupation: An occupation or profession which is customarily conducted on or in
a residential structure or property and which is 1) clearly incidental to and compatible
with the residential use of the property and surrounding residential uses, and 2) which
employs no more than two (2) persons other than family members residing in the home.
Impervious surface: The area covered by buildings and associated constructed facilities,
areas which have been or will be covered by a low-permeability material, such as asphalt
or concrete, and areas such as gravel roads and unpaved parking areas, which have been or
will be compacted through design or use to reduce their permeability. Common impervious
surfaces include, but are not limited to, roof tops, walkways, patios, driveways, parking
lots or storage areas, concrete or asphalt paving, gravel roads, packed earthen materials,
29
and oiled, macadam, or other surfaces which similarly impede the natural infiltration of
stormwater.
Multi-Family Use: The use of a single structure or multiple structures for residential
purposes by more than one independently living family but not including successive
seasonal rentals of a single family residence.
Natural areas and natural communities, Unique natural areas and natural
communities: Areas identified by a governmental agency such as the Maine Department
of Conservation Natural Areas Program as having significant value as a natural area and
any areas identified in the Town's Comprehensive Plan.
Natural capabilities: The ability of the natural conditions at the site to facilitate the
proposed project (for example, contour or ledge).
New nonresidential use: A change in the type of occupancy of a nonresidential building
or structure, or a portion thereof, such that the basic type of use is changed, such as from
retail to office or storage to a restaurant, but not including a change in the occupants.
Nonresidential use: a commercial use, not including agricultural activities, home
occupations, or residential uses.
Principal structure: A building other than one which is used for purposes wholly
incidental or accessory to the use of another building or use on the same premises.
Principal use: A use other than one which is wholly incidental or accessory to another use
on the same premises.
Recharge area: Area composed of permeable, porous material through which precipitation
and surface water infiltrates and directly replenish groundwater in aquifers.
Residential: Used or intended to be used wholly or principally for human habitation.
Rentals of properties or structures to persons for residential purposes are considered to be
a residential use, regardless of the length of tenancy or residency of the property owner.
Right, title or interest: An interest in real estate that is evidenced by (a) holding record
title, (b) having a purchase and sale agreement and seller consent to the action requested,
(c) having a written option to buy, or (d) having a lease that provides some evidence of
authority for the proposed use or structure.
Setback, front: An open area extending the entire width of a lot from lot sideline to lot
sideline and extending in depth at a right angle from the street right-of-way to such depth
as specified. For lots that do not front on a street then the phrase shall mean an open area
extending the entire width of a lot from lot sideline to lot sideline and extending in depth
at a right angle from the side of the lot that is closest to a street. Such area shall be
unoccupied and unobstructed by any building from the ground upward.
Setback, rear: An open area extending the entire width of a lot from lot sideline to lot
sideline and extending at a right angle from the rear property line of such lot to such depth
30
as specified. Such area shall be unoccupied and unobstructed by any building from the
ground upward.
Setback, side: An open area extending along each sideline of a lot between the front
setback and rear setback on such lot and extending at a right angle from the sidelines of
such lot to such depth as specified. Such area shall be unoccupied and unobstructed by any
building from the ground upward.
Structure: Anything constructed or erected, which requires location on the ground or
attached to something having a location on the ground, but not including a tent or vehicle.
Substantially commenced; substantially completed: Construction shall be considered
to be substantially commended when any work beyond the state of excavation, including
but not limited to the pouring of a slab or footings, the installation of piles, the construction
of columns, or the placement of a manufactured home on a foundation has begun.
Construction shall be considered to be substantially completed when it has been completed
to the point where normal functioning, use, or occupancy can occur without concern for
the general health, safety, and welfare of the occupant and the general public. At a
minimum is shall include the completion of no less than seventy (70) percent of the costs
of the proposed improvements within a development and shall include permanent
stabilization and/or revegetation of areas of the site that were disturbed during construction.
Use: The purpose for which land or a building is arranged, designed, or intended, or for
which either land or a building is or may be occupied or maintained.
Vegetation: All live trees, shrubs, ground cover, and herbaceous plants.
Wildlife habitat, significant wildlife habitat: Area identified by a governmental agency
such as the Maine Department of Inland Fisheries and Wildlife as having significant value
as habitat for animals and any areas identified in the Town's Comprehensive Plan.
31
"Appendix I. Trip Generation Manual of the Institute of Traffic Engineers" is incorporated by
reference and contains no revisions.