WIRELESS COMMUNICATIONS FACILITIES ORDINANCE
TOWN OF BROOKSVILLE
TABLE OF CONTENTS
Section
Page
1
Title
1
2
Authority
1
3
Purpose
1
4
Applicability
2
5
Review and Approval Authority
2
New Construction
Expansion of an existing facility
Reconstruction of an existing facility
Expiration of approved applications
6 Application Process
3
Pre-Application Conference
General Rules for All Applications
Planning Board Application Requirements (new construction)
Application Procedure for Planning Board Approval
Planning Board Decision
7
Planning Board Approval Standards
8
8
CEO Approval Requirements (expansion of an existing facility)
10
9
Submission Waiver 10
10
Fees
11
11
Amendment to an Approved Application
11
12
Abandoned or Uncompleted Facilities
11
13
Appeals
12
14
Administration and Enforcement
12
15
Penalties
13
16
Conflict and Severability
13
17
Effective Date
13
18
Definitions
13
1
WIRELESS COMMUNICATIONS FACILITIES ORDINANCE
TOWN OF BROOKSVILLE
Section 1: TITLE
This Ordinance shall be known and cited as the "Wireless Communications
Facilities Ordinance" of Brooksville, Maine (hereinafter referred to as the
"ordinance").
Section 2: AUTHORITY
This ordinance is adopted pursuant to the enabling provisions of Article VIII,
Part 2, Section 1 of the Maine Constitution (Municipal Home Rule); the
provisions of Title 30-A MRSA Section 3001 (Home Rule); and the provisions of
the Planning and Land Use Regulation Act, Title 30-A MRSA Section 4312 et
seq., and 30-A MRSA Section 4452 ('Enforcement and Land Use Laws and
Ordinances').
Section 3: PURPOSE
The purpose of this ordinance is to provide a process and a set of standards
for wireless communications facilities in order to:
--Implement a municipal policy concerning the provision of wireless
communications services and the siting of their facilities,
--Establish clear guidelines, standards and time frames for the Town to
regulate wireless communications facilities,
--Allow competition in wireless communications service,
--Encourage the provision of advanced wireless communications services to
the largest number of businesses, institutions and residents of Brooksville,
--Permit and manage reasonable access to the public rights of way of
Brooksville for wireless communications purposes on a competitively neutral
basis,
--Ensure that all entities providing wireless communication service facilities
and services within Brooksville comply with the Town's ordinances,
--Ensure that Brooksville can continue fairly and responsibly to protect the
public health, safety and welfare of its citizens,
--Encourage the co-location of wireless communications facilities, thus helping
to minimize adverse impacts and to protect the visual character of the Town
of Brooksville,
2
--Enable Brooksville to discharge its public trust consistent with rapidly
evolving federal and state regulatory policies, industry competition and
technological development,
--Further the goals and policies of Brooksville's comprehensive plan, while
promoting orderly development of the town with minimal impacts on existing
uses, and
--Protect the scenic and visual character of the community.
Section 4: APPLICABILITY
This local land use ordinance applies to all construction, expansion and
reconstruction of wireless communications facilities, existing or proposed,
except as provided below:
1) Emergency wireless communications facility: A temporary wireless
communication facility for emergency communications by public
officials or agencies.
2) Amateur (ham) radio station: An amateur (ham) radio station
licensed by the Federal Communications Commission (FCC) provided
that it is not more than fifty (50) feet in height.
3) Parabolic antenna: A parabolic antenna less than seven (7) feet in
diameter and not more than fifty (50) feet in height which is an
accessory use of the property.
4) Maintenance or repair: Maintenance or repair of a wireless
communications facility and related equipment, provided that there is
no change in the height or any other dimension of the facility.
5) Temporary wireless communications facility: A temporary wireless
communications facility in operation for a maximum period of thirty
(30) days.
6) Antenna as accessory use: An antenna that is an accessory use
to a residential dwelling unit, provided that it does not exceed fifty
(50) feet in height.
Section 5: REVIEW AND APPROVAL AUTHORITY
No person shall construct or expand a wireless communications facility
without approval of the CEO and Planning Board as follows:
5.1. New construction. Approval by the Planning Board is required for
construction of a new wireless communications facility.
3
5.2 Expansion of an existing facility. Approval by the CEO is required for
expansion of an existing wireless communication facility.
5.3 Reconstruction of an existing facility.
5.3.1 Non-conforming: A non-conforming wireless communications
facility, removed or destroyed for any reason, may be reconstructed
on the same site, provided that it complies with the maximum height
restriction in section 7.3 and does not make the facility any more non-
conforming.
5.3.2 Conforming: A conforming wireless communications facility,
removed or destroyed for any reason, may be reconstructed on the
same site, provided there is no change in the height or any other
dimension of the facility that would noticeably alter the physical
character of the facility.
5.3.3 Written notification to the Planning Board is required for
reconstruction of an existing wireless communication facility. A surety
(bond) consistent with Section 6.3.11 shall be submitted for approval
with that written notification to the Planning Board before any
reconstruction begins. Reconstruction is allowed only within one year
of the damage or removal of the existing facility.
5.4 Expiration of approved applications. All approvals shall expire within one
(1) year of the date of issuance unless work there under is substantially
completed. If work is not substantially completed within one (1) year, a new
application must be made.
Section 6: APPLICATION PROCESS
6.1 Pre-Application Conference
All persons seeking approval of the CEO or the Planning Board under this
ordinance shall meet with the CEO no less than thirty (30) days before filing
an application. At this meeting the CEO shall explain to the applicant the
ordinance provisions as well as the application forms and submissions that
will be required under this ordinance.
6.2 General Rules for All Applications
All persons seeking approval of the CEO or the Planning Board under this
ordinance shall submit an application which includes the following
information:
6.2.1 Documentation of the applicant's right, title or interest in the
property on which the facility is to be sited, including the name and
address of the property owner and the applicant.
4
6.2.2 A copy of the FCC license for the facility, or a signed statement
from the owner or operator of the facility, attesting that the facility
complies with current FCC regulations, including standards for radio
emissions.
6.2.3 Identification of districts, sites, buildings, structures or objects,
significant in American history, architecture, archaeology, engineering
or culture, that are listed, or eligible for listing, in the National
Register of Historic Places (see 16 U.S.C. 470w(5); 36 CFR 60 and 800).
6.2.4 Location map and elevation drawings of the proposed facility
and any other proposed structures showing color and identifying
structural materials.
6.2.5 List of names, addresses, tax map and lot number of all property
owners within ½ (one-half) mile radius of the proposed structure.
6.2.6 A signed statement that the owner of the facility, and his/her
successors and assigns, agree to:
(i) respond in a comprehensive manner within 30 days to a
request for information from a potential co-location
applicant,
(ii) negotiate in good faith for shared use by third parties,
(iii) allow shared use if an applicant agrees in writing to pay
reasonable charges for co-location,
(iv) require no more than a reasonable charge for shared use,
based on community rates and generally accepted accounting
principles. This charge may include but is not limited to a pro
rata share of the cost of site selection, planning project
administration, land costs, site design, construction and
maintenance, financing, return on equity, depreciation and all
of the costs of adopting the tower or equipment to
accommodate a shared user without causing
electromagnetic interference.
The CEO or Planning Board may request documentation to
substantiate any co-location charges imposed by the party
whose facility is the site of the proposed co-location. Any
documentation provided as substantiation would be
considered confidential and would not be made public or
shared with any party other than the CEO or Planning
Board.
5
6.3 Planning Board Application Requirements (new construction)
In addition to the general rules of Section 6.2, the application shall include the
following information:
6.3.1 A USGS 7.5 minute topographic map showing the location of all
Structures and wireless communications facilities above 150 feet in
height above ground level, except antennas located on roof tops,
within a five (5) mile radius of the proposed facility unless this
information has been previously made available to the municipality.
This requirement may be met by submitting current information
(within thirty days of the date the application is filed) from the FCC
Tower Registration Database.
6.3.2 A site plan prepared and certified by a professional engineer
registered in the State of Maine, indicating the location, type and
height of the proposed facility, antenna capacity, on-site and
abutting off-site land uses, means of access, setbacks from property
lines, and all applicable American National Standards Institute (ANSI)
technical and structural codes.
6.3.3 A boundary survey for the project performed by a land surveyor
licensed by the State of Maine.
6.3.4 A visual assessment, consisting of the following:
(i) Elevation drawings of the proposed facility, and any other
proposed structures, showing height above ground level.
(ii) Landscaping plan indicating the proposed placement of
the facility on the site; location of existing structures, trees
and other significant site features; the type and location of
plants proposed to screen the facility; the method of fencing,
the color of the structure, and the proposed lighting method.
(iii) Photo simulations of the proposed facility taken from
perspectives determined by the CEO. Each photo must be
labeled with the line of sight, elevation, and with the date
taken imprinted on the photograph. The photos shall show
the color of the facility and method of screening.
6.3.5 A narrative which includes:
(i) The extent to which the proposed facility would be visible
from a designated scenic resource,
(ii) The distance to the proposed facility from the noted
viewpoints of a designated scenic resource.
6
6.3.6 A drawing showing the fields of coverage of present wireless
communication facilities and the area proposed to be covered by the
applicant.
6.3.7 A written description of how the proposed facility fits into the
applicant's communications network. This submission does not
require disclosure of confidential business information.
6.3.8 Evidence demonstrating that no existing building, site or
structure can accommodate the applicant's proposed facility. Such
evidence may consist of any one or more of the following:
(i) Evidence that no existing facilities are located within the
targeted market coverage area which meet the applicant's
engineering requirements.
ii) Evidence that existing facilities do not have sufficient height
or cannot be increased in height at a reasonable cost or
without exceeding one hundred, ninety (190) feet to meet the
applicant's engineering requirements.
iii) Evidence that existing facilities do not have sufficient
structural strength to support applicant's proposed antenna
and related equipment. Specifically:
(a) The applicant's proposed equipment would ex-
ceed the structural capacity of the existing facility,
considering the existing and planned use of those
facilities, and these existing facilities cannot be re-
inforced to accommodate the new equipment.
(b) The applicant's proposed antenna or equipment
would cause electromagnetic interference with the
antenna on the existing towers or structures, or the
antenna or equipment on the existing facility would
cause interference with the applicant's proposed
antenna.
(c) Existing or approved facilities do not have space
on which equipment can be placed so it will function
effectively.
(d) The fees, costs or contractual provisions required
by the owner in order to share or adapt an existing
facility are unreasonable and/or the costs exceeding
the pro rata share of a new facility are presumed to
be unreasonable.
7
6.3.9 Evidence that the applicant has made diligent good faith efforts
to negotiate co-location on an existing facility, building or structure
and has been denied access.
6.3.10 Written agreement that the applicant will certify compliance
with all applicable FCC radio frequency emissions regulations within
thirty (30) days of a request from the Town.
6.3.11 A sample form of a surety (bond), to be approved by the
Planning Board, in an amount sufficient to cover the costs of site
improvements and the costs of removal should the facility be
abandoned or uncompleted in accordance with Section 12. That bond
shall specify that the municipality shall be notified by the bonding
agent of any cancellation or reduction of the surety. The Planning
Board shall specify how much of the surety is allocated to completion
of the facility and how much to removal of an abandoned or
uncompleted facility. It is a condition of approval that a certified copy
of the actual surety-bond be filed with the Town within forty-five (45)
days of approval.
6.4 Application Procedure for Planning Board Approval
6.4.1 Seven (7) copies of the application shall be filed with the CEO at
least two (2) weeks prior to the scheduled Planning Board meeting for
review. The application shall be accompanied by the permit
application fee (Section 10.1). Within forty-five (45) days of the filing
of an application, the Planning Board shall review the application and
determine if the application meets the submission requirements. The
CEO and the Planning Board shall review any requests for a waiver
from the submission requirements submitted pursuant to Section 9
and shall act on these requests prior to determining the completeness
of the application.
6.4.2 If the application is complete, the CEO shall notify the applicant
in writing of this determination. If the application is incomplete, the
CEO shall notify the applicant in writing, specifying the additional
materials or information required to complete the application.
6.4.3 The Planning Board shall hold a public hearing within thirty (30)
days of the date on the notice from the CEO to the applicant that the
application was deemed complete. The Planning Board shall publish
the time, date and place of the hearing at least one (1) time at least
seven (7) days prior to the hearing in a newspaper of area-wide
circulation. Property owners within one-half (1/2) mile radius shall be
notified by mail by the Planning Board of the hearing. Failure on the
part of any abutter to receive such notice shall not be grounds for
delay of any consideration of the application nor denial of the project.
8
6.5 Planning Board Decision
Within thirty (30) days of the public hearing, or within another time limit as
may be otherwise mutually agreed upon by the Planning Board and the
applicant, the Board shall approve, approve with conditions or deny the
application in writing, together with the findings on which that decision is
based.
Section 7: PLANNING BOARD APPROVAL STANDARDS
An application for approval by the Planning Board under Section 6 must meet
the following standards.
7.1 Design for Co-location. A new wireless communications facility and related
equipment shall be designed and constructed to accommodate expansion for
future co-location of at least three additional wireless communications
facilities or providers.
7.2 Tower Design. Lattice tower structures without guy-wires are preferred.
Where a monopole and/or guy-wires are specified, applicant must
demonstrate the future utility of such a structure for expansion of service for
the applicant and for co-locators.
7.3 Height. A new wireless communications facility shall be no more than one
hundred ninety (190) feet in height.
7.4 Setback. The base of tower of a new or expanded wireless
communications facility shall be set back one hundred fifty percent (150%) of
its height from all property lines and public roads. The setback may be
satisfied by including the areas outside the property boundaries if secured by
an easement.
7.5 Landscaping. A new wireless communications facility and related
equipment shall be screened with plants from view by abutting properties, to
the maximum extent practicable. Existing plants and natural land forms on the
site shall also be preserved to the maximum extent practicable. Landscaping
shall be exclusively native and non-invasive plants.
7.6 Fencing. A new wireless communications facility shall be fenced to
discourage trespass on the facility and to discourage climbing on any structure
by trespassers.
7.7 Lighting. A new wireless communications facility shall be illuminated only
as necessary to comply with FAA or other applicable state and federal
requirements. Security lighting may be used as long as it is shielded to be
down directional to retain light within the fenced boundaries of the site.
7.8 Color and Materials. A new wireless communications facility must be
constructed with materials and colors that match or blend with the
surrounding natural or built environment, to the maximum extent practicable.
9
Unless otherwise required, muted colors, earth-tones, and subdued hues shall
be used.
7.9 Structural Standards. A new wireless communications facility must
comply
with
the
current
Electronic
Industries
Association/
Tele-
communications Industries Association (EIA/TIA) 222 Revision Standard
entitled "Structural Standards for Steel Antenna Towers and Antenna
Supporting Structures" and with Hancock County Standards for wind shear
and ice load.
7.10 Visual Impact. The proposed wireless communications facility, to the
greatest degree practicable, shall have no unreasonable adverse impact upon
designated scenic resources and structures within the Town, as identified in
the municipally adopted comprehensive plan or by a State or Federal agency,
such as the National Register of Historic Places.
In determining the potential unreasonable adverse impact of the proposed
facility upon scenic resources, the Planning Board may consider the following
factors:
1) The extent to which the proposed wireless communications facility
is visible above tree line from the viewpoint(s) of the impacted
designated scenic resource and the particular scenic areas of value
noted in the Town's Comprehensive Plan.
2) The type, number, height and proximity of existing structures and
features, and the background features within the same line of sight as
the proposed facility.
3) The amount of vegetative screening.
4) The distance of the proposed facility from the viewpoint and the
facility's location within the designated scenic resource.
5) The presence of reasonable alternatives that allow the facility to
function consistently with its purpose.
7.11 If an applicant proposes to locate a new wireless communications facility
on municipal property, the applicant must show the following:
7.11.1 The proposed location complies with applicable municipal
policies and ordinances.
7.11.2 The property lies outside of the Shoreland Zone.
7.11.3 The proposed facility will not interfere with the intended
purpose of the property.
7.11.4 The applicant has adequate liability insurance and a lease
agreement
with
the
municipality
that
includes
reasonable
10
compensation for the use of the property and other provisions to
safeguard the public rights and interests in the property.
Section 8: CEO APPROVAL REQUIREMENTS (for expansion of an existing
facility)
8.1 An application for expansion of a non-conforming facility shall address the
general rules for all applications (Section 6.2) and also include:
8.1.1 A drawing showing the fields of coverage of present wireless
communications facilities and the area proposed to be covered by the
expansion, and
8.1.2 A written description of how the expanded facility will fit into
the applicant's wireless communications network. This submission
does not require disclosure of confidential business information.
8.2 An application for expansion of a conforming facility which was not
detailed in the original application approved by the Planning Board shall
include:
8.2.1 A drawing showing the fields of coverage of present wireless
communications facilities and the area proposed to be covered by the
expansion,
8.2.2 A written description of how the expanded facility will fit into
the applicant's wireless communications network. This submission
does not require disclosure of confidential business information, and
8.2.3 A revised drawing from the application approved by the
Planning Board showing the proposed expansion.
Within thirty (30) days of receipt of the completed application, or within
another time limit as may be mutually agreed upon by the CEO and the
applicant, the CEO shall approve, approve with conditions or deny the
application in writing, together with the findings on which that decision is
based.
Section 9: SUBMISSION WAIVER
The CEO and/or the Planning Board may waive any of the submission
requirements based upon a written request of the applicant submitted at the
time of application. A waiver of any submission requirement may be granted
only if the CEO and/or the Planning Board find in writing that due to special
circumstances of the application the information is not required to determine
compliance with the standards of this ordinance.
11
Section 10: FEES
10.1 Application Fee. An application for CEO and/or for Planning Board
approval shall include payment of an application fee of two hundred fifty
dollars ($250). The application shall not be considered complete until this fee
is paid.
10.2 Planning Board Review Fee. In addition to the application fee required
under Section 10.1 above, the Planning Board may require an applicant to
deposit, in advance, with the Town Treasurer, a sum determined by the
Planning Board to be sufficient to reimburse all outside costs to be incurred by
the Planning Board in its review of the application. Such costs may include,
but are not limited to, costs of professional surveying, engineering and legal
assistance as needed by the Planning Board pursuant to their review of the
application. The purpose of such outside services shall be to provide
independent technical advice to the Planning Board when, in the opinion of
the Planning Board, the public interest or issues raised by the application may
require it. In the event the Planning Board's actual outside review costs
exceed the initial cost estimate, the Planning Board will require the applicant
to deposit additional funds with the Town Treasurer. All funds shall be
deposited in an escrow account and any portion not used shall be returned to
the applicant within thirty (30) days of the Planning Board's decision.
Section 11: AMENDMENT TO AN APPROVED APPLICATION
Any changes to an approved application must be approved by the CEO and/or
the Planning Board, in accordance with Section 5. If there is a transfer of
ownership before or during the building phase, the new owner shall meet
with the CEO and/or the Planning Board.
Section 12: ABANDONED OR UNCOMPLETED FACILITIES
12.1 Abandoned Facilities. A wireless communications facility that is not
operated for a continuous period of twelve (12) months shall be considered
abandoned. The CEO shall notify the owner of an abandoned facility in writing
and order the removal of the facility within ninety (90) days of receipt of the
written notice. The owner of the facility shall have thirty (30) days from the
receipt of the notice to demonstrate to the CEO that the facility has not been
abandoned. If the owner fails to show that the facility is in active operation,
the owner shall have sixty (60) days to remove the facility. If the facility is not
removed within this time period, the municipality may remove the facility at
the facility owner's expense, the cost of which shall first come from any surety
or bond in favor of the municipality under Section 6.3.11.
12.2 Uncompleted Facilities. A wireless communications facility that does not
contain all lot improvements and landscaping in accordance required under
this ordinance by the time it goes into operation shall be considered
12
uncompleted. The CEO shall notify the owner of the facility in writing and
order the completion of said facility within ninety (90) days of receipt of the
written notice. If the facility is not completed within this time period, the
municipality may undertake all uncompleted lot improvements and
landscaping at the facility owner's expense, the cost of which shall first come
from any surety bond in favor of the municipality under Section 6.3.11.
12.3 Release of Surety/Bond. Upon removal of the wireless communications
facility or the completion of said facility, as the case may be, the facility owner
may apply to the Planning Board for release of part or all of the surety bond.
The request shall not be unreasonably withheld so long as the facility has
been removed or completed to the satisfaction of the Planning Board.
Section 13: APPEALS
Any appeal by any aggrieved party with standing from any decision of the CEO
or the Planning Board to approve, approve with conditions or deny any
application made under this ordinance, including any enforcement action or
inaction alleged under Section 14 of this ordinance, shall be to the Superior
Court in accordance with Rule 80(B) of the Maine Rules of Civil Procedure,
said appeal to be filed within thirty (30) days of the written decision, action of
failure or refusal to take action complained of.
Section 14: ADMINISTRATION AND ENFORCEMENT
The CEO, as appointed by the Board of Selectmen, shall enforce this
ordinance. If the CEO finds that any provision of this ordinance has been
violated, the CEO shall notify in writing the person responsible for such
violation, indicating the nature of the violation and ordering the action
necessary to correct it. The CEO may take any other legal action to ensure
compliance with this ordinance.
The Board of Selectmen is authorized to enter into administrative consent
agreements for the purpose of eliminating violations of this ordinance and
recovering fines without court action. Such agreements shall not allow a
violation of this ordinance to continue unless there is clear and convincing
evidence that the violation occurred as a direct result of erroneous advice
given by an authorized municipal official upon which the applicant reasonably
relied to its detriment and there is no evidence that the owner acted in bad
faith and/or that the removal of the violation will result in a threat to public
health and safety or substantial environmental damage.
13
Section 15: PENALTIES
Any person who owns or controls any building, tower or property that violates
this ordinance shall be penalized in accordance with 30-A MRSA §4452. Each
day such violation continues after notification by the CEO shall constitute a
separate offense.
Section 16: CONFLICT AND SEVERABILITY
13.1 Conflicts with other Ordinances. Whenever a provision of this ordinance
conflicts with or is inconsistent with another provision of this ordinance or of
any other ordinance, regulation, or statute, the more restrictive provision
shall apply.
13.2 Severability. The invalidity of any part of this ordinance shall not
invalidate any other part of this ordinance.
Section 17: EFFECTIVE DATE
This ordinance becomes effective immediately upon passage by the Town.
Section 18: DEFINITIONS
Antenna: any system of poles, panels, rods, reflecting discs or similar devices
used for the transmission or reception of radio or electromagnetic frequency
signals.
Antenna Height: the vertical distance measured from the base of the antenna
support structure at grade to the highest point of the structure, even if said
highest point is an antenna. Measurement of tower height shall include
antenna, base pad, and other appurtenances and shall be measured from the
finished grade of the facility site. If the support structure is on a sloped grade,
then the average between the highest and lowest grades shall be used in
calculating the antenna height.
Co-location: the use of a wireless communications facility by more than one
wireless communications provider.
Conforming: a communications facility constructed under the authority of the
Wireless Communication Facilities Ordinance or one complying with the
requirements thereof.
Designated scenic resource: that specific location, view or corridor identified
as a scenic resource in the municipally adopted comprehensive plan or by a
state or federal agency that consists of:
1) a three dimensional area extending out from a particular viewpoint
on a public way or within a public recreational area focusing on a
14
single object, such as a mountain, resulting in a narrow corridor, or
a group of objects, such as a downtown skyline or mountain range,
resulting in a panoramic view corridor.
2) lateral terrain features such as valley sides or woodland as
observed to either side of the observer, constraining the view into
a narrow or particular field, as seen from a viewpoint on a public
way or within a public recreational area.
Expansion: the addition of antennas, towers or other devices and structures
to an existing facility, by the owner or a co-locator, which was not detailed in
the application approved by the Planning Board.
FAA: the Federal Aviation Administration or its lawful successor.
FCC: the Federal Communications Commission, or its lawful successor.
Guy-wire: a tensioned cable between the tower and the ground or other
surface for lateral support.
Height: the vertical measurement from a point on the ground at the mean
finish grade adjoining the foundation, as calculated by averaging the highest
and lowest finished grade around the building or structure, to the highest
point of the building or structure. The highest point shall exclude farm
building components, flagpoles, chimneys, ventilators, skylights, domes, water
towers, bell towers, church spires, processing towers, tanks, bulkheads or
other building accessory features usually erected at a height greater than the
main roofs of buildings.
Historic, archaeological and recreational resources: resources which are:
1. Listed individually in the National Register of Historic Places or
eligible for listing on the National Register;
2. Certified or preliminarily determined by the Secretary of the
interior as contributing to the historical significance of a registered
historic district or a district preliminarily determined by the Secretary
of the Interior to qualify as a registered historic district;
3. Individually listed on a state inventory of historic places in states
with historic preservation programs approved by the Secretary of the
Interior;
4. Individually listed on a local inventory of historic places in
communities with historic preservation programs that have been
certified by Secretary of the Interior through the Maine Historic
Preservation Commission;
5. Areas identified by a government agency such as the Maine Historic
Preservation Commission as having significant value or archaeological
15
resource and any areas identified in the municipality's comprehensive
plan, which have been listed or are eligible for listing; and
6. State and local park and conservation land.
Lattice tower: a type of mount with multiple legs and structural cross-bracing
between the legs that is self-supporting and free-standing.
Line of sight: the direct view of the object from the designated scenic
resource.
Monopole: a mount that is self-supporting with a single shaft of wood, steel,
concrete or other material that is designed for the placement of antennas and
arrays along the shaft.
Mount: the structure or surface upon which antennas and arrays are
mounted.
Non-conforming: a communications facility that is not constructed under the
authority of the Wireless Communications Facilities Ordinance and does not
meet the requirements thereof.
Parabolic antenna (also known as a satellite dish antenna): a bowl-shaped
antenna designed for the reception and/or transmission of radio frequency
communication signals in a specific directional pattern.
Principal use: the use other than one which is wholly incidental or accessory
to another use on the same premises.
Public recreational facility: a regionally or locally significant facility, as defined
and identified either by State statute or in the municipality's adopted compre-
hensive plan, designed to serve the recreational needs of people.
Setback: the distance measured from the base of the tower.
Shall and May: "shall" is mandatory; "may" is permissive.
Substantially completed: 90% of total construction is completed.
Targeted market coverage area: the area which is targeted to be served by
the proposed communications facility.
Unreasonable adverse impact: the proposed project would produce an end
result which is excessively out-of-character with the designated scenic
resources affected, including existing buildings, structures and features
within the designated scenic resource, and/or would significantly diminish the
scenic value of the designated scenic resource.
Viewpoint: that location which is identified either in the Town's compre-
hensive plan or by a federal or state agency and which serves as the basis for
the location and determination of a particular designated scenic resource.
16
Wireless communications facility or facility: any structure, equipment,
antenna, tower or other device which provides radio/television transmission,
commercial mobile wireless services, unlicensed wireless services, cellular
phone services, specialized mobile radio communications (SMR), common
carrier wireless exchange phone services, specialized mobile radio
communications (SMR), common carrier wireless exchange access services,
and personal communications service (PCS) or pager services, or any other
kind of wireless communication transmissions. When a tower or similar
support structure is land-based, "facility" includes the area and all
components including the perimeter fencing.