ZONING ORDINANCE
OFTHE
TOWN OF CASTINE, MAINE
ENACTED BY THE TOWN IN MEETING AsSEMBLED THE
1 sr DAY OF JUNE 2013 AND AS THEREAFTER AMENDED.
ATTEST:
THIS IS A TRUE DOCUMENT. THE ZONING ORDINANCE OF THE TOWN OF CASTINE, MAINE, HAS BEEN
IN EFFECT WITHOUT CHANGE FROM JUNE 1, 2013 TO THE DATE HEREOF, EXCEPT AS AMENDED.
SUS1'!..>A.-M.ACOMBER
CASTINE TOWN CLERK
THIS PAGE INTENTIONALLY LEFT BLANK
ZONING ORDINANCE OF THE TOWN OF CASTINE
TABLE OF CONTENTS
ARTICLE 1: GENERAL PROVISIONS .................................................................... 6
l.!TITLE .............................................................................................................. 6
1.2 REPEAL OF OTHER ORDINANCES ........................................................................ 6
1.3 AUTHORITY ...................................................................................................... 6
1. 4 PURPOSES ....................................................................................................... 7
1.5 APPLICABILITY .................................................................................................. 7
1.6 CONFLICT WITH OTHER ORDINANCES OR WTT'HIN THIS ORDINANCE ......................... 7
1.7 SEVERABILITY .................................................................................................. 7
1.8 AMENDMENTS TO ORDINANCE AND OFFICIAL ZONING MAP ..................................... 7
1.9 ANNUAL ADMINISTRATIVE REPORT .................................................................... 10
1.10 EFFECTIVE DATE .......................................................................................... 10
ARTICLE 2: CONTRACT ZONING ....................................................................... 11
2.1 CONTRACT ZONING AUTHORIZED ...................................................................... 11
2.2 APPLICATION, PUBLIC HEARING, REVIEW AND APPROVAL PROCESS ....................... 11
2.3 TOWN MEETING ACTION .................................................................................. 12
2.4 FEES ............................................................................................................ 13
2.5 EXPIRATION OF REZONING .............................................................................. 13
2.6 NO RIGHTS CREATED BEFORE FINAL TOWN MEETING VOTE ................................. 13
ARTICLE 3: NON .CONFORMITY ......................................................................... 14
3.1 NON-CONFORMITY DEFINED ............................................................................. 14
3.2 GENERAL PROVISIONS ..................................................................................... 14
3.3 NON-CONFORMING USES ................................................................................. 16
3.4 NON-CONFORMING STRUCTURES ...................................................................... 16
3.5 NON-CONFORMING MOBIL HOMES ................................................................... 20
3.6 NON-CONFORMING LOTS ................................................................................. 20
ARTICLE 4: ZONING DISTRICTS ....-..-..-..-..-..-..--..-...-.........-..-....--.--.....-...-..-..-... 22
4.1 ZONING DISTRICTS ESTABLISHED ..................................................................... 22
4.2 STANDARDS ESTABLISHING DISTRICTS .............................................................. 22
4.3 OFFICIAL ZONING MAP .................................................................................... 25
4.4 ZONING DISTRICT BOUNDARY DESCRIPTIONS ..................................................... 25
4.5 UNCERTAINTY OF BOUNDARY LOCATIONS ........................................................... 31
4.6 DIVISION OF LOTS BY DISTRICT BOUNDARIES .................................................... 32
1 \Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04 Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- I l
Amended: OI-Jun-13
Amended·. 23-Sept- 13
Amended: I I-May- !9
Amended. ll-Jul-20
Amended: 11-May-24
last Amended: 07-Jun-25
4.7 DISTRICT OVERLAY REQUIREMENTS .................................................................. 32
ARTICLE 5: LAND USE TABLE AND DIMENSIONAL REQUIREMENTS ..-...--.-.--.-.-. 39
5.1 SYMBOLS USED IN LAND USE TABLE ................................................................. 39
5.2 USES SUBSTANTIALLY SIMILAR TO LISTED USES ................................................. 39
5.3 COMPLIANCE WITH LAND USE STANDARDS ......................................................... 40
5.4 LAND USE TABLE ........................................................................................... 40
5.5 DIMENSIONAL REQUIREMENTS ......................................................................... 47
ARTICLE 6: PERFORMANCE STANDARDS ......................................................... 50
6.1 GENERAL ...................................................................................................... 50
6.2 ARCHAEOLOGICAL OR HISTORICAL SITES ........................................................... 50
6.3 CAMPGROUNDS .............................................................................................. 51
6.4 CONSTRUCTION IN FLOOD HAZARD AREAS ......................................................... 51
6.5 DRIVEWAYS AND WALKWAYS ............................................................................ 51
6.6 DUST, FUMES, VAPORS, GASES, ODORS, AND EXPLOSIVE MATERIALS ................... 51
6.7 EROSION AND SEDIMENT CONTROL ................................................................... 51
6.8 FENCES ........................................................................................................ 54
6.9 FIRE HAZARD MITIGATION IN THE COMMERCIAL DISTRICT .................................... 55
6.10 GROUNDWATER PROTECTION ......................................................................... 56
6.11 HOME OCCUPATIONS .................................................................................... 56
6.12 JUNKYARDS ................................................................................................. 57
6.13 LAND NOT SUITABLE FOR DEVELOPMENT ......................................................... 58
6.14 LIGHTING .................................................................................................... 59
6.15 MINERAL EXPLORATION ................................................................................. 59
6.16 MINERAL EXTRACTION ................................................................................... 60
6.17 MANUFACTURED HOUSING ............................................................................ 62
6.18 MOBIL HOME PARKS/MANUFACTURED HOUSING COMMUNITIES ......................... 63
6.19 Two-FAMILY AND MULTI-FAMILY DWELLINGS .................................................. 64
6.20 MULTIPLE STRUCTURES ON A SINGLE LOT ....................................................... 65
6.21 NOISE ......................................................................................................... 66
6.22 OFF-STREET PARKING ................................................................................... 67
6.23 OIL AND CHEMICAL STORAGE ......................................................................... 70
6.24 ON-SITE CIRCULATION .................................................................................. 71
6.25 POLLUTION LEVELS ....................................................................................... 72
6.26 PRESERVATION AND ENHANCEMENT OF THE LANDSCAPE .................................... 72
6.27 RECREATIONAL VEHICLES .............................................................................. 72
6.28 SIGNS ......................................................................................................... 73
6.29 SITE CONDITIONS...........
. .............................................. 75
2\Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May 19
Amended· 11-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
6.30 SWIMMING POOLS AND SPAS .......................................................................... 76
6.31 TIMBER HARVESTING .................................................................................... 76
6.32 UTILITIES/SEWAGE DISPOSAL/WASTE DISPOSAL/WATER SUPPLY ...................... 76
6.33 ACCESSORY DWELLING UNITS ..................................................................... 78
6.34 AFFORDABLE HOUSING DEVELOPMENTS ........................................................ 79
ARTICLE 7: SHORELAND STANDARDS .............................................................. 80
7.1 AGRICULTURE ................................................................................................ 80
7.2 CLEARING OR REMOVAL OF VEGETATION FOR ACTIVITIES OTHER THAN TIMBER
HARVESTING ................................................................................................. 81
7.3 EROSION AND SEDIMENTATION CONTROL .......................................................... 84
7.4 ESSENTIAL SERVICES .................................................................................. 85
7.5 INDIVIDUAL, PRIVATE CAMPSITES ...................................................................... 85
7.6 MINERAL EXPLORATION AND EXTRACTION .......................................................... 86
7.7 PARKING AREAS ............................................................................................. 88
7.8 PIERS, DOCKS, WHARVES, BRIDGES AND OTHER STRUCTURES AND USES EXTENDING
OVER OR BELOW THE NORMAL HIGH-WATER LINE OF A WATER BODY OR WITHIN A
WETLAND ....................................................................................................... 88
7. 9 PRINCIPAL AND ACCESSORY STRUCTURES .......................................................... 90
7. l O ROADS AND DRIVEWAYS ................................................................................ 91
7.11 SEPTIC WASTE DISPOSAL .............................................................................. 94
7. 12 SOILS .......................................................................................................... 94
7.13 STORM WATER RUNOFF ................................................................................ 94
7.14 'I'rMER HARVESTING ...................................................................................... 95
7.15 WATER QUALITY ........................................................................................... 95
ARTICLE 8: CODE ENFORCEMENT OFFICER PERMITS .-..-.....-..-...-..--.--..-..-..-.-- 96
8.1 CODE ENFORCEMENT OFFICER PERMIT REQUIRED ............................................. 96
8.2 PROCEDURE .................................................................................................. 98
8.3 ACCESS TO SITE AND RECORDS ...................................................................... 101
ARTICLE 9: SITE PLAN REVIEW BY PLANNING BOARD ....-..-..-.-...-..-..-...--..-.--.. 103
9 .1 PURPOSE ..................................................................................................... 103
9.2 ACTIVITIF.,S REQUIRING SITE PLAN REVIEW ....................................................... 103
9.3 ACTIVITIES Nor REQUIRING SITE PLAN REVIEW ................................................ 104
9.4 CLASSIFICATION ........................................................................................... 104
9.5 PROHIBITION ................................................................................................ 105
9.6 SITE PLAN REVIEW APPLICATION ..................................................................... 105
9.7 REVIEW PROCEDURES........
111
31Page
ZDning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
/\mended: 07-May-02
Amended, 04-Apr-05
Amended: 26-Mar-07
Amended; 24-Mar-08
Amended: 04-Apr-09
/\mended: 27-Mar-10
Amended: 02-Nov.JO
Amended: 26·Mar-ll
Amended: Ol-Jun-13
Amended; 23-Sept·l3
Amended: I 1-May-19
Amended: 1 l -Jul-20
Amended: ll-May-24
Last Amended· O?·Jun-25
9.8 PUBLIC HEARING PROCEDURES ...................................................................... 115
9.9 PROFESSIONAL REVIEW ................................................................................. 116
9.10 FAILURE TO AC.'T ......................................................................................... 117
9.11 EXPIRATION OF APPROVALS .......................................................................... 117
9.12 OTHER PERMITS ......................................................................................... 118
9.13 ACCESS TO SITE AND RECORDS .................................................................... 118
9.14 SITE PLAN REVIEW CRITERIA ....................................................................... 119
9.15 WAIVER OF CERTAIN APPLICATION REQUIREMENTS ......................................... 121
9.16 WAIVER OF CERTAIN REVIEW CRITERIA ......................................................... 121
9.17 APPEALS .................................................................................................... 121
ARTICLE 10: CERTIFICATES OF COMPLETION AND OCCUPANCY OR USE .-..... 123
ARTICLE 11: FEES .......................................................................................... 125
11.1 GENERAL PROVISIONS ................................................................................. 125
11.2 BUILDING PERMIT FEES .............................................................................. 125
11.3 SITE PLAN REVIEW FEES ............................................................................. 129
11.4 AFrER-THE-FACT APPLICATION FEE .............................................................. 130
11.5 TECHNICAL REVIEW FEE ............................................................................. 130
11.6 ZONING BOARD OF APPEALS ADMINISTRATION FEES ........................................ 131
11.7 CONTRACT ZONING APPLICATION FEES .......................................................... 131
11.8 ADJUSTMENT OF FEES BY SELECTBOARD ...................................................... 131
ARTICLE 12: ENFORCEMENT ......................................................................... 132
12.1 CODE ENFORCEMENT OFFICER .................................................................... 132
12.2 ENFORCEMENT PROCEDURE ........................................................................ 132
12.3 LEGAL ACTION ........................................................................................... 133
12.4 FINES ....................................................................................................... 133
ARTICLE 13: PLANNING BOARD ...................................................................... 134
13. l AUTHORITY ................................................................................................ 134
13.2 ESTABLISHMENT AND ORGANIZATION OF PLANNING BOARD .............................. 134
13.3 POWERS AND DUTIES .................................................................................. 135
ARTICLE 14: ZONING BOARD OF APPEALS ...................................................... 136
14.1 ESTABLISHMENT AND ORGANIZATION OF ZONING BOARD OF APPEALS ............... 136
14.2POWERSANDDUTIES .................................................................................. 137
14.3APPEALPROCEDURE ................................................................................... 139
14.4 APPEAL TO SUPERIOR COURT ....................................................................... 142
41Page
Zoning Ordinance - Adopted: 28· Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended; 04-Apr-09
Amended: 27·Mar-10
Amended: 02·Nov-10
Amended: 26-Mar- ll
Amended: 01-Jun-13
Amended. 23-Sept-13
Amended: 11-May-19
Amended: ll-Jul-20
Amended: 11- May-24
Last Amended: 07 -Jun-25
ARTICLE 15: DEFINITIONS -.---..-....---...-.....--..-..-..-...-...-..-...-..-...--..-.-..-...-...--.. 143
ZONING MAPS .--..-......-..-..-..-..-....-...---...-..-..--..-..-..--..-...-..-...-..-...-.....-..-.......--.. 169
TABULATION OF AMENDMENTS
-
Amendment 1 .................................................................................. March 26, 2001
Articles amended: 1, 3, 4, 5, 6, 8, 9, 10, 11, 12, 13 14 and 15
-
Amendment 2 ............................................................................. March 25, 2002
Articles amended: 1, 3, 4, 5, 6, 8, 9, 11, 14, 15 and Zoning Map
-
Amendment 3 .................................................................................. May 7, 2002
Articles amended: 4, 5, 6, 8, 11, 12, and 15
-
Amendment 4 ................................................................................. April 4, 2005
Articles amended: 11 and 12
-
Amendment 5 ............................................................................. March 26, 2007
Articles amended: 5, 6, 8, 9, 10, 13 and 15
-
Amendment 6 ............................................................................. March 24, 2008
Articles amended: 1, 4, 5, 6, 8, 9, 11, 14 and 15
-
Amendment 7 ................................................................................ April 4, 2009
Articles amended: 3, 5, 6, 7, 9, 11 and 15
-
Amendment 8
......................... March 27, 2010
Articles amended: 3, 5, 9 and 13
-
Amendment 9 ......................................................................... November 2, 2010
Articles amended: 6
-
Amendment 10 ........................................................................... March 26, 2011
Articles amended: 2, 3, 4, 5, 6, 7, 8, 9, 15 and Zoning Maps
-
Amencbnent 11 ... ... ... ......... ... ...... ... ......... ... ... ......... ...
. ............ June 1, 2013
Articles amended: XXXX.X
-
Amendment 12 .......................... .
... September 23, 2013
Article amended: 5
-
Amendment 13 ............................ .
............. May 11, 2019
Articles amended: 5, 6, 7 and 15
-
Amendment 14 ................................................................................... July 11, 2020
Articles amended: 6
-
Amend!nent 15 ................................................................................... May 11, 2024
Articles amended: 5, 6 and 15
-
Amendment 16 ................................................................................... June 7, 2025
Articles amended: 5, 8, 11 and 15
51Page
Zoning Ord \nance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: OJ-Jun-13
Amended. 23-Sept-13
Amended: I I-May-19
Amended: l 1-Jul-20
Amended: 11-May.24
Last Amended: 07-Jun-25
ARTICLE 1: GENERAL PROVISIONS /Am 1. 26-Mar-0],l__Am2. 25-Mar-0L~m6. 24-Mar-Ofil
1.1. TITLE
This Ordinance shall be known as the "Zoning Ordinance of the Town of Castine,
Maine". It shall be referred to herein as the "Ordinance".
1.2. REPEAL OF OTHER ORDINANCES
The Zoning Ordinance of the Town of Castine, Maine in existence at the time of
the adoption of this Ordinance is hereby repealed. That repeal does not affect or
prevent any pending or future prosecution for violations or abatement of
violations of that repealed ordinance.
1.3. AUTHORITY
This Ordinance is adopted pursuant to Maine Constitution, Article VIII, Part
Second, Section 1, Title 30-A M.R.S.A., § 3001 et seq., Title 30-A M.R.S.A., § 4352
et seq., and Title 38 M.R.S.A., § 435 et seq. 0\_m 0),
1.4. PuRPOSES
A.
To implement the policies, guidelines and recommendations of the current
Castine Comprehensive Plan.
B.
To promote and protect the character of Castine by dividing the Town into
zoning districts according to the use of land and buildings and the intensity
of such uses.
C.
To enhance and protect the visual, natural, commercial, cultural,
architectural, scenic and historic resources of the Town from unreasonable
adverse impacts and to integrate new development harmoniously into the
Town's natural and developed environment. _cirn.0_1
D.
To promote the development of an economically sound and stable
community.
E.
To protect property rights and values by balancing the rights of landowners
to use their land, with the rights of abutting and neighboring landowners to
6IPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- 11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11- May-19
Amended: 11 Jul-20
Amended: 1 l-May-24
Last Amended: 07-Ju.n-25
enjoy their properties without unreasonable disturbance from abutting or
neighboring uses. ! '\m._J_i !And-ii
F.
To establish uniform procedures whereby the Town may review land use
proposals; to establish fair and reasonable standards for reviewing those
proposals; and to provide uniform procedures whereby aggrieved parties
may appeal decisions made under this Ordinance.
1.5. APPLICABILITY
This Ordinance shall apply to all land and water areas within the Town of
Castine. All buildings or structures demolished, constructed, reconstrncted,
altered, enlarged or moved, and all uses of buildings, land and structures, and
any division of land or alteration of lot boundaries, shall be in conformance with
the provisions of this Ordinance. No existing or future building or structure, or
water or land area shall be used except in conformity with this Ordinance. Any
application pending at the time of the enactment of this Ordinance or any
amendment hereto, and which has not yet received substantive review by the
Planning Board, if a Planning Board permit is required, or by the Code
Enforcement Officer, if a Code Enforcement Permit is required, shall be subject to
this Ordinance or the amendments as though the application were submitted on
or after the date of the enactment of the Ordinance or amendment.
1.6. CONFLICT WITH OTHER ORDINANCES OR WITHIN THIS ORDINANCE
Whenever the requirements of this Ordinance are in conflict with the
requirements of any other lawfully adopted rule, regulation, ordinance or statute
which also applies to the proposed development, or with other requirements of
this Ordinance, the requirement imposing the more restrictive or higher standard
shall govern.
1. 7. SEVERABILITY
Should any section or provision of this Ordinance be declared by the court to be
invalid, such decision shall not invalidate any other section or provision of this
Ordinance.
1.8. AMENDMENTS TO ORDINANCE AND OFFICIAL ZoNING MAP
71Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended. 26-Mar-Ql
Amended; 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended: 01-Jun-13
Amended: 23-Sept- 13
Amended. ll-May-19
Amended. 1 l-Jul-20
Amended: 11-May-24
Last Amended· 07-Jun-25
The process for amending the Ordinance and the Official Zoning Map, including
enactment of a wholly new ordinance or map, shall be as follows:
A.
Initiation of the amendment
A proposal to amend the Ordinance or the Official Zoning Map may be
initiated by:
1.
The Planning Board, by a majority vote of its members;
2.
The Selectboard, by a majority vote of its members;
3.
The public, through a written petition signed by at least fifty (50)
residents who are registered to vote in the Town of Castine.
B.
Consideration of the amendment
The following procedures shall be followed in considering a proposed
amendment.
1.
Proposals initiated by the public or by the Selectboard shall be
presented to the Planning Board for review and consideration.
2.
The Planning Board shall, within thirty-five (35) days of proposing an
amendment or receiving a proposed amendment, set a date to hold a
public hearing on the proposed amendment. The Planning Board shall
be deemed to have proposed or received a proposed amendment when
the text is presented in written form at a duly convened business
meeting of the Planning Board. A text submitted for review and
consideration at a Planning Board work session shall not be deemed to
be a proposed amendment. The public hearing on any proposed
amendment shall be held within sixty (60) days of proposal or receipt
by the Planning Board and may be adjourned to a later certain date
unless a majority of the members of the Planning Board or a majority of
the members of the Selectboard object. The public hearing on the
proposed amendment shall be concluded at least thirty (30) days prior
to the regular or special Town Meeting at which the proposed
amendment is to be voted upon.
8 I p a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended. 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-OS
Amended: 26-Mar-07
Amended· 24-Mar-OS
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended. Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended· ll-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
3.
Notice of the public hearing shall be given as required by State law.
4.
The wording of a proposed amendment initiated by public petition may
not be modified at or as the result of any public hearing held by the
Planning Board unless the proposed modified wording is submitted to a
new public hearing.
5.
The wording of a proposed amendment initiated by the Selectboard may
be modified only upon the concurrence of a majority of the Selectboard.
6.
The wording of an amendment proposed by the Planning Board may be
modified upon the concurrence of a majority of the Planning Board.
7.
In the case of a proposed amendment received by the Planning Board
from the Selectboard or the public, the Planning Board shall vote to
approve or disapprove the proposed amendment. This vote shall be by
majority vote of its members and must occur at the public hearing or at
a public meeting held not later than fourteen (14) days following the
public hearing. Such vote of the Planning Board shall be reported in
writing within fourteen ( 14) days following the vote, and the report shall
set forth the Planning Board's reasons for approval or disapproval
together with any recommendations. The vote by the Planning Board is
advisory, only, and shall not affect the proposed amendment in any
way.
C.
Town Meeting action on the amendment
The proposed amendment shall be submitted to the Town Meeting for
approval or disapproval as follows:
1.
The proposed amendment shall be placed on the warrant for the next
regular Tov.rn Meeting, unless a special Town Meeting is called for that
purpose in accordance with State law.
2.
Notice of Town Meeting required to a.mend or enact a zoning ordinance
or map shall be given as required by State law.
3.
A proposed amendment shall require a simple majority of the voters
voting at the Town Meeting to enact the amendment.
9 \ P a g e
Zoning Ordinance -Adopted· 28-Mar-2000
Amended: 26-Mat-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: '27-Mar-JO
Amended: 02-Nov-10
Amended: 26-Mar-[l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended. 11-Jul-20
Amended· ll-May-24
La.st Amended: 07-Jun-25
D.
Notifying the State
Upon adopting any amendment affecting shoreland areas, as described in
Title 38 M.R.S.A., § 435, the Town Clerk shall notify_the Commissioner of
the Department of Environmental Protection (DEP) of the amendment, as
required by Title 38 M.R.S.A., § 438-A(3). All applications considered after
the enactment of, and subject to, such an amendment, shall be evaluated by
the standards set forth in the amendment. In the event the application is
approved, and the DEF later modifies or disapproves the amendment, any
such approval is void and must be re-evaluated by the approving authority
in accordance with the standards eventually approved by the DEP. In the
event the DEP fails to act on the amendment within forty-five (45) days of
submission to the DEF, the amendment shall be deemed to be approved by
the DEP.
E.
List of Amendments
The Town Clerk shall keep a list of the effective dates and the substance of
all amendments to this Ordinance.
1. 9. ANNUAL ADMINISTRATIVE REPORT
The CEO, Planning Board and Zoning Board of Appeals shall each report
annually, in ,:vriting, to the Selectboard, in the month of January, reporting their
respective experience and recommendations with regard to the administration
and application of the Ordinance during the previous year. The failure of any
person or board to make such a report shall not affect the validity of the
Ordinance in any way.
1.10. EFFECTIVE DATE
The effective date of this Ordinance or any amendment hereto is the date of its
enactment by Town Meeting, unless otherwise specified by the Town Meeting
vote.
101Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended. 07-May-02
Amended; 04-Apr-05
Amended: 26-Mar-07
Amended: 24- Mar -08
Amended: 04-Apr-09
Amended: 27-Mar-\O
Amended: 02-Nov-10
Amended: 26-Mar.1 l
Amended: 01-Jun- 13
Amended: 23-Sept-13
Amended; ll-May-19
Amended. ll-Jul-20
Amended· 1 l-May-24
Last Amended: 07-Jun-25
ARTICLE 2: CONTRACT ZONING i"-_!!1--1Q,___g_6-l\'1._ar-1JJ
2.1. CONTRACT ZoNING AUTHORIZED
Contract zoning is hereby authorized. The purpose of such rezoning is to provide
a mechanism whereby specific conditions may be added to the approval of a
zoning district change so as to provide a benefit to the Town not otherwise
obtainable, and/or to mitigate potential adverse effects upon adjacent properties
and the community; it is also a method for permitting an otherwise prohibited or
non-conforming use by contractual agreement upon conditions between the Town
and the applicant, provided the result is deemed beneficial to the Town as well as
to the applicant. The burden shall be upon the applicant in every case arising
under this Article to demonstrate the benefit accruing to the Town from the
proposed contract zoning. A change in zoning under this Section shall not
exempt the use or development of the property from any standards or
requirements otherwise imposed by this Ordinance. Contract zoning is not
available to rezone any portion of the Town to Telecommunications Tower Overlay
District.
2.2. APPLICATION, PUBLIC HEARING, REVIEW, AND APPROVAL PROCEDURES
A.
Application for contract zoning shall be on a Site Plan Review Application
form together with a letter to the CEO requesting a contract zoning change
for a specific property, accompanied by all fees required by Article 1 L
B.
The Planning Board shall give notice of and conduct a public hearing as
required by Article 9.
C.
The Planning Board shall review the application using the Site Plan Review
standards set forth in Article 9 and Title 30-A, M.R.S.A., § 4352(8).
D.
No later than fourteen (14) days following the public hearing, the Planning
Board shall decide by majority vote of its members whether to approve or
disapprove the proposed contract zoning.
E.
The Planning Board shall submit a written report on the proposed contract
zoning to a meeting of the Selectboard no later than thirty (30) days
following the vote of the Planning Board noted above. This report shall state
whether the Planning Board voted to approve or disapprove the contract
111Page
Zoning Ordinance -Adopted; 28-Mar 2000
Amended: 26-Mar-OJ
Amended; 25-Mar-02
/'unended. 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended; 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l 1
Amended: OJ -Jun-13
Amended· 23-Sept-13
Amended: 11 May-19
Amended: 11-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
zoning, and shall include the Findings of Fact and list the conditions and
restrictions which the Planning Board recommends be set out in the
Warrant Article and applied to the property if the zoning change is enacted
at Town Meeting. This report shall also constitute the Planning Board's
report to the Town Meeting on the proposed contract zoning.
2.3. TOWN MEETING ACTION
A.
If the Planning Board approves the proposed contract zoning, it shall be
placed on the warrant for the next regular Town Meeting. If the Planning
Board disapproves the proposed contract zoning, it shall not be placed upon
a Town Meeting Warrant unless a majority of the Selectboard, at their
discretion, vote to do so.
B.
Notice of the Town Meeting required to amend a zoning ordinance or map
shall be given as required by State law. The Warrant Article shall set out all
conditions upon which the property is proposed to be rezoned, and shall
identify the property by reference to book and page of the current deed or
deeds to the property and by map and lot as shown on the Town Tax Maps.
C.
If the proposed contract zoning has the approval of the Planning Board and
includes the conditions and restrictions recommended by the Planning
Board shall require a simple majority of the voters voting at the Town
Meeting to enact the amendment.
D.
lf the proposed contract zoning does not have the approval of the Planning
Board, or if one or more of the conditions or restrictions recommended by
the Planning Board has been deleted or amended, the rezoning shall require
a two-thirds (2 /3) majority of the voters voting at the Town Meeting to pass.
E.
Upon enactment the Town Clerk shall certify a copy of the contract zoning
Warrant Article for recording at the Hancock County Registry of Deeds at the
expense of the applicant. The zoning change shall not become effective until
the certified copy of the rezoning Warrant Article has been duly recorded by
the Register of Deeds. The rezoned property shall thereafter be shown on
the Official Zoning Map.
F.
Upon adopting any conditional zoning affecting shoreland areas, as
described in Title 38 M.R.S.A., § 435, the Town Clerk shall notify the
121Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May"02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: 01-Jun-13
Amended: 23·Sept-13
Amended: 1 l-May-19
Amended: l l-.Jul-20
Amended: 1 l-May-24
Last Amended· 07-Jun-25
2.4. FEES
Commissioner of the Department of Environmental Protection (DEF) of the
amendment, as required by Title 38 M.R.S.A., § 438-A(3). In the event the
DEF fails to act on the amendment within forty-five (45) days of submission
to the DEF, the amendment shall be deemed to be approved by the DEF.
The applicant shall submit Application Fees and Technical Review Fees as
required by Article 11. The rezoning shall not be placed before Town Meeting
until the fees are paid in full.
2.5. ExPIRATION OF REZONING
Where the purpose of the rezoning is in part to permit construction, contract
zoning changes approved by the Town shall expire, and the property revert to its
prior zoning district status, unless work on the project is substantially
commenced within thirteen (13) months of the date of enactment and is
substantially completed within twenty-five (25) months of that date. These
deadlines may be extended by a vote of the Town meeting.
2.6. No RIGHTS CREATED BEFORE FINAL TOWN MEETING VOTE
The submission of a request for contract zoning under this Article, the payment
of application fees or the expenditure of funds by the applicant in presenting
such a request shall not create any vested rights in the application. The conduct
of meetings and hearings, the review of the application, comments by Town
officials or staff, and any preliminary vote, findings or determinations shall not be
construed as creating any entitlement to approval of a request for contract
zoning. The decision whether or not to rezone remains committed to the voters of
the Town of Castine exercising their sole and exclusive judgment as the legislative
body of the Town and will not be made until the Town Meeting votes on the
request.
--1>--
13\Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended. 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended, 26-Mar-07
Amended· 24-Mar-08
Amended; 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: 0 I -Jun- 13
Amended: 23-Sept- 13
Amended: ll-Ma.y-19
Amended. l 1-Jul-20
Amended: 11-May-24
Last Amended; 07-Jun-25
ARTICLE 3: NON-CONFORMITY
:Aml._26-Mar-0l_;_Am2. 25-Mar-0~Am7. 04:Afil'..:09;_Am8_. 27-Mar-l0_;_Aml0. _26-Mar-UlJ
3.1. NON·CONFORMITY DEFINED
A lot, structure, sign, or use that lawfully existed immediately prior to the
enactment of the Ordinance, or any subsequent amendment hereto, and which,
as a result of the enactment or subsequent amendment, fails to comply with any
of the requirements of this Ordinance is a lawful non-conformity. Such
requirements shall include, but are not limited to, the use restrictions and lot
standards for the zoning district in which it is located, or any land use standards
set forth in this Ordinance. An unlawful non-conformity is any other lot,
structure, sign, or use that fails to comply with any of the requirements of this
Ordinance or its amendments.
A.
Non-conforming lot
A non-conforming lot is a single lot which fails to meet any of the area or
dimensional requirements of this Ordinance.
B.
Non-conforming use
A non-conforming use is a use which is not a permitted use in the zoning
district in which it is located.
C.
Non-conforming structure
A non-conforming structure is a structure that does not meet the minimum
setback, maximum height, maximum lot coverage or similar requirements
for the zoning district in which it is located.
D.
Non-conforming sign
A non-conforming sign is a sign that does not meet the standards for signs
found at Article 6 of this Ordinance.
3.2. GENERAL PROVISIONS
The following provisions apply to all non-conformities generally: .:,_::_1-1..c..:'f
14!Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended· 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26- Mar-1 I
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 11-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
A.
Normal repair, upkeep and maintenance
The normal upkeep and maintenance of lawful non-conforming strnctures
and structures housing lawful non-conforming uses, including repairs or
renovations which do not involve expansion of the non-conforming use or
strncture, and such other changes in a lawful non-conforming use or
structure as Federal, State, or local building and safety codes may require,
are permitted.
B.
Transfer of ownership
Any lawful non-conformity may be transferred and the new owner may,
subject strictly to the requirements of this Article, continue such non-
conformity, provided, that nothing contained herein shall be constrned to
permit any person or entity to occupy or use any lot or structure or to
continue any use in violation of any other Federal, State, or municipal
statute, ordinance, or regulation.
C.
Unlawful non-conformity may not continue
Any unlawful non-conformity shall cease or be corrected immediately. Any
continuation of an unlawful non-conformity is a separate violation of this
Ordinance for each day it continues.
D.
Burden of proof to establish lawful non-conformity
The burden of establishing that any non-conformity is a lawful non-
conformity shall, in all cases, be upon the owner of such non-conformity
and not upon the Town of Castine. That burden of proof is proof by clear
and convincing evidence.
E.
Conformity encouraged
All non-conformities shall be encouraged to convert to conformity whenever
possible and, when required by this Ordinance, shall convert to conformity.
Once converted to conformity, no lot, structure, sign, or use shall revert to
non-conformity.
15IPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-!O
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended. 11-Jul-20
Amended: 11 May-24
Last Amended: 07 -Jun-25
3.3. NON-CONFORMING USES
The following additional provisions shall apply to lawful non-conforming uses.
A. Expansion
Subject to Planning Board approval, a non-conforming use within existing
structures or approved expansions of those structures, or an outdoor non-
conforming use of land, may be expanded in area, function or hours or
seasons of use provided such expansion of the non-conforming use will
cause no substantial increase in its adverse impact. The burden of
demonstrating no substantial increase in adverse impact shall be upon the
applicant. In considering such application the Planning Board shall apply
each relevant Site Plan Review criterion set forth in Section 9.14.
B.
Discontinuance
A non-conforming use which ceases for any reason for a period of twenty-
four (24) months, regardless of the intent of the owner or operator, shall not
be resumed, and any subsequent use of the property shall thereafter
conform to the regulations specified by this Ordinance for the district in
which the property is located.
C.
Change to another non-conforming use
A non-conforming use may be changed to another non-conforming use so
long as the new use has no greater adverse impact upon the neighborhood
and the community than the original use, and subject to Site Plan approval
by the Planning Board. The burden of demonstrating no greater adverse
impact shall be upon the applicant.
3.4. NON-CONFORMING STRUCTURES
The following provisions shall apply to lawful non-conforming structures,
including, without limitation, signs. ! \;:-;_,-.,_
161Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-OC/
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: 11-Jul-20
Amended: 11-May-24
Last Amended. 07-Jun-25
A.
Changes to non-conforming structures 1,-\n0'":,,
A non-conforming structure may be relocated, reconstructed, replaced,
added to or expanded after obtaining a permit from the same permitting
authority identified in Article 5, as that for a new structure, if such
construction or expansion does not increase the non-conformity of the
structure. Such construction or expansion is further limited as follows:
1.
Expansion
171Page
A non-conforming structure may be added to or expanded after
obtaining a permit from the same permitting authority as that for a new
structure, if such addition or expansion does not increase the non-
conformity of the structure and is in accordance with subparagraphs
3.4.A.l.a. and 3.4.A. l.b. below.
a.
After January 1, 1989 if any portion of a structure is less than the
required setback from the normal high-water line of a water body
or tributary stream or the upland edge of a wetland, or is located
in a Resource Protection Overlay District, that portion of the
structure shall not be expanded, as measured in floor area or
volume, by 30% or more, during the lifetime of the structure. If a
replacement structure conforms with the requirements of Section
3.4.A.3 and is less than the required setback from a water body,
tributary stream or wetland, the replacement structure may not be
expanded if the original structure existing on January 1, 1989 had
been expanded by 30% in floor area and volume since that date.
;Ar.!J0 i~.
b.
Whenever a new, enlarged, or replacement foundation is
constructed under a non-conforming structure, the structure and
new foundation must be placed such that the setback requirement
is met to the greatest practical extent as determined by the
Planning Board, basing its decision on the criteria specified in
Section 3.4.A.2 Relocation, below. If the completed foundation
does not extend beyond the exterior dimensions of the structure,
except for expansion in conformity with Section 3.4.A. l .a above,
and the foundation does not cause the structure to be elevated by
more than three (3) additional feet, as measured from the uphill
side of the structure (from original ground level to the bottom of
Zoning Ordinance - Adopted: 28· Mar-2000
Amended: 26-Mat·Ol
Amended: 25-Mar-02
Amended·. 07-May-02
Amended: 04-Apr-05
Amended; 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended· 27-Mar-IO
Amended: 02.Nov-10
Amended. 26-Mar-1 I
Amended; 01-Jun- 13
Amended 23-Sept-13
Amended: 11-May-19
Amended; I t-Jul·20
Amended· l 1-May-24
Last Amended: 07.Jun-25
the first floor sill), it shall not be considered to be an expansion of
the structure.
2.
Relocation
A non-conforming structure may be relocated within the boundaries of
the parcel on which the structure is located provided that the site of
relocation conforms to all setback requirements to the greatest
practical extent as determined by the Planning Board, and provided
that the applicant demonstrates that the present subsurface sewage
disposal system meets the requirements of State law and the State of
Maine Subsurface Wastewater Disposal Rules (Rules), or that a new
system can be installed in compliance with the law and said Rules. In
no case shall a structure be relocated in a manner that causes the
structure to be more non-conforming.
In determining whether the building relocation meets the setback to the
greatest practical extent, the Planning Board shall consider the size of
the lot, the slope of the land, the potential for soil erosion, the location
of other structures on the property and on adjacent properties, the
location of the septic system and other on-site soils suitable for septic
systems, and the type and amount of vegetation to be removed to
accomplish the relocation. When it is necessary to remove vegetation
within the water or wetland setback area in order to relocate a
structure, the Planning Board shall require replanting of native
vegetation to compensate for the destroyed vegetation. In addition, the
area from which the relocated structure was removed must be
replanted with vegetation. Replanting shall be required as follows:
i\n1. ii :.".rn.J,.
a.
Trees removed in order to relocate a structure must be replanted
with at least one native tree, three (3) feet in height, for every tree
removed. If more than five trees are planted, no one species of tree
shall make up more than 50% of the number of trees planted.
Replaced trees must be planted no further from the water or
wetland than the trees that were removed.
b.
Other woody and herbaceous vegetation, and ground cover, that
are removed or destroyed in order to relocate a structure must be
re-established. An area at least the same size as the area where
18 I p a g e
Zoning Ordinance -Adopted: 28-Mara2000
Amended: 26-Mar-01
Amended: 25- Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr 09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended; Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: 1 l-Jul-20
Amended· 11-May-24
Last Amended: 07-Jun-25
vegetation and/ or ground cover was disturbed, damaged, or
removed must be reestablished within the setback area. The
vegetation and/ or ground cover must consist of similar native
vegetation and/or ground cover that was disturbed, destroyed or
removed.
c.
Where feasible, when a structure is relocated on a parcel the
original location of the structure shall be replanted 'With vegetation
which may consist of grasses, shrubs, trees, or a combination
thereof.
3.
Reconstruction or Replacement
191Page
Any non-conforming structure which is located less than the required
setback from a water body, tributary stream, or wetland and which is
removed, or damaged or destroyed, regardless of the cause, by more
than 50% of the market value of the structure before such damage,
destruction or removal, may be reconstructed or replaced provided that
a permit is obtained 'Within eighteen (18) months of the date of said
damage, destruction, or removal, and provided that such
reconstruction or replacement is in compliance with the water body,
tributary stream or wetland setback requirement to the greatest
practical extent as determined by the Planning Board in accordance
'With the purposes of this Ordinance. In no case shall a structure be
reconstructed or replaced so as to increase its non-conformity. If the
reconstructed or replacement structure is less than the required
setback it shall not be any larger than the original structure, except as
allowed pursuant to Section 3.4.A.1 above, as determined by the non-
conforming floor area and volume of the reconstructed or replaced
structure at its new location. If the total amount of floor area and
volume of the original structure can be relocated or reconstructed
beyond the required setback area, no portion of the relocated or
reconstructed structure shall be replaced or constructed at less than
the setback requirement for a new structure. When it is necessary to
remove vegetation in order to replace or reconstruct a structure,
vegetation shall be replanted in accordance 'With Section 3.4.A.2 above.
Any non-conforming structure which is located less than the required
setback from a water body, tributary stream, or wetland and which is
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended, 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr·09
Amended: 27-Mar-lO
Amended. 02-Nov-lO
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May 19
Amended: ll-Jul-20
Amended: l 1-May-24
Last Amended: 07-Jun-25
removed by 50% or less of the market value, or damaged or destroyed
by 50% or less of the market value of the structure, excluding normal
maintenance and repair, may be reconstructed in place if a permit is
obtained from the Code Enforcement Officer within one year of such
damage, destruction, or removal.
In determining whether the building reconstruction or replacement
meets the setback to the greatest practical extent the Planning Board
shall consider, in addition to the criteria in Section 3.4.A.2 above, the
physical condition and type of foundation present, if any.
3.5. NON-CONFORMING MOBILE HOMES
Any mobile home lawfully used as a single-family dwelling may be improved by
the addition of a foundation or by other new construction, alteration, or repair,
subject to the requirements of any applicable building code or other law, and
subject to the other provisions of this Ordinance. Notwithstanding any other
provision of this Ordinance, the lawful use of a mobile home as a single-family
dwelling, in any zoning district, which use lawfully existed on the date of the
enactment of this Ordinance may be continued, except that the mobile home
shall not be:
A.
Rebuilt, altered, or repaired after being damaged in excess of fifty percent
(50%) of its replacement cost at the time of destruction as determined by the
CEO; or
B.
Replaced with a different mobile home, unless the new mobile home is
certified, pursuant to 42 U.S.C. Subsection 5415, as amended, as
conforming to all applicable Federal manufactured home construction and
safety standards, or is excluded from the coverage of 42 U.S.C. Subsection
5401 et seq.
3.6. NON-CONFORMING LoTS
A.
Construction on lawful non-conforming lots
A single, lawfully existing, vacant parcel of land, the legal description or
dimensions of which are recorded on a document or map on file at the
Hancock County Registry of Deeds at the effective date of this Ordinance or
20 IP age
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended: 26- Mar-0 1
Amended· 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar· 11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l-May-19
Amended: 11-Jul-20
Amended. 11-May-24
Last Amended: 07 -Jun-25
any amendment, and which, as a result of the enactment or respective
amendment of this Ordinance, does not meet the lot area or dimensional
requirements of the zoning district in which it is located, and which does not
adjoin another parcel in common ownership, may be built upon, without the
need for a variance, subject to the following:
1.
Such building or construction shall, in all other respects, comply with
the provisions of this Ordinance.
2.
Construction of single-family dwellings and accessory structures shall
be permitted after obtaining a permit from the same permitting
authority identified in Article 5, as that for a single-family dwelling on a
conforming lot in that zoning district.
B.
Contiguous built lots
If two or more contiguous lots or parcels are in a single or joint ownership of
record at the time of adoption of this Ordinance, if all or part of the lots do
not meet the dimensional requirements of this Ordinance, and if a principal
use or structure exists on each lot, the non-conforming lots may be
conveyed separately or together, provided that the State Minimum Lot Size
Law and Subsurface Wastewater Disposal Rules are complied with.
C.
Multiple Uses or Structures on a Single Lot
If two or more principal uses or structures existed on a single lot of record
on the effective date of this Ordinance, each may be sold on a separate lot
provided that the above referenced law and rules are complied with. When
such lots are divided each lot thus created must meet the setback
requirements of this Ordinance.
D.
Contiguous lots, vacant or partially vacant
If two or more contiguous lots or parcels are in single or joint ownership of
record at the time of or since adoption or amendment of this Ordinance, if
any of these lots do not individually meet the dimensional requirements of
this Ordinance or subsequent amendments, and if one or more of the lots
are vacant or contain no principal structure the lots shall be combined to
the extent necessary to meet the dimensional requirements.
21 IP age
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr 09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended· l J -May-19
Amended: Jl-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
3. 7 Repealed (iill.,_8.i
ARTICLE 4: ZONING DISTRICTS
_Am 1. 26-Mar-Ql.i Am2. 25_-Mar-02; Am3, 07-MaY:!)2.i_Am6._24-Mar-0JL_Am_l0. 26-Mar:.l!J.]
4.1. ZONING DISTRICTS EsTABLISHED
For the purposes of this Ordinance, the Town of Castine is divided into the
following Zoning Districts:
-
Rural District
-
Village District I
-
Village District II
-
Village District III
-
Commercial District
-
Education District
-
Source Water Protection Overlay District :c:~±~~ --2.
-
Maritime Activity Overlay District .:~r:1-::':
-
Resource Protection Overlay Districts _2'~ ·._:
-
Shoreland Overlay District
-
Telecommunications Tower Overlay District
4.2. STANDARDS ESTABLISHING DISTRICTS
A.
Resource Protection Overlay Districts
The purpose of Resource Protection Overlay Districts is to achieve the most
appropriate uses of areas comprising significant natural, recreational,
economic, historical, archaeological or visual resources of the To-wn; to
restrict the use of environmentally sensitive areas which are severely limited
for development by lack of public roads, inadequate water supply or
deficiencies in other resources and public services and facilities; to protect
land areas along rivers subject to severe bank erosion, undercutting, or river
22\Page
Zoning Ordmance -Adopted: 28-Mar·2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended· 02-Nov-10
Amended: 26-Mar-ll
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended. ll-May-19
Amended: \[.Jul-20
Amended: 11-May 24
Last Amended: 07-Jun-25
bed movement, and lands adjacent to tidal waters which are subject to
severe erosion or mass movement, such as steep coastal bluffs.
And to protect significant marshland, wetlands, streams and shoreland
areas by extending application of the standards of the Mandatory Shoreland
Zoning Act (Title 38 M.R.S.A., § 435 et seq.) to the entire area within any
Resource Protection Overlay District adjoining or enclosing such marshland,
wetlands or shoreland. ,.~\rn. l.:
B.
Shoreland Overlay District
The purpose of the Shoreland Overlay District is to protect the shoreland
resources of the Town; to further the maintenance of safe and healthful
conditions and the general welfare; to prevent and control erosion and water
pollution; protect spawning grounds, fish, aquatic life, bird and other
wildlife habitat; to control building sites, placement and structures and land
uses; to conserve shore cover, to conserve and enhance visual as well as
actual points of access to inland and coastal waters and natural beauty; to
encourage open space uses and to implement the State of Maine's
mandatory shoreland zoning requirements.
C.
Rural District
The purpose of the Rural District is to preserve the rural character of the
District, to provide for the public health and safety, environmental quality,
and economic well-being of the community; to retain certain areas for non-
intensive uses; to retain and enhance open space areas; and to promote
agriculture and forestry.
D.
Village Districts I, II and III
The purpose of the Village Districts is to provide for the public health and
safety, environmental quality, and economic well-being of the community; to
protect the visual, historic and architectural integrity of existing village
development and to ensure that future development is compatible both in
character and use; to provide areas for residential development in locations
compatible with existing development and in a manner appropriate to the
economical provision of community service and utilities. Village District I
has the additional purpose of enabling the use of existing properties in
patterns consistent with those already in use.
23 IP age
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended. 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended· 26-Mar-l 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: Jl-Jul-20
Amended: 1 l-May-24
Last Amended: 07 -Jun-'25
E.
Commercial District
The purpose of the Commercial District is to provide for the public health
and safety, environmental quality and economic well-being of the
community; to encourage the location of commercial uses in those locations
within the community which are best suited for such development; to
provide controls on those uses which by virtue of their size or external effect,
including but not limited to waste discharge, noise, glare, fumes, smoke,
dust, odors, heat, and traffic, could otherwise create nuisances or unsafe or
unhealthy conditions; to avoid the blight, congestion, and inconvenience
caused by inappropriate and poorly located development of commercial
facilities; to insure the most economical means of providing municipal
services to commercial and industrial uses; to assure continued availability
of waterfront property for purposes consistent with historic and appropriate
marine-related uses.
F.
Education District
The purpose of the Education District is to create a defined area for the local
college's main campus, allowing it to fulfill its post secondary educational
mission while providing for the environmental quality and economic well-
being of the community and preserving the unique architectural and scenic
characteristics of the Town.
G.
Source Water Protection Overlay District
The purpose of the Source Water Protection Overlay District is to ensure the
present and future availability of a potable water supply of adequate
quantity and quality; and to control the various land use activities within
the recharge area of the groundwater aquifer and the watershed area of
public water supply ponds, which may jeopardize the quantity and/or
quality of drinking water. 1Ar.nh ..
H.
Maritime Activity Overlay District
The purpose of the Maritime Activity Overlay District is to ensure the
present and future availability of land to support water dependent uses and
24\Page
Zonmg Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr·OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26·Mar- l l
Amended: 01-Jun-13
Amended· 23-Sept·13
Amended: 1 l-May-19
Amended: 1 I-Jul-20
Amended· l l-May-24
Last Amended: 07-Jun-25
to prevent the conversion or displacement of traditional maritime activities
within the Town. :2'::i.l,,~;
I.
Telecommunications Tower Overlay District
The purpose of the Telecommunications Tower Overlay is to comply with the
requirements of the Federal Telecommunications Act of 1996 by providing a
functional location for telecommunications towers or antennas while
preserving the scenic beauty of the Town. ;Am.r)
4.3. OFFICIAL ZONING MAP
Zoning districts established by this Ordinance are defined in the following section
and bounded as shown on the official "Zoning Map of Castine, Maine" which,
together with its notations and amendments, from time to time, is hereby made a
part of this Ordinance. The official copy of the map shall be that map which bears
the certification that it is true and correct, signed by the Chair of the Planning
Board and attested by the Town Clerk and on file in the office of the Town Clerk.
In the event of a conflict between the map and the zoning district boundary
descriptions in Section 4.4, the Section 4.4 description shall control.
4.4. ZONING DISTRICT BOUNDARY DESCRIPTIONS
A.
Resource Protection Overlay District # 1
Beginning 250 feet from the upland edge of the wetland on the eastern
boundary of Lot 29, Map 17; thence running parallel to the shore south
westerly to the eastern lot line of Lot 33. Map 17; thence northerly on said
lot line to the northeastern corner of said lot; thence southwesterly to a
point 250 feet from the upland edge of the wetland; thence running parallel
to the shore in a northerly direction around Blockhouse Point, and
northeasterly to the intersection with the southern lot line of Lot 10, Map
23; thence easterly on said lot line; thence northerly on the eastern lot line
of said lot to a point 300 feet south of the British Canal; thence easterly
running parallel to and 300 feet from the British Canal to a point 25 feet
westward of the centerline of Castine Road; thence running northerly 25 feet
from and parallel to the centerline of Castine Road to a point 25 feet south
of the intersection of the centerlines of Castine Road and Wadsworth Cove
Road; thence running westerly parallel to and 25 feet southerly from the
25 IP age
Zoning Ordinance -Adopted, 28-Mar-2000
Amended: 26-Mar-Ol
Amended; 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: OJ-Jun- 13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: I 1-Ju!-20
Amended: l l -May-24
Last Amended·. 07-Jun-25
centerline of Wadsworth Cove Road a distance of 551 feet; thence turning 90
degrees to the left and running 125 feet southerly; thence turning 90
degrees and running westerly 250 feet; thence southwesterly to the
northeast corner of Lot 10, Map 23; thence along the northern lot line of
said lot to a point 25 feet eastward of the centerline of Wadsworth Cove
Road; thence running northerly parallel to and 25 feet easterly from the
centerline of Wadsworth Cove Road to the northern lot line of Lot 5A, Map
23; thence westerly to the upland edge of the wetland; thence running along
the shore back to the southeasterly lot line of Lot 29, Map 17; thence
northerly along eastern boundary of said lot a distance of 250 feet to the
beginning. Reserving and exempting from Resource Protection District # 1 a
50-foot-wide area enclosing Wadsworth Cove Road, measured to a distance
of 25 feet on either side of its centerline, wherever the Road intrudes upon
the District.
B.
Resource Protection Overlay District #2
Includes all land area sho'Wl1 as Lot 63, on Tax Map 18 of the Town of
Castine, known as the site of Fort Madison.
C.
Resource Protection Overlay District #3
Includes all land area shown as Lot 11, on Tax Map 20 of the Town of
Castine, known as the site of Fort George.
D.
Resource Protection Overlay District #4
Includes all land area shown as Lot 7, on Tax Map 22 of the Town of
Castine, known as the site of Fort Griffith.
E.
Resource Protection Overlay District #5
Includes all land area shown as Lot 51, on Tax Map 18 of the Town of
Castine, known as the site of Fort Pentagbet.
26\Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended. 26-Mar-Ol
Amended: 25-Mar-02
Amended· 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mar-l l
Amended: 01-Jun 13
Amended: 23-Sept-13
Amended: ll-May-19
Amended· 11-J u.l-20
Amended: 1 l-May-24
Last Amended: 07 -Jun-25
F.
Resource Protection Overlay District #6
Includes all land area on Lot 15, Tax Map 20 of the Town of Castine located
within 250 feet of the concrete marker signifying the site of Fort Gosselin.
G.
Resource Protection Overlay District #7
That part of Lots 20 and 20A, on Tax Map 23 of the Town of Castine, which
encompasses the site of Fort Sherbrooke, defined as 168 yards North of Fort
George, a semi-circular battery, 150 feet in extent enclosing a redoubt about
150 feet inside, which measures 46 feet; and all land area encompassing the
ledge containing carvings and initials adjacent to the Fort Sherbrooke site.
H.
Resource Protection Overlay District #8
Beginning at the upland edge of the wetland at the northernmost point of
Mayo Point on Lot 2, Tax Map 27 of the Town of Castine; thence westward
and southerly a distance of one hundred (100) feet thence running parallel
to the shore a distance of one hundred (100) feet from the high water line
southwesterly around Hatch Cove; thence northeasterly one hundred (100)
feet inland from and parallel to the northern shore of Hatch Cove to where it
intersects with the easterly lot line of Lot 23, Tax Map 2; thence southerly
one hundred (100) feet to the upland edge of the wetland following the
eastern boundary of said lot; thence following the upland edge of the
wetland around Hatch Cove to the beginning.
I.
Resource Protection Overlay District #9
Includes all land areas within one hundred (100) feet of the high-water line
of Bog Brook beginning at its mouth on Wadsworth Cove and extending into
the Square along the entire length of the watercourse and all land areas
within two hundred and fifty (250) feet of the upland edge of the freshwater
wetland at the source of Bog Brook. ,_\,_(]./{
J.
Resource Protection Overlay District #10
Includes all land areas within one hundred (100) feet of the high-water line
of the Ice Pond.
271Page
Zornng Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar 01
Amended· 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended, 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Oi-Jun-13
Amended: 23-Sept-13
Amended: l l -May-19
Amended: \ J -Jul-20
Amended: l 1-May-24
Last Amended· 07-Jun-25
K.
Resource Protection Overlay District #11
Includes all land areas within one hundred (100) feet of the high-water line
of Morse Cove Stream beginning at its mouth on Morse Cove and extending
into The Square along the entire length of the watercourse.
L.
Resource Protection Overlay District # 12
Includes all land areas within two hundred and fifty (250) feet of the upland
edge of the freshwater wetland known as Dunc's Meadow that is delineated
as the low area on the USGS topographic map and within one hundred ( 100)
feet of the high-water line of Meadow Brook. !21n.b\
M.
Shoreland Overlay District
Those lands within two hundred and fifty (250) feet, horizontal distance, of
the normal high-water line of any great pond or river; within 250 feet,
horizontal distance, of the upland edge of a coastal wetland, including all
areas affected by tidal action; within 250 feet of the upland edge of a
freshwater wetland; or within seventy-five (75) feet, horizontal distance, of
the normal high-water line of a stream. -0\rn_._Q,'
N.
Rural District
A dividing line is hereby established beginning at the intersection of the
centerline of Wadsworth Cove Road and the Castine Road and extending
easterly to the high-water line on the shore of Hatch Cove and westerly
along the centerline of Wadsworth Cove Road. At that point where the
Wadsworth Cove Road curves to the southwest, the dividing line continues
westerly to the high-water line on the shore of Wadsworth Cove. The Rural
District includes all land and water areas within the boundaries of the Town
to the north of the dividing line and all offshore islands wherever located
within the boundaries of the Town. 3cr::riJ
0.
Village District I
Beginning at the southeastern corner of Lot 51, Tax Map 18 of the Town of
Castine, and following said lot line northwesterly to the centerline of Perkins
Street; thence northeasterly along the centerline of Perkins Street to the
281Page
Zoning Ordinance -Adopted. 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07 · May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Arn ended· 02-Nov-10
Amended: 26-Mar-1 l
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 1 !-May-19
Amended: 1 l-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
intersection of the centerlines of Perkins Street and Tarratine Street; thence
northwesterly along the centerline of Tarratine Street to the intersection of
the centerlines ofTarratine Street and Battle Avenue; thence northeasterly
along the centerline of Battle Avenue to a point on the centerline of Battle
Avenue 150 feet beyond the centerline of Main Street; thence southeasterly
running parallel to and 150 feet from the centerline of Main Street to a point
250 feet from the centerline of Court Street; thence northeasterly to the
intersection with the boundary of the Aquifer Protection Overlay District;
thence following the boundary of said Aquifer Protection Overlay District in a
generally southeasterly direction to the centerline of Court Street; thence
southwesterly along the centerline of Court Street to the intersection with
the centerline of Dyer Lane; thence southeasterly to the intersection with the
centerline of Water Street; thence northeasterly to the northeast corner
boundary of Lot 15, Tax Map 25, thence following the said northeast lot line
to the shore of the Bagaduce River; thence following the shore to the point of
beginning. This District shall not include the Institutional District, or the
Commercial District located within its boundaries.
P.
Village District II
Includes all shore lots northeast of the northeasterly lot line of Lot 15, Tax
Map 25 of the Town of Castine, and all land and water areas to the south of
Battle Avenue as well as to the east of State Street and Dyer Lane not
included in the Educational District, Commercial District or Village District
Q.
Village District Ill
Includes all land and water areas to the south of the dividing line as
described in the description of the Rural District, north of the centerline of
Battle Avenue from the centerline of State Street to the front lot line of Lot
33, Tax Map 17 of the Town of Castine and north of the north, side lot line
of Lot 33, Tax Map 17 .. \n1--\'.
R.
Commercial District
Beginning at the southeastern corner of Lot 110, Tax Map 21 of the Town of
Castine, and following said lot line northwesterly; thence northeasterly along
the northwestern lot line of said lot to the centerline of Water Street; thence
29 IP age
Zoning Ordinance - Adopted: 28 Mar 2000
Amended: 26-Mar-01
Amended. 25-Mar-02
Amended 07-May-02
Amended; 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended, 26-Mar-1 I
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: li-May-19
Amended: Jl-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
northeasterly along the centerline of Water Street to the intersection of the
centerlines of Water Street and Pleasant Street; thence northeasterly along
the centerline of Pleasant Street a distance of 100 feet; thence northeasterly
running parallel to and 100 feet from the centerline of Water Street to a
point 150 feet southwesterly of the centerline of Main Street; thence
northwesterly running parallel to and 150 feet southwesterly from the
centerline of Main Street to Court Street; thence northeasterly along Court
Street to the northeastern corner of Lot 75, Tax Map 21; thence
southeasterly along said lot line and extending in a line parallel to the
centerline of Green Street until it intersects with the western lot line of Lot
67, Tax Map 21; thence following said lot line to the centerline of Green
Street; thence southeasterly along the centerline of Green Street to the
intersection of the centerlines of Green Street and Water Street; thence
northeasterly along the centerline of Water Street to the northwestern corner
of Lot 56, Tax Map 21; thence southeasterly along the northern line of said
lot to the high water line on the shore; thence following the shore
southwesterly to the point of the beginning.
S.
Education District
Includes all land area shown as Lot 23 and Lot 30, on Tax Map 20 of the
Town of Castine, known as the Maine Maritime Academy main campus.
T.
Source Water Protection Overlay District
Beginning on the north line of Battle Avenue at the southwest corner of Lot
2, Tax Map 19 of the Town of Castine; thence along the lot line
northwesterly 558 feet to a corner of Lot 2, Tax Map 19; thence continuing
along the same course to a point 2,100 feet north of Battle Avenue; thence
northeasterly to the southwest corner of Lot 16, Tax Map 23; thence
northeasterly to the northwest corner of Lot 17, Tax Map 23; thence
northerly to the southwest corner of Lot 20, Tax Map 2; thence northeasterly
to the northeast corner of Lot 20, Tax Map 2; thence northerly to the
southwest corner of Lot 21, Tax Map 2; thence northeasterly to the
northeast corner of Lot 2 lA, Tax Map 2; thence southerly along the west line
of Castine Road to a point 300 feet north of Battle Avenue; thence easterly
across Castine Road and along the north line of Windmill Hill Drive to the
northwest corner of Lot 26, Tax Map 26; thence along the lot lines to the
southeast corner of Lot 26, Tax Map 26; thence easterly to the northwest
corner of Lot 5, Tax Map 26; thence along the west lot lines of Lots 5, 4, 3, 2
30 IP age
Zoning Ordmance -Adopted· 28-Mar-2000
Amended; 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-0S
Amerrded: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-\ 0
Amended: 02-Nov-JO
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amerrded: 23-Sept-13
Amended: 11-May-19
Amended· ll-Jul-20
Amended: 11-May-2'1-
Last Amended: 07-Jun-25
and 1, Tax Map 26 to Court Street; thence southerly across Court Street and
along the west line of Spring Street to a point 450 feet south of Court Street;
thence southwesterly to the southwest corner of Lot 5, Tax Map 25; thence
westerly to the southwest comer of Lot 26A, Tax Map 24; thence westerly to
a point on the north line of Battle Avenue 900 feet from Castine Road;
thence along the north line of battle Avenue to the point of beginning.
fr\m.r_/
U.
Telecommunications Tower Overlay District
Includes all land area shown as Lot 3, on Tax Map 8 of the Town of Castine.
V.
Maritime Activity Overlay District
Includes all lots within the Commercial District abutting the Bagaduce
River, specifically the lots shown as Lots 56, 57 A, 57B, 60, 63, 105 and 110
on Tax Map 21 of the Town of Castine. }.rn 2j
4.5. UNCERTAINTY OF DISTRICT BOUNDARY LoCATIONS
Where uncertainty exists with respect to the boundaries of any of the various
Districts shown on the Official Zoning Map, the following rules shall apply:
A.
Boundaries indicated as approximately following the centerlines of streets,
highways, rights of way or alleys shall be construed to follow such
centerlines.
B.
Boundaries indicated as approximately following established lot lines shall
be construed as following such lot lines.
C.
Boundaries indicated as approximately following municipal boundaries shall
be construed as following such municipal boundaries.
D.
Boundaries indicated as approximately following shorelines shall be
construed as following the shoreline. In the event of an alteration in the
location of the shoreline, the boundary shall be deemed to change with the
alteration.
E.
Boundaries indicated as approximately following the centerlines of streams,
rivers, canals, lakes or other bodies of water shall be construed to follow
such centerlines.
31 I P a g e
Zoning Ordinance - Adopted. 28-Mar-2000
Amended: 26-Mar-Ol
Amended· 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- \ l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: l l -Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
F.
Boundaries indicated as approximately being extensions of or parallel to any
property line, centerlines or feature noted above shall be so construed.
G.
Where dimensions are unclear, and the rules of resolving uncertainty listed
above do not resolve the uncertainty, the dimensions as shown on the most
current Tax Map shall control.
H.
When physical or cultural features existing on the ground are at variance
with those shown on the Zoning Map, or in other circumstances where there
is uncertainty with respect to the location of a district boundary, the Zoning
Board of Appeals shall interpret that district boundary.
4.6. DMSION OF LoTS BY DISTRICT BOUNDARIES
Where a district boundary, other than an overlay district boundary, divides a lot
or parcel of land in the same ownership of record at the time the district
boundary is established, the less restrictive district may be extended into the
more restricted portion by no more than fifty (50) feet.
4. 7. DISTRICT OVERLAY REQUIREMENTS
A.
Shoreland Overlay District
The Shoreland Overlay District applies an overlay zone to the land within
the boundaries of the District. In addition to the restrictions of the
underlying district there are specific additional performance standards
found in Article 7 and additional regulations applicable to non-conformities
found in Article 3.
B.
Maritime Activity Overlay District
The Maritime Activities Overlay District applies an overlay zone to the land
within the boundaries of the District. In addition to the restrictions of the
underlying district, only specific uses identified in the Land Use Table,
Section 5.4., are permitted., ~rr, ,--,!
32 IP age
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04 Apr-09
Amended: 27 -Mar- 1 0
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: ll-Jul-20
Amended: ll-May-24
Last Amended 07-Jun-25
C.
Resource Protection Overlay District
The Resource Protection Overlay District applies an overlay zone to the land
within the boundaries of the District. In addition to the restrictions of the
underlying district there are specific additional performance standards
found in Article 7. :,lu.1£;
D.
Source Water Protection Overlay District r0_I_il:f:!,'
The Source Water Protection Overlay District applies overlay requirements to
the land within the boundaries of the District. In addition to uses
prohibited in the underlying districts, certain additional uses are prohibited.
There are also additional requirements for other uses requiring Site Plan
Approval.
1.
Delineation of Zones within the Source Water Protection Overlay
District
There shall be two zones within the District:
-
Zone 1 shall consist of all land lying v.rithin a circle of 300-foot
radius around each water supply well.
-
Zone 2 shall consist of all remaining land lying within the
boundaries of the District.
2.
Permitted Uses within Source Water Protection Zone 1
The follov.ring are permitted uses in Zone 1:
-
Uses directly related to the operations of the Castine Water
Department or approved by it.
-
Any other uses in existence on March 24, 2008.
3.
Prohibited Uses within Source Water Protection Zone 1
Any use not set forth in Section 4. 7.D.2. above is prohibited.
4.
Permitted Uses within Source Water Protection Zone 2
331Page
The following are permitted uses not requiring Site Plan Approval:
Zoning Ordinance -Adopted: 28-Mar-2000
Amended· 26-Mar-01
Amended: 25-Mar-02
Amended, 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar"07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended, 27-Mar-10
Amended·. 02-Nov-10
Amended: 26-Mar-l 1
Amended: OJ-Jun 13
Amended·. '23-Sept-13
Ameuded: Jl-May-19
Amended: ll-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
-
Subsurface sewage disposal system, the design and maintenance
schedule of which is reviewed and approved by the Local Plumbing
Inspector {LPl).
-
Gardening,
-
Residential composting,
-
Residential pesticide or fertilizer application in compliance with
label restrictions,
-
Non-commercial animal husbandry,
-
Forest management activities, and forest product harvesting, so
long as harvest removes less than 40% of the canopy from any lot
within a ten (10) year period,
-
Recreational uses,
-
Municipal uses such as road and facility maintenance,
-
Creating impervious surfaces totaling not more than twenty percent
{20%) of any lot,
-
Storage of not more than ten {10) gallons in the aggregate of
petroleum products in portable containers with secondary
containment,
-
Storage of greater than ten {10) gallons of petroleum products in
fixed containers subject to Section 4.7.4.10 below,
-
Maintenance of any existing structure.
5.
Prohibited uses within Source Water Protection Zone 2
In addition to those uses prohibited in the underlying districts, the
following uses are prohibited in Zone 2:
-
Automobile graveyards or the outdoor storage of more than three
motor vehicles not in regular use.
-
New underground storage tanks or containers for petroleum
products or chemicals after March 24, 2008.
-
Creating impervious surfaces totaling more than twenty percent
{20%) of any lot.
-
Commercial activities involving the disposal of liquid or leachable
waste, except as are routinely permitted for disposal into the Town
sewage system.
-
Commercial waste impoundrnent or disposal.
-
Uncovered waste storage.
34 \ P a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar.Q7
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mar- l l
Amended: Ol-Jun-13
Amended; 23-Sept, 13
Amended: ll-May-19
Amended: 11-Jul-20
Amended: ll-May-24
Last Amended: 07-Jun-25
-
Commercial waste storage for a period exceeding 30 days.
-
Commercial manure or sludge storage or spreading.
-
Uncovered sand and salt piles.
6.
Status of Castine Water Department
For any application for Site Plan Approval in the Source Water
Protection Overlay District, the Castine Water Department shall have
the status of an abutter.
7.
Permitted Use Standards
AH permitted uses within Zone 1 and Zone 2 shall be constructed,
operated and maintained in a manner that will not cause a material
increased risk of contamination or decreased quantity of recharge to
the aquifer and the public water supply ponds as determined by the
Planning Board in its sole discretion. The Planning Board may be
guided in making its determination by advice from consultants chosen
by it and by the advice contained in the manual of the Maine
Department of Health and Human Services Drinking Water Program
entitled Best Management Practices for Groundwater Protection -A
Guide for Local Officials and Public Water Suppliers. (This publication is
available at the Town Office and on the Town web site
www.castine.me. us).
8.
Sanitary wastewater disposal
No use, including home occupations, shall dispose of other than
normal domestic wastewater on-site. No more than 900 gallons per day
of sanitary waste shall be discharged to any one subsurface sewage
disposal system. Septic tanks shall be pumped every three (3) years for
routine maintenance. Pumping shall be observed by the LPL Disposal
of wastewater shall be in compliance with the Maine Subsurface Waste
Water Disposal Rules (CMR 10-144, Chapter 241, as amended).
9.
Petroleum product storage, above ground
-
For inside above ground storage of petroleum for commercial or
private use, tanks (including replacement tanks) installed after
35 j P a g e
Zoning Ordinance -Adopted· 28-Mar-2000
Amended, 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- 10
Amended: 02-Nov- 10
Amended: 26-Mar-ll
Amended: 0 I -Jun- 13
Amended: 23-Sept-13
Amended l 1-May-19
Amended: ll-Jul-20
Amended: l 1-May-24
last Amended: 07 ✓un-25
March 24, 2008 in a fixed location must be designed to contain
leaks, with either double-walled primary containers, or with a single
walled tank set in a secure secondary container having a capacity of
at least 110% of the capacity of the primary tank. There shall be no
floor drains into which leaking oil could drain in a building storing
petroleum products for commercial use.
-
For outside above ground storage of petroleum in fixed tanks
(including replacement tanks) installed after March 24, 2008, tanks
shall be enclosed to prevent accidental toppling and shall have a
cover or roof to prevent filling of the secondary containment with
rainwater.
-
Tanks (including replacement tanks) installed after March 24, 2008
must be installed in accordance with Maine Oil and Solid Fuel
Board Installation of Oil Burning Equipment (CMR 02-381, Chapter
9, as amended).
10. Petroleum product storage, underground
For underground storage of petroleum in existence on March 24, 2008
for commercial or private use, the standards of Maine DEP Rules for
Underground Oil Storage Facilities (CMR 06-096, Chapter 691, as
amended) shall apply. Specifically, regarding design and operation, all
tanks and piping shall be double walled for containment of petroleum
product, and volumes and interstitial spaces shall be continuously
electronically monitored. If portions of the system are to be replaced,
then the design of such replacement shall be in accordance with the
Chapter 691 regulations requiring the maximum security against spills
and leaks of petroleum product.
11. Excavation or mining, fill, sand, gravel and other minerals.
36\Page
The water table shall not be artificially lowered by ditches, trenches,
pumping or other methods. Excavation shall not be allowed below five
feet above the average seasonal high water without Site Plan Approval
from the Planning Board following receipt of a variance from the Maine
DEF for mining below the water table pursuant to Maine DEP Variance
Criteria for the Excavation of Rock, Borrow, Topsoil, Clay or Silt and
Perfonnance Standards for the Storage of Petroleum Products (CMR 06-
096, Chapter 378, as amended).
Zomng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-OCJ
Amended· 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended. 23-Sept-13
Amended: 11-May-19
Amended: ll-Jul-20
Amended; 1 l-May-24
Last Amended: 07-Jun-25
E.
Telecommunications Tower Overlay District
The Telecommunications Tower Overlay District is the only district in which
telecommunications towers or antennas are permitted. By limiting towers to
this District, the Ordinance seeks to comply with the requirements of the
Federal Telecommunications Act of 1996 by providing a functional location
for telecommunications towers or antennas. In order to preserve the scenic
beauty of the Town, certain landscaping, buffering, fencing and aesthetic
requirements apply as additional requirements for Site Plan Approval of
telecommunications towers or antennas. ;_1rn.,;.;
1.
Additional requirements
371 Page
The following requirements apply to Site Plan Approval of
telecommunications towers, in addition to the requirements and
performance standards of Article 6:
a. Towers shall be galvanized steel finish or be painted a neutral color
so as to minimize their visual presence.
b. All telecommunications towers, and any accessory structures, shall
maintain the required setbacks as undisturbed vegetative buffers,
except for the access road. The Planning Board may require
additional plantings in the buffer area to maximize the effectiveness
of the buffer area. The size, spacing and type of plantings shall be
subject to Planning Board approval.
c. All structures at the tower site shall use materials, colors, textures,
screenings and landscaping that will cause the tower and all related
structures to blend into the natural environment to the maximum
possible extent.
d. Towers shall not be lighted unless required by State or Federal law.
If lighting is required the Planning Board may select the lighting
scheme it deems most appropriate from the alternatives acceptable
under law.
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended· 26-Mar-01
Amended: 2S-Mar-02
Amended; 07-May-02
/\mended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-IO
Amended: 02-Nov-10
Amended: 26-Mar-l 1
/\mended. Ohlun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: J J.Jul-20
Amended: ll-May-24
Last /\mended; O?-Jun-25
38\Page
e. Road access to the tower site shall be of minimum width necessary
to allow safe and reasonable access to the site.
f. A security fence of not less than eight (8) feet in height above finish
grade shall surround the tower. Access to the tower shall be
through a locked gate.
g. A telecommunications tower shall not exceed 199 feet in height,
unless the Planning Board determines that a taller tower is
necessary in order to avoid the effect of preventing all personal
wireless services within the Town of Castine and that no alternative
sites, towers or structures are available to provide such services.
See Article 15 for the definition of "personal wireless services."
:_\.rr.Q
Zoning Ordmance -Adopted, 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended, 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended: 04-Apr-09
Amended, 27-Mar-10
Amended: 02-Nov 10
Amended: 26-Mar- l l
Amended: Ol-Jun-13
Amended· 23-Sept-13
Amended: 11- May-19
Amended: 1 l-Jul-20
Amended: 1 !-May-24
Last Amended: 07-Jun-25
ARTICLE 5: LAND USE TABLE AND DIMENSIONAL REQUIREMENTS
[Am_l. 26-Mar-_Ql_;_Am2. 25-IVJ_ar-Q2; Am-2..,_()7-M,!Y.:.Q2; Arn 5, 26-Mar:_QZ;__Am6. _24-fyJar-O~
~m7. 04-Apr-Q.2._; __ AmS_. 27-1\_iar-10; Aml0._26-Mar-lJ_;_='-m.12 23-S~3; A,tn___,_l__3 1 l-M_!!Y:J9; Am_.t§_
ll-May-24· Am.16 07-Jun-2_§]
5.1. SYMBOLS USED IN LAND USE TABLE
The following symbols contained in the Land Use Table have the following
meanings:
A.
District symbols
R ................. Rural District.
V-I ............... Village District I.
V-II .............. Village District II.
V-Ill ............. Village District m.
C.
. Commercial District.
E ................. Educational District .. b1. 1
MA .............. Maritime Activity Overlay District. li}n~
RP ............... Resource Protection Overlay District.
SL ............... Shoreland Overlay District
B.
Permit symbols
Y ................. No permit required.
CEO ............. Requires permit from the CEO.
PB ............... Requires Site Plan Approval from the Planning Board.
NO ............... Use prohibited within the district.
N/A ............. Notapplicable .. 1Jn.1:
5.2. USES SUBSTANTIALLY SIMILAR TO LISTED USES
A.
Similar to uses allowed without a permit
Uses substantially similar to those listed as not requiring a permit, but
which are not listed in the Land Use Table, may be permitted by a ruling, in
writing, of the CEO.
391 Page
Zoning Ordmance ·· Adopted: 28-Mar-2000
Amended; 26-Max-01
Amended; 25-Mar-02
Amended: 07 -May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended. 02-Nov-10
Amended: 26-Mar- l 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11 May-19
Amended; ll-.Jul-20
Amended. 11-May 24
La.st Amended: 07-Jun-25
B. Similar to uses allowed with CEO permit
Uses substantially similar to those listed as requiring a CEO permit, but
which are not listed in the Land Use Table, may be permitted by CEO
permit.
C.
Similar to uses allowed with Site Plan Approval
Uses substantially similar to those listed as requiring Site Plan Approval,
but which are not listed in the Land Use Table, may be permitted by (1) a
ruling of the CEO, in writing, that the use is substantially similar to uses
requiring Approval by the Planning Board, and (2) Site Plan Approval from
the Planning Board.
D.
Similar to prohibited uses
Uses substantially similar to uses listed as prohibited in the Land Use Table
shall be prohibited upon a ruling of the CEO, in writing, that the use is
substantially similar to such prohibited uses.
E.
Written records
The CEO shall maintain copies of all such written rulings.
5.3. COMPLIANCE WITH LAND USE STANDARDS
All uses must occur and be maintained in compliance with the applicable
requirements of this Ordinance.
The granting of permits or approvals does not relieve the applicant from the need
to obtain any other permits or approvals required prior to the commencement of
any activity or use. Such other required permits or approvals may include, but
are not limited to, subdivision approval, building, plumbing and electrical
permits, licenses granted pursuant to Title 38 M.R.S.A., Maine Department of
Environmental Protection and United States Army Corps of Engineers' approvals,
subsurface wastewater disposal permits, sewer connection permits, Maine
Department of Transportation approvals, and the like.
401Page
Zomng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May·02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended: 02-Nov- \0
Amended: 26-Mar·l 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended· ll-Jul-20
Amended: l l-May-2'1
Last Amended; 07 -Jun-25
-LAND USE
R
V-I
♦
ZoNING DISTRICT' ♦
1.
Agriculture and
y
NO
animal husbandry.
2.
Aquaculture
NIA
N/A
Auto service stations
3.
and repair garages,
NO
NO
with or without fuel
dispensing.
4.
Bed & breakfasts.
NO
NO
----------------~~.
Boatyards, marinas,
5.
public launch facility
PB
NO
or commercial
~- _marine railways.
6.
Campgrounds and
PB
NO
mobile home parks.
7.
Cemeteries.
PB
NO
----------
Clearing or removal
8.
of vegetation for
y
y
activities other than
tun ber harvestin&.___
9.
Cluster
PB
NO
developments.
Commercial
10. structures or uses
NO
NO
not otherwise listed.
Commercial vessel or
11. commercial marine
NO
NO
equipment storage
facility.
41 IP age
V-II2
C
V-III2
NO
NO
N/A
N/A
NO
PB
NO
PB
NO
PB
NO
NO
PB
NO
~
y
y
NO
NO
NO
PB
NO
PB
MA
SL
RP
E
OVERLAY
OVERLAY
OVERLAY ·-
NO
NO
y12
PB 1
N/A
PB
PB
PB
NO
NO
PBll
NO
--r-------1-----
NO
NO
PB11
NO
PB
PB
PBll
NO
NO
NO
PBil
NO
NO
NO
PEil
NO
y
CEO
CEO
PB
NO
NO
PBII
NO
PB
PB 10
PBll
NO
PB
PB
PBll
NO
Zoning Ordinance -. Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-10
Amended:02-Nov-10
Amended: 26-Mar-1 l
Amended: 0!-Jun-13
Amended: 23-Sept· 13
Amended·. 11-May-19
Amended: I 1-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
·-
LAND USE
R
V-1
V-112
- ZoNING DISTRICT +
V-III2
Construction or
expansion of any
structure which is
12. located on a non-
PB
PB
PB
conforming lot or any
expansion of any
non-conforming
structure.
Construction or
expansion of
structures and
13. changes of use in the
N/A
N/A
PB
Source Water
Protection Overlay
District.
14.
Demolition of any
CEO
CEO
CE0 2
structure.
15. Dredging or filling
PB
PB
PB
operations.
16. Dwellings/ structures,
CEO
CEO
CEO
'---- one -family.
17. Dwellings/structures,
CEO
CEO
CEO
two -family.
18. Dwellings/ structures,
PB
N0 14
N014
multi-family.
19.
Dwellings, mobile
CEO
NO
NO
homes.
20. Earthmoving of 60
y
y
y2
cubic yards or less.5
Earthmoving of more
21. than 60 cubic yards,
CEO
CEO
CE02
but less than 120
cubic yards.s, 9
Earthmoving of 120
22. cubic yards or
PB
PB
PB
more. 5, 9
23. Essential Services
y
y
y
421 Page
C
PB
N/A
CEO
PB
PB
PB
PB
NO
y
CEO
--
PB
y
E
MA
SL
RP
OVERLAY
OVERLAY
OVERLAY
PB
PB
PBll
PB
N/A
N/A
PBll
N/A
CEO
CEO
CEO
CEO
PB
PB
PBll
PB
PB
NO
CEO
NO
PB
NO
CEO
NO
--
PB
NO
PBll
NO
NO
NO
PBII
NO
y
y
CEO
PB
CEO
CEO
CEO
PB
PB
PB
PB11
PB
y
CEO
CEO
PB
Zoning Ordinance - Adopted: 28-Mar-2000
Arnen~d: 26-Mar-0l
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Arne nded: 04-A.pr-09
Amended: ~7 -Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended: 01-J un- 13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: ll-Ju)-20
Amended: I 1-May-24
Last Amended: 07 .. Jun-25
-·
------
LAND USE
R
V·I
v.112
C
E
MA
SL
RP
♦
ZONING DISTRICT ♦
V-1112
OVERLAY
OVERLAY
OVERLAY
Expansion or change
24.
of a non -conforming
PB
PB
PB
PB
PB
PB
PB 11
PB
use.
Expansion or change
25. to a non -conforming
PB
PB
PB
PB
PB
PB
PBll
PB
lot.
>---
---
26.
Farmers' market
NO
CEO
NO
NO
NO
NO
NO
NO
27.
Fences exceeding six
PB
NO
NO
NO
NO
NO
NO
NO
(6) feet in height.
---·
----~--·- -----
Fences which do not
28.
exceed six (6) feet in
y
y
y
PB
y
PB
y12
y
height and deer
fences.
>--·
29. Home occupations.
PB
PB
PB
PB
PB
PB
PB11
NO
Hospitals, nursing
30. homes and assisted
PB
PB
PB
PB
PB
NO
PBII
NO
living facilities.
31. Individual, private
y
y
y
y
y
NO
CEO
PB
campsites.
Industrial structures
32. or uses not otherwise
NO
NO
NO
NO
NO
PBlO
PEil
NO
listed.
33. Inns and hotels.
NO
NO
NO
PB
NO
NO
PBll
NO
Junkyards,
automobile
34. graveyards and
PB
NO
NO
NO
NO
NO
NO
NO
automobile salvage
yards.
~--
~
35. Libraries and
PB
PB
PB
PB
PB
NO
PEil
NO
museums.
36. Markets and retail
NO
NO
NO
PB
PB
PBlO
PBll
NO
sales.
---------r-----E
Mineral exploration
37. and extraction
PB
NO
NO
NO
NO
NO
PBII
NO
including sand and
gravel extraction
~
---~--
---
43 IP age
Zoning Ordinance-. Adopted: 28-Mar-2000
Amended: 26-Mar-Oi
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended: 26·Mar-07
Amended: 24-Mar-08
Amended: 04·Apr-09
Amended; 27. Mar-10
Amended: 02-Nov- I 0
Amended: 26-Mar- 1 I
Amended: 01-J un - 13
Amended: 23-Sept- I 3
Amended: I l ·May-19
Amended: ll-Jul-20
Amended: l 1-May-24
Last Amended: 07-Jun-25
LAND USE
R
V-1
V-112
- ZONING DISTRICT ♦
V-1112
38. Mixed residential
NO
NO
NO
and commercial.
39.
Mobile Vending Units
y1s
y1s
y1s
ii\m.151
Normal maintenance
40. and repair of a
y
y
y
structure.
41.
Parking areas or
CEO
CEO
CEO
driveways.
42. Piers or docks.
PB
PB
PB
43. Ponds
ys
PB
PB
44.
Po st-secondary
PB
NO
NO
schools.
Pre-elementary,
45. nursery, day care,
PB
PB
PB
elementary and
secondary schools.
46. Private recreational
CEO
CEO
CEO
facilities.
Private,
noncommercial clubs
and gathering/
47.
meeting places of
PB
PB
PB
social, fraternal, civic
and charitable
organizations.
48.
Public recreational
PB
PB
PB
facilities.
Public utilities and
49. sewage treatment
PB
PB
PB
facilities. 3, 7
Religious structures
such as churches,
50. synagogues, chapels,
PB
PB
PB
parish houses or
rectories.
441Page
C
PB
y1s
y
CEO
PB
PB
PB
PB
PB
PB
PB
PB
PB
MA
SL
RP
E
OVERLAY
OVERlAY
OVERlAY
NO
PBl0
PBt1
NO
y1s
y1s
y1s
y1s
y
y
y
y
CEO
CEO
CEO
PB
PB
PB
PBll
PB
PB
NO
PBll
PB
PB
PBlO
PBll
NO
PB
NO
PBll
NO
NO
PBlO
PBll
PB
PB
PBl0
PBll
NO
PB
PB 10
PBll
PB
PB
PB
PBll
PB
PB
NO
PBll
NO
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-OI
Amended: 2 5- Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l-May-19
Amended: 11-Jul-20
Amended: l l -May-2<1
Last Amended: 07-J un ·25
--
·-
,---
LAND USE
R
V-1
V-112
C
E
MA
SL
RP
-
ZONING DISTRICT ♦
V-1112
OVERlAY
OVERLAY
OVERLAY
Non-Mobile Vending
51.
Units, Restaurants
NO
NO
NO
PB
PB
PBI0
PBll
NO
and take-away
prepared food. 4
Sale of produce
raised on premises,
52. which may include
y
y
y
y
y
y
y
y
seasonal sale of
produce raised off
·- premises_._--.--·
-- ~
--
53. Shoreline access.
CEO
CEO
CEO
CEO
CEO
CEO
CEO
PB
54. Shoreline
CEO
CEO
CEO
CEO
CEO
CEO
CEO
PB
stabilization.
---··--
-
55. Signs.
CEO
CEO
CEO
CEO
CEO
CEO
CEO
PB
Solid waste
56. processing or
PB
NO
NO
NO
NO
NO
NO
NO
disposal.
---·
·--.
·----
Telecommunications
towers or antennas
57. subject to the
PB6
NO
NO
NO
NO
NO
NO
NO
performance
standards of Section
4.7.E.
58. Town government
PB
PB
PB
PB
PB
PB
PBII
PB
facilities. 7
·--
-~·
FOOTNOTES
--·-----·-
1.
Agriculture and animal husbandry are allowed in a Resource Protection
Overlay District by Site Plan Approval where the underlying district is the Rural
District.
·-
2.
Site Plan Approval is required for certain activities in the Source Water
Protection Overlay District.
3.
These include overboard discharge units lawfully in existence at the time of the
enactment of this ordinance.
·--
--
_±:_____12oes not include foo~cparation for off-premises retail s_ale or caterinL__
45 j Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-0 I
Amonded: 25-Mar-02
Amonded: 07-May-02
Amended: 04-Apr-05
Amended·, 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended·, 27-Mar-10
Amended: 02-Nov- l 0
Amended: 26-Mar- \ 1
Amended: 0l-Jun-13
Amended: 23-Sept- l 3
Amended: 11-May- I 9
Am~.nded ·, l l -Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
FOOTNOTES
5.
Parking areas, road and driveway construction, mineral exploration disturbing
more than one hundred (100) square feet of soil, mineral extraction, and
earthmoving in any amount in the Shoreland Overlay District requires a permit
from the appropriate permitting authority as set forth in Article 7 of this
Ordinance.
6.
Telecommunications towers are permitted in the Telecommunications Tower
Overlay District, only.
7.
Does not include streetlights, poles, cables, pipes, wires, traffic signs and
similar items placed or erected in the public way, for which no permit is
required under this Ordinance
8.
Only for the purpose of mitigating fire hazards and other danger to public
safety or the environment and conditioned upon submission of a plan for that
stated purpose, including access roads if needed, prepared by a State of Maine
Licensed Forester.
9.
Earthmoving that is incidental to the construction of any structure or other
activity that has been issued a permit from the appropriate permitting
authority does not require Site Plan Approval or a separate permit unless such
earth moving alters the surface or subsurface drainage patterns of the property
or causes the grade of the land to change by more than one-half (1/2) foot.
10. Uses that are not reliant upon water frontage or servicing marine related needs
are not permitted.
11.
If the use is permitted in an underlying district, Site Plan Approval is required
in the Shoreland Overlay District.
12. If the use is permitted in an underlying district, it is also permitted in the
Shoreland Overlay District.
13. The term "structure" means either a "principal structure" or "accessory
structure" as defined in Article 15.
14. Up to four dwelling units may be permitted, in accordance with Section 6.19
15. Authorized after receiving a Mobile Vending Unit Permit in accordance with
Castine Mobile Vending Unit Ordinance. ; An:~, 10'
461 Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-0 l
Amended: 25-Mar.,02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-1 0
Amended: 02-Nov- l 0
Amended: 26-Mar- l l
Amended: 0J-Jun-13
Amended: 23- Sept-13
Amended: l 1-May-19
Amended: 11-Ju l-20
Amended: l l ,May-24
Last Amended: 07 -J un-25
5.5.
DIMENSIONAL REQUIREMENTS J\D:1Jh!
A.
Lot Dimension Table ;Arn. 1; /Arn . .2 1 :..\.t11.Jj [Am_.ii! !An:J-\i
Lots and structures shall meet or exceed the following dimensional
requirements:
DIMENSION
R
V-1
V-11
V-111
MA&
E
-
ZONING DISTRICT ♦
C
Minimum lot area (sq.
85,000
8,250
20,0009
85,000
7,500
N/A
ft.) 12
[Arn l j
Minimum lot width (ft.)
2001
90
100
2001
85
N/A
10, 12
Setbacks (ft.) 12
Front yard
304
10
15
20
102
153
Rear yard
304
10
15
20
102
153
Side yard
304
10
15
20
102
153
Minimum shore
200
100
150
200
100
N/A
frontage (ft.) 10
Maximum percent lot
20
50
30
20
65
60
coverage (%) 12
Structure height (ft.) 8
355,6
357
357
357
357
507
Footnotes
A single bacl<lot for development with a single-family dwelling may be created
1.
with its frontage along a fifty (50) foot wide right-of-way. That right-of-way will
not be deducted from the lot width or lot area of the front lot.
Ten ( 10) feet or no less than the abutting property with the least setback. This
2.
setback reduction only applies to the side of the lot with the abutter
encroachment. ict1:. VO:
For lots that abut a lot located in another district, the setback shall be the
3.
~-~ater of fifteen_ll5) feet or the abutti!!_g_setback.
The front yard setback for telecommunications towers located in the
Telecommunication Tower Overlay District shall be one thousand (1,000) feet
4.
and the rear yard and side yard setbacks for telecommunications towers
located in the Telecommunication Tower Overlay District shall be thirty (30)
feet plus the height of the tower.
471 Page
Zoning Ordinance - Adopted: 28-Mar·2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr·OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- 10
Amended: 26-Mar-1 l
Amended: 01 .Jun- 13
Amended: 23-Sept- 13
Amended: l l-May-19
Amended: J] .Jul-20
Amended: 1 l-May-24
Last Amended: 07 -Jun-25
Footnotes
Telecommunications towers located in the Telecommunication Tower Overlay
5.
District are not subject to the structure height limitation of this section, but
are governed by Section 4. 7. E. 1. ,g_
The Permitting Authority may increase the maximum height by up to ten (10)
feet above the roof for cupolas, chimneys and appurtenances without floor
6.
area where the extension will not cause a hazard, and the feature does not
occupy more than ten percent ( 10%) of the roof area. Religious structures
may have features such as steeples which exceed ten ( 10) feet above the roof.
The Permitting Authority may increase the maximum height by up to ten (10)
feet above the roof for cupolas, chimneys and appur.tenances without floor
area where the extension will not cause a hazard, and each element does not
7.
occupy more than two and one-half percent (2 % % ) of the roof area and all
elements do not occupy more than ten percent (10%) of the roof area.
Religious structures may have features such as steeples which exceed ten ( 10)
feet above the roof.
For buildings in the Shoreland Overlay District, the vertical distance between
8.
the mean elevation of the original grade at the downhill side of the building
and the highest point of the roof.
9.
Lots in Village District II located within the Shoreland Overlay District require
a minimum lot size of 30,000 square feet.
The minimum width of any portion of any lot within one hundred ( 100) feet,
10. horizontal distance, of the normal high-water line of a water body or upland
edge of a wetland shall be equal to or greater than the shore frontage
requirement for a lot with the 2ro2osed use.
11. The term "structure" means either a "principal structure" or "accessory
structure" as defined in Article 15.
48\Page
Zoning Ordinance - AdoptecL 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-0S
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- I 0
Amended: 02-/'l{lv-10
Amended: 26-Mar- l l
Amended: 01-Jun-13
Amended: 23-Sept- 13
Amended: 11-May- 1 9
Amended: l 1-Jul-20
Amended: 11 May 24
Last Amended: 07-Jun-2S
Footnotes
Pursuant to Title 30-A M.R.S.A., § 4353 (4-C), the Planning Board, in
reviewing a cluster subdivision under the applicable provisions of the Castine
Subdivision Ordinance, is allowed to approve development proposals that do
not meet the dimensional standards otherwise required by this Ordinance,
and such approval is not considered the granting of a variance. This authority
does not authorize the reduction of dimensional standards required under the
12. mandatory shoreland zoning laws. This authority does not authorize the
reduction of any dimensional standard in the Commercial District. In the
Rural, Village I, Village II and Village III Districts, this authority does not
authorize the reduction of any dimensional standard to less than the
following: 1) minimum lot area - 50% of required area; 2) minimum lot width -
75% of required width; 3) maxi.mum percent lot coverage - 50% of approved
lot area; and 4) front, rear or side setback - 10 feet. [Am JI
----'----'----------------
B.
Lots partially within a Resource Protection District
No portion of any lot created after August 24, 1981 and lying within a
Resource Protection District may be used to meet the dimensional
requirements of any other district in which the remainder of the lot is
situated.
C.
Within the Shoreland Overlay District, if more than one residential dwelling
unit, principal governmental, institutional, commercial or industrial
structure or use, or combination thereof, is constructed or established on a
single parcel, all dimensional requirements shall be met for each additional
dwelling unit, principal structure, or use.
49 IP age
Zoni11g Ordinance-. Adopted: 28-Mar-.2000
Amended: 26-Mar-0 I
Amended: 25-Mar .. 02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended; 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- l 0
Amended: 26-Mar- l 1
Amended: 0 I-Jun-13
Amended; 23 .. sept- !3
Amended: 1 l-May-19
Amended: 1 l-Jul-20
Amended: J 1-May-24
Last Amended: 07-Jun-25
ARTICLE 6: PERFORMANCE STANDARDS
!Am_l,__26-Mar-0l_;_Am2. 25-Mar-02;Am3. 07-M,~-0£i_ Am 5. 26-Mar-07 _i__ftm 6, _.2_4-Mar-0§_;_
bm'L._04-:AJ:1:r-09i___h.m9. 02-Nov- lQ_;_Aml0, 26-Mar-11; Am.13_ 11-M_gy~l.2.;_Am.14 1 l-Jul-2Q_;_
Am.16 07-Jun-25)
6.1. GENERAL
A.
Purpose
The purpose of the regulations contained in this Article is to allow maximum
utilization of land while assuring against adverse impacts on the
environment and/or neighboring properties, adherence to the current
Castine Comprehensive Plan, and upholding of the public interest. This
assurance is provided by separating the area of the Town of Castine into
zoning districts and permitting specific land uses within each, provided that
a use meets all the additional criteria specified in this Ordinance.
B.
Standards apply to all permits and approvals
The following Land Use Standards shall govern all permits and approvals
issued by the CEO and the Planning Board. Shoreland Standards are
included in Article 7. These standards apply to land uses and activities
within the Shoreland Overlay District. The Shoreland Standards are those
mandated by the State of Maine as part of the Mandatory Shoreland Zoning
Act (Title 38, M.R.S.A., §§ 435-449, as amended). In reviewing applications
submitted pursuant to this Ordinance, the CEO or the Planning Board shall
consider the following performance standards prior to issuing final approval.
1n all instances, the burden of proof of compliance shall be upon the
applicant. iiID._ .. 2:
6.2. ARCHAEOLOGICAL OR HISTORIC SITES
Any proposed land use activity that may disturb an archaeological or historic site
as defined in the Castine Historic Preservation Ordinance, or which is listed or
which has been nominated for listing on the National Register of Historic Places
in accordance with the procedures established by Federal Law shall require Site
Plan approval. In such case the application for Site Plan approval shall attach
comments in writing from the Maine Historic Preservation Commission
concerning the proposed activity, and the Planning Board shall hold a Public
Hearing prior to taking any action with respect to the application. The
501Page
Zoning Ordmance -· Adopted; 28-Mar-2000
Amended: 26- Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended; 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended; 02-Nov-10
Amended: 26-Mar-l I
Amended: Ol-Jun-13
Amended: 23-Sept- 13
Amended; 11-May-19
Amended: 11-Jul 20
Amended: l\-May-24
Last Amended; 07-Jun-25
recommendations of the Maine Historic Preservation Commission shall be
considered by the Planning Board in granting any approvals. The applicant shall
be responsible for obtaining the written comments of the Maine Historic
Preservation Commission. If the site is located within a designated district under
the Castine Historic Preservation Ordinance and the application is approved by
the Planning Board, a condition of such approval shall be that the applicant must
obtain a Certificate of Appropriateness from the Castine Historic Preservation
Commission before any permit is issued. (.\m J 1. \,\lll.1\
6.3. CAMPGROUNDS
Campgrounds shall conform to the minimum requirement imposed under State
licensing procedures and the following additional requirements:
A.
Each recreational vehicle, tent, or shelter site shall contain a minimum of
five thousand (5,000) square feet, not including roads and driveways.
B.
Each recreational vehicle, tent, or shelter site shall be provided with a picnic
table, trash receptacle, and fireplace.
C.
Recreational areas without water-carried sewage facilities shall provide
portable toilets and a service capability for such toilets approved by the
Town's Local Plumbing Inspector {LPI). f6.t.iiJ.
D.
The area intended for placement of the recreational vehicle, tent or shelter
and utility and service buildings, shall be set back a minimum of one-
hundred (100) feet from the exterior lot lines of the camping area, one-
hundred (100) feet from the normal high-water line of any great pond and
seventy five (75) feet from the normal high-water line of all other water
bodies, tributary streams or upland edge of a wetland. ;,\rn.__;::!
E.
All campgrounds shall be screened from adjacent land areas by a
continuous landscaped area not less than twenty-five (25) feet in width
containing evergreen shrubs, trees, fences, walls or any combination which
forms an effective visual barrier of not less than six (6) feet in height.
51 IP age
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 0'1-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- lO
Amended: 02-Nov- lO
Amended: 26-Mar-l 1
Amended· Ol-Jun-13
Amended· 23-Sept-13
Amended· Jl-May-19
Amended: 11-Jul-20
Amended: J 1-May-24
Last Amended: 07-Jun-25
6.4. CONSTRUCTION IN FLOOD llAzARD AREAS
When any part of a development is located in a Flood Hazard Area as identified by
the Federal Emergency Management Agency, the plan shall indicate that all
structures on lots in the development shall be constructed with their lowest floor,
including the basement, at least one {l) foot above the one hundred (100) year
flood elevation, and meet all other requirements of the Floodplain Management
Ordinance for the Town of Castine, Maine. Such a restriction shall be included in
the deed to any lot which is included or partially included in the flood hazard
area. _O:,m. l 1
6.5. DRIVEWAYS AND WALKWAYS
Driveways and walkways constructed at existing ground level are exempt from
the minimum setback requirements of the Lot Dimension Table, Section 5.5.A. No
driveway or walkway may encroach upon any adjoining lot in the absence of a
deeded and recorded right-of-way. f:\J:l..!J_;
6.6. DUST, FUMES, VAPORS, GASES, ODORS, AND Ex.PLOSIVE MATERIALS
A.
Emissions of dust, dirt, fly ash, fumes, vapors or gases which pose an
unreasonable risk of harm to human health or the environment shall be
prohibited.
B.
No land use or establishment shall be permitted to produce unreasonable,
offensive or harmful odors perceptible beyond their lot lines, measured
either at ground or habitable elevations.
C.
No highly flammable or explosive liquids, solids or gases shall be stored in
bulk above ground, unless they are stored in compliance with the
requirements of the rules and regulations adopted by the State of Maine.
6. 7. EROSION AND SEDIMENTATION CONTROL
The following measures relating to conservation, erosion and sediment control
shall be included where applicable as part of all projects submitted for review and
approval under this Ordinance:
52 \Page
Zoning Ordmance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07 -May-02
Amended: 04-Apr-05
Amended: 26- Mar- 07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26"Mar-1 l
Amended: Ol-Jun-13
Amended· 23-Sept-13
Amended: 1 l-May- 19
Amended: l 1-Ju\-20
Amended: 11-May.24
Last Amended: 07-Jun-25
A.
The procedures outlined in the erosion and sedimentation control plan,
prepared and submitted by the applicant, shall be implemented during the
site preparation, construction, and cleanup stages.
B.
Erosion of soil and sedimentation of watercourses and water bodies shall be
minimized by employing the following best management practices:
1.
Stripping of vegetation, soil removal and regrading or other
development shall be done in such a way as to minimize erosion.
2.
Development shall preserve outstanding natural features, keep cut-fill
operations to a minimum and ensure conformity with topography so as
to create the least erosion potential and adequately handle the volume
and velocity of surface water runoff.
3.
The development shall not unreasonably increase the rate or volume of
surface water runoff from the proposed site.
4.
Whenever feasible, natural vegetation shall be retained, protected and
supplemented.
5.
The disturbed area and the duration of exposure shall be kept to a
practical minimum.
6.
Disturbed soils shall be stabilized as quickly as practicable.
7.
Temporary vegetation or mulching shall be used to protect disturbed
areas during development.
8.
Permanent (final) vegetation and mechanical erosion control measures
in accordance with the standards of the Hancock County Soil and
Water Conservation District or the Maine Soil and Water Conservation
Commission shall be installed as soon as practicable after construction
ends.
9.
531Page
Until the disturbed area is stabilized, sediment in the runoff water shall
be trapped by the use of debris basins, sediment basins, silt traps or
other acceptable methods.
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-Il
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended:! 1-May-19
Amended: l 1-Jul-20
Amended: l l"May-24
Last Amended: 07 -Jun-25
10. The top of a cut or the bottom of a fill section shall not be closer than
ten (10) feet to an adjoining property, unless specifically permitted by
the permitting authority. Extraction operations (gravel pits, etc.) shall
not be permitted within one hundred (100) feet of any property line in
absence of the prior written agreement of the owner of such adjoining
property.
11. During grading operations, methods of dust control shall be employed
wherever practicable.
12. Whenever sedimentation is caused by stripping vegetation, regrading or
other development, it shall be the responsibility of the developer
causing such sedimentation to remove it from all adjoining surfaces,
drainage systems and watercourses and to repair any damage at his
expense as quickly as possible.
13. Any activity on a stream, watercourse or swale or upon floodway or
right-of-way shall comply with the Natural Resource Protection Act,
Title 38 M.R.S.A., §§ 480-A and 480-S, as amended. Any such activity
shall also be conducted in such a manner so as to maintain as nearly
as possible the present State of the stream, watercourse, swale,
iloodway, or right-of-way for the duration of the activity and shall be
returned to its original or equal condition after such activity is
completed.
14. Maintenance of drainage facilities or watercourses originating and
completely on private property is the responsibility of the owner to the
point of open discharge at the property line or at a communal
watercourse within the property.
6.8. FENCES
A.
Except as provided in Section 6.8.C. below, no fence or boundary wall shall
exceed six (6) feet in height above the average level of the ground on which it
stands. ,l!1i_t
B.
Screening for licensed junkyards, automobile recycling businesses or
automobile graveyards shall be at least six (6) feet in height but shall not
exceed eight (8) feet in height except to accomplish the required complete
541Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May.02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar- 10
Amended: 02 -Nov- 10
Amended· 26-Mar-1 l
Amended: 01-Jun 13
Amended: 23-Sept-13
Amended: l 1-May-19
Amended: ll-Jul-20
Amended. ! 1-May-24
L.9.st Amended. 07-Jun-25
screening from ordinary view; deer fences erected to protect gardens or
orchards may exceed six (6) feet in height but shall not exceed ten (10) feet
in height; a decorative arbor at a pedestrian gate may exceed six (6) feet in
height but shall not exceed eight (8) feet in height; security fencing for
telecommunications towers shall be at least eight (8) feet in height but shall
not exceed ten (10) feet in height. !Am. Ii [.)rn 11
C.
Fences and boundary walls are exempt from the minimum setback
requirements of the Lot Dimension Table, Section 5.5.A, but a fence shall
not be located where it will obstruct the line of sight at a public street
intersection. [,-\mi_! l'\r.1 :2:
6.9. FIRE lfAz.ARD MITIGATION IN THE COMMERCIAL DISTRICT
Special requirements shall be observed within the Commercial District in order to
lessen potential fire hazards. A fee payable to the Town shall be assessed to the
individual seeking written approval by the Fire Chief. The amount of the fee shall
be set by the Board of Selectmen and adjusted periodically after a Public Meeting
held to present the facts relevant to such setting or adjustment. There shall be
no change of use of a structure and no structure shall be built, moved, replaced,
altered or enlarged without consultation with and approval in writing by the Fire
Chief or designated representative, and subsequent approval by the respective
permitting authority subject to the additional conditions listed below: [.-\rn0 _;>j
A.
Fire trucks and ambulances shall have unobstructed access to the
structure.
B.
Access to the structure shall not be used for parking or storage so as to
hinder passage of emergency vehicles.
C.
Adequate water supply for fire suppression is or v.r:i.11 be available prior to
granting a certificate of occupancy.
D.
Roofs or roof overhangs shall not intrude upon neighboring properties and
roof eaves shall not exceed thirty (30) feet in height from servicing accesses.
E.
Such other safety measures, including but not limited to sprinkler systems,
rated partitions, fire extinguishers or the posting of signs as needed for
specific hazards, as may be required. -\m.,,.
55JPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26 Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May- l 9
Amended: ll-Jul-20
Amended. ll-May-24
Last Amended: 07-Jun-25
6.10. GROUNDWATER PROTECTION
A proposed site development and/or use shall not adversely impact either the
quality or quantity of groundwater available to abutting properties or public
water supply systems. Projects involving common on-site water supply or sewage
disposal systems with a capacity of two thousand (2,000) gallons per day or
greater have demonstrated that the groundwater at the property line shall
comply, following development, with the standards for safe drinking water as
established by the State of Maine.
6.11. HOMEOCCUPATIONS
The purpose of the Home Occupation provision is to permit the conduct of those
businesses which are compatible with the districts in which they are allowed.
Home occupations are limited to those uses which may be conducted within a
residential dwelling or accessory structure without substantially changing the
appearance or condition of the property as a residence or of accessory structures;
A.
Home occupations shall be carried out wholly within a dwelling unit or
accessory structure to a dwelling unit.
B.
No more than three (3) persons who are not family members residing in the
dwelling unit may be employees of a home occupation.
C.
Home occupations shall be clearly incidental and subordinate to the use of a
dwelling unit for residential purposes.
D.
In connection with a home occupation there shall be no exterior signs other
than permitted by the requirements of Section 6.28, no exterior storage of
materials, and no other exterior indication of the home occupation or
variance from the residential character of the premises. ,ArJ_1 7.:
E.
A home occupation shall not create noise, dust, vibration, odor, smoke,
glare, electrical interference, fire hazard, or any other hazard or nuisance to
any greater degree or more frequent extent than that normally experienced
in an average residential building in the district in which it is located.
561Page
Zonmg Ordinance -Adopted. 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07- May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended, 26-Mar- l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: l l-Jul-20
Amended: I l-May-24
l.9.stAmended: 07-Jun-25
F.
Home occupations providing (for a fee) professional, educational and/or
personal services to groups of persons on the premises shall be limited to
serving no more than eight (8) persons at any one time, and to the
generation of no more than two (2} additional non-family vehicles on-site at
any one time.
G.
Home occupations are subject to the Off-Street Parking requirements of
Section 6.22. !20:il,_t
H.
Use permits for home occupations are non-transferable except to members
of the same family who continue to reside in the dwelling.
I.
Yard sales, garage sales and other intermittent sales activities shall not be
deemed a home occupation unless the activity continues for more than two
consecutive weekends or one week, or for more than four weekends per year.
J.
Use of a dwelling or accessory structure to receive requests for information
relating to services rendered off-premises, or the storage of materials or
equipment and used to provide services or products off-premises by a
member of the residing family shall not be deemed to be a home occupation.
K.
Sale of agricultural or garden produce grown on site conducted from tables
or temporary structures shall not be deemed to be a home occupation.
6.12. JUNKYARDS
No person or landowner shall allow any junkyard to be established, operated,
maintained or suffered to exist in violation of Title 30-A M.R.S.A., Chapter 183,
Subchapter 1, as amended and without first obtaining site plan approval by the
Planning Board, a nontransferable land use permit issued by the Selectboard in
accordance with State licensing and local requirements, and complying with the
following provisions:
_'I__Q_1 .0_,
A.
Junkyards shall be located a minimum of two hundred (200) feet from the
edge of the right of way; and shall be set back one hundred (100) feet from
all side and rear lot lines.
B.
Junkyards shall be located a minimum of three hundred (300) feet from any
public park, facility, or grounds.
571 Page
Zonmg Ordinance -Adopted. 28-Mar-2000
Amended: 26-Mar Ol
Amended: 25 Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended. Ol-Jun-13
Amended: 23-Sept-13
Amended·. 1 l-May-19
Amended: 11-Ju] 20
Amended: J l-May-24
Last Amended: 07-Jun-25
C.
Junkyards shall be entirely screened from view by earth berms, plantings or
fences which shall be well constructed and properly maintained at a
minimum height of six (6) feet and be sufficient to accomplish the complete
screening from ordinary view. Screening shall meet the requirements for
materials and appearance set by the Maine Department of Transportation
for junkyards. :~rr,.S.i
D.
In addition, the following provisions apply to all junkyards in the Town of
Castine:
1.
Upon arrival at the junkyard, all fuel, engine oil, radiator, battery,
transmission, fluids, etc., shall be drained from all vehicles, and
appropriate safety precautions, such as the removal of all door and
trunk locks, shall be taken to avoid injury and accidents.
2.
No vehicles may remain intact in the yard for more than thirty (30)
days, and complete processing of vehicles into salvage materials shall
be accomplished within four {4) months.
3.
All junk and salvage materials shall be stored within the screened/
fenced areas and the operation shall be conducted in such a manner as
to prevent unsightliness to the adjacent area.
4.
No open burning of salvage material or junk shall be permitted on the
premises. Waste fluids and unusable materials shall be disposed ofin
an environmentally sound manner. A concrete pad or other impervious
surface shall be provided for draining such fluids.
6.13. LAND NOT SUITABLE FOR DEVELOPMENT
The following lands shall not be included in the calculations of lot area for the
purpose of meeting the requirements of the minimum lot size requirements of
this Ordinance:
A.
Land below the normal high-water line of a water body or upland edge of a
wetland and land beneath roads serving more than two (2) lots;
58!Page
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar·Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24- Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-lO
Amended 26-Mar-1 l
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: ll-Jul-20
Amended: ll-May-24
Last Amended. 07-Jun-25
B.
Land which is located within the one hundred (100) year frequency flood
plain as identified by the Federal Emergency Management Agency or the
Department of Housing and Urban Development, Flood Insurance
Administration, unless the developer shows proof through the submission of
materials prepared by a Registered Land Surveyor which shows that the
property in question lies at least one (1) foot above the one hundred (100)
year flood level. The elevation of filled or made land shall not be considered;
C.
Land which is part of a right of way or easement, including utility
easements. This subsection does not apply to a right-of-way or utility
easement for access to a single backlot for development with a single-family
dwelling; :Am . .;]
D.
Land that has to be created by filling or draining a pond or wetland; and
E.
Land that has been determined to be a freshwater wetland, as defined in
Title 38 M.R.S.A., § 480-B, as amended.
F.
This Section does not apply to an existing lot of record proposed to be used
for a single-family residence.
6.14. LIGHTING
No land use or establishment shall be permitted to produce unreasonable glare or
brightness (0.3 foot-candles) beyond its lot lines. Where practicable, lighting
shall be directed downward and the light source shall be shielded. All exterior
lighting shall be designed to ensure safe movement of people and vehicles, and to
minimize adverse impact on neighboring properties and public ways. Adverse
impact is to be judged in terms of hours of use, hazards to people and vehicular
traffic and potential damage to the value of adjacent properties. Non-residential
lighting that is either installed or replaced after March 24, 2008 shall comply
with the standards of Title 5 M.R.S.A., § 1769, as amended. : \r,:.fii
6.15. MINERAL Ex.PLORATION
The following requirements for mineral exploration activities shall apply in all
districts; additional requirements for the Shoreland Overlay District are
contained in Section 7 .6 below.
591Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended; 26-Mar-01
/\mended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24 Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended· 11-May-!9
Amended: 11-,Jul-20
Amended; l 1-May-24
last Amended: 07-Jun-25
A.
All excavations, including test pits and holes, shall be promptly capped,
refilled, or secured by other equally effective measures so as to reasonably
restore disturbed areas and to protect the public health and safety.
B.
Except when surface waters are frozen, access ways for mineral exploration
activities shall not utilize stream channels bordered by Resource Protection
Districts except to cross the same by the shortest possible route; unless
culverts or bridges are installed in accordance with this Ordinance, such
crossings shall only use channel beds which are composed of gravel, rock or
similar hard surfaces which would not be eroded or otherwise damaged.
C.
Access way approaches to stream channels shall be located and designed so
as to divert water runoff from the way in order to prevent such runoff from
directly entering the stream.
D.
In addition to the foregoing minimum requirements, when conducting
mineral exploration activities and creating and maintaining associated
access ways, provision shall be made to effectively stabilize all areas of
disturbed soil so as to reasonably avoid soil erosion and sedimentation of
surface waters. These measures shall include seeding and mulching if
necessary to insure effective stabilization.
6.16. MINERAL EXTRACTION
The following requirements shall apply to mineral extraction activities in all
districts; additional requirements for the Shoreland Overlay District are
contained in Section 7.6 below.
A.
No portion of any ground area disturbed by the extraction activity shall be
closer than fifty (50) feet from any public roadway or one hundred (100) feet
from any property line in the absence of the prior written agreement of the
owner of such adjoining property.
B.
A natural vegetative screen of not less than fifty (50} feet in width shall be
retained between any facility intended primarily for public use, excluding
privately owned roads, and the mineral exploration or extraction activity.
C.
Within twelve (12) months following the completion of extraction operations
at any extraction site, or when less than one hundred (100) cubic yards of
601Page
Zonmg Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-O!
Amended: 25-Mar-02
Amended; 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-!O
Amended: 02-Nov-!O
Amended. 26-Mar- l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 1 hJul-20
Amended: 11-May-24
Last Amended: 07 -Jun-25
materials are removed in any consecutive twelve (12) month period, ground
levels and grades shall be established in accordance with the following:
1.
All debris, stumps, and similar material shall be removed for disposal
in an approved location, or shall be buried on-site. Only materials
originating on-site may be buried or covered on-site.
2.
The final graded slope shall be two to one (2:1) slope or flatter.
3.
Top soil or loam shall be retained to cover all disturbed land areas,
which shall be reseeded and stabilized with vegetation native to the
areas. Additional topsoil or loam shall be obtained from off-site sources,
if necessary, to complete the stabilization project.
4.
In keeping with the purposes of this Ordinance, the Planning Board
may impose such conditions as are necessary, including any
reasonable form of performance guarantee such as a performance
bond, to minimize the adverse impacts associated with mineral
extraction operations on surrounding uses and resources, including
but not limited to wildlife habitat, fisheries, unusual natural areas,
archaeological resources and historic sites.
D.
The following requirements shall apply to topsoil, sand and gravel extraction
in all districts:
1.
Topsoil shall be considered part of all developments, except mineral
extraction, and shall not be removed from the site except for surplus
topsoil from roads, parking areas, and building excavations.
2.
Extraction shall not be allowed below three (3) feet above the average
seasonal high water table. No ditches, trenches, pumping or other
methods shall be used to lower the water table or permit more gravel
extraction than could occur under normal conditions.
3.
Access roads into and around the pit shall not be oiled, salted, or
paved.
61 \ P a g e
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended· 25-Mar-02
Amended, 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-JO
Amended· 26-Mar- l 1
Amended· Ol -Jun-13
Amended· 23-Sept-!3
Amended: ll-May-19
Amended: 11-Ju1·20
Amended: I 1-May-24
Last Amended: 07 -Jun-25
4.
The pit shall not be used for storage or dumping of any substances that
could produce a harmful leachate, both during operation of the pit and
following its permanent closure.
5.
Storage of hazardous materials and petroleum products in the pit is
prohibited.
6.
Refueling and oil changes in the pit are prohibited, unless adequate
protection and containment is provided.
6.17. MANUFACTUREDHOUSING
A.
Mobile homes sited outside of mobile home parks, shall also meet the
following requirements:
1.
Lot-size dimensions for single-family dwellings apply to lots for mobile
homes.
2.
All ordinances, permit requirements, regulations and statutes
applicable to single-family dwellings apply to mobile homes.
3.
Each mobile home shall have a pitched shingle or metal roof. (,;ir1L i
4.
Each mobile home shall have siding that is residential in appearance
such as is common to on-site built houses.
5.
Each mobile home shall have a permanent foundation.
6.
Any fuel or heating oil tank shall comply with State standards.
B.
Nothing in Section 6. 17 .A shall prevent the relocation of any mo bile home
that was lawfully sited within the Town of Castine as of August 24, 1981.
C.
Modular homes meeting the construction standards for State-certified
manufactured homes are allowed in all districts where other single-family
homes are allowed.
D.
Notwithstanding any other provision of this Ordinance, a mobile home or
construction trailer may be permitted on the site of a construction project
621 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-OCJ
Amended: 27 -Mar -10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended 11-May-19
Amended: 1 l-Jul-20
Amended: l 1-May-24
Last Amended: 07-Jun-25
for not more than two (2) consecutive six (6) month periods provided that a
special permit is issued by the CEO for each six (6) month period. Such
permit may only be issued if the CEO is satisfied that:
1.
The mobile home or construction trailer is a necessary convenience for
the construction project and is clearly subordinate to such project.
2.
No health hazards or problems of sanitation will be caused by improper
disposal of sewage from the mobile home or construction trailer.
3.
The CEO may issue a special permit for use of a mobile home or
construction trailer for a temporary construction office for up to six (6)
months in districts where offices are permitted or on construction sites
anywhere in the Town of Castine.
E.
Except as specifically permitted by this section, no mobile home shall be
used for any purpose, nor placed on any lot, except in the Rural District or
in an authorized mobile home park.
F.
Notwithstanding the other provisions of this Section, unoccupied mobile
homes may be placed on a lot for sale by a dealer where permitted by this
Ordinance.
G.
No mobile home may be located within the Town of Castine unless it meets
the design standards of the National Manufactured Housing Construction
and Safety Standards Act of 1974 (42 U.S.C. §§ 5401 et seq.) for mobile
homes manufactured after June 14, 1976. 'Jm.J_!;:l_c~~i
H.
Pursuant to Title 30-A M.R.S.A. § 4358(4), no new manufactured housing
may be located or constructed within the Town of Castine unless the owner
presents evidence that either the Maine sales tax has been paid on the
manufactured housing or the manufactured housing is being installed or
constructed by a licensed dealer registered to collect Maine sales tax. \;r,_._l.
t~'sl: .1.:
6.18. MOBILE HOME PARKS/MANUFACTURED HOUSING COMMUNITIES
Mobile home parks shall meet the following requirements in addition to any
imposed by State law:
63/Page
Zoning Ordinance -Adopted. 28-Mar-2000
Amended: 26-Mar 01
Amended: 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mar- l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended· ll-May-19
Amended: I l-Jul-20
Amended: J I-May-24
Last Amended: 07-Jun-25
A.
The park shall be landscaped by shrubs and trees so as to be screened by a
fifty (50) foot buffer strip from direct view from the nearest public road.
B.
Each mobile home lot, service structure (such as laundry facilities, park
office, etc.) shall meet the off-street parking requirements of this Ordinance.
C.
Each mobile home lot served by a central on-site subsurface waste disposal
system approved by the Maine Department of Human Services shall be at
least twelve thousand (12,000) square feet in area.
D.
Each mobile home lot served by an individual approved on-site subsurface
waste disposal system shall be at least twenty thousand {20,000) square feet
1n area.
E.
The overall area of the park shall be at least the area of each mobile home
lot as determined above plus areas required for road rights-of-way; buffer
strips; and all setbacks.
F.
All roads in the park shall conform to State standards for mobile home
parks.
G.
Mobile homes located in mobile home parks are not required to have
permanent foundations.
H.
No mobile home may be located in any mobile home park unless it meets the
design standards of the National Manufactured Housing Construction and
Safety Standards Act of 1974 (42 U.S.C. § 5401 et seq.) for mobile homes
manufactured after June 14, 1976. "\rnl_, r_\::1.2:
6.19. Two-FAMILY AND MULTI-FAMILY DWELLINGS
A.
New construction of a two-family dwelling or conversion of an existing single
family dwelling to a two-family dwelling requires a minimum lot size of one
hundred and fifty percent (150%) of the minimum lot size for a single-family
dwelling in the district in which it is built. All other lot dimensional
requirements of this Ordinance must be met. ,_\:nJ_; ij_n:.1r
B.
New construction of or conversion to a multi-family dwelling not in the
Shoreland Overlay District requires the minimum lot size for a single-family
64IPage
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended. 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-)3
Amended: 11-May Jg
Amended: 1 l-Jul-20
Amended· l 1-May-24
Last Amended: 07-Jun-25
dwelling for each dwelling unit on the parcel. All other lot dimensional
requirements of this Ordinance must be met. :.~0-1
C.
New construction of or conversion to a two-family dwelling or a multi-family
dwelling in the Shoreland Overlay District requires: 1) the minimum shore
frontage required for a single-family dwelling for each dwelling unit on the
parcel and 2) a minimum lot size required for a single-family dwelling for
each dwelling unit on the parcel.
D.
A new multi-family dwelling unit and a lot with more than one secondary
structure containing dwelling units, are subject to the provisions of the
Castine Subdivision Ordinance.
E.
In all Districts in which residential uses are allowed, the following additional
dwelling units shall be permitted, provided all applicable dimensional
standards are met: [0 \,nc.l/:.i
1. If a lot does not contain an existing dwelling unit and the lot is not
located in a Designated Growth Area, up to two dwelling units per lot are
permitted. The dwelling units may be within one structure or multiple
structures. ! -\q_:_.:..Lil
2. If a lot does not contain an existing dwelling unit and the lot is located in
a Designated Growth Area, up to four dwelling units per lot are
permitted. The dwelling units may be within one structure or multiple
structures. :,:\.rrr.. l .'>i
3. If a lot contains one existing dwelling unit, the addition of up to two
dwelling units is permitted. The additional units may consist of one
additional dwelling unit within or attached to an existing structure or
one additional detached dwelling unit, or one of each. The addition of up
to two dwelling units under this section shall be subject to review by the
Code Enforcement Officer and shall not require site plan review. -~:,1 _l_:'i
6 .20. MOL TIPLE STRUCTURES AND USES ON A SINGLE LOT
A.
If more than one principal structure is constructed on a single parcel of
land, all dimensional requirements shall be met for each structure.
651 Page
Zoning Ordinance - Adopted: 28-- Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar--02
Amended: 07-May--02
Amended: 04-Apr-05
Amended. 26-Mar-07
Amended: 24-Mar--08
Amended: 04-Apr-09
Amended: 27-Mar--10
Amended: 02-Nov-JO
Amended: 26-Mar- ll
Amended: 01--Jun-13
Amended: 23-Sept--13
Amended: 11-May- 19
Amended: ll-Jul--20
Amended: 11-May--24
Last Amended: 07--Jun-25
C.
Within the Shoreland Overlay District, if more than one residential dwelling
unit, principal governmental, institutional, commercial or industrial structure
or use, or combination thereof, is constructed or established on a single parcel,
all dimensional requirements shall be met for each additional dwelling unit,
principal structure, or use.
6.21. NOISE
No land use or establishment shall be permitted to produce unreasonable noise
perceptible beyond their lot lines, subject to the exceptions herein. Unreasonable
noise shall be noise exceeding the following levels measured on an ANSI Type 1 or
1I meter using the A-weighted network. 7:00 a.m. to 10:00 p.m. - 60 dBA; 10:00
p.m. to 7:00 a.m. - 50 dBA.
A.
Exceptions
1.
Maximum sound levels may be exceeded by 10 dBA for a single period,
no longer than 15 minutes, each day.
2.
Natural phenomena.
3.
Any bell or chime from any clock, school or church.
4.
Any siren, bell, horn or whistle lawfully used by an emergency vehicle,
or any other emergency alarm used in an emergency situation or test,
including the 12:00 Noon test of the firehouse siren.
5.
Warning devices required by OSHA, USCG, or any other State or
Federal regulatory agency.
6.
Aircraft operations which are subject to FAA regulation.
7.
Sporting, cultural, religious or public events permitted by the Board of
Selectmen.
8.
Noise generated by any construction or demolition equipment operated
from 7:00 a.m. to 7:00 p.m.
66 \ P a g e
Zoning Ordinance -AdGpted: 28-Mar-2000
Amended· 26-Mar-01
Amended: 25-Mar·02
Amended: 07-May·02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended; 26-Mar-ll
Amended: OJ-Jun-13
Amended. 23-Sept-13
Amended: 11-May-19
Amended; 11-Ju.l-20
Amended: l l-May-24
Last Amended: 07-Jun-25
9.
Emergency repair work on public utilities.
10. Timber harvesting from 7:00 a.m. to sunset.
11. Noise created by lawful blasting from 7:00 a.m. to 7:00 p.m.
12. Noise created by refuse and solid waste collection from 6;00 a.m. to
7:00 p.m.
13. Noise generated by any stand-by electric generator operated during a
power outage or during an exercise period not exceeding thirty (30)
minutes once a week. ').rn,..0.i
B.
Limitation of exceptions
The exceptions 6.21.A.5, 6, 7, and 12, above shall not apply in determining
the effect on neighboring properties for any use being considered for Site
Plan Approval. The Planning Board may consider any noise related to these
exceptions in determining whether a given use will have an unreasonable
adverse effect upon a neighboring use or upon the neighborhood.
6.22. OFF-STREET PARKING
Traffic safety and the need for emergency vehicle access, especially in the
congested "on-neck" streets, requires establishment of minimum standards for
the provision of parking spaces for businesses, homes and institutions within the
Town. All uses and structures shall have adequate off-street parking to
accommodate all anticipated needs. To accomplish this purpose, all of the
anticipated off-street vehicular parking needs for a proposed use or structure
shall be considered before granting any approvals. Property located in the
Commercial District and the Witherle Memorial Library are exempt from the
following standards unless specifically included. , \n1__~_ '-'\r:-1 -J
A.
Off-street parking standards
I.
A parking space provided to meet the minimum requirements of
Section 6.22.B must be at least 180 square feet in area and must be
dimensioned and configured so that a vehicle can enter and exit the
67 I p a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended; 26-Mar-OI
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- 10
Ameuded· 02-Nov-10
Amended: 26-Mar-J 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: 1 l-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
parking space safely and conveniently and drivers and passengers can
enter and exit the parked vehicle safely and conveniently.
2.
No parking space shall be considered to serve more than one structure
except as provided in Section 6.22.D below. f.\TL_!Jj
3.
Driveways or accesses to parking spaces shall be constructed so as to
minimize potential safety hazards and to provide openings at exits to
public streets that will maximize driver vision.
4.
Parking areas for more than four (4) vehicles or boats shall be
landscaped so as to be screened from direct view from the nearest
public street in order to minimize any adverse effect upon historical
assets of the Town or the value of neighboring properties, to the extent
that such landscaping shall not impair driver vision.
B.
Minimum requirements
1.
Auto Service Stations and Repair Garages: one (1) space for each
regular employee, plus one (1) space for each fifty {50) square feet of
floor area used for service work.
2.
Residential: Two {2) parking spaces for each private residential dwelling
unit and one (1) parking space for each private residential dwelling
unit, created after March 31, 2007, in the Commercial District. For
Affordable Housing Developments, no more than two (2) parking spaces
for every three dwelling units shall be required. j.\n,.:,: [.\n_L.i.5.:
3.
Business and commercial establishments not otherwise listed, libraries,
museums, offices or professional buildings: one ( 1) space for each two-
hundred (200) square feet of the floor area plus one (1) space for each
two (2) employees.
4.
Bed and breakfasts, hotels and inns: One (1) space for each guest suite
or sleeping room and one (1) space for each two (2) employees.
5.
Campgrounds: one {l) space for each recreational vehicle, tent or
shelter space.
68 \ P a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25- Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended: 04-Apr -09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- 11
Amended: 01-Jun-13
Amended: 23-Sept· 13
Amended: 1 l-May-19
Amended: 1 J-Ju\-20
Amended: 11-May-24
Last Amended: 07-Jun-25
6.
Drive-in restaurants and food stands: ten (10) spaces plus one (l)
additional space for each person serving or preparing food on the
largest shift employed at least once a week on a regularly scheduled
basis during the peak season of operations.
7.
Funeral parlors: twenty (20) spaces.
8.
Fraternal organization and club structures: one (1) space for each five
(5) members.
9.
Home occupations shall have sufficient spaces to accommodate the
estimated off-street parking needs of customers as determined by the
Planning Board based upon the anticipated volume of traffic at the site.
10. Hospitals and nursing homes shall have one ( 1) space for each two (2]
beds and one (1) space for each two (2) employees.
11. Places of amusement or public assembly: one (1) space for each fifty
(50) square feet of floor area devoted to patron use.
12. Restaurants and cocktail lounges: one (1) space for each four (4)
customer seats, plus one (1] space for each two (2) employees.
13. Schools shall have one (1) space for each two (2) employees and
additional spaces for students as follows:
a.
Elementary, pre-elementary and daycare/nursery schools: one (1)
space for each ten (10) students.
b.
Secondary: one (1) space for each five (5) students.
c.
Post secondary: two (2) spaces for each three (3) enrolled
students. --~''i:
14. Wholesale businesses: one (1) space for each three hundred (300)
square feet of floor area.
15. For uses not listed in this section, the permitting authority shall
prescribe the number which, in no case, shall be less than the
adequate number to provide for employees, customers and visitors to
the site.
69 I p a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended· 26 Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended. 26-Mar-l l
Amended: OJ -Jun-13
Amended: 23-Sept- l 3
Amended: 1 \-May-19
Amended 11-Ju]-20
Amended: 11-May-24
Last Amended: 07-Jun-25
C.
New structures or expansions
Any new structure or proposed expansion of an existing structure not
possessing the minimum required parking spaces may be approved by the
permitting authority only if all other provisions of this Ordinance are met,
the Fire Chief has been consulted and has approved the new structure or
proposed expansion in writing, no loss of existing off-street parking spaces
will result, and the new structure or proposed expansion is designed so as to
maximize the potential for off-street parking. i,-;\m.::;
D.
Location on other property
If the required automobile parking spaces cannot be provided on the same
lot where the principal use is conducted, the permitting authority can
permit that such spaces may be provided on other off-street property
provided that such property lies within four hundred (400) feet of the main
entrance to such principal use and is in the same zone. Such an automobile
parking space shall be associated with the principal use by deed, easement
or lease, and shall not thereafter be reduced or encroached upon in any
manner, provided however, that it may serve different principal uses at
different times of day. Any off-site parking area located more than four
hundred {400) feet from the main entrance of the principal use is permitted,
provided there is adequate bus transportation from the parking area to and
from the principal use.
6. 23. OIL AND CHEMICAL STORAGE
A.
All storage of petroleum or liquid petroleum products shall be in
conformance with the provisions of Title 38 M.R.S.A., § 541 et seq., as
amended, which, among other things, establishes a ten-year compliance
schedule for the discontinuance and removal of non-conforming
underground oil storage facilities and requires qualified personnel to oversee
the removal of certain underground facilities.
B.
Oil and chemical storage shall be in conformance with rules and regulations
adopted by the State of Maine applicable to the stored substance.
70 I Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-D5
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended. 26-Mar- 11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May 19
Amended· l l-Jul-20
Amended: 11 -May-24
Last Amended: 07 -Jun-25
C.
The applicant shall have the burden of proof that all provisions of the above
laws, rules and regulations have been met before the issuance of any
permits may take place.
6.24. ON-SITE CIRCULATION
A.
Vehicular circulation
The layout of the site shall provide for the safe movement of passenger,
senrice, and emergency vehicles through the site.
1.
Non-residential projects shall provide a clear route for delivery vehicles
with appropriate geometric design to allow turning and backing for all
vehicles, including tractor-trailers.
2.
Except for uses in the Commercial District which meet the Fire Hazard
Mitigation standards of this Article 6, clear routes of access shall be
provided and maintained for emergency vehicles to all portions of the
site and shall be posted with appropriate language.
3.
The layout and design of parking areas shall provide for safe and
convenient circulation of vehicles and prevent their backing out onto a
street.
4.
All streets and access ways shall be designed to harmonize with the
topographic and natural features of the site. The road network shall
provide for vehicular and pedestrian safety, all season emergency
access, snow storage, and delivery and collection senrices.
B.
Pedestrian circulation
The development plan shall provide for a system of pedestrian circulation
within the development. This system shall connect with existing sidewalks if
they exist in the vicinity of the project. The pedestrian network may be
located within the street right-of-way or outside of the right-of-way in open
space or recreation areas. The system shall be designed to link residential
units with recreational and commercial facilities, other common facilities,
school bus stops, and existing sidewalks in the neighborhood.
71 I Pa g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-0 I
Amended· 25-Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov JO
Amended: 26-Mar-l l
Amended: 01-Jun-!3
Amended· 23-Sept-13
Amended. l 1-May-19
Amended· ll-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
6. 25. POLLUTION LEVELS
Any pollutant introduced into soil on the site shall not exceed a concentration in
the ground water that is greater than the guideline established for it in the Safe
Drinking Water Standard, EPA Health Advisory, or NAS Health Advisory. Any
violation of this standard shall be cause to order the immediate cessation of the
use or activity responsible for the contamination. The land owner, contractor,
occupant, or any other person with authority over the land, structure, or activity
responsible for the contamination, shall be jointly responsible for the cost of all
remedial actions and damages resulting therefrom.
6.26. PRESERVATION AND ENHANCEMENT OF THE LANDSCAPE
The landscape shall be preserved in its natural state insofar as practicable by
minimizing tree removal and disturbance of soil, and by retaining existing
vegetation during construction. After construction is completed, landscaping
shall be completed that will define, soften or screen the appearance of off-street
parking areas, buildings and other structures from the public right of way and
abutting properties in order to minimize the encroachment of the proposed uses
on neighboring land uses. Environmentally sensitive areas such as wetlands,
steep slopes, flood plains, and unique natural features shall be maintained and
preserved to the maximum extent possible. Natural drainage areas shall be
preserved to the maximum extent possible.
6.27. RECREATIONAL VEHICLES
Recreational vehicles shall not be used as a permanent dwelling. Any
recreational vehicle used as a temporary dwelling must be stationed only in an
authorized campground, mobile home park or trailer park or as an accessory use
on the premises of a consenting private property owner for use only by members
of the property owner's family or social guests. In order to be considered as a
vehicle and not as a structure, the unit must be registered for operation on the
roads.
72 /Page
Zoning Ordmance -Adopted· 28-Mar-2000
Amended: 26-Mar-Ol
Amended; 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-10
Amended· 02-Nov- 10
Amended; 26-Mar- I 1
Amended: 0 I-Jun" l 3
Amended: 23-Sept-\3
Amended: 11-May-\9
Amended: ll-Ju)-20
Amended: 1 l-May-24
Last Amended: 07 -Jun-25
6.28. SIGNS
A.
General
It is the intent and purpose of this section to preserve the beauty of the
Town and the safety and well-being of its inhabitants while at the same time
allowing reasonable advertising and informational signs by regulating the
type, number, location and size of such signs.
B. Exempted signs
The following signs are exempt from the provisions of this Ordinance:
1.
Customary holiday decorations.
2.
Non-commercial signs not exceeding two (2) square feet in area (e.g.
name signs, no trespassing signs, etc.).
3.
Signs erected and maintained for public safety or welfare, or pursuant
to and in discharge of any educational or other governmental function
or required by law, ordinance or government regulation. [Am _ _!_:
4.
Historical information signs approved by the Selectboard.
5.
Real estate signs, provided such sign shall not exceed five (5) square
feet in area and shall be removed within one (1) week after the sale
closing or rental.
6.
Signs and banners announcing a specific event, such as a yard sale,
public event or charitable activity may be erected not more than a week
prior to the event and must be removed within forty-eight (48) hours of
the conclusion of the event, except as the Selectboard may extend the
announcement period on a case-by-case basis.
7.
Temporary political or opinion signs shall be no more than five (5)
square feet in area and shall be removed within five (5) days after the
referendum, election or meeting.
73 I P a g e
Zoning Ordinance -Adopted· 28-Mar-2000
Amended: 26-Mar-01
Amended, 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- I 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: JI-Jui-20
Amended: ! l-May-24
Last Amended: 07-Jun-25
8.
Open/ closed signs and signs announcing seasonal sales of produce,
which shall be no more than five (5) square feet in area.
9.
Signs identifying contractor(s) on a construction or landscaping site,
provided such sign(s} shall not exceed five (5) square feet in area and
shall be removed when the construction is complete. !~t,. I <.1,
C.
Two-sided signs
Each side of a two-sided sign may be as large as permitted for a one-sided
sign for the activity.
D.
Off-premise signs
Off-premise signs are allowed only as permitted by State law.
E.
On-premise signs
1.
No sign or notice board shall be erected adjacent to any public way in
such a manner as to obstruct clear and free vision and where by reason
of its position, shape, color, illumination or wording the sign may
interfere with, obstruct the view of, or be confused with any authorized
traffic sign, signal or device or otherwise constitute a hazard to
pedestrian or vehicular traffic. i_--\rr1 .l..:l
2.
Flashing, moving or animated signs are prohibited.
3.
No freestanding sign shall be displayed at a height greater than six (6)
feet from the ground level. No sign attached to a building shall be
displayed on or above the roof eaves of the building.
4.
Subject to Section 6.28.C above, no sign shall exceed the following
display surface area:
741 Page
a.
b.
c.
Home occupation (Residential): One (1) sign ofno more than six
(6) square feet.
Commercial District: Eighteen (18) square feet.
Commercial buildings in any other district: The maximum
display area of any sign shall not exceed eighteen (18) square feet.
Zomng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended· 25-Mar-02
Amended· 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- lO
Amended: 26-Mar-1 l
Amended· 01-Jun-\3
Amended; 23-Sept-13
Amended: ll-May-19
Amended: l l-Jul-20
Amended: l l-May-24
Last Amended. 07-Ju.n-25
The maximum total display area of all signs, including attached
and detached, on each commercial building (including principal
structures in lawful non-conforming commercial use} shall not
exceed twenty-seven (27) square feet for each business. Each
business shall display no more than two (2) signs on or adjacent
to each building ... Am.2'
d.
Community, municipal and quasi-municipal facilities: No
more than two (2) identification signs shall be allowed, not to
exceed a total of twelve (12) square feet in area, for each building
devoted to any of the following uses: church, academic building,
academic campus, health care facility, library, public recreation
area or other permitted community, municipal or quasi-municipal
use. Such signs shall be solely for the purpose of identifying the
institution, its services, and activities.
e.
All other uses in all other districts: Ten ( 10) square feet.
5.
Illuminated signs shall comply with the following restrictions:
a.
Illuminated signs shall use indirect lighting not to exceed 10,000
lumens.
b.
Signs with internal illumination are prohibited.
c.
Any illuminated sign located within a structure outside of the
Commercial District or above the ground floor in the Commercial
District shall not be visible outside of the structure.
6.
Notice boards may be approved by the permitting authority if the notice
board does not create a potential traffic or other safety hazard.
6.29. SITE CONDITIONS
A.
During construction, the site shall be maintained and left each day in a safe
and sanitary manner and any condition which could lead to personal injury
or property damage shall be immediately corrected by the developer upon an
order by the CEO or other authorized personnel. The developer shall make
provision for disposal of oil and grease from equipment and the site area
should be regularly treated to control dust from construction activity; and
B.
Developed areas shall be cleared of all stumps, litter, rubbish, brush, weeds,
dead and dying trees, roots and debris. Excess or scrap building materials
75 I Page
Z<lning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- 1 0
Amended: 26-Mar-l l
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11 May-19
Amended: 1 l-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
shall be removed or destroyed immediately upon the request of and to the
satisfaction of the CEO prior to issuing a Certificate of Occupancy.
6.30. SWIMMING POOLS AND SPAS
A.
Outdoor pools shall be enclosed by a barrier wall at least forty-eight (48)
inches in height. The barrier wall may be a stand- alone wall or fence or may
be in combination with a structural pool, spa or hot tub wall or a wall of an
adjacent building to form the barrier around the pool, spa or hot tub. f.'\m. l!
B.
Pool effluent, containing chemicals not found in or exceeding the level found
in the Town potable water, shall be discharged into the Town sanitary sewer
system or other approved disposal system. i,\m. i:
C.
Public pools and spas shall comply with the Maine Department of Health
and Human Services Rules Relating to Public Swimming Pools and Spas
(CMR 10-144, Chapter 202, as amended.) ·,\;:n. 1 ·
6.31. TIMBER HARVESTING
REPEALED - The Bureau of Forestry (Maine Forest Service) will administer the
regulation of all forestry activities within the municipality.
6.32. UTILITIES/ SEWAGE DISPOSAL/ WASTE DISPOSAL/ WATER SUPPLY
A.
Utilities
1.
Any above-ground utility installation shall be located so as to have a
hannonious relation to neighboring properties and the site.
2.
Underground utilities shall be installed prior to the installation of the
final gravel base of the road.
4. The size, type, and location of streetlights and utilities shall be shown on
the plan and approved by the Planning Board.
761 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended· 11 -Jul-20
Amended: l l-May-24
Last Amended· 07-Jun-25
D. Sewage disposal
No permit shall be issued for a project with subsurface sewage disposal
unless:
1.
There is an area of sufficient size of suitable soils, under the Maine
State Plumbing Code, to accommodate the proposed system.
2.
An acceptable plan to construct the absorption area is prepared in
accordance with the Maine State Plumbing Code.
3.
A Subsurface Wastewater Disposal System Permit has been issued by
the Local Plumbing Inspector (LPI). [:\m . .:?_]
C.
Waste disposal
The proposed development shall provide for adequate disposal of solid
wastes and hazardous wastes.
1.
All solid waste shall be disposed of at a licensed disposal facility having
adequate capacity to accept the project's wastes.
2.
All hazardous wastes shall be disposed of at a licensed hazardous
waste disposal facility and evidence of a contractual arrangement with
the facility shall be submitted.
D. Water supply
1.
The project shall be provided with a system of water supply that
provides each use with an adequate supply of water meeting the
standards of the State of Maine.
2.
For general projects as defined in Article 9, the applicant may be
required to constrnct ponds and dry hydrants to provide for adequate
water storage for firefighting purposes. An easement shall be granted to
the Town granting access to the dry hydrants where necessary. The
Planning Board may waive the requirement for fire ponds only upon the
submission of evidence that the soil types in the development will not
permit their construction, or that a nearby water supply is accepted by
771 Page
ZonmgOrdinance-Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: Ol-Jlm-13
Amended: 23-Sept- 13
Amended: \ 1-May-19
Amended: J J .Jul-20
Amended: ll-May-24
Last Amended: 07-Jun-25
the Fire Department as available and adequate for firefighting
purposes.
6.33. ACCESSORY DWELLING UNITS !Am, l '71 .-\m. llii
A. Square Footage / Utilities / Parking / Lot Size Requirements
1.
An accessory dwelling unit shall have no less than one hundred and
ninety (190) gross square feet (GSF) of floor area and no more than: one
thousand (1,000) gross square feet of floor area in the Village One (1)
and Village Two (2) Districts; eleven hundred (1100) GSF in the Village
Three (3) District and twelve hundred (1200) GSF in the Rural District.
No ADU shall consist of more than two (2) sleeping rooms, one (1) full
bathroom, one (1) half bathroom, one (1) kitchen/eating area and one
(1) living/sitting room. [.\m.15! _\m. i::>:
2. The accessory dwelling unit and primary residential structure will
be served by separate utility services. :,\rn.10.!
3. No additional off-street parking space is required for an accessory
dwelling unit. The To-wn of Castine Traffic Ordinance will govern on
street parking. 'A:n. I .'i' [-\1~1 l r,:
5. New construction of single-family dwelling with an accessory dwelling
unit or construction of an accessory dwelling unit at an existing single-
family dwelling requires a minimum lot size for a single-family dwelling
in the district in which it is built and shall meet all required setbacks
and other applicable dimensional requirements. [.-\rn. I ,'ii
6. New construction of an accessory dwelling unit(s) in the Castine Village I,
11, and III overlays (on-neck) require Utility Board technical review to
ensure Castine's sewer and water systems are adequate to meet the
increased sewer and water demand.!_\:·"· l-i_'
781Page
Zoning Ordinance
Adopted. 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar·02
Amended: 07"May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-lO
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 1 l-Jul-20
Amended· 11-May-24
Last Amended: 07-Jun-25
6.34 AFFORDABLE HOUSING DEVELOPMENTS .. -\m 1 :'i'
A. Standards
1. In all Districts where multifamily housing is allowed, an affordable
housing development shall be permitted to have a dwelling unit density
of at least 2-1/2 times the base density that is otherwise allowed in that
location, provided one of the following requirements are met: (1) the
proposed development is located in a Designated Gruwth Area; or (2) the
proposed development is being served by a public, special district or
other centrally managed water system and a public, special district or
other comparable sewer system. f_\mL'i!
2. Before granting final approval of an affordable housing development,
including but not limited to issuing an occupancy permit, the Town shall
require that the owner of the affordable housing development have
executed a restrictive covenant, recorded in the appropriate registry of
deeds, for the benefit of and enforceable by a party acceptable to the
municipality, to ensure that for at least 30 years after completion of
construction: :.--1.m. l ;i:
A. For rental housing, occupancy of all the units designated affordable
in the development will remain limited to households at or below 80%
of the local area median income at the time of initial occupancy; and
,,\;;,.15!
B. For owned housing, occupancy of all the units designated affordable
in the development will remain limited to households at or below
120% of the local area median income at the time of initial
occupancy. ,.-\m 1 s,
3. The owner of an affordable housing development shall provide written
verification to the Town that each unit of the housing development
791 Page
is connected to adequate water and wastewater services before the Town
may certify the development for occupancy. Written verification under
this subsection must include: _--\rn. L'i
A. If a housing unit is connected to a public, special district or other
comparable sewer system, proof of adequate service to support any
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amcnd€d: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: Q4 .. Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: Ol-Jun-13
Amended. 23-Sept-13
Amended. 11-May-19
Amended: ll-Jul-20
Amended: ll-May-24
Last Amended: 07 -.Jun-25
additional flow created by the unit and proof of payment for the
connection to the sewer system; [,<_\m 1,S_j
B. If a housing unit is connected to a septic system, proof of adequate
sewage disposal for subsurface wastewater. The septic system must
be verified as adequate by a local plumbing inspector. Plans for
subsurface wastewater disposal must be prepared by a licensed site
evaluator in accordance with subsurface wastewater disposal rules;
!_Am.ISi
C. If a housing unit is connected to a public, special district or other
centrally managed water system, proof of adequate service to support
any additional flow created by the unit, proof of payment for the
connection and the volume and supply of water required for the unit;
and ii~_m.15:
D. If a housing unit is connected to a well, proof of access to potable
water. Any tests of an existing well or proposed well must indicate
that the water supply is potable and acceptable for domestic use.
,_irn 15!
ARTICLE 7: SHORELAND STANDARDS [Am7._04-Apr-09; Am 10. 26-Mar-11;
Am.13 ll-May-19]
7 .1. AGRICULTURE
A.
All spreading of manure shall be accomplished in conformance with the
Manure Utilization Guidelines published by the Maine Department of
Agriculture on November 1, 2001, and the Nutrient Management Law (Title
7 M.R.S.A., § 4201-4209, as amended). ,:\m. (1J
B.
Manure shall not be stored or stockpiled within one hundred (100) feet,
horizontal distance of water bodies, tributary streams, or wetlands. Within
five (5) years of the effective date of this Ordinance all manure storage areas
within the shoreland zone must be constructed or modified such that the
facility produces no discharge of effluent or contaminated storm water.:-\m. f-):
80 IP age
7..omng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr·OS
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended· 11-Jul-20
Amended· l 1-May-24
Last Amended: 07-Jun-25
C.
Agricultural activities involving tillage of soil greater than forty thousand
(40,000) square feet in surface area within the shoreland zone shall require
a Soil and Water Conservation Plan to be filed with the Planning Board.
Non-conformance with the provisions of said plan shall be considered to be
a violation of this Ordinance. r.-\m.___(-._j
D.
There shall be no new tilling of soil within one hundred (100) feet, horizontal
distance, of the normal high-water line of a great pond classified GPA; within
seventy-five (75) feet, horizontal distance, from other water bodies and
coastal wetlands; nor within twenty-five (25) feet, horizontal distance, of
tributary streams, and freshwater wetlands. Operations in existence on the
effective date of this Ordinance and not in conformance with this provision
may be maintained.
E.
After the effective date of this Ordinance, newly established livestock grazing
areas shall not be permitted within one hundred (100) feet, horizontal
distance, of the normal high-water line of a great pond classified GPA; within
seventy-five (75) feet, horizontal distance of other water bodies and coastal
wetlands, nor; within twenty-five (25) feet, horiwntal distance, of tributary
streams, and freshwater wetlands. Livestock grazing associated with ongoing
farm activities, and which are not in conformance with the above setback
provisions may continue, provided that such grazing is conducted in
accordance with a conservation plan.
7.2. CLEARING OR REMOVAL OF VEGETATION FOR ACTMTIES OTHER THAN TIMBER
HARVESTING
A.
Within the Shoreland Overlay District zoned as a Resource Protection
Overlay District abutting a great pond, there shall be no cutting of
vegetation within the strip of land extending seventy-five (75) feet, horizontal
distance, inland from the normal high-water line, except for the removal of
safety hazards and 'With a permit from the Code Enforcement Officer.
Elsewhere, in any Resource Protection Overlay District the clearing of
vegetation shall be limited to that which is necessary for uses expressly
authorized in that District.
B.
Except in areas as described in Section 7.2.A above, and except to allow for
the development of permitted uses, \Vlthin a strip of land extending one
hundred (100) feet, horizontal distance, inland from the normal high-water
81 I Pa g e
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar 02
/\mended: 07-May 02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept- 13
Amended: l 1-May-19
Amended: ll-Ju]-20
Amended: I 1-May-24
Last Amended: 07-Jun-25
line of a great pond classified GPA or a river flowing to a great pond
classified GPA and seventy-five (75) feet, horizontal distance, from any other
water body, tributary stream, or the upland edge of a wetland, a buffer strip
of vegetation shall be preserved as follows:
1.
There shall be no cleared opening greater than two hundred fifty (250)
square feet in the forest canopy or other woody vegetation as measured
from the outer limits of the tree or shrub crown. However, a footpath
not to exceed six (6) feet in width as measured between tree trunks
and/ or shrub stems is permitted provided that a cleared line of sight to
the water through the buffer strip is not created. r2,._11LJ2i
2.
Selective cutting of trees within the buffer strip is permitted provided
that a well distributed stand of trees and other natural vegetation is
maintained. For the purposes of this section a "well-distributed stand
of trees" adjacent to a great pond classified GPA or a river or stream
flowing to a great pond classified GPA, shall be defined as maintaining
a rating score of twelve (12) or more in any twenty-five (25) foot by
twenty-five (25) foot square (625 square feet) area as determined by the
following rating system based upon tree diameter at four and one half
(4 %) feet above ground level. Adjacent to ·other water bodies, tributary
streams, and wetlands, "well-distributed stand of trees" shall be
defined as maintaining a rating score of eight (8) or more in any twenty-
five (25) foot by twenty-five {25) foot square (625 square feet).
82 JP age
For the purposes of this Section "other natural vegetation" is defined as
retaining existing vegetation under three (3) feet in height and other
ground cover and retaining at least three (3) saplings less than two (2)
inches in diameter at four and one half (4 %) feet above ground level for
each twenty-five (25) foot by twenty-five (25) foot rectangle area. If three
(3) saplings do not exist, no woody stems less than two (2) inches in
diameter can be removed until three (3) saplings have been recruited
into the plot. /\:11 __0] :,",_r_n:...l!
a.
Two (2) to four (4) inches= one (1) point.
b.
Greater than four (4) inches to twelve (12) inches= two (2) points.
c.
Greater than twelve (12) inches= four (4) points.
d.
Notwithstanding the above provisions, no more than forty percent
{40%) of the total volume of trees four (4) inches or more in
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr -09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26"Mar- l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended· ll-May-19
Amended: 1 I-Jul-20
Amended: 1 l-May-24
Last Amended. 07-Jun-25
diameter, measured at four and one-half (4 %) feet above ground
level, may be removed in any ten (10) year period.
e.
Pruning of tree branches is permitted on the bottom one-third (1/3)
of the tree.
3.
In order to protect water quality and wildlife habitat, existing vegetation
under three (3) feet in height and other ground cover, including leaf
litter and the forest duff layer, shall not be cut, covered, or removed,
except to provide for a footpath.
4.
In order to maintain a buffer strip of vegetation, when the removal of
storm-damaged, diseased, unsafe, or dead trees results in the creation
of cleared openings, these openings shall be replanted with native tree
species unless existing new tree growth is present.
5,
The provisions of Section 7.2.B shall not apply to those portions of
public recreational facilities adjacent to public swimming areas.
Cleared areas, however, shall be limited to the minimum area
necessary.
C.
At distances greater than one hundred (100) feet, horizontal distance, from a
great pond classified GPA or a river flowing to a great pond classified GPA,
and seventy-five (75) feet, horizontal distance, from the normal high-water
line of any other water body, tributary stream, or the upland edge of a
wetland, there shall be allowed on any lot, in any ten (10) year period,
selective cutting of not more than forty (40) percent of the volume of trees
four (4) inches or more in diameter, measured 4 1/2 feet above ground level.
Tree removal in conjunction with the development of permitted uses shall be
included in the forty (40) percent calculation. For the purposes of these
standards volume may be considered to be equivalent to basal area.
In no event shall cleared openings for any purpose, including but not limited
to, principal and accessory structures, driveways, lawns and sewage
disposal areas, exceed in the aggregate, 25% of the lot area within the
shoreland zone or ten thousand (10,000) square feet, whichever is greater,
including land previously cleared. This provision shall not apply to the
Commercial and Maritime Activity Overlay Districts.
83 IP age
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended. 25-Mar 02
Amended: 07-May 02
Amendeci". 04-Apr-05
Amended: 26-Mar-07
Amended: 24 Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-10
Amended. 02-Nov-10
Amended: 26-Mar-l l
Amended: Ol-Jun-13
Amended· 23-Sept- 13
Amended: \ l-May-19
Amended: ll-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
D.
Cleared openings legally in existence on the effective date of this Ordinance
may be maintained, but shall not be enlarged, except as permitted by this
Ordinance.
E.
Fields which have reverted to primarily shrubs, trees, or other woody
vegetation shall be regulated under the provisions of this section.
7.3. EROSION AND SEDIMENTATION CONTROL
A.
All activities which involve filling, grading, excavation or other similar
activities which result in unstabilized soil conditions and which require a
permit under this Ordinance shall require a written soil erosion and
sedimentation control plan. The plan shall be submitted to the respective
permitting authority for approval, as required, and shall include, where
applicable, provisions for:
1.
Mulching and revegetation of disturbed soil.
2.
Temporary runoff control features such as hay bales, silt fencing or
diversion ditches.
3.
Permanent stabilization structures such as retaining walls or riprap.
B.
In order to create the least potential for erosion, development shall be
designed to fit with the topography and soils of the site. Areas of steep
slopes where high cuts and fills may be required shall be avoided wherever
possible, and natural contours shall be followed as closely as possible.
C.
Erosion and sedimentation control measures shall apply to all aspects of the
proposed project involving land disturbance, and shall be in operation
during all stages of the activity. The amount of exposed soil at every phase of
construction shall be minimized to reduce the potential for erosion.
D.
Any exposed ground area shall be temporarily or permanently stabilized
within one ( 1) week from the time it was last actively worked, by use of
riprap, sod, seed, and mulch, or other effective measures. In all cases
permanent stabilization shall occur within nine (9) months of the initial date
of exposure. In addition:
84[Page
?.<ming Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25"Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar·08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: OJ-Jun-13
Amended; 23-Sept- 13
Amended: 1 J-May-19
Amended: 11-Jul-20
Amended: 11-May 24
Last Amended: 0'/-Jun-25
1.
Where mulch is used, it shall be applied at a rate of at least one (I) bale
per five hundred (500} square feet and shall be maintained until
vegetation is adequately established.
2.
Anchoring the mulch with netting, peg, and twine or other suitable
method may be required to maintain the mulch cover.
3.
Additional measures shall be taken where necessary in order to avoid
siltation into the water. Such measures may include the use of staked
hay bales and/or silt fences.
E.
Natural and man-made drainage ways and drainage outlets shall be
protected from erosion from water flowing through them. Drainage ways
shall be designed and constructed in order to carry water from a twenty-five
(25) yem storm or greater, and shall be stabilized with vegetation or lined
with rip-rap.
7.4. EsSENTIAL SERVICES
A.
Where feasible, the installation of essential services shall be limited to
existing public ways and existing service corridors.
B.
The installation of essential services, other than road-side distribution lines,
is not allowed in a Resource Protection or Stream Protection District, except
to provide senrices to a permitted use \vi.thin said district, or except where
the applicant demonstrates that no reasonable alternative exists. Where
allowed, such structures and facilities shall be located so as to minimize any
adverse impacts on surrounding uses and resources, including visual
impacts.
C.
Damaged or destroyed public utility transmission and distribution lines,
towers and related equipment may be replaced or reconstructed without a
permit.
7 .5. INDMDUAL, PRIVATE CAMPSITES
Individual, private campsites not associated with campgrounds are permitted
provided the following conditions are met:
85!Page
Zoning Ordmance -Adopted: 28 Mar-2000
Amended· 26-Mar-01
Amended: 2S"Mar-02
Amended: 07-May-02
Amended. 04-Apr-OS
Amended: 26-Mar-07
Amended: ?A-Mar-08
Amended: 04-Apr 09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: O 1-Jun-13
Amended: 23-Sept·l3
Amended. I 1-May-19
Amended: J l-Jul-20
Amended: l l-May-24
last Amended: 07-Jun-25
A.
One campsite per lot existing on the effective date of this Ordinance, or per
thirty thousand (30,000) square feet of lot area within the Shoreland Overlay
District, whichever is less, may be permitted.
B.
Campsite placement on any lot, including the area intended for a
recreational vehicle or tent platform, shall be set back one hundred (100)
feet from the normal high-water line of any great pond classified GPA, and
seventy-five {75) feet from the normal high-water line of all other water
bodies, tributary streams and wetlands. lAn\'----"i".1
C.
Only one recreational vehicle shall be allowed on a campsite. The
recreational vehicle shall not be located on any type of permanent
foundation except for a gravel pad, and no structure except a canopy shall
be attached to a recreational vehicle.
D.
The clearing of vegetation for the siting of the recreational vehicle, tent of
similar shelter in a Resource Protection District shall be limited to one
thousand (1,000) square feet.
E.
A written sewage disposal plan describing the proposed method and location
of sewage disposal shall be required for each campsite and shall be approved
by the LPI prior to issuance of a permit under this Ordinance. Where
disposal is off-site, a written authorization from the receiving facility or land
owner is required as part of the application.
F.
When a recreational vehicle, tent or similar shelter is placed on-site for more
than one hundred and twenty (120) days per year, all requirements for
residential structures shall be met, including the installation of a subsurface
sewage disposal system in compliance with all State regulations, unless the
site is served by a public sewer. Subsurface systems are permitted only in
districts where a residential structure would be permitted.
7.6.
MINERAL EXPLORATION AND EXTRACTION
Mineral exploration to determine the nature or extent of mineral resources shall
be accomplished by hand sampling, test boring, or other methods which create
minimal disturbance of less than one hundred ( 100) square feet of ground
surface. A permit from the Code Enforcement Officer shall be required for mineral
exploration which exceeds the above limitation. All excavations, including test
86jPage
Zoning Ordinance -- Adopted: 28-Mar-2000
Amended: 26-Mar·Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26·Mar-07
Amended: 24- Mar-08
Amended· 04-Apr-09
Amended: 27-Mar- \O
Amended: 02-Nov- 10
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l -May-19
Amended: 1 l-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
pits and holes shall be immediately capped, filled, or secured by other equally
effective measures, so as to restore disturbed areas and to protect the public
health and safety. Mineral extraction may be permitted under the following
conditions:
A.
A reclamation plan shall be filed with, and approved by the Planning Board
before a permit is granted. Such plan shall describe, in detail, procedures to
be undertaken to fulfill the requirements of Section 7.6.C below.
B.
Unless authorized pursuant to the Natural Resources Protection Act, Title
38 M.R.S.A. § 480-C, as amended, no part of any extraction operation,
including drainage and runoff control features shall be permitted within one
hundred (100) feet of the normal high-water line of a great pond or a river
flowing to a great pond, and within seventy-five (75) feet of the normal high-
water line of any other water body, tributary stream, or the upland edge of a
wetland. Extraction operations shall not be permitted within seventy-five
(75) feet of any property line, without written permission of the owner of
such adjacent property.
C.
Within twelve (12) months following the completion of extraction operations
at any extraction site, which operations shall be deemed complete when less
than one hundred ( 100) cubic yards of materials are removed in any
consecutive twelve (12) month period, ground levels and grades shall be
established in accordance with the following;
1.
All debris, stumps, and similar material shall be removed for disposal
in an approved location, or shall be buried on-site. Only materials
generated on-site may be buried or covered on-site.
2.
The final graded slope shall be two to one (2:1) slope or flatter.
3.
Top soil or loam shall be retained to cover all disturbed land areas,
which shall be reseeded and stabilized with vegetation native to the
area. Additional topsoil or loam shall be obtained from off-site sources
if necessary to complete the stabilization project.
4.
In keeping with the purposes of this Ordinance, the Planning Board
may impose such conditions as are necessary to minimize the adverse
impacts associated with mineral extraction operation on surrounding
87 I P a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-0 I
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-!O
Amended· 26-Mar-1 l
Amended: 0 I -Jun- 13
Amended: 23-Sept-13
Amended: 11 May- (9
Amended: l 1-Jul-20
Amended: 11-May-24
l~"tst Am.ended·. 07-Jun-25
uses and resources, including but not limited to any reasonable form of
performance guarantee such as a performance bond.
7.7. PARKING AREAS
A.
Parking areas shall meet the shoreline and tributary stream setback
requirements for structures in the district in which such areas are located,
except that in the Commercial and Maritime Activity Overlay Districts the
parking setback shall be at least twenty-five (25) feet from the normal high-
water line or the upland edge of a wetland. The setback requirement for
parking areas serving public boat launching facilities, in districts other than
the Commercial and Maritime Activity Overlay Districts may be reduced to
no less than fifty (50) feet from the normal high-water line or upland edge of
a wetland if the Planning Board finds that no reasonable alternative exists.
B.
Parking areas shall be adequately sized for the proposed use and shall be
designed to prevent storm.water runoff from flowing directly into a water
body, tributary stream or wetland and where feasible, to retain all runoff on
site.
C.
In determining the appropriate size of proposed parking facilities, the
following shall apply:
1.
A typical space shall be ten (10) feet wide by eighteen (18) feet long,
except that parking spaces for a vehicle and trailer shall be forty (40)
feet long.
2.
Internal travel aisles shall be approximately twenty (20) feet wide.
7 .8. PIERS, DOCKS, WHARVES, BRIDGES AND OTHER STRUCTURES AND USES EXTENDING
OVER OR BELOW THE NORMAL HIGH-WATER LINE OF A WATER BODY OR WITHIN A
WETLAND
A.
Access from shore shall be developed on soils appropriate for such use and
constructed so as to control erosion.
B.
The location shall not interfere with existing developed or natural beach
areas.
881Page
Zoning Ordinance - Adopted: 28"Mar-2000
Amended· 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24- Mar-08
Amended: 04-A.pr-09
Amended: 27-Mar-10
Amended: 02-Nov- \0
Amended: 26-Mar-1 !
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended, l 1-Jul-20
Amended: l l-May-24
Last Amended: 07 -Jun-25
C.
The facility shall be located so as to minimize adverse effects on fisheries
and navigation.
D.
The facility shall be no larger in dimension than necessary to carry on the
activity and be consistent with existing conditions, uses and the character of
the area. Except in the Commercial and Maritime Activity Overlay Districts,
structures built on, over or abutting a pier, wharf, dock or other structure
extending below the normal high-water line of a water body or within a
wetland shall not exceed forty (40) square feet in floor area. A temporary
pier, dock or wharf in non-tidal waters shall not be wider than six (6) feet for
non-commercial uses.
E.
No new structure shall be built on, over or abutting a pier, wharf, dock or
other structure extending below the normal high-water line of a water body
or within a wetland unless the structure requires direct access to the water
as an operational necessity.
F.
No existing structure built on, over or abutting a pier, wharf, dock or other
structure extending below the normal high-water line of a water body or
within a wetland shall be converted to residential dwellings in any district.
G.
Structures built on, over or abutting a pier, wharf, dock or other structure
extending below the normal high-water line of a water body or -within a
wetland shall be subject to Site Plan Review. New permanent piers and
docks on non-tidal waters shall not be permitted unless it is clearly
demonstrated to the Planning Board that a temporary pier or dock is not
feasible, and a permit has been obtained from the Department of
Environmental Protection, pursuant to the Natural Resources Protection
Act. 1 .-\n_1_,_.') i
H.
Except in the Commercial and Maritime Activity Overlay Districts,
structures built on, over or abutting a pier, wharf, dock or other structure
extending below the normal high-water line of a water body or -within a
wetland shall not exceed eight (8) feet in height above the pier, wharf, dock
or other structure.
I.
If the project requires any State or Federal approval, that approval must be
obtained prior to applying to the Town for a permit and included as part of
the application package.
89 IP age
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: OI-Jun-13
Amended: 23-Sept-13
Amended· Jl-May-19
Amended. J l-Jul-20
Amended: ! 1-May-24
Last Amended: 07-Jun-25
7.9. PRINCIPAL AND ACCESSORY STRUCTURES
A.
All new principal and accessory structures shall be set back at least one
hundred ( 100) feet from the normal high-water line of any great pond, and
seventy-five (75) feet from the normal high-water line of any other water
body, tributary stream or the upland edge of any wetland. The water body or
wetland setback provision shall not apply to structures which require direct
access to the water as an operational necessity, such as piers, docks and
retaining walls, or to other functionally water-dependent uses.
For principal structures, water and wetland setback measurements shall be
taken from the top of a coastal bluff that has been identified on Coastal Bluff
maps as being "highly unstable" or ''unstable" by the Maine Geological
Survey pursuant to its "Classification of Coastal Bluffs" and published on
the most recent Coastal Bluff map. If the applicant and the permitting
authority are in disagreement as to the specific location of a "highly
unstable" or "unstable" bluff, or where the top of the bluff is located, the
applicant may at his or her expense, employ a Maine Registered Professional
Engineer, a Maine Certified Soil Scientist, a Maine State Geologist, or other
qualified individual to make a determination. If agreement is still not
reached, the applicant may appeal the matter to the Zoning Board of
Appeals. i.:i..m. 1-;/ ,'_·\m._7'
B.
The lowest floor elevation or openings of all buildings and structures,
including basements, shall be elevated at least one foot above the elevation
of the 100 year flood, the flood of record, or in the absence of these, the flood
as defined by soil types identified as recent flood-plain soils. In those
municipalities that participate in the National Flood Insurance Program and
have adopted the April 2005 version, or later version, of the Floodplain
Management Ordinance, accessory structures may be placed in accordance
with the standards of that ordinance and need not meet the elevation
requirements of this Section.
C.
The total area of all structures, parking lots and other non-vegetated
surfaces, within the Shoreland Zone shall not exceed twenty percent (20%)
of the lot or a portion thereof, located within the Shoreland Zone, including
land area previously developed except in the Commercial and Maritime
Activity Overlay Districts, where lot coverage shall not exceed sixty-five
(65%) percent.
90IPage
Zoning Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended. 07-May-02
Amended. 04-Apr-05
Amended, 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended· 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l 1
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May- 19
Amended: l l"Ju\-20
Amended: l l-May 24
Last Amended: 07-Jun-25
D.
Notwithstanding the requirements stated above, stairways or similar
structures may be allowed with a permit from the Code Enforcement Officer,
to provide shoreline access in areas of steep slopes or unstable soils;
provided that the structure is limited to a maximum of four (4) feet in width;
that the structure does not extend below or over the normal high-water line
of a water body or upland edge of a wetland, (unless permitted by the Board
of Environmental Protection pursuant to the Natural Resources Protection
Act, Title 38 M.R.S.A., § 480-C, as amended}; and that the applicant
demonstrates that no reasonable access alternative exists on the property.
E.
A public utility, water district, sanitary district or any utility company of any
kind may not install services to any new structure located in the shoreland
zone unless written authorization attesting to the validity and currency of all
local permits required under this or any previous Ordinance has been
issued by the appropriate municipal officials or other written arrangements
have been made between the municipal officials and the utility.
7.10. ROADS AND DRIVEWAYS
The following standards shall apply to the construction of roads and/or
driveways and drainage systems, culverts, and other related features.
A.
Roads and driveways shall be set back at least one-hundred (100) feet,
horizontal distance, from the normal high-water line of a great pond
classified GPA or a river that flows to a great pond classified GPA, and
seventy-five (75) feet, horizontal distance from the normal high-water line of
other water bodies, tributary streams, or the upland edge of a wetland
unless no reasonable alternative exists as determined by the Planning
Board. Ifno other reasonable alternative exists, the road and/or driveway
setback requirement shall be no less than fifty (50) feet, horizontal distance,
upon clear showing by the applicant that appropriate techniques will be
used to prevent sedimentation of the water body, tributary stream, or
wetland. Such techniques may include, but are not limited to, the
installation of settling basins, and/or the effective use of additional ditch
relief culverts and turnouts placed so as to avoid sedimentation of the water
body, tributary stream, or wetland.
91 I Pa g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25 Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 0 1-Jun-13
Amended: 23-Sept-13
Amended: l 1-May-19
Amended: 1 J-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
On slopes of greater than twenty (20) percent the road and/or driveway
setback shall be increased by ten ( 10) feet, horizontal distance, for each five
(5) percent increase in slope above twenty (20) percent.
This Section does not apply to approaches to water crossings or to roads or
driveways that provide access to permitted structures and facilities located
nearer to the shoreline or tributary stream due to an operational necessity,
excluding temporary docks for recreational uses. Roads and driveways
providing access to permitted structures within the setback area shall
comply fully with the requirements of this Section except for that portion of
the road or driveway necessary for direct access to the structure.
B.
Existing public roads may be expanded within the legal road right-of-way
regardless of its setback from a water body, tributary stream or wetland.
C.
New roads and driveways are prohibited in a Resource Protection District
(RP) except that the Planning Board may grant a permit to construct a road
or driveway to provide access to permitted uses within the district. A road
or driveway may also be approved by the Planning Board in a Resource
Protection District, upon a finding that no reasonable alternative route or
location is available outside the district. When a road or driveway is
permitted Resource Protection District, the road or driveway shall be set
back as far as practicable from the normal high-water line of a water body,
tributary stream, or upland edge of a wetland.
D.
Road and driveway banks shall be no steeper than a slope of two (2)
horizontal to one (1) vertical, and shall be graded and stabilized in
accordance with the provisions for erosion and sedimentation control
contained in Article 6 of this Ordinance.
E.
Road and driveway grades shall be no greater than ten percent (10%) except
for short segments of less than two hundred (200) feet.
F.
In order to prevent road and driveway surface drainage from directly
entering water bodies, tributary streams or wetlands, roads and driveway
shall be designed, constructed, and maintained to empty onto an
unscari.fied buffer strip at least fifty (50) feet plus two times the average
slope, in width between the outflow point of the ditch or culvert and the
normal high-water line of a water body, tributary stream, or upland edge of
92 IP age
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- ll
Amended: OJ-Jun-13
Amended: 23-Sept- 13
Amended: 1 l-May-19
Amended. 11-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
a wetland. Surface drainage which is directed to an unscarified buffer strip
shall be diffused or spread out to promote infiltration of the runoff and to
minimize channelized flow of the drainage through the buff er strip.
G.
Ditch relief (cross drainage) culverts, drainage dips and water turnouts shall
be installed in a manner effective in directing drainage onto unscarified
buffer strips before the flow gains sufficient volume or head to erode the
road, driveway or ditch. To accomplish this, the following shall apply:
1.
Ditch relief culverts, drainage dips and associated water turnouts shall
be spaced along the road or driveway at intervals no greater than
i di t d . th £ 11
.
t bl
n ca e 1n
e o owmg a e:
Grade (percent)
Spacing (feet)
0-2
250
3-5
200-135
6-10
100-80
11-15
80-60
16-20
60-45
21+
40
2.
Drainage dips may be used in place of ditch relief culverts only where
the grade is ten percent ( 10%) or less.
3.
On sections having slopes greater than ten percent (10%), ditch relief
culverts shall be placed at approximately a thirty (30°) degree angle
down slope from a line perpendicular to the centerline of the road or
driveway.
4.
Ditch relief culverts shall be sufficiently sized and properly installed in
order to allow for effective functioning and their inlet and outlet ends
shall be stabilized with appropriate materials.
H.
Ditches, culverts, bridges, dips, water turnouts and other storm water runoff
control installations associated with roads shall be maintained on a regular
basis to assure effective functioning.
93 IP age
Zoning Ordinance - Adopted: '28-Mar-2000
Amended: 26-Mar-0l
Amended; 25-Mar-02
Amended; 07-May·02
Amended: 04-Apr-05
Amended: 26.Mar·0?
Amended: 24-Mar-08
Amended; 04-Apr-09
Amended: '27-Mar· 10
Amended: 02-Nov- JO
Amended; 26-Mar· I 1
Amended: QJ.Jun-13
Amended: 23-Sept- 13
Amended: l l -May-19
Amended: l l-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun·25
7 .11. SEPTIC WASTE DISPOSAL
All subsurface sewage disposal systems shall be installed in conformance with
the State of Maine Subsurface Wastewater Disposal Rules, and the following: a)
clearing or removal of woody vegetation necessary to site a new system and any
associated fill extensions, shall not extend closer than seventy-five (75) feet,
horizontal distance, from the normal high-water line of a water body or the
upland edge of a wetland and b) a holding tank is not allowed for a first-time
residential use in the Shoreland Zone.
7.12. SOILS
All land uses shall be located on soils in or upon which the proposed uses or
structures can be established or maintained without causing adverse
environmental impacts, including severe erosion, mass soil movement, improper
drainage, and water pollution, whether during or after construction. Proposed
uses requiring subsurface waste disposal, commercial or industrial development
and other similar intensive land uses shall require a soils report based on an on-
site investigation and be prepared by state-certified professionals. Certified
persons may include Maine Certified Soil Scientists, Maine Registered
Professional Engineers, Maine State Certified Geologists and other persons who
have training and experience in the recognition and evaluation of soil properties.
The report shall be based upon the analysis of the characteristics of the soil and
surrounding land and water areas, maximum ground water elevation, presence of
ledge, drainage conditions, and other pertinent data which the evaluator deems
appropriate. The soils report shall include recommendations for a proposed use
to counteract soil limitations where they exist.
7.13. STORMWATERRUNOFF
A.
All new construction and development shall be designed to minimize storm
water runoff from the site in excess of the natural pre-development
conditions. Where possible, existing natural runoff control features, such as
berms, swales, terraces, and wooded areas shall be retained in order to
reduce runoff and encourage infiltration of storm waters.
B.
Storm water runoff control systems shall be maintained as necessary to
ensure proper functioning.
94\Page
Zoning Or<\inance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended, 04-Apr-05
Amended, 26-Mar-07
Amended· 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-10
Amended: 02-Nov-10
Amended: 26- Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May- 19
Amended: 1 l-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
7.14. TIMBER HARVESTING
REPEALED -The Bureau of Forestry (Maine Forest Service) will administer the
regulation of all forestry activities within the municipality.
7.15. WATER QUALITY
No activity shall deposit on or into the ground or discharge to the waters of the
State, any pollutant that, by itself or in combination with other activities or
substances will impair designated uses or the water classification of the water
body tributary stream or wetland.
95jPage
Zoning Ordinance -Adopted: 28-Ma,--2000
Amended: 26-Mar-01
Amended: "25-Mar-02
Amended: 07-May-02
Amended: 04"Apr-05
Amended. 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended· 27-Mar-10
Amended· 02-Nov-10
Amended: 26-Mar-l 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: I l-May-19
Amended: 11-Jul-20
Amended: ll-May-24
Last Amended· 07-Jun"25
ARTICLE 8: CODE ENFORCEMENT OFFICER PERMITS
!Aml. 26-Mar-0l~m2_,_25-Mar-02: Am3, 07-M~A}2_;_Am5,_26-Mar-07;__Am6_,___24-Mar-0&_;_
Am 10. 26-Mar-11; Am.16~7-Jun-25J
8.1. CODE ENFORCEMENT OFFICER PERMIT REQUIRED
A permit from the Code Enforcement Officer {CEO) shall be required before
beginning or undertaking any of the following activities:
A.
Building permit
1.
New construction of buildings and structures unless the construction
is designated in the Land Use Table as not requiring a pem1it. f2_\IL.__0_j
2.
Alteration of existing buildings, structures, or land, or parts thereof,
including but not limited to: · Arn_,__ii~;
a.
Interior renovations for change in use.
b.
Interior renovations which change the structure design. ;:~m.;';ii
i_:\m. loj
c.
Interior renovations exceeding 150 square feet in area or ten
thousand dollars ($10,000) in total project cost. :.'.\m, __ \(11
d.
Finishing an unfinished room or space. 1,im. J.'
e.
Enclosing of open frame porches and decks.
f.
Construction of porches and decks.
g.
Ground or roof mounted installations of solar power array .. i_'\ir._,_1,2
h.
Any activity, not otherwise requiring Site Plan Review by this
Ordinance, requiring a permit under the Natural Resources
Protection Act (NRPA), Title 38 M.R.S.A., § 480-A et seq., including
all Permit by Rule (PER) activities described in CMR 06-096,
Chapter 305, as amended. 1,\n:!_J,
3.
Creation or expansion of roads, driveways or walkways, parking
areas, retaining walls and patios. :iw. l_i ,-\m.i0.;'
4.
The replacement of existing road culverts in the Shoreland Overlay
District, unless the replacement culvert is: .\n_:,.L
96 I P a g e
Zonmg Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended: 04-Apr·OCJ
Amended. 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l-May-19
Amended: 1 l-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
a.
Not more than twenty-five percent (25%) longer than the culvert
being replaced.
b.
Not longer than seventy-five (75) feet; provided that adequate
erosion control measures are taken to prevent sedimentation of
the water, and that the crossing does not block fish passage in the
water course.
5.
The erection, hanging, placement or alteration of a sign or sign
structure.
6.
Stairways or similar structures to provide shoreline access in areas of
steep slopes or unstable soils, in compliance with Section 7.8.D.,
above. ;c}ju.,_\
B.
Moving or demolition permit
Relocation of any structure onto or about a lot, or the demolition of any
structure. If the relocation or demolition is designated in the Land Use
Table as requiring Site Plan Approval from the Planning Board this approval
must be granted before the Code Enforcement Officer can issue a permit.
[.\m 'J,.
C.
Change of use permit
The change in the use of the premises from one land use activity to another,
or the creation of an additional use on the premises, unless the new use is
designated in the Land Use Table as requiring Site Plan Approval from the
Planning Board or as not requiring a permit. If the new use is designated in
the land use table as requiring Site Plan Approval from the Planning Board,
this approval must be granted before the Code Enforcement Officer can
issue a permit.
D.
Activities listed in the Land Use Table
Any activity listed in Article 5 of this Ordinance as requiring a permit from
the CEO. No permit may be issued under this section for an activity which is
part of a site or project that requires Site Plan Approval from the Planning
Board, except as provided in Section 8.1.E, below. · -\,1I_J_; A1r_1_,_,\
971 Page
Zoning Ordinance - Adopted. 28-Mar-2000
Amended: 26 Mar-01
Amended: 25--Mar-02
Amended. 07--May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24--Mar-08
Amended: 04 Apr-09
Amended. 27--Mar-10
Amended. 02-Nov-10
Amended: 26-Mar- l l
Amended: O!-Jun-13
Amended: 23-Sept--13
Amended: ll-May 19
Amended. ] 1-Jul-20
Amended: I l-May-24
Last Amended: 07-Jun-25
E.
Approved Site Plan activities
Any activity approved by the Planning Board under the Site Plan Review
provisions of Article 9 of this Ordinance.
F.
Emergency Permit
Nothing in this Ordinance shall prevent the strengthening or restoration to
safe condition of any part of any building or structure declared to be unsafe
by the CEO. The CEO may issue an emergency permit to mitigate or correct
the unsafe condition, which shall thereafter be attached to any necessary
application to the Planning Board.
G.
Referral to Planning Board
The Code Enforcement Officer {CEO) may refer any application for an
activity, normally requiring only a permit from the CEO under Section 8.1
above, to the Planning Board for Site Plan Approval under Article 9 of this
Ordinance. Any application so referred shall be classified as a Miscellaneous
Project under Section 9.4. 1.\m 25.:_
8.2. PROCEDURE
A.
Application
All applications for a CEO permit shall be submitted in writing to the CEO
on forms provided for the purpose, together with such fees as required in
Article 11 of this Ordinance.
B.
True and Correct Information
All information contained in and attached to a permit application shall be
true and correct. Any false information will invalidate a permit and stop all
work or use authorized by the permit. j.rn._u
C.
Application Requirements
All applications for a CEO permit shall be accompanied by a plan, accurately
drawn to scale or showing actual dimensions or distances, and showing:
981Page
Zomng Ordinance - Adopted; 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended; 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr -09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l 1
Amended: O\-Jun-13
Amended: 23-Sept-13
Amended· 11-May-\9
Amended: 11-Jul-20
Amended: 11-May 24
last Amended: 07-Jun-25
1.
The actual shape and dimensions of the lot for which a permit is
sought.
2.
The location and size of all buildings, structures, and other significant
features currently existing on the lot, as well as all water bodies,
tributary streams and wetlands within two hundred fifty (250) feet of
the property boundaries.
3.
The location of new buildings, structures or portions thereof to be
constructed.
4.
The existing and intended use of each building or structure.
5.
Where applicable, the location of soils test pits, subsurface sewage
disposal system, parking lots and driveways, signs, buffer strips and
private wells.
6.
If the property is not served by a public sewer, a valid plumbing permit
including the site evaluation approved by the Local Plumbing Inspector,
shall be submitted whenever the nature of the proposed structure or
use would require the installation of a subsurface sewage disposal
system.
7.
Such other information as may be reasonably required by the CEO to
provide for the administration and enforcement of this Ordinance.
D.
To whom issued
No permit shall be issued except to the owner of record or his authorized
agent. Written proof of authorization shall be required.
E.
Compliance with Land Use Standards
All activities undertaken pursuant to a permit issued under this Section
shall comply with all applicable standards set forth in Articles 6 and 7 of
this Ordinance.
991 Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-0!
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-!0
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended·. Ol-Jun-13
Amended: 23-Sept-13
Amended· 11-May-19
Amended: 11-Jul-?,0
Amended: ll-May-24
Last Amended: 07-Jun-25
1.
A public utility, water district, sanitary district or any utility company
of any kind may not install services to any new structure located in the
Shoreland Overlay District unless written authorization attesting to the
validity and currency of all local permits required under this or any
previous Ordinance has been issued by the Code Enforcement Officer.
F.
Notification of Abutters
Within three (3) business days of receiving an application, the CEO shall
notify abutting property owners by first class mail, of all permit applications
for activities and uses not requiring Site Plan Review by the Planning Board
except interior remodeling. This notice shall describe the proposed activity
and its location, by street address and tax map and lot number. Notice is to
be sent to the person to whom property tax bills are sent at the address
shown on the Town's tax card for the property.
G.
Deadline for decision
The CEO may, within 10 days of receiving an application, and shall, within
thirty (30) days of receipt of an application:
-
Issue the permit with such terms and conditions as the CEO
considers advisable to ensure that the proposed construction and
uses meet the provisions of the Ordinance.
-
Refer the applicant to the Planning Board for Site Plan Review.
-
Deny the application.
All decisions of the CEO shall be in writing. Failure of the CEO to act within
thirty {30) days shall not constitute approval of the application. 1~m~.'
H.
Copies
One (1) copy of the application, with the permit or other written decision of
the CEO, shall be returned to the applicant, and one (1) copy, with a copy of
the permit or written decision, shall be retained by the CEO as a permanent
public record.
I.
Posting
1.
The CEO shall post each week a list of all building permits issued
within thirty (30) days of the posting. Such list shall include the permit
100 [ P a g e
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr -09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: QJ.Jun-13
Amended: 23-Sept- \3
Amended: l !-May-19
Amended: 11-Jul-20
Amended. 1 l-May-24
last Amended. 07-Jun-25
number, date of issue, name of the property owner of record, and
location of the project. The list shall be posted in a conspicuous place
in Emerson Hall. 1c:1_n..l,__!_j
2.
A copy of the building permit shall be posted by the property owner or
his representative in a conspicuous place at the project site prior to the
commencement of construction. The posted copy shall be protected
from weather damage and shall remain on display for the duration of
all approved construction activity.
J.
Commencement and completion of work
1.
Construction and alteration activities on projects for which a permit
has been granted under this Section shall substantially commence
within twelve (12) months from the date of issuance of the permit and
shall be substantially completed within twenty-four (24) months from
the date of issuance of the permit. ,.--1.n_L._0_,
2.
Activities may be extended for up to twelve (12) months by the CEO, for
good cause, if an application for an extension is submitted in writing to
the CEO on forms provided for the purpose, together with such fees as
required in Article 11 of this Ordinance prior to expiration of the
permit. _Arn_)_,
3.
Activities which are not substantially commenced or substantially
completed within the time limits provided above, or any extension
thereto, shall be subject to new application and the permit issued
under this Section shall be considered void.
K.
Appeals
Appeals from decisions of the CEO may be taken to the Zoning Board of
Appeals pursuant to Article 14 of this Ordinance. \_j,rn_,
8.3. ACCESS TO SITE AND REcoRDS
The CEO shall have reasonable access to the site at all times while processing the
permit application and for the duration of the project to review the progress of the
work and shall have the authority to take photographs on site and to review all
101 IPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-0!
Amended·. 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended·. 26-Mar-07
Amended: 2+Mar-08
Amended: 04 Apr-09
Amended: 27 -Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended: 0 1-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended. ll-Jul-20
Amended. ll-May-24
Last Amended: 07-Jun-25
records and documents related to the project. By making application for a
Building Permit, the applicant and all property owners grant to the CEO
permission to enter upon the affected property and into_any structures involved
in the proposed project, at all reasonable times, to review the proposed project
prior to issuing a permit. By accepting a Building Permit, the applicant and all
property owners grant to the CEO permission to review all records and
documents related to the project and permission to enter upon the affected
property and into any structures involved in the proposed project, at all
reasonable times to review the progress of the work and to inspect the completed
project, to ensure compliance with the permit.and applicable laws. lAm.l, '.Ar:i1.J]
-0-
102 I Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26- Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-lO
Amended: 26-Mar-1!
Amended: 01-Jun-13
Amended 23-Sept- 13
Amended· JJ.May-19
Amended: 11-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
ARTICLE 9: SITE PLAN REVIEW BY PLANNING BOARD
[Am_l, 26-Mar-01; Am2. 25-Mar-02;_Am5. 26-Mar-07; Am6. 24-Mar-08; Am7. 04-Apr-09;
AmS. 27-Mar-lQ;__A_nf!_(l_, ;,:6_-M_a_r:111
9 .1, PuRPOSE
The purpose of Site Plan Review is to promote the public health, safety, and
general welfare by requiring Planning Board review of plans for certain uses or
structures which could have a significant impact on the neighborhood or the
environment but which, when properly designed with respect to their
surroundings, can become uses or structures that are compatible with the
neighborhood and environment.
9.2. ACTMTIES REQUIRING SITE PLAN REVIEW
Except as provided in Section 9.3, below, Site Plan Review and Approval by the
Planning Board shall be required for:
A.
Any proposed use, construction, development or activity designated in
Article 5 (Land Use Table) as requiring Site Plan Approval from the Planning
Board.
B.
The expansion of any existing building or structure devoted to a use
requiring Site Plan Approval from the Planning Board.
C.
The expansion of the parking, loading, outdoor display or storage area of any
commercial, industrial or institutional use requiring Site Plan Approval from
the Planning Board.
D.
Hazardous activities involving the consumption, generation, or handling of:
1.
Hazardous wastes as defined in Title 38 M.R.S.A., § 1303.
2.
Hazardous materials as defined in Title 38 M.R.S.A., § 1317.
3.
Oil, as defined in Title 38 M.R.S.A., § 542.
4.
Low-level radioactive wastes, as defined in Title 38 M.R.S.A., § 1451.
1031 Page
Toning Ordinance -Adopted: 28-Mar,2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04"Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-l l
Amended: OI-Jun-13
Amended: 23-Sept-13
Amended: 11 May-19
Amended: 1 l-Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
E.
Any other use, construction, development or activity for which this
Ordinance requires review and approval by the Planning Board.
9.3. ACTIVITIES NOT REQUIRING SITE PLAN REVIEW
Unless specifically required by Article 5 or by some other provision of this
Ordinance, Site Plan Review shall not be required for any proposed use,
construction, development or activity designated in Article 5 (Land Use Table) as
requiring only a permit from the CEO or as requiring no permit at all. i_,i,,m. s;
A.
Any hazardous activity identified by the Maine Department of Environmental
Protection, as exempt from the definition of hazardous activity in Title 38
M.R.S.A., § 482, Subsection 2-C, including domestic and other uses of
substances in quantities too small to present a significant risk of ground
water contamination.
9.4. CLASSIFICATION
Any proposed use, construction, development or activity subject to Site Plan
Review shall be classified by the CEO into one of the following classes:
A.
General Project
Any proposed use, construction, development or activity not classified by the
CEO as a Miscellaneous Project under Section 9.4.B shall be considered a
General Project under this Section.
B.
Miscellaneous Projects j.\::1 li
A project that involves any of the following:
1.
Any project where Site Plan Review is made necessary solely because
the project is located in a Resource Protection Overlay District.
2.
Any project where Site Plan Review is made necessary solely because
the project is located in the Source Water Protection Overlay District.
!_\rn.f:i'
3.
Home occupations.
104 I p a g e
Toning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l I
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: l 1-May-19
Amended. 11-Jul 20
Amended: 11-May-24
Last Amended: 07-Jun-25
4.
Any application referred by the CEO under Section 8.1 above. 1.-\m .. );
9.5. PROHIBITION
No activity or use described in Section 9.2 shall commence until the property
owner has received Site Plan Approval from the Planning Board and has received
any necessary permits from the CEO under Article 8.
9.6. SITE PLAN REVIEW APPLICATION
Applications for Site Plan Review shall be submitted on application forms
provided by the Town. The executed application form, required fees, and required
plans and related information shall be submitted to the CEO who shall forward it
to the Planning Board if in his opinion the application is complete. The
submission shall contain at least the following exhibits and information:
A.
Application form
A fully executed and signed copy of the application form.
B.
Fees
Site Plan Review Fees in the amounts specified in Article 11.
C.
Original drawing
One (1) original of all maps and drawings on durable, permanent material.
The Planning Board may require Mylar media where it deems it necessary.
D.
Copies
Eight (8) copies of written materials plus eight (8) sets of maps or drawings
containing the information listed below. The written materials shall be
contained in a bound report or a three-ring notebook. The maps or drawings
shall be at a scale sufficient to allow review of the items listed under the
criteria for approval.
105/Page
Zoning Ord ma nee -Adopted: 28-Mar-2000
Amended, 26 Mar-OJ
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended·. 04 Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended. 26-Mar- ll
Amended: O I -Jun-13
Amended: 23-Sept-13
Amended, 11 May-19
Amended: 11-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
E.
General information
The following general information is required:
1.
Name of owner of record and address.
2.
Applicant's name and address if different.
3.
The name of the proposed project.
4.
Names and addresses of all abutting property owners and the names
and addresses of all owners of other property whose closest boundary
line is within one hundred fifty { 150) feet of a boundary line of the
project lot(s) which is the subject of the application. ',\IQ_f}_!
5.
Sketch map showing general location of the site within the Town.
6.
Location map showing the boundaries of all contiguous property under
the control of the owner or applicant regardless of whether all or part is
being developed at this time.
7.
The tax map and lot numbers of the parcel or parcels.
8.
A copy of the deed to the property, option to purchase the property or
other documentation to demonstrate right, title, or interest in the
property on the part of the applicant.
9.
The name, registration number, and seal of each land surveyor,
architect, engineer, and/ or similar professional assisting in the
preparation of the plan.
F.
Information regarding existing conditions
The following information regarding existing conditions is required:
106\Page
Zoning Ordtnance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: OJ-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: l 1-Ju\-20
Amended: l 1-May-24
Last Amended: 07-Jun-25
1.
Zoning classifications(s} of the property and the location of zoning
district boundaries if the property is located in more than one (1)
zoning district or abuts a different district.
2.
The bearings and distances of all property lines of the property to be
developed and the source of this information, prepared by a State of
Maine Registered Land Surveyor as a Standard Boundary Survey. A
Standard Boundary Survey is not required for a Miscellaneous Project.
3.
Location and size of any existing sewer and water mains, culverts, and
drains on the property to be developed and of any that will serve the
development from abutting streets or land.
4.
Location, names, and present widths of existing streets and rights-of-
way within or adjacent to the proposed development.
5.
The location, dimensions and ground floor elevations of all existing
buildings on the site.
6.
The location and dimensions of existing driveways, streets, parking and
loading areas, and walkways on the site.
7.
Location of intersecting roads or driveways within two hundred (200)
feet of the site.
8.
Topography of the project site at an appropriate contour interval ( e.g. 1,
2, or 5 feet) depending on the nature of the use and character of the
site. Site topography information is not required for a Miscellaneous
Project.
9.
Major natural features on the site and including within two hundred
fifty (250) feet of the boundaries of the site, wetlands, streams, great
ponds, floodplains, tributary streams, groundwater aquifers, significant
wildlife habitats including deer wintering areas identified in the current
Castine Comprehensive Plan, scenic areas identified in the current
Castine Comprehensive Plan, archaeological resources or other
1071 Pa g 8
7,oningOrdinance-Adopted, 28-Mar-2000
Amended: 26-Mar-Ol
Amended. 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended, 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr 09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended, 26-Mar- l 1
Amended: 0 l-Jun-13
Amended: 23-Sept- 13
Amended: 11-May 19
Amended: l 1-Jul-20
Amended: Jl-May-24
Last Amended: 07 -Jun-25
important natural features. Major natural features information is not
required for a Miscellaneous Project.
10. Soils information if on-site sewage disposal is proposed. This
information should be detailed enough to allow those portions of the
site not suitable for on-site disposal systems to be identified.
11. The location of open drainage courses, wetlands, significant stands of
trees, and other important natural features, with a description of such
features to be retained.
12. The direction of existing surface water drainage flow across the site.
13. The location and dimensions of existing signs.
14. The location and type of all existing exterior lighting;
15. For projects located within the Source Water Protection Overlay
District, any information required by Section 4.7 .D. [,\,-,,.ri: .. \n,. 7"
16. For lawful non-conforming structures subject to Section 3.4.A.1, the
floor area and enclosed volume of the original structure, the amount of
any previous expansions of the floor area and enclosed volume of the
original structure and the amount of any expansions of the floor area
and enclosed volume of the original structure being currently
requested. [.\f!',. 7":'
G.
Information regarding the proposed project
The following information regarding the proposed project is required:
1.
The location of all building setbacks, yards, and buffers required by
this Ordinance.
2.
The location, dimensions, including heights, and ground floor
elevations of all proposed buildings on the site.
108 I P a g e
2-0ning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: 01-Jun-13
Amended; 23-Sept-13
!\mended: ll-May-19
Amended: ll-Jul-20
Amended: ll-May-24
Last Amended. 07-Jun-25
3.
The location and dimensions of proposed driveways, parking and
loading areas, and walkways.
4.
The location, capacity and dimensions of all proposed water supply and
wastewater disposal systems.
5.
The direction of proposed surface water drainage flow across the site
and the location and size of all proposed catch basins, drainage
ditches, and storm sewers.
6.
Location, front view, and dimensions of proposed signs.
7.
Location and type of proposed exterior lighting.
8.
Proposed landscaping and buffering for non-residential projects.
0\n.1J2.i
9.
If the project includes new construction or any soil disturbance, an
erosion control plan showing methods of controlling erosion and
sedimentation during and after construction.
10. lfthe project is a cluster development or is owned in condominium,
evidence that all requirements relative to establishment of a
homeowners' association or condominium agreement have been met. If
the project is a cluster development, evidence shall be presented that
all other requirements of the Castine Subdivision Ordinance pertaining
to cluster development have been met. The submission shall include
copies of the by-laws or regulations of any homeowners' association or
condominium charged with maintaining common spaces and lands.
Such homeowners' association or condominium documents shall
clearly state that the association or condominium shall properly
maintain private roadways serving the development after the developer
has legally relinquished that responsibility and until such time as the
Town may accept them as public ways.
11. If a public water supply is to be utilized for a fire sprinkler system or
private fire hydrant, a written statement from a professional engineer
109 I p a g e
7,omng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended. 26-Mar-07
Amended· 24-Mar·-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02·Nov-JO
Amended: 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended. l 1-Jul-20
Amended: l 1-May-24
Last Amended: 07 -Jun-25
as to the adequacy of the water supply in terms of quantity and
pressure for both domestic and fire flows.
12. If the project includes a new sewage disposal facility with a capacity of
two thousand (2,000) gallons or more per day, or a new on-site public
water supply system, a groundwater impact analysis prepared by a
groundwater hydrologist.
13. If the project includes a multi-unit housing development providing ten
(10) or more housing units located on a single parcel of land or a non-
residential building or buildings on a single parcel of land which
occupies a ground area in excess of twenty-five thousand (25,000)
square feet, a traffic impact analysis demonstrating the impact of the
proposed project on the capacity, level of service and safety of adjacent
streets.
14. If applicable, written offers of dedication or conveyance to the
municipality, in a form satisfactory to the To"1111 Attorney, of all land
included in the streets, highways, easements, parks, or other open
space dedicated for public mvnership or use.
15. Design and construction drawings prepared by a State of Maine
Registered Professional Engineer for any street or appurtenance,
sanitary sewer system, water system or storm drainage system the
applicant proposes to construct for public -wnership and a signed
statement that the applicant will maintain such facilities until such
time as they may be accepted by the Town.
16. A schedule of construction, including anticipated beginning and
completion dates.
17. A list of the submission and review criteria for which the applicant
seeks a waiver pursuant to Sections 9.15 or 9.16, and a written
explanation of the reasons for seeking the waiver.
11 a I p a g e
Zoning Ordinance - Adllpted: 28-Mar-2000
Amended: 26"Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27,Mar-10
Amended: 02-Nov-10
Amended: 26- Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept- 13
Amended; 11-May- 19
/'unended· 11-Ju\ 20
Amended: 11-May-24
Last Amended. 07 -J un-25
9. 7. REVIEW PROCEDURES
The procedures for Site Plan Review are as follows:
A.
Step l: Submission of completed application to the CEO
The applicant shall submit the requisite number of copies of the application
and supporting information required by Section 9.6.
B.
Step 2: CEO classification and review
1.
Dated receipt
The CEO shall date-stamp the application .. Jrri:J;
2.
Classification
The CEO shall review the application and classify it pursuant to
Section 9.4. 1.-\r~l
3.
Fees submitted
After classification, the applicant shall provide the CEO with the
applicable fees established in Article 11.
4.
Review for completeness
The CEO shall initially review the application and determine whether or
not it is complete.
5.
Notice of incomplete application.
1111Page
If the application is found to be incomplete, the CEO shall, within ten
(10) days, notify the applicant in writing of the information needed to
complete the application. Upon the applicant's submission of such
additional information, Steps 1 and 2 shall be repeated. ;01D... 1_,
Zonmg Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- I 1
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l-May-19
Amended: l l -Jl1]-20
Amended: 11-May-24
Last Amended: 07-Jun-25
6.
Application forwarded
If the application is found to be complete, the CEO shall forward copies
of a complete application and supporting documents to the members of
the Planning Board and place the project on the agenda of the next
regular Planning Board meeting occurring not less than fourteen (14)
days after the CEO determines the application is complete.
7.
Notice to abutters and nearby property owners
Abutting property owners and all owners of other property whose
closest boundary line is within one hundred fifty (150) feet of a
boundary line of the project lot(s) which is the subject of the application
shall be notified by first class mail by the Town, of all pending
applications for Site Plan Review. This notice shall indicate the time,
date, and place of Planning Board consideration of the application.
Notice is to be sent to the person to whom property tax bills are sent at
the address shown on the Town's tax card for the property. :~\m .Li [_\m_i,_l
C.
Step 3: Planning Board review
At the meeting of the Planning Board at which the proposed development is
scheduled to be reviewed, the Planning Board shall:
1.
Determination of completeness
112\ Page
Determine whether or not the application is complete. For applications
filed after March 27, 2010, if an abutter notifies the Planning Board at
or prior to the first site plan review meeting of the Planning Board to
consider the application that there is a boundary line dispute between
the abutter and the applicant, which affects the applicant's ability to
meet the setback requirements of the Ordinance, the Planning Board
shall table the application for a period of one hundred twenty ( 120)
days from the date of the meeting. Upon the expiration of such one
hundred twenty (120) day period or such shorter period if the Planning
Board has received evidence that the boundary line location has been
resolved, at the next regular meeting of the Planning Board: (a) if only
the applicant has submitted a Standard Boundary Survey prepared by
Zonmg Ordmance -Adopted. 28-Mar-2000
Amended: 26-Mar 01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: 0\-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: l l-.Ju!-20
Amended. l l-May-24
Last Amended: 07-Jun-25
a State of Maine Registered Land Surveyor, the Planning Board shall
make its findings based upon such Survey; or (b) if both the applicant
and the abutter have each submitted a Standard Boundary Survey
prepared by a State of Maine Registered Land Surveyor, the Planning
Board shall not review the application until the Planning Board has
received evidence that the boundary line location has been resolved.
--\m 8'
2.
Notice of incompleteness
If the application is determined to be incomplete, the Board shall
inform the applicant, in writing, of the additional information required
by the Planning Board. Upon the applicant's submission of such
additional material, Step 1 shall be repeated. !c\m_ 1: [-'.l..m.1:
3.
Request for waivers of application requirements
Hear any requests from the applicant for waivers pursuant to Sections
9.15 and 9.16.
4.
CEO report
Hear any report of the CEO and if the Town has retained the services of
a professional adviser, the report of the adviser regarding the proposed
development.
5.
Applicant's response
Hear any comments of the applicant regarding the CEO's report and
the Town's professional adviser's report, if any.
6.
Public hearing determination
113IPage
If the application is determined to be complete, the Planning Board
shall deem the application pending and shall set a public hearing. The
Planning Board may set a public hearing on an application on the same
day such application is reviewed for completeness, but no later than
Zomng Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended: 02-Nov- 10
Amended: 26-Mar-1 l
Amended: 01-Jun-13
Amended, 23-Sept-13
Amended: ll-May-19
Amended: l l-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
forty-five (45) days after the Planning Board's determination that the
application is complete. This deadline may be extended by mutual
agreement of the Planning Board and the applicant, either in writing or
orally, on the record at a public meeting. Any public hearing held for
the purpose of hearing testimony regarding proposals requiring Site
Plan Approval under this Ordinance, and notice thereof, shall be
governed by Section 9.8. [Am.7]
D.
Step 4: Planning Board deliberation and decision
1.
Deliberation
Within thirty-five (35) days after the public hearing on an application,
or within thirty-five (35) days of a determination of completeness by the
Planning Board if no hearing is held, the Planning Board shall
deliberate to determine whether the proposed Site Plan complies with
all provisions of this Ordinance and meets the Criteria of Approval set
forth in Section 9.14. This deadline may be extended by mutual
agreement of the Planning Board and the applicant, either in writing or
orally, on the record at a public meeting.
2.
Decision
1141 Page
If the Planning Board finds that the proposed Site Plan complies with
all such standards it shall issue a written decision granting Site Plan
Approval; approval shall, however, be subject to such terms and
conditions set forth in its decision as the Planning Board considers
advisable to ensure conformity with the Site Plan Review Standards
and Criteria or any other provisions of this Ordinance. If the Planning
Board finds that the proposed Site Plan does not comply with all
applicable review standards, it shall issue a decision denying Site Plan
Approval. In either case the Planning Board shall issue its written
decision, which shall include specific findings of fact supporting its
decision, within ten (10) days (exclusive of Saturdays, Sundays and
legal holidays) after the completion of its deliberations.
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended; 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- lO
Amended. 26-Mar-11
Amended. 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended· l l-Jul-20
Amended· l l-May-24
Last Amended: 07-Jun-25
E.
Step 5: CEO building permit or use permit
If the Planning Board approves the Site Plan Application, the CEO shall
issue a permit upon receipt of a written decision issued pursuant to Section
9.7.D.2, above. [,--\m._§i
1.
For lawful non-conforming structures subject to Section 3.4.A.1, the
permit shall indicate the floor area and enclosed volume of the original
structure, the amount of any previous expansions of the floor area and
enclosed volume of the original structure and the amount of any
expansions of the floor area and enclosed volume of the original
structure currently granted by the Planning Board. [,\m.7!
2.
For lawful non-conforming structures subject to Section 3.4.A. l, the
permit is not valid until recorded by the Town in the Hancock County
Registry of Deeds. The applicant shall pay the Town the recording fee
and the Town shall record the permit within thirty (30) days after
receipt of the fee. --\m . ..Ii
9.8 PuBLIC HEARING PROCEDURES
Site Plan Review public hearings and notice thereof shall comply with the
following procedures:
A.
Published notice
Notice of any Site Plan Review public hearing shall be published in a
newspaper of general circulation in the Town of Castine at least ten ( 10)
days prior to the hearing date.
B.
Content of notice
Notice of said hearing shall identify the applicant and the property involved,
describe the specific nature of the proposal, state the date, time and place of
the hearing, and explain how the recipient of the notice may attend and
present evidence. Forms for this purpose shall be available from the CEO.
1151Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar·-Ol
Amended: 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24- Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mtlr-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11 May-19
Amended: ll-Jul-20
Amended: l l-Ma)-24
Last Amended: 07 -Jun-25
C.
Rules
Hearings shall be conducted according to rules adopted by the Planning
Board.
D.
Representation
At any hearing a party may be represented by an agent or attorney provided,
however, if any party is not present, any person acting as that party's agent
or attorney shall provide evidence of such authority.
E.
Continuation
Any hearing may be continued or recessed to another time for good cause,
or upon written or recorded agreement of the Planning Board and the
applicant.
9.9 PROFESSIONAL REvlEW
A.
Additional studies.
The Planning Board may require the applicant to undertake and present
such additional studies as it deems reasonable and necessary to ensure that
the requirements of the Ordinance are met. The cost of all such studies
shall be borne by the applicant.
B.
Independent technical review
The Planning Board may require that an independent consultant(s) review
one (1) or more submissions of an application and the choice of such
professionals shall be at the sole discretion of the Planning Board. The
independent consultant(s) shall report to the Planning Board as to the
project's compliance or non-compliance with the applicable provisions of
this Ordinance and recommend, if appropriate, those actions which will
result in compliance. Such consultants shall be fully qualified to provide the
required information, and may include but not be limited to:
1161Page
Zoning Ordinance - Adopted; 28-Mar-2000
Amended: 26-Mar-O\
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26- Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov·lO
Amended: 26-Mar-ll
Amended. Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: ll-Ju\-20
Amended: l l-May-24
Last Amended: 07 -Jun 25
An Attorney.
-
A Community Planner.
-
A Registered Professional Engineer.
-
A Registered Architect.
-
A Registered Landscape Architect.
-
A Registered Geologist.
-
A Licensed Soil Scientist.
-
A Registered Land Surveyor.
-
Any other Registered/Licensed Professional or independent Expert
Witness deemed fully qualified by the Planning Board.
The cost of such technical review shall be borne by the applicant. The
consultant(s) selected shall estimate the cost of such review and the
applicant shall pay the Town the full estimated cost in accordance with
Section 11.5. 1_:i.o.ifi
9.10. FAILURETOACT
Failure of the Planning Board to act within any of the time requirements set forth
herein shall constitute a denial of the application.
9.11. EXPIRATION OF APPROVALS
A.
All Site Plan Approvals shall expire unless work on the project is
substantially commenced within twelve (12) months from the date of
issuance of the Site Plan Approval and substantially completed within
twenty-four (24) months from the date of issuance of the Site Plan Approval.
: . .\J}l_,_,?_,'
B.
Activities may be extended for up to twelve (12) months by the Planning
Board, for good cause, if an application for an extension is submitted in
writing to the CEO on forms provided for the purpose, together with such
fees as required in Article 11 of this Ordinance prior to expiration of the Site
Plan Approval. ',',1_r,__..:o'ii.
C.
Activities which are not substantially commenced or substantially completed
within the time limits provided above, or any extension thereto, shall be
117\ Page
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended: 02-Nov.JO
Amended: 26-Mar- ll
Amended· 0 l -Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: ll-Jul-20
Arnended: ll-May-24
Last Amended: 07-Jun-25
subject to new application and the Site Plan Approval issued under this
Section shall be considered void. {Am . .2:
9.12. OTHER PERMITS
The granting of Site Plan Approval does not relieve the applicant from the need to
obtain any other permits or approvals required prior to the commencement of any
activity or use. Such other required permits or approvals may include, but are
not limited to, Historic Preservation Certificate, subdivision approval, building,
plumbing and electrical permits, licenses granted pursuant to Title 38 M.R.S.A.,
Maine Department of Environmental Protection and United States Army Corps of
Engineers' approvals, subsurface wastewater disposal permits, sewer connection
permits, Maine Department of Transportation approvals, and the like. The fact
that the applicant may have obtained or may have been granted such permits or
approvals prior to Site Plan review may be considered by the Planning Board as
evidence as to the plan's compliance with applicable review standards, but shall
not be deemed conclusive evidence as to compliance.
9.13. ACCESS TO SITE AND REc0RDS
The Planning Board shall make a site visitation in any case it deems appropriate.
The CEO, members of the Planning Board and any consultant to the Planning
Board shall have reasonable access to the site at all times while reviewing the
permit application and for the duration of the project to review the progress of the
work and shall have the authority to take photographs on site and to review all
records and documents related to the project. By making application for a Site
Plan Review, the applicant and all property O¼Uers grant to the CEO, members of
the Planning Board and any consultant to the Planning Board permission to
enter upon the affected property and into any structures involved in the proposed
project, at all reasonable times, to review the proposed project prior to issuing a
permit. By accepting a Building Permit, the applicant and all property owners
grant to the CEO, members of the Planning Board and any consultant to the
Planning Board permission to review all records and documents related to the
project and permission to enter upon the affected property and into any
structures involved in the proposed project, at all reasonable times, to review the
progress of the work and to inspect the completed project, to ensure compliance
with the permit and applicable laws. :.\m.: j. \rn.2; : \rn.s:
1181Page
Zoning Ordmance - Adopted: 28-Mar"2000
itmended; 26-Mar-Ol
Amended: 25-Mar-02
Amended· 07"May-02
Amended: 04-Apr-OS
Amended: 26- Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26- Mar-1 l
Amended: 0 l -Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended· 1 l-Jlll-20
Amended; l l-May-24
last Amended. 07-Jun-25
9.14. SITE PLAN REVIEW CRITERIA
The Planning Board in reviewing projects requiring Site Plan Approval under this
Ordinance shall make positive written findings that the applicant has submitted
adequate evidence showing that with respect to the completed project: _-\mJi!
A.
The proposed project complies with the dimensional requirements of Article
5, Article 6 and Article 7 which include minimum lot area, minimum lot
width, minimum shore frontage, front yard setback, side yard setback, rear
yard setback, shoreline setback, maximum structure height, maximum
percent oflot coverage and maximum cleared opening. !.\m.h!
B.
The proposed project complies with the district overlay requirements of
Section 4.7 ., if applicable._;.k,.r);
C.
The proposed project complies with the flood hazard area requirements of
Section 6.4., if applicable. [,_\m.hi
D.
Any traffic increase attributable to the proposed project will not result in
unreasonable congestion or unsafe conditions in the vicinity of the proposed
development and adequate provisions have been made for traffic movement
of all types (including pedestrian) into, out of, and within the proposed
project and adequate provisions have been made for off street parking and
loading .. ,~m/:°J:
E.
That the proposed project will be built on soil types which are suitable to the
nature of the project and that adequate provision has been made to avoid
erosion, contamination of ground or surface waters, interference with
adjacent land, over-burdening of natural or artificial drainage systems,
and/or any other adverse effects of inadequate drainage.
F.
Adequate provision has been made to locate and design proposed outdoor
display and/or storage areas so as to avoid any safety hazard to vehicular
and pedestrian traffic on and off the site.
1191Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May 02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov 10
Amended. 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept- \3
Amended: l l-May-19
Amended: 11-Jul-20
Amended: I \-May .. 24
last Amended. 07-Jun-25
G.
Adequate provision has been made to avoid any nuisance to the use of
adjoining public or private property. [Am 6]
H.
Adequate provision has been made with regard to the preservation of
significant natural features and vistas available to the general public as set
forth in the current Castine Comprehensive Plan. The Planning Board shall
not give consideration to private views in making this determination. ':\m.f)!
I.
Adequate provision has been made to avoid unreasonable adverse effects on
the scenic or natural beauty of the area including scenic areas designated in
the current Castine Comprehensive Plan, historic sites, archaeological
resources, rare and irreplaceable natural areas, wildlife habitats including
identified deer wintering areas, existing uses, air quality, water quality, or
other natural resources within the town or in neighboring towns.
J.
Whenever a project is situated, in whole or in part, within the Shoreland
Zone, adequate provision has been made to conserve shoreland vegetation,
visual points of access to waters as viewed from public facilities, and actual
points of public access to waters. ,.\m.i"l:
K.
Adequate provision has been made to prevent any unreasonable adverse
effect upon adjacent or nearby properties or property values; in making this
determination, the Planning Board shall give consideration to conformity of
the project with the purposes of this Ordinance as set forth in Section 1.4.
:.\m.5 [.\m.b!
L.
Adequate provision has been made to avoid any unreasonable burden on
municipal services, including but not limited to water, sewer, fire and police
services. '._-\rn_o:
M.
Adequate provision has been made to assure the proper operation of the
proposed business(es) or activity(ies) on the site through the provision of
adequate and appropriate utilities, drainage, water supply, sewage disposal,
solid waste disposal, access, parking and loading, and other necessary site
improvements.
120 I Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Oi-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: l l-.Jul-20
Amended: 1 I-May-24
Last Amended. 07-.Jun-25
N.
Adequate provision has been made to assure that the proposed development
conforms in all respects with the provisions of this Ordinance.
9.15. WAIVER OF CERTAIN APPLICATION REQUIREMENTS
The Planning Board may, for good cause shown and only upon the written
request of an applicant specifically stating the reasons therefor, waive any of the
application requirements set forth in Section 9.6 provided such waiver will not
materially compromise the review process. The Planning Board may condition
such a waiver on the applicant's compliance with alternative requirements. The
Planning Board shall make a written record of any waivers granted stating the
reasons for granting the waiver. Good cause or grounds to support a waiver may
include the Board's finding that particular submissions are inapplicable,
unnecessary, or inappropriate for a complete review. Notwithstanding the waiver
of a submission requirement, the Planning Board may, at any later point in the
review process, rescind such waiver if it appears that the submission previously
waived is necessary for an adequate review. A request for a submission previously
waived shall not affect the pending status of an application.
9.16. WAIVER OF CERTAIN REVIEW CRITERIA
The Planning Board, may upon the written request of an applicant specifically
stating the reasons therefor, waive any of the Review Criteria set forth in Section
9.14. when it finds that such a waiver is reasonable and that the public health,
safety, or welfare would not be adversely affected by such a waiver. The Planning
Board shall make a written record of any waivers granted stating the reasons for
granting the waiver. Grounds to support a waiver may include the Board's
finding that particular criteria are inapplicable, unnecessary, or inappropriate for
a complete review.
9.17. APPEALS
An aggrieved party who participated in the Site Plan Review process may appeal
the final decision of the Planning Board under Section 9.7.D.2. to the Zoning
Board of Appeals. Such appeal must be filed no later than thirty (30) days after
the Planning Board issues its written decision under Section 9.7.D.2.
Preliminary and procedural determinations made by the Code Enforcement
1211 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- 10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: l 1-Jul-20
Amended· 1 l-May-24
Ulst Amended: 07-Jun-25
Officer or the Planning Board during Site Plan Review, including without
limitation, classification of projects, determination of completeness and granting
or denial of waivers, are not in themselves appealable to the Board of Appeals,
but may be reviewed by the Board of Appeals when it considers a timely appeal
from the final decision from the Planning Board on the Site Plan Review
application.
1221Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar·08
Amended: 04-Apr·09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended· ll-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
ARTICLE 10: CERTIFICATE OF COMPLETION, OCCUPANCY OR USE
:Am 1. 26-Mar-Q_l; Ams. 26_-Mar-07]
10.1. No Certificate of Completion or Occupancy or Use shall be issued unless the
building, structure or use conforms to the provisions of this Ordinance and any
Site Plan or conditions of approval. ,}mJ_,
10.2. A Certificate of Completion issued by the Code Enforcement Officer (CEO) and
certifying applicable provisions of this Ordinance have been satisfied may be
requested by the applicant after any building, structure, or part thereof has
been erected, altered, or moved pursuant to a permit.
0:\JI1. i: ; .-\111_.-,.
10.3. A Certificate of Occupancy and/or Use issued by the CEO and certifying
applicable provisions of this Ordinance have been satisfied must be obtained in
the following circumstances: '.-\rn. i;
A.
After a building has been constructed, expanded or modified for use as an
inn, hotel or bed and breakfast, before such construction, enlargement or
modification may be used or occupied. !,_\~-'.L
B.
After a building has been modified to accommodate additional rental
dwelling units, before such units may be rented, used or occupied. 'An:
C.
After a building has been expanded to accommodate additional
commercial, institutional, or industrial uses, before such spaces may be
used or occupied. : -\nL.: i
D.
After a building or structure has been modified to accommodate a home
occupation, before said home or structure may be used or occupied for a
home occupation. :.-\:n.~!
10.4. No Certificate of Occupancy shall be issued until any necessary approvals or
certifications from the Local Plumbing Inspector (LPI) are obtained. ! \m~0_!
10.5. It is the responsibility of the permit applicant to obtain a Certificate of
Completion, Occupancy and/or Use.' \:~1 · ·
123IPage
Zoning Ordmance - Adopted: 28-Mar-2000
Amended· 26-Mar-01
Amended: 25-Mar-02
Amended; 07-May-02
Amended. 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-l0
Amended: 26-Mar-1 l
Amended: 0!-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: 11-Jul-20
Amended:\ l-May-24
Last Amended: 07-Jun-25
10.6. A Certificate of Completion, Occupancy and/or Use certifies compliance with
the provisions of this Ordinance only and does not certify compliance with any
other codes or standards. (..\rn.l,I
1241Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended. 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended; 27-Mar-JO
Amended: 02-Nov-10
Amended: 26-Mar-l !
Amended: 01-Jun- \3
Amended: 23-Sept-13
Amended· ll-May-19
Amended; l l-Jul-20
Amended: 1 l-May-24
Last Amended. 07-Jun-25
ARTICLE 11: FEES
[Am!. 26-Mar-0_1;. Am2. __ 25-Mar-Q__;_;_Am3. 07-MaY:Q~Am4. 04-~-05_;__Am6, 24-Mar-08;_
~m7_,__Q4-Al2!.:_0__2J
11.1. GENERAL PROVISIONS; -\nL.l..5[
A.
Application incomplete until payment of required fees
Applications for any of the permits, approvals, or certificates specified below
which are not accompanied by a check in the amount of the required fee
shall be considered incomplete and no action will be taken on said
application until a check for the required amount has been received by local
officials.
B.
Check, credit card or cash payment to Town [J.m._j (J 1
All fees may be paid in the form of a check/ cash/ credit or debit card
payable to the Town of Castine. The purpose of the fee shall be clearly
indicated on the check if the applicant is using that form of payment. Any
check returned by a bank for non-payment will immediately void the
application and any resultant permit. Castine will accept credit/ debit card
payments either in person or over the phone. There will be a credit/ debit
card surcharge increase in the fee to defray the credit/debit card processing
cost .. 101.J! ~m. i rJI
11.2. BUILDING PERMIT FEES ,_-i.ni._!Oi
A.
Basic fees
1.
A non-transferable, non-refundable base fee of fifty dollars ($50) plus a
non-transferable_, non-refundable additional fee must accompany the
building permit application. ,Amc.e1 f~Dl .... ,..Lf.!:
2.
A non-transferable, non-refundable fee of fifty dollars ($50) must
accompany the application for a permit extension pursuant to Section
8.2.J.2. [_'.}l_tl.2'- !_·\!_l")_I),
__ \!_!J_.i(-J:
125 / P a 9 e
Zoning Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended; 25-Mar-02
Amended; 07 -May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended; 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-l l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: I l-Jul-20
Amended; l l -May-24
Last Amended: 07-Jun-25
3.
A non-transferable, non-refundable fee of twenty dollars ($20) must
accompany the application for written approval by the Fire Chief
pursuant to Section 6.9. iAm.21 [Am.bl (Am.1.2.i
B.
New building construction additional fee [Am.16]
For new building construction there shall be a non-transferable, non-
refundable base fee of fifty dollars ($50) plus an additional non-transferable,
non-refundable fee. The additional fee is based upon the greater of: 1) the
square footage cost determined by using the New Construction Cost Table (§
11.2.F. below) or 2) the actual cost. The additional fee for new construction
is calculated as follows: li',_m.1 llim.1llim.ill'\m. l Ol
1.
Determine the applicable construction type from Column One of the
New Construction Cost Table. f1m.,__U
2.
Determine the Unit Cost for this type construction from Column Two of
the New Constnzction Cost Table. lAQl.J.i
3.
Multiply the Unit Cost by the square footage of the construction to
determine the total cost of the project. !.'1.m. l 1
4.
Determine the greater of the calculated cost or the actual cost and find
the corresponding cost range in Column One of the Additional Fee
Table(§ 11.2.G. below). [:\rnil_i:\m~
5.
Determine the additional fee in Column Two that corresponds to the
cost range determined above. [Arn.JI
C.
New construction additional fee !Anhlf:i.!
For new construction other than new building construction, there shall be a
non-transferable, non-refundable base fee of fifty dollars ($50) plus an
additional non-transferable, non-refundable fee based upon the estimated
cost of the project. In the event the actual cost of the project exceeds the
estimated cost, the fee corresponding to the actual cost must be paid to the
Town. The applicant shall inform the CEO of the actual cost and the CEO
shall verify this cost. The additional fee for new construction is calculated as
follows: [,\nU, (Am.Ji P,rt!.:.1_6.,1
126\Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended· 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amended: 23-Sept- 13
Amended: 1 l-May-19
Amended: 11-Jul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
1.
The applicant shall inform the CEO of the estimated cost and state the
estimated cost on the application. 'A.m_j_
2.
Find the corresponding cost range in Column One of the Additional Fee
Table (§ 11.2.G below). iAm~I
3.
Determine the additional fee in Column Two that corresponds to the
cost range determined above. :.Jim_l1.
D.
Remodeling fees JA.rr,.J_Eij
For remodeling there shall be a non-transferable, non-refundable base fee of
fifty dollars ($50) plus an additional non-transferable, non-refundable fee
based upon the estimated cost of the remodeling. In the event the actual
cost of the remodeling exceeds the estimated cost, the fee corresponding to
the actual cost must be paid to the Town. The applicant shall inform the
CEO of the actual cost and the CEO shall verify this cost. The additional fee
for remodeling is calculated as follows: i.\m. l. r.\m.2: !.·\:n._1 r)I
1.
The applicant shall inform the CEO of the estimated cost and state the
estimated cost on the application. -:-\m._\_·:
2.
Find the corresponding cost range in Column One of the Additional Fee
Table(§ 11.2.G below). -.,,n_._l,
3.
Determine the additional fee in Column Two that corresponds to the
cost range determined above .. ,--\n-i..J. 1
E.
Demolition-or change of use fees [A_m. l_§J
For demolition or change of use applications, there shall be a non-
transferable, non-refundable base fee of fifty dollars ($50). -\n:. +._ \m. l_<j
1271 Page
Zonmg Ordinance -Adopted. 28· Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended· 04-Apr-09
Amended. 27-Mar-10
Amended 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept- l 3
Amended· l 1-May-19
Amended: l 1-Jul-20
Amended: 1 l-May-24
Last Amended: Q7 .. Jun-25
F.
New Building Construction Cost Table !Arn, li /.\rn.Ji IArn.J) ]'.\1n.7] iArn .. l.c,·,
1. Construction Type
Commercial
All Floors, All Spaces
Industrial
All Floors, All Spaces
Institutional
All Floors, All Spaces
Municipal
All Floors, All Spaces
Residential
Basement, Unfinished
Basement, Finished
Main Living Floor
Secondary Floor(s)
Walk-Up, Unfinished Attic
Garage
Car Area
~
Unfinished Room
Finished Room
Finish an Unfinished Room ' :\ rri,.12 !
Deck !1.m. \_§.]
Covered Porch \Arn. 16 1
Prefabricated/factory-built building 200
square feet or smaller, or temporary
structure !_6,:T,,.lfJ!
1281 Page
2. Unit Cost per Square
Foot
$210.00 J s.f.
$210.00 J s.f.
$210.00 J s.f.
$210.00 J s.f.
$37 .50 / s.f.
$135.00 / s.f.
$1so.oo / s.f.
$150.00 / s.f.
$37.50 / s.f.
$45.00 / s.f.
$37.50 / s.f.
$135.00 / s.f.
$97 .50 / s.f.
$45.00 / s.f.
$90.00 J s.f.
$12.00 / s.f.
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 \
Amended, 01-J un-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: 11-Jul-20
Amended: l 1-May-24
Last Amended: 07 "Jun-25
G.
Additional Fee Table !:}m. _ _L ;'.\m_._1_: ,,Am._L l·-\m.-JQ;
1.
2.
Cost Range of Project
Additional Fee
--
$1
To
$1,500
$25.00
$1,501
To
$5,000
$37.50
$5,001
To
$20,000
$75.00
$20,001
To
$35,000
$87.50
·-~
-----
$35,001
To
$50,000
$150.00
$50,001
To
$75,000
$225.00
$75,001
To
$100,000
$300.00
$100,001
To
$1,000,000
$3.00 per $1,000 of Cost
--------
Costs Over $1,000,000
$1 .50 per $1,000 of Cost
11.3. SITE PLAN REVIEW FEES ',\F,.16'1
The fees required to cover the administrative costs associated with Site Plan
Review under this Ordinance are as follows:
A.
The non-transferable, non-refundable fee to accompany an application for a
General Project is two hundred dollars ($200). : .. \n,_._i'j;
B.
The non-transferable, non-refundable fee to accompany an application for a
Miscellaneous Projects is fifty dollars ($50). ,.~:,, _
1 -Jj
1291 Page
Zoning Ordinance - Adopted: 28·Mar·2D00
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- 10
Amended. 02-Nov-10
Amended: 26-Mar-1 l
Amended·. Ol .,.Jun-13
Amended: 23-Sept-13
Amended: l 1-May-19
Amended: l 1-Jul-20
Amended, 11-May-24
Last Amended: 07-Jun-25
C.
This Ordinance is available for $20.00 per copy and application forms are
available at no cost. IAm._L_(;i_i
11.4. AFTER-THE-FACT APPLICATION FEE
Any Site Plan Review Application or Building & Use Application submitted after
an activity, project or use has commenced shall be subject to an additional non-
transferable, non-refundable fee, in addition to those required by Section 11.2
and Section 11.3 above, equal to twice the fee required by Section 11.2 and
Section 11.3. This fee shall be paid prior to the review of any after-the-fact
application by the Permitting Authority. (c\D'.:.,_(i,'
11.5. TECHNICAL REVIEW FEE
In addition to the fees required by Section 11.2, Section 11.3 and Section 11.4
above, the applicant shall pay a separate fee of five hundred dollars ($500) to be
used to reimburse the time and expenses incurred by the Town's Planning
Consultant, if the Town has retained the services of such a Consultant, and/or
such other independent consultant(s) the Board may deem necessary to assist it
with its review of the application. Such other consultants shall be fully qualified
to provide the required assistance, and may include but are not limited to: i_\m . .L
-
An Attorney.
-
A Registered Professional Engineer.
-
A Registered Architect.
-
A Registered Landscape Architect.
-
A Registered Geologist.
-
A Licensed Soil Scientist.
-
A Registered Land Surveyor.
-
Any other Registered/Licensed Professional or independent Expert Witness
deemed fully qualified by the Planning Board.
This Technical Review Fee shall be paid prior to the start of the Planning Board's
review of any application for Site Plan Review deemed by the Planning Board to
require review by a consultant. This fee shall be paid in the form of a check made
payable to the Town of Castine and the purpose of the fee shall be clearly
indicated on the check. : -~ __1_,
130\Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended· Ol-Jun-13
Amended. 23-Sept-13
Amended: l 1-May-19
Amended: 11 Jul-20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
If the balance of the unexpended funds is drawn down by fifty percent (50%) or
more, the applicant shall be notified and required to pay an additional two
hundred fifty dollars ($250). The applicant shall continue to be notified and
required to pay the appropriate additional amounts as necessary whenever the
balance of the funds is drawn down by fifty percent (50%) of the original amount.
Failure to pay the required amount within thirty (30) days shall also be a
violation of this Ordinance and be cause to stop the review process. Any balance
remaining, after the completion and inspection of required improvements, shall
be returned to the applicant.
11.6. ZoNING BOARD OF APPEALS ADMINISTRATION FEES Jrn._ih:
All applications for administrative appeals and variances to the Zoning Board of
Appeals under this Ordinance shall be accompanied by a non-transferable, non-
refundable fee of two hundred dollars ($200). [A.r1_i___i !-\n: Fi: '-~--"1 __ 1 (J!
11. 7. CONTRACT ZoNING APPLICATION FEES U.£1:1.,.J.'ii
All applications to the Planning Board for contract zoning under this Ordinance
shall be accompanied by non-transferable, non-refundable fee of two hundred
dollars ($200). :-1.rn.2, iAm h' U,nL_I oi
11.8. ADJUSTMENT OF FEES BY SELECTBOARD
Any or all of the foregoing cost schedules or fees may be adjusted from time to
time as circumstances require by vote of the Selectboard, after notice and
hearing. Fees shall at all times not exceed the reasonable cost of processing,
review, regulation and supervision of the application by the Town and its
consultants and the administration of any requirement for a Certificate of
Compliance with any permit conditions. Fee adjustments shall take effect
immediately upon approval and shall be inserted into this Ordinance and
incorporated herein as though originally enacted as part hereof. Fee adjustments
by the Selectboard shall be identified as such and include the date of adjustment.
-0-
131 IPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended. 04-Apr-05
Amended: '26-Mar-07
Amended; 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- 10
Amended: 26-Mar-l 1
Amended: OJ-Jun- 13
Amended; 23-Sept-13
Amended: I 1-May-19
Amended· 1 l-Jul-20
Amended: \ l-May-24
Last Amended: 07-Jun-25
ARTICLE 12: ENFORCEMENT [!\,ml. 26-Mar-01.i_Am3. 07-Mi!Y..:_(g_;__Am4. 04-Apr-0§J
12, l. CODE ENFORCEMENT OFFICER
A.
The Code Enforcement Officer (CEO) shall be appointed pursuant to Title
30-A M.R.S.A., § 2601-A, as amended. IMu .li [Am.:\ 1,\rn.-+:
B.
The CEO shall be certified by the Executive Department, State Planning
Office pursuant to Title 30-A M.R.S.A., § 4451, as amended. :'.',m.,li
C.
It shall be the duty of the CEO to enforce the provisions of this Ordinance
and other Town Ordinances as required therein. l_i1:D.c.J_;
D.
The CEO shall provide staff support to the Planning Board. ,~-'~-
12,2. ENFORCEMENT PROCEDURE
A.
If the CEO shall find that any provision of the Ordinance is being violated,
the CEO shall notify in writing the person responsible for such violation,
indicating the nature of the violation and ordering the action necessary to
correct it, including discontinuance of illegal use ofland, buildings or
structures, or work being done, removal of illegal buildings or structures,
and abatement of nuisance conditions. A copy of such notices shall be
submitted to the Selectboard and be maintained as a permanent record.
Any such notice is not a prerequisite to bringing any legal action noted in
Section 12.3 below, and the failure to give notice shall not in any way affect
such legal action. However, any such notice constitutes a final
determination by the Code Enforcement Officer, which is not merely
advisory and which is subject to review by the Board of Appeals in an
Administrative Appeal under Section 14.2.A, and which, if not appealed,
becomes binding, final administrative action. 1_~m.1 1
B.
The CEO shall conduct on-site inspections to ensure compliance with all
applicable laws and conditions attached to permit approvals. The CEO shall
also investigate all complaints of alleged violations of this Ordinance.
C.
The CEO shall keep a complete record of all essential transactions of his
office, including applications submitted, permits granted or denied, 30-
132 I p a g e
Zoning Ordinance - Adopted; 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- 11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May- \9
Amended: ll-Jul-20
Amended: 11-May 24
Last Amended; 07-Jun-25
percent-expansion records, variances granted or denied, revocation actions,
violations investigated, violations found, and fees collected.
12.3. LEGAL ACTION
The Selectboard, upon notice from the CEO, may institute any and all actions,
and proceedings, either legal or equitable, including seeking injunctions against
violators and the imposition of fines that may be appropriate or necessary to
enforce the provisions of this Ordinance in the name of the Town of Castine. The
Selectboard, or their authorized agent, is hereby authorized to enter into consent
agreements for the purpose of eliminating violations of this Ordinance and
assessing fines without Court action. Such agreements should not allow an illegal
structure or use to continue unless there is clear and convincing evidence that
the illegal structure or use was constructed or conducted as a direct result of
verified erroneous advice given by an authorized Municipal Official and there is
no evidence that the owner acted in bad faith.
12.4. FINES
Any person, including but not limited to a landowner, a landowner's agent or a
contractor, who orders or conducts any activity in violation of this Ordinance
shall be assessed a monetary penalty on a per-day basis in accordance with Title
30-A M.R.S.A. § 4452, as amended. _.-\m. l
-<l>-
133IPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25, Mar 02
Amended: 07 May-02
Amended, 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-lO
Amended: 02 Nov-10
Amended, 26-Mar-ll
Amended, Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 11-Jul- 20
Amended: 11 May 24
Last Amended: 07-Jun-25
ARTICLE 13: PLANNING BOARD lAm 1. 26-Ma!:0J; __ AmS. 26-Mar-_9_7;_Am8. 27-Mar-10]
13.1. AUTHORITY
The Planning Board created by the Town on March 21, 1960 is hereby authorized
to exercise all powers delegated to the Planning Board by the provisions of this
Ordinance. The Planning Board also continues to have the authority to
administer the Town of Castine Subdivision Ordinance, and any other Town
Ordinance granting such powers to the Planning Board.
13.2. EsTABLISHMENT AND ORGANIZATION OF PLANNING BOARD
There shall be a Planning Board of five (5) members and two (2) associate
members appointed by the Selectboard. Only residents of the Town of Castine are
eligible to serve on the Planning Board. Neither a Municipal Officer nor the
spouse of a Municipal Officer may be a member or associate member of the
Board.
The Planning Board in existence at the time of the enactment of this Ordinance is
continued and its members are hereby appointed to serve under this Ordinance
in that capacity and for the balance of their previously appointed terms.
Members shall be appointed by the Selectboard with terms of five (5) years. The
terms of the members shall be such that the term of at least one (1) member will
expire each year. The term of the associate members shall be one (1) year, and
they shall be designated first and second associate in the order of their seniority
by appointment. The Selectboard may dismiss a member or associate member of
the Planning Board for cause, after notice and hearing, before the member's or
associate member's term expires .. ,~m_,~'i.
In the absence or inability of members, the first and/ or second associate shall act
in the order of their seniority by appointment. The associate members may also
act in place of any member who abstains or is unable to vote due to a conflict of
interest or any other reason. In the case of resignation or dismissal of a member,
and with the approval of the Select board, the first associate shall become a
regular member for the remainder of the unexpired five (5) year term, the second
associate shall become the first associate, and the Selectboard shall appoint a
new second Associate for the remainder of the unexpired one (1) year term. [,-\rr~_Si
1341Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-0I
Amended: 25-Mar 02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: 11-Jul-20
Amended: l 1-May-24
Last Amended: 07-Jun-25
The Planning Board shall keep minutes of its proceedings, recording the vote of
each member on all matters coming before the Planning Board. The minutes of
the Planning Board and all correspondence shall be a public record. The
presence of three (3) voting members of the Planning Board shall constitute a
quorum for conducting a meeting and deliberating and voting on a particular
matter. A member who abstains or is disqualified or recused from deliberation
and voting on a particular matter shall not be counted in determining whether a
quorum exists for such matter. The concurring opinion of a majority of the
voting members present is necessary to act on any matter. The only action that
can be taken in the absence of a quorum is to fix the time to which adjourn,
recess or take measures to obtain a quorum. In addition, the Planning Board
may adopt any procedural rules not in conflict with State law or this Ordinance,
which it deems necessary or proper for the conduct of its business. _,J,.m_cf
The question of whether a member has a conflict of interest sufficient to
disqualify the member from participating in the consideration of a particular
matter shall be decided by majority vote of the Planning Board, excluding the
member being challenged. Any member so disqualified or who has recused
himself must abstain entirely from the Planning Board's deliberation and voting
on the matter giving rise to his disqualification or recusal. : J,112_L
13.3. POWERS AND DUTIES
A.
General
The Planning Board shall hear and decide all applications for Site Plan
Review and shall undertake any other activities assigned or allotted to it by
the provisions of this Ordinance.
B.
Forms and procedures
Except for forms and procedures relating to appeals, the Planning Board
shall have authority to adopt and revise forms, charts and other documents
for the administration of this Ordinance, and to adopt and revise
administrative procedures consistent with the provisions of this Ordinance.
-1>-
1351 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: l l-May-19
Amended: 11 Jul-20
Amended: 1 \-May-24
l..9.st Amended: 07-Jun-25
ARTICLE 14: ZONING BOARD OF APPEALS
]Am i. 26_-Mar-01; Am2. _25-M_ar-02; Am6. 24-Ma!:-08]
14.1. EsTABLISHMENT AND ORGANIZATION OF ZoNING BOARD OF APPEALS
There shall be a Zoning Board of Appeals, consisting of five (5) regular members
and two (2) associate members, appointed by the Selectboard. Only residents of
the Town of Castine shall be eligible to serve on the Zoning Board of Appeals.
Neither a municipal officer nor the spouse thereof may be eligible for appointment
as a regular or associate member of the Zoning Board of Appeals. ;~m.ii
A regular member shall be appointed by the Selectboard for a term of five (5)
years. An associate member shall be appointed for a term of one {l) year. So far
as possible, the terms of regular members shall be arranged so that the term of at
least one (1) regular member will expire each year. The Selectboard may dismiss,
prior to the expiration of his/her term, a regular or associate member for just
cause, after notice and hearing. ),\m_,_LJ
In the absence or ineligibility of a regular member an associate may act as a
regular member through appointment by the Chair. In the event of the
resignation or dismissal by the Selectboard of a regular or associate member, the
Selectboard shall fill the vacancy as soon as possible, by appointment. [Am _l,
The Zoning Board of Appeals in existence at the time of enactment of this
Ordinance is continued and its members are hereby appointed to serve under
this Ordinance in that capacity and for the balance of their previously appointed
terrns. :,\:::.L
The Zoning Board of Appeals shall keep minutes of its proceedings, recording the
vote of each member on all matters decided by it. The minutes of the Zoning
Board of Appeals and all correspondence, testimony and documents related to
the appeal shall be a public record. Three (3) members of the Zoning Board of
Appeals are required for a quorum. A concurring vote of three (3) members shall
be required to grant a variance. Any application not receiving three (3) votes in
favor of its granting shall be deemed denied. A member who abstains or is
ineligible to vote shall not be counted to determine a quorum. The Zoning Board
of Appeals shall be governed by the procedures in Title 30-A M.R.S.A., § 2691,
and this Ordinance. {,\:-r1 J;' .1~n . ..?,i
1361Page
Zoning Ordinance ---- Adopted: 28-Mar-2000
Amended. 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov- 10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 11-Jul-20
Amended: l l-May-24
Las\ Amended: 07-Jun-25
The Zoning Board of Appeals may adopt and/or revise any forms, bylaws, and/or
procedural rules not in conflict with applicable law and this Ordinance. The
Board shall file originals of all such forms, bylaws, and/or procedural rules with
the Town Clerk, who shall make copies of each and every such document to be
made available, at the published copying cost, to any person making written
request therefore during regular business hours. Such documents may be read in
the Town Office by any person during regular business hours upon oral request
to the Town Clerk. :Am__:_J i !_\.!J.1__1!
A question of whether a member has a conflict of interest or bias deemed to
disqualify the member from participating in the Board's consideration of a
particular matter shall be decided by the majority vote of the Zoning Board of
Appeals, excluding the member challenged. A member who is either disqualified
by the vote of the Zoning Board of Appeals or who has recused himself/herself
shall abstain entirely from the deliberations of the board and shall not vote on
the matter giving rise to his/her disqualification or recusal. 0222-_._1_,
14 .2. POWERS AND DUTIES
A.
Administrative appeals
To hear and decide appeals alleging error by the CEO and/or Planning
Board in any written order, written determination, final written decision
including a notice of violation issued by the CEO under Section 12.2.A}, or
failure to act, where action is required, in the administration of this
Ordinance. The Board of Appeals may affirm or reverse the order,
determination or decision appealed from or may remand the matter to the
CEO or Planning Board, as appropriate, for correction or action in
accordance with the order of the Zoning Board of Appeals. A decision of the
Zoning Board of Appeals other than a remand to the CEO or Planning Board
constitutes final administrative action, subject to appeal to the Superior
Court under Section 14.4, and is binding on parties, not advisory. The
Board of Appeals does not have authority to review action or inaction of the
Selectboard under Section 12.3. !_J_rn. ;__
B.
Variance appeals
137jPage
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-!O
Amended: 02-Nov- JO
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended· ll-May-19
Amended: I 1-Jul-20
Amended: 11-May-24
Last Amended: 07 ✓un-25
To hear and decide appeals for variances made for {a) reasons of physical
disability and (b) relief from dimensional standards of the Ordinance when
undue hardship is alleged. [Arg_Ji
1.
Disability variances
The Zoning Board of Appeals may grant a variance to an owner of a
dwelling for the purpose of making that dwelling accessible to a person
with a disability who resides in or regularly uses the dwelling pursuant
to Title 30-A M.R.S.A. § 4353(4-A), as amended.
2.
Variances of dimensional standards for practical difficulty
The Zoning Board of Appeals may grant a variance from the
dimensional standards of this ordinance pursuant to Title 30-A
M.R.S.A. § 4353(4-C), as amended when strict application of the
ordinance to the applicant and the applicant's property would cause a
practical difficulty.
3.
Limitations on variances
The Zoning Board of Appeals shall strictly limit the grant of a variance
so as to comply with the provisions of this ordinance, and, in so doing,
may impose specific conditions. The party to whom a variance is
granted shall strictly comply with all conditions. ,.-':,D:;,...'...'
4.
Variances recorded
138jPage
When the Zoning Board of Appeals grants a variance under this
section, a certificate bearing the name of the current property owner,
identifying the property by the reference to the last recorded deed in its
chain of title and indicating that a variance, including any conditions
on the variance, has been granted and the date of the granting, shall be
prepared by the Board of Appeals in recordable form. The certificate
must be recorded by the landowner in the Hancock County Registry of
Deeds within ninety (90) days of the date the variance is granted, or the
variance is void. A variance is neither effective nor valid until duly
recorded as provided in this subsection. No permit shall be issued until
it is established that the variance has been recorded. A variance, after
Zontng Ordinance -Adopted: 28-Mar-2000
Amended; 26-Mar-Ol
Amended: 25--Mar-02
Amended· 07-May-02
Amended: 04-Apr·05
Amended: 26-Mar·07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-l.0
Amended; 02-Nov-l.O
Amended· 26-Mar- l.l.
Amended: 01--Jun-l.3
Amended: 23-Sept 13
Amended, 11-May·19
Amended: l 1-Jul-20
Amended: l.l.-May--24
Last Amended: 07 -Jun-25
being granted and duly recorded as prescribed, shall become void if the
permit to which the variance applies either becomes void under the
provisions of Section 8.2.J of this Ordinance or expires under the
provisions of Section 9.11 of this Ordinance. !Am. r, :.\rn.2'
5.
Shoreland Overlay District- Notice of Variance to DEP
A copy of each variance request, including the application and all
supporting information supplied by the applicant, where such variance
applies to structures or land within the Shoreland Overlay District, shall
be forwarded by the CEO to the Commissioner of the Department of
Environmental Protection at least twenty (20) days prior to action by the
Board of Appeals. Any comments received from the Commissioner prior
to the action by the Board of Appeals shall be made part of the record
and shall be taken into consideration by the Board of Appeals. __ \m_,__12!
A copy of any variance granted by the Zoning Board of Appeals shall be
submitted by the CEO to the Department of Environmental Protection
within seven (7) days of the board's decision, where such variance
applies to structures or land ·within the Shoreland Overlay District.
'_J,,r,J,-,
14.3. APPEAL PROCEDURE
A.
Time limit for appeal
Application for an administrative appeal must be made by an aggrieved
person within thirty (30) days of the date of the decision appealed from, and
not otherwise. '~'li..J
B.
Written notice of appeal
Any appeal shall be made by filing with the Zoning Board of Appeals, on the
official form available at the Town Office, a detailed written statement
indicating the relief requested and why it is contended it should be granted,
with supporting documentation attached. _-~w _
_j
139IPage
Zonmg Ordinance -Adopted: 28 Mar-2OOO
Amended: 26-Mar-O1
Amended: 25-Mar-O2
Amended: O7-May-O2
Amended: O4-Apr-O5
Amended: 26-Mar-O7
Amended: 24-Mar-O8
Amended· O4-Apr-O9
Amended: 27-Mar-lO
Amended: O2-Nov- lO
/\mended 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May 19
Amended: 11-Jul-2O
Amended: l l-May-24
Last Amended: O7-Jun-25
C.
Hearing notices
Notice shall be sent by certified mail/ return receipt requested or hand
delivered to the appellant (including his/her representative), and the
owner(s) of property, if different from the appellant, which is the subject of
the appeal, no later than fourteen ( 14) days prior to the date set for hearing.
Notice by first class mail shall also be sent to abutters and any owner of
property which has a lot line within 150 feet or less from a lot line of the
property which is the subject of the appeal, no later than fourteen (14) days
prior to the date set for hearing. Notice shall be sent to the address shown
on the Town's tax card for the person named as the property owner. :_Am.J_:
'.\rnJ.1,
Notice to Municipal Officers and concerned To¼Tl officials shall be given by
the posting in the Town Office no later than fourteen (14) days prior to the
date set for hearing. _irn X
Notice by the Zoning Board of Appeals giving the date, time, place and a
brief statement of the purpose of the hearing shall be placed in a newspaper
of general circulation in the local area for publication on a date no later than
fourteen {14) days prior to the date set for hearing. :3-rn_l_
D.
Record of the case
Upon receipt of notice of an appeal the CEO shall transmit to the Zoning
Board of Appeals all papers and information in any form which constitute
the complete record of the request, decision, action or failure to act which is
said to have given rise to the appeal. [2,_rn.j_,
E.
Public hearing
A public hearing shall be held by the Zoning Board of Appeals within thirty-
five (35) days from the date of receipt of a completed appeal, with payment of
the prescribed fee, in the Town Office of Castine, Maine 04421 . .\rn. 11 ,.\rn_r.:,:
F.
Hearing by Zoning Board of Appeals
1.
The person filing an appeal, who may be represented by an agent or
attorney, shall have the burden of proof. The Zoning Board of Appeals
shall consider the evidence in the public record and any relevant
140 I P a g e
Zoning Ordmance - Adopted: 28-Mar-2000
Amended: 26--Mar-01
Amended; 25-Mar--02
Amended: 07-May-02
Amended: 04"Apr-05
Amended: 26-Mar--07
Amended: 24--Mar-08
Amended· 04--Apr-09
Amended: 27--Mar-10
Amended: 02--Nov-10
Amended: 26-Mar--11
Amended: 01-Jun--13
Amended: 23-Sept--13
Amended: l 1-May-19
Amended: 1 l-Jul-20
Amended· 11-May-211-
La.st Amended: 07--Jun.25
evidence offered by a person appearing at and participating in the
hearing. An abutter or other person with standing may be made a
party to the appeal if he/ she or his /her representative appears and
participates in the hearing of the appeal. ,Jm-:l.'
2.
The Board has filed bylaws with the Town Clerk, which shall be
available to the public. Said bylaws contain the hearing procedures of
the Zoning Board of Appeals. The Board may revise its bylaws from
time to time, without the need to amend this Ordinance, and shall any
such revised bylaws with the Town Clerk. ;,}n._.L
3.
Following the public hearing of an appeal, the Zoning Board of Appeals
may reverse or affirm the findings of the CEO and/ or Planning Board. A
decision of the CEO or Planning Board may be reversed only upon
condition that the decision or failure to act was contrary to the specific
provisions of this ordinance. In making its decision the Zoning Board of
Appeals may consider evidence de nova as well as the record of the case
submitted under Section 14.3.4, it being expressly declared in this
Ordinance that the Board may what are described as "hybrid
proceedings" in the opinion of the Maine Supreme Judicial Court in
Stewart v. Town of Sedgwick, 200ME 157,757 A.2d 773,_and may
interpret the provisions of the ordinance. Such interpretations shall
thereafter be binding upon the CEO and planning board. Hearings shall
not be continued to other times except for good cause. :,t_.:c,._L
4.
Within thirty-five (35) days after the close of the hearing the zoning
board of appeals shall reach its decision, which shall be issued in
writing within seven (7) days thereafter. ;,._\.rrl._L ~1JJ\
141 I Pa g e
A decision by the Zoning Board of Appeals shall only be made in a
public hearing or meeting. It shall include a written statement of the
board's findings of fact and conclusions of law and the board's order,
which shall become a matter of public record. Copies of the written
decision shall be mailed by certified mail/ return receipt requested or
hand delivered, to the appellant or his/her designated representative,
to the owner(s) of property, if different from the appellant, which is the
subject of the appeal and to the Department of Environmental
Protection, when structures or land within the Shoreland Overlay
District is the subject of the appeal, within seven (7) days from the date
Z<lrnng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Alnendec!; 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
i\rnended: 27-Mar-10
Amended: 0'2-Nov-10
Amended: 26-Mar- l 1
Amended· O!-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: l l-Jul-20
!\mended: l 1-May-24
Last Amended: 07 -Jun-25
on which the board reaches its decision. On the date of mailing to the
appellant, the CEO, Planning Board and chair of the Selectboard shall
receive copies of the decision by posting them in the Town Office in the
mailboxes customarily used for those officers and officials. l,\m. ! 1 [_.\rnJi,
Should the decision of the Zoning Board of Appeals so require, the
Board's order shall include instructions either to the Planning Board
immediately to issue site plan approval to the CEO and/ or to the CEO
immediately to issue a permit, as applicable. r ~m.,.Ji
G.
Reconsideration
The Zoning Board of Appeals has the opportunity, but no obligation, to
reconsider its decision. The vote of the board to reconsider, which may be
upon its own motion or the motion of a party, and any action taken on that
reconsideration must occur and be completed within forty-five (45) days of
the vote on the original decision. A request for reconsideration must be filed
within ten (10) days of the decision to be reconsidered. As provided in Title
30-A M.R.S.A., § 2691, the board may conduct additional hearings and
receive additional evidence and testimony. :.-\rn._ ... :, \rn.11,;
14.4. APPEAL TO SUPERIOR COURT
Appeals of decisions of the Zoning Board of Appeals to the Superior Court are
governed by Title 30-A M.R.S.A., § 2691. , \m. i
142 /Page
Zoning Ordinance - Adopted. 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended: 07-May-02
Amended· 04"Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended, 04-Apr-09
Amended; 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: l l-Jul-20
Amended: l 1-May-24
l..ast Amended: 07-Jun-25
ARTICLE 15: DEFINITIONS
[Am L 26-Mar-0!_;_Am2. 25-Mar-0J.;_ Am3. 07-Ml!,Y-0~AmS._26-Mar-07; Arn_t5_,_24-Ml!!-08_;_
Am7--'----04-.&pr-0..2_;A,ml0. 26-Mar-l_!_;_ Am.13 Il-Ma.v:19;._Am.15 ll-Ma_y-24;_bm.16 07-Jun-:;i§J
15.1. For the purpose of interpreting the Subdivision Ordinance and Zoning
Ordinance, the following terms, phrases and words, unless their context
requires otherwise, shall be defined as follows; first as set forth below, second
in accordance with their generally accepted technical meaning within the
involved scientific disciplines, third as defined by Maine Statues, and fourth
their common dictionary meaning. ! ~iolf).'
15.2. The present tense when used includes the future; the singular includes the
plural; the word " shall " means mandatory; the word "may" is permissive; the
words "used" or "occupied" include the words "intended", "designed" or
"arranged to be used or occupied"; the word "structure" includes the word
"building"; and the word "lot" includes the word "plot."
15.3. The word "dwelling unit" as used in this Ordinance is synonymous to the word
"lot."
15.4. It is intended that this ordinance not be gender specific. Thus, when nouns or
pronouns indicate or imply a male or female, such use shall also mean the
other gender.
100 YEAR FLOOD: The highest level of flood that, on the average, is likely to occur once
every 100 years.
ABUTTER/ ABUTTING: Having a common boundary with, including lots which meet
only at the corners. Streets, alleys or rights of way shall be deemed not to separate
lots, and lots which would otherwise abut except for the width of an intervening street
shall be deemed to abut.
ACCESS: A means of approach or entry to or exit from property.
ACCESSORY DWELLING UNIT: A self-contained dwelling unit located -within, attached to
or detached from a single-family dwelling unit located on the same parcel of land.
_."3l1:-'----'--.~-
143 IP age
ZDning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04 Apr-09
Amended. 27-Mar-10
Amended: 02-Nov-[O
Amended: 26-Mar-1 I
Amended: OJ-Jun-13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: ll-Jul-20
Amended. 11-May-24
Las\ Amended: 07-Jun-25
AFFORDABLE HOUSING DEVELOPMENT: i~\!_Il__l__:;i]
~ For rental housing, a development in which a household whose income does not
exceed 80% of the median income for the area as defined by the United States
Department of Housing and Urban Development under the United States
Housing Act of 1937, Public Law 75-412, 50 Stat. 888, Section 8, as amended,
can afford 51 % or more of the units that the developer designates as affordable
in the development without spending more than 30% of the household's
monthly income on housing costs; and /111]_lJi
B. For o-wned housing, a development in which a household whose income does
not exceed 120% of the median income for the area as defined by the United
States Department of Housing and Urban Development under the United States
Housing Act of 1937, Public Law 75-412, 50 Stat. 888, Section 8, as amended,
can afford 51 % or more of the units that the developer designates as affordable
in the development without spending more than 30% of the household's
monthly income on housing costs. 1.Arn.1 _ _5_!
AGGRIEVED PARTY: An owner of land whose property is directly or indirectly affected by
the granting or denial of a permit or variance under this Ordinance; a person whose
land abuts land for which a permit or variance has been granted; or any other person
or group of persons who have suffered particularized injury as a result of the granting
or denial of such a permit or variance.
AGRlCULTURE: The production, keeping or maintenance for sale or lease, of plants
and/or animals, including but not limited to: forages and sod crops; grains and seed
crops; dairy animals and dairy products; poultry and poultry products; livestock;
fruits and vegetables; and ornamental and green house products. Agriculture does not
include forest management and timber harvesting activities or the construction,
creation or maintenance of land management roads.
ALTERATION: As applied to a building or structure, a change or rearrangement in the
structural parts or in the means of egress; or an enlargement, whether by extending
on a side or by increasing in height; or by the moving from one location or position to
another.
ANIMAL HUSBANDRY: The commercial raising of domestic animals or livestock for
agricultural purposes. This term does not include the commercial raising or boarding
144 JP age
Zoning Ord ma nee - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May·02
Amended: 04-Apr-05
Amended; 26-Mar-07
Amended: 24-Mar-08
Amended. 04-J\pr-09
Amended· 27-Mar-10
Amended; 02-Nov-10
Amended: 26-Mar- 11
Amended: 01-Jun-l3
Amended: 23-Sept-13
Amended. ll-May-19
Amended: ll-Ju.l-20
Amended: I 1-May-24
Last Amended: 07 .Jun-25
of domestic animals for domestic purposes such as kennels; these domestic uses shall
be deemed home occupations.
APPEAL: A means for obtaining review of a decision, determination, order or failure to
act pursuant to the terms of this Ordinance as expressly authorized by the provisions
of this Ordinance.
APPLICANT: The person, partnership, trust, fiduciary, business entity, agent of the
owner or corporation applying for CEO or Planning Board approval. lt may also be a
proposed purchaser or an agent of a proposed purchaser whose purchase and sales
agreement gives him the right to apply as a condition of sale.
AQUACULTURE: The growing or propagation of harvestable freshwater, estuarine, or
marine plant or animal species.
ATTIC: That part of a building which is immediately below, and wholly or partly within,
the roof framing.
AUTO SERVICE STATION/ FILLING STATION: A commercial establishment open to the
public, supplying engine fuel at retail, direct to the customer; the sale of lubricants,
minor accessories and minor services for automobiles may be included.
AUTO REPAIR GARAGE: A commercial establishment open to the public where, with or
without the attendant sale of engine fuels, the following services may be carried out:
general repair, engine rebuilding, rebuilding or reconditioning of motor vehicles;
collision service, such as body, frame, or fender straightening and repair; overall
painting and undercoating of automobiles.
AUTOMOBILE GRAVEYARD: An "automobile graveyard" as defined in Title 30-A M.R.S.A.,
§ 3752 as amended. ',_'\m_i?_i
AVERAGE DAILY TRAFFIC (ADTJ: The average number of vehicles per day that enter and
exit the premises or travel over a specific section of road.
BASEMENT: The substructure of a building with a floor-to-ceiling height of 6 feet or more
and having more than 50% of its volume below the existing ground level which may or
may not be used for living space . .=)._,10
145 IP age
Zonmg Ordinance -Adopted: 28-Mar-2000
Amended. 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended· 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: Ol-Jun-13
Amended: 23-Sept- 13
Amended· l l-May-19
Amended: l l-Jul-20
Amended· l l-May-24
Last Amended: 07-Jun-25
BED AND BREAKFAST: A facility in which breakfast is the only meal served and in which
there are four (4) or fewer rooms, serving eight (8) or fewer people, available for rent.
BOAT LAUNCHING FACILITY: A facility designed primarily for the launching and landing of
watercraft, and which may include an access ramp, docking area, and parking spaces
for vehicles and trailers. ,f_\m_,::;1
BUFFER AREA: Units of land, together with a specified type and amount of vegetative
planting thereon and any structures which may be required between land uses to
eliminate or minimize conflicts between them.
BUILDING: Any roofed structure maintained or intended for use as shelter or enclosure
of persons, animals, goods or property of any kind. vVhere independent units with
separate entrances are divided by walls, each unit is a building.
BULK STORAGE: The storage of liquids, solids or gases which are received by tank
vessel, pipelines, tank car, or tank vehicle and are stored or blended in bulk.
CAMPGROUND: Any land area used to accommodate two (2) or more parties in
temporary living quarters including, but not limited to tents, recreational vehicles
and/or towed travel trailers. Accessory uses, subject to Site Plan Review, include
camper services and facilities such as shower and laundry facilities, electricity, fresh
water, propane and gas sales, ice, outlet for camping supplies and equipment,
recreational services, etc.
CAMPSITE, INDMDUAL PRNATE: An area of land which is not associated with a
campground, but which is developed for repeated camping by only one group not to
exceed ten (10) individuals and which involves site improvements which may include
but not be limited to a gravel pad, parking area, fireplace, or tent platform.
CANOPY: The more or less continuous cover formed by tree crowns in a wooded area .
. \rn._5_;
CERTIFICATE OF COMPLETION: An official document issued by the CEO pursuant to
Article 10 of the Zoning Ordinance, certifying completion of the project for which a
permit was obtained. A Certificate of Completion is not otherwise a certificate of
fitness, safety or suitability. ,\rn L'
CERTIFICATE OF OCCUPANCY: An official document issued by the CEO pursuant to
Article 10 of the Zoning Ordinance upon compliance with all necessary provisions of
1461 Pa g 8
ZoningOrdmance -Adopted; 28-Mar-2000
Amended: 26-Mar-01
Amended; 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended; 24-Mar-08
Amended. 04-Apr-09
Amended; 27-Mar-10
Amended: 02-Nov-10
Amended· 26-Mar-11
Amended: Ol-Jun-13
Amended; 23-Scpt-13
Amended. 11-May- 1 g
Amended; l 1-Jul-20
Amended. l l-May-24
Last Amended: 07-Jun-25
the Zoning Ordinance, allowing the property owner to occupy the premises. A
Certificate of Occupancy is not otherwise a certificate of fitness, safety or suitability.
,.\m.;
CHURCH: A building, together with its accessory buildings and uses, where people
regularly assemble for religious worship and which buildings, together with its
accessory buildings, and uses, is maintained and controlled by a religious body
organized to sustain public worship.
CLUSTER HOUSING: A subdivision (neighborhood) in which the required density and
open spaces are maintained in combination with a group of residences in close
proximity.
CLUSTER SUBDMSION: A subdivision in which the lot sizes are reduced below those
normally required in the zoning district in which the development is located in return
for the provision of permanent open space.
COASTAL WETLAND: All tidal and sub-tidal lands; all lands with vegetation present that
is tolerant of salt water and occurs primarily in salt water or estuarine habitat; and
any swamp, marsh, bog, beach, flat or other contiguous low land that is subject to
tidal action during the highest annual high tide level as identified in tide tables
published by the National Ocean Service. Note: All areas below the highest annual
tide level are coastal wetlands. These areas may consist of rocky ledges, sand and
cobble beaches, mud flats, etc., in addition to salt marshes and salt meadows. !.\m.:\
-.. -\rec. 7_
CODE ENFORCEMENT OFFICER (CEO): A person appointed by the Town Manager and
confirmed by the Board of Selectmen to enforce this Ordinance and to assist the
Planning Board in its administration. _-\qJ.c.')_J
COMMERCIAL USE: The use of lands, buildings, or structures, other than a "home
occupation," defined below, the intent or result of which activity is the generation of
revenue from the buying and selling of goods and/or services and the use of golf
courses and other recreational facilities for which a payment is due from users; does
not include rental of residential buildings and/or dwelling units other than boarding
houses, bed & breakfasts, inns and hotels.
COMMON OPEN SPACE: Common elements or land within or related to a subdivision, not
individually owned, which is designated & intended for the common use or enjoyment
of the residents of the development or the general public. It may include
1471Page
Zomng Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-10
Amended: 02 Nov-10
Amended: 26-Mar- l l
Amended: 01-Jun- \3
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 1 l-Jul-20
Amended: ll-May-24
Last Amended: 07-Jun-25
complementary structures and improvements, which are typically used for
maintenance and operation of open space or for outdoor recreation.
COMPLETE APPLICATION: An application shall be considered complete upon submission
of the required fee and all information required by this Ordinance or by a vote by the
Board to waive the submission of required information.
COMPLETE SUBSTANTIAL CONSTRUCTION: The construction of no less than thirty percent
of the costs of the proposed improvements within a subdivision. If the subdivision is to
consist of individual lots to be sold or leased by the subdivider, the cost of
construction of buildings on those lots shall not be included. If the subdivision is a
planned unit development, or if the applicant proposes to construct the buildings
within the subdivision, the cost of building construction shall be included in the total
costs of proposed improvements.
COMPREHENSIVE PLAN: A document or interrelated documents containing the elements
established under Title 30-A M.R.S.A., § 4326, Sub-Sections 1 - 4, including the
strategies for an implementation program which are consistent with the goals and
guidelines established under Title 30-A M.R.S.A., Sub-Chapter II.
CURRENT EDITION: THE most recent version of the cited regulation, technical manual or
other publication.
DAY CARE FACILITY: As defined in Title 22 M.R.S.A., § 1673, as a house or other place
in which a person or combination of persons maintains or otherwise carries out a
regular program, for consideration, for any part of a day, providing care and protection
for three (3) or more children under the age of sixteen (16) unrelated to the operator,
not to include nursery schools, summer camps, formal public or private schools, and
further defined by the Department of Human Services as follows:
a. Day Care Center: A Day Care Facility as defined in State statutes for thirteen
( 13) or more children on a regular basis; and
b. Day Care Home: A Day Care Facility as defined in State statutes for three (3) to
twelve (12) children on a regular basis.
DECK: An accessory attachment to a principal structure with no roof or framed or
screened walls. It may contain railings with screening and gates to enclose pets or
children. , \m .5.i
1481 Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27 -Mar-10
Amended: 02-Nov-10
Amended· 26-Mar-ll
Amended· Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 I-May-19
Amended: 11-Jul-20
Amended. 11-May-24
Last Amended: 07 -Jun-25
DEDICATION: The transfer of property interests from private to public ownership for a
public purpose. The transfer may be fee-simple interest or of a less-than-fee-simple
interest, including an easement.
DEER FENCES: FENCES specially constructed to prevent deer from attacking gardens or
orchards. Such fences may be constructed of vertical posts of wood, steel or other
suitable material and of horizontally strung wire or coarse wire mesh between such
posts. No vegetation shall be allowed to grow upon and no other material may be
attached to such wire or wire mesh, and no solid material such as wooden planking or
woven matting may be fastened to or strung between posts at a height greater than six
(6} feet. '~n. l_'·
DENSITY: The number of dwelling units per acre or square foot of land.
Designated Growth Area: an area that is designated in the Town's Comprehensive
Plan as suitable for orderly residential, commercial, or industrial development, or any
combination of those types of development, and into which most development
projected over ten (10) years is directed. Designated growth areas may also be referred
to as priority development zones or other terms with a similar intent. , An-'--'---!5
DEVELOPED AREA: Any area on which a site improvement or change is made, including
buildings, landscaping, parking areas and streets.
DEVELOPMENT: A change in land use involving alteration of the land, water or
vegetation, or the addition or alteration of structures or other construction not
naturally occurring.
DIMENSIONAL REQUIREMENTS: Numerical standards relating to spatial relationships
including but not limited to setback, lot area, shore frontage and height. !~\:__;_, c_,,
DRAINAGE: The removal of surface or ground water from land by drains, grading or
other means. Drainage includes the control of runoff to minimize erosion and
sedimentation during and after development and includes the means necessary for
water supply preservation and prevention or alleviation of flooding.
DRIVEWAY: A vehicular access-way less than five hundred (500) feet in length serving
two single-family dwellings or one two-family dwelling.,'.-\~~~.
149 IP age
Zonmg Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 1 l-Ma_y-19
Amended. l 1-Jul-20
Amended: J l -May-24
Last Amended· 07-Jun-25
DwELLING: A room or group of rooms designed and equipped exclusively for use as
permanent, seasonal, or temporary living quarters and containing cooking, sleeping
and toilet facilities. The term shall include single-family, two-family and multiple-
family dwellings, mobile homes and rental units that contain cooking, sleeping, and
toilet facilities regardless of the time-period rented. Recreational vehicles are not
residential dwelling units.
-
Dwelling, Single Family: A room or group of rooms designed and equipped
exclusively for use as living quarters for only one (1) family at a time.
-
Dwelling, Two-Family: A detached or semi-detached building used as living
quarters by two (2) families living independently of each other.
-
Dwelling, Multi-Family: A building or portion thereof used as living quarters by
three (3) or more families living independently of each other and doing their own
cooking in the building, including apartments, group houses and row houses.
EARTH MOVING: Any displacement, addition or subtraction of earth (including loam,
clay, gravel, stone, etc.) from or to a given location.
EASEMENT: Authorization by a property owner for the use by another, and for a
specified purpose, of any designated part of the property.
EASEMENT, CONSERVATION: An easement for the purpose of including, retaining or
protecting natural, scenic or open space values of real property; assuring its
availability for agricultural, forest, recreational or open space use; protecting natural
resources; or maintaining air or water quality.
ENGINEER, PROFESSIONAL: An individual licensed by the State of Maine to engage in the
practice of professional engineering pursuant to Title 32 M.RS.A., Chapter 19, as
amended.
ENGINEER, TowN: Any Maine registered professional engineer employed or retained by
the Town either as staff or as a consultant.
ENGINEERED SUBSURFACE WASTEWATER DISFOSAL SYSTEM: A subsurface wastewater
disposal system designed, installed, and operated as a single wastewater unit to treat
2,000 gallons per day or more; or any system designed to treat wastewater with
characteristics significantly different from domestic wastewater. All such systems shall
be reviewed and approved by the Department of Health and Human Services prior to
the issuance of a permit by the Local Plumbing Inspector.
150\Page
Zoning Ordinance - Adopted: 28-Mar-2000
Amended: 26·Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- l l
Amended: 01-Jun- 13
Amended: 23-Sept-13
Amended: ll-May-19
Amended: 11-Jul-20
Amended: \ l-May-24
Last Amended: 07 -Jun-25
ENLARGEMENT: An addition to the height, floor area or the volume of an existing
building, an increase in the size of any other structure, or an increase in that portion
of a tract of land occupied by an existing use.
EsSENTIAL SERVICES: Gas, electrical or communication facilities; home generators;
steam, fuel, electric power or water transmission or distribution lines, towers and
related equipment; telephone cables or lines, poles and related equipment; gas, oil,
water, slurry or other similar pipelines; municipal sewage lines, collection or supply
systems; and associated storage tanks. Such systems may include towers, poles,
wires, mains, drains, pipes, conduits, cables, fire alarms and police call boxes, traffic
signals, hydrants and similar accessories, but shall not include service drops or
buildings which are necessary for the furnishing of such services. 1,\n_'cc.,~) r.-\m.li,
EXPANSION OF A STRUCTURE: An increase in the height, floor area or volume of a
structure, including all extensions such as, but not limited to attached decks, garages,
porches, and greenhouses. To be attached the extension must abut a common wall
with the original structure.
ExPANSION OF USE: The use of more volume, floor area or ground area devoted to a
particular use. In the Shoreland Overlay District, expansion of a use shall include the
addition of four (4) or more weeks to the operating season of a use. ;,1,_r,;_;ji
FAMILY: Two or more persons occupying a residence, who are related either by
marriage, domestic partnership or consanguinity. 0.!IL.0.;
FARMERS' MARKET: A site or building used by two or more individual vendors,
primarily farmers, for the direct sale to consumers of their products such as nursery
products, natural products, fruits, vegetables, eggs, dairy products, meat, poultry,
fish, grain, honey, maple products, beverages, prepared foods and crafts.
FENCE: An above-ground structure, including stone or brick walls, constructed for the
purpose of dividing, defining or enclosing a lot or portion of a lot.
FLOODPLAIN: Either riverine or inland depression areas. Riverine floodplains are those
areas contiguous to a river, stream, or stream bed whose elevation is greater than the
normal water pool elevation but equal to or lower than the projected one hundred
(100) year flood elevation. Inland depression floodplains, not associated with a stream
system, are low points to which surrounding lands drain.
151\Page
Zoning Ordinance -Adopted. 28-Mar-2000
Amended. 26-Mar Ol
Amended; 25-Mar-02
!',mended; 07-May-02
Amended: 04-Apr-05
Am.ended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended: 27-Mar-IO
Amended, 02-Nov-JO
Amended: 26-Mar- ll
Amended: OI-Jun-13
Amended: 23 Sept-13
Amended: ! I-May-19
/\mended: 1 l -Jul-20
Amended· ll-May-24
La.st Amended: 07-Jun-25
FLOODWAY: The channel of a river or other watercourse and adjacent land areas that
must be reserved in order to discharge the 100 year flood without cumulatively
increasing the water surface elevation by more than one foot in height. 1 ~rn5
FLOOR AREA: The sum of the horizontal surface areas of a structure enclosed by
exterior walls, plus the horizontal area of any unenclosed portions of a structure such
as porches and decks.
FLOWING WATER: Surface water within a stream channel that has a perceptible flow
and is substantially permanent in nature. Such waters are commonly referred to as
rivers, streams, and brooks.
FORESTED WETLAND: A freshwater wetland dominated by woody vegetation that is six
(6) meters tall [approximately twenty (20) feet) or taller. :~\.Q_>-3:
FOUNDATION: The supporting substructure of a building or other structure, excluding
wooden sills and post supports, but including but not limited to basements, slabs,
sills, posts, frost walls or other base consisting of concrete, block, brick or similar
material. !,:\m.:'>:
FRESHWATER WETLAND: Freshwater swamps, marshes, bogs, and similar areas, other
than forested wetlands, which are:
a. Often (10) or more contiguous acres; or of less than ten (10) contiguous acres
and adjacent to a surface water body, excluding any river, stream, or brook such
that in a natural state, the combined surface area is in excess of ten (10) acres;
and
b. Inundated or saturated by surface or ground water at a frequency and for a
duration sufficient to support, and which under normal circumstances do support,
a prevalence of wetland vegetation typically adapted for life in saturated soils.
Freshwater wetlands may contain small stream channels or inclusions of land that do
not conform to the criteria of this definition.
FRONTAGE, SHORE: The horizontal distance, measured in a straight line, between the
intersections of the side lot lines of a lot bordering on a water body or wetland with the
shoreline. ,'.\Iri_:i,
152!Page
Zonmg Ordinance - Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Arn.ended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-OCJ
Amended: 27-Mar-10
Amended: 02"Nov-10
Amended: 26-Mar-11
Amended: OJ-Jun-13
Amended: 23-Sept-13
Amended: I 1-May-19
Arnended: ll-Jul"20
Amended: l l-May-24
Last Amended: 07-Jun-25
FuNCTIONALLY WATER-DEPENDENT USE: Those uses that require, for their primary
purpose, location on submerged lands or that require direct access to, or location in,
coastal or inland waters and that cannot be located away from these waters. These
uses include, but are not limited to, commercial and recreational fishing and boating
facilities, excluding recreational boat storage buildings, fmfish and shellfish
processing, fish storage and retail and wholesale fish marketing facilities, waterfront
dock and port facilities, shipyards and boatbuilding facilities, marinas, navigational
aids, basins and channels, retaining walls, industrial uses dependent upon water-
borne transportation or requiring large volumes of cooling or processing water that
cannot be reasonably be located or operated at an inland site, and uses that primarily
provide general public access to coastal or inland waters. Does not include private
non-commercial boathouses, storage sheds, etc. !J._m.J__ .ijrn._3.
GR.ADE: In relation to buildings, the average of the finished ground level at the center
of each wall of a building.
GREAT PoND: Any inland body of water which in a natural state has a surlace in
excess often (10) acres, and any inland body of water artificially formed or increased
which has a surface area in excess of thirty (30} acres, except where the artificially
formed or increased body of water is completely surrounded by land held by a single
owner.
GREAT POND CLASSIFIED GPA: Any great pond classified GPA, pursuant to Title 38
M.R.S.A. Article 4-A § 465-A. This classification includes some, but not all
impoundments of rivers that are defined as great ponds. :tm.2.'
GROUND COVER: Small plants, fallen leaves, needles and twigs, and the partially
decayed organic matter of the forest floor .. :_-\m.iJ!
HEIGHT: The vertical distance between the mean elevation of the original (prior to
construction) grade at the building and the highest point of the roof. For buildings in
the Shoreland Overlay District, the vertical distance between the mean elevation of the
original grade at the downhill side of the building and the highest point of the roof.
For those structures without roofs, the highest point of the structure. For buildings
with multiple roofs, each roof shall be considered in relation to the original grade upon
which that part of the structure rests. ij_0:_,_,':i
HIGH INTENSITY SOIL SURVEY: A map prepared by a certified Soil Scientist, identifying
the soil types down to one-eighth (118) acre or less at a scale equivalent to the
153jPage
Zoning Ordinance - Adopted; 28-Metr-2000
Amended; 26-Mar-01
Amended. 25-Mar-02
Amended: 07 -May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended· 24-Mar-08
Amended; 04-Apr-09
Amended: 27 Mar- JO
Amended: 02-Nov-10
Amended·. 26-Mar-ll
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May- 19
Amended. I 1-Jul-20
Amended: 11,May-24
Las! Amended; 07-Jun-25
subdivision plan submitted. The soils shall be identified in accordance with the
National Cooperative Soil Survey. The map shall show the location of all test pits used
to identify the soils and shall be accompanied by a log of each sample point identifying
the textural classification and the depth to a seasonal high-water table or bedrock at
that point. Single test pits and their evaluation for suitability for subsurface
wastewater disposal systems shall not be considered to constitute high intensity
surveys.
HOME OCCUPATION: An occupation or profession which can be conducted within the
principal residential dwelling unit or an accessory structure on the premises where the
applicant resides and: 1) which is clearly incidental to and compatible with the
residential character of the property and neighborhood; 2) which employs no more
than three (3) persons other than family members residing in the home; and 3) which
meets all the requirements of this Ordinance. !.\m .. \
HOSPITAL: An institution providing health services, primarily for inpatients, and
medical or surgical care of the sick or injured, including as an integral part of the
institution, such related facilities as laboratories, outpatient departments, training
facilities, central service facilities and staff offices.
HOTEL AND INNS: A facility in which more than four (4) but no more than twenty-four
(24) rooms are available for rent. Meals may be served.
IMPERVIOUS SURFACE: Surfaces which do not absorb water, specifically all buildings,
parking areas, driveways, roads, sidewalks and any areas of concrete or asphalt. In
the case of lumber yards, areas of stored lumber constitute impervious surfaces.
INCREASE IN NON-CONFORMITY OF A STRUCTURE: Any change in the structure or
property which causes further deviation from the dimensional standard(s) creating the
non-conformity such as, but not limited to, reduction in water body or yard setback
distances, increase in lot coverage, or increase in height of a structure. Property
changes or structure expansions which either meet the dimensional standard, or
which causes no further increase in the linear extent of non-conformity of the existing
structure shall not be considered to increase non-conformity. {For example, there is
no increase in non-conformity within a setback if an expansion extends no further into
the required setback area than does any portion of the existing non-conforming
structure.) A structure may expand laterally provided the expansion extends not
closer to the point from which the setback is measured. Included in this allowance
are expansions which fill in irregularly shaped structures. ,,;m_'i.
1541 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended· 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: OJ-Jun- 13
Amended: 23-Sept-13
Amended: ll-May-19
Amend,:d. ll-Jul-20
Amended: I l-May-24
La.st Amended: 07-Jun-25
INDUSTRIAL: The assembling, fabrication, finishing, manufacturing, packaging or
processing of goods, or the extraction of minerals. _A;n,.3.
INSTITUTIONAL: A non-profit or quasi-public use, or institution such as a church,
library, public or private school, hospital, municipally owned or operated building,
structure or land used for public purposes . . --\x,_.5;
JUNKYARD: As used in this Ordinance the term junkyard means either:
a. An "automobile graveyard" as defined in Title 30-A M.R.S.A., § 3752 as
amended; or
b. A ''junkyard" as defined in Title 30-A M.R.S.A., § 3752 as amended. ;,\m 5
LEVEL OF SERVICE: A qualitative measure that incorporates the collective factors of
speed, travel time, traffic interruptions, freedom to maneuver, safety, driving comfort
and convenience, and operating costs provided by a highway facility under a particular
volume condition, as established by the Institute of Transportation Engineer's
Transportation and Traffic Engineering Handbook, 2nd edition.
LICENSED FORESTER: A forester licensed under Title 32 M.R.S.A. Chapter 76. [A,11,_.-'i:
LOADING AREA: An off-street space or berth on the same lot with a building or
contiguous to a group of buildings for the temporary parking of a commercial vehicle
while loading or unloading merchandise or materials, and which abuts upon a street,
alley or other appropriate means of access.
LOCAL PLUMBING INSPECTOR (LPI): A person appointed by the Selectboard to enforce
the Maine Internal Plumbing Rules and the Maine Subsurface Wastewater Disposal
Rules. ,,\;r_l_J_;
LoT: A parcel of land undivided by any street or public road and occupied by, or
designated to be developed for, one (1) building or principal use and the accessory
buildings or uses incidental to such building, use, or development, including such
open spaces and yards as are designed, and arranged or required by this Ordinance
for such building, use, or development.
LoT AREA: The area of land enclosed within the boundary lines of a lot, minus land
considered not suitable for development under the provisions of this Ordinance
155IPage
Zonmg Ordinance - Adopted; 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended· 07-May-02
Amended: 04 Apr-05
Amended: 26·Mar-07
Amended. 24-Mar-08
Amended. 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amended: 23-Sept-13
Amended: I 1-May-19
Amended: 11-Jul 20
Amended: 1 l-May-24
Last Amended: 07-Jun-25
including land below the normal high-water line of a water body or upland edge of a
wetland and areas beneath roads serving more than two lots. :,\r_r_1_,jl
LoT COVERAGE: The maximum combined ground floor area of all principal and
accessory buildings on a lot, divided by the area of such lot, the result expressed as a
percentile. In the Shoreland Overlay District lot coverage also includes all
unrevegetated areas. f_.:l,rn. \J
LOT LINE: A line bounding a lot which divides one lot from another, or from a street or
any other public or private space, as defined below:
a. Front Lot Line: That lot line which fronts upon or runs most nearly parallel to
the nearest public highway, road or street. \:\i_Q,_l:
b. Rear Lot Line: That lot line which is parallel to and most distant from the front
lot line of the lot; in the case of an irregular, triangular, or gore-shaped lot, a line
twenty {20) feet in length, entirely within the lot, parallel to and at the maximum
possible distance
from, the front line shall be considered to be the rear lot line. In the case of lots
which have frontage on more than one road or street, the rear lot line shall be
opposite the lot line along which the lot takes access to a street.
c. Side Lot Line: Any lot line other than a front or rear lot line.
LoT, NON-CONFORMING: A single lot of record which, at the effective date of adoption or
amendment of this Ordinance, does not meet the area or dimensional requirements of
this Ordinance.
LoT OF REcoRD! A lot the dimensions of which are contained in a deed, instrument or
plan recorded in the Hancock County Registry of Deeds.
LoT WIDTH: The horizontal distance between the side lot lines as measured at the road
frontage or the site of the principal structure, whichever results in the greater width.
LoT WIDTH, MINIMUM: The closest distance between the side lot lines of a lot. When
only two lot lines extend into the shoreland zone, both lot lines shall be considered to
be side lot lines.
MANUFACTURED HOUSING OR HOME: A structural unit or units designed to be used as a
dwelling and constructed in a manufacturing facility and then transported by the use
of its own chassis, or placed on an independent chassis, to a building site. For
156[Page
Zontng Ordinance -Adopted: 28-Mar-2000
Amended: 26--Mar-01
Amended, 25--Mar-02
Amended: 07--May-02
Amended: 04-Apr--05
Amended: 26-Mar--07
Amended: 24--Mar-08
Amended: 04-Apr-09
Amended: 27--Mar-10
Amended: 02-Nov--10
Amended: 26-Mar--11
Amended: Oi-Jun--13
Amended: 23--Sept- \3
Amended: 11--May-\9
Amended: 11--Jul-20
Amended. 11--May-24
Last Amended: 07--Jun-25
purposes of this Ordinance, three (3) types of manufactured housing will be referred
to:
a. Pre HUD Code Mobile Home: A structure constructed prior to June 15, 1976,
transportable in one or more sections which is 8 body feet or more in width and
is 32 body feet or more in length and which is built on a permanent chassis and
designed to be used as a dwelling with or without a permanent foundation
when connected to the required utilities and includes the plumbing, heating, air
conditioning and electrical systems contained therein.
c. HUD Code Mobile Home: A structure constructed after June 15, 1976, which
the manufacturer certifies is constructed in compliance with the United States
Department of Housing and Urban Development ("HUD") standard, meaning a
structure, transportable in one or more sections, which, in the traveling mode,
is 8 body feet or more in width and 40 body feet or more in length or, when
erected on site, is 320 or more square feet, and which is built on a permanent
chassis and designed to be used as a dwelling, with or without a permanent
foundation, when connected to the required utilities, including the plumbing,
heating, air-conditioning and electrical systems contained therein; except that
such term shall include any structure which meets all the requirements of this
paragraph except the size requirements and with respect to which the
manufacturer voluntarily files a certification required by the Secretary of the
United States Department of Housing and Urban Development and complies
with the standards established under the National Manufactured Housing
Construction and Safety Standards Act of 1974, 42 United States Code 5401, et
seq.
d. State Certified Modular Home: A structure the manufacturer certifies is
constructed in compliance with the State's Manufactured Housing Act and
regulations, transportable in one or more sections, that are not constructed on
a permanent chassis and are designed to be used as dwellings on foundations
when connected to required utilities, including the plumbing, heating air-
conditioning or electrical systems contained therein. Such homes may not be
more than one story in height but may have a non-habitable attic space.
MANUFACTURED HOUSING COMMUNITY: A parcel or adjoining parcels of land under
single ownership, which has been planned and improved for the placement of three or
more manufactured homes as defined above, where no more than 50% of the homes
are "State Certified Modular Homes" that are no more than one story in height but
1571Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended. 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended. 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar-11
Amended: 01-Jun-13
Amended· 23-Sept-13
Amended: 11-May-19
Amended. ll-Jul-20
Amended: ll-May-24
Last Amended: 07 -Jun-25
may have a non-habitable attic space and where at least 50% of the homes are "Pre
HUD Code Mobile Homes" or "HUD Code Mobile Homes", but shall not include a
construction camp or a campground. "Manufactured Housing Community" is
synonymous with "Mobile Home Park" as used in this Ordinance.
MARINA: A commercial wharf or other business establishment having frontage on
navigable water within the town and providing for hire offshore mooring or docking
facilities for boats as its principal use, and which may provide accessory services and
facilities such as boat and boat-related sales, boat hauling, repair and construction,
engine servicing, indoor and outdoor storage of boats and marine equipment, bait and
tackle shops, ice, water, and marine fuel.
MARKET: Premises in which produce, foodstuffs and/or manufactured goods are
offered for retail sale to the general public.
MARKET VALUE: The estimated price a property will bring in the open market and
under prevailing market conditions in a sale between a willing seller and a willing
buyer, both conversant with the property and with prevailing general price levels.
MINERAL ExPLORATION: Hand sampling, test boring, or other methods of determining
the nature or extent of mineral resources which create minimal disturbance to the
land and which include reasonable measures to restore the land to its original
condition.
MINERAL EXTRACTION: Any operation within any twelve (12) month period which
removes more than one hundred (100) cubic yards of soil, topsoil, loam, sand, gravel,
clay, rock, peat, or other like material from its natural location and to transport the
product removed, away from the extraction site.
MOBILE HOME PARK: See "MANUFACTURED HOUSING COMMUNITY" above.
MOTOR VEHICLE: Every vehicle which is self-propelled and designed for carrying
persons or property or which is used for the transportation of persons.
MOTOR VEHICLE, UNSERVJCEABLE: Any motor vehicle which is wrecked, dismantled,
cannot be operated legally on any Maine public highway, or which is not being used
for the purpose for which it was manufactured.
1581Page
Zoning Ordmance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended. 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended: 26-Mar- \ l
Amended· Ol-Jun-13
Amended: 23-Sept- 13
Amended: 11-May. [9
Amended. 1 hlul-20
Amended: 11-May-24
Last Amended: 07-Jun-25
MULTI-UNIT RESIDENTW,: A residential structure containing three (3) or more
residential dwelling units. l::.\.Ql.2!
NATIVE: Indigenous to the local forests. i \rn.0)
NEIGHBOR/ NEIGHBORING: An abutter or a property owner situated Vvithin one
hundred fifty (150) feet of a lot boundary. ;_,:_\iIUl!
NET REsIDENTIAL AREA: The total area available for the subdivision as shovm on the
proposed subdivision plan minus the area for streets or access.
NON-CONFORMING LOT: See "LOT, NON-CONFORMING" above. ,3_JE_._5_,
NON-CONFORMING STRUCTURE! See "STRUCTURE, NON-CONFORMING" below. !l.!11./jj
NON-CONFORMING USE: See "USE, NON-CONFORMING" below. '~\'""f:_,_,_~j
NORMAL HIGH-WATER LINE (NON-TIDAL WATERS): That line which is apparent from
visible markings, changes in the character of soils due to prolonged action of the water
or changes in vegetation, and which distinguishes between predominantly aquatic and
predominantly terrestrial land. Areas contiguous with rivers and great ponds that
support non-forested wetland vegetation and hydric soils and that are at the same or
lower elevation as the water level of the river or great pond during the period of normal
high-water are considered part of the river or great pond. Note: Acljacent to tidal
waters, setbacks are measured from the upland edge of the coastal wetland. :~\rn .. ~_-
NORMAL MAINTENANCE AND REPAIR: Any work necessary to maintain an improvement
or structure in its original or previously improved State or condition. Normal
maintenance and repair shall not include reconstruction, change in design, change in
structure, change in uses, change :in location, change in size or capacity.
NURSING HOME: A facility for the care of the aged or infirm person, or a place of rest
for those suffering bodily disorders; but not including facilities for surgical care or
institutions for the care and treatment of mental illness, alcoholism, or narcotics
addiction.
OPEN SPACE: Undeveloped natural, wooded or unwooded land.
1591 Page
Zoning Ordinance -Adopted· 28-Mar-2000
Amended· 26 Mar-OJ
Amende,:J: 25-Mar-D2
Amended: 07-May 02
Amended: 04-Apr--05
Amended. 26--Mar-07
Amended: 24--Mar-08
Amended: 04-Apr--09
Amended: 27-Mar--10
Amended: 02-Nov--10
Amended; 26--Mar-l 1
Amended: O!-Jun-13
Amended: 23-Sept--13
Amended: ll-May--19
Amended: l J-Jul-20
Amended: 1 J-M,,y--24
Last Amended· 07 -Jun-25
OPEN SPACE USE: A use which does not disturb the existing state of the land except to
restore this land to a natural condition.
OWNER: The person or persons having the right of legal title to, beneficial interest in, or
a contractual right to purchase a lot or parcel of land.
PARKING AREA (SH0RELAND ZONE): An area for parking motor vehicles excluding the
area associated with a driveway used for parking two or fewer vehicles.
PARKING LoT: An open area other than a street used for the parking of more than four
(4) motor vehicles and available for public use whether free, for compensation, or as
an accommodation for clients or customers.
PERMITTING AUTHORITY: The person or entity responsible for issuing a particular
permit or approval under this Ordinance. The permitting authority -will be either the
CEO or the Planning Boa.rd.
PERSONAL WIRELESS SERVICES: Any communications service which, for a fee to the
public or a substantial portion thereof, provides for the transmission between or
among points specified by the user, of information of the user's choosing, without
change in the form or content of the information sent or received, and:
a. is comprised of for-profit radio communications between mobile and fixed radio
stations, and linked to public switched communications networks (example:
commercial ship-to-shore radio facilities);
b. which is transmitted or received by means of devices which do not require
individual FCC licenses, but excluding direct-to-home satellite services (example:
cellular telephone services); or
c. which offers access to telephone exchange services or facilities for the purpose
of origination or termination of telephone toll services by a common carrier of
interstate or foreign radio transmissions.
PERSON: An individual, corporation, governmental agency, municipality, trust, estate,
partnership association, two or more individuals having a joint or common interest, or
other legal entity.
PESTICIDE: Am substance or mixture of substances intended for preventing,
destroying, repelling or mitigating any pests, and any substance or mixture of
160)Page
Zonmg Ordinat1ce -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended· 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended. 02-Nov-10
Amended: 26-Mar-ll
Amended: 01-Jun 13
Amended: 23-Sept- 13
Amended· 1 I-May- 19
Amended· l l-.Jul-20
Amended: 1 l-May-24
Last Amended. 07-Jun-25
substances intended for use as a plant regulator, defoliant or desiccant .. ,1.fu.,_.{I
PIERS, DOCKS, WHARVES, BRIDGES, AND OTHER STRUCTURES OR USES ExTENDING OVER
OR BEYOND THE NORMAL HIGH-WATER LINE OR WITHIN A WETLAND: .-1,iJ..c.L
a.
Temporary: Structures which remain in or over the water for less than seven
\7} months in any period of twelve (12) consecutive months.
b. Permanent: Structures which remain in or over the water for seven (7) months
or more in any period of twelve (12) consecutive months.
PLAN:
a. Sketch Plan: Conceptual maps, renderings and supportive data describing the
project proposed by the applicant for initial review by the Board prior to submitting
an application for Subdivision approval.
b. Final Plan: The final drawings on which the applicant's plan of Subdivision is
presented to the Board for approval.
c. Recording Plan: An original of the paper and mylar versions of the final plan
suitable for recording at the Registry of Deeds.
PLANNING BOARD: The Planning Board established by the Town on March 21, 1960.
PORCH: An accessory attachment to a principal structure having a roof, canopy, or
av.ming. It may have framed or screened walls or railings v.rith screening and gates to
enclose pets or children. ,·.112.]:
PROJECT: Any activity requiring approval by the appropriate Permitting Authority
under this Ordinance.
PuBLIC FACILITY: Any facility, including, but not limited to, buildings, property,
recreation areas, and roads, which are owned, leased, or othenvise operated, or
funded by a governmental body or public entity. '..:C1_1_l i'
PuBLIC UTILITY: A firm, person, corporation, municipal department, board or
commission authorized by the Maine Public Utilities Commission to furnish gas,
steam, electricity, communication facilities, or transportation of water to the public.
1611 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-OS
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
!',mended: 27-Mar- lO
Amended: 02-Nov-10
Amended: 26-Mar-ll
Amended: 01-Jun-13
Amended· 23-Sept-l3
Amended: ll-May-19
Amended· ll-Jul-20
Amended: 11-May-24
La.st Amended: O?-Jun-25
REcONSTRUCTION: The restoration, remodeling or rebuilding of a structure, whether
necessitated by deterioration, obsolescence, casualty or other occurrence, where the
costs of such work equal or exceed the value of the property in its existing condition.
REcREATIONAL FACILITY: A place designed and equipped for the participation in sports,
leisure time activities, and other customary and usual recreation activities, including
swimming pools, but excluding boat launching facilities.
REcREATIONAL FACILITY, PRlvATE: AN accessory recreational facility located on private
residential property for the use of the property owner or guests at no charge, including
but not limited to swimming pools and tennis courts.
REcREATIONAL VEHICLE: A vehicle or an attachment to a vehicle designed to be towed
and designed for temporary sleeping or living quarters for one or more persons, and
which may include a pick-up camper, travel trailer, tent trailer, camp trailer, and
motor home. In order to be considered as a vehicle and not as a structure, the unit
must remain with its tires on the ground and must be registered with the State
Division of Motor Vehicles.
REsTAURANT: An establishment whose principal business is the sale of food and/or
beverages to consumers in a ready-to-consume state, and whose principal method of
operation includes one or more of the following characteristics:
a. Customers normally provided with an individual menu, are served their food and
beverages by a restaurant employee at the same table or counter at which food and
beverages are consumed;
b. A cafeteria type operation where food and beverages generally are consumed
within the restaurant building; or
c. A carry-out or delivery service, drive-in service, and service or consumption
outside a fully enclosed structure, but excluding catering for off-premises
consumption.
RETAINING WALL: A vertical or near vertical structure constructed of wood, concrete,
masonry or rock design to retain soil upgradient from the base of the wall. ;~rr._J_f2,
RIPRAP: Rocks, irregularly shaped, and at least six (6) inches in diameter, used for
erosion control and soil stabilization, typically used on ground slopes of two (2) units
horizontal to one {l} unit vertical or less.
1621 Page
Zoning Ordtrnmce -Adopted: 28-Mar-2000
/\mended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended; 04-Apr-05
Amended: 26-Mar-07
Amended; 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- 10
Amended: 02-Nov-10
Amended: 26-Mar-l l
Amended: 01-Jun- 13
Amended: 23-Sept-13
Amended: 1 l-May-19
Amended. ll-Jul-20
Amended, l 1-May-24
Last Amended: 07-Jun-25
RrvER: A free-flowing body of water including its associated flood plain wetlands from
that point at which it provides drainage for a watershed of twenty-five (25} square
miles to its mouth. Note: The portion of a river that is subject to tidal action is a
coastal wetland. i.:1.!Il :ii.
ROAD OR STREET: A thoroughfare or way consisting of a bed of exposed mineral soil,
gravel, asphalt, or other surfacing material constructed for or created by the repeated
passage of motorized vehicles, excluding driveways as defined above.
a. Private Road or Street: A thoroughfare or way designated for private use and
maintained by a property owner or group of property owners.
b. Public Road or Street: A public thoroughfare, way, or easement permanently
established for passage of persons or vehicles.
c. Collectors: These roads handle internal traffic movements within a town or
between a group of towns and are designed for moderate speed travel. The only
collectors in Castine are State Highways, routes 166, 166A and 199.
d. Local: These are lightly traveled streets whose primary purpose is to serve
residential areas. They are designed for slow speed travel and to carry low volumes
of traffic for short distances.
e. Cul-de-sac: A street -with only one outlet and having the other end for the
reversal of traffic movement.
f. Industrial or Commercial Street: Streets servicing industrial or commercial
uses.
g. Private Right-of-Way: A minor residential street servicing no more than eight
dwelling units, which is not intended to be dedicated as a public way.
ROOM: A walled or partitioned portion of space within a structure or building as
defined below:_T.o:\:'7.,_1_,
a. Unfinished Room: A space only enclosed by open stud walls and/ or exposed
structural members of the building. ;.'.l,11.J_
b. Finished Room: A space with any higher level of finish than that of an
unfinished room. ·,~U':_1_,_I_,
SALT MARSH: Areas of coastal wetland (most often along coastal bays) that support salt
tolerant species, and where at average high tide during the growing season, the soil is
irregularly inundated by tidal waters. The predominant species is saltmarsh cordgrass
(Spartina alterniflora). More open areas often support widgeon grass, eelgrass, and
Sago pondweed.
1631 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26--Mar-01
Amended. 25-Mar--02
Amended: 07-May--02
Amended: 04-Apr--05
Amended: 26-Mar--07
Amended: 24--Mar-08
Amended: 04--Apr-09
Amended: 27-Mar--10
Amended; 02--Nov-10
.-',mended. 26--Mar-1 l
.-',mended: Ol-Jun--13
Amended: 23-Sept-]3
Amended: JI -May J 9
Amended· l 1-Jul--20
Amended: J l-May--24
Last /\.mended: 07-Jun--25
SALT MEADOW: Areas of a coastal wetland that support salt tolerant plant species
bordering the landward side of salt marshes or open coastal water, where the soil is
saturated during the growing season but which is rarely inundated by tidal water.
Indigenous plant species include salt meadow cordgrass (Spartina patens) and black
rush; common three-square occurs in fresher areas. 1:\rn.5;
SAND AND SALT PILES: A mixture of salt and sand or salt stored for .vinter road and
yard maintenance. :0.G~~:
SETBACK: The nearest horizontal distance from a lot line or from the normal high-
water line of a water body or tributary stream or the upland edge of a wetland or from
the road right-of-way to the nearest part of a structure, parking space, or other
regulated object or area. [.-\rn.~;
a. Setback, Front: The setback between the front lot line and the nearest part of a
stn1cture or other regulated object or area.
b. Setback, Rear: The setback between the rear lot line and the nearest part of a
structure or other regulated object or area.
c. Setback, Side: The setback between the side lot line and the nearest part of a
structure or other regulated object or area.
d. Setback, Shoreline: The nearest horizontal distance from the nonnal high-
water line of a water body or tributary stream or the upland edge of a wetland and
the nearest part of a structure or other regulated object or area.
SERVICE DROP: Any utility line extension which does not cross or run beneath any
portion of a water body provided that: f:~lS:i
a. In the case of electrical service
1. the placement of wires and/or the installation of utility poles is located
entirely upon the premises of the customer requesting service or upon a
roadway right-of-way; and
2. the total length of the extension is less than one thousand (1,000) feet.
b. In the case of telephone service
1. the extension, regardless oflength, will be made by the installation of
telephone wires to existing utility poles, or
2. the extension requiring the installation of new utility poles or placement
underground is less than one thousand (1,000) feet in length.
1641Page
?,.:ming Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended· 25-Mar-02
Amended: 07 -May-02
/\mended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-A.pr-09
Amended: 27-Mar-JO
Amended: 02-Nov-JO
Amended: 26-Mar-1 l
Amended: Ol-Jun-13
Amended; 23-Sept-13
Amended: ll-May-19
Arnended: l l -Ju\-20
Amended: 1 l-May-24
Last Amended. 07-Jun-25
SHORE FRONTAGE: See FRONTAGE, SHORE
SHORELAND ZONE/SHORELAND OVERLAY DISTRICT: The land area located within two
hundred and fifty (250) feet, horizontal distance, of the normal high-water line of any
great pond or river; within 250 feet, horizontal distance, of the upland edge of a
coastal wetland, including all areas affected by tidal action; v.rithin 250 feet of the
upland edge of a freshwater wetland; or within seventy-five (75) feet, horizontal
distance, of the normal high-water line of a stream. [.6.!I',c..,_''<,
SHORELINE: The normal high-water line, or upland edge of a freshwater or coastal
wetland. ;A1_:_1_,___:=,_·
SHORELINE AccESs: A stairway or similar structure to provide shoreline access in areas
of steep slopes or unstable soils and where no reasonable access alternative exists on
the property; the structure is limited to a maximum of four (4) feet in width and the
structure shall not extend below or over the normal high-water line of a water body or
upland edge of a wetland, (unless permitted by the Board of Environmental Protection
pursuant to the Natural Resources Protection Act, Title 38 M.R.S.A. § 480-C). ·;_jj!.1:l}
SIGNIFICANT RlvER SEGMENTS: See Title 38 M.R.S.A. § 437, as amended. ·)1r.,'5';
SIGHT DISTANCE: The length of unobstructed view from a particular access point to the
farthest visible point of reference on a roadway. Used herein as a reference for
unobstructed road visibility.
SIGN: Any structure, display, logo, device or representation which is designed or used
to advertise or call attention to anything, person, business, activity or place, and
which is visible to the public. A sign does not include any flag, pennant or insignia of
a nation, State, town or other political entity. Whenever dimensions of a sign are
specified, they shall include frames. Each visible sign face shall constitute a separate
sign, except that a sign with two (2) faces shall be considered one (1) sign so long as
the distance between the faces does not exceed twelve (12) inches. ',jrn'"I
STREAM: A free-flm;ving body of water from the outlet of a great pond or the confluence
of two (2) perennial streams as depicted on the most recent edition of a United States
Geological Survey 7.5-minute series topographic map, or if not available, a 15-minute
series topographic map, to the point where the body of water becomes a river, or flows
to another water body or wetland within the Shoreland Area.
1651Page
Zoning Ordinance -Adopted; 28-Mar-2000
i>,mended; 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04·Apr-05
Amended: 26-Mar-07
Amended: 24-Mar 08
/\mended: 04-Apr-09
Amended: 27-Mar-10
Amended 0'2-Nov-10
Amended: 26-Mar-l I
Amended: 0 I-Jun-13
Amended·. 23-Sept 13
Amended· 11-May 19
Amended· ll -Jul-20
Amended: I 1-May-24
Last Amended 07-Jun-25
STREET: See "RoAD OR STREET" above.
STRUCTURE: Anything built for the support, shelter or enclosure of persons, animals,
goods, or property of any kind, together with anything constructed or erected with a
fixed location on or in the ground, exclusive offences, tents in place for ten (10) days
or less, and poles, wiring and other aerial equipment normally associated with service
drops as well as guying and guy anchors. The term includes walls in the Shoreland
Zone and structures temporarily or permanently located, such as decks, patios, raised
walkways and satellite dishes larger than thirty-nine (39) inches in diameter. ;2_rn_.J_,
1,\r,i .. 2; (.\ni.S' i\m.7'.
STRUCTURE, ACCESSORY: A structure which is incidental and subordinate to the
principal structure. A deck or similar extension of the principal structure or a garage
attached to the principal structure by a roof or a common wall is considered part of
the principal structure.
STRUCTURE, NON-CONFORMING: A structure that does not meet the minimum setback,
maximum height, maximum lot coverage or similar requirements for the zoning
district in which it is located.
STRUCTURE, PRINCIPAL: A structure other than one which is used for purposes wholly
incidental or accessory to the use of another structure or use on the same premises.
SUBDMSION: The term shall be defined as in Title 30-A MRSA §4401, sub-§4, as
amended.
SUBSTANTIAL COMPLETION/SUBSTANTIALLY COMPLETED: Completion of ninety percent
(90%) of a permitted structure or use measured as a percentage of estimated total
cost.
SUBSTANTIAL CoMMENCEMENT: Completion of thirty percent (30%) of a permitted
structure or use measured as a percentage of estimated total cost.
SUBSURFACE SEWAGE DISPOSAL SYSTEM: Any system designed to dispose of waste or
waste water on or beneath the surface of the earth; includes, but is not limited to:
septic tanks; disposal fields; grandfathered cesspools; holding tanks; pretreatment
filter, piping, or any other fixture, mechanism, or apparatus used for those purposes;
does not include any discharge system licensed under Title 38 M.R.S.A. § 414, any
surface waste water disposal system, or any municipal or quasi-municipal sewer or
waste water treatment system. :,.1,__rr_1c..5,,
166 I P a g e
Zoning Ordinance - Adopted· 28-Mar-2000
Amended: 26-Mar-01
Amended· 25-Mar-02
Amended: 07 -May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended. 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar- lO
Amended: 02-Nov-10
Amended: 26-Mar- l 1
Amended: 01-J u.n- 13
Amended; 23-Sept- l 3
Amended; 11-May- l<J
Amended, 11 Ju.1-20
Amended: 11-May-24
Last Amended. 07-Ju.n-25
SUBSURFACE SEWAGE DISPOSAL REPLACEMENT SYSTEM: A system intended to replace:
1.) an existing system which is either malfunctioning or being upgraded with no
significant change of design flow or use of the structure, or 2.) any existing overboard
wastewater discharge. i,_\m.i'il
SUSTAINED SLOPE: A change in elevation where the referenced percent grade is
substantially maintained or exceeded throughout the measured area.
TELECOMMUNICATIONS TOWER: Any structure, antenna, tower or other device which
provides radio/television transmission, commercial mobile wireless services,
unlicensed wireless services, cellular phone services, specialized mobile radio
communications (SMR), common carrier wireless exchange access and phone services,
and personal communications service (PCS) or pager service, but excluding private
ham radio. ,\rn_.1.i
TIDAL WATERS: All waters affected by tidal action during the highest annual tide.
r,:\m .. \
TOWN: The Town of Castine, Maine.
TRACT OR PARCEL OF LAND: All contiguous land in the same ownership whether or not
the tract is separated at any point by an intermittent or non-navigable stream, tidal
waters where there exists no flow at low tide, or a private road established by the land
owners or the abutting landowners. Lands located on opposite sides of a public or
private road shall be considered each a separate tract or parcel of land unless such a
road was established by the owner of land on both sides thereof. Private roads created
before September 23, 1971 shall be considered the same as public roads.
TRIBUTARY STREAM: A channel between defined banks created by the action of surface
water, whether intermittent or perennial, and which is characterized by the lack of
terrestrial vegetation or by the presence of a bed, devoid of topsoil, containing
waterborne deposits or exposed soil, parent material or bedrock, and which is
connected hydrologically with other water bodies. This definition does not include rills
or gullies forming because of accelerated erosion in disturbed soils where vegetation
has been removed by human activity and does not include the term "stream" as
defined elsewhere in this Ordinance and only applies to that portion of the tributary
stream located within the shoreland zone of the receiving water body or wetland.
Note: Shoreline setback requirements apply to tributary streams within the Shoreland
zone. },.m,_.s
1671 Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amended: 26-Mar-Ol
Amended: 25-Mar-02
Amended· 07 -May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended· 02-Nov-10
Amended: 26-Mar 11
Amended: 01-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended: 1 l-Jul-20
Amended: l l-May-24
Last Amended: 07 -Jun-25
UPLAND EDGE OF A WETLAND: The boundary between upland and wetland. For
purposes of a coastal wetland, this boundary is the line formed by the landward limits
of the salt tolerant vegetation and/or the highest annual tide level, including all areas
affected by tidal action. For purposes of a freshwater wetland, the upland edge is
formed where the soils are not saturated for a duration sufficient to support wetland
vegetation; or where the soils support the growth of wetland vegetation, but such
vegetation is dominated by woody stems that are six (6) meters (approximately twenty
(20) feet) tall or taller. 1,-\m.5]
USE: The purpose or activity for which land or any building thereon is designed,
arranged, or intended, or for which it is occupied or maintained.
USE, ACCESSORY: A use which is incidental and subordinate to the principal use.
Accessory uses, when aggregated, shall not subordinate the principal use of the lot.
USE, NON- CONFORMING: A use which is not a permitted use in the zoning district in
which it is located. Other than the non-conforming use, all other standards of the
Castine Zoning Ordinance shall apply to a lot with a non-conforming use. i.\m. lfJ!
USE, PRINCIPAL: A use other than one which is wholly incidental or accessory to
another use on the same premises.
VEGETATION: All shrubs and other plants including all live trees of four and one-half
(4½) feet or more in height, of whatever diameter.
VELOCITY ZONE: An area of special flood hazard extending from offshore to the inland
limit of the primary frontal dune along an open coast and any other area subject to
high velocity wave action from storms or seismic sources. :Arn ,c;·
VOLUME OF A STRUCTURE: The volume of all portions of a structure enclosed by roof
and fixed exterior walls as measured from the exterior faces of these walls and roof,
including roofed and screened porches.
WATER Boov: Any great pond, river or stream. [-\m5
WATER CROSSING: Any project extending from one bank to the opposite bank of a river,
stream, tributary stream, or wetland whether under, through, or over the water or
wetland. Such projects include, but may not be limited to roads, fords, bridges,
168[Page
Zomng Ordinance·· Adopted: 28-Mar-2000
Amended: 26-Mar-01
Amended: 25-Mar-02
Amended: 07-May-02
Amended: 04-Apr-05
Amended: 26-Mar-07
Amended: 24-Mar-08
Amended: 04-Apr-09
Amended: 27-Mar-10
Amended: 02-Nov-10
Amended. 26-Mar-1 l
Amended. Ol-Jun-13
Amended: 23-Sept-13
Amended: 11-May-19
Amended· 1 l-Jul-20
Amended: l l-May-24
Last Amended: 07-Jun-25
culverts, water lines, sewer lines, and cables as well as maintenance work on these
crossings. This definition includes crossings for timber harvesting equipment and
related activities. ,Ar.n,.Si
WALKWAY: A pedestrian access-way six (6) feet or less in width. ,_\r.U_,_l,
a. Private Walkway: A pedestrian access-way designated for private use and
maintained by a property owner .. -\:·nJ i
b. Public Walkway: A public thoroughfare, way, or easement permanently
established for passage of persons. :Am.J !
WETLAND: A freshwater or coastal wetland. :"\:cn.0'1
WOODY VEGETATION: Live trees or woody, non-herbaceous shrubs. 2---ml'.
1
YARD: The area of land on a lot not occupied by buildings.
a. Front Yard: The open, unoccupied space on the same lot with the principal
building between the front lot line and the nearest part of any building on the lot
and extending the entire width of the lot.
b. Rear Yard: The open, unoccupied space on the same lot with the principal
building between the rear lot line and the nearest part of any building on the lot
and extending the entire width of the lot.
c. Side Yard: The open, unoccupied space on the same lot with the principal
building between a side lot line and the nearest part of any building on the lot,
extending from the front yard to the rear line.
ZONING MAPS [Am 2. 25-Mar·02;_Aml0._26-Mar-11J
Zoning maps follow.
1691Page
Zoning Ordinance -Adopted: 28-Mar-2000
Amc,nded 26--Mar-O!
Amended: 25-Mar--02
Amended: 07--May-02
Amended: 04--Apr-05
Amended· 26--Mar-07
Amended: 24--Mar-08
Amended: 04-Apr--09
Amended: 27--Mar-!O
Amended: 02--Nov 10
Amended: 26--Mar- l l
Amended· Ol-Jun--13
Amended: 23-Sept--13
Amended: 11--May- 19
Amended. ll-Jul--20
Amended: l l-May--24
Last Amended: 07 -Jun--25