1
Solar Energy Systems Ordinance
Town of Dedham, Maine
Effective February 4, 2021
Section 1: Purpose
1. To promote the general welfare, public health, and providing for public safety of the
community.
2. To meet the goals of the Dedham Comprehensive Plan.
3. To conserve the environment, wildlife habitat, fisheries & natural areas.
4. To fit solar energy systems (SES) harmoniously into the fabric of the community by providing
standards for these systems.
5. To preserve visual landscapes of scenic or aesthetic value as determined by the Dedham
Planning Board (DPB) in accordance with the objectives of the Dedham Comprehensive Plan
and the Dedham Land Use Ordinance.
Section 2: Authority
1. This ordinance is enacted pursuant to the Home Rule Authority granted to the Town in
accordance with provisions of 30 MRSA §3001.
2. The DPB is vested with the authority to approve, approve with conditions, or reject any
application for a Solar Energy System (SES) as defined in this ordinance.
3. The DPB may hire independent professional consultants to review SES applications to
determine: a) the impact to nearby properties, b) public safety implications, or c) address other
issues with a SES application.
4. The cost (if any) for such professional consultancy will be borne by the applicant. DPB will
notify the applicant with the consultants name and qualifications, the reason for the
consultation, and the estimated cost. The DPB will work with the applicant to arrange a
payment schedule for this cost.
Section 3: Definitions
1. Solar Energy System (SES): A system that converts energy from sunlight into electricity using
photovoltaics (PV), or indirectly using concentrated solar radiation, or a combination of the two.
2. Solar Array: Multiple solar PV panels combined to create a source of electrical power; a part of
an SES.
3. Height of building: The vertical measurement from grade to the highest point of a building,
excluding chimneys, television antennae, HVAC systems, and roof mounted solar arrays.
4. Array Mount:
The manner in which a PV array is affixed to the roof or ground - roof mount or
ground mount.
5. Solar Energy System Size Classification:
6. Residential - From 501 square feet to 5000 square feet array panel area.
a. Small - From 5001 to 15000 square feet array panel area.
b. Medium - From 15001 to 87000 square feet array panel area.
c. Large - 87001 and above square feet of array panel area.
7. SES Facility: A facility where solar power is produced.
2
Section 4: Exempt Solar Energy Systems
The following SES are exempt from this ordinance:
1. Residential Size Class roof mounted arrays on any legally permitted residential or residential
accessory structure.
2. Ground or pole mounted arrays for private use with a panel area of less than 501 square feet if not
within the resource protection zone.
3. Solar Energy Systems mounted on cell phone towers.
Section 5: Zoning Districts
Solar Energy Systems are allowed in the following zoning districts labelled Yes, subject to securing site
plan approval and building permits:
1. Resource Protection
-
No
2. Growth 1
-
Yes - with Planning Board Approval
3. Growth 2A
-
Yes - with Planning Board Approval
4. Growth 2B
-
Yes - with Planning Board Approval
5. Rural Residential
-
Yes - with Planning Board Approval
Section 6: Site Plan Review & Performance Standards
1. Standards for Roof Mounted and Small size Ground Mounted SES: All SES and associated wiring
shall be installed in compliance with the PV systems standards of the latest edition of the National
Electric Code (NEC).
2. Additional Standards for Medium and Large size Ground Mounted SES: In addition to the
standards listed in section 6.1 above, Medium and Large Size Ground Mounted SES shall comply
with the following:
A) The applicant for an SES permit will supply the Code Enforcement Officer (CEO) with
a Site Plan Review application.
B) Visual and environmental buffers must be maintained at the project's periphery and shall
extend the width of the required setback; by the preservation of native vegetation (tree &
woody-shrub species) or by the planting of native species.
C) If utilizing cleared land for proposed "meadow" based stormwater treatment, semi-annual
(Spring & Fall) inspection of the meadow areas shall be performed until a meadow grass
sod is established. Grading of washouts and reseeding of eroded "meadow" areas shall
be performed according to Maine Department of Environmental Protection (ME DEP)
Best Management Practices.
D) Meadow stormwater treatment areas shall be managed by mowing in lieu of herbicide
treatment.
E) For safety reasons, the entire periphery of the SES shall be surrounded by an agricultural
welded wire type fence 72 inches high (at a minimum) positioned 6 inches off the ground.
3. Additional Standards for Large size Ground Mounted SES: In addition to the standards listed in
sections 6.1 & 6.2 above, Large Size Ground Mounted SES shall comply with the following:
A) Signage on the access gate to the SES will identify the owner and list a 24 hour
emergency contact phone number.
B) The SES owner will provide to the Dedham Fire Chief, a site plan, electrical schematic
of the facility, standard security measures for the facility, and an emergency response
plan.
3
4. Abandonment, Decommissioning & Removal of Large SES: In addition to all standards listed in
sections 6.1, 6.2, & 6.3 above, Large Size Ground Mounted SES shall comply with the following:
A) The owner or operator of the SES shall notify the CEO by certified mail with the
date of discontinued operations, or the expiration of a lease to operate the facility,
and shall physically remove the entire SES installation no more than 365 days
from the date of discontinued operations.
B) Decommissioning & removal shall consist of the physical removal of PV panels, array
support structures, foundations, to a depth of at least four (4) feet below grade, electrical
switchgear, and associated transmission lines from the site.
C) Decommissioning & removal shall also consist of off-site disposal of all solid & liquid
waste in accordance with local, state & federal regulations.
D) Stabilization of the site via revegetation shall be performed and shall use ME DEP Best
Management Practices as necessary, to avoid erosion.
E) Absent a notice of decommissioning or written notice of extenuating circumstances, a
Large SES will be considered abandoned when it fails to operate for more than one year.
The CEO will notify the party responsible by certified mail that they must remove the
facility and restore the site within one year. A copy of this notice will be sent to the
Dedham Board of Selectmen.
F) If the owner or operator of the SES fails to remove the installation within 365 days of
abandonment, the town retains the right to use all available means to cause an abandoned
Large SES to be removed. All costs thus incurred will be paid from the performance bond
for that purpose held by the Town of Dedham.
5. General Standards Applicable to all SES:
A) The property owner of record will be the responsible party for maintaining &
operating the SES on a parcel, unless a lease or equivalent instrument is executed
between the property owner of record and a proposed operator of the SES. A copy
of the instrument shall be submitted to the CEO.
B) Approval of an SES application via this ordinance is conditional upon compliance with
the Dedham Land Use Ordinance, Maine Natural Resources Protection Act, Maine Site
Location of Development Law, and Maine Stormwater Management Law.
C) An SES shall not be constructed until an SES application has been approved, or approved
with conditions, by the Dedham Planning board, and a building permit has been issued by
the CEO.
D) Any SES site lighting shall be shielded & downcast such that light does not spill onto an
adjacent parcel or the night sky.
Section 7: Application and Permit Fees
1. SES building permit applications shall be accompanied by a permit fee as outlined in the Dedham
Fee policy.
2. If SES construction is not completed within two years of the date of issuance of the building permit
for the SES, the building permit will expire. All permits will expire upon decommissioning.
4
Section 8: Site Plan Review & Application Materials
The following materials shall be submitted for evaluation of all non-exempt SES permit applications as
part of the DPB site plan review process.
1) A site plan showing proposed system components and their dimensions, exterior lighting, and
vegetation clearing areas, stamped and certified by a State of Maine Licensed Professional
Engineer.
2) Proof of title, right, or interest, such as ownership, easement, lease, or purchase option for the
location being considered.
3) A site location map which shows the boundaries of the proposed facility, property boundary
lines, contiguous properties under total or partial control of the applicant, any significant
resources or historic sites within one (1) mile of the proposed development, and any
significant wildlife habitat (per ME DEP under the Site Location of Development Law) and
the ME Natural Resources Protection Act which may be impacted.
4) Written confirmation that all applicable State agencies with jurisdiction over the project have
been notified of the application and the location of all system components covered by this
application.
5) A description of the proposed facility to include specifications for, and numbers of, the solar
panels, transformers, rectifiers, other components, and all associated equipment. A listing of
nominal sound levels at the SES periphery, and an outline of emergency shutdown
procedures.
6) A revegetation plan for any cleared areas.
7) A decommissioning plan that meets the requirements of Section 4 above; signed by the party
responsible for the removal of the SES and the owner of the parcel where the SES is proposed.
This plan shall be recorded in the Hancock County Registry of Deeds prior to SES operation.
8) A Waste Stream Management Plan (including recycling percentages) for demolition waste &
debris at the SES site. This waste includes concrete, wood, scrap metal & wire, and clearing
& grading waste.
9) Documentation of abutting property owner notification by certified mail of the application
for SES. This notification by the applicant at least 15 days prior to the initial DPB or CEO
consideration, shall indicate the time, place, and date of the initial consideration. If a public
hearing is called by the DPB or CEO, a notice will be posted by the town at least 15 days
prior to the hearing, and include the date, time, and place of the hearing.
10) The applicant will submit seven (7) copies of the above materials at least 10 days in advance
of a DPB meeting date when the applicant wishes to be on the agenda.
11) The DPB will review the application packet for completeness; if incomplete, a list of
outstanding items will be sent to the applicant in a timely fashion. When complete, the
application will be preliminarily reviewed by the DPB for compliance with the ordinance
standards.
12) A final DPB review documenting any conditions of approval will take place subsequent to
the preliminary review. If approved, the application will be sent to the CEO for the issuance
of a construction permit.
Section 9: Guarantee of Removal
At the time of approval of a proposed SES, and prior to starting construction of an SES, the applicant
must guarantee to cover the costs of removal of the facility.
5
1) The amount of the guarantee shall be equal to the estimated SES removal cost provided by a
licensed professional engineer; or an estimate provided by a professional array construction
company. These estimates to be provided by the applicant. An updated estimate shall be provided
by the applicant to the town every 5 years from the date of the permit issued, using these types
of estimate sources.
2) An updated estimate shall be provided by the applicant to the town every 5 years from the date
of the permit issued, using these types of estimate sources. If the estimated costs increases more
than 15% from the previous estimate, the facility owner shall provide additional security in the
amount of the increase.
3) Type and contents of guarantee - Interest Bearing Escrow Account.
A cash contribution equal to the estimated removal cost shall be made by either a certified check
made out to the Town of Dedham and deposited into a savings account, or the purchase of a
certificate of deposit:
For any account opened by the applicant, the Town of Dedham shall be named as the owner or
co-owner, and the consent of the Town of Dedham shall be required for a withdrawal. Any
interest earned on the escrow account shall be returned to the applicant unless the town has found
it necessary to draw on the account, in which case, the interest earned shall be proportionally
divided between the amount returned to the applicant and the amount withdrawn to perform the
necessary work.
4) Type and contents of guarantee - Performance Bond.
A Performance Bond shall detail the condition of the bond, the method for release of the entire
bond or portions thereof to the Town of Dedham, and the procedures for collection by the Town.
The bond documents shall specifically reference the SES facility for which approval is sought.
Section 10: Severability
This ordinance is severable; if any phrase, clause, sentence, or provision is declared to be contrary to
law, the validity of the remainder shall not be affected, unless the application of any remaining portion
of the ordinance would result in action which would be inconsistent with the objectives of this ordinance.