Town of Dedham
SUBDIVISION ORDINANCE
June 14, 2003
TABLE OF CONTENTS
SECTION______________________________________________________________________ PAGE
SECTION I:
GENERAL PROVISIONS
1
A.
TITLE
1
B.
AUTHORITY
1
C.
APPLICABILITY
1
D.
CONFLICT WITH OTHER ORDINANCES
1
E.
SUPERSEDURE
1
F.
SEPARABILITY
1
G.
AMENDMENTS
1
1.
INITIATION
1
2.
PROCESS OF ADOPTION
2
H.
EFFECTIVE DATE
2
SECTION II:
PURPOSES
3
A.
PROTECT GENRAL WELFARE
3
B.
PROTECT ENVIRONMENT
3
C.
PROMOTE COMMUNITY DEVELOPMENT
3
D.
BALANCE PROPERTY RIGHTS
3
E.
REDUCE FISCAL IMPACT
3
F.
ESTABLISH PROCEDURES AND STANDARDS
3
SECTION III:
ADMINISTRATION
4
A.
ADMINISTRATION BODY
4
B.
APPROVAL REQUIRED
4
C.
PERMITS TO BE APPLIED FOR BEFORE APPROVAL
4
D.
COMMENCENMENT AND COMPLETION OF WORK
4
E.
CERTIFICATE OF CONSTRUCTION REQUIRED
4
F.
CONDITONS OF APPROVAL
4
G.
PUBLIC HEARINGS
5
SECTION IV:
CRITERIA OF APPROVAL
6
A.
POLLUTION
6
B.
SUFFICIENT WATER SUPPLY
6
C.
MUNICIPAL WATER SUPPLY
6
D.
EROSION
6
E.
TRAFFIC
6
F.
SEWAGE DISPOSAL
6
G.
MINICIPAL SOLID WASTE`
6
H.
AESTHETIC, CULTURAL AND NATURAL VALUES
6
I.
CONFOMITY WITH LOCAL ORDINANCES AND PLANS
7
J.
FINANCIAL AND TECHNICAL CAPACITY
7
K.
SURFACE WATERS
7
L.
GROUND WATER
7
M.
FLOOD AREAS
7
N.
FRESHWATER WETLANDS
7
O.
RIVER, STREAM OR BROOK
7
P.
STORM WATER
7
Q.
STATE SUBDIVISION LAW CRITERIA
7
R.
WRITTEN FINDINGS OF FACT REQUIRED
8
S.
BURDEN OF PROOF
8
SECTION V:
VIOLATIONS AND ENFORCEMENT
9
A.
RECORDING OF SUBDIVISION PLAN WITHOUT
PRIOR APPROVAL PROHIBITED
9
B.
CONVEYANCE WITHOUT RECORDING PROHIBITED
9
C.
CONVEYANCE OF LOTS NOT SHOWN ON FINAL PLAN PROHIBITED
9
TABLE OF CONTENTS
SECTION PAGE
D.
CONVEYANCE WITHOUT APPROVAL PROHIBITED
9
E.
UTILITY HOOKUPS PRIOR TO APPROVAL PROHIBITED
9
F.
DEVELOPMENT PRIOR TO APPROVAL PROHIBITED
9
G.
ROAD COMPLETION PRIOR TO CONVEYANCE REQUIRED
9
H.
FAILURE TO COMPLY WITH CONDITIONS OF APPROVAL
10
I.
FAILURE TO PAY
10
J.
OWNER RESPONSIBLE FOR OFF-SITE SEDIMENTATION
10
K.
NUISANCES
10
L.
CODE ENFORCEMENT OFFICER
10
M.
LEGAL ACTIONS
10
N.
FINES
10
O.
CONTRACTOR LIABILITY
10
SECTION VI:
APPEAL TO SUPERIOR COURT
11
SCETION VII:
ADMINISTRATIVE PROCEDURES
12
A.
AGENDA REQUIRED
12
B.
APPROVAL REQUIRED
12
C.
AGENDA MAY BE LIMITED
12
SECTION VIII:
PRE-APPLICATION CONFERENCE/SKETCH PLAN REVIEW
13
A.
GENERAL
13
B.
PROCEDURE
STEP 1:
ADVANCE REQUEST TO BE PLACED ON
AGENDA REQUIRED
13
STEP 2:
CEO REVIEW OF SUBMISSIONS FOR
COMPLETENESS
13
STEP 3:
PLANNING BOARD REVIEW OF SKETCH
PLAN AND EXHIBITS
13
STEP 4:
CLASSIFICATION OF SUBDIVISION
13
STEP 5:
CONTOUR INTERVALS ESTABLISHED
13
STEP 6:
ON-SITE INSPECTION DATE SET
13
C.
SUBMISSION PACKET
14
1.
SKETCH PLAN
14
2.
EXHIBITS TO ACCOMPANY SKETCH PLAN
14
D.
RIGHTS NOT VESTED
14
SECTION IX:
SUBDIVISION REVIEW PROCESS: MINOR SUBDIVISIONS
15
A.
MINOR SUBDIVISIONS MAY HAVE TO COMPLY WITH
MAJOR SUBDIVISION REQUIREMENTS
15
B.
SUBMISSION PACKET
15
1.
APPLICATION AND EXHIBITS
15
2.
FINAL SUBDIVISION PLAN
15
3.
ADMINISTRATIVE FEES AND ESCROW ACCOUNT
15
C.
PROCEDURE
15
STEP 1:
REQUEST FOR FINAL PLAN REVIEW
15
STEP 2:
CEO REVIEWS SUBMISSION PACKET FOR COMPLETENESS
15
STEP 3:
NOTICE TO ABUTTERS AND ADJACENT MUNICIPALITY
16
STEP 4:
PLANNING BOARD REVIEWS FINAL PLAN AND
APPLICATION
16
STEP 5:
FINAL PLAN PUBLIC HEARING
16
STEP 6:
PLANNING BOARD DECISION ON FINAL PLAN
16
STEP 7:
SIGNATURES
17
STEP 8:
FILING OF APPROVED FINAL PLAN
17
TABLE OF CONTENTS
SECTION PAGE
SECTION X:
SUBDIVISION REVIEW PROCESS: MAJOR SUBDIVISIONS
18
A.
PROCEDURE
18
STEP 1:
REQUEST FOR REVIEW OF PRELIMINARY
18
STEP 2:
CEO REVIEWS SUBMISSION PACKET FOR COMPLETENESS
18
STEP 3:
NOTICE TO ABUTTERS AND ADJACENT MUNICIPALITY
18
STEP 4:
PLANNING BOARD REVIEWS PRELIMINARY PLAN
AND APPLICATION
18
STEP 5:
PRELIMINARY PLAN PUBLIC HEARING
19
STEP 6:
PLANNING BOARD DECISION ON PRELIMINARY PLAN
19
STEP 7:
REQUEST FOR REVIEW OF FINAL PLAN
19
STEP 8:
CEO REVIEWS SUBMISSION PACKET FOR
COMPLETENESS
19
STEP 9:
NOTICE TO ABUTTERS AND ADJACENT
MUNICIPALITY OF FINAL PLAN
20
STEP 10:
PLANNING BOARD REVIEWS FINAL PLAN
20
STEP 11:
FINAL PLAN PUBLIC HEARING
20
STEP 12:
PLANNING BOARD DECISION ON FINAL PLAN
20
STEP 13:
SIGNATURES
20
STEP 14:
FILING OF APPROVED FINAL PLAN
21
B.
SUBMISSION PACKET
21
1.
APPLICATION AND ATTACHMENTS
21
2.
FINAL SUBDIVISION PLAN
21
3.
ADMINISTRATIVE FEES AND ESCROW ACCOUNT
21
SECTION XI:
FILING PROCEDURES FOR APPROVED SUBDIVISIONS
22
A.
FILING OF PLANNING BOARD ORDERS REQUIRED PRIOR TO SIGNING
OF AND FILING OF APPROVED FINAL SUBDIVISION PLANS
22
B.
FILING SECURITY DEPOSIT REQUIRED
22
C.
SIGNING OF APPROVED FINAL SUBDIVISION PLANS
22
D.
FILING OF THE SIGNED SUBDIVISION PLAN
22
E.
FAILURE TO FILE AS REQUIRED TO RESULT IN VOIDING OF
APPROVAL AND FORFEITURE OF FILING
22
F.
RETURN OF FILING SECURITY DEPOSIT
22
G.
FOREITED DEPOSITS ACCRUE TO THE TOWN
22
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS
23
A.
APPLICATION FORM
23
B.
INFORMATION TO BE SUBMITTED
23
1. INFORMATION REGARDING THE APPLICANT
23
2. INFORMATION REGARDING PARCEL
PROPOSED TO BE SUBDIVIDED
23
3. INFORMATION REGARDING PROPOSED SUBDIVISION
24
C.
EXHIBITS TO ACCOMPANY SUBDIVISION APPLICATIONS
24
EXHIBIT 1:
LOCATION MAP
24
EXHIBIT 2:
TAX MAP
25
EXHIBIT 3:
DOCUMENTATION OF RIGHT, TITLE
OR INTEREST
25
EXHIBIT 4:
WRITTEN AND GRAPHIC HISTORY OF OWNERSHIP
AND DIVISION
25
EXHIBIT 5:
AGENT'S LETTER OF AUTHORIZATION
25
EXHIBIT 6:
WATER SUPPLY-INDIVIDUAL WELLS
25
EXHIBIT 7:
WATER SUPPLY-COMMON SYSTEM
25
EXHIBIT 8:
HIGH INTENSITY SOIL SURVEY
26
TABLE OF CONTENTS
SECTION PAGE
EXHIBIT 9:
SWCD EROSION CONTROL SPECIFIACTIONS
AND PLAN
26
EXHIBIT 10:
EROSION AND SEDIMENTATION CONTROL PLAN
AND SPECIFICATIONS
26
EXHIBIT 11:
TRAFFIC IMPACT ANALYSIS
28
EXHIBIT 12:
HIGHWAY ENTRANCE PERMITS
28
EXHIBIT 13:
INTERIOR ROAD DESIGN
28
EXHIBIT 14:
INTERIOR ROAD MAINTENANCE
28
EXHIBIT 15:
SEWAGE DISPOSAL-INDIVIDUAL SUBSURFACE
DISPOSAL SYSTEMS
29
EXHIBIT 16:
SEWAGE DISPOSAL-COMMON SUBSURFACE
DISPOSAL SYSTEMS
29
EXHIBIT 17:
SOLID WASTE GENERATION AND DISPOSAL
STATEMENT
29
EXHIBIT 18:
SOLID WASTE GENERATION REPORT
29
EXHIBIT 19:
SLUDGE DISPOSAL FACILITY STATUS AND
CONTRACT
29
EXHIBIT 20:
SLUDGE DISPOSAL FACILITY STATUS CONTRACT
29
EXHIBIT 21:
AESTHETIC, CULTURAL AND NATURAL VALUES
IMPACT STATEMENT
30
EXHIBIT 22:
VISUAL RESOURCES IMPACT ASSESSMENT
30
EXHIBIT 23:
HISTORIC RESOURCES IMPACT ASSESSMENT
30
EXHIBIT 24:
UNIQUE NATURAL RESOURCES IMPACT
ASSESSMENT
30
EXHIBIT 25:
FISHERIES AND WILDLIFE HABITAT IMPACT
ASSESSMENT
30
EXHIBIT 26:
COMPLIANCE STATEMENT
30
EXHIBIT 27:
COMPLIANCE MEMO-LOCAL ORDINANCES
AND PLANS
30
EXHIBIT 28:
COMPLIANCE MEMO-STATE AND FEDERAL LAWS
AND REGULATIONS
31
EXHIBIT 29:
FINANCIAL CAPACITY REPORT
31
EXHIBIT 30:
TECHNICAL ABILITY
31
EXHIBIT 31:
SURFACE WATER MANAGEMENT STATEMENT
31
EXHIBIT 32:
SURFACE WATER MANAGEMENT PLAN
32
EXHIBIT 33:
GROUND WATER RESOURCES IMPACT STATEMENT
32
EXHIBIT 34:
NITRATE ASSESSMENT
32
EXHIBIT 35:
WATER QUALITY BACKGROUND ASSESSMENT
32
EXHIBIT 36:
RECOMMENDATIONS FOR MIMIMIZING OR
ELIMINAING WATER QUALITY IMPACTS
33
EXHIBIT 37:
FLOOD HAZARD PROTECTION STATEMENT
33
EXHIBIT 38:
FRESHWATER WETLAND PROTECTION
STATEMENT
33
EXHIBIT 39:
FRESHWATER WETLANDS MAP
33
EXHIBIT 40:
FLOWING WATERS PROTECTION STATEMENT
33
EXHIBIT 41:
FLOWING WATERS MAP
33
EXHIBIT 42:
STORM WATER MANAGEMENT PLAN
34
SECTION XIII: PREPARATION AND SUBMISSION REQUIREMENTS FOR PRELIMINARY
AND FINAL SUBDIVISION PLANS
36
A.
PREPARATION AND SUBMISSION REQUIREMENTS:
PRELIMINARY SUBDIVISION PLANS
36
1. NUMBER OF COPIES TO BE SUBMITTED
36
TABLE OF CONTENTS
SECTION PAGE
2. SHEET SIZE
36
3. PLAN SCALE
36
B.
INFORMATION TO BE SHOWN ON PRELIMINARY
SUBDIVISION PLANS
36
1. GENERAL INFORMATION
36
2. BOUNDARY SURVEY
36
3. CONTOUR LINES
36
4. PROPOSED LOT LINES AND LOT NUMBERS
37
5. EXISTING MAN-MADE FEATURES
37
6. EXISTING NATURAL FEATURES
37
7. NAMES OF ADJACENT PROPERTY OWNERS
37
8. PROPOSED IMPROVEMENTS
37
9. PUBLIC IMPROVEMENTS
37
10. COMMON AND/OR PUBLIC AREAS AND FACILITIES
37
11. FLOOD HAZARD AREA BOUNDARIES
37
12 EXISTING ZONING
37
13. SURVEYOR/PLANNER'S CERTIFICATION AND SEAL
38
C.
PREPARATION AND SUBMISSION REQUIREMENTS:
FINAL SUBDIVISION PLANS
38
D.
INFORMATION TO BE SHOWN ON FINAL
SUBDIVISION PLANS
38
1. FINAL APPROVAL BLOCK
38
SECTION XIV:
APPLICATION FEES AND TECHNICAL REVIEW ACCOUNT
39
A.
APPLICATION PACKET FEE
39
1. COPIES OF SUBDIVISION APPLICATIONS
39
2. COPIES OF ORDINANCE
39
B.
APPLICATION PROCESSING FEES
39
1. MINOR SUBDIVISIONS
39
2. MAJOR SUBDIVISIONS
39
3. PUBLIC HEARING FEES
39
C.
TECHNICAL REVIEW ACCOUNT
39
SECTION XV:
REVISIONS TO EXISTING PLANS AND TRANSFER OR APPROVAL
41
A.
REVISIONS TO EXISTING PLAN
41
B.
TRANSFER OF APPROVAL
41
SECTION XVI: GENERAL PERFORMANCE STANDARDS
42
A.
CONFORMANCE WITH COMPREHENSIVE PLAN
42
B.
RELATIONSHIP TO MUNICIPAL SERVICES
42
C.
PRESERVATION AND ENHANCEMENT OF THE LANDSCAPE
42
D.
RELATIONSHIP TO SCENIC CHARACTER OF THE NEIGHBORHOOD
42
E.
RETENTION OF OPEN SPACES AND NATURAL OR HISTORIC
FEATURES
42
F.
LAND NOT SUITABLE FOR DEVELOPMENT
43
G.
TOPSOIL AND VEGETATION REMOVAL
43
H.
EROSION AND SEDIMENTATION CONTROL
44
I.
LOT STANDARDS
44
J.
UTILITIES
45
K.
CONSTRUCTION IN FLOOD HAZARD AREAS
45
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS
46
A.
GENERAL REQUIREMENTS
46
B.
ROAD DESIGN STANDARDS
46
C.
ROAD CONSTRUCTION STANDARDS
48
TABLE OF CONTENTS
SECTION PAGE
1.
MINIMUM THICKNESS OF MATERIAL AFTER COMPACTION
48
2. PREPARATION
48
3. BASES AND PAVEMENT
48
D.
CLEANUP
49
E.
ROAD NAMES, SIGNS AND LIGHTING
49
F.
DRIVEWAY CULVERTS
50
G.
CERTIFICATION OF CONSTRUCTION
50
SECTION XVIII: BUFFER AND SCREENING STANDARDS
51
A.
SPECIAL BUFFER REQUIREMENTS ALONG TOWN WAYS
51
B.
BUFFERS AND SCREENING
52
C.
PLANT MATERIAL MAINTENANCE BOND REQUIRED
53
SECTION XIX: STORM DRAINAGE DESIGN AND CONSTRUCTION STANDARDS
54
A.
GENERAL PROVISIONS
54
B.
STORM WATER MANAGEMENT DESIGN STANDARDS
54
C.
STORM DRAINAGE CONSTRUCTION STANDARDS
55
1. REINFORCED CONCRETE PIPE
55
2. CORRUGATED METAL PIPE
55
3. ABS PIPE
55
4. CORRUGATED PLASTIC PIPE
55
5. MANHOLES
55
6. CATCH BASINS
55
7. DRAIN INLET ALIGNMENT
55
8. MANHOLE PLACEMENT
56
9. CATCH BASIN AND MANHOLE MAINTENANCE
56
SECTION XX:
PROVISION FOR CLUSTER DEVELOPMENT
57
A.
PURPOSE
57
B.
ALLOWABLE REDUCTION IN REQUIREMENTS
57
C.
PERFORMANCE STANDARDS
57
SECTION XXI:
ADDITIONAL REQUIRED IMPROVEMENTS
58
A.
MONUMENTS
58
B.
WATER SUPPLY
58
C.
SEWAGE DISPOSAL
58
D.
SURFACE DRAINAGE
59
E.
WALKWAYS, TRAILS
59
SECTION XXII: DEDICATION AND MAINTENANCE OF COMMON OPEN SPACE AND
SERVICES
60
A.
DEDICATION
60
B.
MAINTENANCE OF COMMON SPACE IN SUBDIVISIONS
60
SECTION XXIII: PERFORMANCE GUARANTEES
61
A.
TYPES OF GUARANTEES
61
B.
CONTENTS OF GUARANTEE
61
C.
ESCROW ACCOUNT
61
D.
PERFORMANCE BOND
61
E.
LETTER OF CREDIT
61
F.
CONDITIONAL AGREEMENT
62
G.
PHASING OF DEVELOPMENT
62
H.
RELEASE OF GUARANTEE
62
I.
DEFAULT
62
J.
PRIVATE ROADS
62
TABLE OF CONTENTS
SECTION PAGE
SECTION XXIV: WAIVERS
63
A.
WAIVER OF SUBMISSION REQUIREMENTS
63
B.
WAIVER OF PERFORMANCE STANDARDS
63
C.
WAIVERS OF REQUIRED IMPROVEMENTS
63
D.
WAIVERS OF CONDITIONALLY GRANTED
63
E.
WAIVERS LIMITED
63
F.
WAIVER REVOCABLE
63
SECTION XXV:
DEFINITIONS
64
1
SECTION I: GENERAL PROVISIONS
SECTION USER'S GUIDE: This section contains general information related to the title of
the Ordinance, the statutory authority under which it was prepared and adopted, and the
procedure for its amendment.
A. TITLE
This Ordinance shall be known and be cited as the "Subdivision Ordinance of the Town of Dedham,
Maine."
B. AUTHORITY
This Ordinance is enacted under the authority granted to the Town by the statutes of the State of
Maine and in accordance with the provisions of Title 30-A, MRSA, Section 4403.
C. APPLICABILITY
The provisions of this Ordinance shall apply to subdivisions as defined by this Ordinance and by Title
30-A, MRSA, Section 4401 and 4402 as amended, all lands within the boundaries of the Town of
Dedham.
D. CONFLICT WITH OTHER ORDINANCES
Whenever the requirements of this Ordinance are in conflict with the requirements of any other
lawfully adopted rule, regulation, ordinance, deed restriction or covenant, the more restrictive
requirements shall govern.
E. SUPERSEDURE
All Ordinances and parts of Ordinances in conflict with this Ordinance are hereby repealed, but only
to the extent of such conflict. The Subdivision Ordinance in effect at the time that this Subdivision
Ordinance is enacted is hereby repealed. Provided, however, that all lawfully adopted Ordinances or
parts thereof shall remain in full force and effect with respect to any violation thereof in existence at
the time of adoption of this Ordinance, and provided further that any such violation shall be deemed a
violation of this Ordinance and subject to its terms and provisions.
F. SEPARABILITY
In the event that any section, subsection or any provision of this Ordinance shall be declared by any
court of competent jurisdiction to be invalid for any reason, such decision shall not be deemed to
affect the validity of any other section, subsection or other portion of this Ordinance; to this end, the
provisions of this Ordinance are hereby declared to be severable.
G. AMENDMENTS
The procedure to be followed in initiating and securing amendments to this Ordinance is as follows:
1. INITIATION
A proposal to amend this Ordinance may be initiated by:
a. The Planning Board, by majority vote;
b. The Board of Selectmen,
c. Any 5 qualified voters may begin initiative proceedings by a request in writing to the Town
Clerk. The Clerk shall provide the appropriate petition blanks within 5 days of when they are
2
requested. The complete text of the proposed amendment shall be included in the request.
All papers of the petition shall be uniform in size and style and shall be assembled as one
instrument for filing. They shall contain or have attached there to throughout their circulation
the full text of the proposed amendment. These 5 qualified voters shall be referred to as the
Requesting Committee during the initiative procedure. The Requesting Committee shall have
30 days from the acceptance date of the request by the Town Clerk to cause the petitions to
be signed by 5% of the number of votes cast in the town at the last Gubernatorial Election but
not fewer than 70 voters. Any voter of Dedham may circulate the petition. The petition shall
be signed only once by qualified voters of the town and each voter's signature shall be
followed by his/her address. An affidavit-of-the-circulator, similar to that which is required in
MSRA title 30-A, section 2102(3) (b)(3), as amended, will be required.
Petitioners may present their petitions to the Clerk at any time during the circulation period.
Within 7 days after the petition circulation period ends, the Clerk shall certify to the Board of
Selectmen and notify the Requesting Committee that the petition has been signed by 5% of
the total of qualified voters who cast votes in the last Gubernatorial Election but not fewer
than 70 voters.
Should fewer qualified voters than required by this ordinance sign the petition in the specific
time, the petition shall have no further force or effect, and all proceedings thereon shall be
terminated. A request to initiate the same amendment may not be accepted by the Clerk until
120 days after the expiration of the previous filing period. The Board of Selectmen shall
process the request for the Subdivision Ordinance amendment in accordance with proper
procedure. Any such proposed amendment may be examined by the Town Attorney before
being circulated for signatures. The Town Attorney is authorized to edit the form of such
proposed amendment for the purpose of avoiding repetitions, illegalities, and unconstitutional
provisions, and to assure accuracy in its text and references, and clarity and precision in its
phraseology, but he/she shall not materially change its meaning and effect. If the Town
Attorney cannot edit or correct the proposed amendment, he/she shall so advise the
Requesting Committee who may revise the proposed amendment. If not revised, the Town
Attorney shall advise the voters at the public hearing of the shortcomings of the proposed
amendment.
d. When an amendment is proposed by other than the municipal officers or Planning Board, a
fee of to be established by policy approved by the Selectmen shall accompany the proposal
to cover the cost of review, hearings, and advertisements. This fee is non-refundable.
2. PROCESS OF ADOPTION
The process to be followed in adopting an amendment to this Ordinance is as follows:
a. Proposed amendments must first be submitted to the Planning Board for their consideration.
b. The Planning Board shall, within thirty (30) days of receiving a proposed amendment, set a
date to hold a public hearing on the proposed amendment.
c. Notice of the public hearing shall be given pursuant to the provisions of Section III.H of this
Ordinance.
d. The Planning Board shall make its official report at the next Board of Selectmen Meeting
following the public hearing.
e. Amendments adopted by the Board of Selectmen shall follow standard procedure.
H. EFFECTIVE DATE
The provisions of this Ordinance shall become effective the day of their enactment.
3
SECTION II: PURPOSES
SECTION USER'S GUIDE: This section explains the purposes of this Ordinance.
A. PROTECT GENERAL WELFARE
To assure the comfort, convenience, safety, health and welfare of the citizens of Dedham;
B. PROTECT ENVIRONMENT
To protect the natural resources from unacceptable adverse impacts and to integrate new
development harmoniously into the Town's natural environment;
C. PROMOTE COMMUNITY DEVELOPMENT
To promote the development of an economically sound and stable community;
D. BALANCE PROPERTY RIGHTS
To protect property rights and values by balancing the rights of landowners to use their land for the
purposes regulated by this Ordinance with the corresponding rights of abutting and neighboring
landowners to enjoy their property without undue disturbance;
E. REDUCE FISCAL IMPACT
To provide the means for evaluating subdivision proposals for their fiscal impact on the municipality's
ability to provide and improve necessary public facilities and services;
F. ESTABLISH PROCEDURES AND STANDARDS
To establish procedures whereby the Town Officials may review the developments regulated by this
Ordinance by providing fair and reasonable standards for evaluating such developments; and to
provide a public hearing process through which Town residents may raise questions and receive
answers regarding how such developments may affect them.
4
SECTION III: ADMINISTRATION
SECTION USER'S GUIDE: This section contains provisions for the administration of this
Ordinance including specific provisions for certificates of compliance, conditions of approval,
and public hearings.
A. ADMINISTERING BODY
The Planning Board of the Town of Dedham, hereinafter called the Board, shall administer this
Ordinance.
B. APPLICATION REQUIRED
Applications for approval shall be submitted in writing to the Board, on forms provided by it. The
Board may require the submission of whatever additional information is necessary to determine
compliance with the provisions of this Ordinance.
C. PERMITS TO BE APPLIED FOR BEFORE APPROVAL
Applications for approval under this Ordinance will not be considered complete for processing until all
other required local, state, and federal permits have been applied for and evidence that they have
been applied for or acquired has been provided to the Board.
D. COMMENCEMENT AND COMPLETION OF WORK
Construction and alteration activities on projects for which approval has been granted under this
Ordinance shall commence within six (6) months of the date of approval and shall be completed
within eighteen (18) months.
Activities which are not commenced or substantially completed within the time limits provided above
shall be subject to new application and the prior approval issued under this Ordinance shall be
considered void, unless an extension has been granted by the Board.
Activities may be extended for up to twelve (12) months at a time by the Planning Board upon a
showing of good cause where a written request setting forth the reasons for the extension is
submitted not later than thirty (30) days prior to the pending commencement or completion date.
E. CERTIFICATE OF CONSTRUCTION REQUIRED
No land in a subdivision requiring approval under this Ordinance shall be conveyed, rented, leased,
or occupied without a certificate of construction issued by the Code Enforcement Officer indicating
that all of the required public improvements have been constructed as required.
F. CONDITIONS OF APPROVAL
The Board may in approving applications attach such reasonable and appropriate terms and
conditions, in addition to those required elsewhere in this Ordinance, that it finds necessary to further
the purposes of this Ordinance. Such terms and conditions may include, but are not limited to,
specifications for:
1. Specific sewage or other waste disposal facilities;
2. Specific water supply facilities;
3. Landscaping and planting screens;
4. Sureties and bonds;
5
5. Restrictive covenants;
SECTION III: ADMINISTRATION (continued)
6. Location of piers, docks, parking areas and signs; and
7. Any other term or condition of approval necessary to fulfill the purposes of this Ordinance.
Violation of any of these terms or conditions shall be considered a violation of this Ordinance.
G. PUBLIC HEARINGS
In scheduling public hearings under this Ordinance, the Board shall notify the Applicant at least
twenty (20) days in advance of the date, time and place of the hearing. The Board shall publish notice
of the hearing at least seven (7) days in advance in a newspaper of general circulation in the area at
least two (2) times and shall post such notice in at least two (2) conspicuous public places. The first
notice shall appear at least seven (7) days in advance of the hearing.
At any hearing, a party may be represented by an agent or attorney. Hearings shall not be continued
to other times except for good cause. The applicant's case shall be presented first. To maintain
orderly procedure, each side shall proceed without interruption. Questions may be asked through the
Chair. All persons at the hearing shall abide by the order of the Chairman of the Board.
Whenever a public hearing is held pursuant to this Ordinance, the matters in that hearing may be
carried over until the next regularly or specially scheduled meeting of the Planning Board for further
public hearing without affecting any decisional deadline applicable to the Planning Board.
Ten (10) days after the public hearing, the administrative record shall close. Within thirty (30) days of
the public hearing, the Board shall reach a decision on the proposed subdivision plan and shall inform
the applicant and the Board of Selectmen in writing within ten (10) days of its decision stating its
reasons. The Board shall prepare detailed, written findings of fact, as well as its conclusions and the
reasons or basis thereof. These findings shall not be based on feelings or unsubstantiated
allegations, but upon all reasonable and admissible evidence that is submitted prior to the closing of
the record.
6
SECTION IV: CRITERIA OF APPROVAL
SECTION USER'S GUIDE: This section contains the criteria by which the Board will judge all
applications submitted pursuant to this Ordinance.
In approving applications submitted pursuant to this Ordinance, the Board shall find that:
A. POLLUTION
The proposed subdivision will not result in undue water or air pollution. In making this determination,
the Board shall at least consider:
1. The elevation of the land above sea level and its relation to the flood plains;
2. The nature of soils and subsoils and their ability to adequately support waste disposal;
3. The slope of the land and its effect on effluents;
4. The availability of streams for disposal of effluents; and
5. The applicable state and local health and water resource rules and regulations.
B. SUFFICIENT WATER SUPPLY
The proposed subdivision has sufficient water available for the reasonably foreseeable needs of the
subdivision;
C. MUNICIPAL WATER SUPPLY
The proposed subdivision will not cause an unreasonable burden on an existing water supply, if one
is to be utilized;
D. EROSION
The proposed subdivision will not cause unreasonable soil erosion or a reduction in the land's
capacity to hold water so that a dangerous or unhealthy condition results;
E. TRAFFIC
The proposed subdivision will not cause unreasonable highway or public road congestion or unsafe
conditions with respect to use of the highways or public roads existing or proposed;
F. SEWAGE DISPOSAL
The proposed subdivision will provide for adequate sewage waste disposal; and will not cause an
unreasonable burden on municipal services if they are utilized;
G. MUNICIPAL SOLID WASTE DISPOSAL
The proposed subdivision will not cause an unreasonable burden on the municipality's ability to
dispose of solid waste, if municipal services are to be utilized;
H. AESTHETIC, CULTURAL AND NATURAL VALUES
The proposed subdivision will not have an undue adverse effect on the scenic or natural beauty of the
area, aesthetics, historic sites, significant wildlife habitat identified by the Department of Inland
Fisheries and Wildlife or the municipality, or rare and irreplaceable natural areas or any public rights
for physical or visual access to the shoreline;
7
SECTION IV: CRITERIA OF APPROVAL (continued)
I.
CONFORMITY WITH LOCAL ORDINANCES AND PLANS
The proposed subdivision conforms with this subdivision ordinance and any duly adopted
Comprehensive Plan, development plan or land use plan, if any. In making this determination, the
municipal reviewing authority may interpret these ordinances and plans;
J. FINANCIAL AND TECHNICAL CAPACITY
The subdivider has adequate financial and technical capacity to meet the standards of this section;
K. SURFACE WATERS
Whenever situated entirely or partially within the watershed of any pond or lake or within 250 feet of
any wetland, great pond or river as defined in Title 38, Chapter 3, Subchapter I, Article 2-B, the
proposed subdivision will not adversely affect the quality of that body of water or unreasonably affect
the shoreline of that body of water;
L. GROUND WATER
The proposed subdivision will not, alone or in conjunction with existing activities, adversely affect the
quality or quantity of ground water;
M. FLOOD AREAS
Based on the Federal Emergency Management Agency's Flood Boundary and Floodway Maps and
Flood Insurance Rate Maps, and information presented by the applicant, whether the subdivision is in
a flood-prone area. If the subdivision, or any part of it, is in such an area, the subdivider shall
determine the 100-year flood elevation and flood hazard boundaries within the subdivision. The
proposed subdivision plan must include a condition of plan approval requiring that principal structures
in the subdivision will be constructed with their lowest floor, including the basement, at least one foot
above the 100-year flood elevation;
N. FRESHWATER WETLANDS
All potential freshwater wetlands within the proposed subdivision have been identified on any maps
submitted as part of the application, regardless of the size of these wetlands. Any mapping of
freshwater wetlands may be done with the help of the local soil and water conservation district.
O. RIVER, STREAM OR BROOK
Any river, stream or brook within or abutting the proposed subdivision has been identified on any
maps submitted as part of the application. For purposes of this section, "river, stream or brook" has
the same meaning as in Title 38, Section 480-B, Subsection 9.
P. STORM WATER
The proposed subdivision will provide for adequate storm water management.
Q. STATE SUBDIVISION LAW CRITERIA
In addition to the criteria above, the Board shall find that the proposed subdivision meets any
additional criteria added by the Legislature to Title 30-A, MRSA, Section 4404, from time to time.
8
SECTION IV: CRITERIA OF APPROVAL (continued)
R. WRITTEN FINDINGS OF FACT REQUIRED
In approving subdivisions under this Ordinance, the Board shall consider the criteria above; and
before granting approval, shall make written findings of fact that the provisions of this Ordinance have
been met.
S. BURDEN OF PROOF
In all instances the burden of proof of compliance with the above criteria shall be upon the person
proposing the subdivision.
9
SECTION V: VIOLATIONS AND ENFORCEMENT
SECTION USER'S GUIDE: This section contains specific provisions describing those actions
which shall be considered violations of this Ordinance and procedures for enforcement. It also
provides that contractors shall be held liable for their actions which are in violation of this
Ordinance. The violations enumerated in this section shall not be exclusive; any other section
that identifies a violation shall be valid.
A. RECORDING OF SUBDIVISION PLAN WITHOUT PRIOR APPROVAL PROHIBITED
No plan of a division of land within the municipality which would constitute a subdivision under this
Ordinance shall be recorded in the Registry of Deeds until a Final Plan has been approved by the
Board in accordance with this Ordinance.
B. CONVEYANCE WITHOUT RECORDING PROHIBITED
No person may sell, lease, develop, build upon or convey for consideration, or offer or agree to sell,
lease, develop, build upon or convey for consideration any land in a subdivision which has not been
approved by the Board and recorded in the Registry of Deeds.
C. CONVEYANCE OF LOTS NOT SHOWN ON FINAL PLAN PROHIBITED
No person may sell, lease, develop, build upon or convey for consideration, or offer or agree to sell,
lease, develop, build upon or convey for consideration any land in an approved subdivision which is
not shown on the Final Plan as a separate lot.
D. CONVEYANCE WITHOUT APPROVAL PROHIBITED
No person may sell, lease, develop, build upon or convey for consideration, or offer or agree to sell,
lease, develop, build upon or convey for consideration any land in a subdivision requiring approval
under this Ordinance, which has not been approved as required by this Ordinance.
E. UTILITY HOOKUPS PRIOR TO APPROVAL PROHIBITED
A public utility, water district, sanitary district, or any utility company of any kind may not install
services to any lot or dwelling unit in a subdivision, unless written authorization attesting to the validity
and currency of all local permits required by the Town of Dedham has been issued by the appropriate
municipal officers or other written arrangements have been made between the municipal officers and
the utility.
F. DEVELOPMENT PRIOR TO APPROVAL PROHIBITED
Development of a subdivision or project requiring approval under this Ordinance, without Board
approval shall be a violation. Development includes grading or construction of roads, grading of land
or lots, or construction of buildings which require a Final Plan approved as provided in this Ordinance.
G. ROAD COMPLETION PRIOR TO CONVEYANCE REQUIRED
No lot in a subdivision may be sold, leased, or otherwise conveyed before the Road upon which the
lot fronts is completed in accordance with this Ordinance up to and including the entire frontage of the
lot. No unit in a multi-family development shall be occupied before the road upon which the unit is
accessed is completed in accordance with this Ordinance.
10
SECTION V: VIOLATIONS AND ENFORCEMENT (continued)
H. FAILURE TO COMPLY WITH CONDITIONS OF APPROVAL
Failure to comply with any conditions of approval shall be construed to be a violation of this
Ordinance and shall be grounds for revoking the approved development plan, initiating legal
proceedings to enjoin construction, development or any specific activity violating the conditions of
permit approval or applying the legal penalties provided herein.
I. FAILURE TO PAY
Failure to pay application fees, filing fees, and technical review accounts as required by this
Ordinance shall be considered a violation of this Ordinance, which will stop the review process and
void approvals.
J. OWNER RESPONSIBLE FOR OFF-SITE SEDIMENTATION
Whenever sedimentation is caused by stripping vegetation, re-grading or other development, it shall
be the responsibility of the owner to remove sediment from all adjoining surfaces, drainage systems
and watercourses and to repair any drainage, at his expense, as quickly as possible. Failure to do so
within two (2) weeks after official notification by registered mail (return receipt requested) by the Code
Enforcement Officer shall be considered a violation of this Ordinance.
K. NUISANCES
Any violation of this Ordinance shall be deemed a nuisance.
L. CODE ENFORCEMENT OFFICER
It shall be the duty of the Code Enforcement Officer to enforce the provisions of this Ordinance. If the
Code Enforcement Officer shall find that any provision of this Ordinance is being violated, the person
or persons responsible for such violation, shall be notified in writing, including the nature of the
violation and ordering the action necessary to correct it, including the discontinuance of illegal use of
land, buildings, or structures, and abatement of nuisance conditions. A copy of such notice shall be
maintained as a permanent record.
M. LEGAL ACTIONS
When there is a violation of this Ordinance, the Selectmen, upon notice from the Code Enforcement
Officer, are hereby authorized and directed to institute any and all actions and proceedings, either
legal or equitable, including seeking injunctions of violations and the imposition of fines, that may be
appropriate or necessary to enforce the provisions of this Ordinance in the name of the Town. The
Code Enforcement Officer, upon certification, is hereby authorized to represent the Town in District
Court pursuant to Title 30-A, MRSA, Sec. 4451 et seq.. In any case, the Town Attorney may
prosecute such actions.
N. FINES & FEES
Any violation of this Ordinance is punishable pursuant to Title 30-A, MRSA, section 4452. The
provisions of that statute governing fines and fees are expressly applicable to violations under this
ordinance. Each day such violation is continued is a separate offense. All such fines shall accrue to
the Town.
O. CONTRACTOR LIABILITY
Any contractor involved in any activity regulated by the provisions of this Ordinance may be held
liable for violating this Ordinance if the necessary permits and/or approvals for such activity have not
been obtained.
11
SECTION VI: APPEAL TO SUPERIOR COURT
SECTION USER'S GUIDE: This section contains specific provisions regarding the appeal of Planning
Board decisions to Superior Court.
An appeal may be taken within thirty (30) days after any decision is rendered by the Planning Board,
by any party to Superior Court in accordance with State Law.
12
SECTION VII: ADMINISTRATIVE PROCEDURES
A. AGENDA REQUIRED
In order to provide an orderly process for reviewing applications, an agenda shall be prepared in
advance of each regularly scheduled Planning Board meeting.
B. APPROVAL REQUIRED
After the effective date of this Ordinance, no person shall engage in any activity requiring a permit
under this Ordinance without first obtaining the approval of the Board.
C. AGENDA MAY BE LIMITED
The Planning Board, in order to conduct a thorough review of applications submitted to it, may limit
such review to one subdivision application per regularly scheduled meeting.
13
SECTION VIII: PRE-APPLICATION CONFERENCE/SKETCH PLAN REVIEW
SECTION USER'S GUIDE: This section contains provisions related to the procedures to be followed and
submissions required during the Pre-Application/Sketch Plan Review stage of the subdivision review
process provided by this Ordinance.
A. GENERAL
All applicants shall meet with the Planning Board prior to the formal submission of a subdivision plan
to generally discuss their proposed subdivision and to obtain guidance from the Planning Board in the
development of the plan.
B. PROCEDURE
The procedures for Sketch Plan Review are as follows:
STEP 1:
ADVANCE REQUEST TO BE PLACED ON AGENDA REQUIRED
The applicant shall request, through the Code Enforcement Officer, to be placed on the
Planning Board's agenda, for a pre-application conference, at least twenty-eight (28)
days prior to the regularly scheduled meeting at which the applicant wishes to be heard.
STEP 2:
CEO REVIEW OF SUBMISSION PACKET FOR COMPLETENESS
The Code Enforcement Officer shall not place an applicant on the agenda until
determining that the applicant has presented the submission packet as specified in
subsection C of this section.
STEP 3:
PLANNING BOARD REVIEWS SKETCH PLAN AND EXHIBITS
At the pre-application meeting, the Planning Board shall review the Sketch Plan and
accompanying exhibits with the applicant, answer the applicant's questions, and make
specific suggestions to be incorporated by the applicant in subsequent submissions.
STEP 4:
CLASSIFICATION OF SUBDIVISION
At the pre-application meeting, the Planning Board shall classify the proposed subdivision
as either a minor or major subdivision and so notify the applicant in writing.
STEP 5:
CONTOUR INTERVAL ESTABLISHED
At the pre-application meeting, the Planning Board shall determine the contour intervals
for subsequent submissions and shall notify the applicant in writing that either 1, 2, or 5-
foot contour intervals are required.
STEP 6:
ON-SITE INSPECTION DATE SET
At the pre-application meeting, the Planning Board shall schedule an on-site inspection of
the tract or parcel to be subdivided and shall notify the applicant of the time and date in
writing.
The on-site inspection shall be jointly attended by the applicant or a duly authorized
agent and by at least one member of the Planning Board or an individual appointed by
the chairman of the Planning Board to act as the Board's authorized representative for
such inspection.
14
SECTION VIII: PRE-APPLICATION CONFERENCE/SKETCH PLAN REVIEW (continued)
C. SUBMISSION PACKET
The submission packet required for Sketch Plan Review shall include the following:
1. SKETCH PLAN
A Sketch Plan, showing the information specified in d. below, shall be submitted to the Planning
Board.
a. NUMBER OF COPIES:
Ten (10) paper copies of the Sketch Plan shall be submitted.
b. SHEET SIZE:
The Sketch Plan shall be at least 11 x 17 inches, but no larger than 24 x 36 inches in size.
c. PLAN SCALE:
The Sketch Plan shall be drawn to scale.
d. INFORMATION TO BE SHOWN ON THE PLAN:
The following information shall be shown on all Sketch Plans:
1) The outline of the tract or parcel to be subdivided, with known or, if not known, acreage of
parcel, estimated perimeter dimensions;
2) True north arrow;
3) The scale to which the plan is drawn;
4) The proposed layout of lots, roads, driveways, and building locations;
5) Identification of general areas of slopes fifteen percent (15%) or greater, areas of
exposed ledge, streams and floodplain;
6) Location of public utilities proposed to be utilized;
7) Wetlands, regardless of size, prepared by a State Certified Soil Scientist or Geologist
registered in the State of Maine, based on an on-site investigation, streams or ponds
located in whole or in part on the parcel proposed to be subdivided.
8) The tax map and lot numbers from Tax Assessor's Office describing the parcel proposed
to be subdivided; and
9) The present zoning classification of the parcel.
2. EXHIBITS TO ACCOMPANY SKETCH PLAN
Exhibits 1, 2, 3, and 4 as specified in Section XII.C of this Ordinance shall accompany the
Sketch Plan and be submitted with the Sketch Plan to the Code Enforcement Officer when
requesting a pre-application conference.
D. RIGHTS NOT VESTED
The submittal or review of the pre-application sketch plan shall not be considered the initiation of the
review process for the purposes of bringing the plan under the protection of Title 1, MRSA, Section
302.
15
SECTION IX: SUBDIVISION REVIEW PROCESS: MINOR SUBDIVISIONS
SECTION USER'S GUIDE: This section contains provisions related to the process to be
followed during the review of Minor Subdivisions.
A. MINOR SUBDIVISION MAY HAVE TO COMPLY WITH MAJOR SUBDIVISION REQUIREMENTS
The Planning Board may require, where it deems it necessary for the protection of public health,
safety and general welfare, that a Minor Subdivision complies with all or any of the procedural and
submission requirements of a Major Subdivision.
B. SUBMISSION PACKET
The submission packet required for Minor Subdivisions shall include the following:
1. APPLICATION AND EXHIBITS
An application and attachments for Planning Board review of Minor Subdivisions shall be
submitted as specified in Section XII of this Ordinance.
2. FINAL SUBDIVISION PLAN
A Final Subdivision Plan for Planning Board review of Minor Subdivisions shall be submitted as
specified in Section XIII of this Ordinance.
3. ADMINISTRATIVE FEES AND ESCROW ACCOUNT
An administrative fee and escrow account for Planning Board review of Minor Subdivisions shall
be submitted as specified in Section XIV of this Ordinance.
C. PROCEDURE
The procedures for reviewing Minor Subdivision Plans are as follows:
STEP 1:
REQUEST FOR FINAL PLAN REVIEW
Within six (6) months after classification of the proposed subdivision as a Minor
Subdivision, the Applicant shall submit a complete Final Plan to the Code Enforcement
Officer and request, through the Code Enforcement Officer, to be placed on the Planning
Board's agenda.
Such a request shall be made at least twenty-eight (28) days prior to the regularly
scheduled meeting at which the applicant wishes to be heard.
Failure to do so within the six (6) months of classification may require a new pre-
application conference.
STEP 2:
CEO REVIEWS SUBMISSION PACKET FOR COMPLETENESS
The Code Enforcement Officer shall not place an applicant on the agenda until
determining that the applicant has presented the submission packet required for Minor
Subdivisions by this Ordinance.
If the Code Enforcement Officer determines that the submission packet is not complete,
the submissions shall be returned to the applicant with a Notice Of Incomplete
Submission, specifying the required information found to be missing. If the Code
Enforcement Officer determines that the submission packet is complete, the
16
SECTION IX: SUBDIVISION REVIEW PROCESS: MINOR SUBDIVISIONS (continued)
applicant shall be issued a Dated Receipt Of Application and place the application on the
agenda of the next regularly scheduled Planning Board meeting.
STEP 3:
NOTICE TO ABUTTERS AND ADJACENT MUNICIPALITY
Upon the issuance of a Dated Receipt Of Application, the Code Enforcement Officer shall
notify by mail all abutting property owners of the proposed subdivision, and the Clerk and
Planning Board of municipalities that abut or include any portion of the proposed
subdivision, if the proposed subdivision in fact abuts or is in part within another
municipality.
Such notice shall specify that a Final Plan and application for a proposed Minor
Subdivision has been received, the location of the proposed Minor Subdivision, and give
a general description of the proposal.
STEP 4:
PLANNING BOARD REVIEWS FINAL PLAN AND APPLICATION
Within thirty (30) days from the receipt of an application, the Planning Board shall review
the Final Plan and submissions for completeness.
If the Planning Board determines that the application is not complete, it shall issue the
applicant a Notice Of Incomplete Application specifying the additional information
expected prior to further action on the application.
The applicant shall have thirty (30) days thereafter to submit a complete Final Plan. A
failure to submit a complete Final Plan within that time shall require that the Preliminary
Plan be re-reviewed as provided in Section VIII, pre-application conference/sketch plan
review.
If the Planning Board determines that the application is complete, it shall issue the
applicant a Notice of Complete Application.
A Notice Of Complete Application does not constitute the Planning Board's approval of
the information submitted. The Planning Board reserves the right to request additional
information throughout the review process up to and until Final Plan Approval.
Full evaluation of the Final Plan shall begin only after the Planning Board has determined
that a complete application has been filed. This evaluation may commence at the same
meeting at which the determination of completeness has been made.
STEP 5:
FINAL PLAN PUBLIC HEARING DISCRETIONARY
Within thirty (30) days of the Planning Board's determination that a complete application
has been submitted or within such other time limit as may be mutually agreed to by the
Planning Board and the Applicant, the Planning Board may decide that the proposed
Minor Subdivision lacks such complexity that a public hearing is not warranted and not
hold a public hearing on the Final Plan of the proposed Minor Subdivision.
Notice of the public hearing shall be given pursuant to the provisions of Section III.G of
this Ordinance.
STEP 6.
PLANNING BOARD DECISION ON FINAL PLAN
Within sixty (60) days of the Planning Board's determination that a complete application
has been submitted, or within thirty (30) days of the public hearing should a public
hearing be held, or within such other time limit as may be mutually agreed to by the
Planning Board and the Applicant, the Planning Board shall approve, approve with
conditions, or disapprove the Final Plan of the proposed Minor Subdivision.
17
SECTION IX: SUBDIVISION REVIEW PROCESS: MINOR SUBDIVISIONS (continued)
The Planning Board's failure to grant an approval within the deadlines specified above
shall constitute a denial of the application by the Board, unless the applicant waives the
specified deadlines.
In issuing its decision, the Planning Board shall make written findings of fact and
conclusions of law that the proposed Final Plan does or does not meet the criteria in
Section IV of this Ordinance.
STEP 7:
SIGNATURES
Upon approving the Final Plan, those members of the Planning Board voting for approval
shall sign two (2) reproducible copies and two (2) paper copies of the approved
Subdivision Plan.
STEP 8:
FILING OF APPROVED FINAL PLAN
Planning Board Orders and approved Final Plans for Minor Subdivisions shall be filed in
the Hancock County Registry of Deeds as specified in Section XI of this Ordinance.
18
SECTION X: SUBDIVISION REVIEW PROCESS: MAJOR SUBDIVISIONS
SECTION USER'S GUIDE: This section contains provisions related to the process to be
followed during the review of Major Subdivisions.
A. PROCEDURE
The procedures for reviewing Major Subdivision Plans are as follows:
STEP 1:
REQUEST FOR REVIEW OF PRELIMINARY PLAN
Within six (6) months after classification of the proposed subdivision as a Major
Subdivision, the Applicant shall request, through the Code Enforcement Officer, to be
placed on the Planning Board's agenda for Major Subdivision Preliminary Plan review.
Such a request shall be made at least twenty-eight (28) days prior to the regularly
scheduled meeting at which the applicant wishes to be heard.
Failure to do so within six (6) months of classification may require a new pre-application
conference.
STEP 2:
CEO REVIEWS SUBMISSION PACKET FOR COMPLETENESS
The Code Enforcement Officer shall not place an applicant on the agenda until
determining that the applicant has presented the submission packet required for
Preliminary Plan review of Major Subdivisions by this Ordinance.
If the Code Enforcement Officer determines that the submission packet is not complete,
the submissions shall be returned to the applicant with a Notice Of Incomplete
Submission, specifying the required information found to be missing.
If the Code Enforcement Officer determines that the submission packet is complete, the
applicant shall be issued a Dated Receipt Of Application and place the application on the
agenda of the next regularly scheduled Planning Board meeting.
STEP 3:
NOTICE TO ABUTTERS AND ADJACENT MUNICIPALITY
Upon the issuance of a Dated Receipt Of Application, the Code Enforcement Officer shall
notify by mail all abutting property owners of the proposed subdivision, and the Clerk and
Planning Board of municipalities that abut or include any portion of the proposed
subdivision, if the proposed subdivision in fact abuts or is in part within another
municipality.
Such notice shall specify that a Preliminary Plan and application for a proposed Major
Subdivision has been received, the location of the proposed Major Subdivision, and give
a general description of the proposal.
STEP 4:
PLANNING BOARD REVIEWS PRELIMINARY PLAN AND APPLICATION
Within thirty (30) days from the receipt of an application, the Planning Board shall review
the Preliminary Plan and submissions for completeness.
If the Planning Board determines that the application is not complete, it shall issue the
applicant a Notice Of Incomplete Application specifying the additional information
expected prior to further action on the application.
If the Planning Board determines that the application is complete, it shall issue the
applicant a Notice of Complete Application.
19
SECTION X: SUBDIVISION REVIEW PROCESS: MAJOR SUBDIVISIONS (continued)
A Notice of Complete Application does not constitute the Planning Board's approval of
the information submitted. The Planning Board reserves the right to request additional
information throughout the review process up to and until Final Plan Approval.
Full evaluation of the Preliminary Plan shall begin only after the Planning Board has
determined that a complete application has been filed. This evaluation may commence
at the same meeting at which the determination of completeness has been made.
STEP 5:
PRELIMINARY PLAN PUBLIC HEARING MANDATORY
Within thirty (30) days of the Planning Board's determination that a complete application
has been submitted, or within such other time limit as may be mutually agreed to by the
Planning Board and the applicant, the Planning Board shall hold a public hearing on the
Preliminary Plan of the proposed Major Subdivision.
Notice of the public hearing shall be given pursuant to the provisions of Section III.G of
this Ordinance.
STEP 6:
PLANNING BOARD DECISION ON PRELIMINARY PLAN
Within thirty (30) days of the public hearing, or within such other time limit as may be
mutually agreed to by the Planning Board and the Applicant, the Planning Board shall
approve, approve with conditions, or disapprove the Preliminary Plan of the proposed
Major Subdivision.
In issuing its decision, the Planning Board shall make written findings of fact that the
proposed Preliminary Plan does or does not meet the criteria in Section IV of this
Ordinance. No signature on the Preliminary Plan shall be required.
STEP 7:
REQUEST FOR REVIEW OF FINAL PLAN
Within six (6) months after approval of a Preliminary Plan for a Major Subdivision, the
applicant shall submit a complete plan to the Code Enforcement Officer and request,
through the Code Enforcement Officer, to be placed on the Planning Board's agenda for
Final Plan review.
Such a request shall be made at least thirty (30) days prior to the next regularly
scheduled meeting at which the applicant wishes to be heard.
Failure to do so within the six (6) months of Preliminary Plan approval shall require that
the Preliminary Plan be re-reviewed as provided in Steps 1 through 6, above.
Time spent by the Code Enforcement Officer in reviewing the packet pursuant to Step 8
shall not be counted in computing whether six (6) months have passed. This amendment
shall apply to all applications, including those that have already received substantive
review. Applications that have received substantive review at the time that this
amendment is approved shall have six (6) months from the date of approval of the
amendment to comply with these requirements.
STEP 8:
CEO REVIEWS SUBMISSION PACKET FOR COMPLETENESS
The Code Enforcement Officer shall not place an applicant on the agenda until
determining that the applicant has presented the submission packet required for Final
Plan review of Major Subdivisions by this Ordinance.
If the Code Enforcement Officer determines that the submission packet is not complete,
the submissions shall be returned to the applicant with a Notice Of Incomplete
Submission, specifying the required information found to be missing.
20
SECTION X: SUBDIVISION REVIEW PROCESS: MAJOR SUBDIVISIONS (continued)
If the Code Enforcement Officer determines that the submission packet is complete, the
applicant shall be issued a Dated Receipt of Application and place the application on the
agenda of the next regularly scheduled Planning Board meeting.
STEP 9:
NOTICE TO ABUTTERS AND ADJACENT MUNICIPALITY OF FINAL PLAN
Upon the issuance of a Dated Receipt Of Application, the Code Enforcement Officer shall
notify by mail all abutting property owners of the proposed subdivision, and the Clerk and
Planning Board of municipalities that abut or include any portion of the proposed
subdivision, if the proposed subdivision in fact abuts or is in part within another
municipality.
Such notice shall specify that a Final Plan and application for a proposed Major
Subdivision has been received, the location of the proposed Major Subdivision, and give
a general description of the proposal.
STEP 10:
PLANNING BOARD REVIEWS FINAL PLAN
Within thirty (30) days from the receipt of the Final Plan, the Planning Board shall notify
the applicant in writing either that the Final Plan is complete or, if the Final Plan is
incomplete, the specific additional action needed to make a complete Final Plan.
If the Planning Board finds that the application is incomplete the applicant shall have
thirty (30) days thereafter to submit a complete Final Plan. A failure to submit a complete
Final Plan within that time shall require that the Preliminary Plan be re-reviewed as
provided in Steps 1 through 6, above; to be followed by compliance with Steps 7 through
9, above.
STEP 11:
FINAL PLAN PUBLIC HEARING
Within thirty (30) days of the Planning Board's determination that a complete application
has been submitted, or within such other time limit as may be mutually agreed to by the
Planning Board and the applicant, the Planning Board may decide to hold a public
hearing on the Final Plan of the proposed Major Subdivision.
Notice of the public hearing shall be given pursuant to the provisions of Section III.G of
this Ordinance.
STEP 12:
PLANNING BOARD DECISION ON FINAL PLAN
Within sixty (60) days of the Planning Board's determination that a complete application
has been submitted, or within thirty (30) days of the public hearing, in the event the
Planning Board decides to hold a public hearing, or within such other time limit as may be
mutually agreed to by the Planning Board and the Applicant, the Planning Board shall
approve, approve with conditions, or disapprove the Final Plan of the proposed Major
Subdivision.
In issuing its decision, the Planning Board shall make written findings of fact and
conclusions of law that the proposed Final Plan does or does not meet the criteria in
Section IV of this Ordinance.
STEP 13:
SIGNATURES
Upon approving the Final Plan, those members of the Planning Board voting for approval
shall sign two (2) reproducible copies and two (2) paper copies of the approved
Subdivision Plan.
21
SECTION X: SUBDIVISION REVIEW PROCESS: MAJOR SUBDIVISIONS (continued)
STEP 14:
FILING OF APPROVED FINAL PLAN
Planning Board Orders and approved Final Plans for Major Subdivisions shall be filed in
the Hancock County Registry of Deeds as specified in Section XI of this Ordinance.
B. SUBMISSION PACKET
The submission packet required for Major Subdivisions shall include the following:
1. APPLICATION AND ATTACHMENTS
An application and attachments for Planning Board review of Major Subdivisions shall be
submitted as specified in Section XII of this Ordinance.
2. FINAL SUBDIVISION PLAN
A Final Subdivision Plan for Planning Board review of Major Subdivisions shall be submitted as
specified in Section XIII of this Ordinance.
3. ADMINISTRATIVE FEES AND ESCROW ACCOUNT
An administrative fee and escrow account for Planning Board review of Major Subdivisions shall
be submitted as specified in Section XIV of this Ordinance.
22
SECTION XI: FILING PROCEDURES FOR APPROVED SUBDIVISIONS
SECTION USER'S GUIDE: This section contains provisions related to the process to be
followed in filing Planning Board Orders and approved Subdivision Plans in the Registry of
Deeds.
A. FILING OF PLANNING BOARD ORDERS REQUIRED PRIOR TO SIGNING OF AND FILING OF
APPROVED FINAL SUBDIVISION PLANS
A copy of the Planning Board's Order regarding any Final Subdivision Plans, including the Board's
findings of fact and conclusions and any conditions of approval shall be filed, by the applicant, in the
Hancock County Registry of Deeds.
The book and page number of such recording shall appear and be referenced on the approved Final
Subdivision Plan prior to the recording of such Plan, as set forth in Section C below.
B. FILING SECURITY DEPOSIT REQUIRED
Prior to the Planning Board's signing of the Final Subdivision Plan, the applicant shall provide the
Planning Board with a filing securing deposit, in the form of a cashier's check, in the amount specified
in the policy adopted by the Selectmen made payable to the Town of Dedham.
C. SIGNING OF APPROVED FINAL SUBDIVISION PLANS
Upon receipt of a copy of the recorded Planning Board Order, stamped by the Hancock County
Registry of Deeds, and a filing security deposit, the Planning Board shall enter in ink, in the places
provided in the Final Subdivision Plan Approval Block, the book and page and/or file numbers where
such Planning Order is recorded in the Hancock County Registry of Deeds.
After entering the book and page numbers, a majority of the members of the Planning Board shall
sign, their names in ink in the places provided, on the two (2) reproducible copies and two (2) paper
copies of the approved Final Subdivision Plan.
D. FILING OF THE SIGNED SUBDIVISION PLAN
The signed original Final Subdivision Plan shall be filed, by the applicant, within thirty (30) days of the
date of Planning Board signatures, in the Hancock County Registry of Deeds.
E. FAILURE TO FILE AS REQUIRED TO RESULT IN VOIDING OF APPROVAL AND FORFEITURE
OF FILING SECURITY DEPOSIT
In the event that the applicant fails to file the approved Final Subdivision Plan within the thirty (30)
days provided in Section D above, the Planning Board's approval shall be considered void and the
filing security deposit forfeited.
F. RETURN OF FILING SECURITY DEPOSIT
Upon receipt from the applicant, of a copy of the approved Final Subdivision Plan, stamped and dated
by the Registry of Deeds, the filing security deposit shall be refunded to the applicant by the Town.
G. FORFEITED DEPOSITS ACCRUE TO THE TOWN
In the event the applicant forfeits his/her filing security deposit, such funds shall accrue to the benefit
of the Town.
23
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS
SECTION USER'S GUIDE: This section contains provisions related to the application forms to
be used in the Subdivision Review Process and the information to be provided thereon and
information to be attached thereto.
A. APPLICATION FORM
The application form used in the subdivision review process contained in this Ordinance shall be
provided by the Town, filled out by the Applicant and shall include the information required below.
B. INFORMATION TO BE SUBMITTED
The following information shall be included in the application forms submitted to the Planning Board
With the Final Plans for all Minor Subdivisions and with the Preliminary Plans for all Major
Subdivisions:
1. INFORMATION REGARDING THE APPLICANT
a. The name, address, and phone number of the Owner of Record (Applicant).
b. Information regarding the applicant's right, title, or interest in the parcel proposed to be
subdivided.
c. Information as to whether or not the applicant is a corporation and, if so, whether or not the
corporation is licensed to do business in Maine.
d. The name, address, and phone number of the applicant's authorized agent (if an agent is
applying on behalf of applicant).
e. The name, address, phone number, and registration number of the Land Surveyors, and/or
Land Planners employed by the applicant to design the proposed subdivision.
f.
The name, address, and phone number of the individuals to whom all communications from
the Planning Board should be directed.
g. Information regarding the applicant's interest in any property abutting the parcel proposed to
be subdivided and that the proposed subdivision plan covers his/her entire, contiguous
holdings.
2. INFORMATION REGARDING PARCEL PROPOSED TO BE SUBDIVIDED
a. The book and page numbers from Registry of Deeds describing the parcel proposed to be
subdivided.
b. The tax map and lot numbers from Tax Assessor's Office describing the parcel proposed to
be subdivided.
c. The existing use of the property proposed to be subdivided.
d. The total acreage of parcel proposed to be subdivided.
e. The present zoning of parcel proposed to be subdivided.
f.
Whether or not the parcel proposed to be subdivided is part of a prior approved subdivision.
g. Whether or not any part of the parcel proposed to be subdivided is within the Shoreland
Zone.
h. Whether or not there are any freshwater wetlands prepared by a State Certified Soil Scientist
24
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
or Geologist registered in the State of Maine, based on an on-site investigation, streams
or ponds located in whole or in part on the parcel proposed to be subdivided.
i.
Whether or not there are any significant groundwater aquifers located in whole or in part on
the parcel proposed to be subdivided.
j.
Whether or not the parcel proposed to be subdivided is in whole or in part located within an
identified special flood hazard area.
k. Whether or not the parcel proposed to be subdivided has any identified critical natural
resources or wildlife habitats, as identified in the 1994 Comprehensive Plan (amended
October 5, 1995), located in whole or in part on the parcel proposed to be subdivided.
l. The location of snowmobile trails shown on the Interconnecting Trail System map
published by the Maine Department of Conservation, or recognized, club-maintained trails.
m. Whether or not the parcel proposed to be subdivided contains any scenic areas as
identified in the 1994 Comprehensive Plan (amended October 5, 1995).
3. INFORMATION REGARDING PROPOSED SUBDIVISION
a. Name of the proposed subdivision.
b. Type of proposed subdivision. (e.g.: residential, commercial, mobile home, mixed, etc.)
c. Number of lots and/or units proposed.
d. Information regarding proposed methods of disposing of sewage wastes generated by the
proposed subdivision.
e. Information regarding proposed methods of supplying water required by the proposed
subdivision.
f.
Information regarding proposed methods of disposing of solid wastes generated by the
proposed subdivision.
g. Information regarding proposed methods of controlling and/or preventing soil erosion and
sedimentation resulting from the proposed subdivision.
h. Information regarding proposed methods of handling changes in storm water and/or surface
water drainage patterns resulting from the proposed subdivision.
i.
Information regarding proposed interior subdivision roads.
j.
Information regarding proposed methods of handling traffic volumes projected to be
generated by the proposed subdivision.
k. Estimated dates of starting and completing any proposed construction.
l.
Estimated costs of required and proposed improvements.
C. EXHIBITS TO ACCOMPANY SUBDIVISION APPLICATIONS
The following are specifications for exhibits to accompany subdivision applications.
EXHIBIT 1:
LOCATION MAP
All subdivision applications shall be accompanied by a copy of a 7.5 minute USGS
quadrangle map or maps, in the center of which the boundaries of the proposed
25
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
subdivision have been delineated, trimmed to an 8 ½"x11" sheet size.
EXHIBIT 2:
TAX MAP
All subdivision applications shall be accompanied by a copy, reduced to 8 1/2" x 11",
of the Property Tax Map on which the parcel proposed to be subdivided is located,
with the property cross-hatched or otherwise graphically identified. Copies of these
maps are available at the Town Offices.
EXHIBIT 3:
DOCUMENTATION OF RIGHT, TITLE OR INTEREST
All subdivision applications shall be accompanied by a copy of a deed, purchase and
sale agreement, or similar document demonstrating a legal right, title, or interest in
the parcel proposed to be subdivided.
EXHIBIT 4:
WRITTEN AND GRAPHIC HISTORY OF OWNERSHIP AND DIVISION
All subdivision applications shall be accompanied by a written and graphic history of
the ownership of the property and any division of the property during the past five (5)
years. This history shall include the names and addresses of persons to whom any
divisions have been conveyed, the date of any such conveyances, and copies of
such conveyances as recorded in the Hancock County Registry of Deeds. When
submitted as part of an application for Preliminary Plan approval, such a History of
Ownership and Division shall be signed by a licensed attorney or be signed and
stamped by a registered Land Surveyor.
EXHIBIT 5:
AGENT'S LETTER OF AUTHORIZATION
All subdivision applications shall be accompanied by a letter signed by the owner of
the parcel proposed to be subdivided authorizing someone other than him/herself to
act as his/her agent, if an agent is representing the owner.
EXHIBIT 6:
WATER SUPPLY - INDIVIDUAL WELLS
If Individual Wells are proposed, all subdivision applications shall be accompanied by
a letter including calculations of subdivision's foreseeable water needs, certifying that
sufficient, healthful water for the reasonably foreseeable needs of the subdivision is
available, prepared by a licensed well-driller knowledgeable of the area, or other
qualified professional.
EXHIBIT 7:
WATER SUPPLY - COMMON SYSTEM
If a Common Water Supply System is proposed, all subdivision applications shall be
accompanied by a report prepared by a registered professional engineer or geologist,
including the following;
a. Calculations of project's foreseeable water needs;
b. Certification that sufficient, healthful water for the reasonably foreseeable needs
of the subdivision is available:
c. Certification that the design of common well(s) is in conformance with Maine
Drinking Water Regulations, Title 22 MRSA, Section 2601; and
d. A detailed description of the proposed method for providing appropriate long-
term operation and maintenance of system and name of person or entity proposed to
be responsible for operation and maintenance of system.
26
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
EXHIBIT 8:
HIGH INTENSITY SOIL SURVEY
All subdivision applications shall be accompanied by a medium Intensity Soil Survey
Map and a written report describing the soils present on the site, prepared by a
Maine Certified Soil Scientist. The Board may require High Intensity Soil Survey
mapping for areas of intensive development such as roads and structures.
EXHIBIT 9:
SWCD EROSION CONTROL SPECIFICATIONS AND PLAN
If a Minor Subdivision, the application shall be accompanied by written Erosion and
Sedimentation Control Specifications and an Erosion and Sedimentation Control
Plan, prepared in consultation with the Hancock County Soil and Water Conservation
District, or any qualified professional.
EXHIBIT 10:
EROSION AND SEDIMENTATION CONTROL PLAN AND SPECIFICATIONS
If a Major Subdivision, the application shall be accompanied by written Erosion and
Sedimentation Control Specifications, prepared and stamped by a qualified
professional, which describes measures to be followed to control erosion and
sedimentation during and after the construction of the proposed subdivision
including:
a. TEMPORARY EROSION AND SEDIMENTATION CONTROL:
1.) A site map showing:
a.) Existing and proposed two foot contours in contrasting lines;
b.) The limits of areas disturbed by construction;
c.) The location of roads, lots, buffer strips, topsoil stockpiles, all existing
and proposed culverts, ditches, diversions, waterways and subsurface
drainage systems; and
d.) The location of all temporary erosion controls including hay bale barriers,
stone check dams, silt fencing, and sedimentation basins.
2.) Calculations, including;
a.) Stone check dam spacing calculations; and
b.) Sedimentation basin sizing calculations based on SCS TR-55 or TR-20
storm water runoff calculations using a 10 year, 24 hour storm event with a
minimum 10 hour detention time.
b. PERMANENT EROSION CONTROL
1.) A site map showing:
a.) Existing and proposed two foot contours in contrasting lines;
b.) The location of roads, lots, culvert, ditches, waterways, diversion, buffer
strips, detention basins, subsurface drainage systems, inlet and outlet
protection aprons, ditch rip-rapping, and plunge pool; and
c.) Drainage area and flow lines used for sizing calculations of culverts,
waterways, diversions, and ditches.
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
27
2.) Calculations, including:
a.) Man-made culvert and ditch capacity calculations based on a 10 year,
24 hour storm. Address overflow during a 25 year, 24 hour storm where
the system feeds a detention basin;
b.) Culvert capacity calculations for natural drainage features are to
be based on a 25 year, 24 hour storm;
c.) A schematic diagram should accompany each culvert capacity
calculation. Each schematic should show road crown, inlet invert, and
headwater elevation all relative to the outlet invert, including culvert type,
length, and diameter;
d.) Diversion, waterways, outlet protection aprons, plunge pools, and
rip-rap sizing calculations based on recommendation by the
Maine Erosion and Sedimentation Control Handbook for Construction,
Best Management Practices, March 1991; and
e.) Subsurface drainage systems capacity calculations.
c. DETAIL SHEETS:
1. Plans suitable for bidding and construction, including the following details:
a.) Grassed and rip-rap ditches, waterways, and diversions;
b.) Hay bale barriers, silt fences, and stone check dams;
c.) Culverts, plunge pools, inlet and outlet protection;
d.) Catch basin and pipe installation;
e.) Sedimentation basin; and
f.) Erosion control notes including:
i)
Disturbed area seed, mulch, lime, and fertilizer types, rates and
application methods. Such areas shall be permanently stabilized
within 15 days of final grading, or temporarily stabilized within 30
days of initial disturbance of soil. Such areas shall be stabilized
within 7 days when located on stream, river or lake watersheds;
ii) Schedule outline: erosion control and construction sequence of
ponds, roads and ditches, seeding dates, and frequency of erosion
and sedimentation control inspections and maintenance;
iii) Plans to minimize acreage of disturbed land open at any time;
iv) The name, address, and telephone number of the person(s)
responsible for inspecting the erosion control measures; and
v) Provision to remove temporary erosion control measures.
28
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
EXHIBIT 11:
TRAFFIC IMPACT ANALYSIS
If a Major Subdivision, the application shall be accompanied by a Traffic Impact
Analysis, prepared by a registered Professional Engineer experienced in Traffic
Analysis, which includes the following:
a. Estimate of number and types of daily vehicle trips generated by the proposed
subdivision;
b. Travel routes to be utilized by the proposed subdivision from the site to the main
thoroughfare;
c. Duration of traffic movement, generated by the proposed subdivision from the
site to the main thoroughfare, both during and after project construction from the
site to the main thoroughfare;
d. Off-site distribution of traffic generated by the proposed subdivision;
e. Discussion of turning movement at nearby intersections; and
f.
Accident Records on nearby intersections and public roads.
EXHIBIT 12:
HIGHWAY ENTRANCE PERMITS
If the subdivision proposes a new entrance(s) onto any State Highway, the
application shall be accompanied by a copy of the Entrance Permit(s) issued by the
Maine Department of Transportation.
EXHIBIT 13:
INTERIOR ROAD DESIGN
All subdivisions will have interior roads, and the application shall be accompanied by
the following documents related to the design of such roads:
a. A typical road cross-section;
b. If road has a grade greater than five percent (5%) at any point and/or if there are
significant cut and fill areas, a Road Profile prepared by a registered Professional
Engineer;
c. When road profiles are required, road cross sections at fifty foot (50') intervals
along the profile and at fifty feet (50') in front of and fifty feet (50) past the profile
section.
d. Plan view of each road intersection created by the project which shows the
following:
1)
Names of the intersecting roads;
2)
Speed limits on each of the intersecting roads; and
3)
Left and Right sight distances.
EXHIBIT 14:
INTERIOR ROAD MAINTENANCE
If the subdivision proposes interior roads, the application shall be accompanied by
the following documents related to the maintenance of such roads:
29
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
a. If roads are to remain private, a Statement describing provisions to assure their
proper long term maintenance and repair; or
b. If roads are to be dedicated to Town, a Statement describing provisions made to
assure their proper maintenance until Town accepts responsibility.
EXHIBIT 15:
SEWAGE DISPOSAL - INDIVIDUAL SUBSURFACE DISPOSAL SYSTEMS
If individual subsurface disposal systems are proposed, the application shall be
accompanied by a report prepared by a licensed Site Evaluator including:
a. A Map showing the location of test pits for each lot;
b. Complete soil profile logs for each test pit; and
c. Form HHE 200's for each proposed subsurface disposal system.
EXHIBIT 16:
SEWAGE DISPOSAL - COMMON SUBSURFACE DISPOSAL SYSTEMS
If a common and/or engineered system is proposed, the application shall be
accompanied by a report prepared by a registered Professional Engineer including:
a. System design drawings and specifications; and
b. A letter of review and approval from the Division of Health Engineering, Maine
Department of Human Services.
EXHIBIT 17:
SOLID WASTE GENERATION AND DISPOSAL STATEMENT
If a Minor Subdivision, the application shall be accompanied by a Solid Waste
Generation and Disposal Statement indicating the amount of solid waste and sewage
sludge likely to be generated by the proposed subdivision and the steps proposed to
appropriately dispose of the solid waste and sewage sludge likely to be generated.
EXHIBIT 18:
SOLID WASTE GENERATION REPORT
If a Major Subdivision, the application shall be accompanied by a Report, prepared
by a qualified professional, calculating the amount of solid waste and sewage sludge
likely to be generated by the proposed subdivision.
EXHIBIT 19:
SOLID WASTE DISPOSAL FACILITY STATUS AND CONTRACT
If a Commercial Landfill is proposed to be used to dispose of the subdivision's solid
waste, the application shall be accompanied by a letter from the Bureau of Land
Quality Control of the Maine Department of Environmental Protection confirming the
legal status of the commercial landfill and a copy of the contract which covers the
hauling and disposal of the subdivision's solid waste for the next five (5) years.
EXHIBIT 20:
SLUDGE DISPOSAL FACILITY STATUS AND CONTRACT
If a private/commercial sludge disposal area is proposed to be used to dispose of the
subdivision's sludge waste, the application shall be accompanied by a letter from the
Bureau of Land Quality Control of the Maine Department of Environmental Protection
confirming the legal status of the private/commercial sludge disposal area and a copy
of the contract which covers the hauling and disposal of the sludge waste for the next
five (5) years.
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
30
EXHIBIT 21:
AESTHETIC, CULTURAL AND NATURAL VALUES IMPACT STATEMENT
If a Minor Subdivision, the application shall be accompanied by a written Statement
detailing the presence of any significant historic or archaeologic resources, significant
fish and wildlife habitats, significant registered natural/critical areas, or identified
scenic resources on or adjacent to the proposed subdivision and steps that have
been taken or will be taken to minimize any adverse impact from the proposed
subdivision on such significant resources.
EXHIBIT 22:
VISUAL RESOURCES IMPACT ASSESSMENT
If a Major Subdivision, the application shall be accompanied by a Visual Resources
Impact Assessment, prepared by a qualified professional, describing the steps that
have been taken and will be taken to reduce the visual impact of the proposed
subdivision on surrounding properties and efforts made or to be made to preserve
existing elements of the site which contribute to maintenance of scenic character.
EXHIBIT 23:
HISTORIC RESOURCES IMPACT ASSESSMENT
If a Major Subdivision, the application shall be accompanied by a Letter from the
Maine Historic Preservation Commission commenting on any historic sites,
structures, or archaeologic sites located on or near the proposed subdivision and, if
any, an Historic Resources Impact Assessment, prepared by a qualified professional,
describing the steps that have been taken or will be taken to minimize the
subdivision's potential impact on any identified structures or sites.
EXHIBIT 24:
UNIQUE NATURAL RESOURCES IMPACT ASSESSMENT
If a Major Subdivision, the application shall be accompanied by a Letter from the
Maine Critical Areas Program commenting on any "rare and irreplaceable natural
areas" located on or near the project site and, if any, a Unique Natural Resources
Impact Assessment, prepared by a qualified professional, describing the steps that
have been taken or will be taken to minimize the subdivisions potential impact on any
identified natural areas.
EXHIBIT 25:
FISHERIES AND WILDLIFE HABITAT IMPACT ASSESSMENT
If a Major Subdivision, the application shall be accompanied by a Letter from the
Maine Department of Inland Fisheries and Wildlife commenting on any significant
fisheries and/or wildlife habitat located on or near the project site and, if any, a
Fisheries and Wildlife Habitat Impact Assessment, prepared by a qualified
professional, describing provisions made to minimize the subdivision's potential
adverse impact on any of the identified significant fisheries and wildlife habitat.
EXHIBIT 26:
COMPLIANCE STATEMENT
If a Minor Subdivision, the application shall be accompanied by a written statement
prepared by the applicant or his/her agent describing the steps taken or to be taken
to comply with all applicable design, dimensional, and procedural provisions of this
Ordinance and to comply with each of the other criteria of approval contained in
Section IV of this Ordinance.
EXHIBIT 27:
COMPLIANCE MEMO - LOCAL ORDINANCES AND PLANS
If a Major Subdivision, the application shall be accompanied by a Regulatory
Compliance Memorandum, prepared by a qualified professional, outlining the
project's conformance with the Town's adopted Comprehensive Plan, this
Subdivision Ordinance, and other applicable locally adopted Ordinances and
regulations.
31
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
EXHIBIT 28:
COMPLIANCE MEMO - STATE AND FEDERAL LAWS AND REGULATIONS
If a Major Subdivision, the application shall be accompanied by a Regulatory
Compliance Memorandum, prepared by a qualified professional, outlining the
project's conformance with all applicable State and Federal laws and regulations,
including copies of the completed applications for all required State and Federal
permits and approvals.
EXHIBIT 29:
FINANCIAL CAPACITY REPORT
All subdivision applications shall be accompanied by a Financial Capacity Report
which shall include the following:
a. An itemized list of all of the proposed subdivision's estimated planning, design,
development, and construction costs; and
b. If the applicant is a corporation, a copy of the most recent corporate annual
report showing sufficient financial capacity to cover the costs associated with
completing the proposed subdivision as required and explanatory material
interpreting the report; or
c. If the proposed subdivision is to be personally financed, a bank letter or other
documentary evidence demonstrating the availability of sufficient funds to
appropriately cover the costs associated with completing the subdivision as
required; and
d. If the proposed subdivision is to be personally financed, a Project Financing Plan
including the following:
1) A cash equity commitment of twenty percent (20%) of the estimated costs;
plus
2) A financial schedule for the remaining financing; and
3) A letter of commitment for the remaining funding required stating any and all
conditions of commitment.
EXHIBIT 30:
TECHNICAL ABILITY
All subdivision applications shall be accompanied by the resume of the applicant
describing his/her technical ability to undertake the proposed subdivision including
any prior experience and appropriate training, and the resumes of all professionals
involved in the planning, design, development, and construction of the proposed
subdivision, describing their technical and professional training, expertise, experience
and special ability to undertake their respective roles in the proposed subdivision.
EXHIBIT 31:
SURFACE WATER MANAGEMENT STATEMENT
All subdivision applications shall be accompanied by a Surface Water Management
Statement which includes the following:
a. The name, if known, and location of any flowing water including brooks and
streams on or abutting the property;
b. If the project is within the watershed of a lake or pond, the name of that lake
and/or pond;
c. Description of the general topography of the parcel proposed to be subdivided;
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
32
d. Description of how the proposed subdivision will or will not cause any alteration
of natural drainage ways including intermittent streams, perennial streams, and
vegetated swales;
e. Identification of any portion of the site subject to ponding or flooding; and
f.
Description of how changes in surface water drainage will affect other properties
and how these effects will be controlled.
EXHIBIT 32:
SURFACE WATER MANAGEMENT PLAN
If a Major Subdivision, the application shall be accompanied by a Surface Water
Management Plan prepared by a qualified professional showing the following:
a. All existing water bodies, water courses, drainage ways, channels, intermittent
and perennial streams within the project site;
b. The nature, width, and location of proposed easements, rights-of-way, culverts,
catch basins or other means of channeling surface/storm water within the
proposed subdivision and over adjacent properties;
c. All proposed vegetative filter/buffer strips;
d. Pre-development and post-development drainage watersheds with their
associated hydraulic length lines; and
e. Identification of any portion of the site subject to ponding or flooding.
EXHIBIT 33:
GROUND WATER RESOURCES IMPACT STATEMENT
If a Minor Subdivision, the application shall be accompanied by a written Statement
prepared by the applicant describing the measures taken and to be taken to prevent
degradation of existing ground water quality on and adjacent to the proposed
subdivision.
EXHIBIT 34:
NITRATE ASSESSMENT
If a Major Subdivision, the application shall be accompanied by a Hydro-geologic
Assessment, prepared by a registered geologist, describing the following:
a. The presence of sand and gravel aquifers located on or near the project site;
b. The depth to, direction, and rate of flow of groundwater;
c. An assessment of the potential of the project for adverse effects to on-site wells,
off-site wells, and the quality of adjacent surface waters;
d. Recommendations for minimizing or eliminating adverse effects from nitrates and
nitrites on drinking water supplies and on on-site or adjacent flowing and surface
waters; and
e. Proposals for implementation of recommendations.
EXHIBIT 35:
WATER QUALITY BACKGROUND ASSESSMENT
If a Major Subdivision and deemed warranted by the Planning Board, the application
shall be accompanied by a Water Quality Background Assessment, prepared by a
registered geologist, describing the existing Phosphorous (P),
Phosphorous/Potassium/Nitrogen ratio (PKN), Nitrate Ammonia (NH3-N), Nitrates
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
33
(NO3-N), Nitrites (NO2-N), Sodium (Na), and Chlorine (Cl) levels in on-site and
adjacent groundwater and/or surface waters.
EXHIBIT 36:
RECOMMENDATIONS FOR MINIMIZING OR ELIMINATING WATER QUALITY
IMPACTS
If a Major Subdivision and a Water Quality Background Assessment has been
requested, the application shall be accompanied by written Recommendations for
Minimizing or Eliminating Water Quality Impacts, prepared by a registered geologist,
describing the steps taken and to be taken to minimize or eliminate the adverse
effects from existing Phosphorus (P), Phosphorus/Potassium/Nitrogen ratio (PKN),
Nitrate Ammonia (NH3-N), Nitrates (NO3-N), Nitrites (NO2-N), Sodium (Na), and
Chlorine (Cl) levels in on-site drinking water supplies and on on-site and adjacent
groundwater and/or surface waters, including a detailed Implementation Strategy for
the implementation of actions recommended.
EXHIBIT 37:
FLOOD HAZARD PROTECTION STATEMENT
If any part of the proposed subdivision is located within a one hundred (100) year
flood-prone area as shown on Federal Emergency Management Agency's Flood
Boundary and Floodway Maps, the application shall be accompanied by a written
Statement describing the steps taken or to be taken in the planning design and
development of the proposed subdivision to prevent flood damage on-site and to
prevent increased flood damage on downstream properties.
EXHIBIT 38:
FRESHWATER WETLAND PROTECTION STATEMENT
If the parcel proposed to be subdivided contains within it or abutting it, in whole or in
part, any freshwater wetlands, as defined in Title 38, MRSA, Section 480-B,
subsection 4, regardless of size, the application shall be accompanied by a
Freshwater Wetlands Protection Statement describing the steps taken or to be taken
in the planning, design, and development of the proposed subdivision to prevent
adverse impact to freshwater wetland values.
EXHIBIT 39:
FRESHWATER WETLANDS MAP
If the parcel proposed to be subdivided contains within it or abutting it, in whole or in
part, any freshwater wetlands, as defined in Title 38, MRSA, Section 480-B,
subsection 4, regardless of size, the application shall be accompanied by a
Freshwater Wetlands Map prepared by a State Certified Soil Scientist or Geologist,
registered in the State of Maine, based on an on-site investigation, of the parcel
showing the location and boundaries of any such freshwater wetlands.
EXHIBIT 40:
FLOWING WATERS PROTECTION STATEMENT
If the parcel proposed to be subdivided contains within it or abutting it, in whole or in
part, any river, stream or brook as defined in Title 38, MRSA, Section 480-B,
subsection 9, the application shall be accompanied by a Flowing Waters Protection
Statement describing the steps taken or to be taken in the planning, design, and
development of the proposed subdivision to prevent adverse impact on any such
rivers, streams, or brooks.
EXHIBIT 41:
FLOWING WATERS MAP
If the parcel proposed to be subdivided contains within it or abutting it, in whole or in
part, any river, stream, or brook, as defined in Title 38, MRSA, Section 480-B,
subsection 9, the application shall be accompanied by a Flowing Waters Map
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
34
showing the location, configuration, and direction of flow of any such rivers, streams,
or brooks.
EXHIBIT 42:
STORM WATER MANAGEMENT PLAN
If a Major Subdivision, the application shall be accompanied by a Storm Water
Management Plan, prepared by a qualified professional, which includes the following:
a. FOR OFF-SITE WATERSHEDS
1) A narrative describing:
a) How the proposed site is oriented within the watershed;
b) How runoff from the site will affect the watershed hydrography and nearby
properties;
c) Whether or not it is possible to reduce the watershed peak flow by
detaining stormwater runoff on-site; and
d) Areas and structures that historically flood or may be affected by
increased flows.
2) The following maps showing the actual project boundaries and watershed
boundaries, sub-area, and flow lines, on each:
a) USGS 7.5 minute series quadrangle map; and
b) USDA SCS Medium Intensity Soil Survey Map.
b. FOR ON-SITE WATERSHEDS
1) Stormwater runoff calculations, modeling pre-development and post-
development conditions, using either SCS's TR-55 or TR-20 methodologies,
including;
a) A narrative describing how the calculations were performed;
b) Runoff curve assumptions, consistent with clearing limits legally
guaranteed through conservation easements or deed restrictions, etc.;
c) Runoff calculations performed for 2, 10, and 25 year, 24 hour storm events;
and
d) Runoff Curve Number, Time of Concentration, and Travel Time
calculations for each sub-area.
2) Separate pre-development and post-development maps, each with the
following details:
a) Existing and proposed two (2) foot contour lines, clearly contrasting;
b) Site soils, surveyed at an appropriate level of detail;
c) Project and drainage area boundary lines;
d) Sub-area boundaries;
SECTION XII: SUBDIVISION APPLICATION AND ATTACHMENTS (continued)
35
e) Stormwater time of concentration and time of travel routing lines divided
into flow type segments;
f)
All ponded and wetland areas, existing and proposed;
g) All man-made and natural drainage ways;
h) All existing and proposed culverts; and
i)
Locations of all piping systems.
3) If calculations indicate that stormwater detention is necessary, the following
information is also required:
a) Detention basin sizing calculations, including stage-storage curves, and
outlet velocities;
b) Detail and sizing calculations for the outlet and emergency spillway;
c) Embankment material specifications with compaction requirements if any
type of dike is to be constructed;
d) Location of detention and outlet structure shown on the site plan;
e) A detail sheet showing plan and cross sectional views of the detention
basin, outlet structure, emergency overflow structure, and associated rip-
rapped areas; and
f)
A Narrative describing the operation and maintenance of the detention
basin(s) and other assorted structures, during construction and when
project is complete. This Narrative should include provisions for
excavating accumulated sediments or debris and identify who will have
legal responsibility for maintenance.
36
SECTION XIII: PREPARATION AND SUBMISSION REQUIREMENTS FOR PRELIMINARY AND
FINAL SUBDIVISION PLANS
SECTION USER'S GUIDE: This section contains specifications related to the preparation and
submission of Preliminary and Final Subdivision Plans.
A. PREPARATION AND SUBMISSION REQUIREMENTS: PRELIMINARY SUBDIVISION PLANS
Preliminary Subdivision Plans shall be prepared and submitted to the Planning Board, through the Code
Enforcement Officer, as follows:
1. NUMBER OF COPIES TO BE SUBMITTED
Preliminary Subdivision Plans shall be submitted in ten (10) sets of one or more maps or
drawings, printed or reproduced on paper. Ten (10) copies of the Plan(s) reduced to a size of 8
1/2 x 11 inches shall be submitted in addition, ten (10) copies of the application and required
exhibits shall be submitted with the Preliminary Plans.
2. SHEET SIZE
Preliminary Subdivision Plans shall be 24 by 36 inches in size, and shall have a margin of two (2)
inches outside of the borderline on the left side for binding and a one (1) inch margin outside the
border along the remaining sides.
3. PLAN SCALE
Preliminary Subdivision Plans shall be drawn to a scale of within a range of twenty (20) feet to
one hundred feet (100) to the inch.
B. INFORMATION TO BE SHOWN ON PRELIMINARY SUBDIVISION PLANS
The following information shall be shown on Preliminary Subdivision Plans:
1. GENERAL INFORMATION
The proposed name of the subdivision, name of the Town, the date the Plan was prepared, true
north arrow, graphic map scale, names and addresses of the record owner, applicant, and
professional or professional firm who prepared the plan.
2. BOUNDARY SURVEY
A boundary survey of the tract made and certified by a Maine licensed land surveyor prepared in
accordance to the Rules set forth by the Maine Board of Licensure for Professional Land
Surveyors. Said boundary survey shall include, but not limited to, the following:
a. Boundary lines of the tract with bearings no less than to the nearest 30 seconds, distances
no less than to the nearest 0.01-foot, curve data and any additional information to reproduce
the survey mathematically;
b. Type of monument set or found at each parcel corner;
c. Rights of way and easements of record within or immediately surrounding the tract.
3. CONTOUR LINES
Contour lines at the interval specified by the Board, showing elevations in relation to Mean Sea
Level (NGVD).
37
SECTION XIII: PREPARATION AND SUBMISSION REQUIREMENTS FOR PRELIMINARY AND
FINAL SUBDIVISION PLANS (continued)
4. PROPOSED LOT LINES AND LOT NUMBERS
Proposed lot lines with appropriate dimensions in decimals of a foot and lot areas in square feet
for lots smaller than 43,560 square feet in area and in acres to the nearest one hundredth of an
acre for lots greater than 43,560 square feet. All proposed lots shall be numbered.
5. EXISTING MAN-MADE FEATURES
The location, names, and widths of existing roads, highways, easements, building lines, parks
and other open spaces on or adjacent to the proposed subdivision and the location and size of
existing sewers, utility poles, water mains, culverts, other underground utilities and drainage ways
on or adjacent to the proposed subdivision.
6. EXISTING NATURAL FEATURES
The location and configuration of existing water bodies, watercourses and wetlands on or
immediately adjacent to the parcel prepared by a State Certified Soil Scientist or Geologist,
registered in the State of Maine, based on an on-site investigation existing water bodies,
watercourses and the cover types (open field, open shrub, wooded, etc.), and other significant
physical features, including the location of any trees larger than twenty-four (24) inch diameter at
breast height in areas of proposed construction or where clearing of trees will be likely to occur.
7. NAMES OF ADJACENT PROPERTY OWNERS
The names of the owners of record of all abutting properties, including those of any properties
directly across and along any existing public road abutting the proposed subdivision.
8. PROPOSED IMPROVEMENTS
The location, names, and widths of any proposed roads, rights-of-way, easements, building lines,
common open spaces associated with the proposed subdivision and the location and size of any
proposed sewer lines, sewage disposal areas, water mains, wells, culverts and drainage ways
associated with the proposed subdivision.
9. PUBLIC IMPROVEMENTS
The location and width of any existing and proposed roads or other public improvements, within
the proposed subdivision, shown on the Official Map and/or the Comprehensive Plan, if any.
10. COMMON AND/OR PUBLIC AREAS AND FACILITIES
Identification of all parcels and facilities proposed to be dedicated for common use and/or public
ownership and/or use, and the conditions of such dedication and a description of their proposed
improvement and management.
11. FLOOD HAZARD AREA BOUNDARIES
If any portion of the subdivision is in a flood-prone area, the boundaries of such areas and the
100-year flood elevation.
12. EXISTING ZONING
The names and boundaries of any existing local zoning designations applicable to the property
proposed to be subdivided.
38
SECTION XIII: PREPARATION AND SUBMISSION REQUIREMENTS FOR PRELIMINARY AND
FINAL SUBDIVISION PLANS (continued)
13. SURVEYOR/PLANNER'S CERTIFICATION AND SEAL
The name, signature, registration number, and seal of the land surveyor who prepared the survey
and the architect, engineer, or planning consultant who designed the plan.
C. PREPARATION AND SUBMISSION REQUIREMENTS: FINAL SUBDIVISION PLANS
Final Minor and Final Major Subdivision Plans shall be prepared and submitted to the Planning
Board, through the Code Enforcement Officer, in the same manner as required for Preliminary
Subdivision Plans by subsection A, above.
D. INFORMATION TO BE SHOWN ON FINAL SUBDIVISION PLANS
The same information required to be shown on Preliminary Subdivisions Plans, by subsection B,
above, shall be shown on all Final Minor and Final Major Subdivision Plans.
In addition, the following shall be shown on all Final Minor and Final Major Subdivision Plans:
1. FINAL PLAN APPROVAL BLOCK
An Approval Block to record the approval of the Final Plan shall be permanently affixed to Final
Minor and Final Major Subdivision Plans and shall read as follows:
APPROVAL BLOCK
This Subdivision Plan has been approved with conditions by the Dedham Planning
Board in accordance with Title 30-A, MRSA, Section 4401, et seq..
Approved lots may be sold or leased only in accordance with all applicable terms and
conditions included in and/or attached to the written Order issued by the Planning
Board on / / , and recorded in the Hancock County Registry of Deeds in Book
________ on page ________.
Signed
________________________________
____________________________________
____________________________________
____________________________________
____________________________________
____________________________________
____________________________________
Date
____________________________________
39
SECTION XIV: APPLICATION FEES AND TECHNICAL REVIEW ACCOUNT
SECTION USER'S GUIDE: This section contains provisions regarding the various fees required to be
submitted with subdivision applications and escrow accounts to be established for assisting with the costs
of reviewing the proposed subdivision.
A. APPLICATION PACKET FEE
The Application Packet Fee required to cover printing costs for copies of the Application Form and
copies of this Ordinance are as follows:
1. COPIES OF SUBDIVISION APPLICATIONS
The non-refundable fee for copies of the Subdivision Application Form is set in the policy adopted
by the Selectmen.
2. COPIES OF ORDINANCE
The non-refundable fee for copies of this Ordinance is set in the policy adopted by the Selectmen.
B. APPLICATION PROCESSING FEES
The Application Processing Fees required to cover the administrative handling costs associated with
subdivision review under this Ordinance are as follows:
1. MINOR SUBDIVISIONS
The non-refundable fee must accompany the application of Minor Subdivision Final Plans. The
amount of the fee is set by policy adopted by the Selectmen.
2. MAJOR SUBDIVISIONS
The non-refundable fee must accompany the application of Major Subdivision Preliminary Plans.
This per residential unit fee is established by policy adopted by the Selectmen.
3. PUBLIC HEARING FEE
The fees required to cover the costs associated with the publication in a paper of general
circulation and mailing to all property owners within 300 feet of the proposed subdivision
of the required notices for public hearings are listed in the policy established and adopted by the
Selectmen. These fees are payable.
C. TECHNICAL REVIEW ACCOUNT
In addition to the fees for copies of the Application and Ordinance and the Application Processing
Fee, the applicant shall pay a separate fee per lot or dwelling unit to be deposited in a special
account designated for the particular subdivision application, to be used by the Planning Board for
hiring independent, consulting, and legal services to review the application. The amount of this fee is
established through the fee policy adopted by the Selectmen.
This Technical Review Fee shall be paid prior to the start of the Planning Board's review of the Final
Plan of a Minor Subdivision or the Preliminary Plan of a Major Subdivision.
This fee shall be paid in the form of a check made payable to the Town of Dedham and the purpose
of the fee shall be clearly indicated on the check. The town shall deposit this fee in a special bank
account which is separate and distinct from all other Planning Board and Town accounts.
If the balance in this account is drawn down by 50% or more, the Board shall notify the applicant, and
require that an additional fee per lot or dwelling unit be deposited by the applicant. The Board shall
continue to notify the applicant and require an additional fee per lot or dwelling unit be deposited as
necessary whenever the balance of the account is drawn down by 50% of the original deposit. The
40
SECTION XIV: APPLICATION FEES AND TECHNICAL REVIEW ACCOUNT (continued)
per lot or dwelling unit additional fee will be equal to the original technical review fee established by policy
adopted by the Selectmen.
Any balance in the account remaining, after the completion and inspection of required improvements,
shall be returned to the applicant.
41
SECTION XV: REVISIONS TO EXISTING PLANS AND TRANSFER OF APPROVAL
SECTION USER'S GUIDE: This section contains provisions related to revisions of previously approved
Subdivision Plans.
A. REVISIONS TO EXISTING PLAN
Any application for subdivision approval which constitutes a revision or amendment to a Final
Subdivision Plan, which has been previously approved, shall indicate that fact on the application and
shall identify the original subdivision being revised or amended and reference the Book and Page in
the Registry of Deeds where the plan is recorded.
Applications for revisions to existing plans shall comply with all of the fees, procedural requirements,
and submissions required of this Ordinance for their classification.
The Planning Board shall make findings of fact and conclusions of law that the proposed revisions do
or do not meet the criteria of approval provided in Section IV.
B. TRANSFER OF APPROVAL
If the transfer in ownership of any approved subdivision involving public improvements or private road
construction is anticipated prior to the successful completion of such improvements, the owner shall
notify the Planning Board. The new owner shall be required to submit a subdivision plan amendment
to the Planning Board for its review and actions.
42
SECTION XVI: GENERAL PERFORMANCE STANDARDS
SECTION USER'S GUIDE: This section contains general performance standards with which all
subdivision proposals submitted for approval pursuant to this Ordinance must comply.
In reviewing applications submitted pursuant to this Ordinance, the Board shall consider the following
performance standards and make written findings that each has been met prior to issuing final approval.
A. CONFORMANCE WITH COMPREHENSIVE PLAN
All proposed subdivisions shall be in conformance with the Comprehensive Plan and Policy
Statements of the Town and with the provisions of all pertinent local ordinances and regulations,
State and Federal laws and regulations.
B. RELATIONSHIP TO MUNICIPAL SERVICES
The proposed development shall not have an unreasonable adverse impact on the municipal services
including municipal road systems, fire department, police department, sewer and water systems, solid
waste program, schools, open spaces, recreational programs and facilities, and other municipal
services and facilities.
C. PRESERVATION AND ENHANCEMENT OF THE LANDSCAPE
The landscape shall be preserved in its natural state insofar as reasonably practicable by minimizing
tree removal, disturbance of soil, and retaining existing vegetation during construction. After
construction is completed, landscaping shall be planted that will define, soften or screen the
appearance of off-street parking areas, buildings and other structures from the public right-of-way and
abutting properties in order to enhance the physical design of the proposed development, and to
minimize the encroachment of the proposed uses on neighboring land uses.
D. RELATIONSHIP TO SCENIC CHARACTER OF THE NEIGHBORHOOD
Proposed buildings, structures and roads shall be related harmoniously to the terrain and to existing
buildings and structures in the vicinity that have a visual relationship to the proposed subdivision, so
they will not have an unreasonable adverse effect on the scenic character of the surrounding area, or
on scenic resources identified in the 1994 Comprehensive Plan (amended October 5, 1995).
E. RETENTION OF OPEN SPACES AND NATURAL OR HISTORIC FEATURES
1. In any subdivision larger than twenty (20) acres, or more than ten (10) lots or dwelling units, the
applicant shall provide at least ten (10) percent of his total area as usable open space. In any
subdivision twenty (20) acres or less, or containing ten (10) lots or dwelling units or less, the
Board may require the developer to provide at least ten (10) percent of his total area as usable
open space. It is desirable that areas reserved for recreation be at least two (2) acres in size and
easily accessible from all lots within the subdivision.
2. Land reserved for open space purposes shall be of a character, configuration, and location
suitable for the particular use intended. For example a site intended to be used for active
recreation purposes, such as a playground or a play field, should be relatively level and dry, have
a total frontage on one or more roads of at least two hundred (200) feet, and have no major
dimensions of less than two hundred (200) feet. Sites selected primarily for scenic or passive
recreation purposes shall have such access as the Board may deem suitable and no less than
twenty-five (25) feet of road frontage. The configuration of such sites shall be deemed adequate
by the Board with regard to scenic attributes to be preserved, together with sufficient areas for
trails, lookouts, etc. where necessary and appropriate.
3. Where the proposed subdivision is located on a lake, pond, river or stream, a portion of the
waterfront area, shall be included in the reserved land. The land so reserved shall be at least 200
feet wide measured perpendicularly from the normal high water mark.
43
SECTION XVI: GENERAL PERFORMANCE STANDARDS (continued)
4. If the Planning Board determines that the reservation of land for parks and/or recreational
purposes would be inappropriate or that the land is not suitable or is insufficient in amount, the
Board may waive the requirement of land reservation on the condition that the Applicant deposit a
cash payment in lieu of land reservation with the Town Clerk. Such a payment shall be placed in
a trust fund to be used exclusively for the purchase and development of neighborhood sites for
parks, playgrounds and other recreational purposes. The amount of such payment shall be not
more than 10% of the appraised market value, including improvements, for each lot approved on
the final plan.
5. The Board may require that the development plans include a landscape plan that will show the
preservation whenever practicable of any existing trees larger than twenty-four (24) inches
diameter 4 feet from the ground, the replacement of trees and vegetation, graded contours,
streams and the preservation of scenic, historic or environmentally significant areas. Cutting of
trees on the northerly borders of lots should be avoided as far as possible, to retain a natural wind
buffer.
F. LAND NOT SUITABLE FOR DEVELOPMENT
The following lands shall not be included in the calculations of lot area for the purpose of meeting the
requirements of the minimum lot size for the zone in which the development is located:
1. Land which is situated below the normal high water mark of any water body;
2. Land which is located within the one hundred (100) year frequency flood plain as identified by the
Federal Emergency Management Agency or the Department of Housing and Urban
Development, Flood Insurance Administration, unless the applicant shows proof through the
submittal of materials prepared by a Registered Land Surveyor which show that the property in
question lies at least one (1) foot above the one hundred (100) year flood level. The elevation of
filled or made land shall not be considered;
3. Land which is part of a right-of-way, or easement, including utility easements;
4. Land that has been created by filling or draining a pond or wetland;
5. Land that is located within a Resource Protection Zoning Classification;
6. Land consisting of Recent Flood Plain Soil;
7. Any area with sustained slopes of 20% or greater; and
8. Land defined herein as a freshwater wetland.
G. TOPSOIL AND VEGETATION REMOVAL
1. Topsoil shall be considered part of the development and shall not be removed from the site
except for surplus topsoil from roads, parking areas, and building excavations.
2. Except for normal thinning, clearing for approved construction, landscaping, and cutting of trees
to provide access to direct sunlight, existing vegetation shall be left intact to prevent soil erosion.
The Board shall require an applicant to take measures to correct and prevent soil erosion in the
proposed development.
3. To prevent soil erosion of shoreline areas, tree cutting in a strip paralleling the shoreline of a
water body, and extending one hundred (100) feet inland from all points along the normal high
water mark shall be limited in accordance with the clearing of vegetation provisions of the State of
Maine Guidelines for Municipal Shoreland Zoning Ordinances in effect at the time.
SECTION XVI: GENERAL PERFORMANCE STANDARDS (continued)
44
H. EROSION AND SEDIMENTATION CONTROL
The following measures relating to conservation, erosion and sediment control shall be included
where applicable as part of all projects submitted for review and approval under this Ordinance.
1. The procedures outlined in the erosion and sedimentation control plan, prepared and submitted
by the applicant, shall be implemented during the site preparation, construction, and clean-up
stages.
2. Erosion of soil and sedimentation of watercourses and water bodies shall be minimized by
employing the following best-management practices:
a. Stripping of vegetation, soil removal and re-grading or other development shall be done in
such a way as to minimize erosion;
b. Development shall keep cut-fill operations to a minimum and ensure conformity with
topography so as to create the least erosion potential and adequately handle the volume and
velocity of surface water runoff;
c. The development shall not unreasonably increase the rate or volume of surface water runoff
from the proposed site;
d. Whenever feasible, natural vegetation shall be retained, protected and supplemented;
e. The disturbed area and the duration of exposure shall be kept to a practical minimum;
f.
Disturbed soils shall be stabilized as quickly as practicable;
g. Temporary vegetation or mulching shall be used to protect disturbed areas during
development;
h. Permanent (final) vegetation and mechanical erosion control measures in accordance with
the standards of the County Soil and Water Conservation District or the Maine Soil and Water
Conservation Commission shall be installed as soon as practicable after construction ends;
i.
Until the disturbed area is stabilized, sediment in the run-off water shall be trapped by the use
of debris basins, sediment basins, silt traps or other acceptable methods;
j.
The top of a cut or the bottom of a fill section shall not be closer than ten (10) feet to an
adjoining property, unless otherwise specified by the Board.
k. During grading operations, methods of dust control shall be employed wherever practicable;
l.
It is the responsibility of any person performing any activity on or across a communal stream,
watercourse or swale or upon the floodway or right-of-way thereof to maintain as nearly as
possible the present state of the stream, water course, swale, floodway or right-of-way during
the duration of such activity and to return it to its original or equal condition after such activity
is completed; and
m. Maintenance of drainage facilities or watercourses originating and completely on private
property is the responsibility of the owner to the point of open discharge at the property line or
at a communal watercourse within the property.
I.
LOT STANDARDS
1. All the lot configurations should be designed to maximize the use of solar energy on building sites
with suitable orientation.
SECTION XVI: GENERAL PERFORMANCE STANDARDS (continued)
45
2. Lot configuration and area shall be designed to provide for adequate off-road parking and service
facilities based upon the type of development contemplated.
3. Lots with multiple frontages shall be avoided wherever possible. When lots do have frontage on
two or more roads, the plan, and deed restrictions shall indicate vehicular access shall be located
only on the less traveled way.
4. Wherever possible, side lot lines shall be perpendicular to the road.
5. The division of tracts into parcels with substantially more than the required minimum lot size shall
be laid out in such a manner as either to provide for or preclude future re-subdivision. Where
public utilities could be extended to the development in the foreseeable future, the development
shall be designed to accommodate the extensions of utilities.
6. If a lot on one side of a stream, road or other similar barrier fails to meet the minimum
requirements for lot size, it may not be combined with a lot on the other side of the stream, or
road to meet the minimum lot size, unless such lots are established lots of record prior to the
adoption of this Ordinance.
7. Flag lots and other odd shaped lots in which narrow strips are joined to other parcels in order to
meet minimum dimensional requirements are prohibited, unless such lots are established lots of
record prior to the adoption of this Ordinance.
8. All lots shall have a minimum of four (4) sides.
J. UTILITIES
1. The Board may require electric, cable television, and telephone lines to be underground. Any
utility installations remaining above ground shall be located so as to have a harmonious relation
to neighboring properties and the site.
2. Underground utilities shall be installed prior to the installation of the final gravel base of the road.
3. The size, type, and location of street lights and utilities shall be shown on the plan and approved
by the Board.
K. CONSTRUCTION IN FLOOD HAZARD AREAS
When any part of a development is located in a Flood Hazard Area as identified by the Federal
Emergency Management Agency, the plan shall indicate that all structures on lots in the development
shall be constructed with their lowest floor, including the basement, at least one foot above the
100-year flood elevation, and meet all other State and Federal requirements. Such a restriction shall
be included in the deed to any lot which is included or partially included in the flood hazard area.
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS
SECTION USER'S GUIDE: This section contains specific road design and construction standards
applicable to all subdivisions requiring approval under this Ordinance.
A. GENERAL REQUIREMENTS
In approving applications submitted pursuant to this Ordinance, the following requirements shall apply:
1. The proposed development shall provide for safe access to and from public and private roads.
Safe access shall be assured by providing an adequate number and location of access points
with respect to sight distances, intersections, schools and other traffic generators.
2. Curb cuts shall be limited to the absolute minimum number and widths necessary for safe
entering and exiting. The proposed development shall not have an unreasonable adverse impact
on the town road system and shall assure safe interior circulation within its site by separating
pedestrian and vehicular traffic and providing adequate parking and loading areas.
46
3. Provisions shall be made for providing and maintaining convenient and safe emergency vehicle
access to all buildings and structures at all times.
4. The Board shall not approve any development plan unless proposed roads are designed in
accordance with the specifications contained in this Ordinance. Pavement, but not base
standards, may be waived in the Rural Resource/Residential (R-3) and Shoreland Residential
(R-4) Zones, provided that the developer enters into a legally binding arrangement preventing
such gravel road from becoming the responsibility of the Town without three affirmative votes of
the Board of Selectmen and prior paving to Town standards. Approval of a Final Plan by the
Board, shall not be deemed to constitute or be evidence of acceptance by the Town of any road
or easement.
B. ROAD DESIGN STANDARDS
1. These design standards shall be met by all roads within subdivisions reviewed under this
Ordinance, and shall control the roadway, shoulders, curbs, sidewalks, drainage systems,
culverts, and other appurtenances.
2. Roads shall be designed to discourage through traffic within residential developments except
where such roads are proposed in the Town's Official Map, Land Use Plan, or Development Plan.
3. Where a development borders an existing narrow road (not meeting the width requirements of the
standards for roads in this Ordinance), or when the Comprehensive Plan indicates plans for
realignment or widening of a road that would require use of some of the land in the development.
The Planning Board may require that the development plan indicate reserved areas for widening
or realigning the road marked "Reserved for Road Realignment (Widening) Purposes." Land
reserved for such purposes may not be included in computing lot area or setback requirements of
this Ordinance. When such widening or realignment is indicated on the Official Map, the reserve
area shall not be included in any lot, but shall be reserved to be deeded to the Town or State.
4. Where a Major subdivision abuts or contains an existing Town Way, no residential lot may have
vehicular access directly on to the existing Town Way. This requirement shall be noted on the
Plan and in the deeds of any lot with frontage on the Town Way.
5. Any development containing ten (10) or more dwelling units or lots shall have at least two (2) road
connections with existing public roads, roads shown on an Official Map, or roads on an approved
development plan for which performance guarantees have been filed and accepted.
47
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS (continued)
6. The following design standards apply to subdivision roads:
DESCRIPTION
DIMENSION
Minimum Right Of Way Width
50'
Minimum Pavement Width
20'
Shoulder Width
3'
Maximum Grade
8%
Minimum Centerline Radius on Curves
200'
Minimum Tangent Between Curves of Reverse Alignment
200'
Roadway Crown
1/4" /ft.
Angle of all Road Intersections
approximately
90 degrees
Maximum Grade within 75' of Intersections
3%
Minimum Curb Radii at Intersections
25'
Minimum r/o/w Radii at Intersections
10'
7. The centerline of the roadway shall be the centerline of the right-of-way.
8. DEAD END ROADS:
In addition to the design standards above, dead-end roads shall be constructed to provide a
cul-de-sac turn-around with the following requirements for radii: Sixty five (65) foot property line
radii and fifty (50) foot outer edge of travel way radii. The Board may require the reservation of a
twenty (20) foot easement in line with the dead end road to provide continuation of pedestrian
traffic or utilities to the next road. The Board may also require the reservation of a fifty (50) foot or
greater, easement in line with the dead end road to provide continuation of the road where future
subdivision or development is possible.
9. GRADES, INTERSECTIONS, AND SIGHT DISTANCES:
a. Grades of all roads shall conform in general to the terrain, so that cut and fill are minimized
while maintaining the grade standards above.
b. All changes in grade shall be connected by vertical curves to provide for the minimum sight
distances below.
POSTED SPEED
(MPH)
15
20
25
30
35
40
45
50
55
SIGHT DISTANCE
(FT)
150
200
250
300
350
400
450
500
550
c. Where new road intersections or driveway curb-cuts are proposed, sight distances, as
measured along the road onto which traffic will be turning, shall be based upon the posted
speed limit and conform to the table above: Where necessary, corner lots shall be cleared of
all growth and sight obstructions, including ground excavation, to achieve the required
visibility.
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS (continued)
48
d. Cross (four-cornered) road intersections shall be avoided insofar as possible, except as
shown on the Comprehensive Plan or at other important traffic intersections. A minimum
distance of two hundred (200) feet shall be maintained between center lines of side roads.
10. Where installed, curbing shall be granite or bituminous concrete and shall be installed on a
thoroughly compacted gravel base of six (6) inches minimum thickness, except bituminous
curbing shall be installed on the base course of the pavement. The specified pavement's width
above shall be measured between the curbs.
C. ROAD CONSTRUCTION STANDARDS
1. MINIMUM THICKNESS OF MATERIAL AFTER COMPACTION:
ROAD MATERIALS
AGGREGATE SUB-BASE COURSE
Maximum sized stone = 4"
18"
CRUSHED AGGREGATE BASE COURSE
4"
HOT BITUMINOUS PAVEMENT
Total Thickness
Surface Course
Base Course
3"
1"
2"
2. PREPARATION:
a. Before any clearing has started on the right of way, the centerline and sidelines of the new
road shall be staked or flagged at fifty (50) foot intervals.
b. Before grading is started, the entire right-of-way shall be cleared of all stumps, roots, brush,
and other objectionable material. All ledge, large boulders, and tree stumps shall be
removed from the right-of-way and all the stumps shall be disposed of in an approved stump
dump area.
c. All organic materials shall be removed to a depth of two (2) feet below the subgrade of the
roadway. Rocks and boulders shall also be removed to a depth of two (2) feet below the
subgrade of the roadway. On soils which have been identified by the Town's Consulting
Engineer as not suitable for roadways, the subsoil shall be removed from the street site to a
depth of two feet below the subgrade and replaced with material meeting the specifications
for aggregate sub-base below.
d. Side slopes less than or equal to a slope of three (3) feet horizontal to one (1) foot vertical,
and shall be graded, limed, fertilized, and seeded according to the specifications of the
erosion and sedimentation control plan. Side Slopes greater than 3 to 1 shall be engineered
using best management practices, that are acceptable to the Planning Board.
e. All underground utilities shall be installed prior to paving to avoid cuts in the pavement.
Building sewers and water service connections shall be installed to the edge of the
right-of-way prior to paving.
3. BASES AND PAVEMENT:
a. Road bases shall be constructed as follows:
1) The Aggregate Sub-base Course shall be sand or gravel of hard durable particles free
from vegetative matter, lumps or balls of clay and other deleterious substances. The
gradation of the part that passes a three (3) inch square mesh sieve shall meet the
following grading requirements:
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS (continued)
49
SIEVE
DESIGNATION
PERCENTAGE BY WEIGHT
PASSING SQUARE MESH SIEVE
1/4 inch
No. 40
No. 200
25-70%
0-30%
0-7%
Aggregate for the sub-base shall contain no particles of rock which will not pass the six (6)
inch square mesh sieve.
If Geotextile Fabric is proposed, or required it shall be installed under the Sub-base Course.
2) The Aggregate Base Course shall be screened or crushed gravel of hard durable
particles free from vegetative matter, lumps or balls of clay and other deleterious
substances. The gradation of the part that passes a three (3) inch square mesh sieve
shall meet the following grading requirements:
SIEVE
DESIGNATION
PERCENTAGE BY WEIGHT
PASSING SQUARE MESH SIEVE
1/2 inch
1/4 inch
No. 40
No. 200
45-70%
30-55%
0-20%
0-5%
Aggregate for the base shall contain no particles of rock which will not pass the two (2) inch
square mesh sieve.
b. PAVEMENT JOINTS: Where pavement joins an existing pavement, the existing pavement
shall be cut along a smooth line and form a neat, even vertical joint.
c. CURBS AND GUTTERS: Road curbs and gutters shall be installed as required by the Board.
Curbs shall be vertical except when sloped curbs are specifically allowed by the Board.
d. PAVEMENTS: Minimum standards for the base layer of pavement shall be the M.D.O.T.
specifications for plant mix grade B with an aggregate size no more than three quarter (3/4)
inch maximum, applied in a two inch (2") minimum compacted thickness.
Minimum standards for the surface layer of pavement shall meet the M.D.O.T. specifications
for plant mix grade C with an aggregate size no more than one half (1/2) inch maximum,
applied in a one inch (1") minimum compacted thickness.
D. CLEANUP
Following road construction, the developer or contractor shall conduct a thorough clean-up of stumps
and other debris from the entire road right-of-way. If on-site disposal of the stumps and debris is
proposed, the site shall be indicated on the Plan, and be suitably covered with fill and topsoil, limed,
fertilized, and seeded.
E. ROAD NAMES, SIGNS, AND LIGHTING
Roads which join and are in alignment with roads of abutting or neighboring properties shall bear the
same name. Names of new roads shall not duplicate, nor bear phonetic resemblance to the names
of existing roads within the Town, and shall be subject to the approval of the Board. The developer
shall reimburse the Municipality for the costs of installing road name, traffic safety and control signs.
Road lighting shall be installed as approved by the Board.
SECTION XVII: ROAD DESIGN AND CONSTRUCTION STANDARDS (continued)
50
F. DRIVEWAY CULVERTS
The minimum size of any driveway culvert shall be fifteen (15) inches in diameter. The minimum and
maximum lengths, respectively shall be twenty four (24) and thirty six (36) feet in length.
G. CERTIFICATION OF CONSTRUCTION
Upon completion of road construction a written certification signed by a professional engineer
registered in the State of Maine, approved by the Planning Board, shall be submitted to the Planning
Board at the expense of the applicant, certifying that the proposed way meets or exceeds the design
and construction requirements of this Ordinance. "As built" plans may be required by the Planning
Board.
51
SECTION XVIII: BUFFER AND SCREENING STANDARDS
SECTION USER'S GUIDE: This section contains specific standards relating to the buffers and screening
required along property lines and Town Ways.
A. SPECIAL BUFFER REQUIREMENTS ALONG TOWN WAYS
In approving applications submitted pursuant to this Ordinance, the Board shall require the applicant
to meet the following buffer and screening standards:
1. All areas located along Town Ways, within seventy-five (75) feet of the centerline of such ways,
shall be used as buffer areas. Within these buffer areas, the following minimum plantings and
buffers shall be required:
NUMBER PER 100 LINEAR
FEET
BUFFER AREA LOCATION
WIDTH
STRUCTURE
CT
UT
SH
ET
Screening for all one
story buildings
20'
N/A
3
7
30
9
Screening for all buildings of
two or more stories
20'
N/A
4
12
30
18
Screening of all parking
areas which are visible from
Town Ways
N/A
Berm
N/A
N/A
18
N/A
Total screening, where
required by Planning
Board
N/A
Fencing or
Berm Wall
N/A
N/A
18
N/A
LEGEND: CT = Canopy Trees
UT = Under story Trees
SH = Shrubs
ET = Evergreen Trees
2. Unless otherwise specifically indicated by the Board, all plant materials required by the Board
under this Ordinance, shall meet the following minimum size standards:
PLANT MATERIAL TYPE
PLANTINGS IN BUFFER AREAS
ABUTTING VACANT LANDS
ALL OTHER
PLANTINGS
CANOPY TREES
Single stem
Multi-Stem Clump
1.5 inch caliper
6 feet height
2.0 inch caliper
10 feet height
UNDER STORY TREES
4 feet height
1.5 inch caliper
EVERGREEN TREES
3 feet height
5-7 feet height
SHRUBS
Deciduous
Evergreen
15 inches height
12 inches height
24 inches height
18 inches height
SECTION XVIII: BUFFER AND SCREENING STANDARDS (continued)
52
3. All plantings required under this Ordinance shall be of a type and species appropriate for the soil
types and climatic conditions in Dedham, Maine.
B. BUFFERS AND SCREENING
1. Buffers in the form of fences, landscaping, berms and mounds shall be required to minimize any
adverse impacts or nuisance on the site or on adjacent properties.
2. Buffers shall be considered in or for the following areas and purposes:
a. Along property lines, to shield various uses from each other;
b. Along interior roads running parallel to roads exterior to the site, to prevent confusion,
particularly at night;
c. Parking areas, garbage collection areas, and loading and unloading areas; and
d. To block prevailing wind patterns and to stop wind-borne debris from leaving the site.
3. Buffers shall be sufficient to shield structures and uses from the view of incompatible abutting
properties and public road ways, and to otherwise prevent any nuisances.
4. Exposed storage areas, service areas, exposed machinery installation, sand and gravel
extraction operations, truck-loading areas, utility buildings and structures, and areas used for the
storage or collection of discarded automobiles, auto parts, metals or any other articles of salvage
or refuse, and similar accessory areas and structures, shall have sufficient setbacks and
screening to provide an audio/visual buffer sufficient to minimize their adverse impact on other
land uses within the development site and surrounding properties, such as a stockade fence or a
dense evergreen hedge six (6) feet or more in height.
5. Where a potential safety hazard to children would be likely to arise, physical screening sufficient
to deter small children from entering the premises shall be provided and shall be maintained in
good condition.
6. Natural features shall be maintained wherever possible to provide a buffer between the proposed
development and incompatible abutting properties and public roadways. When natural features
such as topography, gullies, stands of trees, shrubbery, or rock outcrops do not exist or are
insufficient to provide a buffer, other kinds of buffers shall be considered.
7. Evergreens can be used as buffers, provided they are planted in two (2) or three (3) rows of
staggered plantings. The rows should be seven (7) feet apart and the evergreens planted six (6)
feet on center.
8. Fencing and screening shall be durable and properly maintained at all times by the owner.
9. Fencing and screening shall be so located within the property line to allow access for
maintenance on both sides without intruding upon abutting properties.
10. All buffer areas shall be maintained in a neat and sanitary condition by the owner.
SECTION XVIII: BUFFER AND SCREENING STANDARDS (continued)
53
C. PLANT MATERIAL MAINTENANCE BOND REQUIRED
Prior to issuance of any permit, the applicant shall furnish to the Town of Dedham a bond, letter of
credit, or other form of security approved by the Board, equal to at least twenty-five percent (25%) of
the value of all plantings required under this subsection. The bond shall be binding for a minimum of
three (3) years and shall be subject to the condition that required plantings be maintained in
accordance with the terms of the Board's approval and in a good and healthy condition.
Notwithstanding the requirement of a bond from the applicant, the owner of any premises approved
by the Board under any section of this Ordinance shall have a continuing obligation to maintain
required plantings in accordance with the terms of the Board's approval and in a good and healthy
condition.
SECTION XIX: STORM DRAINAGE DESIGN AND CONSTRUCTION STANDARDS
SECTION USER'S GUIDE: This section contains specific standards relating to the design and
construction of storm water management systems.
54
A. GENERAL PROVISIONS
In approving applications submitted pursuant to this Ordinance, the Board shall require the applicant
to meet the following storm drainage design and construction standards:
1. The storm drainage system will not adversely affect neighboring properties, downstream water
quality, or cause soil erosion. Whenever possible, on-site absorption and/or evaporation of
run-off waters shall be utilized to minimize discharges from the site.
2. Surface water runoff shall be minimized and detained on-site if possible or practicable. If it is not
practicable to detain water on site, downstream improvements to the channel may be required of
the developer to prevent flooding caused by his project. The natural state of watercourses,
swales, floodway or rights-of-way shall be maintained as nearly as possible. The design basis is
a twenty-five (25) year storm.
B. STORM WATER MANAGEMENT DESIGN STANDARDS
1. Adequate provision shall be made for disposal of all storm water generated within the
development and any drained ground water through a management system of swales, culverts,
under drain, and water courses. The storm water management system shall be designed to
conduct storm water flows to existing watercourses.
2. All components of the storm water management system shall be designed to meet the criteria of
a twenty-five (25) year storm based on rainfall data for the closest reporting station to Dedham,
Maine.
3. The minimum pipe size for any storm drainage pipe shall be fifteen (15) inches in diameter. The
minimum and maximum lengths, shall be based upon common engineering practices that take
into account frost protection and future maintenance. Maximum trench width at the pipe crown
shall be the outside diameter of the pipe plus two (2) feet. Pipe shall be bedded in a fine granular
material, containing no stones larger than three (3) inches, lumps of clay, or organic matter,
reaching a minimum of six (6) inches below the bottom of the pipe extending to six (6) inches
above the top of the pipe.
4. Catch basins shall be installed where necessary and located at the curb line.
5. Inlets and outlets shall be stabilized against soil erosion by stone rip-rap or other suitable
materials to reduce storm water velocity.
6. The storm water management system shall be designed to accommodate complete watershed
drainage, taking into account existing conditions and approved or planned developments not yet
built and shall include a surplus design capacity factor of twenty-five (25) percent for potential
increases in upstream runoff.
7. Downstream drainage requirements shall be studied to determine the effect of the proposed
development. The storm drainage shall not overload existing or future planned storm drainage
systems downstream from the development. The developer shall be responsible for financing
any improvements to existing drainage systems required to handle the increased storm flows.
SECTION XIX: STORM DRAINAGE DESIGN AND CONSTRUCTION STANDARDS (continued)
8. Where soils require a subsurface drainage system, the drains shall be installed and maintained
separately from the storm water drainage system.
C. STORM DRAINAGE CONSTRUCTION STANDARDS
55
1. REINFORCED CONCRETE PIPE:
Reinforced Concrete Pipe shall meet the requirements of ASTM Designation C-76 (AASHTO M
170). Pipe classes shall be required to meet the soil and traffic loads with a safety factor of 1.2
on the .01 inch crack strength with a Class B bedding. Joints shall be of the rubber gasket type
meeting ASTM Designation C 443-70, or of an approved preformed plastic jointing material such
as "Ramnek". Perforated Concrete Pipe shall conform to the requirements of AASHTO M 175 for
the appropriate diameters.
2. CORRUGATED METAL PIPE:
Corrugated Metal Pipe shall be bituminous coated meeting the requirements of AASHTO
Designation M 190 Type C for iron or steel pipe or AASHTO Designation M 196 for aluminum
alloy pipe for sectional dimensions and type of bituminous coating. Pipe gauge shall be as
required to meet the soil and traffic loads with a deflection of not more than five (5) percent.
3. ABS PIPE:
ABS (Acrylonitrile-butadiene-styrene) composite pipe and fittings shall conform to the
requirements of AASHTO M 264 and AASHTO M 265. Perforated pipe shall conform to the
requirements of AASHTO M 36, Type III.
4. CORRUGATED PLASTIC PIPE:
Corrugated Plastic Pipe shall conform to the requirements of AASHTO M-252.
5. MANHOLES:
Manholes shall be of precast concrete truncated cone section construction meeting the
requirements of ASTM Designation C 478 or precast concrete manhole block construction
meeting the requirements of ASTM Designation C 139, radial type. Bases may be cast in place
3000 psi 28 day strength concrete or may be of precast concrete, placed on a compacted
foundation of uniform density. Metal frames and traps shall be set in a full mortar bed and tops
shall conform to the requirements of AASHTO M 103 for carbon steel castings, AASHTO M 105,
Class 30 for gray iron castings or AASHTO M 183 (ASTM A 283, Grade B or better) for structural
steel.
6. CATCH BASINS:
Catch Basins shall be of precast concrete truncated cone section construction meeting the
requirements of ASTM Designation C 478 or precast concrete manhole block construction
meeting the requirements of ASTM Designation C 139, radial type. Castings shall be sized for
the particular inlet condition with the gratings perpendicular to the curb line. Bases may be cast
in place 3000 psi 28 day strength concrete or may be of precast concrete, placed on a compacted
foundation of uniform density. Metal frames and traps shall be set in a full mortar bed with tops
which shall conform to the requirements of AASHTO M 183 (ASTM A 283, Grade B or better) for
structural steel.
7. DRAIN INLET ALIGNMENT:
Drain inlet alignment shall be straight in both horizontal and vertical alignment unless specific
approval of a curvilinear drain is obtained in writing from the Board, after consultation with an
Engineer chosen by the Town. All consultation expenses will be borne by the developer.
SECTION XIX: STORM DRAINAGE DESIGN AND CONSTRUCTION STANDARDS (continued)
8. MANHOLE PLACEMENT:
Manholes shall be provided at all changes in vertical or horizontal alignment and at all junctions.
On straight runs, manholes shall be placed at a maximum of four hundred (400) foot intervals.
9. CATCH BASIN AND MANHOLE MAINTENANCE:
56
Upon completion each catch basin or manhole shall be cleaned of all accumulation of silt, debris
or foreign matter and shall be kept clean until final acceptance of the road by the Town.
57
SECTION XX: PROVISION FOR CLUSTER DEVELOPMENT
SECTION USER'S GUIDE: This section allows innovative approaches to housing and environmental
design by authorizing the Planning Board to reduce certain requirements of this Ordinance for applications
proposing clustered development.
A. PURPOSE
The purpose of these provisions is to allow for innovative concepts of housing development where
maximum variations of design may be allowed, provided that the net residential density shall be no
greater than is permitted by this Ordinance.
In addition, the purpose of allowing Cluster Development shall be to encourage housing development
which will result in:
1. Additional open space and recreation areas;
2. A pattern of development which preserves trees, outstanding natural topography and geologic
features and reduces soil erosion; and
3. An efficient use of land resulting in small networks of utilities and streets.
B. ALLOWABLE REDUCTION IN REQUIREMENTS
To accomplish the purposes above, the layout and dimensional requirements of this Ordinance may
be reduced as follows:
1. The Board may reduce area requirements by not more than fifty percent (50%) but only if a net
area at least equal in area to the cumulative lot size reduction is maintained as common or public
land;
2. The Board shall not increase building height limitations; and
3. The modification of requirements under this section shall not require a variance and no finding of
undue hardship shall be required;
C. PERFORMANCE STANDARDS
All cluster developments approved by the Board must meet the following requirements:
1. All the requirements and standards of this Ordinance, except those dealing with lot layout and
dimensions, shall be met.
2. The minimum area of land in a cluster development shall be ten (10) acres.
3. No building shall be constructed on soil types that are poorly drained.
4. Where a cluster development is proposed on a parcel which abuts a water body, a portion of the
shoreline, as well as reasonable access to it, shall be part of the common land.
5. In cluster developments all dwelling units within each cluster shall be connected to a common
water supply and distribution system, either public or private.
6. In cluster developments all dwelling units within each cluster shall be connected to a common
sewer system or to a central collection and treatment system.
7. Buildings shall be oriented with respect to scenic vistas, natural landscape features, topography,
south-facing slopes, and natural drainage areas in accordance with an overall plan for site
development and landscaping.
58
SECTION XXI: ADDITIONAL REQUIRED IMPROVEMENTS
SECTION USER'S GUIDE: This section contains specific information regarding additional site
improvements required of all developments approved under this Ordinance.
The following improvements are required for all subdivisions, unless waived by the Board in accordance
with provisions of this Ordinance.
A. MONUMENTS
1. Iron pin or stone monuments shall be set at all road intersections and points of curvature.
2. Iron pin or stone monuments shall be set at all corners and angle points of the development
boundaries where the interior angle of the subdivision boundaries is one hundred thirty five (135)
degrees or less.
3. Stone monuments shall be a minimum of four (4) inches square at the top and four (4) feet in
length. After they are set, drill holes, one-half (1/2) inch deep shall locate the point or points
described above.
4. All other development boundary corners and angle points, as well as all lot boundary corners and
angle points shall be marked by suitable permanent monumentation including, but not limited to
the following:
a. A granite monument;
b. A concrete monument;
c. An iron pin; or
d. A drill hole in ledge.
B. WATER SUPPLY
1. The Board may allow the use of individual wells or a private central water supply system.
2. Dug wells shall be prohibited.
3. When a development is to be served by a central water supply system, the complete supply
system, including any required fire ponds and dry hydrants, shall be installed at the expense of
the subdivider.
4. If a central water supply system is provided by the developer, the location and protection of the
source as well as the design, construction, and operation of the system shall conform to the
standards of the Maine Rules Relating to Drinking Water.
5. The applicant shall construct ponds and dry hydrants to provide for adequate water storage for
fire-fighting purposes. An easement shall be granted to the Town granting access to the dry
hydrants where necessary. The Board may waive the requirement for fire ponds only upon a
finding by the Board that adequate, alternate firefighting provisions exist or will be built as part of
the approved plan. When calculating the minimum water supplies needed for firefighting,
generally accepted standards, including but not limited to the 1999 edition of National Fire
Protection Association 1231 Water Supplies for Suburban and Rural firefighting, shall be used..
C. SEWAGE DISPOSAL
1. The applicant shall submit evidence of soil suitability for subsurface sewage disposal prepared by
a Maine Licensed Site Evaluator in full compliance with the requirements of the State of Maine
Subsurface Wastewater Disposal Rules. In addition, on lots in which the limiting factor has been
identified as being within 24 inches of the surface, a second site with suitable soils shall be shown
59
SECTION XXI: ADDITIONAL REQUIRED IMPROVEMENTS (continued)
as a reserve area for future replacement of the disposal area. The reserve area shall be show in
the plan and restricted so as not to be built upon.
2. Disposal areas shall not be permitted on soils or on a lot which requires a New System Variance
from the Subsurface Wastewater Disposal Rules.
D. SURFACE DRAINAGE
1. Where a development is traversed by a stream, river, or surface water drainage-way, or where
the Board feels that surface water runoff to be created by the subdivision should be controlled,
there shall be provided easements or drainage rights-of-way with swales, culverts, catch basins
or other means of channeling surface water within the subdivision and over other properties. This
surface water management system shall be designed by a Registered Professional Engineer.
2. Drainage easements for existing water courses or proposed drainage ways at least thirty (30) feet
wide, conforming substantially with the lines of existing natural drainage, shall be provided and
indicated on the Plan.
3. The developer shall provide a statement from a qualified professional that the proposed
development will not create erosion, drainage or runoff problems either in the development or in
other properties. Where the peak runoff from the development onto other properties is increased
either in volume or duration, easements from the abutting property owners, allowing such
additional discharge shall be obtained.
4. A surface water drainage plan, showing ditching, culverts, storm drains, easements, and other
proposed improvements, meeting the standards of Section XVII, shall be submitted.
E. WALKWAYS, TRAILS
1. When the subdivision is within the Village Center Zone and abuts any state or town road, or is
within two thousand feet (2,000') of a school, the applicant shall install three-foot (3') wide
sidewalks, or pedestrian walkways/bikeways. These sidewalks or pedestrian walkways/ bikeways
shall be designed to enable pedestrians and bicyclists to travel safely without entering the travel
portion of the road.
60
SECTION XXII: DEDICATION AND MAINTENANCE OF COMMON OPEN SPACE AND SERVICES
SECTION USER'S GUIDE: This section contains specific provisions regarding the dedication and
maintenance of common open space and common services in subdivisions.
A. DEDICATION
1. All common land in subdivisions shall be owned jointly or in common by the owners of the
dwelling units by means of a homeowners' association, by an association which has as its
principal purpose the conservation or preservation of land in essentially its natural condition, or by
the Town.
2. Further subdivision of the common land or its use for other than non-commercial recreation or
conservation purposes, except for easements for utilities or drainage, shall be prohibited.
Structures and buildings accessory to non-commercial recreational or conservation uses may be
erected on the common land, except drainage easement.
3. The common open space shall be shown on the Final Plan of the proposed subdivision with
appropriate notation on the plan to indicate that:
a. It shall not be used for future building lots; and
b. A part or all of the common open space may be dedicated for acceptance by the municipality
or other organization acceptable to the Board.
B. MAINTENANCE OF COMMON SPACE IN SUBDIVISIONS
1. If any or all of the common open space are to be reserved for use by the residents, the by-laws of
the proposed homeowners' association shall specify maintenance responsibilities and shall be
submitted to the Board prior to Final Plan approval.
2. Covenants for mandatory membership in the homeowners association setting forth the owners'
right, interests, and privileges in the association and the common property, shall be reviewed by
the Board and shall be included in the deed for each lot or dwelling.
3. The homeowners' association shall have the responsibility of maintaining the common property
unless or until dedication is accepted by the municipality or other organization acceptable to the
Board.
4. The association shall levy annual charges against all owners of dwelling units to defray the
expenses connected with the maintenance of common property and tax assessments.
5. The developer or subdivider shall maintain control of the common property, and be responsible
for its maintenance until development sufficient to support the association has taken place.
61
SECTION XXIII: PERFORMANCE GUARANTEES
SECTION USER'S GUIDE: This section contains specific provisions relating to required performance
guarantees and how they will be administered.
A. TYPES OF GUARANTEES
With submittal of the application for Final Plan approval for any Major Subdivision, the developer shall
provide one of the following performance guarantees for an amount adequate to cover the estimated
construction costs of all required improvements, taking into account the time-span of the construction
schedule and the inflation rate for construction costs.
1. Either a certified check payable to the Town or a savings account or certificate of deposit all
naming the Town as owner, for the establishment of an escrow account, as provided for in
Section C, below;
2. A performance bond payable to the Town issued by a surety company, approved by the Board of
Selectmen and Town Attorney, as provided for in Section D, below;
3. An irrevocable letter of Credit from a financial institution establishing funding for the construction
of the development, from which the Town may draw if construction is inadequate, approved by
the Board of Selectmen and Town Attorney, as provided for in Section E, below; or
4. An offer of conditional approval limiting the number of units built or lots sold until all required
improvements have been constructed, as provided for in Section F, below.
The conditions and the amount of the performance guarantee shall be determined by the Board with
the advice of the Town's Consulting Engineer, Road Commissioner, Municipal Officers and/or Town
Attorney.
B. CONTENTS OF GUARANTEE
The performance guarantee shall contain a construction schedule, cost estimates for each major
phase of construction taking into account inflation, provisions for inspections of each phase of
construction, provisions for the release of part or all of the performance guarantee to the developer,
and a date after which the developer will be in default allowing the Town access to the funds to finish
construction, as provided for in Section I, below.
C. ESCROW ACCOUNT
A cash contribution to the establishment of an escrow account shall be made by either a certified
check made out to the Town, the direct deposit into a savings account, or the purchase of a certificate
of deposit. For any account opened by the developer, the Town shall be named as owner or
co-owner, and the consent of the Town shall be required for a withdrawal. Any interest earned on the
escrow account shall be returned to the developer.
D. PERFORMANCE BOND
A performance bond shall detail the conditions of the bond, the method for release of the bond or
portions of the bond to the developer, and the procedures for collection by the Town. The bond
documents shall specifically reference the subdivision for which approval is sought.
E. LETTER OF CREDIT
An irrevocable letter of credit from a bank or other lending institution shall indicate that funds have
been set aside for the construction of the development and may not be used for any other project or
loan.
62
SECTION XXIII: PERFORMANCE GUARANTEES (continued)
F. CONDITIONAL AGREEMENT
The Board, at its discretion may provide for the developer to enter into a binding agreement with the
Town in lieu of the other financial performance guarantees. Such an agreement shall provide for
approval of the Final Plan on the condition that no more than two (2) lots be sold or built upon until
either:
1. It is certified by the Board, or its agent, that all of the required improvements have been installed
in accordance with this Ordinance and the regulations of the appropriate utilities; or
2. A performance guarantee, acceptable to the Town is submitted in an amount necessary to cover
the completion of the required improvements at an amount adjusted for inflation and prorated for
the portions of the required improvements already installed.
Notice of the agreement and any conditions shall be on the Final Plan which is recorded at the
Registry of Deeds. Release from the agreement shall follow the procedures for release of the
performance guarantees contained in Subsection H.
G. PHASING OF DEVELOPMENT
The Board may approve plans to develop a major subdivision in separate and distinct phases. This
may be accomplished by limiting final approval to those lots or buildings abutting that section of the
proposed development's road which is covered by a performance guarantee. When development is
phased, road construction shall commence from an existing public way. All dead end roads shall be
provided with a permanent or temporary cul-de-sac. Final approval of lots in subsequent phases
shall be given only upon satisfactory completion of all requirements pertaining to previous phases.
H. RELEASE OF GUARANTEE
Prior to the release of any part of the performance guarantee, the Board shall determine to its
satisfaction, in part upon the report of the Town's consulting Engineer and whatever other agencies
and departments may be involved, that the proposed improvements meet or exceed the design and
construction requirements for that portion of the improvements for which the release is requested.
I.
DEFAULT
If, upon inspection, the Town's consulting engineer finds that any of the required improvements have
not been constructed in accordance with the plans and specifications filed as part of the application,
he shall so report in writing to the Code Enforcement Officer, the Board of Selectmen, the Board, and
the subdivider or developer. The Town of Dedham shall take any steps necessary to preserve the
Town's rights.
Failure to construct in accordance with approved plans and specifications shall be a violation of this
ordinance and punishable pursuant to title 30-A, MRSA, Section 4452.
J. PRIVATE ROADS
Where the development roads are to remain private roads, the following words shall appear on the
recorded plan:
"All roads in this development shall remain private roads to be maintained by the developer or the lot
owners and shall not be accepted or maintained by the Town."
63
SECTION XXIV: WAIVERS
SECTION USER'S GUIDE: This section authorizes the Board, under special circumstances, to waive
portions of the submission requirements, performance standards and improvements required by this
Ordinance and provides that such waiver be granted only with conditions.
A. WAIVER OF SUBMISSION REQUIREMENTS
Where the Board makes written findings of fact that there are special circumstances of a particular
site proposed to be subdivided, it may waive portions of the submission requirements, provided the
public health, safety and welfare are protected and provided the waivers do not have the effect of
nullifying the intent and purpose of the Official Map, the Comprehensive Plan, or any Ordinance.
B. WAIVER OF PERFORMANCE STANDARDS
Where the Board makes written findings of fact that there are special circumstances of a particular
site proposed to be subdivided, it may waive portions of the performance standards, unless otherwise
indicated in this Ordinance, to permit a more practical and economical development, provided the
public health, safety and welfare are protected, and provided the waivers do not have the effect of
nullifying the intent and purpose of the Official Map, the Comprehensive Plan, or any ordinance.
C. WAIVERS OF REQUIRED IMPROVEMENTS
Where the Board makes written findings of fact that due to special circumstances of a particular site
proposed to be subdivided, the provision of certain required improvements is not requisite to provide
for the public health, safety or welfare, or are inappropriate because of inadequate or lacking
connecting facilities adjacent to or in proximity to the proposed subdivision or development, it may
waive the requirement for such improvements, subject to appropriate conditions.
D. WAIVERS CONDITIONALLY GRANTED
In granting waivers to any of the provisions of this Ordinance in accordance with subsections A, B,
and C, above, the Board shall require such conditions as will assure the purposes and objectives of
this Ordinance are met.
E. WAIVERS LIMITED
No other waivers of the provisions of this Ordinance may be granted, except as expressly authorized
by this section.
F. WAIVER REVOCABLE
All waivers granted by the Planning Board under this Section of the Ordinance are revocable up to
the date of Final Plan approval.
64
SECTION XXV: DEFINITIONS
SECTION USER'S GUIDE: This section contains specific definitions for words and phrases used in this
Ordinance.
A. CONSTRUCTION OF LANGUAGE
In this Ordinance, certain terms and words shall be interpreted as follows:
1. The words "persons" and "applicant" includes individuals, firms, associations, corporations,
organizations, and similar entities;
2. Words used or defined in one tense or form shall include other tenses or derivative forms;
3. Words in the singular number shall include the plural number and words in the plural shall include
the singular number;
4. The masculine gender shall include the feminine and the feminine shall include the masculine;
5. The word "shall" is mandatory;
6. The word "may" is permissive;
7. In case of difference of meaning or implication between the text of this Ordinance and any map,
illustration, or table, the text shall control.
B. DEFINITIONS
For the purpose of interpreting this Ordinance, the following terms, phrases, words and their
derivations shall have the meaning given herein.
1. APPLICANT
The assessed owner or owners of land to be subdivided or person with documented right, title, or
interest in the land to be subdivided.
2. CLUSTER DEVELOPMENT
A subdivision or development in which the lot sizes are reduced below those normally required in
return for the provision of permanent open space owned in common by lot and/or unit owners, the
Town, or a land conservation organization, as allowed by the Planning Board.
3. COMPLETE APPLICATION
An application presented to the Planning Board which includes (1) receipt for fee paid; (2)
completed application form; (3) Planning Board notification stating that all other submissions
required herein for that type of application have been received and are satisfactory.
4. COMPREHENSIVE PLAN OR POLICY STATEMENT
Any part or element of the overall plan or policy for development of the Town as defined in Title
30-A, MRSA, Section 4311, et seq.
5. CONTIGUOUS LOTS
Lots in the same ownership which adjoin at any line or point, except that lots on opposite sides of
a public or private road shall be each considered a separate tract or parcel unless such road was
established by the owner of land on both sides thereof.
65
SECTION XXV: DEFINITIONS (continued)
6. DRIVEWAY
Driveway shall mean a private way providing 4-wheel vehicular access from a public way
to not more than two lots with buildings thereon.
7. EASEMENT
The authorization of the property owner for the use by another, and for a specified purpose, of
any designated part of his property.
8. ENGINEER
Municipal Engineer or consulting engineer licensed by the State of Maine.
9. ENVIRONMENTALLY SENSITIVE AREAS
Those significant natural, scenic, historic, and archaeological areas which have been
identified in the Town of Dedham, Maine.
10. FINAL PLAN
The final drawings on which the applicant's plan of subdivision is presented to the Board
or approval and which, if approved, shall be recorded at the Registry of Deeds.
11. FRESHWATER WETLAND
Freshwater Wetlands shall be defined as in Title 38 M.R.S.A., Sec. 480B, Natural Resources
Protection Act. According to 1989 statutes, Freshwater Wetlands are defined as follows:
"Freshwater Wetlands" means freshwater swamps, marshes, bogs and similar areas which are:
a. Often (10) or more contiguous acres, or of less than ten (10) contiguous acres and adjacent
to a surface water body, excluding any river, stream, or brook, such that in a natural state, the
combined surface area is in excess of ten (10) acres;
b. Inundated or saturated by surface or ground water at a frequency and for a duration sufficient
to support, and which under normal circumstances do support, a prevalence of wetland
vegetation typically adapted for life in saturated soils; and
c. Not considered part of a great pond, coastal wetland, river, stream or brook.
These areas may contain small stream channels or inclusion of land that do not conform to the
criteria of this subsection.
Delineating standards shall be as per current rules and regulations of the Maine Department of
Environmental Protection. Wetland mapping to be submitted as a requirement of this ordinance
shall be prepared and signed by a State Certified Soil Scientist or Geologist, registered in the
State of Maine.
12. FRONTAGE
The linear distance between the sidelines of a lot, measured along the line that borders upon
whatever right-of-way serves as legal access to the lot. For the purposes of these regulations,
the following ways shall constitute legal access to a lot along which frontage may be measured:
a. A way accepted by or established as belonging to the Town of Dedham, or the State of
Maine, provided access is not specifically prohibited;
SECTION XXV: DEFINITIONS (continued)
66
b. A way, whether dedicated to public ownership or not, as shown on an approved subdivision
plan.
Frontage dimensions shall meet or exceed the minimum frontage required by the Town's Zoning
Ordinance.
13. HIGH INTENSITY SOIL SURVEY
A Class A soil survey, conducted by a Certified Soil Scientist and prepared according to the
standards of the National Cooperative Soil Survey, resulting in a soils map in which the mapping
units are single phases of soils series and the mapping units delineated are contrasting soils of
one eight (1/8) acre or less in size.
14. LEGISLATIVE BODY
Board of Selectmen.
15. LOT
Any separate or distinct unit of land, structure or part of structure, whether residential or non-
residential, with a clearly separate but not necessarily different, use or intended use from the lot
or lots adjacent to it, with the exception of auxiliary buildings for a single-family residence, not
intended for human occupancy. Included under this definition of a lot would be apartments,
shopping centers, and groups of non-residential buildings with different uses, even if owned by
the same person.
16. MEDIUM INTENSITY SOIL SURVEY
A Class C soil survey, conducted by a Certified Soil Scientist and prepared according to the
standards of the National Cooperative Soil Survey, resulting in a soils map in which the mapping
units are single phases of soils series and the mapping units delineated are contrasting soils of
three (3) acres or less in size.
17. NET ACREAGE
The total acreage available for the subdivision or development, and shown on the proposed
subdivision or development plan, minus the area for roads or access and the areas which are
unsuitable for development.
18. NGVD
National Geodetic Vertical Datum.
19. NORMAL HIGH WATER ELEVATION OF INLAND WATERS
Along lakes, ponds, and streams, the elevation at which vegetation changes from predominantly
aquatic to predominantly terrestrial; along streams, the highest elevation on the bank of a channel
at which the water has left a definite mark.
20. OFFICIAL MAP
The maps adopted by the Municipality showing the location of public property, ways used in
common by more than two (2) owners of abutting property, and approved subdivisions; and any
amendments thereto adopted by the Municipality or additions thereto resulting from the approval
of subdivision plans by the Planning Board and the subsequent filing for record of such approved
plans.
SECTION XXV: DEFINITIONS (continued)
67
21. OFFICIAL SUBMITTAL DATE
The date upon which the Board issues a receipt indicating that a complete application has been
submitted.
22. ONE-HUNDRED-YEAR FLOOD
The highest level of flood that, on the average, is likely to occur once every 100 years (that has a
one percent chance of occurring in any year).
23. PERSON
Includes an individual, firm, association, partnership, trust, company, corporation, municipal or
other local government entity, quasi-municipality, state agency, educational or charitable
organization or institution or other legal entity.
24. PLANNING BOARD
The Planning Board of the Town of Dedham, Maine.
25. PLANNING BOARD ORDER
A written decision of the Planning Board including findings of fact, conclusions of law, decisions,
and conditions and/or terms of approval, if any.
26. PRELIMINARY SUBDIVISION PLAN
The preliminary drawings indicating the proposed layout of the subdivision to be submitted to the
Board for its consideration.
27. RECENT FLOOD PLAN SOILS
The following soil series as described and identified by the National Cooperative Soil Survey:
Alluvial
Cornish
Charles
Fryeburg
Hadley
Limerick
Lovewell
Medomak
Ondawa
Podunk
Rumney
Saco
Suncook
Sunday
Winooski
28. REPRODUCIBLE COPIES OF FINAL PLAN
Mylars, plastic film, or other durable, permanent, stable based, transparent material upon which
Final Subdivision Plans are drawn and upon which the Planning Board signs at the time of final
approval.
29. RIGHT-OF-WAY
A street or other area over which is given legal right of passage. A public right-of-way is a way
dedicated to the use of the public and accepted for ownership by the Town of other level of
government.
30. ROAD
Public and private ways such as Town ways, public rights-of-way, and private rights-of-way.
68
SECTION XXV: DEFINITIONS (continued)
31. SUBDIVISION
As defined by Title 30-A, M.R.S.A., Section 4401, as the same may be amended from time to
time, except that a lot of forty (40) acres or more shall be counted as a lot.
32. SUBDIVISION, MAJOR
Any subdivision containing more than three (3) lots or dwelling units, or any proposed road
construction.
33. SUBDIVISION, MINOR
Any subdivision containing not more than three (3) lots or dwelling units and with all lots abutting
on an existing public way.
34. TOWN
Town of Dedham, Maine
35. TRACT OR PARCEL OF LAND
All contiguous land in the same ownership, whether or not the tract is separated at any point by an