TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 1 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Site Plan Review Ordinance
Of The
TOWN OF
FRANKLIN, MAINE
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 2 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Original Ordinance Enacted
March 28, 2026
Attest and Certified By: ___________________________________
Deborah T Lurvey
Town Clerk, Franklin, Maine
Date: __________________________________
Pages: 56
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 3 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Site Plan Review Ordinance
Section 1. General Provisions
A.
Title
This Ordinance shall be known as the "Site Plan Review Ordinance of the Town of Franklin,
Maine." It shall be referred to herein as the "Ordinance."
B.
Authority
This Ordinance is adopted pursuant to the enabling provisions of Article VIII, Part 2 of the
Maine Constitution (Municipal Home Rule), the provisions of 30-A M.R.S.A. § 3001 (Home
Rule) and the provisions of the Planning and Land Use Regulation Act 30-A M.R.S.A. Chapter
187 (Comprehensive Planning and Regulation or "Growth Management Act") and 30-A
M.R.S.A. § 4452 (Enforcement of Land Use Laws and Ordinances) as may be amended from
time to time, and the Comprehensive Plan of the Town of Franklin.
No activity or use requiring Site Plan Review shall commence until the property owner has
received Site Plan Approval from the CEO or Planning Board as appropriate, and has complied
with any other applicable provisions of this ordinance. No plumbing or other permits or
certificate of compliance shall be issued by the municipal officers or Code Enforcement
Officer for any use or development within the scope of this ordinance until the Site Plan
Application has been reviewed and approved. The issuing authority may modify or waive any
of the submission requirements when it determines that because of the size of the project or
circumstances of the site such requirements would not be applicable or would be an
unnecessary burden upon the applicant and that such modifications or waiver will not
adversely affect the abutting landowners or the general health, safety, or welfare of the Town.
Permits can be transferred with the approval of the issuing authority.
C.
Purpose
1.
To assure the safety, health, and welfare of the people of the Town of Franklin.
2.
To promote an economically sound and stable community.
3.
To lessen danger and congestion of traffic on public roads.
4.
To protect and preserve the natural environment of the Town of Franklin.
5.
To establish orderly and uniform procedures whereby the Town may review high
impact projects to ensure that the other purposes of this Ordinance are met.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 4 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
D.
Applicability
1.
This ordinance does not apply to single family dwellings or the construction, alteration,
or enlargement of a single family or two-family dwelling which when completed are less
than three thousand five hundred (3,500) total square feet when including the combined
footprint of all structures on a single lot. This ordinance does not apply to home-based
occupations or home-based fishing, agricultural, professional, or forestry activities. This
ordinance does not apply to uses existing at the adoption of the ordinance.
2.
This ordinance shall apply to all development proposals for establishment, alteration, or
change of use of commercial, retail, industrial, institutional buildings and structures and
multiple family dwellings consisting of three or more attached dwelling units and their
accessory uses and structures. The one-time expansion of a structure or accessory
building footprint by six hundred (600) square feet or less in any five (5) year period may
be permitted by the Code Enforcement Officer.
3.
A person who has right, title, or interest in a parcel of land, or their authorized agent,
must obtain site plan approval prior to commencing any of the following activities on the
parcel:
a.
Obtaining a building or plumbing permit for the activities, or undertaking any
alteration or improvement of the site including grubbing or grading.
b.
The construction or placement of any new building or structure for a nonresidential
use, or the expansion or conversion of an existing building for a nonresidential use,
including accessory buildings and structures, if such buildings or structures have a
total area for all floors of four thousand (4,000) square feet or more.
c.
The conversion of an existing nonresidential use, in whole or in part, to another
nonresidential use if the new use changes the basic nature of the existing use such
that it increases the intensity of on- or off-site impacts of the use subject to the
standards and criteria of site plan review described in this ordinance.
d.
The modification or expansion of an existing residential structure that increases the
number of dwelling units in the structure by three (3) or more in any five (5) year
period. Pursuant to Maine law, such a project is also subject to subdivision review.
e.
The establishment of a new nonresidential use even if no buildings or structures are
proposed, including uses such as gravel pits, cemeteries, golf courses, and other
nonstructural nonresidential uses.
f.
The conversion of an existing non-residential building or structure, in whole or part,
into three (3) or more dwelling units within a five (5) year period.
g.
The construction or expansion of paved areas or other impervious surfaces,
including walkways, access drives, and parking lots involving an area of more than
two thousand five hundred (2,500) square feet within any three (3) year period.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 5 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
E.
Conflict with Other Laws
This Ordinance shall not repeal, annul, or in any way impair or remove the necessity of
compliance with any other rule, regulation, by-law, permit or provision of law. Where this
ordinance imposes a greater restriction upon the use of land buildings or structures, the
provisions of this ordinance shall control.
F.
Severability
Should any section or provision of this Ordinance be declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of this Ordinance.
G.
Effective Date
The effective date of this Ordinance or any amendments hereto is the date of its adoption at a
Town Meeting.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 6 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 2. Definitions
In this Ordinance certain terms or words shall be interpreted as follows:
- The word "person" includes a firm, association, organization partnership, trust company, or
corporation, as well as an individual;
- The present tense includes the future tense, the singular number includes the plural, and the
plural includes the singular;
- The word "shall" is mandatory, and the word "may" is permissive;
- The words "used" or "occupied' include the words "intended", "designed" or "arranged to
be used or occupied";
- The word "building", includes the word "structure", and the word "dwelling" includes the
word "residence";
- The word "lot" includes the words "plot" or "parcel".
In case of any difference of meaning or implication between the text of this Ordinance and any map
or illustration, the text shall control.
Terms not defined shall have the customary dictionary meaning.
In this Ordinance the following terms shall have the following meanings unless a contrary meaning is
required by the context or is specifically prescribed.
Abutting Lot: A lot which abuts, is contiguous to, or joins at a border or boundary, including lots
across a road, the lot(s) subject to the Site Plan Review requirement and any contiguous lots under
common ownership.
Accessory Structure or Use: A use or structure which is incidental and subordinate to the principal
use or structure. Accessory uses, when aggregated, shall not subordinate the principal use of the lot.
Aggrieved Party: An owner of land whose property is directly or indirectly affected by the granting
or denial of a permit or variance under this Ordinance; a person who owns an abutting lot to that lot
for which a Site Plan Review Permit or variance has been granted; or any other person who has
suffered particularized injury as a result of the granting or denial of such Site Plan Review Permit or
variance.
Agricultural Activities: The production, keeping or maintenance for sale or lease, of plants and/or
animals, including but not limited to forages and sod crops, grains and seed crops, dairy animals and
dairy products, poultry and poultry products, livestock, fruits and vegetables, and ornamentals and
greenhouse products. Agricultural activities do not include the processing of agricultural products
for market or consumption such as slaughterhouses, packing plants or canneries.
Aquaculture: The growing or propagation of harvestable freshwater, estuarine, or marine plant or
animal species.
Attic: That part of a structure immediately below and wholly or partly within the roof framing.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 7 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Automobile Graveyard: A yard, field, or other outdoor area used to store three (3) or more
unregistered or uninspected motor vehicles, as defined in Title 29-A, Section 101, Subsection 42, or
parts of the vehicles. "Automobile graveyard" includes an area used for automobile dismantling,
salvage, and recycling operations.
Basement: Any portion of a structure with a floor to ceiling height of six (6) feet or more and
having more than fifty per cent (50%) of its volume below the existing ground level.
Billboard: A sign, structure or surface larger than six (6) square feet which is available for
advertising purposes for goods or services rendered off the premises, excluding directional signs.
Building: A structure built for the support or shelter of persons, animals, goods or property of any
kind.
Campground: Any premises established for camping, including recreational vehicle parks, for
which a fee is charged.
Campsite: An area in a campground designed for use by a single recreational vehicle, tent, or
shelter.
Change of Use: The change from an existing use to another use, including without limitation, the
addition of a new use to an existing use. Example: Residential to Commercial
Change Order: Any addition, omission, substitution or alteration to construction or use described in
an approved site plan. Also called variations or variation orders.
Channel: A natural or artificial watercourse with definite bed and banks to confine and conduct
continuously or periodically flowing water. Channel flow is water flowing within the limits of the
defined channel.
Code Enforcement Officer (CEO): A person appointed by the Municipal Officers to administer and
enforce this Ordinance. Reference to the Code Enforcement Officer shall be construed to include
Building Inspector, Electrical Inspector, and the like where applicable.
Commercial: An activity the intent or result of which is to generate revenue from the buying and
selling of goods and/or services, exclusive of rental of single-family or duplex dwellings. This
definition includes non-profit organizations and activities.
Commercial Recreation Facility: Any commercial enterprise that provides recreational activities
including, but not limited to, racquet ball clubs, health clubs, amusement parks, and golf courses.
Commercial Use: The use of lands, buildings, or structures, other than a "home occupation,"
defined below, the intent and result of which activity is the production of income from the buying
and selling goods and/or services exclusive of rental of residential buildings and/or dwelling units.
Conforming Use: A use of building(s), structures, or land which complies with all applicable
provisions in this Ordinance.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 8 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Constructed: Includes built, erected, reconstructed moved upon or any physical operations on the
premises which are required for construction excavation fill, drainage, and the like, shall be
considered a part of construction.
Dimensional Requirements: Numerical standards relating to spatial relationships including but not
limited to setback, lot area, frontage and height.
Driveway: A vehicle access-way less than five hundred (500) feet in length serving two lots or less.
Duplex Dwelling: A detached or semi-detached building consisting of two (2) dwelling units.
Dwelling: A fixed structure, containing one or more dwelling units.
Dwelling Unit: A room or group of rooms designed and equipped exclusively for use as living
quarters for only one (1) family, including provisions for living, sleeping, cooking, and eating and, if
present, a home occupation.
Emergency Operations: Operations conducted for the public health, safety or general welfare, such
as protection of resources from immediate destruction or loss, law enforcement and operations to
rescue human beings, property and livestock from the threat of destruction or injury.
Essential Services: The construction, alteration or maintenance of gas, electrical or communication
facilities, steam, fuel, electric power or water transmission or distribution lines, towers and related
equipment; telephone cables or lines, poles and related equipment gas, oil, water, slurry, or other
similar pipelines; municipal sewage lines, collection or supply systems; and associated storage tanks.
Such systems may include towers, poles, wires, mains, drains, pipes, conduits, cables; fire alarms
and police call boxes, traffic signals, hydrants and similar accessories, but shall not include service
drops or buildings which are necessary for the furnishing of such services.
Excavation: Any removal of earth or material from its original position.
Expansion of a Structure: An increase in the floor area or volume of a structure, including all
extensions such as, but not limited to attached decks, garages, porches and greenhouses.
Expansion of Use: The addition of one or more weeks or months to a use's operating season;
additional hours of operation; or the use of more floor area or ground area devoted to a particular
use.
Extraction Operations: The movement of two hundred (200) cubic yards or more of soil, earth,
loam, gravel, naturally loose rock, and/or other mineral deposits in any one (1) year. The removal or
filling of material incidental to construction, alteration or repair of a building or in the grading and
landscaping incidental thereto and the removal of filling or transfer of material incidental to
construction alteration or repair of a public or private way or essential services are exempted.
Family: One or more persons occupying a premises and living as a single housekeeping unit as
distinguished from a group occupying a boarding house, lodging house, or hotel such unit shall not
exceed five (5) persons not related by blood or marriage.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 9 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Filling: Depositing or dumping any matter on or into, the ground or water.
Flood: A temporary rise in stream flow or tidal surge that results in water overtopping its banks and
inundating adjacent areas.
Flood Plain: The land adjacent to a water body which have been or may be covered by the regional
flood.
Floodway: The channel of a stream and those portions of the flood plain adjoining the channel that
are required to carry and discharge the flood water or flood flows of any river or stream.
Floor Area: The sum of the horizontal surface areas of a structure enclosed by exterior walls
(including the gross habitable portions of any attic or basement), plus the horizontal surface area of
any unenclosed portions of a structure such as porches and decks.
Footprint: The area enclosed by the outside perimeter of a structure at ground level.
Forest Management Activities: Timber cruising and other forest resource evaluation activities,
pesticide or fertilizer application, management planning activities, timber stand improvement,
pruning, regeneration of forest stands, and other similar or associated activities, exclusive of timber
harvesting and the construction creation or maintenance of roads.
Foundation: The supporting substructure of a building or other structure including but not limited
to basements, slabs, sifts, posts, or frost walls.
Height of a Structure: The vertical distance between the mean original grade at the downhill side of
the structure and the highest point of the structure, excluding chimneys, steeples, antennas, and
similar appurtenances which have no floor area. Cupolas, domes, widow's walks, and similar
features that are not inhabited, and are mounted on a building roof for observation and/or decorative
purposes are also excluded under the following conditions, all of which must apply:
1. The feature is on a legally existing conforming structure.
2. The feature does not extend beyond the exterior walls of the existing structure.
3. The feature has a floor area of fifty-three (53) square feet or less.
4. The feature does not increase the height of the existing structure by more than seven (7) feet.
High Intensity Soil Survey: A "high intensity soil survey" as defined by the Maine Association of
Professional Soil Scientists.
Home Occupation: An occupation or profession which is customarily conducted on or in a
residential structure or property and which is
1) clearly incidental to and compatible with the residential use of the property and
surrounding residential uses, and
2) which employs no more than two (2) persons other than family members residing in the
home.
Home occupation shall not include activities which do not necessitate permanent alteration and, to
structures on or about the premises.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 10 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Individual Private Campsite: An area of land which is not associated with a campground, but
which is developed for repeated camping by only one group not to exceed ten (10) individuals and
which involves site improvements which may include but not be limited to gravel pads, parking
areas, fire places, or tent platforms.
Industrial: The assembling, fabrication, finishing, manufacturing, packaging or processing of
goods, or the extraction of minerals.
Impervious Surface: Surfaces which do not absorb water, including, without limitation, all
buildings, parking areas, driveways, roads, sidewalks, and any areas of concrete or asphalt. In the
case of lumberyards, areas of stored lumber constitute impervious surfaces.
Loading Area: An off-street space or berth on the same lot with a building or contiguous to a group
of buildings for the temporary parking of a commercial vehicle while loading or unloading
merchandise or materials, and which abuts upon a street, alley, or other appropriate means of access.
Lot: A parcel of land undivided by any public road.
Lot Area: The area of land enclosed within the boundary lines of a lot, minus areas beneath roads
serving more than two lots.
Lot Coverage: The percentage of the plot or lot covered by all buildings.
Lot Line: A line bounding a lot that divides one lot from another, or from a public road
Lot Lines: The lines bounding a lot as defined below:
Front Lot Line: On an interior lot, the line separating the lot from the street. On a corner or
through lot, the line separating the lot from either street.
Rear Lot Line: The lot line opposite the front line. On a lot pointed at the rear, the rear lot
line shall be an imaginary line between the side lot lines, parallel to the front lot line, not less
than ten (10) feet long, lying farthest from the front lot line corner lot. The rear lot line shall
be opposite the front lot line of least dimensions.
Side Lot Line: Any lot line other than the front lot line or rear line.
Lot Interior: Any lot other than a corner lot.
Lot Width: The horizontal distance between the side lot lines, measured at the frontage setback line.
Lot of Record: A parcel of land, the dimensions of which are shown on a document or map on file
with the County Register of Deeds or in common use by the Town or County Officials.
Major Development: A project which has been classified as such under the provisions of Section
4.B. (or reclassified under Section 4.C.) of this Ordinance.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 11 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Methadone Clinic: A program or facility operated for the purpose of providing treatment for
persons with heroin or other opiate addictions, when treatment provided includes administration or
prescription of methadone or other opiate replacements for either detoxification or maintenance
purposes. For the purposes of this ordinance, the term "methadone clinic" includes but is not limited
to substance abuse treatment programs licensed by the State of Maine Department of Behavioral and
Developmental Services Office of Substance Abuse to provide opioid supervised withdrawal and
maintenance treatment services under 14-118 Code of Maine Regulations Section 4.16.
Mineral Exploration: Hand sampling, test boring, or other methods of determining the nature or
extent of mineral resources which, create minimal disturbance to the land and which include
reasonable measures to restore the land to its original condition.
Mineral Extraction: Any operation within any twelve (12) month period which removes more than
two hundred (200) cubic yards of soil, topsoil, loam, sand, gravel, clay, rock, peat, or other like
material from its natural location and to transport the product removed, away from the extraction
site.
Minor Development: All projects subject to this Ordinance not classified as a Major Development.
Mobile Home: A structure designed as a dwelling unit for location on permanent foundation, and
containing sleeping accommodations, a toilet, a tub or shower bath, and kitchen facilities, including
major appliances and furniture, with plumbing and electrical connections provided for attachment to
outside systems; and designed to be transported after fabrication on its own wheels. A mobile home
shall contain not less than four hundred fifty (450) square feet of gross floor area.
Mobile Home Park: A plot of land laid out to accommodate at least three (3) mobile homes.
Multi-Unit Residential: A residential structure containing three (3) or more residential dwelling
units.
Non-Conforming Building or Use: A building, structure, use of land, or portion thereof existing at
the effective date of adoption or amendment of this Ordinance which does not conform to all
applicable provisions of this Ordinance.
Non-Conforming Lot: A single lot of record which, at the effective date of adoption or amendment
of this Ordinance, does not meet the area, frontage, or width requirement of the district in which it is
located.
Non-Conforming Structure: A structure, which does not meet any one or more of the following
dimensional requirements: setback, height or lot coverage, but which is allowed solely because it
was in lawful existence at the time this Ordinance or subsequent amendments took effect.
Non-Conforming Use: Use of buildings, structures, premises, land or parts thereof which is not
permitted in the district in which it is situated, but which is allowed to remain solely because it was
in lawful existence at the time this Ordinance or subsequent amendments took effect.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 12 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Open Space Use: A use not involving: a structure; earth-moving activity or the removal or
destruction of vegetative cover; spawning grounds, or fish, aquatic, life, bird, and other wildlife
habitat.
"Open Space" carries a separate and different meaning under the Assessing Standards.
Owner: The person having the right of legal title to, beneficial interest in, or a contractual right to
purchase a lot.
Permitting Authority: The person (CEO) or entity (Planning Board) responsible for issuing a
particular permit or approval under this Ordinance.
Person: An individual, corporation, governmental agency, municipality, trust, estate, partnership,
association, two or more individuals having a joint or common interest, or other legal entity.
Planned Unit Development: Land under unified management, planned and developed as a whole
according to comprehensive and detailed plans, including streets, utilities, lots or building sites, site
plans and design principles for all buildings intended to be located, constructed, used and related to
each other, and for other uses and improvements on the land. Development may be a single
operation or a programmed series of provisions for operation and maintenance of such areas and
improvements and facilities necessary for common use by the occupants of the development.
Premises: One or more lots which are in the same ownership and are contiguous, separated only by
a road or water body including all buildings, structures, and improvements.
Principal Structure: A building other than one that is used for purposes wholly incidental or
accessory to the use of another building or use on the same premises. A deck or similar extension of
the principal structure or a garage attached to the principal structure by a roof or a common wall is
considered part of the principal structure.
Principal Use: A use other than one that is wholly incidental or accessory to another use on the
same premises.
Public Facility: Any facility, including, but not limited to, buildings, property, recreation areas, and
roads, which are owned, leased, or otherwise operated, or funded by a governmental body or public
entity.
Public Road: A road designated for public use; typically maintained by a governmental body such
as a town, county, state, or the Federal government.
Recreational Facility: A place designed and equipped for the conduct of sports, leisure time
activities, and other customary and usual recreational activities, excluding boat launching facilities.
Recreational Vehicle: A vehicle or vehicular attachment designed for temporary sleeping or living
quarters for one or more persons, including, without limitation, a pickup camper, travel trailer, tent
trailer, motor home, or converted van or truck.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 13 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Replacement System: A system intended to replace:
1) an existing system which is either malfunctioning or being upgraded with no significant
change of design flow or use of the structure or
2) any existing overboard wastewater discharge.
Residential Dwelling Unit: A room or group of rooms designed and equipped exclusively for use as
permanent seasonal or living quarters for only one family. The term shall include mobile homes but
not recreational vehicles.
Residential Solar Collector: A device, structure, or part of a device or structure that is designed and
used to transform solar energy into thermal, chemical, or electrical energy to meet the water heating,
space heating, space cooling, or electricity generation requirements of one residential dwelling, as
referenced in Maine Statute Title 33, Chapter 28-A, §1421, as may be amended.
Riprap: Rocks, irregularly shaped, and at least six (6) inches in diameter, used for erosion control
and soil stabilization, typically used on ground slopes of two (2) units horizontal to one (1) unit
vertical or less.
Road: A thoroughfare, way, or easement permanently constructed for or created by the repeated
passage of vehicles.
Service Drop: Any utility extension which does not cross or run beneath any portion of a water
body provided that:
1. In the case of electric service:
a.
the placement of wires and/or the installation of utility poles is located entirely upon
the premises of the customer requesting service or upon a roadway right-of-way; and
b.
the total length of the extension is less than one thousand (1000) feet.
2. In the case of telephone service:
a.
the extension, regardless of length, will be made by the installation of telephone wires
to existing utility poles, or
b.
the extension requiring the installation of new utility poles or placement underground
is less than one thousand (1,000) feet in length.
Setback: The minimum horizontal distance from a lot line to the nearest part of a structure.
Shoreline: As defined in the "Shoreland Zoning Ordinance for the Town of Franklin, Maine".
Shore Frontage: The horizontal distance, measured in a straight line, between the intersections of
the lot lines with the shoreline at the normal high-water line or the upland edge of a coastal wetland.
The terms "normal high-water line" and "coastal wetland" shall have the meanings set forth in 38
M.R.S.A. § 480-B.
Shoreland Area: All areas to which the Shoreland Zoning Ordinance for the Municipality of
Franklin is applicable.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 14 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Site Plan Approval: A decision by the permitting authority to approve a project as a result of Site
Plan Review.
Site Plan Review: The process of evaluating an application for a project under this Ordinance.
Site Plan Review Permit: A written order granting Site Plan Approval.
Signs: A name, identification, description, display, or illustration which is affixed to, painted, or
represented; directly or indirectly upon a building, structure, parcel, or lot and which relates to an
object, product, place, activity, person, institution, organization, or public business.
Single-Family Dwelling: A detached or semi-detached building consisting of one (1) dwelling unit.
Street: A public road.
Structure: Anything built for the support, shelter, or enclosure of persons, animals, goods, or
property of any kind, together with anything constructed or erected with a fixed location on or in the
ground, exclusive of fences, poles, signs, sidewalks, driveways, or parking lots. The term includes
structures temporarily or permanently located, such as tents, decks, raised walkways, handicapped
access ramps, external stairways, gazebos, and satellite dishes.
Subdivision: A subdivision is the division of a tract or parcel of land into three (3) or more lots
within any five (5) year period as defined in MRSA 30A, Section 4401, whether accomplished by
sale, lease, development, building, or otherwise, except when the division is accomplished by
inheritance, order of court or gift to a relative, unless the intent of such gifts is to avoid the
objectives of this section.
In determining whether a parcel of land is divided into three (3) or more lots, land retained by the
sub divider for his own use as a single family residence for a period of at least five (5) years shall not
be included.
No sale or lease of any lot or parcel shall be considered as being a part of subdivision if such a lot or
parcel is forty (40) acres or more in size, except where the intent of such sale or lease is to avoid the
objectives of this statute.
Substantial Start: Completion of thirty (30) percent of a permitted structure or use measured as a
percentage of estimated total cost.
Substantially Complete: the stage in the progress of construction or development of a structure or
use when all conditions of permit approval are in place and function as intended by the Planning
Board, and the structure or use can be legally occupied and/or operated for its declared purpose.
Timber Harvesting: The cutting and removal of trees from their growing site, and the attendant
operation of cutting and skidding machinery but not the construction or creation of roads. Timber
harvesting does not include the clearing of land for approved construction.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 15 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Variance: A relaxation of the terms of this Ordinance where such variance would not be contrary to
the public interest and where, owing to conditions peculiar to the property and not the result of the
actions of the applicant, a literal enforcement of the Ordinance would result in undue hardship. A
financial hardship shall not constitute grounds for granting a variance. The crucial points of variance
are undue hardship and unique circumstances applying to the property.
Vegetation: All live trees, shrubs, ground cover, and other plants.
Volume of a Structure: The volume of all portions of a structure enclosed by roof and fixed exterior
walls as measured from the exterior faces of these walls and roof.
Water Crossing: Any project extending from one bank to the opposite bank of a river or stream,
whether under, through, or over the water course. Such projects include but may not be limited to
roads, fords, bridges, culverts, water lines, sewer lines, and cable as well as maintenance work on
these crossings.
Yard: The area of land on a lot not occupied by the principal building.
Yard Front: The area of land between the front lot line and the nearest part of the principal
building.
Yard Rear: The area of land between the rear lot line and the nearest part of the principal building.
Yard Side: The area of land between the side lot line and nearest part of the principal building.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 16 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 3. Site Plan Review Required
A.
Permit Required
No person shall commence or undertake any land use activity within the Town of Franklin
without first obtaining a Site Plan Review Permit as indicated by the following Table of Land
Uses.
B.
Table of Land Uses
Land Use Activity
Site Plan
Review
Permit
Required?
1. One or two single-family dwellings which when completed are less than
three thousand five hundred (3,500) total square feet when including the
combined footprint of all structures on a single lot.
No
2. Duplex dwelling which when completed are less than three thousand five
hundred (3,500) total square feet when including the combined footprint of
all structures on a single lot.
No
3. Conversion of a single-family dwelling on a single lot to a duplex dwelling
without expanding the existing footprint.
No
4. Any structure or activity that is an accessory structure or use to items 1
through 3, above which when completed are less than three thousand five
hundred (3,500) total square feet when including the combined footprint of
all structures on a single lot.
No
5. Subdivisions subject to review under the Franklin Subdivision Ordinance.
No
6. All agricultural activities.
No
7. Forest management activities.
No
8. The construction of any new structure not otherwise exempted by this
table.
Yes
9. Any new commercial use of land not otherwise exempted by this table.
Yes
10. Any expansion of an existing commercial use that results in any of the
following:
a. lot coverage greater than fifty percent (50%);
b. total floor area of all floors and all structures on a lot combined that are
greater than four thousand (4,000) square feet in area; or
c. total impervious surfaces on the lot in excess of four thousand (4,000)
square feet or seventy five percent (75%) of lot area.
Yes
11. Any use that will result in substantial waste water discharge as described in
Section 4.B.1. of this Ordinance.
Yes
12. The interior expansion of any commercial use structure that increases the
floor area used for commercial purposes by fifty percent (50%) or more.
Yes
13. Any use that will result in substantial groundwater extraction as described
in Section 4.B.2. of this Ordinance.
Yes
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 17 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
C.
Permitting for Solar Energy Systems
1.
Ground mounted solar energy systems
a.
Ground mounted solar energy systems which exceed one (1) acre in area are
permitted through the Solar Facilities Ordinance of the Town of Franklin Maine.
b.
Ground-mounted solar energy systems between five thousand (5,000) square feet
and one (1) acre in area must comply with the dimensional requirements and buffer
requirements of the Solar Facilities Ordinance of the Town of Franklin Maine.
c.
Ground-mounted solar energy systems that exceed one (1) acre in system area for
which at least fifty percent (50%) of the energy generated is consumed by a
principal use on the same parcel of land must comply with the dimensional
requirements and buffer requirements of the Solar Facilities Ordinance of the Town
of Franklin Maine.
2.
Residential solar energy systems are permitted through the General Zoning Ordinance of
the Town of Franklin Maine or the Shorelands Zoning Ordinance for the Town of
Franklin Maine, as determined by the land use District the system will be sited in.
D.
Quarrying
Quarrying operations are permitted and licensed through the Quarry License Ordinance of the
Town of Franklin Maine.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 18 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 4. Application Procedures
The Planning Board shall use the following procedures in reviewing applications for site plan
review.
A.
Classification of Projects
Each project subject to Site Plan Review shall be classified by the CEO as a Major
Development or a Minor Development.
B.
Major Developments
Any project involving any of the following shall be classified by the CEO as a Major
Development. Any project initially classified as a Major Development may be reclassified as a
Minor Development upon a finding by the Planning Board that the project does not meet any
of the requirements for classification as a Major Development. After such reclassification all
further review shall be conducted by the CEO.
1.
Projects with substantial waste water discharge.
Projects that are not served by a public sewer, which will generate a daily average
discharge of more than two thousand (2,000) gallons of waste water, and which will meet
any one of the following three conditions:
a.
The project is located within three hundred (300) feet of a sand and gravel aquifer,
as shown on the relevant map of Significant Sand and Gravel Aquifers published by
Maine Geological Survey;
b.
Any part of the project is located in an area to which the Shoreland Zoning
Ordinance for the Town of Franklin is applicable; or
c.
Any part of the project is located in the watershed of the Franklin Water District.
2.
Projects with substantial groundwater extraction.
Projects extracting one thousand (1,000) gallons or more of groundwater per day.
3.
Projects involving hazardous materials, oil, or radioactive substances.
Hazardous activities involving the consumption, generation, or handling of:
a.
Hazardous wastes as defined in 38 M.R.S.A. § 1303-C;
b.
Hazardous matter as defined in 38 M.R.S.A. § 1317;
c.
Oil, as defined in 38 M.R.S.A. § 542; and
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 19 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
d.
Low-level radioactive wastes, as defined in 38 M.R.S.A. § 1451.
4.
Building footprint in excess of four thousand (4,000) square feet.
Any building or buildings on a single lot constructed or erected with a fixed location on
or in the ground or attached to something on or in the ground which occupies a footprint
in excess of four thousand (4,000) square feet.
5.
Impervious surfaces in excess of four thousand (4,000) square feet.
Any project in which total impervious surface(s) will occupy a ground area in excess of
four thousand (4,000) square feet.
6.
Conversion or Expansion of a Major Development
Any project which is a conversion or expansion of an existing project meeting the
description of a Major Development.
7.
CEO Determination of Potential Significant Impact
Any project which the CEO determines
a. M ay have significant impact to the physical, social, economic, or the
environmental welfare of the Town
b. Or has characteristics that make it reasonable and necessary to conduct a professional
review (as described in Section 5.E.) prior to considering the application for Site Plan
Approval.
C.
Minor Developments
A project not classified by the CEO as a Major Development shall be considered a Minor
Development under this Ordinance. Any project initially classified as a Minor Development
may be reclassified as a Major Development upon a finding by the CEO and/or the Franklin
Planning Board that the project meets the requirements for classification as a Major
Development. After reclassification, all further review shall be conducted by the Planning
Board.
D.
Submission Requirements
1.
Major and Minor Developments
All projects requiring Site Plan Review shall submit the information specified in Section
4.I. Major Developments meeting the criteria in Section 4.B.1. (Projects with substantial
waste water discharge) and Section 4.B.2. (Projects with substantial groundwater
extraction) shall submit additional information as provided in Section 4.J.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 20 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
2.
Waiver
The permitting authority may waive any of the submission requirements upon the written
request of an applicant for good cause shown. The permitting authority must state the
facts constituting good cause in writing. No waiver may be granted if it will unduly
restrict the review process. The permitting authority may condition such a waiver on the
applicant's compliance with alternative requirements. Good cause may include the
permitting authority's finding that particular submissions are inapplicable, unnecessary,
or inappropriate for a complete review. Notwithstanding the waiver of a submission
requirement, the permitting authority may, at any later point in the review process,
rescind such waiver if it appears that any submission requirement previously waived is
necessary for an adequate review. A request for submission previously waived shall not
affect the pending status of an application.
3.
Procedures
Applications for Site Plan Review shall be submitted on forms provided by the Town.
The complete application form, required fees, and the required plans and related
information shall be submitted to the CEO who shall examine the materials for
completeness of application and, for Major Developments, forward these materials to the
Planning Board.
E.
Major Development Application Submission and Review Procedures
The applicant must prepare and submit a site plan review application, including the
development plan and supporting documentation that meets the submission requirements set
forth below. This material must be submitted to the Code Enforcement Officer twenty-one
(21) days prior to meeting at which application will be considered.
1. At the time formal application is made, the Code Enforcement Officer shall give a dated
receipt to the applicant and the applicant shall notify by certified mail all owners of
property within five hundred (500) feet of any boundary of the parcel on which the
proposed development is located. Written notice of the pending application shall be
provided by the CEO to the Select Board, Fire Chief, and other interested parties.
2. Within forty-five (45) days of the receipt of a formal site plan review application, the
Planning Board shall review the material and determine whether or not the submission is
complete. If the application is determined to be incomplete, the Board shall notify the
applicant in writing of this finding, shall specify the additional materials required to make
the application complete and shall advise the applicant that the application will not be
considered by the Board until the additional information is submitted to the Board. These
steps, except the notification requirements, shall be repeated until the application is found
to be complete. Notifications on state of application completeness may be provided
verbally to the applicant and/or their representative at the regular meeting considering
said application.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 21 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
3. As soon as the Board determines that the application is complete, the Board shall:
a.
notify the applicant in writing of this finding, if not provided verbally
b.
meet the notification requirements of Subsection B.4. below, and
c.
place the item on the agenda for substantive review within forty-five (45) days of
this finding or at the next scheduled Planning Board meeting, whichever is later.
4.
Before taking action on any application, the Planning Board shall hold a public hearing.
The Board shall notify by certified mail, the owners of all property within five hundred
(500) feet of the property involved, at least ten (10) days in advance of the hearing, of the
nature of the application and of the time and place of the public hearing As soon as the
application is found to be complete, the Planning Board shall hold a public hearing on the
application within forty-five (45) days. The Planning Board shall notify the Code
Enforcement officer, Municipal Officers, and the Board of Appeals, at least twenty (20)
days in advance, of the time and place of the hearing. Notice of the hearing shall be
posted in the Town Office at least thirteen (13) days in advance of the public hearing.
The notice shall be published at least two (2) times in a newspaper that complies with
Title 1, Section 601 and that has a general circulation in the municipality. The date of the
first publication shall be at least twelve (12) days before the hearing, and the date of the
second publication must be at least seven (7) days before the hearing. The owners of
property shall be considered to be those against whom taxes are assessed. Failure of any
property owner to receive a notice of public hearing shall not necessitate another hearing
or invalidate any action by the Planning Board.
5.
After the first meeting at which the application is considered, the Planning Board may
hold an on-site inspection of the site to review the existing conditions, field verify the
information submitted and investigate the development proposal. The Board may decide
not to hold an on-site inspection when the site is snow covered or otherwise impassable
due to customary seasonable conditions. If an application is pending during a period
when there is snow cover or the site is impassable, the deadline by which the Planning
Board shall take final action on the application as specified in B.6. may be extended,
which extension shall not exceed forty (40) days after the Board is able to conduct an on-
site inspection. Written notice of the on-site inspection shall be provided to all parties
entitled to notice under Subsection B.1.
6.
The Planning Board shall take final action on said application within forty-five (45) days
of determining that the application is complete. The Board shall act to deny, to approve,
or to approve the application with conditions. The Board may impose such conditions as
are deemed advisable to assure compliance with the standards of approval.
In issuing its decision, the Planning Board shall make written findings of fact establishing
that the proposed development does or does not meet the standards of approval and other
requirements of the Town. The Board shall notify the applicant, all officials who
received notice under Subsection B.4., and all parties who requested to be notified of the
action of the Board, including the findings of fact, and any conditions of approval. This
requirement can be met through the distribution of minutes of the meeting containing the
findings of fact and decision of the Board.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 22 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
All time limits provided for in this section may be extended by mutual agreement of the
applicant and Planning Board.
F. Final Approval and Filing
Upon completion of the requirements of this Section and an approval vote by the majority of
the Planning Board, the application shall be deemed to have final approval and the site plan
shall be signed by a majority of the members of the Board and must be filed with the Code
Enforcement Officer.
G.
Fees
1.
Application Fee
An application for site plan review must be accompanied by an application fee of fifteen
hundred (1,500) dollars. This fee is intended to cover the cost of the Town of Franklin's
administrative processing of the application. The fee shall not be refundable.
This application fee must be paid to the Town of Franklin and evidence of payment of the
fee must be included with the application.
2.
Technical Review Fee
The Planning Board may require the applicant(s) or their authorized agent to deposit in
escrow with the Town an amount of money sufficient to cover the costs for any
professional review of the application that the Planning Board may feel is reasonably
necessary to protect the general welfare of the Town. This escrow payment shall be
made before the Planning Board engages any outside party to undertake this review and
to make recommendations to the Planning Board. Any part of the escrow payment in
excess of the final costs for the review shall be returned to the owner(s) or their agent.
3.
After-the-Fact Application Fee
The After-the-Fact Application fee shall be forty-five hundred (4,500) dollars. See
Section 7B, Violations.
4.
Site Plan Review Approval Extensions
Extensions of the Substantial Start and Substantial Completion time requirements (see
Section 5.G., Expirations of Approvals) may be requested from the Code Enforcement
Officer. The fee for extensions shall be fifty (50) percent of the original permit fee.
5.
Apportionment of Fees
Fees levied under this ordinance shall be apportioned ten (10) percent to the Code
Enforcement Officer and ninety (90) percent for administration.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 23 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
6.
Notification Costs
All costs of notifications per requirements of this section or any other section of this
Ordinance shall be borne by the Applicant.
H.
Public Hearing Procedures
Site Plan Review public hearings shall comply with the following procedures:
1.
Rules
Hearings shall be conducted according to rules adopted by the Planning Board.
2.
Representation
At any hearing a party may be represented by an authorized representative. Any person
acting as that party's authorized representative shall provide written evidence of such
authorization.
3.
Continuation
Any hearing may be continued or recessed to another time for good cause, or upon
written or recorded agreement of the permitting authority conducting the hearing and
the applicant.
I.
Requirements for All Applications
The following materials and items are required of all applications.
1.
Application Form
A fully executed and signed copy of the application form.
2.
Copies
a.
Applications for Minor Developments shall include three (3) copies of written
materials plus three (3) sets of maps or drawings containing the information listed
below.
b.
Applications for Major Developments shall include ten (10) copies of written
materials plus ten (10) sets of maps or drawings containing the information listed
below.
c.
All maps or drawings shall be at a scale sufficient to allow review of the items
listed under the criteria for approval.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 24 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
d.
All Applications must include one set of electronic documents (pdf).
3.
General Information
The following general information is required:
a.
Name, address and complete contact information of owner of record and the
facility operator's name and address if different;
b.
Applicant's name, address, and complete contact information if different.
c.
Authorized representative's name, address, written authorization and complete
contact information, if the applicant is so represented.
d.
The name of the proposed project;
e.
Names and addresses of all abutting lot owners with property within five-hundred
(500) feet of any boundary line of the proposed project lot(s), together with
certification by the applicant (on a form provided by the Town) that notice of the
applicant's intent to file the application has been provided to each abutting lot
owner by certified mail;
f.
Sketch map showing general location of the site within the Town;
g.
Location map showing the relationship of the proposed project to adjacent
properties and to the general surrounding area within three thousand (3,000) feet
of any property line of the site, and the location of any identified sand and gravel
aquifers within three hundred (300) feet of the project. The scale shall not be
smaller than 1" = 400'; reduced tax maps showing owner's names and other
required information may be acceptable;
h.
The tax map(s) and lot number(s) of the lot where the project is located and of
abutting lots;
i.
A copy of the current deed to the lot, option to purchase the lot or other
documentation to demonstrate right, title, or interest in the lot on the part of the
applicant; and
j.
The name(s), registration number(s), and seal(s) of the land surveyor, architect,
landscape architect, engineer, and/or similar professionals assisting with the
preparation of the plan.
4.
Site Information
The following information regarding the proposed project and existing conditions is
required. This information must accompany, or be submitted on, a map using the
following scale and showing the date of the map, magnetic north, the scale, and the
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 25 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
identity of the draftsman:
Acres
Scale
1 to 10
1" = 10' to 1" = 50'
10+ to 50
1" = 50' to 1" = 100'
50+ (lots <= 4 acres)
1" = 100'
50+ (lots > acres)
1" = 200'
a.
Zoning classification(s) of the lot and the location of zoning district boundaries if
the lot is wholly or partially located in a shoreland area.
b.
The bearings and distance of all lot lines of the lot on which the project is located
and the source of this information.
c.
Location and size of all existing and proposed wells, sewer, and water mains,
culverts, drains, above or below ground utilities, and waste water disposal systems
on the lot on which the project is located, and of any of these items that currently
serves or will serve the project from abutting lots or public roads.
d.
Location, names and widths of all existing and proposed roads and rights-of-way
adjacent to the proposed project.
e.
The location, dimensions, and ground floor elevations of all existing and proposed
buildings on the lot.
f.
The location and dimensions of all existing and proposed driveways, roads, parking,
and loading areas and walkways on the lot.
g.
The existing and proposed topography of the site at an appropriate contour interval
(not greater than five (5) feet) depending on the nature of the use and character of
the lot.
h.
Major natural features on the site and including, within two hundred fifty (250) feet
of the lot lines, wetlands, streams, ponds, floodplains, groundwater aquifers,
significant wildlife habitats including bird nesting, staging, and feeding areas and
deer yards, archaeological resources, or other important natural features.
i.
The direction and amount of pre-development and proposed surface water drainage
flow across and from the site, based upon 24-hour, 2-, 10- and 25-year storms.
Where proposed flows exceed pre-development flows by ten (10) percent or more,
the applicant shall submit a storm water management plan, showing the steps taken
to minimize the impact of storm water runoff. The storm water management plan
shall be based upon 24-hour, 2-, 10- and 25-year storms.
j.
The location and type of all existing and proposed exterior signs.
k.
A copy of such covenants or deed restrictions, if any, as are intended to cover all or
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 26 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
part of the lot. Such covenants or deed restrictions shall be referenced on the plan.
l.
The location of all existing and proposed building setbacks, yards, and buffers
required by this Ordinance.
m.
Elevation view of the building and signs, showing heights and materials.
n.
Landscaping plan showing the building(s), existing and proposed vegetation,
walkways, and exterior lighting. Drawings to be at the scale designated in Section
4.E.6.
o.
For any project that will dispose of its wastewater through any subsurface
wastewater system, a completed Maine Department of Health, and Human Services
(Maine DHHS) Health Engineering site evaluation and subsurface wastewater
disposal system application showing adequate soils, and adequate system design
and capacity.
p.
A schedule of construction, including anticipated beginning and completion dates,
and the estimated total cost of the project.
q.
The permitting authority may, at its discretion, require the applicant to provide a
visual impact assessment which may include photo simulations of the proposed
facility taken from perspectives determined by the permitting authority, or its
designee.
r.
Projects involving the storing, generating, or handling of hazardous wastes or
materials, oil or radioactive wastes shall specify the exact amount and nature of all
such substances that will be on the site, and the specific method of handling and
containing those substances that will be used.
s.
An erosion control and sedimentation control plan setting forth the measures to be
taken to comply with Section 6.C.1.
t.
The proposed location of any temporary or permanent exterior lighting, including
intensity in lumens, color temperature, type, size and direction.
u.
A noise management plan when the proposed use or activity will generate sustained
noise levels in excess of ten (10) dB, A-scale, greater than the pre-
construction/existing average background noise levels at the property boundaries.
5.
Approval Block
Space must be provided on the plan drawing for the signatures of the Planning Board and
date together with the following words, "Approved: Town of Franklin Planning Board".
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 27 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
6.
Waivers Sought By Applicant
A list of the submission requirements for which the applicant seeks a waiver under
Section 4.D.2., and a written explanation of the reasons that the waiver is sought.
J.
Additional Reports for Specific Project Types
1.
Projects with substantial waste water discharge (Section 4.B.1.) must submit a high
intensity soil survey and a hydrogeologic assessment, which shall include, at a minimum,
the following information:
a.
A map showing basic soil types on the lot.
b.
The depth of the water table at representative points throughout the lot.
c.
Drainage conditions throughout the lot.
d.
Data regarding the existing ground water quality, either from test wells on the lot or
from existing wells on the lot or on abutting lots.
e.
An analysis and evaluation of the impact of the project on ground water resources,
including a projection of nitrate-nitrogen concentrations associated with the project.
Projects within the watershed of a lake or pond shall include phosphate impact
calculations.
f.
The location of any existing or proposed subsurface wastewater disposal systems
and wells on the lot and within two hundred (200) feet of the lot lines.
g.
Projections of post-development water quality at any wells within the lot or within
five hundred (500) feet from the point of contamination, whichever is the shorter
distance. These projections shall be based upon a drought condition assumption of
sixty (60) percent of annual average recharge from precipitation.
h.
The signature and seal of the Certified Geologist who prepared the assessment.
The Planning Board may require additional information where necessary to evaluate the
project's compliance with this Ordinance.
2.
Projects with substantial groundwater extraction (Section 4.B.2.) shall submit a
groundwater extraction impact assessment which shall include, at a minimum, the
following information:
a.
A statement from the applicant specifying the quantity of ground water to be
extracted expressed as the annual total, the maximum monthly rate by calendar
month, and the maximum daily rate. These rates shall be maximum rates, which
rates shall not be exceeded without further Site Plan Approval by the Planning
Board.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 28 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
b.
For projects coming under the jurisdiction of the Maine DHHS, a letter from that
agency containing its review comments.
c.
A report prepared by a Certified Geologist showing:
i. A map of the aquifer tributary to the spring(s), well(s) or excavation(s) from
which the water is to be extracted. The map shall include sufficient detail to
support a calculation of sustained yield during a ten (10) year drought, as well
as an estimate of any potential interaction between or among this and adjacent
aquifers.
ii. Calculations based upon the investigation showing the aquifer characteristics,
the rates of draw-down and rebound, the sustainable yearly, monthly (by
calendar month) and daily extraction rates, the cone of depression that may
develop about the project and impacts upon the water table in the tributary
aquifer and other private or public wells within one thousand (1,000) feet of the
proposed extraction facilities.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 29 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 5. Site Plan Review Process
A.
Purpose
The purpose of Site Plan Review is to promote the public health, safety, and general welfare by
requiring CEO or Planning Board review of plans for certain uses or structures which have a
significant potential impact on the neighborhood or the environment and which, when properly
designed with respect to their surroundings, can become uses or structures that are compatible
with the neighborhood and environment.
B.
Prohibition
No activity or use requiring a Site Plan Review Permit shall commence until the applicant has
been granted the requisite Site Plan Approval from the applicable permitting authority and
complied with all other applicable provisions of this Ordinance.
C.
Review Procedures
The procedures for Site Plan Review are as follows:
1.
Submission of completed application to the CEO.
The applicant shall submit the requisite number of copies of the application and
supporting information required by this Ordinance, as described in Section 4.
2.
CEO Classification and Review
a.
Dated Receipt
The CEO shall issue the applicant a dated receipt and will date-stamp the
application.
b.
Classification
The CEO shall review the application and classify it as either a Major or Minor
Development in accordance with the provisions of this Ordinance.
c.
Fees Submitted
After classification, the applicant shall provide the CEO with the applicable review
fees.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 30 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
d.
Review for Completeness
The CEO shall initially review the application and determine whether or not it is
complete.
e.
Notice of Incomplete Application
If the application is found to be incomplete, the CEO shall, within ten (10) days,
notify the applicant in writing of the information needed to complete the
application. Upon the applicant's submission of such additional information, the
process above shall be repeated.
3.
Complete Applications
Upon finding an application to be complete, the CEO shall take the following action with
regard to that application.
a.
Minor Developments
Applications determined to be Minor Developments will be reviewed and acted
upon by the CEO in accordance with the procedures set forth below, and the other
requirements of this Ordinance.
b.
Major Developments forwarded to the Planning Board
The CEO shall forward copies of a complete application and supporting documents
determined to be Major Developments to the Chair of the Planning Board, who will
place the project on the agenda of the next regular Planning Board meeting
occurring not more than forty-five (45) days after the CEO determines the
application is complete.
c.
Notice of Public Hearing to Abutting Lot Owners
For any Major Development project, a public hearing will be held on the project,
and the Planning Board shall notify abutting lot owners of the date, time, and place
of such hearing by certified mail when the hearing date has been determined.
4.
Planning Board Review
For Major Developments, the Planning Board shall meet to review the project as follows.
The Planning Board shall:
a.
CEO Report
Hear any report of the CEO and, if the Town has retained the services of a
Professional adviser, the report of the adviser regarding the proposed project;
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 31 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
b.
Applicant's Response
Hear any comments of the applicant regarding the CEO and professional advisor
reports;
c.
Request for Waivers
Hear any requests from the applicant for waivers;
d.
Determination of Completeness
Determine whether or not the application is complete;
e.
Notice of Incompleteness
If the application is determined to be incomplete, the Planning Board shall inform
the applicant of the information required to make the application complete. Upon
the applicant's submission of such additional material, previous steps in Sections
5.C.2. through 4. shall be repeated; and
f.
Public Hearing Determination
If the application is determined to be complete, the Planning Board shall set the
matter for a public hearing conducted by the Planning Board. The public hearing
shall take place within forty-five (45) days of the Planning Board's determination
that the application is complete. This deadline may be extended by mutual
agreement of the Planning Board and the applicant, either in writing or orally, on
the record, at a public meeting.
5.
Deliberation and Decision
a.
Deliberation
Within forty-five (45) days after the public hearing on an application or, if no
hearing is held, within forty-five (45) days of a determination of completeness by
the CEO, the permitting authority shall decide the matter. For Major
Developments, the Planning Board shall deliberate the matter at a public meeting.
Site Plan Approval shall be granted if the proposed project complies with all
applicable criteria and minimum standards set forth in Section 6. This deadline
may be extended by mutual agreement of the permitting authority and the applicant
in writing, or (in the case of Major Developments) either in writing or orally, on the
record, at a public meeting.
b.
Decision
If the permitting authority finds that the proposed project complies with all criteria
and minimum standards of this Ordinance it shall issue an order granting Site Plan
Approval subject to such terms and conditions as the permitting authority finds are
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 32 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
reasonably necessary to ensure conformity with the criteria and minimum standards
of this Ordinance.
If the permitting authority finds that the proposed project does not comply with all
applicable review criteria and minimum standards, it shall issue an order denying
Site Plan Approval.
In either case the permitting authority shall, within thirty (30) days after the
completion of its deliberations, issue specific written findings of fact supporting its
decision. This period may be extended by mutual agreement of the applicant and
permitting authority.
The decision shall state any conditions of approval that apply to the project and the
reason for the imposition of those conditions. A copy of the decision shall be sent
to the applicant at the address provided on the application. Decisions by the CEO
shall also be sent to any abutting lot owner who responded, in writing, to the notice
sent by the CEO.
D.
Professional Review of Major Developments
1.
Additional Studies
The Planning Board may require the applicant to undertake any additional studies which
it deems reasonable and necessary to ensure that the requirements of the Ordinance are
met. The cost of all such studies shall be borne by the applicant.
2.
Independent Technical Review
The Planning Board may require that an independent consultant(s) review one (1) or
more submissions of an application. The independent consultant(s) shall report to the
Planning Board as to the project's compliance or non-compliance with the applicable
provisions of this Ordinance and recommend, if appropriate, those actions which will
result in compliance. Such consultants shall be fully qualified to provide the required
information in the State of Maine, and may include, but not be limited to:
An Attorney;
A Community Planner;
A Registered Professional Engineer;
A Registered Architect;
A Licensed Landscape Architect;
A Registered Geologist;
A Licensed Soil Scientist;
A Registered Land Surveyor;
or
Any other Registered/Licensed Professional or Independent Expert Witness deemed fully
qualified by the Planning Board.
The consultant(s) selected shall estimate the cost of such review and the applicant shall
deposit with the Town the full estimated cost to the extent it exceeds the amount paid as a
technical review fee.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 33 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
E.
Failure to Act
Failure of the permitting authority to act within any of the time requirements set forth herein
shall constitute a denial of the application.
F.
Appeals
When the Board of Appeals reviews a decision of the Code Enforcement Officer the Board of
Appeals shall hold a "de novo" hearing. At this time the Board may receive and consider new
evidence and testimony, be it oral or written. When acting in a "de novo" capacity the Board
of Appeals shall hear and decide the matter afresh, undertaking its own independent analysis of
evidence and the law, and reaching its own decision.
When the Board of Appeals hears a decision of the Planning Board, it shall hold an appellate
hearing, and may reverse the decision of the Planning Board only upon finding that the
decision was contrary to specific provisions of the Ordinance or contrary to the facts presented
to the Planning Board. The Board of Appeals may only review the record of the proceedings
before the Planning Board. The Board of Appeals shall not receive or consider any evidence
which was not presented to the Planning Board, but the Board of Appeals may receive and
consider written or oral arguments. If the Board of Appeals determines that the record of the
Planning Board proceedings is inadequate, the Board of Appeals may remand the matter to the
Planning Board for additional fact finding.
1.
Appeal Procedure
a.
Making an Appeal
(i)
An administrative or variance appeal may be taken to the Board of Appeals by
an aggrieved party from any decision of the Code Enforcement Officer or the
Planning Board, except for enforcement-related matters as described in
Section 7.B. Such an appeal shall be taken within thirty (30) days of the date
of the official, written decision appealed from, and not otherwise, except that
the Board, upon a showing of good cause, may waive the thirty (30) day
requirement.
(ii) Applications for appeals shall be made by filing with the Board of Appeals a
written notice of appeal which includes:
a.
A concise written statement indicating what relief is requested and why
the appeal or variance should be granted.
b.
A sketch drawn to scale showing lot lines, location of existing buildings
and structures and other physical features of the lot pertinent to the relief
sought.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 34 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
(iii) Upon receiving an application for an administrative appeal or a variance, the
Code Enforcement Officer or Planning Board, as appropriate, shall transmit to
the Board of Appeals all materials constituting the record of the decision
appealed from.
(iv) The Board of Appeals shall hold a public hearing on an administrative appeal
or a request for a variance within thirty (30) days of its receipt of a complete
written application, unless this time period is extended by the parties.
b.
Decision by Board of Appeals
(i)
A majority of the full voting membership of the Board shall constitute a
quorum for the purpose of deciding an appeal.
(ii) The person filing the appeal shall have the burden of proof.
(iii) The Board shall decide all administrative appeals and variance appeals within
thirty (30) days after the close of the hearing, and shall issue a written
decision on all appeals.
(iv) The Board of Appeals shall state the reasons and basis for its decision,
including a statement of the facts found and conclusions reached by the
Board. The Board shall cause written notice of its decision to be mailed or
hand-delivered to the applicant. Copies of written decisions of the Board of
Appeals shall be given to the Planning Board, Code Enforcement Officer, and
the municipal officers.
2.
Appeal to Superior Court
Except as provided by 30-A M.R.S.A. section 2691(3)(F), any aggrieved party who
participated as a party during the proceedings before the Board of Appeals may take an
appeal to Superior Court in accordance with State laws within forty-five (45) days from
the date of any decision of the Board of Appeals.
3.
Reconsideration
In accordance with 30-A M.R.S.A. Section 2691(3)(F), the Board of Appeals may
reconsider any decision within forty-five (45) days of its prior decision. A request to the
Board to reconsider a decision must be filed within ten (10) days of the decision that is
being reconsidered. A vote to reconsider and the action taken on that reconsideration
must occur and be completed within forty-five (45) days of the date of the vote on the
original decision. Reconsideration of a decision shall require a positive vote of the
majority of the Board members originally voting on the decision, and proper notification
to the landowner, petitioner, planning board, code enforcement officer, and other parties
of interest, including abutters and those who testified at the original hearing(s). The
Board may conduct additional hearings and receive additional evidence and testimony.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 35 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Appeal of a reconsidered decision to Superior Court must be made within fifteen (15)
days after the decision on reconsideration.
G.
Expiration of Approvals
1.
Unless specifically authorized by the permitting authority at the time Site Plan Approval
is granted, all Site Plan Approvals shall expire unless work on the project is substantially
commenced within twelve (12) months from the date Site Plan Approval is granted. If
work is not substantially completed within twenty-four (24) months from the date Site
Plan Approval is granted, approval shall expire.
2.
Site Plan Approval extensions may be granted prior to expirations for commencement of
the work or change, or for substantial completion.
3.
Once Site Plan Approval or approval extensions have expired, a new application and Site
Plan Approval shall be required prior to the commencement of any project activity or use.
H.
Other Permits
The granting of Site Plan Approval does not relieve the applicant from the need to obtain any
other permits or approvals required prior to the commencement of any activity or use. Such
other required permits or approvals may include, but are not limited to, building and plumbing
permits, permits required under other ordinances of the Town of Franklin, licenses granted
pursuant to 38 M.R.S.A., § 1022, Maine Department of Environmental Protection and United
States Army Corps of Engineers' approvals, subsurface wastewater disposal permits, sewer
connection permits, and Maine Department of Transportation approvals. The fact that the
applicant may have obtained or may have been granted such permits or approvals prior to Site
Plan Review may be considered by the Planning Board as evidence as to the project's
compliance with applicable review standards, but shall not be deemed conclusive evidence as
to compliance. The written order granting Site Plan Approval constitutes the Site Plan Review
Permit for the project.
I.
Access to Site and Records
The CEO shall have reasonable access to the site at all times to review the progress of the work
and shall have the authority to review all records and documents related to the project. The
applicant, by accepting Site Plan Approval, waives any objection to the CEO having access to
the site to review the progress of the work or to review all records and documents related to the
project.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 36 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 6. Site Plan Review Criteria
The permitting authority, in reviewing projects requiring Site Plan Approval under this Ordinance,
shall make positive written conclusions and factual findings as to whether the applicant has
submitted adequate evidence showing that the following criteria have been met.
In addition, the minimum standards listed in this Section shall govern all permits and approvals
issued under this Ordinance. In reviewing applications submitted pursuant to this Ordinance, the
permitting authority shall consider these minimum standards prior to issuing final approval. In all
instances, the burden of proof shall be upon the applicant.
A.
Parking and Loading
PARKING AREA GEOMETRICS
A = Stall angle, B = Stall width, C = Stall length, D = Aisle width (1-way/2-way)
A
B
C
D
0°
9.0'
22.0'
12.0/20.0' Min.
45°
9.0'
18.0'
12.0/19.0'
60°
9.0'
18.0'
15.0/20.0'
75°
9.5'
19.0'
20.0/21.0'
90°
10.0'
20.0'
(N/A)/24.0'
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 37 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Off-street parking must conform to the following standards:
1.
Parking areas with more than two (2) parking spaces must be arranged so that it is not
necessary for vehicles to back into the street.
2.
All parking spaces, access drives, and impervious surfaces must be located at least five
(5) feet from any side or rear lot line, except where standards for buffer yards require a
greater distance. No parking spaces or asphalt type surface shall be located within five
(5) feet of the front property line. Parking lots on adjoining lots may be connected by
access-ways not exceeding twenty-four (24) feet in width.
3.
Parking stalls and aisle layout must conform to the following standards: ten (10) feet
wide by twenty (20) feet long.
4.
In lots utilizing diagonal parking, the direction of proper traffic flow must be indicated by
signs, pavement markings or other permanent indications and maintained as necessary.
5.
Parking areas for nonresidential uses must be designed to permit each motor vehicle to
proceed to and from the parking space provided for it without requiring the moving of
any other motor vehicles. Double stack parking may be permitted for resident parking in
conjunction with residential uses if both spaces in the stack are assigned to the occupants
of the same dwelling unit.
6.
Provisions must be made to restrict the "overhang" of parked vehicles when it might
restrict traffic flow on adjacent through roads, restrict pedestrian or bicycle movement on
adjacent walkways, or damage landscape materials.
7.
Off Street Parking and Loading:
a.
No structure shall be erected nor shall any of the following uses be established
unless at least the minimum number of off-street parking spaces as provided below
is provided. Off-street parking, either by means of open-air spaces or by garage
space, in addition to being a permitted use, shall be considered as an accessory use
when required or provided to serve conforming uses located in any District.
b.
The following minimum off-street parking requirements shall be provided and
maintained in case of new construction, alterations and changes of use or as deemed
appropriate by the Planning Board:
[1]
Residential - Two (2) parking spaces for each dwelling unit
[2]
Home Occupation - Minimum of two (2) additional spaces beyond two (2)
spaces required for each dwelling unit
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 38 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
c.
Transient Accommodations:
[1]
Bed and Breakfast accommodations, motels, hotels, boarding houses, and
inns with ten (10) rooms or less - Two (2) parking spaces plus one space for
each guest room.
[2]
Motels, hotels, boarding houses, and inns with more than ten (10) rooms -
One (1) parking space for each guest plus one (1) for each three (3)
employees.
d.
Schools: Five (5) parking spaces for each classroom plus one (1) for each four (4)
employees.
e.
Hospitals, Nursing Homes (bed facilities only): One (1) parking space for every
three (3) beds, plus one (1) for each employee based on the expected average
employee occupancy.
f.
Funeral Parlors: Twenty (20) spaces or as determined by the Planning Board.
g.
Theaters, Churches, and Other Public Assembly Places: One (1) parking space
for every four (4) seats or for every one hundred (100) square feet or major fraction
thereof of assemblage space if no fixed seats.
h.
Retail Stores and Businesses: One (1) space for every two hundred (200) square
feet of retail area, plus one for every two employees.
i.
Automotive Repair and Service Stations: One (1) space for each regular
employee plus one (1) space for each fifty (50) square feet of floor area.
j.
Roadside Farm Stand: Four (4) spaces.
k.
Restaurants, Eating and Drinking Establishments: One (1) parking space for
every four (4) seats, plus one (1) for every two (2) employees.
l.
Drive-In Restaurants and Dairy Stands: Ten (10) spaces plus one additional
space for each person serving or preparing food.
m.
Professional Offices and Public Buildings: One (1) parking space for every two
hundred (200) square feet of working space.
n.
Other Commercial Recreation Establishments (mini-golf courses, etc.): The
number of spaces deemed appropriate by the Planning Board.
o.
Industrial: One (1) parking space for each one and one half (1.5) employees,
based on the highest expected average employee occupancy, plus employee, visitor,
and customer parking to meet the needs of specific operations.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 39 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
p.
Maritime Activities - Commercial and Recreational: One (1) per every slip and
or mooring and one (1) per every two employees
q.
For uses not specifically listed in this section, the Code Enforcement Officer shall
prescribe the number which in no case will be less than an adequate number for
employees and customers and visitors anticipated on the site.
r.
Location On Other Property: If the required automobile parking spaces cannot
be provided on the same lot where the principal use is conducted, the Planning
Board can permit that such spaces may be provided on other off-street property
provided that such property lies within one thousand (1,000) feet of the main
entrance to such principal use. Such automobile parking space shall be associated
with the principal use and shall not thereafter be reduced or encroached upon in any
manner, provided however, that it may serve different principal uses at different
times of day.
s.
If the applicant demonstrates to the Planning Board that the proposed project, which
is outside the shoreland zone, will not have an adverse impact on parking
congestion in the area, the Board may waive the parking standards.
B.
Traffic Movement, Congestion and Safety
Criterion: Adequate provision has been made for traffic movement of all types, including
pedestrian, into, out of and within the proposed project and any traffic increase attributable to
the project will not result in unreasonable congestion or unsafe conditions on a road in the
vicinity of the project. The permitting authority shall consider traffic movement both on-site
and off-site in making its determination under this criterion.
Minimum Standards:
1.
Vehicular Circulation
The layout of the site shall provide for the safe movement of passenger, service, and
emergency vehicles through the site.
a.
Clear routes of access shall be provided and maintained for emergency vehicles to
all portions of the site and shall be posted with appropriate language.
b.
The layout and design of access ways and parking areas shall provide for safe and
convenient circulation of vehicles, including delivery vehicles, and prevent their
backing out onto a street.
c.
All roads shall be designed to harmonize with the topographic and natural features of
the site. The road network shall provide for vehicular and pedestrian safety, all season
emergency access, snow storage, and delivery and collection services.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 40 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
2.
Pedestrian Circulation
The site plan must provide for a system of pedestrian ways within the development
appropriate to the type and scale of development. This system must connect the major
building entrances/exits with parking areas and with existing sidewalks, if they exist or
are planned in the vicinity of the project. The pedestrian network may be located either
in the street right-of-way or outside of the right-of-way in open space or recreation areas.
The system must be designed to link the project with residential, recreational, and
commercial facilities, schools, bus stops, and existing sidewalks in the neighborhood or,
when appropriate, to connect with amenities such as parks or open space on or adjacent to
the site.
C.
Soil Types, Erosion, Contamination, Drainage, etc.
Criterion: The project will be built on soil types which are suitable to the nature of the project
and adequate provision has been made to avoid erosion, contamination of ground or surface
waters, interference with adjacent land, over-burdening of natural or artificial drainage systems
and/or any other adverse effects of inadequate drainage.
Minimum Standards:
1.
Conservation, erosion, and sediment control.
a.
The procedures outlined in the erosion and sedimentation control plan prepared and
submitted by the applicant shall be implemented during the site preparation,
construction, and cleanup stages.
b.
Erosion of soil and sedimentation of watercourses and water bodies shall be
minimized by employing the Maine Erosion and Sediment Control Best
Management Practices (BMPs). To the extent the applicant cannot employ all of
the BMPs, the application shall identify all BMPs from which relief is sought,
together with the reason the BMP cannot be employed and any alternative measures
proposed by the applicant. The permitting authority will determine whether to
waive full compliance with the BMPs as part of its Site Plan Review.
c.
In addition:
i.
The project shall preserve outstanding natural features, keep cut-fill operations
to a minimum and ensure conformity with topography so as to create the least
erosion potential and adequately handle the volume and velocity of surface
water runoff;
ii.
Whenever feasible, natural vegetation shall be retained, protected, and
supplemented;
iii.
The disturbed area and the duration of exposure shall be kept to a practical
minimum;
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 41 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
iv.
Permanent (final) vegetation and mechanical erosion control measures shall
be installed as soon as practicable;
v.
The top of a cut or the bottom of a fill section shall not be closer than ten (10)
feet to an abutting lot, unless specifically permitted by the permitting
authority.
vi.
Extraction operations* shall not be permitted within fifty (50) feet of property
lines and private roads and within one hundred (100) of public roads, unless
specifically permitted by the permitting authority and upon the prior written
agreement of the owner of such abutting lot or road. Whenever sedimentation
is caused by stripping vegetation, re-grading, or other development, it shall be
the responsibility of the applicant to remove it from all adjoining surfaces,
drainage systems and watercourses and to repair any damage at their expense
as quickly as possible; and
vii. Maintenance of drainage facilities or watercourses originating completely on
private property is the responsibility of the applicant to the point of open
discharge at the lot line or at a communal watercourse on the lot.
* See Definitions, Section 2. Extraction operations do not include quarries,
which are permitted and licensed under the Quarry License Ordinance of the
Town of Franklin Maine.
2.
Stormwater Management
Criterion: Adequate provision has been made for management of stormwater flows
within the project property and for flows which could extend beyond the project property
lines.
All stormwater management systems required by this Ordinance shall be designed
consistent with the following documents, as applicable:
a. M.R.S.A. 38 § 420-C and 420-D;
b.
The most recent version of the Maine Department of Environmental
Protection Stormwater Management Rules (Chapters 500 and 502) and with
the following volumes:
i.
Volumes I: Stormwater Management Manual
ii.
Volume II: Phosphorus Control in Lake Watershed: A Technical
Guide to Evaluating Development; and
iii.
Volume III: BMPs Technical Design Manual.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 42 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
3.
Groundwater Protection
a.
The quantity of water to be taken from groundwater shall not substantially lower the
water table, cause salt water intrusion into any existing well, cause unreasonable
changes in groundwater flow, or unreasonable ground subsidence, based upon ten
(10)- year drought water levels.
b.
The project shall not cause pollution or unreasonable diminution of the aquifer from
which it is extracted.
c.
Any project located in a defined public water supply aquifer recharge area shall not
have an unreasonable adverse effect upon that public water supply.
d.
Any pollutant introduced into soil on the site shall not exceed a concentration in the
ground water that is greater than the guideline established for it in the Maine CDC
Maximum Exposure Guidelines (MEGs) for Drinking Water. Any violation of this
standard shall be cause to order the immediate cessation of the use or activity
responsible for the contamination.
e.
The project shall not increase any contaminant concentration in ground water to
more than one-half of the Primary Drinking Water Standards, nor more than the
Secondary Drinking Water Standards (however, where existing ground water
pollution already exceeds the Secondary Drinking Water Standards, the project
shall not cause the concentration of the parameters in question to exceed one
hundred fifty percent (150%) of the ambient concentration).
f.
All projects shall be designed to minimize any increase in storm water runoff from
the site from the natural predevelopment conditions. Storm water runoff systems
should be designed to facilitate aquifer recharge where it is advantageous to
compensate for groundwater withdrawals and infiltration, but should avoid recharge
where the groundwater effects may be harmful.
g.
Where possible, existing natural runoff control features such as berms, swales,
terraces, and wooded areas shall be retained in order to reduce runoff. The use of
enclosed components (such as pipes, etc.) should be minimized where natural
systems are able to accommodate runoff.
h.
Design of permanent runoff storage facilities should consider safety, appearances,
recreational use, and the cost and effectiveness of maintenance operations in
addition to the primary storage function.
i.
Energy dissipaters and other forms of outfall protection shall be employed where
enclosed drains discharge into soils subject to erosion.
j.
Storm water management systems shall be maintained as necessary to ensure that
they function properly.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 43 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
k.
If the project will result an increased total flow of runoff that will be discharged into
municipal stormwater systems, the applicant shall pay for the cost of improvements
to the municipal system so that it will have the capacity to handle one hundred
twenty five percent (125%) of the projected total flow. Payment shall be made
within thirty (30) days of the date Site Plan Approval is granted. No construction
may commence on the project before this payment is made.
D.
Outdoor Displays and Storage Areas
Criterion: Adequate provision has been made to locate and design proposed outdoor display
and/or storage areas so as to avoid any safety hazard to vehicular and pedestrian traffic on and
off the site.
E.
Hazards and Nuisances
Criterion: Adequate provision has been made to avoid any hazard to travel on public or private
ways, or any glare or other nuisance to the use of adjoining public or private property.
Minimum Standards:
1.
Emissions
a.
Emissions of dust, dirt, fly ash, fumes, vapors, or gases which pose an unreasonable
risk of harm to human health or the environment shall be prohibited.
b.
No land use activity shall be permitted to produce unreasonable, offensive, or
harmful odors perceptible beyond the lot lines, measured either at ground or
habitable elevations.
2.
Lighting
a.
No land use activity shall be permitted to produce unreasonable glare or brightness
beyond the lot lines.
b.
Lighting fixtures shall be shielded or hooded so that the lighting elements are not
exposed to normal view of motorists, pedestrians, or buildings on abutting lots.
c.
Direct or indirect illumination shall not exceed 0.5 foot-candles upon residences on
abutting lots.
d.
All exterior lighting shall be designed to ensure safe movement of people and
vehicles, and to minimize adverse impact on abutting lots and public roads. Adverse
impact is to be judged in terms of hours of use, hazards to people and vehicular
traffic and potential damage to the value of abutting lots. Lighting shall be arranged
to minimize glare and reflection on abutting lots and the traveling public.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 44 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
3.
Hazardous Materials
a.
No highly flammable or explosive liquids, solids or gases shall be stored in bulk
above ground, unless they are stored in compliance with the requirements of the
rules and regulations adopted by the State of Maine.
b.
All storage of petroleum or liquid petroleum products shall be in conformance with
the provisions to 38 M.R.S.A. §§ 541-560 which, among other things, establishes a
ten-year compliance schedule for the discontinuance and removal of non-
conforming underground storage facilities and requires qualified personnel to
oversee the removal of certain underground facilities.
c.
Oil and chemical storage shall be in conformance with rules and regulations
adopted by the State of Maine applicable to the stored substance.
4.
Burden of Proof
The applicant shall have the burden of proof to assure the Planning Board or CEO that all
provisions of the above statutes have been met before Site Plan Approval may be granted.
F.
Buffers, Screening, Landscaping, Natural Features
Criterion: Adequate provision has been made with regard to buffers, screening, landscaping
and the preservation and enhancement of significant natural features.
G.
Avoidance of Adverse Effects, Generally
Criterion: Adequate provision has been made to avoid unreasonable adverse effects on the
scenic or natural beauty of the area or the community in general, including scenic areas
designated in the most recent Comprehensive Plan adopted by the Town, historic sites,
archaeological resources, rare and irreplaceable natural areas, wildlife habitats including
identified deer wintering areas, existing uses, air quality, water quality, or other natural
resources within the Town or in neighboring towns.
Minimum Standards:
1.
Any proposed land use activity that may disturb an archaeological site as determined by
the Maine Historic Preservation Commission, or historic site which is listed on or eligible
to be listed on the National Register of Historic Places, shall require the applicant to
submit comments in writing from the Maine Historic Preservation Commission
concerning the proposed project. These comments shall be considered by the permitting
authority in deciding whether to grant the permit.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 45 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
H.
Avoidance of Adverse Effects on Nearby Properties
Criterion: Adequate provision has been made to prevent any undue adverse effect upon
abutting or nearby lots.
Minimum Standards:
1.
Wastewater Disposal
The development must be provided with a method of disposing of sewage which is in
compliance with the State Plumbing Code
a.
When two (2) or more lots or buildings in different ownership share the use of a
common subsurface disposal system, the system must be owned and maintained in
common by an owners' association. Covenants in the deeds for each lot must
require mandatory membership in the association and provide for adequate funding
of the association to assure proper maintenance of the system.
2.
Water Supply
The development must be provided with a system of water supply that provides each use
with an adequate supply of water.
a.
If the project is to be served by a public water supply, the applicant must secure and
submit a written statement from the supplier that the proposed water supply system
conforms with its design and construction standards, will not result in an undue
burden on the source or distribution system, and will be installed in a manner
adequate to provide needed domestic and fire protection flows.
b.
Where groundwater pollution exceeds the Primary Drinking Water Standards and
the project is to be served by on-site ground water supplies, the applicant shall
provide adequate evidence of the manner in which the water quality will be
adequately improved or treated.
c.
For Major Developments over one thousand (1000) feet by road beyond a
municipal pressurized fire hydrant, the applicant shall construct ponds and/or dry
hydrants to provide for adequate water storage for firefighting purposes. An
easement shall be granted to the Town granting access to the dry hydrants where
necessary. The Planning Board may waive the requirement for dry hydrants or
ponds only with the written concurrence of the Franklin Fire Chief.
3.
Utilities
a.
The development must be provided with electrical, telephone and
telecommunication service adequate to meet the anticipated use of the project. If
the service in the street or on adjoining lots is underground, the new service must be
placed underground.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 46 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
4.
Natural Features
a.
Unless an acceptable landscaping plan is presented and approved by the Planning
Board, the landscape must be preserved in its natural state insofar as practical by
minimizing tree removal, disturbance, and compaction of soil, and by retaining
existing vegetation insofar as practical during construction. Extensive grading and
filling must be avoided as far as possible.
5.
Lot Line Setback
a.
Except as provided in Section 6.H.5.c. below, all structures must be set back at least
ten (10) feet from all lot lines and must be set back at least seventy-five (75) feet
from the centerline of any public road and at least fifty (50) feet from the edge of
the traveled way of any private road.
b.
Original non-conforming structures are not subject to the setback requirements
above; however, replacements or significant repairs to such structures shall be subject
to such requirements except as provided in Section 6.H.3.c. below.
c.
In the event a non-conforming structure is removed, damaged, or destroyed, such
structure may be repaired or replaced, subject to the following provisions:
i.
Any such reconstruction or replacement may not increase the footprint of the
previous structure within the setback area. Furthermore, reconstructed or
replaced buildings may not be sited within the footprint of a previous non-
building structure.
ii.
A permit for the project must be obtained within eighteen (18) months of the
date of the damage, destruction, or removal of the non-conforming structure.
iii.
The provisions of Section 6.A. and Section 6.B. will only apply to the same
extent that they applied to the non-conforming structure and its commercial
use.
iv.
An existing commercial use of a non-conforming structure may be changed to
another commercial use provided that the proposed use has no greater adverse
impact on the subject and adjacent properties and resources than the former
use as determined by the permitting authority.
v.
A permit for the repair or replacement of a non-conforming structure shall
only be granted in the event no reasonable alternative is available. The
historic appearance and context of the non-conforming structure shall be a
factor in making the determination of reasonableness.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 47 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
I.
Municipal Services
Criterion: Adequate provision has been made to avoid any undue burden on municipal
services including, but not limited to, water, fire, public road maintenance, solid waste
disposal, and police services.
J.
Provision for Proper Operation
Criterion: Adequate provision has been made to assure the proper operation of the proposed
business(es) or activity(ies) on the site through the provision of adequate and appropriate safety
measures, utilities, drainage, water supply, sewage disposal, solid waste disposal, access,
parking and loading, and other necessary site improvements.
Minimum Standards:
1.
For Major Developments, the project owner and operator of record shall have adequate
technical and financial capacity to construct, operate, and decommission, as needed, the
proposed development or land use activities on the site.
K.
Campgrounds
Criterion: Campgrounds shall meet the following requirements, in addition to the other
requirements of this Ordinance.
Minimum Requirements:
1.
Campsites and all structures shall be located at least one hundred (100) feet from any lot
line.
2.
Campsites shall be laid out and screened in such a manner that they are not visible from
abutting public roads, residences, or approved subdivision lots.
3.
Site density shall not exceed twenty (20) tent sites or sixteen (16) recreational vehicle
sites per acre (excluding circulation roads).
4.
Campsites located in a shoreland area, shall have a minimum shore frontage of seventy-
five (75) feet.
5.
A minimum of two hundred (200) square feet of off-street parking plus maneuvering
space shall be provided for each recreational vehicle, tent, or shelter site.
6.
There shall be a minimum of twenty-five (25) feet between recreational vehicles.
7.
There shall be a minimum of seventy-five (75) feet between recreational vehicles and tent
sites.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 48 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
8.
Each recreational vehicle, tent site or covered shelter site shall include at least one picnic
table per site, and at least one (1) covered trash receptacle for every three (3) sites. Trash
receptacles shall be emptied at least once per day.
9.
There shall be one toilet and lavatory for each five (5) campsites. Water and sewage
systems shall conform to state regulation.
10. Each campsite shall be equipped with a masonry or metal fireplace, the construction of
which is approved by the Franklin Fire Chief.
L.
Signs
Criterion: Adequate provision has been made to ensure that any signs associated with the
project do not create a safety hazard.
Minimum standards:
1. Signs may be illuminated only by shielded, non-flashing lights.
M. Site Conditions
Criterion: Adequate provision has been made to ensure that, during construction, the site and
surrounding area is safe.
Minimum standards:
1.
During construction, the site shall be maintained and left each day in a safe and sanitary
manner, and any condition that could lead to personal injury or property damage, shall be
immediately corrected by the applicant upon an order by the CEO or other authorized
person. The applicant shall make provision for disposal of oil and grease from
equipment, and the site area should be regularly treated to control dust from construction
activity; and
2.
Developed areas shall be cleared of all stumps, litter, rubbish, brush, weeds, dead and
dying trees, roots, and debris. Excess or scrap building materials shall be removed or
destroyed immediately upon the request of and to the satisfaction of the CEO.
N.
Ordinance Conformity
Criterion: Adequate provision has been made to assure that the proposed project conforms in
all respects with the provisions of this Ordinance.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 49 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
O.
Permissible Solar Farms
Criterion: Permissible solar farms shall meet the requirements of the Solar Facilities
Ordinance of the Town of Franklin Maine.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 50 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 7
Enforcement
A.
Enforcement Authority
The CEO is authorized to enforce the provisions of this Ordinance, and to take legal action for
enforcement at the direction of the Municipal Officers of the Town.
B.
Violations
1.
Any person who undertakes any land use activity listed in Section 3 as requiring a Site
Plan Review Permit, without first obtaining such permit, violates this Ordinance. Each
day that such use continues shall constitute a separate violation of this Ordinance.
2.
Any person who has been notified by the Code Enforcement Officer they are in violation
of Section 7.B.1. may apply for an After-the-Fact Site Plan Review Permit. All other
requirements of this Ordinance shall apply.
3.
Any person who, having received a Site Plan Review Permit, thereafter conducts the land
use activity in such a manner contrary to any condition set forth in the Site Plan Review
Permit, or to the provisions of this Ordinance, violates this Ordinance. Each day that
such use continues shall constitute a separate violation of this Ordinance.
4.
Every violation of this Ordinance may be prosecuted pursuant to 30-A M.R.S.A. § 4452.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 51 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 8. Post Approval Activities
A.
Limitation of Approval
1.
Construction must be substantially commenced within twelve (12) months of date of
approval.
2.
Construction must be substantially complete and the project must be operational within
twenty-four (24) months of date of approval.
3.
The applicant may apply for twelve (12) month extensions of either substantial
commencement or substantial completion/commencement of operation dates. Such
extensions will be reviewed and approved or denied by the Planning Board. Conditions
under the Ordinance in place under which the original approval was granted will apply
for the duration of the extension periods.
B.
Incorporation of Approved Plan
One copy of the approved site plan must be included with the application for the building
permit for the project and all construction activities must conform to the approved plan,
including any conditions of approval and minor changes approved by the Code Enforcement
Officer to address field conditions.
C.
The Approved Plan shall be filed in the Town Office.
D.
Improvement Guarantees
1.
Application
a.
Improvement Guarantee
Improvement guarantees may be required for all offsite improvements required by
this Ordinance, when the Planning Board finds that the scale of the improvements
warrants guarantees. The Planning Board may require the posting of an
improvement guarantee in such amount and form as specified in Subsection D.2
below as is reasonably necessary to ensure the proper installation of all off-site
improvements required as conditions of approval. The nature and duration of the
guarantee shall be structured to achieve this goal without adding unnecessary costs
to the applicant.
b.
Upon substantial completion of all required improvements, the applicant must
notify the Planning Board of the completion or substantial completion of
improvements, and must send a copy of such notice to the appropriate Municipal
Officials. The respective Municipal Officials shall inspect all improvements and
must file a report indicating either approval, or rejection of such improvements with
a statement of reasons for any rejection. At the discretion of the respective
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 52 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Municipal Officials, inspection of improvements may require the services of
professional reviewers as listed in Section 5.D.2. of this Ordinance. The cost of all
such services shall be borne by the applicant
c.
The Planning Board shall either approve, or reject the improvements on the basis of
the report of the Municipal Officials.
d.
If the improvements are approved, the guarantee shall be released. Where approval
of a portion of multiple improvements is granted, the developer shall be released
from liability only for that portion of the improvements approved after inspection
by the respective Municipal Officials listed in Subsection D.1.b. above.
e.
Improvements which have been rejected may be resubmitted for inspection after
corrections for deficiencies identified in the reports of the respective Municipal
Officials listed in Subsection D.1.b. above, up to the date of default (see Section
8.D.3.).
2.
Form of Guarantee
With submittal of the application, the applicant shall provide one of the following
improvement guarantees for an amount adequate to cover the total costs of all required
improvements.
a.
Either a certified check payable to the Town or a savings account or certificate of
deposit naming the Town as owner, for the establishment of an escrow account; or
b.
An irrevocable letter of credit from a financial institution establishing funding for
the construction of the required improvements from which the Town may draw if
the improvements do not meet the conditions of approval.
c.
The conditions and amount of the improvement guarantee shall be determined by
the Planning Board with the advice of professional reviewers as listed in Section
5.D.2. of this Ordinance, if applicable, at the cost of the applicant.
3.
Contents of Guarantee
The performance guarantee shall contain cost estimates for each major phase of the
required improvements, if applicable and a date after which the applicant will be in
default and the Town shall have access to the funds to finish the required improvements.
The date of default may be extended by mutual agreement of the respective parties.
4.
Escrow Account
The improvement guarantee shall contain a completion schedule, cost estimates for each
major phase of the provisions for the release of part or all of the improvement guarantee
to the applicant and a date after which the applicant will be in default and the Town shall
have access to the funds to finish the required improvements.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 53 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
For any account opened by the applicant, the municipality shall be named as owner or co-
owner, and the consent of the municipality shall be required for a withdrawal. Any
interest earned on the escrow account shall be returned to the applicant unless the
municipality has found it necessary to draw on the account, in which case the interest
earned shall be proportionately divided between the amount returned to the applicant and
the amount withdrawn to complete the required improvements.
5.
Letter of Credit
An irrevocable letter of credit from a bank or other lending institution shall indicate that
funds have been set aside for the required improvements and may not be used for any
other project or loan.
6.
Phasing of Development
The Board may approve phased improvement guarantees, when required improvements
are approved in separate and distinct phases development.
7.
Performance Guarantee Review
Any proof of financial capacity shall be reviewed no later than sixty (60) days before the
expiration of the guarantee, and adjusted if necessary. The applicant may also request
adjustments in the guarantee.
8.
Release of Guarantee
Prior to the release of any part of the performance guarantee(s), the steps outlined in
Section 8.D.1., Subsections (b) though (e) of this Ordinance must be completed.
9.
Default
If, upon inspection on or after the date of default listed in Section 8.D.3. of this
Ordinance, the CEO or other inspecting official finds that any of the required
improvements have not been performed in accordance with the approved conditions of
approval, plans and specifications, he/she shall so report in writing to the Municipal
Officers, the Planning Board, and the applicant and guarantor. The applicant shall have
thirty (30) days unless otherwise specified by the CEO, to remedy any insufficiency
noted. Thereafter, Municipal Officers shall take any steps necessary to enforce the
guarantee and remedy the insufficiencies.
E.
Submission of As-Built Plans
Any project involving the construction of more than five thousand (5,000) square feet of gross
floor area or ten thousand (10,000) square feet of impervious surface, must provide the Code
Enforcement Officer with a set of construction plans showing the building(s) and site
improvements as actually constructed on the site, as opposed to as-described in the original
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 54 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
application. These change order plans must be submitted within forty (40) days of the
substantial completion of the project or occupancy of the building.
F.
Minor Changes to Approved Plans
Minor changes in approved plans necessary to address field conditions may be approved by the
Code Enforcement Officer provided that any such change does not affect compliance with the
standards or alter the essential nature of the proposal. Any such change must be endorsed in
writing on the approved plan by the Code Enforcement Officer.
G.
Amendments to Approved Plans
Approvals of site plans are dependent upon and limited to the proposals and plans contained in
the application and supporting documents submitted and affirmed to by the applicant. Any
variation from the plans, proposals, and supporting documents, except minor changes that do
not affect approval standards, is subject to Planning Board review and approval.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 55 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Section 9. Amendments to the Ordinance
Amendments of this ordinance may be initiated by the Select Board, the Planning Board, or as
specified in Title 30-A M.R.S.A. §2522.
This Ordinance may be amended as follows:
A. By a majority vote of the governing body if the proposed amendment is recommended by
a majority vote of the Planning Board
B.
By 2/3 majority vote of the governing body if the proposed amendment is not
recommended by the Planning Board.
In either case, the Planning Board shall hold a public hearing at least 30 days prior to the meeting of
the governing body. Notice of the hearing shall be posted in the Town Office at least thirteen (13)
days in advance of the Public Hearing. The notice shall be published at least two (2) times in a
newspaper that complies with Title 1, Section 601 and that has a general circulation in the
municipality. The date of the first publication shall be at least twelve (12) days before the hearing,
and the date of the second publication must be at least seven (7) days before the hearing.
TOWN OF FRANKLIN, MAINE
Ordinance
Ordinance - Site Plan Review Ordinance
Page 56 of 56
Ordinance Original - 03/28/2026
Ordinance Revision - None
Appendix - Warrant Articles
Annual Town Meeting - March 28, 2026
Article # 30 - ""Shall the document entitled 'Proposed Site Plan Review Ordinance of the Town of
Franklin, ME', as posted with the warrant and made available for inspection at the Town Office, be
enacted?"
Draft of the Site Plan Review Ordinance is available at the Franklin Town Office.
The above proposed ordinance was recommended by the Franklin Planning Board at the 02/19/2026
meeting, by a vote of six (6) in favor and none (0) opposed.
Motioned to accept the article as written. Motion Passed.