f [. _ - \ ' Town of
eo j Harpswell
ubdivision
Ordinance
TOWN OF HARPSWELL
SUBDIVISION ORDINANCE
Approved March 16, 1996
Amended March 6, 1999
Amended March 11, 2000
Amended August 23, 2001
Amended March 16, 2002
Amended November 23, 2002
Amended March 8, 2003
Amended May 20, 2004
Amended March 11, 2006
Amended March 10, 2007
Amended March 20, 2010
Amended March 9, 2013
Amended March 15, 2014
Amended March 14, 2015
Amended March 11, 2017
Amended March 10, 2018
Amended June 8, 2021
(This replaces the Subdivision Ordinance reenacted March 19, 1990)
Citizen's Note: Generally, a subdivision is the division of a tract or parcel of land into
three (3) or more lots within any five (5) year period in accordance with State Law (30-A
M.R.S.A. §4401[4]) as that subsection may be amended from time to time. For a specific,
determination, consult the Code Enforcement Officer.
1
Table of Contents
Subdivision Ordinance
Section 1. Purpose.............ccccceeeee eee ee scree ne nene eee eee cee ee tee bene eae eeeaeneneeeteesegengeneas 4
Section 2. Authority and Administration ..................00c:eeeseeeceeeeeeeteeeeteteeteseteesees A
Section 3. Applicability............... cece ccecceesetseeeseseeeeeeeenseencesseteesseserscetssereresesss 4
Section 4. Availability...............cccccece eee ee eae neee eee eee c ene enesestaeeseneeneecsteeaeeeee rents 5
Section 5. Severability..............cccecceece scence erence nsee eee ee ners eee sees eeene ene eeene een eee ens 5
Section 6. Conflict with Other Ordinances............ 2... c ces ee eee e een ee eee e eres enon eee nance ees 5
Section 7. Waiver and Modification of Subdivision Submissions.....................0..ccseees 5
Section 8. Submission of Documents and Review Schedule................cceeec eee ee eee e enone 5
8.1. Application Review Process..............ceceeceeeceseeeeeseeeeenenenesseneneneetee 0
8.2. FN 00) | Cer: 1500) 7
8.3. ASOT 05 00 ESI) (0) 6 8
8.4. Notification. 2.0.0.0... 0. ccc ceccecceneecesseeeeeeaenseeeseecereerserttectcsstesccsss LT
8.5. Determination of Complete Application...............0.cccceeseeeeeeseeeneeeenes 17
8.6. Site ViSitS..........cccecceece sete ce eeceeeeeceessescetccterescsesecssssssessctsecsssens 17
8.7. Public Hearing.............c ccc eeeeeeeec eee eeeseeeeecretssssscssssssssssssssssesene 18
8.8. Planning Board Review............cscseeeeceeec cere teesesesesssetessssestsesssssere 18
8.9. Planning Board Approval or Denial of the Subdivision........................ 18
8.10. Recording of the Approved Subdivision Plan.................ccccceeseeeeserenee 19
8.11. Inspection of Subdivision Improvements...............cccsceceeeeeeeenereeeern 19
8.12. Plan Revisions after Approval................ ccs ccecseese ses eeeeveecnsesseresesnne 20
8.13. Phasing of Development............... se ceceeeeeeeeeeeeeeeetetetetettstsseseesenee 20
weeee OLA, Lot Line Amendment..............cccccceeeeceeeeeeteeeeeereeseensseesssersesesses 20
Section 9. Approval Standards...............e ce cecccceeeneeseeesectesesesersstenesesssssssssssesens 21
9.1. Conformance. .........:ecceeceeceeeeen eee eeneeceteereerestessrtseesscttessscesesesee DL
9.2. Municipal Services............ccccseeeeceeeceeeeeeeceesetseterettsesstesctsessseses 21
9.3. Preservation of the Landscape...............ccceceseecceeeeeeeeersereerseasrreesees 21
9.4. LOtS. occ. e cece cece ec enc cece ec eneeaeestceeseeeessesessstseseenererecessesseterscessess DL
9.5. Land Not Suitable for Development................c:sccsceeeeeeeeeeeeeeseseseens 20
9.6. Required Improvements..............seeeeeseseeteeeseeeeeseteeesesetteseseeseeees 20
9.7. Erosion and Sedimentation Control................sceeseseeeeeeeseeceeeenenenee 27
9.8. Utilities. 0.0... cc ccc cc ese nc eases steeesectcessenerrscestereeserserseesereees 28
9.9. Construction in Flood Hazard Areas.............cccsceeeeeeeeeeeescceereeseeeens 28
9.10. Impact on Wetlands........... 0 ccececececececec sete eeeseenersteesessseseetereete 28
9.11. Impact on Groundwater.............c cece cece ee eeceeereetetesetesesssteesesseseees 29
9.12. Stormwater Management.............:cceceeeeeeeee seer ete esesreeseesstsstsettense SO
9.13. Offshore Islands..............cccecesescseeeeenceneeeteseeeetescrtststerstsetsssstene 30
9.14. Aesthetic, Cultural, and Natural Values...............cceceeeeeeeeeeeeerererereee 31
9.15. Traffic......ccce ccc ece cece eee enc eee eeceeeensenesetetscteterestecetsststestsessestsesees OL
9.16. Homeowners/Landowners Association... ..............0ccsseeeeeseeeeeeseetesseee 32
9.17. Community Docks............c cece eee ce cert eens re eceseereressessetsrssssssssens 33
2
9.18. Workforce Housing.............. 0. cceceeceseeeeeeeesectstseeseesereesssstecssesseas 34
9.19 Spaghetti Lots are Prohibited. ..................ccecece ee eeeeseseeetectestsssseenee 34
9.20 Liquidation Harvesting. .............cccecesseceeececereeececseeseestsrseetessessss 34
Section 10. Performance Guarantee. ................cc cece ececeeecceeesteetescesseetersetesessseses 34
10.1. Requirement. ......... 0... cect eccee ee eceeceeeeeceeteseeeseetessstttsessesssssscseses 34
10.2. Form of Guarantee............c cece ce eceeteceeeetesestessessssssssatssessesesssess 34
10.3. Amount of Guarantee........... 0.2... ccececeec cee ec eet eeseeceseeeseetsesstsssssesee 34
10.4. Release of Guarantec............ cece ce cece eeeeeeteeeeeeeeetasssessessssessccssennee 3S
10.5. Default..... 0... ce cee ncneeneeeeeeeeteeseasecsetettettsseesssseesctstsacenne 35
Section 11. Public Acceptance of Streets, Easements, or Open Space................ccsceeee 35
Section 12. Enforcement..............cccccceeec ences eceeeesececeessceseeeseesesseatettessersreseseenee OS
Section 13. Expiration of Subdivision Plan Approval.............cccsecseseeseeesesessseccessenes 36
Section 14, Appeals............c cece ccc cc nce e eee nen cece eeseaeeeeseeeseseseeeeeenessenteeegeesess 36
Section 15. Interpretation, Validity, Conflict of Ordinances, and Effective Date............ 36
15.1. Editorial Notes............. ccc ccceceecenteceneeeeeceeesaeeeesssssescesctecssssssessee 36
15.2. Validity, Conflict of Ordinances, and Effective Date................0..c0..008. 36
THIS UNOFFICIAL TABLE OF CONTENTS IS NOT A PART OF THE ORDINANCE AND IS
PROVIDED FOR CONVENIENCE ONLY.
3
SECTION 1. PURPOSE
The purpose of this Ordinance is to further the intent of Harpswell's Comprehensive Plan in
protecting the safety, health, and quality of the environment, including groundwater resources,
and the future quality of life in the Town, and to encourage use of the best planning by private
developers. This Ordinance also seeks to establish an orderly, equitable, and expeditious
procedure for reviewing subdivision applications and to provide clear standards that encourage
orderly growth in the community. To this end the Planning Board shall follow the procedures
and criteria in this Ordinance when reviewing subdivision applications and before granting
approval shall find that the provisions of this Ordinance and State rules and regulations have
been met.
SECTION 2. AUTHORITY AND ADMINISTRATION
2.1. This Ordinance is known as the "Town of Harpswell Subdivision Ordinance", it governs
subdivisions within the limits of the Town, and replaces the Town Subdivision Ordinance
re-enacted on March 10, 1990. This Ordinance is adopted pursuant to Home Rule Powers
as provided for in Article VIII, part 2, section 1 of the Maine Constitution and 30-A
Maine Revised Statutes Annotated (M.R.S.A.), § 3001, municipal subdivision law 30-A
M.R.S.A. § 4401 et seq., as the same may be amended from time to time.
Throughout this Ordinance there are "Citizen's Notes". These notes shall not be
considered part of this Ordinance as adopted by the Town, but shall only be considered
as an aid for citizens to use and as a guide to the intent of ordinance provisions and their
proper interpretation.
2.2. The Planning Board shall administer this Ordinance.
2.3. -- If, after review of the Town's Site Plan Review Ordinance pursuant to 30-A M.R.S.A.
§ 4402(6), as it may be amended from time to time, the Planning Board determines that
the Town's Site Plan Review Ordinance provides for a review and approval process for
the division of a new or existing structure into three (3) or more dwelling units whether
the division is accomplished by sale, lease, development or otherwise and their accessory
structures that is at least as stringent as that provided by this Subdivision Ordinance, then
the Planning Board shall review applications for approval of multi-unit residential uses
and their accessory structures under the Town's Site Plan Review Ordinance.
2.4. Definitions
For purposes of this Ordinance, certain terms or words used herein shall be defined as set
forth in the Definitions Addendum, as may be amended from time to time.
SECTION 3. APPLICABILITY
This Ordinance applies to all parcels of land proposed for subdivision in accordance with 30-A
M.R.S.A. § 4401[4], as that section may be amended from time to time, or division of land within
the boundaries of the Town of Harpswell previously subdivided.
For purposes of this Ordinance, a tract or parcel of land means all contiguous land in the same
ownership, provided that lands located on opposite sides of a road are not considered separate
4
tracts or parcels of land unless the road was established by the owner of land on both sides of the
road before September 22, 1971.
SECTION 4. AVAILABILITY
A certified copy of this Ordinance shall be filed with the Municipal Clerk and shall be accessible
to any member of the public. Copies shall be made available to the public at a reasonable cost
and at the expense of the person making the request. Notice of availability of this Ordinance
shall be posted.
SECTION 5. SEVERABILITY
Should any section or provision of this Ordinance be declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of the Ordinance, unless otherwise
provided by State law.
SECTION 6. CONFLICT WITH OTHER ORDINANCES
Whenever a provision of this Ordinance conflicts with or is inconsistent with another provision
of this Ordinance or of any other ordinance, regulation or statute, the more restrictive shall
control unless otherwise provided by state law.
SECTION 7. WAIVER AND MODIFICATION OF SUBDIVISION SUBMISSIONS
The Planning Board may modify or waive any of the preliminary conceptual plan or final
subdivision plan submission requirements when it determines that, because of the size of the
project or circumstances of the site, these requirements would not be applicable or would be an
unnecessary burden on the applicant and that a modification or waiver would not adversely affect
the Planning Board's ability to evaluate whether the application meets the standards of 30-A
M.R.S.A. § 4401 et seq., as may be amended from time to time, and Section 6 of this Ordinance.
These modifications shall not modify the standards as contained in the Ordinance.
When the Planning Board grants a waiver to any of the submissions required by this Ordinance
for a final subdivision plan, the approved subdivision plan shall indicate the waivers granted and
the date on which they were granted.
SECTION 8. SUBMISSION OF DOCUMENTS AND REVIEW SCHEDULE
8.1. Application Review Process
8.1.1. Pre-application Procedures
8.1.1.1. Prior to submitting a formal application for subdivision review to the Planning
Board, the applicant and/or his/her representative shall attend a preapplication conference
with the Town Planner or his/her designee. A preapplication conference is mandatory and
an application will not be accepted for processing until a preapplication conference has
been held. The preapplication conference shall be informal and informational in nature.
There is no fee for a preapplication conference, and such a meeting shall not cause the plan
to be a pending application or proceeding under 1 M.R.S.A. §302, as it may be amended
from time to time.
5
The purposes of the preapplication conference are to:
(a) Allow the staff to understand the nature of the proposed subdivision and the issues
involved in the proposal;
(b) Allow the applicant to understand the subdivision review process and required
submissions and fees;
(c) Allow the staff to provide the applicant with written material about two approaches
for subdivision design, the Flexible Lot Size approach and the Two Acre Lot Size
approach and to discuss the potential for applying each of these approaches to the
proposed subdivision;
(d) Identify potential issues that need to be addressed in future submissions; and
(e) Make the applicant aware of any opportunities for coordinating the development with
community policies, programs, or facilities.
8.1.1.2. There are no formal submission requirements for a preapplication conference.
However, the applicant should be prepared to discuss the following with the Town Planner:
(a) The proposed site, including its location, size, and general characteristics;
(b) The nature of the proposed subdivision;
(c) Any issues or questions about existing municipal regulations and their applicability
to the project; and
(d) Any anticipated requests for waivers from the submission requirements and the basis
for the requests.
8.1.1.3. Following the preapplication conference with the Town Planner, the applicant may
proceed with preparing and submitting an application for submission to the Planning
Board.
8.1.2. Preliminary Conceptual Plan
An applicant for subdivision review, other than a lot line amendment in accordance with
Section 8.13, shall prepare and submit to the Planning Board a preliminary conceptual
plan and related information for study, and, if necessary, alteration and modification,
prior to the submission of a final plan. Preliminary conceptual plans shall comply with
the requirements set forth in Section 8.3. The Planning Board review of the preliminary
conceptual plan submission shall be informational and shall not result in any formal
approval or disapproval of the project by the Planning Board. The Planning Board shall
review the submission to determine if the information provides a clear understanding of
the parcel's characteristics and its potential for subdivision and development and if the
preliminary conceptual plan is consistent with the development and conservation
potential of the parcel. The applicant may request that the review of the preliminary
conceptual plan submission be done in two (2) steps to allow feedback from the Planning
Board to be considered in the preparation of the conceptual subdivision plan. In this case,
the first step is the review of the site inventory and analysis (Section 8.3.1.2) and the
second step is the subsequent review of the preliminary conceptual subdivision plan
(Section 8.3.1.3). The outcome of the review process shall be a determination by the
Planning Board of the issues and constraints that must be addressed in the final
6
subdivision application including any suggested revisions to the conceptual subdivision
plan. The applicant shall not submit the final plan until the applicant has received from
the Planning Office written comments summarizing the Planning Board's review of the
preliminary conceptual plan. Review of the preliminary conceptual plan shall not
constitute approval of the final plan, but rather it shall be deemed an expression of
suitability of the design submitted on the preliminary conceptual plan as a guide to the
preparation of the final plan. The Planning Board shall complete its review of the
preliminary conceptual plan application within seventy-five (75) days of finding the
application to be complete unless the applicant chooses to have the application reviewed
in two steps. In this case, the Planning Board shall complete its review of the site
inventory and analysis within forty-five (45) days of its initial consideration and its
review of the preliminary conceptual plan within sixty (60) days of the initial
consideration of the preliminary conceptual plan. All of these time frames may be
extended with the consent of the applicant.
8.1.2.1. Preliminary Conceptual Plan Expiration
Within one (1) year of the completion of the review of the preliminary conceptual plan,
the applicant shall submit the final plan, which shall be prepared in accordance with
Section 8.3, or else said preliminary conceptual plan review shall expire.
8.1.3. Final Plan
A final plan shall comply with the requirements set forth in Section 8.3 and include the
following additional items:
(a) Space for the signatures of a legal majority of the Planning Board, the date of approval,
and the words "Approved by the Town of Harpswell Planning Board, pursuant to 30-A
M.R.S.A. § 4401 et seq., as may be amended from time to time.";
(b) One (1) or more original drawing meeting the requirements of the Cumberland County
Registry of Deeds for the recording of plans;
(c) Identification of all terms and conditions of approval adopted by the Planning Board,
including the following standard condition of approval: 'The property shown on this
plan may be developed and used only as depicted on this approved plan. All elements
and features of the plan and all representations made by the applicant in the record of
the Planning Board proceedings are conditions of the approval. No change from the
conditions of approval is permitted unless an amended plan is first submitted to and
approved by the Planning Board";
(d) Proper identification of the location of all permanent monuments; and
(e) A performance guarantee in accordance with the requirements of Section 10.
8.2. Applications
All applications for a subdivision shall be submitted to the Planning Office at least twenty-one
(21) working days in advance of a regularly scheduled Planning Board meeting. The applicant
shall provide ten (10) copies of the application, plans, and supporting documentation.
The Planning Office shall issue a dated receipt to the applicant. The Town Planner or his/her
designee shall review the submission to determine its compliance with the applicable submission
requirements. If the Town Planner deems the application to be provisionally complete for
7
placement on the Planning Board's agenda, the application shall be scheduled for the next
Planning Board meeting for a formal review of completeness, unless the agenda cannot
accommodate the request, in which case, it will be scheduled for the next Planning Board
meeting. If the Town Planner deems the application to be incomplete, she/he shall advise the
applicant in writing of that determination together with the additional or corrected information
required and shall inform the applicant in writing that the application will not be placed on the
Planning Board's agenda until it is complete. If the applicant disagrees with the Town Planner's
provisional determination, the applicant may request that the chair of the Planning Board include
the application on the Planning Board's next available agenda.
8.3. Submissions
The Planning Office shall submit to the Planning Board Chair the ten (10) copies of the complete
subdivision plan, application, and a copy of the dated receipt showing when the application was
received by the Planning Office.
The Planning Office shall issue a dated receipt, both to the applicant and to the Code
Enforcement Office, showing the fact that the plans have been received for consideration.
A complete application shall include:
8.3.1. Preliminary Conceptual Plan Application
A complete application for preliminary conceptual plan review shall include four (4) components
as follows:
1. A completed application form;
2. A location map in compliance with Section 8.3.1.1;
3. A site inventory and analysis in compliance with Section 8.3.1.2; and
4. A conceptual subdivision plan based on the four (4) step design process as set forth in
Section 8.3.1.3.
8.3.1.1. Location Map
The location map shall be adequate to show the relationship of the proposed subdivision to
adjacent properties, and to allow the Planning Board to locate the subdivision within the
Town. The map shall show:
8.3.1.1.1. All areas within one thousand (1,000) feet of the property line of the proposed
subdivision;
§.3.1.1.2. Existing subdivisions in the proximity of the proposed subdivision referenced
by the Registry of Deeds book and page number;
8.3.1.1.3. Location, names, and widths of existing and proposed rights-of-way;
§.3.1.1.4. Boundaries and designations of zoning districts; and
§.3.1.1.5. An outline of the proposed subdivision and any remaining portion of the
applicant's property if the location map covers only a portion of the applicant's entire
contiguous holding.
8
8.3.1.2. Site Inventory and Analysis
The site inventory and analysis is intended to provide both the applicant and the Planning
Board and staff with an understanding of the parcel and the opportunities and constraints
imposed on its use and development by both the natural and built environment. It is anticipated
that this analysis will result in a development plan that reflects the conditions of the parcel and
that the areas most suitable for the proposed use will be utilized while those that are not suitable
or present significant constraints will be avoided to the maximum extent possible. Therefore,
the submission requirements contained herein provide that the applicant submit basic
information about the parcel and an analysis of that information.
The site inventory and analysis must contain, at a minimum, all of the following information:
8.3.1.2.1. The names, addresses, and phone numbers of the record owner and the applicant.
8.3.1.2.2. The names and addresses of all consultants working on the project, such as the
surveyor, engineer, land planner, site evaluator, wetlands scientist.
8.3.1.2.3. Evidence of right, title, or interest in the property.
8.3.1.2.4. Ten (10) copies of an accurate scale inventory plan of the parcel or the portion
of the parcel proposed for subdivision at a scale of not more than one hundred (100) feet
to the inch showing as a minimum:
(a) The name of the development, north arrow, date and scale.
(b) The boundaries of the parcel.
(c) The relationship of the parcel to the surrounding area, including nearby conservation
land and subdivisions within one thousand (1,000) feet of the parcel.
(d) The topography of the parcel at an appropriate contour interval as determined by the
Town Planner or his/her designee depending on the nature of the use and character of
the parcel (in most instances, 2' contours will be necessary unless no grading or
infrastructure construction is planned).
(ce) The major natural features of the parcel and those located within five hundred (500)
feet of the parcel, including coastal and freshwater wetlands, significant vernal pools,
streams, ponds, floodplains, groundwater aquifers, significant wildlife habitats and
fisheries or other important natural features (if none, so state). This information must
be based on field determination for the parcel to be subdivided, unless the Planning
Board determines that information from available, published sources is adequate to
allow the review of the opportunities and constraints of the parcel. The information on
conditions on adjacent property may be from available, published sources.
(f) The location or existence of historic, archaeological, scenic or other critical resources
and culturally significant features on the parcel.
(g) A Class B high intensity soil survey for the portion of the parcel proposed to be
developed.
(h) The proposed method of sewage disposal, including the results of all site evaluations
to determine the suitability for on-site sewage disposal showing both test pits that are
acceptable and those that are not.
9
(i) The location of any areas with known or suspected groundwater quality or quantity
problems that may limit the ability to establish on-site wells.
(j) Existing buildings, structures, or other improvements on the lot and on adjacent lots
within two hundred fifty (250) feet of the parcel (if none, so state).
(k) Existing restrictions or easements on the lot (if none, so state).
(1) The location and size of existing utilities or improvements servicing the lot (if none, so
state).
8.3.1.2.5. Ten (10) copies of a site analysis plan at the same scale as the inventory plan (see
Section 8.3.1.2.4 above) highlighting the opportunities and constraints of the parcel. This
plan should enable the Planning Board to determine: which portions of the parcel are
unsuitable for development or use (Primary Conservation Areas); which portions of the lot
are unsuitable for on-site sewage disposal; which areas of the lot have development
limitations or conservation value (e.g. soil constraints, groundwater issues, wildlife habitat,
fisheries, scenic vistas, drainage concerns, historic or archaeological resources) that should
be addressed in the development plan; which areas may be subject to off-site conflicts or
concerns (e.g., noise, lighting, traffic, existing dwellings on adjacent lots); and which areas
are most suited to the proposed use.
§.3.1.2.6. Ten (10) copies of a narrative describing the existing conditions of the parcel,
the proposed use and the constraints or opportunities created by the site. This submission
should include any traffic studies, utility studies, market studies or other preliminary work
that will assist the Planning Board in understanding the site and the proposed use.
8.3.1.3. Conceptual Subdivision Plan
The conceptual subdivision plan must be based on the site inventory and analysis and
reflect the suitability of the parcel for development and conservation identified in the
analysis. The plan shall show the general layout of the subdivision, including the locations
of dwelling sites or building envelopes, lot lines, streets, protected or common open space,
and other common facilities. The plan shall be drawn at the same scale as the site analysis
plan. The plan shall be developed based on the following Four Step Design Process and
the steps shall be documented: Applicants shall submit a plan that is the end result of this
process, but may be asked by the Planning Board to submit four (4) separate sketch maps
indicating the findings resulting from each step of the design process. In deciding whether
it is necessary to submit separate sketch maps for each of the steps listed above, the
Planning Board shall consider the size of the parcel and whether the site includes a
significant amount of environmentally sensitive areas.
The following four (4) step design process is intended to allow the developer the full
potential of the legally allowable number of lots, while at the same time preserving
valuable natural resources and open space.
8.3.1.3.1. Step 1 of the 4 Step Design Process: Delineation of Natural Resource or
Conservation Areas
A. Identify the portions of the parcel that have significant development restrictions due to
natural constraints (Primary Conservation Areas) or that have significant natural or cultural
10
resource value (Secondary Conservation Areas) based on the site analysis.
B. If the applicant is proposing a Flexible Lot Size subdivision, calculate the area of
required open space in accordance with the provisions of Section 9.4.3 of this ordinance.
C. If the applicant is proposing a Flexible Lot Size subdivision, designate the proposed
location of open space(s) on the conceptual subdivision plan based on Section 9.4.3. This
should be done on the basis of practical considerations related to the tract's configuration,
its context to resource areas on neighboring properties, the priorities listed in Section 9.4.3
for open space areas, and the applicant's subdivision objectives.
D. If the applicant is not proposing a Flexible Lot Size subdivision, designate areas that are
not appropriate for development as dwelling sites and adjacent areas, roads, and other
structural improvements.
8.3.1.3.2. Step 2 of the 4 Step Design Process: Location of Dwelling Sites
Potential dwelling sites shall be tentatively located using the results of Step 1 as a base,
as well as other relevant data from the Site Analysis, such as topography and soils.
Dwelling sites should generally be located not closer than one hundred (100) feet from
Primary Conservation Areas and fifty (50) feet from Secondary Conservation Areas,
taking into consideration the potential negative impacts of residential development on
such areas, as well as the potential positive benefits of such locations to provide attractive
views and visual settings for residences. In addition, the dwelling sites should be located
taking into account the location of existing dwellings on lots adjacent to the subdivision,
the character of the area between the existing dwellings and the potential dwelling sites,
and the potential for negative impacts on existing dwellings. The location of the dwelling
sites in a Flexible Lot Size Subdivision should avoid concentrating units in the portions
of the site immediately adjacent to existing dwellings outside of the subdivision.
8.3.1.3.3. Step 3 of the 4 Step Design Process: Alignment of Streets
Upon designating the dwelling sites, a street plan shall be designed to provide vehicular
access to each dwelling and bearing a logical relationship to topographic conditions.
Impacts of the street plan on natural resources or proposed conservation lands shall be
minimized, particularly with respect to crossing environmentally sensitive areas such as
wetlands and traversing slopes exceeding twenty percent (20%). Street connections shall
generally be encouraged to minimize the number of new cul-de-sacs and to facilitate access
to and from dwellings in different parts of the tract (and adjoining parcels) while
minimizing the potential for cut-thru traffic and speeding.
8.3.1.3.4. Step 4 of the 4 Step Design Process: Drawing in the Lot Lines
Upon completion of the preceding three (3) steps, lot lines shall be drawn as required to
delineate the boundaries of individual lots. Wherever possible, lot lines shall be
perpendicular to the street.
11
8.3.2. Final Subdivision Plan Application
The final subdivision plan shall consist of one (1) or more maps to a scale of not more than
fifty (50) feet per inch. The following information shall either be shown on the final
subdivision plan or accompany the application for the final subdivision plan. Information
indicated with an asterisk may be submitted as part of an updated site inventory and analysis:
Section Submission Requirement Lot Minor | Major
Line Sub Sub
Amend . °
ment
8.3.2.1. Proposed name of subdivision plan
8.3.2.2. The Tax Assessor's map and lot numbers for the property proposed to x x Xx
be subdivided.
8.3.2.3. Verification of right, title, or interest in the property
8.3.2.4. A standard boundary survey as specified by the Board of Licensure xX XxX xX
for Professional Land Surveyors.
8.3.2.5. The topography of the site shall be shown by two (2) foot contour x x
intervals in relation to mean sea level. The Planning Board may allow
larger contour intervals or require more detailed contour information
if it finds that the information is necessary to complete review of the
application. Existing buildings, springs, water courses, wetlands,
vegetative cover, rock outcroppings, and other essential existing
physical features shall also be located.
8.3.2.6. A copy of all existing and proposed covenants, deed restrictions, x xX Xx
easements, rights-of-way, or other encumbrances affecting the
oroperty, delineated wherever possible.
8.3.2.7. The number of acres within the proposed subdivision, the square xX x XxX
footage of proposed lots.
8.3.2.8. The date the plan was prepared, magnetic north arrow, graphic map x x xX
scale, names and addresses of the record owner, applicant, engineer,
and individual or company who prepared the plan, including
appropriate seals.
8.3.2.9. Names of record owners of abutting properties, including any x Xx Xx
properties directly across rights-of-way or traveled ways. For
purposes of abutter notifications, a separate list of abutters with
addresses should be submitted.
8.3.2.10. The location of any zoning boundaries affecting the property and a Xx Xx xX
description of the proposed uses to be located on the site, including
quantity and type of residential units.
8.3.2.11. A copy of the Cumberland County Medium Intensity Soil Survey. P| we [x |
12
8.3.2.12. Proposed method of sewage disposal, including site evaluations x x
indicating suitability of the soil for sewage disposal on each lot. Test
pit analyses and completed sewage disposal design prepared by a
licensed site evaluator, shall be provided. Each test pit or boring must
be staked and identified on the subdivision plan. If a variance is
required according to the Maine State Plumbing Code, the Planning
Board may request a second evaluation to be done by the State
Division of Health Engineering or by a professional designated by the
Planning Board. The proposed subdivision plan shail also indicate the
locations where wells cannot be located because of sewage disposal
setbacks.
8.3.2.13. Proposed type of water supply system(s) and documentation by a x
Certified Geologist or Registered Engineer that the groundwater
system will support adequate supply and quality.
8.3.2.14. Proposed method for handling solid waste disposal Fd x | lx |
8.3.2.15, Documentation of adequate water quantity to serve the subdivision Xx
based on information from neighboring wells, obtained from property
owners and well drillers.
8.3.2.16. The location, proposed names, widths, grades, road profiles, radii, xX xX
length of curves, and central angle of curves for all existing and
proposed road rights-of-way, pavement and/or gravel lines, and
entrances to a public road. Copies of Maine Department of
Transportation (MDOT) approval for entrances onto existing State
highways shall also be required.
8.32.17. An estimate of the amount, type, and impact of vehicular traffic to be x
generated on a daily basis and at peak hours based on the assumption
of two (2) cars per residential dwelling unit or a figure generated from
the most recent edition of a recognized trip generation manual.
8.3.2.18. The location of existing or proposed utilities on or adjacent to the XxX xX
subdivision.
8.3.2.19*. | The boundaries of any flood hazard areas and the one hundred (100) Xx X XxX
year flood elevation as defined by the Federal Emergency
Management Agency (FEMA).
8.3.2.20. A surface drainage plan that shows the location and size of ditches, x x x
culverts, drainage ways, easements, and other improvements on or
adjacent to the proposed subdivision and the direction of flow.
8.3.2.21. Description of any problems with drainage, soils, or topography, or a x x
representation that, in the opinion of the applicant, none exist.
13
8 3.2.22. A hydrogeologic assessment prepared by a Certified Geologist x X
experienced in hydrogeology if:
8.3.2.22.1. Documented problems exist with the quality or quantity of
| water in wells in the vicinity of the development; or
8.3.2.22.2. Part of the subdivision is located in the area recommended
as having lot sizes of 4.2 acres on Map 3 "Recommended minimum
lot sizes based on Groundwater Protection" of the 1987
Comprehensive Plan and the applicant proposes lot sizes of less than
4.2 acres; or
Citizen's Note: The 4.2 acre restriction is not automatically part of
the Subdivision Ordinance.
8.3.2.22.3. The assessment shall include:
8.3.2.22.3.1. The depth of the water table at representative points
throughout the proposed development
8.3.2.22.3.2. Data on existing groundwater quality and quantity,
either from test wells in the subdivision, from existing wells on
neighboring property, or from data gathered during development
of the 1993 Comprehensive Plan
Citizen's Note: This information is on file in the Code
| Enforcement Office
8.3.2.22.3.3. Existing and post-construction drainage conditions
throughout the proposed subdivision
8.3.2.22.3.4. A map showing the location of all existing and
proposed subsurface wastewater disposal systems and all existing
and proposed drinking wells within the subdivision and all existing
systems within three hundred (300) feet of its boundary
8.3.2.22.3.5. Assessment of the potential for saltwater intrusion
when the proposed subdivision is located adjacent to areas
reporting high chloride content of drilled wells as shown on Map 2
"Future Land Use Map" of the 1993 Comprehensive Plan or where
there is evidence for potential saltwater intrusion
8.3.2.22.3.6. A map showing the location of all existing and
proposed subsurface wastewater disposal systems and all existing
and proposed drinking wells within the subdivision and all existing
systems within three hundred (300) feet of its boundary
14
8.3.2.23*. The location or existence of historic, archeological, scenic, or other xX xX
critical resources known to exist in the proposed subdivision. For any
proposed land use activity involving structural development or soil
disturbance on sites listed on the National Register of Historic Places,
the applicant shall provide evidence that they have submitted their
proposal to the Maine Historic Preservation Commission for review
and comment. The Planning Board may require a written statement
from the Maine Historic Preservation Commission indicating the
proposed development will not adversely impact archeological or
historic resources or recommending how the proposed development
might be modified to minimize any adverse impact on archeological
or historic resources.
8.3.2.24. Written statement of how proposed subdivision plan fits in with the Xx xX
character of the Town as set forth in the most recently adopted edition
of the Town's Comprehensive Plan.
8.3.2.25*. | The location of significant wildlife habitat or rare and irreplaceable Xx XxX
natural areas located in or near the proposed subdivision as identified
by the Department of Inland Fisheries and Wildlife (IFW) and the
Natural Heritage Data Base in the Department of Economic and
Community Development (DECD) or in the 1987 or 1993
Comprehensive Plans, and shellfish habitats and other marine
environments which may be affected by the development.
8.3.2.26*. | The location, names, and dimensions of existing and proposed public XxX
or private parks and other open spaces on or adjacent to the
subdivision and a description of any proposed improvements and their
management.
8.3.2.27. If parks or other open spaces are proposed to be deeded to the Town, Xx
a homeowners/landowners association, land trust, or other non-profit
organization, the location of the open space shall be shown on the
subdivision plan. Written offers of cession to the organization and
copies of agreements or documents showing the manner in which
open spaces will be retained by the applicant or lot owners shall be
submitted.
8.3.2.28. If a homeowners/landowners association is to be formed, xX xX
documentation of the standards contained in Paragraph 9.16 of this
Ordinance.
A soil erosion and sedimentation control plan in conformance with 4 x
Section 9.7 of this Ordinance.
£3230. | Location and dimensions ofall fencing and soreening, || |_|
8.3.2.31. Construction cost estimates for improvements to be completed by the x xX
applicant prior to the sale of lots and an estimate of the time period
required for completion of the development.
15
8.3.2.32. Subdivisions proposed for offshore islands must provide maps Xx x
indicating mainland support facilities, including private landings,
moorings, and a minimum of two (2) parking spaces for each lot. Also
required is documentation of title, right, or interest in mainland
property for support facilities. If mainland support facilities are
located in another municipality, the applicant must provide a written
statement of approval from that municipality.
8.3.2.33. If the subdivision plan involves substantial improvements, such as Xx Xx
construction of utilities, the Planning Board may require evidence of
financial capacity to complete the proposed improvements.
8.3.2.34, The following approvals, if applicable, must be obtained in writing: Xx x
8.3.2.34.1. A Wastewater Discharge License if required from the
Maine Department of Environmental Protection (DEP);
8.3.2.34.2. Approval from the Maine Department of Human Services
(DHS) if an engineered sewage disposal system is to be utilized or if
the applicant proposes to provide a central water supply system; or
8.3.2.34.3. Approval from the Local Plumbing Inspector indicating
that the wastewater disposal permits can be obtained.
8.3.2.35. At the option of the applicant or the Planning Board, any other x x xX
information that may be necessary for the full and proper
consideration of the subdivision plan.
8.3.2.36. Any application for subdivision approval which constitutes a revision Xx Xx x
or amendment to a subdivision plan which has been previously
approved shall indicate that fact on the application and shall identify
and provide a copy of the original signed plan being revised or
amended.
*Note: When the Planning Board requires the applicant to seek comments from a group or
agency outside of Town Officials, including but not limited to the Harpswell Historical
Society and Maine Department of Inland Fisheries and Wildlife, the applicant shall provide
written documentation of the request for comments. The applicant shall include in the written
request reference to this Section of the Ordinance which specifies that if the applicant has not
received written comments from the specified group or agency within forty-five (45) days of
receipt of the request, the Planning Board may assume that the group or agency has no
concerns with the proposed development.
8.3.3. Fee for Independent Consulting Services
In addition to the application fee, every application for a subdivision shall be accompanied by the
payment of an independent consulting fee assessed on a per lot or per dwelling unit basis,
whichever amount is greater, in such amount as may be established by the Board of Selectmen
from time to time. The payment shall be deposited in an individual trust account which is
separate and distinct from all other Planning Board and Town accounts.
16
The Planning Board may use the funds in the individual trust account to hire independent
consulting services to review the application. The applicant shall provide additional funds, as
necessary, to cover the cost of independent consulting services.
Any balance in the account remaining after a decision on the application by the Planning Board,
whether approved or denied, shall be refunded to the applicant after all payment of all consulting
services related to review of the subdivision.
8.4. Notification
When an application for either a preliminary conceptual plan or a final subdivision plan is
received, the Municipal Office, at the applicant's expense, shall give a dated receipt to the
applicant and shall notify, by first class mail, all record owners of abutting properties and the
clerk and reviewing authority of any municipalities that abut or include any portion of the
subdivision, specifying the location of the proposed subdivision and including a general
description of the project. Failure of any property owner to receive the notice sent as required
under this subsection shall not necessitate another public meeting or invalidate any action taken
by the Planning Board.
8.5. Determination of Complete Application
Within thirty (30) days of receipt of a subdivision plan and fee, the Planning Board shall notify
the applicant in writing whether or not the application is complete, and if incomplete, of any
additional submissions which are required.
A fee schedule for subdivision applications shall be established and revised from time to time by
the Selectmen after notice, public hearing, and recommendation of the Planning Board in
conformance with 30-A M.R.S.A. § 4355, as may be amended from time to time. Application
fees shall be payable by check to the Town. Application fees are to be paid at the time of
submission of a preliminary conceptual plan or at the time of submission of a final plan for those
applications that file a preliminary and final plan simultaneously.
Upon determination that a complete application has been submitted, the Planning Board shall
issue a dated receipt to the applicant. If the Planning Board determines the application is
incomplete, the application will be heard at the Planning Board meeting following submission of
a complete application.
The Planning Board may notify a number of appropriate departments, committees, or individuals
of the application for the proposed subdivision, including but not limited to the Road
Commissioner, Harpswell SAD 75 representatives, Conservation Commission, Marine
Resources Committee, local Fire Chief, and other affected parties as appropriate. The Planning
Board may request that these officials and the Code Enforcement Office comment upon
consistency with local codes and the adequacy of departments to service the proposed
subdivision.
8.6. Site Visits
After submission of a complete application for a preliminary conceptual plan, the Planning Board
shall conduct a site visit to provide members the opportunity to view the site. The site visit shall
17
be scheduled prior to the meeting at which the application is considered so that all parties,
including the applicant or representative of the applicant, owners of abutting properties and
interested members of the public, have reasonable opportunity to participate as a matter of due
process as a public proceeding under Maine's Right to Know Law, | M.R.S.A. §401 et seq., as
may be amended from time to time. The Planning Board may hold a second site visit when the
application for a final plan is received following the same procedures.
8.7. Public Hearing
The Planning Board shall hold a public hearing on all final subdivision applications within thirty
(30) days of determination of a complete application. The Planning Board shall publish notice of
the date, time, and place of the meeting in a local newspaper at least two (2) times. The date of
the first publication must be at least seven (7) days prior to the public hearing. In addition, the
Planning Board, at the applicant's expense, shall notify by first class mail, all record owners of
abutting property. Failure of any property owner to receive the notice sent under as required this
subsection shall not necessitate another public meeting or invalidate any action taken by the
Planning Board. To be considered by the Planning Board, all comments must be received in
writing prior to this public hearing, or made verbally at the public hearing.
8.8. Planning Board Review
The Planning Board shall discuss the final plan application at a regularly scheduled meeting
within forty-five (45) days of receipt of a complete application.
8.8.1. The applicant, or a duly authorized representative, shall attend the meeting of the
Planning Board to discuss the subdivision plan. In the case of an authorized representative, the
Planning Board will require a letter showing that the representative is in fact authorized to
represent the applicant.
8.8.2. Before the Planning Board grants approval of the subdivision, the Planning Board shall
find that the applicant has met all standards of 30-A M.R.S.A., § 4404, as it may be amended
from time to time, and Section 9 of this Ordinance in accordance with Section 8.9 below.
8.8.3. Before the Planning Board grants approval of the subdivision, the applicant shall meet
the performance guarantee requirements contained in Section 10 of this Ordinance.
8.9. Planning Board Approval or Denial of the Subdivision
The Planning Board shall, within thirty (30) days of a public hearing, and/or within sixty (60)
days of determining it has received a complete application, or within any other time limit that is
otherwise mutually agreed to, issue an order:
8.9.1. Denying approval of the proposed subdivision, or
8.9.2. Granting approval of the proposed subdivision, or
8.9.3. Granting approval upon any terms and conditions that it considers advisable to:
18
8.9.3.1. Satisfy the criteria listed in 30-A M.R.S.A. § 4404, as may be amended from time
to time,
8.9.3.2. Satisfy the criteria and regulations adopted under the provisions of this Ordinance,
and
8.9.3.3. Protect and preserve the public's health, safety, and general welfare.
The reasons for any denial, conditions of approval, or other stipulations shall be stated in the
written findings of the Planning Board. If the Planning Board grants a waiver of any submission
requirement, it shall state in the written findings the character and extent of the waiver, specify
that the waiver has been granted in accordance with Section 7 of this Ordinance, and will not
inhibit the Planning Board's ability to evaluate whether the application meets the standards of 30-
A M.R.S.A. § 4401 et seq., as may be amended from time to time, and Section 9 of this
Ordinance.
The action of the Planning Board shall be recorded on the subdivision plan with the date of
action over the signatures of the members of the Planning Board.
When the subdivision is approved, the applicant shall pay the cost of reproducing the required
copies of the approved plan for Town records.
8.10. Recording of the Approved Subdivision Plan
The applicant shall, within ninety (90) days of Planning Board approval, submit the signed
subdivision plan to the Cumberland County Registry of Deeds and report the book and page
numbers to the CEO within one hundred and twenty (120) days so the references can be recorded
on the Town's copies of the plan. The plan shall either contain all the conditions of approval or
the applicant shall record a separate document that contains all the conditions of approval under
the same terms and provisions as those applying the plan. If the applicant fails to record the
signed plan and report the book and page number to the CEO within the required time frame,
approval shall be null and void and the CEO shall note that fact on all Town records.
8.11 Inspection of Subdivision Improvements
The following provisions shall apply to any subdivision that includes as part of the approved
subdivision plan the construction of capital improvements including but not limited to roads,
drainage facilities, common areas, and similar facilities.
8.11.1 Pre-Construction Notice -- At least ten (10) working days prior to the start of
construction of any improvements the subdivider or his/her contractor, engineer or other agent
shall notify the Code Enforcement Office in writing of the planned start of construction.
8.11.2 Inspection of Construction -- Prior to the start of construction the Code
Enforcement Officer shall determine whether inspection of the improvements will be the
responsibility of the Code Enforcement Officers or whether the Town will need to retain outside
assistance in conducting the inspections of the facilities.
8.11.3 Outside Inspection Services -- If the Code Enforcement Officer determines that
outside assistance is needed to provide for the inspection of the improvements, the subdivider
shall deposit an amount equal to two (2) percent of the estimated costs of the improvements to
19
pay for the costs of the inspections. The funds shall be held in a separate account and shail be
used only for the purpose of inspecting the improvements. If there are any unexpended funds in
the account at the satisfactory closeout of all construction activity, the remaining balance shall be
returned to the subdivider. If the inspection fund is drawn down by more than ninety (90) percent
and the Code Enforcement Officer determines that there is a need for further inspection services,
the subdivider shall deposit an addition one (1) percent of the estimated construction costs in the
account. Once the initial deposit is made, the Code Enforcement Officer shall arrange for
appropriate inspection services from a qualified individual.
8.11.4 Inspections -- The Code Enforcement Officer or outside inspector shall conduct
periodic inspections of the improvements. If the inspecting official finds that any of the
improvements are not being or have not been constructed in accordance with the approved plans,
conditions of approval, and/or Town's ordinances the inspector or Code Enforcement Officer
shall prepare a written report documenting the deficiencies. The report shall be provided to the
subdivider and his/her engineer and/or contractor and to the chair of the Planning Board. The
Code enforcement Officer shall take any necessary steps to ensure compliance with the approved
plans. If the subdivider fails to correct the deficiencies the Code Enforcement Officer shall refer
the matter to the Board of Selectmen for enforcement action.
8.12. Plan Revisions after Approval
No changes may be made in any subdivision plan after approval has been given by the Planning
Board unless the plan is first resubmitted and the Planning Board approves any modifications in
conformance with 30-A M.R.S.A. § 4404 and Section 12 of this Ordinance, as may be amended
from time to time. This provision does not prohibit minor field changes during construction,
made with the approval of the CEO or his or her delegate. In the event that an amended plan is
recorded without complying with this requirement, it shall be considered null and void and the
Planning Board shall record at the Registry of Deeds and with the Town Clerk an affidavit
stating the facts and setting forth the legal conclusion that the plan is null and void.
8.13. Phasing of Development
The Planning Board may permit the subdivision plan to be divided into two (2) or more separate
and distinct phases subject to any conditions it deems necessary to insure the orderly
development of the plan. This may be accomplished by limiting approval to those lots or areas
abutting that phase of the proposed subdivision road which is covered by a performance
guarantee. When development is phased, road and any other construction shall commence from
an existing public way. Approval of lots or other development in subsequent phases shall be
given only upon satisfactory completion of all requirements pertaining to previous phases.
If the subdivision plan requires the Town to expand, add to, or purchase new facilities, the
applicant shall provide an alternative development plan, including but not limited to phasing,
construction delays to coincide with public funding of the required improvements, and/or private
funding options.
8.14. Lot Line Amendments
Any proposal to revise, relocate or otherwise amend the lot line (or lines) of a lot (or lots) shown
on a subdivision plan that has been previously approved by the Planning Board that, if approved
20
by the Planning Board, would result in the same or smaller number of lots as existing prior to the
proposed lot line amendment must still be reviewed and approved by the Planning Board, but the
applicant may submit an abbreviated application as set forth in Section 8.3.2 regarding
submission requirements for a "Lot Line Amendment."
SECTION 9. APPROVAL STANDARDS
When reviewing any subdivision plan, the Planning Board shall determine that the proposed
subdivision in conjunction with any other existing or approved development meets the review
criteria in 30-A M.R.S.A § 4404 and this Section, as may be amended from time to time.
Burden of Proof; Findings of Fact
In all instances, the burden of proof is upon the person proposing the subdivision. In issuing its
decision, the Planning Board shall make findings of fact establishing that the proposed
subdivision does or does not meet the criteria described in this Section.
9.1. Conformance
All proposed developments must be in conformity with all pertinent local, State, and Federal
ordinances, laws, and regulations.
9.2. Municipal Services
The proposed development shall not have an unreasonable adverse impact on municipal services
including the municipal road systems, fire department, solid waste program, schools, and other
municipal services and facilities.
9.3. Preservation of the Landscape
The landscape must be preserved in its natural state insofar as practicable by minimizing tree
removal, disturbance of soil, and retaining existing vegetation during construction. The Planning
Board may allow the removal of trees to create open meadows and scenic vistas which are part
of the overall subdivision.
9.4. Lots
9.4.1. Two-Acre Lot Size Subdivisions -- The minimum lot size for lots in a Two-Acre Lot
Size subdivision shall be eighty thousand (80,000) square feet per dwelling unit. The minimum
road frontage per lot for subdivisions shall be one hundred fifty (150) feet, and the minimum
shore frontage per lot for subdivisions shall be one hundred fifty (150) feet.
9.4.2. Flag lots and other odd shape lots in which narrow strips are joined to other parcels in
order to meet minimum lot size requirements are prohibited in Two-Acre Lot Size
subdivisions.
9.4.3. Flexible Lot Size Subdivisions -- The applicant may propose, and the Planning Board
may approve, a subdivision design in which the lots are smaller and have less road frontage
than required for a Two-Acre Lot Size subdivision and in which at least half of the parcel is
preserved as open space in accordance with the provisions of this Section.
21
9.4.3.1 Purpose -- The purposes of the Flexible Lot Size subdivision provisions are to:
1) provide the property owner or subdivider with flexibility in the design and layout of a
subdivision recognizing the development constraints for Two-Acre Lot Size subdivisions in
many areas of the community, 2) allow for the creation of developments with a stronger
neighborhood character, and 3) provide for the permanent protection of protected and
common open space that is consistent with the Town's long range goals for preserving the
community's natural, cultural and scenic resources.
9.4.3.2 Maximum Number of Lots -- The intention in allowing Flexible Lot Size
subdivisions is that a property owner or subdivider can create approximately the same
number of lots that they could in a Two-Acre Lot Size subdivision. The maximum number
of lots allowed in a Flexible Lot Size subdivision shall be calculated based on the following
formula:
The Total Area of the Parcel
Minus
Fifteen percent (15%) of the Total Area of the Parcel
Minus
Land Not Suitable for Development (see Section 9.5)
Equals
The Net Useable Area of the Parcel
Divided by
Eighty thousand (80,000) Square Feet per Unit/Lot
Equals
The Maximum Number of Lots/Units Allowed in a Flexible Lot Size Subdivision
If the applicant proposes to include workforce housing as part of the subdivision, the
maximum number of lots allowed shall be adjusted according to the density bonuses for
workforce housing set out in Section 11.18 of the Basic Land Use Ordinance.
9.4.3.3 Minimum Size of Lots -- To provide property owners and subdividers with
flexibility in the design of a Flexible Lot Size subdivision, there is no minimum lot size
requirement subject to the following limitations:
9.4.3.3.1 -- Lots that have their primary road frontage on an existing public road must
have a minimum lot area of forty thousand (40,000) square feet.
9.4.3.3.2 -- For one-unit residential lots with less than twenty thousand (20,000) square
feet of lot area, the applicant must demonstrate that the lot will meet the requirements of
the State Minimum Lot Size law.
9.4.3.3.3 -- For lots that will have more than one (1) dwelling unit or a nonresidential use,
the applicant must demonstrate that the lot will meet the requirements of the State
Minimum Lot Size law.
9.4.3.3.4 -- No lot that is located entirely within the Shoreland Zone shall have less than
required minimum lot area required by the Shoreland Zoning Ordinance. Lots that are
located partially within the Shoreland Zone may be smaller than required by the
22
Shoreland Zoning Ordinance if the principal building and the on-site sewage disposal
system are located outside of the Shoreland Zone.
9.4.3.4 Minimum Road Frontage -- To encourage the creation of lots that do not front on
existing public roads, lots in a Flexible Lot Size subdivision shall conform to the following
minimum frontage requirements:
Lots that front on an existing public road 150 feet per unit
Lots that front on an existing private road 75 feet per unit
Lots that front on a new road within the subdivision 40 feet per unit
9.4.3.5 Lot Shape -- To allow flexibility in the design of the subdivision in accordance with
the process laid out in Section 8.3.1.3, there are no limitations on the shape of lots in a
Flexible Lot Size subdivision as long as each lot contains a suitable development site of an
appropriate size to accommodate the anticipated development. Flag lots and other
irregularly-shaped lots are allowed as long as they are consistent with the overall utilization
of the parcel based on the site inventory and analysis and conceptual subdivision plan.
9.4.3.6 Sewage Disposal -- Sewage disposal may be provided by individual, shared, or
common subsurface sewage disposal facilities. The components of the systems may be
located on the lot which they serve or may be located off the lot including within the
protected or common open space in accordance with Section 11.4 of the Basic Land Use
Ordinance.
9.4.3.7 Perimeter Buffer -- Whenever any portion of a lot in the Flexible Lot Size
subdivision is located within twenty (20) feet of a parcel that is not part of the Flexible Lot
Size subdivision, that portion of the lot shall be maintained as a vegetated buffer. No
principal or accessory buildings, structural improvements (other than fences as part of an
approved buffer), lawns, gardens, storage of personal items, or similar activities shall occur
within this area. As part of the subdivision plan, the applicant shall provide details for how
this buffer will be treated and maintained. If the area is currently wooded or heavily
vegetated, this should be retained if possible. Where this area is not currently wooded, the
applicant shall provide for the establishment of a vegetated buffer sufficient to provide
visual relief to the abutting property. The Planning Board may waive or reduce this
requirement to allow for utilities to cross the buffer or to retain scenic views.
9.4.3.8 Minimum Protected or Common Open Space -- The concept of a Flexible Lot
Size subdivision is to allow for smaller lots in return for a substantial portion of the parcel
being set aside as open space. The minimum amount of land included in protected or
common open space shall be determined by the following formula:
One hundred percent (100%) of the area of the parcel that is unsuitable for development
(see Section 9.5)
Plus
Fifty percent (50%) of the area of the remaining acreage of the parcel (total area of the
parcel minus the area unsuitable for development
23
9.4.3.9 Location of the Protected or Common Open Space -- The protected or common
open space shall be located in accordance with the site inventory and analysis. In
determining which land should be included in the open space, the applicant shall be
guided by the following priorities:
9,4.3.9.1 First Priority -- Primary Conservation Areas -- Most or all of the identified
Primary Conservation Areas should be included in the protected or common open space.
9.4.3.9.2 Second Priority -- Secondary Conservation Areas -- After including the
Primary Conservation Areas in the open space, the following Secondary Conservation
Areas should be considered for inclusion in the protected or common open space in the
following order:
(a) Land that has been used for traditional access to the water or public beaches.
(b) Land that will be used to provide new or expanded access to the water.
(c) Land within one hundred (100) feet of tidal waters or streams that drain to tidal
waters.
(d) Land that is within two hundred fifty (250) feet of a significant vernal pool.
(e) Land that is adjacent to land that is owned by the Town, a land trust, formally
organized conservation organization, or state agency or that is otherwise
permanently protected as open space.
(f) Land which will allow for the continuation or connection of trails whether or not
such a facility is proposed as part of the subdivision.
(g) Land that maintains the integrity of blocks of unfragmented habitat or that
protects identified habitats and/or travel areas between habitat blocks.
(h) Land containing identified historic or archeological sites or significant cultural
features such as stone walls and specimen trees.
(i) Land that is in current or planned agricultural or managed forestry use.
(j) Land that is in current or planned commercial fisheries use.
(k) Land that protects scenic views visible from public property or the views of
abutting property owners or of dwellings to be built within the subdivision.
(1) Land that is located within a focus area identified in the Town's adopted Open
Space Plan.
9.4.3.10 Use of Protected or Common Open Space
For purposes of this section, protected or common open space areas must comply with the
following:
a. The common open spaces must be dedicated to the recreational amenity and
environmental enhancement of the development, must protect natural resources, and
must be recorded as such. For the purpose of these provisions, common open space
means an area that:
1) is not encumbered in any way by a principal structure;
24
2) is not devoted to use as a roadway, road right-of-way, parking lot, sidewalk, or
similar structural improvements;
3) is left in its natural or undisturbed state, except for low-intensity recreational
facilities including the cutting of trails for non-motorized recreation, unless the land
will be managed by an approved sustainable forestry plan signed by a Licensed
Maine Forester, or for community gardens, or for continuance of currently existing
agricultural use, or for components of subsurface sewage disposal or water supply
systems;
4) is capable of being used and enjoyed for the purpose of informal and unstructured
recreation and relaxation; and
5) is legally and practicably accessible to residents of lots in the development out of
which the open space is taken unless the open space will be owned by a private
party for agricultural or other natural resource use or such access will compromise
the natural resource value of the open space.
b. The common open space shall be controlled by one (1) or more of the following
methods:
1) common ownership by the owners of the units within the development with
covenants or deed restrictions approved by the Planning Board establishing
restrictions on the use of the open space and provisions for its permanent
management; and/or
2) transfer, with permanent restrictions, to a land trust or other recognized
conservation organization; and/or
3) ownership by a private party for agricultural or other natural resource use provided
that permanent restrictions are in place to provide for its continued use for this
purpose.
c. Any development proposed under this section shall specify the ownership, use,
management, and entity responsible for maintenance of all common areas and facilities.
When the open space will be protected through covenants or deed restrictions, those
provisions must provide that the covenants or deed restrictions are enforceable by the
owner of any lot in the subdivision, by the owner of any lot outside of the subdivision
that abuts the common open space, or by the Town of Harpswell. The covenants, deed
restrictions and/or conservation easements shall provide for the monitoring of
compliance with the restrictions at least once every two (2) years. A report of the
monitoring setting out the findings of the monitoring and any needed corrective action
shall be submitted to the Conservation Commission. The Conservation Commission
shall review the monitoring report and shall have the opportunity to conduct an on-site
visit if necessary to verify the findings of the monitoring report. If the homeowners
association or easement holder fails to conduct the required monitoring, the
Conservation Commission may carry out the monitoring. If the Town takes action to
monitor or enforce the covenants, deed restrictions, or conservation easements, the cost
of such monitoring and/or enforcement shall be recoverable by the Town from the
25
homeowners association or easement holder. The Planning Board shall approve the
arrangements for the ownership, control, use and maintenance of the common open
space in accordance with the standards of subsections (a) and (b) above as part of the
approval of a final subdivision plan. No changes in the use or management of common
open space shall be made without Planning Board approval and a note shall be provided
on the approved subdivision plan to this effect.
d. Any common open space or facility not retained by a private owner shall be
maintained by a developer or homeowners' association unless and until it is transferred
in its entirety to a recognized conservation organization and until the transfer actually is
completed. The formation and incorporation by the developer of a homeowners'
association, if one is proposed, shall be accomplished prior to final subdivision
approval.
9.5. Land Not Suitable for Development
The following land shall not be included in the calculation of the area of a lot for the purposes of
meeting minimum lot size or other density or dimensional requirements:
9.5.1. Land below the maximum high water line of a great pond, stream, or tributary stream,
stream, or pond;
9.5.2. Land below the HAT of a coastal wetland,
9.5.3. Land below the upland edge of a freshwater wetland with a contiguous area of more than
twenty thousand (20,000) square feet,
9.5.4. Land which is part of a road, or a transportation right-of-way, or easement serving more
than two (2) lots, except rights-of-way or easements used exclusively for pedestrian access, and
9.5.5. Land created by the filling or draining of a great pond, stream, tributary stream, or
coastal or freshwater wetland.
Citizen's Note: The filling or draining of a water body, tributary stream, or wetland will usually
require State and Federal approval.
9.6. Required Improvements
The following improvements are required for all subdivisions:
9.6.1. Lot Markers
9.6.1.1. Permanent markers must be set at all road intersections and points of curvature,
points of tangency, and intersections.
9.6.1.2. Permanent markers must be set at all corners and angle points of the subdivision
boundaries.
9.6.2. Water Supply
9.6.2.1. The proposed subdivision plan must have sufficient water available for the
reasonably foreseeable needs of the development.
26
9.6.2.2. If a central water supply system is provided by the applicant, the location and
protection of the source, and design, construction, and operation of the system must
conform to the standards of the Maine Rules Relating to Drinking Water (C.M.R. 10-144
231). The Code Enforcement Office shall be notified by the Planning Board of the location
of a proposed community water supply for reference in future amendment of the
Comprehensive Plan.
9.6.2.3. Lot design shall permit the placement of wells and subsurface wastewater disposal
areas, and reserve sites for subsurface wastewater disposal areas in compliance with the
Maine Subsurface Wastewater Disposal Rules.
9.6.2.4. Individual wells shall be sited and constructed to prevent infiltration of surface
water, and contamination from subsurface wastewater disposal systems and other sources
of potential contamination.
9.6.2.5. Water supplies shall meet the primary Drinking Water Standards contained in the
Maine Rules Relating to Drinking Water. If existing water quality contains contaminants in
excess of the secondary drinking water standards in the Maine Rules Relating to Drinking
Water, that fact shall be disclosed in a note on the Plan to be recorded in the Cumberland
County Registry of Deeds.
9.6.3. Sewage Disposal
9.6.3.1. The subsurface disposal must be in full compliance with the requirements of the
State of Maine Subsurface Wastewater Disposal Rules and to minimize adverse impacts on
ground water quality. In addition, the Planning Board may request the applicant to pay for a
second assessment of the site if the site has been identified as being marginally acceptable
according to the Maine State Plumbing Code.
9.6.3.2. Any septic system must be placed at least one hundred (100) feet from any existing
well whether the well is on the property or on contiguous property.
9.6.3.3. If common or cluster septic systems are used, a second site suitable for subsurface
disposal must be available.
9.6.4. Fire Protection
Provisions must be made for adequate emergency vehicle access to the subdivision and for
water supply for fire protection.
9.7. Erosion and Sedimentation Control
9.7.1. The proposed subdivision plan will not cause soil erosion or a reduction in the land's
capacity to hold waters such that a dangerous or unhealthy condition results.
9.7.2. The following measures relating to soil conservation and erosion and sediment control
shall be included where applicable as part of all projects submitted for review and approval
under this Ordinance:
27
9.7.2.1. The procedures outlined in the erosion and sedimentation control plan, submitted
by the applicant, shall be implemented during the site preparation, construction, and clean-
up stages.
9.7.2.2. Erosion of soil and sedimentation of watercourses and water bodies shall be
controlled by employing the following best management techniques:
9,7.2.2.1. Stripping of vegetation, soil removal, and regrading or other development
must be done in such a way to control erosion;
9.7.2.2.2. Development must preserve outstanding natural features and ensure
conformity with topography so as to create the least erosion;
9.7.2.2.3. The rate of surface runoff from the proposed development shall not be
increased;
9,7.2.2.4. Whenever possible, natural vegetation shall be retained;
9.7.2.2.5. Disturbed soils must be stabilized as quickly as possible;
9.7.2.2.6. Permanent vegetation and mechanical erosion control measures, in
accordance with the standards of the most recent edition of Environmental Quality
Handbook as published by the Maine Soil and Water Conservation Commission, must
be installed as soon as possible; and
9.7.2.2.7. Maintenance of drainage facilities or watercourses originating and completely
on private property is the responsibility of the owner to the point of discharge at the
property line.
9.7.3. Topsoil shall be considered part of the subdivision and shall not be removed from the
site except for surplus topsoil from roads, parking areas, and building excavations.
9.8. Utilities
9.8.1. Any utility installations remaining above ground must be located, where possible, in
existing public ways and existing service corridors, and so as to avoid crossing open areas and
scenic views as identified in the Comprehensive Plan.
9.8.2. The size and proposed location of utilities must be shown on the plans.
9.9. Construction in Flood Hazard Areas
When any part of a development is located in a Flood Hazard Area as identified by the Federal
Emergency Management Agency, the plan must be in conformance with the Harpswell
Floodplain Management Ordinance.
9.10. Impact on Wetlands
Subdivision plans shall be designed to minimize impact on wetlands.
28
Septic systems and structures must be set back at least two hundred fifty (250) feet from the
upland edge of moderate or high value wetlands, at least seventy-five (75) feet from a water
body, tributary stream, or the upland edge of a coastal or freshwater wetland; and at least
twenty-five (25) feet from the upland edge of a forested wetland.
If the Local Plumbing Inspector, upon review of written evidence submitted by a soil scientist
licensed to practice in Maine, determines that the only practical alternative for a specific
subsurface wastewater disposal system is within the seventy-five (75) foot setback of the upland
edge of a coastal or freshwater wetland, or within the twenty-five (25) foot setback from the
upland edge of a forested wetland, the Planning Board may waive the setback requirement for
that specific subsurface wastewater disposal system, and set appropriate conditions on the system
as recommended by the Local Plumbing Inspector, provided that the waiver does not have the
effect of nullifying the purpose of this Ordinance or violating the State of Maine Subsurface
Waste Water Disposal Rules. When the Planning Board grants a waiver pursuant to this
paragraph, the final plan to be recorded at the Registry of Deeds shall indicate the waiver granted
and the date on which it was granted.
Except as specifically approved by the Maine Department of Environmental Protection or United
States Army Corps of Engineers, roads shall be located to avoid crossing a wetland, tributary
stream, or water body and must be set back at least two hundred fifty (250) feet from the upland
edge of moderate or high value wetlands, at least seventy-five (75) feet from the upland edge of a
coastal or freshwater wetland, and at least twenty-five (25) feet from the upland edge of a
forested wetland.
Any cutting of vegetation or timber harvesting in a wetland area described in this Section or
within the setbacks outlined above shall be conducted in accordance with Section 11.15 of the
Town's Basic Land Use Ordinance or, where applicable, Section 15.14 of the Shoreland Zoning
Ordinance.
Citizen's Note: The filling or draining of a water body, tributary stream, wetland, or pond will
usually require State and Federal approval.
9.11. Impact on Groundwater
9.11.1. The proposed subdivision plan will not alone, or in conjunction with abutters or other
existing activities, adversely affect the quality or quantity of groundwater.
9.11.2. A subdivision plan must not increase the nitrate concentration in the groundwater at the
boundary to more than ten (10) milligrams per liter.
9.11.3. Subsurface wastewater disposal systems and drinking water wells shall be constructed
as shown on the map submitted with the assessment. If construction standards for drinking
water wells are recommended in the assessment, those standards must be included as a note on
the final plan.
9.11.4. The proposed subdivision plan shall use on-site techniques to assure that the amount of
aquifer recharge post-development is no less than the amount before development.
29
9.11.5. Groundwater withdrawals by a proposed subdivision shall not lower the water table
beyond the boundaries of the subdivision.
9.11.6. Water conservation devices shall be used by the applicant to minimize negative
groundwater impacts of the development.
9.12. Stormwater Management
9.12.1. The Planning Board shall consider the impact of the proposed subdivision on erosion,
drainage, and runoff on the development itself and on adjacent properties and water bodies. In
assessing impacts, the Planning Board shall consider site visits, existing drainage problems,
topographical information, and, if deemed necessary, a runoff analysis based on a twenty-five
(25) year storm as submitted by the applicant. Subdivisions of five (5) or more lots must be
reviewed and endorsed by an independent consultant hired by the Town.
9.12.2. Adequate provisions must be made for disposal of all storm-water generated within the
subdivision and any drained groundwater through a management system of swales, culverts,
underdrains, and storm drains. Stormwater shall be treated to remove oil, grease, sediment, and
other contaminants prior to discharge into a water body or tributary stream.
9.12.3. The stormwater management system must be designed to conduct stormwater flows to
existing water courses or storm drains, except where retention basins are designed or
groundwater recharge is desirable. The stormwater management system shall make provisions
so as to not have adverse effect on neighboring properties, downstream water quality, soil
erosion, or the public drainage system.
9,12.3.1. The minimum size for any storm drainage pipe shall be twelve (12) inches. All
downstream pipes must be the same size or larger. Pipe must be embedded in a fine
granular material.
9,12.3.2. Catch basins must be installed where necessary.
9,12.3.3. Outlets must be stabilized against soil erosion.
9.12.4. Stormwater runoff systems must infiltrate, detain, or retain water falling on the site
such that the rate of flow from the site does not exceed that which would occur in the
undeveloped state.
9.12.5. Where a subdivision is traversed by a stream, tributary stream, or surface water
drainage way, the surface water runoff to be created by the subdivision shall be controlled.
Easements for existing or proposed drainage rights-of-way shall be provided with swales,
culverts, catch basins, or other means of channeling surface water within the subdivision
and over other properties. The easements or rights-of-way shall be at least thirty (30) feet
wide and substantially conform with the lines of existing and proposed drainage ways.
9.13. Offshore Islands
Subdivisions proposed for offshore islands will require deeded mainland support facilities
including private landing and at least two (2) parking spaces per lot.
30
9.14. Aesthetic, Cultural, and Natural Values
The proposed subdivision plan will preserve the scenic and natural beauty of the area, aesthetics,
historic sites, significant wildlife habitat identified by the Department of Inland Fisheries and
Wildlife or the municipality, or rare and irreplaceable natural areas or any public rights for
physical or visual access to the shoreline.
The developer may offer the Town, Land Trust, or appropriate conservation group the title or
easement to existing and future points of public access to the shoreline and open spaces valuable
for aesthetic, historic, or wildlife habitat or used for traditional recreation.
The Planning Board may require the inclusion of a note on the subdivision plan and deed
restriction on the affected lots restricting the clearing of trees to those areas designated on the
subdivision plan.
9.14.1. All subdivision plans must conform with the wildlife management guidelines
developed by the Maine Department of Inland Fisheries and Wildlife (MIFW) for the
protection of significant wildlife habitat. Any clearing of vegetation that takes place within
seventy-five (75) feet of the upland edge of a wetland designated as high or moderate value for
waterfowl habitat by the MIFW or in the Comprehensive Plan shall be limited to that which is
necessary for allowed uses. This restriction shall appear as a note on the subdivision plan and
as a deed restriction on the affected lots.
9.14.2. All subdivisions must be designed so as not adversely to impact rare natural areas as
identified by the Natural Heritage Data Base in the Department of Economic and Community
Development.
9.14.3. All subdivisions must be designed so that the completed development shall protect
shellfish habitats and other marine environments.
9.14.4. All subdivisions shall be designed to protect historic, archaeological, scenic, or other
critical resources known to exist in the proposed subdivision.
9.14.5. All subdivisions must be designed to ensure that important scenic areas and open
spaces, as identified in the Comprehensive Plan for Harpswell, are maintained.
9.14.6. If the land proposed for subdivision is located on Route 24, Route 123, Cundy's Harbor
Road, or Mountain Road and at the time of application is forested, a wooded buffer strip no
less than twenty-five (25) feet in width shall be left along the road right-of-way. If at the time
of application, the land is not wooded, a buffer strip no less than twenty-five (25) feet in width
shall be left along the road right-of-way.
9.15. Traffic
9.15.1. The proposed subdivision plan will not cause unreasonable highway or public road
congestion or unsafe conditions for vehicular traffic and pedestrians.
31
9.15.2. General Requirements
9.15.2.1. Proposed subdivisions must provide for safe access to and from public and private
roads. Safe access shall be assured by providing adequate access points with respect to
sight distances, intersections, schools, and other traffic generators. An entrance permit will
be required from the Maine Department of Transportation. The road serving the
subdivision shall be adequate to carry the anticipated traffic.
9,15.2.2. Provisions must be made for providing and maintaining convenient and safe
emergency vehicle access to all structures at all times.
9,15.2.3. The proposed subdivision plan must provide for safe and convenient access for
pedestrians within the subdivision and from the subdivision to surrounding development
and open areas.
9.15.2.4. Upon receipt of the subdivision plan, the Planning Board may forward it to the
Road Commissioner or to the Town's Consulting Engineer for review and comment.
9.15.3. Road Design and Construction Standards
9.15.3.1. The road design and construction standards contained in the Road Ordinance must
be met by all roads within developments reviewed under this Ordinance, regardless of
whether the road is intended to be public or private. If the applicant can provide clear and
convincing evidence that an alternate road design is necessary to preserve community
character and the resulting design will not create safety or maintenance problems for the
Town, the Planning Board may waive the travel way width, shoulder width, or slope
requirements of the Road Ordinance.
9.15.3.2. All roads must be platted along contour elevations which will result in minimum
grades and greatest visibility whenever practicable, with consideration given for anticipated
use of the land.
9.15.3.3. The proposed road layout must be coordinated with the road system of the
surrounding areas. All roads must provide for the continuation of or connection to existing
roads in surrounding areas and provide means of ingress and egress for surrounding lots or
parcels of land.
Where necessary, as determined by the Planning Board, to safeguard against hazards for
traffic and pedestrians and/or to preserve the traffic bearing capacity of existing roads,
provisions shall be made for turning lanes, guard rails, traffic directional islands, frontage
roads, shared driveways, sidewalks, bicycle ways, and traffic controls on existing roads.
The applicant will pay for any safety improvement required on existing roads as a result of
the subdivision plan.
9,16. Homeowners/Landowners Association
If commonly owned property is proposed, the subdivision plan shall have a
Homeowners/Landowners Association which, at a minimum, shall provide for the following:
32
9.16.1. Covenants for mandatory membership in the Homeowners/Landowners association
setting forth the owners' rights, interests, and privileges in the association and the common
property and facilities, to be included in the deed for each lot or dwelling.
9.16.2. Articles of incorporation of the proposed Homeowners/Landowners association as a
not-for-profit corporation.
9.16.3. By-laws of the proposed Homeowners/Landowners association specifying the
responsibilities and authority of the association, the operating procedures of the association,
and providing for proper capitalization of the association to cover the costs of major repairs,
maintenance, and replacement of common facilities.
9.16.4. Where a proposed subdivision would use an existing private road(s) for access,
provision requiring the subdivision developer and/or lot owners to contribute fairly to the cost
of maintenance, repair, and replacement of such road(s).
9.16.5. Where an alternate subdivision design is proposed, provision requiring the subdivision
developer and/or lot owners to contribute fairly to the cost of maintenance, repair, and
replacement of the common septic system(s), well(s), and/or open space.
These provisions must satisfy the Planning Board that the homeowners/landowners association
has the responsibility of maintaining the common property or facilities, has the power to levy
annual charges against all owners of lots or dwelling units to defray the expenses connected with
the maintenance, repair, and replacement of common property and facilities and tax assessments,
has the power to place a lien on the property of members who fail to pay dues or assessments,
and that the applicant shall maintain control of the common property, and be responsible for its
maintenance until development sufficient to support the association has taken place.
The developer shall maintain control of common open space and facilities and be responsible for
their maintenance until at least fifty-one percent (51%) of the development's lots or units have
been completed and sold, with evidence of such completion and sales submitted to and approved
by the Planning Board.
Covenants for mandatory membership in the association shall be approved by the Planning
Board and included in the deed for each lot or unit or incorporated by reference from a master
document recorded in the Cumberland County Registry of Deeds.
9.17. Community Docks
For any subdivision located in whole or in part the Shoreland Zone, no new wharf, pier, dock
and/or float shall be constructed to service only one lot if the upland area on which the wharf,
pier, dock and/or float is proposed to be located may reasonably be arranged to service more than
one lot, in which case the wharf, pier, dock and/or float may only be improved and used as a
community dock for as many of the lots in the subdivision as it can reasonably accommodate.
Community docks shall be reviewed and approved by the Planning Board in accordance with the
terms of the Shoreland Zoning Ordinance.
33
9.18. Workforce Housing Any subdivision that is to include Workforce Housing Units or
Lots shall comply with Section 11.18, Workforce Housing, of the Town's Basic Land Use
Ordinance, as may be amended from time to time.
9.19. Spaghetti Lots are prohibited If any lots in the proposed subdivision have shore
frontage on a river, stream, brook, great pond, or coastal wetland, as these features are defined in
Title 38, Section 480-B, none of the lots created within the subdivision shall have a lot depth to
shore frontage ratio greater than 5 to 1.
9.20. Liquidation Harvesting Timber on the parcel being subdivided has not been harvested
in violation of rules adopted pursuant to Title 12, Section 8869 Subsection 14.
SECTION 10. PERFORMANCE GUARANTEE
10.1. Requirement
Prior to approval of the subdivision plan, the Planning Board shall require documentation that
the applicant has financial capacity to carry out the proposed project. A performance guarantee,
letter of credit or similar agreement with the Planning Board may be required for the following,
whether on-site or off-site:
10.1.1. The construction of roads and/or buffer improvements;
10.1.2. The construction of any water supply or sewage system other than individual on-site
facilities;
10.1.3. The construction of drainage systems, erosion control measures, or water supply
systems for fire protection; and
10.1.4. The construction of other improvements, such as buffer strips, intended to minimize
adverse effects on the public or on abutting properties.
10.2. Form of Guarantee
The performance guarantee may be tendered as a certified check payable to the Town, a savings
account passbook in the name of the Town, an irrevocable letter of credit from a financial
institution acceptable to the Selectmen, or a faithful performance bond running to the Town and
issued by a surety company licensed to do business in the State of Maine and acceptable to the
Selectmen.
10.3. Amount of Guarantee
The amount of the performance guarantee is one hundred twenty-five percent (125%) of the cost
of the requirements of Subsection 10.1. All guarantees are conditioned upon the completion of
all such improvements within two (2) years from the date of approval or another agreed upon
date based on Section 8.12 of this Ordinance.
34
10.4. Release of Guarantee
Prior to the release of any part of the performance guarantee, the Planning Board shall determine
to its satisfaction, in part upon the report of the CEO or the Town's consultant and whatever
other agencies and departments may be involved, that the proposed improvements meet or
exceed the design and construction requirements for that portion of the improvements for which
the release is requested.
10.5. Default
If, upon inspection, the CEO or the Town's consultant finds that any of the required
improvements have not been constructed in accordance with the approved plan and
specifications filed as part of the application, he or she shall so report in writing to the Board of
Selectmen, the Planning Board, and the applicant. The performance guarantee shall then remain
in place until the provisions of Subsection 10.4 are met.
If the requirements of Subsection 10.4 are not met within a reasonable period of time after such
notice, the Selectmen may utilize the funds from the guarantee to cause the completion of the
improvements or to restore the site to its pre-development condition.
SECTION 11. PUBLIC ACCEPTANCE OF ROADS, EASEMENTS, OR OPEN SPACE
The approval by the Planning Board of a subdivision plan shall not constitute or be evidence of
any acceptance by the Town of any road, easement, or open space shown on such plan. Such
acceptance may only be accomplished by the voters of the Town at Town Meeting.
SECTION 12. ENFORCEMENT
12.1. No building permit shall be issued under the Town's Ordinance, no building or site
disturbance shall commence, and no plan of a division or development of land within the Town
which constitutes a subdivision shall commence until the plan is recorded in the Cumberland
County Registry of Deeds.
12.2. No person, firm, corporation, or other legal entity may sell, lease, develop, build upon,
occupy any building or structure, or convey for consideration, offer or agree to sell, lease,
develop, build upon, occupy any building or structure, or convey for consideration any land in a
subdivision which has not been approved by the Planning Board and recorded in the Cumberland
County Registry of Deeds, nor may any person, firm, corporation, or other legal entity convey
any land in any approved subdivision plan unless the required permanent markers are set.
12.3. No person, firm, corporation, or other legal entity may convey, offer, or agree to convey
any land in an approved subdivision which is not shown on the approved plan as a separate lot.
12.4. Development of a subdivision without Planning Board approval is a violation of this
Ordinance and State law.
12.5. Violations of this Ordinance are punishable in accordance with the 30-A M.R.S.A.
§4452, as may be amended from time to time.
35
SECTION 13. EXPIRATION OF SUBDIVISION APPROVAL
Approval of a subdivision plan shall lapse if the applicant, or his or her successor, has not
substantially started construction of approved improvements within one (1) year or within such
time period as may be agreed upon in writing by the Planning Board and the applicant. One (1),
one (1) year extension may be granted by the Planning Board. Three (3) months prior to the
expiration date for substantial start of construction, the CEO shall notify the applicant by
certified mail of the date of expiration.
SECTION 14. APPEALS
Any aggrieved party who participated in the proceedings before the Planning Board may take an
appeal to the Board of Appeals within forty-five (45) days from the date of any decision of the
Planning Board.
SECTION 15. INTERPRETATION, VALIDITY, CONFLICT OF ORDINANCES, AND
EFFECTIVE DATE
15.1. Editorial Notes
Throughout this Ordinance there are editorial "citizen's notes" which are reproduced in italicized
print. These notes shall not be considered part of this Ordinance as adopted by the Town, but
shall only be considered guides to the intent of Ordinance provisions and their proper
interpretation.
15.2. Validity, Conflict of Ordinances, and Effective Date
Should any section or provision of this Ordinance for any reason be held void and invalid, it shall
not affect the validity of any other section or provision.
36