TOWN OF HARRISON
Bear River Aquifer Protection
Ordinance
Adopted June 25, 1988
AMENDED AT THE ANNUAL TOWN MEETING
ON JUNE 14, 2006
AMENDED AT THE ANNUAL TOWN MEETING
ON JUNE 13, 2007
AMENDED AT THE ANNUAL TOWN MEETING
ON JUNE 10, 2009 A True Attested copy Date: June 11, 2009
A TRUE COPY ATTESTED
________________________
Judith E. Colburn
TOWN CLERK
1
TABLE OF CONTENTS
Page
Section 1
Purpose
2
Section 2
Findings
2
Section 3
Definitions
3
Section 4
District Boundaries
5
Section 5
District Use and Space Standards
6
Section 6
Administrations and Enforcement
8
Section 7
Submission Requirements
10
Section 8
Performance Standards
11
Section 9
Nonconformance
13
Section 10
Appeals
13
Section 11
Legal Provisions
14
Section 1. Purpose
2
A. To manage the groundwater recharge areas of the Bear River Aquifer in order to maintain the
present rate of recharge and, where possible. To enhance recharge - thus ensuring a dependable
water supply to the town for the future.
B. To protect the aquifer from contaminants, which can reasonable be, expected to accompany
certain uses of land or activities, thereby maintaining the aquifer's high water quality.
Section 2. Findings
A. The Towns of Bridgton and Harrison are fortunate in that they have access to a water supply
that is both plentiful and of excellent quality. From the Bear River Aquifer, the Harrison Water
District draws water to serve many customers in Harrison and North Bridgton (including
Bridgton Academy). The total demand from customers is 3,000,000 gallons of water per month, a
rate that is consistent through out the year. The rate of demand is significantly lower than the
rate defined as being a "safe yield rate" by Robert G. Gerber, Inc.
B. Rainfall replenishes the aquifer through a process known as a recharge. Increasing density of
development creates impervious surfaces (areas which water cannot penetrate to reach ground
water), which decrease the amount of water available for use from aquifers. Diminishing
recharge also decreases the amount of water available to dilute pollutants.
C. The most likely sources of toxic water pollution are not necessarily large industries, but often-
small businesses such as gas stations, dry cleaners, and automotive shops. Other pollution
problems result from elevated concentrations of nitrates, and are linked to more common land
uses such as household septic systems and use of fertilizers for agriculture.
D. W. Bradford Caswell, after completing a hydrogeological study of the Bear River Aquifer in the
summer of 200 states:
"An overlying glacial-marine clay layer tends to protect the geographically small aquifer from
accidental surface spills of contaminants. Much of the land overlying the aquifer is currently
owned by the Water District. Establishment of the travel-time boundaries for control of
certain land uses will provide still more protection of the aquifer from contaminants
introduced at or near land surface. Most importantly, however, this investigation and
analysis show without a doubt that the Bear River is your primary source of ground water
recharge when the aquifer is pumped, and that maintenance of high quality river water
through protection of the Bear River Watershed from introduction of potential contamination
substances is of the utmost importance to the Water District and its customer. Commonsense
land-use control measures to ensure that the present high quality of river water is not
diminished in future years are required."
E. Changes in the Federal Drinking Water Standards may require utilities; now using surface water
supplies, to undertake additional treatment processed which could entail significant future costs.
Maintaining the high quality of underground water sources such as the Bear river aquifer,
including potential well points less influenced by the river itself, will give the Harrison Water
District flexibility in the future when considering options for the efficient delivery of clean
drinking water.
3
Section 3. Definitions
Agriculture: The cultivation of soil, producing or raising of crops, for commercial or other purposes,
on more than one acre. The term shall also include tree, plant and shrub nurseries and versions
thereof.
Animal Husbandry: Keeping more than 5 animal units (1 animal unit represents 1,000 pounds of
live animal weight).
Automobile Graveyard: As defined by 30-A, M.R.S.A., Section 3752.
Aquifer: A saturated body of soil or rock that will yield economically significant quantities of water
to wells and springs. Aquifers that yield over 10 gallons per minute are considered "high yield". The
estimated yield of the Bear River Aquifer is 50 gallons per minute and over.
Commercial Animal Feedlots: A lot, building or combination of lots and buildings intended for the
confined feeding, breeding, raising or holding of animals for commercial purposes and specifically
designed as a confinement area in which manure may accumulate. Pastures shall not be considered
animal feedlots under this Ordinance.
Commercial Use: A business in which the principal uses is the sale of goods and/or services to the
general public or other businesses. Indoor storage of goods and equipment is permitted as an
accessory use. Outdoor storage and uses that fit the definition of industrial use are not included in
this definition.
Cone of Depression (or Draw down Cone): A depression that is created by a well in the
potentiometric surface of a body of groundwater and that has the shape of an inverted cone and
develops around the well from which water is being drawn.
Disposal: The discharge, deposit, injection, dumping, spilling, leaking, incinerating, or placing of
leach able materials in or on any land or water.
Dog Kennel: Possession of more than 3 dogs on any one property constitutes a kennel.
Draw Down: The difference between the elevation of static water elevation and of the water table at
that point when the well is being pumped.
Dwelling Unit: A room or group of rooms designed and equipped exclusive for use as living quarters
for only one family, including provisions for living, sleeping, cooking, and eating. This term shall not
include hotels, motels, and bed and breakfast establishments without cooking facilities in individual
rooms or suites.
Engineered Subsurface Disposal System: A system or a combination of individually or jointly owned
systems that serve a single building or group of associated buildings with a total design flow in excess
of 2,000 gallons per day. Examples include condominium projects and clustered systems serving
residential dwellings. Residential dwellings with individual systems shall not be included.
Full Hydrogeological Study: A study by a Maine licensed geologist or hydrologist that analyzes the
subsurface geology of a site, particularly as it relates to groundwater characteristics. Also, assesses
the impact a proposed subsurface waste disposal system or other activity will have on the quality of
this groundwater.
4
Hazardous Material: Any gaseous, liquid or solid materials or substances designated as hazardous
by the United States Environmental Protection Agency and/or the Maine Department of
Environmental Protection.
Home Occupation: An occupation or profession carried out for gain by a resident and conducted as
an accessory use in or about the residential dwelling unit. To be considered a home occupation and
not a commercial business, the home occupation must be secondary and incidental to the primary
use of the premises as a residence, be carried on wholly within the principal structure or accessory
structures hereto and be conducted primarily by a member or members of the family residing in the
dwelling unit.
Examples of Home Occupations include; but are not limited to
1. Beauty Shops
2. Office of Physician or dentist
3. Daycare center
4. Woodworking
(The term does not include auto repair or auto body shops)
Impervious Surface: Natural or man-made material on the ground that does not allow water to
penetrate into the soil. Impervious surfaces consist of all buildings, paved parking lots, roads and
sidewalks, and any area of concrete, asphalt, plastic or metal or gravel.
Industrial Use: A use that involves the mechanical transformation of materials into new products,
including manufacture, compounding, assembly or treatment of articles or materials.
In law Apartments - Separate living quarters included in an existing single-family residence for use
by parents, grandparents, or dependents. An in-law apartment shall not be considered an additional
dwelling unit if no expansion of the structure takes place to accommodate the apartment.
Junkyards: As defined by 30-A M.R.S.A. Section 3752.
Leachable Material: Liquid or solid materials that are capable of releasing harmful contaminants.
Multifamily Dwelling: A structure that houses two or more dwelling units as defined.
Off Road Vehicle: Any vehicle not manufactured for on highway use and intended for recreational
purposes.
Petroleum: Oil, gasoline, petroleum products and their by-products, and all other hydrocarbons
that is liquid under normal atmospheric conditions.
Primary Recharge Area: The area contributing most directly to the groundwater source. For the
purpose of this ordinance, the primary recharge area is that area with the Town of Harrison
identified in the Robert G. Gerber report as "Maximum Primary Recharge Area." The primary
recharge area also includes the lateral limits of the aquifer, which is defined as the area of glacial
outwash that extends approximately 1,000 feet to either side of the Bear River.
Recharge Area: The area of land or water that contributes water to an aquifer. For the purpose of
this ordinance, the recharge area of the Bear River Aquifer is comprised of a primary and secondary
recharge area.
5
Safe Yield: The amount of water that can be withdrawn annually from a groundwater source
without producing an undesirable effect. Undesirable effects include depletion of groundwater
reserves, intrusion of low quality water, contravention of water rights and other, such as depletion of
stream flow and local subsidence.
Secondary Recharge Area: The area contributing less directly than the primary recharge area but
which constitutes a significant percentage of total recharge to the aquifer. For the purpose of this
ordinance, the secondary recharge area shall consist of the drainage area of the Bear River in
Harrison and Bridgton as established by topographical high points, excluding the area defined as the
primary recharge area.
Single Family Dwelling: A dwelling designed for or occupied exclusively by one family.
Sludge: Residual materials produced by water or sewage treatment processes and by septic tanks.
Solid Waste: Useless, unwanted, or discarded solid material with insufficient liquid content to be
free flowing. This includes, but is not limited to, rubbish, garage, scrap materials, junk and refuse.
Toxic Substance: Any substance that has the capacity to produce injury, or illness to humans
through ingestion, inhalation, or absorption into the body.
Watershed: The area of contribution to a surface water body. Topographic high points define it.
Section 4. District Boundaries
A. For the purpose of this ordinance, and in order to carry out its regulations, the Bear River
Aquifer Protection District shall be delineated on a tax map titled "Aquifer Protection District Map:
Town of Harrison"
B. A copy of said map will be available for inspection in the Town Office and shall be updated as
new information relevant to the criteria listed below, provided by a Maine Licensed Geologist,
warrants that it be changed.
C. The Aquifer Protection District includes two sub districts.
1. District A consists of the primary recharge area for the acquifer within the Town of Harrison
as defined herein.
2. District B consists of the watershed of the Bear River within the Town of Harrison as
determined by U.S.G.S. maps, exclusive of District A. This area constitutes a secondary
recharge area.
D. Revisions to Map
1. Where the bounds of Aquifer Protection district, or the position of a site in relation to the
District, is in dispute, the burden of proof shall be upon the owner (s) or occupier (s) of the
land in question to show where they should be properly located.
2. No changes to the Aquifer Protection District Map shall be made until the Planning board
holds a public hearing. Notice shall be at least ten (10) days prior to such hearing in a
6
newspaper of general circulation in the Town of Harrison and to all abutters of affected
property. At said hearing the Planning Board shall hear evidence demonstrating why the
boundary of the Aquifer Protection District or sub district shall be changed. Evidence shall
include a report from a geologist licensed in the State of Maine with proven experience in
hydrogeology. The Board shall also notify the Harrison Water District of the hearing at least
fourteen (14) days prior to the date of the hearing. Within thirty (30) days of the hearing, the
Planning board shall decide whether to recommend to the Selectmen that the proposed
Aquifer Protection Map amendment be placed on the next Annual Town Meeting warrant.
3. Any time the Aquifer Protection Map is revised, the date of adoption of the revised map by
the Annual Town Meeting and the signature of the Town Clerk certifying the revision shall be
noted on the map.
E. Revisions to Ordinance
1. No changes to the Aquifer Protection Ordinance shall be made until the Planning Board
holds a public hearing. Notice shall be at least 14 days prior to such hearing in a newspaper of
general circulation in the Town of Harrison. At said hearing, the Planning Board shall hear
evidence pertaining to the proposed changes. The Board shall also notify the Harrison Water
District at least 14 days prior to the hearing. Within 30 days, the Planning Board shall decide
whether to recommend to the Board of Selectmen that the proposed changes be placed on the
next Annual Town Meeting Warrant.
Section 5. District Uses and Space Standards
A. Uses of Land within Districts A and B
Land Use
Zone A
Zone B
1. Residential
Accessory uses
P
P
Single-Family homes
P P
Home occupation
PB PB
Multi-family home
PB
PB
In-Law apartments
PB
PB
2. Commercial
Agriculture
P
P
Animal husbandry other than
Commercial animal feedlots X
PB
Boat, Small Engine, and Motor Vehicle
Service and Repair X PB
Campgrounds X X
Car washes
X X
Commercial uses with non-domestic X X
Waste systems
Dry Cleaning establishments X X
7
Forestry/timber harvesting subject to the P P
performance standards of the Town's
Shoreland Zoning Ordinance within
250 ft of Bear River.
Furniture Stripping
X X
Gas Stations X X
Kennels X X
Photo processors X X
Truck terminals X X
3. Industrial
Sand and gravel extraction
X PB
Junkyard/Automobile graveyard X X
Manufacturing PB PB
Metal plating X X
Sawmills or wood processing plants PB PB
Other industrial uses PB PB
4. Miscellaneous
Cemetery
X X
Disposal or storage of solid waste, X X
Hazardous materials, or leach able
Materials (unless specifically permitted
within the District)
Engineered (wastewater disposal ) system X PB
When accompanied b a full hydrogeological study and
meeting the performance standards herein
Open Space P P
Outdoor recreation, except those which P P
Disrupt the surfaces of hillsides or other
Watershed areas
Footbridge and bicycle paths
P P
Uncontained salt, sand/salt storage piles X X
Wastewater disposal system P P
Use of off-road vehicles
X P
Public Utilities PB PB
Contained salt, sand/salt storage piles X X
Roads and parking areas within P P
impervious surface standards
Application of chemical fertilizer, X P
herbicides or pesticides on more than 1
acres of land
Application of chemical fertilizer X
PB
herbicides or pesticides on more than 5
acres of land
Demolition stump dumps X PB
Subsurface storage of petroleum and other X
X
refined petroleum products with the
exception of household heating oil where
the underground storage tank in full
compliance with volume 2 of the Code
of Maine Rules, 4th Printing, DEP Bureau
of Oil and Hazardous Materials, Ch. 691
8
Regulations for...Underground Storage
Facilities.
Petroleum storage for commercial or
X X
industrial use
Land application of manure on one acre
or more of land X X
Nonresidential pipelines for transmission X X
of oil, gas, or hazardous materials
Aerial spraying of herbicides, pesticides X X
X = Not Permitted
P = Permitted (provided that performance standards contained in Section 8 of this Ordinance are met)
PB = Required Planning Board review according to the procedures and standards contained in the Town of Harrison
Site Plan Review Ordinance
C. Space standards within Zone A
1. Minimum Lot size: 120,000 square feet
2. Maximum Density: One dwelling unit per 120,000 square feet
3. Minimum Road Frontage: 250 feet per lot. Road frontage may be measured at the building
setback line for lots on cul-de-sacs.
4. Minimum Setbacks:
a. Street - 50 feet, Side and rear - 20 feet
5. Maximum lot coverage with impervious surface: 10%
6. Setbacks from Bear River
a. Building - 100 feet
b. Waste Water disposal
New construction - 200 feet
Replacement system - as close to 200 feet as lot will allow
D. Space Standards within Zone B
1. Minimum Lot Size: 40,000 square feet
2. Maximum Density: One dwelling unit per 40,000 square feet
3. Minimum Road Frontage: 150 feet per lot, plus 50 feet for each additional dwelling unit
beyond the first. Road frontage may be measured at the
building setback line for lot on cul-de-sacs.
4. Minimum Setbacks:
a. Building: Front - 50 feet, Side and rear - 20 feet
b. River: 100 feet
c. Septic: New construction - 200 feet from river
Replacement system - as close to 200 ft as lot will allow
5. Maximum lot coverage with impervious surface: 30%
Section 6. Administration and Enforcement
A. Enforcement
1. No activity or land use may be conducted in Zone A or B except in accordance with these
provisions. Failure to conform to these provisions shall constitute a violation and shall be
subject to penalties and actions set forth in this Ordinance.
9
2. In reviewing subdivisions and site plans located entirely or partially within Aquifer Protection
Districts, the Planning Board shall apply requirements and standards of this ordinance to
those of the Subdivision Guidelines or Site Plan Ordinance.
3. For areas within the Aquifer Protection Districts that are governed by the Shoreland Zoning
Ordinance, the more restrictive standards shall be applied.
4. If any portion of a lot is located in Zone A or B, all the land located in Zone A shall be
governed by regulations for Zone A, and the land located in Zone B shall be governed by
regulations in Zone B.
5. Individuals proposing uses permitted in Section 5 shall submit all applicable information
required in Section 7 (submission requirements) to the CEO with a building permit
application. The CEO shall review this information to determine whether the proposed use
or dwelling meets the requirements of the Aquifer Protection District. The CEO shall notify
the Chairperson of the Planning Board and the chairperson of the Harrison Water District
Trustees of any applications for uses proposed in the Aquifer Protection District. The
Harrison Water District Board of Trustees will have 30 days from the postmarked date to
review the application before the permit is issued by the Code Enforcement Officer.
6. The Planning Board (hereafter referred to as "the Board") shall review all other proposed
uses required listed in Section 5.
a. The Board may consult other local boards or groups regarding uses or development in the
Aquifer Protection District such as the Conservation Commission.
b. The board may require an applicant to submit a hydrogeological study examining the
potential impact of the proposed use on groundwater quality. A state Certified Geologist
must prepare the study with proven experience in hydrogeology. The Board may hire an
expert to review all information submitted by the applicant and may charge the applicant
the cost of the consultant.
c. The Board shall notify the Harrison Water District of any applications for uses proposed
in the Aquifer Protection District. The Board shall request Water District review of the
development or use as a condition of its approval.
d. Such information requested by the Board from outside parties shall be incorporated into
the public record and be made available to the applicant.
e. The Board shall, after a public hearing with due notice, approve, deny, or approve with
conditions an application if it makes a positive finding, based on the information presented
that:
The proposed use meets the specific requirements set forth in this
ordinance and will be in compliance with all applicable state and
federal laws:
The proposed use meets all applicable performance standards:
The proposed use will not create the risk of bacterial or viral
contamination of groundwater in Zone A;
Control measures proposed to prevent adverse impacts on water quality
are adequate and reliable;
The use will not involve disposal of solid waste, hazardous materials, or
Leach able materials as prohibited under the terms of the District;
Petroleum stored-on-site will be properly contained so as to prevent
contamination of the groundwater by leaks or spills.
7. The Code Enforcement Officer shall enforce the provisions of the Aquifer Protection District.
The Code Enforcement Officer may, at reasonable hours, with the consent of the property
owner, occupant, or agent, enter on any property for compliance with the provisions of this
District.
8. The Board can require installation and regular sampling of water quality monitoring wells
for any use deemed to be significant actual or potential source of pollution.
10
a. The number, location, and depth of the monitoring wells shall be determined by a licensed
engineer or hydrogeologist chosen or approved by the Town in accordance with
"Guidelines for Monitoring Well Installation and Sampling" (Tolman, Maine Geologic
Survey, 1983).
b. Results from monitoring well samples shall be submitted to the Water District with
evidence showing that the contaminate concentrations meet the performance standards
for pollution levels.
9. For subdivisions located in the Aquifer Protection District, the Planning Board shall apply the
purpose, terms, and criteria of this District to its review. The Board may require submissions
of a hydrogeological study prepared by a State Certified Geologist with proven experience in
hydrogeology, which examines a subdivision's impact on groundwater quality.
10. The code Enforcement Officer is authorized to issue a cease and desist order whenever he
becomes aware of violations of this ordinance. Any person, firm or corporation being the
owner of or having contact or use of any building or premises, who violates this cease and
desist order, or is found guilty of violating any other provisions of this Ordinance, commits a
civil violation is subject to a fine of not less than $100 and not more than $2,500 for each
violation. Each day such a violation is permitted to exist after notification thereof shall
constitute a separate offense.
Section 7. Submission Requirements
A. Applications for permission to carry out any activity in Zone A or B shall be accompanied by a
fee of $25.00 and the following information.
1. Site Plan drawn to a scale no smaller than 1 inch equals 100 feet showing:
a. Aquifer Protection District boundaries if they cross the parcel.
b. Boundaries of the property and abutting streets.
c. Outlines of all buildings.
d. Layout and location of access drives, parking areas and vehicular maneuvering areas.
e. Location of all petroleum storage tanks.
f. Location of buffers, landscaping, and existing vegetation which will be retained.
g. Location and description of storage areas and types of materials to be stored.
h. Location of wastewater disposal systems or public sewer facilities.
i. Location of all public and private water supplies on the property and abutting properties.
A description of the manner in which the applicant shall meet all applicable Performance Standards.
B. Where applicable:
1. A complete list of all chemicals, pesticides, fuels and other potentially toxic or hazardous
materials to be used or stored on the premises in quantities greater than those associated with
normal household use, and a description of measures to provide for control of spills.
2. For animal husbandry operation, a Conservation Plan, approved by the local Soil and Water
Conservation District.
3. For dwellings with subsurface waste disposal systems, a completed site evaluation form
(HHE-200).
C. If required by the Board:
1. A map showing groundwater contours of the seasonal high water table.
2. A hydrogeological study of the proposed use's impact on groundwater quality.
3. Water quality data from on-site monitoring wells.
4. Any other information needed to prove that the use will not adversely affect groundwater
quality.
11
Section 8. Performance Standards
All site plan and subdivision proposals and other proposals for structures, uses and activities within
the Aquifer protection district shall conform to use and space standards of the governing subdistrict
and the following minimum levels of performance.
A. General Standards
1. All such proposals shall be consistent with the need to protect the quality and quantity of
Harrison and Bridgton's groundwater supply.
2. In cases where proposed uses are not listed as permitted or prohibited uses above, the Board
shall make a finding on whether the use is permitted or prohibited based on its similarity or
dissimilarity with listed permitted and prohibited uses and whether its impacts would be
more substantial than that of a low-density residential use.
3. Whenever possible, streets, roads and parking areas shall be designated and constructed so
that reduced application of road salt can occur without creating winter safety problems and
so that runoff from such uses is channeled to avoid or minimize groundwater contamination.
B. Erosion and Sediment Control
1. Erosion and sedimentation shall be minimized by adherence to erosion control management
practices contained in the "Environment Quality Handbook", dated March 1986, published
by the Maine Soil and Water Conservation Commission.
2. For residential subdivisions, commercial and industrial developments and other large-scale
developments, a sedimentation and erosion plan meeting the standards of the Cumberland
County Soil and Water Conservation District shall be prepared by the applicant.
C. Home Occupations
1. Home occupations shall be accessory to a residential use and clearly incidental and secondary
to the residential use of the dwelling unit.
2. No more than two (2) persons other than the residents occupying such dwelling shall be
employed.
3. In no way shall the appearance of the structure be altered or the occupation be conducted in a
manner which would cause the premises to differ from its residential character either in the
use of colors, materials, construction. lighting, or the emission of sounds, noises, smoke, dust,
glare, odors, electrical interference, heat or vibrations.
4. No traffic shall be generated by such a home occupation that would be considered
incompatible in a residential neighborhood, and any need for parking generated by the
conduct of such home occupation shall be met off the street and other than in a required front
yard.
5. Provisions must be made for adequate off street parking requirements based on the
maximum number of users that the home occupation may attract during peak operating
hours, the vehicles of any outside employees, and parking to meet the normal requirements of
the dwelling unit.
6. Evidence shall be provided that the subsurface disposal system on the site can accommodate
the wastewater generated by the home occupation.
12
D. Manure Storage
Agricultural operations must provide manure containment facilities for manure storage.
Facilities must be adequate to hold one year's production and must be covered.
E. Preservation of Landscape
The landscape shall be preserved in its natural state, insofar as is practicable, by minimizing tree,
vegetation and soil removal, retaining existing vegetation wherever possible, and keeping grade
changes consistent with neighboring areas.
F. Runoff
1. For residential subdivisions, commercial and industrial developments and other large-scale
developments, the developer shall submit a storm water runoff plan, showing calculations for
predevelopment and post development runoff for the site for a 25 year, 24 hour frequency
storm, and planned runoff control measures.
2. Unless it can be shown that an increase in runoff will have no off-site impact, peak runoff
from the site in the developed state will not be increased beyond that in the undeveloped state.
G. Subsurface Waste Disposal Systems
1. On-site waste disposal systems shall be designed and located so as to avoid or minimize
groundwater contamination.
2. Disposal of hazardous materials to subsurface waste disposal systems, including organic
solvents designed for cleaning septic systems is prohibited.
3. Engineered Systems in "B" districts shall be reviewed and approved by the Division of
Human Services, Health Engineering Division. In addition, the applicant shall submit to the
Board a full hydrogeological study of the proposed engineered system.
The study shall demonstrate that the development will not increase any contaminate
concentration in the groundwater to more than one-half of the Primary Drinking Water
Standards adopted by the State of Maine. The study shall also demonstrate that the project
will not increase any contaminant concentration in the groundwater to more than Secondary
Drinking Water Standard adopted by the State of Maine, Department of Human Services.
4. Proposals for on-site septic systems within the 200-day travel period of District A will also
require a full hydrological study. The Planning Board may also require hydrological
studies for proposed subdivisions within District A that because of size, type location or
topography are deemed a potential threat to groundwater quality. In reviewing these
studies, the Planning Board shall apply the standard of subsection G.3 above.
D. Sand and Gravel Extraction
1. Pits shall not be excavated lower than five (5) feet above the average seasonal high water
table.
2. Petroleum products shall be kept out of pits. Refueling and oil changes that must be
conducted in the pit shall take place over a containment area constructed to contain the
maximum possible spill from entering the ground.
13
3. Absorbent pads shall be kept on-site to be used immediately should any petroleum products
be spilled on the soil.
4. No hazardous materials shall be used, stored or deposited within the excavation area.
5. Access roads into and around the pit shall not be oiled, salted, or paved.
6. No ditches, trenches, pumping or other methods shall be used to lower the water table to
permit more gravel extraction than could occur under natural conditions.
7. Access to the pit shall be strictly controlled at all times with locking gates, and when the
operations are finished, all vehicular entrances shall be made impassable.
8. Structures and subsurface waste disposal systems shall be sited a minimum seventy-five (75)
feet from the gravel pit slopes in excess of forty (40) percent.
9. Reclamation projects shall whenever possible, use trees for re-vegetation purposes.
Section 9. Nonconforming Uses
A. Structures, uses and lots which were legally existing as of ___________ (effective date of this
Ordinance shall be treated as nonconforming and may continue and be maintained, repaired and
improved.
B. All expansions of structures (outside the Shoreland Zone) nonconforming because of density, lot
size, frontage, and setback shall be permitted as long as they meet the other standards of this
Ordinance and do not make the structure more non-conforming.
C. Expansions of non-residential structures/facilities that are nonconforming because the use
carried out within the structure of facility is prohibited by this Ordinance shall not be permitted.
In cases of undue hardship, the board of appeals may issue a variance for a one-time increase of
no more than fifteen (15) percent of the gross floor area of the existing structure, as long as this
expansion meets the other standards of this Ordinance.
D. Construction of one principal, permitted use on non-conforming lots of record legally in
existence on ____________ (effective date of this Ordinance), is permitted if all other standards
of this Ordinance are met.
E. Expansions of uses or structures in excess of the impervious surface ratio shall only be permitted
in cases of hardship and shall be reviewed by the Board of Appeals as variances.
Section 10. Appeals
A. Administrative Appeals
1. If the Planning Board or Code Enforcement Officer disapproves an application for a building
permit, septic or subsurface sanitary disposal system permit, or any use permit issued under
the authority of this Ordinance, or grants any of these permits subject to conditions that are
objectionable to the applicant or any abutting landowner or any aggrieved party, or when it is
claimed that the provisions of the Ordinance do not apply, or that the true intent of the
Ordinance has been misconstrued or wrongfully interpreted, the applicant, an abutting
landowner, town officials, or other aggrieved party may appeal the decision of the Planning
Board or code Enforcement Officer in writing to the Board of Appeals, within thirty (30) days
of the Planning Board's or the code Enforcement Officer's decision. The Board of Appeals
may reverse the Planning Board's or the Code Enforcement Officer's decision after holding a
public hearing if a finding is made that the decision was clearly contrary to the provisions of
the Ordinance or was unsupported by substantial evidence. Public hearings shall be held in
accordance with the provisions of M.R.S.A. Title 30-A Section 2691 as amended.
Administrative appeals shall be administered according to the provisions of Section 16 H. (3)
of the Harrison Shoreland Zoning Ordinance.
14
2. If the Planning Board disapproves an application for subdivision which is subject to the
provisions of the Ordinance, or approves an application for subdivision subject to conditions
that are objectionable to the applicant or any abutting landowner or any aggrieved party, or
when it is claimed that the provisions of the Ordinance do not apply, or that the true intent of
the Ordinance has been misconstrued or wrongfully interpreted, an appeal from the order of
decision of the Planning Board may be taken by the applicant, an abutting landowner, town
officials, or any aggrieved party to Maine Superior Court in accordance with Rule 80B of the
Maine Rules of Civil Procedure.
B. Variances
In certain instances where a literal application of the standards of this Ordinance would
cause the imposition of an undue hardship, as defined in M.R.S.A. Title 30-A Section 4353 as
amended, upon an applicant, the Board of Appeals may grant a variance to these standards.
A variance shall not be granted by the Board of appeals unless and until a written application
for a variance has been filed and reviewed by the Board of Appeals in accordance with the
provision of the Harrison Shoreland Zoning Ordinance.
Section 11. Legal Provisions
A. Authority
This Ordinance has been prepared in accordance with the provisions of Revised Statutes of
Maine, as amended.
B. Title
This Ordinance shall be known and cited as the Bear River Aquifer Protection Ordinance.
C. Interpretation
Interpretation of what may not be clear in this Ordinance shall be according to the intent of the
Ordinance and the Comprehensive Plan.
D. Conflict within this Ordinance or with other Ordinances
Whenever a provision of this Ordinance conflicts with or is inconsistent with another provision of
the Ordinance or any other Ordinance, regulation or statue, the more restrictive provision shall
control.
E. Separability
Should any section or provision of this ordinance be declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of this Ordinance.
F. Effective Date
The effective date of this Ordinance is __June 10, 2009