TOWN OF HARRISON
TOWER
ORDINANCE
ENACTED: JUNE 9, 1999
A True Copy
ATTEST: ____________________________
Judith E. Colburn, Town Clerk
TOWN OF HARRISON
Proposed Telecommunications Towers, Antennas and Associated Facilities
Ordinance
This Ordinance is enacted pursuant to the Municipal Home Rule Authority (30A
MRSA 2101 et seq), Municipal Ordinance Authority (30A MRSA 3001 et seq), and
the Town of Harrison Comprehensive Plan.
SECTION 1. PURPOSE
This Ordinance is designed and intended to balance the interests of the residents of
the Town of Harrison, telecommunications providers, and telecommunications
customers in the siting of telecommunications facilities within the Town. These
purposes are also intended:
A. To minimize the adverse impact of such facilities including visual impacts,
environmental impacts, impacts to historically significant areas, health and
safety
impacts and property value impacts.
B. To encourage co-location of carriers and minimize the total number of towers
located
within the town.
C. To permit the construction of new towers only where all other reasonable
opportunities
have been exhausted.
D. To encourage the users of towers and antennas to configure them in a way that
minimizes the need for additional towers in the Town of Harrison.
E. To provide for the removal of structures which are no longer being used for
telecommunications purposes.
SECTION 2. DEFINITIONS
Alternative Tower Structure - shall mean clock towers, bell steeples, light poles and
water towers, and similar alternative-design mounting structures that camouflage
or conceal the presence of antennas or towers.
Antenna - shall mean any exterior apparatus designed for commercial transmission
of telephonic, radio, or television, or similar communications through the sending
and/or receiving of electromagnetic waves.
Co-Location - shall mean the location of more than one telecommunications facility
(use) on a tower or alternative tower structure.
FAA - shall mean the Federal Aviation Administration.
FCC - shall mean the Federal Communications Commission.
Height - shall mean, when referring to a tower or other structure, the distance
measured from ground level to the highest point on the tower or other structure,
even if said highest point is an antenna.
Telecommunications Facility - shall mean any structure, antenna, tower, or other
device which provides radio/television transmission, commercial mobile wireless
services, unlicensed wireless services, cellular phone services, specialized mobile
radio communications (SMR), common carrier wireless exchange access services,
and personal communications service (PCS) or pager services. Telecommunications
Facilities shall be considered a principal use. Pre-existing accessory use
towers/antennas shall be exempt from this definition.
Threshold Height - shall mean the height, as defined above, below which a
telecommunications facility does not need review and approval as a special
exception, unless otherwise noted herein.
Tower - shall mean any structure, whether freestanding or in association with a
building or other permanent structure, that is designed and constructed primarily
for the purposes of supporting one or more antennas, including self-supporting
lattice towers, guy towers, or monopole towers. The term includes radio and
television transmission towers, microwave towers, common-carrier towers, cellular
towers, alternative tower structures, and similar structures.
SECTION 3. PERMITS REQUIRED
A. All new telecommunications facilities which exceed 35 feet in height in the
shoreland
zone and all towers exceeding 70 feet in all other areas must apply for, acquire
and
conform to the requirements of a permit from the Planning Board as more
particularly
referred to in Section 4 below.
B. New telecommunications facilities below those threshold heights shall be
considered a
permitted accessory use, and shall need only to apply for and receive a building
permit
from the Code Enforcement Officer, if such telecommunications facility is
accessory to a
principal use on the lot and is used for the private communications of the owner
of or
business location on the lot.
C. All telecommunications facilities proposing to locate on existing tower or
alternative
tower structures below the threshold heights as set forth above shall apply for
and
conform to the requirements of a building permit from the Code Enforcement
Officer.
D. All other telecommunications facilities below the threshold heights as set forth
above
shall apply for and conform to the requirements of a building permit from the
Code
Enforcement Officer.
SECTION 4. APPLICATION PROCEDURE
A. All applications under this section shall be reviewed by the Planning Board of
the Town
of Harrison in accordance with the procedure, standards and submission
requirements
set forth below and of the Harrison Site Plan Review Ordinance and the
Harrison
Shoreland Zoning Ordinance as applicable.
B. All activities or construction that require a permit in accordance with this
Ordinance
shall be submitted in an application to the Code Enforcement Officer. The Code
Enforcement Officer, after reviewing the application to determine if it contains
sufficient information as required below, will schedule the completed application
for
review at the next available meeting of the Planning Board.
C. Each application for a permit under this Ordinance shall submit a scaled plan
and
application in accordance with the following submission requirements:
1. Location of the proposed structure, including map/lot number and street
address.
2. Name of owner or operator of the telecommunications facility and owner of
property.
3. Proof of right, title and interest to use the property on which the
telecommunications
facility is proposed.
4. Name of company (ies) responsible for constructing and/or maintaining the
telecommunications facility.
5. Date the telecommunication facility, in cases of co-location, was initially
constructed or
is proposed to be constructed.
6. A description and construction detail of the telecommunication facility,
including: plot
plan identifying location of the tower on the property; dimensions of the tower;
structural supports, if any: lighting; color; and equipment located on the
structure, if
any. This description shall also identify any accessory structures that are
essential to
operation of the telecommunication facility.
7. A topographical map, drawn at a scale of 1 inch = 50 feet (or other appropriate
scale as
determined by the Planning Board) of the property proposed as location of the
structure. The topographic map shall identify: accurate contours at not less
than 5
foot intervals (or other dimensions of the property; appropriate scale as
determined by
the Planning Board) existing vegetation, particularly noting height, diameter,
density,
quality, and type (deciduous or evergreen) of existing trees, wetlands,
floodplains,
streams and open bodies of water; ledge outcrops; soils data, medium intensity;
all
existing structures on the property; and any right-of-ways, easements, or
similar
encumbrances on the property; and other significant features.
8. A locus map drawn at a scale of not less than 1 inch = 100 feet (or other
appropriate
scale as determined by the Planning Board) that identifies all properties, all
residences,
all non-residential structures, all roads and the natural topography (vegetation
and
contours at 20 foot intervals) of the area located within a radius of 1000 feet of
the
proposed telecommunication facility location.
9. A landscape plan prepared at a scale of 1 inch = 50 feet (or other appropriate
scale as
determined by the Planning Board) that identifies how the applicant shall
satisfy
landscape, screening and buffering requirements.
10. A visual impact analysis prepared by a landscape architect or other qualified
professional that quantifies the amount of visual impact on properties located
within
500 feet, within 2,500 feet and within 2 miles of the proposed telecommunication
structure. This analysis will include recommendations to mitigate adverse
visual
impacts on such properties.
11. An analysis prepared by a qualified professional that describes why this site and
structure is critical to the operation for which it is proposed. The analysis shall
address, at a minimum; existing and proposed service area maps; how this
structure is
integrated with other company operations, particularly other structures in
Harrison
and surrounding communities; future expansion needs in the area; the affect on
company operations if this structure is not constructed in this location; other
sites
evaluated for location of this structure and how such sites compare to the
proposed
site; other options, if any, which could be used to deliver similar services,
particularly if
the proposed equipment can be co-located (shared use) on an existing structure;
and
an analysis to the projected life cycle of this structure and location.
12. Certification by a structural engineer that construction of the structure shall
satisfy all
Federal, State and Local building code requirements as well as be able to satisfy
the
needs of maximum permitted co-location at the site (as approved by the
Planning
Board) per the height limits of the applicable zoning district.
13. Payment of all required performance guarantees as a condition of plan
approval - with
a note on the plan so stating.
D. The Planning Board has discretion to request additional information to proceed
with
the review process the cost of producing such additional information to be borne
solely
by applicant.
E. All applications shall be accompanied by fees as set by the Town of Harrison.
SECTION 5. REVIEW PROCEDURES
A. The Planning Board shall make its decision to approve, approve with conditions,
or deny a permit within 90 days after review begins or within another time limit as
may be mutually agreed to by the Board and the Applicant.
B. The Planning Board shall schedule a public hearing within forty-five (45) days of
taking up the application. Notification of the hearing shall be provided:
1. By the Applicant in writing, at least ten (10) days prior to the hearing, to all
owners of property that directly abut or are located within one thousand (1,000) feet
of any property line of the property for which the permit is requested. (Notice to
the owners within the first 500 feet shall be by certified mail the remaining notice
shall be by first class mail). Notice shall also be given by certified mail to any town
located within 1,000 feet of the proposed telecommunications facility. The applicant
also shall present proof of such notification satisfactory to the Code Enforcement
Officer. The notification shall include: the name of the applicant location of the
property, a brief description of the project, and a plot plan identifying the proposed
site layout in relation to nearby streets and properties.
2. By the Town posting notice of such hearings in the Municipal Office a minimum
of ten (10) days in advance of the hearing.
3. By the Town advertising in a newspaper of general circulation within the Town
notice of the hearing a minimum of ten (10) days in advance of the hearing.
C. The Planning Board will, after a public hearing and review of the application,
issue Findings of Fact and Conclusions which outline the reasons it approves,
approves with conditions, or denies the telecommunication structure application.
The Board shall use the standards identified in the Harrison Site Plan Review
Ordinance as well as those noted below (Section VI) to make its decision. The
Planning Board may impose conditions in any permit issued hereunder to ensure
conformity with the purposes of this Ordinance and the Town of Harrison
Comprehensive Plan.
SECTION 6. REVIEW GUIDELINES
A. The Planning Board will be guided in its considerations by the following
standards:
1. Height of proposed tower or other structure does not exceed that which is
essential for its intended use and public safety.
2. Proximity of tower to residential development or zones does not create undue
impact on the value or use of property (ies) in such residential areas.
3. Nature of uses on adjacent and nearby properties and the degree of
incompatibility of the proposed construction or activity with such adjacent and
nearby uses.
4. Surrounding topography of the proposed site and the degree to which any
specific topographical features render the proposed site incompatible with the
purposes of this Ordinance, or require special consideration (s) as to drainage,
erosion and sedimentation control.
5. Surrounding tree coverage and foliage and the extent to which the proposed site
or construction would disturb or diminish such coverage and foliage, or require
special consideration (s) as to landscaping or buffering.
6. Design of the tower, antenna, or facility with particular reference to design
characteristics that have the effect of reducing or eliminating visual obtrusiveness
including the need for landscaping or other site improvement (s).
7. The safety and utility of any proposed ingress and egress to the site.
8. Availability of suitable existing towers and other alternative tower structures or
locations as discussed in Section 7.
9. Visual impacts on view sheds, ridge lines, and other impacts resulting from tower
location, tree and foliage clearing and placement of incidental structures, powerlines
and access roads.
10. Visual impacts on the view from any public park, natural scenic vista, historic
building or major view corridor.
11. That the proposed facility/tower/dish be constructed in such a manner not to
result in needless height, mass, and guy-wire supports with documentation having
provided and review regarding the design capacity and/or the remaining co-location
capacity of the tower/facility.
12. The proposed facility will minimize potential effects on wildlife.
B. The Planning Board may use any technical and professional services necessary
to assist in their review of a Facility. Services may include but are not limited to:
an analysis of shared use, an analysis of visual impact, an analysis of the structure
satisfying federal and state requirements, an analysis of alternative sites, and other
issues required to satisfying requirement of this section. The applicant shall be
required to pay all costs involved with these professional services.
C. The code Enforcement Officer may use professional and technical services to
inspect construction of an approved project. The applicant shall pay all costs
incurred for these inspection services.
SECTION 7. PERFORMANCE: STANDARDS/DIMENSIONAL
REQUIREMENTS
A. Height
Towers, antennas and facilities shall not exceed a height of 150 feet except that
where evidence of acceptable design and co-location is provided to the Planning
Board, an additional 25 feet of height per each additional user is permitted, (based
upon signed agreements to be filed with the Code Enforcement Officer prior to the
issuance of any building permit). No telecommunications facility shall exceed a
height of 200 feet.
B. Setbacks
1. All telecommunications towers shall be setback from the lot lines of any
residential use or residential zoning district a distance equal to at least 125% of the
tower height. The tower height used shall be the maximum design height approved
for the site.
2. Tower, guys and accessory facilities shall meet the minimum zoning district
setback requirements.
C. Aesthetics, Landscaping, Buffers & Fencing
1. Towers shall have a galvanized steel finish or be painted a neutral color so as to
reduce visual obstructiveness.
2. All telecommunications structures shall maintain the required setbacks as
undisturbed vegetated buffers, except for the access road. The Planning Board may
require additional plantings in the buffer area to enhance the quality and
effectiveness of the buffer area to serve as a visual screen. The size and quantity of
plantings shall be subject to Planning Board approval.
3. At a tower site, the design of the buildings and related structures shall, to the
extent possible, use materials, colors, textures, screenings and landscaping that will
blend the tower facilities to the natural settings and built environment.
4. Towers shall not be artificially lighted, unless required by the FAA or other
Federal or State authority. If lighting is required, the Planning Board may review
the available lighting alternatives and approve the design that would cause the least
disturbance of the surrounding properties and views.
5. Road access to the telecommunications structure shall be so located to minimum
size necessary to allow safe access.
6. The base of a telecommunications tower may not be located in a wetland or
floodplain.
7. A security fence or wall not less than eight (8) feet in height from the finished
grade shall be provided around the tower. Access to the tower shall be through a
locked gate.
D. Investigation of Existing Alternative Towers, Sites & Structures
Applicants shall identify all existing and proposed (on file in the Municipal Office)
towers, including their heights, located in the town within one mile of the town
boundaries. Applicants must provide evidence of the lack of antenna space on all
such towers, (except in cases where tower access is denied by tower owner), and
shall identify other tower structures and sites which have been investigated as an
alternative to constructing a new tower. Applicant shall address the use of co-
location and/or other alternative tower structures and shall demonstrate that they
cannot provide adequate communication service utilizing such existing towers or
structures.
E. Co-Location
The applicant and owner shall allow other future wireless service carrier, using
functionally equivalent personal wireless technology to co-locate antennae,
equipment and facilities on a telecommunication tower and site, unless satisfactory
evidence is presented and the Planning Board concurs that technical constraints
prohibit co-location. Space shall be provided at no charge to public agencies namely
police, fire, ambulance, communications and Highway if requested at the time of
review by the Planning Board.
F. Other Requirements
1. Building Code and Safety Standards - To ensure the structural integrity of
telecommunications facilities, the owner shall ensure that it is designed, constructed
and maintained in conformance with application Federal, State and Local building,
electrical and safety codes.
2. Advertising - No advertising or signage is permitted on telecommunications
facilities.
SECTION 8. PERFORMANCE GUARANTEES AND REMOVAL OF
ABANDONED/UNUSED FACILITIES GENERAL GUARANTEE
A. No building permit may be issued until the applicant has filed a performance
guarantee with the Town Manager equal to 100% of the cost of completing the
following improvements;
1. The construction of any drainage systems involving piping, culverts, or retention
or detention facilities; and
2. The construction of erosion and sedimentation control measures or landscaping
required to meet the standards of this section; and
3. other site improvements requires by the Board to meet the standards of this
section.
B. Removal of Abandoned/Unused Facilities
1. The owner of a telecommunications facility shall be required to remove the tower
should it not be used for the use or uses approved for a period of twelve (12)
consecutive months. An applicant for a permit under this sections shall post a
performance guarantee with the Town prior to obtaining a permit that is equal to
125% of the cost of removing the structure.
2. The performance guarantee covering such removal shall be for a minimum term
of five years. It must contain a mechanism, satisfactory to the Town, for review of
the cost of removal of the structure every five years, and a mechanism for
increasing the amount of the guarantee should the revised cost estimate so
necessitate.
SECTION 9. HAM RADIO
1. Amateur Radio
This ordinance shall not govern any tower, or the installation of any antenna that is
owned and operated by a federally-licensed amateur radio station operator and the
tower or antenna is used for the exclusive purpose of amateur radio operations.
2. Citizen Band Radios
This ordinance shall not govern the installation of any antenna that is used for the
exclusive purpose of facilitating the use of a Citizen Band Radio.
3. Receive-Only Antennas
This ordinance shall not govern any tower, or the installation of any antenna that is
used exclusively for receive only antennas, except any towers in this section shall be
limited to (70) feet in height.
SECTION 10. ENFORCEMENT
Any construction of or on or use of any premises for telecommunications purposes
as set forth above without first obtaining a permit as required hereunder, or any use
of any site or facility not in compliance with the terms and conditions set forth in
any permit issued hereunder, or any material misstatement of fact in any
application or supporting documentation discovered subsequent to the issuance of
any permit hereunder, or any failure to comply with and maintain the performance
guaranties and/or removal requirements set forth hereunder, or any failure to
observe and comply with any provision of this ordinance, shall be deemed a
violation of this Ordinance. This Ordinance shall be enforced, and any violations
hereof abated, by the municipal officers of the Town of Harrison or their duly
authorized designees, and shall be enforceable by and under, and subject to all the
terms, fines and penalties of 30A MRSA 4451 and 4452, as amended, which are
incorporated herein by reference.
SECTION 11. APPEALS
Any appeal by the aggrieved party with standing from any decision of the Code
Enforcement Officer or the Planning board to approve, approve with conditions or
deny any application hereunder shall initially be to the Harrison Board of Appeals,
said appeal to be filed within thirty (30) days of the decision, action or failure or
refusal to take action complained of. Any appeal shall be governed by the
provisions of 30A MRSA 2691.
SECTION 12. SEPARABILITY
If any section, part of a section or any provision of this Ordinance is declared by a
court of competent jurisdiction, invalid or unenforceable such declaration shall not
affect the validity or enforceability of the Ordinance as a whole, or any part or
provision other than that specifically declared to be unconstitutional, invalid or
unenforceable.
SECTION 13. NO RETROACTIVE EFFECT
This Ordinance does not render illegal any structure, facility or use which legally
existed or was under active construction at the effective date of this Ordinance.
Permits issued prior to the adoption of this Ordinance remain valid for a period of
one year from the initial date of issuance.
SECTION 14. AMENDMENT
This Ordinance may be amended by a vote of a Town Meeting, upon a town meeting
warrant article submitted by the Planning Board after public hearing.
SECTION 15. EFFECTIVE DATE
This Ordinance takes effect and is in force as of the date of its enactment by a duly
called annual or special Town Meeting.