ic TOWN OF HUDSON
as a 2150 Hudson Road
wameay i Hudson, Maine 04449
A 1855 VW Phone: 207-327-1284 » Fax: 207-327-2870
ELECTRIC TRANSMISSION LINE CORRIDORS AND FACILITIES ORDINANCE
Tat
on yA
a So
ps anaes wt
THE ENACTING AUTHORITY FOR THIS ORDINANCE IS THE VOTING MAJORITY OF THE
CITIZENS OF THE TOWN OF HUDSON MAINE ON THIS DATE: {O| 2 \ AO
a ATTESTED: Zane ea
Town Clerk
TABLE OF CONTENTS
I. Title ------~--------------~-------- 22 === nnn nn 3
UI. Authority ------------------------------2n2mn nero aann nan ann ncn 3
iil. PUIPOS€ -~-------------------------- += 0 nnn nnn nnn nnn nnn nnn nnn mene nnn 3
IV. Applicability ---------------------------------------------------------------- 3
Vv. Effective Date ----------------_-_-__-____--------------------------------------_ 3
Vi. Fee Schedule ----------------------------------------------~----------nnnnnn--
A. Application Fees ------------------------------------------------------------ 3
B. Escrow Fund Fees ------------------------------------------------__ 4
VIL. Enforcement -----------------------------==+- 22m nnn nnn nnn nnn nnn nnn 4
Vil. Review Criteria and Compliance Standards for Electric 5
Transmission Line Corridors and Facilities------------------------------
IX. Public Health and Safety Standards---------------------------------------._ 5-6
A. A. Stray Voltage-------------------------------------------------------------------_ 6
B, 8. Fire and Extraordinary Events------------------------------------------- 6
C. C. Maintenance--------------------------------------- 2m nnn 6
X. Environmental Standards ---------------------------------------------- 7
Xl. Financial Standards ----------------------------------------------------------_ 7-8
Xi. Decommissioning Standards ----------------------------==+-=------------- 8-9
XIII. Permit Submission Requirement and Procedural Review 9-12
Standards -------------------------+---- === === === noon
XIV. Conflict and Severability ------------------------------------------------- 12
XV. Amendments ------------------------------------------------+-==- 222m nnn 12
XVI. Definitions ---------------------------------------------------------------------_ 12-13
Page 2 of 13
I. Title
This Ordinance shall be known and cited as the Town of Hudson "Electric Transmission Line
Corridors and Facilities Ordinance" (hereinafter referred to as "this Ordinance")
il. Authority
This Ordinance is adopted pursuant to the enabling provisions of Article Vill, Part 2,
Section 1 of the Maine Constitution; the provisions of Title 30-A M.R.S. Section 3001, and
the provisions of the Planning and Land Use Regulation Act, Title 30-A M.R.S. Section
4312 et seq.
i. Purpose
The purpose of this Ordinance isto provide a set of standards for the construction and
expansion of Electric Transmission Line Corridors and Facilities in the Town of Hudson,
and to ensure that Hudson can continue to fairly and responsibly encourage orderly
growth and development while protecting the Town's rural character; and to safeguard
economic, agricultural, forest and scenic resources from development which threatens
those resources. These standards are also intended to:
1. Minimize the adverse impacts of electrical transmission lines on surrounding land
use, including visual impacts, environmental impacts, impacts to historically
significant areas, health and safety impacts, and property value impacts.
2, Ensure that the Transmission Corridor does not land-lock any property.
3. Allow the Town to protect public health, safety, and welfare.
4. Support the goals and policies of the Town's Comprehensive Plan.
Iv. Applicability
This Ordinance applies to all Electric Transmission Line Corridors and Facilities up to 46 kV in
the Town of Hudson proposed to be constructed or expanded after the effective date of
this Ordinance.
Vv. Effective Date
This Ordinance is effective upon adoption at a Town Meeting.
Vi. Fee Schedule
A. Application Fees
' All applications for Electric Transmission Line Corridors and Facilities shall make
payable a non-refundable fee of $2500to the Town of Hudson.
Page 3 of 13
B. Escrow Fund Fees
See Section 12: Financial Standards for any applicable escrow fees.
Vil. Enforcement
A. It isthe Code Enforcement Officer's duty to enforce the provisions of this Ordinance.
If the Code Enforcement Officer ("CEO") shall find that any provision of this
Ordinance is being violated, the CEO shall notify in writing the person responsible for
such violation, indicating the nature of the violation and an ordering of the action
necessary to correct it, including the discontinuance of illegal structures, illegal work
being done and abatement of nuisance conditions. A copy of such notices shall be
submitted to the Town Office and maintained as a permanent record.
B. When the above action does not result in the correction or abatement of the
violation or nuisance condition, the Town Select Board, upon notice from the Code
Enforcement Officer, are hereby directed to institute any and all actions and
proceedings, either legal or equitable, including seeking injunctions of violations and
the imposition of fines, that may be appropriate or necessary to enforce the
provisions of this Ordinance in the name of the Town of Hudson
1. The CEO shall keep a complete record of all essential transactions, including
applications submitted, revocation of permits, appeals, court actions, violations
investigated, violations found, and fees collected. Any violation of this Ordinance
shall be deemed a nuisance. Any person, including but not limited to a landowner
or easement owner, or their agents or a contractors, who violates any provision or
requirement of this Ordinance shall be penalized in accordance with Title 30-A
M.R.S. Section 4452 or any other legal regulatory guidance of local, state or federal
agencies.
2. The Code Enforcement Officer shall investigate all complaints of alleged violations
of this Ordinance.
3. Development of any kind without Planning Board Approval shall be a violation of
law. Development includes, but not limited to, excavation, adding fill, grading or
construction of roads, grading land or lots, removal of trees or vegetation within
the proposed corridor, or commencement of construction or structures which
requires a plan approved as provided in this Ordinance.
4. The Code Enforcement Officer shall conduct on-site inspections at their discretion
to ensure compliance with all applicable laws and conditions attached to permit
approvals.
VII. Review Criteria and Compliance Standards for Electric Transmission Line Corridors and
Page 4 of 13
Facilities
An ETLFC shall not adversely affect the general health, safety or welfare of the residents
of Hudson, and shall not adversely affect the environment or wildlife, and shall comply
with the following criteria:
This Ordinance applies to all ETLCFs, as defined herein, proposed to be constructed and
operated after the effective date of this Ordinance.
It shall be a violation of this Ordinance to begin construction or operate an ETLCF, as
defined herein, without a permit:
1, It shall be a violation of this Ordinance to construct or expand an ETLCF withan
operating capacity over 46 kV.
2. It shall be a violation of this Ordinance to construct or erect any infrastructural
components for an ETLCF that exceed 70 feet in height.
3. Underground power and transmission lines shall be buried at a depth consistent
with state public utility engineering standards to prevent transient ground
currents and stray voltage.
4, The burden of compliance with all aspects of this Ordinance is on the Applicant and
the Owner/Operator of the ETLCF. Approva! of a permit by the Planning Board
does not abrogate or reduce the responsibility of the Applicant or the
Owner/Operator to comply with this Ordinance.
IX. Public Health and Safety Standards
A. Stray Voltage Assessment and Requirements
1. An application for ETLCF shall include reports of stray voltage analysis in
accordance with this section. The Applicant shall conduct and include a report
of a pre-construction stray voltage test on all occupied structures located
within one half (0.5) mile radius of the project parcels. The tests shall be
performed by a Planning Board approved investigator, using 2 protocol which
is also approved by the Planning Board and paid for by the Applicant. A report
of the tests shall be provided with the permit application and shall be
provided to the owners of all property included in the study area. The
Applicant shall seek written permission from property owners prior to
conducting testing on such owners' property. The Applicant shall not be
required to perform testing on property where owners have provided written
refusal to grant permission to conduct the testing.
2. Following construction of the ETLCF, and within one year after commencing
Page 5 of 13
operation, the Applicant shall conduct a post construction stray voltage test
on all occupied structures located within one half (0.5) mile radius of the
project parcels. The tests shall be performed by a Planning Board approved
investigator, using a protocol which is also approved by the Planning Board
and paid for by the Applicant. A report of the tests shall be provided with the
permit application and shall be provided to the owners of all property
included in the study area. The Applicant shall seek written permission from
property owners prior to conducting testing on such owners' property. The
Applicant shail not be required to perform testing on property where owners
have provided written refusal to grant permission to conduct the testing.
3. The Applicant or subsequent Owner/Operator shal! provide neutral isolation
devices to property owners where testing reveals neutral-to-earth voltages
more than one haff (0.5) volts caused by the ETLF project.
4. The Owner/operator shall be responsible for all costs incurred with the pre-
and post- construction tests and repairs.
B. Fire and Extraordinary Events
1. Fire Prevention: An Application for a permit to construct an ETLCF shall include
a Fire Prevention and Fire Fighting Plan that has been approved by the Town of
Hudson Fire Chief. The plan shall include a list of hazardous materials that may
be encountered.
2. The Owner/Operator of any ETLCF shall notify the Town of Hudson Planning
Board of any "extraordinary event(s)" within 24 hours of that event.
Extraordinary events shall include but not be limited to catastrophic
component failure, fire, or injury caused by the ETLCF or any other event that
affects the public health and safety of the town or its residents.
C. Maintenance
1. Prior to energizing any ETLCF a written Operations and Maintenance plan shall
be submitted to and approved by the Town Planning Board, which shall
include a vegetation management plan for all land within the project
boundary.
2. Vegetation management for all land within the project boundaries shall be
performed by mechanical means and without the use of chemical herbicides
and pesticides.
X. Environmental Standards
Page 6 of 13
A. ETLCF projects shall be designed, constructed, and maintained so as to avoid
undue adverse impacts to groundwater, wells and aquifers. The Planning Board
shall require as a condition of issuing a permit for an ETLCF that a pre-construction
baseline study of all wells, springs, and other water sources within two hundred
fifty (250) feet of the project boundary site be conducted. The study shall be
designed and carried out by a water quality professional selected, contracted,
and paid for by the Applicant but approved by the Planning Board in writing.
B, Two years after completion of construction of an ETLCF for which the Planning
Board has required a pre-construction baseline water quality study as described
in Section 11. i. of this Ordinance, a post construction water quality study of all
wells, springs and other water sources within two hundred fifty (250) feet of the
project boundary site. The study shall be designed and carried out by a water
quality professional selected, contracted, and paid for by the Applicant but
approved by the Planning Board in writing. If degradation or contamination is
found to have occurred, fines and/or permanent remedies as required by the
Town of Hudson, or the State of Maine shall be the responsibility of the
Owner/Operator.
c. The Owner/Operator of the ETLCF shall not a!low or undertake any blasting
without notifying the Town of Hudson and submitting a blasting plan in accordance
with the latest DEP and MSHA standards. The blasting plan shall be reviewed
and approved by the Hudson Planning Board before any blasting takes place.
Forty-eight {48} hour notice shall be given to all residents within a two-mile
radius of the blasting area (measured horizontally) before blasting can take place.
Xl. Financial Standards
A. An Applicant for development of an ETLCF shall provide evidence satisfactory to the
Town of Hudson Planning Board that the project is financially viable. Evidence of
financial viability shal! include:
1. A budget for the construction of the project.
2. Proof of adequate financing for all aspects of the construction.
3. Owner(s)/Operator(s) of the ETLCF shall be held responsible for all liability
and expenses related to and incurred or created by the existence of the
ETLCF.
B. In reviewing an application and/or ongoing project operations for compliance with
this Ordinance, The Planning Board and/or CEO may, at their discretion, retain
professional services as necessary to assist with its review, including but not limited
Page 7 of 13
to those of an attorney, engineer, biologist, land use planner or other professional. If
the Planning Board deems that such services are indeed necessary, they shall inform
the Applicant who will then have fourteen (14) days to deposit in a joint escrow
account with the Town of Hudson the sum of $50,000 as partial payment towards
such expenses.
C. Ifsucha fund is established and the balance of the funds falls below $25,000 the
Applicant, upon notice shall submit an additional $25,000 to replenish the fund. If, at
any time after such notification, the balance of this fund stays below $25,000 for a
period of 30 days, the Application or Operational License shall be considered to
have been withdrawn. The escrow account shall remain in service after completion of
the transmission corridor to reimburse the town for all expenses incurred from
responding to any issues related to the transmission corridor. If any delay in
replenishing the fund generates a delay in reviewing the application or operations,
thenthe deadline for completing the review is extended accordingly.
Xi. Decommissioning Standards
A. The Owner/Operator of an ETLCF shall at their own expense be responsible for the
complete decommissioning of the project and site restoration if the ETLCF ceases to
transmit electricity for a period of twelve (12) consecutive months. Abandonment
will be grounds for immediate decommissioning.
B. Decommissioning shall include timely removal and disposal outside the Town of
Hudson of all parts of the project in accordance with local, state, and federal laws and
regulations. Areas of disturbed earth shall be graded, seeded or otherwise re-
vegetated following guidelines provided by the CEO.
C. All maintenance and downtime of all ETLCFs, or any other situation leading to the
interruption of electricity transmission by the ETLCF shall be promptly reported to
the Municipal Officers of the Town of Hudson.
D. A professional engineer shall be selected, contracted, and paid for by the Applicant
but approved by the Planning Board in writing to estimate the total cost of
decommissioning without consideration of the salvage value of the equipment. No
permit for a project shall be issued until decommissioning funds in the form of a
performance or surety bond, letter of credit or other form of financial assurance
approved by the Town of Hudson Planning Board has been provided. If a bond is
used, such bond shall be issued by an entity listed on the U.S. Treasury Department
Circular 570 or successor document.
E. Estimates, as described above, shall be redone annually every five (5) years after the
anniversary of the granting of a project permit and the Owner/Operator of the
project shall be required to maintain decommissioning funds that are at least equal
to the most recent estimate.
Page 8 of 13
F. If the Owner/Operator of the project does not complete decommissioning within
the time prescribed in this Ordinance, the Town of Hudson may take such action as
necessary to secure the posted decommissioning funds and to ensure completion of
the decommissioning.
G. Decommissioning funds shall not be released except upon written approval of the
Town of Hudson Select Board.
XII. Permit Submission Requirement and Procedural Review Standards
A. Initial Application Submission Requirements and Review Process
An initial application for a Permit to construct or expand an ETLCF shall include the
following:
1, Applicant's name, address and contact information.
2, Acomplete and detailed site plan including all characteristics of the proposed
project.
3. Corridor of proposed transmission line. The person filing a petition under this
section for approval of a proposed transmission line shall submit a map to the
Planning Board with its application. The map must:
a. Be available to the public at the offices of the commission and at the
local town office where any portion of the proposed transmission line is to
be located; (PL 1991, c. 640, §3 (AMD).]
b. Indicate the proposed corridor or corridors of the transmission line and a
description of any planned equipment and facilities to be placed there;
and [PL 1991, c.) 640, §3 (AMD).] c. and be prepared in cooperation with
the appropriate natural resource protection agencies and the affected
municipalities. [PL 1991, c. 640, §3 (NEW).] [1999, c. 398, Pt. A, §46 (amd);
§§104, 105 {aff).] [PL 2007, c. 148, §4 (AMD).)
4, Evidence that the Applicant owns the subject land or has a satisfactory land
easement for all the land associated with the ETLCF project.
5. Evidence that the project as proposed has been presented to and approved
by the following agencies: Maine Natural Areas Program, Maine Department
of Inland Fisheries and Wildlife, Maine Historic Preservation Commission, the
Maine Department of Transportation, Maine Department of Agriculture,
Conservation & Forestry, Maine Department of Environmental Protection and
Maine Public Utilities Commission
6. Awritten summary prepared by a qualified engineer detailing all required
Page 9 of 13
permits for the construction of an ETLCF.
7. For all required permits listed in the preceding sub-paragraph, the Applicant/
Operators shall submit all required permits issued by all local, state, and
federal agencies for both the construction and operation of the proposed
ETLCF.
8. Evidence that the Applicant has identified the location of al! underground
utilities and will conduct all construction operations in accordance with M.R.S.
Title 23, §3360-A Protection of Underground Facilities.
9. Payment forthe initial application fee is payable to the Town of Hudson.
10. Within ninety (90) days of receipt of an initial application for a permit, the
Planning Board shall, with assistance from such staff, consultants,
committees, or commissions as it deems appropriate, will notify the
Applicant in writing that the application is complete, or if the application is
incomplete, and shall inform the Applicant of the specific additional material
needed to complete the application. The Planning Board may extend this
ninety (90) day period at its discretion.
11. After the Planning Board determines that an initial application for a permit is
complete, the Planning Board shall determine whether the initial application
meets the requirements of this Ordinance. In determining whether the
application meets the requirements of this Ordinance, the Planning Board
may obtain services from such staff and consultants as it deems appropriate
which will be paid for by the Applicant.
12. ~---- Within ninety (90) days of determining that an initial application for a permit
meets the requirements, the planning board shall approve the application for
a permit with conditions or disapprove the application for a permit. The time
limit for review may be extended by mutual agreement between the planning
board and applicant.
13. The Planning Board shall make findings of facts and conclusions relative to the
standards in this Ordinance. If the Planning Board finds that all standards have
been met, they shall approve the application for a permit. If the Planning
Board finds that any of the standards of this Ordinance have not been met,
the Planning Board shall either approve or deny the application with
conditions to ensure the standards will be met. The reasons for any
conditions shall be stated in the findings of facts and conclusions.
B. Final Application
The final application for a permit to construct and operate an ETLCF shall include the
following:
Page 10 of 13
1. Updates to information provided in the initial application.
2. Any and all relevant updates, changes or modifications to the project that may
impact the Planning Boards ability to make a sound decision to approve or
deny an application.
3. The Applicant shall pay for the services of all consultants that the Planning
Board deems necessary to evaluate the application. Such consultants shall be
chosen by the Planning Board. Failure of the Applicant to make such payments
renders the application void.
4, Payment of the final application is payable to the Town of Hudson within
ninety (90) days of receipt of a final application for a permit, the Planning
Board shall, with assistance from such staff, consultants, committees, or
commissions as it deems appropriate, notify the Applicant in writing that the
application is complete or not and shall inform the Applicant of the specific
additional material needed to complete the application. The Planning Board
may extend this ninety (90) day period at its discretion.
After the Planning Board determines that a final application for a permit is
complete, the Planning Board shall determine whether the final application
meets the requirements of this Ordinance. In determining whether the
application meets the requirements of this Ordinance, the Planning Board
may obtain services from such staff and consultants as it deems appropriate
which will be paid for by the Applicant.
5. Within ninety (90) days of determining that a final application for a permit
meets the requirements, the Planning Board shall approve the application for
a permit with conditions or disapprove the application for a permit. The time
limit for review may be extended by mutual agreement between the Planning
Board and Applicant.
6. The Planning Board shall make findings of facts and conclusions relative to the
standards in this Ordinance. If the Planning Board finds that all standards have
been met, they shall approve the final application for a permit. If the Planning
Board finds that any of the standards of this Ordinance have not been met,
the Planning Board shall either deny the Application or approve the
application with conditions to ensure the standards will be met. The reasons
for any conditions shall be stated in the findings of facts and conclusions.
7. If construction or operation of the activity hasnot begun within two (2) years,
this permit shall lapse, and the Applicant shal! reapply to the Planning Board
for anew permit. The Applicant may not begin construction until a new
permit is granted.
Page 11 of 13
XIV. Conflict and Severability
A. Conflict
Whenever a provision of this ordinance conflicts with or is inconsistent with
another provision of this ordinance or of any other ordinance, regulation, or statute,
the more restrictive provision shall apply.
B. Severability
The invalidity of any part of this ordinance shall not invalidate any other part of this
ordinance.
XV. Amendments
The Planning Board of the Town of Hudson, Maine shall have the authority to initiate
amendments to this Ordinance. The Planning Board shall first determine that such an
amendment is in the public interest, is consistent with the purpose and intent of this
Ordinance, and will not have a significant, adverse effect upon public safety and the
environment. Any Planning Board proposed amendment shall then be forwarded to the
Select Board to determine if the proposal should be presented to the voters. All
proposed amendments must be adopted by a majority vote from the Town of Hudson
voters at a Town Meeting.
XVI. Definitions
Unless specifically defined below, words and phrases used in this ordinance shall have
the same meaning as they have at common law and give this ordinance its most
reasonable application. Words in the present tense include the future, the singular
number includes the plural and the plural number includes the singular. The word "may"
is permissive; "shall" is mandatory and not discretionary. When a particular publication
or standard is referenced, it shall include any revised or replacement publication or
standard. When a particular agency or organization is referenced, it shall include any
successor agency or organization responsible for the same matters.
Applicant: Person, or persons, or entity applying for a permit or license to the Town of
Hudson pursuant to this Ordinance.
CEO: Town of Hudson Code Enforcement Officer
Electric Transmission Line Corridors and Facility (ETLCF): Any project, whose main
purpose is the transmission or distribution of electricity, and all its affiliated
improvements, buildings or facilities that contain or support electrical transmission or
distribution systems with an operating voltage of 46 kV or greater.
ETLCF: Electric Transmission Line Corridors and Facility
Page 12 of 13
Kilovolt (kV): Unit of electrical potential equa! to 1,000 volts.
Occupied Structure: A building in which people live, work or frequent including
seasonal/recreational uses, or building in which animals are housed.
Owner/Operator: The person or entity that is the legal owner of the ETLCF
including successors and assigns, and any person or entity that has the authority or
responsibility to operate the ETLCF on a day-to-day basis. An Owner/Operator must
have the legal authority to represent and make binding representations and decisions
on behalf of the ETLCF.
Permit: Written approval issued by the Town of Hudson, empowering the holder
thereof to construct a facility in accordance with this Ordinance.
Project Boundary: The boundaries of the ETLCF to which the Owner/Operator has legal
right, title or interest, or the option to acquire the same, and as shown on the site plan
submitted to and approved by the Planning Board in accordance with this Ordinance.
Project Parcel: Any parcel of real estate on which all or any part of the ETLCF will be
constructed.
Property Line: The line of demarcation along the ground surface and the vertical
extension of that line which constitutes a Jegally enforceable boundary or monument
which separates real property owned or controlled by owner(s) from contiguous real
property owned or controlled by another person.
Page 13 of 13