Chapter 24
Solar Ordinance
Adopted at Special Town Meeting
January 5, 2021
Solar Ordinance
Adopted by January 17, 2023
Section 1. Title
This ordinance shall be known and may be cited as the "Solar Ordinance"
Section 2. Purpose
The purpose of this ordinance is to establish a municipal review procedure and performance standards
for Solar Energy Systems (SES), including those typically characterized as "Solar Farms", These standards
are intended to:
a. Establish clear guidelines, standards and time frames for the Town to regulate Solar Energy
Systems;
b. Permit the Town to fairly and responsibly protect public health, safety and welfare:
c. Minimize any potential adverse effect of solar development on surrounding land use;
d. Provide for the decommissioning/removal of panels associate utility structures that are no
longer being used for energy generation and transmissions purposes; and
e. Support the goals and policies of the Comprehensive plan, including orderly development,
efficient use of infrastructure, and protection of natural scenic, and agriculture resources.
Section 3. Applicability
Solar Energy Systems (SES) are subject to location and permitting requirements as set forth in the Town
of Milford, Solar Ordinance table below. A Solar Energy System approved for construction prior to the
effective date of this ordinance shall not be required to meet the terms and conditions of the ordinance.
Any physical modification to any existing prior Solar Energy System, whether or not existing prior to the
effective date of the ordinance that expands, or relocates the footprint of the Solar Energy System, shall
require approval under this ordinance. Routine maintenance and replacements require permits.
INFRASTRUCTURE Mixed River Village Light Conservation
Residential Residential Industrial
Solar Energy System, Code Code Code Code Code Code
SMALL Accessory-Scale- Enforcement | Enforcement | Enforcement | Enforcement | Enforcement
Roof Mounted Enforcement
Solar Energy System, Planning Planning Planning Planning Planning Planning Board
SMALL /Accessory-Scale- | Board Board Board Board Board
Ground Mounted
Solar Energy System, Planning Planning Planning
Medium- Scale Board Board Board
Solar Energy System Planning Planning Planning
Large-Scale Board Board Board
Page 1 of 10
a a. Tye Ves) )
| TOWN OF MILFORD = @an@@u
Solar Ordinance
Section 4. Definitions
Solar Energy Systems (SES): A solar photovoltaic cell, module, array, solar hot air or water collector
device, including all solar related equipment, which relies upon solar radiation as an energy source for
collection, inversion, storage and distribution of solar energy for electricity generation or transfer of
stored heat.
Solar Energy System, Small-Scale: also known as an 'Accessory- Scale System'. A Solar Energy System
whose physical size based on total airspace projected over the ground is less than 3,000 Square feet and
/or that generates a nameplate capacity of less than 20KW. Such a system may consist of one (1) or
more freestanding ground, or roof mounted, solar arrays or solar related equipment, and is intended to
primarily reduce on site consumption of utility power of fuels. Such a system generally occupies 1,750
square feet or surface area or less (equivalent to a rated nameplate capacity of 10KW or less).
Solar Energy System Roof-Mounted: A Solar Energy System that is mounted on the roof of a building or
structure; may be of any size. (Small, Medium or Large-scale)
Solar Energy System Ground-Mounted: A Solar Energy System that is structurally mounted to the
ground and is not roof-mounted; may be any size (small, medium, or Large-scale)
Solar Energy Systems Medium-Scale: A Solar Energy System whose physical size based on total airspace
projected over the ground is equal to or greater than 3,000 square feet but less than 4 acres (174,240
Square feet), and /or that generates a nameplate capacity of 2OKW up to, but not including, 1MW.
Solar Energy Systems Large-Scale: A Solar Energy System whose physical size is based on total airspace
projected over the ground is equal to or greater than 5 acres (217,800 square feet}, and/ or that
generates a nameplate capacity of MW or greater
Battery Storage: Battery storage has to meet NFPA 70(NEC) and NFPA 1 (FC) and any state and local
standards and codes.
Kilowatt (KW): A unit for measuring power that is equivalent to 1,000 watts
Megawatt (MW): A unit for measuring power that is equivalent to one million watts, or 1,000 Kilowatts
Megawatt Hour (MWH)}: A megawatt hour is equal to 1,000 kilowatt hours (KWH). It is equal to 1,000
kilowatts of electricity used continuously for one hour.
Rated Nameplate Capacity: The maximum rated output if electric power production of the photovoltaic
system in watts of Direct Current (DC).
Solar Energy: Radiant energy (direct, diffuse, and/ or reflective) received from the sun.
' Solar Array: A grouping of multiple solar modules with the purpose if harvesting solar energy.
Solar Farm: Please see Solar Energy System.
Page 2 of 10
Sai -
Solar Ordinance
Solar Related Equipment: Items including a solar photovoltaic cell, module, array, solar hot air or water
collector device panels, lines, pumps, batteries, mounting brackets, framing, fencing, foundations or
other structures used or intended to be used for collection and management of solar energy.
Pure Tone: The simplest periodic sound; a constant sound created as a pressure disturbance that
fluctuates sinusoidally as fixed frequency.
Section 5. Application and permit fee.
A. Application fee:
a. Solar Energy System, Small-Scale. The application fee is the standard building permit
fee.
b. Solar Energy System, Medium-Scale. The application fee is $500
c. Solar Energy System Large-Scale. The application fee is $2,500.
B. Permit fee: Standard building permit fee.
Section 6. Specific Application Requirements
An application for a Large or Medium scaled Solar Energy System permit shall include the following at
the cost of the applicant:
1) Adetailed description of the owner and operator qualifications and track record to run the
facility;
2) Pre construction site review, soil science and profile from Maine D.E.P. and Inland fisheries
and wildlife
3) If the operator will be leasing the land, a copy of the agreement clearly outlining the
relation inclusive of the rights and responsibilities of the operator, landowner and any other
responsible party with regard to the SES and the life of the agreement;
4) Adescription of how and to whom the energy will be sold;
5) Acopy of the agreement and schematic details of the connection arrangement with the
transmission system, clearly indicating which party is responsible for various requirements
and how they will be operated and maintained;
6) The layout, design and installation shall conform to applicable industry standards, such as
those of the American National Standards(ANS|), underwriters laboratories (UL), the
American Society for Testing and Materials (ASTM), Institute of Electrical and Electronics
Engineers (IEEE), Solar Rating and Certification Corporation (SRCC), Electrical Testing
Laboratory (ETL), Florida Energy Center (FSEC) or other similar certifying organizations, and
shall comply with local ordinances, and with all other applicable fire and life safety
Page 3 of 10
"Tae Srna
TOWN OF MILFORD ('@xeeeg
Solar Ordinance
requirements. The manufacture specifications for the key components of the system shall
be submitted as part of the application;
7) Adescription of the panels to be installed, including make, model and associated major
system components;
8) Aconstruction plan and timeline, identifying contractors, site control and anticipated on-line
date;
9) An operations and maintenance plan including site control and the projected operating life
of the System; such plan shall include measures for maintaining safe access to the
installation, stormwater controls, as well as general procedures for operational maintenance
of the installation. Additionally, such plan shall describe efforts to promote beneficial flora
and fauna (e.g. honeybees, butterflies, etc.) as well as minimizing the use of pest-control
substances (e.g. pesticides, herbicides, fungicides, and/or insecticides); to the extent
possible without hindering operation of the facility
10) An emergency management plan for all anticipated hazards;
11) A stormwater management plan, certified by a licensed Maine engineer, that demonstrates
stormwater from the SES will infiltrate into the ground beneath the SES at a rate equal to
that of the infiltration rate prior to the placement of the system;
12) A background noise measurement for the site location as performed by a qualified
professional:
13) Proof of financial capacity to construct and operate the proposed facility;
14) A decommissioning plan, including
a. Adescription of the trigger for implanting the decommissioning plan. There is a
rebuttable presumption that decommissioning is required if 10% or less permitted
capacity of electricity is generated for continuous period of twelve (12) months. The
applicant may rebut presumption by providing evidence, such as a force majeure
event that interrupts the generation of electricity, that although the project has not
generated electricity for a continuous period of twelve (12) months, the project has
not been abandoned and should not be decommissioned.
b. A description of the work required to physically remove all Solar Energy System and
Solar Related components, including associated foundations, building, cabling,
electrical components, and any other associated facilities to the extent they are not
otherwise in or proposed to be placed into productive use. All earth disturbed
Page 4 of 10
"Oe Oa?)
ET "ei"
Solar Ordinance
during decommissioning must be graded and re-seeded, unless the landowner of
the affected land requests otherwise in writing and subject to the Planning Board
approval.
i, At the time of decommissioning, the applicant may provide evidence of
plans for continued beneficial use of any or all of the components of the
Solar Energy System. Any changes to the approved decommissioning plan
shall be subject to review and approval by the planning board.
c. An estimate of the total cost of decommissioning value of the equipment and
itemization of the estimated major expenses, including the projected costs of
measures taken to minimize or prevent adverse effects on the environment during
implementation of the decommissioning plan. The itemization of major costs may
include, but is not limited to, the cost of the following activities: panel removal,
panel foundation removal and permanent stabilization, building removal and
permanent stabilization, transmission corridor removal and permanent stabilization
and road infrastructure removal and permanent stabilization.
d. Demonstration in the form of a performance bond, surety bond, letter of credit, or
other form of financial assurance as may be acceptable to the Planning Board that
upon the end of the useful life of the Solar Energy System the applicant will have the
necessary financial assurance in place for 100% of the estimated total cost of
decommissioning, subject to a review of such cost by the Code Enforcement Officer.
The financial assurance shall include a provision granting the Town the ability to
access the funds and property and perform the decommissioning of the facility is
abandoned or the applicant or subsequent responsible party fails to meet their
obligations after reasonable notice, to be defined in the agreement and approved
by the Planning Board. For a Medium Scaled SES, the applicant may propose
securing the necessary financial assurance in phases, as long as the total required
financial assurance is in place a minimum of 5 years prior to the expected end of the
useful life of the Solar Energy System.
i. Note the applicant may apply to the Code Enforcement Officer for release
of the guarantee at such time that it or its assignees remove the system and
associated abandoned structures, and such completed removal is found to
be satisfactory by the Planning Board.
ii. Evaluate and update bond every 5 years.
Section 7. Standard Approval
The following standards must also be met:
Large and Medium- Scaled Ground-Mounted Solar Energy Systems:
1. Lots - SES shall not exceed 20% coverage of a lot area. Lot coverage shall be calculated based on the
total SES airspace projected over the ground.
Page 5 of 10
era Sm Ley,
TOWN OF MILFORD (ai
Solar Ordinance
2. Legal Responsibilities - The applicant must provide proof that it has authorization to construct, use
and maintain the property and any access drive for the life of the project and including the
decommissioning of the project. The roles and responsibilities of the system owner, operator,
landowner and any other party involved in the project must be clear and meet the satisfaction of the
Planning Board that the public interest is protected. The owner or operator of a Ground Mounted Solar
Energy System shall build and maintain it in compliance with all relevant Federal, State and Local Laws,
Regulations, and Ordinances.
3. Deed Registration -- Any Large or Medium Scaled SES shall be incorporated into the description of the
real property in the lot/property deed and registered with the Penobscot County Registry of Deeds as a
condition of Planning Board approval.
4. Setback - Structures within a SES shall be setback a minimum of 200 feet from all lot lines. Any solar
photovoltaic cells or arrays shall be subject to a maximum height of 10 feet above the ground surface.
Associated SES structures shall be subject to the maximum height regulations specified for principal and
accessory buildings within the applicable zoning district.
5. Prohibited Locations - Components of a ground mounted SES shall not be placed within any legal
easement or right-of-way location, or be placed within any stormwater conveyance system, or in any
other manner that would alter or impede stormwater runoff from collecting in a constructed
stormwater conveyance system,
6. Utility Notification - No grid-intertied photovoltaic system shall be installed until evidence has been
given to the Planning Board that the applicant has an agreement with the utility to accept the power.
Off-grid systems are exempt from this requirement.
7, Fence - Ground Mounted Solar Energy Systems shall be protected by an approved perimeter fence.
Such fences shall allow for small wildlife passage and movement.
8. Signage - A sign shall be required to identify the owner/operator and provide a 24-hour emergency
contact phone number. Solar energy systems shall not be used for displaying any advertising. A clearly
visible warning sign shall be placed at the base of all pad-mounted transformers and substations and on
the any fence surrounding the SES informing individuals of potential voltage hazards.
9. Screening - Lots on which Ground Mounted Solar Energy Systems are located shall utilize buffers /
screening from roads and residences by plantings, berms, and natural topographical features. Ground
mounted SES shall be screened from view to the greatest extent practical of any adjacent property that
is residentially zoned or used for residential purposes, as well as any public way. The screen shall consist
of a vegetative barrier which provides a visual screen. In lieu of a vegetative screen, a fence that
provides visual screening, and meets requirements of the controlling ordinance, may be allowed only if a
vegetative screen is deemed impractical by the Planning Board.
10. Glare -- All SES shall be situated to eliminate concentrated glare onto nearby structures or roadways.
11. Noise -- No noise generated by the SES or Solar Related Equipment shall be 10 decibels (dB) greater
than the preconstruction / existing background level, nor generate a Pure Tone measured at the lot
Page 6 of 10
x POF IN
Solar Ordinance
lines. The background noise limit will be based on background noise during the quietest period of the
night, typically 3:00 am.
12. Lighting - Lighting shall be limited to that required for safety and operational purposes and shall be
shielded from interference with abutting properties. Lighting of the SES shall be directed downward and
shall incorporate full cut-off fixtures to reduce light pollution and shall otherwise comply with the Town
of Milford Land Use Ordinance. Other than required lighting, lighting shall not be used / visible between
9pm and 7am.
13. Impervious Assessment - The surface area of the arrays of a ground mounted SES, regardless of the
mounted angle of any solar panels, may or may not be considered impervious contingent upon
conformity with the stormwater management plan.
14. Utility Connections - Reasonable efforts, as determined by the Planning Board, shall be made to
place all utility connections from the solar photovoltaic installation underground, depending on
appropriate soil conditions, shape, and topography of the site and any requirements of the utility
provider. Electrical transformers for utility interconnections may be above ground if required by the
utility provider.
15. Emergency Services -- SES owner or operator shall provide a copy of the project summary, electrical
schematic, and site plan to the Fire Chief. Upon request, the owner or operator shall coordinate with
local emergency services in developing an emergency response plan. A coded key box, or agreed
equivalent, shall be provided and installed by the operator to be used to allow emergency service
personnel continuous access. All means of shutting down the solar energy system shall be clearly
marked. The owner or operator shall identify a responsible person for public inquiries throughout the
life of the installation.
16. Maintenance Conditions - The SES owner or operator shall maintain the facility in good condition.
Maintenance shall include, but not be limited to, painting, structural repairs, vegetative screening,
fences, landscaping and plantings, and integrity of security measures. The SES must be properly
maintained and be kept free from all hazards, including, but not limited to, faulty wiring, loose
fastenings, being in an unsafe condition or detrimental to public health, safety or general welfare. Site
access shall be maintained to a level acceptable to the fire chief for emergency response. The owner or
operator shall be responsible for the cost of maintaining the SES and any access road(s), including
regular plowing of snow to maintain road access.
17. Satisfaction with All Aspects of Capacity and Plans Submitted -- The Planning Board must find that
the Applicant has the capacity to finance, safely operate and decommission the SES.
18. Removal - When any portion of a ground mounted SES is removed, any earth disturbance must be
graded and re-seeded, unless authorized for another developed use.
19. Alternatives Assessment - As determined by the Planning Board, if a proposed ground-mounted SES
does not meet the standards in this Ordinance, associated Town LUO standards, or goals and objectives
as established in the Town's Comprehensive Plan, the applicant must reapply and demonstrate
compliance with the previous mentioned standards and ordinances.
Page 7 of 10
i 8 SP 2a»,
Solar Ordinance
Small-Scaled Ground-Mounted Solar Energy Systems:
1. Lots - SES shall not exceed 10% coverage of a lot area. Lot coverage shall be calculated based on the
total SES airspace projected over the ground. All SES should be designed and located to ensure solar and
physical access without reliance on and/or interference to/from adjacent properties.
2. Setback - Structures within a SES shall be setback a minimum of 50 feet from the side and rear
property lines and meet the front setback requirements for structures within the zoning district (50
feet). Any solar photovoltaic cells or arrays shall be subject to a maximum height of 10 feet above the
ground surface. Associated SES structures shall be subject to the maximum height regulations specified
for principal and accessory buildings within the applicable zoning district.
3. Prohibited Locations - Components of a ground mounted SES shall not be placed within any legal
easement or right-of-way location, or be placed within any stormwater conveyance system, or in any
other manner that would alter or impede stormwater runoff from collecting in a constructed
stormwater conveyance system.
4. Signage - Solar energy systems shall not be used for displaying any advertising.
5. Screening - Lots on which Ground Mounted Solar Energy Systems are located shall utilize buffers /
screening from roads and residences by plantings, berms, and natural topographical features. Ground
mounted SES shall be screened from view of any adjacent property that is residentially zoned or used for
residential purposes, as well as any public way. The screen shall consist of a vegetative barrier which
provide a visual screen. In lieu of a vegetative screen, a fence that provides visual screening, and meets
requirements of the controlling ordinance, may be allowed only if a vegetative screen is deemed
impractical by the Planning Board.
6. Glare -- All SES shall be situated to eliminate concentrated glare onto nearby structures or roadways.
7. Lighting - Lighting shall be limited to that required for safety and operational purposes and shail be
shielded from interference with abutting properties. Lighting of the SES shall be directed downward and
shall incorporate full cut-off fixtures to reduce light pollution and shall otherwise comply with the
provisions of the Town of Milford's Land Use Ordinance. Lighting shall not be used / visible between
9pm and 7am.
8. Preservation of Town's ordinance's and policies - All reasonable efforts, as determined by the
Planning Board, shall be made to ensure any SES is consistent with the ordinance's of the community
via visual consistency with local neighborhood area, maintenance of scenic views, maintenance of open
space land and farms, and the Town Comprehensive Plan, and associated Town planning documents.
Roof Mounted Solar Energy Systems:
1. The owner shall provide evidence certified by an appropriately licensed professional that the roof is
capable of supporting the collateral load of the SES.
2. SES mounted on roofs of any building shall be subject to the maximum height regulations specified for
principal and accessory buildings within the applicable zoning district.
Page 8 of 10
° fm deren THe ad }
| TOWN OF MILFORD = @ewi@
Solar Ordinance
3. Glare -- All SES shall be situated to eliminate concentrated glare onto nearby structures or roadways.
4. For firefighter access, a minimum three (3) foot buffer zone is required from the ridge and three (3) ft.
from the edge of the roof or parapet.
5. Preservation of Town's Ordinance's and Policies - All reasonable efforts, as determined by the
Planning Board, shall be made to ensure any SES is consistent with the land use, ordinance's, and
policies of the community via consistency with local neighborhood area, maintenance of scenic views,
maintenance of open space land and farms, and the Town Comprehensive Plan, and associated Town
planning documents.
Section 8. Decommissioning and Removal
1. Any Ground Mounted Solar Energy System that has reached the end of its useful life, ceases to
generate power or has been abandoned shall be removed pursuant to a plan approved by the
Pianning Board during the application process. The landowner, or SES owner or operator shall
physically remove the installation no more than 180 days after the date of discontinued
Operations. The owner or operator shall notify the Code Enforcement Officer by certified mail,
return receipt requested, of the proposed date of the discontinued operations and plans for
removal.
2. Decommissioning shall consist of:
a. physical removal of all solar energy systems, structures, equipment, security barriers and
transmission lines from the site;
b. disposal of all solid and hazardous waste in accordance with Local, State and Federal waste
disposal regulations; and
c. stabilize or re-vegetation of the site as necessary to minimize erosion. Restoration should be
native vegetation only suitable to the location that is Friendly to wildlife and insects in that area. The
Code Enforcement Officer may allow the owner or operator to leave landscaping or designated below-
grade foundations to minimize erosion and disruptions to vegetation. Restore soil to pre construction
soil profile.
3. Absent a notice of a proposed date of decommissioning or written notice of extenuating
circumstances, a Ground Mounted Solar Energy System shall be considered abandoned when it fails to
generate 10% or less permitted capacity of electricity for a continuous period of twelve (12) months
without having first obtained the written consent of the Code Enforcement Officer. Determination of
abandonment shall be made by the Code Enforcement Officer.
4. If the owner or operator of a Ground Mounted Solar Energy System fails to remove the
installation in accordance with the requirements of this section within 180 days of abandonment or the
proposed date of decommissioning, the Town of Milford retains the right to use the performance
guarantee and any and all legal or available means necessary to cause an abandoned, hazardous or
decommissioned solar energy system to be removed.
Section 9. Modifications
Page 9 of 10
SS Devt Lurie wwe Wes dare ati .
Solar Ordinance
1. Any physical modification to any existing SES, whether or not existing prior to the effective date of
this Ordinance, shall require review and approval under this Ordinance
2. Any modifications to a Medium to Large Scaled Ground-Mounted Solar Energy System made after
issuance of the required town permit(s) shall require approval by the Planning Board.
3. Any modifications to a Small-Scaled Ground-Mounted Solar Energy System made after issuance of
the required town permit(s) shall require approval by the Code Enforcement Officer.
4. Application fees for modifications shall be consistent with the overall size of the SES, not solely the
modification.
5. Permit fees for modifications shall be based on the modified portion of the SES.
Section 10. Authority
1. This Ordinance is adopted pursuant to the enabling provisions of 30-A, M.R.S. § 3001, Ordinance
Power, the provisions of 30-A, M.R.S. § 4352,Title 30-A M.R.S.A. Sections 4312 to 4350, zoning
(Comprehensive Planning and Land Use Regulation, or "Growth Management" Act).
2. To the extent that any provision of this Ordinance is deemed invalid by a court of competent
jurisdiction, such provision shall be removed from the Ordinance and the balance of the Ordinance shall
remain valid.
Section 12. Effective Date and Duration
This Ordinance shall take effect on upon enactment by the Town of Milford unless
otherwise provided and shall remain in effect until it is amended or repealed.
Section 12. Enforcement Violations and Penalties
This Ordinance shall be enforced by the municipal officers or their designee. Violation of this Ordinance
shall be subject to the enforcement and penalty provisions of 30-A, M.R.S. § 4452, Enforcement of Land
Use Laws and Ordinances.
Adopted a Meeting January 17, 2023
Atteste
Leniessia Curtis, Town Clerk Town Seal