Town of Moscow
solar Farm Ordinance
Synopsis: Ordinance to allow solar farms in rural areas subject to setback, height, screening,
maintenance, safety and decommissioning requirements, subject to Planning Board approval.
Whereas the Town of Moscow deems it in the best interest of its citizens to enact a Solar
Farm Ordinance.
Now Therefore the Town of Moscow does ordain as follows:
Section 1. Title
This Ordinance shall be known and may be cited as the "Solar Farm Ordinance'.
Section 2. Purpose
The purpose of this Ordinance is to allow solar farms in rural areas subject to setback, size,
height, screening, maintenance, safety, and decommissioning requirements, subject to Planning
Board approval.
Section 3. Applicability
A. This ordinance shall apply to all commercial solar installations within the Town of
Moscow.
B. This Ordinance shall authorize Ground Mounted Solar Energy Systems to be installed
only in arural area in the Town of Moscow.
section 4. Definitions
The following words and terms shall mean the following for purposes of this section:
Abandonment: To give up, discontinue, or withdraw from. Any solar farm that ceases to produce
energy on a continuous basis for 180 days will be considered abandoned.
Building: Any structure having a roof supported by columns or walls, and designated or
intended for the shelter, support, enclosure or protection of persons, equipment, animals or
chattels.
Decommissioning Plan: A document that details the planned shut down or removal of a solar
farm from operation or usage, including abandonment as defined in this Ordinance.
Fence: A continuous barrier extending from the surface of the ground to a uniform height (to be
established through the special use permit process), constructed of steel, or other metal, or any
substance of a similar nature and strength.
1 of 5
Gate: A door or other device attached to a fence which, when opened, provides a means of
ingress and egress of person and things for which it was intended, and which, when closed,
forms a continuous barrier as a part of the fence to which it is attached.
Ground Mounted Solar Energy System: for purposes of this Ordinance: (a) a solar energy
system that is structurally mounted to the ground; 9b) has a physical size based on total
airspace projected over the ground is greater than 25 acres; and (c) that is not directly
connected to a Residential Structure.
Residence: A building used as a dwelling for one or more families or persons.
Solar Energy System (SES): a facility whose primary purpose is to harvest energy by
transforming solar energy into another form of energy or transferring heat from a collector to
another medium using mechanical, electrical, or chemical means.
Section 5. Applications and Permit Fee
The application fee for a solar energy system is $2,500.
Section 6. Specific Application Requirements
An application for a Solar Energy System (SES) Permit must also include the following, at the
cost of the applicant:
1. Adescription of the owner of the SES, the operator if different, and detail of
qualifications and track record to run the facility;
2. lf the operator will be leasing the land, a copy of the agreement (minus financial
compensation) clearly outlining the relationship inclusive of the rights and responsibilities
of the operator, landowner and any other responsible party with regard to the SES and
the life of the agreement:
3. A description of how and to whom the energy produced will be sold;
4. Acopy of the agreement and schematic details of the connection arrangement with the
transmission system (most likely Central Maine Power), clearly indicating which party is
responsible for various requirements and how they will be operated and maintained:
S. The layout, design and installation shall conform to applicable industry standards, such
as those of the American National Standards (ANSI), Underwriters Laboratories (UL),
the American Society for Testing and Materials (ASTM), Institute of Electrical and
Electronics Engineers (IEEE), Solar Rating and Certification Corporation (SRCC),
Electrical Testing Laboratory (ETL), Florida Solar Energy Center (FSEC) or similar
certifying organizations, and shall comply with local ordinances, and with all other
applicable fire and life safety requirements. The manufacturer specifications for the key
components of the system shall be submitted as part of the application;
6. A description of the panels to be installed, including make and model, and associated
major system components;
/. Aconstruction plan and timeline, identifying known contractors, site control and
anticipated on-line date;
2of5
8. An operations and maintenance plan, including site control and the projected operating
life of the system; such a plan shall include measures for maintaining safe access to the
installation, stormwater controls, as well as general procedures for operational
maintenance of the installation. Additionally, such plans shall include efforts to promote
beneficial flora and fauna (e.g. honeybees, butterflies, etc.) as well as a commitment to
not using pest-control substances (e.g. pesticides, herbicides, fungicides, and/or
insecticides).
9. Escrow amount for decommissioning will be determined during the application phase.
Section 7. Dimensional Requirements
A. Ground Mounted Solar Energy Systems will not exceed 14 feet in height.
B. Minimum Sgt setback shall be 1,000 feet from any dwelling.
C. Lot coverage for Ground Mounted Solar Energy Systems shall be calculated based on
the area of the supporting structure that is in contact with the ground and not the area of
the panels as long as the area under the panels remains vegetated.
D. Residential solar systems of less than 40 kw are exempt from this Ordinance.
Section 8. Screening, Security, Maintenance and Regulatory Compliance
A. Subject to the approval of the Moscow Planning Board, the lots on which Ground
Mounted Solar Energy Systems are located shall be buffered from roads and residences
by plantings and berms, and natural topographical features.
B. Subject to the approval of the Moscow Planning Board, the lots on which Ground
Mounted Solar Energy Systems are located shall be protected by a perimeter fence.
One or more signs shall be affixed to the fence identifying the owner of the facility and
emergency contact information.
C. For Purposes of emergency services, the owner or operator of a Ground Mounted Solar
Energy Systems shall provide a copy of the project summary, electrical schematic, and
site plan to the Moscow Fire Chief. Upon request, the owner or operator shall cooperate
with the Fire Department in developing an Emergency Response Plan. All means of
shutting down the system shall be clearly marked on the plan. The owner or operator
shall identify a responsible person to the Code Enforcement Officer and the Fire Chief
for public inquiries throughout the life of the installation.
D. The owner or operator of a Ground Mounted Solar Energy System shall maintain the
facility in good condition. Maintenance shall include but not be limited to, painting,
structural repairs, vegetation control and integrity of security measures. Site access shall
be maintained to a level acceptable to the Moscow Fire Chief. The owner or operator
shall be responsible for the cost of maintaining the access road(s) unless the road(s) Is
accepted as a public way.
E. The owner or operator of a Ground Mounted Solar Energy System shall build and
maintain it in compliance with all relevant Federal, State and Local Laws, Regulations
and Ordinances.
3 ord
F. All commercial solar farms must be of a taxable nature and subject to real estate and
personal property taxes.
Section 9. Violations and Enforcement
A. Violation
Any construction of buildings or structures, and any use of land, buildings or structures
except in conformance with the provisions of this Ordinance shall be deemed a violation
of this Ordinance and a nuisance.
B. Code Enforcement Officer
It shall be the duty of the Code Enforcement Officer to enforce the provisions of this
Ordinance. If the Code Enforcement Officer shall find that any provision of this
Ordinance is being violated, he/she shall notify in writing the person responsible for such
violation, indicating the nature of the violation and ordering the action necessary to
correct the violation, including discontinuance of illegal use of land, buildings, structures,
and abatement of nuisance conditions. A copy of such notices shall be maintained as a
permanent record.
C. Legal Actions
When the above does not result in the correction or abatement of the violation or
nuisance condition, the Selectmen, upon notice from the Code Enforcement officer are
hereby authorized to institute any and all actions and proceedings, either legal or
equitable, including seeking injunctions of violations and the imposition of fines, that may
be appropriate or necessary to enforce the provisions of the Ordinance in the name of
the municipality.
D. Penalties
Any person or persons who violate any provision(s) of this Ordinance or any permit
issued under the provisions of this Ordinance, shall be subject to civil penalties in
accordance with the provisions of Title 30-A §4452.
E. Contractor Liability
Any contractor involved in activity regulated by the provisions of this Ordinance may be
held liable for violating the Ordinance if the necessary permits for said activity have not
been obtained or if work performed by the contractor does not conform to all conditions
of approval of the permit or the terms of the Ordinance.
F. Appeals
The Board of Appeals shall hear appeals from final decisions of the Code Enforcement
Officer and Planning Board on decisions to grant or deny permits or approvals pursuant
to this Ordinance in accordance with the Town's Board of Appeals Ordinance. Appeals
shall be filed within 30 days of the Code Enforcement Officer or Planning Board's official,
written decision on the application.
Section 10. Performance Guarantee
A. Any Ground Mounted Solar Energy System that has reached the end of its useful life,
ceases to generate power or has been abandoned shall be removed pursuant to a plan
approved by the Moscow Planning Board during the application process. The owner or
4of 5
operator shall physically remove the installation no more than 180 days after the date of
discontinued operations. The owner or operator shall notify the Code Enforcement
Officer by certified mail, return receipt requested, of the proposed date of the
discontinued operations and plans for removal.
B. Decommissioning shall consist of: (1) physical removal of all solar energy systems,
structures, equipment, security barriers and transmission lines from the site; (2) disposal
of all solid and hazardous waste in accordance with Local, State and Federal waste
disposal regulations; and (3) stabilize or re-vegetation of the site as necessary to
minimize erosion. The Code Enforcement Officer may allow the owner or operator to
leave landscaping or designated below-grade foundations to minimize erosion and
disruptions to vegetation.
C. Absent a notice of a proposed date of decommissioning or written notice of extenuating
circumstances, Ground Mounted Solar Energy Systems shall be considered abandoned
when it fails to generate electricity for more than 180 days without having first obtained
the written consent of the Code Enforcement Officer. Determination of abandonment
shall be made by the Code Enforcement Officer.
D. If the owner or operator of a Ground Mounted Solar Energy System fails to remove the
installation in accordance with the requirements of this section within 180 days of
abandonment or the proposed date of decommissioning, the Town of Moscow retains
the right to use the performance guarantee and any and all legal or available means
necessary to cause an abandoned, hazardous or decommissioned solar energy system
to be removed.
Section 11. Authority
A. This Ordinance is adopted pursuant to the enabling provisions of Article VIII, Part 2,
Section 1 of the Maine Constitution, provisions of 30-A M.R.S. §3001, Ordinance Power,
and the provisions of 30-A, M.R. S. §4352, Zoning.
B. To the extent that any provision of this Ordinance is deemed invalid by a court of
competent jurisdiction, such provision shall be removed from the Ordinance and the
balance of the Ordinance shall remain valid.
Section 12. Effective Date and Duration
This Ordinance shall take effect upon enactment by the Town of Moscow unless otherwise
provided and shall remain in effect until it is amended or repealed.
Section 13. Enforcement Violations and Penalties
This Ordinance shall be enforced by the municipal officers or their designee. Violation of this
Ordinance shall be subject to the enforcement and penalty provisions of 30-A, M.R.S. §4452,
Enforcement of Land Use Laws and Ordinances.