SHORELAND ZONING ORDINANCE
Town of Naples
adopted November 14, 1974
amended March I0, 1990
amended December 16, 1991
amended June 13, 2000
amended June 11, 2002
amended December 29, 2003
amended June 21, 2006
amended June 24, 2009
amended June 16, 2010
amended June 8, 2011
amended February 25, 2013
amended June 4, 2014
amended June 9, 2018
amended April 30, 2019
amended April 29, 2021
amended June 14, 2022
amended June 11, 2024
amended November 4,2025
Attested:
TABLE OF CONTENTS
Section 1. PURPOSES 4
Section 2. AUTHORITY
4
Section 3. APPLICABILITY
4
Section 4. EFFECTIVE DATE
4
A. Effective Date of Ordinance and Ordinance Amendments 4
B. Sections 15.0
4
Section 5. AVAILABILITY
4
Section 6. SEVERABILITY
4
Section 7. CONFLICTS WITH OTHER ORDINANCES 5
Section 8. AMENDMENTS
5
Section 9. DISTRICTS AND ZONING MAP
5
Section 10. INTERPRETATION OF DISTRICT BOUNDARIES
5
Section 11. LAND USE REQUIREMENTS 6
Section 12. NON-CONFORMANCE 6
A. Purpose
6
B. General
6
C. Non-Conforming Structures 6
1. Expansions
6
2. Foundations
8
3. Relocation
8
4. Reconstruction or Replacement
9
5. Change of Use of a Non-Conforming Structure 9
D. Non-Conforming Uses
10
1. Expansions
10
2. Resumption Prohibited
10
3. Change of Use 10
E. Non-Conforming Lots
10
1. Non-Conforming Lots 10
2. Contiguous Built Lots
10
3. Contiguous Lots- Vacant or Partially Built 11
Section 13. ESTABLISHMENT OF DISTRICTS 11
A. Resource Protection District 11
B. Limited residential District 12
C. Limited Commercial District 12
D. Stream Protection District 12
E. Causeway Overlay District 13
Section 14. TABLE OF LAND USES 14
Section 15. LAND USE STANDARDS 16
A. Minimum Lot Standards 16
B. Principal and Accessory Structures 17
C. Aquatic Structures, Moorings and Other Structures 19
D. Watercraft 19
E. Campgrounds 19
F. Individual Private Campsites 20
G. Commercial and Industrial Uses 21
H. Parking Areas 21
I. Roads and Driveways 22
J. Signs 24
K. Storm Water Runoff 24
L. Septic Waste Disposal 24
M. Essential Services 25
N. Mineral Exploration and Extraction 25
O. Agriculture 26
P. Timber Harvesting 27
Q. Clearing or Removal of Vegetation for Activities 27
R. Hazard Trees, Storm-Damaged Trees, and Deed Tree Removal 30
S. Exemptions to Clearing and Vegetation Removal Requirements 31
T. Revegetation Requirements 33
U. Erosion and Sedimentation Control 34
V. Soils 35
W. Water Quality 36
X. Archaeological Sites 36
Y. Residential and Campground Common Area Frontage/Density 36
Section 16. ADMINISTRATION 36
A. Administering Bodies and Agents 36
B. Permits Required 37
C. Permit Application 37
D. Photographic Record Required 38
E. Procedure for Administering Permits 38
F. Special Exceptions 39
G. Expiration of Permit 39
H. Installation of Public Utility Service 41
I. Appeals 41
1. Powers and Duties of the Board of Appeal 41
2. Variance Appeals 41
3. Administrative Appeals 43
4. Setback Reduction Appeals 43
5. Setback Reduction Procedure 44
6. Appeal Procedure 44
7. Appeal to Superior Court 45
8. Reconsideration 45
J. Enforcement 46
1. Nuisances 46
2. Code Enforcement Officer 46
3. Legal Actions 46
4. Fines 47
Section 17. DEFINITIONS 47
Naples Shoreland Zoning Ordinance Amended June, 2024
4
Section 1. Purposes
The purposes of this Ordinance are to further the maintenance of safe and healthful
conditions; to prevent and control water pollution; to protect fish and spawning grounds,
aquatic life, bird, and other wildlife habitat; to protect buildings and lands from flooding and
accelerated erosion; to protect archaeological and historic resources to protect freshwater
wetlands; to control building sites, placement of structures and land uses; to conserve
shore cover, and visual as well as actual points of access to inland waters; to conserve
natural beauty and open space; and to anticipate and respond to the impacts of
development in shoreland areas.
Section 2. Authority
This Ordinance is enacted in accordance with the provisions of Title 38 Sections 435 -449
of the Maine Revised Statutes Annotated (M.R.S.A.), and pursuant to the Town's home rule
authority and the authority to regulate moorings in Great Ponds delegated to the Town
by Title 38 M.R.S.A.. Section 3.
Section 3. Applicability
This Ordinance applies to all land areas within 250 feet horizontal distance of the:
- normal high-water line of any great pond or river.
- upland edge of a freshwater wetland,
and all land areas within 75 feet, horizontal distance, of the normal high-water line
of a stream. This Ordinance also applies to any structure built on over or abutting a
dock, wharf or pier, or other structure, extending or located below the normal high-
water line of a water body or within a wetland.
Section 4. Effective Date
A. Effective Date of Ordinance and Ordinance Amendments. This Ordinance. which was
adopted by the municipal legislative body on December 16, 1991, shall not be effective
unless approved by the Commissioner of the Department of Environmental Protection. A
certified copy of the Ordinance or Ordinance Amendment attested and signed by the
Municipal Clerk. shall be forwarded to the commissioner for approval. If the Commissioner
fails to act on this Ordinance or Ordinance Amendment, within forty-five(45) days of the
Commissioner's receipt of the Ordinance or Ordinance Amendment, it shall be
automatically approved.
B. Any application for a permit submitted to the municipality within the forty-five (45) day
period shall be governed by the terms of this Ordinance, or Ordinance Amendment if the
Ordinance or Ordinance Amendment is approved by the Commissioner.
Section 5. Availability
A certified copy of this Ordinance shall be filed with the Municipal Clerk and shall be
accessible to any member of the public. Copies shall be made available to the public at
reasonable cost at the expense of the person making the request. Notice of availability of
this Ordinance shall be posted.
Section 6. Severability
Should any section or provision of this Ordinance be declared by the courts to be invalid,
Naples Shoreland Zoning Ordinance Amended June, 2024
5
such decision shall not invalidate any other section or provision of the Ordinance.
Section 7. Conflicts with Other Ordinances
Whenever a provision of this Ordinance conflicts with or is inconsistent with another
provision of this Ordinance or of any other ordinance, regulation or statute administered by
the municipality, the more restrictive provision shall control.
Section 8. Amendments
This Ordinance may be amended by majority vote of the legislative body. Copies of
amendments, attested and signed by the Municipal Clerk, shall be submitted to the
Commissioner of the Department of Environmental Protection following adoption by the
municipal legislative body and shall not be effective unless approved by the Commissioner
of the Department of Environmental Protection. If the Commissioner fails to act on any
amendment within forty-five (45) days of the Commissioner's receipt of the amendment, the
amendment is automatically approved. Any application for a permit submitted to the
municipality within the forty-five (45) day period shall be governed by the terms of the
amendment if such amendment is approved by the Commissioner.
Section 9. Districts and Zoning Map
A. Official Shoreland Zoning Map:
The areas to which this Ordinance is applicable are hereby divided into the
following districts as shown on the Official Shoreland Zoning Map. Which is made a
part of this Ordinance:
1. Resource Protection
2. Limited Residential
3. Limited Commercial
4. Stream Protection
5. Causeway Overlay District
B. Scale of Map
The Official Shoreland Zoning Map has been drawn at a scale of not less than:
inch-2000 feet. District boundaries are delineated and a legend indicating the
symbols for each district has been placed on the map.
C. Certification of Official Shoreland Zoning Map
The Official Zoning Map shall be certified by the attested signature of the
Municipal Clerk and shall be located in the municipal office. In the event the
municipality does not have a municipal office the Municipal Clerk shall be the
custodian of the map.
D. Changes to the Official Shoreland Zoning Map If amendments, in
accordance with Section 8 are made in the district boundaries or other matter
portrayed on the Official Shoreland Zoning Map such changes shall be made on
the Official Zoning Map within thirty (30) days after the amendments has been
approved by the Commissioner of the Department of Environmental Protection.
Section 10. Interpretation of District Boundaries
Unless otherwise set forth on the Official Shoreland Zoning Map, district
boundary lines are property lines, the centerlines of street, roads and right of way
Naples Shoreland Zoning Ordinance Amended June, 2024
6
and the boundaries of the shoreland area as defined herein. Where uncertainty
still exists as to the exact location of district boundary line, the Board of Appeals
shall be the final authority as to location.
The depiction of the Shoreland Overlay Districts on the zoning map for the Town
of Naples are merely illustrative of their general location. The boundaries of
these districts hall be determined by measurement on the ground of the distance
indicated on the maps from the normal high-water mark of the water body or
the upland edge of wetland, regardless of the location of the boundary shown on
the map.
Section 11. Land Use Requirements
Except as hereinafter specified no building structure land shall hereafter be used
or occupied and no building or structure or part thereof shall hereafter be
erected, constructed, expanded, move, or altered and no new lot shall be created
except in conformity with all of the regulations herein specified for the district in
which it is located unless a variance is granted.
Section 12. Non-Conformance
A. Purpose.
It is the intent of this Ordinance to promote land use conformities, except those non-
conforming conditions that existed before the effective date of this Ordinance or
amendments there to shall be allowed to continue, subject to the requirements set forth in
Section 12. Except as otherwise provided in this Ordinance, a non-conforming condition
shall not be permitted to become more non-conforming.
B. General.
(1) Transfer of Ownership. Non-conforming structure, lots, and uses may be
transferred and the new owner may continue the non-conforming use or continue
to use the non-conforming structure or lot, subject to the provision of this
Ordinance.
(2) Repair and Maintenance. This Ordinance allows, without a permit. the
normal upkeep and maintenance of non-conforming uses and structures including
repairs or renovations that do not involve expansion of the non-conforming use or
structure. and such other changes in a non-conforming use or structure as federal,
slate, or local building and safety codes may require.
C. Non-conforming Structures
(1) Expansions. All new principal and accessory structures. excluding
functionally water- dependent uses must meet the water body, tributary stream, or
wetland setback requirements contained in Section 15(8)( I). A non-conforming
structure may be added to or expanded after obtaining a permit from the same
permitting authority as that for a new structure if such addition or expansion does
not increase the non-conformity of the structure and is in accordance with
subparagraphs (a) through (b) below.
(a). Expansion of any portion of a structure within 25 feet of the normal high-water
line of a water body, tributary stream, or upland edge of a wetland is prohibited
even if the expansion will not increase nonconformity with the water body, tributary
stream, or wetland setback requirement. Expansion of an accessory structure that
Naples Shoreland Zoning Ordinance Amended June, 2024
7
is located closer to the normal high-water line of a water body, tributary stream, or
upland edge of a wetland than the principal structure is prohibited even if the
expansion will not increase nonconformity with the water body, tributary stream, or
wetland setback requirement.
(b). Notwithstanding paragraph (a), above, if a legally existing non-conforming
principal structure is entirely located less than 25 feet from the normal high-water
line of a water body, tributary stream, or upland edge of a wetland, that structure
may be expanded as follows as long as all other applicable standards of land use
adopted by the municipality are met and the expansion is not prohibited by Section l
2(C)(I).
(i) The maximum total footprint for the principal structure may not be
expanded to a size greater than 800 square feet or 30% larger than the footprint
that existed on January 1,1989 whichever is greater. The maximum height of the
principal structure may not be made greater than 15 feet or the height of the existing
structure whichever is greater.
(c.) All other legally existing nonconforming principal and accessory structures
that do not meet the water body, tributary stream, or wetland setback requirements
may be expanded or altered as follows as long as other applicable standards of
land use adopted by the municipality are met and the expansion is not prohibited by
Section I 2(C)(I) or Section I 2(C)( l )(a) above.
(i) For structures located less than 75 feet from the normal high-water line of a water
body, tributary stream, or upland edge of a wetland the maximum combined total footprint
for all structures may not be expanded to a size greater than 1,000 square feet or 30%
larger than the footprint that existed on January 1, 1989,whichever is greater. The
maximum height of any structure may not be made greater than 20 feet or the height of the
existing structure, whichever is greater.
(ii) For structures located less than100 feet from the normal high-water line
of a great pond classified as GPA or a river flowing to a great pond classified as
GPA, the maximum combined total footprint for all structures may not be
expanded to a size greater than 1,500 square feet or 30% larger than the footprint
that existed on January 1, 1989, whichever is greater. The maximum height of any
structure may not be made greater than 25 feet or the height of the existing
structure, whichever is greater. Any portion of those structures located less than
75 feet from the normal high-water line of a water body, tributary stream, or upland
edge of a wetland must meet the footprint a nd height limits in Section12(C)(l)(b)(i)
and Section 12(C)(l)(c)(i), above.
(iii) In addition to the limitations in subparagraphs (i) and (ii), for structures
that are legally nonconforming due to their location within the Resource
Protection District when located at less than 250 feet from the normal high-
water line of a water body or the upland edge of a wetland. the maximum
combined total footprint for all structures may not be expanded to a size greater
than 1,500 square feet or 30% larger than the footprint that existed at the time
the Resource Protection District was established on the lot, whichever is
greater. The maximum height of any structure may not be made greater than
25 feet or the height of the existing structure whichever is greater except that
any portion of those structures located less than 75 feet from the normal high-
Naples Shoreland Zoning Ordinance Amended June, 2024
8
water line of a water body, tributary stream, or upland edge of a wetland must
meet the footprint and height limits in Section l 2(C)(l)(b)(i) and Section l
2(C)(l)(c)(i). above.
(d) An approved plan for expansion of a nonconforming structure must be
recorded by the applicant with the registry of deeds within 90 days of approval.
The recorded plan must show the existing and proposed footprint of the non-
conforming structure the existing and proposed structure height the footprint of
any structures on the parcel, the Shoreland Line boundary and evidence of
approval by the municipal review authority. Plans must include at a minimum:
(i) The method of expansion (whether the applicant utilized the thirty
(30) percent or the footprint expansion option).
(ii) The existing and proposed footprint of the structure in addition to the
footprint of other non-conforming structures on the parcel.
(iii) The existing and proposed structure height.
(iv) A scaled drawing showing the location of the structure and other
structures on the lot in relation to the water body, tributary, stream, or wetland.
(2) Foundations. Whenever a new, enlarged. or replacement foundation is constructed
under a non-conforming structure, the structure and new foundation must be placed such
that the setback requirement is met to the greatest practical extent as determined by the
Code Enforcement Officer or its designee, basing its decision on the criteria specified in
Section 12(C)(3) Relocation, below.
(3) Relocation. A non-conforming structure may be relocated within the boundaries of
the parcel on which the structure is located provided that the site of relocation conforms to
all setback requirements to the greatest practical extent as determined by the Code
Enforcement Officer or its designee, and provided that the applicant demonstrates that the
present subsurface sewage disposal system meets the requirements of State law and the
State of Maine Subsurface Wastewater Disposal Rules (Rules), or that a new system can
be installed in compliance with the law and said Rules. In no case shall a structure be
relocated in a manner that causes the structure to be more non-conforming.
In determining whether the building relocation meets the setback to the greatest practical
extent, the Code Enforcement Officer or its designee shall consider the size of the lot, the
slope of the land, the potential for soil erosion, the location of other structures on the
property and on adjacent properties, the location of the septic system and other on-site
soils suitable for septic systems, and the type and amount of vegetation to be removed to
accomplish the relocation.
When it is necessary to remove vegetation within the water or wetland setback area
in order to relocate a structure, the Code Enforcement Officer shall require
replanting of native vegetation to compensate for the destroyed vegetation in
accordance with Section l5(S). [n addition, the area from which the relocated
structure was removed must be replanted with vegetation. Replanting shall be
required as follows:
(a)
Trees removed in order to relocate a structure must be replanted with
at least one native tree, three (3) feet in height. for every tree removed. If more
than five trees are planted, not one species of tree shall make up more than
Naples Shoreland Zoning Ordinance Amended June, 2024
9
50% of the number of trees planted. Replaced trees must be planted no further
from the water or wetland than the trees that were removed.
Other woody and herbaceous vegetation, and ground cover, which are
removed or destroyed in order to relocate a structure must be re-established.
An area at least the same size as the area where vegetation and/or ground
cover was disturbed, damaged, or removed must be reestablished within the
setback area. The vegetation and/or ground cover must consist of similar
native vegetation and/or ground cover that was disturbed. destroyed or
removed.
(b)
Where feasible. when a structure is relocated on a parcel the original
location of the structure shall be replanted with vegetation which may consist of
grasses, shrubs, trees, or a combination thereof.
(4) Reconstruction or Replacement. Any non-conforming structure which is
located less than the required setback from a water body, tributary stream, or
wetland and which is removed, or damaged or destroyed, regardless of the cause,
by more than 50% of the market value of the structure before such damage,
destruction or removal, maybe reconstructed or replaced provided that a permit is
obtained within eighteen (18) months of the date of said damage, destruction, or
removal, and provided that such reconstruction or replacement is in compliance with
the water body, tributary stream or wetland setback requirement to the greatest
practical extent as determined by the Code Enforcement Officer or its designee in
accordance with the purposes of this Ordinance. ln no case shall the structure be
reconstructed or replaced so as to increase its non-conformity. If the reconstructed or
replacement structure is less than the required setback it shall not be any larger than
the original structure, except as allowed pursuant to Section 12(C)(I) above, as
determined by the non-conforming footprint of the reconstructed or replaced structure
at it new location. If the total footprint of the original structure can be relocated or
reconstructed beyond the required setback area, no portion of the relocated or
reconstructed structure shall be replaced or constructed at less than the setback
requirement for a new structure. When it is necessary to remove vegetation in order
to replace or reconstruct a structure, vegetation shall be replanted in accordance
with Section 12(C)(3) above.
Any non-conforming structure which is located less than the required setback from
a water body, tributary stream, or wetland and which is removed by 50% or less of
the market value, or damaged or destroyed by 50% or less of the market value of
the structure, excluding normal maintenance and repair, may be reconstructed in
place if a permit is obtained from the Code Enforcement Officer within one year of
such damage, destruction, or removal.
In determining whether the building reconstruction or replacement meets the
setback to the greatest practical extent the Code Enforcement Officer or it designee
hall consider. in addition to the criteria in Section 12 (C)(3) above. the physical
condition and type of foundation present, if any.
(5) Change of Use of a Non-conforming Structure. The use of a non-conforming
structure may not be changed to another use unless the Code Enforcement Officer.
Naples Shoreland Zoning Ordinance Amended June, 2024
10
after receiving a written application determines that the new use will have no
greater adverse impact on the water body, tributary, stream, or wetland, or on the
subject or adjacent properties and resources than the existing use.
In determining that no greater adverse impact will occur, the Code Enforcement
Officer shall require written documentation from the applicant regarding the
probable effects on public health and safety, erosion and sedimentation, water
quality, and wildlife habitat, vegetative cover, visual and actual point of public
access to water natural beauty, floodplain management, archaeological and
historic resources, commercial fishing and maritime activities, and other
functionally water-dependent uses.
(D) Non-conforming Uses
(1) Expansions. Expansion of non-conforming uses are prohibited, except those non-
- conforming residential uses may, after obtaining a permit from the Code
Enforcement Officer, be expanded within existing residential structures or within
expansions of such structures as allowed in Section 12(C)(I) above.
(2) Resumption Prohibited. A lot, building or structure in or on which a non-
conforming use is discontinued for a period exceeding one year, or which is
superseded by a conforming use, may not again be devoted to a non-conforming
use except that the Code Enforcement Officer may, for good cause shown by the
applicant, grant up to a one-year extension to that time period. This provision shall
not apply to the resumption of the use of a residential structure provided that the
structure has been used or maintained for residential purposes during the
preceding five (5) year period.
(3) Change of Use. An existing non-conforming use may be changed to another
non-conforming use provided that the proposed use has no greater adverse
impact on the subject and adjacent properties and resources than the former use,
as determined by the Code Enforcement Officer. The determination of no greater
adverse impact shall be made according to criteria listed in Section 12(C)(5)
above.
E. Non-conforming Lots
(1) Non-conforming Lots: A non-conforming lot of record as of the effective date
of this Ordinance or amendment thereto may be built upon. without the need for a
variance, provided that such lot is in separate ownership and not contiguous with
any other lot in the same ownership, and that all provisions of this Ordinance
except lot area, lot width and shore frontage can be met. Variances relating to
setback or other requirements not involving lot area, lot width or shore frontage
shall be obtained by action of the Board of Appeals.
(2) Contiguous Built Lots: If two or more contiguous lots or parcels are in a single
or joint ownership of record at the time of adoption of this Ordinance, if all or part of
the lots do not meet the dimensional requirements of this Ordinance, and if a
principal use or structure exists on each lot, the non-conforming lots may be
conveyed separately or together, provided that the State Minimum Lot Size Law
(12 M.R.S.A. sections4807- A through 4807-D) and the State of Maine Subsurface
Naples Shoreland Zoning Ordinance Amended June, 2024
11
Wastewater Disposal Rules are complied with.
If two or more principal uses or structures existed on a single lot of record on the
effective date of this ordinance each may be sold on a separate lot provided that
the above referenced law and rules are complied with. When such lots are divided
each lot thus created must be as conforming as possible to the dimensional
requirements of this Ordinance.
(3) Contiguous Lots - Vacant or Partially Built: lf two or more contiguous lots or
parcels are in single or joint ownership of record at the time of or since adoption or
amendment of this Ordinance. if any of these lots do not individually meet the
dimensional requirements of this Ordinance or subsequent amendments, and if
one or more of the lots are vacant or contain no principal structure; the lots shall be
combined to the extent necessary to meet the dimensional requirements.
This provision shall not apply to 2 or more contiguous lots, at least one of which is
non-conforming, owned by the same person or persons on the effective date of this
Ordinance and recorded in the registry of deeds if the lot is served by a public
sewer or can accommodate a subsurface sewage disposal system in conformance
with the State of Maine Subsurface Wastewater Disposal Rules; and
(a)
Each lot contains at least 100 feet of shore frontage and at least 20,000
square feet of lot area; or
(b)
Any lots that do not meet the frontage and lot size requirements
of Section 12(E)(3)(a) are reconfigured or combined so that each new lot
contains at least 100 feet of shore frontage and 20,000 square feet of lot area.
DEFINITION OF FOOTPRINT:
Footprint- "Footprint'· means the entire area of ground covered by the structure(s)
on a lot, including but not limited to cantilevered or similar overhanging extensions.
as well as unenclosed structures, such as patios and decks.
Section 13. Establishment of Districts
(A) Resource Protection District
The Resource Protection District includes areas in which development would
adversely affect water quality, productive habitat, biological ecosystems, or
scenic and natural values. This district shall include the following areas when
they occur within the Limits of the shoreland zone, exclusive of the Stream
Protection District, except those areas which are currently developed, and
areas which meet the criteria for the Limited Commercial need not be included
within the Resource Protection District.
1. Areas within 250 feet, horizontal distance. of the upland edge of
freshwater, wetlands and wetlands associated with great ponds and rivers
which are rated "moderate" or "high' value waterfowl and wading bird habitat.
including nesting and feeding areas by the Maine Department of Inland
Fisheries and Wildlife (MDIF&W) that are depicted on a Geographic
Information System (GIS) data layer maintained by either MDIF&W or the
Naples Shoreland Zoning Ordinance Amended June, 2024
12
Department as of December 31, 2008. For the purposes of this paragraph
"wetlands associated with great ponds and rivers. Shall mean areas
characterized by non-forested wetland vegetation and hydric soils that are
contiguous with a great pond or river, and have a surface elevation at or
below the water level of the great pond or river during the period of normal
high water. "Wetlands associated with great ponds or rivers" are considered to
be part of that great pond or river.
2. Flood plains along rivers and flood plains along artificially formed great
ponds along rivers, defined by the 100-year flood plain as designated on the
Federal Emergency Management Agency's (FEMA) Flood Insurance Rate Maps
or Flood Hazard Boundary Maps, or the flood of record, or in the absence of
these, by soil types identified as recent flood plain soils.
3. Areas of two or more contiguous acres with sustained slopes of 20% or
greater.
4. Areas of two (2) or more contiguous acres supporting wetland vegetation
and hydric soils, which are not part of a freshwater wetland as defined, and which
are not surficial connected to a water body during the period of normal high
water.
5. Land areas along rivers are subject to severe bank erosion, undercutting, or
riverbed movement.
6. Other important wildlife habitat.
7. Natural sites or significant scenic or esthetic value.
8. Areas designated by federal, state, or municipal governments are natural
areas of significance to be protected from development.
9. Other significant areas which should be included in this district to fulfill the
purposes of this Ordinance such as. but not limited to existing public access
areas and certain significant archaeological and historic sites deserving of long-
term protection as determined by the municipality after consultation with the
Maine Historic Preservation Commission.
(B) Limited Residential District
The Limited Residential District includes those areas suitable for residential and
recreational development. It includes areas other than those in the Resource
Protection District, or Stream Protection District, and areas which are used less
intensively than those in the Limited Commercial District.
(C) Limited Commercial District
The Limited Commercial District includes areas of mixed, light commercial and
residential uses, exclusive of the Stream Protection District. This district includes areas
of two or more contiguous acres in size devoted to a mix of residential and low intensity
business and commercial uses. Industrial uses are prohibited.
(D) Stream Protection District
The Stream Protection District includes all land areas within seventy-five (75) feet,
horizontal distance, of the normal high-water line of a stream, exclusive of those
areas within two hundred fifty (250) feet, horizontal distance. of the normal high- water
Naples Shoreland Zoning Ordinance Amended June, 2024
13
line of a great pond or river, or within two hundred and fifty (250) feet, horizontal
distance, of the upland edge of a freshwater wetland. Where a stream and its
associated shoreland area is located within two hundred and fifty (250) feet, horizontal
distance, of the above water bodies or wetlands, that land area shall be regulated
under the terms of the shore land district associated with that water body
or wetland.
(E) Causeway Overlay District
A. The Causeway Overlay District shall be a mix of commercial uses on the
ground level and residential and/or commercial uses on upper levels. The
Causeway Overlay District overlays the Shoreland Zoning Limited Commercial
District, as shown on the Official Shoreland Zoning Map.
B. Only those uses permitted in the Shoreland Zoning Limited Commercial
District (as set forth in Section 14, Table I of the Shoreland Zoning
Ordinance for the Town of Naples) shall be allowed in the Causeway Overlay
District, except as follows:
i. No residential use shall be allowed on the ground level of any structure.
whether a single-story or a multi-story structure.
ii. Residential, commercial. governmental, institutional, and any other
permitted use, including a combination thereof shall be allowed on any
upper level of a multi- story structure.
C. All land uses and structures within the Causeway Overlay District shall
conform with the following minimum lot area, shore frontage, and setback
requirements:
i.
Minimum lot area and minimum shore frontage requirements:
Minimum Lot
Area
(sq. ft.)
Minimum
Shore
Frontage (ft.)
Residential use (per dwelling unit) 40,000
200
Commercial, Governmental, or
Institutional use (per principal
structure)
60,000
300
Public and Private Recreational
Facilities
40,000
200
ii. Minimum setback requirements:
Minimum shore setback from normal high watermark (ft.): 100
Naples Shoreland Zoning Ordinance Amended June, 2024
14
Minimum setback from lot lines (ft.): 20
The requirements set forth in this supersede the minimum lot area, shore
frontage, and setback requirements set forth in Section 15.A of the
Shoreland Zoning Ordinance for the Town of Naples. All other
requirements of Section 15.A shall apply.
Section 14. Table of Land Uses
All land use activities, as indicated in Table I, Land Uses in the
Shoreland Zone, shall conform with all of the applicable land use standards
in Section 15. The district designation for a particular site shall be
determined from the Official Shoreland Zoning Map.
Key to Table 1:
Yes - Allowed (no permit required, but the use must comply with all
applicable land use standards).
No - Prohibited.
PB - Allowed with approval by the Planning Board and permit issued by
the CEO where appropriate.
CEO - Allowed with permit issued by the Code Enforcement Officer. LPI -
Allowed with permit issued by the Local Plumbing Inspector.
Abbreviations:
RP- Resource Protection; LR - Limited Residential; CO- Causeway
Overlay
LC - Limited Commercial; SP - Stream Protection
TABLE 1- LAND USES IN THE SHORELAND ZONE
LAND USE DISTRICTS
SP
RP
LR
LC
CO
1.
Non-intensive recreational uses not
requiring structures such as hunting,
fishing, and hiking
Yes
Yes
Yes
Yes
Yes
2.
Motorized vehicular traffic on existing
roads and trails
Yes
Yes
Yes
Yes
Yes
3.
Clearing or removal of vegetation for
activities
CEO
CEO1 CEO
CEO
CEO
4.
Fire prevention activities
Yes
Yes
Yes
Yes
Yes
5.
Signs
Yes
Yes
Yes
Yes
Yes
6.
Wildlife management practices
Yes
Yes
Yes
Yes
Yes
7.
Soil and Water conservation practices Yes
Yes
Yes
Yes
Yes
8.
Mineral Exploration
No
Yes2
Yes2
Yes2
Yes
9.
Mineral Extraction including sand and
gravel extraction
No
PB3
PB
PB
PB
Naples Shoreland Zoning Ordinance Amended June, 2024
15
10.
Surveying and Resource Analysis
Yes
Yes
Yes
Yes
Yes
11.
Emergency operations
Yes
Yes
Yes
Yes
Yes
12.
Agriculture
Yes
PB
Yes
Yes
Yes
13.
Aquaculture
PB
PB
PB
Yes
Yes
14.
Principal structures and uses
A. One and Two family residential,
including driveways
PB4,10 No10
CEO10 CEO10 CEO
B. Multi-Unit Residential
No
No
PB
PB
PB
C. Commercial
No
No9
No9
PB
PB
D. Industrial
No
No
No
No
No
E. Governmental and Institutional
No4
No
PB
PB
PB
F. Small non-residential facilities
for educational, scientific, or
nature interpretation purposes
PB
PB
CEO
CEO
CEO
15.
Structures accessory to allowed uses PB
4,10,11
PB
1,10,11
CEO
10,11
CEO
10,11
CEO
16.
Conversations of seasonal
residences to year-round residences
LPI
No
LPI
LPI
LPI
17.
Home Occupations
CEO
PB
CEO
CEO
CEO
18.
Private sewage disposal systems for
allowed uses
LPI
NO
LPI
LPI
LPI
19.
Essential Services
PB6
PB6
PB
PB
PB
A. Roadside distribution lines
(34.5KV and lower)
CEO6
CEO6 Yes1,1
Yes1,1
Yes
B. Non-roadside or cross-country
distribution lines involving ten
poles or less in the shoreland
zone
PB6
PB6
PB
PB
PB
C. Non-roadside or cross-country
distribution lines involving eleven
or more poles in the shoreland
zone
PB6
PB6
PB
PB
PB
D. Other essential services
PB6
PB6
PB
PB
PB
20.
Service drops, as defined, to allowed
uses
Yes
Yes
Yes
Yes
Yes
21.
Public and private recreational areas
involving minimal structural
development
PB
PB
PB
CEO
CEO
22.
Individual, private campsites
CEO
CEO
CEO
CEO
CEO
23.
Campgrounds
No
No7
PB
PB
No
24.
Road construction
PB
No8
PB
PB
PB
25.
Parking facilities
No
No7
PB
PB
PB
26.
Marinas
PB
No
PB
PB
PB
27.
Filling and earthmoving of <10 cubic
yards
CEO
CEO
Yes
Yes
Yes
Naples Shoreland Zoning Ordinance Amended June, 2024
16
28.
Filling and earthmoving of > 10 cubic
yards
PB
PB
CEO
CEO
CEO
29.
Uses similar to allowed uses
CEO
CEO
CEO
CEO
CEO
30.
Uses similar to uses requiring a CEO
permit
CEO
CEO
CEO
CEO
CEO
31.
Uses similar to uses requiring a PB
permit
PB
PB
PB
PB
PB
1 In RP not allowed within 75 feet horizontal distance of the normal high-water line of great ponds, except to
remove safety hazards.
2 Requires permit from the Code Enforcement Officer is more than 100 square feet of surface area in total is
disturbed.
3. In RP not allowed in areas so designated because of wildlife value.
4. Provided that a variance from the setback requirement is obtained from the Board of Appeals
6 See further restrictions in Section 15.M.2 Except when area is zoned for resource protection due to flood plain
criteria in which case a permit is required from the PB except as provided in Section 15.1.4
7. Except for commercial uses otherwise listed in this Table, such as marinas and campgrounds, which are allowed
in the respective district.
8. Excluding bridges and other crossings not involving earthwork, in which case no permit is required.
9. Permit not required but must file a written "notice of intent to construct" with CEO.
10. Accessory apartments are prohibited in the Shoreland Zone.
11. Bedrooms are prohibited in accessory structures.
NOTE: A person performing any of the following activities shall require a permit from the Department of
Environmental Protection, pursuant to 38 M.R.S.A., Section 480-C, if the activity occurs in, on, over or
adjacent to any freshwater or coastal wetlands, great pond, river, stream o brook and operates in such
a manner that material or soil may be washed into them:
A. Dredging, bulldozing, removing or displacing soil, sand, vegetation, or other
materials
B. Draining or otherwise dewatering
C. Filing, including adding sand or other material to a sand dune; or
D. Any construction or alteration of any permanent structure.
Section 15. Land Use Standards
All land use activities within the shoreland zone shall conform with the following
minimum provisions, if applicable.
A. Minimum Lot Standards
Minimum Lot
Area (sq. ft.)
Minimum
Shore
Frontage (ft.)
Minimum Bldg.
Setback from Lot
Lines (ft).
Residential(per dwelling unit) 60,000*
200
20
Governmental,
Institutional,
Commercial or Industrial (per
principal structure)
60,000
200
20
Public and Private
Recreational Facilities
60,000
200
20
Naples Shoreland Zoning Ordinance Amended June, 2024
17
1. Land below the normal high-water line of a water body or upland edge of a
wetland and land beneath roads serving more than two (2) lots shall not be
included toward calculating minimum lot area.
2. Lots located on opposite sides of a public or private road shall be considered
each a separate tract or parcel of land unless such road was established by the
owner of land on both sides thereof after September 22, 1971.
3. The minimum width of any portion of any lot within one hundred (100) feet.
horizontal distance, of the normal high-water line of a water body or upland
edge of a wetland shall be equal to or greater than the shore frontage
requirement for a lot with the proposed use.
4. If more than one residential dwelling unit, principal governmental,
institutional, commercial, or industrial structure or use, or combination
thereof, is constructed or established on a single parcel all dimensional
requirements shall be met for each additional dwelling unit, principal
structure, or use.
B. Principal and Accessory Structures
1. All new principal and accessory structures shall be set back at least one hundred (1
00) feet, horizontal distance from the normal high-water line of great ponds classified
GPA and rivers that flow to great ponds classified GPA, and seventy- five (75) feet,
horizontal distance, from the normal high-water line of other water bodies, tributary
Streams, or the upland edge of a wetland. In the Resource Protection District the
setback requirement shall be 250 feet, horizontal distance except for structures, roads,
parking spaces, or other regulated objects specifically allowed in that district in which
case the setback requirements specified above shall apply. The following great ponds
are classified GPA in Naples: Long Lake, Brandy Pond, Sebago Lake. Trickey Pond,
Peabody Pond, Cold Rain Pond, and Holt Pond.
In addition:
a. On a non-conforming lot of record on which only a residential structure exists, and it
is not possible to place an accessory structure meeting the required water body,
tributary stream, or wetland setbacks the Code Enforcement Officer may issue a permit
to place a single accessory structure with no utilities, for the storage of yard tools and
similar equipment. Such accessory structure shall not exceed eighty (80) square feet in
area nor eight (8) feet in height and shall be located as far from the shoreline or tributary
stream as practical and shall meet all other applicable standards, including lot coverage
and vegetation clearing limitations. In no case shall the structure be located closer to
the shoreline or tributary stream than the principal structure.
b. Alternative energy structures may be placed within the setback area but only in a
legally existing clearing and any additional vegetation removal necessary must conform
to the vegetation removal provisions within the ordinance. In addition, the extent of a
proposed alternative energy project must be limited by design to the energy needs of
Naples Shoreland Zoning Ordinance Amended June, 2024
18
the existing use on the property. The sale of energy to the power grid must be limited to
incidental excess power generation. Projects designed for commercial generation of
power must comply with structure setback requirements.
c. The waterbody, tributary stream or wetland setback provision shall not apply to
Municipally owned structures within the reclaimed areas of Route 302 and the Naples
Bay Bridge Project area.
2. Principal or accessory structures and expansions of existing structures
which are permitted in the Resource Protection, Limited Residential, Limited
Commercial, and Stream Protection Districts shall not exceed thirty-five (35)
feet in height. This provision shall not apply to structures such as transmission
towers, windmills, antennas, and similar structures having no floor area.
3. The lowest floor elevation or openings of all buildings and structures,
including basements shall be elevated at least one foot above the elevation of
the 100-year flood, the flood of record, or in the absence of these, the flood as
defined by soil types identified as recent flood plain soils. In those municipalities
that participate in the National Flood Insurance Program and have adopted the
April 2005 version, or later version of the Floodplain Management Ordinance,
accessory structures may be placed in accordance with the standards of that
ordinance and need not meet the elevation requirements of this paragraph.
4. Non-vegetated surfaces within the shoreland zone shall not exceed twenty
percent (20%) of the lot or a portion thereof located within the shoreland zone.
including land area previously developed. The non-vegetated surfaces within
the Shoreland zone for Municipally owned/controlled Naples Causeway Project
shall not exceed 20% of the lot or a portion thereof located within the Shoreland
zone including land area previously developed. These limitations do not apply
to public boat launching facilities regardless of the district in which the facility is
located.
For the purposes of calculating lot coverage, non-vegetated surfaces include,
but are not limited to the following: structures, driveways, parking areas, and
other areas from which vegetation has been removed.
5. Retaining walls that are not necessary for erosion control shall meet the
structure setback requirement, except for low retaining walls and associated till
provided all of the following conditions are met:
a. The site has been previously altered, and an effective vegetated buffer does
not exist.
b. The wall(s) is(are) at least 25 feet horizontal distance from the normal high-
water line of a water body, tributary stream, or upland edge of a wetland.
c. The site where the retaining wall will be constructed is legally existing lawn or
is a site eroding from lack of naturally occurring vegetation and which cannot be
stabilized with vegetative plantings.
d. The total height of the wall(s), in the aggregate are no more than 24 inches.
e. Retaining walls are located outside of the 100-year floodplain on rivers.
Naples Shoreland Zoning Ordinance Amended June, 2024
19
streams, and tributary streams as designated on the Federal Emergency
Management Agency's (FEMA) Flood Insurance Rate Maps or Flood
hazard Boundary Maps, or the flood of record, or in the absence of these, by soil
types identified as recent flood plain soils.
f. The area behind the wall is revegetated with grass, shrubs, trees, or a
combination thereof, and no further structural development will occur within the
setback area, including patios and decks; and
g. A vegetated buffer area is established within 25 feet, horizontal
distance, of the normal high-water line of a water body, tributary stream, or
upland edge of a wetland when a natural buffer area does not exist.
The buffer area must meet the following characteristics:
I. The buffer must include shrubs and other woody and herbaceous
vegetation. Where natural ground cover is lacking the area must be
supplemented with leaf or bark mulch.
II. Vegetation plantings must be in quantities sufficient to retard
erosion and provide for effective infiltration of storm water runoff.
III. Only native species may be used to establish the buffer area.
IV. A minimum buffer width of 15 feet, horizontal distance, is required
measured perpendicularly to the normal high-water line or upland edge of a
wetland.
V. A footpath not to exceed the standards in Section 15.P.2.a, may
traverse the buffer.
6. Notwithstanding the requirements stated above, stairways or similar
structures may be allowed with a permit from the Code Enforcement Officer, to
provide shoreland access in areas of steep slopes or unstable soils provided
that the structure is limited to a maximum of four (4) feet in width; that the
structure does not extend below or over the normal high-water line of a water
body or upland edge of a wetland (unless permitted by the Department of
Environmental Protection pursuant to the Natural Resources Protection Act, 38,
Section 480-C); and that the applicant demonstrates that no reasonable access
alternative exists on the property.
C. Aquatic Structures. Moorings and Other Structures and Uses
Extending Over or Below the Normal High-Water Line of a Water Body or
Within a Wetland, and Shoreline Stabilization. See Section 6 of Mooring
and Waterfront Ordinance.
D. Watercraft. See Mooring and Waterfront Ordinance.
E. Campgrounds: Campgrounds shall conform to the minimum requirements
imposed under State licensing procedures and the following:
State licensed campgrounds located in Naples as of November 18, 1988
(Licensed by the Division of health Engineering. Department of Human
Services):
Naples Shoreland Zoning Ordinance Amended June, 2024
20
CAMPGROUNDS LOCATION SITES
Bay of Naples Family Camping Route 11/114 150
Brandy Pond Camps Songo School Road 28
Brandy Pond Park Route 302 77
Colonial Mast Campground Kansas Road 79
Four Seasons Camping Area Route 302 115
Loon's Haven Campground Route 11/114 125
The Quinby's Thompson's Point 20
1. Campgrounds shall contain a minimum of five thousand (5000) square feet of
land, not including roads and driveways for each site. Land supporting wetland
vegetation, and land below the normal high-water line of a water body shall not be
Included in calculating land area per site.
2. The areas intended for placement of a recreational vehicle, tent, or shelter, and
utility and service buildings shall be set back a minimum of one hundred (100) feet,
horizontal distance, from the normal high-water line of a great pond classified GPA
or a river flowing to a great pond classified GPA, and seventy-five (75) feet,
horizontal distance, from the normal high-water line of other water bodies, tributary
streams, or the upland edge of a wetland.
F. Individual Private Campsites: Individual, private campsites not associated with
campgrounds are allowed provided that the following conditions are met:
1. One campsite per lot existing on the effective date of this Ordinance or one
campsite per thirty thousand (30,000) square feet of lot area within the
shoreland zone, whichever is less, may be permitted.
2. When an individual private campsite is proposed on a lot that contains
another principal use and/or structure, the lot must contain the minimum lot
dimensional requirements for the principal structure and/or use, and the
individual private campsite separately.
3. Campsite placement on any lot including the area intended for a recreational
vehicle or tent platform, shall be set back one hundred (100) feet, horizontal
distance, from the normal high-water line of a great pond classified GPA or
river flowing to a great pond classified GPA and seventy-five (75) feet,
horizontal distance from the normal high-water line of other water bodies.
tributary streams, or the upland edge of a wetland.
4. Only one recreational vehicle shall be allowed on a campsite. The
recreational vehicles shall not be located on any type of permanent
foundation except for a gravel pad, and no structure except a canopy shall be
attached to the recreational vehicle.
5. The clearing of vegetation for the siting of the recreational vehicle, tent or
similar shelter in a Resource Protection District shall be limited to one thousand
(1000) square feet.
a. A written sewage disposal plan describing the proposed method and
location of sewage disposal shall be required for each campsite and shall be
approved by the Local Plumbing Inspector. Where disposal is off-site written
authorization from the receiving facility or landowner is required.
Naples Shoreland Zoning Ordinance Amended June, 2024
21
b. When a recreational vehicle, tent or similar shelter is placed on-site for
more than one hundred and twenty (120) days per year all requirements for
residential structures shall be met including the installation of a subsurface
sewage disposal system in compliance with the State of Maine Subsurface
Wastewater Disposal Rules unless served by public sewage facilities.
G. Commercial and Industrial Uses: The following new commercial and
i n d ustrial uses are prohibited within the shoreland zone adjacent to great ponds
classified GPA. and rivers and streams which flow to great ponds classified
GPA:
1. Auto washing facilities
2. Auto or other vehicle service and/or repair operations, including body shops
3. Chemical and bacteriological laboratories
4. Storage of chemicals including herbicides, pesticides, or fertilizers other
than amounts normally associated with individual households or farms
5. Commercial painting, wood preserving, and furniture stripping
6. Dry cleaning establishments
7. Electronic circuit assembly
8. Laundromats, unless connected to a sanitary sewer
9. Metal plating, finishing, or polishing
10. Petroleum or petroleum product storage and/or sale except for storage on
same property as use occurs and except for storage and sales associated with
marinas
11. Photographic processing
12. Printing
13. Medical Marijuana Cultivation
H. Parking Areas:
1. Parking areas shall meet the shoreline and tributary stream setback
requirements for structures for the district in which such areas are located. The
setback requirement for parking areas serving public boat launching facilities
shall be no less than fifty (50) feet, horizontal distance, from the shoreline or
tributary stream if the Planning Board finds that no other reasonable alternative
exists further from the shoreline or tributary stream.
2. Parking areas shall be adequately sized for the proposed use and shall be
designed to prevent storm water runoff from flowing directly into a water body, tributary,
stream, or wetland and where feasible to retain all runoff on-site.
3. In determining the appropriate size of proposed parking facilities the following shall
apply:
i. Typical parking space: Approximately ten (10) feet wide and twenty (20)
feet long except that parking spaces for a vehicle and boat trailer shall be forty
(40) feet long.
ii. Internal travel aisles: Approximately twenty (20) feet wide.
I. Roads and Driveways: The following standards shall apply to the
construction of roads and/or driveways and drainage systems, culverts, and
Naples Shoreland Zoning Ordinance Amended June, 2024
22
other related features:
1. Roads and driveways shall be set back at least one hundred (100) feet.
horizontal distance, from the normal high-water line of a great pond
classified GPA or a river that flows to a great pond classified GPA, and
seventy-five (75) feet, horizontal distance, from the normal high-water line
of other water bodies, tributary streams, or the upland edge of a wetland
unless no reasonable alternative exists as determined by the Planning
Board. If no other reasonable alternative exists the road and/or driveway
setback requirement shall be no less than fifty (50) feet, horizontal
distance, upon clear showing by the applicant that appropriate techniques
will be used to prevent sedimentation of or transport of
phosphorus to the water body, tributary stream, or wetland. Such
techniques may include, but are not limited to the installation of settling
basins, and/or the effective use of additional ditch relief culverts and
turnouts placed so as to avoid sedimentation of the water body, tributary
stream, or wetland.
On slopes of greater than twenty percent (20%) the road and/or driveway
setback shall be increased by ten (10) feet, horizontal distance, for each
five percent (5%) increase in slope above twenty percent (20%).
Section 15.1.1 does not apply to approaches to water crossings nor to
roads or driveways that provide access to permitted structures, and
facilities located nearer to the shoreline or tributary stream due to an
operational necessity.
Roads and driveways providing access to permitted structures within the
setback area shall comply fully with the requirements of Section 15.1.1
except for that portion of the road or driveway necessary for direct
access to the structure.
2. Existing public roads may be expanded within the legal road right-of-way
regardless of their setback from a water body, tributary stream, or
wetland.
3. New roads and driveways are prohibited in a Resource Protection District
except that the Planning Board may grant a permit to construct a road or
driveway to provide access to permitted uses within the district. A road or
driveway may also be approved by the Planning Board in a Resource
Protection District upon finding that no reasonable alternative route or
location is available outside the district. When a road or driveway is
permitted in a Resource Protection District the road and/or driveway shall
be set back as far as practicable from the normal high-water line of a water
body, tributary stream, or upland edge of a wetland.
4. Road and driveway banks shall be no steeper than a slope of two (2)
Naples Shoreland Zoning Ordinance Amended June, 2024
23
horizontal to one (1) vertical and shall be graded and stabilized in
accordance with the provisions for erosion and sedimentation control
contained in Section 15.U.
5. Road and driveway grades shall be no greater than ten percent (10%) except
for segments of less than two hundred (200) feet.
6. ln order to prevent road and driveway surface drainage from directly entering
water bodies, tributary streams, or wetlands, roads and driveways shall be
designed, constructed, and maintained to empty onto an unscarified buffer
strip at least fifty (50) feet plus two times the average slope in width between
the outflow point of the ditch or culvert and the normal high-water line of a
water body, tributary stream, or upland edge of a wetland. Surface drainage
which is directed to an unscarified buffer strip shall be diffused or spread out
to promote infiltration of the runoff and to minimize channelized flow of the
drainage through the buffer strip.
7. Ditch relief (cross drainage), drainage dips and water turnouts shall be
installed in a manner effective in directing drainage onto unscarified buffer
strips before the flow gains sufficient volume or head to erode the road,
driveway, or ditch. To accomplish this, the following shall apply:
A. Ditch relief culverts. drainage dips and associated water turnouts
shall be spaced along the road or driveway at intervals no greater
than indicated in the following table:
Grade
(Percent)
Spacing
(Feet)
0-2
250
3-5
200-135
6-10
I00-80
11-15
80-60
16-20
60-45
21+
40
B. Drainage dips may be used in place of ditch relief culverts only
where the grade is ten percent (10%) of less.
C. On sections having slopes greater than ten percent ( 1 0 % ) ditch relief
culverts shall be placed at approximately a thirty (30) degree angle
down slope from a line perpendicular to the centerline of the road or
driveway.
D. Ditch relief culverts shall be sufficiently sized and properly installed in
order to allow for effective functioning, and their inlet and outlet ends
shall be stabilized with appropriate materials.
8. Ditches, culverts, bridges, dips, water turnouts, and other storm water runoff
Naples Shoreland Zoning Ordinance Amended June, 2024
24
control installations associated with roads and driveways shall be maintained
on a regular basis to assure effective functioning.
J.
Signs:
The following provisions shall govern the use of signs in the
Resource Protection and Stream Protection Limited Residential and Limited
Commercial Districts:
1. Signs relating to goods and services sold on the premises shall be allowed
provided that such signs shall not exceed six (6) square feet in area and shall
not exceed two (2) signs per premises. In the Limited Commercial however,
such signs shall not exceed sixteen (16) square feet in area. Signs relating to
goods or services not sold or rendered on the premises shall be prohibited.
2. Name signs are allowed, provided such signs shall not exceed two (2) signs
per premises, and shall not exceed twelve (12) square feet in the aggregate.
3. Residential users may display a single sign not over three (3) square feet in
area relating to the sale, rental, or lease of the premises.
4. Signs relating to trespassing and hunting shall be allowed without restriction
as to number provided that no such sign shall exceed two (2) square feet in
area.
5. Signs relating to public safety shall be allowed without restriction.
6. No sign shall extend higher than twenty (20) feet above the ground.
7. Signs may be illuminated only be shielded non-flashing lights.
K. Storm Water Runoff:
1. All new construction and development shall be designed to minimize storm
water runoff from the site in excess of the natural predevelopment conditions.
Where possible existing natural runoff control features such as berms, swales,
terraces, and wooded areas shall be retained in order to reduce runoff and
encourage infiltration of storm waters.
2. Storm water runoff control systems shall be maintained as necessary to
ensure proper functioning.
L. Septic Waste Disposal:
1. All subsurface sewage disposal systems shall be installed in conformance
with the State of Maine Subsurface Wastewater Disposal Rules, and the
following:
a. Clearing or removal of woody vegetation necessary to site a new
system and any associated fill extensions shall not extend closer than
seventy-five (75) feet horizontal distance from the normal high-water line
of a water body or the upland edge of a wetland and a holding tank is not
allowed for a first-time residential use in the shoreland zone.
b. The minimum setback for new subsurface sewage disposal
systems shall be no less than one hundred (100) horizontal feet from the
normal high-water line of a perennial water body. The minimum setback
distances from water bodies for new subsurface sewage disposal
systems shall not be reduced by variance.
Naples Shoreland Zoning Ordinance Amended June, 2024
25
M. Essential Services:
1. Where feasible, the installation of essential services shall be limited to
existing public ways and existing service corridors.
2. The installation of essential services other than road-side distribution
Iines, is not allowed in a Resource Protection or Stream Protection
District, except to provide services to a permitted use within said district,
or except where the applicant demonstrates that no reasonable
alternative exists. Where allowed such structures and facilities shall be
located so as to minimize any adverse impacts on surrounding uses and
resources including visual impacts.
3. Damaged or destroyed public utility transmission and distribution lines
towers and related equipment may be replaced or reconstructed without
a permit.
N . Mineral Exploration and Extraction: Mineral exploration to determine the
nature or extent of mineral resources shall be accomplished by hand sampling,
test boring, or other methods which create minimal disturbance of less than one
hundred (100) square feet of ground surface. A permit from the Code
Enforcement Officer shall be required for mineral exploration, which exceeds the
above limitation. All excavations. including test pits and holes shall be
immediately capped, filled, or secured by other equally effective measures, to
restore disturbed areas and to protect the public health and safety.
Mineral extraction may be permitted under the following conditions:
1. A reclamation plan shall be filled with and approved by the Planning
Board before a permit is granted. Such plan shall describe in detail the
procedures to be undertaken to fulfill the requirements of Section 15.N.3
below.
2. No part of any extraction operation including drainage and runoff control
features shall be permitted within one hundred (100) feet, horizontal
distance of the normal high-water line of a great pond classified GPA or a
river flowing to a great pond classified GPA and within seventy-five (75)
feet horizontal distance of the normal high-water line of any other water
body, tributary stream, or the upland edge of a wetland. Extraction
operations shall not be permitted within fifty (50) feet, horizontal distance,
of any property line without written permission of the owner of such adjacent
property.
3. Within twelve (12) months following the completion of extraction operations at
any extraction site, which operations shall be deemed complete when less
than one hundred (100) cubic yards of materials are removed in any
consecutive twelve (12) month period, ground levels and grades shall be
established in accordance with the following:
A. All debris, stumps, and similar material shall be removed for disposal in an
Naples Shoreland Zoning Ordinance Amended June, 2024
26
approved location or shall be buried on-site. Only materials generated on-site
may be buried or covered on-site.
The State of Maine Solid Waste Laws, 38, M.R.S.A,
Section 130 I and the solid waste management
rules, Chapters 400-419 of the Department of
Environmental Protection's regulations may contain
other applicable provisions Regarding disposal of
such materials.
B. The final graded slope shall be two and one-half to one (21/2:1 slope or
flatter.
C. Topsoil or loam shall be retained to cover all disturbed land areas which shall
be reseeded and stabilized with vegetation native to the area. Additional
topsoil or loam shall be obtained from off-site sources if necessary, to
complete the stabilization project.
4. In keeping with the purposes of this Ordinance, the Planning Board may impose
such conditions as are necessary to minimize the adverse impacts associated
with mineral extraction operations on surrounding uses and resources.
O. Agriculture
1. All spreading of manure shall be accomplished in conformance with the
Manure Utilization Guidelines published by the former Maine Department of
Agriculture on November 1, 2001, and the Nutrient Management Law (7
M.R.S.A. sections 4201-4209).
2. Manure shall not be stored or stockpiled within one hundred (100) feet,
horizontal distance, of a great pond classified GPA or a river flowing to a great
pond classified GPA, or within seventy-five (75) feet horizontal distance of
other water bodies, tributary streams, or wetlands. All manure storage areas
within the shoreland zone must be constructed or modified such that the
facility produces no discharge of effluent or contaminated storm water.
3. Agricultural activities involving tillage of soil greater than forty thousand
(40,000) square feet in surface area, within the shoreland zone shall
require a Conservation Plan to be filed with the Planning Board non-
conformance with the provisions of said plan shall be considered to be a
violation of this Ordinance.
Assistance in preparing a Conservation Plan may be available through the
local oil and Water Conservation District office.
4. There shall be no new tilling of soil within one hundred (100) feet horizontal
distance of the normal high-water line of a great pond classified GPA: within
seventy-five (75) feet, horizontal distance, from other water bodies: nor within
twenty-five (25) feet. horizontal distance, of tributary streams and freshwater
Naples Shoreland Zoning Ordinance Amended June, 2024
27
wetlands. Operations in existence on the effective date of this ordinance and
not in conformance with this provision may be maintained.
5. Newly established livestock grazing areas shall not be permitted within
one hundred (100) feet horizontal distance; of the normal high-water Iine
of a great pond classified GPA; within seventy-five (75) feet horizontal
distance of other water bodies, nor within twenty-five (25) feet. horizontal
distance of tributary streams and freshwater wetlands. Livestock
grazing associated with ongoing farm activities, and which are not in
conformance with the above setback provisions may continue provided
that such grazing is conducted in accordance with a Conservation Plan
that has been filed with the Planning Board.
P. Timber Harvesting: State of Maine Department of Conservation's Bureau of
Forestry shall administer timber harvesting standards in the shoreland zone.
Q. Clearing or Removal of Vegetation for Activities Other Than Timber
Harvesting:
1. In a Resource Protection District abutting a great pond, there shall be no cutting
of vegetation within the strip of land extending seventy-five (75) feet, horizontal
distance, inland from the normal high-water mark except to remove hazard trees
as described in Section 15(Q).
Elsewhere in any Resource Protection District the cutting or removal of
vegetation shall be limited to that which is necessary for uses expressly
authorized in that district.
2. Except in areas as described in Section Q.1 above, within a strip of land
extending one hundred (100) feet, horizontal distance, inland from the normal
high-water line of a great pond classified GPA or a river flowing to a great pond
classified GPA or within a strip extending seventy-five (75) feet, horizontal
distance from any other water body, tributary stream, or the upland edge of a
wetland a buffer strip of vegetation shall be preserved as follows:
A. There shall be no cleared opening greater than two hundred fifty (250)
square feet in the forest canopy (or other existing woody vegetation if a
forested canopy is not present) as measured from the outer limits of the
tree crown or shrub. However, a single footpath not to exceed six (6)
feet in width as measured between tree trunks and/or shrub stems is
allowed for accessing the shoreline provided that a cleared line of sight
to the water through the buffer strip is not created.
B. Selective cutting of trees within the buffer strip is allowed provided that a
well distributed stand of trees and other natural vegetation is
maintained. For the purposes of Section 15.Q.2.b.. a "well-distributed
stand of trees" adjacent to a great pond classified GPA or a river or
stream flowing to a great pond classified GPA, shall be defined as
maintaining a rating score of 24 or more in each 25-foot by 50-foot
rectangular (1250 square feet) area as determined by the following
Naples Shoreland Zoning Ordinance Amended June, 2024
28
rating system:
Diameter of Tree at 4 ½ Feet
Above Ground Level (inches)
Points
2- <4 inches
1
4-<8 inches
2
8 - <12 inches
4
12 inches or greater
8
Adjacent to other water bodies, tributary streams, and wetlands, a "well- distributed
stand of trees" is defined as maintaining a minimum rating score of 16 per 25-foot by
50-foot rectangular area.
[Note: As an example, adjacent to a great pond, if a 25-foot x 50- foot plot
contains four (4) trees between 2 and 4 inches in diameter, two (2) trees between
4 and 8 inches in diameter, three (3) tree between 8 and 12 inches in diameter,
and two trees over 12 inches in diameter, the rating score is:
(4x1) + (2x2) +(3x4) + (2x8) = 36 points
Thus, the 25-foot by 50-foot plot contains trees worth 36 points. Trees totaling 12
points (36 - 24 = 12) may be removed from the plot provided that no cleared
openings are created.
The following shall govern in applying this point system:
i. The 25-foot by 50-foot rectangular plots must be established where the
landowner or lessee proposes clearing within the required buffer.
ii. Any plot not containing the required points must have no vegetation
removed except as otherwise allowed by this Ordinance.
iii. Any plot containing the required points may have vegetation removed
down to the minimum points required or as otherwise allowed by this Ordinance.
iv. Where conditions permit, no more than 50% of the points on any 25-foot
by 50-foot rectangular area may consist of trees greater than 12 inches by diameter.
For the purposes of Section 15.Q.2.b. ·'other natural vegetation·' is defined as retaining
existing vegetation under three (3) feet in height and other ground cover and retaining at
least five (5) saplings less than two (2) inches in diameter at four and one half (4 ½) feet
above ground level for each 25- foot by 50-foot rectangular area. If five saplings do not
exist, no woody stems less than two (2) inches in diameter can be removed until 5
saplings have been recruited into the plot.
Notwithstanding the above provisions, no more than forty percent (40%) of the total
volume of trees four (4) inches or more in diameter measured at 4½ feet above ground
level may be removed in any ten (10) year period.
A. In order to protect water quality and wildlife habitat, existing vegetation under
three (3) feet in height and other ground cover including leaf litter and the forest
Naples Shoreland Zoning Ordinance Amended June, 2024
29
duff layer shall not be cut, covered, or removed, except to provide for a footpath
or other permitted uses as described in Section 15.Q paragraphs 2 and 2.a
above.
B. Pruning of tree branches on the bottom ½ of the tree is allowed.
C. In order to maintain a buffer strip of vegetation, when the removal of storm
damaged, dead or hazard trees results in the creation of cleared openings, these
openings shall be replanted with native tree species in accordance with Section
15 (Q). below, unless existing new tree growth is present.
D. In order to maintain the vegetation in the shoreline buffer clearing or removal of
vegetation for allowed activities, including associated construction and related
equipment operation, within or outside the shoreline buffer must comply with the
requirements of Section I 5.Q(2).
Section 15.Q.2 does not apply to those portions of public
recreational facilities adjacent to public swimming areas
as long as cleared areas are limited to the minimum area
necessary.
3. At distances greater than one hundred (100) feet. horizontal distance, from a
great pond classified GPA or a river flowing to a great pond classified GPA,
and seventy-five (75) feet, horizontal distance, from the normal high- water
line of any other water body, tributary stream, or the upland edge of a
wetland, there shall be allowed on any lot, in any ten (10) year period,
selective cutting of not more than forty percent (40%) of the volume of trees
four (4) inches or more in diameter measured 4½ feet above ground level.
Tree removal in conjunction with the development of permitted uses shall be
included in the forty percent (40%) calculation. For the purposes of these
standards, volume may be considered to be equivalent to basal area.
In no event shall cleared openings for any purpose, including but not limited
to, principal and accessory structures, driveways, lawns and sewage
disposal areas, exceed in the aggregate, 25% of the lot area within the
shoreland zone or ten thousand (10,000) square feet, whichever is greater,
including land previously cleared. This provision applies to the portion of a
lot within the shoreland zone, including the buffer area.
4. Legally existing nonconforming cleared openings may be maintained, but
shall not be enlarged, except as allowed by this Ordinance.
5. Fields and other cleared openings which have reverted to primarily shrubs
and trees. or other woody vegetation shall be regulated under the provisions
of Section 15.Q.
R. Hazard Trees. Storm-Damaged Trees. and Dead Tree Removal:
Naples Shoreland Zoning Ordinance Amended June, 2024
30
1. Hazard trees and dead trees in the shoreland zone may be removed with a
permit from the Code Enforcement Officer if the following requirements are
met:
A. Within the shoreline buffer if the removal of a hazard tree results in a
cleared opening in the tree canopy greater than two hundred and fifty
(250) square feet, replacement with native tree species is required,
unless there is new tree growth already present. New tree growth must
be as near as practicable to where the hazard tree was removed and
be at least two (2) inches in diameter, measured at four and one half
(4.5) feet above the ground level. If new growth is not present, then
replacement trees shall consist of native species and be at least four
(4) feet in height and be no less than two (2) inches in diameter.
Stumps may not be removed.
B. Outside of the shoreline buffer, when the removal of hazard trees
exceeds forty (40) percent of the volume of trees four (4) inches or
more in diameter, measured at four and one half (4.5) feet above
ground level in any ten (10) year period, and/or results in cleared
openings exceeding twenty-five (25) percent of the lot area within the
shoreland zone, or ten thousand (10,000) square feet whichever is
greater replacement with native tree species is required. unless there
is new tree growth already present. New tree growth must be as near
as practicable to where the hazard tree was removed and be at least
two (2) inches in diameter measured at four and one half (4.5) feet
above the ground level. If new growth is not present. then
replacement trees shall consist of native species and be at least two
(2) inches in diameter measured at four and one half (4.5) feet above
the ground level.
C.
The removal of standing dead trees, resulting from natural causes. is
permissible without the need for replanting. as long as the removal
does not result in the creation of new lawn areas. or other permanently
cleared areas, and stumps are not removed. For the purposes of this
provision dead trees are those trees that contain no foliage during the
growing season.
D. The Code Enforcement Officer may require the property owner to
submit an evaluation from a licensed forester or arborist before any
hazard tree or dead tree can be removed within the shoreland zone.
E. The Code Enforcement Officer may require more than a one-for-
one replacement for hazard trees removed that exceed eight (8)
inches in diameter measured at four and one half (4.5) feet above
the ground level.
Naples Shoreland Zoning Ordinance Amended June, 2024
31
2. Storm-damaged trees in the shoreland zone may be removed with a
permit from the Code Enforcement Officer if the following requirements
are met:
A. Within the shoreline buffer when the removal of storm-damaged
trees results in a cleared opening in the tree canopy greater than two
hundred and fifty (250) square feet replanting is not required, but the area
shall be required to naturally revegetate, and the following requirements
must be met:
The area from which a storm-damaged tree is removed does not
result in new lawn areas. or other permanently cleared areas.
ii. Stumps from the storm-damaged trees may not be removed.
iii. Limbs damaged from a storm event may be pruned even if they
extend beyond the bottom one-third (1/3) of the tree: and
iv. If after one growing season. no natural regeneration or regrowth
is present replanting of native tree seedlings or saplings is
required at a density of one seedling per every eighty (80) square
feet of lost canopy.
B. Outside of the shoreline buffer, if the removal of storm damaged trees
exceeds 40% of the volume of trees four (4) inches or more in diameter,
measured at four and one half (4.5) feet above the ground level in any ten
(10) year period, or results, in the aggregate, in cleared openings exceeding
25% of the lot area within the shoreland zone or ten thousand ( I0,000)
square feet, whichever is greater, and no natural regeneration occurs within
one growing season, then native tree seedlings or saplings shall be replanted
on a one-for-one basis.
S. Exemptions to Clearing and Vegetation Removal Requirements:
The following activities are exempt from the clearing and vegetation removal
standards set forth in Section I5(P), provided that all other applicable requirements
of this chapter are complied with, and the removal of vegetation is limited to that
which is necessary:
1. The removal of vegetation that occurs at least once every two (2) years for
the maintenance of legally existing areas that do not comply with the
vegetation standards in this chapter, such as but not limited to cleared
openings in the canopy or fields. Such areas shall not be enlarged, except
as allowed by this section. If any of these areas, due to lack of removal of
vegetation every two (2) years, reverts back to primarily woody vegetation,
Naples Shoreland Zoning Ordinance Amended June, 2024
32
the requirements of Section15(P) apply.
2. The removal of vegetation from the location of allowed structures or allowed
uses when the shoreline setback requirements of Section15(8) are not
applicable.
3. The removal of vegetation from the location of public swimming areas
associated with an allowed public recreational facility.
4. The removal of vegetation associated with allowed agricultural uses, provided
best management practices are utilized, and provided all requirements of
Section 15 (N) are complied with.
5. The removal of vegetation associated with brownfields or voluntary response
action program (VRAP) projects provided that the removal of vegetation is
necessary for remediation activities to clean-up contamination on a site in
commercial fisheries and maritime activities district or other equivalent zoning
district approved by the Commissioner that is part of a state or federal
brownfields program or a voluntary response action program pursuant 38
M.R.S.A section 343-E, and that is located along a river that does not flow to
a great pond classified as GPA pursuant to 38 M.R.S.A. section 465-A.
6. The removal of non-native invasive vegetation species, provided the
following minimum requirements are met:
A. If removal of vegetation occurs via wheeled or tracked motorized
equipment, the wheeled or tracked motorized equipment is operated
and stored at least twenty-five (25) feet, horizontal distance, from
the shoreline, except that wheeled or tracked equipment may be
operated or stored on existing structural surfaces, such a pavement
or gravel.
B. Removal of vegetation within twenty-five (25) feet. horizontal distance.
from the shoreline occurs via hand tools: and
C. If applicable clearing and vegetation removal standard are exceeded
due to the removal of non-native invasive species vegetation, the area
shall be revegetated with native species to achieve compliance.
NOTE: An updated list of non-native invasive vegetation is maintained by the
Department of Agriculture, Conservation and Forestry's Natural Areas Program:
http://www.maine.gov/dacf/map/features/invasive_plants/invasives.htm
7. The removal of vegetation associated with emergency response activities
conducted by the Department, the U .S. Environmental Protection Agency,
the U.S.Coast Guard, and their agents.
Naples Shoreland Zoning Ordinance Amended June, 2024
33
T. Revegetation Requirement:
When revegetation is required in response to violations of the vegetation standards set
forth in Section 15(P), to address the removal of non- native invasive species of
vegetation. or as a mechanism to allow for development that may otherwise not be
permissible due to the vegetation standards, including removal of vegetation in
conjunction with a shoreline stabilization project, the revegetation must comply with the
following requirement .
1. The property owner must submit a revegetation plan, prepared w i t h and
signed by a qualified professional, which describe revegetation activities
and maintenance. The plan must include a scaled site plan, depicting where
vegetation was, or is to be removed, where existing vegetation is to remain,
and where vegetation is to be planted, including a list of all vegetation to be
planted.
2. Revegetation must occur along the same segment of shoreline and in the
same area where vegetation was removed and at a density comparable to
the pre-existing vegetation, except where a shoreline stabilization activity
does not allow revegetation to occur in the same area and at a density
comparable to the pre-existing vegetation. in which case revegetation
must occur along the same segment of shoreline and as close as possible
to the area where vegetation was removed.
3. If part of a permitted activity, revegetation shall occur before the expiration
of the permit:
lf the activity or revegetation is not completed before the expiration of the
permit. a new revegetation plan shall be submitted with any renewal or
new permit application.
4. Revegetation activities must meet the following requirements for trees and
saplings:
A. All trees and saplings removed must be replaced with native
noninvasive species.
B. Replacement vegetation must at a minimum consist of saplings.
C. If more than three (3) trees or saplings are planted, then at least
three (3) different species shall be used.
D. No one species shall make up 50% or more of the number of
trees and saplings planted.
E. If revegetation is required for a shoreline stabilization project.
and it is not possible to plant trees and saplings in the same
Naples Shoreland Zoning Ordinance Amended June, 2024
34
area where trees or saplings were removed, then trees or
sapling must be planted in a location that effectively
reestablishes the screening between the shoreline and
structures: and
F. A survival rate of at least eighty (80) percent of planted trees or
saplings is required for a minimum five (5) year's period.
5. Revegetation activities must meet the following requirements for woody
vegetation and other vegetation under three (3) feet in height:
A. All wood vegetation and vegetation under three (3) feet in
height must be replaced with native noninvasive species of
woody vegetation and vegetation under three (3) feet in height as
applicable.
B. If more than three (3) woody vegetation plants are to be planted,
then at least three (3) different species shall be planted.
C. No one species shall make up 50% or more of the number of planted
woody vegetation plants; and
D. Survival of planted woody vegetation and vegetation under three
feet in height must be sufficient to remain in compliance with the
standards contained within this chapter for minimum of five (5)
years
6. Revegetation activities must meet the following requirement for ground vegetation
and ground cover:
A. All ground vegetation and ground cover removed must be replaced
with native herbaceous vegetation in quantities and variety sufficient to prevent
erosion and provide for effective infiltration of storm water.
B. Where necessary due to a lack of sufficient ground cover, an area
must be supplemented with a minimum four (4) inch depth of leaf mulch and/or
bark mulch to prevent erosion and provide for effective infiltration of storm water:
and
C. Survival and functionality of ground vegetation and ground cover must
be sufficient to remain in compliance with the standard contained within this
chapter for a minimum of five (5) years.
U. Erosion and Sedimentation Control
1. AII activities which involve filling, grading, excavation, or other similar
activities which result in un-stabilized soil conditions, and which require
Planning Board approval shall also require a written soil erosion and
sedimentation control plan. The plan shall include, where applicable,
provision for:
i. Mulching and revegetation of disturbed soil.
Naples Shoreland Zoning Ordinance Amended June, 2024
35
ii. Temporary runoff control feature such a hay bales, silt fencing
or diversion ditches.
iii. Permanent stabilization structures such as retaining walls or
riprap.
2. All activities described above in subsection 1 that require Planning Board
approval shall require that the Erosion and Sedimentation Control Plan be
reviewed and approved by the Cumberland County oil and Water
Conservation District.
3. In order to create the least potential for erosion, development shall be
designed to fit with the topography and soi Is of the site. Areas of steep
slopes where high cuts and fills may be required shall be avoided wherever
possible, and natural contours shall be followed as closely as possible.
4. Erosion and sedimentation control measures shall apply to all aspects of the
proposed project involving land disturbance and shall be in operation during
all stages of the activity. The amount of exposed soil at every phase of
construction shall be minimized to reduce the potential for erosion.
5. Any exposed ground area shall be temporarily or permanently stabilized
within one (1) week from the time it was last actively worked, by use of riprap,
sod, seed, and mulch, or other effective measures. In all cases, permanent
stabilization shall occur within nine (9) months of the initial date of exposure.
In addition:
A. Where mulch is used it shall be applied at a rate of at least one (1) bale
per five hundred (500) square feet and shall be maintained until a catch of
vegetation is established.
B. Anchoring the mulch with netting, peg and twin or other suitable method
may be required to maintain the mulch cover.
C. Additional measures shall be taken where necessary in order to avoid
siltation into the water. Such measures may include the use of staked hay
bales and/or silt fences.
6. Natural and man-made drainage ways and drainage outlets shall be protected
from erosion from water flowing through them. Drainage ways shall be
designed and constructed in order to carry water from a twenty-five (25) year
storm or greater and shall be stabilized with vegetation or lined with riprap.
V. Soils
All land uses shall be located on soils in or upon which the proposed uses or
structures can be established or maintained without causing adverse
environmental impacts, including severe erosion, mass soil movement, improper
drainage, and water pollution whether during or after construction. Proposed
uses requiring subsurface waste disposal, and commercial or industrial
development and other similar intensive land uses, shall require a soils report
based on an on-site investigation and be prepared by state-certified
Naples Shoreland Zoning Ordinance Amended June, 2024
36
professionals. Certified persons may include Maine Certified Soil Scientists,
Maine Registered Professional Engineers, Maine State Certified Geologists, and
other persons who have training and experience in the recognition and
evaluation of soil properties. The report shall be based upon the analysis of
the characteristics of the soil and surrounding land and water areas, and
maximum ground water elevation, presence of ledge, drainage conditions,
and other pertinent data which the evaluator deems appropriate. The soils
report shall include recommendations for a proposed use to counteract
soil limitations where they exist.
W. Water Quality
No activity shall deposit on or into the ground or discharge to the waters of
the State any pollutant that. by itself or in combination with other activities
or substances, will impair designated uses or the water classification of
the water body, tributary stream, or wetland.
X. Archaeological Sites
Any proposed land use activity involving structural development or soi I
disturbance on or adjacent to sites listed on, or eligible to be listed on the
National Register of Historic Places, as determined by the permitting
authority shall be submitted by the applicant to the Maine Historic
Preservation Commission for review and comment, at least twenty (20)
days prior to action being taken by the permitting authority. The
permitting authority shall consider comments received from the
Commission prior to rendering a decision on the application.
Y. Residential and Camp2.round Common Area Frontage and Campground
Density
1. The shorefront common area shall have a minimum of fifty (50) feet of
shoreline frontage for each residential dwelling unit which has access to
the shorefront. No rights of use shall be granted to persons other than
owners of residential dwelling units.
2. The shorefront common area of a campground shall have a minimum
shoreline frontage of twelve and on half ( 12.5) feet per campsite, with a
minimum of nine hundred (900) feet total. The campground shall contain
a minimum of five thousand (5,000) square feet for each campsite,
excluding roads. driveways. wetlands and land below the normal high-
water line.
Section 16. Administration
A. Administering Bodies and Agents
1. Code Enforcement Officer: A code Enforcement Officer shall be
Naples Shoreland Zoning Ordinance Amended June, 2024
37
appointed in accordance with the provisions of State Law.
2. Planning Board: A Planning Board shall be created in accordance with
the provisions of State Law.
3. Board of Appeals: A Board of Appeals shall be created in accordance
with the provisions of 30-A M.R.S.A., section 2691.
B. Permits Required-
After the effective date of this Ordinance no person shall without first
obtaining a permit engage in any activity or use of land or structure
requiring a permit in the district in which such activity or use would occur;
or expand, change, or replace an existing use or structure; or renew a
discontinued nonconforming use. A person who is issued a permit
pursuant to this Ordinance shall have a copy of the permit on site while
the work authorized by the permit is performed.
1. A permit is not required for the replacement of an existing road
culvert as long as:
a. The replacement culvert is not more than 25% longer
than the culvert being replaced.
b. The replacement culvert is no longer than 75 feet; and
c. Adequate erosion control measures are taken to prevent
sedimentation of the water, and the crossing does not
block fish passage in the watercourse.
2. A permit is not required for an archaeological excavation as
long as the excavation is conducted by an archaeologist listed on
the State Historic Preservation Officer's level 1 or level 2 approved
list, and unreasonable erosion and sedimentation is prevented by
means of adequate and timely temporary and permanent
stabilization measures.
3. Any permit required by this Ordinance shall be in addition to any
other permit required by other law or ordinance.
C. Permit Application:
1. Every applicant for a permit shall submit a written application.
including a scaled site plan, on a form provided by the municipality, to the
appropriate official as indicated in Section 14.
2. All applications shall be signed by an owner or individual who can
show evidence of right, title, or interest in the property or by an agent.
Naples Shoreland Zoning Ordinance Amended June, 2024
38
Representative tenant or contractor of the owner with authorization from
the owner to apply for a permit hereunder certifying that the information in
the application is complete and correct.
3. All applications shall be dated, and the Code Enforcement Officer or
Planning Board as appropriate shall note upon each application the date
and time of its receipt.
4. If the property is not served by a public sewer, a valid plumbing permit
or a completed application for a plumbing permit, including the site
evaluation approved by the Plumbing Inspector, shall be submitted
whenever the nature of the proposed structure or use would require
the installation of a subsurface sewage disposal system.
5. When an excavation contractor will perform an activity that requires or
results in more than one (1) cubic yard of soil disturbance the person
responsible for management of erosion and sedimentation control
practices at the site must be certified in erosion control practices by
the Maine Department of Environmental Protection. This person must
be present at the site each day earthmoving activity occurs for a
duration that is sufficient to ensure that proper erosion and
sedimentation control practices are followed. This is required until
erosion and sedimentation control measures have been installed which
will either stay in place permanently or stay in place until the area is
sufficiently covered with vegetation necessary to prevent soil erosion.
The name and certification number of the person who will oversee the
activity causing or resulting in soil disturbance shall be included on the
permit application. This requirement does not apply to a person or firm
engaged in agriculture or timber harvesting if best management
practices for erosion and sedimentation control are used: and
municipal. state and federal employees engaged in projects
associated with that employment.
D. Photographic record required- Applicants for a permit for development
within the shoreland zone shall provide to the Code Enforcement Officer
preconstruction photographs and. no later than 20 days after completion of the
development. postconstruction photographs of the shoreline vegetation and
development site.
E. Procedure for Administering Permits-
Within thirty-five (35) days of the date of receiving a written application. the
Planning Board or Code Enforcement Officer as indicated in Section 14 shall
notify the applicant in writing either that the application is a complete application
or if the application is incomplete that the specified additional material is needed
to make the application complete. The Planning Board or the Code Enforcement
Officer, as appropriate, shall approve. approve with conditions. or deny all perm
Naples Shoreland Zoning Ordinance Amended June, 2024
39
it applications in writing within thirty-five (35) days of receiving a completed
application. However, if the Planning Board has a waiting list of applications a
decision on the application shall occur within thirty-five (35) days after the first
available date on the Planning Board's agenda following receipt of the
completed application or within thirty-five (35) days of the public hearing if one
is held. Permits shall be approved if the proposed use or structure is found to be
in conformance with the purposes and provisions of this Ordinance.
The Code Enforcement Officer or Planning Board shall have the authority to deny the
issuance of a permit, or suspend, or revoke a permit to the owner or occupant for further
development of the land on which a violation has occurred until the violation is removed,
abated, or otherwise corrected and any penalties and court-awarded costs are paid.
The applicant shall have the burden of proving that the proposed land use
activity is in conformity with the purposes and provisions of this Ordinance.
After the submission of a complete application to the Planning Board, the Board
shall approve an application or approve it with conditions if it makes a positive
finding based on the information presented that the proposed use.
1. Will maintain safe and healthful conditions.
2. Will not result in water pollution, erosion, or sedimentation to surface
waters.
3. Will adequately provide for the disposal of all wastewater.
4. Will not have an adverse impact on spawning grounds, fish, aquatic life,
bird, or other wildlife habitat.
5. Will conserve shore cover and visual. as well as actual points of access to
inland waters.
6. Will protect archaeological and historic resources as designated in the
comprehensive plan.
7. Will avoid problems associated with flood plain development and
use.
8. Is in conformance with the provisions of Section 15. Land Use Standards,
and is not inconsistent with the policies set forth in the Town's
Comprehensive Plan.
If a permit is either denied or approved with conditions, the reasons as well as the
conditions shall be stated in writing. No approval shall be granted for an application
involving a structure if the structure would be located in an unapproved subdivision
or would violate any other local ordinance or regulation or statute administered by
the municipality is responsible for enforcing.
F. Special Exceptions- In addition to the criteria specified in Section 16(B) above,
excepting structure setback requirements, the Planning Board may approve a permit
for a single-family residential structure in a Resource Protection District provided
that the applicant demonstrates that all of the following conditions are met.
Naples Shoreland Zoning Ordinance Amended June, 2024
40
1. There is no location on the property other than a location within the Resource
Protection District, where the structure can be built.
2. The lot on which the structure is proposed is undeveloped and was
established and recorded in the registry of deeds of the county in which the lot
is located before the adoption of the Resource Protection District.
3. All proposed buildings, sewage disposal systems and other improvements
are:
A. Located on natural ground slopes of less than 20%; and
B. Located outside the floodway of the 100-year flood-plain along
rivers and artificially formed great ponds along rivers and outside
the velocity zone in areas subject to tides based on detailed flood
insurance studies and as delineated on the Federal Emergency
Management Agency's Flood Boundary and Floodway Maps and
Flood Insurance Rate Maps: all buildings, including basements,
are elevated at least one foot above the 100-year flood-plain
elevation: and the development is otherwise in compliance with
any applicable municipal flood-plain ordinance.
If the floodway is not shown on the Federal Emergency Management
Agency Maps. it is deemed to be 1/2 the width of the 100-year flood-plain.
4. The total footprint, including cantilevered or similar overhanging
extensions, of all principal and accessory structures is limited to a
maximum of 1,500 square feet. This limitation shall not be altered by
variance.
5. All structures, except functionally water-dependent structures. are set back
from the normal high-water line of a water body, tributary stream, or upland
edge of a wetland to the greatest practical extent but not less than 75 feet.
horizontal distance. In determining the greatest practical extent. The
Planning Board shall consider the depth or the lot the slope of the land, the
potential for soil erosion the type and amount of vegetation to be removed,
the proposed building site's elevation in regard to the flood plain, and its
proximity to moderate-value and high-value wetlands.
G. Expiration of Permit: Permits shall expire one year from the date of
issuance if a substantial start is not made in construction or in the use of the
property during that period. If a substantial start is made within one year of the
issuance of the permit the applicant shall have one additional year to complete
the project at which time the permit shall expire. One-year extensions may be
granted by the Planning Board. in its sole discretion, only upon written
application by the owner of the property.
Naples Shoreland Zoning Ordinance Amended June, 2024
41
H. Installation of Public Utility Service: Any public utility water district
sanitary district or any utility company of any kind may not install services to any
new structure located in the shoreland zone unless written authorization
attesting to the validity and currency of all local permits required under this or
any previous Ordinance, has been issued by the appropriate municipal officials
or other written arrangements have been made between the municipal officers
and the utility following installation of service the company or district shall
forward the written authorization to the municipal officials indicating that the
installation has been completed.
I. Appeals
1. Powers and Duties of the Board of Appeals:
a.
Administrative Appeals: To hear and decide administrative
appeals. on an appellate basis, where it is alleged by an aggrieved
party that there is an error in any order, requirement, decision. or
determination made by. or failure to act by the Planning Board or
Harbor Master in the administration of this ordinance; and to hear and
decide administrative appeals on a de nova basis where it is alleged
by an aggrieved party that there is an error in any order, requirement,
decision or determination made by, or failure to act by, the Code
Enforcement Officer in his or her review of and action on a permit
application under this Ordinance. Any order, requirement, decision or
determination made, or failure to act, in the enforcement of this
ordinance is not appealable to the Board of Appeals.
b.
Variance Appeals: To authorize variances upon appeal. within
the limitation set forth in this Ordinance.
c. Setback Reduction Appeals: To grant reductions from the
requirements set forth in Section 15.A of this Ordinance for minimum
setbacks of structures from lot boundary lines. Setback Reduction
appeals shall not be used, and are not available to reduce the
minimum setbacks of structures from water bodies as provided in this
Ordinance.
2. Variance Appeals: Variances may be granted only under the following
conditions:
A. Variances may be granted only from dimensional
requirements including but not limited to, lot width, structure height,
percent of lot coverage, and setback requirements.
B. Variances shall not be granted for establishment of any uses
otherwise prohibited by this Ordinance.
C. The Board shall not grant a variance unless it finds that:
1. The proposed structure or use would meet the provisions of
Section 15 except for the specific provision which has created
the non-- conformity and from which relief is sought; and
Naples Shoreland Zoning Ordinance Amended June, 2024
42
2. The strict application of the terms of this Ordinance would
result in undue hardship. The term "undue hardship" shall
mean:
A. That the land in question cannot yield a reasonable return
unless a variance is granted.
B. That the need for a variance is due to the unique
circumstances of the property and not to the general conditions
of the neighborhood.
C. That the granting of a variance will not alter the
essential character of the locality; and
D. That the hardship is not the result of action taken by the
applicant or a prior owner.
E. Notwithstanding Section 16.F.2.c.ii. above, the Board of
Appeals, or the Code Enforcement Officer if authorized in
accordance with 30-A MRSA §4353-A, may grant a variance to
an owner of a residential dwelling for the purpose of making that
dwelling accessible to a person
with a disability who resides in or regularly use the
dwelling. The board shall restrict any variance granted
under this subsection solely to the installation of
equipment or the construction of structures necessary for
access to or egress from the dwelling by the person with
the disability. The board may impose conditions on the
variance, including limiting the variance to the duration of
the disability or to the time that the person with the
disability live in the dwelling. The term "structures
necessary for access to or egress from the dwelling shall
include railing, wall or roof systems necessary for the
safety or effectiveness of the structure. Any permit issued
pursuant to this subsection is subject to Sections 16.F.2.g
and 16.F.4.b.iv, below.
F. The Board of Appeals shall limit any variances granted
as strictly as possible in order to ensure conformance with
the purposes and provisions of this Ordinance to the
greatest extent possible, and in doing so may impose
such conditions to a variance as it deems necessary. The
party receiving the variance hall comply with any condition
imposed.
G. A copy of each variance request, including the
application and all supporting information supplied by the
applicant, shall be forwarded by municipal officials to the
Commissioner of the Department of Environmental
Protection at least twenty (20) day prior to action by the
Board of appeals. Any comments received from the
Commissioner prior to action by the Board of Appeals shall
be made part of the record and shall be taken into
Naples Shoreland Zoning Ordinance Amended June, 2024
43
consideration by the Board of Appeals.
3. Administrative Appeals:
When the Board of appeals review a decision of the Code Enforcement Officer
the Board of Appeals shall hold a '·de novo" hearing. At this time, the Board
may receive and consider new evidence and testimony. be it oral or written.
When acting in a .de nova" capacity the Board of Appeals shall hear and decide
the matter afresh. undertaking its own independent analysis of evidence and
the law. and reaching its own decision.
When the Board of Appeals hears a decision of the Planning Board. it shall hold
an appellate hearing, and may reverse the decision of the Planning Board
only upon finding that the decision was contrary to specific provisions of
the Ordinance or contrary to the fact presented to the Planning Board. The
Board of Appeal may only review the record of the proceedings before the
Planning Board. The Board of Appeals shall not receive or consider any
evidence which was not presented to the Planning Board, but the Board of
appeals may receive and consider written or oral argument. If the Board of
appeals determines that the record of the Planning Board proceedings is
inadequate, the Board of Appeals may remand the matter to the Planning
Board for additional fact finding.
4. Setback Reduction Appeals:
1. Setback Reduction-
The Board of Appeals may grant reduction from the minimum setback
requirements set forth in section 15(A) of this ordinance according to all of the following
criteria:
A. Setback reduction appeals are only available to reduce the minimum
requirements for setbacks of structures from Lot boundary lines.
Setback reduction appeals shall not be used, and are not available, to
reduce required minimum setbacks of structures from bodies of water
as provided in this ordinance.
B. Setback reduction appeals may only be granted and are only available
for:
i. Lots in existence as of November 1988.
ii. Lots with a residential dwelling as the principal structure.
C. The Board of appeals shall grant a setback reduction appeal if the
Board finds that granting the setback reduction will not result in
unreasonable interference with the privacy interests of the abutting
landowners.
D. In granting a setback reduction the Board of Appeals may attach
reasonable conditions which it may deem necessary to serve the
Naples Shoreland Zoning Ordinance Amended June, 2024
44
purpose of this ordinance.
E. A setback reduction appeal shall not be granted to enable construction
or renovation that will create additional dwelling units.
F. A setback reduction appeal shall not be granted if it will result in an
impervious surface lot coverage of greater than thirty percent (30%).
G. A setback reduction appeal shall not be granted to enable construction
or renovation that will result in more than one garage on the lot that is
the subject of the appeal.
H. Setback reduction appeals may only be granted the minimum extent
necessary to accomplish the purpose of the appeal. Setbacks may not
be reduced by appeal to less than the following absolute minimum
setbacks:
i. Side Yard: 10 feet
ii. Front Yard: 15 feet
iii. Rear Yard: 15 feet
5. Setback Reduction Procedure:
A.
A complete application with request.
B.
A survey showing current structures located on land and setback
C.
All approved requests must be filed with the Cumberland County
Registry of Deeds with forms supplied by Code Enforcement Officer
office before issuance of any building permit.
6. Appeal Procedure:
A.
Making an Appeal
i. An administrative or variance appeal may be taken to the Board of
Appeals by an aggrieved party from any decision of the Code
Enforcement officer or the Planning Board. except for enforcement-
related matters as described in Section 16.F.1 above. Such an
appeal shall be taken within thirty (30) days of the date of the official,
written decision appealed from. and not otherwise, except that the
Appeals Board. upon showing of good cause, may waive the thirty
(30) day requirement.
Applications for appeals shall be made by filing with the Board of Appeals a
written notice of appeal 'which includes:
A. A concise written statement indicating what relief is requested and why the
appeal or variance should be granted.
B. A sketch drawn to scale showing lot lines location of existing buildings and
structures and other physical features of the lot pertinent to the relief sought.
C. Upon receiving an application for an administrative appeal, or a variance. the
Code Enforcement Officer or Planning Board. as appropriate shall transmit to
Naples Shoreland Zoning Ordinance Amended June, 2024
45
the Board of Appeals all of the papers constituting the record of the decision
appealed from.
D. The Board of Appeals shall hold a public hearing on an administrative appeal
or a request for a variance within thirty- five (35) days of its receipt of a
complete written application unless this time period is extended by the
parties.
B. Decision by Board of Appeals
i. A majority of the full voting membership of the Board shall constitute a quorum for
the purpose of deciding an appeal.
ii. The person tiling the appeal shall have the burden of proof.
iii. The Board shall decide all administrative appeals and variance appeals within
thirty-five (35) days after the close of the of the hearing and shall issue a written
decision on all appeals.
iv. The Board of Appeals shall state the reasons and basis for its decision including
a statement of the facts found and conclusions reached by the Board. The Board
shall cause written notice of its decision to be mailed or hand-delivered to the
applicant and to the Department of Environmental Protection within seven (7) days
of the Board's decision. Copies of the written decision of the Board of Appeals shall
be given to the Planning Board, Code Enforcement Officer, and the municipal
officers.
7. Appeal to Superior Court:
Except as provided by 30-A M.R.S.A. section 2691.3.F. any aggrieved party who
participated as a party during the proceedings before the Board of Appeals may take
an appeal to Superior Court in accordance with State laws within forty-five (45) days
from the date of any decision of the Board of Appeals.
8. Reconsideration:
In accordance with 30-A M.R.S.A. section 2691.3.F. the Board of Appeals may
reconsider any decision within forty-five (45) days of its prior decision. A request to the
board to reconsider must be filed within ten ( 10) days of the decision that is being
reconsidered. A vote to reconsider and the action taken on that reconsideration must
occur and be completed within forty-five (45) days of the date of the vote on the original
decision. Reconsideration of a decision shall require a positive vote of the majority of
the board members originally voting on the decision, and proper notification to the
landowner, petitioner, planning board, code enforcement officer, and other parties of
interest, including abutters and those who testified at the original hearings(s). The Board
may conduct additional hearings and receive additional evidence and testimony.
Appeal of a reconsidered decision to Superior Court must be made within fifteen (15)
days after the decision on reconsideration.
Naples Shoreland Zoning Ordinance Amended June, 2024
46
J. Enforcement
1. Nuisances: Any violation of this Ordinance shall be deemed to be a nuisance.
2. Code Enforcement Officer:
A. It shall be the duty of the Code Enforcement Officer to enforce the provisions
of this Ordinance. If the Code Enforcement Officer shall find that any
provision of this Ordinance is being violated he or she shall notify in writing
the person responsible for such violation indicating the nature of the violation
and ordering the action necessary to correct it, including discontinuance of
illegal use of land, buildings or structures, or work being done, removal of
illegal buildings or structures, and abatement of nuisance conditions. A copy
of such notices shall be submitted to the municipal officers and be maintained
as a permanent record.
B. The Code Enforcement Officer shall conduct on-site inspections to
ensure compliance with all applicable inspections to ensure
compliance with all applicable laws and conditions attached to permit
approvals. The Code Enforcement Officer shall also investigate all
complaints of alleged violations of this Ordinance.
C. The Code Enforcement Officer shall keep a complete record of all
essential transactions of the office including applications submitted,
permits granted or denied, variances granted or denied, revocation
actions, revocation of permits, appeals, court actions, violations
investigated, violations found, and fees collected.
3. Legal Actions:
When the above action does not result in the correction or abatement of
the violation or nuisance condition the Municipal Officers upon notice
from the Code Enforcement Officer are hereby directed to institute any
and all actions and proceedings either legal or equitable including seeking
injunctions of violations and the imposition of tines that may be
appropriate or necessary to enforce the provisions of this Ordinance in
the name of the municipality. The municipal officers or their authorized
agent are hereby authorized to enter into administrative consent
agreements for the purpose of eliminating violations of this Ordinance
and recovering tines without court action. Such agreements shall not
allow an illegal structure or use to continue unless there is clear and
convincing evidence that the illegal structure or use was constructed or
conducted as a direct result of erroneous advice given by an authorized
municipal official and there is no evidence that the owner acted in bad
faith or unless the removal of the structure or use will result in a threat or
hazard to public health and safety or will result in substantial
environmental damage.
Naples Shoreland Zoning Ordinance Amended June, 2024
47
4. Fines:
Any person including but not limited to a landowner a landowner's agent
or contractor, builder or developer who violates any provision or
requirement of this Ordinance shall be penalized in accordance with 30-
A.M.R.S.A ., section 4452.
Section 17. Definitions:
Aggrieved party - an owner of land whose property is directly or indirectly
affected by the granting or denial of a permit or variance under this Ordinance; a
person whose land abuts land for which a permit or variance has been granted;
or any other person or group of persons who have suffered particularized injury
as a result of the granting or denial of such permit or variance.
Accessory Structure or use- A use or structure, which is incidental and
subordinate to the principal use or structure. Accessory uses when aggregated
shall not subordinate the principal use of the lot. A deck or similar extension of
the principal structure or a garage attached to the principal structure by a roof,
or a common wall is considered part of the principal structure.
Agriculture - the production, keeping or maintenance for sale or lease of plants
or animals including but not limited to, forages and sod crops, grains, and seed
crops dairy animals and dairy products, poultry, and poultry products. livestock.
fruits and vegetables and ornamental green-house products. Agriculture does
not include forest management and timber harvesting activities or marijuana
uses.
Aquaculture - the growing or propagation of harvestable freshwater, estuarine,
marine plant, or animal species.
Basal Area - the area of cross-section of a tree stem at 4 1/2 feet above ground
level and inclusive of bark.
Basement - any portion of a structure with a floor-to-ceiling height of 6 feet or
more and having more than 50% of its volume below the existing ground level.
Bedroom- A room, whether or not combined with any functions, customarily
used or dedicated for the purpose of sleeping for one or more individuals, it shall
include rooms used as dens. lofts and the like.
Boat Launching Facility - a facility designed primarily for the launching and
landing of watercraft, and which may include an access ramp, docking area, and
parking spaces for vehicles and trailers.
Bureau of Forestry - State of Maine Department of Agriculture, Conservation.
Naples Shoreland Zoning Ordinance Amended June, 2024
48
and Forestry. Bureau of Forestry.
Campground - An area devoted to overnight recreational or educational use
where the land is divided into sites or lots for which a charge is made, either on
a short-term basis, by sale, rent, lease or condominium type of financing or
ownership: and/or any area or tract of land to accommodate two (2) or more
parties in temporary living quarters, including but not limited to tents,
recreational vehicles or other shelters.
Canopy - the more or less continuous cover formed by tree crowns in a
wooded area.
Commercial use - the use of lands, buildings, or structures, other than a "home
occupation," defined below, the intent and result of which activity is the
production of income from the buying and selling of goods and/or services,
exclusive of rental of residential buildings and/or dwelling units.
Development - a change in land use involving alteration of the land, water, or
vegetation, or the addition or alteration of structures or other construction not
naturally occurring.
Dimensional requirements - numerical standards relating to spatial
relationships including but not limited to setback, lot area, shore frontage, and
height.
Disability - any disability, infirmity, malformation, disfigurement, congenital
defect, or mental condition caused by bodily injury, accident, disease, birth
defect, environmental conditions or illness; and also includes the physical or
mental condition of a person which constitutes a substantial handicap as
determined by a physician or in the case of mental handicap, by a psychiatrist or
psychologist, as well as any other health or sensory impairment which requires
special education, vocational rehabilitation or related services.
Driveway - a vehicular access-way less than five hundred (500) feet in length
serving two single-family dwellings or one two-family dwelling, or less.
Dwelling- A room or group of rooms designed and equipped exclusively for use
as permanent. seasonal or temporary living quarters for only one family.
including provisions for living. cooking and eating.
Emergency operations - operations conducted for the public health, safety, or
general welfare, such as protection of resources from immediate destruction or
loss, law enforcement. and operations to rescue human beings. property and
livestock from the threat of destruction or injury.
Essential services- gas, electrical or communication facilities; steam, fuel,
Naples Shoreland Zoning Ordinance Amended June, 2024
49
electric power or water transmission or distribution lines. towers and related
equipment: telephone cables or lines, poles, and related equipment:
gas,oil,water, slurry, or other similar pipelines: municipal sewage lines,
collection, or supply systems: and associated storage tanks. Such systems may
include towers, poles, wires. mains drains, pipes, conduits, cables, fire alarm,
sand police call boxes, traffic signals, hydrants, and similar accessories, but
shall not include service drops or buildings which are necessary for the
furnishing of such services.
Expansion of a structure - an increase in the footprint of a structure including
all extensions such as, but not limited to attached decks, garages, porches, and
greenhouses.
Expansion of use - the addition of one or more months to a use's operating
season; or the use of more footprint of a structure or ground area devoted to a
particular use.
Family- one or more persons occupying a premises and living as a single
housekeeping unit.
Floodway - the channel of a river or other watercourse and adjacent land areas
that must be reserved in order to discharge the 100-year flood without cumulatively
increasing the water surface elevation by more than one foot in height.
Floor area - the sum of the horizontal areas of the floor(s) of a structure enclosed
by exterior walls.
Footprint - the entire area of ground covered by the structure(s) on a lot,
including but not limited to cantilevered or similar overhanging extensions, as
well as unenclosed structures, such as patios and decks.
Forested wetland - a freshwater wetland dominated by woody vegetation that
is six (6) meters tall (approximately twenty (20) feet) or taller.
Foundation - the supporting substructure of a building or other structure,
excluding wooden sills and post supports, but including basements, slabs, frost
walls, or other base consisting of concrete, block, brick, or similar material.
Freshwater wetland - freshwater swamps, marshes, bogs, and similar areas,
other than forested wetlands, which are:
(1)
Of ten or more contiguous acres; or of less than 10 contiguous
acres and adjacent to a surface water body, excluding any river, stream,
or brook, such that in a natural state, the combined surface area is in
excess of 10 acres; and
Naples Shoreland Zoning Ordinance Amended June, 2024
50
(2)
Inundated or saturated by surface or ground water at a frequency
and for a duration sufficient to support, and which under normal
circumstances do support, a prevalence of wetland vegetation typically
adapted for life in saturated soils.
Freshwater wetlands may contain small stream channels or inclusions of
land that do not conform to the criteria of this definition.
Functionally water-dependent uses - those uses that require, for their primary
purpose, location on submerged lands or that require direct access to, or
location in, coastal or inland waters and that cannot be located away from these
waters. The uses include, but are not limited to, commercial and recreational
fishing and boating facilities, finfish and shellfish processing, fish-related storage
and retail and wholesale fish marketing facilities, waterfront dock, and port
facilities. shipyards and boat building facilities, marinas, navigation aids. basins
and channels, shoreline structures necessary for erosion control purposes,
industrial uses dependent upon water-borne transportation or requiring large
volumes of cooling or processing water that cannot reasonably be located or
operated at an inland site, and uses that primarily provide general public access
to coastal or inland waters. Recreational boat storage buildings are not
considered to be a functionally water-dependent use.
Great pond - any inland body of water which in a natural state has a surface
area in excess of ten acres, and any inland body of water artificially formed or
increased which has a surface area in excess of thirty (30) acres except for the
purposes of this Ordinance, where the artificially formed or increased inland
body of water is completely surrounded by land held by a single owner.
Great pond classified GPA - any great pond classified GPA pursuant to 38
M.R.S.A. Article 4-A Section 465-A. This classification includes some but not all
impoundments of rivers that are defined as great ponds.
Ground cover - small plants, fallen leaves, needles and twigs, and the partially
decayed organic matter of the forest floor.
Harvest Area - the area here timber harvesting and related activities including
the cutting of trees, skidding, yarding, and associated road construction take
place. The area affected by a harvest encompasses the area within the outer
boundaries of these activities. excepting unharvested areas greater than 10
acres within the area affected by a harvest.
Hazard tree - a tree with a structural defect. combination of defects, or disease
resulting in a structural defect that under the normal range of environmental
conditions at the site exhibits a high probability of failure and loss of a major
structural component of the tree in a manner that will strike a target. A normal
range of environmental conditions does not include meteorological anomalies,
such as but not limited to hurricanes, hurricane-force winds, tornados,
Naples Shoreland Zoning Ordinance Amended June, 2024
51
microbursts; or significant ice storm events. Hazard trees also include those
trees that pose a serious and imminent risk to bank stability. A target is the area
where personal injury or property damage could occur if the tree or a portion of
the tree fails. Targets include roads, driveways, parking areas, structures,
campsites, and any other developed area where people frequently gather and
linger.
Height of a structure - the vertical distance between the mean original (prior
to construction) grade at the downhill side of the structure and the highest point
of the structure, excluding chimneys, steeples, antennas, and similar
appurtenances that have no floor area.
Home occupation - An occupation or profession which is customarily
conducted on or in a residential structure or property and which is 1.) clearly
incidental to and compatible with the residential use of the property and
surrounding residential uses: and 2) which employs no more than two (2)
persons other than family members residing in the home. A medical marijuana
Registered Caregiver is not considered a Home Occupation.
Impervious Surface- Structures and other man-made improvements to land
and material covering the land. which substantial reduce the infiltration of water.
Impervious surfaces shall include but not be limited to roofs, paved areas,
parking lots, and driveways, regardless of surface materials.
Increase in nonconformity of a structure - any change in a structure or
property which causes further deviation from the dimensional standard(s)
creating the nonconformity such as but not limited to reduction in water body,
tributary stream or wetland setback distance increase in lot coverage or
increase in height of a structure. Property changes or structure expansions
which either meet the dimensional standard, or which cause no further increase
in the linear extent of nonconformance of the existing structure shall not be
considered to increase nonconformity. For example. there is no increase in
nonconformity with the setback requirement for water bodies, wetlands, or
tributary streams if the expansion extends no further into the required setback
area than any portion of the existing nonconforming structure. Hence, a
structure may be expanded laterally provided that the expansion extends no
closer to the water body, tributary stream, or wetland than the closest portion of
the existing structure from that water body, tributary stream, or wetland.
Included in this allowance are expansions which in-fill irregularly shaped
structures.
Individual private campsite - an area of land which is not associated with a
campground, but which is developed for repeated camping by only one group
not to exceed ten (10) individuals and which involves site improvements which
may include but not be limited to a gravel pad, parking area, fireplace. or tent
platform.
Naples Shoreland Zoning Ordinance Amended June, 2024
52
Industrial - The assembling, fabrication, finishing, manufacturing, packaging, or
processing of goods, or the extraction of minerals.
Institutional - a non-profit or quasi-public use, or institution such as a church,
library, public or private school, hospital, or municipally owned or operated
building. structure or land used for public purposes.
Lot area -The area of land enclosed within the boundary lines of a lot, minus
land below the normal high-water line of a water body or upland edge of a
wetland and areas beneath roads serving more than two lots.
Marina - a business establishment having frontage on navigable water and, as
its principal use, providing for hire offshore moorings or docking facilities for
boats, and which may also provide accessory services such as boat and related
sales, boat repair and construction, indoor and outdoor storage of boats and
marine equipment, bait and tackle shops and marine fuel service facilities.
Market value - the estimated price a property will bring in the open market and
under prevailing market conditions in a sale between a willing seller and a willing
buyer, both conversant with the property and with prevailing general price
levels.
Medical Marijuana Registered Caregiver- A caregiver, as defined in 22
M.R.S. § 2422, that is required to registered with the state pursuant to 22
M.R.S. § 2425-A.
Mineral exploration - hand sampling, test boring, or other methods of
determining the nature or extent of mineral resources which create minimal
disturbance to the land, and which include reasonable measures to restore the
land to its original condition.
Mineral extraction - any operation within any twelve (12) month period which
removes more than one hundred (100) cubic yards of soil, topsoil, loam, sand,
gravel, clay, rock, peat, or other like material from its natural location and to
transport the product removed, away from the extraction site.
Minimum lot width - the closest distance between the side lot lines of a lot.
When only two lot lines extend into the shoreland zone, both lot lines shall be
considered to be side lot lines.
Multi-unit residential - a residential structure containing three (3) or more
residential dwelling units.
Native - indigenous to the local forests.
Naples Shoreland Zoning Ordinance Amended June, 2024
53
Non-conforming condition - non-conforming lot, structure or use which is
allowed solely because it was in lawful existence at the time this Ordinance or
subsequent amendment took effect.
Non-conforming lot - a single lot of record which, at the effective date of
adoption or amendment of this Ordinance does not meet the area, frontage,
or width requirements of the district in which it is located.
Non-conforming use- use of buildings, structure, premises, land, or parts
thereof which is not allowed in the district in which it is situated, but which is
allowed to remain solely because it was in lawful existence at the time this
Ordinance or subsequent amendments took effect.
Non-native invasive species of vegetation - species of vegetation listed
by the Maine Department of Agriculture Conservation and Forestry a being
invasive in Maine ecosystems and not native to Maine ecosystems.
Non-conforming structure - a structure which d es not meet any one or
more of the following dimensional requirements: setback, height, lot
coverage, or footprint, but which is allowed solely because it was in lawful
existence at the time this Ordinance or sub-sequent amendments took
effect.
Normal High-Water Line (non-tidal waters)- That line which is apparent from
visible markings change in the character of oil due to prolonged action of the
water or change in vegetation and which distinguishes between predominantly
aquatic and predominantly terrestrial land. Area contiguous with rivers and
great ponds that support non-forested wetland vegetation and hydric soils and
that are at the same or Iower elevation as the water level of the river or great
pond during the period of normal high-water are considered part of the river or
great pond.
Outlet stream - any perennial or intermittent stream, as shown on the most
recent highest resolution version of the national hydrography dataset
available from the United States Geological Survey on the website of the
United States Geological survey or the national map, which flows from a
freshwater wetland.
Person - an individual, corporation, governmental agency, municipality,
trust, estate, partnership, association, two or more individuals having a joint
or common interest, or other legal entity.
Point of Attachment - Means the point on an aquatic structure where the
structure is physically attached to an adjacent upland. If an aquatic structure is
not attached to the land, the "point of attachment" shall mean the point on the
structure closest to the adjacent upland.
Naples Shoreland Zoning Ordinance Amended June, 2024
54
Primary or Legal Residence - A building or dwelling being currently used by the
owner as his/her main place of dwelling or home. A person may have only one
primary or legal residence.
Principal structure - a structure other than one which is used for purposes
wholly incidental or accessory to the use of another structure or use on the
same lot.
Principal use - The primary or predominant use. An activity that is conducted
with the principle use and such activity that either constitutes only an incidental
or insubstantial part of the total activity that takes place on a lot; or is commonly
associated with the principal use and is integrally related to it, is regarded as
"accessory to the principal use." An accessory to the principal use is regarded
as "incidental or insubstantial" if it is both incidental and insubstantial in and of
itself, and in relation to the principal use.
Quantitative measures for consideration in this determination include the
percentage and total amount of square footage attributed to the accessory to
the principle use and sales or income derived from the accessory to the
principal use.
Public facility - any facility, including, but not limited to buildings, property,
recreation areas, and roads, which are owned, leased, or otherwise operated, or
funded by a governmental body or public entity.
Recent floodplain soils - the following soil series as described and identified by
the National Cooperative Soil Survey:
Fryeburg Hadley
Limerick
Lovewell Medomak
Ondawa
Alluvial
Cornish
Charles
Podunk
Rumney
Saco
Suncook Sunday
Winooski
Recreational facility - a place designed and equipped for the conduct of sports,
leisure time activities, and other customary and usual recreational activities,
excluding boat launching facilities.
Recreational vehicle - a vehicle or an attachment to a vehicle designed to be
towed and designed for temporary sleeping or living quarters for one or more
persons, and which may include a pick-up camper, travel trailer, tent trailer, camp
trailer, and motor home. In order to be considered as a vehicle and not as a
structure. the unit must remain with its tires on the around and must be
registered with the State Division of Motor Vehicles.
Replacement system - a system intended to replace 1.) an existing system
Naples Shoreland Zoning Ordinance Amended June, 2024
55
which is either malfunctioning or being upgraded with no significant change of
design flow or use of the structure or 2.) any existing overboard wastewater
discharge.
Residential dwelling unit - a room or group of rooms designed and equipped
exclusively for use as permanent, seasonal, or temporary living quarters for
only one family at a time. and containing cooking, sleeping and toilet facilities.
The term shall include mobile homes and rental units that contain cooking and
sleeping and toilet facilities regardless of the time period. Recreational vehicles
are not residential dwelling units.
Residual Stand - a stand of trees remaining in the forest following timber
harvesting and related activities
Riprap - rocks, irregularly shaped. and at least six (6) inches in diameter used
for erosion control and soil stabilization, typically used on ground slopes of two
(2) units horizontal to one (1) unit vertical or less.
River - a free-flowing body of water including its associated floodplain wetlands
from that point at which it provides drainage for a watershed of twenty-five (25)
square miles to its mouth.
NOTE: The portion of a river that is subject to tidal action is a coastal wetland.
Road - a route or track consisting of a bed of exposed mineral soil, gravel. asphalt,
or other surfacing material constructed for or created by the repeated passage of
motorized vehicles, excluding a driveway as defined.
Salt marsh - Areas of coastal wetland (most often along coastal bays) that
support salt tolerant species and where at average high tide during the growing
season, the soil is irregularly inundated by tidal waters. The predominant
species is salt marsh cordgrass (Spartina alterniflora). More open areas often
support widgeon grass, eelgrass, and Sago pondweed.
Salt meadow - Areas of a coastal wetland that support salt tolerant plant
species bordering the landward side of salt marshes or open coastal water,
where the soil is saturated during the growing season, but which is rarely
inundated by tidal water. indigenous plant species include salt meadow
cordgrass (Spartina patens) and black rush; common three-square occurs in
fresher areas.
Sapling - a tree species that is less than two (2) inches in diameter at four and
one half (4.5) feet above ground level.
Seasonal Dwelling: A dwelling that is not used as a permanent place of
Naples Shoreland Zoning Ordinance Amended June, 2024
56
residence and occupied continuously for not more than seven (7) months in any
calendar year.
Seedling - a young tree species that is less than four and one half (4.5) feet in
height above ground level.
Service drop - any utility line extension which does not cross or run beneath any
portion of a water body provided that:
1. In the case of electric service
A. the placement of wires and/or the installation of utility poles is located
entirely upon the premises of the customer requesting service or upon a
roadway right-of- way; and
B. The total length of the extension is less than one thousand (1,000) feet.
2. In the case of telephone service
A. The extension, regardless of length. will be made by the installation of
telephone wires to existing utility poles, or
B. The extension requiring the installation of new utility poles or placement
underground is less than one thousand (1,000) feet in length.
Setback-Land: Setbacks are footage requirements for the installation of all
structures from the front, rear, and side property lines of all lots.
Setback Water- the nearest horizontal distance from the normal high-water line of a
water body or tributary stream, or upland edge of a wetland, to the nearest part of a
structure, road, parking space or other regulated object or area.
Shore frontage - the length of a lot bordering on a water body or wetland measured
in a straight line between the intersections of the lot lines with the shoreline.
Shoreland zone - the land area located within two hundred and fifty (250) feet.
horizontal distance, of the normal high-water line of any great pond or river; within
250 feet, horizontal distance, of the upland edge of a coastal wetland. including all
areas affected by tidal action; within 250 feet of the upland edge of a freshwater
wetland; or within seventy-five (75) feet, horizontal distance. of the normal high-
water line of a stream.
Shoreline - the normal high-water line, or upland edge of a freshwater or coastal
wetland.
Significant River Segments - See Appendix A or 38 M.R.S.A. section 437.
Naples Shoreland Zoning Ordinance Amended June, 2024
57
Significant Wildlife Habitat: Includes habitat for species appearing on the official
state or federal lists of endangered or threatened species; high and moderate value
deer wintering areas and travel corridors as defined by the Department of Inland
Fisheries and Wildlife; high and moderate value waterfowl and wading bird habitats.
including nesting and feeding area as defined by the Department of Inland Fisheries
and Wildlife; critical spawning and nursery area for Atlantic Sea Run Salmon as
defined by the Atlantic Sea Run Salmon Commission; and shorebird nesting and
feeding and staging areas as defined by the Department of Inland Fisheries and
Wildlife.
Storm-damaged tree - a tree that has been uprooted, blown down, is lying on
the ground, or that remains standing and is damaged beyond the point of
recovery as the result of a storm event.
Stream - a free-flowing body of water from the outlet of a great pond or the
confluence of two (2) perennial streams as depicted on the most recent. highest
resolution version of the national hydrography dataset available from the United
States Geological Survey on the website of the United States Geological Survey
or the national map to the point where the stream becomes a river or where the
stream meets the shoreland zone of another water body or wetland. When a
stream meets the shoreland zone of a water body or wetland and a channel form
downstream of the water body or wetland as an outlet, that channel is also a
stream.
Structure - anything temporarily or permanently located, built, constructed, or
erected for the support, shelter or enclosure of persons, animals, goods or
property of any kind or anything constructed or erected on or in the ground. The
term includes structures temporarily or permanently located, such as decks,
patios, and satellite dishes. Structure does not include fences: poles and wiring
and other aerial equipment normally associated with service drops including guy
wires and guy anchors; subsurface wastewater disposal systems as defined in
Title 30-A, section 420 I, subsection 5; geothermal heat exchange wells as
defined in Title 32, section 4700-E, subsection 3-C; or wells or water wells as
defined in Title 32, section 4700-E, subsection 8.
Substantial start - completion of thirty (30) percent of a permitted structure or
use measured as a percentage of estimated total cost.
Subsurface sewage disposal system - any system designed to dispose of
waste or wastewater on or beneath the surface of the earth; includes, but is not
limited to; septic tanks, disposal fields, grandfathered cesspools, holding tanks,
pretreatment filter, piping, or any other fixture, mechanism or apparatus used for
those purposes; does not include any discharge system licensed under 38
M.R.S.A. section 414, any surface wastewater disposal system. or any
municipal or quasi-municipal sewer or wastewater treatment system.
Naples Shoreland Zoning Ordinance Amended June, 2024
58
Sustained slope - a change in elevation where the referenced percent grade is
substantially maintained or exceeded throughout the measured area.
Tree - a woody perennial plant with a well-defined trunk(s) at least two (2) inches
in diameter at four and one half (4.5) feet above the ground. with a more or less
definite crown and reaching a height of at least ten (10) feet at maturity.
Tributary stream- means a channel between defined banks created by the
action of surface water, which is characterized by the lack of terrestrial
vegetation or by the presence of a bed, devoid of topsoil, containing waterborne
deposits or exposed soil, parent material, or bedrock; and which is connected
hydrologically with other water bodies. "Tributary stream," does not include rills
or gullies forming because of accelerated erosion in disturbed soils where the natural
vegetation cover has been removed by human activity.
This definition does not include the term "stream" as defined elsewhere in this
Ordinance and only applies to that portion of the tributary stream located within the
shoreland zone of the receiving water body or wetland.
NOTE: Water setback requirements apply to tributary streams within the shoreland
zone.
Upland edge of a wetland - the boundary between upland and wetland. For
purposes of a coastal wetland, this boundary is the line formed by the landward
limits of the salt tolerant vegetation and/or the highest annual tide level, including all
areas affected by tidal action. For purposes of a freshwater wetland the upland
edge is formed where the soils are not saturated for a duration sufficient to support
wetland vegetation, or where the soils support the growth of wetland vegetation, but
such vegetation is dominated by woody stems that are six (6) meters
(approximately twenty (20) feet) tall or taller.
Vegetation - all live trees, shrubs, and other plants including without limitation, trees
both over and under 4 inches in diameter, measured at 4 1 /2 feet above ground
level.
Velocity zone - an area of special flood hazard extending from offshore to the
inland limit of the primary frontal dune along an open coast and any other area subject
to high velocity wave action from storms or seismic sources.
Volume of a structure - the volume of all portions of a structure enclosed by roof and
fixed exterior walls as measured from the exterior faces of these walls and roof.
Water body - any great pond, river, or stream.
Naples Shoreland Zoning Ordinance Amended June, 2024
59
Water crossing - any project extending from one bank to the opposite bank of a
river, stream, tributary stream, or wetland whether under, though. or over the water
or wetland. Such projects include but may not be limited to roads and fords, bridges,
culverts, water lines, sewer lines, and cables as well as maintenance work on these
crossings. This definition includes crossings for timber harvesting equipment and
related activities.
Wetland - a freshwater or coastal wetland.
Woody Vegetation - live trees or woody, non-herbaceous shrubs.