TOWN OF NEW PORTLAND, MAINE
WIND ENERGY FACILITY ORDINANCE
1.0 Title. This ordinance shall be known as the Town of New Portland, Maine, Wind Energy Facility Ordinance.
2.0 Purpose. The purpose of this Ordinance is to protect the health, safety, and general welfare of the residents and property
owners of New Portland by establishing reasonable and uniform regulations for Wind Energy Facilities (WEFs).
3.0 Authority. This Ordinance is adopted pursuant to the enabling provisions of Article VIII, part 2, Section 1 of the Maine
Constitution; the provisions of 30-A M.R.S.A. Section 3001 (Home Rule), and the provisions of the Planning and Land Use
Regulation Act 30-A M.R.S.A. Section 4312, et seq.
3:1 Conflicts with Other Ordinances, Laws and Regulations. If there is a conflict between provisions in this
Ordinance or between a provision in this Ordinance and a provision of any other ordinance, regulation, or statute from any
jurisdiction, the more restrictive provision shall apply.
32 Validity and Severability. Should any section or provision of this Ordinance be declared by the courts to be
invalid, such a decision shall not invalidate any other section or provision of the Ordinance.
3:3 Administration. This Ordinance shall be administered by the Planning Board and Code Enforcement Officer of the
Town of New Portland.
3.4 Amendments. Amendments may be proposed by a majority of the Planning Board. This Ordinance may be
amended by a majority vote at a Town Meeting which must be presented at a Public Hearing before such a vote may be
taken. If the Ordinance is amended as described above, the amendments shall apply retroactively to any Application that is
pending.
4.0 Effective Date.
4.1 This Ordinance shall become effective on the date of its passage. MARCH 3, 2012
5.0 Applicability. This ordinance applies to all Wind Energy Facilities and Meteorological Towers in the Town of New
Portland proposed to be constructed or operated after the effective date of this Ordinance.
6.0 Definitions.
Acoustic Hazard. Annoyances and hazards owing to the sound produced by a WEF.
Applicant. Person, or persons or entity applying for a Meteorological Tower permit or Wind Energy Facility permit to
the Town of New Portland Planning Board.
Blade glint. The intermittent reflection of the sun off the surface of the blades of a Wind Turbine
Board Of Appeals (BOA)
CEO means Town of New Portland Code Enforcement Officer
Covenants. A legal agreement, convention or promise by two or more parties by deed in writing, signed, and delivered,
by which one of the parties pledges himself to the other that something is done, or shall be done, or shall not be done, or
stipulates the truth of certain facts. For this Ordinance this legal agreement shall contain stipulations required and put
forth herein and shall be a covenant running with land.
D = Distance measured in feet.
Page 1 of 21
€ ', ----
Debris Hazard. Hazard owing to the possibility that the parts of a WEF or material (ice or other debris) accumulated on its
rotating elements could be dislodged and fall or be thrown some distance onto surrounding property.
Decibel (dB) means the practical unit of measurement for sound pressure level; the number of decibels of a measured
sound is equal to 20 times the logarithm to the base 710 of the ratio of the sound pressure of the measured sound to the
sound pressure of a standard sound (20 micropascals); abbreviated "dB."
dB(A) or dBA means the abbreviation designating both the unit of measure sound level, the decibel, and the mode of
measurement that uses the A-weighting of a sound level meter.
dB(C) or dBC means the abbreviation designating both the unit of measure sound level, the decibel, and the mode of
measurement that uses the C-weighting of a sound level meter.
Engineering drawing. Rendering of an object or land area using drafting instruments or CAD showing all critical
features and appropriate dimensions to describe the subject.
Environmentally Sensitive Areas. Such areas shall include but not limited to wetlands, vernal pools, seeps or springs,
steep slopes (equal to or greater than 15%), watersheds, flood plains, significant habitat for wildlife, fish, and plants.
Flicker Hazard. Annoyance and hazard produced by alternating changes in light intensity caused by the movement
of wind turbine blades casting shadows on the ground or a stationary object.
Flicker Receptor -- any Non-participating Landowner's property within two miles of any Turbine.
Flicker Hazard Report -- see section 9.9
Geological Instability. Can include possible fault lines, areas of potential landslides, heavily fractured or unstable
bedrock that would cause the tower and/or structure to fall or collapse.
Ho. Height overall. Height of a Meteorological Tower or WEF Turbine from ground level to the highest point on the
structure or the highest point of any rotating element, whichever is higher.
Inhabitant means one who resides actually and permanently in a given place, and has his domicile there.
LAeq means the energy-equivalent sound pressure level measured in decibels with a sound level meter set for A-
weighting, "Fast" response over a measurement period; expressed as LAeq or Leq in dBA.
Le = Criterion sound level, dBA, set to 30 dBA, consistent with the World Health Organization's Night Noise Guideline
2009, to prevent biological effects, to protect public health in risk groups including children, elderly and those with disease
or pre-existing health conditions and, to minimize sleep disturbance at night; a criterion level of 30 decibels (LAeq) for
continuous intrusive noise as the level above which biological effects, medical impacts on sensitive populations, and sleep
disturbance were found with sufficient evidence under comprehensive medical and scientific peer review by World Health
Organization.
LCeq means the energy-equivalent sound pressure level measured in decibels with a sound level meter set for C-
weighting, "Fast" response over a measurement period; expressed as LCeq or Leq in dBC.
Lp = Sound Pressure Level measured in dBA in accordance with American National Standards $12.9 -- Part 3, "Quantities
and Procedures for Description and Measurement of Environmental Sound" or ANS! $12.18.
Ls = Safety Factor, shall be 2 dBA unless otherwise authorized by the Town Planning Board, to account for variations
in meter total instrument response.
Lu = Uncertainty factor, shall be 5 dBA unless otherwise authorized by the Town Planning Board, based on measured
maximum hourly sound levels at wind turbine facilities in Maine compared to predicted sound levels and the resulted
required corrections of 5 dB.
Lw = Manufacturer's Guaranteed Maximum Sound Power Level, in dBA re 1pW, under any operating conditions, including high
Page 2 of 21
winds, yawing, furling, and power outages, whether electrically loaded or unloaded. The Manufacturer's Guaranteed Maximum Sound
Power Level in dBA that is reported must be the maximum level that the turbine produces over its entire operational range at all wind
speeds and this figure must also have been verified by an independent certified testing laboratory.
Maximum sound level (also Lmax) means the maximum sound pressure level measured in decibels with a sound level
meter set for A-weighting, "Fast" meter response over a measurement period; expressed as Lmax in dBA.
Meteorological Tower (MT). Tower constructed to mount instruments at one or more heights above grade for the purpose
of collecting wind or other meteorological data.
n = Number (quantity) of wind turbines, where the expression 4log(n) represents the change in sound level due to the
increase in the number of turbines based on independent analysis of measured noise levels around wind turbine facilities in
Maine, and -0.5 dB is required when converting from sound power level to sound pressure level assuming spherical
spreading, for dimensions in feet.
Owner/Operator. The person or entity that is the legal owner of the WEF, including successors and assigns, and that
has the authority and responsibility to operate the WEF on a day-to-day basis. An Owner/Operator must have the legal
authority to represent and bind.
Property line. Any boundary between parcels of land owned or leased by different persons or groups of persons.
Sia. Falling and Debris Hazard setback requirement (ft)
Sc. Flicker Hazard setback requirement (ft)
Ss. Acoustic Hazard setback requirement (ft)
Sound level meter means an instrument for the measurement of sound levels conforming to ANSI type ! or type II
standards.
Sound pressure level means the level of a sound measured in dB units with a sound level meter which has a uniform
(flat) response over the band of frequencies measured. Sound pressure levels are referenced to 20 micropascals;
expressed as [sound level] dB re 20uPA.
Sound power level is calculated from a sound pressure level at a given distance by the formula Lw=Lp+20logD+0.5, dB re 10°?
W where Lp is measured in accordance with American National Standards $12.9 ~ Part 3, "Quantities and Procedures for
Description and Measurement of Environmental Sound" or ANSI
$12.18, or Lw=Lp-6+10log(4pi(D)), dB re 107 W where Lp is measured in accordance with AWEA/IEC 61400-11 using a
1-meter flat ground board. D is the distance from the source (typically the hub height plus % the rotor diameter).
Setback Area. The entire land base that falls within the Setback for a particular MT or WEF.
Setback. A distance measured horizontally in feet from a property line to the closest point of any WEF turbine or
Meteorological Tower.
Type 0: Micro Wind Energy Facility. One or more wind turbines, each with a nameplate capacity of less than 1 kW anda
turbine height (measured to the top of an upright blade) of 35 feet or less.
Type 1: Small Wind Energy Facility. A single wind turbine with a nameplate capacity of 10 kW or less and a turbine
height (measured to the top of an upright blade) of 80 feet or less.
Type 2: Intermediate Wind Energy Facility. A single wind turbine with a nameplate capacity of less than 100 kW and or a
turbine height (measured to the top of an upright blade) of 150 feet or less.
Type 3: Large/Commercial Wind Energy Facility. A single wind turbine with a nameplate capacity of 100 kW or a turbine
height (measured to the top of an upright blade) of more than 150 feet. Or a WEF composed of two or more turbines each
Page 3 of 21
with a nameplate capacity of 100 kW or more. Or a WEF (of any size or number of turbines) 25% or more of whose power
is intended for sale or use by entities or persons other than the generator.
W means power in Watts.
Wind Energy Facility (WEF). All equipment, structures, roads, and power lines that together form a system for the
production of electrical power using ambient wind as a source of motive power.
Wind Energy Facility Turbine (WEFT). Any machine constructed to convert ambient wind energy to
electromotive energy.
7.0 Documents. Various State documents and Standards Bodies' documents are referred to throughout this document
8.0 Design, Manufacture, and Construction Standards
8.1 The design and manufacture of all meteorological towers, all wind turbines, and all other components of a WEF
shall conform to applicable national, state, and local standards for the wind industry, such as those established by the
American National Standards Institute (ANSI), Underwriters Laboratories, and similar certifying organizations. All MTs and
all components of a WEF shall conform to local, state, and national building codes.
8.2 Meteorological towers (MT) must be less than 200 feet in height, and must be designed so as not to require
lighting. Guy wires are allowed but must be designed so as to limit Environmental Hazard to wildlife, especially birds and
bats. For MTs connected with the potential development of commercial WEFs, a Decommissioning Bond will be required to
ensure timely removal of the equipment.
8.3 Underground power and transmission lines shall be buried at a depth consistent with state public utility
engineering standards to prevent transient ground currents and stray voltage.
8.4 An application for a permit for a Type 3 WEF that will be connected to the Public Utility Grid shall include a Public Utility
Grid Impact Statement documenting all anticipated changes to the public utility grid within the Town of New Portland due to the
WEF. The Statement shall be signed and approved by the Maine Public Utilities Commission and shall include proof of
leases or rights of way for transmission lines, and an analysis of the residual capacity in the grid that will be available to
other local generating projects after the construction of the WEF.
8.5 AWEFT with a nameplate capacity of more than 10 kW shall be equipped with a redundant braking system that
includes both aerodynamic over-speed controls (including variable pitch, tip, and other similar systems) and mechanical
brakes. Mechanical brakes shall operate in fail-safe mode. Stall regulation shall not be considered a sufficient braking
system for over-speed protection on WEFTs with a nameplate capacity of more than 10 kW.
8.6 WEFs shall be designed and sited to prevent the disruption or loss of emergency or private radio, telephone,
television, or similar signals. Interference with such communications shall be grounds for ordering the immediate shut
down of the WEF until the interference has been remedied.
8.7 The minimum distance between the ground and the blades of a WEF shall be 25 feet as measured at the lowest
point in the arc of the blades.
8.8 WEFs shall be mounted on towers or on poles with guy wires except that WEFs with a nameplate capacity of
less than 1 kW may be mounted on structure roof tops.
8.9 The color of WEFTs and MTs shall be off-white or grey or some other unobtrusive color approved by the Town of
New Portland Planning Board.
8.10 | WEFs shall not be used to display signs or advertising except for signs at ground level identifying the turbine
manufacturer, the WEF Owner/Operator, emergency contact information, and appropriate warnings as required by
national, state, and local laws.
8.11. All construction activities must conform to the approved detailed site plan, including any conditions of approval
Page 4 of 21
. and changes approved by the Code Enforcement Officer and/or the Planning Board.
8.12 Modification During Construction If at any time it appears necessary or desirable to modify the approved plans before
or during construction of the WEF, the Code Enforcement Officer, with assistance at the Applicant's expense from such staff,
consultants or experts as the CEO deems appropriate, is authorized to approve minor modifications due to unforeseen
circumstances such as encountering hidden outcrops of bedrock, natural springs, etc. The Code Enforcement Officer shall
issue any approval under this section in writing and shall transmit a copy of the approval to the Selectmen and Planning
Board. Revised plans shall be filed with the Planning Board for the record. For major modifications such as relocation of
rights-of-way, relation of WEFTs, changes in grade by more than 1%, etc., the Applicant shall submit to the Planning board
an amended plan for review and approval.
9.0 Public Health and Safety Standards
9.1 Setback Standards. All MTs and WEFs must be sited so as to satisfy the Setback Standards calculated
in Table 1 for the following hazards: If more than one set-back requirement applies, the greatest set-back distance
shall be met. All set-back distance measurements shall be based on horizontal distances between the center axis
of any WEF Turbine and a property line.
° Falling and Debris Hazard
° Flicker Hazard
° Acoustic Hazard (See Table 2 for calculations of typical setback distances)
Page 5 of 21
SETBACK DISTANCE STANDARDS
ALL MEASUREMENTS AND DISTANCES ARE MEASURED HORIZONTALLY IN FEET FROM
TURBINE(S) to PROPERTY LINES
METEOROLOGICAL
SETBACK (FT) TOWER TYPE 0 & TYPE 1 TYPE 2 TYPE 3
FALLING & DEBRIS|Sfrq=HoX1.5 Stig=HoX1.5 Sfidg=HoX1.5 S#g=HoX1.5
HAZARD Where: Syq Setback Distance] Where: Sg. Setback Distance |Where: Stig. Setback Distance |VWhere: Syg. Setback Distance
Hp Height Overall Ho- Height Overall Ho- Height Overall Hop- Height Overall
FLICKER HAZARD|Not Applicable So=(Ho/.176)x1.5 Flicker Hazard Report Flicker Hazard Report
Must not exceed limits specified |Must not exceed limits specified
Where: Sc. Setback Distance in section 9.9 in section 9.9
Ho. Height Overall Ho. Height Overall Ho. Height Overall Ho. Height Overall
Not including 120° to 240° True
ACOUSTIC HAZARD|Not Applicable Ss=10*((Ly+Ly+Ls+4tog(n)-.5-30)/20) | Ss=104((LwtLy+Lg+4log(n)-.5-30/20)| Ss=10"((Ly+LytL¢+4log(n)-.5-30)/20)
Where:Ss- Setback Distance |[Where:S<s- Setback Distance Where:Ss- Setback Distance
Lw- Manufacturer's Guaranteed Lw- Manufacturer's Guaranteed Ly- Manufacturer's Guaranteed
Maximum Sound Power Level, in dBA] Maximum Sound Power Level, in dBA re] Maximum Sound Power Level, in dBA
re 1pW Tpw Re ipWw
Ly- Uncertainty Factor = 5 Lu- Uncertainty Factor = 5 Lu- Uncertainty Factor = 5
Ls- Safety Factor = 2 Ls- Safety Factor = 2 Ls- Safety Factor = 2
n- No. of Turbines n- No. of Turbines n- No. of Turbines
for one turbine 4log(n)=0 for one turbine 4log(n)=0 for one turbine 4log(n)=0
Lw- Manufacturer's Guaranteed Maximum Sound Power Level, in dBA re 1pW
The Manufacturer's Guaranteed Maximum Sound Power Level in dBA that is reported must be the. __
maximum level that the turbine produces over its entire operational range at all wind speeds and this figure
must also have been verified by an independent certified testing laboratory.
Page 6 of 21
'
\
ne
Acoustic Setback Distance is MEASURED HORIZONTALLY IN FEET FROM TURBINE(S) to
PROPERTY LINES
Power Level, dBA re 1pwW
Page 7 of 21
9.2 The applicant shall compute by using the formula in Table tor look up in Table 2, as appropriate, and graph the
required setback for each hazard as a circle for a single unit or as a series of connected arcs for multiple units
centered on each turbine and submitted with the required setback graphically superimposed to scale on town maps
identifying lot owners and lot property lines.
9.3 Acoustic Standards. Sound levels due to the operation of the WEF shall not exceed 30 dBA or 50 dBC
at property lines or structures in the Town of New Portland.
9.3.1 Sound measurements shall be carried out at appropriate property lines or structures as soon as
possible after the Town of New Portland Planning Board determines that a violation of the noise standards
may have occurred.
9.3.2 All sound measurements shall be made by a professional acoustical engineer who is a Full Member
of the Institute of Noise Control Engineering (INCE) or who possesses some comparable qualification. The
engineer shall be chosen by the Owner/Operator from a list provided and contracted by the Planning Board
and paid by the Owner/Operator.
9.3.3 Except as specifically noted otherwise, sound measurements shall be conducted in compliance with
the American National Standards Institute (ANSI Standard S12.18-1994, as amended, "Outdoor
Measurements of Sound Pressure."
9.3.4 Sound level meters and calibration equipment shall comply with the latest version of ANSI Standard
$1.4, as amended, "Specifications for General Purpose Sound Level Meters," and shall have been
calibrated at a recognized laboratory within one year before the sound measurements are carried out.
9.4 An Application for a permit to construct a Type 3 WEF with one or more turbines having a nameplate
capacity of 100 kW or more shall include a Fire Prevention and Fire Fighting Plan that has been approved by the
Town of New Portland Fire Department. The plan shall identify a response plan to address all potential WEF fire
scenarios and include a list of hazardous materials that may be encountered.
9.5 The Owner/Operator of a Type 3 WEF with one or more turbines having a nameplate capacity of 100 kW
or more shall ensure that the WEF complies with the following fire control and prevention measures and assumes
responsibility for all associated incremental costs.
° Use of fireproof or fire resistant building materials and buffers as required by state law or the New
Portland Fire Department.
e Incorporation of a self-contained fire protection system in the WEF turbine nacelle.
° Maintenance of firebreak areas, cleared of vegetation, as required by state law or the New Portland Fire
Department.
° Provision for any additional fire fighting or rescue personnel, services, training, materials, and vehicles as
may be required to deal with any emergency related to the WEF that is beyond the current capabilities of
the New Portland Fire Department.
9.6 The Owner/Operator of all WEFs shall be responsible for compliance with all ordinances, regulations, and
laws applicable to the generation, storage, cleanup, and disposal of hazardous materials connected with the WEF.
9.7 Road and Property Risk Assessment
9.7.1 An application for a permit to construct a Type 2 or Type 3 WEF shall include a Road and Property
Risk Assessment that has been approved by the Town of New Portland Road Commissioner and/or Board of
Selectmen.
9.7.2 The Town of New Portland Planning Board shall require changes to the Road and Property
Risk Assessment plan that it deems appropriate to protect public safety, to protect public and private
property, and to address anticipated costs to the town.
Page 8 of 21
9.7.3. A qualified third party engineer, chosen by the Applicant from a list provided and contracted by the
Planning Board and paid by the Applicant, shall document road conditions prior to the construction of the
WEF, and again within thirty days after construction is complete. Any road damage determined by the
engineer to have been caused by the applicant or his contractors shall be promptly repaired at the
applicant's expense.
9.7.4 The Town of New Portland may bond the roads in compliance with state regulations, and the bond is to
be paid by the applicant prior to the transport of WEF components.
9.8. The Owner/Operator of the any WEF shall notify the Town of New Portland Planning Board of any "extraordinary
event" within 24 hours after that event. Extraordinary events shall include but not be limited to tower collapse,
catastrophic turbine failure, fires, leakage of hazardous materials, unauthorized entry into a tower base, thrown blade
or hub, injury caused by the WEF, and any other event that affects the public health and safety of the town or its
residents.
9.9 Flicker Hazard Limits and Flicker Hazard Report/study.
WEFs shail be designed and sited so that shadow flicker will not fall on a Flicker Receptor as defined in Section 6.0 .
An exception to this standard may be made based on the following condition only, namely that the total flicker from all
proposed WEF towers does not exceed 1 hour per year for any given Flicker Receptor.
If different amounts of flicker fall on different parts of a Flicker Receptor -- the worst case amount shall be used for
calculations.
The predictive annualized caiculation shall assume clear weather, but take into account seasonal tracking of the sun.
Field verification and modeling, if necessary, will be paid for by the Applicant and hired independently by the Town.
The Application shall include a detailed shadow flicker assessment model and an estimate of the expected amount
of flicker. This study must meet the following requirements.
a. A registered professional regularly engaged in this type of work shall prepare the study. The Planning Board
shail retain a Qualified Independent Shadow Flicker Consultant paid for in advance by the Applicant. The
consultant will review this study and assist the Planning Board in determining whether the proposed WEF
will comply with the standards set forth in this Ordinance. The Applicant shall pay in advance for the cost of
the study and its review.
b. The study will examine the areas within a two-mile radius of any WT in the proposed WEF.
c. The model will be calculated using the following minimum inputs:
i. Turbine locations (proposed and existing)
ii. Flicker Receptor locations
iii. Existing topography (elevation contours and vegetation)
iv. Rotor diameter, blade width and hub height
v. Joint wind speed and direction distribution (wind rose table)
vi. Hours of sunshine (long term monthly references)
d. The model may be prepared by use of current aerial photography and topographical maps.
@. The study shall estimate the locations and durations of shadow flicker caused by the proposed
WEF within the study area. The study shall clearly indicate the duration of shadow flicker at
locations throughout the study area, showing the total number of hours per year anticipated.
f. The study must include a statement of the assumptions made, methodology applied, and data
used by the study. This information must be sufficient to allow an independent third party to
Page 9 of 21
verify the results of the study.
g. The study shall also include a paint sample that demonstrates the color, texture and gloss of the
proposed surface coating and a certification that the proposed surface coating will not create a
reflective surface conducive to blade glint.
Blade glint is prohibited.
9.10 -- Visual Impact Assessment
A Visual Impact Assessment shall be submitted as part of the initial application for a Wind Energy Facility within the
Town of New Portland. In determining whether or not the proposed development will have a negative effect on the
scenic character and/or a negative aesthetic impact on the residents, the Board shall address the question, Would
this particular project result in undue harm to valuable aesthetic resources within the town of New Portland?"
The Board shall weigh the following questions:
1. Is the proposed wind energy facility located within an area of obvious scenic significance?
2. Would the facility significantly degrade views or scenic resources of New Portland.
3. Is the facility in a landscape area that is a visually distinct for the town?
4, |s the facility unreasonably close to residences that would be affected as a result of noise or shadow flicker.
5. Will the facility occupy an area valued for its wilderness characteristics?
6. Would the facility's scale in terms of turbine height or numbers of turbines overwhelm the landscape in which it is
built?
The Preliminary Application for a Wind Energy Facility shall include the following:
Project Description:
1. Description of all elements of the proposed project (enumerated in the list of required documentation which must
accompany an application for a permit)
i. Detailed Characteristics of proposed turbines (e.g. height, rotor diameter, color, rated noise levels, the
number planned to be erected and their actual locations:
ii. Complete description of meteorological towers;
iii, Roads;
iv. Collector, distribution and transmission lines;
v. Temporary or permanent storage areas;
vi. Substations;
vii. Any other structures associated with the project.
vill. Identification of site clearings, including clearing for turbines, roads, power lines, substations.
ix. Description and location of all site regrading that will be engineered, including the amount of cut and fill,
locations, and clearing required.
Page 10 of 21
x. Simulated photos and video of the proposed facility which illustrates items A-H above.
xi. Note. This information forms the basis for all aesthetic review by the Board
2. Viewshed analysis map showing all areas of New Portland, superimposed over the New Portland Property Map,
from which any part of the WEFT's of a proposed wind-energy facility would potentially be visible. This shall be a
computer generated map based on digital-elevation models which illustrate where the tips of each turbine and all
aspects of the facility sited in section 1, i - xi above could potentially be visible from all year-round and seasonal
residences within the boundaries of the Town. If complex topography makes it difficult to determine whether a
particular turbine or other object will be visible from a particular point, a line-of-sight analysis shall be submitted.
3. Virtual Simulations of how the facility will appear from each New Portland residence designated in paragraph 2
above and shall be prepared using photographic simulations or photomontages based on still photographs taken from
each of the above locations. Photographs shall be taken with a 50-mm lens or digital equivalent that creates a 38.6
degree angle of view. Global positioning system (GPA) location points of all sites named above shall be recorded for
each simulation. The accuracy of these simulations shall be verified by an expert in the field of digital images. This
expert shall be commissioned by the Planning Board and paid for by the applicant.
4. Using a DEM (digital-elevation model), create accurate digital images of the facility from each of the GPS
coordinates representing each identified location. Exact turbine locations as well as roads, meteorological towers,
and other project infrastructure will be inserted into the model. images of the turbine and other structures and
ancillary projects shall be created on the DEM using a program such as Visual Nature Studio and merged with a
photograph using a digital photo-editing program. The relationship between the size of the each photograph and the
distance of the observer shall be such that a realistic image in created. The formula for determining the correct size
of the image in relation to the distance viewed is: Distance from viewer=Width of image/( 2 * tan(hFoV/2))
5. Field assessment and Inventory of views.
A field inventory of views from all designated residences shall be presented. In addition to photographically
documenting and mapping viewing locations above, the following information shall be recorded; distance from
project, duration of view, angle of view, scenic quality of view, focal point of view of the project, characteristics of the
view(intermittent, panoramic, and foreground, middle ground and background elements in the view.) The documents
outlined in section 9.10 shall be presented to the residents of New Portland at a public hearing for their review and
input to the Board.
10.0 Environmental Standards
10.1 The siting and construction of all WEFs shall meet all the applicable standards and ordinances of the Town
of New Portland, Maine and be consistent with the Town of New Portland Comprehensive Plan.
10.2 'If required by the laws of the State of Maine, a Department of Environmental Protection Site Location
of Development permit shall be obtained and submitted with an application for a WEF permit. If submitted, this
permit shall be considered adequate evidence that sections 10.3 and 10.4 of this Ordinance have been
satisfied.
10.3 Environmentally Sensitive Areas. The design, construction, and maintenance of a WEF shall
protect all environmentally sensitive areas that may be affected by its siting. Such areas shall include but not
limited to wetlands, vernal pools, seeps or springs, steep slopes (equal to or greater than 15%), watersheds,
100 year flood plains, significant habitat for wildlife, fish, and plants as defined by The Maine Department of
Inland Fisheries and Wildlife and The Maine Natural Areas Program. An application for a Type 3 WEF permit
shall demonstrate appropriate measures for protecting all such areas during both construction and operation
of the WEF.
10.4 Wildlife Protection.
10.4.1. The application for a Type 3 WEF shall include a Wildlife Protection Plan based on pre-
Page 11 of 21
construction field studies designed and carried out by a qualified wildlife biologist chosen by the
Applicant from a list provided and contracted by the Planning Board and paid by the applicant. Such
studies shail describe the possible adverse effects of the WEF on birds, bats, animals and their
habitats, and shall propose remedies for these effects.
10.4.2 Post Construction Wildlife Protection Field Studies. Within three years after completion of
construction of a Type 3 WEF, studies to ascertain its actual effect on wildlife shall be designed and
carried out by a qualified wildlife biologist chosen by the Owner/Operator from a list provided by the
Planning Board and paid by the Owner/Operator. If these studies demonstrate undue adverse effects
on wildlife caused by the WEF, the Owner/Operator in consultation with the Maine Department of
Inland Fisheries and Wildlife (MDIFW) shall design and implement an appropriate mitigation plan. The
plan shall be submitted to the Town of New Portland Planning Board for approval. The Owner/Operator
shall be responsible for the full cost of carrying out the plan under the supervision of the MDIFW.
10.5 Erosion Control. Type 3 WEFs shall be designed , constructed, and maintained in accordance with
accepted erosion and sediment control methods as set out in the Maine Erosion Control Handbook for
Construction; The Best Management Practices, dated March (2003).
10.6 Water Quality Protection.
10.6.1 Type 3 WEFs shall be designed, constructed, and maintained so as to avoid undue adverse
impacts to groundwater, including sand and gravel aquifers. The Planning Board may require as
condition of issuing a permit for a Type 3 WEF that a pre-construction baseline study of all wells,
springs, and public water sources within the watershed of the WEF site be conducted. The study shall
be designed and carried out by a water quality professional chosen by the Applicant from a list
provided and contracted by the Planning Board and paid by the Applicant.
10.6.2 Post Construction Groundwater Quality Study. Within two years after completion of
construction of a Type 3 WEF for which the Planning Board has required a pre-construction baseline
Water Quality Study as described in section 10.6.1 of this Ordinance, a Post Construction Water
Quality study of all wells, springs, and public water sources within the watershed of the WEF site shall
be designed and carried out by a water quality professional chosen by the Applicant from a list
provided by the Planning Board and paid by the Owner/Operator. If degradation or contamination is
found to have occurred, fines and/or permanent remedies as required by the Town of New Portland or
the State of Maine shall be the responsibility of the Owner/Operator.
10.7 Hazardous Wastes. The Owner/ Operator shail be responsible for compliance with all state and
federal regulations applicable to the use and disposal of hazardous wastes involved in or generated by the
WEF's construction and operation. This responsibility shail extend to safe and lawful disposal of the by-products
of any Acid Rock Testing and Mitigation Plan.
10.8 Blasting. Owner/Operator of a WEF shall not undertake any blasting without notifying the Town of
New Portland and submitting a blasting plan in accordance with the latest DEP Standards. The blasting plan
shall be reviewed and approved by the New Portland Planning Board before any blasting takes place. Forty-
eight hour notice shall be given to all residents within a two mile radius of the blasting area (measured
horizontally) before blasting can begin.
10.9 Light Pollution. All WEFs shall be designed and sited to minimize nighttime light pollution and shall
not exceed the minimal requirements by the Federal Aviation Authority. Red lights shall be used instead of
white if possible and shall be shielded to the greatest extent possible from viewers on the ground. An
applicant for a WEF shall provide a plan showing all lighting on and around the WEF.
10.10 Radar Interference. The Applicant shall contact the FAA and The Department of Defense to obtain
written approval that all proposed Wind Turbines and associated facilities are approved by them under all
operating conditions.
Page 12 of 21
11.0 Financial Standards
11.1 An applicant for a Type 3 WEF shall provide evidence satisfactory to the Town of New Portland
Planning Board that the project is financially viable. Evidence of financial viability shall include the
following:
. A budget for the construction of the WEF
° Proof of adequate financing for all aspects of the construction
. Proof of adequate financing for operations and maintenance including salaries over the lifetime of the
project
. Proof of the applicant's technical ability to implement the project as proposed
. Proof of long-term power purchase contracts if 25% or more of the WEF output is intended for sale.
. Proof of adequate funds for Decommissioning as specified in section 11.3 of this Ordinance
11.2 The Owner/Operator of a Type 3 WEF shall maintain a current general liability policy for the WEF
covering bodily injury and property damage commensurate with the scope and scale of the project. Proof of
current insurance must be presented to the Planning Board with the application for a permit and every year
thereafter on the date of the insurance's annual renewal.
11.3. The Owner/Operator of a Type 3 WEF shall, at his/her expense, be responsible for complete
Decommissioning of the WEF and site restoration within twelve months after it ceases to generate electricity,
or after its operational license has been revoked. Abandonment will be grounds for immediate revocation of
license.
11.3.1 Decommissioning shall include removal and disposal outside the Town of New Portland of all
parts of the WEF (including foundations) in accordance with local, state and federal laws and
regulations. Areas of disturbed earth shall be graded, seeded, or otherwise re-vegetated following
guidelines provided by the CEO.
11.3.2 A Professional Engineer shall be chosen by the Applicant from a list provided and contracted
by the Planning Board and paid by the Applicant to estimate the total cost of Decommissioning without
consideration of the salvage value of the equipment. No permit for a Type 3 WEF shall be issued until
Decommissioning Funds have been posted by the Applicant with a bonding company or a Federal or State-
chartered lending institution (the Escrow Agent) authorized to conduct such business in the State of Maine
and approved by the Town of New Portland Planning Board and Board of Selectmen.
11.3.3 Estimates as described in section 11.3.2 shall be redone annually on the anniversary of
the granting of a WEF Permit, and the Owner/Operator of the WEF shall be required to maintain
Decommissioning Funds that are at least equal to the most recent estimate.
11.3.4 Decommissioning funds may be in the form of a performance bond, surety bond, letter
of credit or other form of financial assurance acceptable to the Town of New Portland Planning
Board and Board of Selectmen.
11.3.5 If the Owner/Operator of the WEF does not complete Decommissioning within the time
prescribed in section 11.3 of this Ordinance, the Town of New Portland may take such action as
necessary (including court action) to secure the posted Decommissioning Funds and to ensure
completion of the Decommissioning.
11.3.6 The Escrow Agent shall not release the Decommissioning Funds except upon written
approval of the Town of New Portland Planning Board and Board of Selectmen.
Page 13 of 21
11.4 Any promises of any benefits to be conferred upon the Town of New Portland by the applicant shall be
documented and submitted with the Final Application. These benefits shall become a legally enforceable
provision of the permit.
11.5 In reviewing an application and/or ongoing WEF operations for compliance with this Ordinance, the
Planning Board and/or CEO may, at their discretion, retain professional services as necessary to assist with its
review, including but not limited to those of an attorney, engineer, biologist, or land use planner. If the Planning
Board deems that such services are indeed necessary -- then they shall inform the applicant who will then have
fourteen (14) days to deposit in a joint escrow account with the Town the sum of $50,000 as partial payment
towards such expenses.
If such a fund is established and the balance of the fund falls below $25,000, the Applicant upon notice shall
submit an additional $25,000 to replenish the fund. If at any time after such notification the balance of this fund
stays below $25,000 for a period of 30 days or any time the level of funds is insufficient to complete reviews
that are required - the Application or Operational License shall be considered to have been withdrawn. The
balance of the escrow account shall be returned to the Owner/operator after all expenses have been paid. If
any delay in replenishing the fund generates a delay in reviewing the application or operations -- then the
deadline for completing the review is extended accordingly.
12.0 Ethical Standards
12.1 All deliberations concerning the permitting and regulation of WEFs shall be conducted at
public meetings for which notice has been duly given.
12.2 Conflicts of Interest. No elected or appointed official or employee of the Town of New Portland who
has a financial interest in the WEF under consideration shall be directly or indirectly involved in the permitting
or other regulation of that WEF. Financial interest includes but is not limited to the following:
® Having right, title or interest in land on which any part of the WEF will be constructed
° Having signed for the Applicant's benefit a Covenant with financial remuneration
° Having a financial arrangement such as employment or the promise of employment--including
employment as an outside contractor--with the Applicant Serving as a paid representative of
an individual or company that derives income from the development of wind power
13.0 Permitting and Licensing Authority
13.1 No person shail construct or install a WEF without obtaining a permit from the planning board in
accordance with this ordinance.
13.2 The Town of New Portland Planning Board is authorized to review all applications for permits to erect
Meteorological Towers and to construct Wind Energy Facilities and all applications for operational licenses
to operate such Facilities in the Town of New Portland. The Planning Board shall approve, reject, or
conditionally approve with conditions all applications brought before it for WEF and MT permits in the Town
of New Portland. No Wind Energy Facility as herein defined may be constructed or used, except in
conformity with the provisions of this Ordinance. The Applicant has the burden of proving that the application
is in compliance with the requirements of this Ordinance.
13.3 Approval of Variations From Plans
The granting of any permit is dependent upon and limited to the proposals and plans contained in the
application and supporting documents submitted to and affirmed to by the applicant. Any variation from
these plans, proposals and supporting documents is subject to review and approval prior to implementation.
Page 14 of 21
13.4 Compliance With All Applicable Laws
The applicant shall secure and comply with all applicable federal, state and local licenses, permits,
authorizations, conditions, agreements and orders prior to or during construction and operation, as
appropriate.
13.5 The Town of New Portland Planning Board and/or its designated agents or representatives shall have
the right to access and inspect WEF sites.
13.6 The Town of New Portland Planning Board reserves the right to limit the number of applications for WEF
permits that are under review at any given time. Only one application for a Type 3 WEF permit will be accepted
or processing at any given time.
13.7 The Maine Department of Environmental Protection (DEP) may be required to review WEF applications
within the Town of New Portland. When making its own determination about such applications, the Planning
Board shall consider, to the extent applicable, findings in the DEP review.
14.0 Permit and Operational License Requirements
14.1. Meteorological Tower (MT). The application for a permit for an MT shall be submitted in at least ten
hard copies and five CDs to the Town of New Portland Planning Board and shall include the following
information:
For type 0, 1, 2 and 3 WEF Applications
° Applicant and property owner name, address and contact information
e Proposed location of the MT including lot designation
e Intended period of data collection and date MT will be removed
For type 3 WEF Applications only -- the following additional information is required:
° Engineering drawing of proposed tower structure, instrument package, and guy system, if any
° Engineering drawing of proposed tower base
° Engineering drawing of tower location showing property lines and setback
requirements (as specified in Table 1 of this Ordinance)
° Any building, use or construction permits required by other authorities because of the size or
construction of the tower
° Plans for mitigation of Environmental Hazard to wildlife for towers requiring guy systems
° Description of intention
° Decommissioning Bond for MT
° A legally enforceable agreement that the applicant shall pay (in advance if required by the Town of
New Portland Planning Board) for the services of all consultants that the Planning Board deems
necessary to evaluate the application.
° Application Fee: See WEF - Fees Document
14.1.1 Within 90 days of the Planning Board's receiving a Meteorological Tower (MT) application the
Planning Board shall, with assistance from such staff, consultants, committees or
Page 15 of 21
commissions as it deems appropriate, notify the applicant in writing that the application is
complete or, if the application is incomplete, shall inform the applicant of the specific
additional material needed to complete the application.
For Type 3 Applications only -- the Funding for the above shall be paid for by applicant as per
section 11.5. The Planning Board reserves the option to hold a public hearing for a proposed
MT,
14.1.2 Within 45 days (or 60 days for Type 3 WEF Application) of determining the MT application is
complete, the Planning Board shall approve the MT Application, approve the MT Application
with conditions, or disapprove the MT Application. The time limit for review may be extended
by mutual agreement between the Planning Board and the Applicant.
14.2. Wind Energy Facility (WEF). A Preliminary Application for a Permit to Construct a Type 0, Type 1, and Type
2 WEF shall include at least five hard copies. A Type 3 WEF shall include at least ten hard copies. Type 3 WEF
applications shall also include five CDs of the complete application.
Upon approval of the Preliminary WEF Application, a Final WEF Application shall be prepared and submitted in at
least five hard copies for Type 0, Type 1 and Type 2 WEFs. A Type 3 WEF shall include at least ten hard copies.
Type 3 WEF applications shall also include five CDs of the complete application. Approval of the Final WEF
Application shall constitute a Permit to Construct the WEF.
14.2.1 The Preliminary Application shall include the following items.
Type 0, 1, 2 and 3 WEFs:
+ Applicant and property owner's name, address and contact information
* Nameplate data for the type of WEF turbine(s) to be used including manufacturer, model, rated power
output and maximum sound power level
Type 3 WEFs shall also include the following:
* Evidence of the Applicant's right, title or interest in the land on which the project is proposed to be sited
e =6if the applicant is not the underlying fee owner of the land, a signed statement by the underlying
landowner(s) in recordable form acknowledging that the landowner(s) will be financially responsible if
the owner/operator fails to reclaim the site as required, and that any removal and reclamation costs
incurred by the Town shall become a lien on the real estate and other property and may be collected
from the landowner(s) in the same manner as property taxes.
A Detailed Site Plan that shall include
* Total acreage occupied by the facility;
« detailed map of the area showing parcel boundaries and individual wind Turbine locations and their
distances to boundaries and existing structures;
* location of existing and proposed transmission lines, substations, driveways, access and maintenance
roads. All proposed electric transmission and distribution lines shall be shown and shall be placed
underground;
* location of meteorological or wind testing towers
* location of wells, abandoned and active, within a half mile radius of project boundary.
* Engineering drawing of the type of WEF turbine to be used
Page 16 of 21
* Certification of the non-reflecting properties of the WEF turbine's external surfaces
* Engineering drawing of the tower base for the type of WEF turbine to be used
* Engineering or architectural drawings of all planned structures, including structures for support and
maintenance of the WEF
* Description of intended use, including energy storage and grid connections, and the percentage (if
any) of generation intended for sale or use by entities or persons other than the applicant
* Engineering drawings and/or electrical schematics of any energy storage equipment or facilities
* Calculations and supporting data for all setback requirements (as specified in Table 1 of this
Ordinance). For Type 3 WEFs, setback requirements must be calculated for each WEF turbine.
* Overlay of Town of New Portland property maps showing the setback area and all property lines and
rights of way affected by the setback requirements
* -- List of property owners whose property, wholly or in part, lies within the setback areas
+ Shadow-Flicker Hazard Report as specified in Table 1 and section 9.9 of this Ordinance
* Visual Impact Assessment as specified in 9.10
* The applicant shall pay (in advance if required by the Town of New Portland Planning Board) for the
services of all consultants that the Planning Board deems necessary to evaluate the application. Such
consultants shall be chosen by the Planning Board. Failure of the Applicant to make such payment
renders the Application void.
. Fire Prevention and Fire Fighting Plan as specified in sections 9.4 - 9.5 of this Ordinance
. Road and Property Risk Assessment as specified in section 9.7 of this Ordinance
. Plan to protect Environmentally Sensitive Areas, as specified in section 10.3 of this Ordinance
. Wildlife Protection Plan as specified in section 10.4 of this Ordinance
. Baseline Water Quality Study (if required) as specified in section 10.6 of this Ordinance
. Plan for the handling and disposal of Hazardous Wastes as specified in section 10.7 of this
Ordinance
° Plan to minimize Light Pollution as specified in section 10.9 of this Ordinance
. Blasting Plan as specified in Section 10.8 of this Ordinance
+ Fees: See WEF - Fees Document
14.2.1.1 Within 60 days for Type 0, 1 or 2 or within 120 days for Type 3 of the Planning
Board's receiving a Preliminary WEF Application, the Planning Board shail, with assistance from such staff,
consultants, committees or commissions as it deems appropriate, notify the applicant in writing that the
application is complete or, if the application is incomplete, shall inform the applicant of the specific
additional material needed to complete the application. The Planning Board may extend the amount of time
for reviewing the Preliminary Application if resources do not allow for a proper review in the allotted time.
e For Type 3 Applications, the Planning Board shall hold a public hearing within 60 days of the date of
determination of a completed preliminary application. The Planning Board shall publish the time,
date, and place of the hearing in at least three public locations. All landowners within 2 miles of a
Page 17 of 21
WEF shall be notified by the Planning Board of the hearing. All landowners within 2 miles of any
WEF shall be notified by the Applicant via Certified Mail return receipt requested of the hearing.
Public hearings by the Planning Board shall be conducted according to the procedures outlined in
title 30-A M.R.S.A. Section 2691, Subsection 3 (A), (B), (C), (D), and (E).
14.2.1.2 After the Planning Board determines that a Preliminary WEF Application is complete, the
Planning Board shall determine whether Preliminary WEF Application meets all requirements of this
Ordinance. In determining whether the Application meets the requirements of this Ordinance, the
Planning Board may obtain assistance from such staff and consultants as it deems appropriate which
will be paid for by the applicant as per 11.5
14.2.1.3 Within 45 days for a Type 0, 1 or 2 or within 90 days for a Type 3 WEF of determining the
Preliminary WEF Application is complete, the Planning Board shall approve the Preliminary WEF
Application, approve the Preliminary Application with conditions, or disapprove the Preliminary WEF
Application. The time limit for review may be extended by mutual agreement between the Planning
Board and the Applicant.
14.2.1.4 The Planning Board shail make findings of fact and conclusions relative to the
standards contained in this Ordinance. If the Planning Board finds that all standards have been met,
they shall approve the Preliminary WEF Application. If the Planning Board finds that any of the
standards of this Ordinance have not been met, the Planning Board shall either deny the Preliminary
WEF Application or approve the Preliminary WEF Application with conditions to ensure all of the
standards will be met. The reasons for any conditions shall be stated in the findings of facts and
conclusions.
14.2.2 The Final Application shall include the following items:
° Updates to information provided in the preliminary application, including additions, corrections, and any
other changes
For Type 3 Applications only:
. Results of any meteorological testing
* Any building use or construction permits required by other authorities due to the scope of the intended
project
. Public Utility Grid Impact Statement as specified in section 8.4 of this Ordinance
° Financial analysis for Type 3 WEFs, including evidence of financial capacity to carry out the project, as
specified in section 11.1 of this Ordinance
. Proof of general liability insurance as specified in section 11.2 of this Ordinance
* Decommissioning bond for Type 3 WEFs as specified in section 11.3 of this Ordinance
. Statement of Benefits promised to the Town of New Portland
* The applicant shall pay (in advance if required by the Town of New Portland Planning Board) for the services
of all consultants that the Planning Board deems necessary to evaluate the application. Such consultants shall
be chosen by the Planning Board. Failure of the Applicant to make such payment renders the Application
void.
. Posting of the estimated total cost of Decommissioning Funds as specified in section 11.3
° Fees See WEF - Fees Document
14.2.2.1 Within 45 days for Type 0, 1 or 2 or 120 days for Type 3 of the Planning Board's receiving a Final
WEF Application, the Planning Board shall, with assistance from such staff, consultants, committees or
Page 18 of 21
commissions as it deems appropriate, notify the applicant in writing that the application is complete or, if the
application is incomplete, shall inform the applicant of the specific additional material needed to complete
the application. The Planning Board may extend the amount of time for reviewing the Final Application if
resources do not allow for a proper review in the allotted time.
14.2.2.2 The Planning Board shall hold a public hearing within 60 days of the date of determination of a
complete Final WEF Application for a Type 3 WEF. The Planning Board shall publish the time, date, and
place of the hearing at least two times, the date of the first publication to be at least seven days prior to the
hearing in a newspaper of area wide circulation. All landowners within 2 miles of a WEF shall be notified by
the Applicant via Certified Mail return receipt requested of the hearing. Public hearings by the Planning Board
shall be conducted according to the procedures outlined in title 30-A M.R.S.A. Section 2691, Subsection 3
(A), (B), (C), (D), and (E).
14.2.2.3 After the Planning Board determines that a Final WEF Application is complete, the Planning Board shall
determine whether the Application meets all requirements of this Ordinance. In determining whether the Final WEF
Application meets the requirements of this Ordinance, the Planning Board may obtain assistance from such staff
and consultants as it deems appropriate.
14.2.2.4 Within 45 days for a Type 0, 1 or 2 or within 90 days for a Type 3 of determining the Final WEF
Application is complete, the Planning Board shall approve the Final WEF Application, approve the Final
WEF Application with conditions, or disapprove the Final WEF Application. The time limit for review may
be extended by mutual agreement between the Planning Board and the Applicant. The Planning Board
may extend the amount of time for approving the Final Application if resources do not allow for a proper
review in the allotted time.
14.2.2.5 The Planning Board shall make findings of fact and conclusions relative to the standards
contained in this Ordinance. If the Planning Board finds that all standards have been met, they shall approve
the Final WEF Application. If the Planning Board finds that any of the standards of this Ordinance have not
been met, the Planning Board shall either deny the Final WEF Application or approve the Final WEF
Application with conditions to ensure all of the standards will be met. The reasons for any conditions shall be
slated in the findings of facts and conclusions.
14.2.2.6 _ Initiation of Activity Within two Years. If construction or operation of the activity is not begun
within 2 years, this permit shall lapse and the applicant shall reapply to the board for a new permit. The
applicant may not begin construction of operation of the activity until a new permit is granted. Reapplications
for permits shall state the reasons why the applicant will be able to begin the activity within two years from
the granting of a new permit, if so granted. Reapplications for permits may include information submitted in
the initial application by reference.
14.3 An Operational License is required for the operation of any type 3 WEF built in the Town of New Portland
after the effective date of this Ordinance. An application for an Operational License shall be submitted in ten hard
copies to the Town of New Portland Planning Board after the WEF has been fully built.
14.3.1 The application for an original Operational License shall include the following items:
e An Inspection Report certifying the structural and operational integrity of the WEF. This Report shall
be signed by a Maine licensed professional engineer chosen by the Town of New Portland Planning
Board and paid by the Owner/Operator of the WEF.
° A signed statement that the Applicant has read this Ordinance, understands all its provisions, and
agrees to abide by them.
e Fee: See WEF - Fees Document.
14.3.2 An Operational License shall be valid for one year and can be renewed by submission of a new
Inspection Report and Fee as specified in section 14.3.1 of this Ordinance at least thirty days before
expiration of the License.
Page 19 of 21
14.3.3. An Operational License shall be revoked and the WEF required to cease operations if the
Town of New Portland Planning Board determines that the WEF is violating any of the standards and
requirements of this Ordinance. The Operational License shall not be reinstated until the Planning Board
is satisfied that all violations have ceased and all problems have been corrected.
14.3.4 An Operational License shall automatically terminate upon transfer of ownership of the WEF. The
new Owner/Operator shall apply for a new Operational License and shall not operate the Type 3 WEF until
the new License has been issued.
14.3.4.1 The Application for an Operational License by a new Owner/Operator shall contain the
following items:
° Copies of the original Permit Applications, updated as necessary, and signed by the new
Applicant
. A copy of the original Operational License Application, updated as necessary, and
signed by the new Applicant
° A statement, signed by the new Applicant, that he/she has read this Ordinance,
understands it, and will abide by all of its provisions.
. Fee: See WEF - Fees Document.
14.3.4.2 A new Applicant for an Operational License for a Type 3 WEF shall provide evidence
satisfactory to the Town of New Portland Planning Board that the project remains financially viable.
Evidence of financial viability shall include the following:
= Proof of long-term power purchase contracts
= Proof of ongoing subsidies from all sources
* Proof of adequate funds for Decommissioning as specified in Section 11.3 of this
Ordinance.
14.3.4.3 Within 45 days of the Planning Board receiving an Application for a Type 3 WEF
Operational License, the Planning Board shall, with assistance from such staff, consultants,
committees or commissions as it deems appropriate, notify the applicant in writing that the
application is complete or, if the application is incomplete, shall inform the applicant of the
specific additional material needed to complete the application. The Planning Board may extend
the amount of time for reviewing the Application if resources do not allow for a proper review in
the allotted time.
14.3.4.4 Within 90 days of the determining that the Operational License Application is complete, the
Planning Board shall determine whether the Type 3 WEF Application meets the requirements for an
Operational License. In determining whether the Type 3 WEF Application meets the requirements of
this Ordinance, the Planning Board may obtain assistance from such staff and consultants as it
deems appropriate. The Planning Board may extend the amount of time for reviewing the Preliminary
Application if resources do not allow for a proper review in the allotted time.
14.3.4.5 The Planning Board shall make findings of fact and conclusions relative to the standards
contained in this Ordinance. If the Planning Board finds that all standards have been met, they shall
approve the Type 3 WEF application. If the Planning Board finds that any of the standards of this
Ordinance have not been met, the Planning Board shall either deny the Type 3 WEF Application or
approve the Type 3 WEF Application with conditions to ensure all of the standards will be met. The
reasons for any conditions shail be stated in the findings of facts and conclusions.
15.0 Violations and Enforcement
Page 20 of 21
15.1 It shall be the duty of the Code Enforcement Officer to enforce the provisions of this Ordinance and the
Code Enforcement Officer is given all powers to do so under 30-A M.R.S.A. §4452.
If the Code Enforcement Officer shall find that any provision of this Ordinance is being violated, he/she shall
notify in writing the persons responsible for such violation, indicating the nature of the violation and ordering
the action necessary to correct it. He/she shail order discontinuance of illegal use of land, buildings or
structures, removal of illegal buildings, structures, additions, or work being done, or shall take any other action
authorized by this Ordinance to ensure compliance with or to prevent violation of its provisions. The Code
Enforcement Officer shall use the monies deposited in the Escrow account described in 11.5 to help determine
whether or not a violation has occurred. These monies are not refundable to the Applicant regardless of the
outcome of the investigation.
15.2 The Code Enforcement Officer shall keep a complete record of all essential transactions of the
office, including applications submitted, permits granted or denied, variances granted or denied, revocation
actions, revocation of permits, appeals, court actions, violations investigated, violations found, and fees
collected.
15.3. Legal Action and Violations: When the actions taken in Section 15.1 do not result in the correction or
abatement of the violation or nuisance condition, the Municipal Officers, upon notice from the Code
Enforcement Officer, shall institute or cause to be instituted any and all actions and proceedings, either legal or
equitable, including seeking injunctions of violations and the imposition of fines, that may be appropriate or
necessary to enforce the provisions of this Ordinance in the name of the Municipality.
15.4 Fines: Any person, including, but not limited to, a landowner, a landowner's agent or a contractor, who
orders or conducts any activity in violation of this Ordinance, shall be penalized in accordance with Title 30-A,
Maine Revised Statutes, Annotated, Subsection 4452 and by a fine of not less than $100 nor more than
$2,500 per offense with each day on which such violation continues. Each day the violation exists shall be
considered a separate violation. The Selectmen are authorized to enter into a Consent Agreement and in
such cases court action is not necessary.
16.0 Appeals
Any appeal by an aggrieved party from an action of the Planning Board in administering the provisions of this
Ordinance shall be made to the Somerset County Superior Court in accordance with the procedures of Rule 80B.
WEF -- Fees Document
WEF Type Initial Application Final Application
[TypeO | 8 8S one time
Typel | 8 8 Sone time
'Type2 |S $50 one time
$250 $1000 $5000 annual
---- j SUVANLD War /PoDe of
L. Okeert dhadk VL or p On
Worn Pe) ,A01\
One x DOWD Vous CUI
Page 21 of 21
'
a
4 be
" €