SOLAR ENERGY ORDINANCE
TABLE OF CONTENTS
1. Purpose
2. Authority
3. Definitions
4. Applicability
5. Dimensional Standards
6. Performance and Installation Standards
7. Site Plan Review and Application Materials
8. Guarantee of Removal
9. Application and Permit Fees
10. Severability
11. Appendix A
1. Purpose
A. To be consistent with the philosophy of the Planning Board, as stated in the Land
Use Regulations, of "reasonable and orderly growth... without the undesirable
impact of an undue surge of speculation and development within the boundaries
of the Town of Penobscot."
B. To support the intent of the Planning Board, as stated in the Shoreland Zoning
Ordinance, "to further the maintenance of safe and healthful conditions" and "to
conserve natural beauty and open space."
C. To balance the rights of property owners to derive benefit from their land with the
value of the rural and scenic qualities that are prized by our residents and
visitors.
D. To protect the town's natural and rural character while allowing for development
that responds to the effects of a changing climate and the desire for energy
independence.
E. To uphold the vision expressed in the Comprehensive Plan that the town will
"encourage development in a manner that maintains our rural and scenic
qualities."
October 2025 Final
2
2. Authority
A. This ordinance is enacted pursuant to the Home Rule Authority granted to the
Town in accordance with provisions of 30 MRSA ❡ 3001.
B. The Penobscot Planning Board (PPB) is vested with the authority to approve,
approve with conditions, or reject any application for a Solar Energy System
(SES) as defined in this ordinance.
C. The PPB may hire independent professional consultants to review SES
applications to 1) determine the impact to nearby properties, 2) determine public
safety implications, or 3) address other issues with any SES application,
construction, or operation.
D. The cost (if any) for such professional consultancy will be borne by the applicant.
The PPB will notify the applicant with the consultant's name and qualifications,
the reason for the consultation, and the estimated cost.
E. The CEO and PPB will have the authority to monitor the construction, operation,
and decommissioning of any project covered by this ordinance.
3. Definitions
Decommissioning: The physical removal of all components of a solar energy
development, including but not limited to solar panels and associated anchoring
systems, foundations and all electrical equipment. Part of the decommissioning process
includes returning the site to a state that is safe and usable for other purposes.
Electrical Equipment: Any device associated with a Solar Energy System, such as an
outdoor electrical unit/control box, that transfers energy from the Solar Energy System
to the intended location.
Electricity Generation (production, output): The amount of electric energy produced
by transforming other forms of energy, commonly expressed in kilowatt-hours (kWh) or
megawatt-hours (MWh).
Height of building: The vertical measurement from grade to the highest point of a
building, excluding chimneys, television antennae, and HVAC systems.
Mounting: The manner in which a Solar Energy System (SES) or Photovoltaic (PV)
system is affixed to a roof or the ground (i.e., roof mount, or ground mount).
October 2025 Final
3
Power: The rate at which work is performed (the rate of producing, transferring, or
using energy). Power is measured in Watts (W), kilowatts (kW), Megawatts (MW), etc.,
in Alternating Current (AC).
Solar Array: Multiple solar PV panels combined to create a source of electrical power,
a part of a Solar Energy System.
Solar Collector: A solar PV cell, panel, or array, or solar thermal collector device, that
relies upon solar radiation as an energy source for the generation of electricity or
transfer of stored heat.
Solar Energy System (SES): A system of devices or structural design features,
including all related equipment, whose primary purpose is to harvest energy by
transforming solar energy into another form of energy or transferring heat from a
collector to another medium using mechanical, electrical or chemical means.
SES as defined by this ordinance:
Private Residential Solar Energy System (PRSES): A solar energy system
primarily or solely for on-site residential use, with a rated nameplate capacity of up to 40
(forty) kilowatts.
Commercial Solar Energy System (CSES): A solar energy system primarily or
solely for on-site use by a business or a group of buildings, with a rated nameplate
capacity of up to a total of 120 (one hundred and twenty) kilowatts.
Distributive Generation Solar Energy System (DGSES): A solar energy system
primarily or solely for off-site grid use, with a surface area of up to 10 (ten) acres,
including any required setbacks, and a rated nameplate capacity of up to 1 (one)
Megawatt.
Solar Energy System, Ground-Mounted: A solar energy system that is structurally
mounted to the ground and is not roof-mounted.
Solar Energy System, Roof-Mounted: A Solar Energy System that is mounted on the
roof of a building or structure.
Tilt: The angle of the solar panels or solar collector relative to horizontal. Fixed tilt and
adjustable tilt are utilized depending on equipment.
October 2025 Final
4
4. Applicability
The provisions of this Ordinance shall apply to:
A. Private Residential Solar Energy Systems (PRSES):
A solar energy system principally used to capture solar energy, convert it to
electrical energy or thermal power, and supply electrical or thermal power,
primarily or solely for on-site residential use. The system consists primarily of one
or more roof-mounted or free-standing ground mounted solar arrays or modules
and solar related equipment, intended primarily to reduce on-site consumption of
utility power and/or fuels. Solar arrays or modules that are mounted on the roofs
or walls of private residences shall not be subject to permit requirements but
shall adhere to SES standard of the National Electric code. Ground mounted
systems shall require a permit and shall be required to meet land use regulation
setbacks but shall be exempt from maximum lot coverage regulations. Rated
nameplate capacity can be up to 40 (forty) kW.
B. Commercial Solar Energy Systems (CSES):
An area of land or other area used by a business or a group of buildings for a
solar energy system principally used to capture solar energy, convert it to
electrical energy or thermal power, and supply electrical or thermal power,
primarily or solely for commercial use or the use of buildings located nearby. A
CSES consists of one or more free-standing, ground or roof mounted solar
arrays or modules, and solar related equipment, intended primarily to reduce on-
site consumption of utility power and/or fuels. Rated nameplate capacity of a
CSES can be up to a total of 120 (one hundred and twenty) kW.
C. Distributive Generation Solar Energy Systems (DGSES):
An area of land or other area used by a property owner and/or corporate entity
for a solar energy system principally used to capture solar energy, convert it to
electrical energy or thermal power, and supply electrical or thermal power,
primarily or solely for off-site utility grid use, and consisting of one or more free-
standing ground-mounted solar arrays or modules, or solar related equipment,
intended primarily to reduce off-site consumption of utility power and/or fuels. A
DGSES can be up to 10 (ten) acres in surface area, and is limited to a rated
nameplate capacity of up to 1 (one) megawatt. The 10 (ten) acre limit includes
any required setbacks.
October 2025 Final
5
5. Dimensional Standards
A. Ground-Mounted Solar Energy Systems shall be limited to 22 (twenty-two) feet in
height. Height shall be measured from the lowest point of each individual
structure above grade to the maximum height through all angles of tilt. Maximum
height of roof mounted systems shall be kept as close to original structure roof
lines as possible.
B. SES setbacks shall conform to the Land Use Regulations. A DGSES shall be
required to maintain a 75- (seventy-five) foot setback from any property line or
public road right-of-way.
6. Performance and Installation Standards
A. Standards for roof-mounted and ground-mounted SES: All SES and
associated wiring shall be installed in compliance with the PV systems standards
of the latest edition of the National Electric Code (NEC). The PRSES shall also
conform with the Town of Penobscot's Land Use Regulations. PRSES ground-
mounted systems are required to apply for a building permit and be approved by
the Penobscot Planning Board before construction.
B. Additional Standards for CSES and DGSES Ground-Mounted: In addition to
the standards listed in section 6.A above, CSES and DGSES shall comply with
the following:
1) The applicant for an SES permit will supply the Penobscot Planning Board
(PPB) with a construction permit application.
2) Visual and environmental buffers must be maintained at the project's
periphery and shall extend the width of the required setback, by the
preservation of native vegetation (tree and woody-shrub species) or by the
planting of native species.
3) If utilizing cleared land for proposed "meadow" based stormwater
treatment, semi-annual (spring and fall) inspection of the meadow areas
shall be performed until a meadow grass sod is established. Grading of
washouts and reseeding of eroded "meadow" areas shall be performed
according to Maine Department of Environmental Protection (ME DEP)
Best Management Practices.
October 2025 Final
6
4) Meadow stormwater treatment areas shall be managed by mowing in lieu
of herbicide treatment.
5) For safety reasons, the entire periphery of the SES shall be surrounded by
an agricultural welded wire type fence 72 (seventy-two) inches high (at a
minimum) positioned 6 (six) inches off the ground.
6) The property owner of record will be the responsible party for maintaining
and operating the SES on a parcel, unless a lease or equivalent
instrument is executed between the property owner of record and a
proposed operator of the SES. A copy of the instrument shall be submitted
to the PPB.
7) Approval of an SES application via this ordinance is conditional upon
compliance with all applicable local, state, and federal laws and
regulations, including but not limited to the Penobscot Land Use
Regulations, Maine Natural Resources Protection Act, Maine Site Location
of Development Law, Maine Stormwater Management Law, and state
statutes governing the siting of solar energy systems on agricultural lands.
(See Appendix A)
8) An SES shall not be constructed until an SES application has been
approved, or approved with conditions, by the Penobscot Planning Board,
and a building permit has been issued by the PPB.
9) Any SES site lighting shall be shielded and downcast such that light does
not spill onto an adjacent parcel or the night sky, and is Dark Sky
compliant.
10) The Planning Board may require a scenic assessment for a DGSES,
consisting of a landscaping plan indicating the proposed placement of the
facility on the site, location of existing trees and other significant site
features, and the method of fencing and vegetative buffer.
11) To the greatest practical extent, all electrical wiring and utility connections
shall be installed underground, except for transformers and controls. The
Planning Board will take into consideration prohibitive costs and site
limitations in making their determinations.
October 2025 Final
7
12) Transfer of ownership: Any approval for a DGSES is non-transferable to a
new owner or operator without written notification to the Penobscot
Planning Board. The new owner or operator shall provide documentation
to the Board acknowledging their full acceptance of all terms and
conditions of the original permit approval, including the decommissioning
plan and financial guarantee, prior to the finalization of the transfer. The
town reserves the right to review and approve the transfer of the financial
guarantee to ensure it remains valid and sufficient.
C. Additional Standards for DGSES: In addition to the standards listed in sections
6.A and 6.B above, DGSES shall comply with the following:
1) Any DGSES must maintain a minimum one-mile radius from any other
DGSES.
2) Signage on the access gate to the SES will identify the owner and list a
24-hour emergency contact phone number.
3) The SES owner will provide to the Penobscot Fire Chief a site plan,
electrical schematic of the facility, standard security measures for the
facility, an emergency response plan and the Material Safety Data Sheets
(MSDS) of the panels and any other equipment.
D. Abandonment, Decommissioning and Removal of DGSES: In addition to all
standards listed in sections 6.A, 6.B, and 6.C above, DGSES Ground Mounted
SES shall comply with the following:
1) The owner or operator of the SES shall notify the PPB by certified mail
with the date of discontinued operations, or the expiration of a lease to
operate the facility, and shall physically remove the entire SES installation
no more than 365 days from the date of discontinued operations.
2) Decommissioning and removal shall consist of the physical removal of PV
panels, array support structures, foundations to a depth of at least 4 (four)
feet below grade (or to bedrock, whichever is less), electrical switchgear,
and associated transmission lines from the site.
3) Decommissioning and removal shall also consist of off-site disposal of all
solid and liquid waste in accordance with local, state and federal
regulations.
October 2025 Final
8
4) Stabilization of the site via revegetation shall be performed and shall use
ME DEP Best Management Practices as necessary, to avoid erosion.
5) Absent a notice of decommissioning or written notice of extenuating
circumstances, a DGSES will be considered abandoned when it fails to
operate for more than one year. The PPB will notify the party responsible
by certified mail that they must remove the facility and restore the site
within one year. A copy of this notice will be sent to the Penobscot Select
Board.
6) If the owner or operator of the DGSES fails to remove the installation
within 365 days of abandonment, the town retains the right to use all
available means to cause an abandoned DGSES to be removed. All costs
thus incurred will be paid from the decommissioning bond for that purpose
held by the Town of Penobscot.
7. Site Plan Review and Application Materials
The following materials shall be submitted for evaluation of all DGSES permit
applications as part of the PPB site plan review process.
A. A site plan showing proposed system components and their dimensions, exterior
lighting, and vegetation clearing areas, stamped and certified by a State of Maine
Licensed Professional Engineer.
B. Proof of title, right, or interest, such as ownership, easement, lease, or purchase
option for the location being considered.
C. Evidence of a formal application submitted to the electrical utility for an
interconnection study. Final issuance of a building permit by the town shall be
contingent upon the applicant providing a copy of an executed Interconnection
Agreement with the utility, demonstrating that the utility has approved the
project's connection to the grid. The document shall show available extra
capacity for future use. The Planning Board may refuse an application if capacity
of equipment would limit future PRSES and CSES projects because of limited
capacity.
D. A site location map which shows the boundaries of the proposed facility, property
boundary lines, contiguous properties under total or partial control of the
applicant, any significant resources or historic sites within 1/2 (one-half) mile of
the proposed development, and any significant wildlife habitat (per ME DEP
under the Site Location of Development Law) and the ME Natural Resources
Protection Act which may be impacted.
October 2025 Final
9
E. Written confirmation that all applicable State agencies with jurisdiction over the
project have been notified of the application and the location of all system
components covered by this application.
F. A description of the proposed facility to include specifications for, and numbers
of, the solar panels, transformers, rectifiers, other components, and all
associated equipment. A listing of nominal sound levels at the SES periphery,
and an outline of emergency shutdown procedures.
G. A revegetation plan for any cleared areas.
H. A decommissioning plan that meets the requirements of Section 6 above, signed
by the party responsible for the removal of the SES and the owner of the parcel
where the SES is proposed. This plan shall be recorded in the Hancock County
Registry of Deeds prior to SES operation.
I. A Waste Stream Management Plan (including recycling percentages) for
demolition waste and debris at the SES site. This waste includes concrete, wood,
scrap metal and wire, and clearing and grading waste.
J. Documentation of abutting property owner notification by certified mail of the
application for SES. This notification by the applicant at least 15 (fifteen) days
prior to the initial PPB or CEO consideration, shall indicate the time, place, and
date of the initial consideration. If a public hearing is called by the PPB or CEO, a
notice will be posted by the town at least 15 (fifteen) days prior to the hearing,
and include the date, time, and place of the hearing.
K. The applicant will submit 7 (seven) copies of the above materials at least 10 (ten)
days in advance of a PPB meeting date when the applicant wishes to be on the
agenda.
L. The PPB will review the application packet for completeness; if incomplete, a list
of outstanding items will be sent to the applicant in a timely fashion. When
complete, the application will be preliminarily reviewed by the PPB for
compliance with the ordinance standards.
M. A final PPB review documenting any conditions of approval will take place
subsequent to the preliminary review. If approved, the application will be sent to
the CEO for the issuance of a construction permit within 60 (sixty) days.
N. The applicant shall submit the manufacturer's specification sheets, including
Material Safety Data Sheets (MSDS), for all solar panels, inverters, and major
components to be installed. The Planning Board, at its discretion and at the
applicant's expense, may require an independent, third-party inspector, approved
by the Board, to periodically verify that the materials being installed match those
specified in the application and that construction conforms to the approved site
plan.
October 2025 Final
10
8. Guarantee of Removal
At the time of approval of a proposed DGSES and prior to starting construction of a
DGSES the applicant must guarantee to cover the costs of removal of the facility.
A. The amount of the guarantee shall be equal to the estimated SES removal cost
provided by a licensed professional engineer, or an estimate provided by a
professional array construction company. These estimates are to be provided by
the applicant.
B. An updated estimate shall be provided by the applicant to the town Select Board
every 5 (five) years from the date of the permit issued, using these types of
estimate sources. If the estimated cost increases more than 15% from the
previous estimate, the facility owner shall provide additional security in the
amount of the increase within 90 days of the town's request. Failure to provide
the required additional security shall constitute a violation of this ordinance and
be grounds for the Select Board to declare the facility in default and call upon the
existing bond to secure the town's future decommissioning costs.
C. Type and contents of guarantee - Decommissioning Bond. A Decommissioning
Bond shall detail the condition of the bond, the method for release of the entire
bond or portions thereof to the Town of Penobscot, and the procedures for
collection by the Town. The bond documents shall specifically reference the SES
facility for which approval is sought.
9. Application and Permit Fees
A. SES building permit applications shall be accompanied by a permit fee as
required by the PPB.
B. If SES construction is not completed within two years of the date of issuance of
the building permit for the SES, the building permit will expire. All permits will
expire upon decommissioning.
10. Severability
This ordinance is severable; if any phrase, clause, sentence, or provision is declared to
be contrary to law, the validity of the remainder shall not be affected, unless the
application of any remaining portion of the ordinance would result in action which would
be inconsistent with the objectives of this ordinance.
October 2025 Final
11
Appendix A
Penobscot Solar Energy Ordinance
Findings of Fact
Name of applicant_______________________________________ Date______________
(eg: Motion: The Board finds as a fact that based upon the information presented by the
applicant the proposed use ............. for each of the 9 criteria below)
After the submission of a completed application to the Planning Board, the Board shall approve
an application or approve it with conditions if it makes a positive finding based on the
information presented that the proposed use:
(1) Will maintain safe and healthful conditions;
(2) Will not result in water pollution, erosion, or sedimentation to surface waters;
(3) Will adequately provide for the disposal of all wastewater;
(4) Will not have an adverse impact on spawning grounds, fish, aquatic life, bird or other wildlife
habitat;
(5) Will conserve shore cover and visual as well as actual points of access to inland and coastal
waters;
(6) Will protect archaeological and historic resources as designated in the comprehensive plan;
(7) Will not adversely affect existing commercial fishing or maritime activities in a Commercial
Fisheries/Maritime Activities District;
(8) Will avoid problems associated with floodplain development and use; and
(9) Is in conformance with the provisions of the Land Use Regulations of the Town of
Penobscot.
Final Overall Motion:
Conditions (if any):
If a permit is either denied or approved with conditions, the reasons as well as conditions shall
be stated in writing. No approval shall be granted for an application involving a structure if the
structure would be located in an unapproved subdivision or would violate any other local
ordinance, or regulation or statute administered by the municipality.