Town of Roxbury
Land Use Ordinance
Amended June 23", 2022
Be it enacted by the Town of Roxbury as follows:
Section 1. Purpose
The purpose of this Ordinance is to promote the health, safety and general welfare of the people
of the Town of Roxbury by the application of land use standards of land use. Specifically, this
Ordinance is intended:
1. To preserve from development those wetlands that have significant value in the
natural regulation of the drainage system of the region, in the recharging of
aquifers, and in the protection of wildlife;
Zi To prevent steep slopes from serious erosion that may be caused by heavy run-off
after disturbance of the vegetative cover and topsoil;
3. To prevent unsanitary conditions that may be created by development on steep
slopes.
Section 2. Applicability and Authority |
This Ordinance applies to all land areas within the Town of Roxbury except for those areas
regulated by the Town of Roxbury Shoreland Zoning Ordinance. The Mountain District shall
include all areas of the mountain ridge comprised of the portions of Record Hill located within
the Town of Roxbury, Flathead Mountain, Mine Notch, Partridge Peak, and North and South
Twin Mountains that are located at or above an elevation of fifteen hundred feet (1500 feet)
above sea level. The General District shall include all other land areas outside the Shoreland
District and the Mountain District.
This Ordinance is adopted pursuant to the provisions of Article VIII Part Second of the Maine
Constitution, and provisions of Title 30-A M.R.S.A. Section 3001.
Section 3. Effective Date
The effective date of this Ordinance is June 8, 1976, and subsequent amendments. A certified
copy of this Ordinance shall be filed with the County Register of Deeds, according to the
requirements of State law.
Section 4. Validity and Severability
Should any section or provision of this Ordinance be declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of this Ordinance.
Section 5. Amendments
This Ordinance may be amended by a majority vote of the governing body.
Section 6. Non-Conforming Uses
A. Any lawful use of building, structures, premises, land or parts thereof existing at
the effective date of this Ordinance or amendments there to and not in
conformance with the provisions of the Ordinance shall be considered to be a
non-conforming use.
B. Any non-conforming use may continue and may be maintained, repaired and
improved. No such non-conforming use may be expanded, changed to another
non-conforming use, or renewed after it has been discontinued for a period of 12
calendar months or more without a permit from the Planning Board.
C. Any non-conforming lot of record existing before the effective date of this
Ordinance and not adjoined by other land of the same ownership may be used in
accordance with State law and section 7 of this Ordinance.
Section 7. Uses
Land Uses permitted in the General District and Mountain District in conformance with the land
use standards of this Ordinance, are shown below;
Key: Yes-- Allowed (no Town or Municipal permit required)
No -- Prohibited
CEO- Requires permit issued by the Code Enforcement Officer
PB Permit -- Requires permit issued by Planning Board
* -- - Subject to specific Land Use Standards
Land Use General Mountain
District District
Non-intensive recreational uses not requiring | Yes Yes
structures, such as hunting, fishing, and hiking
Motorized vehicular traffic on roads and trails, | Yes Yes
and snowmobiling
Forest management activities except for Yes Yes
timber harvesting
Timber harvesting*
Fire Prevention activities
Wildlife management practices
Soil and water conservation practices
Mineral exploration*
Surveying and Resource analysis
Emergency operation as defined
Harvesting of wild crops
Agriculture*
Principal Structures* Ec Ls eed
Land Use General Mountain
pees [Di
Permit 1
|
|
| Small non-residential facilities for educational,
scientific or nature interpretation purposes
| Public and private parks and recreational areas
involving minimal structural development.
|
Private sewage disposal systems
| | Public Utilities, including sewage collection
|
| | Filling or other earth-moving activity of less
than 10 cubic yards
Mineral extraction
| Filling or other earth-moving activity of more | Yes Yes
ftanityads ee [YE [YS
|
Uses similar to uses requiring a CEO permit CEO CEO Permit
etna eee lem [OO
|
Wind Energy
1. This use allowed upon submission to the Planning Board of a Site Location of
Development Permit from the Maine Department of Environmental Protection. A Wind
Energy Facility that has made such a submission must abide by the terms and conditions
of the submitted Site Location of Development Permit, or such Wind Energy Facility will
be considered to be in violation of this ordinance, enforced pursuant to Section 9. A
Planning Board Permit is required for Wind Energy Facilities that do not hold a Site
Location of Development permit from the Maine Department of Environmental
Protection
Section 8. Lane Use Standards
All land use activities shall conform to the following applicable land use standards:
A. General Regulations
1. Wetlands: No wetland of more than five acres shall be filled, nor shall it be used
3
for the disposal of agricultural and nonagricultural wastes. The Town shall have
authority to regulate in the same manner the use of any smaller wetland which is,
or may become, of significant value to the community as an aquifer recharge area
| or as public open space. Wetland filling may require State and Federal permits.
For the purpose of this Ordinance, a wetland is defined as marshland or other low-
lying, level area, characterized by frequent or seasonal flooding, and a high water
table, and by soils consisting of partly decomposed organic matter intermixed
with silt, clay and sand. The extent of a wetland shall be determined by on-site
investigation.
2. Steep Slopes: No residential, commercial or industrial structure, and no road to
such a structure, shall be built on a slope of 15% or more, unless it shall be done
in accordance with plans prepared for the site by a licensed professional engineer.
Plans shall be prepared for the disposal of storm water without serious erosion of
the topsoil and roadbed and without sedimentation of any stream or other body of
water. Where applicable, detailed plans shall be prepared for the disposal of
sanitary wastes without nuisance or danger to health.
The degree of slope shall be determined by measurements at 50 foot intervals at
the location of the proposed structure or road. The Town shall designate a
surveyor to measure the slope, and may assess the owner of the land for the cost
of the survey.
os Residential Lot Standards: Lots shall meet or exceed the following minimum
requirements:
With or without Sanitary Sewers
87,120 square feet (2 Acres)
A. If more than one residential dwelling unit is constructed on a single
parcel, the minimum lot size requirement shall be met for each
additional dwelling unit.
B. Structures shall not cover more than 20% of any lot.
4, Manufactured Housing Safety Standards
The purpose of these standards is to establish a condition of safety that will
allow the mobile home to perform in a manner that will greatly reduce hazards
that present an imminent and unreasonable risk of death or serious personal
injury to its inhabitants or other residents of the park.
A. These standards shall apply to all manufactured housing built before June
15, 1976, or not built according to the National Manufactured Housing
Construction and Safety Standards Act of 1974, United States Code, Title
42, Chapter 70, to be located in a mobile home park.
1. All homes with roofs added after construction will require a
professional engineer to review the roof design to determine that the
roof and home can withstand the rigors of State of Maine winter or
wind uplifts that may occur.
2. A person holding a master license issued by the State of Maine Oil
and Solid Fuel Examining Board shall inspect and certify that the
heating and fuel system meets the requirements of NFPA-31 -
Installation of Oil Burning Equipment as adopted by that Board, or
other applicable standards here-after revised or enacted.
3. A person holding a master license issued by the State of Maine
Electricians Examining Board shall inspect and certify that the
electrical system is safe and meets the National Electrical Code in
effect at the time the home was constructed.
5. Campgrounds: Campgrounds shall conform to the minimum requirements
imposed under State licensing procedures and the following:
A. Camping areas shall contain a minimum of 5,000 square feet of suitable
land, not including roads and driveways, for each site.
6. Erosion and Sedimentation Control: Filling, grading, lagooning, dredging, earth-
moving activities, and other land use activities shall be conducted in such manner
to prevent to the minimum extent possible, erosion and sedimentation of surface
waters.
7. Mineral Exploration: Mineral exploration to determine the nature or extent of
mineral resources shall be accomplished by hand sampling, test boring, or other
methods which create minimal disturbances. A permit from the Planning Board
shall be required for mineral exploration which exceeds the above limitations.
8. Road Construction
A. Roads shall be located, constructed, and maintained in such a manner that
minimal erosion hazard results. Adequate provision shall be made to
prevent soil erosion and sedimentation of surface waters.
B. Additionally, all roads constructed shall conform with the following
standards:
1. Road crossings of watercourses shall be kept to the minimum
number necessary;
2. Bottoms of culverts shall be installed to allow for fish and wildlife
passage;
3. All cut or fill banks and areas of exposed mineral soil shall be
revegetated or otherwise stabilized as soon as possible; and
4, Bridges or culverts of adequate size and design shall be provided
for all road crossings of watercourses which are to be used when
surface waters are unfrozen.
9. Sanitary Standards: All subsurface sewage disposal systems shall be installed in
accordance with the Maine Subsurface Disposal Rules #144 CMR 241.
10. Soils: All land uses shall be located on soils in or upon which the proposed uses
or structures can be established or maintained without causing adverse
environmental impacts, including severe erosion, mass soil movement, and water
pollution, whether during or after construction.
Proposed uses requiring subsurface waste disposal, and commercial or industrial
development and other similar intensive land uses, shall require a soils report,
prepared by a State-certified soil scientist or geologist based on an on-site
investigation. Suitability considerations shall be based primarily on criteria
employed in the National Cooperative Soil Survey as modified by on-site factors
such as depth to water table and depth to refusal.
11. | *Temporary Structures:
The Planning Board is authorized to issue a permit for temporary structures and temporary uses.
Such permits shall be limited as to time and service, but shall not be permitted for more than 180
days. The Planning Board is authorized to grant extensions for demonstrated cause. Temporary
structures and uses shall meet the requirements of:
Shall apply to structures erected for a period of less than 180 days. Tents and other
membrane structures erected for a period of less than 180 days shall comply with the
International fire code. Those erected for a longer period of time shall comply with
applicable sections of this ordinance.
Temporary structures and uses shall conform to the structural strength, fire safety, means
of egress, accessibility, light, ventilation, and sanitary requirements of this code as
necessary to ensure public health, safety and general welfare.
A. Temporary structures in conjunction with construction work.
Temporary structures used in conjunction with construction work shall be
permitted only during the period that the construction work is in progress.
Permits for temporary structures shall be issued for a six (6) month period and
may be renewed by the Planning Board.
B. Temporary Structures in conjunction with Disasters:
1. Temporary structures including temporary living quarters used in
conjunction with disasters such as fire, flood, lightening, hurricanes,
and ice or snowstorms and other forces of nature shall be permitted
only during the period of restoration work is in progress.
2. Restoration work includes the repairing, rebuilding, and altering of a
premise, land or structure to a former, normal or unimpaired state or
condition including but not limited to the cleaning and removal of
debris, trash, and waste.
3. Temporary structures shall not encroach any further upon the setback
requirements of the structure destroyed. Any deviation from those
setbacks must be approved by the Code Enforcement Officer.
4. Temporary living quarters shall be connected to the existing septic
system or to an alternate system which, in either case, must comply
with the Plumbing Code and approved by the Local Plumbing
Inspector.
5. Permits for temporary structures shall be issued for a six (6) month
period and may be renewed by the Planning Board for a maximum on
one extension provided a duly authorized building and plumbing
permit has been issued for a permanent structure.
C. Exceptions: Temporary storage structures that consist of a metal frame
covered by a tarp like shell.
Section 9. Administration
A. Enforcement
After the effective date of this Ordinance, no person, firm or corporation shall erect, alter or change
the use of a building, or change the use of land, in any area subject to the regulations set forth in
this Ordinance until a permit for such action has been issued by the Town in accordance with
the requirements of Section 7 of this Ordinance. No building permit shall be issued for any
structure or use involving the construction, installation or alteration of plumbing facilities
unless a permit for such facilities has been secured by the applicant or his authorized agent,
according to the requirements of this Ordinance. The Code Enforcement Officer shall be given
free access at reasonable hours to structures or land regulated by this Ordinance. Permits shall
not be denied if the proposed use is found to be in conformance with the provisions of this
Ordinance. All permits shall either be approved or denied within 60 days of receipt of a
completed application, including all information requested. Upon complaint by Code
Enforcement Officer, a person, firm or corporation may be enjoined from the erection,
alteration, or occupation of any structure, or the use of any land, that violates these regulations.
A person, firm, or corporation which violates these regulations shall be penalized in accordance
with 30-A, M.R.S.A. section 4452. Each day during which the violation exists shall be
considered a separate offense.
B. Board of Appeals
fy There is hereby created the Board of Appeals of the Town of Roxbury pursuant to
the provisions of State Law.
2. Variances
The Board of Appeals may, upon written application of the affected landowner, grant a
variance from the strict application of the Ordinance under the following conditions;
A. The strict application of the terms of this Ordinance would result in undue
hardship to the applicant;
B. The hardship is not the result of action taken by the applicant or a prior
owner; and
C. The Board of Appeals, based on clear and convincing evidence presented
to it, makes a finding that the proposed use would meet the provisions of
this Ordinance.
A variance is authorized only for lot area, lot coverage by structures, and setbacks. A
Variance shall not be granted to permit a use or structure otherwise prohibited.
3, Appeals to Board of Appeals
The Board of Appeals may, upon written application of an aggrieved party and after
public notice, hear appeals from determinations of the Planning Board or Code
Enforcement Officer, in the administration of this Ordinance. Such hearings shall be held
in accordance with State laws. Following such hearing, the Board of Appeals may
reverse the decision of the Planning Board or Code Enforcement Officer, only upon a
finding that the decision is clearly contrary to specific provisions of this Ordinance.
Conflict with other Ordinances
This Ordinance shall not in any way impair or remove the necessity of compliance with any
other applicable rule, ordinance, regulation, bylaw, permit, or provision of law. Where this
Ordinance imposes a greater restriction upon the use of land, buildings or structures, the
provisions of this Ordinance shall control.
Section 10. Definitions
Terms not defined herein shall have the customary dictionary meaning; as used in this
Ordinance, the following definitions shall apply:
Accessory Structure: A structure of the nature customarily incidental or subordinate to
that of the principal structure or the primary use to which the premises are devoted.
Aggrieved Party: A person whose land is directly or indirectly affected by the grant or
denial of a permit or variance under this Ordinance, a person whose land abuts land for
which a permit or variance has been granted, or a group of five or more citizens of the
municipality who represent an interest adverse to the grant or denial of such permit or
variance.
Emergency Operations: Emergency operations shall include operations conducted for the
public health, safety or general welfare, such as protection of resources from immediate
destruction or loss, law enforcement, and operations to rescue human beings and
livestock from the threat of destruction or injury.
Essential Services: Gas, electrical, communication facilities, steam fuel or water supply,
transmission, or distribution systems.
Forest Management Activities: Timber cruising and other forest resource evaluation
activities, pesticide or fertilizer application, management planning activities, timber stand
improvement, pruning, regeneration of forest stands, and other similar or associated
activities, exclusive of timber harvesting and the construction, creation or maintenance of
roads.
Manufactured Housing/Mobile Home Unit: Means structures, transportable in one or two
sections, which were constructed in a manufacturing facility and are transported to a
building site and designed to be used as dwellings when connected to the required
utilities, including the plumbing, heating, air conditioning and electrical systems
contained therein and as otherwise defined in 30-A M.R.S.A.
section 4358(1).
Mineral Extraction: Any operation which within any twelve (12) successive month period
removes more than 5,000 cubic yards of soil, topsoil, loam, sand, gravel, clay, peat, or
other like material from its natural location, and to transport the product removed away
from the extraction site.
Principal Structure: The structure in which the primary use of the lot is conducted.
Residential Dwelling Unit: A room or group of rooms designed and equipped exclusively
for the use as permanent, seasonal, or temporary living quarters for only one family. The
term shall include mobile homes.
Road: A route or track consisting of a bed of exposed mineral soil, gravel, asphalt, or
other surfacing material constructed for or created by the repeated passage of motorized
vehicles.
Structure: Anything built for the support, shelter, or enclosure of persons, animals, goods,
or property of any kind.
Temporary Structure: A structure which is permitted within a land use district without
any foundation or footing and which is removed when the designated time period,
activity, or use for which the temporary structure was erected has ceased.
Timber Harvesting: The cutting and removal of timber for the primary purpose of selling
or processing forest products. The cutting or removal of trees in the shoreland zone on a
lot that has less than two (2) acres not be considered timber harvesting.
Wetland: Areas enclosed by the normal high water mark of inland waters and areas
otherwise identified on the basis of soils, vegetation, or other criteria as inland wetlands
including but not limited to swamps, marshes or bogs.
Wind Energy Facility: An electricity-generating facility consisting of more than one wind
turbine under common ownership or operating control that includes substations, MET
towers, cables/wires and other structures accessory to such facility, whose main purpose
is to supply electricity to off-site customer(s). Wind Energy Facilities are not considered
to be "Industrial Structures," as that term is used in this Ordinance.
Given under our hands this 28" day of June. s y 4
TIMOTHY DEROUCHE
--7"
hs g | _
RAY HODSDON
BOARD OF SELECTMEN
TOWN OF ROXBURY
A TRUE COPY /
Attest: | c
BRITTA RDON, Town Clerk
Ordinance Adopted: March 2", 1976
Ordinance Amended: January 15", 2009
Ordinance Amended: June 23", 2022 [Article 3]
Town of Roxbury, Maine 04275