FLOODPLAIN MANAGEMENT ORDINANCE
ARTICLE I - ESTABLISHMENT
The (Town/City) Town of Sebec, Maine elects to comply with the requirements of the
National Flood Insurance Act of 1968 (P.L. 90-488, as amended). The National Flood Insurance
Program, established in the aforesaid Act, provides that areas of the (Town/City) Town having a
special flood hazard be identified by the Federal Emergency Management Agency and that
floodplain management measures be applied in such flood hazard areas. This Ordinance
establishes a Flood Hazard Development Permit system and review procedure for development
(Town/City) Town of Sebec, Maine.
ARTICLE II - PERMIT REQUIRED
Before any construction or other development (as defined in Article XIII), including the
placement of manufactured homes, begins within any areas of special flood hazard established in
Article I, a Flood Hazard Development Permit shall be obtained from the Selectmen*. This
permit shall be in addition to any other building permits which may be required pursuant to the
codes and ordinances of the (Town/City) Town of Sebec, Maine.
ARTICLE III - APPLICATION FOR PERMIT
The application for a Flood Hazard Development Permit shall be submitted to the
Selectmen* and shall include:
A. The name and address of the applicant;
B. An address and a map indicating the location of the construction site;
C. A site plan showing the location of existing and/or proposed structures, sewage disposal
facilities, water supply facilities, areas to be cut and filled, and the dimensions of the lot;
D. A statement of the intended use of the structure;
E. A statement as to the type of sewage system proposed;
2
F. Specification of dimensions of the proposed structure;
G. The elevation in relation to Mean Sea Level, or to a locally established datum in Zone A
only, of the:
1. Base flood at the proposed site of all new or substantially improved structures,
which is determined:
a. In Zones A1-30, AE, AO, and AH from data contained in the "Flood
Insurance Study - (Town/City) of Sebec, Maine," as described in Article I;
or,
b. In Zone A, to be the elevation of the ground at the intersection of the
floodplain boundary and a line perpendicular to the shoreline which passes
along the ground through the site if the proposed building;
2. Highest and lowest grades at the site adjacent to the walls of the proposed
building;
3. Lowest floor, including basement; and whether or not such structures contain a
basement; and,
4. Level, in the case of non-residential structures only, to which the structure will be
floodproofed;
H. A description of a base flood elevation reference point established on the site of all new
or substantially improved structures;
I. A written certification by a registered Maine surveyor that the elevations shown on the
application are accurate;
J. Certification by a registered professional engineer or architect that floodproofing methods
for any non-residential structures will meet the floodproofing criteria of Article III,
paragraph G.4; Article VI, paragraph G; and other applicable standards in Article VI;
K. A description of the extent to which any water course will be altered or relocated as a
result of the proposed development; and,
L. A statement of construction plans describing in detail how each applicable development
standard in Article VI will be met.
3
ARTICLE IV - APPLICATION FEE AND EXPERT'S FEE
A non-refundable application fee of $0.00 shall be paid to the (Town/City) Town Clerk
and a copy of a receipt for the same shall accompany the application.
An additional fee may be charged if the Town has expenses they will be billed
accordingly* and/or Board of Appeals needs the assistance of a professional engineer or other
expert. The expert's fee shall be paid in full by the applicant within 10 days after the town
submits a bill to the applicant. Failure to pay the bill shall constitute a violation of the ordinance
and be grounds for the issuance of a stop work order. An expert shall not be hired by the
municipality at the expense of an applicant until the applicant has either consented to such hiring
in writing o been given an opportunity to be heard on the subject. An applicant who is
dissatisfied with a decision of the Selectmen* may appeal that decision to the Board of Appeals.
ARTICLE V - REVIEW OF FLOOD HAZARD DEVELOPMENT PERMIT
APPLICATION
The Selectmen* shall:
A. Review all applications for the Flood Hazard Development Permit to assure that proposed
building sites are reasonably safe from flooding and to determine that all pertinent
requirements of Article VI (Development Standards) have, or will be met;
B. Utilize, in the review of all Flood Hazard Development Permit application, the base flood
data contained in the "Flood Insurance Study - (Town/City) Town of Sebec, Maine" as
described in Article I. In special flood hazard areas where base flood elevation data are
not provided, the Selectmen* shall obtain, review and reasonably utilize any base flood
elevation and floodway data from federal, state or other sources, including information
obtained pursuant to Article III, paragraph G.1.b; Article VI, paragraph I; and Article
VIII, paragraph D, in order to administer Article VI of this ordinance;
C. Make interpretations of the location of boundaries of special flood hazard areas shown on
the maps described in Article I of this Ordinance;
D. In the review of Flood Hazard Development Permit applications, determine that all
necessary permits have been obtained from those federal, state, and local government
4
agencies from which prior approval is required by federal or state law, including but not
limited to Section 404 of the Federal Water Pollution Control Act Amendments of 1972,
33 U.S.C. 1334;
E. Notify adjacent municipalities, the Department of Environmental Protection, and the
Maine State Planning office prior to any alteration or relocation of a water course and
submit copies of such notifications to the Federal Emergency Management Agency;
F. Issue a two-part Flood Hazard Development Permit for elevated structures. Part I shall
authorize the applicant to build a structure to and including the first horizontal floor only
above the base flood level. At the time the applicant shall provide the Code Enforcement
Officer with an application for Part II of the Flood Hazard Development Permit and shall
include an Elevation Certificate completed by a registered Maine surveyor for
compliance with the elevation requirements of Article VI, paragraphs F, G, or H.
Following review of the application, which review shall take place within 72 hours of
receipt of the application, the Code Enforcement Officer shall issue Part II of the Flood
Hazard Development Permit. Part II shall authorize the applicant to complete the
construction project; and,
G. Maintain, as a permanent record, copies of all the Flood Hazard Development Permits
issued and data relevant thereto, including reports of the Board of Appeals on variances
granted under the provisions of Article VII of this Ordinance.
ARTICLE VI - DEVELOPMENT STANDARDS
All developments in areas of special flood hazard shall meet the following applicable
standards:
A. New construction or substantial improvement of any structure shall:
1. be designed or modified and adequately anchored to prevent floatation, collapse,
or lateral movement of the structure resulting from hydrodynamic and hydrostatic
loads, including the effects of buoyancy;
2. use construction materials that are resistant to flood damage;
3. Use construction methods and practices that will minimize flood damage; and,
5
4. Use electrical, heating, ventilation, plumbing, and air conditioning equipment, and
other service facilities that are designed and/or located so as to prevent water from
entering or accumulating within the components during conditions of flooding.
B. All new and replacement water supply systems shall be designed to minimize or
eliminate infiltration of flood waters into the systems.
C. All new and replacement sanitary sewage systems shall be designed and located to
minimize or eliminate infiltration of flood waters into the system and discharges from the
systems into flood waters.
D. On-site waste disposal systems shall be located and constructed to avoid impairment to
them or contamination from them during flooding.
E. All development shall be constructed and maintained in such a manner that no reduction
occurs in the flood carrying capacity of any water course.
F. New construction or substantial improvement of any residential structure located within:
1. Zones A1-30, AE, and AH shall have the lowest floor (including basement)
elevated to at least one foot above the base flood elevation.
2. Zones AO and AH shall have adequate drainage paths around structures on
slopes, to guide floodwaters away from the proposed structures;
3. Zone AO shall have the lowest floor (including basement) elevated above the
highest adjacent grade:
a. at least one foot higher than the depth specified in feet on the
community's Flood Insurance Rate Map; or,
b. at least three feet if no depth number is specified.
4. Zone A shall have the lowest floor (including basement) elevated to at least one
foot above the base flood elevation utilizing information obtained pursuant to
Article III, paragraph G.1.b.; Article V, paragraph B; or Article VIII, paragraph
D.
G. New construction or substantial improvement of any non-residential structure located
within:
1. Zones A1-30, AE, and AH shall have the lowest floor (including basement)
elevated to at least one foot above the base flood elevation, or together with
attendant utility and sanitary facilities shall:
6
a. be floodproofed to at least one foot above the base flood level so that
below that elevation the structure is watertight with walls substantially
impermeable to passage of water;
b.have structural components capable of resisting hydrostatic and
hydrodynamic loads and the effects of buoyancy; and,
c. be certified by a registered professional engineer or architect that the
design and methods of construction are in accordance with accepted
standards of practice for meeting the provisions of this section. Such
certification shall be provided with the application for a Flood Hazard
Development Permit, as required by Article III, paragraph J and shall
include a record of the elevation above the means sea level of the lowest
floor including basement.
2. Zones AO and AH shall have adequate drainage paths around structures on
slopes, to guide floodwaters away from the proposed structures.
3. Zone AO shall have the lowest floor (including basement) elevated above the
highest adjacent grade:
a. at least one foot higher than the depth specified in feet on the
community's Flood Insurance Rate Map; or,
b. at least three feet if no depth number is specified; or,
c. together with attendant utility and sanitary facilities be floodproofed to
meet the elevation requirements of this section and floodproofing
standards of Article VI, paragraph G.1.
4. Zone A shall have the lowest floor (including basement) elevated to at least one
foot above the base flood elevation utilizing information obtained pursuant to
Article III, paragraph G.1.b.; Article V, paragraph B; or Article VIII, paragraph
D.
H. New or substantially improved manufactured homes located within:
1. Zones A1-30, AE, or AH shall:
a. be elevated on a permanent foundation such that the lowest floor is at
least one foot above the base flood elevation; and,
7
b. be securely anchored to an adequately anchored foundation system to
resist flotation, collapse, or lateral movement. Methods of anchoring may
include, but are not limited to:
1) over-the-top ties anchored to the ground at the four corners of the
manufactured home, plus two additional ties per side at
intermediate points (manufactured homes less than 50 feet long
require one additional tie per side); or by,
2) frame ties at each corner of the home, plus five additional ties
along each side at intermediate points (manufactured home less
than 50 feet long require four additional ties per side).
3) All components of the anchoring system described in Article VI,
paragraph H.1.b. (1) (2) shall be capable of carrying a force of
4800 pounds.
2. Zones AO and AH shall have adequate drainage paths around structures on
slopes, to guide floodwaters away from the proposed structures.
3. Zones AO shall have the lowest floor (including basement) elevated above the
highest adjacent grade:
a. at least one foot higher than the depth specified in feet on the
community's Flood Insurance Rate Map; or,
b. at least three feet if no depth number is specified; and
c. meet the requirements of Article VI, paragraph H.1.(a) (b).
4. Zone A shall have the lowest floor (including basement) elevated to at least one
foot above the base flood elevation utilizing information obtained pursuant to
Article II, paragraph G.1.b.; Article V, paragraph B; or Article VIII, paragraph D.
I. Floodways:
1. In Zones A1-30 and Ae riverine areas, for which a regulatory floodway is
designated on the community's "Flood Boundary and Floodway Map,"
encroachments, including fill, new construction, substantial improvement, and
other development shall not be permitted in the floodway unless a technical
evaluation certified by a registered professional engineer is provided
8
demonstration that such encroachments will not result in any increase in flood
levels within the community during the occurrence of the base flood discharge.
2. In Zones A1-30 and AE riverine area, for which no regulatory floodway is
designated, encroachments, including fill, new construction, substantial
improvement, and other development shall not be permitted unless a technical
evaluation certified by a registered professional engineer is provided
demonstrating that the cumulative effect of the proposed development, when
combined with all other existing development and anticipated development:
a. will not increase the water surface elevation of the base flood more than
one foot at any point within the community; and,
b. is consistent with the technical criteria contained in Section 2-7 entitles
"Hydraulic Analyses," Flood Insurance Study - Guidelines and
Specifications for Study Contractors, (FEMA 37/September, 1985, as
amended).
3. In Zone A riverine areas, in which the regulatory floodway is determined to be the
channel of the river or other water course and the adjacent land areas to a distance
of one-half the width of the floodplain as measured from the normal high water
mark to the upland limit if the floodplain, encroachments, including fill, new
construction, substantial improvement, and other development shall not be
permitted unless a technical evaluation certified by a registered professional
engineer is provided meeting the requirements of Article VI, paragraph I.2.
J. New construction or substantial improvement of any structure in Zones A1-30, AE, AO,
AH and A that meets the development standards of Article VI, including the elevation
requirements of Article VI, paragraphs F, G, or H and is elevated on posts, columns,
piers, piles, "stilts," or crawlspaces less than three feet in height may be enclosed below
the elevation requirements provided all the following criteria are met or exceeded:
1. Walls, with the exception of crawlspaces less than three feet in height, shall not be
part of the structural support of the building; and,
2. Enclosed area are not "basements" as defined in Article XIII; and,
9
3. Enclosed areas shall be designed to automatically equalize hydrostatic flood
forces on exterior walls by allowing for the entry and exit of floodwaters. Designs
for meeting this requirement must either:
a. be certified by a registered professional engineer or architect; or,
b. meet or exceed the following minimum criteria:
1) a minimum of two openings having a total net area of not less than
one square inch for every square foot of the enclosed area;
2) the bottom of all openings shall be no higher than one foot above
the lowest grade; and,
3) openings may be equipped with screens, louvers, valves, or other
coverings or devices provided that they permit the entry and exit of
flood waters automatically without any external influence or
control such as human intervention, including the use of electrical
and other non-automatic mechanical mean; and,
4. The enclosed area shall not be used for human habitation; and,
5. The enclosed area may be used for building maintenance, access, parking
vehicles, or storing of articles and equipment used for maintenance of the
building.
ARTICLE VII - CERTIFICATE OF COMPLIANCE
No land in a special flood hazard area shall be occupied or used and no structure which is
constructed or substantially improved shall be occupied until a Certificate of Compliance is
issued by the Code Enforcement Officer subject to the following provisions:
A. The applicant shall submit an Elevation Certificate completed by:
1. a registered Maine surveyor for compliance with Article VI, paragraphs F, G, or
H; and,
2. a registered professional engineer or architect, in the case of floodproofed non-
residential structures, for compliance with Article VI, paragraph G.
B. The application for a Certificate of Compliance shall be submitted by the applicant in
writing along with a completed Elevation Certificate to the Code Enforcement Officer.
10
C. The Code Enforcement Officer shall review the application within 10 working days of
receipt of the application and shall issue a Certificate of Compliance, provided the
building conforms with the provisions of this Ordinance.
ARTICLE VIII - REVIEW OF SUBDIVISION AND DEVELOPMENT PROPOSALS
The Planning Board shall, when reviewing subdivisions and other proposed
developments that require review under other federal law, state law or local ordinances or
regulations and all projects on 5 or more acres, or in the case of manufactured home parks
divided in to two or more lots, assure that:
A. All such proposals are consistent with the need to minimize flood damage.
B. All public utilities and facilities, such as sewer, gas, electrical and water systems are
located and constructed to minimize or eliminate flood damages.
C. Adequate drainage is provided so as to reduce exposure to flood hazards.
D. All proposals include base flood elevation and, in a riverine floodplain, floodway data.
E. Any proposed development plan shall include a statement that the developer will require
that structures on lots in the development be constructed in accordance with Article VI of
this ordinance and that such requirement will be included in the any deed, lease, purchase
and sale agreement, or document transferring or expressing an intent to transfer any
interest in real estate or structure, including but not limited to a time share interest. The
statement shall clearly articulate that the municipality may enforce any violation of the
construction requirement and that fact shall also be included in the deed on any other
document previously described. The construction shall also be clearly stated on any map,
plat, or plan to be signed by the Planning Board or local reviewing authority as part of the
approval process.
ARTICLE IX - APPEALS AND VARIANCES
The Board of Appeals of the (Town/City) Town of Sebec may, upon written application
of an aggrieved party, hear and decide appeals from determinations of the Code Enforcement
11
Officer* in administration of the provisions of this Ordinance. The Board of Appeals may grant a
variance from the requirements of this Ordinance consistent with state law and the following
criteria:
A. Variances shall not be granted within any designated regulatory floodway if any increase
in flood levels during the base flood discharge would result.
B. Variances shall be granted only upon:
1. a showing of good and sufficient cause: and,
2. a determination that should a flood comparable to the base flood occur, the
granting of a variance will not result in increased flood heights, additional threats
to public safety, public expense, or create nuisances, cause fraud or victimization
of the public or conflict with existing local laws and ordinances; and,
3. a showing that the existence of the variance will not cause a conflict with other
state, federal or local laws or ordinances; and,
4. a determination that failure to grant the variance would result in "undue
hardship," which in this subsection means:
a. that the land in question cannot yield a reasonable return unless a variance
is granted; and,
b. that the need for a variance is due to the unique circumstances of the
property and not to the general conditions in the neighborhood; and,
c. that the granting of a variance will not alter the essential character or the
locality; and,
d. that the hardship is not the result of action taken by the applicant or a
prior owner.
C. Variances shall only be issued upon determination that the variance is the minimum
necessary, considering the flood hazard, to afford relief.
D. Variances may be issued by a community for new construction, substantial
improvements, or other development for the conduct of a functionally dependent use
provided that:
1. other criteria of Article IX and Article VI-I are met; and,
2. the structure or other development is protected by methods that minimize flood
damages during the base flood and create no additional threats to public safety.
12
E. Variances may be issued by a community for the reconstruction, rehabilitation, or
restoration of structures listed on the National Register of Historic Places or a State
Inventory of Historic Places, without regard to the procedures set forth in Article IX,
paragraphs A through D.
F. Any applicant who meets the criteria of Article IX, paragraphs A through E shall be
notified by the Board of Appeals in writing over the signature of the Chairman of the
Board of Appeals that:
1. the issuance of a variance to construct a structure below the base flood level will
result in greatly increased premium rates for flood insurance up to amounts as
high as $25 per $100 of insurance coverage;
2. such construction below the base flood level increases risks to life and property;
and,
3. the applicant agrees in writing that the applicant is fully aware of all the risks
inherent in the use of land subject to flooding, assumes those risks and agrees to
indemnify and defend the municipality against any claims filed against it that are
related to the applicant's decision to use land located in a floodplain and that the
applicant individually releases the municipality from any claims the applicant
may have against the municipality that are related to the use of land located in a
floodplain.
G. The Board of Appeals shall submit to the Code Enforcement Officer* a report of all
variance actions, including justification for the granting of the variance and an
authorization for the Code Enforcement Officer* to issue a Flood Hazard Development
Permit, which includes any conditions to be attached to said permit.
ARTICLE X - ENFORCEMENT AND PENALTIES
A. It shall be the duty of the Code Enforcement Officer to enforce the provisions of this
Ordinance pursuant to 30 MRSA § 4966.
B. The penalties contained in 30 MRSA § 4966 shall apply to any violation of this
ordinance.
13
C. In addition to any other actions, the Code Enforcement Officer, upon determination that a
violation exits, shall submit a declaration to the Administrator of the Federal Insurance
Administration requesting a denial of flood insurance. The valid declaration shall consist
of:
1. the name of the property owner and address or legal description of the property
sufficient to confirm its identity or location;
2. a clear and unequivocal declaration that the property is in violation of a cited state
or local law, regulation, or ordinance;
3. a clear statement that the public body making the declaration has authority to do
so and a citation to that authority;
4. evidence that the property owner has been provided notice of the violation and the
prospective denial of insurance; and,
5. a clear statement that the declaration is being submitted pursuant to Section 1316
of the National Flood Insurance Act of 1968, as amended.
AERTICLE XI - VALIDITY AND SEVERABLITIY
If any section or provision of this Ordinance is declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of this Ordinance.
ARTICLE XII - CONFLICT WITH OTHER ORDINANCES
This Ordinance shall not in any way impair or remove the necessity of compliance with
any other applicable rule, ordinance, regulation, bylaw, permit, or provision of law. Where this
Ordinance imposes a greater restriction upon the use of land, buildings, or structures, the
provisions of this Ordinance shall control.
ARTICLE XIII - DEFINITIONS
Unless specifically defined below, words and phrases used in this Ordinance shall have
the same meaning as they have at common law and to give this Ordinance its most reasonable
14
application. Words used in the present tense include the future, the singular number includes the
plural, and the plural number includes the singular. The word "may" is permissive; "shall" is
mandatory and not discretionary.
1. "Adjacent Grade" - means the natural elevation of the ground surface prior to
construction next to the proposed walls of a structure.
2. "Area of Shallow Flooding" - means a designated AO and AH zone on a
community's Flood Insurance Rate Map (FIRM) with a one percent or greater
annual chance of flooding to an average depth of one to three feet where a clearly
defined channel does not exist, where the path of flooding is unprecedented, and
where velocity flow may be evident. Such flooding is characterized by ponding or
sheet flow.
3. "Area of Special Flood Hazard" - means the land in the floodplain having a one
percent or greater chance of flooding in any given year, as specifically identified
in the Flood Insurance Study cited in Article I of this Ordinance.
4. "Base Flood" - means the flood having a one percent chance of being equaled or
exceeded in any given year, commonly called the 100-year flood.
5. "Basement" - means any area of the building having its floor subgrade (below
ground level) on all sides.
6. "Building" - see "structure."
7. "Certificate of Compliance" - A document signed by the Code Enforcement
Officer stating that a structure is in compliance with all of the provisions of this
Ordinance.
8. "Code Enforcement Officer" - any person or board responsible for performing the
inspection, licensing, and enforcement duties required by a particular statute or
ordinance.
9. "Development" - means any change caused by individuals or entitles to improved
or unimproved real estate, including but not limited to the construction of
buildings or other structures; the construction of additions or substantial
improvements to buildings or other structures; mining, dredging, fillings, grading,
paving, excavation, or drilling operations; and the storage, deposition, or
15
extraction of materials, public or private sewage disposal systems or water supply
facilities.
10. "Elevated Building" - means a non-basement building (i) built, in the case of a
building in Zones A1-30, AE, A, A99, AO, AH, B, C, X, or D, to have the top of
the elevated floor, elevated above the ground level by means of piling, columns,
posts, piers, or "stilts;" an (ii) adequately anchored so as not to impair the
structural integrity of the building during a flood of up to one foot above the
magnitude of the base flood. In case of Zones A1-30, AE, A, A99, AO, AH, B, C,
X, or D, "elevated building" also includes a building elevated by means of fill or
solid foundation perimeter walls less than three feet in height with openings
sufficient to facilitate the unimpeded movement of flood waters.
11. "Elevation Certificate" - An official form (FEMA Form 81-31, Sep 83, as
amended) that (i) is used to verify compliance with the floodplain management
regulations of the National Flood Insurance Program; and (ii) is required as a
condition for purchasing flood insurance.
12. "Flood" or Flooding" - means:
a) A general and temporary condition of partial or complete inundation of
normally dry land areas from:
1)
The overflow of inland or tidal waters.
2)
The unusual and rapid accumulation or runoff of surface
waters from any source.
b) The collapse or subsidence of land along the shore of a lake or other body
of water as a result of erosion or undermining caused by waves or currents
of water exceeding anticipated cyclical levels or suddenly caused by an
unusually high water level in a natural body of water, accompanied by a
severe storm, or by an unanticipated force or nature, such as flash flood or
an abnormal tidal surge, or by some similarly unusual and unforeseeable
event which results in flooding as defined in paragraph (a) (1) of this
definition.
16
13. "Flood Elevation Study" - means an examination, evaluation and determination
of flood hazards and, if appropriate, corresponding water surface elevations.
14. "Flood Insurance Rate Map" (FIRM) - means an official map of a community, on
which the Administrator of the Federal Insurance Administration has delineated
both the special hazard areas and the risk premium zones applicable to the
community.
15. "Flood Insurance Study" see "Flood Elevation Study."
16. "Floodplain" or "Flood-prone Area" - means any land area susceptible to being
inundated by water from any source (see definition of "flooding").
17. "Floodplain Management" - means the operation of an overall program of
corrective and preventative measures for reducing flood damage, including but
not limited to emergency preparedness plans, flood control works, and floodplain
management regulations.
18. "Floodplain Management Regulation" - means zoning ordinances, subdivision
regulations, building codes, health regulations, special purpose ordinances (such
as a floodplain ordinance, grading ordinance, and erosion control ordinance) and
other applications of police power. The term describes such state or local
regulations, in any combination thereof, which provide standards for the purpose
of flood damage prevention and reduction.
19. "Flood Proofing" - means any combination of structural and non-structural
additions, changes, or adjustments to structures which reduce or eliminate flood
damage to real estate or improved real property, water and sanitary facilities,
structures and their contents.
20. "Floodway" - "see Regulatory Floodway"
21. "Floodway Encroachment Lines" - mean the lines marking the limits of
floodways on federal, state, and local floodplain maps.
22. "Freeboard" - means a factor of safety usually expressed in feet above a flood
level for purposes of floodplain management. "Freeboard" tends to compensate
for the many unknown factors, such as wave action, bridge openings, and the
hydrological effect of urbanization of the watershed, that could contribute to flood
17
heights greater than the height calculated for a selected size flood and floodway
conditions.
23. "Functionally Dependent Use" - means a use which cannot perform its intended
purpose unless it is located or carried out in close proximity to water. The term
includes only docking facilities, port facilities that are necessary for the loading
and unloading of cargo or passengers, and ship building and ship repair facilities,
but does not include long-term storage or related manufacturing facilities.
24. "Locally Established Datum" - means, for purposes of this ordinance, an
elevation established for a specific site to which all other elevations at the site are
referenced. This elevation is generally not referenced to the National Geodetic
Vertical Datum (NGVD) or any other established datum and is used in areas
where Mean Sea Level data is too far from a specific site to be practically used.
25. "Lowest Floor" - means the lowest floor of the lowest enclosed area (including
basement). An unfinished or flood resistant enclosure, usable solely for parking of
vehicles, building access, or storage in an area other than a basement area that is
not considered a building's lowest floor provided that such enclosure is not built
so as to render the structure in violation of the applicable non-elevation design
requirements Article VI of this ordinance.
26. "Manufactured Home" - means a structure, transportable in one or more sections,
which is built on a permanent chassis and is designed for use with or without a
permanent foundation when connected to the required utilities. For floodplain
management purposes the term "manufactured home" also includes park trailers,
travel trailers, and other similar vehicles placed on site for greater than 180
consecutive days.
27. "Manufactured Home Park or Subdivision" - means a parcel (or contiguous
parcels) of land divided in to two or more manufactured home lots for rent or sale.
28. "Mean Sea Level" - means, for purposes of the National Flood Insurance
Program, The National Geodetic Vertical Datum (NGVD) of 1929 or other
datum, to which base flood elevations shown on a community's Flood Insurance
Rate map are referenced.
18
29. "New Construction" - means structures for which the "start of construction"
commenced on or after the effective date of floodplain management regulations
adopted by a community.
30. "100-year flood" see "Base Flood."
31. "Regulatory Floodway" - (i) means the channel of a river or other water course
and the adjacent land area that must be reserved in order to discharged the base
flood without cumulatively increasing the water surface elevation more than one
foot, and (ii) in Zone A is considered to be the channel of a river or other water
course and the adjacent land areas of a distance of one-half the width of the
floodplain as measured from the normal high water mark to the upland limit of the
flood plain.
32. "Riverine" - means relating to, formed by, or resembling a river (including
tributaries), stream, brook, etc.
33. "Start of Construction" - means the date the building permit was issued, provided
the actual start of construction, repair, reconstruction, placement, substantial
improvement or other improvement was within 180 days of the permit date. The
actual start means either the first placement of permanent construction of a
structure on a site, such as the pouring of slab or footings, the installation of piles,
the construction of columns, or any work beyond the stage of excavation; or the
or the placement of a manufactured home on a foundation. Permanent
construction does not include land preparation, such as clearing, grading and
filling; nor does it include the installation of streets and/or walkways; nor does it
include excavation for basement, footings, piers, or foundations or the erection of
temporary forms; nor does it include the installation on the property of accessory
buildings, such as garage or sheds not occupied as dwelling units or not part of the
main structure.
34. "Structure" - means, for floodplain management purposes, a walled and roofed
building. A gas or liquid storage tank that is principally above ground is also a
structure.
35. "Substantial Improvement" - means any repair, reconstruction, or improvement
of a structure, the value of which equals or exceeds 50% of the market value of
19
the structure either before the improvement or repair is started or, if the structure
has been damaged and is being restored, before the damage occurred For purposes
of this definition "substantial improvement" is considered to occur at the time of
the first alteration of any wall, ceiling, floor, floor, or structural part of the
building commences, whether or not that alteration affects the external
dimensions of the structure. The term does not, however, include either (1) any
project for improvement of a structure to comply with existing state or local
health, sanitary, or safety code specifications which are solely necessary to assure
safe living conditions or (2) any alteration of a structure listed on the national
register of Historic Places or a State Inventory of Historic Places.
36. "Variance" - means a grant of relief by a community from the terms of a
floodplain management regulation.
37. "Violation" - means the failure of a structure or other development to dully
comply with a community's floodplain management regulations or ordinance.
ARTICLE XIV - ABROGATION
This ordinance repeals and replaces any municipal ordinance previously enacted to
comply with the National Flood Insurance Act of 1968 (P.L. 90-488, as amended).
60.3©