SOUTH PORTLAND CODE
Table of Contents
SUBDIVISIONS
ARTICLE I. IN GENERAL
1
Sec. 24-1. Title.
1
Sec. 24-2. Authority.
1
Sec. 24-3. Definitions.
1
Sec. 24-4. Standards.
5
Sec. 24-4.1.
Off-site public improvements.
8
Sec. 24-5. Fee schedule.
9
Sec. 24-6. Applicability date of amendments evidenced by Ordinance #4-20/21.
10
Secs. 24-7. Reserved.
10
ARTICLE II. PLANS
1
DIVISION 1. PREAPPLICATION
1
Sec. 24-8. Preapplication.
1
Sec. 24-9. Reserved.
1
DIVISION 2. MINOR SUBDIVISION
1
Sec. 24-10.
General.
1
Sec. 24-11.
Procedure.
2
Sec. 24-12.
Submissions.
2
Sec. 24-13.
Additional Requirements for Minor Subdivision Applications.
7
Secs. 24-14--24-16. Reserved.
7
DIVISION 3. MAJOR SUBDIVISION--PRELIMINARY PLAN
7
Sec. 24-17.
Procedure.
7
Sec. 24-18.
Submissions.
8
Sec. 24-19.
Preliminary plan requirements.
9
Secs. 24-20--24-23. Reserved.
11
DIVISION 4. MAJOR SUBDIVISION--FINAL PLAN
12
Sec. 24-24.
Procedure.
12
Sec. 24-25.
Submissions.
14
Sec. 24-26.
Final approval and filing.
17
SOUTH PORTLAND CODE
Sec. 24-27.
Plan revisions after approval.
17
Sec. 24-28.
Inspection and required improvements.
21
Sec. 24-29.
Public acceptance of streets, recreation areas.
24
Sec. 24-30.
Improvement completion time.
24
Secs. 24-31--24-34. Reserved.
24
ARTICLE III. ENFORCEMENT
1
Sec. 24-35.
Procedure.
1
Secs. 24-36.
Enforcement Officer.
2
Secs. 24-37. Reserved.
2
ARTICLE IV. GENERAL REQUIREMENTS OF ALL SUBDIVISIONS
1
Sec. 24-38.
General requirements.
1
Secs. 24-39, 24-40. Reserved.
5
ARTICLE V. DESIGN AND CONSTRUCTION STANDARDS
1
Sec. 24-41.
Streets (General).
1
Sec. 24-42.
Street standards.
1
Sec. 24-43.
Storm drainage design and construction standards.
2
Sec. 24-44.
Sanitary sewer design and construction standards.
3
Sec. 24-45
Alteration of Freshwater Wetlands
5
Secs. 24-46--24-49. Reserved.
5
ARTICLE VI. GENERAL CONSTRUCTION REQUIREMENTS
1
Sec. 24-50.
General construction requirements.
1
Secs. 24-51, 24-52. Reserved.
2
ARTICLE VII. MONUMENTS
1
Sec. 24-53.
Monuments.
1
Secs. 24-54, 24-55. Reserved.
1
ARTICLE VIII. VARIANCES AND WAIVERS; ACCEPTANCE OF STREETS
1
Sec. 24-56.
Variances and waivers.
1
Sec. 24-57.
Public interest governs acceptance of streets.
1
Sec. 24-58. Modification of local street standards - stormwater management.
1
Sec. 24-59.
Reserved.
3
SOUTH PORTLAND CODE
ARTICLE IX. NONRESIDENTIAL SUBDIVISIONS
1
Sec. 24-60.
Procedure and standards.
1
Sec. 24-61.
Vehicular access and traffic.
1
Secs. 24-62--24-65. Reserved.
1
ARTICLE X. PERFORMANCE GUARANTEE OR BOND AND RELEASE OF GUARANTEE
1
Sec. 24-66.
Performance guarantees required.
1
Sec. 24-67.
Form, amount and duration of performance guarantee.
1
Sec. 24-68.
Release of performance guarantee.
2
Secs. 24-69--24-72. Reserved.
2
ARTICLE XI. APPEALS
1
Sec. 24-73.
Appeals.
1
ARTICLE XII. SEPARABILITY AND EFFECTIVE DATE
1
Sec. 24-74.
Separability and effective date.
1
ARTICLE XIII. FORMS
1
Sec. 24-75.
Performance bond--Surety company.
1
Sec. 24-76.
Performance bond--Secured by deposit.
2
Sec. 24-77.
Performance guarantee--Irrevocable letter of credit.
3
SOUTH PORTLAND CODE
SOUTH PORTLAND CODE
SOUTH PORTLAND CODE OF ORDINANCES
Chapter 24
SUBDIVISIONS*
----------
* Editor's note--As currently set out Ch. 24 is derived from Ord. No. 8-75, adopted April 7, 1975. Said ordinance is included herein as enacted, including
arrangement, article and section designations and titles and numbering.
Prior to the enactment of Ord. No. 8-75, Ch. 24 was derived from Code 1966: Ord. No. 6-71, adopted June 7, 1971; Ord. No. 7-74, adopted May 20, 1974: and
Ord. No. 13-74, adopted June 17, 1974.
----------
Art. I. In General, §§ 24-1--24-7
Art. II. Plans, §§ 24-8--24-34
Div. 1. Preapplication, §§ 24-8, 24-9
Div. 2. Minor Subdivision, §§ 24-10--24-16
Div. 3. Major Subdivision--Preliminary Plan, §§ 24-17--24-23
Div. 4. Major Subdivision--Final Plan, §§ 24-24--24-34
Art. III. Enforcement, §§ 24-35--24-37
Art. IV. General Requirements, §§ 24-38--24-40
Art. V. Design and Construction Standards, §§ 24-41--24-49
Art. VI. General Construction Requirements, §§ 24-50--24-52
Art. VII. Monuments, §§ 24-53--24-55
Art. VIII. Variances and Waivers, §§ 24-56--24-59
Art. IX. Nonresidential Subdivisions, §§ 24-60--24-65
Art. X. Performance Guarantee or Bond and Release of Guarantee, §§ 24-66--24-72
Art. XI. Appeals, § 24-73
Art. XII. Separability and Effective Date, § 24-74
Art. XIII. Forms, §§ 24-75--24-77
SOUTH PORTLAND CODE
SOUTH PORTLAND CODE
ARTICLE I. IN GENERAL
Sec. 24-1.
Title.
This chapter shall be cited as the "Subdivision Control Ordinance"
or the "Ordinance Governing the Subdivision of Land."
(Ord. No. 8-75, 4-7-75)
Sec. 24-2.
Authority.
This chapter is enacted under the authority granted to the city by
the statutes of the State of Maine.
(Ord. No. 8-75, 4-7-75)
Sec. 24-3.
Definitions.
As used in this chapter, the following words and phrases shall
have the meanings ascribed to them in this section:
Archaeological resource. A site with established or potential
value as a location of prehistoric or historic archaeological
significance as recognized by the City Council and contained in the
South Portland Inventory of Archeological and Historic Resources.
Coastal wetlands. All tidal and subtidal lands; all areas with
vegetation present that is tolerant of salt water and occurs primarily
in a salt water or estuarine habitat; and any swamp, marsh, bog, beach,
flat or other contiguous lowland that is subject to tidal action during
the highest tide level for the year in which the activity is proposed as
identified in tide tables published by the National Ocean Service.
Coastal wetlands may include portions of coastal sand dunes.
Comprehensive plan. Any part or element of the overall plan or
policy for development of the city as defined in Title 30 M.R.S.A.
Section 4961.
Construction
drawings
means
drawings
showing
the
location,
profile, grades, size and type of drains, sewers, water mains,
underground fire alarm ducts, underground power ducts and underground
1
SOUTH PORTLAND CODE
telephone ducts, pavements, cross section of streets, miscellaneous
structures, drainage, easements, etc.
Diameter at breast height (DBH). The diameter of a standing tree
measured 4.5 feet from ground level.
Easement. The authorization of the property owner for the use by
another, and for a specified purpose, of any designated part of their
property.
Freshwater wetland. Freshwater swamps, marshes, bogs and similar
areas that are not considered part of a great pond, coastal wetland,
river, stream, or brook and that are inundated or saturated by surface
water or groundwater at a frequency and for a duration sufficient to
support, and which under normal circumstances do support, a prevalence
of wetland vegetation typically adapted to life in saturated soils.
Freshwater wetland of special significance - A freshwater
wetland meeting one or more of the following:
-
is located within two hundred fifty (250) feet (measured
horizontally) of a coastal wetland;
-
is located within two hundred fifty (250) feet (measured
horizontally) of the normal highwater line, and within the same
watershed, of any pond classified GPA [a State water quality
classification related to Great Ponds, of which there are none in
South Portland];
-
contains, under normal circumstances, at least twenty
thousand (20,000) square feet of aquatic vegetation, emergent marsh
vegetation, or open water;
-
is a floodplain wetland that is inundated during a 100 year
storm event as evidenced by the Federal Emergency Management Agency
(FEMA) maps or other site specific information;
-
contains significant wildlife habitat that has been mapped,
identified, or defined by the Maine Department of Inland Fisheries
and
Wildlife
in
accordance
with
the
state
Natural
Resources
Protection Act at the time of the filing of an application;
-
is identified as a peatland dominated by shrubs, sedges,
and sphagnum moss; or
-
contains a natural community that is critically imperiled
(S1) or imperiled (S2) as defined by the Maine Natural Areas Program.
2
SOUTH PORTLAND CODE
Engineer. Professional engineer licensed by the State of Maine.
Final
subdivision
plan.
The
final
drawings
on
which
the
subdivider's plan of subdivision is presented to the planning board for
approval and which, if approved, may be filed for record with the city
clerk and county registry of deeds.
Historic resource. A building, structure, site, or object with
established historic significance as recognized by the City Council
and contained in the South Portland Inventory of Archaeological and
Historic Resources.
Hydric soil - A soil that formed under conditions of saturation,
flooding, or ponding long enough during the growing season to develop
anaerobic conditions in the upper part.
Land subdivisions. A subdivision shall be defined in accordance
with the laws of the State of Maine.
Legislative body. City council.
Official
submittal
date.
The
time
of
submission
of
a
preapplication plan, final plan for minor subdivision, preliminary plan
for major subdivision or final plan for major subdivision shall be
considered the submission date of the application for such plan
approval to the board, complete and accompanied by any required fee and
all data required by these standards. At such time as the planning
board determines that it has before it a completed application it shall
notify the applicant in writing of the official submittal date.
Preliminary subdivision plan. The preliminary drawings indicating
the proposed layout of the subdivision to be submitted to the planning
board for its consideration.
Professional Wetland Scientist - Based on directly related
graduate-level education and on extensive directly related work
experience, a knowledgeable professional experienced in wetland
science.
Project Disturbance Area. The area of the site impacted by the
project in a manner such that vegetated areas are disturbed or
removed. The Project Disturbance Area shall include all proposed
structures, and site improvements, as well as areas disturbed for
construction staging and operations.
Significant wildlife habitat. Any area that is identified as
significant wildlife habitat in accordance with the state's Natural
Resources Protection Act.
3
SOUTH PORTLAND CODE
South Portland Street Design Manual. The most recent edition of
the manual kept on file with the City Clerk and the Department of
Public Works that sets forth street types, user priorities, street
zone widths, and specific street design elements to us in the City's
public streets, which manual is adopted by, and may be amended by,
the Director of Public Works, in consultation with the
Sustainability, Water Resource Protection, and Planning and
Development Departments.
Street. A publicly dedicated way accepted by the city or, if not
accepted, approved by the planning board with the proposed improvements
conditioned by a performance bond in accord with section 24-24 of the
subdivision ordinance.
Subdivider. Assessed owner or owners of land to be subdivided.
Subdivider's agent. That person who has written authorization to
act for the assessed owner or owners of land to be subdivided.
Subdivision, major. Any subdivision containing more than four (4)
lots, or any subdivision requiring any new street extension, or the
extension of municipal facilities; provided, however, the planning
board may reclassify a proposal as a minor subdivision if such
reclassification will not be inconsistent with the purposes of this
ordinance to protect the public's interest; provided, further, that no
proposed subdivision containing more than six (6) parcels of land, six
(6) buildings, or ten (10) dwellings may be eligible for such
reclassification.
Subdivision, minor. A subdivision containing not more than four
(4) lots and not otherwise qualifying for definition as a major
subdivision.
Upland buffer - A vegetated strip of land adjacent to a coastal
or freshwater wetland or other waterbody that is intended to protect
the wetland or waterbody by filtering sediments and absorbing
nutrients and to provide wildlife habitat and wildlife travel
corridors.
Vernal pool. A natural, temporary to semi-permanent body of
water occurring in a shallow depression that typically fills during
the spring or fall and may dry during the summer. Vernal pools have
no permanent inlet or outlet and no viable populations of predatory
fish. A vernal pool may provide the primary breeding habitat for wood
frogs (Rana sylvatica), spotted salamanders (Ambystoma maculatum),
blue-spotted salamanders (Ambystoma laterale), and fairy shrimp as
4
SOUTH PORTLAND CODE
well as valuable habitat for other plants and wildlife, including
several rare, threatened, and endangered species.
Vernal pool, significant. A vernal pool that is defined as
significant in accordance with the state's Natural Resources
Protection Act determined by the number and type of pool-breeding
amphibian egg masses in a pool, or the presence of fairy shrimp
(Eubranchipusspp.) or use of the pool by threatened or endangered
species.
(Ord. No. 8-75, 4-7-75; Ord. No. 7-83/84, 9-19-83, Ord. No. 3-01/02, 9/5/01 [Fiscal Note: Less than
$1000]; Ord. No. 10-07/08, 3/17/08 [Fiscal Note: Less than $1000]; Ord No. 3-14/15, 7/7/14 [Fiscal
Note: Less than $1000]; Ord. No. 4-20/21, 10/6/2020 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24,
4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-4.
Standards.
When reviewing any subdivision for approval, the Planning Board
shall consider the following criteria, and before granting approval,
shall determine that:
(a) The proposed subdivision will not result in undue water or air
pollution. In making this determination it shall at least
consider: 1) the elevation of the land above sea level and its
relation to the floodplains; 2) the nature of soils and subsoils
and their ability to adequately support waste disposal; 3) the
slope of the land and its effect on effluents; 4) the availability
of streams for disposal of effluents; and 5) the applicable state
and local health and water resources regulations;
(b) The proposed subdivision has sufficient water available for the
reasonably foreseeable needs of the subdivision;
(c) The proposed subdivision will not cause an unreasonable burden on
an existing water supply, if one is to be used;
(d) The proposed subdivision will not cause unreasonable soil erosion
or reduction in the land's capacity to hold water so that a
dangerous or unhealthy condition may result;
(e) The proposed subdivision will not cause unreasonable highway or
public road congestion or unsafe conditions with respect to use of
the highways or public roads existing or proposed;
5
SOUTH PORTLAND CODE
(f) The proposed subdivision will provide for adequate sewage waste
disposal and will not cause an unreasonable burden on municipal
services if they are utilized;
(g) The proposed subdivision will not cause an unreasonable burden on
the ability of the municipality to dispose of solid waste, if
municipal services are to be utilized;
(h) The proposed subdivision will not have an undue adverse effect on
the scenic or natural beauty of the area, aesthetics, historic
sites, significant wildlife habitat identified by the Maine
Department of Inland Fisheries and Wildlife or the municipality,
or rare and irreplaceable natural areas including the undue loss
of trees and open space, or any public rights for physical or
visual access to the shoreline;
(i) The proposed subdivision is in conformance with this ordinance,
other applicable ordinances and regulations and the city's
comprehensive plan;
(j) The subdivider has adequate financial and technical capacity to
meet the standards of this section;
(k) Whenever situated, in whole or in part, within the watershed of
any pond or lake, or within two hundred fifty (250) feet of any
wetland, great pond or river as defined in Title 38, chapter 3,
subchapter I, article 2-B, the proposed subdivision will not
adversely effect the quality of such body of water or unreasonably
effect the shoreline of such body of water, and shall avoid or
minimize to the extent feasible tree removal;
(l) The proposed subdivision will not, alone or in conjunction with
existing activities, adversely affect the quality or quantity of
ground water;
(m) If the subdivision, or any part of it, is in a flood-prone area
based on the Federal Emergency Management Agency's Flood Boundary
and Floodway Maps and Flood Insurance Rate Maps, and information
presented by the applicant as to whether the subdivision is in a
flood-prone area, the subdivider shall determine the 100-year
flood
elevation
and
flood
hazard
boundaries
within
the
subdivision.
The proposed subdivision plan must include a
condition of plan approval requiring that principal structures in
the subdivision will be constructed with their lowest floor,
including the basement, at least one foot above the 100-year flood
elevation;
(n) The proposed subdivision will be carried out so that:
6
SOUTH PORTLAND CODE
(1) The alteration of any freshwater wetlands on the property
will be avoided to the extent feasible considering cost,
existing technology and logistics based upon the overall
purpose of the project and the physical and natural
features of the site;
(2) The area of freshwater wetlands that is altered will be
limited to the minimum amount necessary;
(3) A twenty-five foot wide naturally vegetated buffer strip
will be maintained between the activity and any river,
stream or brook (this is in addition to any requirement for
an upland buffer in accordance with Sec. 27-1526(e)); and
(4) The
project,
including
any
alteration
of
freshwater
wetlands, will not violate any state water quality law,
including those governing the classification of the State's
waters.
All freshwater wetlands within the subdivision must be
identified on any maps submitted as part of the application,
regardless of the size of these wetlands, and any trees of DBH
10 inches or greater located within the upland buffer of the
wetland shall be identified by size, species and health. In
determining whether the proposal avoids the alteration of
wetlands to the extent feasible and if the area of any
alteration is the minimum necessary to complete the project, the
Planning Board shall be guided by the State of Maine's Natural
Resources Protection Act, Wetlands and Waterbodies Protection
Rules Chapter 310 as revised December 5, 2006.
(o) Any river, stream or brook within or abutting the proposed
subdivision has been identified on any maps submitted as part of
the application. For the purposes of this section, "river, stream
or brook" has the same meaning as in Title 38, section 480-B,
subsection 9;
(p) The proposed subdivision will provide for adequate stormwater
management;
(q) If any lots in the proposed subdivision have shore frontage on a
river, stream, brook, great pond, or coastal wetland as these
features are defined in Title 38, section 480-B, none of the lots
created within the subdivision have a lot depth to shore frontage
ratio greater than 5 to 1; and
7
SOUTH PORTLAND CODE
(r) For any proposed subdivision that crosses municipal boundaries,
the proposed subdivision will not cause unreasonable traffic
congestion or unsafe conditions with respect to the use of
existing public ways in an adjoining municipality in which part of
the subdivision is located.
(Ord. No. 8-75, 4-7-75; Ord. No. 11-88/89, 11-7-88; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than
$1000]; Ord. No. 10-07/08, 3/17/08 [Fiscal Note: Less than $1000]; Ord. No. 18-08/09, 4/22/09 [Fiscal
Note: Less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note: Less than $1000]; Ord. No. 4-20/21,
10/6/2020 [Fiscal Note: Less than $1000])
Sec. 24-4.1.
Off-site public improvements.
(a) The board may require that a subdivider construct or reconstruct
off-site improvements. Public improvements shall include but not
be limited to waste water collection and treatment facilities,
storm water drainage systems, solid waste facilities, fire
protection facilities, roads and traffic control devices, parks
and other open space areas. All such improvements shall be
constructed according to the design and construction standards
established in this chapter unless waived by the board.
(b) In determining whether off-site public improvements shall be
constructed by a subdivider, the board shall take into account:
(1) The present condition of the affected public facilities and
the existing level of municipal services;
(2) The burden on the existing public facilities and level of
services caused by the proposed development;
(3) The city's comprehensive plan for public improvements; and
(4) The reports and recommendations of the Director of Public
Works and other department/division heads. As an alternative
to a requirement that an applicant construct off-site public
improvements to serve a proposed subdivision, the board may
approve the execution of a developer agreement between a
subdivider and the city pursuant to which a subdivider may
make full or proportional payment toward the construction
costs of needed public improvements. Any such agreement must
be recommended by the city manager and approved by the city
council.
(c)
If the board requires off-site public improvements to be made by
an applicant, the subdivider shall post performance guarantees
required by this chapter.
8
SOUTH PORTLAND CODE
(Ord. No. 11-88/89, 11-7-88; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; Ord. No.
19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-5.
Fee schedule.
Application fees as required by this chapter shall be as specified
in the Schedule of License, Permit, Inspection and Application Fees
established by City Council order.
(a) Independent Consulting and Peer Review Fees.
(1) In addition to the application fee, every applicant may
also be required by the Planning Director to pay a
consulting cost fee to cover 100% of the City's costs
related to independent geotechnical, hydrologic, wetland
scientist, engineering, traffic, architectural, planning,
legal and similar professional consulting services incurred
in the City's review of the application. This fee must be
paid to the City and shall be deposited in a non-interest
bearing escrow account. When a consulting cost fee is
required, the application will be considered incomplete
until evidence of payment of this fee is submitted to the
Planning Director. If the initial fee proves to be
insufficient to meet the City's professional review costs,
the Planning Director may assess an additional fee(s) to
cover such professional review costs. Any excess amount
deposited with the City in advance shall be promptly
refunded to the applicant after final action on the
application.
(2) The consulting cost fee may be used by the Planning
Director only to pay reasonable costs incurred by the
Planning Department, at its discretion, which relate
directly to the review of the application pursuant to the
review criteria. The results of the consultation or peer
review for which such fees are assessed shall be available
for public review, but such results shall be deemed to have
been made solely for the benefit of the City and shall
remain its property. Such fees shall be assessed for the
privilege of review and shall be payable without regard to
consultation or peer review results or the outcome of the
application.
(3) No building permit or certificate of occupancy may be
issued nor subdivision plat released until all fees
assessed hereunder have been paid in full.
9
SOUTH PORTLAND CODE
(4) Any dispute regarding the application of this provision or
the amount required to be paid, either in advance or upon
completion, may be appealed in writing within ten (10) days
of notice of the amount assessed hereunder to the Planning
Director. If the dispute is not resolved to the
applicant's satisfaction by the Planning Director, the
matter may be appealed in writing within ten (10) days of
the Planning Director's decision on the dispute to the City
Manager. The City Manager, after due notice and
investigation and for good cause shown, may affirm, modify
or reverse the disputed decision, reduce the amount
assessed or increase the amount assessed.
(Ord. No. 8-75, 4-7-75; Ord. No. 9-87/88, 8-17-87; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than
$1000]; Ord. No. 4-09/10, 9/9/09 [Fiscal Note: Less than $1000]; Ord. No. 7-10/11, 9/20/10 [Fiscal
Note: Less than $1000])
Sec. 24-6. Applicability date of amendments evidenced by Ordinance #4-20/21.
Notwithstanding the provisions of 1 M.R.S.A. § 302 or any other
law to the contrary, the amendments to this ordinance evidenced by
Ordinance #4-20/21, when enacted, shall govern any application for
which the Planning and Development Department has not, prior to
September 22, 2020, issued a completeness review letter indicating that
the application is complete and that the project has been tentatively
scheduled for a Planning Board public hearing agenda. In the case of a
"major subdivision" as defined in this chapter, the amendments to this
ordinance evidenced by Ordinance #4-20/21, when enacted, shall govern
any application for which the Planning and Development Department has
not, prior to September 22, 2020, issued a completeness review letter
indicating that the final subdivision plan application is complete and
that the final subdivision plan has been tentatively scheduled for a
Planning Board public hearing agenda.
(Ord. No. 4-20/21, 10/6/2020 [Fiscal Note: Less than $1000])
Secs. 24-7. Reserved.
(Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; (Ord. No. 4-20/21, 10/6/2020 [Fiscal Note:
Less than $1000])
10
SOUTH PORTLAND CODE
ARTICLE II. PLANS
DIVISION 1. PREAPPLICATION
Sec. 24-8.
Preapplication.
(a) A subdivider may meet with the planning board prior to formal
submission of a plan in order to generally discuss their proposal.
At such time they may submit a sketch plan showing an outline of
the lands, proposed roads and any other general conditions which
may be pertinent to the planning board's classification of the
subdivision.
(b) After such preliminary inspection the planning board will classify
the sketch plan into one of two (2) categories as defined in
section 24-3:
Minor subdivision;
Major subdivision.
(Ord. No. 8-75, 4-7-75; Ord. No. 7-83/84, 9-19-83)
Sec. 24-9. Reserved.
DIVISION 2. MINOR SUBDIVISION
Sec. 24-10.
General.
The planning board may require, where it deems it necessary for
the protection of public health, safety and welfare, that a minor
subdivision comply with all or any of the requirements specified for
major subdivision.
(Ord. No. 8-75, 4-7-75)
1
SOUTH PORTLAND CODE
Sec. 24-11.
Procedure.
(a) Within six (6) months after classification of the sketch plan as a
minor subdivision by the planning board, the subdivider shall
submit an application for approval of a final plan at least ten
(10) days prior to a scheduled meeting of the board. Failure to do
so shall require resubmission of the plan to the planning board
for reclassification.
(b) All applications for plan approval for minor subdivisions or
amended minor subdivisions shall be accompanied by a fee as
specified in the Schedule of License, Permit, Inspection and
Application Fees established by City Council order.
(c) The subdivider, or their duly authorized representative, shall
attend the meeting of the planning board to discuss the final
plan.
(d) The planning board shall, within sixty (60) days from the date of
submission, approve, approve with conditions or disapprove the
final plan. The board shall specify in writing its reasons for any
such conditions or disapproval. Any such decision by the planning
board shall be accompanied by and based upon a statement of
findings of fact.
(Ord. No. 8-75, 4-7-75; Ord. No. 9-87/88, 8-17-87; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than
$1000]; Ord. No. 7-10/11, 9/20/10 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal
Note: Less than $1000])
Sec. 24-12.
Submissions.
The subdivision plan for a minor subdivision shall consist of one
original and three (3) copies of one or more maps or drawings drawn to
a scale of not more than one hundred (100) feet to the inch, which
shall be legibly reproduced on a durable material or clearly drawn in
India ink on linen, and size of the sheets shall be eight and one-half
(8 1/2) by eleven (11) inches or a multiple thereof, but in no case
larger than twenty-four (24) by thirty-six (36) inches.
Such sheets shall have a margin of one and a half (1 1/2) inches
outside of the border line on the left side for binding and a one-half
( 1/2) inch margin outside the border along the remaining sides. Space
shall be reserved thereon for endorsement by all appropriate agencies.
The application for approval of a minor subdivision shall include all
the following information:
2
SOUTH PORTLAND CODE
(1) A copy of such covenants or deed restrictions as are intended to
cover all or part of the tract.
(2) An actual field survey of the boundary lines of the tract, giving
complete descriptive data by bearings and distances, made and
certified by a licensed land surveyor. The corners of the tract
shall be located on the ground and marked by monuments as herein
required, and shall be referenced as shown on the plan.
(3) Sufficient data acceptable to the Planning Director or other duly
designated person to determine readily the location, bearing and
length of every lot line, and boundary line and to reproduce such
lines upon the ground. Where practical these should be tied to
reference points previously established.
(4) The survey of the outside boundaries of the tract and the
computation of the lot lines shall be performed to an accuracy of
one foot in five thousand (5,000) feet. The surveyor if requested
shall furnish copies of computation sheets for outside boundaries
to the planning board for approval showing:
(a) Sketch of traverse lines;
(b) Closures;
(c) Adjustments;
(d) Coordinates; and
(e) Computation of outside boundaries.
(5) Contour lines at intervals of two (2) feet or at such intervals as
the planning board may require, based on United States Geological
Survey datum at mean sea level.
(6) A minimum of three (3) corners of the perimeter of the proposed
subdivision tract shall be marked with granite or concrete
monuments. All granite or concrete monuments shall be a minimum 4"
square four (4) feet long and set six (6) inches aboveground
except in lawns, drives, and parking areas where they shall be
flush. Properly set existing granite or concrete monuments that
do not meet these dimension requirements may be considered
satisfactory. If the subsurface is ledge between one and three (3)
feet deep, a two-foot diameter concrete encasement based on the
ledge shall be required. If the ledge is less than one foot deep a
one-inch steel rod shall be grouted into the ledge.
3
SOUTH PORTLAND CODE
(7) A soils report identifying the soils boundaries and names in the
proposed development with the soils information superimposed upon
the plot plan in accord with the USDA Soil Conservation Service
National Cooperative Soil Classification.
(8) All on site sewerage and water supply facilities shall be shown
designed to meet the minimum specifications of these standards and
all pertinent state and local ordinances. Compliance shall be
stated on the plan and signed by a licensed civil engineer.
(9) Proposed name of the subdivision or identifying title.
(10)The date, north point, graphic map scale, name and address of
record owner and subdivider and names of adjoining property
owners.
(11)The applicant's evaluation and demonstration of the adequacy and
availability of public improvements necessary to serve the
proposed subdivision.
(12)If the applicant is required by Sec. 27-1526, Performance
Standards
for
the
Alteration
of
Freshwater
Wetlands,
to
demonstrate
compliance
with the general standard for the
alteration of freshwater wetlands, and the parcel contains
freshwater
wetlands,
the
application
must
contain
the
information set forth in either a. or b. below.
(a) Subdivisions Requiring a Permit for the Alteration of
Wetlands Under the Maine Natural Resources Protection Act - A
subdivision that will involve the alteration of a freshwater
wetland that requires a permit other than a "permit-by-rule"
from the Maine Department of Environmental Protection (DEP)
under the Natural Resources Protection Act must include the
materials submitted for such permit or approval, including all
supporting documentation, as part of the site plan review
application. A project subject to a DEP '"permit-by-rule" must
submit the information set forth in (b). If an upland buffer is
required
in
accordance
with
Sec.
27-1432,
the
following
additional information must be provided:
1. A delineation of all wetlands and proposed upland buffers on
the subdivision plan or a separate plan at the same scale as the
subdivision plan.
2. A description of the proposed treatment of the upland buffer
to maintain/create these as naturally vegetated buffer strips.
If planting will be done within the upland buffer to meet this
4
SOUTH PORTLAND CODE
requirement, the type and extent of planting shall be provided
in either a tabular or plan form.
3. A narrative describing how the upland buffer will be managed
and maintained over time including drafts of proposed easements,
deed restrictions, or other legally binding documentation.
(b) Subdivisions That Do Not Require a Permit for the Alteration
of Wetlands Under the Maine Natural Resources Protection Act - A
subdivision on a parcel that contains a freshwater wetland but
that does not require a permit from the Maine Department of
Environmental Protection (DEP) under the Natural Resources
Protection
Act
or
a
project that is subject to a DEP
"permit-by-rule" must provide the following information as part
of the application:
1.
A plan and accompanying documentation delineating the
location, type, and area of freshwater wetlands on the parcel
prepared by a professional wetland scientist either on the site
plan or on a separate plan drawn at the same scale as the site
plan. The documentation must describe the vegetation, soils,
and hydrology of the identified wetlands and identify any
freshwater wetlands of special significance. The plan must show
any areas of marsh or open water within the identified
freshwater wetlands.
This plan must also show existing and
proposed buildings, structures, roads, and other improvements on
the parcel, and any waterbodies on the parcel or within
seventy-five (75) feet of the wetlands.
2. A statement that there will be no alteration of freshwater
wetlands or, if alteration is proposed, a plan showing the area
of freshwater wetlands proposed to be filled or otherwise
altered. This may be a separate plan or be included as part of
the plan required in 1.
3. Color photographs showing the characteristics of the wetland
vegetation, soils, and hydrology on the parcel. The photos must
be labeled and keyed to the plan provided in 1.
4. If alteration of any freshwater wetlands is proposed, the
submission must include an alternatives analysis report prepared
by a professional wetland scientist. This report must address
whether there is a practical alternative to the proposed
wetlands alteration and, if there is no practical alternative,
how the extent of wetland alteration has been minimized. The
report must assess at least the following:
5
SOUTH PORTLAND CODE
a. Whether the need for the alteration could be avoided by
using, managing, or expanding one or more other sites.
b. Whether the need for the alteration could be avoided or
minimized by reducing the size, scope, configuration, or density
of the activity as proposed.
c. Whether the need for the alteration could be avoided or
minimized by the location or design of the activity.
5. If upland buffers are required in accordance with Sec. 27-1432,
the following additional information must be provided:
a. A delineation of all proposed upland buffers on the
subdivision plan or a separate plan at the same scale as the
subdivision plan.
b. A description of the proposed treatment of the upland buffer
to maintain/create these as naturally vegetated buffer strips.
If planting will be done within the upland buffer to meet this
requirement, the type and extent of planting shall be provided
in either a tabular or plan form.
c. A narrative describing how the upland buffer will be managed
and maintained over time including drafts of proposed easements,
deed restrictions, or other legally binding documentation.
(13)A Basic Stormwater Management Plan meeting the requirements of
Sec. 27-1536, Performance Standards with Respect to Stormwater
Management.
(14)Information on the presence on the property of any historic or
archaeological resources, significant wildlife habitat
identified by the Department of Inland Fisheries and Wildlife or
the City, vernal pools, or rare or irreplaceable natural areas,
or any public rights for physical or visual access to the
shoreline (including copies of any legal instruments relating to
any such public rights) on or across the property.
(15)A description of how the impact of the development activities on
vernal
pools,
including
significant
vernal
pools,
and
significant wildlife habitats will be minimized and what actions
will be taken to mitigate any negative impacts on these
resources. If the proposed activities require a permit or other
approval under the state's Natural Resources Protection Act or
from the Army Corps of Engineers, any such application and
supporting information shall be provided as part of the
submission.
6
SOUTH PORTLAND CODE
(16)A narrative describing how historic or archaeological resources
will be preserved and incorporated into the development plan.
If a resource will be removed, altered, or not included as part
of the development plan, a statement shall be provided as to why
the resource cannot be preserved and the options considered but
rejected for including it as part of the development plan.
(Ord. No. 8-75, 4-7-75; Ord. No. 11-88/89, 11-7-88; Ord. No. 10-93/94, 11-1-93; Ord. No. 4-06/07,
10/2/06 [Fiscal Note: Less than $1000]; Ord. No. 10-07/08, 3/17/08 [Fiscal Note: Less than $1000]; Ord.
No. 18-08/09, 4/22/09, [Fiscal Note: Less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note: Less
than $1000]; Ord. No. 3-14/15, 7/7/14 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24, 4/16/2024
{Fiscal Note: Less than $1000])
Sec. 24-13.
Additional Requirements for Minor Subdivision Applications.
Minor subdivision applications shall include all requirements as
outlined in Ordinance Section 24-38, General Requirements for major
subdivisions - final plan.
(Ord. No. 3-01/02, 9/5/01 [Fiscal Note: Less than $1000])
Secs. 24-14--24-16. Reserved.
DIVISION 3. MAJOR SUBDIVISION--PRELIMINARY PLAN
Sec. 24-17.
Procedure.
(1) The application for conditional approval of the preliminary plan
shall be accompanied by a fee as specified in the Schedule of
License, Permit, Inspection and Application Fees established by
City Council order.
(2) The subdivider, or their duly authorized representative shall
attend the meeting of the planning board to discuss the
preliminary plan.
(3) Within thirty (30) days after formal submission of a preliminary
plan, the planning board shall take action to give preliminary
plan approval, with or without conditions, or disapprove such
preliminary plan. The reasons of any condition required or the
grounds for disapproval shall be stated upon the records of the
7
SOUTH PORTLAND CODE
planning board. Prior to preliminary approval the planning board
may hold a public hearing after reasonable notice of such hearing
shall be given
to the applicant. The planning director shall prepare and deliver
public hearing notices to the newspaper. All public hearing legal
notices published in the newspaper shall be paid for by the
applicant. The applicant is responsible for arranging direct
payment to the newspaper.
(4) When granting preliminary approval to a preliminary plan, the
planning board shall state the conditions of such approval, if
any, with respect to:
1.
The specific changes which it will require in the final plan;
2.
The character and extent of the required improvements for
which waivers may have been requested and which in its
opinion may be waived without jeopardy to the public health,
safety, and general welfare;
3.
The amount of improvement or the amount of all bonds therefor
which it will require as prerequisite to the approval of the
final subdivision plan. The decision of the planning board
plus any conditions imposed shall be noted on three (3)
copies of the preliminary plan. One copy shall be returned to
the subdivider, one retained by the planning board and one
forwarded to the municipal officers.
(5) Preliminary approval of a preliminary plan shall not constitute
approval of the final plan, but rather it shall be deemed an
expression of approval of the design submitted on the preliminary
plan as a guide to the preparation of the final plan. The final
plan shall be submitted for approval of the planning board and for
recording upon fulfillment of the requirements of these standards
and the conditions of the preliminary approval, if any. Prior to
approval of the final subdivision plan, the planning board may
require additional changes as a result of new information obtained
at a public hearing.
(Ord. No. 8-75, 4-7-75; Ord. No. 4-85/86, 8-5-85; Ord. No. 9-87/88, 8-17-87; Ord. No. 8-89/90, 9-18-89;
Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note: Less
than $1000])
Sec. 24-18.
Submissions.
(a) Location map. The preliminary plan shall be accompanied by a map
drawn at a scale of not over four hundred (400) feet to the inch
to show the relation of the proposed subdivision to the adjacent
8
SOUTH PORTLAND CODE
properties and to the general surrounding area. The preliminary
plan shall show all the area within one thousand (l 000) feet of
any property line of the proposed subdivision. Within such area
the location map shall show:
(1) All existing subdivisions and approximate tract lines of
acreage parcels together with the names of the record owners
of all adjacent parcels of land, those directly abutting or
directly
across
any
street
adjoining
the
proposed
subdivision.
(2) Locations, widths and names of existing, filed or proposed
streets, easements, and building lines pertaining to the
proposed subdivision and to the adjacent properties.
(3) The boundaries and designations of zoning districts, parks
and other public spaces.
(4) An outline of the proposed subdivision together with its
street system and an indication of the future probable street
system of the remaining portion of the tract, if the
preliminary
plan
submitted
covers
only
part
of
the
subdivider's entire holding.
(b) If the applicant is required by Sec. 27-1526. Performance
Standards
for
the
Alteration
of
Freshwater
Wetlands,
to
demonstrate
compliance
with the general standard for the
alteration of freshwater wetlands, and the parcel contains
freshwater
wetlands,
the
application
must
contain
the
information set forth in Sec. 24-12(12) of the submission
requirements for minor subdivisions.
(Ord. No. 8-75, 4-7-75; Ord. No. 10-07/08, 3/17/08 [Fiscal Note: Less than $1000]; Ord. No. 6-10/11,
9/20/10 [Fiscal Note: Less than $1000])
Sec. 24-19.
Preliminary plan requirements.
The preliminary subdivision shall be submitted in four (4) copies
of one or more maps or drawings which may be printed or reproduced on
paper with all dimensions shown in feet or decimals of a foot, drawn to
a scale of one inch equals not more than one hundred (100) feet,
showing or accompanied by the following information:
(1) Proposed subdivision name or identifying title and the name of the
municipality.
9
SOUTH PORTLAND CODE
(2) Name and address of record owner, subdivider and designer of
preliminary plan. This will be required only when final plans are
submitted.
(3) Number of acres within the proposed subdivision, location of
property lines, existing easements, buildings and other essential
existing physical features.
(4) The names of all subdivisions immediately adjacent and the names
of owners of record of adjacent acreage.
(5) The provisions of the zoning ordinance applicable to the area to
be subdivided and any zoning district boundaries affecting the
subdivision.
(6) The location and size of any existing sewers and water mains on
the property to be subdivided.
(7) Location, names and present widths of existing and proposed
streets, highways, easements, building lines, alleys, parks and
other public open spaces.
(8) The width and location of any streets within the area to be
subdivided, and the width, location, grades, and street profiles
of all streets or other public ways proposed by the subdivider.
(9) Contour lines at intervals of two (2) feet or at such intervals as
the planning board may require, based on United States Geological
Survey datum.
(10)A soils report identifying the soils boundaries and names in the
proposed development with the soils information superimposed upon
the plot plan in accord with the USDA Soil Conservation Service
National Cooperative Soil Classification.
(11)Typical cross sections of the proposed grading for roadways and
sidewalks.
(12)Date, true north bearing and graphic scale.
(13)Deed description and map of survey of tract boundary made and
certified by a registered land surveyor, tied into established
reference points.
(14)Connection with existing water supply or alternative means of
providing water supply to the proposed subdivision.
10
SOUTH PORTLAND CODE
(15)Connection with existing sanitary sewerage system or alternative
means of treatment and disposal proposed.
(16)If a private sewage disposal system is proposed, it shall comply
with all requirements of the Maine State Department of Health and
Welfare
and
all related requirements of the city's sewer
ordinance.
(17)A
Post-Construction
Stormwater
Management
Plan
meeting
the
requirements of Sec. 27-1536, Performance Standards with Respect
to Stormwater Management.
(18)The proposed lot lines with dimensions and suggested locations of
buildings.
(19)The location of temporary markers adequate to enable the board, if
requested by the board, to locate readily and appraise the basic
layout in the field.
(20)All parcels of land proposed to be dedicated to public use and the
conditions of such dedication.
(21)The location of all natural features or site elements to be
preserved.
(22)A grading plan may be required for any or all lots as determined
by the planning board.
(23)Preliminary layout of any bridges required.
(24)Information on the presence on the property of any historic or
archaeological resources, significant wildlife habitat
identified by the Department of Inland Fisheries and Wildlife or
the City, vernal pools, or rare or irreplaceable natural areas,
or any public rights for physical or visual access to the
shoreline (including copies of any legal instruments relating to
any such public rights) on or across the property.
(25)A description of how the impact of the development activities on
vernal
pools,
including
significant
vernal
pools,
and
significant wildlife habitats will be minimized and what actions
will be taken to mitigate any negative impacts on these
resources. If the proposed activities require a permit or other
approval under the state's Natural Resources Protection Act or
from the Army Corps of Engineers, any such application and
supporting information shall be provided as part of the
submission.
11
SOUTH PORTLAND CODE
(26)A narrative describing how historic or archaeological resources
will be preserved and incorporated into the development plan.
If a resource will be removed, altered, or not included as part
of the development plan, a statement shall be provided as to why
the resource cannot be preserved and the options considered but
rejected for including it as part of the development plan.
(Ord. No. 8-75, 4-7-75; Ord. No. 22-76, 10-4-76; Ord. No. 4-81/82, 9-9-81; Ord. No. 4-06/07, 10/2/06
[Fiscal Note: Less than $1000]; Ord. No. 18-08/09, 4/22/09 [Fiscal Note: $1000]; Ord. No. 6-10/11,
9/20/10 [Fiscal Note: Less than $1000]; Ord. No. 3-14/15, 7/7/14 [Fiscal Note: Less than $1000]; Ord.
No. 3-14/15 purported to include amendments to Sec. 24-19(24), (25) and (26) as part of Sec. 24-18;
this was a scrivener's error and has been corrected by the Editor."
Secs. 24-20--24-23. Reserved.
DIVISION 4. MAJOR SUBDIVISION--FINAL PLAN
Sec. 24-24.
Procedure.
(a) The subdivider shall, within six (6) months after the preliminary
approval of the preliminary plan, file with the planning board an
application for approval of the final subdivision plan in the form
described herein. If the final plan is not submitted to the
planning board within six (6) months after the approval of the
preliminary plan, the planning board may refuse without prejudice
to act on the final plan and require resubmission of the
preliminary plan. All applications for final plan approval for
major subdivisions or for amended major subdivisions shall be
accompanied by a fee as specified in the Schedule of License,
Permit, Inspection and Application Fees established by City
Council order.
(b) No final plan of a proposed major subdivision shall be officially
submitted to the planning board until the applicant shall have
first secured in writing the approval of such proposed subdivision
from the State of Maine Department of Environmental Protection if
the proposed subdivision:
(1) Occupies a land area in excess of twenty (20) acres, or
(2) Involves a structure or structures having in excess of sixty
thousand (60,000) square feet of ground area coverage, or
12
SOUTH PORTLAND CODE
(3) Requires a license from the said department of environmental
protection under some regulation such as waste discharge or
air quality; or
(4) In any other way falls within the jurisdiction of and is
subject to review by said department of environmental
protection including permits for activities subject to the
Natural Resources Protection Act.
(c) Water
supply
system
proposals
contained
in
the
proposed
subdivision final plan shall be approved in writing, which written
approval shall accompany the proposed final plan upon official
submission, and which approval shall be from the following
authority:
(1) The servicing water department or district if public water
service is to be used, or
(2) The State of Maine Department of Health and Welfare if the
subdivider proposes to provide a central water supply system,
or
(3) A professional engineer licensed by the State of Maine and
qualified in the field of civil engineering if individual
wells serving each building site are to be used,
(4) The planning board may also require the subdivider to submit
the results of water quality tests for such water supply, as
performed by the State of Maine Department of Health and
Welfare.
(d) Sewage disposal systems shall be in accordance with all applicable
laws, codes and regulations of the State of Maine and City of
South Portland, Maine.
(e) The planning board shall, within thirty (30) days after official
submission of a final plan of a proposed subdivision, conduct a
public hearing on such plan. Notice of the public hearing shall be
published in a newspaper of local circulation at least seven (7)
days prior to date of such hearing and such notice shall also be
posted in three (3) places in the city at least seven (7) days
prior to such hearing. The planning director shall prepare and
deliver public hearing notices to the newspaper. All public
hearing legal notices published in the newspaper shall be paid for
by the applicant. The applicant is responsible for arranging
direct payment to the newspaper.
13
SOUTH PORTLAND CODE
(f) No final plan shall be in order for approval or approval with
conditions until after the applicant or developer shall have filed
with the director of finance of the city a performance bond or
guarantee as required by the provisions of this chapter.
(g) The planning board shall, within thirty (30) days after the public
hearing on a final plan, approve, approve with conditions, or
disapprove the final plan. Any such decision of the planning board
shall include findings of fact, and any approval with conditions
or disapproval shall be accompanied by the reasons therefor in
writing. Failure of the planning board to act within the required
time period shall constitute disapproval of such plan, except that
the applicant and board may mutually agree to such other time
limit for any final action as may be necessary and mutually
agreeable.
(h) No plan may be approved by the planning board as long as the
applicant, subdivider or principals of any such applicant or
subdivider shall be in default or shall have failed to complete
improvements on any previously approved plan by the city. Such
default or failure to complete shall constitute conclusive
evidence of the inability of such applicant or developer to comply
with the terms of this chapter or to complete work required by a
plan.
(Ord. No. 8-75, 4-7-75; Ord. No. 4-85/86, 8-5-85; Ord. No. 9-87/88, 8-17-87; Ord. No. 8-89/90, 9-18-89;
Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; Ord. No. 10-07/08, 3/17/08 [Fiscal Note: Less
than $1000]; Ord. No. 7-10/11, 9/10/11 [Fiscal Note: less than $1000])
Sec. 24-25.
Submissions.
(A) The final plan shall consist of four (4) copies of one or more
maps or drawings which shall be printed or reproduced in the same
manner as the preliminary plan. Space shall be reserved thereon
for endorsement by all appropriate agencies. The final plan shall
show:
(1) All of the information presented on the preliminary plan and
location map and any amendments thereto suggested or required
by the board.
(2) The name, registration number, seal, and signature of the
engineer or land surveyor who prepared the plan.
(3) Street names and lines, pedestrian ways, lots, easements and
areas to be reserved for or dedicated to public use.
(4) An actual field survey of the boundary lines of the tract,
giving complete descriptive data by bearings and distances,
14
SOUTH PORTLAND CODE
made and certified by a licensed land surveyor. The corners
of the tract shall be located on the ground and marked by
monuments as herein required, and shall be referenced as
shown on the plan.
(5) Sufficient data to determine readily the location, bearing
and length of every lot line and boundary line and to
reproduce such lines upon the ground. Where practical these
should be tied to reference points previously established.
(6) The survey of the outside boundaries of the tract and the
computation of the lot lines shall be performed to an
accuracy of one foot in five thousand (5,000) feet. The
surveyor shall furnish copies of computation sheets for
outside boundaries showing:
(a) Sketch of traverse lines;
(b) Closures;
(c) Adjustments;
(d) Coordinates; and
(e) Computation of outside boundaries.
(7) Contour lines at intervals of two (2) feet or at such
intervals as the planning board may require, based on United
States Geological Survey datum.
(8) A minimum of 3 corners of the perimeter of the subdivision
tract shall be marked with granite or concrete monuments.
All granite or concrete monuments shall be a minimum 4"
square and four (4) feet long and set six (6) inches
aboveground except in lawns, drives, and parking areas, where
they shall be flush.
Properly set existing granite or
concrete
monuments
that
do
not
meet
these
dimension
requirements
may
be
considered
satisfactory.
If the
subsurface is ledge between one and three (3) feet deep, a
two-foot diameter concrete encasement based on the ledge
shall be required. If the ledge is less than one foot deep a
one-inch steel rod shall be grouted into the ledge.
(9) By proper designation, all public open space for which offers
of cession are made by the subdivider and those spaces to
which title is reserved by them.
15
SOUTH PORTLAND CODE
(10)Lots and blocks within the subdivision numbered in accordance
with local practice.
(11)Construction plans for streets, sanitary sewers, and storm
drainage systems shall be designed and prepared by a
professional engineer registered in the State of Maine.
Drawings shall show the plan, profile, cross sections and
details of appurtenances and shall be prepared in accordance
with the provisions of this chapter, including the South
Portland Street Design Manual. Drawings submitted to the
planning board for its review shall have been previously
reviewed by a registered engineer and appropriate agencies,
unless this prerequisite review is waived by the Planning
Board or deferred through conditions of approval.
Plans shall be bound and submitted to the planning board in
the following order. Plans not submitted in this order will
be cause for rejection by the planning board:
1.
Cover
sheet.
To include but not limited to the
following:
(a) Plan showing layout of total subdivision including
development phases if applicable.
(b) Contours at two-foot intervals.
(c) Layout of sanitary and storm sewers.
(d) Layout of brooks, streams or other natural drainage
features.
(e) Summary table to include road names, road lengths,
sanitary and storm sewer lengths in each road.
2.
Construction drawings. Drawings are to include all
engineering information necessary to locate streets,
storm drains, and sanitary sewers both in plan and
profile and shall conform to accepted engineering
practices. Typical cross sections shall be provided
showing the materials to be used in all phases of
construction as applicable in the South Portland Street
Design Manual.
3.
Plat plan. The plat plan will be the last drawing in the
set. All drawings previous to the plat plan will be
numbered consecutively. The plat plan will not be
numbered as part of the set.
16
SOUTH PORTLAND CODE
(B) There shall be submitted to the board with final plan:
(1) Written offers of cession to the city of all public open
space shown on the plan, and copies of agreements or other
documents showing the manner in which spaces, title to which
is reserved by the subdivider, are to be maintained.
(2) Written evidence that the city manager and corporation
counsel are satisfied with the legal sufficiency of the
documents referred to in subparagraph (1), above. Such
written evidence shall not constitute an acceptance by the
municipality of any public open space referred to in
subparagraph (1), above.
(3) A performance bond or guarantee in a form and amount meeting
the requirements of this chapter to secure completion of all
improvements required by the board and written evidence that
the city manager, or his/her designee has reviewed and
approved said bond or guarantee in accordance with the
provisions of this chapter.
(4) Written evidence from the municipal fire chief to the effect
that the final plan meets all fire regulation requirements.
(5) The applicant's evaluation and demonstration of the adequacy
and availability of public improvements necessary to serve
the proposed subdivision.
(Ord. No. 8-75, 4-7-75; Ord. No. 22-76, 10-4-76; Ord. No. 11-88/89, 11-7-88; Ord. No. 10-93/94,
11-1-93; Ord. NO. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000], Ord. No. 12-19/20, 11/7/19 [Fiscal
Note: Less than $1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-26.
Final approval and filing.
(a) Upon completion of the requirements stated in this division,
including planning board approval, and notation to that effect
upon the plan, the plan shall be deemed to have final approval and
a copy of the final plan as approved shall be filed by the
applicant with the municipal officers. The plan shall then be
recorded in the Cumberland County Registry of Deeds by the
subdivider. Any subdivision plan not so filed or recorded within
ninety (90) days of the date upon which such plan is approved and
signed by the planning board as herein provided shall become null
and void, unless the particular circumstances of said applicant
warrant the planning board granting an extension which shall not
exceed two (2) additional periods of ninety (90) days.
17
SOUTH PORTLAND CODE
(b) The Planning Board may approve plans to develop a major
subdivision in separate and distinct phases subject to any
conditions the Planning Board deem necessary in order to insure
the orderly development of the plan. This may be accomplished by
limiting final approval to those lots or areas abutting that
section of the proposed subdivision street that is covered by a
performance guarantee. When development is phased, road and any
other construction shall commence from an existing public way.
Final approval of lots or other development in subsequent phases
shall
be
given
only
upon
satisfactory
completion
of
all
requirements pertaining to previous phases. The Planning Board
shall establish commencement of construction and completion of
construction deadlines for each phase of the development upon
approval of each phase.
(Ord. No. 8-75, 4-7-75; Ord. No. 7-10/11, 9/10/11 [Fiscal Note: Less than $1000]; Ord. No. 7-10/11,
9/10/20 [Fiscal Note: Less than $1000])
Sec. 24-27.
Plan revisions after approval.
(a) Any subdivision plan that has been previously approved by
the Planning Board, may not be changed without amended
subdivision review and approval by the Planning Board.
(b) Amendments to plans previously approved by the Planning
Board shall be subject to one of the following levels of
review:
(1) Minor
Amendments,
pursuant
to
the
provisions
outlined in Sec. 24-27(c) below.
(2) Major
Amendments,
pursuant
to
the
provisions
outlined in Sec. 24-27(d) below.
(c) Planning Board Consent Calendar Review.
(1) The following project amendments to a previously
approved subdivision are eligible for Planning Board
Consent Calendar review:
(A)
Amendments to lot lines where all lots remain
conforming and no new lots are created. All
current owners of lots or units shown on the
recorded plan shall receive notice of the
consent
calendar
review
for
a
lot
line
adjustment.
18
SOUTH PORTLAND CODE
(B)
Modifications
to
landscaping
that
do
not
reduce landscaped area by more than 500 sq.
ft.
(C)
Modifications to landscaping to relocate or
amend trees that were provided as mitigation
trees for tree loss, where the number and
quality of trees provided as mitigation is not
reduced.
(D)
Modifications to utilities, including redesign
of utility networks or connections and the
addition
of
new
utilities
(e.g.,
adding
natural gas lines to a project that did not
initially propose a gas line connection). The
modifications to utilities cannot involve new
easements
or
modifications
to
existing
easements, must maintain equivalent service
capacity, and cannot negatively impact open
space and natural resources (e.g., a new
utility trench location that results in new
tree removal).
(E)
Applicant, property owner, and agent contact
information updates.
(F)
Amendments to stormwater design so long as
there is no loss of stormwater management
capacity on site, no more than a 15% increase
in municipal MS4 discharge, no new easements or
modifications to existing easements, and no
negative impacts to open space and natural
resources (e.g., a new utility trench location
that results in new tree removal shall be
evaluated by the Planning Board).
(G)
Modifications to impervious area resulting in
no more than 250 sq. ft. of new impervious
area. Increases in impervious area may be
offset
by
a
corresponding
decrease
in
impervious area elsewhere on the same parcel.
(H)
Redesigning
parking
areas,
with
no
modifications to site access (e.g., no new
curb cuts or relocated curb cuts).
(2) Minor Amendment applications shall be submitted to the
19
SOUTH PORTLAND CODE
Planning Director, and the Planning Director shall place
all complete applications on the Consent Calendar of a
Planning Board meeting for action by the Planning Board.
The application shall be accompanied by a recommendation
on the application from the Planning Director, which
shall be prepared in consultation with City staff and
consultants
as
may
be
necessary.
Third-party
consultation shall be conducted in accordance with Sec.
24-5(a) of this chapter.
(3) The Planning Board may take action on a Minor Amendment
application without specific discussion as part of a
slate of Consent Calendar items, take the item off the
Consent Calendar for specific discussion, postpone the
item to enable the provision of further public notice,
determine that the proposed change or set of changes
are not minor in nature and do not qualify for the
minor amendment change review procedure as outlined
above,
or
take
such
other
action
as
it
deems
appropriate.
(4) Minor Amendment applications may be approved by the
Planning Board if they:
(A) do
not
amount
to
a
waiver
or
substantial
alteration
of
any
condition
or
requirement
previously set by the Planning Board;
(B) do not affect an approval standard; and
(C) meet all applicable ordinances and laws.
(d) Major Amendments Requiring a Duly Noticed Planning Board
Public Hearing.
(1) Amendments or modifications to a previously approved
subdivision plan that meet any of the following
criteria shall be subject to a Planning Board public
hearing,
duly
noticed
in
accordance
with
the
requirements of this chapter:
(A) Modifications
that
amount
to
a
waiver
or
substantial
alteration
of
any
condition
of
20
SOUTH PORTLAND CODE
approval previously set by the Planning Board;
(B) Modifications that affect an approval standard or
modify the basis for finding conformance with an
applicable standard;
(C) Modifications
to
lot
lines
in
an approved
subdivision where new lots are created;
(D) Modifications
that
otherwise
do
not
meet
applicable ordinances and/or laws;
(E) Modifications
that
may
otherwise
meet
the
criteria for Planning Board Consent Calendar
(Minor
Amendment)
review
pursuant
to
Sec.
24-27(c) but which are, in the sole discretion of
the Planning Director, appropriate for more
enhanced
review
and
therefore
require
a
duly-noticed
public
hearing
pursuant
to
24-27(d)(1).
(Ord. No. 8-75, 4-7-75 Ord. No. 3-01/02, 9/5/01 [Fiscal Note: Less than $1000] Ord. No. 12-19/20,
11/7/19 [Fiscal Note: Less than $1000]; Ord. No. 6-23/24, 11/14/2023)
Sec. 24-28.
Inspection and required improvements.
A)
At least thirty (30) days prior to the beginning of construction
of the required improvements, and prior to the issuance of a
building permit, the subdivider shall notify the Planning Director
that it seeks to start construction. The Planning Director shall
coordinate a pre-construction meeting to review, at a minimum, the
following:
(1) Type of improvement(s).
(2) Description of and amount of work to be completed.
(3) Beginning date.
(4) Duration of construction.
(5) Erosion
and
sedimentation
control,
and
other
site
stabilization.
21
SOUTH PORTLAND CODE
(6)
Planning Board requirements and conditions.
Construction shall be scheduled continuously until date of
completion.
B)
[RESERVED]
(C) [RESERVED]
(D) If the Planning Director or other duly designated person shall
find, upon receiving reports of inspection of the improvements
performed before expiration date of the performance bond, that any
of the required improvements have not been constructed in
accordance with plans and specifications filed by the subdivider,
the Planning Director shall notify the subdivider and, if
necessary, the bonding company, and take all necessary steps to
preserve the municipality's rights under the bond. The Planning
Board shall be notified of any action to utilize a performance
bond at its next public meeting following the call for use of the
performance bond.
E)
If at any time before or during the construction of the required
improvements the subdivider seeks to modify the location or design
of such required improvements, an application shall be filed by
the subdivider with the Planning Division for review and approval
by the planning board. The Planning Director or other duly
designated person shall issue any authorization under this section
in writing and shall transmit a copy of such authorization to the
planning board at its next regular meeting.
(F) The applicant shall be required to maintain all improvements and
provide for snow removal on streets and sidewalks until acceptance
of said improvements by the city council.
(G) Upon completion of the subdivision the subdivider shall notify the
planning board in writing stating that all improvements have been
completed. Along with this statement shall be submitted the
following information:
(a) As-builts of all construction drawings previously approved by
the planning board as final plans, and to include the
following:
(1) Cover sheet to include:
22
SOUTH PORTLAND CODE
a.
Total layout of subdivision showing phases of
construction if applicable.
b.
Layout of water mains, hydrants, sanitary and storm
sewers.
c.
Contours at two-foot intervals.
d.
Summary table to include road name, length and
total length of sanitary and storm sewer.
e.
Index of streets.
(2) Construction drawings. As-built information concerning
street locations; plan and profile of storm and sanitary
sewers; plan and profile of drainage courses as provided
for in the original final drawings approved by the
planning board.
(3) Plat plan.
(H) Street improvements shall be completed in accordance with the
provisions of this chapter and the Code of Ordinances. The
improvements are to include the following:
(1) All utilities shall be constructed and operative. The
utilities
shall
include, but not be limited to, the
following:
(a) Sanitary sewers.
(b) Storm sewers and drainage.
(c) Water.
(d) Natural gas.
(e) Telephone (underground).
(f) Electrical (underground).
(2) Street paving and related base materials:
(a) All work within the City right-of-way shall require a
street opening permit application and approval in
accordance with Chapter 23, Street and Sidewalks, of the
Code of Ordinances.
23
SOUTH PORTLAND CODE
(3) Street curbing and esplanades:
(a) No curb cuts shall be allowed until the subdivider has
first obtained the necessary curb cut permits as stated
in Chapter 23, Article III, of the City Ordinances.
(4) Driveway aprons: Driveway aprons shall be constructed at the
time the street is constructed should curb cut be obtained as
outlined in (3) above. Base material requirements shall be
the same as that of the street. Pavement shall be applied
within the time frame designated in section 24-30 (b) of this
chapter.
(5) Sidewalks:
(a) Where no sidewalks are to be installed the ground within
the right-of-way shall be graded as provided for in the
South Portland Street Design Manual.
(b) Where sidewalks are to be provided (a) shall apply and
granular base materials shall be provided. Pavement
shall be applied within the time frame designated in
section 24-30 (b) of this chapter.
(I) Unless specifically otherwise provided in this chapter, or by
action of the city council, the subdivider or applicant shall be
liable for payment of the full cost of all improvements required
for completion of any subdivision in accordance with the plan as
finally approved.
(Ord. No. 8-75, 4-7-75; Ord. No. 34-76, 11-1-76; Ord. No. 35-76, 12-6-76; Ord. No. 4-06/07, 10/2/06
[Fiscal Note: less than $1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-29.
Public acceptance of streets, recreation areas.
The approval by the planning board of a subdivision plan shall not
be deemed to constitute an acceptance by the city of any street,
easement, or other open space shown on such plan.
When a park, playground, or other recreation area shall have been
shown on the plan, approval of the plan shall not constitute an
acceptance by the municipality of such areas. The planning board shall
require the plan to be endorsed with appropriate notes to this effect.
The planning board may also require the filing of a written agreement
between the applicant and the municipal officers covering future deed
and title, dedication, and provision for the cost of grading,
developing, equipment, and maintenance of any such recreation area.
24
SOUTH PORTLAND CODE
(Ord. No. 8-75, § 4-7-75)
Sec. 24-30.
Improvement completion time.
(a) Any person, firm, or corporation making a subdivision in the City
of South Portland agrees to have all improvements required by
section 24-28 (H)(1) through (5) completed before any building
constructed within the confines of the subdivision is occupied.
Should a building become occupied and said improvements not
completed the subdivider shall be in violation of this chapter.
The official occupancy date shall be that issued by the building
inspector's
office.
All
improvements
are
to
include
the
construction of streets from a previously constructed city street
to the extremity of the lot in question.
(b) All required improvements shall be completed no later than two (2)
years after approval of the final plan. Should the subdivider
request an extension it shall be made in writing to the planning
board. Should the planning board grant an extension it shall be
for a period not to exceed six (6) months. Only one extension
shall be granted. Should the subdivider not complete the required
improvements within the time specified the subdivider shall be in
violation of this chapter.
(Ord. No. 34-76, 11-1-76)
Secs. 24-31--24-34. Reserved.
25
SOUTH PORTLAND CODE
ARTICLE III. ENFORCEMENT
Sec. 24-35.
Procedure.
(a) No plan of a subdivision of land within the City of South Portland
which would constitute a subdivision as defined herein shall
hereafter be filed or recorded in the registry of deeds until a
final plan thereof shall have been approved by the planning board
in accordance with all of the requirements, design standards, and
construction specifications set forth elsewhere in this chapter,
nor until such approval shall have been entered on such final plan
by the planning board.
(b) No person, firm, corporation or other legal entity may convey,
offer or agree to convey any land in a subdivision which has not
been approved by the planning board and recorded in the registry
of deeds.
(c) Any person, firm, corporation or other legal entity who conveys,
offers or agrees to convey any land in a subdivision which has not
been approved as required by this section shall be punished by a
fine as set forth by state law or in the Code of Ordinances, City
of South Portland, Maine for each such conveyance, offering or
agreement. The attorney general, district attorney or the City of
South Portland or the appropriate municipal officers may institute
proceedings to enjoin the violation of this section.
(d) No public utility, water district, sanitary district or any
utility company of any kind shall serve any lot in a subdivision
for which a final plan has not been approved by the planning
board.
(e) Not only is making a subdivision without planning board approval a
violation of law, but so also within such a subdivision is grading
or construction of roads, grading of land or lots, or construction
of buildings until such time as a final plan of such subdivision
shall have been duly prepared, submitted, reviewed, approved, and
endorsed as provided in these standards, and until the original
copy of the final plan so approved and endorsed has been duly
recorded in the Cumberland County Registry of Deeds.
(f) In the event that the subdivider shall fail to comply with the
requirements of section 24-28(F), the building inspector may issue
a stop work order directing cessation of all work in the
subdivision, or the planning board, after notice and hearing, may
1
SOUTH PORTLAND CODE
revoke its approval of the final plan, or both such steps may be
taken.
(Ord. No. 8-75, 4-7-75)
Secs. 24-36.
Enforcement Officer.
It shall be the duty of the Code Enforcement Officer or other person
duly authorized to act in his or her absence or incapacity to enforce
the provisions of this chapter. If the enforcement officer finds
that any of the provisions of this chapter are being violated, he/she
shall notify in writing the person responsible for such violations,
indicating the nature of the violation and ordering the action
necessary to correct it. The enforcement officer shall order
discontinuance of illegal use of land, buildings, or structures,
removal of illegal buildings or structures or of additions,
alterations, or structural changes thereto; discontinuance of any
illegal work being done; or shall take any other action authorized by
this chapter to insure compliance with or to prevent violation of its
provisions.
(Ord. No. 3-01/02, 9/5/01 [Fiscal Note: Less than $1000])
Secs. 24-37. Reserved.
2
SOUTH PORTLAND CODE
ARTICLE IV. GENERAL REQUIREMENTS OF ALL SUBDIVISIONS
Sec. 24-38.
General requirements.
In reviewing applications for the subdivision of land, the board
shall consider the following general requirements. In all instances the
burden of proof shall be upon the person proposing the subdivision.
(A) Subdivision plan shall conform to the comprehensive plan. Any
proposed subdivision shall be in conformity with the comprehensive
plan of South Portland and with the provisions of all pertinent
state and local codes and ordinances.
(B) Preservation of natural and historic features. The applicant for a
proposed subdivision shall provide a grading and landscape plan
that
shows
the Project Disturbance Area that includes the
proposed structures or improvements as well as construction
staging and operations activity that will disturb the site ,
graded contours, streams and the preservation of scenic, historic
or environmentally desirable areas. Within the Project Disturbance
Area, the plan shall identify the drip line of the trees, the
existing location of trees with a 10 inch DBH or greater, or 30
inch DBH or greater in aggregate for a multi-stemmed tree, the
species and health of trees to be removed, and replacement trees.
The street and lot layout shall be adopted to the topography.
Extensive grading and filling shall be avoided as far as possible.
(C) Blocks.
(1) The length, width and shape of blocks shall be determined
with due regard to:
Provision of adequate building sites suitable to the special
needs of the type of use contemplated.
Zoning requirements as to lot sizes and dimensions.
Needs for convenient access, circulation, control and safety
of street traffic.
(2) Blocks shall not be less than four hundred (400) feet, nor
more than one thousand two hundred (1,200) feet in length
except as the planning board considers necessary to secure
the efficient use of land or desired features of street
pattern. In blocks exceeding eight hundred (800) feet in
length, the planning board may require the reservation of a
1
SOUTH PORTLAND CODE
twenty-foot wide easement through the block to provide for
the crossing of underground utilities and pedestrian traffic
where needed or desirable and may further specify, at its
discretion, that a four-foot wide paved footpath be included.
The planning board shall require the subdivider to provide
for the proper maintenance of any such easement.
(D) Lots.
(1) The lot size, width, depth, shape and orientation and the
minimum building setback lines shall be appropriate for the
location of the subdivision and for the type of development
and use contemplated.
(2) Depth and width of properties reserved or laid out for all
purposes shall be adequate to provide for off-street parking
and service facilities for vehicles required by the type of
use and development contemplated.
(3) Double frontage lots and reverse frontage lots shall be
avoided except where essential to provide separation of
residential development from traffic arteries or to overcome
specific disadvantages of topography and orientation. A
planting screen easement of at least ten (10) feet, across
which there shall be no right of access, shall be provided
along the line of lots abutting such a traffic artery or
other disadvantageous use.
(4) Side lot lines shall be substantially at right angles or
radial to street lines.
(5) No person shall make a subdivision within the city unless all
lots of the proposed subdivision have frontage, as regulated
by the zoning ordinance, upon a way granting legal access.
The following ways shall constitute legal access to a lot:
1.
A way accepted by or established as belonging to the
city, provided access is not specifically prohibited.
2.
A way shown on a plan approved in accordance with the
provisions of the subdivision.
3.
A private way (unaccepted street) existing prior to June
17, 1963, which way is shown on a plan recorded in the
registry of deeds prior to such date and is deemed
adequate by the planning board as evidenced by the
board's endorsement on a final plan for the subdivision
of land. In its approval of an existing private way, the
2
SOUTH PORTLAND CODE
board may make whatever requirements it feels necessary
to improve the way commensurate with the projected use
of same.
(E) Easements for natural drainageways. Where a subdivision is
traversed by a natural watercourse, drainageway, channel, or
stream, the subdivider shall, prior to approval of the plan by the
Planning Board, be prepared to convey to the city a storm water
and drainage easement or right-of-way in a form acceptable to the
city the confines of which conform substantially with the lines of
such watercourse and such further width or construction, or both,
as will assure that no flooding occurs and all storm water can be
disposed of properly. Such easement or right-of-way shall not be
less than thirty (30) feet in width. This section shall not be
construed as rendering the City liable for any subsequent drainage
problems or flooding. The Planning Board may reduce the width of
the easement upon the positive recommendation of the Director of
Water Resource Protection or his/her designee if the narrower
easement will allow the drainageway to be maintained or if the
unique characteristics of the site make the creation of a wider
easement impractical.
(F) Utilities.
(1) The location of public utilities, such as streetlights,
electrical lines, telephone lines, gas lines, fire hydrants,
etc., shall be installed in accordance with the provisions of
this chapter. All utilities will be located underground
unless otherwise approved by the planning board.
(2) The following shall constitute the utility provisions of this
Subdivision Ordinance, and reference is made to the South
Portland Street Design Manual.
(a) Electrical systems.
Belowground.
Location: Under sidewalk area (either side).
Operational width: Five (5) feet.
Minimum depth: Two (2) feet six (6) inches of
cover.
Aboveground.
Poles and light standards (either side).
3
SOUTH PORTLAND CODE
Face of structure one foot in back of face of curb,
or four (4) feet inside right-of-way line.
(b) Gas systems.
Location: On south and east side of street. Five (5)
feet inside of pavement edge or curb.
Operational width: Six (6) feet.
Minimum depth: Four (4) feet of cover.
(c) Sewer/storm systems.
Location:
Highway center line for sanitary. Gutter
lines for storm (at curb) both and/or either side of
street.
Operational width: Six (6) feet.
Recommended minimum depth: Seven (7) feet for sanitary,
four (4) feet for storm.
(d) CATV/telephone systems.
Belowground.
Location: Under sidewalk area (either side).
Operational width: Five (5) feet.
Minimum cover: Three (3) feet.
Aboveground.
Poles and pedestals (either side).
Face of structure one foot in back of face of curb,
or four (4) feet six (6) inches inside right-of-way
line.
(e) Water systems.
Location: On north and west side of street. Five (5)
feet inside of pavement edge or curb face.
Operational width: Six (6) feet.
4
SOUTH PORTLAND CODE
Recommended minimum depth: Six (6) feet of cover.
Hydrants: One foot in back of face of curb.
(f) Traffic/street lighting.
Location: Adjacent and generally parallel to pole line
(either side).
Minimum depth: Two (2) feet.
(G) Additional requirements. Street trees, site trees, esplanades, and
open green spaces may be required at the discretion of the
planning board to complement the architecture, enhance the human
scale, reinforce circulation paths, highlight entrances, provide
shade, provide new or mitigate for lost significant habitat and
natural resources, and add color and seasonal interest. Where such
improvements are required, they shall be incorporated in the final
plan and executed by the subdivider as construction of the
subdivision progresses.
(H) Flood damage prevention.
(1) The planning board shall determine that all subdivision
proposals reviewed are consistent with the need to minimize
flood damage, and
(2) All utilities and facilities, including but not limited to,
sewer, gas, electrical and water systems are so located,
elevated and constructed as to minimize or eliminate flood
damages, and
(3) That adequate drainage is provided so as to reduce exposure
to flood hazard, and
(4) That in all subdivision proposals for developments greater in
number than forty (40) lots or greater in total area than
five (5) acres (whichever is the lesser), base flood
elevation data be provided by the developer in both the
preliminary and final subdivision plans.
(Ord. No. 8-75, 4-7-75; Ord. No. 6-77, 5-16-77; Ord. No. 18-08/09, 4/22/09 [Fiscal Note: Less than
$1000]; Ord. No. 4-20/21. 10/6/2020 [Fiscal Note: Less than $1000] ]; Ord. No. 19-23/24, 4/16/2024
[Fiscal Note: Less than $1000])
Secs. 24-39, 24-40. Reserved.
5
SOUTH PORTLAND CODE
6
SOUTH PORTLAND CODE
ARTICLE V. DESIGN AND CONSTRUCTION STANDARDS
Sec. 24-41.
Streets (General).
(a) Street classification definitions and designation. Refer to the
most recent of the South Portland Street Design Manual for street
type definitions and designations. A proposed new street within a
subdivision may be preliminarily classified by the subdivder using
the Street Design Manual for guidance, but the planning board may
modify that classification to the one that the planning board
determines to be the most appropriate under the specific facts and
circumstances of the project.
(b) Street signs.
(1) Streets which join or are in alignment with streets of
abutting or neighboring properties shall bear the same name.
Names of new streets shall not duplicate, nor bear phonetic
resemblance to the names of existing streets within the
municipality and shall be subject to approval of the board.
(2) Street name signs shall be furnished and installed by the
city.
(c) Future street extensions. Reserve strips prohibiting access to
streets or adjoining property shall not be permitted, except
where, in the opinion of the planning board, such strips shall be
in the public interest.
d)
Sidewalks. Sidewalks will be provided at the discretion of the
planning board. Refer to the most recent of the South Portland
Street Design Manual for sidewalk construction standards.
(Ord. No. 8-75, 4-7-75; Ord. No. 19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-42.
Street standards.
1
SOUTH PORTLAND CODE
(A) Refer to the most recent version of the South Portland Street
Design Manual for street design and construction standards. In
addition to the standards set forth in the Street Design Manual,
the latest edition of the Maine Department of Transportation (DOT)
Design Standards also apply. In cases where the City's standards
differ from those of Maine DOT, the City's standards shall guide
but DOT shall be consulted. State and State Aid roads, as
classified by Maine DOT, shall require a design exception from the
Engineering Council for any deviations from the Maine DOT Design
Standards.
(B) Dead-end streets. This section applies to local streets as
described in the South Portland Street Design Manual only.
The following requirements shall be fulfilled:
Maximum length of dead-end street: Six hundred (600) feet measured
from the center line of feeder street to center of turnaround
radius.
Radii of turnaround at end:
Property line: Sixty-five (65) feet.
Outer edge of pavement: Fifty-five (55) feet.
Inner edge of pavement: Thirty-three (33) feet.
(Ord. No. 8-75, 4-7-75; Ord. No. 18-76, 8-16-76; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than
$1000]; Ord. No. 18-08/09, 4/22/09 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal
Note: Less than $1000])
Sec. 24-43.
Storm drainage design and construction standards.
(A) Intent. Recognizing that development activity increases storm
water runoff by reducing the infiltrative capacity of the soils and
that storm water runoff poses dangers of flooding, adds pollution to
water resources, and increases erosion and sedimentation, the purpose
of the City's stormwater management requirements is to encourage the
disposal of storm water on the land at the site of development and, to
the extent practicable, to do so through the wise use of the natural
features of the site. This policy will preserve the natural drainage
system, valuable topsoil, water quality and wildlife habitat during and
after construction through infiltration, detention, or retention of
water falling on the site. The disposal of storm water shall not
2
SOUTH PORTLAND CODE
constitute a threat to public health, safety and welfare and shall not
degrade the quality of South Portland's surface water or groundwater
below state or city standards. It shall be the responsibility of the
developer to adequately provide for the necessary control of storm
water runoff and erosion.
(B) Standards for storm water runoff.
(1)
Minor subdivisions must comply with the standards set forth
for Basic Stormwater Management Plans in Sec. 27-1536,
Performance Standards with Respect to Stormwater Management.
(2)
Major subdivisions must comply with the standards set forth
for Post-Construction Stormwater Management Plans in Sec.
27-1536, Performance Standards with Respect to Stormwater
Management.
(Ord. No. 8-75, 4-7-78; Ord. No. 4-81/82, 9-9-81; Ord. No. 21-00/01, 4/18/01 [Fiscal Note: Less than
$1000]; Ord. No. 4-06/07, 10/2/06, [Fiscal Note: Less than $1000]; Ord. No.18-08/09, 4/22/09 [Fiscal
Note: Less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note: Less than $1000])
Sec. 24-44.
Sanitary sewer design and construction standards.
(a) Intent. An adequately piped sanitary sewer system including
appurtenances such as manholes, wye connections and leads shall be
provided for the adequate removal of sanitary wastes.
(b) Standards.
(1) All sanitary sewer systems within the subdivision shall be
designed to meet criteria dictated by the zoned area. Design
computation shall be submitted to the planning board for
approval.
(2) Upstream sewage shall be accommodated by an adequately sized
system
through
the
proposed
subdivision
for
existing
conditions and potential development in the upstream area or
areas tributary to the proposed subdivision, as determined by
the planning board.
(3) Existing down-stream sewage facilities shall be studied to
determine the effect of the proposed subdivision's sewage.
The developer shall demonstrate to the satisfaction of the
planning board that the sewage from the proposed subdivision
will not in any way overload the existing sewer systems
downstream from the proposed subdivision.
3
SOUTH PORTLAND CODE
(4) Manholes shall be located at intervals not to exceed four
hundred (400) feet and shall be located at intersections and
changes of direction. Drop manholes will be required where
invert differences of incoming to outgoing sewer pipes are
two (2) feet or greater. The average velocity when flowing
full shall not be less than two (2) feet per second. If a
sewer changes direction in a manhole without change of size a
drop of four hundredths (.04) foot will be provided in the
manhole. If the sewer changes size, the crowns of the inlets
and outlet sewers are to be at the same elevation. Branches
coming into a manhole shall have their crowns at the same
elevation as that of a larger sewer. These criteria are
minimal
and
the
actual
engineering
design
will
take
precedence.
(5) Materials. The following materials shall be utilized for
sanitary sewer construction:
(a) Reinforced concrete pipe. Reinforced concrete pipe for
gravity sewers shall conform to standard specifications
for reinforced concrete sewer pipe, ASTM C-76. Pipe
classes shall be as required to meet soil and traffic
loads with a factor of safety of 1.2 on .01 inch crack
strength with Class B bedding. Joints in the pipe shall
be of the tongue and groove type incorporating a single
rubber gasket in which the gasket is in compression and
which will permit both longitudinal and angular movement
without leakage. The gaskets shall conform to the
requirements of ASTM designation C-443.
(b) Asbestos cement pipe. Asbestos cement pipe shall meet
the requirements of ASTM designation C-428 and shall be
designed to resist soil and traffic loads with a factor
of safety of 1.5 on the crushing strength with a Class B
bedding. Joints will be the rubber gasket type meeting
the requirements of ASTM D-1869 and installed in
accordance with the manufacturer's direction.
(c) Clay
pipe.
Clay
pipe
shall
conform
to
standard
specifications ASTM C-200. Joints shall be of flexible
gasket type meeting the requirements of ASTM designation
C-425 latest revision.
(d) Manholes. Manhole super structure shall be of precast
reinforced concrete conforming to the requirements of
ASTM designation C-478. Joints shall be of the flexible
gasket type and meeting the requirements of ASTM
designation C-433.
4
SOUTH PORTLAND CODE
(e) Testing. Pipelines will be tested for leakage between
manholes as the work progresses. The inspector will
conduct the test, but the developer will furnish all
apparatus
required
in
connection
with
tests.
The
infiltration or exfiltration of groundwater into any
section of pipe shall not exceed five hundred (500)
gallons
per
one
inch
diameter
of
pipe
mile
in
twenty-four (24) hours. At all times when work is not in
progress all open ends of pipes and fittings shall be
securely closed to the satisfaction of the inspector so
that no trench water or earth will enter the pipes or
fittings. Any section of pipe already laid and found to
be defective shall be replaced.
(Ord. No. 8-75, 4-7-75)
Sec. 24-45
Alteration of Freshwater Wetlands
(a) If the parcel contains freshwater wetlands and the activity is
not exempt from having to demonstrate compliance with the
freshwater wetland alteration standard of Sec. 27-1526, the plan
must provide for upland buffers adjacent to the identified
freshwater wetlands in accordance with Sec. 27-1526(e) and
preserve, to the maximum extent possible, trees located within
the upland buffer.
(b) If the parcel contains freshwater wetlands, and if any of these
freshwater wetlands will be altered, the project shall provide
compensation
or
mitigation for the wetland alteration if
required by Sec. 27-1526(d) in accordance with the provisions of
that section. The Planning Board may require that trees removed
within the affected wetland area or its upland buffer are
replaced.
(Ord. No. 10-07/08, 3/17/08 [Fiscal Note: less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note:
Less than $1000]; Ord. No. 4-20/21, 10/6/2020 [Fiscal Note: Less than $1000])
Secs. 24-46--24-49. Reserved.
5
SOUTH PORTLAND CODE
6
SOUTH PORTLAND CODE
ARTICLE VI. GENERAL CONSTRUCTION REQUIREMENTS
Sec. 24-50.
General construction requirements.
(a) Trenching. All trenching shall be accomplished in accordance with
all appropriate state and federal safety requirements.
(b) Maximum trench width at the pipe crown shall be the outside
diameter of the pipe plus two (2) feet.
(c) Pipe shall be bedded in crushed or screened stone with a minimum
depth of six (6) inches to provide a Class B bedding. The stone
will be deposited in the trench and brought to proper invert
grade. The maximum size of stone aggregate will be three-fourths (
3/4) inch. When the trench bottom has been excavated below grade
it shall be filled and thoroughly compacted to grade before the
utility pipe is placed. When the excavated trench bottom is not
sufficiently firm to properly support the utility pipe, the
Planning Director, in consultation with the Director of Public
Works, may direct the subdivider to excavate below grade and bed
the trench bottom with a specified depth of select material.
Unless otherwise shown on the final plan the stone shall be
brought to the spring line of the pipe. Bedding materials other
than those stated above may be used, subject to the review and
approval of the Planning Director, in consultation with the
Director of Public Works. Allowances to excavate below grade and
bed the trench, or to alter bedding materials as allowed in this
subsection shall not require Planning Board review and approval.
(d) Alignment shall be straight in both the horizontal and vertical
unless specific approval of a curvilinear drain is obtained in
writing from the planning board.
(e) Manholes shall be provided at all changes in vertical or
horizontal alignment, and at all junctions. On straight runs
manholes shall be placed at a maximum of four hundred (400) foot
intervals.
(f) All drain outlets shall be terminated in an end wall of concrete
construction or shall be riprapped to prevent erosion. Facilities
for energy dissipation shall be provided.
(g) Underdrains shall be laid with perforations down with a backfill
consisting of graded stone or gravel.
(Ord. No. 8-75, 4-7-75; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24,
4/16/2024 [Fiscal Note: Less than $1000])
1
SOUTH PORTLAND CODE
Secs. 24-51, 24-52. Reserved.
2
SOUTH PORTLAND CODE
ARTICLE VII. MONUMENTS
Sec. 24-53.
Monuments.
(a) Granite or concrete monuments a minimum four (4) inches square and
4' long with a flat top shall be set at all street corners, at all
points where the street line intersects the exterior of the
subdivisions and at angle points and points of curve in each
street. The top of the monument shall have an indented cross to
identify properly the location and shall be set flush with the
finished grade.
Properly set existing granite or concrete
monuments that do not meet these dimension requirements may be
considered satisfactory.
(b)All other lot corners, except those required to have granite or
concrete monuments, shall be marked with minimum 3/4" iron pipe
not less than three-fourths (3/4) inch in diameter or 5/8" steel
rebar a minimum of twenty-four (24) inches long. All such markers
shall be set 6" above ground, except in lawns, drives, and parking
areas where they shall be flush.
(Ord. No. 8-75, 4-7-75; Ord. No. 10-93/94, 11-1-93)
Secs. 24-54, 24-55. Reserved.
1
SOUTH PORTLAND CODE
2
SOUTH PORTLAND CODE
ARTICLE VIII. VARIANCES AND WAIVERS; ACCEPTANCE OF STREETS
Sec. 24-56.
Variances and waivers.
(1) Where the planning board finds that extraordinary and unnecessary
hardships may result from strict compliance with these standards
or where there are special circumstances of a particular plan, it
may vary these standards so that substantial justice may be done
and the public interest secured; provided that such variations
will not have the effect of nullifying the intent and purpose of
the official map, the comprehensive plan or the zoning ordinance,
where such exist.
(2) Where the planning board finds that, due to special circumstances
of
a
particular
plan,
the
provision
of
certain
required
improvements is not requisite in the interest of public health,
safety and general welfare, or is inappropriate because of
inadequacy or lack of connecting facilities adjacent or in
proximity
to
the proposed subdivision, it may waive such
requirements, subject to appropriate conditions.
(3) In granting variances and modifications, the planning board shall
require
such
conditions as will, in its judgment, secure
substantially the objectives of the requirements so varied or
modified.
(4) Notwithstanding any other provisions of this chapter to the
contrary, the planning board shall have no authority to grant a
variance or waiver to any right-of-way requirements under this
chapter.
(Ord. No. 8-75, 4-7-75; Ord. No. 15-85/86, 11-18-85)
Sec. 24-57.
Public interest governs acceptance of streets.
Nothing in this article is to be construed as a limitation on the
City Council's authority to accept any street in the city as a public
street whenever the public interest so requires.
(Ord.No.7-96/97, 9-4-96)
Sec. 24-58. Modification of local street standards - stormwater management.
The Planning Board, with input from the Planning Director, in
consultation with the Fire Chief and the Director of Public Works, or
their designees, may approve the design and construction of a new
1
SOUTH PORTLAND CODE
local street as described in the South Portland Street Design Manual
or the extension or alteration of an existing local street that does
not conform to the standards of Sec. 24-41, Streets (General), and
Sec. 24-42, Street standards, as part of a Post-Construction
Stormwater Management Plan if the Planning Board finds that the
modification of the street design is necessary to meet the stormwater
management standards of Sec. 27-1536, Performance Standards with
Respect to Stormwater Management. If the street is constructed in
accordance with the design approved by the Planning Board, the
modification of the standards shall not preclude the street from
being accepted as a public street in accordance with the City's
street acceptance procedures.
The Planning Board's authority to modify the local street standards
as part of a Post-Construction Stormwater Management Plan is limited
to the following areas:
(1) Pavement width - the Planning Board may reduce the minimum
pavement width to not less than twenty-four (24) feet but only
if the Planning Board finds that the reduced width will allow
for safe traffic movement and adequate, all-season emergency
vehicle access to the lots served by the street.
(2) Sidewalks - the Planning Board may allow a sidewalk to be
provided on only one side of the street and may reduce the
minimum width of sidewalks to not less than four (4) feet but
only if the sidewalk will not be maintained by the City. In
addition, the Planning Board may allow the sidewalk to be
located immediately adjacent to the travelway or curb without
provisions for an esplanade.
(3) Curbing - the Planning Board may allow the use of discontinuous
curbing or alternative curbing material that allows stormwater
to drain from the roadway into a stormwater facility or the
stormwater system without going into a conventional underground
storm sewer.
(4) Stormwater system - the Planning Board may allow the use of an
open stormwater drainage system or a system that drains
stormwater directly into stormwater treatment facilities rather
than a conventional underground storm sewer.
(5) Materials - The Planning Board may allow the use of alternative
provisions for the roadway and sidewalk base and subbase as part
of the stormwater management system and may allow the use of
pervious paving materials for sidewalks.
As part of a Post-Construction Stormwater Management Plan, the
Planning Board may allow stormwater facilities that treat the
stormwater runoff from private property to be located within the
street right-of-way if the Planning Board finds that there is no
appropriate location for the facilities on the private property, that
2
SOUTH PORTLAND CODE
the location of the facilities within the street right-of-way will
not adversely impact the City's ability to maintain the street and
related improvements, and that permanent, enforceable provisions for
the maintenance and replacement of the stormwater facilities by the
private property owner are established in a form acceptable to the
City as part of the approved stormwater management plan.
(Ord. No. 18-08/09, 4/22/09 [Fiscal Note: Less than $1000]; Ord. No. 6-10/11, 9/20/10 [Fiscal Note:
Less than $1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Sec. 24-59.
Reserved.
3
SOUTH PORTLAND CODE
4
SOUTH PORTLAND CODE
ARTICLE IX. NONRESIDENTIAL SUBDIVISIONS
Sec. 24-60.
Procedure and standards.
Any subdivision proposed for other than residential uses shall
comply with the procedures, requirements and standards applicable to
major subdivisions as set forth in this chapter.
(Ord. No. 8-75, 4-7-75)
Sec. 24-61.
Vehicular access and traffic.
Notwithstanding any other provisions of the Code of Ordinances,
City of South Portland, Maine, the planning board shall consider
vehicular access, traffic flow and projected traffic flow increase
resulting from such proposed subdivision and may require that such
subdivision and all uses therein be serviced and access provided by
means of one or more entrances complying with the specifications
contained in Sec. 23-37. Maximum allowed curb cut width, with a
splitter island.
(Ord. No. 8-75, 4-7-75; Ord. No. 10-02/03, 1/22/03 [Fiscal Note: Less than $1000]; Ord. No. 19-23/24,
4/16/2024 [Fiscal Note: Less than $1000])
Secs. 24-62--24-65. Reserved.
1
SOUTH PORTLAND CODE
2
SOUTH PORTLAND CODE
ARTICLE X. PERFORMANCE GUARANTEE OR BOND AND RELEASE OF GUARANTEE
Sec. 24-66.
Performance guarantees required.
No approved subdivision plat requiring approval under the
provisions of this chapter, shall be released, by the Planning
Department, to the applicant after receiving Planning Board approval
until the city receives a faithful performance bond running to the
city and issued by a surety company licensed to do business in the
State of Maine, or an irrevocable letter of credit from a financial
institution acceptable to the city in the amount required under
section 24-67. Notwithstanding any other provisions of this chapter
to the contrary, any such performance guarantee must be filed within
the ninety (90) days after receipt of final planning board approval.
In the event such performance guarantee has not been tendered and
approved by the Planning Director, the applicant may request an
additional ninety day subdivision approval by submitting a an amended
subdivision application. No work may begin on such project until such
performance guarantee(s) has been received and approved by the city
and the subdivision plat has been released by the Planning Department
to the applicant for recording at the Cumberland County Registry of
Deeds.
(Ord. No. 8-75, 4-7-75; Ord. No. 22-83/84, 5-7-84, Ord. #3-01/02, 9/5/01 {Fiscal Note: Less than
$1000])
Sec. 24-67.
Form, amount and duration of performance guarantee.
The certified check, performance bond, or irrevocable letter of
credit required under this article shall be accompanied by a guarantee
or be in a form comparable to the sample forms at forth elsewhere in
this article. The performance guarantee shall be valid for the duration
of time required for completion and approval of the improvements
required by the provisions of this chapter. The performance guarantee
shall be in an amount equal to the greater of (a) the cost of all
public improvements and other improvements affecting the public health,
safety, or welfare as determined by the planning board and required
under the provisions of this chapter or (b) the cost of reasonable
restoration of the subdivision tract, which amount shall be determined
by the city manager, or his/her designee with the advice of various
city departments and agencies concerned. The performance guarantee
shall be in the form set forth elsewhere in this chapter or in a form
substantially similar thereto and approved by the corporation counsel.
1
SOUTH PORTLAND CODE
(Ord. No. 8-75, 4-7-75; Ord. No. 22-83/84, 5-7-84, Ord. No. 12-19/20, 11/7/19 [Fiscal Note: Less than
$1000])
Sec. 24-68.
Release of performance guarantee.
(a) The performance guarantee required by this article shall not be
released by the planning board until the applicant establishes
that all work required under the approved subdivision plan,
including
all
improvements which served as the basis for
establishing the amount of the performance guarantee, has been
completed in accordance with approved plans and has been inspected
and found satisfactory by the Planning Director pursuant to the
requirements of this chapter.
(b) The performance guarantee shall not be released until the
subdivider has furnished to the planning board a statement from a
registered land surveyor that all pertinent bounds or monuments
have been accurately installed.
(c) The performance guarantee shall not be released by the planning
board until the subdivider has furnished the Planning Director an
accurate record plan and profile (original ink drawings on linen)
of all drainage lines and structures, sanitary and storm sewerage
lines and appurtenances, water mains and appurtenances, and all
other utilities as actually installed with sufficient ties for
proper identification.
(Ord. No. 8-75, 4-7-75; Ord. No. 22-83/84, 5-7-84; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than
$1000]; Ord. No. 19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])
Secs. 24-69--24-72. Reserved.
2
SOUTH PORTLAND CODE
ARTICLE XI. APPEALS
Sec. 24-73.
Appeals.
(1) An appeal from a decision of the planning board on any final plan
may be taken to the superior court.
(Ord. No. 8-75, 4-7-75)
1
SOUTH PORTLAND CODE
2
SOUTH PORTLAND CODE
ARTICLE XII. SEPARABILITY AND EFFECTIVE DATE
Sec. 24-74.
Separability and effective date.
(1) The invalidity of any provision of these standards shall not
invalidate any other part.
(2) These standards shall take effect immediately on adoption of the
same by the city council.
(Ord. No. 8-75, 4-7-75)
1
SOUTH PORTLAND CODE
2
SOUTH PORTLAND CODE
ARTICLE XIII. FORMS
Sec. 24-75.
Performance bond--Surety company.
KNOW ALL MEN BY THESE PRESENTS that ________ as
Principal and ________ a corporation duly organized and
existing under the laws of the State of ________ and having
a usual place of business in ________, as Surety, hereby
bind and obligate themselves and their respective heirs,
executors, administrators, successors and assigns, jointly
and severally, to the City of South Portland, Maine,
municipal corporation, in the sum of ________ dollars.
The condition of this obligation is that if the
Principal shall fully and satisfactorily observe and perform
in the manner and in the time therein specified, all of the
covenants, conditions, agreements, terms and provisions
contained in the following:
1.
Application for Approval of Final Plan signed by the
Principal and dated ________.
2.
The Subdivision Control Ordinance as enacted by the
City of South Portland, Maine.
3.
The Definitive Plan as defined by the above Ordinance
and as qualified by the Certificate of Approval issued
by
the
Planning
Board
dated
________
then
this
obligation shall be void; otherwise, it shall remain in
full force and effect.
Whenever the Principal shall be, and declared by the
Planning Board to be in default under the Definitive Plan
and its Certificate of Approval, the Surety may promptly
remedy the default or shall promptly:
1.
Complete the Definitive Plan in accordance with its
terms and conditions, or
1
SOUTH PORTLAND CODE
2.
Obtain a bid or bids for submission to Planning Board
for completing the Definitive Plan in accordance with
its terms and conditions, and upon determination by
Planning Board and Surety of the lowest responsible
bidder, arrange for a contract between such bidder and
Planning Board and make available as work progresses
sufficient funds to pay the cost of completion; but not
exceeding, including other costs and damages for which
the Surety may be liable hereunder, the amount set
forth in the first paragraph hereof.
IN WITNESS WHEREOF we have hereunto set our hands and
seals this ________ day of ________, 1975.
Principal
By
(Title)
Surety
By
Attorney-in-Fact
(Ord. No. 8-75, 4-7-75)
Sec. 24-76.
Performance bond--Secured by deposit.
KNOW ALL MEN BY THESE PRESENTS that ________ of
________ hereby binds and obligates himself/itself and
his/their
executors,
administrators,
devisees,
heirs,
successors and assigns to the City of South Portland, Maine
municipal corporation, in the sum of ________ dollars, and
has secured this obligation by the deposit with the
Treasurer of the said City of South Portland of said sum in
money or negotiable securities.
The condition of this obligation is that if the
undersigned or his/its executors, administrators, devisees,
heirs, successors and assigns shall fully and satisfactorily
observe and perform in the manner and in the time therein
2
SOUTH PORTLAND CODE
specified, all of the covenants, conditions, agreements,
terms and provisions contained in the following:
1.
Application for Approval of Final Plan signed by the
Principal and dated ________.
2.
The Subdivision Control Ordinance as enacted by the
City of South Portland, Maine.
3.
The Definitive Plan as defined by the above Ordinance
and as qualified by the Certificate of Approval issued
by
the
Planning
Board
dated
________
then
this
obligation shall be void, otherwise, it shall remain in
full force and effect, and that portion of the
aforesaid security required to complete the Principal's
obligation under this agreement shall become the sole
property of said City of South Portland as liquidated
damages.
IN WITNESS WHEREOF the undersigned has hereunto set his
hand and seal this ________ day of ________, 19________.
____________________
(Ord. No. 8-75, 4-7-75)
Sec. 24-77.
Performance guarantee--Irrevocable letter of credit.
[Date]
TO: City of South Portland
This letter shall constitute an irrevocable letter of
credit verifying that this lending institution has on
account and available a sum or sums not less than [include
amount] for the account of [name of subdivider] to be paid
to the City of South Portland upon receipt of your signed,
written statement that payment is due based upon the
developer's default or failure to construct or install in a
timely and satisfactory manner (including inspection and
approval by the Planning Director) the improvements listed
below on or before [add termination date].
3
SOUTH PORTLAND CODE
[Here list improvements]
This obligation, however, shall be reduced by the
amount(s) stated for each of the above-listed improvements
upon receipt of written certification from the Planning
Director that the corresponding improvements have been
satisfactorily completed, inspected and approved by the city
prior to notice in writing by the city of any such default
or failure by the developer.
In the event that the developer has failed to perform
or is in default in timely and satisfactory completion of
the improvements referred to above, any funds collected by
the City of South Portland under this obligation shall be
used towards completion of said improvements or reasonable
restoration of the subdivision tract.
We hereby agree with the City of South Portland, its
successors and assigns, acting in compliance with the terms
of this obligation, that the same shall be duly honored upon
notice duly given on or before [add termination date].
Very truly yours,
[signed
by
official
of
lending
institution]
(Ord. No. 22-83/84, 5-7-84; Ord. No. 4-06/07, 10/2/06 [Fiscal Note: Less than $1000]; Ord. No.
19-23/24, 4/16/2024 [Fiscal Note: Less than $1000])