Solar Energy Systems (SES) Ordinance
Adopted by the Town of Stockton Springs: June 13, 2026
Attested By: L Vian £ ea 4 ul mbtoo
Title: FAD ChrcK
Seal:
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
TOWN OF STOCKTON SPRINGS, MAINE
SOLAR ENERGY SYSTEMS (SES) ORDINANCE
TABLE OF CONTENTS
ARTICLE 1: PURPOSE
ARTICLE 2: TITLE, AUTHORITY, AND ADMINISTRATION
A. Title
B. Authority
C. Administration
ARTICLE 3: APPLICABILITY
A. New Applicants
B. Current Applicants
ARTICLE 4: APPLICATION PROCEDURE
A. Pre-Application Meeting
B. Planning Board Meeting Request
C. Site Review
D. Formal Application
E. Application Fee
ARTICLE 5: REQUIRED APPLICATION INFORMATION FOR INDUSTRIAL SES
A. Application Information
B. Financial and Technical Capacity
C. Project Narrative and Supplemental Information
D. Site Plan
E. Existing Conditions Documentation
F. Proposed Conditions Documentation
G. Landscape / Screening Plan
H. Environmental Impact Assessment and Stormwater Management
I. Public Safety Submittal Requirements
J. End of Life - Decommissioning and Site Restoration Plan
ARTICLE 6: REVIEW STANDARDS
A. General Standards of Review
B. General Restrictions and Dimensional Standards
ARTICLE 7: FINANCIAL RESPONSIBILITIES
A. Liability and Environmental Insurance
B. Escrow
C. Abandonment
D. Decommissioning
E. Performance Guarantee / Financial Assurance Bond
ARTICLE 8: INSPECTIONS / UPDATES TO APPROVED PLAN / REVALUATION
A. Anniversary Submission to CEO
B. Reporting to the Town
ARTICLE 9: ENFORCEMENT, ADMINISTRATIVE CONSENT AGREEMENT, AND LEGAL ACTIONS
A. Enforcement
B. Administrative Consent Agreement
C. Legal Actions
D. Change of Ownership
ARTICLE 10: APPEALS
ARTICLE 11: DEFINITIONS
MAP 1: TOWN OF STOCKTON SPRINGS ZONING MAP
TABLE 1: SOLAR ORDINANCE REFERENCE CHART
Page 1 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
ARTICLE 1: PURPOSE: The purpose of this ordinance is to establish a municipal review procedure and performance standards for any
Solar Energy Systems (SES). These standards are intended to:
A. Establish clear guidelines, standards, and time frames for the Town to promote responsible Solar Energy Systems (SES).
B. Permit the Town to fairly and responsibly protect public health, safety, and welfare.
C. Minimize any adverse effects of solar development on surrounding land use and protect town property values.
D. Provide for the decommissioning and removal of solar panels and associated utility structures that are no longer being used for
energy generation and transmission purposes.
E. Support the goals and policies of the Town of Stockton Springs, including orderly development and preservation of the town's
character, efficient use of infrastructure, and protection of natural, scenic, and agricultural resources of the Town.
ARTICLE 2: TITLE, AUTHORITY, AND ADMINISTRATION
A. Title: This ordinance shall be known as the Solar Energy Systems Ordinance of the Town of Stockton Springs, Maine.
B. Authority: This Ordinance is adopted pursuant to Home Rule Power as provided for in Article 8 of the State of Maine
Constitution and under the authority granted to the Town by the Statutes of the State of Maine, Title 30-A M.R.S.A. § 3001,
Ordinance Power, the provisions of 30-A M.R.S.A. §4311 et seq. (Comprehensive Planning and Land Use Regulation or "Growth
Management Act", and the Solar Permitting on High Value Agricultural Land Rule).
C. Administration: This Ordinance shall be administered by the Planning Board and where applicable, Stockton Springs' duly
appointed Code Enforcement Officer (CEO) and the Select Board.
1. This Ordinance may be amended by a majority vote at a Town Meeting. Amendments shall be initiated by majority
vote of the Planning Board; or by request of the Board of Selectmen to the Planning Board; or on petition of ten percent
(10%) of the votes cast in the last gubernatorial election in the Town. The Planning Board shall conduct a public
hearing on any proposed amendment.
2. Whenever the requirements of this Ordinance are inconsistent with the requirements of any other ordinance, code or
statute, the more restrictive requirements shall apply.
3. If any section, clause, paragraph, sentence or phrase of this Ordinance shall, for any reason, be held to be invalid or
unconstitutional, such invalid section, clause, paragraph, sentence or phrase is hereby declared to be severable; and any
such invalid or unconstitutional section, clause, paragraph, sentence or phrase shall in no way affect the remainder of
this Ordinance.
4. This Ordinance shall be effective upon its adoption by vote of the eligible voters of the Town of Stockton Springs at
the Annual Town Meeting.
ARTICLE 3: APPLICABILITY
A. New Applicants: This Ordinance applies to all solar energy systems including Industrial, Commercial, and Residential, as
defined as Solar Energy Systems (SES) in Article 11: Definitions, including those with battery backup systems.
1. Residential and Commercial SES shall apply for and must receive approval from the CEO prior to the
commencement of construction / installation.
2. Industrial SES shall apply for and seek planning board approval.
B. Current Applicants: Any previously approved, and legally operating solar energy system facility may continue subject to the
Planning Board approved plans and conditions of approval. Any modifications being sought to previously approved plans shall be
subject to Planning Board review and must meet the conditions of this Ordinance. All proposed expansions shall also meet the
conditions and intent of this Ordinance.
Page 2 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
ARTICLE 4: APPLICATION PROCEDURE
A. Pre-application Meeting: Prior to submitting a formal application, the applicant or his/her representative may request a
pre-application conference with the Planning Board. Said request shall be made, in writing, to the Towns Code Enforcement
Officer at least fourteen (14) days prior to the date of the meeting. Applicant shall provide the Planning Board with whatever
information, relative to the proposed project, is available at the time of the pre-application conference. A pre-application
conference is strongly advised. The pre-application conference shall be informal and informational in nature. There shall be no
fee for a pre-application review, and such review shall not cause the plan to be a pending application or proceeding under Title 1
M.R.S.A. §302. No decision on the substance of the plan shall be made at the pre-application conference.
B. Planning Board Meeting Request:
1. Allow the Planning Board to understand the nature of the proposed use and the issues involved in the proposal.
2. Allow the applicant to understand the development review process and required submissions.
3. Identify issues that need to be addressed in future submissions.
4. Make the applicant aware of any opportunities for coordinating the development with community policies,
programs, or facilities.
C. Site Review: The Board may schedule a site inspection in accordance with Section D.7. below.
1. The proposed site, including its location, size, and general characteristics.
2. The nature of the proposed use and potential development.
3. Any issues or questions about existing municipal regulations and their applicability to the project.
4. Any requests for waivers from the submission requirements.
D. Formal Application: Application Submission and Review Procedures.
1. The applicant shall submit eight (8) collated paper copies of all written materials in addition to eight (8) collated
printed plan sets and a digital copy of all plans and written materials in a digitally formatted document / application to
the Town's Code Enforcement Officer (CEO).
2. The applicant must prepare and submit a site plan review application, including the development plan and
supporting documentation that meets the submission requirements set forth below. This material must be submitted to
the Code Enforcement Officer twenty one (21) days prior to the meeting at which application will be considered.
3. At the time formal application is made, the Code Enforcement Officer shall give a dated receipt to the applicant and
shall notify by first-class mail all property owners within five hundred (500) feet of the parcel on which the proposed
development is located. Written notice of the pending application shall be provided to the Select Board, Town Manager,
Fire Chief, and other interested parties.
4. Within thirty (30) days of the receipt of a formal site plan review application, the Planning Board shall review the
material and determine whether or not the submission is complete. If the application is determined to be incomplete, the
Board, or designee, shall notify the applicant in writing of this finding, shall specify the additional materials required to
make the application complete, and shall advise the applicant that the application will not be considered by the Board
until the additional information is submitted to the Board. These steps, except the notification requirements, shall be
repeated until the application is found to be complete.
5. As soon as the Board determines that the application is complete, the Board, or designee, shall notify the applicant
in writing of this finding; meet the notification requirements of Section 6 below; and place the item on the agenda for
substantive review within thirty (30) days of this finding or at the next scheduled Planning Board meeting, whichever is
later.
Page 3 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
6. As soon as the application is found to be complete, the Planning Board may schedule a public hearing, and shall
notify the applicant on which the proposed development is located, per the requirements set forth in Section 8 below. If
the Planning Board does not schedule a public hearing, the Planning Board will allow those so notified in Section 3
above to comment on the application before deliberations on Section 9 of this Ordinance commence.
7. After the first meeting at which the application is considered, the Planning Board may hold an on-site inspection of
the site to review the existing conditions, field verify the information submitted and investigate the development
proposal. The Board may decide not to hold an on-site inspection when the site is snow covered or otherwise
inaccessible due to customary seasonable conditions. If an application is pending during a period when there is snow
cover or the site is inaccessible, the deadline by which the Planning Board shall take final action on the application as
specified in Section 8 below may be extended, which extension shall not exceed thirty (30) days after the Board is able
to conduct an on-site inspection. Written notice of the on-site inspection shall be provided to all parties entitled to
notice under Section 3 above.
8. The Planning Board shall take final action on said application within thirty (30) days of determining that the
application is complete or at the next scheduled Planning Board meeting, whichever is later. The Board shall act to
deny, to approve, or to approve the application with conditions. The Board may impose such conditions as are deemed
advisable to assure compliance with the standards of approval. In issuing its decision, the Planning Board shall make
written findings of fact establishing that the proposed development does or does not meet the standards of approval and
other requirements of the Town. The Board, or designee, shall notify the applicant, all officials who received notice
under Section 6 above, and all parties who requested to be notified of the action of the Board, including the findings of
fact, and any conditions of approval. This requirement can be met through the distribution of minutes of the meeting
containing the findings of fact and decision of the Board.
9. All time limits provided for in this section may be extended by mutual agreement of the applicant and Planning
Board.
E. Application Fee:
1. An application for site plan review must be accompanied by an application fee in such amount established by the
Application, License, Permit, and Other Fees Ordinance. The fee schedule will be provided to the applicant by the Code
Enforcement Officer upon request. This application fee must be paid to the Town of Stockton Springs and evidence of
payment of the fee must be included with the application.
2. If/when peer review consultants have been engaged by the Town to review any element of an application, as
discussed in Article 6: Review Standards -- A. General Standards of Review, a peer review escrow account shall
also be established.
3. Fee Schedule:
(a) Industrial SES:
$2500.00 application fee
$500.00 annual fee per SES location
(b) Residential SES:
$30.00 application fee
(c) Commercial SES:
$100.00 application fee
ARTICLE 5: REQUIRED APPLICATION INFORMATION FOR INDUSTRIAL SES
General Standards: The Planning Board shall approve, deny, or approve with conditions all applications for Industrial SES. The
applicant shall have the burden of proving that their application is in full compliance with the requirements contained within this
Ordinance. Applications for Industrial SES require Planning Board review and approval for land use. The submission shall
contain at minimum the following exhibits and information:
A. Application Information: Applications for site plan review must be submitted on application forms provided by the Town of
Stockton Springs. The complete application form, evidence of payment of the required fees, and the required plans and related
information must be submitted to the Code Enforcement Officer. The submission must contain at least the following exhibits and
information unless specifically waived in writing. The Planning Board may waive any of the submission requirements based upon
a written request of the applicant. Such a request must be made at the time of the pre-application conference or at the initial
Page 4 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
review of the application if no pre-application conference is held. A waiver of any submission requirement may be granted only if
the Board makes a written finding that the information is not required to determine compliance with the standards.
1. Name and address, telephone numbers, and email addresses of the owner of record, developer, copy of the deed to
the property, option to purchase the property, or other documentation to demonstrate right, title or interest in the
property on the part of the applicant. A copy of the purchase and sale agreement / lease agreement including all terms
shall be provided, with any financial / personal information being redacted.
2. The names and contact information of any agents representing the project and written authorization of such.
3. Project name, address, and Tax Map and Lot number.
4. Names, addresses and Tax Map and Lot number of all abutting property owners or within one thousand feet (1,000')
of the proposed subject property, including a plan illustrating abutting properties in relation to the project.
B. Financial and Technical Capacity: The applicant shall provide evidence of adequate financial and technical capacity to meet
the standards required by this Ordinance. The Applicant shall provide the cost of the proposed development and evidence of
financial capacity to complete it (i.e. letter from a bank, lending institution, or other similar source of financing; indicating the
name of the project, amount of financing required, and statement from the financing source for the funding of the project shall be
provided).
C. Project Narrative and Supplemental Information: The Applicant shall provide a detailed project narrative addressing the
following:
1. A description of the proposed solar energy generating system, including a narrative of the project; the project
location; the total electrical generation capacity of the solar energy system; dimensions of all components and
respective manufacturers; and a description of associated components and how the system and associated components
comply with the standards of this article.
2. A detailed description of the existing site conditions, including photographs from ground and sky perspectives and
vantage points from abutting properties shall be provided. It shall specifically address all issues related to the protection
of waterbodies, wetlands, endangered species, species habitat, and rare or endangered plants.
3. A detailed description of how the project will meet the screening standards contained within this Ordinance,
including a Landscape Plan. If any plantings are required to meet the screening standards contained within this
Ordinance, the Plan must be developed by a licensed landscape architect.
4. Information on any connections to the grid including evidence of meeting the local electric utility's transmission and
distribution interconnection requirements (this item may be a condition of approval if a copy of the application for
interconnection with the electric utility provider is submitted, but not yet approved prior to the determination of
approval). A plan illustrating the location of all connections and associated equipment from the proposed solar facility
to the electrical grid.
5. Documentation that the solar SES equipment has been approved under the UL certification program and that the
system complies with all applicable local, state and federal codes/regulations and the standards regarding signal
interference. Electrical component and connection information shall be in sufficient detail to allow for a determination
that it meets state electrical codes. The documentation shall include anticipated life expectancy of the project and its
components.
6. The anticipated construction date, construction timeline, construction completion date, and duration of the project.
7. Location, height, intensity and bulb type of all external lighting fixtures, the direction of illumination and methods to
eliminate glare affecting adjoining properties.
8. The Application shall include information related to any air pollution generated from the site, during construction
and when the facility is operational, including dust, fumes, vapors, and gases and includes a statement of compliance
with MDEP regulations.
9. The Application shall include information related to any noise, glare, or vibration generated from the facility during
construction and when the facility is operational.
Page 5 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
10. The Applicant shall demonstrate that the development has sufficient water available for the reasonably foreseeable
needs of the proposed use. The application shall further demonstrate that development will not lower the existing water
quality of on-site or adjacent rivers, streams, brooks, wetlands, ponds, lakes, or groundwater.
11. The Applicant shall provide information that any sewage generated on the property will be disposed of in
conformity with laws and rules of the Maine Department of Environmental Protection, and/or the State Plumbing Code
and other applicable regulations.
12. The proposed development will provide for the adequate and timely disposal of solid wastes and hazardous wastes,
during the construction and when the facility is operational. The plan shall demonstrate that all solid waste will be
disposed of at a licensed disposal facility having adequate capacity to accept the project's wastes and that all hazardous
waste will be disposed of at a licensed hazardous waste disposal facility and evidence of a contractual arrangement with
the facility shall be submitted.
13. The applications shall include a list of the approvals required from state and/or Federal agencies, such as MDEP,
MDIFW, Historical Preservation Society or The National Registry Commission (if applicable). The applicant shall
provide proof that actions have been taken to secure required permits. (Note: The Town will not issue permits for the
project until all required permits have been received by the Town)
D. Site Plan: An accurate scaled site plan of the subject property showing the planned location of the proposed solar energy
generating system and all associated facilities; property lines, adjoining streets and access; topographic contour lines; existing and
proposed buildings; fencing; structures; potential shade from nearby trees and structures; vegetation; driveways, parking and curb
cuts on the subject property; specifications for all proposed electrical cabling/transmission lines, associated equipment and
landscaping, including the tallest finished height of the solar collectors.
1. The site plan shall show any proposed off-site modifications to provide grid connections, or to maintain the proposed
solar energy system, and roadway access to the installation.
2. Perimeter Survey, signed and sealed by Professional Surveyor relating to reference points showing:
a) True and Magnet north point.
b) Graphic scale.
c) Corners of parcel.
d) Existing property markers.
e) Date of survey.
f) Property acreage / square footage.
g) Required setbacks.
h) Existing locations and dimensions of any utility, sewer, water lines, easements, drainage ways, public or
private rights-of-way.
E. Existing Conditions Documentation:
1. Name of the project, boundaries, and location map showing the site's location within the Town, North arrow and
scale of the plan. Depending on the location of the property, a larger-scale locus map may be required showing other
major developments in the area and other important natural resource features and the project's relationship to these
features.
2. Existing site conditions and proposed development site conditions including such as streams, rivers, wetlands, vernal
pools, and similar natural or environmentally sensitive features.
Page 6 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
3. High resolution satellite / aerial photos of the existing project site and digitally modified images of the site
illustrating all proposed tree / vegetation clearing areas, security fencing, development area, entrance/exits, and existing
and proposed property lines.
4. High resolution satellite / aerial photos of the site relative to Town with major local roadways and landmarks
identified.
5. Contour lines at two foot (2') intervals.
6. Existing and type of vegetation.
7. Easements, utilities, property / access rights, covenants, deed restrictions and similar.
8. All existing structures, land uses, property lines, including structures and access drives within one thousand feet
(1,000') from the development area as defined. The abutting properties shall be identified by property owner, address
and Tax Map and Lot number.
9. All plans or drawings shall be at a scale sufficient to allow review of the items listed, but in no case shall the scale
exceed fifty feet (50') to the inch for that portion of the tract of land being proposed for development.
FE. Proposed Conditions Documentation: The proposed condition plan shall include the following:
1. Existing and proposed topography at a minimum of two-foot (2') contours. The location of any one hundred (100)
year flood plain shall also be shown and base flood elevations given. Indicate areas within the proposed site and within
fifty-feet (50') of the proposed site, where ground removal or filling is required, and give its approximate volume in
cubic yards. The Planning Board may require a high-intensity soils map, prepared by a soils scientist licensed in the
State of Maine, if conditions warrant.
2. Natural features such as streams, rivers, wetlands and environmentally sensitive areas and required setbacks from
said natural resources. This shall include any resources impacted by the development area.
3. Wetland Delineation Mapping, including required setbacks and proposed impact areas.
4. The proposed vehicle access point to the site and sight lines from both directions shall be provided. All areas utilized
for parking / loading, during construction and operation of the facility shall be provided and shall meet the short and
long term needs of the project.
5. Location of all present and proposed utility systems, including sewerage system, water supply system, telephone,
cable and electrical systems.
6. All existing and/or proposed easements, utilities, property / access rights, and property covenants.
7. Solar panel areas and all associated equipment / structures, such as; transformers, and existing or proposed above
ground power lines shall be clearly identified on all plans including the maximum proposed heights of all structures.
G. Landscape / Screening Plan: Applications shall include detailed landscape / screening information. The plan/s shall include,
at minimum, the following:
1. Required and proposed setbacks of the proposed development area, in compliance with Stockton Springs existing
land use ordinance.
2. Existing vegetation / tree lines and proposed clearing areas, including any proposed selective cutting areas for solar
corridors.
3. Solar panels and associated equipment.
4. Existing natural features and showing all existing natural land features, trees, forest cover and water sources (ponds,
streams, lakes, brooks, wetlands and drainage retention areas) and all proposed changes to these features.
Page 7 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
5. The application shall provide a soil stabilization plan of the solar panel "development area". This plan shall explain
what vegetation is proposed to be removed, how it will be removed, existing and proposed topography and the proposed
methods of stabilizing the land beneath the solar panels.
6. Ideally the project will be completely screened utilizing existing vegetation which will remain for the duration of the
project. The project screening plan shall include photographs of existing vegetation surrounding the development area
taken* from the adjacent roadway and abutting properties. For developments that can't immediately meet the screening
requirements of this Ordinance utilizing existing vegetation, the Planning Board may consider an alternative plan. This
shall include a landscape plan approved by the CEO which demonstrates that it will conform to the standards and intent
of this Ordinance. Renditions of the buffer area shall be provided illustrating the proposed landscaping at installation
(prior to facility operation) and comparisons of the growth of the proposed plantings that can reasonably be expected
after five (5) years and ten (10) years of planting.
H. Environmental Impact Assessment and Stormwater Management: Applications shall include at minimum, the following
information for the Planning Board to evaluate the environmental impacts of the proposed development:
1. A Stormwater Management Plan, prepared by an engineer licensed in the State of Maine shall be provided. Any site
plan triggering MDEP Chapter 500, Stormwater Management Rules, shall conform to those regulations. The applicant
shall obtain all necessary MDEP permits before the Planning Board grants project approval, unless the Planning Board
grants such approval with conditions.
2. The Stormwater Drainage Plan shall show the existing and proposed method of handling storm water run-off, the
direction of flow of the run-off, through the use of arrows, drainage ditches, swales, retention basins, and storm sewers.
3. The Application shall include an endangered species inventory and review, and eventual approval, from Main
Department of Inland Fisheries and Wildlife (MDIFW) Maine Department of Environmental Protection (MDEP) and
other associated agencies involved with the application review and permitting prior to Final Plan approval.
4. A wildlife corridor shall be provided, via a six inch (6") gap under the required security fencing, which shall be
provided to allow wildlife to retain access through the site.
5. The narrative and / or mapping shall also specifically address anticipated temperature increases around proposed
vegetation clearing areas and their relationship to adjacent wetlands, streams and other waterbodies and the endangered
species who live in and around them.
6. The Application shall provide a detailed erosion control plan, by a licensed engineer, discussing and illustrating the
protective measures that will be undertaken to minimize soil erosion and sedimentation of watercourses and water
bodies utilizing best management practices specified in the Maine Erosion and Sediment Control Best Management
Practices Manual as amended.
I. Public Safety Submittal Requirements: The Applicant for Industrial SES shall provide a detailed narrative and associated
plans regarding public safety and emergency site access. The following information shall be included in the Application:
1. The Application shall illustrate that the layout of the facility provides for the safe movement of passenger, service,
and emergency vehicles throughout the site. The plan shall show that all-season emergency access, snow removal and
storage, and delivery and collection services can be safely accommodated. The roadway should also be maintained in
good working order to prevent obstruction or damage to Town vehicles. An unimpeded emergency vehicle turnaround
area shall be provided, and illustrated on all plans. The turn-around shall accommodate the largest emergency
apparatus. The site safety and access plan shall be reviewed and approved by the Stockton Springs Road Commissioner
and Fire Chief or their appointed designee prior to final plan approval.
2. The plan shall conform to the following:
a) A security fencing plan shall be provided, illustrating the locations of all proposed fences, fence openings /
gates, and fully dimensioned interior access lanes shall be provided.
b) All proposed equipment / activities should be located completely within enclosed fencing.
c) Knox Key / Combination Boxes shall be provided at all gates and access points and shall be illustrated on
the submitted emergency access site plan.
Page 8 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
d) Fencing shall be installed with a six inch (6") gap at the bottom to allow wildlife to utilize the site while
not being trapped inside the site. The plans shall include fully dimensioned security fence details including,
access gate details, and all required warning signage.
3. The application shall provide an emergency response plan with inventories of all equipment/ chemicals onsite,
equipment shut down locations and methods and all emergency procedures. The plan requires review and written
approval from the Fire Chief prior to final approval being granted by the Planning Board.
4. The Application shall include a Property Maintenance Plan which shall include long and short term maintenance
such as painting, structural repairs, repairing damaged panels and integrity of safety and security measures.
5. The locations of all associated electrical equipment such as transformers, equipment pads, etc. shall be illustrated on
submitted plans. All equipment utilized in the operation shall be illustrated on all site plans and be fully dimensioned
on detail sheets, including all above ground utilities and their means of support.
6. There should be minimal, if any lighting, since these will mostly be in rural areas. Any lighting should be fully cut off, downward
directed, and not cast onto neighboring properties or create glare in roadways
7. Solar Panels shall be constructed of anti-reflective materials and a statement of such shall be included with the
Application. The manufacturer's detailed description of the materials included and data regarding the degree of
anti-reflectivity will be provided. Any hazardous materials used in the solar panels will be identified.
J. End of Life --- Decommissioning and Site Restoration Plan: The proposal shall include a project decommissioning plan that
includes:
1. A chronicle and timeline of the entire decommissioning process, from the date when the facility ceases energy
production, through the Town's release of the financial surety required for the project.
2. A list of the equipment and materials that will be removed from the property, and any materials used for the
operation, decommissioning and site restoration that are proposed to remain on site. Only decomposable organic
materials may be disposed of on site.
3. A landscape plan, approved by the CEO, showing the improvements that will be undertaken to revegetate and
stabilize all areas that were disrupted by the project and closure of such. The plans shall include photographs of the
pre-installation conditions of the site and renderings of the site post-restoration.
4. All landscape materials utilized to meet the buffer standards for the project shall remain on the property until site
re-development plans have received approvals from the Town.
5. A detailed decommissioning and site restoration estimate shall be provided in compliance with Article 7: D.
Decommission.
ARTICLE 6: REVIEW STANDARDS
A. General Standards of Review:
1. The Planning Board shall approve, deny, or approve with conditions all applications for the development of a SES.
The applicant shall have the burden of proving that his/her application is in compliance with the requirements of this
Ordinance. After the submission of a complete application, the Planning Board shall approve an application or approve
it with conditions if it makes a positive finding based on review of the standards contained within this Ordinance.
2. The Planning Board shall process and review each application in a similar and equitable manner. In order to
accomplish this, the Planning Board shall follow the procedures listed in this section for each stage of the review
process.
3. In addition, at any stage of the review process, when the Planning Board determines it is necessary to ensure
compliance with the standards of this chapter, the Planning Board shall have the authority to refer, at the applicant's
expense, all Industrial SES applications to the following: Fire Chief, Town Attorney, and/or qualified peer review
Page 9 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
professionals of the Town's choosing, when the proposed site plan is deemed significant because of its size, location,
effect on the environment, complexity of design, traffic impact, or other similar factors. At such time as the Planning
Board decides to refer a proposed site plan to any consultant for review, it shall inform the applicant, in writing, of its
decision and of the estimated peer review fee/s. The Planning Board shall take no further action to consider the
application and all time periods requiring action by the Planning Board shall be stayed until the applicant pays to the
Code Enforcement Officer the estimated peer review fee. The Planning Board shall inform the applicant of the actual
fee and receive payment for any outstanding balance or refund the difference, if any, prior to making a final decision on
the proposed Application.
4. Peer reviewer/s, such as those named above, may further be hired by the Town, as professional consultants, to inspect
the improvements performed before the expiration date of the performance bond or, before issuance of a Certificate of
Operation. If any of the required improvements have not been constructed in accordance with plans and specifications
filed by the applicant, he/she shall report to the Code Enforcement Officer and the Select Board. The Town shall then
notify the applicant and, if necessary and applicable, the bonding company and take all necessary steps to preserve the
municipality's rights under the bond.
5. Applications that received Planning Board approval under this section shall expire if elements of the site work
beyond clearing of the site for new development or changes to an existing development are not commenced within one
year from the date of Planning Board Approval, or if the work or change is not substantially completed within two (2)
years from the date the approval was granted.
6. Renewal of a permit shall be treated as a new application at the Board's discretion and shall be subject to all
provisions of this Ordinance. The Planning Board may grant a maximum of two (2), six (6) months project approval
extensions, providing;
a) The extension request is made in writing.
b) The written request is made a minimum of thirty (30) calendar days in advance of project approval
expiration.
c) The extension request includes an explanation to why the action is being sought and the reasoning why the
Board should grant the extension.
d) The Planning Board may not grant an extension request if it would prohibit a pending application for
another Industrial SES from moving forward.
7. Minor changes in approved plans necessary to address field conditions or structure orientation may be authorized by
the Code Enforcement Officer provided that any such change does not affect the standards of this Ordinance or alter the
intent of the approval. A request for any change to an approved plan shall be in writing to the Code Enforcement
Officer. In making the determination to approve any change to an approved plan, the Code Enforcement Officer shall
consult with the Planning Board Chair or the Chair's designee. All approvals for minor changes to approved plans shall
be in writing by the Code Enforcement Officer. A copy of the written approval and revised site plan shall be filed with
the Planning Board within thirty (30) calendar days from the date of the written approval. Approvals of site plans are
dependent upon and limited to the proposals and plans contained in the application and supporting documents
submitted and affirmed by the applicant. Any variation from the plans, proposals and supporting documents, except
minor changes as permitted above, is subject to review and approval by the Planning Board.
8. The Planning Board may waive any submission requirements and non-dimensional standards of this Ordinance,
provided that such waiver will not have the effect of nullifying the purpose of this Ordinance or any other ordinance or
law. In granting any waiver, the Planning Board shall require such conditions as will, in its judgment, substantially
secure the objectives of the requirements so waived.
9. All construction, performed under the authorization of a building permit or Certificate of Operation issued for a
development within the scope of this chapter, shall be in conformance with the approved site plan.
10. The application will not be approved or approved with conditions unless the Code Enforcement Officer has been
provided with written confirmation that the public utility company to which the system will be connected has been
informed of the customer's intent to install a grid connected system. The Code Enforcement Officer will not issue a
Certificate of Operation until the owner provides a copy of the final inspection report and connection approval from the
utility company.
Page 10 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
11. The Application shall conform to the standards within the criteria for approval contained within this Ordinance.
12. The determination of compliance with the screening requirements contained within the Ordinance shall be
determined by the Planning Board and enforced by the CEO.
13. An appeal of a decision, condition or interpretation by the Planning Board must be submitted to the Board of
Appeals within 30 days after the date of the Planning Board vote which affects the decision, condition or interpretation
unless specifically listed within the Ordinance. See ARTICLE 10 - APPEALS.
B. General Restrictions and Dimensional Standards: Due to the unique nature of Industrial SES and the need to screen the use
from adjacent roadways and residential uses, the following restrictions and dimensional standards shall apply:
1. Dimensional standards are as follows:
a) The Town will authorize a total maximum development area of hundred (100) acres of land dedicated to
Industrial SES. Once the maximum has been reached, no additional applications will be accepted unless and
until the Ordinance is amended and approved at a Town Meeting, or an existing Industrial SES has been
decommissioned.
b) The maximum development area for each Industrial SES, as defined in this Ordinance, shall be a
maximum of ten (10) acres.
c) The development area of all ground mounted Industrial SES shall be setback a minimum of one hundred
fifty feet (150') from all roadways and abutting properties.
d) Solar panels shall not exceed a maximum of fifteen feet (15') in height when oriented at maximum tilt to
the vertical.
e) All associated equipment / structures, such as transformers, and similar shall not exceed fifteen feet (15") in
height and be located so as not to be unsightly or hazardous to the public and will be landscaped or otherwise
buffered so as to screen the components from public view.
f) The development must utilize below ground power lines where feasible, from the property connecting to
the electrical network, but it shall be a maximum of fifty feet (50') in height from the existing grade.
g) Industrial scale battery storage (battery farm) is not permitted.
2. In addition to the above dimensional standard, Industrial SES shall be screened / buffered from roadways and
abutting properties. Whenever feasibly possible natural features and vegetation shall be retained in order to adequately
screen the site. Setbacks and screening shall be based upon the amount of existing vegetation and/or natural features
being preserved. As such setbacks from all property shall meet one of the below setback and screening standards:
a) If the property has an existing visual buffer which is proposed to remain, which will screen the use from
abutting properties and roadways, the development area shall be setback a minimum of one hundred fifty feet
(150'), providing:
1) The setback / buffer is located entirely on the property being utilized for the development or
within the lease area. The natural one hundred fifty foot (150') minimum buffer / screen will remain
intact and protected in place for the life of the Industrial SES installation.
2) The buffer may consist of any combination of natural features such as existing vegetation, rock
outcroppings, elevation changes and similar natural features.
3) If the Planning Board finds that small gaps within the natural buffer exist, the Applicant may be
required to submit a landscape plan if infill plantings are required.
4) Soil Stabilization: All areas proposed to be cleared for solar panel installation shall include a soil
stabilization plan. The plan shall include native ground covering grasses / plantings.
Page 11 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
b) Plantings of native plants are strongly encouraged with a focus on pollinators.
c) For developments that can't meet the screening requirements of this Ordinance, utilizing existing
vegetation in combination with natural features, the Planning Board may consider an alternative plan. The
Applicant shall demonstrate that it will meet the intent of the screening requirements within the Ordinance.
This "alternative plan" shall provide, at minimum the following:
1) A landscape plan shall be provided. This plan shall demonstrate that the site can meet the
screening requirements of this Ordinance by providing a naturalistic designed landscape plan using
a mix of native evergreen and deciduous trees, shrubs and understory vegetation. The intent of the
landscape plan is to provide the fullest visual screening of the facility in the shortest period of time,
while providing plantings that will provide fuller / denser coverage over time.
2) The development area shall be surrounded by a planting zone, a minimum of fifty feet (50')
wide. This planting zone may be located anywhere within the required one hundred fifty feet (150')
setback area to provide the most visual screening of the development area as feasible as possible.
The planting area shall be placed so as to not require any selective cutting / trimming, for the
creation of shade management / solar corridors in the future.
3) All plantings shall be staggered, to allow room for growth, and a planting zone designed as a
natural feature with interspersed plantings of various heights and species.
4) All required plantings shall be installed prior to the facility being operational and shall be
maintained for the duration of the project. A note shall be placed on the landscape plan stating that
"all required plantings that become damaged, diseased, dead or dying shall be replaced with the
same / similar plantings (size & species) at the time of replacement".
ARTICLE 7: FINANCIAL RESPONSIBILITIES
A. Liability and Environmental Insurance: The Development Owner shall maintain a current general liability policy for the
SES that covers bodily injury and property damage with limits in an amount commensurate with the scope and scale of the SES
Development. The Applicant annually shall provide certificates of insurance to the Town of Stockton Springs.
B. Escrow: The Planning Board, with notice to the applicant, will hire independent expert consultants or specialists as they may
deem necessary for advice in carrying out the provisions of this ordinance. All costs and expenses shall be paid for by the
applicant through an escrow account. The escrow account shall be established when requested by the Town, for an initial amount
of ten thousand dollars ($10,000) in the name of the Town. If the escrow amount falls below fifty percent (50%) of the original
required deposit amount, full replenishment is required within thirty (30) calendar days of notice to the applicant. The Town
reserves the right to cease review if escrow amounts are insufficient and the applicant fails to replenish the account upon request
by the Town.
C. Abandonment:
1. Industrial SES, or a portion thereof, shall be decommissioned if it ceases to generate electricity for a continuous
period of twelve (12) months after the start of operation. An extension of up to a year may be granted by the Planning
Board depending on extenuating circumstances.
2. As part of permitting Industrial SES, the applicant shall submit a Decommissioning Plan to the Town with a cost
estimate for the costs of decommissioning.
D. Decommissioning: Plan shall include financial assurance, naming the Town as beneficiary, to cover the costs associated with
decommissioning the abandoned solar energy system through the life span of the facility. An independent and certified licensed
Professional Engineer, selected by the Town, shall be retained to help establish the cost of decommissioning, without regard to
salvage value, and itemize the estimated major expenses to restore the site to the requirements of the approved site restoration
plan or MDEP approval, if applicable, or the requirements of the MDEP in effect at the time of decommissioning, whichever is
more restrictive to the owner. The Decommissioning Plan will also include a defined timeline for the decommissioning process.
1. If the owner fails to complete the decommissioning of the Industrial SES within the established timelines, the Town
may take such action as necessary (including court action, with all legal costs to be paid by the owner) to secure the
posted decommissioning funds and to complete the decommissioning work. In the case of abandonment, the Town shall
Page 12 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
utilize the decommissioning funds to decommission the solar energy system and take such action as necessary,
including court action, to secure funds and to ensure completion of the decommissioning should the posted
decommissioning fund not be sufficient to complete decommissioning.
2. The Planning Board shall not approve an application for an Industrial SES until the applicant has submitted an
executed Decommissioning Access Agreement that authorizes the Town, or its agents, to enter onto the solar energy
system property for the purposes of implementing the Decommissioning Plan upon the occurrence of a triggering event,
as described in the Decommissioning Plan, that requires the implementation of decommissioning activities and the
owner fails or refuses to commence decommissioning activities, such that the Town is authorized to access the bond or
other financial guarantee to permit the Town to decommission the facility. The Decommissioning Access Agreement
shall run with the land and shall be executed in a form suitable for recording in the County Registry of Deeds. Once a
solar energy system has been decommissioned, the Town will release the Decommissioning Access Agreement and
notify the County Registry of Deeds.
3. The financial assurance of decommissioning funds may be in the form of a performance bond, surety bond, or other
form of bonded assurance, and shall demonstrate the financial assurance to the satisfaction of the CEO during
permitting phases, and to the Select Board thereafter. Prior to the issuance of a Building Permit, the owner shall post
and maintain decommissioning funds in an amount no less than one hundred fifty percent (150%) of the cost of
decommissioning the project to be constructed under that Building Permit, as well as the cost to restore the site area
developed under the permit. The financial assurance shall be maintained at one hundred fifty percent (150%) for the rest
of the life of the solar energy system regardless of change of ownership. The CEO will inform the owner of the amount
of coverage required at each two (2) year update/revaluation, described herein and the owner will provide proof of
required coverage within thirty (30) calendar days of notification. Failure to do so will cause the Certificate of
Operation to be rescinded.
4. Prior to final decommissioning, the owner of the Industrial SES shall submit a final decommissioning plan to the
CEO for final review and approval. No decommissioning shall begin without CEO approval. The final plan shall
include but not be limited to the following:
a) Anticipated start date of decommissioning.
b) Anticipated completion date of decommissioning.
c) Methods to remove all parts of the solar energy system including foundations and how they will be
disposed of or recycled.
d) Areas and methods to restore disturbed land areas.
e) Cost for decommissioning based on Sub-Section 2 above.
f) All solar energy system materials shall be disposed of or recycled in a licensed facility; only rock, soil, and
vegetation may be disposed of on-site. All foundations shall be removed to a minimum of twenty-four inches
(24) below ground, except where the CEO finds that at least twenty-five percent (25%) of the area where the
solar energy system is located was farmed, has soils designated as significant for farming, or is intended to be
farmed, in which case foundations shall be removed to forty-eight inches (48") below ground.
5. Any proposed changes to the approved Decommissioning Plan, any changes that impact Bond, Escrow,
Decommissioning, or Safety need to be immediately communicated to and approved by the CEO.
E. Performance Guarantee / Financial Assurance Bond:
1. In the event the owner is unable to secure an underwritten bond, etc. due to no underwriting entities existing, the
Select Board may consider accepting one hundred fifty percent (150%) funded escrow account as an alternative. The
escrow account would be opened by the owner prior to construction at a financial institution approved by the Select
Board, in the name of the Town, to be managed by the Town Treasurer, in an amount to be established initially and at
every two (2) year update/revaluation as described in this article.
ARTICLE 8: INSPECTIONS / UPDATES TO APPROVED PLAN / REVALUATION: For Industrial SES
Page 13 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
A. Anniversary Submission to CEO: On every second (2nd) anniversary of the date of Certificate of Operation issuance, the
owner shall submit to the CEO the following updated materials:
1. Updated Engineer's cost estimate for decommissioning of the project.
2. Updates for emergency or safety plans.
3. An Inspection Fee/Enforcement Fee in an amount established by the Select Board to cover anticipated solar energy
systems-related inspection/enforcement costs during the coming two year period, based on its past experience with such
costs. The time span between the two (2) year Update/Revaluation requirements may be changed at the discretion of the
CEO. The owner must be informed in writing within seven (7) calendar days of the decision being made, including the
reason(s) for the change and the new date for the Update.
4. Proof that all financial responsibilities described above are fulfilled.
B. Reporting to the Town: The reports to the Town shall include the following:
1. Dates and times of all scheduled or unscheduled inspection and maintenance visits.
2. Items identified for maintenance, replacement or repair and date / action taken towards resolution.
3. All safety and security incidents, with or without emergency services involvement.
4. Equipment failures and new equipment installed, including storage and monitoring systems since the initial approval
or last update.
ARTICLE 9: ENFORCEMENT, ADMINISTRATIVE CONSENT AGREEMENT, AND LEGAL ACTIONS
A. Enforcement: It shall be the duty of the Code Enforcement Officer to enforce the provisions of this Ordinance. If the Code
Enforcement Officer shall find that any provision of this Ordinance is being violated, they shall notify by registered mail the
property owner, responsible for such violation, indicating the nature of the violation and ordering the action necessary to correct
it, including discontinuance of illegal use of land, buildings, or structures. A copy of such notices shall be maintained as a
permanent record.
B. Administrative Consent Agreement: The Select Board, or their authorized agent, are hereby authorized to enter into
administrative consent agreements for the purpose of eliminating violations of this Ordinance and recovering fines without Court
action. Any person or corporation who violates any of the provisions of this Ordinance or fails to comply with any of the
requirements thereof shall, be punished by a fine of not less than one hundred dollars ($100) nor exceed twenty five hundred
dollars ($2,500) per day, as determined by the Town via Consent Agreement. Each day on which such violations shall continue
and shall constitute a separate offense. If the Consent Agreement process is initiated, but ultimately fails to result in an
agreement, the Town may initiate judicial proceedings to achieve a resolution. The Town is not obligated to negotiate or enter into
such agreement, and may initiate and / or continue judicial proceedings, including daily fines, at any time while the violation/s
exists. In considering the terms of any administrative consent agreement the Selectmen shall consult with the Code Enforcement
Officer. Such agreements shall not allow an illegal structure or use to continue unless there is clear and convincing evidence that
the illegal structure or use was constructed or conducted as a direct result of erroneous advice given by an authorized municipal
official and there is no evidence that the owner acted in bad faith, or unless the removal of the structure or use will result in a
threat or hazard to public health and safety or will result in substantial environmental damage.
C. Legal Actions: When the above actions do not result in the correction or abatement of the violation or nuisance condition, the
Select Board, upon notice from the Code Enforcement Officer, are hereby required to institute any and all actions and
proceedings, including seeking injunctions of violations and the imposition of fines, that may be appropriate or necessary to
enforce the provisions of this Ordinance in the name of the municipality, under 30-A M.R.S.A. § 4452.
D. Change of Ownership: Within 30 business days of a change in ownership, the new owner(s) or designated
representative shall submit a memo to the Town of Stockton Springs stating they have reviewed the SES Ordinance, the
application for the solar farm acquired with all of its related documentation and will abide by the requirements in these
documents.
Page 14 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
ARTICLE 10: APPEALS: The owner of the property, abutting landowner, or any person of standing aggrieved by a decision of the CEO
or the Planning Board under this Ordinance may appeal the decision to the Board of Appeals. Written notice of an appeal must be filed with
the Board of Appeals within thirty (30) calendar days of the decision. The notice of appeal shall clearly state the reasons for the appeal and
that the Appellant has legal standing.
ARTICLE 11: DEFINITIONS
ABANDONMENT: Industrial (SES), or a portion thereof, shall be decommissioned if it ceases to generate electricity for a continuous
period of twelve (12) months.
ABUTTER: The owner(s) of property within one thousand feet (1,000') of the perimeter of the Solar Energy System (SES) installation site
and any additional landowners as deemed necessary by the Planning Board, regardless if the properties are separated by a public or private
street or right of way. The owners of property shall be considered to be the parties listed by the Tax Assessor of Stockton as the ones against
whom taxes are assessed.
ACCESSORY STRUCTURE OR USE: A use or structure which is customarily both incidental and subordinate to the principal structure
and is on the same lot only. Accessory uses, when aggregated, shall not subordinate the principal use of the lot. A deck or similar extension
of the principal structure or a garage attached to the principal structure by a roof or a common wall is considered part of the principal
structure.
ADMINISTRATIVE CONSENT AGREEMENT: Administrative Consent Agreement authority allows violations to be resolved in a
negotiated settlement without the need for going to court. The Agreements are voluntary, and the terms and conditions of such agreements
are the product of a negotiation process between the violator, the Town and / or other regulatory agencies. If the Administrative Consent
Agreement process is initiated, but ultimately fails to result in an agreement, the Town may initiate judicial proceedings to achieve a
resolution. The Town is not obligated, to negotiate, or enter into such agreement, and may initiate and / or continue judicial proceedings,
including daily fines, at any time while the violation/s exists.
AGGRIEVED PARTY: An owner of land whose property is directly or indirectly affected by the granting or denial of an approval, permit
or waiver under this Ordinance; a person whose land abuts or is within one thousand feet (1000') of the project, or is across a road or street
or body of water from the project for which an approval, permit or waiver has been granted; or any other person or group of persons who
have suffered particularized injury as a result of the granting or denial of such approval, permit or waiver.
APPLICANT: A person or entity who applies for a Solar Energy System (SES). An applicant can be the landowner of record or (SES)
energy provider or agent of record with the landowner's (or other legally designated representative) written permission.
BATTERY BACKUP SYSTEMS: Large capacity battery that is grid or solar charged and connected to grid connected electrical system.
This connection can be either manual or automatic transfer switch with the intent of powering a home or business automatically during a
utility outage or manually as an alternative to utility power.
BONDING: A surety bond or guarantee. See - SURETY:
BUFFER: A way to screen the more intensive land use from the less intensive land use through the installation of landscaping, mounding,
and/or fencing materials. Screening consists of a planting strip, existing vegetation, a slightly opaque wall or fence, or combination thereof,
to the reasonable satisfaction of the Planning Board.
BUILDING PERMIT: The official written document to be displayed at the construction site that grants the authorization for the
construction. This document is issued by the Code Enforcement Officer and required for subsequent operating permits.
CEO: The Town of Stockton Springs' duly appointed Code Enforcement Officer. (See: CODE ENFORCEMENT OFFICER).
CERTIFICATE OF OPERATION: The permit granted by the Stockton Springs' Code Enforcement Officer allowing the (SES) owner to
bring the installation online to generate power at the property to the utility grid. Should operators fail to operate as the application was
approved or in an unsafe manner the Code Enforcement Officer may rescind the Certificate of operation after notice and a hearing with the
Owner, CEO and any additional relevant participants as requested by the Owner or CEO.
CODE ENFORCEMENT OFFICER (CEO): A person certified under Title 30-A MRSA, Section 4451 (including exceptions in
subsection 4451, paragraph 1) and employed by a the Town of Stockton Springs to enforce all applicable comprehensive planning and land
use laws and ordinances.
Page 15 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
COMPLETE APPLICATION: An application shall be considered complete upon submission of the required fee and all information
required by this Ordinance and by a vote by Planning Board that an application has been deemed complete. The Planning Board shall issue
a written statement to the applicant upon its determination that an application is complete.
CONSENT AGREEMENT: See ADMINISTRATIVE CONSENT AGREEMENT.
CONSTRUCTION: Includes building, erecting, altering, reconstructing, moving upon or any physical operations on the premises which
are required for construction. Excavating, fill, drainage, and the like, shall be considered a part of construction.
DECOMMISSIONING: The process of removing the solar energy system and restoring the site to the standards described in the
applicant's Town permit, the Maine DEP approval, if applicable, or the state's standards in effect at the time of decommissioning,
whichever are more restrictive to the owner.
DEVELOPMENT AREA: The total area of the (SES) contained within the security fencing of the development. Properties are limited to
a single (SES) with a maximum of 10 acres of development area.
DEVELOPMENT AREA - TOTAL ALLOWABLE ACRAGE: The Town will authorize a maximum of 100 acres of allocated land to
Industrial SES development within the Town of Stockton Springs . Once the 100 acre maximum has been reached, no additional
applications will be accepted. Each application is limited to a maximum of 10 acres of development area.
DRIVEWAY: A vehicular access-way serving one (1) lot that provides access to a street.
EXPANSION OF USE: The increase of the footprint of the development area, structures or land area devoted to a particular use including
any increase in energy production beyond approved limits.
FOUNDATION: The supporting substructure of a building or other structure, excluding wooden sills and post supports, but including
basements, slabs, frost walls, or other base consisting of concrete, block, brick or similar material. This term includes any method of
support / connection of solar panels systems to the ground.
FULL CUT-OFF LIGHTING FIXTURES: All light fixtures must be fully shielded and emit no light above the horizontal plane. There
shall be no sag or drop lenses, side light panels, uplight panels, or similar lighting that is not dark sky compliant.
GAME FENCING: a fence constructed to a standard which is substantially more than a stock fence and which effectively controls the
movement of wild animals out of or into defined area
GROUND MOUNTED SOLAR ENERGY SYSTEM: A Solar Energy System that is structurally mounted to the ground and is not
roof-mounted.
GUARANTEE: See Surety.
HIGH INTENSITY SOIL SURVEY: A map prepared by a Certified Soil Scientist, identifying the soil types down to 1/8 acre or less at a
scale equivalent to the subdivision plan submitted. The soils shall be identified in accordance with the National Cooperative Soil Survey.
The map shall show the location of all test pits used to identify the soils and shall be accompanied by a log of each sample point identifying
the textural classification and the depth to seasonal high water table or bedrock at that location. Single soil test pits and their evaluation for
suitability for subsurface waste water disposal systems shall not be considered to constitute high intensity soil surveys.
INDUSTRIAL SCALE BATTERY FARM: Shall include, but not be limited to, any battery types or similarly designed electrical energy
storage devices or units that store the electrical energy developed by the (SES) and allows for the discharge of this electrical energy into an
electrical grid operated for the purposes of supplying electricity. Units of this type may be self-contained or constructed or placed within a
building or container.
LOT: An area of land in one ownership, or leasehold, with ascertainable boundaries established by deed or instrument of record, or a
segment of land ownership defined by lot boundary lines on a land subdivision plan duly approved by the Planning Board and recorded in
the County Registry of Deeds.
LOT COVERAGE: The percentage of the lot covered by all buildings, driveways, parking areas, other areas where vegetation is removed,
and all of the area enclosed within the security fencing.
MDEP: Maine Department of Environmental Protection.
Page 16 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
MDIFW: Maine Department of Inland Fisheries and Wildlife
MOUNTING: The manner in which a Solar Energy System is affixed to the ground, a wall, or a roof.
M.R.S.A.: Maine Revised Statutes Annotated.
OWNER: The owners of property shall be considered to be the parties listed by the Tax Assessor of Stockton Springs as the ones against
whom taxes are assessed. The owner holds the ultimate responsibility for any actions taken on the property that are in violation of any
federal, state and local codes and ordinances.
PEER REVIEW PROFESSIONALS: Independent expert consultants such as attorneys, licensed engineer/s, landscape architects, land
use consultants, traffic engineers, and similar professionals recognized for their relevant expertise in reviewing development applications of
this nature, when it is deemed significant because of its size, location, effect on the environment, complexity of design, traffic impact, or
other similar factors. Peer Review Consultants review applications on behalf of, and report their findings directly to, the Town, and their
associated fees are paid from an established Peer Review Escrow Account.
PEER REVIEW ESCROW ACCOUNT: The financial account established, by the Applicant, for the Peer Review Professional fees to be
paid from, for their reviewing the application on behalf of the Town. The Planning Board or Select Board may, with notice to the applicant,
hire independent expert consultants or specialists as they may deem necessary for advice in carrying out the provisions of this ordinance.
PERFORMANCE GUARANTEE: A performance bond or surety bond held by the Town of Stockton Springs; issued by an insurance
company or bank to guarantee satisfactory completion of the project by the applicant; also denotes a collateral deposit of "good faith
money".
PERSON OF STANDING: any "persons aggrieved," which state courts have interpreted to include neighbors of the property in question,
tenants, or taxpayers, provided they can show they are specially affected compared to the public at large.
RARE AND ENDANGERED SPECIES: Endangered, threatened or rare plants, animals or communities, identified by the Maine Natural
Areas Program.
ROAD: Any public or private way designed for vehicular access, other than driveways, farm roads, trails or logging roads. The term
"roads" includes synonymous words including, street, avenue, highway, lane, way, etc.
ROOF-MOUNTED SOLAR ENERGY SYSTEMS: A Solar Energy System that is mounted on the roof of a building or structure.
SETBACK: The minimum horizontal distance from a lot line, right of way or normal high-water line to the nearest part of a structure,
road, parking space or other regulated object or area.
SES: Solar Energy System (SES)
SIGNIFICANT WILDLIFE HABITAT: The following areas to the extent that they have been mapped by MDIFW;; habitat for species
appearing on the official State or Federal lists of endangered or threatened species; high and moderate value deer wintering areas and travel
corridors as defined by MDIFW; high and moderate waterfowl and wading bird habitats, including nesting and feeding areas as defined by
MDIFW; and as may be identified in the Stockton Springs Comprehensive Plan.
SOLAR ARRAY: Multiple solar panels combined together to create one Solar System.
SOLAR ARRAY DEVELOPMENT AREA: The aggregate area occupied by the complete assembly of a ground mounted Solar Energy
System, including but not limited to:
1. The solar photovoltaic (PV) technology (included but not limited to, solar panels) and associated mounting hardware and equipment.
2. Battery Backup Systems and associated structures.
3. All inter-panel space.
4. All impervious surfaces. The Solar Array Development Area does not include areas adjacent to the ground mounted Solar Energy
System that must, by virtue of an easement, lease condition, or other legal instrument be kept free of structures or vegetation (other than
grass) in order to capture the unobstructed flow of solar insolation (sunlight) for the Solar Energy System, and does not include driveway(s)
required to access the solar array development area.
Page 17 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
SOLAR CORRIDOR: The practice of selective cutting / pruning trees to capture the unobstructed flow of solar insolation (sunlight) by
the solar photovoltaic (PV) technology. Solar corridors may not encroach upon required buffering areas.
SOLAR ENERGY: Radiant energy (direct, diffuse and/or reflective) received from the sun.
SOLAR ENERGY SYSTEM (SES): A solar energy system whose primary purpose is to harvest energy by transforming solar energy into
another form of energy or transferring heat from a collector to another medium using mechanical, electrical, or chemical means. It may be
roof-mounted or ground mounted, and may be any one of the following three types:
1. Residential SES: A system used for producing energy at the property where the applicant resides. Residential systems will be completely
roof top mounted, or a maximum of one half (%) acre in ground surface.
2. Commercial SES: A system used for producing energy at a property where the applicant operates a business or where the applicant rents
or leases space to another individual or entity.
3. Industrial SES: A system used primarily for the production of energy for the power grid.
SOLAR ENERGY SYSTEM, Ground Mounted: A Solar Energy System that is structurally mounted to the ground and is not
roof-mounted.
SOLAR ENERGY SYSTEM, Roof-Mounted: A Solar Energy System that is structurally mounted to the roof of a structure.
SOLAR PANEL: That part or portion of a solar energy system containing one or more receptive cells or modules, the purpose of which is
to convert solar energy into electricity.
START OF CONSTRUCTION: The time when all required approvals have been obtained; bonding and inspection fees have been
established; applicable Conditions of Approval have been met; building and inspection fees paid and a building permit is granted to the
owner by the Code Enforcement Officer to commence with construction on the site including land preparation, such as clearing, grading
and filling or the first placement of permanent construction of a structure on a site, such as the pouring of a slab or footing.
STRUCTURE: Anything constructed or erected, the use of which requires a fixed location on or in the ground or in the water, or an
attachment to something having a fixed location on the ground, including buildings, signs, commercial park rides and games, carports,
porches, and other building features, including stacks and antennas, but not including sidewalls, fences, driveways, parking lots, and field or
garden walls or embankment retaining walls.
SURETY: Surety bond or guarantee; a pledge or formal promise made to secure against loss, damage, default or for the fulfillment of an
obligation; a guarantee or security; the payment of a debt. The type of surety /guarantee shall be approved by the Select Board and may
include any of the following: a certified check payable to the Town of Stockton Springs, a savings account passbook issued in the name of
the Town or a faithful performance bond running to the Town of Stockton Springs; issued by a surety company authorized to do business in
Maine.
UNDERSTORY VEGETATION: The vegetation layer of trees and shrubs between the forest canopy and the ground cover.
VEGETATION: All live trees, shrubs, ground cover, and other plants, including without limitations, trees, both over and under four (4)
inches in diameter, measured four and one half (4.5) feet above the ground.
WILDLIFE CORRIDORS: A wildlife corridor allows small land species to retain traveling avenues between two similar yet fragmented
habitat areas. As they relate to (SES), a six inch (6") gap under all required security fencing shall be provided.
Page 18 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
MAP 1: TOWN OF STOCKTON SPRINGS ZONING MAP
MG ey TOWN OF STOCKTON SPRINGS la a
Ret ZONING MAP \\ H\
ey ae 5086 ase 'ee -------- | [
-- "GHAIR, TOWN OF STOCKTON SPRINGS SELECTMEN \ a =
prosPect < aes 'int S \ Lees = : snsv =
q = ae e G2 Bl <1 OL TANG -- \\ jee AgF*
ESET
2 f\ a 4 a
e ee rs Ae es
ESS | OSS
Veriicss | {er
o | a 2 MI IONS VS és LEGEND
X(t] Mill Cove 7) oe
Page 19 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
TABLE 1: SOLAR ORDINANCE REFERENCE CHART
[esi [So
as
pm | a
es
|
Page 20 of 21
DRAFT Town of Stockton Springs, Maine
Solar Energy Systems Ordinance
Amendment to:
"APPLICATION, LICENSE, PERMIT, AND OTHER FEES ORDINANCE"
To be added to "Schedule of Fees"
SOLAR ENERGY SYSTEMS (SES)
Co
*Needs review and guidance
Page 21 of 21