TOWN OF STONINGTON
COMMERCIAL CONSTRUCTION SITE PLAN REVIEW ORDINANCE
Enacted: 03/06/2006 Last Amended: 03/11/2024
TABLE OF CONTENTS
SECTION PAGE
I. Purpose I
II. Authority and Administration 1
II. Applicability 1
IV. Site Plan Content and Application Procedure 3
V. Review Procedures 3
VI. Performance Standards 4
VII. General Provisions 7
VIII Enforcement 7
IX. Validity 7
Appendix: Definitions 8
Commercial Construction Site Plan Review Ordinance
SECTION I: PURPOSE
Substantial commercial development or major commercial changes in the uses of land or
buildings can cause a substantial impact upon the cost and efficiency of municipal services
and upon the environment of the town. Such development can impact neighbors' well
capacity or water quality; septic leach fields; and the quality of life in regards to noise and/or
odor. Ona greater scale it can affect sewers, waterlines and other public utilities;
recreational facilities; solid waste disposal; fire and police protection, open spaces, road
systems and circulation, and traffic congestion. The placement of buildings and structures
can affect property values, the aesthetic and visual characteristics of the neighborhood and
town, and the general health, safety, and welfare of the community. It is the purpose of this
ordinance to ensure that such impacts are addressed. This ordinance addresses any
commercial development, providing guidelines for commercial, retail, industrial, and
institutional building construction. It also addresses multiple family dwellings consisting of
three or more dwelling units with common attached walls.
SECTION II: AUTHORITY AND ADMINISTRATION
A. This ordinance is adopted pursuant to Home Rule Powers as provided for in the Maine
Constitution.
B. The Planning Board and the Code Enforcement Officer of the Town shall administer this
ordinance.
C. No activity or use requiring Site Plan Review shall commence until the property owner
has received Site Plan Approval from the CEO or Planning Board as appropriate, and has
complied with any other applicable provisions of this ordinance. No plumbing or other
permits or certificate of occupancy shall be issued by the municipal officers or Code
Enforcement Officer for any use or development within the scope of this ordinance until
the Site Plan Development Application has been reviewed and approved. The Planning
Board may modify or waive any of the submission requirements when it determines that
because of the size of the project or circumstances of the site such requirements would
not be applicable or would be an unnecessary burden upon the applicant and that such
modifications or waiver will not adversely affect the abutting landowners or the general
health, safety, or welfare of the Town. Permits can be transferred with the approval of
the Planning Board.
SECTION III: APPLICABILITY
A. This ordinance does not apply to single family dwellings or the construction, alteration,
or enlargement of a single family or two-family dwelling. This ordinance does not apply
Revision Date: March 11, 2024 Page 1] of 11
Commercial Construction Site Plan Review Ordinance
to home based occupations or home based fishing, agricultural or forestry activities. This
ordinance does not apply to uses existing at the adoption of the ordinance.
B. This ordinance shall apply to all development proposals for establishment, alteration, or
change of use of commercial, retail, industrial, institutional buildings and structures and
multiple family dwellings consisting of three or more attached dwelling units and their
accessory uses and structures, as well as to any proposed demolition activities. This
ordinance does not apply to home based occupations, agricultural or forestry activities. A
person who has right, title, or interest in a parcel of land must obtain site plan approval
prior to commencing any of the following activities on the parcel, obtaining a building or
plumbing permit for the activities, or undertaking any alteration or improvement of the
site including grubbing or grading:
1. The construction or placement of any new building or structure for a nonresidential
use, or the expansion or conversion of an existing building for a nonresidential use,
including accessory buildings and structures, if such buildings or structures have a
total area for all floors of 5,000 square feet or more.
2. The conversion of an existing nonresidential use, in whole or in part, to another
nonresidential use if the new use changes the basic nature of the existing use such that
it increases the intensity of on- or off-site impacts of the use subject to the standards
and criteria of site plan review described in this ordinance.
3. The conversion of an existing nonresidential use, in whole or in part, to a residential
use if the new use changes the basic nature of the existing use beyond 50% of its
current square footage. Residential uses are allowed above or behind a principal
commercial use provided that a minimum depth of 10'of groundfloor uses be
externally oriented retail sales uses, restaurants, personal services, museums, art
galleries or pedestrian-oriented personal service uses.
4. The construction, conversion or expansion of a residential building containing 3 or
more dwelling units. All new proposed subdivision lots, apartment units, or
condominium units are required to include 10% of such units be made available as
low- to moderate-income housing. Pursuant to Maine law, such a project is also
subject to subdivision review.
5. The construction or expansion of paved areas or other impervious surfaces, including
walkways, access drives, and parking lots involving an area of more than 2,500
square feet within any 3 year period.
Revision Date: March 11, 2024 Page 1] of 11
Commercial Construction Site Plan Review Ordinance
SECTION IV: SITE PLAN CONTENT AND APPLICATION PROCEDURES
A. The Board of Selectmen shall adopt a Site Plan Development Application which shall
require as a minimum:
1. Adequate maps, including surveys where appropriate
2. Pertinent information on the applicant;
3. Information on the project property before any new development
4, Information on ail proposed construction
5. Statement of financial capability
6. Evaluation of off-site public facilities
7. Adequacy of fire safety provisions, water and sewage disposal, roads and pedestrian
access
8. Estimate of construction cost; start date; estimated completion date
9. Application fees
B. The CEO shall initially review an application. If the CEO determines the application is
incomplete, the applicant shall provide such additional information as requested before
the review process can continue.
C. Abutting property owners shall be notified by mail by the Town of all pending
applications for Site Plan Review.
SECTION V. REVIEW PROCEDURES
A. Initial Review: The Planning Board shall determine whether the application is
complete, taking into account all factors, including the report of the CEO; any
comments or requests for waivers from the applicant; or any report from a
professional consultant previously retained by the Planning Board in regards to the
proposed development. If the application is determined to be complete, the Planning
Board shall set the matter for a hearing to take place within 30 days. Ifthe
application is incomplete, the applicant shall be notified in writing of the additional
information required.
B. The Planning Board may require that an independent consultant review the
application. The consultant(s) selected shall estimate the cost of such review and the
applicant shall deposit with the Town the full estimated cost.
C. Upon receipt of additional requested information, the Planning Board shall conduct
an initial review again and schedule a public hearing if it finds that the application is
complete.
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
D. Public hearings by the Planning Board shall be conducted according to the procedures
outlined in M.S.R.A. 30A Section 291. Notice of a hearing shall be published at least
10 days prior to the hearing date. Parties to a hearing may be represented by an agent
or attorney. Any hearing may be continued or recessed to another time for good
cause, or upon recorded agreement of the Planning Board and the applicant.
E. Within 30 days of the public hearing the Planning Board shail either approve or
approve with conditions or disapprove the application. The time limit for review may
be extended by mutual agreement between the Planning Board and the applicant.
F. In approving or disapproving an application, the CEO or Planning Board shall make
written conclusions and factual findings as to whether the applicant has submitted
sufficient evidence showing that each of the Performance Standards listed below has
been fully satisfied, or a waiver granted.
SECTION VI: PERFORMANCE STANDARDS
The following standards are to be used by the Planning Board in judging applications for
site plan review and shall serve as minimum requirements for approval of the site plan.
In all instances, the burden of proof shall be on the applicant and such burden of proof
shall include the production of evidence necessary for the Planning Board to review the
application.
A. Advertising Features: The size, location, design, lighting and materials of all
exterior signs and outdoor advertising structures or features shall not detract from the
design of proposed buildings and structures and the surrounding properties.
B. Emergency vehicle Access: Convenient and safe emergency vehicle access to all
buildings and structures at all times shall be provided for and maintained.
C. Existing Utilities, Septic and Wells: The development shall not impose an
unreasonable burden on sewers, sanitary and storm drains, water lines or other public
utilities; nor on existing septic/leach fields or wells.
D. Exterior Lighting: All exterior lighting shall be designed to minimize impact on
neighboring properties.
E. Financial/Technical Capacity; The developer has adequate financial and technical
capacity to meet the above state standards.
F. Lot Standards: Lot configuration and area should be designed to provide for
adequate off-road parking service facilities. The maximum lot coverage for buildings
is 50 percent. The maximum height of buildings is 35 feet. The minimum setbacks
are:
1. Front yard: 25 feet from edge of right-of-way.
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
2. Side yard: 20 feet from property line.
3. Rear yard: 20 feet from property line.
4, Shoreland: As per Shoreland Zoning Ordinance.
G. Municipal Services: The development will not have an unreasonable adverse impact
on the municipal services including municipal road systems, fire department, police
department, solid waste program, sewage treatment plant, schools, open spaces,
recreational programs and facilities, and other municipal services and facilities.
H. Noise: The project shall not result in unreasonable noise beyond the lot lines.
I. Parking and Circulation: The layout and design of all means of vehicular and
pedestrian circulation, including walkways, interior drives and parking areas shall
provide for safe general interior circulation, separation of pedestrian and vehicular
traffic, service traffic, loading areas, and arrangement and use of parking areas. The
proposed site shall include sufficient on-site parking spaces for the projected need.
These requirements may be waived if off-street municipal parking is available for
existing buildings converting upper floors or rear units into year round housing units.
J. Pollution: Will not result in undue water or air pollution. In making this
determination the Planning Board shall at least consider:
1. the elevation of land above sea level and its relation to the flood plain;
2. the nature of the soils and subsoils and their ability to adequately support water
disposal;
3. the slope of the land and its effects on effluents.
4. The proper handling and disposal of any hazardous materials
K. Preserve and Enhance the Landscape: The landscape shall be preserved in its
natural state insofar as practical by minimizing tree removal, disturbance of soil,
retaining vegetation during construction. After construction is completed,
landscaping shall be designed and planted that will define, soften or screen the
appearance of off-street parking areas from the public right-of-way and abutting
properties and/or structures in order to enhance the physical design of the building(s)
or site, and to minimize the encroachment of the proposed use on neighboring land-
use.
L. Relationship of the Proposed Buildings to the Environment: Proposed structures
shall be related harmoniously to the terrain and to existing buildings in the vicinity
which have a visual relationship to the proposed buildings. Special attention shall be
paid to the bulk, location and height of the building(s) and such natural features as
slope, soil type and drainage ways. The project shall not have a significant adverse
impact on archaeological resources or historic buildings as identified in the Town's
Comprehensive Plan (2018). The Planning Board reserves the right to require an
archaeological or historic survey as necessary.
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
M. Surface Water Drainage: Adequate provisions shall be made for surface drainage
so that removal of surface waters will not adversely affect neighboring properties,
downstream conditions, soil erosion, public ways or the public storm drainage
system. Whenever possible, on-site absorption of run-off waters shall be utilized to
minimize discharges from the site.
N. Soil Erosion: Will not cause unreasonable soil erosion or reduction in the capacity of
the land to hold water so that a dangerous or unhealthy condition may result.
O. Special Features of the Development: Exposed storage areas, exposed machinery
installation, service areas, utility buildings and similar structures shall have sufficient
setbacks and screening to provide an audio/visual buffer sufficient to minimize their
adverse impact on other land uses within the development area and surrounding
properties.
P. Scenic/Natural Beauty: Will not have an undue adverse effect on the scenic or
natural beauty of the area, aesthetics, archaeological or historic sites or buildings or
rare and irreplaceable natural areas.
Q. Sewage Waste Disposal: Will provide for adequate sewage waste disposal. If
served by the Stonington Sanitary District, will not unduly burden the District's
capacity.
R. Shoreland Zone: Whenever situated in whole or in part, within 250 feet of any
pond, lake, river or tidal waters, will not adversely affect the quality of such body of
water or unreasonably affect the shoreline of such body of water.
S. Vehicular Access: The proposed site layout shall provide for safe access and egress
from public and private roads by providing adequate location, numbers and controls
of access points including site distances, turning lanes, traffic signalization, when
required by existing and projected traffic flow on the municipal road system.
T. Water: Has sufficient water available for the reasonable foreseeable needs of the
development, and will not cause an unreasonable burden or damage to the local
groundwater supply. No project with an estimated daily average consumption in
excess of 1,000 gallons shall be served by the Stonington Water Company.
SECTION VII: GENERAL PROVISIONS
A. The Planning Board may require the filing of a Performance Bond or the execution of
a conditional agreement with the municipality by the applicant for required
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
improvements and infrastructures affecting the health, safety and welfare of the
Town.
B. Failure of the permitting authority to act within any of the time requirements set forth
herein shall constitute a denial of the application.
C. All Site Plan Approvals shall expire unless work on the project is substantially
commenced within 12 months from the date of issuance. If work is not substantially
completed within 24 months from the date of issuance, a new application shall be
required.
D. The granting of Site Plan Approval does not relieve the applicant from the need to
obtain any other permits or approvals required prior to the commencement of any
activity or use.
E. The CEO shall have reasonable access to the site at all times to review the progress of
the work and shall have authority to review all records and documents related to the
project. The applicant, by accepting Site Plan Approval, waives any objection to the
CEO having access to the site to review the progress of the work or to review all
records and documents related to the project.
F. Appeal process shall be the same as in the Stonington Shoreland Zoning Ordinance.
SECTION VIII: VIOLATIONS; ENFORCEMENT AND FINES
A. Violation and enforcement: The Selectmen, upon finding that any provision of this
ordinance or the conditions of a permit issued under this ordinance are being violated,
are authorized to institute legal proceedings to enjoin violations of this ordinance.
The Code Enforcement Officer will undertake all other enforcement action, such as
inspections, notices and stop work orders.
B. Fines: A person who violates a provision of this ordinance or the conditions of a
permit shall be guilty of a civil violation subject to the fines as specified in Title 30-
A, M.R.S.A. 4452. Such persons shall also be liable for court costs and reasonable
attorney fees incurred by the municipality.
SECTION IX: VALIDITY; SEPARABILITY AND CONFLICT WITH OTHER
ORDINANCES
A. Validity and Separability: Should any section or provision of this ordinance be
declared by any court to be invalid, such decision shall not invalidate any other
section or provision of the ordinance.
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
B. Conflict with other ordinances: Whenever the requirements of this ordinance are
inconsistent with the requirements of any other ordinance, code or statute, the more
restrictive requirements shall apply.
APPENDIX A: DEFINITIONS
A. Construction of Language
In the interpretation and enforcement of this ordinance, all words other than those
specifically defined in the ordinance shall have the meaning implied by their context in
the ordinance or their ordinarily accepted meaning. In the case of any difference of
meaning or implication between the text of this ordinance and any map, illustration, or
table, the text shall control. The word "lot" includes the words "plot" and "parcel". The
word "building" includes the word "structure". The word "used" or "occupied", as
applied to any land or building shall be construed to include the words "intended,
arranged, or designed to be used or occupied".
B. In this ordinance the following terms shall have the following meanings:
ABUTTING PROPERTY: Any lot which is physically contiguous with the subject lot
even if only at a point and any lot which is located directly across a street or right-of-way
from the subject lot such that the extension of the side lot lines of the subject lot would
touch or enclose the abutting property.
ACCESSORY STRUCTURE OR USE: A use or structure which is incidental and
subordinate to the principal use or structure. Accessory uses, when aggregated shall not
subordinate the principal use of the lot. A deck or similar extension of the principal
structure or a garage attached to the principal structure by a roof or a common wall is
considered part of the principal structure.
ACCESSORY DWELLING UNIT (ADU): a self-contained dwelling unit located unit
located within, attached to or detached from a single-family dwelling unit located on the
same parcel of land that cannon be rented for less than 90 days,
AGRICULTURE: The cultivation of the soil or raising crops, including gardening as a
commercial operation. The term shall also include greenhouses, nurseries and versions
thereof, but these two terms, when used alone, shall refer specifically to a place where
flowers plants, shrubs, and/or trees are grown for sale.
ALTERATION: Structural changes, rearrangement, change of location, or addition to a
building, or structure other than repairs and modifications in building equipment
involving a 50% increase in floor space on a minor development and any increase in floor
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
space in a major development or bulk of the building or structure at any time or in total
since the effective date of this ordinance. The term shall also include change,
modification, or addition of a deck, dormer, staircase, or roof of the building.
BUILDING FOOTPRINT: The area covered by a building measured from the exterior
surface of the exterior walls at grade level exclusive of cantilevered portions of the
building. Where the building is elevated above grade level! on posts or similar devices, the
building footprint is the area the building would cover if it were located at ground level.
BUILDING: Any 3 dimensional enclosure constructed of any building materials or any
space for any use or occupancy
CHANGE IN USE: A change in the type of occupancy of a building or structure, or a
portion thereof, such that the basic type of use is changed, such as from retail! to office or
storage to a restaurant, but not including a change in the occupants. The term "change of
use" includes the addition of a new use to an existing use.
CURB CUT: The opening along the curb line or street right-of-way line at which point
vehicles may enter or leave the street.
ENLARGEMENT OR EXPANSION OF A STRUCTURE: An increase of the building
footprint and/or increase in the height of the structure beyond its present highest point.
Alterations of existing buildings which are required in order to meet the requirements of
the Americans with Disabilities Act (ADA) and/or the State Fire Code are not considered
to be enlargements or expansions of a structure and are not required to meet otherwise
applicable setback requirements, provided the alterations are the minimum necessary to
satisfy the ADA and/or State Fire Code.
ENLARGEMENT OR EXPANSION OF USE: Any intensification of use in time,
volume, or function, whether or not resulting from an increase in the footprint, height,
floor area, land area or cubic volume occupied by a particular use. Increases which are
required in order to meet the requirements of the Americans with Disabilities Act and/or
the State Fire Code are not considered to be enlargements or expansions of use.
FLOOR AREA: The sum of the horizontal areas of the floor(s) of a structure enclosed by
exterior walls.
GROUNDWATER: All of the water found beneath the surface of the ground. For
purposes of aquifer protection, this term refers to the subsurface water present in aquifers
and recharge areas.
HOME BASED OCCUPATION - An occupation or profession which is customarily
conducted on or in a residential structure or property and which is clearly incidental to
and compatible with the residential use of the property and surrounding residential uses
Revision Date: March 11, 2024 Page 11 of 11
Commercial Construction Site Plan Review Ordinance
and which employs no more than 2 persons other than family members residing in the
home.
HISTORIC OR ARCHAEOLOGICAL RESOURCES: Areas identified by a
governmental agency such as the Maine Historic Preservation Commission as having
significant value as an historic or archaeological resource and any areas identified in the
municipality's comprehensive plan.
LOT AREA: The area of land enclosed within the boundary lines of a lot, minus land
below the normal high-water line of a water body or upland edge of a wetland and areas
beneath roads serving more than two lots.
PRINCIPAL STRUCTURE: A building other than one which is used for purposes wholly
incidental or accessory to the use of another building or use on the same premises.
PRINCIPAL USE: A use other than one which is wholly incidental or accessory to
another use on the same premises.
SETBACK, FRONT: An open area extending the entire width of a lot from lot sideline to
lot sideline and extending in depth at a right angle from the street right-of-way to such
depth as specified. Such area shall be unoccupied and unobstructed by any building from
the ground upward.
STRUCTURE: Anything constructed or erected, which requires location on the ground or
attached to something having a location on the ground, but not including a tent or vehicle.
SUBSTANTIALLY COMMENCED; SUBSTANTIALLY COMPLETED: Construction
shall be considered to be substantially commenced when any work beyond the state of
excavation, including but not limited to, the pouring of a slab or footings, the installation
of piles, the construction of columns, or the placement of a manufactured home on a
foundation has begun. Construction shall be considered to be substantially completed
when it has been completed to the point where normal functioning, use, or occupancy can
occur without concern for the general health, safety, and welfare of the occupant and the
general public. At a minimum it shall include the completion of no less than 70 percent of
the costs of the proposed improvements within a development and shall include
permanent stabilization and/or revegetation of areas of the site that were disturbed during
construction.
USE: The purpose for which land or a building is arranged, designed, or intended, or for
which either land or a building is or may be occupied or maintained.
A True Copy Attest: the Cc . bebe Town Clerk