TOWN Of UNITY
LAND USE ORDINANCE
ADOPTED: MARCH 25, 1995
REVISED: MARCH 26, 2011
REVISED: LD 2003 - SEPTEMBER 28, 2024
LAST REVISED: MARCH 22, 2025
Board of Selectmen Ordinance Certification
_ ae Alt] 45, 202s
Antonjo Avila, Chairman Date
David Wakefield, Vice Zhairman D --_-- --
VB Meol ai Gol i ae
ChristophérShédyak, Member Date
UNITY LAND USE ORDINANCE
Table of Contents
Section I. General Provisions
VT. Tithe. eee ee eeeececsseeecssacecessecessesesessesescestesertuesettressttstecsteteessee
2. Authority. 0... cccccccccccseccececsseecersssecevsrsusessstseesetttesevtvteresestseeseeses 4
3. PUPPOSES. 0.0... eeccccccccceeseceesecssecsecssecesesueereettesesttsttesetetatecertrseeeesesss 4
4. Applicability. 0000 cccececesececsesseeeeseseetratetesesttttttettestessres 5
5. Conflicts with Other Ordinances, Laws and Regulations.....................5
6. Validity and Severability. 0.0.0.0... coc ccceeeeseseessseeesttreertttestteseene 5
7. Effective Date; Repeal of Prior Ordinances. .............cccccccecccccececececeeeeee 5
8. Availability. 00.0. ccccceccscccccrscesersrseversttrtesttttttsertttesereenD
9. AMONdMEeNtS. 000.0... ce cccccccecesceccsessessersrseseeseteterttetesstttteseeteese
Section Il. Administration
1. Administering Bodies and Agents...........000..cccccceeeecesereecetteeestssessereeeees
2. Permits REQuired.......... i cccccccccccsscecsesssceeesssrseesen seteeeeesttteesestteeesese ®
3. Types of Permits...........0...cccccccccccsssssesetee seseesseesttetsteseesttesseseesss 8
4. State Fire Marshal Permits. ....0000.0000cccccccccceeeceseecersececstseeessseserseeeee 10
5. Permit Application. .......000.ccccccccececcesscesseccecsseecssecssseestssesssssesesaresesseee TI
6. Procedures for Administering Permits........0...000..cccccccsccceeeseeeeereeeeeeeeee 15
7. Conditions for Permit Approval. ........00.00cccccccccscescssecesesseseteveseesessresseeee 17
8. Burden Of Proof... ccc ccceeccccessececcssesesesseessessecssesssessevssevrevtneetsrereeeee 17
Q. EXpiration.... ccc cecceceseceseeecssccsseeseescsssessecsssecsssteseesssesteseseeseesseeees V7
10. Enforcement 00... ee ecccceecseecseesseeesssseccssesstessccsseseesssetecsserereeerenee D7
TT. Appeals... ec ccccescesecssecsseceseesscssessecsssesseessestevsseseesessvraseteteeseeee 18
Section Ill. Non-Conformance
VT. PUPPOSC oo... cc eeececescecseeeeseecersseesececssttssseeeessertrsaeeesersretttsateeseee 19
2. General Requirement. ........0....ccccccceeecccecessecsesssseevertrseeersttteesestseeee 19
3. Non-Conforming Structures. ......0000.ccccccccecscccceesscesessrseeveestrnserentreee V9
4. Non-Conforming Uses............0cccccccccessseceesssseecessetesessttresesststseeseeees 20
5. Non-Conforming Lots. .......0.0.cccccccccccscccecesssceceesssssecssssseceventtreesecsrenee 21
6. Non-Conforming Signs. ..............cccccecsccesscsecsecsessecestsseeerteverteeerssteee 21
Section IV. Definition of Districts
1. Overview of District Delineations ....00.0cc occ ccceeeceeceecreceeeessteeeee 21
2. Baseline Districts 0.2.0... cccesceccesesceeccssececesssssseestterreseettneesenees 22
3. Overlay Districts 2.00... ccccceceeccseccevsesesecesesecesstateesestttessersttaseee 22
Section V. Dimensional Requirements
1. Lot Requirement .............cccccccceccscscecesesssssececeserststeeeeeeeestettssseeeeees 28
2. Road Access Management. .............0.cccccccceececceseessecesstssressestrseeseesees 26
3. Structural Requirement. .......0.0000. ccccccccceccsscecessecssesssecevertreeeseensneee 27
4. Agricultural Protection Setback. ........0..cccccccecccceesseseesestseeeseettreeeeee 28
Section VI. Farmland Protection Incentive Measure
1. PULPOSC oie eccccececsseceeeceseseecessueeesteseeeserstressttstesettstetsstssesessees 3O
2. Applicability. 0.0... ccccccccccccceccscceserecssneestsesetsrtrssesevtitesstesersees BO
3. Specific MEASUrE. 0... ccc ccc eceecccceveseeeesetseseesteteesttsteeeeststesersees BO
4. Administration... cece ccccccceecccenssesseseeceasesensesectteesteteststeerssessees SO
5. Preserved Open Land. ..........cccccccccesccceeesecesssseceseetseccestaverecsistecessveeeee 1
Section VII. Special Performance Standards
1. Parking Areas... ccc cccccsccccecsscecenssscesseceseseetrresertreseesttsstssssseseeeee 1
2. Commercial SIQNs. ..........0.0.ceccccceccccessccceesevesecertsseessreetssteseseseesseseees 2
3. Retail Activity in the Rural District. 000000000 cecccceecessceessseresseesesees 88
4. Retail Activity in the Downtown District. 0000.00... ccceeeceeeeecseeesssseeees 34
5. Special Requirements for Village District....00...000ccccceceeessceeesseeeseees 84
6. Special Requirements for Large Commercial Complexes. .................34
7. Commercial Impacts Throughout Town .0.......cccccecceeceeessseeeeseseeeeeees 35
9. (4). Driveways and Roads............. ccc cecceeeeceseetseseststtssesesttrteeeenes 35
10.(5). Mobile Home Parks........0..cccccccceceesesesesecerereceststesttstesetstessssseees 36
11.Energy Systems Development......0..... 0.0... ccc cee cce cence cee eee eee sereees 39
12. Requirements for Small and Intermediate Wind Turbines. ................39
Section Vill. Downtown Design Guidelines
1. PULPOSE. 0... eee eecccccceseceeecescseeccerssseceessssecversrsesesttriseretareseettseerersese 40
2. Applicability 2.0.0... cccceccsecceeseccnssecenssseessserstsecesuseetresstsesestereees 44
3. Specific Provisions. ..........ccccccccescccccssscececsececeetcsecsevtsseeecssascecessreeeeee 4
4. Special Design Review Committee... cece cceececccceseccesesseseeeeesenee 42
5. (4). Visual Screening Alternative..........000 ccc eccceceesccesecsseeeeeeeteeeeeees 43
6. (5). Administration & Appealls.........0..0ccccccceceececeseeceee censeevetseesserereee 43
Section IX. Aquifer Protection Standards
1. PUPPOSE. ooo... eee cceceeseeceecceessesseecessersssssseecesevsttsteescesrtttstteeeseeseee 43
2. Applicability. 00... ceccccceccscesesssccesesrsssestesvesestsessttesesttes, 44
3. Conditional USES 2.0.0... ccccccccecsscsecesseseesstrsvesettstesertesesettssseee 44
4. Approval Procedure, .........ccccccccccccecsssseccessssseesenseeestttteseesttsesesersene 44
5. Performance Standards. ........0.00.0ccccecccccccesscesenseeeeesecsttesecsseeeessrseees 46
Section X. Development Review
1. PUPPOSE. ooo... ccc cecettseeccececersscecccecessstssesecevsvtnttetesserttttttereererees 47
2. Applicability. 0.0.0... ececcscccccesseccesssecccersreseesttaeerestitersnteesesss 4D
3. Classification of Projects. 0.0.0... ccccccceseceseseseeetetsecesersevessesseerees 48
4. Application Procedure. oo... cccccsecccccccesesseseceseststrseerersvertttteeeess, 48
5. Standards for Approval. ..........000cccccccccccccceceeserreeeeeecettaveseesesseserseee D1
6. Appeals. oo... ccccceceeeeeccesesssseseecesssssteesseevessttavevessssttatererseeses DQ
Section XI. Definitions
1. Construction of Language ............ccccccccccecscceesscesersestesseestseesertreeeeess BQ
2. Definition Of Terms ......0... cc cccccccccccssscceceessscesesssseveessreserttsseessrseeee DQ
APPENDIX 1: Development Review Application Content Requirements............66
Pave 3|72
Section |. General Provisions
1. Title
This Ordinance shall be known and cited as the Unity Land Use Ordinance
and will be referred to as "this Ordinance."
2. Authority
This Ordinance is adopted pursuant to the enabling provisions of Article VIII,
Part 2, Section 1 of the Maine Constitution, the provisions of Title 30-A
MR.SA, Section 3001 (Home Rule), Title 30-A MR.SA, Sections 4311 et seq.
(Comprehensive Planning and Land Use Regulation, or "Growth Management"
Act), and Title 30-A MR.SA, Sections 4401 et seq. (Subdivision Law). This
Ordinance is founded upon and pursuant to Unity's Comprehensive Plan as
adopted on March 27, 1993 and amended on October 26, 1993.
3. Purposes
The purposes of this Ordinance are to fulfill policies expressed
within Unity's 1993 Comprehensive Plan, as restated below:
A. to allow for affordable residential and commercial growth, while
preserving Unity's rural character, particularly its open land, scenic
beauty and reasonable tax rate;
B. to guide growth to make efficient use of land and public facilities;
C. to help protect the natural resources of the community from
degradation;
D. to foster harmonious co-existence of commercial, residential,
recreational and other potentially conflicting activities;
E. to provide a degree of clarity and consistency to the Town's treatment
of growth and development;
F. to invite and encourage additional complementary commercial and
industrial development;
G. to protect landowners' rights and freedom of choice in development
activities;
H. to minimize adverse traffic impacts; and
|. to promote the health, safety, and general welfare of the residents of
the community.
4. Applicability
The provisions of this Ordinance shall govern all land and all structures
within the boundaries of the Town of Unity.
5. Conflicts with Other Ordinances, Laws and Regulations
Whenever a provision of this Ordinance conflicts with or is inconsistent with
another provision of this Ordinance or of any other ordinance, regulation or
statute from any jurisdiction, the more restrictive provision shall control.
6. Validity and Severability
Should any section or provision ofthis Ordinance be declared by the courts to be
invalid, such decision shall not invalidate any other section or provision of the
Ordinance.
7. Effective Date; Repeal of Prior Ordinances
This Ordinance becomes effective on April |, 1995. This Ordinance repeals and
replaces the Unity Minimum Lot Size Ordinance and the Unity Building Permit
Ordinance.
8. Availability
A copy of this Ordinance shall be available for review at the town office.
Additional copies shall be made available to Unity residents upon request.
9. Amendments
A. Anamendmenttothis Ordinance may be adopted by a majority vote of Town
Meeting. A proposal to amend this Ordinance may be placed on the
warrant of any Town Meeting by:) 1) the Planning Board; 2) the
Comprehensive Plan Committee; 3) the municipal officers; or 4) written
petition of at least 25 voters registered to vote in Unity, filed with the
municipal officers.
B. Prior to a Town Meeting at which a proposed amendment will be
considered, the Planning Board shall hold a public hearing. Notification of
the hearing shall be posted at the town office and advertised in a
newspaper of general circulation in the municipality on two occasions,
once at least 14 days prior to the hearing, and a second time 7-14 days
prior to the hearing.
C. If an amendment is proposed which changes land regulation within 500
feet of a common town border, the Town Clerk shall forward notice to the
Selectmen and Planning Board of adjacent communities at least ten days
in advance of the public hearing. The adjacent community may provide
verbal or written testimony.
D. At any time this Ordinance is amended, the Town Clerk is authorized to
insert and/or delete amendments, add and/or delete inconsistent
references within the Ordinance caused by such amendment(s), and
renumber sections of the amended Ordinance in a logical and appropriate
fashion, provided said changes do not result in any substantive alteration
in the meaning of the Ordinance.
Section Il. Administration
1. Administering Bodies and Agents
A. Board of Selectmen
The Board of Selectmen shall appoint or reappoint a Code Enforcement
Officer (CEO) annually by July 1st. The Board of Selectmen shall provide
the necessary authorization and support for the CEO in enforcing the
provisions of this Ordinance, including the retention of an attorney if
necessary to assist in the prosecution of a serious violation.
B. Code Enforcement Officer
The Code Enforcement Officer shall have the following powers and duties:
a) Enforce the provisions of this Ordinance.
b) Review applications for occupancy permits and issue such permits
where authorized by this Ordinance;
c) Review applications for building permits, and recommend action to the
Planning Board as authorized in this Ordinance.
d) With the consent of the owner, occupant, or agent, enter any property at
reasonable hours to inspect the property or building for compliance with
this Ordinance.
e) Investigate complaints and reported violations.
f) Keep written inspection reports and thorough records.
g) Issue violation notices.
h) Participate in appeals procedures.
i) Confer with the Board of Selectmen as necessary to obtain proper
authorization for prosecution and/or retention of legal counsel.
j) Appear in court when necessary.
k) Confer with citizens and assist them in understanding this Ordinance.
1) Attend meetings of the Board of Appeals and the Planning Board.
m) Revoke a permit within his jurisdiction after notice and hearing if it was
Page 6|72
issued in error or if it was based on erroneous information. Inform the
Planning Board of any similar problems discovered in permits issued by
the Board.
C. Town Clerk
The Town Clerk shall keep blank application forms for each type of permit
on file at the town office. The Clerk shall receive all permit applications
and fees due, and forward applications to the appropriate administrative
body for review. The Clerk shall maintain a file of permit applications,
permits and enforcement notices.
D. Planning Board
The municipal Planning Board shall be responsible for reviewing and acting
upon applications for building permits, development permits, road
construction permits, and lot permits.
E. Road Commissioner
The municipal Road Commissioner shall perform site evaluations and
play a role in issuing driveway and road construction permits. The Road
Commissioner shall maintain close communication with the CEO and
; the Planning Board to facilitate consistent treatment of permit
applications.
F. Board of Appeals
The municipal Board of Appeals shall be responsible for deciding
administrative appeals and variance requests according to the
procedures outlined in the Board of Appeals Ordinance for the Town of
Unity.
Page 7|72
2. Permits Required
A person must obtain a permit before engaging in any of the following
activities:
1) constructing a new driveway or road;
2) constructing, expanding, or paving for certain parking lots located
in the downtown district;
3) building, locating or relocating any structure larger than 100 square
feet;
4) expanding any existing structure by more than 100 square feet;
5) exterior renovations to those downtown properties that must follow
Design Guidelines. (See Section Vill for what type of properties are
exempt.)
6) dividing of land or structures in a way that constitutes a subdivision
(as defined);
7) engaging in any new "high-impact" land-use activity, as outlined in
this Ordinance;
8) creating a new lot;
9) occupying any of the following:
* anew residential structure (accessory dwelling unit, single-
family dwelling unit, or multi-family dwelling unit);
* conversion of an existing structure into a dwelling unit;
* anew building addition (larger than 250 square feet);
* anew rental or accessory dwelling unit created within an
existing structure;
* any structure or rental unit that has been vacant for more
than one year;
* any structure that will be used for commercial activities new
to that structure.
3.Types of Permits
1) Driveway Permit: A driveway permit shall be obtained from the Road
Commissioner and Code Enforcement Officer before a location is
finalized and any construction is begun.
2) Road Construction Permit: A road construction permit shall be obtained
from either the Road Commissioner and CEO, or from the Planning
Board, as outlined in this Ordinance, before a location is finalized and
any construction is begun.
3) Parking Lot Permit: A parking lot permit shall be obtained from the
Planning Board for: a) constructing any new parking area or paving any
existing parking area which will accommodate more than 10 vehicles in
the downtown district or more than 3 vehicles in the village district; or b)
expanding any existing parking area so that the combination of existing
Page 8172
and new space will accommodate more than 10 vehicles in the
downtown district or more than 3 vehicles in the village district.
4) Building Permit: A building permit shall be obtained from the Planning
Board for: a) constructing, locating or relocating any structure larger
than 100 square feet; and b) expanding any existing structure by more
than 100 square feet. (See Requirements for Building Permit
Applications for Accessory Dwelling Units (Section Il Administration,
Subsection 5, Permit Application, C) and Requirements for Building
Permit Applications for Additional Dwelling Units on One Lot (Section II
Administration, Subsection 5, Permit Application, D) below for details).
5) Development Permit: A development permit shall be obtained from the
Planning Board for: a) any use that qualifies as a high-impact land use
activity (as defined); and b) any use constituting a subdivision (as
defined) of land or structure.
6) Lot Permit: A lot permit shall be obtained from the Planning Board for
the creation of any new lot.
7) Occupancy Permit: An occupancy permit shall be obtained from either
the Planning Board or CEO, as outlined in this Ordinance, prior to
occupancy of:
a) any new structure intended for human habitation, including building
additions larger than 100 square feet;
b) any new rental unit (commercial or residential) created within an existing
structure;
c) the creation/establishment of an accessory dwelling unit (ADU), either
within an existing structure (accessory structure or principal structure),
attached to an existing structure, or as a stand-alone structure;
d) any existing structure or rental unit within that structure that has been
vacant for more than a year; or
e) any structure that will be used, in whole or in part, for a commercial
enterprise that is new to that structure (other than a home-based
business, which is exempted).
Issuance of these local permits will be conditional on receipt of all necessary
State permits, as well.
8) Sign Permit: A sign permit shall be obtained by the Code Enforcement
Officer before erecting any commercial sign that is either larger than 10
square feet or illuminated.
4. State Fire Marshal Permits
As of January 1, 1996, the State Fire Marshal requires that construction
and renovation of certain classes of buildings be professionally designed
Page 9|72
and receive a Construction Permit and a Barrier-Free Permit. It is the
responsibility of applicants for local building permits to contact the Office of
the State Fire Marshal to learn more about state requirements. Applicants
may wish to seek State approval after receiving local approval, in which
case local approval will be conditional on subsequent state approval.
Conversely, applicants may wish to obtain State permits before submitting
a local application. Applicants who are proposing work that is subject to
Unity's Design Guidelines are urged to meet with the Planning Board to
discuss these Guidelines before they seek design approval from the State
Fire Marshal.
Page 10| 72
5. Permit Application
A. Application Procedure
Every applicant for a permit shall submit a written application, including a
scaled site plan, on a form provided by the municipality, to the Town Clerk
at the town office.
All applications shall be signed by the owner or owners of the property or
other person authorizing the work, certifying that the information in the
application is complete and correct. If the person signing the application is
not the owner or lessee of the property, then that person shall submit a
letter of authorization from the owner or lessee.
Upon receipt of the completed application and the required fee, the Clerk
shall stamp the application with the date of receipt and forward the
application to the appropriate party (i.e., the Planning Board, Code
Enforcement Officer; and/or Road Commissioner).
B. Requirements for Building Permit Applications
1) All building permit applications requesting approval for a new
structure or building addition that will result in the discharge of
wastewater shall contain one of the following:
| e evidence that a septic system capable of receiving and
adequately treating the anticipated discharge either already
exists or will be constructed, in accordance with 10-144 CMR
Ch.241, State of Maine Subsurface Wastewater Disposal Rules,
as amended.
e evidence that a connection to the Unity Utilities District either
already exists or has been approved.
2) All building permit applications involving downtown properties that
must follow Design Guidelines shall include sufficient detail to allow
the Planning Board to assess adequately either the proposed design
or landscaping plan.
C. Requirements for Building Permit Applications for Accessory Dwelling
Units
For the purposes of this Ordinance, Accessory Dwelling Unit and
Accessory Apartments shall be referred to as ADUs. These standards
apply to residential Accessory Dwelling Units for which a permit is sought
after the adoption date of this Ordinance.
Page 11|72
The property owner of record must provide written verification that the
proposed unit(s) can be connected to adequate water and wastewater
services prior to the issuance of a certification for occupancy. Written
verification must include the following:
i. If connected to the Unity Utilities District, or equivalent centralized
system, proof of adequate capacity to accommodate the added
wastewater created by an additional unit and proof of payment for the
connection to the sewer system;
ii. If connected to a septic system, proof of adequate sewage disposal for
subsurface wastewater. The septic system must be verified as adequate
by a local plumbing inspector pursuant to 30-A MRS §4221. Plans for a
subsurface wastewater disposal must be prepared by a licensed site
evaluator in accordance with 10-144 CMR Ch.241, State of Maine
Subsurface Wastewater Disposal Rules, as amended:
iii. If connected to a centrally managed water system as defined in this
Ordinance, proof of adequate service to support any additional flow
created by the unit and proof of payment for the connection to the
system;
iv. If proposed to be connected to a well, the applicant must include proof
that the water supply is potable, acceptable for domestic use, and can
accommodate anticipated demand.
1) A lot where a single-family dwelling unit is the principal structure may
establish one accessory dwelling unit.
2) ADUs are exempt from any density requirements or lot area
requirements related to the area in which the ADU is constructed, except
that an ADU in a Shoreland Zone must meet state and municipal shoreland
zoning requirements.
3) All ADUs and any new or existing structure containing an ADU, must
meet the setback and dimensional requirements for each district in which
the ADU is established, as set forth in this Ordinance.
4) ADUs do not count towards the total number of dwellings for
requirements of this Ordinance.
5) All residential dwelling units, including ADUs, permitted after January
1, 2024, may not be construed to interfere with, abrogate or annul the
validity or enforceability of any valid and enforceable easement, covenant,
deed restriction or other agreement or instrument between private parties
Page 12|72
that imposes greater restrictions than those provided in this section, as long
as the agreement does not abrogate rights under the United States
Constitution or the Constitution of Maine.
6) An ADU may be constructed:
i. Within an existing dwelling unit on the lot;
ii. Attached to a single-family dwelling unit;
iii. As anew structure on the lot for the primary purpose of creating an ADU;
or
iv. Within an existing accessory structure if the setback requirements of the
municipal ordinance are met.
7) The accessory dwelling unit must be at least 190 square feet in size,
unless the Technical Building Code and Standards Board, pursuant to 10
M.R.S. § 9722, as may be amended, adopts a different minimum standard:
if so, that standard applies.
8) Additional parking requirements for the ADU beyond those required
for the single-family dwelling are not permitted.
9) An ADU is allowed on a non-conforming lot or in a non-conforming
structure if the ADU does not further increase the non-conformity, meaning
the ADU does not further increase deviation from the dimensional
standard(s) creating the non-conformity.
10) An After-the-Fact permit may be obtained for an ADU that was not
built with municipal approval as long as the Accessory Dwelling Unit
otherwise meets the requirements set forth in this Ordinance, provided
proper documentation has been submitted to the CEO.
D. Requirements for Building Permit Applications for Additional Dwellings on One
Lot.
1) These standards apply to residential dwelling units for which a permit is sought
after the adoption date of this Ordinance.
2) The property owner of record must provide written verification that the proposed
additional dwelling unit(s) can be connected to adequate water and wastewater
services prior to the issuance of a certification for occupancy. Written verification
must include the following:
i. If connected to the Unity Utilities District or equivalent centralized system, proof of
adequate capacity to accommodate the added wastewater created by an
additional unit and proof of payment for the connection to the sewer system;
li. If connected to a septic system, proof of adequate sewage disposal for subsurface
wastewater. The septic system must be verified as adequate by a local plumbing
Page 13172
inspector pursuant to 30-A MRS §4221. Plans for a subsurface wastewater
disposal must be prepared by a licensed site evaluator in accordance with 10-144
CMR Ch.241, State of Maine Subsurface Wastewater Disposal Rules, as
amended;
ili. If connected to a centrally managed water system as defined in this Ordinance,
proof of adequate service to support any additional flow created by the unit and
proof of payment for the connection to the system;
iv. If proposed to be connected to a well, the applicant must include proof that the
water supply is potable, acceptable for domestic use, and can accommodate
anticipated demand.
3) All residential dwelling units must comply with the Shoreland Zoning requirements
established by the Department of Environmental Protection under Title 38, chapter
3, and municipal Shoreland Zoning Ordinances.
4) All residential dwelling units permitted after January 1, 2024, may not be construed
to interfere with, abrogate or annul the validity or enforceability of any valid and
enforceable easement, covenant, deed restriction or other agreement or
instrument between private parties that imposes greater restrictions than those
provided in this section, as long as the agreement does not abrogate rights under
the United States Constitution or the Constitution of Maine.
5) Housing units and additional dwelling units on a single lot developed under this
Section must comply with this Ordinance for minimum lot dimensional
requirements per dwelling unit in the District in which the lot is located. (Section V
Dimensional Requirements, D)
6) This Section shall not be construed to exempt a property owner from the applicable
provisions of the State subdivision statute, 30-A M.R.S. §4401-4408, or the
subdivision section of this Ordinance relating to division of a tract or parcel of land.
E. Application Fees
No fee will be charged for a lot permit. A schedule of fees for all other
permits shall be approved by the Board of Selectmen upon the
recommendation of the Planning Board. No permits shall be issued until
all fees have been paid.
Page 14] 72
6. Procedure for Administering Permits
A. Building Permits
The Town Clerk shall forward a copy of received applications to the
Code Enforcement Officer. The CEO shall contact the applicant and
schedule a site visit at a mutually agreeable time. The site visit should
occur within 10 business days after the application was submitted to the
Town Clerk.
Within 2 business days of the site visit, the CEO shall:
a) decide whether or not to recommend the application for approval to
the Planning Board;
b) communicate this decision to the applicant; and,
c) forward a copy of the application, together with his/her
recommendation, to the Planning Board.
If the CEO is incapacitated or otherwise unavailable for a site visit within
10 business days, the Town Clerk may, at the request of the applicant,
forward a copy of the application directly to the Planning Board, which
may consider the application without a site visit.
All applications for building permits received by the Planning Board
within 3 business days of a regular Board meeting, shall be placed on
the agenda of that meeting. The Planning Board shall review all
applications, and decide whether or not to grant building permits.
Wherever practical, the Board will act on each application at the first
meeting where it is taken up. If it is found that additional information is
required, the application will be considered old business and given
priority for continued review at the next meeting, provided the additional
information is supplied by the applicant.
B. Driveway Permits
The Town Clerk shall forward a copy of received applications for a
driveway permit to both the CEO and the Road Commissioner. The CEO
shall contact the applicant and the Road Commissioner to arrange a
joint site visit of the property. If the CEO and Road Commissioner both
find that the requirements of this Ordinance shall be met by the
applicant, they shall jointly approve a driveway permit.
C. Road Construction Permits
The Town Clerk shall forward a copy of received applications for a road
construction permit to the Planning Board, the CEO, and the Road
Commissioner. The CEO shall contact the applicant and the Road
Page 15|72
Commissioner to arrange a joint site visit of the property, for the purpose
of gathering information. The application shall be discussed at the next
Planning Board meeting. If the Planning Board finds that the proposed
road will serve a new subdivision or other activity that triggers
development review, then the application for a road construction permit
will be decided by the Planning Board with input from the CEO and Road
Commissioner, and a road construction permit will be issued if and when
a development permit is issued. If the Planning Board finds that the
proposed road does not serve an activity that would trigger development
review, then the application for a road construction permit will be
decided jointly by the CEO and Road Commissioner. In either case, a
permit shall be issued wherever the requirements of this Ordinance are
met.
D. Development Permit
Detailed procedures are outlined in Section X
E. Lot Permit
The Town Clerk shall forward a copy of received applications for a lot
permit to the Planning Board. If an application is received by the Clerk
within 4 business days of the Planning Board's next meeting, it shall be
placed on the agenda of that meeting. The Board shall approve all
applications that meet the lot requirements of this Ordinance.
F. Residential Occupancy Permit
The Town Clerk shall forward a copy of the received application to both
the CEO and the Chair of the Planning Board. The CEO shall contact the
applicant and schedule a site visit at a mutually agreeable time. The CEO
may issue an Occupancy Permit wherever he/she feels all local and state
requirements are being met and proper documentation has been
provided with required verification for residential Occupancy Permits.
For Residential Occupancy Permits, the Planning Board and CEO may
only deny a permit if some requirement of this Ordinance, another
municipal ordinance, or state law is not being met.
G. Commercial Occupancy Permit
For Commercial Occupancy Permits, the CEO may issue the permit
when all local and state requirements are met, except where the
proposed use is likely to:
a) result in a net increase of more than 20 employees;
. b) exceed existing off-street parking; or
Page 16|72
c) create any noise, odor, or other nuisance disturbing to neighboring
properties.
In such circumstances, the Planning Board shall consider the permit
application, in consultation with the CEO.
For Commercial Occupancy Permits, the Planning Board and CEO may
only deny a permit if some requirement of this Ordinance, another
municipal ordinance, or state law is not being met.
7. Conditions for Permit Approval
Permits may be made subject to reasonable conditions to ensure conformity
with the purposes and provisions of this Ordinance. If a permit is approved
with conditions, the condition shall be clearly stated in writing.
8. Burden of Proof
The applicant shall have the burden of proving that the proposed land use
activity is in conformity with the purposes and provisions of this Ordinance.
9. Expiration
A permit authorizing construction will expire within one year of the date of
issuance if no substantial start (as defined) is made on construction. A lot
permit and subdivision approval will expire if any newly created lots are not
recorded with the Registry of Deeds within 60 days of the Planning Board's
decision.
10. Enforcement
A. Any violation of this Ordinance shall be deemed to be a nuisance.
B. Enforcement Procedure
1) The Code Enforcement Officer shall enforce the provisions of this
Ordinance. If the Code Enforcement Officer finds that any provision
is being violated, he/she shall notify in writing the person responsible
for such violation, indicating the nature of the violation and ordering
the action necessary to correct it. (Such actions may include:
discontinuance of an illegal use of land, buildings or structures;
termination of work being done; removal of illegal buildings or
structures; and abatement of nuisance conditions.) A copy of such
notices shall be submitted to both the municipal officers and
Planning Board and be maintained as a permanent record by the
Town Clerk.
Pause 17|72
2) The Code Enforcement Officer shall conduct on-site inspections to
insure compliance with all applicable laws and conditions attached
to permit approvals. The Code Enforcement Officer shall also
investigate all complaints of alleged violations of this Ordinance.
3) The Code Enforcement Officer shall keep a complete record of all
essential transactions, including applications submitted, permits
granted or denied, variances granted or-denied; complaints
received, revocation actions, appeals, court actions, violations
investigated, violations found, and fees collected. Copies shall be
provided to the Town Clerk for permanent filing in the town office.
C. Legal Actions & Penalties
When the CEO's actions do not result in the correction or abatement of
the nuisance, he may request that the municipal officers institute
various actions and proceedings, either legal or equitable, including
seeking injunctions or imposing fines, as may be appropriate or
necessary to enforce the provisions of this Ordinance.
The municipal officers are authorized to enter into administrative consent
agreements for the purpose of eliminating violations of this Ordinance
without Court action. Such agreements shall not allow an illegal structure
or use to continue unless: a) there is clear and convincing evidence that the
illegal structure or use was constructed or conducted as a direct result of
erroneous advice given by an authorized municipal official; and b) there is
no evidence that the owner acted in bad faith.
Any person, including a landowner, a landowner's agent or a contractor, who
orders or conducts any activity in violation ofthis Ordinance shall be penalized
in accordance with Title 30-A MR.SA Section 4452.
11. Appeals
An applicant or other aggrieved party may appeal any decision of the Road
Commissioner, Code Enforcement Officer or Planning Board, or apply for a
variance, by filing with the Board of Appeals according to the procedures outlined
in the Board of Appeals Ordinance for the Town of Unity.
Pave 18| 72
Section Ill Non-Conformance
1. Purpose
It is the intent of these provisions to promote land use conformities, except that
non-conforming conditions that legally existed as of the effective date of this
Ordinance or any amendment thereto shall be allowed to continue, subject to the
requirements set forth in this section.
2. General Requirements
A. Transfer of Ownership
Non-conforming structures, lots, and uses may be transferred, and the new
owner may continue the non-conforming use or continue to use the non-
conforming structure or lot, subject to the provisions of this Ordinance.
B. Repair and Maintenance
This Ordinance allows, without a permit pursuant to this Ordinance, the
normal upkeep and maintenance of non-conforming uses and structures.
3. Non-Conforming Structures
A. Expansion
A non-conforming structure may be added to or expanded after obtaining a
building permit from the Planning Board, if such addition or expansion does
not increase the non-conformity of the structure. This includes the
establishment and addition of an accessory dwelling unit within, or
attached to an existing, non-conforming structure.
B. Relocation
A non-conforming structure may be relocated within the boundaries of the
parcel on which the structure is located provided that the site of relocation
conforms to all setback or other dimensional requirements to the greatest
practical extent as determined by the Planning Board, and provided that
the applicant demonstrates that the present subsurface sewage disposal
system meets the requirements of State law and the State of Maine
Subsurface Wastewater Disposal Rules or that a new system can be
installed in compliance with the law and said Rules. fu no case shall a
structure be relocated in a manner that causes the structure to be more
non-conforming. -
Page 19] 72
In determining whether the building relocation meets the setback or other
dimensional requirements to the greatest practical extent, the Planning
Board shall base its decision on the size of the lot, the location of other
structures on the property, and the location of the septic system and any
wells that may be impacted.
C. Reconstruction or Replacement
A non-conforming structure may be replaced or rebuilt within one year
from the date of removal or destruction of the original structure. The new
structure may also be non-conforming, but it shall not be any more non-
conforming than the original structure.
4. Non-Conforming Uses
A. Expansions
Non-conforming uses that legally existed as of April 1, 1995 may expand
in the same location, subject to all applicable standards of this Ordinance.
B. Resumption Prohibited
A lot, building or structure in or on which a non-conforming use is
| discontinued for a period exceeding one year, or which is superseded by
a conforming use, may not again be devoted to a non-conforming use.
C. Change of Use
An existing non-conforming use may be changed to another non-
conforming use provided that the Planning Board finds that the proposed
use is equally or more appropriate to the location than the existing non-
conforming use, and that the proposed use will have no greater adverse
impact on adjacent properties than the former use.
The determination of appropriateness shall be based on the probable
changes in traffic (volume and type), parking, noise, potential for litter,
wastes or by-products, fumes, odors, or other nuisances likely to result
from such change of use. The performance standards of this Ordinance
shall apply to such requests to establish new non-conforming uses.
Page 20|72
5. Non-Conforming Lots
A. A non-conforming lot of record as of April 1, 1995 may be built upon,
provided that applicable performance standards and the requirements of
the State of Maine Subsurface Wastewater Disposal Rules are met. The
use of the lot must be one that is allowed in the district(s) in which it is
located.
B. The construction or establishment of an Accessory Dwelling Unit
(ADU) on a non-conforming lot is permitted if the ADU does not
increase the non-conformity.
6. Non-Conforming Signs
Non-conforming signs in existence on April 1, 2003 may be repaired, but
may not be enlarged, raised in height, or otherwise modified in ways that
are not allowed for new signs.
Section IV. Definition of Districts
1. Overview of District Delineations
A. Introduction
There are two baseline land use districts in Unity: the Downtown District
and the Rural District. All land in town is either in one or the other of
these two districts. Beyond that, there are three overlay districts within
which land may also fall: the Village District, the Aquifer Protection
District, and the Shoreland District. All five districts are delineated on
the Unity Land Use Map that is incorporated into this Ordinance.
B. Interpretation of District Boundaries
Unless specifically stated otherwise in this Ordinance, district boundary
lines are property lines and the centerlines of roads. Boundaries based
upon natural features shall be established by field measurement.
Should there be a conflict between the Land Use Map and wording of
this Ordinance, the wording shall prevail. Should it occur that the
Planning Board and an applicant cannot agree on the interpretation of
a district boundary, the Board of Appeals shall be the final authority as
to location.
Page 21|72
2. Baseline Districts
A. Downtown District
The Downtown District encompasses those portions of downtown
which are already developed and contiguous areas that could be
developed. The district's borders coincide, roughly, with the land area
that could be served by the Unity Utilities District. The Downtown
District is considered the growth area, into which development will be
directed.
The Downtown District comprises the polygon of land bounded by the
following delineations as represented on Unity's tax maps, listed
clockwise: northern boundary of parcels with frontage on Route 220
from Bangor Road to Back Troy Road (Map 11, Lots 44 & 45, Map 12,
Lots 30, 31-1, 30- 2, 31 & 32), west down the middle of the Back Troy
Road back to Route 220, south down the middle of Route 220 to the
southern boundaries of Map 12, Lots 13, 14 & 16 to Sandy Stream;
along Sandy Stream to the northeast boundary of Map 11, Lots 60-2 &
60-3, and the northwest and northeast boundaries of Map 11, Lot 61 to
Quaker Hill Road; west down Quaker Hill Road to the eastern boundary
of Map 11, Lot 59 (Unity College), moving clockwise along this
boundary until it meets Bacon Brook; moving downstream along Bacon
Brook until it intersects with the CMP transmission line right:-of-way
(ROW); through the center of the CMP transmission line ROW across
the Albion Road through Map 11, Lot 1 to the west boundary of Lot 1
to Sandy Stream; along Sandy Stream, crossing School Street to the
southwest boundary of Map 11, Lot 35; following the Lot 35 lot line
counter-clockwise to the western boundary of Lot 36, across Kanokolus
Road and the railroad tracks to include Map 11, Lot 37 to Unity Pond;
along Unity Pond to the northern border of Map 11, Lot 41 (Athletic
Complex) to the Bangor Road; north on the Bangor Road to the
northern boundary of Map 11, Lot 44.
B. Rual District
The Rural District comprises all of Unity that is outside of the
Downtown District.
3. Overlay Districts
A. Village District
The Village District comprises the older village center of the
Downtown District. It consists of properties with frontage on:
Paee 22|72
a) Depot Street from Main Street to the fire station and north
boundary of Map 11, Lot 16 (the Bagley property);
b) Main Street from the railroad tracks to Sandy Stream;
c) Murdock Lane;
d) Vickery Lane;
e) Wood Lane;
f) Kanokolus Beach Road (FR# 1) to the cemetery; and
g) Milmac Road.
B. Aquifer Protection District
The Aquifer Protection District comprises the area of land overlying
the sand and gravel aquifer associated with Sandy Stream, as shown
on the Land Use Map.
C. Shoreland District
The Shoreland District comprises the area of land identified in the Unity
Shoreland Zoning Ordinance and shown on the Land Use Map.
D. Retail Growth District
The Retail Growth District shall encompass all lots bordering School
Street, from Main Street to the bridge over Sandy Stream.
Section V. Dimensional Requirements
1. Lot Requirements
A. Purpose
This provision is designed to encourage creativity and diversity in
development design. In the Downtown District served by public sewer,
small lots are allowed. In the Rural District, lots may also be made
relatively small, as long as they are interspersed with larger lots to meet
the requirements for average lot size. There is no specific road frontage
requirement, but rather, more flexible requirements concerning lot
access and lot shape.
B. Applicability
These standards apply to all new lots created after April 1, 1995.
C. Basic Lot Size Requirements
Page 23|72
1) Downtown District
The minimum size for new lots served by sewer is 10,000 square
feet.
NOTE: Residential subdivisions involving lots of this size must set aside
additional land foropen space, as outlined in SectionX5.B.
The minimum size for other new lots is 20,000 square feet. The
applicant must show that a proposed lot--regardless of size is
provided with adequate subsurface wastewater treatment. Such
treatment can be provided on the lot or potentially off the lot, if
connected to an approved shared use system.
2) Rural District
New lots created by dividing a larger parcel must meet requirements
both for minimum lot size and for average lot size. The average size
of all created lots shall be at least 120,000 square feet, except in
some instances where properties are located in the shoreland zone,
as described in C(3) below
The minimum size for any single lot is 20,000 square feet. The
applicant must show that a proposed lot--regardless of size-- is
provided with adequate subsurface wastewater treatment. Such
treatment can be provided on the lot or potentially off the lot, if
connected to an approved shared use system.
When lots are created, their deeds shall state which portion of their
land area is undevelopable under existing ordinance because it is
tied up in satisfying average lot size requirements. A certified copy
of this deed language shall be provided to the Planning Board within
90 days of approval of a lot permit, and no building permit may be
issued for this lot until such documentation is provided.
3) Shoreland Zone
Portions of both the Downtown District and Rural District are also located
in the shoreland zone. Unity's Shoreland Zoning Ordinance contains
additional lot requirements, which mustalso be followed.
Forthe purposes of calculating average lotsize, a shorefront lot located in
the Rural District can be divided into two lots, provided that the resulting
average size of the two lots is at least 80,000 square feet and that all other
lot requirements of the Shoreland Zoning Ordinance are met. Each
additional lot after the second will require an additional 120,000 square
feet, on average.
Page 24|72
D. Further Lot Size Requirements (by district)
The lot size requirements detailed for each district are for the placement of
one residential dwelling unit.
a) In districts that allow residential uses, each primary or principal
dwelling is allowed one Accessory Dwelling Unit (ADU). While ADUs
must comply with Shoreland Zoning requirements, they are exempt
from lot area requirements. This information is detailed under
Section Il, Subsection 5, Permit Application C. Requirements for
Building Permit Applications for Accessory Dwelling Units.
b) If more than one principal dwelling unit is constructed or established
on a single lot, all dimensional requirements for land area shall be
met for each additional dwelling unit and/or principal structure. This
information is detailed under Section II, Subsection 5, Permit
Application D. Requirements for Building Permit Applications for
Additional Dwellings on One Lot.
1) Downtown District
When all the principal structures on the lot are served by sewer, each
principal structure beyond the first requires an additional 10,000 square
feet. When any principal structure on the lot is served by subsurface
wastewater treatment, each principal structure beyond the first requires
an additional 20,000 square feet. For all downtown lots, every dwelling
unit beyond the second requires an additional 2,500 square feet.
(EXAMPLE: A 4unit apartment building connected to the sewer must be
ona lot of 15,000 square feet.)
2) Rural District
Each principal structure beyond the first requires an additional 20,000
square feet. Each dwelling unit beyond the second requires an additional
10,000 square feet.
E. LotAccess
In order to ensure that remote lots may be serviced by roads or utilities in the
future, any new lot that is not located along a public road or a private road built
to standards (outlined in Section VI), must have a minimum 50 foot right-of-
way of deeded access to a public road or a private road built to standards.
This right-of-way may be shared by multiple lots. It shall be suitable for
installing utilities and for constructing a driveway (if it serves three or fewer
lots) or a private road (if it serves more than three lots).
F. Lot Shape
Page 25|72
In order to prevent the creation of long narrow lots that often restrict access to
and the productivity of contiguous back land, no newly created lot shall have
a ratio of length to width of greater than 5:1.
The Planning Board may waive this requirement if the applicant offers a
satisfactory plan for back land access and management.
2. Road Access Management
A. Purpose
This provision outlines a road access requirement as an alternative to
a road frontage requirement.
B. Applicability
These requirements apply to all access points onto public roads in the
Rural District that are created by new roads or driveways. (NOTE: A
circular driveway is considered one access point).
C. Access Point Frontage Requirements
Any new access point (constructed after April 1, 1995) located along a
public road in the Rural District must be an average of 200' from any
other access point. An access point may be closer than 200' to the next
access point as long as the average standard is maintained. Thus, 3
access points may be located along 600' of road frontage, 5 access
points along 1000' of road frontage, etc. Averages incorporating land
under separate ownership must place a deed restriction on the other
land to guarantee that the average will not be exceeded.
D. Access Point Dimensions
Each new driveway or parking lot entrance--at the point where it
connects to a public road--shall not exceed 11' in width if one-way or 22'
in width if two-way (excluding the flare that occurs at the actual point of
intersection). The provision does not apply to driveways for: a) fire
stations; b) ambulance companies; or c) commercial businesses
located in the Rural District.
The flare that occurs when a new road or driveway intersects with an
existing public road shall be based on a curb radius of between 5' and
15', which is sufficient to allow safe turning of trucks and emergency
vehicles while keeping speeds low and minimizing pedestrian hazards.
The Planning Board may allow larger curb radii in select instances, but
only where: a) the new intersection results from a driveway or road that
Page 26| 72
primarily serves a commercial facility that will generate substantial truck
traffic; and b) special measures are taken to ensure pedestrian comfort
and safety. In no instance may the Planning Board allow larger curb
radii within the Village District.
3. Structural Requirements
A. Applicability
These requirements apply to all new structures constructed after April
1, 1995.
B. Building Height
The roof ridge of buildings shall be no higher than 35' above grade.
Buildings may contain steeples, cupolas, or other ornaments that
exceed this height. Buildings higher than 30' shall be designed to
facilitate access to roofs for fire-fighting purposes.
New structures are limited to two stories of livable space above grade,
unless specific, written approval is granted by the Fire Chief. The Chief
shall base this decision upon the Fire Department's ability to evacuate
people safely from upper stories of the structure.
C. Building Setbacks from Front Property Line
1) Rural District
Structures must be set back at least 50' from the road centerline
or 15' from the edge of the road right-of-way (i.e., the front
property line), whichever is further back.
2) Downtown District
a) General Requirement
Structures must be set back at least 50' from the road centerline
or 15' from the edge of the road right-of-way (i.e., front property
line), whichever is further back.
b) Special Exception
Wherever existing structures are located closer to the road
right-of-way than 15', new structures on adjoining lots may be
located as close to the road right-of-way as those existing
structures:
Page 27|72
D. Building Setbacks from Side and Rear Property Lines
1) Basic Dimensional Standard
In order to minimize the chance that a building fire will spread to
another building, structures under separate ownership shall
maintain a 30' separation distance. To meet this objective, all
permanent structures shall be placed at least 15' from side and rear
property lines.
2) Performance Standard Option
The use of certain construction materials or the installation of fire
extinguishing systems, such as sprinkler systems, may substitute
for the side and rear setback requirement. A structure may be
located closer than 15' to the side or rear boundary upon approval
of the Fire Chief. In the Downtown District, the Planning Board may
also approve two owners sharing a single wall, if approved by the
Fire Chief and acceptable to both property owners.
Any use of this performance standard option will require a current
survey of the property lines or a recorded boundary line agreement
between the two property owners.
4. Agricultural Protection Setback
A. Purpose
These setback requirements are designed to help protect owners of
commercial farmland from encroaching development, and to help
prevent conflicts between commercial agriculture and other land uses.
B. Applicable Farmland
In the Rural District, these setback requirements apply to all commercial
farmland (as defined), regardless of size, used in whole or in part for
crop production, either currently, or at any time within the past three
years. In the Downtown, this provision applies to all commercial
farmland (as defined), of at least 10 acres, used in whole or in part for
crop production, either currently, or at any time within the past three
years.
C. Property Covered
These setback requirements apply to all property that is located within
Page 28|72
300' of applicable farmland (as described in paragraph B above) in the
Rural District and within 150' of applicable farmland in the Downtown
District, unless that property is owned by the owner of the applicable
farmland.
Lots created after April 1, 1995 that are adjacent to applicable farmland
shall be designed so that the setback requirements listed below may be
met. The Planning Board shall not issue a lot permit for any lot intended
for new development that is so small that these setback requirements
could not be met.
Lots created after April 1, 1995 that are not adjacent to applicable
farmland at the time of creation, are exempt from the setback
requirements listed below. The owner of such a lot is not obligated to
follow these setback requirements, regardless of the future use of
adjacent land.
Lots existing as of April 1, 1995 that are adjacent to applicable farmland
but are too small to allow the setback requirements listed below to be
met, shail be exempt from these requirements.
Lots existing as of April 1, 1995 that are adjacent to applicable farmland
and are large enough to allow the setback requirements listed below to
be met, are obligated to meet these requirements.
The Planning Board shall determine whether a lot that existed as of April
1, 1995 is too small or large enough for the setback requirements to be
met, based on the practical sites for locating a principal structure and a
well on that lot.
D. Setback Requirements
Water wells supplying drinking water to dwellings may not be located
within 300' of applicable farmland in the Rural District or within 150' of
applicable farmland in the Downtown District.
Principal structures (as defined) may not be located within 100' of
applicable farmland in the Rural District or within 50' of applicable
farmland in the Downtown District.
These requirements do not prevent replacement of an existing structure
or well.
E. Inapplicability to some property.
These setback requirements do not apply to property owned by the
owner of the applicable farmland.
F. Appeals
An aggrieved party may appeal these requirements in accordance with
the procedures of the Board of Appeals Ordinance for the Town of Unity.
Section VI. Farmland Protection Incentive Measure
1. Purpose
This measure is intended to alleviate some development pressures on
productive farmland, by providing an incentive to locate development on
other land.
2. Applicability
This measure applies to "productive farmland" located in the Rural District.
Productive farmland is defined as land which has historically been used for
commercial crop production, or that meets the definition of either prime,
unique, or significant farmland soils as defined by the Soil Conservation
Service. Land supporting commercial orchards and Christmas trees is
considered productive farmland, while that supporting other trees is not,
unless it meets one of the soil definitions outlined above.
3. Specific Measure
A parcel may be divided into more building lots than otherwise possible, if
structures are placed off productive farmland and a portion of farmland is
preserved. Depending on the configuration of such a parcel, a landowner
may actually be able to create twice as many lots.
Where the landowner meets two conditions, the average size of new lots
can be reduced to 60,000 square feet (sf). (Individual lots may be made as
small as 20,000 sf, as long as the average size of lots is no smaller than
60,000 sf.) The first condition is that any lot created at a higher density
(than one lot per 120,000 sf) cannot either locate structures or impervious
surfaces on productive farmland, or otherwise diminish the land's potential
for cultivation. The second condition is that for every lot created at the
higher density, at least 40,000 sf of productive farmland must be preserved.
This preserved land may be contained within the new lot, or within any other
lot within the Town.
4. Administration
All applicants for a building permit or development permit who seek this
Page 30] 72
"density bonus" shall request this as part of their application. They shall
provide: a) a map of the property clearly showing the proposed lot lines and
the delineation between productive farmland and other land, if applicable;
and b) a written statement specifying the productive farmland that will be
preserved as open land.
The Planning Board shall grant the requested permit with the requested
density bonus if the application satisfies: a) the requirements outlined
herein; and b) all other applicable requirements of Unity's Land Use
Ordinance. Final approval shall be conditional on the placement of formal
deed restrictions on the requisite amount of productive farmland.
5. Preserved OpenLand
Open land shall be preserved through deed restrictions. Any such
restriction may only be removed by a vote of the town at the annual Town
Meeting.
Preserved open land may be divided into separate ownership, and sold
or otherwise transferred as each owner sees fit. The land may be fenced,
or used to locate temporary, agricultural structures--such as calf hutches-
-that do not reduce the land's potential for cultivation. But the land may
not be used for structures or impervious surfaces, or other activities that
would diminish the land's potential for cultivation, including removal of
topsoil.
Section Vil. Special Performance Standards
1. Parking Areas
A. Parking Requirement
All buildings or building additions constructed after April 1, 1995 must
provide parking to accommodate all anticipated need. Generally, this
need will be met through the construction of new off-street parking
areas. However, for commercial buildings in the Downtown District,
some of this need may be met through on-street parking, where such
parking will not create traffic or visibility problems, as determined by
the Planning Board. Specific requirements for residential uses are
outlined below.
Accessory Dwelling Units: An Accessory Dwelling Unit may not be
subject to any additional parking requirements beyond those
required of the single-family dwelling unit on the lot where the ADU
is located.
Page 31|72
Multi-Family Dwellings: All buildings being converted or expanded
into multi-family dwellings after April 1, 1996 shall provide off-street
parking to accommodate all anticipated need.
B. Landscaping Requirement (Downtown District only)
In the Downtown District, larger-sized off-street parking areas
constructed after April 1, 1996 that are clearly visible from a public
road shall be landscaped to reduce visual impact. All parking areas
designed to accommodate more than 10 vehicles shall provide a
minimum 6' landscaped buffer between the parking area and the
road right-of-way. All parking areas designed to accommodate more
than 20 vehicles shall also provide landscaped islands or peninsulas
within the parking area so that a minimum of 5% of the area's interior
is landscaped.
C. Screening Requirement (Village District only)
In the Village District, off-street parking areas built after April 1, 1995
shall not detract from the existing residential character of the
neighborhood. To meet this objective, any new parking area
designed to accommodate more than three vehicles shall be located
behind a building or otherwise screened from clear view. Parking
spaces designated for elderly or handicapped people are exempt
from this requirement.
2.Commercial Signs
A sign permit must be obtained to erect any commercial sign that is
either larger than 10 square feet or illuminated. A sign permit may be
issued by the Code Enforcement Officer, as outlined in Section Il.
A property owner shall conform to the following standards for
commercial signs whether or not a sign permit is required:
A. No sign may contain blinking or flashing lights.
B. An internally lit sign may only be lit while the business is open.
C. No sign erected after April 1, 2003 may be internally lit.
D. Any sign erected after April 1, 2003 that is located in the Rural
District may only be lit while the business is open.
E. Any sign erected after April 1, 2003 that is illuminated must utilize
low glare lighting that is directed downward. -
F. Nosign may be placed in a way that creates a hazard to pedestrian
or vehicular traffic.
G. A sign's height may not exceed the height of the building it
advertises.
H. A business classified as a "home occupation" (as defined) may not
erect a sign larger than 10 square feet (i.e., 4' x 2.5' or 5' x 2 or any
Page 32] 72
other combination that equals 10 sf) without being reclassified as a
"home-based enterprise" (as defined).
|. No more than two free-standing signs may be placed on each lot,
unless the development is a large one that triggered "development
review" and through that process the Planning Board agreed to
allow additional signs.
J. Signs also need to meet any additional requirements that may be
imposed by the Planning Board through the "development review"
process that is required for large developments.
These standards also apply to any exterior vending machine that is
clearly visible from a public road. These standards do not apply to
temporary signs (as defined) or seasonal decorations.
These standards do not prevent the repair of non-conforming signs that
existing prior to April 1, 2003, provided that the repair does not increase
non-conformity.
3. Retail Activity in the Rural District
A business or other entity located in the Rural District may only engage in retail
activity involving sales of goods or services if one of the following conditions
exist:
A. the activity occurs at a home-based business; or
B. theactivity primarily involves the sale of goods that are either grown, made,
or substantially altered on the premises, or of services related to those
goods; or
a) the activity is not expected to attract more than 20 car trips of retail
customers per day; or
b) the activity occurs less frequently than 15 days in a given year; or
c) the business is primarily engaged in the sale or repair of motor vehicles or
other motorized equipment such as lawn mowers or chainsaws.
Applicability: These standards apply to all enterprises that are new to a
particular site or expansions of existing enterprises that would trigger
development review (Section X). Thus, these standards donot apply to existing
enterprises already doing business at a site, including expansions of those
businesses that are not large enough to trigger development review.
4. Retail Activity in the Downtown District
All new businesses (except home-based businesses) located in the Downtown
District that are engaged in retail activity involving sales of goods or services shall
be located either in the Village District or the Retail Growth District. The Retail
Growth District shall encompass all lots bordering School Street, from Main Street
tothe bridge over Sandy Stream.
5. Special Requirements for Village District
Any new building or building addition constructed within the Village District for non-
residential use may not exceed a building footprint of 2,000 square feet, except that
the Planning Board may approve footprints of up to 4,000 square feet where the site
has been creatively designed and laid out in manner that does not detract from the
historic, small town character of the Village District.
No commercial activities occurring in the Village District may create noise, light,
glare, odor, smoke or dust that either exceed average residential levels or in any
way detract from the small town character of the Village District, as determined by
the Planning Board.
6. Special Requirements for Large Commercial Complexes
All commercial complexes located in the Downtown District that involve more than
10,000 square feet of indoor space must be located and designed to minimize
vehicular traffic and to enhance downtown convenience and walkability, through
the following measures:
A. New sidewalks, both within the complex and connecting the complex to
existing Downtown sidewalks and nearby business activities;
B. The use of "shared used" parking areas, both within the complex and
in conjunction with nearby businesses, wherever possible, in an effort
to limit pavement and encourage "one-stop" shopping;
C. Extensive landscaping designed to break-up parking areas and to
make pedestrian routes attractive;
D. "Human-scale" lighting, with light poles never exceeding 20' in height,
and perhaps less in certain settings, as determined by the Planning
Board;
E. Adequate provision for bicycle movement and parking;
F. Conformity with any community plans approved by Town Meeting that
involve bike routes, a van service, or other alternative transportation
strategies.
These requirements do not apply to existing commercial complexes unless
those complexes are expanded, and the expansion involves more than 2,000
square feet of indoor space and the total amount of indoor space after the
expansion will exceed 10,000 square feet.
Page 34|72
7. Commercial Impacts throughout Town
No commercial activity except farming, logging, or mineral extraction (such
as operating a gravel pit) may create noise, light, glare, odor, smoke or dust
that -as observed at the property line- exceed common background levels for
such nuisances, as determined by the Planning Board. This requirement
does notpertain to impacts that occur during construction or that occur on a
temporary basis.
Any business engaged in the repair of motor vehicles that did not previously
exist in Unity as of April 1, 2003, or that moves to a new location within Unity
after that date, shall store all inoperative vehicles, machinery, parts, or
products either within a building or within an enclosed area concealed from
public view from adjacent properties by an opaque screen (involving
landscaping, fencing, structures, or some combination).
8. Lighting
All exterior non-residential lighting erected after April 1, 2003, must be low
glare lighting directed downward, where the direct light being emitted does
not either fall directly on abutting property or create a safety hazard on a
roadway.
. In the Rural District, the following additional standards apply, if the lighting
involves either: 1) commercial activities that are new to a location after April
1, 2003; or 2) expansions occurring after April 1, 2003:
A. Commercial activities may not illuminate exterior displays of products.
B. Commercial parking areas may only be illuminated when the business
isopen.
C. Ata commercial facility, the total intensity of lighting that is visibly from
a public road or abutting property may not exceed levels customarily
associated with residences, as determined by the Planning Board.
Nothing in this section applies to lighting that was already in place as of April
1, 2003. Nor does it in any way prevent the use of exterior lighting in
emergencies or as holiday decorations.
9. Driveways and Roads
A. Permit Required
A permit must be obtained before construction on a new road or
driveway may be begun, as outlined in Section II of this Ordinance.
B. Locational Restrictions
Driveways and roads must comply with the Road Access
Page 35|72
Management guidelines outlined in Section V of this Ordinance.
C. Construction Standards - Driveways
NOTE: A driveway may serve up to 3 principal structures and/or lots
before being considered a road.
A new driveway that is over 150' in length and that serves a year-
round residence requires one of the following: a) a 12' travel way, 12"
gravel base, and a suitable place for a firetruck to tum around; or b)
a signed statement from the Fire Chief stating that the proposed
driveway appears adequate for emergency vehicle access. Any new
driveway that is shorter than 150' or that doesn't serve year- round
residences is exempt from this requirement.
D. Construction Standards - Roads
A new private road must have a 50' right-of-way, an 18" gravel base,
a 12' travel way, 2' shoulders, and adequate culverts. Any road which
may be offered for acceptance to the community must meet the
standards of Unity's StreetConstruction Ordinance.
10. Mobile Home Parks
| A. Applicability
| These performance standards apply to all mobile home parks
established in Unity after April 1, 1995, as well as to expansions of
mobile home parks existing on that date. They shall be applied in
addition to the Development Review standards applied to all
subdivisions. If there is a conflict, the most restrictive legally
enforceable provision shall apply. Mobile home parks are not eligible
for the creation of Accessory Dwelling Units.
B. Performance Standards
1) Lot Size, Width and Density
Lots in a mobile home park shall meet the following lot size, width
and density requirements.
a) Lots served by public sewer:
Minimum lot size= 6,500 square feet
Minimum lot width = 50 feet
b) Lots served by individual subsurface sewage disposal
system:
Minimum lot area= 20,000 square feet
Page 36|72
Minimum lot width = 100 feet
c) Lots served by a central subsurface wastewater disposal
system:
Minimum lot area= 12,000 square feet
Minimum lot width= 75 feet
d) Lots within the Shoreland District shall meet the lot area, lot
width, setback, and shore frontage requirements outlined in
Unity's Shoreland Zoning Ordinance.
2) Setbacks
a) Mobile homes and accessory structures shall be placed at
least 15 feet back from the edge of the park road right-of-
way and from adjacent lotlines.
b) Mobile homes in a mobile home park but adjacent to a public
road shall be set back from the public road a distance equal
to the setback requirement for other structures in the district.
3) Road Standards
Private roads within a mobile home park must have a right-of-
way of at least 23' and be adequately maintained by the park
owner or operator. Any road within a mobile home park which
may be offered for acceptance to the community must meet the
standards of Unity's Street Construction Ordinance.
4) Parking Requirements
For each mobile home lot there shall be provided and
maintained at least 2 off-street parking spaces. Each parking
space shall contain a minimum area of 200 square feet with
minimum dimensions of 10 feet by 20 feet.
5) Utility Requirements
All mobile home parks shall provide permanent electrical, water
and sewage disposal connections to each mobile home in
accordance with applicable State and local rules and
regulations.
6) Buffer Strip
A buffer strip shall be provided within 25 feet of all property lines
whenever the density of dwelling units within the park is at least
twice the density of units allowed by this Ordinance on abutting
property. Within the buffer strip, visual screening shall be
provided. Whenever possible, this screening shall consist of
landscaping with native vegetation. It shall block from view at
least 80% of the mobile home park and shall be maintained as
long as the park is operated.
7) Conversion of Park
No lot in a mobile home park may be sold or conveyed without
the prior approval of the Planning Board. Any such lot sold or
conveyed shall meet the lot size requirement of the district in
which it is located.
11. Energy System Development
A. Zoning Ordinances
For rules Governing the development of larger wind turbines, refer to
Unity's "Wind Turbine Generator Ordinance" (2011). For rules
governing the development of solar farms, refer to the "Unity Solar
Farm Ordinance" (2022). For rules governing the development of
ETFC's (Electric Transmission Facilities of Corridors), refer to "Unity
Electric Transmission and Corridors Ordinance" (2024)
12. Requirements for Small and Intermediate Wind Turbines
A. Purpose
This section provides rules to govern the development of small and
intermediate wind turbines,
B. Applicability
This section applies to all wind turbines that: 1) are shorter than 150
feet above surface grade (measured with a blade at its highest arc);
and 2) have a manufacturer's nameplate capacity of less than 100 kW.
Turbines of this size are classified as either Type 1 (Small) or Type 2
(Intermediate) under Unity's Wind Turbine Generator Ordinance. That
Ordinance does not apply to Type 1 and Type 2 turbines, but only to
larger turbines (Type 3 and Type 4).
C. Specific Requirements
Page 38 |72
Wind turbines shall be set back from the property line a distance that
is at least 110% of the height of the structure, measured vertically from
the tip of the blade at its highest arc to the surface of the ground at the
base of the structure.
The minimum distance between the ground and any turbine blade
(measured at its lowest arc) shall be 25 feet.
Wind turbines shall be sited so that no obtrusive shadow flicker occurs
off the applicant's property. Shadow flicker is defined as alternating
changes in light intensity caused by the motion of turbine blades
casting shadows.
Wind turbines shall be a non-obtrusive color such as white, off-white,
or grey.
Wind turbines shall not display any signs or advertising other than the
manufacturer's nameplate.
Wind turbines shall not be artificially lit, except if required by state or
federal law.
Wind turbines shall comply with all state or federal requirements.
NOTE: Under current state law, no wind turbines are allowed within
the shoreland zone.
D. Special Application Procedures
All abutting property owners shall be notified by the applicant of
his/her intent to submit an application for a wind turbine.
All applicants for a wind turbine under this Ordinance shall submit a
standard building permit application and follow the procedures for
that, except that the application shall contain an addendum that
includes: 1) an accurate, detailed site plan showing the proposed
location of the structure, the boundaries of the applicant's property,
and the distances from the structure to all property lines; 2) a copy of
a standard USGS topographic map clearly showing the proposed
location of the structure and the boundaries of the applicant's property
in relation to abutting properties; and 3) a list of all abutting property
owners and a description of how the applicant notified them.
Section Vill. Downtown Design Guidelines
1. Purpose
Page 39|72
These Guidelines are intended to help preserve and enhance the
"traditional character" of downtown Unity, by assuring that new downtown
development is compatible with that character.
The traditional character of downtown Unity is more the result of the basic
design and placement of buildings than specific architectural styles.
Some of the features that define that character include pitched roofs,
vertically oriented windows, and pleasing scale and proportions. Such
features are evident in most of Unity's buildings constructed before 1950,
and in many constructed thereafter.
These Guidelines stress general design features rather than specific
architectural styles. A newly constructed building must follow certain
standards for roof pitch and windows, but need not follow a particular
style. An existing building may be renovated in keeping with its existing
style, or in any way that is allowed for new construction. The goal is to
preserve and enhance downtown Unity's special character, but in a way
that allows flexibility and encourages diversity.
2. Applicability
These Guidelines only apply to certain construction activities within the
: Downtown District (for example, all renovations to existing single-family
homes are exempt), and only to design features that are "clearly visible"
from the public road.
DEFINITION: A "clearly visible" feature is one that an average person passing
down a road would notice. Forinstance, asmall feature on the side ofa building
that is only visible from one place on the roadway is not "clearly visible." In
almost all cases, the back side of buildings is not affected; inmany other cases
(where landscaping or neighboring buildings shield public view), the sides and
even the front of buildings may not be affected. (See "Visual Screening Alternative"
described later.)
Applicable activities include:
A. the construction of any new building downtown, except certain single-
family homes as exempted below;
B. any exterior renovation made to a downtown commercial building
built, sold, or leased (to a new tenant) after April 1, 1995;
C. any exterior renovation made to a downtown multi-family residence
built or sold after April 1, 1995;
D. any exterior renovation made to a downtown single-family home for
the purpose of converting it into a commercial building or multi-family
residence;
Page 40|72
E. any addition made to a downtown commercial building or multi-family
residence, or to a single family home for the purpose of converting it
into a commercial building or multi-family residence.
Thus, the following activities are exempt: 1) renovations or additions
made to any existing single-family home as long as it remains a single-
family home; 2) renovations made to any existing multi-family residence
as long as it remains under existing ownership; and 3) renovations made
to any existing commercial building as long as it remains under existing
ownership or tenancy.
In addition, new single-family homes constructed on lots that existed as
of April 1, 1995 are exempt, as long as the lot remains in the same
ownership as it was on April 1, 1995.
3. Specific Provisions
Unless following the "Visual Screening Alternative" (described later), all
applicable construction activities shall follow specific guidelines for: A)
basic design (scale, proportion, and size); B) key exterior features (roofs,
windows, dormers, porches, and siding); and C) building placement
(elevation, setback, and orientation).
A) Basic Design
Any new commercial building or multi-family residence shall be
constructed so that its scale and proportions are compatible with the
traditional character of downtown Unity. This means that large
buildings with a single, visible wall-face of 40 (or more) linear feet
must follow one of two strategies: 1) "breaking up" the building
visually (through use of juts, changes in rooflines, etc.) to give the
appearance of smaller components; or 2) constructing the building in
a traditional style for large buildings (Examples: a traditional barn,
Unity Hardware Store).
Existing buildings may be renovated and/or expanded either in ways
that are similar to their existing styling, or in ways that would be
allowed for new construction. Where an existing building is expanded
in a way that would not be allowed for new construction, the volume
of the addition may not exceed the volume of the existing structure
by more than 30%.
B) Key Exterior Features
The visible portions of the roofs of new buildings shall follow one of
many traditional styles, including gable, hip, and gambrel. Gable
roofs shall be pitched at a minimum of 8:12, unless it meets one of
the exemptions described later. Hipped roofs shall be pitched at a
minimum of 5:12. (Pitch standards do not apply to the roofs of
porches, or small building additions or projections, as long as such
roofs are compatible with the building's overall roof design.) The
Planning Board may, at its discretion, allow: 1) gable roofs to be
pitched as low as 7:12 on larger buildings, if a higher pitch would, in
the opinion of the Planning Board, create a height problem; or 2)
gable roofs to be pitched as low as 6:12 on traditionally-styled
buildings that have two full stories above-ground before the roof
begins.
Porches, dormers, or other building projections clearly visible from
the street shall be compatible with the architectural character of the
building. Any exterior stairway shall be designed and/or placed so
that the impact on the building's overall lines are minimized.
The clearly visible windows and doors of all new buildings shall be
placed in a traditional pattern. In particular, clearly visible windows
shall have a vertical orientation, the result of using either traditional,
narrow windows (roughly 2 times higher than they are wide) or wider
windows that retain a vertical orientation through the use of mullions
or other architectural devices. Building renovations that involve
window or door replacement shall either use components similar to
what existed before, or components that are allowed for new
buildings.
The building exterior clearly visible from the street should be
compatible with the traditional character of downtown Unity.
Clapboard (including vinyl, concrete, and aluminum siding), shingles,
or traditional brick are examples of compatible sidings. Brash or
fluorescent exterior colors are not allowed.
C) Building Placement
A new building's foundation elevation (above grade), its setback
(from the road), and its orientation (toward the road) shall be
compatible with neighboring structures that are located on the same
road and within 200' of the new building.
4. Special Design Review Committee
The Planning Board shall create a Design Review Committee to help
review proposed designs on all new commercial and_ institutional
buildings that trigger both Downtown Design Guidelines and
Development Review. This Committee shall consist of three members. At
Page 42|72
least one member shall be a Unity resident. At least two members shall
have professional design experience. This Committee shall be provided
copies of plans of proposed buildings and landscaping, and given an
opportunity to provide feedback on these plans to the Planning Board
before any permit is issues. The Committee's input will be advisory to the
Planning Board. Those Committee members who live outside out town
may, at the Planning Board's discretion, be compensated an amount not
to exceed $50 per application, paid for by the applicant.
5. Visual Screening Alternative
Construction activities need not comply with the "Specific Provisions" if the
resulting structure is located at least 200 feet from the road right of way and is
screened from view (from the street) through appropriate landscaping. Such
landscaping shall consist of trees or shrubs that effectively and attractively
screen at least 80% of the building from view throughout the year. This means
that screening mustinclude either adequate conifers and/or very dense buffers
of deciduous trees. The owner of a property that was issued a building permit
conditional on this visual screening alternative will be considered in violation of
this ordinance if the requirement of screening at least 80% of the building from
view throughout the year is not accomplished within 5 years of construction.
6. Administration & Appeals
Where these Guidelines are applicable, an applicant for a building permit shall
seek either: 1) design approval (complying with the "Specific Provisions"); or 2)
landscaping approval (complying with the "Visual Screening Alternative"). The
building permit application shall provide sufficient detail to allow the Planning
Board to assess adequately, either the proposed design or landscaping plan.
(This would include building elevation drawings for all new structures or major
renovations.)
Where the Planning Board finds that either a design or landscaping plan does
not satisfy the intent of these Guidelines, it shall deny approval and explain to
the applicant in writing the reasons for doing so. Where appropriate, the
Planning Board shall suggest to the applicant ways the design or landscaping
plan may be modified to satisfy the Guidelines. The applicant may resubmit a
modified building permit application without an additional fee.
Appeals may be made in accordance with the procedures outlined in the Board
of Appeals Ordinance for the Town of Unity.
Section IX. Aquifer Protection Standards
Page 43|72
1. Purpose
This section is designed to ensure that new land use activities conducted
over: 1) the sand and gravel aquifer associated with Sandy Stream; or 2)
the bedrock aquifer underlying the downtown area, together with its direct
run-on recharge area, do not harm these valuable sources of groundwater.
2. Applicability
The Aquifer Protection District shall include the following areas of land:
a) land overlying the sand and gravel aquifer associated with Sandy
Stream. This land area is identified on the Land Use Map. District
boundaries were derived from the Maine Geological Survey (Open file
report 87-24C, Plate 2 of 3, Map 30). If an applicant wishes to
challenge the district boundary, he/she shall present hydrogeologic
evidence to support the claim. The evidence shall be prepared by
a geologist, certified to practice in the State of Maine.
b) land within the Downtown District; and
c) land within the "Run-on Recharge Area" serving downtown as
shown on the map entitled "Plate |-Overburden Data" prepared
by Cashwell, Eichler and Hill, Inc., as part of the Downtown Unity
Water Resources Evaluation completed in October 1995, or as
transferred onto the Land Use Map and so noted.
3. Conditional Uses
All proposed land uses in the Aquifer Protection District shall comply
with the requirements of this section.
4. Approval Procedure
A) All Applicants
All applicants for a building permit or a development permit who
propose activities in the Aquifer Protection District which have
the potential to contaminate groundwater as determined by the
Planning Board shall include as part of their applications
descriptions of: a) their intended use of ground water; b) the
potential sources of ground water contamination from any of
Puge 44|72
their proposed land use activities; and c) their proposed means
of preventing any potential contamination.
B) Additional Requirements of High Water Uses in Downtown
District
1) Applicability
Applicants proposing wells fitting any of the following three
conditions must demonstrate no adverse impact will occur
to any existing well as a result of the proposed operation.
Adverse impact shall be defined as an unreasonable
lowering of the operating level and/or a decrease in the
ability of the well to provide potable water.
a) All applicants whose proposed activity will pump a new or
existing well in the Downtown District at a long-term
average rate of 2 gallons per minute (GPM) or more.
(Note: 2 GPM equates to a use servicing up to 60 people at
48 gallons per day per person, or 2880 gallons per day.)
b) All applicants whose proposed activity will pump a new
or existing well in the Downtown District at a long-term
average rate of 1 GPM or more, if there is an existing
well within 200 radial feet of the proposal well. (Note: 1
GPM equates to a use servicing up to 30 people at 48
gallons per day per person, or 1440 gallons per day.)
c) Any new or existing well that is considered to be a Public
Water System by State definition.
2) Requirement
A developer who falls into any of the above three conditions
must engage a qualified Professional Engineer or Maine
Certified Geologist to demonstrate that no adverse impacts
will occur as a result of pumping the proposed well. In most
cases the proposed well will have to be pump tested for a
24-to-48-hour period. Water level measurements must be
taken in the pumping well and in at least one observation
well, and in all existing wells within 500 radial feel of the
pumping well (assuming each well owner grants permission
to open the well and make depth to water measurements
periodically during the pumping period). The consultant will
analyze the pumping test data using standard hydraulic
techniques in order to define the anticipated drawdown in
Page 45|72
the pumping, observation, and neighboring wells. Any
known potential source of groundwater contamination
within a 500-foot radius of the pumping well must be
identified and the possibility of contamination migration
under the proposed new pumping regime evaluated. A
report must be prepared for Planning Board review. It is the
responsibility of the developer to demonstrate the lack of
adverse impact. Remedies to offset or abate any predicted
adverse impacts may be offered by the consultant for Town
review and possible approval.
C) Conditions for Approval
The Planning Board shall grant the requested permit if the
application satisfies: a) the performance standards of this
section; and b) all other applicable requirements of this
Ordinance.
5. Performance Standards
1) Provision shall be made to protect against discharge or loss of
toxic or hazardous materials resulting from corrosion, accidental
damage, spillage, or vandalism. These provisions shall include:
spill control measures at hazardous material delivery, storage
and transfer points; secured storage areas for toxic or hazardous
materials; and indoor storage provisions for corrodible or
leachable materials. Handling and storage of toxic and
hazardous materials shall meet performance standards
established by the Maine Department of Environmental
Protection.
2) For uses that involve significant volumes of liquid chemicals, all
activities shall be conducted under cover and over an
impermeable surface. Use of dikes, liners, or other effective
techniques will be required to enable collection of any spill that
might occur. All materials will be handled and stored in properly
covered and secured containers and disposed of according to all
applicable federal and state regulations.
3) Proposed activities shall not negatively impact the quality or
quantity of the groundwater.
4) Proposed "high use" wells located within the Downtown District
shall demonstrate that no adverse impact shall occur to any
existing well as a result of the proposed well's operation.
(NOTE: A "high-use" well is any well that will pump a long-term
Page 46|72
average rate of 1 GPM if located within 200 radial feet of other wells
or 2 GPM regardless of location.)
5) All new wells of any intended pumping rate located in the
Downtown District shall be located at least 85 radial feet from
neighboring wells, unless a Maine certified geologist can
demonstrate to the Planning board's satisfaction that due to
relative depth or other factors, there is no scientific likelihood of
well interference posed by the proposed well.
Page 47|72
Section X. Development Review
1. Purpose
Development Review provides the Planning Board with the opportunity
to closely examine subdivisions and high impact developments. Such
developments must meet the special standards of this section.
2. Applicability
Development review is required for any development that:
1) qualifies as a subdivision of land and/or structure under State law:
2) qualifies as a "high impact" activity by meeting any of the following
criteria:
a) is estimated to generate over 100 car and/or 20 heavy truck trips
per day;
b) involves one or more structures with a combined gross floor area
of over 20,000 square feet;
Cc) involves the installation of any combination of pavement,
d) buildings, or other impervious surfaces that together cover more
than 20,000 square feet.
e) is likely to create any noise, odor, glare, vibration, smoke, dust,
electrical disturbance, activity at unreasonable hours, or other
nuisance that would disturb persons on neighboring properties
if not adequately designed and/or buffered;
f) is expected to draw more than 2000 gallons of groundwater per
day for uses other than agriculture; or
g) involves the construction or expansion of a mobile home park,
campground, or fairground
h) involves the construction or expansion of a commercial
telecommunications facility involving a tower higher than 100
feet above ground level.
Development review is also required for any expansion of a development
that would meet the definition of a high impact activity if built new,
wherever that expansion is expected to involve any of the following:
A. An increase of over 50 car and/or 10 heavy truck trips per day;
B. An increase of more than 1,000 square feet of building space, unless
the increase involves an agricultural facility such as a barn or
greenhouse being built in the Rural District
C. Construction of a new parking area;
D. An expected increase in any noise, odor, glare, vibration, smoke,
dust, activity at unreasonable hours, or other nuisance that would
Page 48 |72
disturb persons on neighboring properties if not adequately
designed and/or buffered, unless the impact is the result of
commercial farming.
3. Classification of Projects
Projects subject to development review shall be divided into two classes,
TYPE 1 and TYPE 2.
TYPE 1 developments shall include: a) projects involving the construction
or addition of less than 20,000 square feet of gross nonresidential floor
area; b) projects involving the installation of less than 20,000 square feet
of impervious surfaces; and c) projects involving the creation of less than
five lots and/or dwelling units.
TYPE 2 developments shall include: a) projects involving the construction
or addition of 20,000 or more square feet of gross nonresidential floor
area; b) projects involving the installation of 20,000 or more square feet
of impervious surfaces; c) projects involving the creation of five or more
lots and/or dwelling units; d) projects involving the establishment or
expansion of a mobile home park, campground, or fairground; e) projects
involving the non-agricultural use of more than 2000 gallons of
groundwater per day; and f) other projects requiring review which are not
classified as TYPE 1.
If the applicant is uncertain as to the classification of the project, he/she
may request a determination from the Planning Board.
4. Application Procedure
A. Application Process
The process involves the following steps:
1) attend an initial meeting, where application submission
requirements are reviewed;
2) submit a development review application in two stages (a
Preliminary Plan Stage and a Final Plan Stage).
B. Initial Meeting
Applicants shall schedule an initial meeting with the Planning Board,
prior to a formal submission of a development review application.
The Board and the applicant will discuss the proposed project and
review the various submission requirements.
The Planning Board may at this meeting waive specific application
submission requirements when an applicant can show that such
requirements are not relevant to the proposed project.
The Planning Board shall restrict its submission requirements to
those that are relevant to determining the project's compliance with
the provisions of this Ordinance. The granting of a waiver of a
submission requirement does not, however, prevent the Board from
requesting the information at a later stage of development review, if
the Board finds that the information is, in fact, relevant to the
proposed project.
C. Development Review Application
A development review application is required for both TYPE 1 and
TYPE 2 developments. The applicant shall prepare this application
in accordance with APPENDIX 1, and file it with the Town Clerk.
The development review application shall be reviewed in two
Stages: a Preliminary Plan stage and a Final Plan stage.
1)Preliminary Plan Stage
The Planning Board shall review any development review
application received at least 10 days before its next meeting at that
meeting. The applicant or his/her agent shall attend this meeting.
At this meeting, the Planning Board shall determine that the
application is either complete or incomplete (and thus requires that
additional information be supplied). If the Board finds the
submission incomplete, it shall outline for the applicant whatever
portions of the submission it finds lacking, and why. A revised
application submitted at least 10 days before the next Planning
Board meeting shall be reviewed at that meeting.
If the Board finds the submission complete, it shall decide within 60
days of making this finding, whether to approve or disapprove the
Preliminary Plan. It shall base its decision upon the standards listed
later in this section. If the Planning Board votes to approve the
Preliminary Plan (either with or without conditions), the applicant is
authorized to submit a Final Plan. However, approval of the
Preliminary Plan shall not constitute either approval of the Final
Plan or an intent to approve the Final Plan. If the Planning Board
votes to disapprove the Preliminary Plan, the applicant shall be
notified in writing and the specific causes of disapproval shall be
noted.
Page 530|72
A public hearing may be held during this Preliminary Plan stage. A
hearing for TYPE 2 projects will be held automatically, whereas a
hearing for TYPE 1 projects will be held at the discretion of the
Planning Board. Any public hearing shall be held within 30 days of
determining that the application is complete, and shall follow the
notification requirements outlined in Section I-9. The applicant may
be charged an additional fee to cover advertisement costs.
2)Final Plan Stage
The applicant may submit a Final Plan anytime within six months of
the Planning Board's approval of the Preliminary Plan. The Final
Plan shall contain the same basic information as the Preliminary
Plan, though that information may be modified to more clearly make
the case to the Planning Board.
The same timetable shall be followed for the Final Plan stage as
was followed for the Preliminary Plan stage regarding
determination of a complete application and making a decision on
the application. A public hearing may be held at the discretion of
the Planning Board.
The Planning Board shall base its decision of whether to approve or
disapprove a Final Plan upon the standards listed later in this
section. If the Planning Board votes to disapprove the Final Plan,
the applicant shall be notified in writing and the specific causes of
disapproval shall be noted. If the Planning Board votes to approve
the Final Plan, it shall issue a development permit, provided that all
other requirements of this Ordinance are met.
The Planning Board may either disapprove an application or delay
final action for up to six months if the applicant has within the past
five years received Planning Board approval for a building or
development where the applicant has not yet met conditions of that
approval to the satisfaction of the Board, provided that the Board
notifies the applicant in writing of the conditions that it feels have not
been satisfied within 7 days of completion of the Preliminary Plan
Stage. The Planning Board may interpret the "applicant" to be the
same in two applications submitted under different names, if the
same person or entity has a major or controlling role in both
applications.
D. Professional Review
If needed to ensure an application complies with this Ordinance, the
Planning Board may hire a professional of its choice to conduct an
Page 51] 72
independent analysis of any portion of an application. In such
instances, the Board shall choose a professional, obtain an estimate
for the work, and notify the applicant that the amount of the estimate
must be paid to the Town before any further consideration is given
to the application. No work will be initiated until the applicant pays
the estimated amount to the Town. Following completion of the
work, the applicant will be either billed for any cost incurred over the
estimate, or refunded any remaining balance.
5. Standards for Approval
The Planning Board shall base its decision for approving a development
permit based on requirements found elsewhere in the Ordinance plus the
standards outlined below. These standards are not intended to
discourage creativity, invention and innovation. The Planning Board may
waive certain standards upon a determination they are not applicable to
the proposed activity or not necessary to carry out the intent of this
Ordinance. Before granting approval for any subdivision, the Board shall
find that the applicant also meets the requirements of30-A MR.SA 4404.
A. Preservation of Land. Land shall be preserved in its natural state,
insofar as practicable, by minimizing tree and soil removal, retaining
existing vegetation where desirable, and keeping any grade
changes in character with the general appearance of neighboring
areas. Environmentally sensitive areas such as wetlands, steep
slopes, flood plains and unique natural features shall be maintained
and preserved to the extent possible. The Planning Board may
require that any structure and any potentially threatening land use
be set back 50' from these areas. Natural drainage areas shall also
be preserved to the extent possible.
All developments shall be configured to preserve productive
farmland (as defined) to the maximum extent practical. New
structures and roads may be built on farmland to the extent allowed
under other provisions of this Ordinance, but the applicant shall
seek creative measures to minimize development that: 1) occurs on
productive farmland; or 2) divides a single field; or 3) otherwise
reduces the ease with which a parcel of farmland can be farmed in
the future. Such measures may include: 1) interspersing small and
large lots to maximize single ownership of a given field; or 2)
locating some or all structures in woodland abutting farmland; or 3)
utilizing other strategies which the applicant or Planning Board may
devise.
All TYPE 2 developments occurring on parcels of land containing 5
or more acres of productive farmland (as defined) shall adhere to
the following standards: 1) no more than 15% of the farmland may
be used for structures, roads, or other impervious surfaces, with the
exception that use is allowed for an agricultural facility (such as a
barn or greenhouse, and associated road access); and
2) the remaining farmland shall be retained in a manner that
facilitates use for agriculture. The Planning Board may waive these
standards if the applicant preserves by permanent deed restriction
another parcel of productive farmland located in Unity that is equal
or greater in size.
B. Open Space. Any residential development that will contain more
than one dwelling unit -on average--for every 20,000 square feet of
land area shall set aside additional land as open space for use by
the development's residents. This additional land shall be equal or
greater in area to 10% of the minimum area required for such a
development elsewhere in this Ordinance. (For example: A 4- unit
apartment building on a sewered lot would require 15,000 square
feet--under Section V.1.D-- plus another 1,500 square feet under
this 10% provision.) No more than 25% of this land may consist of
wetlands, steep slopes, or other land unsuitable for active
recreation.
The Planning Board may waive this provision if the development is
located within 500' of public open space of suitable size and
features, and if that open space is linked to the development by a
safe pedestrian route.
C. Access to the Site. Vehicular access to the site shall be on roads
which have adequate capacity to accommodate the additional traffic
generated by the development. Pedestrian walkways shall be
adequate to provide safe access to the site.
If the proposed development activity is estimated to increase
vehicular traffic by 10% or more over existing levels, and if that
represents a traffic level for which the existing road is inadequate,
then the applicant will be required to upgrade affected roads to meet
the additional demand. The Planning Board may approve a
development not meeting this requirement if the applicant
demonstrates that:
1) A public agency has committed funds to construct the
improvements necessary to bring the level of access to this
standard, or
2) The applicant will assume financial responsibility for the
improvements necessary to bring the level of service to this
Pave $3] 72
standard and will guarantee the completion of the
improvements within 1 year of approval of the project.
D. Access into the Site. Vehicular access into the development shall
be designed to providefor safe access and to minimize adverse
traffic impacts. Any new driveway or road that will intersect with an
existing public street shall be designed to provide a minimum sight
distance of ten times the posted speed limit in each direction, as
measured from the point at which the new driveway or road meets the
public street.
1) In subdivisions, the number of new driveways intersecting directly
with the existing street shall be minimized. Wherever practical,
such driveways shall flow into a new road (or roads) which then
intersect with the existing street.
2) Points of intersection shall be located to avoid hazardous conflicts
with existing turning movements and traffic flows.
3) The grade of any new road or commercial driveway shall be a
maximum of 3% for a distance of 25 feet from its intersection with
any existing street. If determined necessary for traffic safety, the
Planning Board may require that a moderate grade extend for a
greater distance from the intersection.
E. Internal Vehicular Circulation. The layout of the site shall provide for the
safe movement of passenger, service and emergency vehicles through
the site. Adequate parking will be provided for all anticipated use of the
development. Off-street parking areas shall be designed so vehicles do
not need to back out onto a public street.
F. Pedestrian Circulation. If located within the Downtown District, the
development plan shall provide for a system of safe pedestrian
circulation within the development. This system shall connect with
existing sidewalks if they exist in the vicinity of the project. The
pedestrian network may be located either in the street right-of-way or
outside of the right-of-way in open space or recreation areas. The
developer shall describe a plan for summer and winter maintenance of
the pedestrian system.
G. Erosion _and_sediment_control. The site shall be developed in
accordance with the following measures:
1) Stripping of vegetation and regrading shall be done in such a way
as to minimize erosion.
Page 54|72
2) The disturbed area and the duration of exposure of the disturbed
area shall be kept to a practical minimum.
3) Temporary vegetation or mulching shall be used to protect
exposed critical areas during development.
4) The permanent (final) vegetation and erosion control measures
shall be installed as soon as practical on the site. -
5) Until the disturbed area is stabilized, sediment in the runoff water
shall be trapped.
6) Whenever sedimentation is caused by stripping vegetation,
regrading or other development, it shall be the responsibility of
the developer causing such sedimentation to remove itfrom all
adjoining surfaces, drainage systems and watercourses and to
repair any damage at his or her expense as quickly as possible.
7) Development shall be undertaken in a manner that adequately
manages surface water runoff.
8) Any activity on a stream, watercourse or swale or upon a floodway
or right-of-way shall comply with the State's Natural Resources
Protection Act, Title 38 M.R.S.A. Sections 480A-480S. Any such
activity shall also be conducted in such a manner so as to maintain
as nearly as possible the present state of the stream, watercourse,
swale, floodway or right-of-way for the duration of the activity and
shall be returned to its original or equal condition after such activity
is completed.
9) Maintenance of drainage facilities or watercourses originating and
completely on private property is the responsibility of the owner to
the point of open discharge at the property line or at a communal
watercourse within the property.
H. Construction Site Conditions During construction, the site shall be
maintained and lefteach day in a safe and sanitary manner.
I. Surface Water Drainage. Adequate provisions shall be made for surface
drainage so that removal of surface waters will not adversely affect
neighboring properties, downstream conditions, or the public storm
drainage system and shall be held to a zero percent or less off-site
increase in quantity after development. On-site absorption shall be
utilized to minimize discharges whenever possible. All drainage
calculations shall be based on a twenty-five year storm frequency.
Emphasis shall be placed on the protection of floodplains and wetlands;
Pave 55|72
preservation of stream corridors; establishment of drainage rights-of-
way and the adequacy of the existing system; and the need for..
improvements, both on site and off site, to adequately control the rate,
volume and velocity of storm drainage. Maintenance responsibilities
shall be reviewed to determine their adequacy.
J. Groundwater Protection. The proposed development shall not adversely
impact either the quality or quantity of groundwater available to abutting
properties or public water supply systems.
K. Fire Protection. All TYPE 2 developments that are not located near
adequate sources of water for fire fighting (as determined by the Fire
Chief), may be required to install a pond (or other water source) and a dry
hydrant. The Planning Board shall make this decision in consultation with
the Fire Chief.
L. Drinking Water Supply. The development shall be provided withasystem
of water supply that provides each use with an adequate supply of water
meeting the minimum standards ofthe State of Maine for drinking water.
M. Sewage Disposal.
1) Inan area served by public sewer, the development shall connect
to the Unity Utilities District. The developer may be required to pay
an installation fee that covers the Utilities District's costs for
providing adequate service to the site.
2) All individual on-site septic systems shall be designed by a
licensed soil evaluator in full compliance with the Maine State
Plumbing Code, asamended.
N. Exterior Lighting. All exterior lighting shall be designed to ensure safe
movement of people and vehicles, and to minimize adverse impact
on neighboring properties and public ways. Adverse impact is to be
judged in terms of hazards to people and vehicular traffic and
potential damage to the value of adjacent properties. Lighting shall
be arranged to minimize glare and reflection on adjacent properties
and the traveling public. Strobe or flashing lights of any type are
prohibited, unless required by State or federal law for safety (e.g. on
radio towers).
0. Odor. The proposed development shall not produce offensive or
harmful odors perceptible beyond their lot lines, either at ground or
habitable elevation.
Page 56|72
P. Noise. The proposed development shall not raise noise levels to the
extent that abutting and/or nearby residents are adversely affected.
Q. Landscaping. Landscaping shall be designed and installed to: 1)
enhance the physical design of the building(s) and site; 2) to
minimize the encroachment of the proposed use on neighboring land
uses; and 3) to soften the appearance of off-street parking areas.
R. Relation of Proposed Development _to Existing Setting. The
developer shall demonstrate that proposed structures and utility
installations relate harmoniously to the terrain and to existing
buildings in the vicinity.
S. Financial and Technical Capacity. The applicant: must haveadequate
financial and technical capacity to meet these standards.
T. Comprehensive Plan. The proposed activity must be in conformance
with the Comprehensive Plan.
U. Additional Standards for Commercial Telecommunications Towers. All
commercial telecommunications towers higher than 100 feet in height
above ground level shall adhere to the following standards:
1) Setback: A new or expanded tower must be set back 105% of its
height from the property boundary. The setback may be satisfied
by land outside the property boundary if secured by easement
satisfactory to the Planning Board. The setback may be reduced
if the applicant demonstrates that the tower is designed to
collapse such that neighboring properties would not be affected.
2) Screening: Related equipment and structures must be screened
with plants from view of abutting property owners and public
roadways. Existing plants and natural landforms on the site shall
be preserved to the maximum extent possible.
3) Fencing: The facility must be fenced to discourage trespass.
4) Lighting: The facility must be illuminated only to the extent
necessary to comply with FAA or other applicable state and
federal requirements. However, security lighting may be used as
long as i is shielded to be down directional and designed to
minimize impact on abutting property.
5) Materials and Colors: The facility must be constructed with
materials and colors that match the surrounding natural
environment to the maximum extent practicable.
6) Structural Standards: The applicant must demonstrate to the
Planning Board's satisfaction that the facility is structural
designed to meet or exceed current industry standards. The
structural design must be signed by a qualified professional
Pave 57) 72
engineer, registered in the State of Maine.
7) Co-location: The applicant shall demonstrate that co-location on
an existing telecommunications tower cannot provide
comparable service to the residents of Unity. (It is recognized
that a different location will likely result in different service
characteristics; the applicant shall not merely identify these
differences, but demonstrate to the satisfaction of the Planning
Board that the proposed location will clearly provide better
service to the residents of Unity.) The owner of the facility and
his/her successors and assigns shall agree to: a) respond in a
timely, comprehensive manner to a request for inforn1ation from
a potential co-location applicant, in exchange for a reasonable
fee not in excess of the actual cost of preparing a response; b)
negotiate in good faith for shared use of the facility by third
parties; c) allow shared use of the facility with any party that
agrees in writing to pay reasonable charges for co- location; and
d) require no more than a reasonable charge for shared use of
the facility, based on Maine market rates and generally
accepted accounting principles.
8) Frequency Emissions: The applicant shall demonstrate how the
facility will comply with FCC regulations. During the life of the
facility, the owner agrees, upon request of the municipality, to
certify compliance with all applicable FCC radio frequency
emissions regulations in a manner understandable to the
average citizen.
9) Abandonment: A facility shall be considered abandoned if it is
not operated for a continuous period of 12 months at any point
after all municipal permits are issued. (If a facility was permitted
before March 31, 2009, and is not operating as of that date, it
shall be considered abandoned if it is not operating by March
31, 2010 The CEO shall notify the owner of an abandoned
facility in writing and order removal of the facility within 90 days
of the receipt of the written notice. The owner of the facility shall
have 30 days from the receipt of the notice to demonstrate to
the CEO that the facility has not been abandoned. If the owner
fails to show that the facility is in active operation, the owner shall
have 60 days to remove the facility. If the facility is not removed
within this time period, the municipality may remove the facility
at the owner's expense. The owner of the facility shall pay all
site reclamation costs deemed necessary and reasonable to
return the site to its pre-construction condition, including
removal of roads and reestablishment of vegetation. The
Planning Board may require the applicant to post a surety bond
to cover eventual facility removal in case of abandonment.
Page 58|72
6. Appeals
If the Planning Board disapproves an application or grants approval with
conditions that are objectionable to the applicant or to any abutting
landowner or any aggrieved party, who can demonstrate a direct
negative impact, or when it is claimed that the provisions of this section
do not apply, or that the true intent and meaning of the Ordinance has
been misconstrued or wrongfully interpreted, the applicant, an abutting
landowner, or other aggrieved party may appeal the decision to the
Board of Appeals.
Section XI. Definitions
1.Construction of Language
In the interpretation and enforcement of this Ordinance, all words other than
those specifically defined in the Ordinance shall have the meaning implied by
their context in the Ordinance or their ordinarily accepted meaning. Where any
uncertainty arises, the Board of Appeals shall be the final authority.
The present tense includes the future tense, the singular number includes the
plural, and plural numbers include the singular.
The words "shall," "will" and "must" are mandatory; the word "may" is
permissive. The word "lot" includes the word "parcel".
The word "structure" includes the word "building".
The term "municipal officers" means the Unity Board of Selectmen.
2.Definition of Terms
In this Ordinance the following terms shall have the following meanings:
Abutter - the owner of any property with one or more common boundaries, or across
the street or stream from, the property involved in an application or appeal. ---
Access (or accessway) - legal right-of-way connecting a parcel of land with a road.
Access point - junction of a vehicular accessway and the public or private road
accessed.
Accessory Dwelling Unit (ADU) - A self-contained dwelling unit located within, attached
to, or detached from a single-family dwelling unit located on the same parcel of land. An
Accessory Dwelling Unit shall be subordinate to the principal structure or principal
dwelling unit on the lot. An accessory dwelling unit must be a minimum of 190 square feet
Page 59|72
unless the Technical Building Code and Standards Board, pursuant to 10 M.R.S. § 9722,
as may be amended, adopts a different minimum standard; if so, that standard applies.
Accessory structure or use - a use or structure which is incidental and subordinate
to the primary or principal use or structure. Accessory uses, when aggregated shall
not subordinate the principal use of the lot. A deck or similar extension of the principal
structure or a garage attached to the principal structure by a roof or a common wall
is considered part of the principal structure.
Agriculture - the production, keeping or maintenance for sale or lease, of plants
and/or animals, including but not limited to: forages and sod crops; grains and seed
crops; dairy animals and dairy products; poultry and poultry products; livestock; fruits
and vegetables; and ornamental and green house products. Agriculture does not
include forest management and timber harvesting activities.
Aggrieved party - an owner of land whose property is directly or indirectly affected
by the granting or denial of a permit or variance under this Ordinance; a person whose
land abuts land for which a permit or variance has been granted; or any other person
or group of persons who have suffered particularized injury as a result of the granting
or denial of such permit or variance.
Attached - Connected by a shared wall to the principal structure or having physically
connected finished spaces.
| Back land - any lot or parcel of land that does not have frontage on a public or private
road.
Building - same as structure.
Centrally Managed Water System - A water system that provides water for human
consumption through pipes or other constructed conveyances to at least 15 service
connections or serves an average of at least 25 people for at least 60 days a year as
regulated by 10-144 C.M.R. Ch. 231, Rules Relating to Drinking Water. This water
system may be privately owned.
Clearly visible - A feature that an average person passing down a road would notice.
For instance, a small feature on the side of a building that is only visible from one
place on the roadway is not "clearly visible." In almost all cases, the back side of
buildings is not affected; in many other cases (where landscaping or neighboring
buildings shield public view), the sides and even the front of buildings may not be
affected.
Commercial farmland - any piece of land used to grow crops or livestock, in a way
that directly contributes at least $300 per acre in market value.
Pase 60|72
Commercial use - the use of lands, buildings, or structures, other than a "home
occupation" (as defined below), the intent and result of which activity is the production
of income from the buying and selling of goods and/or services, exclusive of rental of
residential buildings and/or dwelling units.
Comprehensive Plan - A document or interrelated documents consistent with 30-A
M.R.S. §4326(1)-(4), including the strategies for an implementation program which are
consistent with the goals and guidelines established pursuant to Title 30-A Chapter 187
Subchapter II.
Density Requirements - The maximum number of dwelling units allowed on a lot, subject
to dimensional requirements.
Designated Growth Area - An area that is designated in a Unity's comprehensive plan
as suitable for orderly residential, commercial, or industrial development, or any
combination of those types of development, and into which most development projected
over ten (10) years is directed. Designated growth areas may also be referred to as
priority development zones or other terms with a similar intent. If a municipality does not
have a comprehensive plan, "designated growth area" means an area served by a public
sewer system that has the capacity for the growth-related project, an area identified in the
latest Federal Decennial Census as a census-designated place or a compact area of an
urban compact municipality as defined by 23 M.R.S. §754.
Dimensional requirements - numerical standards relating to spatial relationships
including but not limited to setback, lot area, shore frontage, driveway separation and
building height.
District - a specified portion of the municipality, delineated on the Unity Land Use Map,
within which certain regulations and requirements or various combinations thereof
apply under the provisions of this Ordinance.
Driveway - a vehicular accessway serving one principal structure or lot. This term
may also collectively include "shared driveways", which serve 2 or 3 principal
structures or lots. They are treated the same for regulatory purposes.
Dwelling - any building or structure or portion thereof designed or used for residential
purposes.
Dwelling Unit - Any part of a structure which, through sale or lease, is intended for human
habitation, including single-family and multifamily housing, condominiums, time-share
units, and apartments.
Existing Dwelling Unit - A residential dwelling unit in existence on a lot at the time of
submission of a permit application to build additional units or ADUs on that lot.
Expansion of a structure - an increase in the floor area or volume of a structure,
including all extensions such as, but not limited to attached decks, garages, porches
and greenhouses.
Expansion of use - the addition of months to a use's operating season; or the use
of more floor area or ground area devoted to a particular use.
High-impact activity- a land use activity that has any of the characteristics outlined
in Section VIII.
Home-based enterprise - any enterprise located on the same parcel as the
residence of the owner of a business with no more than six full-time (or equivalent)
non-resident employees and utilizing no more than 20,000 square feet.
Home occupation - a home-based enterprise in which: a) the business activity is
conducted completely within the dwelling unit or structure accessory thereto (e.g.
home, garage), and b) the principal use of the property remains residential.
Housing - Any part of a structure which, through sale or lease, is intended for human
habitation, including single-family and multi-family housing, condominiums, time-
share units, and apartments.
Impervious surface - one that does not absorb moisture, including but not limited to
; rooftops and paved areas.
Industrial use - the assembling, fabrication, finishing, manufacturing, packaging or
processing of goods, or the extraction of minerals.
Land Use Ordinance - An ordinance or regulation of general application adopted by
the municipal legislative body which controls, directs, or delineates allowable uses of
land and the standards for those uses.
Lot - an area of land in one ownership, or one leasehold, with ascertainable
boundaries established by deed or instrument of record, or a segment of land
ownership defined by lot boundary lines on a land subdivision plan duly approved by
the Planning Board and recorded in the County Registry of Deeds.
Lot area - the area of land enclosed within the boundary lines of a lot, minus land
below the normal high-water line of a water body or upland edge of a wetland and
areas beneath roads serving more than two lots.
Lot width - the distance between the side boundaries of the lot measured at the front
setback line.
Page 62|72
Low-impact activity- a land use activity that is conducted in such a manner that no
noise, odor, vibration, smoke, dust, electrical disturbance, glare, activity at
unreasonable hours, or other nuisance shall be detectable at the property line.
Manufactured housing or mobile home unit - a structure, transportable in one or
two sections, which was constructed in a manufacturing facility and is transported to
a building site and designed to be used as a dwelling when connected to the required
utilities.
Mobile home park - a parcel of land under unified ownership approved by the Town
for the placement of 3 or more manufactured homes.
Multifamily Dwelling - A structure containing three (3) or more dwelling units.
Municipality - A city or a town, excluding all unorganized and deorganized townships,
plantations, and towns that have delegated administration of land use controls to the
Maine Land Use Planning Commission pursuant to 12 M.R.S. § 682(1).
New parking area - any parking area constructed after the effective date of this
Ordinance, or any modification to an existing parking area that will use 500 square
feet or more of land than was previously not utilized for either parking or vehicular
access.
Non-conforming lot- a single lot of record which, at the effective date of adoption or
amendment of this Ordinance, does not meet the area, frontage, or width
requirements of the district in which it is located.
Non-conforming structure - a structure which does not meet any one or more of
the following dimensional requirements; setback, height, or lot coverage, but which
is allowed solely because it was in lawful existence at the time this Ordinance or
subsequent amendments took effect.
Non-conforming use - use of buildings, structures, premises, land or parts thereof
which is not permitted in the district in which it is situated, but which is allowed to
remain solely because it was in lawful existence at the time this Ordinance or
subsequent amendments took effect.
Parcel - same as lot
Parking area - any off-street area used for the parking of vehicles that is not a driveway.
The principal function of a parking area is to park vehicles, whereas the principal function
of a driveway is to provide a vehicular accessway. Driveways are often used to park
vehicles, but rarely do they allow several vehicles to arrive and depart freely, without the
need to move other vehicles. (Note: See also definition of "new parking areas.'?
Page 63|72
Person - an individual, corporation, governmental agency, municipality, trust, estate,
partnership, association, two or more individuals having a joint or common interest, or
other legal entity.
Potable - Safe for drinking as defined by the U.S. Environmental Protection Agency's
(EPA) Drinking Water Standards and Health Advisories Table and Maine's interim
drinking water standards for six different perfluoroalkyl and polyfluoroalkyl substances
(PFAS), Resolve 2021 Chapter 82, Resolve, To Protect Consumers of Public Drinking
Water by Establishing Maximum Contaminant Level for Certain Substances and
Contaminants.
Principal structure - A structure in which the main or primary use is conducted. For
example, houses and office buildings are usually principal structures, while garages,
barns and sheds are accessory structures. A Principal Structure is also known as a
Primary Structure.
Principal use - any use which is not incidental or accessory.
Private road or roadway - a privately-owned road, neither open to nor maintained by the
Town or general public.
Productive farmland - land that has historically been used for commercial crop production,
or that meets the definition of either prime, unique or significant farmland soils as defined by
the Soil Conservation Service.
Pastureland varies widely in nature and will be evaluated on a case-by-case basis as to its
viable agricultural value. Land supporting orchards and Christmas trees is considered
productive farmland, while that supporting other trees is not, unless it meets one of the soil
definitions outlined above.
Public road or roadway - any roadway which is owned, leased, or otherwise operated by
a governmental body or public entity.
Residential Use - A use permitted in an area by a municipal legislative body to be used
for human habitation. Residential uses may include single-family, duplex, triplex,
quadplex, and other multifamily housing; condominiums; time-share units; and
apartments. For purposes of this Ordinance, the following uses are not included under
this definition: dormitories, congregate living facilities, campgrounds, campsites, hotels,
motels, beds and breakfasts, or other types of lodging accommodations, and transient
housing or short-term rentals.
Restrictive Covenant - A provision in a deed, or other covenant conveying real property,
restricting the use of the land.
Right-of-way- all public or private roads and streets, state and federal highways, private
ways (now called public easements), and public land reservations for the purpose of public
access, including utility rights-of-way.
Pause 64|72
Road - any public or private way designed for vehicular access, other than driveways,
shared driveways, farm roads, trails or logging roads. The term "road" includes the normal
meaning conveyed by synonymous words including street, avenue, highway, and way.
Seasonal use - one that takes place no more than seven months of the year.
Setback Requirements - The minimum horizontal distance from a lot line, shoreline, or
road to the nearest part of a structure, or other regulated object or area as defined in this
Ordinance.
Shore frontage - the length of a lot bordering on a water body measured in a straight line
between the intersections of the lot lines with the shoreline at normal high-water elevation.
Shared driveway - a vehicular accessway serving two or three dwelling units, lots or
structures.
Sign - any structure, logo, device or representation which is designed or used to advertise
orcall attention to anything, person, business, activity or place and is visible from any public
way. In does not include the flag, pennant or insignia of any nation, state or town. A2-sided
sign is considered one sign for purposes ofthis Ordinance. (Note: See also definition of
"temporary sign")
Single-family Dwelling Unit - A structure containing one (1) dwelling unit.
Structure - Anything temporarily or permanently located, built, constructed or erected for
the support, shelter or enclosure of persons, animals, goods or property of any kind or
anything constructed or erected on or in the ground as defined in 38 M.R.S. § 436-A(12).
The term includes structures temporarily or permanently located, such as decks, patios,
steps, landings, and satellite dishes. Structure does not include fences; poles and wiring
and other aerial equipment normally associated with service drops, including guy wires
and guy anchors; subsurface waste water disposal systems as defined in 30-A M.R.S. §
4201(5); geothermal heat exchange wells as defined in 32 M.R.S. § 4700-E(3-C); or wells
or water wells as defined in 32 M.R.S. § 4700-E(8).
Subdivision - the division of a tract or parcel of land into 3 or more lots within any
5-year period that begins on or after September 23, 1971. This definition applies
whether the division is accomplished by sale, lease, development, buildings or
otherwise. The term "subdivision" also includes the division of a new structure or
structures on a tract or parcel of land into 3 or more dwelling units within a 5-year
period, the construction or placement of 3 or more dwelling units on a single tract or
parcel of land and the division of an existing structure or structures previously used
for commercial or industrial use into 3 or more dwelling units within a 5-year period.
Lots of 40 acres or greater in size are considered lots within this definition and
come under municipal review.
Pave 65|72
Substantial start - completion of 20 percent of a permitted structure or use measured
as a percentage of estimated total cost.
Subsurface sewage disposal system - a collection of treatment tank(s), disposal
area(s), holding tank(s) and pond(s), surface spray system(s), cesspool(s), well(s),
surface ditch(es), alternative toilet(s), or other devices and associated piping
designed to function as a unit for the purpose of disposing of wastes or wastewater
on or beneath the surface of the earth. The term shall not include any wastewater
discharge system licensed under 38 MR.SA Section 414, any surface wastewater
disposal system licensed under 38 MR.SA Section 413 Subsection 1-A, or any public
sewer. The term shall not include a wastewater disposal system designed to treat
wastewater which is in whole or in part hazardous waste as defined in 38 MR.SA
Chapter 13, subchapter 1.
Temporary sign - a non-illuminated sign displayed for 15 days or less in any 30 day
period.
Variance - a relaxation of the terms of this Ordinance where such relaxation will not
be contrary to the public interest where, owing to conditions peculiar to the property,
and not the result of the actions of the applicants, and where a literal enforcement of
the Ordinance would result in undue hardship.
Vegetation - all live trees, shrubs, ground cover, and other plants.
Paxze 66|72
APPENDIX |
Development Review Application Content
Requirements
A. Requirements for bothTYPE 1 and TYPE 2 Developments
All development review applications shall contain:
1) A signed copy of the application cover sheet available from the Town Clerk
provided as the cover page to the written report.
2) Nine copies of a written report containing sufficient detail so that a reviewer can
gain a comprehensive understanding of the proposed development. This means that
the report shall include copies of the most important maps and drawings.
3) At least two full-size copies of all maps and drawings.
Each development review application shall contain the following information, less those
specific items waived by the Board as outlined in Section VIII-4:
1) General Information
a) the name of the proposed development, if any;
b) name and address of owner(s) of record, and of applicant if different;
Cc) ifthe applicant is not an owner of the property, written certification signed
by the owner(s) that the applicant is their duly authorized agent;
d) names and addresses of all property owners within 500 feet of the edge of
the property line;
e€) number of acres contained in the parcel:
f) boundaries of all contiguous property under the control of the owner or
applicant regardless of whether all or part is being developed at this time;
g) the tax map and lot number of the parcel or parcels;
h) a copy of the deed to the property, option to purchase the property or other
documentation to demonstrate right, title or interest in the property on the
part of the owner;
i) the name, registration number and seal of the land surveyor, architect, engineer
| and/or similar professional who prepared the plan;
Page 67|72
2) Existing Conditions
a) district classification(s) of the property and the location of district
boundaries ifthe property is located in 2 or more land-use districts or abuts
a different district;
b) the bearings and distances of all property lines of the property to be
developed and thesource of this information;
c) location and size of any existing sewer and water mains, culverts and drains
on the property to be developed, and of any that will serve the development
from abutting streets or land (If any neighboring land currently relies on the
property for drainage, this shall be clearly noted.);
d) location, names, and present widths of existing streets and rights-of-way within
or adjacent to the proposed development;
e) the location, dimensions and ground floor elevations of all existing buildings
on the site;
f) the location and dimensions of existing driveways, streets, parking and loading
areas and walkways on the site;
g) location of intersecting roads or driveways within 200 feet of the site;
h) the location of open drainage courses, wetlands, stands of trees, and other
important natural features, with a description of such features to be
retained;
i) the location of areas within or adjacent to the development that contain high
value wildlife habitat as mapped by the Maine Department of Inland Fisheries
and Wildlife and/or contained in the Unity Comprehensive Plan;
j) general boundaries and description of vegetative cover, with trees of over 18
11 in diameter at breast height indicated if within 100' of the proposed
development activity;
k) the direction of existing surface water drainage across the site;
1) location of flood hazard area, if applicable;
m) the location and approximate depth of any wells on the property and within 500
feet of each property line that may be used for domestic water supply;
n) the location and dimensions of existing signs;
Pave 68! 72
0) location and dimensions of any existing easements and copies of existing
covenants or deed restrictions; and
Pp) location, dimensions and description of any portion of the land including in or
abutting the proposed development that is currently used for commercial
agriculture, including the name of the farmer utilizing the land.
3) Proposed Development Activity
a) the location of all building setbacks and buffers required by this Ordinance;
b) the location, dimensions, and ground floor elevations (i.e., the base height of
the first floor above grade) of all proposed buildings on the site;
c) elevation drawings of all proposed buildings;
d) the location and dimensions of proposed driveways, parking and loading areas,
and walkways;
e) distance from neighboring driveways if accessing public road:
f) the location and dimensions of all provisions for water supply and wastewater
disposal, including location of snow storage and removal, if applicable;
g) the direction of proposed surface water drainage across the site;
h) location and dimensions of proposed signs;
i) location and type of exterior lighting;
j) proposed landscaping and buffering, and indication of where clearing of
existing vegetation will take place;
k) location and description of any open space and/or public dedication to bemade,
including ownership of and plans for ongoing maintenance of the property.
1) copies of applicable State approvals and permits, provided however, that the
Board may approve development plans subject to the issuance of specified
State approvals and permits where it determines that it is not feasible for the
applicant to obtain them at the time of development review.
m) a schedule of construction, including anticipated beginning and completion
dates.
Page 69|72
B. Additional Requirements for TYPE 2 Developments
Each TYPE 2 development review application shall contain the following information, less
those specific items waived by the Board as outlined in Section VIII-4:
1) The following pre-existing conditions:
a) the topography of the site at an appropriate contour interval (2 foot to IO foot)
depending on the nature of the use and character of the site;
b) major natural features of the site including wetlands, streams, ponds, flood
plains, groundwater aquifers, significant wildlife habitats or other important
natural features;
c) existing restrictions or easements on the site;
d) the location and size of existing utilities or improvements servicing the site;
€) general soils information identifying prime farmland soils and soils with poor
septic suitability; and
f) existing or previous agricultural usage of the property and abutting properties.
2) Proposed topography of the site at an appropriate contour interval.
3) A storm water drainage and erosion control program showing:
a) the existing and proposed method of handling storm water run-offs;
b) the direction of flow of the run-off through the use of arrows;
c) the location, elevation, and size of all catch basins, dry wells, drainage ditches,
swales, retention basins, and storm sewers;
d) engineering calculations used to determine drainage requirements based upon
the 25-year 24-hour storm frequency, if the project will significantly alter the
existing drainage pattern due to such factors as the amount of new impervious
surfaces (such as paving and building area) being proposed; and
e) methods of controlling erosion and sedimentation during and after construction.
4) If the development is a high user of water (i.e., over 2000 gallons per day), or is located
on a sensitive site, or is otherwise felt to pose a potential source of disruption to
existing water supply and/or flowage, a groundwater impact analysis prepared by a
qualified professional engineer or geologist, certified to practice in the State of Maine.
. Impact on existing wells within 500 radial feet of the proposed new water usage shall
Pave 70|72
be evaluated as outlined in Section IX Aquifer Protection Standards.
5) A utility plan showing, in addition to provisions for water supply and wastewater
disposal, the location and nature of electrical, telephone, and any other utility services
to be installed on the site.
6) Aplanting schedule keyed to the site plan and indicating the general varieties and sizes
of trees, shrubs, and other plants to be planted on the site.
7) An estimate of the amount and type of vehicular traffic, at peak hour and average
daily levels.
8) An analysis of the anticipated need for parking created by the development when
fully occupied.
9) If involving over 40 parking spaces or estimating over 400 vehicle trips per day, a
traffic impact analysis demonstrating the impact of the proposed project on the
capacity, level of service and safety of adjacent streets, together with any
recommended street improvements.
10) The location, width, typical cross-section, grades and profiles of all proposed
streets and sidewalks.
11) Construction drawings for streets, sanitary sewers, water and storm drainage
systems, designed and prepared by a professional engineer registered in the
State of Maine.
12) The location of any pedestrian ways, lots, easements, open spaces and other
areas to be reserved for or dedicated to public use and/or ownership. For any
proposed easement, the developer shall submit the proposed easement language
with a signed statement certifying that the easement will be executed upon
approval of the development. In the case of any streets or other ways dedicated
to public ownership, the developer shall submit a signed statement that he/she
will maintain such streets or ways year-round until such time as the Town may
accept them as public ways.
13) A plan to provide adequate water to the site for fire protection, using either
existing Sources or new sources.
14) A copy of such covenants or deed restrictions, if any; as are intended to cover all
or part of the tract. Such covenants or deed restrictions shall be referenced on the
plan.
15) Written offers of dedication or conveyance to the municipality, in a form
satisfactory to the Town Attorney, of all land included in the streets, highways,
. easements, parks, or other open space dedicated for public use, and copies of
Page 71|72
agreements or other documents showing the manner in which open spaces, title
to which is reserved by the developer, are to be maintained.
16) If the development is a condominium with commonly held property, evidence that
all requirements relative to establishment of a homeowners' association or
condominium owners' association have been met. If the development is a
clustered development, evidence shall be presented that all other requirements of
this Ordinance pertaining to clustered development have been met. The
submission shall include copies of the by-laws of any homeowners' or
condominium association charged with maintaining common spaces and lands.
Homeowners' associations or condominium documents shall clearly state that the
association or condominium shall properly maintain private roadways serving the
development after the developer has legally relinquished that responsibility and
until such time as the Town may accept them as public ways.
17) Cost of the proposed development and evidence of financial capacity to complete
it.
C. Additional Submittal Requirements for Telecommunications Towers and
Facilities
1) A copy of the FCC license for the facility or a signed statement from the owner or
operator attesting that the facility complies with FCC regulations.
2) A site plan prepared by a qualified Professional Engineer registered in Maine
indicating the location, type, and height of the facility proposed to be built or
expanded, antenna capacity, on-site and abutting off-site land uses, means of
access, setbacks, and all applicable American National Standards Institute (ANS!)
technical and structural codes.
3) Certification that the proposed facility will comply with all FCC radio emission
standards.
4) A scenic assessment including elevation drawings of the proposed facility anda
landscaping plan.
5) A written description of how the proposed facility fits into the applicant's
telecommunications network.
6) Evidence demonstrating that no existing site or structure can accommodate the
applicant's proposed facility, due to insufficient location, height, structural
capacity, access, or affordability.
7) Asigned statement that the owner of the facility and his/her successors or assigns
agree to the standards and requirements outlined in Section X of this Ordinance
concerning co-location.
Page 72|72