Town of Waterford
Town of Waterford, Maine
SHORELAND ZONING ORDINANCE
Adopted: March, 7, 1992
Amended: March 1, 2003
Amended: March 28, 2005
Amended: March 3, 2007
Amended: March 6, 2010
Amended: March 3, 2012
Amended: March 5, 2016
Amended: March 4, 2023
Town of Waterford
Town of Waterford
TABLE OF CONTENTS
NOTE: TABLE OF CONTENTS NOT CURRENT
Section 1.
Purposes ............................................................................................................................................ 1
Section 2.
Authority ........................................................................................................................................... 1
Section 3.
Applicability ..................................................................................................................................... 1
Section 4.
Effective Date of Ordinance and Ordinance Amendments ............................................................... 1
Section 5.
Availability ....................................................................................................................................... 2
Section 6.
Severability ....................................................................................................................................... 2
Section 7.
Conflicts with Other Ordinances ....................................................................................................... 2
Section 8.
Amendments ..................................................................................................................................... 2
Section 9.
Districts and Zoning Map ................................................................................................................. 2
A.
Official Shoreland Zoning Map ........................................................................................................ 2
B.
Scale of Map ..................................................................................................................................... 2
C.
Certification of Official Shoreland Zoning Map ............................................................................... 3
D.
Changes to the Official Shoreland Zoning Map ................................................................................ 3
Section 10.
District Boundaries ........................................................................................................................... 3
Section 11.
Land Use Requirements .................................................................................................................... 3
Section 12.
Non-conformance.............................................................................................................................. 3
A.
Purpose .............................................................................................................................................. 3
B.
General .............................................................................................................................................. 3
C.
Non-conforming Structures ............................................................................................................... 3
D.
Non-conforming Uses ....................................................................................................................... 7
E.
Non-conforming Lots ........................................................................................................................ 7
Section 13.
Establishment of Districts ................................................................................................................. 8
A.
Resource Protection District ............................................................................................................. 8
B.
Rural Shoreland District .................................................................................................................... 9
C.
Stream Protection District ................................................................................................................. 9
Section 14.
Table of Land Uses ........................................................................................................................... 9
Section 15.
Land Use Standards ........................................................................................................................ 11
A.
Minimum Lot Standards ................................................................................................................. 11
B.
Principal and Accessory Structures ................................................................................................. 11
C.
Piers, Docks, Wharfs, Bridges and Other Structures and Uses Extending Over or Below the
Normal High-Water Line of a Water Body or Within a Wetland, and Shoreline Stabilization ...... 14
D.
Campground .................................................................................................................................... 15
E.
Individual Private Campsites .......................................................................................................... 15
F.
Commercial and Industrial Uses ..................................................................................................... 16
G.
Parking Areas .................................................................................................................................. 16
H.
Roads and Driveways ...................................................................................................................... 16
I.
Signs ................................................................................................................................................ 19
J.
Storm Water Runoff ........................................................................................................................ 19
K.
Septic Waste Disposal ..................................................................................................................... 19
L.
Essential Services ............................................................................................................................ 19
M.
Mineral Exploration and Extraction ................................................................................................ 20
N.
Agriculture ...................................................................................................................................... 21
O.
Reserved .......................................................................................................................................... 21
O-1.
Timber Harvesting - Statewide Standards ...................................................................................... 21
P.
Clearing or Removal of Vegetation for Activities Other Than Timber Harvesting ........................ 29
Q.
Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal. ................................................... 31
R.
Exemptions to Clearing and Vegetation Removal Requirements ................................................... 32
S.
Revegetation Requirements. ........................................................................................................... 33
T.
Erosion and Sedimentation Control ................................................................................................ 35
U.
Soils ................................................................................................................................................ 35
V.
Water Quality .................................................................................................................................. 36
W.
Phosphorous Loading Rates ............................................................................................................ 36
X.
Archaeological Sites ....................................................................................................................... 37
Town of Waterford
Y.
Recreational Trails .......................................................................................................................... 37
Section 16.
Administration ................................................................................................................................ 38
A.
Administering Bodies and Agent .................................................................................................... 38
B.
Permit Required .............................................................................................................................. 38
C.
Permit Application .......................................................................................................................... 38
D.
Procedure for Administering Permits .............................................................................................. 39
E.
Independent Review and Advice .................................................................................................... 40
F.
Expiration of Permit ........................................................................................................................ 40
G.
Financial Guarantee ........................................................................................................................ 41
H.
Installation of Public Utility Service ............................................................................................... 41
I.
Special Exceptions .......................................................................................................................... 41
J.
Appeals ........................................................................................................................................... 42
Section 17.
Definitions ............................................................................................................................. 47
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
1
Shoreland Zoning Ordinance
Town of Waterford
Section 1.
Purposes
The purposes of this Ordinance are to further the maintenance of safe and healthful conditions; to prevent and
control water pollution; to protect fish spawning grounds, aquatic life, bird and other wildlife habitat; to
protect buildings and lands from flooding and accelerated erosion; to protect freshwater wetlands; to control
building sites, placement of structures and land uses; to conserve shore cover, and visual as well as actual
points of access to inland waters; to conserve natural beauty and open space; and to anticipate and respond to
the impacts of development in shoreland areas.
Section 2.
Authority
This Ordinance has been prepared in accordance with the provisions of Title 38 Sections 435-449 of the
Maine Revised Statutes Annotated (M.R.S.A.).
Section 3.
Applicability
This Ordinance applies to all land areas within 250 feet, horizontal distance, of the normal high-water line of
any great pond or river; within 250 feet, horizontal distance, of the upland edge of a freshwater wetland; and
within 75 feet, horizontal distance, of the normal high-water line of a stream. This ordinance also applies to
any structure built on, over or abutting a dock, wharf or pier, or other structures extending below the normal
high-water line of a water body or within a wetland.
All of the requirements applicable to the great ponds shall also apply to the following rivers and streams:
Crooked River, Bear River, City Brook, and the outlet of McWain Pond to the Crooked River. All of the
requirements applicable to stream protection district shall also apply to the northerly outlet of Little Moose
Pond to its junction with Mutiny Brook. [Amended March 7, 1998]
Section 4.
Effective Date of Ordinance and Ordinance Amendments
This Ordinance, which was amended by the municipal legislative body on March 7, 1992 and as amended
through March 3, 2012 shall not be effective unless approved by the Commissioner of the Department of
Environmental Protection. A certified copy of the Ordinance or Ordinance amendment, attested and signed by
the Town Clerk, shall be forwarded to the Commissioner for approval. If the Commissioner fails to act on
this Ordinance or Ordinance amendment within forty-five (45) days of its receipt of the Ordinance or
Ordinance amendment, it shall be automatically approved.
Any application for a permit submitted to the Town within the forty-five (45) day period shall be governed by
the terms of this Ordinance or Ordinance amendment if the Ordinance or Ordinance amendment is approved
by the Commissioner.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
2
Section 5.
Availability
A certified copy of this Ordinance shall be filed with the Town Clerk and shall be accessible to any member
of the public. Copies shall be made available to the public at reasonable cost at the expense of the person
making the request. Notice of availability of this Ordinance shall be posted.
Section 6.
Severability
Should any section of provision of this Ordinance be declared by the courts to be invalid, such decision shall
not invalidate any other section or provision of the Ordinance.
Section 7.
Conflicts with Other Ordinances
Whenever a provision of this Ordinance conflicts with or is inconsistent with another provision of this
Ordinance or of any other ordinance, regulation or statute administrated by the municipality, the more
restrictive provision shall control.
Section 8.
Amendments
A. This Ordinance may be amended by majority vote of the legislative body (Town Meeting).
Amendments may be initiated by majority vote of the Planning Board or by request of the
Board of Selectmen to the Planning Board or on petition of 10% of the votes cast in the last
gubernatorial election in the Town. The Planning Board shall conduct a public hearing on any
proposed amendment.
B Copies of amendments, attested and signed by the Town Clerk, shall be submitted to the
Commissioner of the Department of Environmental Protection following adoption by the town
legislative body and shall not be effective unless approved by the Commissioner. If the
Commissioner fails to act on any amendment within forty-five (45) days receipt of the
amendment, the amendment is automatically approved. Any application for a permit submitted
to the Town within the forty-five (45) day period shall be governed by the terms of the
amendment, if such amendment is approved by the Commissioner.
Section 9.
Districts and Zoning Map
A.
Official Shoreland Zoning Map
The areas to which this Ordinance is applicable are hereby divided into the following districts as
shown on the Official Shoreland Zoning Map(s) which are made a part of this Ordinance:
1.
Resource Protection District
2.
Rural Shoreland District
3.
Stream Protection District
B.
Scale of Map
The Official Shoreland Zoning Map shall be drawn at a scale of not less than: 1 inch = 2,000
feet. District boundaries shall be clearly delineated and a legend indicating the symbols for each
district shall be placed on the map.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
3
C.
Certification of Official Shoreland Zoning Map
The Official Shoreland Zoning Map shall be certified by the attested signature of the Town Clerk
and shall be located in the Town Office.
D.
Changes to the Official Shoreland Zoning Map
If amendments, in accordance with Section 8, are made in the district boundaries or other matter
portrayed on the Official Shoreland Zoning Map such changes shall be made on the Official
Shoreland Zoning Map within thirty (30) days after the amendment has been approved by the
Commissioner of the Department of Environmental Protection.
Section 10.
District Boundaries
The District Boundaries are as shown on the adopted shoreland zoning map and as defined in this Ordinance.
Although wetlands are shown on the Official Shoreland Zoning Map, the actual boundaries shall be
determined by field investigation. Where uncertainty exists as to the exact location of district boundary lines,
they shall be determined by field verification.
Section 11.
Land Use Requirements
Except as hereinafter specified, no building, structure or land shall hereafter be used or occupied, and no
building or structure or part thereof shall hereafter be erected, constructed, expanded, moved, or altered and
no new lot shall be created except in conformity with all of the regulations herein specified for the district in
which it is located, unless a variance is granted.
Section 12.
Non-conformance
A.
Purpose
It is the intent of this Ordinance to promote land-use conformities, except that non-conforming
conditions that existed before the effective date of this Ordinance or amendments thereto shall be
allowed to continue, subject to the requirements set forth in this section. Except as otherwise
provided in this Ordinance, a non-conforming condition shall not be permitted to become more
non-conforming.
B.
General
1.
Transfer of Ownership: Non-conforming structures, lots, and uses may be
transferred, and the new owner may continue the non-conforming use or continue to use
the non-conforming structure or lot, subject to the provisions of this Ordinance.
2.
Repair and Maintenance: This Ordinance allows, without a permit, the normal
upkeep and maintenance of non-conforming uses and structures including repairs or
renovations that do not involve expansion of the non-conforming use or structure, and such
other changes in a non-conforming use or structure as federal, state, or local building and
safety codes may require.
C.
Non-conforming Structures
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
4
1.
Expansions: All new principal and accessory structures, excluding functionally
water-dependent uses, must meet the water body, tributary stream, or wetland setback
requirements contained in Section 15.B.1. A non-conforming structure may be added to
or expanded after obtaining a permit from the same permitting authority as that for a new
structure if such addition or expansion does not increase the non-conforming of the
structure and is in accordance with subparagraphs a and b below.
a.
Expansion of any portion of a structure within 25 feet of the normal high-
water line of a water body, tributary stream, or upland edge of a wetland is
prohibited, even if the expansion will not increase nonconformity with the water
body, tributary stream or wetland setback requirement. Expansion of an accessory
structure that is located closer to the normal high-water line of a water body,
tributary stream, or upland edge of a wetland than the principal structure is
prohibited, even if the expansion will not increase nonconformity with the water
body, tributary stream, or wetland setback requirement.
Notwithstanding paragraph a, above, if a legally existing nonconforming principal
structure is entirely located less than 25 feet from the normal high-water line of a
water body, tributary stream, or upland edge of a wetland, that structure may be
expanded as follows, as long as all other applicable municipal land use standards are
met and the expansion is not prohibited by Section 12.C.1.
(i)
The maximum total footprint for the principal structure may not be
expanded to a size greater than 800 square feet or 30% larger than the
footprint that existed on January 1, 1989, whichever is greater. The
maximum height of the principal structure may not
be made greater
than 15 feet or the height of the existing structure, whichever is greater.
c.
All other legally existing nonconforming principal and accessory structures that do
not meet the water body, tributary stream, or wetland setback requirements may be
expanded or altered as follows, as long as other applicable municipal land use
standards are met and the expansion is not prohibited by Section 12.C.1 or Section
12.C.1.a, above.
(i)
For structures located less than 75 feet from the normal high-water line of a
water body, tributary stream, or upland edge of a wetland, the maximum
combined total footprint for all structures may not be expanded to a size
greater than 1,000 square feet or 30% larger than the footprint that existed
on January 1, 1989, whichever is greater. The maximum height of any
structure may not be made greater than 20 feet or the height of the existing
structure, whichever is greater.
(ii)
For structures located less than 100 feet from the normal high-water line of
a great pond or a river flowing to a great pond, the maximum combined
total footprint for all structures may not be expanded to a size greater than
1,500 square feet or 30% larger than the footprint that existed on January 1,
1989, whichever is greater. The maximum height of any structure may not
be made greater than 25 feet or the height of the existing structure,
whichever is greater. Any portion of those structures located less than 75
feet from the normal high-water line of a water body,
tributary stream, or
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
5
upland edge of a wetland must meet the footprint and height limits in
Section 12.C.1.b.(i) and Section 12.C.1.c.(i), above.
(iii)
In addition to the limitations in subparagraphs (i) and (ii), for structures that
are legally nonconforming due to their location within the Resource
Protection District when located at less than 250 feet from the normal high-
water line of a water body or the upland edge of a wetland, the maximum
combined total footprint for all structures may not be expanded to a size
greater than 1,500 square feet or 30% larger than the footprint that existed at
the time the Resource Protection District was established on the lot,
whichever is greater. The maximum height of any structure may not be
made greater than 25 feet or the height of the existing structure, whichever
is greater, except that any portion of those structures located less than 75
feet from the normal high-water line of a water body, tributary stream, or
upland edge of a wetland must meet the footprint and height limits in
Section 12.C.1.b.(i) and Section 12.C.1.c.(i), above.
d.
An approved plan for expansion of a nonconforming structure must be recorded by
the applicant with the registry of deeds, within 90 days of approval. The recorded
plan must show the existing and proposed
footprint of the non-conforming
structure, the existing and proposed structure height, the footprint of any other
structures on the parcel, the shoreland zone boundary and evidence of approval by
the municipal review authority.
e.
No structure which is less than the required setback from the normal high-water line
of a water body, tributary stream, or upland edge of a wetland shall be expanded
toward the water body, tributary stream, or wetland.
2.
Foundations. Whenever a new, enlarged, or replacement foundation is constructed under a non-
conforming structure, the structure and new foundation are must be placed such that the
setback requirement is met to the greatest practical extent as determined by the Planning
Board, basing its decision on the criteria specified in Section12.C.3, Relocation, below.
3.
Relocation: A non-conforming structure may be relocated within the boundaries of the parcel
on which the structure is located provided that the site of relocation conforms to all setback
requirements to the greatest practical extent as determined by the Planning Board, and
provided that the applicant demonstrates that the present subsurface sewage disposal-system
meets the requirements of State law and the State of Maine Subsurface Wastewater Disposal
Rules (Rules), or that a new system can be installed in compliance with the law and said Rules.
In no case shall a structure be relocated in a manner that causes the structure to be more non-
conforming.
In determining whether the building relocation meets the setback to the greatest practical
extent, the Planning Board shall consider the size of the lot, the slope of the land, the potential
for soil erosion, the location of other structures on the property and on adjacent properties, the
location of the septic system and other on-site soils suitable for septic systems, and the type
and amount of vegetation to be removed to accomplish the relocation. When it is necessary to
remove vegetation within the water or wetland setback area in order to relocate a structure, the
Planning Board shall require replanting of native vegetation to compensate for the destroyed
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
6
vegetation in accordance with Section 15.S. In addition, the area from which the relocated
structure was removed must be replanted with vegetation. Replanting shall be required as
follows:
a.
Trees removed in order to relocate a structure must be replanted with at least one
native tree, three (3) feet in height, for every tree removed. If more than five trees
are planted, no one species of tree shall make up more than 50% of the number of
trees planted. Replaced trees must be planted no further from the water or wetland
than the trees that were removed.
Other woody and herbaceous vegetation, and ground cover, that are removed or
destroyed in order to relocate a structure must be re-established. An area at least the
same size as the area where vegetation and/or ground cover was disturbed, damaged,
or removed must be reestablished within the setback area. The vegetation and/or
ground cover must consist of similar native vegetation and/or ground cover that was
disturbed, destroyed or removed.
b.
Where feasible, when a structure is relocated on a parcel the original location of the
structure shall be replanted with vegetation which may consist of grasses, shrubs,
trees, or a combination thereof.
4.
Reconstruction or Replacement: Any non-conforming structure which is located less than the
required setback from a water body, tributary stream, or upland edge of a wetland and which is
removed, or damaged or destroyed, regardless of the cause, by more than 50% of the market
value of the structure before such damage, destruction or removal, may be reconstructed or
replaced provided that a permit is obtained within eighteen (18) months, of the date of said
damage, destruction, or removal, and provided that such reconstruction or replacement is in
compliance with the water body, tributary stream or wetland setback requirement to the
greatest practical extent as determined by the Planning Board in accordance with the purposes
of this Ordinance. In no case shall a structure be reconstructed or replaced so as to increase its
non-conformity. If the reconstructed or replacement structure is less than the required setback
it shall not be any larger than the original structure, except as allowed pursuant to Section
12.C.1 above, as determined by the non-conforming footprint of the reconstructed or replaced
structure at its new location. If the total footprint of the original structure can be relocated or
reconstructed beyond the required setback area, no portion of the relocated or reconstructed
structure shall be replaced or constructed at less than the setback requirement for a new
structure. When it is necessary to remove vegetation in order to replace or reconstruct a
structure, vegetation shall be replanted in accordance with Section 12.C.3 above.
Any non-conforming structure which is located less than the required setback from a water
body, tributary stream, or wetland and which is removed by 50% or less of the market
value, or damaged or destroyed by 50% or less of the market value of the structure,
excluding normal maintenance and repair, may be reconstructed in place if a permit is
obtained, from the code enforcement officer within one year of such damage, destruction
or removal.
In determining whether the building reconstruction or replacement meets the water setback
to the greatest practical extent the Planning Board shall consider in addition to the criteria
in Section 12.C.3 above, the physical condition and type of foundation present, if any.
5.
Change of Use of a Non-conforming Structure
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
7
The use of a non-conforming structure may not be changed to another use unless the
Planning Board, after receiving a written application, determines that the new use will
have no greater adverse impact on the water body or wetland, or on the subject or adjacent
properties and resources than the existing use.
In determining that no greater adverse impact will occur, the Planning Board shall require
written documentation from the applicant, regarding the probable effects on public health
and safety, erosion and sedimentation, water quality, fish and wildlife habitat, vegetative
cover, visual and actual points of public access to waters, natural beauty, flood plain
management, archaeological and historic resources, and other functionally water-
dependent uses.
D.
Non-conforming Uses
1.
Expansions: Expansions of non-conforming uses are prohibited, except that non-
conforming residential uses may, after obtaining a permit from the Planning Board, be
expanded within existing residential structures or within expansions of such structures as
permitted in section 12.C.1 above.
2.
Resumption Prohibited: A lot, building or structure in or on which a non-conforming use
is discontinued for a period exceeding five years, or which is superseded by a conforming
use, may not again be devoted to a non-conforming use except that the Planning Board
may, for good cause shown by the applicant, grant up to a one-year extension to that time
period. This provision shall not apply to the resumption of use of a residential structure
provided that the structure has been used or maintained for residential purposes during the
preceding five (5) year period.
3.
Change of Use: An existing non-conforming use may be changed to another non-
conforming use provided that the proposed use has no greater adverse impact on the
subject and adjacent properties and resources than the former use, as determined by the
Planning Board. The determination of no greater adverse impact shall be made according
to criteria listed in Section 12.C.5 above.
E.
Non-conforming Lots
1.
Non-conforming Lots: A non-conforming lot of record as of the effective date of this
Ordinance or amendment thereto may be built upon, without the need for a variance,
provided that such lot is in separate ownership and not contiguous with any other lot in the
same ownership, and that all provisions of this Ordinance except lot area, lot width and
shore frontage can be met. Variances relating to setback or other requirements not
involving lot area, lot width or shore frontage shall be obtained by action of the Board of
Appeals.
2.
Contiguous Built Lots: If two or more contiguous lots or parcels are in a single or joint
ownership of record at the time of adoption of this Ordinance, if all or part of the lots do
not meet the dimensional requirements of this Ordinance, and if a principal use or structure
exists on each lot, the non-conforming lots may be conveyed separately or together,
provided that the State Minimum Lot Size Law and State of Maine Subsurface Wastewater
Disposal Rules are complied with.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
8
If two or more principal uses or structures existed on a single lot of record on the effective
date of this Ordinance, each may be sold on a separate lot provided that the above
referenced law and rules are complied with. When such lots are divided, each lot thus
created must be as conforming as possible to the dimensional requirements of this
Ordinance.
3.
Contiguous Lots - Vacant or Partially Built: If two or more contiguous lots or parcels are
in single or joint ownership of record at the time of or since adoption or amendment of this
Ordinance, if any of these lots do not individually meet the dimensional requirements of
this Ordinance or subsequent amendments, and if one or more of the lots are vacant or
contain no principal structure the lots shall be combined to the extent necessary to meet the
dimensional requirements.
Section 13.
Establishment of Districts
A.
Resource Protection District
The Resource Protection District includes areas in which development would adversely affect
water quality, productive habitat, biological ecosystems, or scenic and natural values. This
district shall include the following areas when they occur within the limits of the shoreland zone,
exclusive of the Stream Protection District, except those areas which are currently developed.
1.
Areas within 250 feet, horizontal distance, of the upland edge of freshwater wetlands and
wetlands associated with great ponds and rivers, which are rated "moderate" or "high"
value waterfowl and wading bird habitat, including nesting and feeding areas, by the
Maine Department of Inland Fisheries and Wildlife (MDIF&W) that are depicted on a
Geographic Information System (GIS) data layer maintained by either MDIF&W or the
Department as of December 31, 2008. For the purposes of this paragraph "wetlands
associated with great ponds and rivers" shall mean areas characterized by non-forested
wetland vegetation and hydric soils that are contiguous with a great pond or river, and have
a surface elevation at or below the water level of the great pond or river during the period
of normal high water. "Wetlands associated with great ponds or rivers" are considered to
be part of that great pond or river.
2.
Flood plains along rivers and flood plains along artificially formed great ponds along
rivers, defined by the 100-year flood plain as designated on the Federal Emergency
Management Agency=s (FEMA) Flood Insurance Rate Maps or flood Hazard Boundary
Maps.
3.
Areas of two (2) or more contiguous acres within sustained slopes of 20% or greater within
the shoreland zone.
4.
Areas of two (2) or more contiguous acres supporting wetland vegetation and hydric soils,
which are not part of a freshwater wetland as defined, and which are not surficially
connected to a water body during the period of normal high water.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
9
B.
Rural Shoreland District
The Rural Shoreland includes those areas suitable for residential and recreational development
and some very low intensity commercial activity. It includes areas other than those in the
Resource Protection District or Stream Protection District.
C.
Stream Protection District
The Stream Protection District includes all land areas within seventy-five (75) feet, horizontal
distance, of the normal high-water line of a stream as defined and/or depicted on the Official
Shoreland Zoning Map, exclusive of those areas within two-hundred and fifty (250) feet,
horizontal distance, of the normal high-water line of a great pond, or river, or within two hundred
fifty (250) feet, horizontal distance, or the upland edge of a freshwater wetland. Where a stream
and its associated shoreland are located within two hundred fifty (250) feet, horizontal distance,
of the above water bodies or wetlands, that land area shall be regulated under the terms of the
shoreland district associated with that water body or wetland.
Section 14.
Table of Land Uses
All land use activities, as indicated in Table 1, Land Uses in the Shoreland Zone, shall conform with all of the
applicable land use standards in Section 15. The district designation for a particular site shall be determined
from the Official Shoreland Zoning Map. Where uncertainty exists as to the exact location of district
boundary lines, field verification of the authority or board with jurisdiction shall prevail as to the exact
location of the District boundary line.
Key to Table 1:
Yes -
Allowed (No permit required but the use must comply with all applicable land use
standards.)
No -
Prohibited
PB -
Requires permit issued by the Planning Board
CEO -
Requires permit issued by the Code Enforcement Officer
LPI -
Requires permit issued by the Local Plumbing Inspector
Abbreviations:
RP - Resource Protection
RS - Rural Shoreland District
SP - Stream Protection District
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
10
TABLE 1. LAND USES IN THE SHORELAND ZONE
LAND USES
DISTRICT
SP
RP
RS
1. Non-intensive recreational uses not requiring structures such as
hunting, fishing and hiking
yes
yes
yes
2. Motorized vehicular traffic on existing roads and trails
yes
yes
yes
3. Forest management activities except for timber harvesting & land
management roads
yes
yes
yes
4. Timber harvesting
yes
CEO1
yes
5.Clearing or removal of vegetation for activities other than timber harvesting
CEO
CEO1
yes
6. Fire prevention activities
yes
yes
yes
7. Wildlife management practices
yes
yes
yes
8. Soil and water conservation practices
yes
yes
yes
9. Mineral exploration
no
yes2
yes2
10. Mineral extraction including sand and gravel extraction
no
no
PB
11. Surveying and resource analysis
yes
yes
yes
12. Emergency operations
yes
yes
yes
13. Agriculture
yes
PB
yes
14. Aquaculture
PB
PB
PB
15. Principal structures and uses
A. One and two family residential, including driveways
PB3
no
PB
B. Multi-unit residential
no
no
PB
C. Commercial
no
No
no
D. Industrial
no
no
no
E. Governmental and institutional
no
no
PB
F. People Camps
no
no
PB
G. Residential Institutional
no
no
PB
H. Small non-residential facilities for educational, scientific, or nature
interpretation purposes
PB
PB
PB
16. Structures accessory to allowed uses
PB3
PB
CEO
17. A. Temporary piers, docks, wharfs, bridges and other structures and uses
extending over or below the normal high-water line or within a wetland
B. Moored/floating swim docks 100 sq. ft. and less
C. Moored/floating swim docks greater than 100 sq. ft.
CEO7
yes
no
CEO7
yes
no
CEO7
yes
no
18. Conversions of seasonal residences to year-round residences
LPI
no
LPI
19. Home occupations
PB
PB
PB
20. Private sewage disposal systems for allowed uses
LPI
LPI
LPI
21. Essential services
PB4
PB4
PB
A. Roadside distribution lines (34.5kV and lower)
CEO4
CEO4
Yes5
B. Non-roadside or cross-country distribution lines involving ten poles or less in the
shoreland zone
PB4
PB4
CEO
C. Non-roadside or cross-country distribution lines involving eleven or more poles in
the shoreland zone
PB4
PB4
PB
D. Other essential services
PB4
PB4
PB
22. Service drops, as defined, to allowed uses
yes
yes
yes
23. Public and private recreational areas involving minimal structural development
PB
PB
PB
24. Individual, private campsites
CEO
CEO
CEO
25. Campgrounds
no
No
PB
26. Road construction
PB
No6
PB
27. Land management roads
yes
PB
yes
28. Parking facilities
no
No
PB
29. Marinas
no
no
no
30. Filling and earth moving of <10 cubic yards
CEO
CEO
yes
31. Filling and earth moving of >10 cubic yards
PB
PB
CEO
32. Signs
yes
yes
yes
33. Uses similar to allowed uses
CEO
CEO
CEO
34. Uses similar to uses requiring a CEO permit
CEO
CEO
CEO
35. Uses similar to uses requiring a PB permit
PB
PB
PB
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
11
36. Appurtenant structure to recreational vehicle
no
no
CEO
37. Recreational Trails
CEO
CEO
CEO
1In RP not allowed within 75 feet horizontal distance, of the normal high-water line of great ponds, except to remove safety hazards.
2Requires permit from the Code Enforcement Officer if more than 100 square feet of surface area, in total, is disturbed.
3 Provided that a variance from the setback requirement is obtained from the Board of Appeals.
4 See further restrictions in Section 15(L(2).
5 Permit not required, but must file a written "notice of intent to construct" with CEO.
6Except as provided in Section 15(H)(4).
7 Excluding bridges and other crossings not involving earthwork, in which case no permit is required.
Section 15.
Land Use Standards
All land use activities within the shoreland zone shall conform with the following provisions, if
applicable.
A.
Minimum Lot Standards
1.
Standards
Minimum Lot Area
(acres)
Minimum Shore
Frontage (ft.)
Residential per dwelling unit
2 acres
200
Governmental, Institutional
per principal structure
2 acres
300
Public and Private
Recreational Facilities
2 acres
200
2.
Land below the normal high-water line of a water body or upland edge of a wetland and land
beneath roads serving more than two (2) lots shall not be included toward calculating minimum lot
area.
3.
Lots located on opposite sides of a public or private road shall be considered each a separate tract or
parcel of land unless such road was established by the owner of land on both sides thereof after
September 22, 1971.
4.
The minimum width of any portion of any lot within one hundred (100) feet, horizontal distance, of
the normal high-water line of a water body or upland edge of
a wetland shall be equal to or greater than the shore frontage requirement for a lot with the proposed
use.
5.
If more than one residential dwelling unit, principal governmental, institutional, commercial or
industrial structure or use, or combination thereof, is constructed or established on a single parcel,
all dimensional requirements shall be met for each additional dwelling unit, principal structure or
use.
Note: Before March 5, 1988 lot size requirement was 2 acre
Between March 5, 1988 and March 7, 1992 lot size requirement was 1 acre.
B.
Principal and Accessory Structures
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
12
1.
All new principal and accessory structures shall be set back at least one hundred (100) feet,
horizontal distance, from the normal high-water line of great ponds and rivers that flow to
great ponds, and seventy-five (75) feet , horizontal distance, from the normal high-water
line of other water bodies, tributary streams, or the upland edge of a wetland. In the
Resource Protection District the setback requirement shall be 250 feet, horizontal distance,
except for structures, roads, parking spaces or other regulated objects specifically allowed
in that district in which case the setback requirements specified above shall apply.
The water body, tributary stream, or wetland setback provision shall neither apply to
structures which require direct access to the water body or wetland as an operational
necessity, such as piers, docks and retaining walls, nor to other functionally water-
dependent uses.
On a non-conforming lot of record on which only a residential structure exists, and it is not
possible to place an accessory structure meeting the required water body, tributary stream
or wetland setbacks, the code enforcement officer may issue a permit to place a single
accessory structure, with no utilities, for the storage of yard tools and similar equipment.
Such accessory structure shall not exceed eighty (80) square feet in area nor eight (8) feet
in height, and shall be located as far from the shoreline or tributary stream as practical and
shall meet all other applicable standards, including lot coverage and vegetation clearing
limitations. In no case shall the structure be located closer to the shoreline or tributary
stream than the principal structure.
2.
The minimum setback for all new principal and accessory structures from all property lines
(except from the normal high water line or upland edge of a wetland) shall be twenty-five
(25) feet.
3.
Principal or accessory structures and expansions of existing structures which are permitted
in the Resource Protection, Rural Shoreland and Stream Protection Districts, shall not
exceed thirty-five (35) feet in height. This provision shall not apply to structures such as
transmission towers, windmills, antennas, and similar structures having no floor area.
4.
The lowest floor elevation or openings of all buildings and structures including basements
shall be elevated at least one foot above the elevation of the 100 year flood, the flood or
record, or in the absence of these, the flood as defined by soil types identified as recent
floodplain soils.
5.
Non-vegetated surfaces shall not exceed a total of twenty (20) percent of the portion of the
lot located within the shoreland zone. This limitation does not apply to public boat
launching facilities regardless of the district in which the facility is located.
For the purposes of calculating lot coverage, non-vegetated surfaces include, but are not
limited to the following: structures, driveways, parking areas, and other areas from which
vegetation has been removed. Naturally occurring ledge and rock outcroppings are not
counted as non-vegetated surfaces when calculating lot coverage for lots of record on
March 24, 1990 and in continuous
existence since that date.
6.
Notwithstanding the requirements stated above, stairways or similar structures may be
allowed with a permit from the Code Enforcement Officer, to provide shoreline access in
areas of steep slopes or unstable soils provided, that the structure is limited to a maximum
of four (4) feet in width; that the structure does not extend below or over the normal high-
water line of a water body or upland edge of a wetland, (unless permitted by the
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
13
Department of Environmental Protection pursuant to the Natural Resources Protection Act,
Title 38, Section 480-C); and that the applicant demonstrates that no reasonable access
alternative exists on the property.
7.
Retaining walls that are not necessary for erosion control shall meet the structure setback
requirement, except for low retaining walls and associated fill provided all of the following
conditions are met:
a.
The site has been previously altered and an effective vegetated buffer does not exist;
b.
The wall(s) is(are) at least 25 feet, horizontal distance, from the normal high-water
line of a water body, tributary stream, or upland edge of a wetland;
c.
The site where the retaining wall will be constructed is legally existing lawn or is a
site eroding from lack of naturally occurring vegetation, and which cannot be
stabilized with vegetative plantings;
d.
The total height of the wall(s), in the aggregate, are no more than 24 inches;
e.
Retaining walls are located outside of the 100-year floodplain on rivers, streams, and
tributary streams, as designated on the Federal Emergency Management Agency's
(FEMA) Flood Insurance Rate Maps or Flood Hazard Boundary Maps, or the flood
of record, or in the absence of these, by soil types identified as recent flood plain
soils.
f.
The area behind the wall is revegetated with grass, shrubs, trees, or a combination
thereof, and no further structural development will occur within the setback area,
including patios and decks; and
g.
A vegetated buffer area is established within 25 feet, horizontal distance, of the
normal high-water line of a water body, tributary stream, or upland edge of a
wetland when a natural buffer area does not exist. The buffer area must meet the
following characteristics:
(i)
The buffer must include shrubs and other woody and herbaceous vegetation.
Where natural ground cover is lacking the area must be supplemented with
leaf or bark mulch;
(ii)
Vegetation plantings must be in quantities sufficient to retard erosion and
provide for effective infiltration of stormwater runoff;
(iii) Only native species may be used to establish the buffer area;
(iv) A minimum buffer width of 15 feet, horizontal distance, is required, measured
perpendicularly to the normal high-water line or upland edge of a wetland;
(v)
A footpath not to exceed the standards in Section 15.P.2.a, may traverse the
buffer;
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
14
C. Piers, Docks, Wharfs, Bridges and Other Structures and Uses Extending Over or Below
the Normal High-Water Line of a Water Body or Within a Wetland, and Shoreline
Stabilization
1.
A permit is required for first time dock installation or enlargement from the Code
Enforcement Officer.
2.
No more than one pier, dock, wharf or similar structure extending or located below the
normal high-water line of a water body or within a wetland is allowed on a single lot; except
that when a single lot contains at least twice the minimum shore frontage as specified in
Section 15.A, a second structure may be allowed
and may remain as long as the lot is
not further divided.
3.
Access from shore shall be developed on soils appropriate for such use and constructed so
as to control erosion.
4.
The location shall not interfere with existing developed or natural beach areas.
5.
The facility shall be located so as to minimize adverse effects on fisheries.
6.
The facility shall be no larger in dimension than necessary to carry on the activity and be
consistent with the surrounding character and uses of the area. A temporary pier, dock, or
wharf shall not be wider than six feet for non-commercial uses.
7.
No new structures shall be built on, over or abutting a pier, wharf, dock or other structure
extending beyond the normal high-water line of a water body or within a wetland unless
the structure requires direct access to the water body or wetland as an operational
necessity.
8.
Docks and wharfs that are not permanent shall be removed not later than November 1 of
each year.
9.
No existing structures built on, over or abutting a pier, dock, wharf or other structure
extending beyond the normal high-water line of a water body or within a wetland shall be
converted to residential dwelling units in any district.
10.
New permanent piers and docks shall not be permitted unless it is clearly demonstrated to
the Planning Board that a temporary pier or dock is not feasible, and a permit has been
obtained from the Department of Environmental Protection, pursuant to the Natural
Resources Protection Act.
11.
Vegetation may be removed in excess of the standards in Section 15(P) of this Ordinance
in order to conduct shoreline stabilization of an eroding shoreline, provided that a permit is
obtained from the Planning Board. Construction equipment must access the shoreline by
barge when feasible as determined by the Planning Board.
a.
When necessary, the removal of trees and other vegetation to allow for
construction equipment access to the stabilization site via land must be
limited to no more than 12 feet in width. When the stabilization project is
complete the construction equipment accessway must be restored.
b.
Revegetation must occur in accordance with Section 15(S).
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
15
D.
Campground
Campgrounds shall conform to the minimum requirements imposed under State licensing
procedure and the following:
1.
Campgrounds shall contain a minimum of five thousand (5,000) square feet of land, not
including roads and driveways, for each site. Land supporting wetland vegetation, and
land below the normal high-water line of a water body shall not be included in calculating
land area per site.
2.
The areas intended for placement of a recreational vehicle, tent or shelter, and utility and
service buildings shall be set back a minimum of one hundred (100) feet, horizontal
distance, from the normal high-water line of a great pond or a river flowing to a great
pond, and seventy-five (75) feet, horizontal distance, from the normal high-water line of
other water bodies, tributary streams identified in Section 9, or the upland edge of a
wetland.
3.
Recreational vehicles that are located on any site that does not comply with Section 15.D.2
above shall be moved off the site and beyond the applicable setback between November 1
and April 1 annually.
E.
Individual Private Campsites
Individual, private campsites not associated with campgrounds are allowed provided the
following conditions are met:
1.
One campsite per lot existing on the effective date of this Ordinance, or thirty thousand
(30,000) square feet of lot area within the shoreland zone, whichever is less, may be
permitted.
2.
When an individual private campsite is proposed on a lot that contains another principal
use and/or structure, the lot must contain the minimum lot dimensional requirements for
the principal structure and/or use, and the individual private campsite separately.
3.
Campsite placement on any lot, including the area intended for a recreational vehicle or
tent platform, shall be set back one hundred (100) feet, horizontal distance, from the
normal high-water line of a great pond or river flowing to a great pond, and seventy-five
(75) feet, horizontal distance, from the normal high-water line of other water bodies,
tributary streams, or the upland edge of a wetland.
4.
Only one recreational vehicle shall be allowed on a campsite. The recreational vehicles
shall not be located on any type of permanent foundation except for a gravel pad, and no
structure except a canopy shall be attached to the recreational vehicle.
5.
The clearing of vegetation for the siting of the recreational vehicle, tent or similar shelter
in a Resource Protection District shall be limited to one thousand (1,000) square feet.
6.
A written sewage disposal plan describing the proposed method and location of a sewage-
disposal system shall be required for each campsite and shall be approved by the Local
Plumbing Inspector. Where disposal is off-site, written authorization from the receiving
facility or land owner is required.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
16
7.
When a recreational vehicle, tent or similar shelter is placed on-site for more than one
hundred and twenty (120) days per year, all requirements for residential structures shall be
met, including the installation of a subsurface sewage disposal system in compliance with
the State of Maine Subsurface Wastewater Disposal Rules unless served by public sewage
facilities.
F.
Commercial and Industrial Uses
No new commercial and industrial uses are allowed within any shoreland zone except as may be
permitted in Section 14.
G.
Parking Areas
1.
Parking areas shall meet the shoreline and tributary stream setback requirements for
structures for the district in which such areas are located.
2.
Parking areas shall be adequately sized for the proposed use and shall be designed to
prevent stormwater runoff from flowing directly into a water body, and where feasible, to
retain all runoff on-site.
3.
In determining the appropriate size of proposed parking facilities, the following shall
apply:
a.
Typical parking space: Approximately ten (10) feet wide and twenty (20) feet long,
except that parking spaces for a vehicle and boat trailer shall be forty (40) feet long.
b.
Internal travel aisles: Approximately twenty (20) feet wide.
H.
Roads and Driveways
The following standards shall apply to the construction of roads and/or driveways and drainage
systems, culverts and other related features.
1.
Roads and driveways shall be set back at least one hundred (100) feet, horizontal distance,
from the normal high-water line of a great pond, or a river that flows to a great pond, and
seventy-five (75) feet, horizontal distance, from the normal high-water line of other water
bodies, tributary streams, or the upland edge or a wetland unless no reasonable alternative
exists as determined by the Planning Board. If no other reasonable alternative exists, the
road and/or driveway setback requirement shall be no less than fifty (50) feet, horizontal
distance, upon clear showing of the applicant that appropriate techniques will be used to
prevent sedimentation of the water body tributary stream or wetland. Such techniques may
include, but are not limited to, the installation of settling basins, and/or the effective use of
additional ditch relief culverts and turnouts placed so as to avoid sedimentation of the
water body, tributary stream, or wetland.
On slopes of greater than twenty (20) percent, the road and/or driveway setback shall be
increased by ten (10), horizontal distance, feet for each five (5) percent increase in slope
above twenty (20) percent.
Section 15.H.1 does not apply to approaches to water crossings nor to roads or driveways
that provide access to permitted structures and facilities located nearer to the shoreline or
tributary stream due to an operational necessity, excluding temporary docks for
recreational uses. Roads and driveways providing access to permitted structures within the
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
17
setback area shall comply fully with the requirements of Section 15.H.1 except for that
portion of the driveway necessary for the direct access to the structure.
2.
Existing public roads may be expanded within the legal road right-of-way regardless of
their setback from a water body tributary stream or wetland.
3.
New roads and driveways are prohibited in a Resource Protection District except, that the
planning board may grant a permit to construct a road or driveway to provide access to
permitted uses within the district. A road or driveway may also be or as approved by the
Planning Board in a Resource Protection District, upon a finding that no reasonable
alternative route or location is available outside the district. When a road or driveway is
permitted in a Resource Protection District the road and/or driveway shall be set back as
far as practicable from the normal high-water line of a water body, tributary stream, or
upland edge of a wetland.
4.
Road and driveway banks shall be no steeper than a slope of two (2) horizontal to one (1)
vertical, and shall be graded and stabilized in accordance with the provisions for erosion
and sedimentation control contained in Section 15.Q.
5.
Road and driveway grades shall be no greater than ten (10) percent except for short
segments of less than two hundred (200) feet.
6.
In order to prevent road and driveway surface drainage from directly entering water
bodies, tributary streams or wetlands roads and driveways shall be designed, constructed
and maintained to empty onto an unscarified buffer strip at least fifty (50) feet plus two (2)
times the average slope, in width between the outflow point of the ditch or culvert and the
normal high-water line of a water body, tributary stream, or upland edge of a wetland.
Surface drainage which is directed to an unscarified buffer strip shall be diffused or spread
out to promote infiltration of the runoff and to minimize channelized flow of the buffer
strip.
7.
Ditch relief (cross drainage) culverts, drainage dips and water turnouts shall be installed in
a manner effective in directing drainage to unscarified buffer strips before the flow gains
sufficient volume or head to erode the road, driveway or ditch. To accomplish this, the
following shall apply:
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
18
a.
Ditch relief culverts, drainage dips and associated water turnouts shall be spaced
along the road or driveway at intervals no greater than indicated in the following
table:
Grade
(Percent)
Spacing
(Feet)
0-2
250
3-5
200-135
6-10
100-80
11-15
80-60
16-20
60-45
21+
40
b.
Drainage dips may be used in place of ditch relief culverts only where the grade is
ten (10) percent or less.
c.
On sections having slopes greater than ten (10) percent, ditch relief culverts shall be
placed at approximately a thirty (30) degree angle down slope from a line
perpendicular to the centerline of the road or driveway.
d.
Ditch relief culverts shall be sufficiently sized and properly installed in order to
allow for effective functioning and their inlet and outlet ends shall be stabilized with
appropriate materials.
8.
Ditches, culverts, bridges, dips, water turnouts and other storm water runoff control
installations associated with roads and driveways shall be maintained on a regular basis to
assure effective functioning.
9.
A permit is not required for the placement of an existing road culvert as long as the
replacement culvert is:
a.
not more than one standard culvert size wider in diameter than the culvert being
replaced;
b.
not more than twenty-five percent (25%) longer than the culvert being replaced;
c.
not longer than seventy-five (75) feet; and
d.
provided that adequate erosion control measures are taken to prevent sedimentation
of the water and that the crossing does not block fish passage in the water course.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
19
I.
Signs
The following provisions shall govern the use of signs in the Resource Protection, Stream
Protection, and Rural Shoreland Districts.
1.
Signs relating to goods and services sold on the premises shall be permitted, provided that
such signs shall not exceed six (6) square feet in area and shall not exceed two (2) signs
per premises. Signs relating to goods or services not sold or rendered on the premises shall
be prohibited.
2.
Name signs shall be permitted, provided such signs shall not exceed two (2) signs per
premises and not exceed twelve (12) square feet in aggregate.
3.
Residential users may display a single sign not over three (3) square feet in area relating to
the sale, rental, or lease of the premises.
4.
Signs relating to trespassing and hunting shall be permitted without restriction as to
number provided that no such sign shall exceed two (2) square feet in area.
5.
Signs relating to public safety shall be permitted without restriction.
6.
No sign shall extend higher than twenty (20) feet above the ground.
7.
Signs may be illuminated only by shielded, non-flashing lights.
J.
Storm Water Runoff
1.
All new construction and development shall be designed to minimize storm water runoff
from the site in excess of the natural predevelopment conditions. Where possible, existing
natural runoff control features, such as berms, swales, terraces and wooded areas shall be
retained in order to reduce runoff and encourage infiltration of storm waters.
2.
Storm water runoff control systems shall be maintained as necessary to ensure proper
functioning.
K.
Septic Waste Disposal
1.
All subsurface sewage-disposal systems shall be installed in conformance with the State of
Maine Subsurface Wastewater Disposal Rules and the following:
a.
Clearing or removal of woody vegetation necessary to site a new system and any
associated fill extensions, shall not extend closer than seventy-five (75) feet,
horizontal distance, from the normal high-water line of a water body or the upland
edge of a wetland; and
b.
A holding tank is not allowed for a first time residential use in the shoreland zone.
L.
Essential Services
1.
Where feasible, the installation of essential services shall be limited to existing public
ways and existing service corridors.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
20
2.
The installation of essential services, other than road-side distribution lines, is not
permitted in a Resource Protection or Stream Protection District, except to provide
services to a permitted use within said district, or except where the applicant demonstrates
that no reasonable alternative exists. Where permitted, such structures and facilities shall
be located so as to minimize any adverse impacts on surrounding uses and resources,
including visual impacts.
3.
Damaged or destroyed public utilities transmission lines, towers and related equipment
may be replaced or reconstructed without a permit.
M.
Mineral Exploration and Extraction
Mineral exploration to determine the nature or extent of mineral resources shall be accomplished
by hand sampling, test boring, or other methods which create minimal disturbance of less than
one hundred (100) square feet of ground surface. A permit from the Code Enforcement Officer
shall be required for mineral exploration which exceeds the above limitation. All excavations,
including test pits and holes shall be immediately capped, filled or secured by other equally
effective measures to restore disturbed areas and to protect the public health and safety.
Mineral extraction may be permitted under the following conditions:
1.
A reclamation plan shall be filed with, and approved by, the Planning Board before a
permit is granted. Such plan shall describe in detail procedures to be undertaken to fulfill
the requirements of Section 15.M.4 below.
2.
No part of any extraction operation, including drainage and runoff control features shall be
permitted within one hundred (100) feet, horizontal distance, of the normal high-water line
of a great pond, a river or the upland edge of a wetland and within seventy-five (75) feet,
horizontal distance, of the normal high-water line of any other water body, stream, or
tributary stream. Extraction operations shall not be permitted within one hundred (100)
feet of any property line, without written permission of the owner of such adjacent
property.
3.
Within twelve (12) months following the completion of extraction operations at any
extraction site, which operations shall be deemed complete when less than one hundred
(100) cubic yards of materials are removed in any consecutive twelve (12) month period,
ground levels and grades shall be established in accordance with the following:
a.
All debris, stumps, and similar material shall be removed for disposal in an
approved location, or shall be buried on-site. Only materials generated on-site may
be buried or covered on-site.
b.
The final graded slope shall be two and one-half to one (21/2:1) slope or flatter.
c.
Top soil or loam shall be retained to cover all disturbed land areas, which shall be
reseeded and stabilized with vegetation native to the area. Additional top soil or
loam shall be obtained from off-site sources if necessary to complete the
stabilization project.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
21
4.
In keeping with the purposes of this Ordinance, the Planning Board may impose such
conditions as are necessary to minimize the adverse impacts associated with mineral-
extraction operations on surrounding uses and resources.
N.
Agriculture
1.
All spreading of manure shall be accomplished in conformance with the Manure
Utilization Guidelines published by the former Maine Department of Agriculture on
November 1, 2001, and the Nutrient Management Law (7 M.R.S.A. sections 4201-4209).
2.
Manure shall not be stored or stockpiled within one hundred (100) feet, horizontal
distance, or a great pond or a river flowing to a great pond, or within seventy-five (75) feet
horizontal distance, of other water bodies, tributary streams, or wetlands. All manure
storage areas within the shoreland zone must be constructed or modified such that the
facility produces no discharge of effluent or contaminated storm water.
3.
Agricultural activities involving tillage of soil greater than forty thousand (40,000) square
feet in surface areas, within the shoreland zone shall require a Conservation Plan to be
filed with the Planning Board. Non-conformance with the provisions of said plan shall be
considered to be a violation of this Ordinance.
4.
There shall be no new tilling of soil within one hundred (100) feet, horizontal distance, of
the normal high-water line of a great pond and within seventy-five (75) feet, horizontal
distance, from other water bodies, tributary streams, streams, and wetlands. Operations in
existence on the effective date of this ordinance and not in conformance with this provision
may be maintained.
5.
Newly established livestock grazing areas shall not be permitted within one hundred (100)
feet, horizontal distance, of the normal high-water line of a great pond; within seventy-five
(75) feet, horizontal distance of other water bodies, nor; within twenty-five (25) feet,
horizontal distance, of tributary streams, and wetlands.
Livestock grazing associated within on-going farm activities, and which are not in
conformance with the above setback provisions may continue, provided that such grazing
is conducted in accordance with a Conservation Plan that has been filed with the Planning
Board.
O.
Reserved
O-1.
Timber Harvesting - Statewide Standards
1.
Shoreline integrity and sedimentation. Persons conducting timber harvesting and related
activities must take reasonable measures to avoid the disruption of shoreline integrity, the
occurrence of sedimentation of water, and the disturbance of water body and tributary
stream banks, water body and tributary stream channels, shorelines, and soil lying within
water bodies, tributary streams and wetlands. If, despite such precautions, the disruption of
shoreline integrity, sedimentation of water, or the disturbance of water body and tributary
stream banks, water body and tributary stream channels, shorelines, and soil lying within
water bodies, tributary streams and wetlands occurs, such conditions must be corrected.
2.
Slash treatment. Timber harvesting and related activities shall be conducted such that
slash or debris is not left below the normal high-water line of any water body or tributary
stream, or the upland edge of a wetland. Section 15.O-1.2 does not apply to minor,
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
22
incidental amounts of slash that result from timber harvesting and related activities
otherwise conducted in compliance with this section.
a.
Slash actively used to protect soil from disturbance by equipment or to stabilize
exposed soil, may be left in place, provided that no part thereof extends more than 4
feet above the ground.
b.
Adjacent to great ponds, rivers and wetlands:
1)
No accumulation of slash shall be left within 50 feet, horizontal distance, of
the normal high-water line or upland edge of a wetland; and
2)
Between 50 feet and 250 feet, horizontal distance, of the normal high-water
line or upland edge of a wetland, all slash larger than 3 inches in diameter
must be disposed of in such a manner that no part thereof extends more than 4
feet above the ground.
3.
Timber harvesting and related activities must leave adequate tree cover and shall be
conducted so that a well-distributed stand of trees is retained. This requirement may be
satisfied by following one of the following three options:
a.
Option 1 (40% volume removal), as follows:
1)
Harvesting of no more than 40 percent of the total volume on each acre of
trees 4.5 inches DBH or greater in any 10 year period is allowed. Volume
may be considered to be equivalent to basal area;
2)
A well-distributed stand of trees which is windfirm, and other vegetation
including existing ground cover, must be maintained; and,
3)
Within 75 feet, horizontal distance, of the normal high-water line of rivers,
streams, and great ponds, and within 75 feet, horizontal distance, of the
upland edge of a freshwater wetland, there must be no cleared openings. At
distances greater than 75 feet, horizontal distance, of the normal high-water
line of a river or great pond or upland edge of a wetland, timber harvesting
and related activities must not create single cleared openings greater than
14,000 square feet in the forest canopy. Where such openings exceed 10,000
square feet, they must be at least 100 feet, horizontal distance, apart. Such
cleared openings will be included in the calculation of total volume removal.
Volume may be considered equivalent to basal area.
b.
Option 2 (60 square foot basal area retention), as follows:
1)
The residual stand must contain an average basal area of at least 60 square
feet per acre of woody vegetation greater than or equal to 1.0 inch DBH, of
which 40 square feet per acre must be greater than or equal to 4.5 inches
DBH;
2)
A well-distributed stand of trees which is windfirm, and other vegetation
including existing ground cover, must be maintained; and,
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
23
3)
Within 75 feet, horizontal distance, of the normal high-water line of water
bodies and within 75 feet, horizontal distance, of the upland edge of wetlands,
there must be no cleared openings. At distances greater than 75 feet,
horizontal distance, of the normal high-water line of a river or great pond, or
upland edge of a wetland, timber harvesting and related activities must not
create single cleared openings greater than 14,000 square feet in the forest
canopy. Where such openings exceed 10,000 square feet, they must be at least
100 feet, horizontal distance, apart. Such cleared openings will be included in
the calculation of the average basal area. Volume may be considered
equivalent to basal area.
c.
Option 3 (Outcome based), which requires: An alternative method proposed in an
application, signed by a Licensed Forester or certified wildlife professional,
submitted by the landowner or designated agent to the State of Maine Department of
Conservation's Bureau of Forestry (Bureau) for review and approval, which
provides equal or better protection of the shoreland area than this rule.
Landowners must designate on the Forest Operations Notification form required by
12 M.R.S.A. chapter 805, subchapter 5 which option they choose to use. If
landowners choose Option 1 or Option 2, compliance will be determined solely on
the criteria for the option chosen. If landowners choose Option 3, timber harvesting
and related activities may not begin until the Bureau has approved the alternative
method.
The Bureau may verify that adequate tree cover and a well-distributed stand of trees
is retained through a field procedure that uses sample plots that are located randomly
or systematically to provide a fair representation of the harvest area.
4.
Skid trails, yards, and equipment operation. This requirement applies to the construction,
maintenance and use of skid trails and yards in shoreland areas.
a.
Equipment used in timber harvesting and related activities shall not use river, stream
or tributary stream channels as travel routes except when surface waters are frozen
and snow covered, and the activity will not result in any ground disturbance.
b.
Skid trails and yards must be designed and constructed to prevent sediment and
concentrated water runoff from entering a water body, tributary stream, or wetland.
Upon termination of their use, skid trails and yards must be stabilized.
c.
Setbacks:
1)
Equipment must be operated to avoid the exposure of mineral soil within 25
feet, horizontal distance, of any water body, tributary stream, or wetland. On
slopes of 10 percent or greater, the setback for equipment operation must be
increased by 20 feet, horizontal distance, plus an additional 10 feet, horizontal
distance, for each 5 percent increase in slope above 10 percent. Where slopes
fall away from the resource, no increase in the 25-foot setback is required.
2)
Where such setbacks are impracticable, appropriate techniques shall be used
to avoid sedimentation of the water body, tributary stream or
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
24
wetland. Such techniques may include the installation of sump holes or
settling basins, and/or the effective use of additional ditch relief culverts and
ditch water turnouts placed to avoid sedimentation of the water body, tributary
stream, or wetland. If, despite such precautions, sedimentation or the
disruption of shoreline integrity occurs, such conditions must be corrected.
5.
Land Management Roads. Land management roads, including approaches to crossings of
water bodies, tributary stream channels, and freshwater wetlands, ditches and other related
structures, must be designed, constructed, and maintained to prevent sediment and
concentrated water runoff from directly entering the water body, tributary stream or
wetland. Surface water on or adjacent to water crossing approaches must be diverted
through vegetative filter strips to avoid sedimentation of the watercourse or wetland.
Because roadside ditches may not extend to the resource being crossed, vegetative filter
strips must be established in accordance with the setback requirements in Section 15.O-
1.7.
a.
Land management roads and associated ditches, excavation, and fill must be set
back at least:
1)
100 feet, horizontal distance, from the normal high-water line of a great pond,
river or freshwater wetland;
2)
50 feet, horizontal distance, from the normal high-water line of streams; and
3)
25 feet, horizontal distance, from the normal high-water line of tributary
streams
b.
The minimum 100 foot setback specified in Section 15.O-1. 5.a.1 above may be
reduced to no less than 50 feet, horizontal distance, and the 50 foot setback specified
in Section 15.O-1. 5.a.2 above may be reduced to no less than 25 feet, horizontal
distance, if, prior to construction, the landowner or the landowner's designated agent
demonstrates to the Planning Board's satisfaction that no reasonable alternative
exists and that appropriate techniques will be used to prevent sedimentation of the
water body, tributary stream, or wetland. Such techniques may include, but are not
limited to, the installation of settling basins, and/or the effective use of additional
ditch relief culverts and turnouts placed to avoid sedimentation of the water body,
tributary stream or wetland. If, despite such precautions, sedimentation or the
disruption of shoreline integrity occurs, such conditions must be corrected.
c.
On slopes of 10 percent or greater, the land management road setback must be
increased by at least 20 feet, horizontal distance, plus an additional 10 feet,
horizontal distance, for each 5 percent increase in slope above 10 percent.
d.
New land management roads are not allowed within the shoreland area in a
Resource Protection District, unless, prior to construction, the landowner or the
landowner's designated agent makes a clear demonstration to the Planning Board's
satisfaction that no reasonable alternative route exists outside the shoreland zone,
and that the new road must be set back as far as practicable from the normal high-
water line and screened from the river by existing vegetation.
e.
Ditches, culverts, bridges, dips, water turnouts and other water control installations
associated with roads must be maintained on a regular basis to assure effective
functioning. Drainage structures shall deliver a dispersed flow of water into an
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
25
unscarified filter strip no less than the width indicated in the setback requirements in
Section 15.O-1.7. Where such a filter strip is impracticable, appropriate techniques
shall be used to avoid sedimentation of the water body, tributary stream, or wetland.
Such techniques may include the installation of sump holes or settling basins, and/or
the effective use of additional ditch relief culverts and ditch water turnouts placed to
avoid sedimentation of the water body, tributary stream, or wetland. If, despite such
precautions, sedimentation or the disruption of shoreline integrity occurs, such
conditions must be corrected.
f.
Road closeout and discontinuance. Maintenance of the water control installations
required in Section 15.O-1.5.e must continue until use of the road is discontinued
and the road is put to bed by effective installation of water bars or other adequate
road drainage structures at appropriate intervals, constructed to avoid surface water
flowing over or under the water bar, and extending a sufficient distance beyond the
traveled way so that water does not reenter the road surface.
g.
Upgrading existing roads. Extension or enlargement of presently existing roads must
conform to the provisions of Section 15.O-1. Any nonconforming existing road may
continue to exist and to be maintained, as long as the nonconforming conditions are
not made more nonconforming.
h.
Exception. Extension or enlargement of presently existing roads need not conform to
the setback requirements of Section 15.O-1.5.a if, prior to extension or enlargement,
the landowner or the landowner's designated agent demonstrates to the Planning
Board's satisfaction that no reasonable alternative exists and that appropriate
techniques will be used to prevent sedimentation of the water body, tributary stream,
or wetland. Such techniques may include, but are not limited to, the installation of
settling basins, and/or the effective use of additional ditch relief culverts and
turnouts placed to avoid sedimentation of the water body, tributary stream, or
wetland. If, despite such precautions, sedimentation or the disruption of shoreline
integrity occurs, such conditions must be corrected.
i.
Additional measures. In addition to the foregoing minimum requirements, persons
undertaking construction and maintenance of roads and river, stream and tributary
stream crossings must take reasonable measures to avoid sedimentation of surface
waters.
6.
Crossings of waterbodies. Crossings of rivers, streams, and tributary streams must allow
for fish passage at all times of the year, must not impound water, and must allow for the
maintenance of normal flows.
a.
Determination of flow. Provided they are properly applied and used for the
circumstances for which they are designed, methods including but not limited to the
following are acceptable as a means of calculating the 10 year and 25 year frequency
water flows and thereby determining water crossing sizes as required in Section
15.O-1: The United States Geological Survey (USGS) Methods; specifically:
Hodgkins, G. 1999. Estimating the Magnitude of Peak Flows for Streams in Maine
for Selected Recurrence Intervals. U.S. Geological Survey. Water Resources
Investigations Report 99-4008. 45 pp.
b.
Upgrading existing water crossings. Extension or enlargement of presently existing
water crossings must conform to the provisions of Section 15.O-1. Any
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
26
nonconforming existing water crossing may continue to exist and be maintained, as
long as the nonconforming conditions are not made more nonconforming; however,
any maintenance or repair work done below the normal high-water line must
conform to the provisions of Section 15.O-1.
c.
Other Agency Permits. Any timber harvesting and related activities involving the
design, construction, and maintenance of crossings on waterbodies other than a
river, stream or tributary stream may require a permit from the Land Use Regulation
Commission, the Department of Environmental Protection, or the US Army Corps
of Engineers.
d.
Any timber harvesting and related activities involving the design, construction, and
maintenance of crossings of freshwater wetlands identified by the Department of
Inland Fisheries and Wildlife as essential wildlife habitat require prior consultation
with the Department of Inland Fisheries and Wildlife.
e.
Notice to Bureau of Forestry. Written notice of all water crossing construction
maintenance, alteration and replacement activities in shoreland areas must be given
to the Bureau prior to the commencement of such activities. Such notice must
contain all information required by the Bureau, including:
1)
a map showing the location of all proposed permanent crossings;
2)
the GPS location of all proposed permanent crossings;
3)
for any temporary or permanent crossing that requires a permit from state or
federal agencies, a copy of the approved permit or permits; and
4)
a statement signed by the responsible party that all temporary and permanent
crossings will be constructed, maintained, and closed out in accordance with
the requirements of this Section.
f.
Water crossing standards. All crossings of rivers require a bridge or culvert sized
according to the requirements of Section 15.O-1. 6.g below. Streams and tributary
streams may be crossed using temporary structures that are not bridges or culverts
provided:
1)
concentrated water runoff does not enter the stream or tributary stream;
2)
sedimentation of surface waters is reasonably avoided;
3)
there is no substantial disturbance of the bank, or stream or tributary stream
channel;
4)
fish passage is not impeded; and,
5)
water flow is not unreasonably impeded.
Subject to Section 15.O-1. 6.f. 1.5) above, skid trail crossings of streams and
tributary streams when channels of such streams and tributary streams are frozen
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
27
and snow-covered or are composed of a hard surface which will not be eroded or
otherwise damaged are not required to use permanent or temporary structures.
g.
Bridge and Culvert Sizing. For crossings of river, stream and tributary stream
channels with a bridge or culvert, the following requirements apply:
1)
Bridges and culverts must be installed and maintained to provide an opening
sufficient in size and structure to accommodate 25 year frequency water flows
or with a cross-sectional area at least equal 3 times the cross-sectional area of
the river, stream, or tributary stream channel.
2)
Temporary bridge and culvert sizes may be smaller than provided in Section
15.O-1. 6.g.1 if techniques are effectively employed such that in the event of
culvert or bridge failure, the natural course of water flow is maintained and
sedimentation of the water body or tributary stream is avoided. Such crossing
structures must be at least as wide as the channel and placed above the normal
high-water line. Techniques may include, but are not limited to, the effective
use of any, a combination of, or all of the following:
a)
use of temporary skidder bridges;
b)
removing culverts prior to the onset of frozen ground conditions;
c)
using water bars in conjunction with culverts;
d)
using road dips in conjunction with culverts.
3)
Culverts utilized in river, stream and tributary stream crossings must:
a)
be installed at or below river, stream or tributary stream bed elevation;
b)
be seated on firm ground;
c)
have soil compacted at least halfway up the side of the culvert;
d)
be covered by soil to a minimum depth of 1 foot or according to the
culvert manufacturer's specifications, whichever is greater; and
e)
have a headwall at the inlet end which is adequately stabilized by riprap
or other suitable means to reasonably avoid erosion of material around
the culvert.
4)
River, stream and tributary stream crossings allowed under Section 15.O-1,
but located in flood hazard areas (i.e. A zones) as identified on a community's
Flood Insurance Rate Maps (FIRM) or Flood Hazard Boundary Maps
(FHBM), must be designed and constructed under the stricter standards
contained in that community's National Flood Insurance Program (NFIP). For
example, a water crossing may be required to pass a 100-year flood event.
5)
Exception. Skid trail crossings of tributary streams within shoreland areas
and wetlands adjacent to such streams may be undertaken in a manner not in
conformity with the requirements of the foregoing subsections provided
persons conducting such activities take reasonable measures to avoid the
disruption of shoreline integrity, the occurrence of sedimentation of water,
and the disturbance of stream banks, stream channels, shorelines, and soil
lying within ponds and wetlands. If, despite such precautions, the disruption
of shoreline integrity, sedimentation of water, or the disturbance of stream
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
28
banks, stream channels, shorelines, and soil lying within ponds and wetlands
occurs, such conditions must be corrected.
h.
Skid trail closeout. Upon completion of timber harvesting and related activities, or
upon the expiration of a Forest Operations Notification, whichever is earlier, the
following requirements apply:
1)
Bridges and culverts installed for river, stream and tributary stream crossings
by skid trails must either be removed and areas of exposed soil stabilized, or
upgraded to comply with the closeout standards for land management roads in
Section15.O-1. 6.i below.
2)
Water crossing structures that are not bridges or culverts must either be
removed immediately following timber harvesting and related activities, or, if
frozen into the river, stream or tributary stream bed or bank, as soon as
practical after snowmelt.
3)
River, stream and tributary stream channels, banks and approaches to
crossings of water bodies and tributary streams must be immediately
stabilized on completion of harvest, or if the ground is frozen and/or snow-
covered, as soon as practical after snowmelt. If, despite such precautions,
sedimentation or the disruption of shoreline integrity occurs, such conditions
must be corrected.
i.
Land management road closeout. Maintenance of the water control features must
continue until use of the road is discontinued and the road is put to bed by taking the
following actions:
1)
Effective installation of water bars or other adequate road drainage structures
at appropriate intervals, constructed to reasonably avoid surface water flowing
over or under the water bar, and extending sufficient distance beyond the
traveled way so that water does not reenter the road surface.
2)
Water crossing structures must be appropriately sized or dismantled and
removed in a manner that reasonably avoids sedimentation of the water body
or tributary stream.
3)
Any bridge or water crossing culvert in roads to be discontinued shall satisfy
one of the following requirements:
a)
it shall be designed to provide an opening sufficient in size and
structure to accommodate 25 year frequency water flows;
b)
it shall be designed to provide an opening with a cross-sectional area at
least 3 1/2 times the cross-sectional area of the river, stream or tributary
stream channel; or
c)
it shall be dismantled and removed in a fashion to reasonably avoid
sedimentation of the river, stream or tributary stream.
If, despite such precautions, sedimentation or the disruption of shoreline
integrity occurs, such conditions must be corrected.
7.
Slope Table
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
29
Filter strips, skid trail setbacks, and land management road setbacks must be maintained as
specified in Section 15.O-1, but in no case shall be less than shown in the following table.
Average slope of land between exposed mineralWidth of strip between exposed
soil and the shoreline (percent)
mineral soil and shoreline
(feet along surface of the ground)
0
25
10
45
20
65
30
85
40
105
50
125
60
145
70
165
P.
Clearing or Removal of Vegetation for Activities Other Than Timber Harvesting
1.
In a Resource Protection District abutting a great pond, there shall be no cutting of
vegetation within the strip of land extending 75 feet, horizontal distance, inland from the
normal high-water line, except to remove hazard trees as described in section Q.
Elsewhere, in any Resource Protection District the cutting or removal of vegetation shall
be limited to that which is necessary for uses expressly authorized in that district.
2.
Except in areas as described in Section P.1, above, within a strip of land extending one-
hundred (100) feet, horizontal distance, inland from the normal high-water line of a great
pond or a river flowing to a great pond, or within a strip extending seventy-five (75) feet,
horizontal distance, from any other water body, tributary stream, or the upland edge of a
wetland, a buffer strip of vegetation shall be preserved as follows:
a.
There shall be no cleared opening greater than 250 square feet in the forest canopy
(or other existing woody vegetation if a forested canopy is not present) as measured
from the outer limits of the tree or shrub crown. However, a single footpath not to
exceed six (6) feet in width as measured between tree trunks and/or shrub stems is
allowed for accessing the shoreline provided that a cleared line of sight to the water
through the buffer strip is not created.
b.
Selective cutting of trees within the buffer strip is allowed provided that a well
distributed stand of trees and other natural vegetation is maintained. For the
purposes of Section 15.P.2.b a "well-distributed stand of trees" adjacent to a great
pond or a river or stream flowing to a great pond, shall be defined as maintaining a
rating score of 24 or more in each 25-foot by 50-foot rectangular (1250 square feet)
area as determined by the following rating system.
Diameter of Tree at 4-1/2 feet Above
Points
Ground Level (inches)
2 - < 4 in.
1
4 - <8 in.
2
8-< 12 in.
4
12 in. or greater
8
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
30
Adjacent to other water bodies, tributary streams, and wetlands, a "well-distributed
stand of trees" is defined as maintaining a minimum rating score of 16 per 25-foot
by 50-foot rectangular area.
The following shall govern in applying this point system:
1)
The 25-foot by 50-foot rectangular plots must be established where the
landowner or lessee proposes clearing within the required buffer;
2)
Each successive plot must be adjacent to, but not overlap a previous plot;
3)
Any plot not containing the required points must have no vegetation removed
except as otherwise allowed by this Ordinance;
4)
Any plot containing the required points may have vegetation removed down
to the minimum points required or as otherwise allowed by is Ordinance;
5)
Where conditions permit, no more than 50% of the points on any 25-foot by
50-foot rectangular area may consist of trees greater than 12 inches in
diameter.
For the purposes of Section 15.P.2.b "other natural vegetation" is defined as
retaining existing vegetation under three (3) feet in height and other ground cover
and retaining at least five (5) saplings less than two (2) inches in diameter at four
and one half (4 ½) feet above ground level for each 25-foot by 50-foot rectangle
area. If five saplings do not exist, no woody stems less than two (2) inches in
diameter can be removed until 5 saplings have been recruited into the plot.
Notwithstanding the above provisions, no more than 40% of the total volume of
trees four (4) inches or more in diameter, measured at 4 1/2 feet above ground level
may be removed in any ten (10) year period.
c.
In order to protect water quality and wildlife habitat, existing vegetation under three
(3) feet in height and other ground cover, including leaf litter and the forest duff
layer, shall not be cut, covered, or removed, except to provide for a footpath or other
permitted uses as described in Section 15. P paragraphs 2 and 2.a above.
d.
Pruning of tree branches, on the bottom 1/3 of the tree is allowed.
e.
In order to maintain a buffer strip of vegetation, when the removal of storm-
damaged, dead or hazard trees results in the creation of cleared openings, these
openings shall be replanted with native tree species unless existing new tree growth
is present.
Section 15.P.2 does not apply to those portions of public recreational facilities
adjacent to public swimming areas as long as cleared areas are limited to the
minimum area necessary.
f.
In order to maintain the vegetation in the shoreline buffer, clearing or removal of
vegetation for allowed activities, including associated construction and related
equipment operation, within or outside the shoreline buffer, must comply with the
requirements of Section 15.P.2. In order to maintain the vegetation in the shoreline
buffer, clearing or removal of vegetation for allowed activities, including associated
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
31
construction and related equipment operation, within or outside the shoreline buffer,
must comply with the requirements of Section 15.P.2.
3.
At distances greater than one hundred (100) feet, horizontal distance, from a great pond or
a river flowing to a great pond, and seventy-five (75) feet, horizontal distance, from the
normal high-water line of any other water body, tributary stream, or the upland edge of a
wetland, there shall be allowed on any lot, in any ten (10) year period, selective cutting of
not more than forty (40) percent of the volume of trees four (4) inches or more in diameter,
measured 4 1/2 feet above ground level. Tree removal in conjunction with the
development of permitted uses shall be included in the forty (40) percent calculation. For
the purposes of these standards volume may be considered to be equivalent to basal area.
In no event shall cleared openings for any purpose, including but not limited to, principal
and accessory structures, driveways, lawns and sewage disposal areas, exceed in the
aggregate, 25% of the lot area within the shoreland zone or ten thousand (10,000) square
feet, whichever is greater, including land previously cleared. This provision applies to the
portion of a lot within the shoreland zone, including the buffer area.
4.
Legally existing nonconforming cleared openings may be maintained, but shall not be
enlarged, except as allowed by this Ordinance.
5.
Fields and other cleared openings which have reverted to primarily shrubs, trees, or other
woody vegetation shall be regulated under the provisions of Section 15.P.
Q.
Hazard Trees, Storm-Damaged Trees, and Dead Tree Removal.
1. Hazard trees in the shoreland zone may be removed without a permit after consultation with
the Code Enforcement Officer if the following requirements are met:
a.
Within the shoreline buffer, if the removal of a hazard tree results in a cleared opening
in the tree canopy greater than two hundred and fifty (250) square feet, replacement
with native tree species is required, unless there is new tree growth already present.
New tree growth must be as near as practicable to where the hazard tree was removed
and be at least two (2) inches in diameter, measured at four and one half (4.5) feet
above the
ground level. If new growth is not present, then replacement trees
shall consist of native species and be at least four (4) feet in height, and be no less than
two (2) inches in diameter. Stumps may not be removed.
b.
Outside of the shoreline buffer, when the removal of hazard trees exceeds forty (40)
percent of the volume of trees four (4) inches or more in diameter, measured at four
and one half (4.5) feet above ground level in any ten (10) year period, and/or results in
cleared openings exceeding twenty-five (25) percent of the lot area within the
shoreland zone, or ten thousand (10,000) square feet, whichever is greater,
replacement with native tree species is required, unless there is new tree growth
already present. New tree growth must be as near as practicable to where the hazard
tree was removed and be at least two (2) inches in diameter, measured at four and one
half (4.5) feet above the ground level. If new growth is not present, then replacement
trees shall consist of native species and be at least two (2) inches in diameter,
measured at four and one half (4.5) feet above the ground level.
c.
The removal of standing dead trees, resulting from natural causes, is permissible
without the need for replanting or a permit, as long as the removal does not result in
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
32
the creation of new lawn areas, or other permanently cleared areas, and stumps are not
removed. For the purposes of this provision dead trees are those trees that contain no
foliage during the growing season.
d.
The Code Enforcement Officer may require the property owner to submit an
evaluation from a licensed forester or arborist before any hazard tree
can be
removed within the shoreland zone.
e.
The Code Enforcement Officer may require more than a one-for-one replacement for
hazard trees removed that exceed eight (8) inches in diameter measured at four and
one half (4.5) feet above the ground level.
2. Storm-damaged trees in the shoreland zone may be removed without a permit after
consultation with the Code Enforcement Officer if the following requirements are met:
a.
Within the shoreline buffer, when the removal of storm-damaged trees
results in a
cleared opening in the tree canopy greater than two hundred
and fifty (250) square feet,
replanting is not required, but the area shall be required to naturally revegetate, and the
following requirements must be met:
(i)
The area from which a storm-damaged tree is removed does not result in new
lawn areas, or other permanently cleared areas;
(ii) Stumps from the storm-damaged trees may not be removed;
(iii) Limbs damaged from a storm event may be pruned even if they extend
beyond the bottom one-third (1/3) of the tree; and
(iv) If after one growing season, no natural regeneration or regrowth is present,
replanting of native tree seedlings or saplings is required at a density of one
seedling per every eighty (80) square feet of lost canopy.
b.
Outside of the shoreline buffer, if the removal of storm damaged trees exceeds 40% of
the volume of trees four (4) inches or more in diameter, measured at four and one half
(4.5) feet above the ground level in any ten (10) year period, or results, in the aggregate,
in cleared openings exceeding 25% of the lot area within the shoreland zone or ten
thousand (10,000) square feet, whichever is greater, and no natural regeneration occurs
within one growing season, then native tree seedlings or saplings shall be replanted on a
one-for-one basis.
R.
Exemptions to Clearing and Vegetation Removal Requirements
The following activities are exempt from the clearing and vegetation removal standards set forth in
Section 15.P, provided that all other applicable requirements of this Ordinance are complied with, and the
removal of vegetation is limited to that which is necessary:
1 . The removal of vegetation that occurs at least once every two (2) years for the maintenance of
legally existing areas that do not comply with the vegetation standards in this chapter, such as but
not limited to cleared openings in the canopy or fields. Such areas shall not be enlarged, except
as allowed by this section. If any of these areas, due to lack of removal of vegetation every two
(2) years, reverts back to primarily woody vegetation, the requirements of Section 15.P apply;
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
33
2 . The removal of vegetation from the location of allowed structures or allowed uses, when the
shoreline setback requirements of section 15.B are not applicable;
3 . The removal of vegetation from the location of public swimming areas associated with an
allowed public recreational facility;
4 . The removal of vegetation associated with allowed agricultural uses, provided best management
practices are utilized, and provided all requirements of section 15.N are complied with;
5 . The removal of non-native invasive vegetation species, provided the following minimum
requirements are met:
a. If removal of vegetation occurs via wheeled or tracked motorized equipment, the wheeled or
tracked motorized equipment is operated and stored at least twenty-five (25) feet, horizontal
distance, from the shoreline, except that wheeled or tracked equipment may be operated or
stored on existing structural surfaces, such as pavement or gravel;
b. Removal of vegetation within twenty-five (25) feet, horizontal distance, from the shoreline
occurs via hand tools; and
c. If applicable clearing and vegetation removal standards are exceeded due to the removal of
non-native invasive species vegetation, the area shall be revegetated with native species to
achieve compliance.
6. The removal of vegetation associated with emergency response activities conducted by the
Department, the U.S. Environmental Protection Agency, and their agents.
S.
Revegetation Requirements.
When revegetation is required in response to violations of the vegetation standards set forth in Section
15.P, to address the removal of non- native invasive species of vegetation, or as a mechanism to allow for
development that may otherwise not be permissible due to the vegetation standards, including removal of
vegetation in conjunction with a shoreline stabilization project, the revelation must comply with the
following requirements.
1. The property owner must submit a revegetation plan, prepared with and signed by a qualified
professional, that describes revegetation activities and maintenance. The plan must include a
scaled site plan, depicting where vegetation was, or is to be removed, where existing vegetation
is to remain, and where vegetation is to be planted, including a list of all vegetation to be planted.
2. Revegetation must occur along the same segment of shoreline and in the same area where
vegetation was removed and at a density comparable to the pre-existing vegetation, except where
a shoreline stabilization activity does not allow revegetation to occur in the same area and at a
density comparable to the pre-existing vegetation, in which case revegetation must occur along
the same segment of shoreline and as close as possible to the area where vegetation was
removed:
3. If part of a permitted activity, revegetation shall occur before the expiration of the permit. If the
activity or revegetation is not completed before the expiration of the permit, a new revegetation
plan shall be submitted with any renewal or new permit application.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
34
4. Revegetation activities must meet the following requirements for trees and saplings:
a. All trees and saplings removed must be replaced with native noninvasive species;
b. Replacement vegetation must at a minimum consist of saplings;
c. If more than three (3) trees or saplings are planted, then at least three (3) different species
shall be used;
d. No one species shall make up 50% or more of the number of trees and saplings planted;
e. If revegetation is required for a shoreline stabilization project, and it is not possible to plant
trees and saplings in the same area where trees or saplings were removed, then trees or
sapling must be planted in a location that effectively reestablishes the screening between the
shoreline and structures; and
f.
A survival rate of at least eighty (80) percent of planted trees or saplings is required for a
minimum five (5) years period.
5. Revegetation activities must meet the following requirements for woody vegetation and other
vegetation under three (3) feet in height:
a. All woody vegetation and vegetation under three (3) feet in height must be replaced with
native noninvasive species of woody vegetation and vegetation under three (3) feet in height
as applicable;
b. Woody vegetation and vegetation under three (3) feet in height shall be planted in quantities
and variety sufficient to prevent erosion and provide for effective infiltration of stormwater;
c. If more than three (3) woody vegetation plants are to be planted, then at least three (3)
different species shall be planted;
d. No one species shall make up 50% or more of the number of planted woody vegetation
plants; and
e. Survival of planted woody vegetation and vegetation under three feet in height must be
sufficient to remain in compliance with the standards contained within this Ordinance for
minimum of five (5) years
6. Revegetation activities must meet the following requirements for ground vegetation and ground
cover:
a. All ground vegetation and ground cover removed must be replaced with native herbaceous
vegetation, in quantities and variety sufficient to prevent erosion and provide for effective
infiltration of stormwater;
b. Where necessary due to a lack of sufficient ground cover, an area must be supplemented with
a minimum four (4) inch depth of leaf mulch and/or bark mulch to prevent erosion and
provide for effective infiltration of stormwater; and
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
35
c. Survival and functionality of ground vegetation and ground cover must be sufficient to
remain in compliance with the standards contained within this chapter for minimum of five
(5) years.
T.
Erosion and Sedimentation Control
1.
All activities which involve filling, grading, excavation or other similar activities which
result in unstabilized soil conditions and which require a permit shall require a written soil
erosion and sedimentation control plan. The plan shall be submitted to the permitting
authority for approval and shall include, where applicable, provisions for:
a.
Mulching and revegetation of disturbed soil.
b.
Temporary runoff control features such as hay bales, silt fencing or diversion
ditches.
c.
Permanent stabilization structures such as retaining walls or rip-rap.
2.
In order to create the least potential for erosion, development shall be designed to fit with
the topography and soils of the site. Areas of steep slopes where high cuts and fills may be
required shall be avoided wherever possible, and natural contours shall be followed as
closely as possible.
3.
Erosion and sedimentation control measures shall apply to all aspects of proposed project
involving land disturbance, and shall be in operation during all stages of the activity. The
amount of exposed soil at every phase of construction shall be minimized to reduce the
potential for erosion.
4.
Any exposed ground area shall be temporarily or permanently stabilized within one (1)
week from the time it was last actively worked, by use of rip-rap, sod, seed, and mulch, or
other effective measures. In all cases permanent stabilization shall occur within nine (9)
months of the initial date of exposure. In addition:
a.
Where mulch is used, it shall be applied at a rate of at least one (1) bale per five
hundred (500) square feet and shall be maintained until a catch of vegetation is
established.
b.
Anchoring the mulch with netting, peg and twine or other suitable method may be
required to maintain the mulch cover.
c.
Additional measures shall be taken where necessary in order to avoid siltation into
the water. Such measures may include the use of staked hay bales and/or silt fences.
5.
Natural and man-made drainage ways and drainage outlets shall be protected from erosion
from water flowing through them. Drainageways shall be designed and constructed in
order to carry water from a twenty-five (25) year storm or greater, and shall be stabilized
with vegetation or lined with rip-rap.
U.
Soils
All land uses shall be located on soils in or upon which the proposed uses or structures can be
established or maintained without causing adverse environmental impacts, including severe
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
36
erosion, mass soil movement, improper drainage, and water pollution, whether during or after
construction. Proposed uses requiring subsurface waste disposal, and commercial or industrial
development and other similar intensive land uses, shall require a soils report based on an on-site
investigation and be prepared by state-certified professionals. Certified persons may include
Maine Certified Soil Scientists, Maine Registered Professional Engineers, Maine State Certified
Geologists and other persons who have training and experience in the recognition and evaluation
of soil properties. The report shall be based upon the analysis of the characteristics of the soil
and surrounding land and water areas, maximum ground water elevation, presence of ledge,
drainage conditions, and other pertinent data which the evaluator deems appropriate. The soils
report shall include recommendations for a proposed use of counteract soil limitations where they
exist.
V.
Water Quality
1.
No activity shall deposit on or into the ground or discharge to the waters of the State any
pollutant that, by itself or in combination with other activities or substances will impair
designated uses or the water classification of the water body tributary stream or wetland.
The washing, bathing, or cleaning of humans, animals, or objects with soaps, detergents, or
cleaning agents shall be prohibited in water bodies or in areas adjacent to water bodies if
wash water can enter the surface water without absorption into the soils.
2.
One of the following methods of phosphorus mitigation must be employed if the footprint
of any structure is enlarged within the setback area adjacent to a Great Pond.
a.
The existing undisturbed natural wooded buffer strip between the structure and the
water body shall be at least 50 feet in depth; or
b.
A 50 foot natural wooded buffer strip shall be created by allowing a 50-foot strip to
revert to natural vegetation. Woody vegetation shall be planted if lacking; or
c.
An infiltration system designed to accommodate the runoff from the entire structure
that would be generated by a 24-hour two-inch rainfall and approved by the Code
Enforcement Officer shall be constructed.
3.
Wells may be located within the setback area if all of the following provisions are met:
a.
The access corridor for equipment does not exceed 20 feet in width and must follow
any existing or proposed footpath. The Code Enforcement Officer may expand this
20-foot limit to the minimum extent needed where access is difficult.
b.
All slag shall be removed from the ground, and no sedimentation from erosion shall
enter any adjacent water body.
c.
All areas not covered by the footpath shall be stabilized immediately and fully
revegetated within nine months.
4.
No provisions of this Ordinance shall prohibit the revegetation or stabilization of a
disturbed area if a stabilization plan is filed with and approved by the Code Enforcement
Officer. The use of fertilizer containing phosphorus within the buffer area is prohibited,
except as part of an approved stabilization plan.
W.
Phosphorous Loading Rates
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
37
All land uses requiring Planning Board approval within the Shoreland Zone adjacent to a Great
Pond or river or stream flowing to a Great Pond, shall limit phosphorus export from the site
based on approval of one of the following methods of phosphorus control:
1.
Point System
The Planning Board may issue a permit if the applicant meets or exceeds thirty (30) points
based on the following schedule:
a.
10 points for correcting an existing erosion problem on the site
b.
10 points for a clearing limitation of 15,000 square feet and less
c.
15 points for a clearing limitation of 10,000 square feet and less
d.
15 points for the installment of rock-lined drip edges or other infiltration systems to
serve the new construction
e.
20 points for a 50-foot wide buffer located downslope of the developed area
f.
25 points for a 75-foot wide buffer located downslope of the developed area
g.
30 points for a 100-foot wide buffer located downslope of the developed area
Special Exemptions: Additions to non-conforming structures must meet or exceed a total
of twenty-five (25) points and conform with Section S, of this ordinance (Water Quality),
Subsection 2.
2.
Technical Analysis
The applicant does not exceed the allotted phosphorus export to the water body based on
the phosphorus loading schedules established in Table 1, Section 5 of Waterford=s Site
Plan Review and in calculated in accordance with Stormwater Management for Maine
(Maine Department of Environmental Protection et al., January 2006 with revisions as
amended).
X.
Archaeological Sites
Any proposed land use activity involving structural development or soil disturbance on or
adjacent to sites listed on, or eligible to be listed on the National Register of Historic Places, as
determined by the permitting authority shall be submitted by the applicant to the Maine Historic
Preservation Commission for review and comment, at least twenty (20) days prior to action being
taken by the permitting authority. The permitting authority shall consider comments received
from the Commission prior to rendering a decision on the application.
Y.
Recreational Trails
Recreational trails constructed for or created by the repeated passage of motorized vehicles shall
meet the Roads and Driveways standards, including ATV trails.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
38
Recreational trails must be designed and constructed to shed water, avoid erosion, and minimize
channelized flow to the water body, tributary stream or wetland.
Recreational trails shall be designed and constructed such that soil erosion will be prevented;
such prevention measures may include steps, water bars, drainage dips, and minor side-sloping of
trails, in addition to any necessary lining of the trail with erosion control mulch.
Recreational trails must meet the structure setback; except for primitive trails and trail spurs as
provided below; and except for structural water crossings that are no more than four (4) feet in
width, which are necessary in wet, rocky or unstable areas.
Primitive trails must meet the structure setback to the greatest practical extent, except for
portions constructed over existing structural development such as pavement, concrete, and non-
vegetated gravel areas.
Primitive trails and trail spurs shall be constructed using hand tools only, including power hand
tools.
Trail spurs shall be limited to one per lot of record where a water access footpath allowed under
the Clearing of Vegetation standards (Section 15.P.2.a) does not exist.
Section 16.
Administration
A.
Administering Bodies and Agent
1.
Code Enforcement Officer
2.
Board of Appeals
3.
Planning Board
B.
Permit Required
1.
After the effective date of this Ordinance no person shall, without first obtaining a permit,
engage in any activity or use of land or structure requiring a permit in the district in which
such activity or use would occur; or expand, change, or replace an existing use or
structure; or renew a discontinued nonconforming use. A person who is issued a permit
pursuant to this Ordinance shall have a copy of the permit on site while the work
authorized by the permit is preformed.
2.
A permit is not required for an archaeological excavation as long as the excavation is
conducted by an archaeologist listed on the State Historic Preservation Officer's level 1 or
level 2 approved list, and unreasonable erosion and sedimentation is prevented by means
of adequate and timely temporary and permanent stabilization measures.
3.
Any permit required by this Ordinance shall be in addition to any other permit required by
other law or ordinance.
C.
Permit Application
1.
Every applicant for a permit shall submit a written application, including a scaled site plan,
on a form provided by the municipality, to the appropriate official (as indicated in Section
14). An application for a permit shall be accompanied by a non-refundable fee, of $25.00
plus $1.00 per $1,000.00 of the estimated cost including materials and labor over
$2,000.00. This application fee shall be made by cash or check, payable to the Town. The
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
39
selectmen shall have the authority to revise this fee from time to time after conducting a
public hearing
2.
All applications shall be signed by the owner or owners of the property or other person
authorizing the work, certifying that the information in the application is complete and
correct. If the person signing the application is not the owner or lessee of the property then
that person shall submit a letter of authorization from the owner or lessee.
3.
All applications shall be dated, and the Code Enforcement Officer or Planning Board, as
appropriate, shall note upon each application the date and time of its receipt.
4.
A valid plumbing permit or a completed application for the plumbing permit, including the
site evaluation approved by the Plumbing Inspector, shall be submitted whenever the
nature of the proposed structure would require the installation of a subsurface sewage
disposal system.
5.
Any application for an after the fact permit shall be accompanied by a non-refundable fee
double that required in Section C.1. above.
6.
When an excavation contractor will perform an activity that requires or results in more
than one (1) cubic yard of soil disturbance, the person responsible for management of
erosion and sedimentation control practices at the site must be certified in erosion control
practices by the Maine Department of Environmental Protection. This person must be
present at the site each day earthmoving activity occurs for a duration that is sufficient to
ensure that proper erosion and sedimentation control practices are followed. This is
required until erosion and sedimentation control measures have been installed, which will
either stay in place permanently or stay in place until the area is sufficiently covered with
vegetation necessary to prevent soil erosion. The name and certification number of the
person who will oversee the activity causing or resulting in soil disturbance shall be
included on the permit application. This requirement does not apply to a person or firm
engaged in agriculture or timber harvesting if best management practices for erosion and
sedimentation control are used; and municipal, state and federal employees engaged in
projects associated with that employment.
D.
Procedure for Administering Permits
Within thirty-five (35) days of the date of receiving a written application, the Planning Board or
Code Enforcement Officer, as indicated in Section 14, shall notify the applicant in writing either
that the application is a complete application, or if the application is incomplete, that specified
additional material is needed to make the application complete. The Planning Board or Code
Enforcement Officer, as appropriate, shall approve, approve with conditions, or deny all permit
applications in writing within thirty-five (35) days of receiving a completed application.
However, if the Planning Board has a waiting list of applications, a decision on the application
shall occur within thirty-five (35) days of the public hearing, if one is held. Permits shall be
approved if the proposed use or structure is found to be in conformance with the purposes and
provisions of this Ordinance.
The applicant shall have the burden of proving that the proposed land use activity is in
conformity with the purposes and provisions of this Ordinance.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
40
After the submission of a complete application to the Planning Board, the Board shall approve an
application or approve it with conditions if it makes a positive finding based on the information
presented that the proposed use:
1.
Will maintain safe and healthful conditions;
2.
Will not result in water pollution, erosion, or sedimentation to surface waters;
3.
Will adequately provide for the disposal of all wastewater;
4.
Will not have an adverse impact on spawning grounds, fish, aquatic life, bird or
other wildlife habitat;
5.
Will conserve shore cover and visual, as well as actual, points of access to inland
waters;
6.
Will protect archaeological and historic resources as designated in the
comprehensive plan;
7.
Will avoid problems associated with flood plain development and use; and
8.
Is in conformance with the provisions of Section 15, Land Use Standards.
If a permit is either denied or approved with conditions, the reasons as well as conditions shall be
stated in writing. No approval shall be granted for an application involving a structure if the
structure would be located in an unapproved subdivision or would violate any other local
ordinance or regulation of any State law which the municipality is responsible for enforcing.
E.
Independent Review and Advice
1.
Professional Services. The Planning Board may require that an appropriate professional or
consultant review one or more aspects of an application for compliance or noncompliance,
with this Ordinance and to advise the Board.
The professional or consultant shall first estimate the cost of such review and the applicant
shall deposit, with the Town, the full estimated cost, which the Town shall place in an
escrow account. The Town shall pay the professional or consultant from the escrow
account and reimburse the applicant if funds remain after payment.
2.
Additional Studies. The Planning Board may require the applicant to undertake any study
which it deems reasonable and necessary to demonstrate and ensure that the requirements
of the Ordinance are met. The costs of such studies shall be borne by the applicant.
F.
Expiration of Permit
Following the issuance of a permit, if no substantial start is made in construction or in the use of
the property within one year of the date of the permit, the permit shall lapse and become void.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
41
G.
Financial Guarantee
Prior to final approval of any plan, the Planning Board may require the applicant to post a bond,
letter of credit, escrow agreement, or other financial guarantee acceptable to the Board, in such
amount as is reasonably necessary, to ensure completion of all improvements and in such form as
is approved by the Board and the Town Selectmen.
The Town and its agents shall have access to the site at all times to review the progress of the
work and shall have the authority to review all records and documents related to the project.
H.
Installation of Public Utility Service
No public utility, water district, sanitary district or any utility company of any kind may install
services to any new structure located in the Shoreland Zone, unless written authorization attesting
to the validity and currency of all local permits required under this or any previous ordinance, has
been issued by the appropriate Town officials or other written arrangements have been made
between the Town officials and the utility. Following installation services, the company or
district shall forward written authorization to the Town officials, indicating that installation has
been completed.
I.
Special Exceptions
In addition to the criteria specified in Section 16.D above, excepting structure setback
requirements, the Planning Board may approve a permit for a single family residential structure
in a Resource Protection District provided that the applicant demonstrates that all of the
following conditions are met:
1.
There is no location on the property, other than a location within the Resource Protection
District, where the structure can be built.
2.
The lot on which the structure is proposed is undeveloped and was established and
recorded in the registry of deeds of the county in which the lot is located before the
adoption of the Resource Protection District.
3.
All proposed buildings, sewage disposal systems and other improvements are:
a.
Located on natural ground slopes of less than 20%; and
b.
Located outside the floodway of the 100-year flood-plain along rivers and
artificially formed great ponds along rivers and outside the velocity zone in areas
subject to tides, based on detailed flood insurance studies and as delineated on the
Federal Emergency Management Agency's Flood Boundary and Floodway Maps
and Flood Insurance Rate Maps; all buildings, including basements, are elevated at
least one foot above the 100-year flood-plain elevation; and the development is
otherwise in compliance with any applicable municipal flood-plain ordinance.
If the floodway is not shown on the Federal Emergency Management Agency Maps,
it is deemed to be 1/2 the width of the 100-year flood-plain.
4.
The total footprint, including cantilevered or similar overhanging extensions, of all
principal and accessory structures is limited to a maximum of 1,500 square feet. This
limitation shall not be altered by variance.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
42
5.
All structures, except functionally water-dependent structures, are set back from the
normal high-water line of a water body, tributary stream or upland edge of a wetland to the
greatest practical extent, but not less than 100 feet, horizontal distance. In determining the
greatest practical extent, the Planning Board shall consider the depth of the lot, the slope of
the land, the potential for soil erosion, the type and amount of vegetation to be removed,
the proposed building site's elevation in regard to the flood-plain, and its proximity to
moderate-value and high-value wetlands.
J.
Appeals
1.
Powers and Duties of the Board of Appeals. The Board of Appeals shall have the
following powers:
a.
Administrative Appeals: To hear and decide administrative appeals, on an appellate
basis, where it is alleged by an aggrieved party that there is an error in any order,
requirement, decision, or determination made by, or failure to act by, the Planning
Board in the administration of this Ordinance; and to hear and decide administrative
appeals on a de novo basis where it is alleged by an aggrieved party that there is an
error in any order, requirement, decision or determination made by, or failure to act
by, the Code Enforcement Officer in his or her review of and action on a permit
application under this Ordinance. Any order, requirement, decision or determination
made, or failure to act, in the enforcement of this ordinance is not appealable to the
Board of Appeals.
b.
Variance Appeals: To authorize variances upon appeal, within the limitations set
forth in this Ordinance.
2.
Variance Appeals. Variances may be granted only under the following conditions:
a.
Variances may be granted only from dimensional requirements including, but not
limited to, lot width, structure height, percent of lot coverage, and setback
requirements.
b.
Variances shall not be granted for establishment of any uses otherwise prohibited by
this Ordinance.
c.
The Board shall not grant a variance unless it finds that:
1)
The proposed structure or use would meet the provisions of Section 15 except
for the specific provision which has created the non-conformity and from
which relief is sought; and
2)
The strict application of the terms of this Ordinance would result in undue
hardship. The term "undue hardship" shall mean:
a)
That the land in question cannot yield a reasonable return unless a
variance is granted;
b)
That the need for a variance is due to the unique circumstances of the
property and not to the general conditions in the neighborhood;
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
43
c)
That the granting of a variance will not alter the essential character of the
locality; and
d)
That the hardship is not the result of action taken by the applicant or a
prior owner.
d.
Notwithstanding Section 16.K.c.2) above, the Board of Appeals or the codes
enforcement officer if authorized in accordance with 30-A MRSA section
4353-A may grant a variance to an owner of a residential dwelling for the
purpose of making that dwelling accessible to a person with a disability who
resides in or regularly uses the dwelling. The board shall restrict any variance
granted under this subsection solely to the installation of equipment or the
construction of structures necessary for access to or egress from the dwelling
by the person with the disability. The board may impose conditions on the
variance, including limiting the variance to the duration of the disability or to
the time that the person with the disability lives in the dwelling. The term
"structures necessary for access to or egress from the dwelling" shall include
railing, wall or roof systems necessary for the safety or effectiveness of the
structure. Any permit issued pursuant to this subsection is subject to
Sections 16.J.2.f and 16.J.4.b.4 below.)
e.
The Board of Appeals shall limit any variances granted as strictly as possible in
order to ensure conformance with the purposes and provisions of this Ordinance to
the greatest extent possible, and in doing so may impose such conditions to a
variance as it deems necessary. The party receiving the variance shall comply with
any conditions imposed.
f.
A copy of each variance request, including the application and all supporting
information supplied by the applicant, shall be forwarded by the municipal officials
to the Commissioner of the Department of Environmental Protection at least twenty
(20) days prior to action by the Board of Appeals. Any comments received from the
Commissioner prior to the action by the Board of Appeals shall be made part of the
record and shall be taken into consideration by the Board of Appeals.
3.
Administrative Appeals
When the Board of Appeals reviews a decision of the Code Enforcement Officer the Board
of Appeals shall hold a "de novo" hearing. At this time the Board may receive and
consider new evidence and testimony, be it oral or written. When acting in a "de novo"
capacity the Board of Appeals shall hear and decide the matter afresh, undertaking its own
independent analysis of evidence and the law, and reaching its own decision.
When the Board of Appeals hears a decision of the Planning Board, it shall hold an
appellate hearing, and may reverse the decision of the Planning Board only upon finding
that the decision was contrary to specific provisions of the Ordinance or contrary to the
facts presented to the Planning Board. The Board of Appeals may only review the record
of the proceedings before the Planning Board. The Board Appeals shall not receive or
consider any evidence which was not presented to the Planning Board, but the Board of
Appeals may receive and consider written or oral arguments. If the Board of Appeals
determines that the record of the Planning Board proceedings are inadequate, the Board of
Appeals may remand the matter to the Planning Board for additional fact finding.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
44
4.
Appeal Procedure
a.
Making an Appeal
1)
An administrative or variance appeal may be taken to the Board of Appeals by
an aggrieved party from any decision of the Code Enforcement Officer or the
Planning Board, except for enforcement-related matters as described in
Section 16.K1.a above. Such an appeal shall be taken within thirty (30) days
of the date of the official, written decision appealed from, and not otherwise,
except that the Board, upon a showing of good cause, may waive the thirty
(30) day requirement.
2)
Applications for appeals shall be made by filing with the Board of Appeals a
written notice of appeal which includes:
a)
A concise written statement indicating what relief is requested and why
the appeal or variance should be granted.
b)
A sketch drawn to scale showing lot lines, location of existing buildings
and structures and other physical features of the lot pertinent to the
relief sought.
3)
Upon receiving an application for an administrative appeal or a variance, the
Code Enforcement Officer or Planning Board, as appropriate, shall transmit to
the Board of Appeals all of the papers constituting the record of the decision
appealed from.
4)
The Board of Appeals shall hold a public hearing on an administrative appeal
or a request for a variance within thirty-five (35) days of its receipt of a
complete written application, unless this time period is
extended by the
parties.
b.
Decision by Board of Appeals
1)
A majority of the full voting membership of the Board shall constitute a
quorum for the
purpose of deciding an appeal.
2)
The person filing the appeal shall have the burden of proof.
3)
The Board shall decide all administrative appeals and variance appeals within
thirty five (35) days after the close of the hearing, and shall issue a written
decision on all appeals.
4)
The Board of Appeals shall state the reasons and basis for its decision,
including a statement of the facts found and conclusions reached by the
Board. The Board shall cause written notice of its decision to be mailed or
hand-delivered to the applicant and to the Department of Environmental
Protection within seven (7) days of the Board's decision. Copies of written
decisions of the Board of Appeals shall be given to the Planning Board, Code
Enforcement Officer, and the municipal officers.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
45
5)
Appeal to Superior Court. Except as provided by 30-A M.R.S.A. section
2691(3)(F), any aggrieved party who participated as a party during the
proceedings before the Board of Appeals may take an appeal to Superior
Court in accordance with State laws within forty-five (45) days from the date
of any decision of the Board of Appeals.
6)
Reconsideration. In accordance with 30-A M.R.S.A. section 2691(3)(F), the
Board of Appeals may reconsider any decision within forty-five (45) days of
its prior decision. A request to the Board to reconsider a decision must be
filed within ten (10) days of the decision that is being reconsidered. A vote to
reconsider and the action taken on that reconsideration must occur and be
completed within forty-five (45) days of the date of the vote on the original
decision. Reconsideration of a decision shall require a positive vote of the
majority of the Board members originally voting on the decision, and proper
notification to the landowner, petitioner, planning board, code enforcement
officer, and other parties of interest, including abuttors and those who testified
at the original hearing(s). The Board may conduct additional hearings and
receive additional evidence and testimony.
Appeal of a reconsidered decision to Superior Court must be made within
fifteen (15) days after the decision on reconsideration.
K.
Enforcement
1.
Nuisances
Any violation of this Ordinance shall be deemed to be a nuisance.
2.
Code Enforcement Officer
a.
It shall be the duty of the Code Enforcement Officer to enforce the provisions of this
Ordinance. If the Code Enforcement Officer shall find that any provision of this
Ordinance is being violated, he or she shall notify in writing the person responsible
for such violation, indicating the nature of the violation and ordering the action
necessary to correct it, including discontinuance of illegal use of land building or
structures, or work being done, removal of illegal buildings or structures, and
abatement of nuisance conditions. A copy of such notices shall be submitted to the
municipal officers and be maintained as a permanent record.
b.
The Code Enforcement Officer shall conduct on-site inspections to insure
compliance with all applicable laws and conditions attached to permit approvals.
The Code Enforcement Officer shall also investigate all complaints of alleged
violations of this Ordinance.
c.
The Code Enforcement Officer shall keep a complete record of all essential
transactions of the office, including applications submitted, permits granted or
denied, variances granted or denied, revocation actions, revocation of permits,
appeals, court actions, violations investigated, violations found, and fees collected.
3.
Legal Actions
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
46
a.
When the above action does not result in the correction or abatement of the violation
or nuisance condition, the Municipal Officers, upon notice from the Code
Enforcement Officer, are hereby directed to institute any and all actions and
proceedings, either legal or inequitable, including seeking injunctions of violations
and the imposition of fines, that may be appropriate or necessary to enforce the
provisions of this Ordinance in the name of the municipality.
b.
The Town Officers, or their authorized agent, are hereby authorized to enter into
administrative consent agreements for the purpose of eliminating violations of this
Ordinance and recovering fines without Court Action. Such agreements shall not
allow an illegal structure or use to continue unless there is clear and convincing
evidence that the illegal structure or use was constructed or conducted as a direct
result of erroneous advice given by an authorized municipal official and there is no
evidence that the owner acted in bad faith, or unless the removal of the structure or
use will result in a threat or hazard to public health and safety or will result in
substantial environmental damage.
Any approved administrative consent agreement shall be recorded in the Oxford
County Registry of Deeds within thirty (30) days of its signing by the violator. In
addition a one copy shall be attached to the assessment records and one copy
forwarded to the Chair of the Planning Board.
4.
Fines
Any person, including but not limited to a landowner, a landowner=s agent or a contractor,
who violates any provision or requirement of this Ordinance shall, be penalized in
accordance with Title 30-A, Maine Revised Statutes Annotated, Section 4452.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
47
Section 17.
Definitions
Accessory structure or use - a use or structure which is incidental and subordinate to the principal use or
structure. Accessory uses, when aggregated shall not subordinate the principal use of the lot. A deck or
similar extension of the principal structure or a garage attached to the principal structure by a roof or a
common wall is considered part of the principal structure.
Acre - 43,560 square feet.
Agriculture - the production, keeping or maintenance for sale or lease, of plants and/or animals, including but
not limited to: forages and sod crops; grains and seed crops; dairy animals and dairy products; poultry and
poultry products; livestock; fruits and vegetables; and ornamental and green house products. Agriculture does
not include forest management and timber harvesting activities.
Aggrieved party - an owner of land whose property is directly or indirectly affected by the granting or denial
of a permit or variance under this Ordinance; a person whose land abuts land for which a permit or variance
has been granted; or any other person or group of persons who have suffered particularized injury as a result
of the granting or denial of such permit variance.
Appurtenant Structure to Recreation Vehicle - A factory-manufactured rigid metal or vinyl enclosure, with
the dimensions not exceeding eight feet in width nor the length of the recreational vehicle, and designed for
use with the recreational vehicle.
Aquaculture - the growing or propagation of harvestable freshwater, plant or animal species.
Basal area- the area of cross-section of a tree stem at 4 ½ feet above ground level and inclusive of bark.
Basement - any portion of a structure with a floor-to-ceiling height of 6 feet or having more than 50% of its
volume below the existing ground level.
Bed and Breakfast - A private home in which one or rooms are rented and breakfast is provided to those
renting a room.
Boat-Launching Facility - a facility designed primarily for the launching and landing of watercraft, and
which may include an access ramp, docking area, and parking spaces for vehicles and trailers.
Bureau of Forestry - State of Maine Department of Agriculture, Conservation, and Forestry, Bureau of
Forestry.
Campground - any area or tract of land to accommodate two (2) or more parties in temporary living quarters,
including, but not limited to tents, recreational vehicles or other shelters.
Canopy- the more or less continuous cover formed by tree crowns in wooded areas.
Commercial use - the use of lands, buildings, or structures, other than a Ahome occupation,@ defined below,
the intent and result of which activity is the production of income from the buying or selling of goods and/or
services, exclusive of rental of residential buildings and/or dwelling units. Commercial use does not include
timber harvesting or the commercial recreational use dependent upon and associated with the waterbody.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
48
Cross-sectional area - the cross-sectional area of a stream or tributary stream channel is determined by
multiplying the stream or tributary stream channel width by the average stream or tributary stream channel
depth. The stream or tributary stream channel width is the straight line distance from the normal high-water
line on one side of the channel to the normal high-water line on the opposite side of the channel. The average
stream or tributary stream channel depth is the average of the vertical distances from a straight line between
the normal high-water lines of the stream or tributary stream channel to the bottom of the channel.
Development- a change in land use involving alteration of land, water or vegetation, or the addition or
alteration of structures or other construction not naturally occurring.
DBH- the diameter of a standing tree measured 4.5 feet from ground level.
Dimensional requirements - numerical standards relating to spatial relationships including but not limited to
setback, lot area, shore frontage and height.
Disability - Any disability, infirmity, malformation, disfigurement, congenital defect or mental condition
caused by bodily injury, accident, disease, birth defect, environmental conditions or illness; and also includes
the physical or mental condition of a person which constitutes a substantial handicap as determined by a
psychologist as well as any other health or sensory impairment which requires special education, vocational
rehabilitation or related services.
Disruption of shoreline integrity - the alteration of the physical shape, properties, or condition of a shoreline
at any location by timber harvesting and related activities. A shoreline where shoreline integrity has been
disrupted is recognized by compacted, scarified and/or rutted soil, an abnormal channel or shoreline cross-
section, and in the case of flowing waters, a profile and character altered from natural conditions.
Discontinued Use - The cessation or the stopping of an activity.
Driveway - a vehicular access-way less than five-hundred (500) feet in length serving two single-family
dwellings or one two-family dwelling, or less.
Emergency operations - operations conducted for the public health, safety or general welfare, such as
protection of resources from immediate destruction or loss, law enforcement, and operations to rescue human
beings, property and livestock from the threat of destruction or injury.
Essential services - gas, electrical or communication facilities; steam, fuel, electric power or water
transmission or distribution lines, towers and related equipment; telephone cables or lines, poles and related
equipment; gas, oil, water, slurry or other similar pipelines; municipal sewage lines, collection or supply
systems; and associated storage tanks. Such systems may include towers, poles, wires, mains, drains, pipes,
conduits, cables, fire alarms and police call boxes, traffic signals, hydrants and similar accessories, but shall
not include service drops or buildings which are necessary for the furnishing of such services.
Expansion of a structure - an increase in the footprint of a structure, including all extensions such as, but not
limited to: attached decks, garages, porches and greenhouses.
Expansion of use - the addition of one or more months to a use's operating season; or the use of more
footprint of a structure or ground area devoted to a particular use.
Family - one or more persons occupying a premises and living as a single housekeeping unit.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
49
Floor area - the sum of the horizontal areas of the floor(s) of a structure enclosed by exterior walls.
Footprint- the entire area of ground covered by the structure(s) on a lot, including but not limited to
cantilevered or similar overhanging extensions, as well as unenclosed structures, such as patios and decks.
Forest management activities - timber cruising and other forest resource evaluation activities, pesticide or
fertilizer application, management planning activities, timber-stand improvement, pruning, regeneration of
forest stands, and other similar or associated activities, exclusive of timber harvesting and the construction,
creation or maintenance of roads.
Forested wetlands - a freshwater wetland dominated by woody vegetation that is six (6) meters tall
(approximately twenty (20) feet) or taller.
Forest Stand - a contiguous group of trees sufficiently uniform in age class distribution, composition, and
structure, and growing on a site of sufficiently uniform quality, to be a distinguishable unit.
Foundation - the supporting substructure of a building or other structure, excluding wood sills and post
supports, but including basements, slabs, frostwalls or other base consisting of concrete, block, brink or
similar material.
Freshwater wetland - freshwater swamps, marshes, bogs and similar areas, other than forested wetlands,
which are:
1. of ten (10) or more contiguous acres; or of less than ten (10) contiguous acres and adjacent to a
surface water body, excluding any river, stream or brook such that in a natural state, the combined
surface areas is in excess of ten (10) acres; and
2. inundated or saturated by surface or groundwater at a frequency and for a duration sufficient to
support, and which under normal circumstances do support, a prevalence of wetland vegetation
typically adapted for life in saturated soils.
Freshwater wetlands may contain small stream channels or inclusions of land that do not conform to the
criteria of this definition.
For the purposes of this Ordinance, the upland edge (the shoreline) of a freshwater wetland is defined as the
boundary line at which the hydrological and biological characteristics in item 2 above no longer occur, or
where the wetland becomes a forested wetland.
Functionally water-dependent uses - those uses that require, for their primary purpose, location on
submerged lands or that require direct access to, or location in, inland waters and which cannot be located
away from these waters. The uses include, but are not limited to commercial and recreational fishing and
boating facilities, fish storage and retail and wholesale fish marketing facilities, waterfront dock facilities and
boat building facilities, navigation aides, basins and channels, shoreland structures necessary for erosion
control, industrial uses dependent upon water-borne transportation or requiring large volumes of cooling or
processing water and which cannot reasonably be located or operated at an inland site and uses that provide
general public access to inland waters. Recreational boat storage buildings are not considered to be a
functionally water-dependent use.
Great pond - any inland body of water which in a natural state has a surface area in excess of ten (10) acres,
and any inland body of water artificially formed or increased which has a surface area in excess of thirty (30)
acres except for the purposes of this Ordinance, where the artificially formed or increased inland body of
water is completely surrounded by land held by a single owner.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
50
Ground cover- small plants, fallen leaves, needles and twigs, and partially decayed organic matter of the
forest floor.
Harvest Area - the area where timber harvesting and related activities, including the cutting of trees,
skidding, yarding, and associated road construction take place. The area affected by a harvest encompasses
the area within the outer boundaries of these activities, excepting unharvested areas greater than 10 acres
within the area affected by a harvest.
Hazard tree - a tree with a structural defect, combination of defects, or disease resulting in a structural defect
that under the normal range of environmental conditions at the site exhibits a high probability of failure and
loss of a major structural component of the tree in a manner that will strike a target. A normal range of
environmental conditions does not include meteorological anomalies, such as, but not limited to: hurricanes;
hurricane-force winds; tornados; microbursts; or significant ice storm events.
Hazard trees also include those trees that pose a serious and imminent risk to bank stability. A target is the
area where personal injury or property damage could occur if the tree or a portion of the tree fails. Targets
include roads, driveways, parking areas, structures, campsites, and any other developed area where people
frequently gather and linger.
Height of a structure - the vertical distance between the mean original grade at the downhill side of the
structure and the highest point of the structure, excluding chimneys, steeples, antennas and similar
appurtenances that have no floor area.
Home occupation - An occupation or profession which is carried on in no more than 1,000 square feet of a
dwelling unit or accessory structure or thirty-three percent (33%) of the floor area of a detached, single-family
dwelling unit and which does not change the character thereof (by way of illustration and not of limitation, the
term Ahome occupation@ shall include such items as breads, cookies, or preserves, rugs, birdhouses, fishing
flies, and quilts). The term Ahome occupation@ shall include both professional and personal services.
A retail sales outlet does not qualify as a Ahome occupation@ unless the item sold is a product of the owner=s
labor (e.g., manufactured, produced, created, or grown).
Increase in the non-conformity of a structure - any change in a structure or property which causes further
deviation from the dimensional standard(s) creating the non-conformity such as, but not limited to, reduction
in water body, tributary stream or wetland setback distance, increase in lot coverage, or increase in height of a
structure.
Property changes or structure expansions which either meet the dimensional standard or which cause no
further increase in the linear extent of the non-conformance of the existing structure shall not be considered
to increase the non-conformity. For example, there is no increase in non-conformity with the setback
requirement for water bodies, wetlands, or tributary streams if the expansion extends no further into the
required setback area than does any portion of the existing non-conforming structure. Hence, a structure may
be expanded laterally provided that the expansion extends no closer to the water body, tributary stream or
wetland than the closest portion of the existing structure from that water body, tributary stream or wetland.
Included in this allowance are expansions which in-fill irregularly shaped structures.
Individual private campsite - an area of land which is not associated with a campground, but which is
developed for repeated camping by only one group not to exceed ten (10) individuals and which involves site
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
51
improvements which may include but not be limited to gravel pads, parking areas, fire places, or ten
platforms.
Industrial - the assembling, fabrication, finishing, manufacturing, packaging or processing of goods, or the
extraction of minerals.
Institutional - A building devoted to some public, governmental, educational, charitable, medical or similar
purpose.
Land Management Road - a route or track consisting of a bed of exposed mineral soil, gravel, or other
surfacing materials constructed for, or created by, the passage of motorized vehicles and used primarily for
timber harvesting and related activities, including associated log yards, but not including skid trails or skid
roads.
Licensed Forester - a forester licensed under 32 M.R.S.A. Chapter 76.
Lot - an area of land in one ownership, or one leasehold, with ascertainable boundaries established by deed or
instrument of record, or a segment of land ownership defined by lot boundary lines on a land subdivision plan
duly approved by the Planning Board and recorded in the County Registry of Deeds.
Lot area - the area of land enclosed within the boundary lines of a lot, minus land below the normal high-
water line of a water body or upland edge of a wetland and areas beneath roads serving more than two (2)
lots.
Marina - a business establishment having frontage on navigable water and, as its principal use, providing for
hire offshore moorings or docking facilities for boats, and which may also provide accessory services such as
boat and related sales, boat repair and construction, indoor and outdoor storage of boats and marine
equipment, boat and tackle shops and marine fuel service facilities.
Market value - the estimated price a property will bring in the open market and under prevailing market
conditions in a sale between a willing seller and a willing buyer, both conversant with the property and with
prevailing general price levels.
Minimum lot width - the closest distance between the side lot lines of a lot. When only two lot lines extend
into the shoreland zone, both lot lines shall be considered to be side lot lines.
Mineral exploration - hand sampling, test boring, or other methods of determining the nature or extent of
mineral resources which create minimal disturbance to the land and which include reasonable measures to
restore the land to its original condition.
Mineral extraction - any operation within any twelve (12) month period which removes more than one
hundred (100) cubic yards of soil, topsoil, loam, sand, gravel, clay, rock, peat, or other like material from its
natural location and transports the product removed from the extraction site.
Multi-unit residential - a residential structure containing three (3) or more residential dwelling units.
Native- indigenous to local forests.
Non-conforming condition- non-conforming lot, structure, or use which is allowed solely because it was in
lawful existence at the time this Ordinance or subsequent amendment took effect.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
52
Non-conforming lot - a single lot of record which, at the effective date of adoption or amendment of this
Ordinance, does not meet the area, frontage, or width requirements of the district in which it is located.
Non-conforming structure - a structure which does not meet any one or more of the following dimensional
requirements; setback, height, lot coverage, or footprint, but which is allowed solely because it was in lawful
existence at the time this Ordinance or subsequent amendments took effect.
Non-conforming use - use of buildings, structures, premises, land or parts thereof which is not permitted in
the district in which it is situated, but which is allowed to remain solely because it was in lawful existence at
the time this Ordinance or subsequent amendments took effect.
Non-native invasive species of vegetation - species of vegetation listed by the Maine Department of
Agriculture, Conservation and Forestry as being invasive in Maine
ecosystems and not native to Maine
ecosystems.
Normal high-water line - that line which is apparent from visible markings, changes in the character of soils
due to prolonged action of the water or changes in vegetation, and which distinguishes between
predominantly aquatic and predominantly terrestrial land. Areas contiguous with rivers that support non-
forested wetland vegetation and hydric soils and that are at the same or lower elevation as the water level of
the river during the period of normal high-water are considered part of the river.
Outlet stream - any perennial or intermittent stream, as shown on the most recent highest resolution version
of the national hydrography dataset available from the United States Geological Survey on the website of the
United States Geological Survey or the national map, that flows from a freshwater wetland.
Outstanding river segments - includes the Crooked River, as listed in Title 38, Section 480-P.
People Camps - A combination of program and facilities established for the primary purpose of providing an
outdoor group living experience for children and/or adults with social, recreational, spiritual, and educational
objectives and operated and used for five or more consecutive days during one or more seasons of the year.
People camps include day camps, residential camps and trip and travel camps.
Person - an individual, corporation, governmental agency, municipality, trust, estate, partnership, association,
two or more individuals having a joint or common interest, or other legal entity.
Piers, docks, wharfs, bridges and other structures and uses extending over or beyond the normal high-
water line or within a wetland -
Temporary: Structures which remain in or over the water for less than seven (7) months in any period
of twelve (12) consecutive months and are removed by November 1 of each year.
Permanent: Structures which remain in or over the water for seven (7) months or more in any period of
twelve (12) consecutive months and remain in or over the water after November 1 of each year.
Primitive trail - a public or private path or trail, with a tread path no more than three (3) feet in width and an
overall clearance of four (4) feet in width, established for walking, hiking, non-motorized biking purposes,
snow-shoeing, or cross-country skiing. Primitive trails are not structures if there is no base material used such
as, but not limited to, pavement, concrete, gravel or similar material.
Principal structure - the structure in which the primary use of the lot is conducted.
Principal use - the primary use to which the premises are devoted.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
53
Public facility - any facility, including, but not limited to, buildings, property, recreation areas, and roads,
which are owned, leased, or otherwise operated, or funded by a governmental body or public entity.
Recent flood plain soils - the following soil series as described and identified by the National Cooperative
Soil Survey:
Alluvial
Cornish
Charles
Fryeburg
Hadley
Limerick
Lovewell
Medomak
Ondawa
Podunk
Rumney
Saco
Suncook
Sunday
Winooski
Recreational facility - a place designed and equipped for the conduct of sports, leisure time activities, and
other customary and usual recreational activities, excluding boat launching facilities.
Recreational trail - a way across land, used primarily for recreational purposes including, but not limited to,
such uses as: bicycling, Nordic (cross-country) skiing, day hiking, equestrian activities, jogging or similar
fitness activities, trail biking, overnight or long distance backpacking, roller skating, in-line skating, dog
sledding, running, snowmobiling, canoe and kayak portaging; and vehicular travel by motorcycle, four-wheel
drive or all terrain, off-road vehicles. Recreational trail use may be limited to foot, horse or other non-
motorized means of transportation, or combination of any of them. Recreational trail includes the terms
primitive trail and trail spur.
Recreational vehicle - a vehicle or an attachment to a vehicle designed to be towed, and designed for
temporary sleeping or living quarters for one or more persons, and which may include a pick-up camper,
travel trailer, tent trailer, camp trailer, and motor home. In order to be considered as a vehicle and not as a
structure, the unit must remain with its tires on the ground, be attached to the site only by quick disconnect
type utilities and security devices, have no permanently attached additions, and must be registered with the
State Division of Motor Vehicles and be consistent with the applicable definitions promulgated by the Maine
Department of Environmental Protection and the Maine Department of Health and Human Services.
Replacement system - a system intended to replace: 1) an existing system which is either malfunctioning or
being upgraded with no significant change of design flow or use of the structure, or 2) any existing overboard
wastewater discharge.
Residential dwelling unit - a room or group of rooms designed and equipped exclusively for use as
permanent, seasonal, or temporary living quarters for only one family. The term shall include mobile homes,
but not recreational vehicles.
Residential Institutional - A use providing recreation, counseling, education and/or other rehabilitative
services where the individuals commonly reside at the facility.
Residual basal area- the average of the basal area of trees remaining on the harvest site.
Residual Stand - a stand of trees remaining in the forest following timber harvesting and related activities
Riprap - rocks, irregularly shaped, and at least six (6) inches in diameter, used for erosion control and soil
stabilization, typically used on ground slopes of two (2) units horizontal to one (1) unit vertical or less.
River - a free-flowing body of water including its associated flood plain wetlands from that point at which it
provides drainage for a watershed of twenty-five (25) square miles to its mouth.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
54
Road - a route or track consisting of a bed of exposed mineral soil, gravel, asphalt, or other surfacing material
constructed for or created by the repeated passage of motorized vehicles, excluding driveways as defined.
Sapling - a tree species that is less than two (2) inches in diameter at four and one half (4.5) feet above
ground level.
Seedling - a young tree species that is less than four and one half (4.5) feet in height above ground level.
Service drop - any utility line extension which does not cross or run beneath any portion of a water body
provided that:
1. in the case of electric service
a.
the placement of wires and/or the installation of utility poles is located entirely upon the
premises of the customer requesting service or upon a roadway right-of-way; and
b.
the total length of the extension is less than one-thousand (1,000) feet.
2. in the case of telephone service
a.
the extension, regardless of length, will be made by the installation of the telephone wires
to existing utility poles, or
b.
the extension requiring the installation of new utility poles or placement underground is
less than one-thousand (1,000) feet in length.
Setback - the nearest horizontal distance from the normal high-water line of a water body or tributary stream,
or upland edge of a wetland, to the nearest part of a structure, road, parking space or other regulated object or
area.
Shore frontage - the length of a lot bordering on a water body or wetland measured in a straight line between
the intersections of the lot lines with the shoreline.
Shoreland zone - the land area located within two hundred and fifty (250) feet, horizontal distance, of the
normal high-water line of any great pond, or river; within 250, horizontal distance, feet of the upland edge of
a freshwater wetland; or within seventy-five (75) feet, horizontal distance, of the normal high-water line of a
stream.
Shoreline- the normal high-water line or upland edge of a freshwater wetland.
Skid Road or trail- a route repeatedly used by forwarding machinery or animal to haul or drag forest
products from the stump to the yard or landing, the construction of which requires minimal excavation.
Slash- the residue, e.g., treetops and branches, left on the ground after a timber harvest.
Storm-damaged tree - a tree that has been uprooted, blown down, is lying on the ground, or that remains
standing and is damaged beyond the point of recovery as the result of a storm event.
Stream - a free-flowing body of water from the outlet of a great pond or the confluence of two (2) perennial
streams as depicted on the most recent, highest resolution version of the national hydrography dataset
available from the United States Geological Survey on the website of the United States Geological Survey or
the national map to the point where the stream becomes a river or where the stream meets the shoreland zone
of another water body or wetland and as may be depicted on the Official Shoreland Zoning Map. When a
stream meets the shoreland zone of a water body or wetland and a channel forms downstream of the water
body or wetland as an outlet, that channel is also a stream.
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
55
Structure - anything temporarily or permanently located, built, constructed or erected for the support, shelter
or enclosure of persons, animals, goods or property of any kind, or anything constructed or erected on or in
the ground. The term includes structures temporarily or permanently located, such as decks, patios, and
satellite dishes. Structure does not include fences; poles and wiring and other aerial equipment normally
associated with service drops, including guy wires and guy anchors; subsurface waste water disposal systems
as defined in Title 30-A, section 4201, subsection 5; geothermal heat exchange wells as defined in Title 32,
section 4700-E, subsection 3-C; or wells or water wells as defined in Title 32, section 4700-E, subsection 8.
Substantial start - completion of thirty (30) percent of a permitted structure or use measured as a percentage
of estimated total cost.
Subsurface sewage-disposal system - any system designed to dispose of waste or waste water on or beneath
the surface of the earth; includes, but is not limited to: septic tanks; disposal fields; grandfathered cesspools;
holding tanks; pretreatment filter, piping, or any other fixture, mechanism, or apparatus used for those
purposes; does not include any discharge system licensed under 38 M.R.S.A. section 414, any surface waste
water disposal system, or any municipal or quasi-municipal sewer or waste water treatment system..
Sustained slope - a change in elevation where the referenced percent grade is substantially maintained or
exceeded throughout the measured area.
Swim dock - floating docks/platforms not attached to the shore.
Timber harvesting - the cutting and removal of timber for the primary purpose of selling or processing forest
products. "Timber harvesting" does not include the cutting or removal of vegetation within the shoreland zone
when associated with any other land use activities. The cutting or removal of trees in the shoreland zone on a
lot that is less than two (2) acres within the shoreland zone shall not be considered timber harvesting. Such
cutting or removal of trees shall be regulated pursuant to Section 15.P, Clearing or Removal of Vegetation for
Activities Other than Timber Harvesting.
Timber harvesting and related activities - timber harvesting, the construction and maintenance of roads used
primarily for timber harvesting and other activities conducted to facilitate timber harvesting.
Trail spur - a primitive trail with no base material that extends toward the shoreline from a recreational
trail.
Tree - a woody perennial plant with a well-defined trunk(s) at least two (2) inches in diameter at four and one
half (4.5) feet above the ground, with a more or less definite crown, and reaching a height of at least ten (10)
feet at maturity.
Tributary stream - means a channel between defined banks created by the action of surface water, which is
characterized by the lack of terrestrial vegetation or by the presence of a bed, devoid of topsoil, containing
waterborne deposits or exposed soil, parent material or bedrock; and which is connected hydrologically with
other water bodies. "Tributary stream" does not include rills or gullies forming because of accelerated
erosion in disturbed soils where the natural vegetation cover has been removed by human activity.
This definition does not include the term "stream" as defined elsewhere in this Ordinance, and only applies to
that portion of the tributary stream located within the shoreland zone of the receiving water body or wetland.
Upland edge of a wetland - the boundary between upland and wetland. For the purposes of a freshwater
wetland, the upland edge is formed where the soils are not saturated for a duration sufficient to support
Town of Waterford
Shoreland Zoning Ordinance-Amended March 4, 2023
56
wetland vegetation; or where the soils support the growth of wetland vegetation, but such vegetation is
dominated by woody stems that are six (6) meters (approximately twenty (20 feet or taller.
Vegetation - all live trees, shrubs, and other plants including without limitation, trees both over and under
four (4) inches in diameter, measured at 4 2 feet above ground level.
Volume of a structure - the volume of all portions of a structure enclosed by roof and fixed exterior walls as
measured from the exterior faces of these walls and roof.
Water body - any great pond, river or stream.
Water crossing - any project extending from one bank to the opposite bank or a river, stream, tributary
stream, or wetland whether under, through, or over the water course. Such projects include but may not be
limited to roads, fords, bridges, culverts, water lines, sewer lines, and cables as well as maintenance work on
these crossings. This definition includes crossings for timber harvesting equipment.
Wetland - a freshwater wetland.
Windfirm - the ability of a forest stand to withstand strong winds and resist windthrow, wind rocking, and
major breakage.
Wood vegetation- live trees or wood, non-herbaceous shrubs.
Adopted: March, 7, 1992
Amended: March 1, 2003
Amended: March 28, 2005
Amended: March 3, 2007
Amended: March 6, 2010
Amended: March 3, 2012
Amended: March 5, 2016
03.15.16-JAM