1
LAND USE ORDINANCE
Planning Board Meetings
2nd Tuesday of each month, 6:00 p.m.
West Bath Town Hall
Town of West Bath
219 Fosters Point Rd.
West Bath, ME 04530
Tel: (207) 443-4342
Fax: (207) 443-3256
www.westbath.org
Last Amended: February 2026
2
Table of Contents
Article I. General Provisions ........................................................................................ 5
Purposes ...................................................................................................................... 5
Statutory Authority ....................................................................................................... 5
Applicability .................................................................................................................. 5
Administrative Bodies................................................................................................... 6
Approvals and Permits ................................................................................................. 8
Validity and Severability ............................................................................................. 10
Conflicting Ordinances ............................................................................................... 10
Amendments .............................................................................................................. 11
Effective Date ............................................................................................................. 12
References ................................................................................................................. 12
Article II. Land Use Districts, Overlay Zones, and Requirements ........................ 13
District Boundary Descriptions, Overlay Zones, & Map.............................................. 13
District 1. High Density Coastal .................................................................................. 13
District 2. Residential ................................................................................................. 14
District 3. Rural Residential ........................................................................................ 15
District 4. Business & Commercial ............................................................................. 15
District 5. Urban Development Park ........................................................................... 15
Mobile Home Park Overlay Zone ............................................................................... 16
Resource Protection Overlay Zone ............................................................................ 16
Shoreland Overlay Zone ............................................................................................ 17
Special Industrial & Transportation Overlay Zone ...................................................... 19
Use Regulations & Requirements .............................................................................. 20
Land Use Matrix ......................................................................................................... 21
Minimum Lot Standards ............................................................................................. 28
Article III. Site Plan Review ..................................................................................... 30
Project Classes .......................................................................................................... 30
Procedure .................................................................................................................. 31
Pre-Application Meeting ............................................................................................. 31
Fees ........................................................................................................................... 32
Application ................................................................................................................. 32
Final Approval ............................................................................................................ 32
Submissions ............................................................................................................... 33
General Performance Standards for Site Plan Review .............................................. 35
Waivers ...................................................................................................................... 57
3
Article IV. Subdivisions ........................................................................................... 58
Purpose ...................................................................................................................... 58
Definitions & Standards: Small vs. Large Subdivision ................................................ 58
Pre-Application Procedure ......................................................................................... 59
Application Procedure ................................................................................................ 60
Preliminary Plan Submission ..................................................................................... 62
Final Plan Submission ................................................................................................ 68
Final Approval and Filing ............................................................................................ 72
Revisions to Approved Plans ..................................................................................... 73
General Standards ..................................................................................................... 74
Performance Guarantees ........................................................................................... 88
Article V. Specific Standards .................................................................................. 90
Accessory Dwelling Units ........................................................................................... 90
Affordable Housing Development .............................................................................. 91
Business and Commercial Development ................................................................... 92
Mineral Exploration and Extractions ........................................................................... 94
Mobile Home Parks .................................................................................................... 94
Home Occupations..................................................................................................... 96
Setback Reduction Plan - UDP District ..................................................................... 97
Small Wind Energy Conversion Systems ................................................................... 97
Domesticated Chickens ........................................................................................... 101
Solar Energy Systems .............................................................................................. 102
Communication Towers ........................................................................................... 105
Indoor and Outdoor Places for Eating and Drinking; Live Entertainment ................. 109
Food Trucks ............................................................................................................. 110
Agriculture ................................................................................................................ 110
Campgrounds not in the Shoreland Zone ................................................................ 111
Kennels and Animal Accommodations ..................................................................... 111
Bed and Breakfasts .................................................................................................. 111
General Industrial/Manufacturing Uses .................................................................... 111
Junkyards ................................................................................................................. 111
Daycares .................................................................................................................. 112
Change of Use ......................................................................................................... 112
Article VI. Non-Conformance ................................................................................ 113
Purpose .................................................................................................................... 113
Definition .................................................................................................................. 113
Non-Conforming Uses .............................................................................................. 113
Non-Conforming Lots ............................................................................................... 113
Non-Conforming Structures ..................................................................................... 114
Reconstruction/Replacement ................................................................................... 114
Expansions .............................................................................................................. 115
Greatest Practical Extent Criteria ............................................................................. 118
4
Article VII. Appeals ................................................................................................ 119
Composition, Appointments, Qualifications, & Terms .............................................. 119
Organization & Meetings .......................................................................................... 119
Conflict of Interest .................................................................................................... 120
Powers & Duties ...................................................................................................... 120
Variances ................................................................................................................. 121
Application ............................................................................................................... 122
Procedure ................................................................................................................ 122
Standards of Review ................................................................................................ 122
Conditions of Approval ............................................................................................. 125
Expiration ................................................................................................................. 125
Re-application .......................................................................................................... 125
Misrepresentation .................................................................................................... 125
Prior to Work ............................................................................................................ 125
Notice to Department of Environmental Protection .................................................. 125
Article VIII. Shoreland Zone .................................................................................. 126
Shoreland Zone Overlay District .............................................................................. 126
Purpose .................................................................................................................... 126
SZO District Applicability .......................................................................................... 126
Additional Requirements .......................................................................................... 127
Lot Size and Shore Frontage ................................................................................... 129
Piers, Docks, Wharves, Bridges, and Other Structures ............................................ 130
Shoreland Zone Overlay Permit Requirements and Exceptions .............................. 131
Shoreland Zone Administration ................................................................................ 150
Special Exceptions for Development within Resource Protection ............................ 153
Article IX. Enforcement & Penalties ..................................................................... 155
Article X. Definitions .............................................................................................. 156
5
ARTICLE I. GENERAL PROVISIONS
1.1
PURPOSES
The purposes of this Ordinance are to:
-
Further the maintenance or safe and healthful conditions, prevent and
control water pollution;
-
Protect spawning grounds, fish, aquatic life, bird and other wildlife habitat;
-
Control building sites, placement of structures , land use;
-
Protect buildings and land from flooding and accelerated erosion;
-
Protect archaeological and historic resources
-
Protect commercial fishing and maritime industries;
-
Protect freshwater and coastal wetlands;
-
Conserve shore cover, and visual as well as actual points of access to
inland and coastal waters;
-
Conserve natural beauty and open space;
-
Integrate findings of the Comprehensive Plan; and
-
Anticipate and respond to the impact of development.
1.2
STATUTORY AUTHORITY
This Ordinance is prepared in pursuant to Maine Revised Statutes Annotated
(M.R.S.A), Title 30-A, Sections 2691, 3001, 4351-4353, 4358, 4403, and 4452;
38 M.R.S.A Sections 435-449, and any other applicable provisions of the
statutes; as well as pursuant to the Comprehensive Plan of the Town of West
Bath.
1.3
APPLICABILITY
1.3.1: The present uses of land and existing structures shall not be affected
by this Ordinance unless public health and safety is threatened.
1.3.2: The use of any land, building, or structure; the division of any tract of
land; and any construction or alteration of any building or structure must be in
conformance with the standards and procedures set forth in this Ordinance. All
uses of land, buildings, or structures; construction or modification of buildings;
and divisions of land that do not meet the requirements of this Ordinance are
prohibited; except for those lawfully nonconforming uses, buildings, structures,
or lots provided in Article VI (Nonconforming Uses).
6
1.4
ADMINISTRATIVE BODIES
1.4.1. PLANNING BOARD
A. Composition, Appointments, Qualifications and Terms
1. The Town of West Bath shall have a Planning Board consisting of
five (5) members and two (2) alternate members, each of whom shall
be appointed by the Select Board. All members of the Planning Board
shall be residents of the Town of West Bath. Members of the Select
Board shall not be eligible to serve on the Planning Board. Members
of the Planning Board shall serve staggered five (5) year terms. If a
vacancy occurs, the term of the PERSON appointed to fill the
vacancy shall be for the period of the unexpired term. The terms of
the members shall expire on June 30 unless a replacement has not
been appointed, in which case the term of the expiring member shall
be extended until a replacement is named.
B.
Organization and Meetings
1. The Planning Board shall elect annually a Chair and Vice Chair from
its membership. The election of officials shall occur at the first meeting
of the Board after June 30th of each year. Town staff may serve as the
Planning Board's recording secretary.
2. The Chair's duties shall consist of calling the meetings, establishing
agendas for each meeting, presiding at all meetings, and representing
the Planning Board before other bodies. The Vice Chair shall be
responsible for carrying out the duties of the Chair in his/her absence
or incapacity. The Secretary shall be responsible for keeping minutes
of the proceedings of the Planning Board and for making the minutes
available to the public.
3. The Planning Board shall meet at least once per month, provided that
there is business for the Planning Board to address. Special meetings
may be called at the request of the Chair, or upon a written request of
at least three (3) members of the Planning Board.
7
4. Public notice of all meetings of the Planning Board shall be provided
in accordance with State law, and outlined in Article III (Site Plan
Review) or Article IV (Subdivision). Meetings of the Planning Board
shall be open to the public and shall be conducted in accordance with
such rules of procedure as the Planning Board may adopt in
compliance with applicable State and local laws.
5. A quorum shall consist of three (3) members of the Planning Board.
All members present and not excused from voting shall vote on each
agenda item. The Secretary shall record results of all votes, and the
vote of a majority of those members present and voting shall be
required for the passage of any item of the Planning Board's business.
C. Conflicts of Interest
1. No member of the Planning Board shall vote on or participate in any
matter in which he/she has a bias or conflict of interest, including, but
not limited to, a direct or indirect pecuniary interest, as defined in 30-
A M.R.S.A. § 2605, in the matter before the Planning Board. Any
question of whether a particular issue involves a bias or conflict of
interest sufficient to disqualify a member from voting thereon shall be
decided by a majority vote of the remaining members of the Planning
Board.
D. Powers and Duties
1. The Planning Board shall administer the Land Use Ordinance:
1. For all land uses outlined in Article II (Land Use Matrix).
2. For all subdivision plan and amendments thereto.
3. For all uses in the Shoreland Overlay Zone chart outlined in Article II
(Shoreland Zone).
1.4.2. Code Enforcement Officer - The Code Enforcement Officer shall
administer the Land Use Ordinance for all uses not administered by
the Planning Board unless the Code Enforcement Officer requests
Planning Board review.
1.5 . APPROVALS AND PERMITS
1.5.1. Approvals and Permits Required - After the effective date of this
Ordinance, no PERSON shall engage in any use of land requiring an approval
or permit or expand or change an existing non-conforming use without first
obtaining the required approval(s) and/or permit(s).
8
1.5.2. Fees - For the purpose of defraying normal costs associated with the
processing of applications by the Town, the Select Board may establish a fee
schedule, subject to annual review, setting forth fees to be collected by the Town
from applicants for each type of approval or permit required under this
Ordinance. Any approval or Building permit obtained after the use or Building
has commenced shall be assessed three (3) times the normal fee.
1.5.3. It shall be unlawful to construct, add to, alter, remove, or demolish any
STRUCTURE without first filing with the Planning Board or Code Enforcement
Officer an application in writing and obtaining the necessary approval(s) and/or
permit(s) as outlined in Article III. Upon receiving an application in the proper
form, the Planning Board or Code Enforcement Officer shall review the
application and make inspection, as necessary, within a reasonable time. If the
application meets the requirements of this Ordinance, the Planning Board or
Code Enforcement Officer shall issue the approval, approval subject to
conditions or permit within a practicable time, or a refusal in writing stating the
reason for refusal. A copy of either action shall be filed with the Select Board.
The Code Enforcement Officer shall file a monthly report with the Select Board
description of activities which are within his jurisdiction and his action in respect
to them.
1.5.4. Applications - Applications for approvals and permits shall be submitted
in writing. The Code Enforcement Officer or the Planning Board may require
the submission of whatever information is necessary to determine conformance
with the provisions of this Land Use Ordinance.
1.5.5. Right, title or interest in the application property must be provided for all
applications. Leases must be signed by lessor.
1.5.6 All required abutter notifications shall be sent to all appropriate parties via
certified return receipt mail by Town staff no less than 14 days before any
hearing. Notification fees shall be in accordance with the current Town Fees &
Penalties Schedule and reimbursed to the Town by the Applicant at the time of
application.
1.5.7. Issuance of Approvals and Permits - Approvals and permits shall not be
denied if the proposed use is found to be in conformance with the provisions of
this Ordinance. Planning Board Approvals are valid for 1 year and can be
renewed if the project is still compliant with all standards and criteria as of the
9
date of renewal. Building permits issued by the Code Enforcement Officer are
valid for 6 months and can be renewed by the Code Enforcement Officer.
1.5.8. All Building permits issued by the Code Enforcement Officer after
approval by the Planning Board - The Planning Board shall approve or deny
those applications on which it is empowered to act as stated in this Ordinance.
1.5.9. Planning Board Review Criteria - The Planning Board may, after the
submission of a COMPLETE APPLICATION, including all information requested,
grant a permit be issued if it makes a positive finding on the information
presented to it that the proposed use:
A. Will not result in unsafe or unhealthful conditions.
B. Will not result in erosion or sedimentation.
C. Will not result in water pollution.
D. Will not result in damage to spawning grounds, fish, aquatic life, birds and
other wildlife habitat.
E. Will conserve actual points of public access to waters.
F. Will avoid problems associated with floodplain development and use.
G. Is in conformance with the provisions of this Ordinance and other applicable
law..
1.5.10. Conditions - Approvals may be subject to reasonable conditions to
ensure conformity with the provisions of the Town's Ordinances and the
policies expressed in the Town's COMPREHENSIVE PLAN, and as may be
required to protect public safety.
1.5.11. Constructions must commence within six (6) months from the
STRUCTURE building permit date of issue unless permit is renewed by the
Code Enforcement Officer.
1.5.12. Occupancy/Use Permit - The following applies to commercial uses only
(including those portions of a STRUCTURE and/or property utilized for a home
business):
A. A certificate of occupancy/use shall be required and obtained from the
Code Enforcement Officer prior to the occupancy or use of any Building,
STRUCTURE, or any portion thereof which has been erected, structurally
altered or changed in its use or STRUCTURE, or with regard to the
creation of a new use or change in use of any parcel of land or portion
thereof currently existing or hereinafter created. Before the issuance of the
10
certificate of occupancy/use, the Code Enforcement Officer shall
determine that the proposed use of the STRUCTURE or land conforms to
the requirements of the Land Use Ordinance.
B. A change of occupancy that maintains the same land use classification
shall not require a certificate of occupancy unless site plan review is
required. Where a Building permit or other land use permit is required, an
application for a certificate of occupancy/use shall be filed concurrently
with that application and shall clearly state the intended use or uses of the
property. The certificate of occupancy/use may only be issued after a
determination that all work has been completed on the site and/or
STRUCTURE in conformance with Town Ordinances, any approved site
plan or SUBDIVISION plan, any other applicable town, state and federal
requirements, and any conditions of approval imposed by the Planning
Board on the project. Occupancy without the required certificate shall be
deemed to be a violation of this Ordinance and subject to enforcement
action as provided in Article VIII (Enforcement and Penalties).
C. The Code Enforcement Officer may issue a temporary certificate of
occupancy/use for a period of time not to exceed six (6) months where it
has been determined that adequate safeguards are in place to ensure the
timely completion of the work. The Code Enforcement Officer may require
the posting of a bond or other financial security or guarantee to ensure
completion of the project in accordance with its permitting.
1.6. VALIDITY AND SEVERABILITY
Should any section or provision of this Ordinance become void or invalid, such
decision shall not void or invalidate any other section, subsection, or portion of
this Ordinance.
1.7. CONFLICTING ORDINANCES
Whenever a provision of this Ordinance is in conflict with another provision of any
other lawfully adopted rule, regulation, Ordinance, deed restriction, or covenant,
the most restrictive or that imposing the higher standards shall govern.
1.8. AMENDMENTS
11
A. Annual Town Budget Meeting. This Ordinance may be amended by a
majority vote at any Annual Town Budget Meeting in accordance with the
requirements of 30-A M.R.S.A. § 3002, Ordinance Enactment Procedure,
and § 4352, Zoning Ordinances.
B. Special Town Meeting.
1. Purpose. While it is contemplated that the normal amendment process
for this Land Use Ordinance shall require presentation and adoption
at the Town's Annual Town Budget Meeting, it is recognized that, from
time to time, circumstances require that changes be made to
accommodate the needs of the community and its citizens and to
provide a process to deal with Ordinance changes in a more timely
fashion, where it is deemed that such change is appropriate and a
more timely consideration by the Town Budget Meeting is deemed
necessary.
2. Criteria. Land Use Ordinance changes proposed at a Special Town
Meeting shall meet the following criteria, which are mandatory and
may not be waived:
a. The Planning Board and/or Code Enforcement Officer have
reviewed the proposed Ordinance changes and have made a
recommendation regarding the proposed amendments.
b. The Board of Appeals has reviewed the proposed Ordinance
changes and has submitted its opinion that the objectives of the
amendment(s) require changes to the Land Use Ordinance and
such objectives cannot be met under existing Ordinance
provisions.
c. The Planning Board has determined the proposed Ordinance
change(s) conform with the provisions of the Town of West Bath
COMPREHENSIVE PLAN.
d. The Town has had an opportunity to have Ordinance amendments
reviewed by the Town Attorney and such other organizations and
municipal consultants as the Select Board may deem appropriate.
e. The procedures set forth in subsection 3 below have been
followed.
3. Public Notification and Participation.
a. Planning Board Public Hearing. At the point in time where an
amendment is proposed under the expedited process provided in
this Subsection, the Planning Board shall schedule a Public
Hearing. Notification of the Public Hearing shall be published in a
newspaper of general circulation within the Town of West Bath.
12
There shall be two (2) publications. The first no less than fourteen
(14) days prior to the scheduled Public Hearing.
b. Select Board's Public Hearing. At the point in time when the
proposed Ordinance amendments are in draft form, the Select
Board shall schedule a Public Hearing to allow public comment and
receive input regarding the proposed amendments. Notification of
the Public Hearing shall be in the same manner as the Planning
Board Public Hearing in Section a above.
c. Additional Public Hearing. If the Select Board's Public Hearing
provided for in Section b, above, results in significant changes, as
determined by the Select Board, to the original draft of the
amendments, a subsequent public hearing shall be held to receive
public comment and input on the amended draft. The procedure
for calling such a public hearing shall be the same as the Planning
Board's hearing except that notice to parties-in-interest and
abutters shall not be required.
d. Rejection by Voters. If proposed amendments to the Land Use
Ordinance are rejected by the voters at a Special Town Meeting,
those same amendments may not be presented at another Special
Town Meeting; but may only be considered at the Town's Annual
Town Budget Meeting.
4. A copy of all amendments to the Shoreland Zone shall be sent to the
Department of Environmental Protection within thirty (30) days of the
effective date of such amendments.
1.9.
EFFECTIVE DATE
The effective date of this Ordinance is May 4, 2026, with subsequent
amendments effective as of the date of their adoption by Town Budget Meeting.
1.10. REFERENCES
A. References in the text of this Ordinance to Articles refer to Articles of this
Ordinance, unless otherwise specified.
B. This document, originally titled "Town of West Bath Land Use
Ordinances", shall, as of May 4, 2026, be entitled "Town of West Bath
Land Use Ordinance".
13
ARTICLE II. LAND USE DISTRICTS, OVERLAY ZONE, AND REQUIREMENTS
2.1
DISTRICT BOUNDARY DESCRIPTIONS, OVERLAY ZONES AND MAP
2.1.1. Districts with Overlay Zones. Wherever a LOT or a portion of a LOT of land
is within an overlay zone the more restrictive district or overlay zone shall apply
to the portion of the LOT within the overlay zone
2.1.2. Individual LOTS in more than one District. Wherever an individual LOT is
in more than one district the portion of the LOT within a given district shall be
subject to the provisions of this Ordinance applicable to that district.
2.1.3. Description. LOT numbers used in describing boundaries or land included
in districts correspond to the LOT numbers on the 1999 tax maps. An offset
distance from a ROAD used in defining a district boundary is measured from the
center of the traveled way in a direction perpendicular to the edge of the traveled
way, unless otherwise noted. The boundaries of the districts and overlay zones
that are described in this Article are shown on a map entitled "Land Use
Ordinance District and Overlay Zone Map As Amended 2016", as may be
amended from time to time, certified by the attested or conformed signature of
the Town Clerk, and posted at the Town Hall. Until the mapping of the Resource
Protection Overlay Zone is completed, the map shall incorporate a note stating
that there are boundaries of this overlay zone not shown on the map but which
are defined by the text of the Ordinance. In event of conflict between this map
and any boundary descriptions contained in this Article, the text describing the
boundaries shall govern.
A.
DISTRICT 1. High Density Coastal (HDC)
This district, formerly known as the High Density Shoreland, is based on historical
development trends along seven different coastal parts of the coast. This district
is not to be confused with the Shoreland Zone requirements under the State
statute 38 M.R.S.A. § 435-449.
This district consists of seven (7) areas as defined below:
1. Bull Rock - Includes from map U-11 LOTS 3, 3A, 2, 25 through 32,
and from map U- 12 LOTS 17 through 20.
2. Kings Point - Includes from map U-13 LOTS 2 through 33 and the
portion of LOT 34 southerly of LOT 10.
3. Rockhaven - Includes from map U-15 LOTS 2 through 15 and from
map U-16 LOTS 6 through 17.
4. Fosters Point - Includes from map U-17 LOTS 7, 8, 10, 10A, 11, 12, 14,
and 16
through 22.
5. Sabino - Includes from map U-22 LOTS 1 through 6, 8 through 24,
26, 28, 29, and from map U-23 LOTS 5 through 16 excepting 7A, 7B,
and 7C.
14
6. Birch Point - Includes from map U-24 LOTS 1A, 2 through 11, 13
through 15, 17 through 24, and the portion of 25A northwesterly of the
STREAM passing through said LOT (LOT 16 in 1993) and from map
U-25 LOTS 1 through 36.
7. Brighams and Shoal Coves - Includes from map U-26 LOTS 1 through
19, and from map U-27 LOTS 1 through 7, 9 through 12, 13A through
15, 17 through 22, 24 through
27, 30, 32, 33, 34, and 36 through 41.
B.
DISTRICT 2. Residential
The purpose of the Residential District is to protect residential properties by
allowing small-scale developments with low-intensity development and other
uses that compliment residential developments and uses. These areas are
marked on the maps as follows:
1. New Meadows ROAD - the area near New Meadows Lake and Creek
designated as "Residential" on the Land Use Ordinance District and
Overlay Zone Map.
2. Central West Bath - Beginning at a point on the east side of Back
Cove Creek where said creek intersects the north side of Hill Road;
thence easterly along Hill Road to the western corner of map R-2 LOT
26A; thence along the northern boundaries of map R-2 LOT 26A, map
R-3 LOT 46 and map R-2 LOTS 15J, 15G, 15F, 15E, 15D,
15K and 15B and on the same bearing crossing Berrys Mill Road;
thence northerly along the east side of said ROAD to the northern line
of map R-2 LOT 6; thence easterly along the northern boundary of
said LOT to the Lily Pond and the town line; thence northerly along
said town line to a point offset 500' southerly of the State Road (Old
Route #1); thence westerly parallel to the State Road at an offset of
500' to a point offset 300' southerly of the Bull Rock Road; thence
westerly parallel to said ROAD at an offset of 300' to a point offset 300'
easterly of the Fosters Point Road; thence southerly paralleling said
ROAD to the northern boundary of map U-12 LOT 15D; thence
westerly along said boundary to Fosters Point Road and crossing said
ROAD to the southeasterly corner of map U-12 LOT 9; thence
southerly along the west side of Fosters Point Road to a point opposite
the north side of Hill Road; thence crossing Fosters Point Road and
easterly along the north side of Hill Road to the point of beginning.
3. Fosters Point - All land west of Fosters Point Road not included in
other districts with the district's southern boundary being the northern
boundary of map U-17 LOT 23.
4. Winnegance - Including all land easterly of Campbells Pond Road and
Brigham Cove Road not included in other districts. Also including map
R-6 LOTS 59 through 65, 66A through 71, 72A, and the portion of 69D
sought of a line connecting the northeast corner of 69E and the
southwest corner of 71. The portion of Winnegance Pond, westerly of
the town line is included in this district.
15
C.
DISTRICT 3. Rural Residential
The purpose of this district is to retain the rural character of West Bath. This
district encompasses the majority of the land area in West Bath and is intended
for non-intensive uses and traditional rural activities.
D.
DISTRICT 4. Business & Commercial
The purpose of this district is to encourage commercial and high-density
development along parcels surrounding the State highway as well as State Road
between Bath and Brunswick.
Beginning at a point where the high water mark of the New Meadows Lake
intersects with the south side of the Route #1 right-of-way; thence southerly
along the high waterline of the New Meadows Lake and River to a point offset
500′ and southerly of the State Road (Old Route #1); thence easterly
paralleling State Road to a point of intersection offset 300′ westerly of Fosters
Point Road; thence southerly paralleling, and 300′ offset, the west side of
Fosters Point Road to the southern boundary of map U-12 Lot 10; thence
easterly along the southern boundaries of map U-12 Lots 10, 10A and 9 and
continuing across the Fosters Point Road to the northern boundary of map U-
12 Lot 15D and continuing easterly along said boundary to a point offset 300′
from Fosters Point Road; thence northerly paralleling the Fosters Point Road,
and 300′ offset, to an intersection point offset 500′ southerly of the Bull Rock
Road; thence easterly paralleling the Bull Rock Road at an offset of 500′ to an
intersection point that is also offset 500′ southerly of the State Road; thence
easterly paralleling the State Road at an offset of 500′ to the West Bath/Bath
town line; thence northerly along the West Bath/Bath town line to a point on
the southerly right-of-way boundary of Route 1, the divided highway right-of-
way, thence westerly along said highway right-of-way to New Meadows Lake
and the point of beginning.
E.
DISTRICT 5. Urban Development Park
The purpose of this district is to encourage industrial and commercial uses likely
requiring access to centralized sewer and water systems. This district includes
all land that is north of Route 1, west of the Bath town line, east of the CMP
power transmission line right of way (Plan of Sec. 77, 132/97), and south of the
southern boundary of Map R1 LOT 12. Also includes the whole of Map R1 LOT
02 and 03. The majority of land in this district is in Wing Farm Business Park.
F.
MOBILE HOME PARK OVERLAY ZONE
Beginning at a point on the north side of State Road at the eastern boundary
of map U-9 Lot 2A; thence northeasterly and northerly by said boundary to the
eastern boundary of map U-9 Lot 1; thence continuing northerly by said
boundary to the southern boundary of the CMP transmission line corridor
16
thence northeasterly across said corridor to the northwestern boundary of map
R-1 Lot 16; thence northeasterly by said boundary to the southern boundary
of the Route 1 right-of-way; thence easterly along said right-of-way to the Bath
town line; thence southerly along said line to the north side of State Road;
thence westerly along said Road to the point of beginning.
G.
RESOURCE PROTECTION OVERLAY ZONE
Although all the boundaries of this overlay zone are not shown on the Land
Use District and Overlay Zone Map, the Resource Protection Overlay Zone,
as described in this subsection is currently in effect. Boundaries of this overlay
zone are as described in the applicable portion(s) of this subsection. When
necessary, determinations of boundaries shall be made on the ground by the
Code Enforcement Officer.
This overlay zone includes areas in which development would adversely affect
water quality, productive habitat, biological ecosystems, or scenic and natural
values. This overlay zone shall include the following areas:
1. Areas within 250 feet, horizontal distance of the UPLAND EDGE of
the WETLANDS located in the northeastern corner of West Bath. Said
WETLAND is known as Whiskeag and is fed by New Meadows Creek.
2. Areas within 75 feet, horizontal distance, of the normal high-water line
of New Meadows Creek and Back Cove Creek, and all WETLAND
abutting said creeks.
3. Areas within the Shoreland Overlay Zone of two (2) or more
contiguous acres with sustained slopes of 20% or greater.
4. Areas of two (2) or more contiguous acres supporting WETLAND
vegetation and hydric soils, which are not part of a freshwater or
COASTAL WETLAND as defined and which are not surfacially
connected to a WATER BODY during normal spring high water.
5. Habitat for species appearing on the official State or Federal lists of
endangered or threatened species; high and moderate value deer
wintering areas and travel corridors as defined by Department of
Inland Fisheries and Wildlife; Areas within 250 feet, horizontal
distance, of the upland edge of freshwater wetlands, salt marshes and
salt meadows, and wetlands associated with great ponds and rivers
which are rated "moderate" or "high" value waterfowl and wading bird
habitat, including nesting and feeding areas, by the Maine Department
of Inland Fisheries and Wildlife (MDIF&W) that are depicted on a
Geographic Information System (GIS) data layer maintained by either
MDIF&W or the MDEP as if May 1, 2006.
6. For the purpose of this paragraph "wetlands associated with great
ponds and rivers" shall mean areas characterized by non-forested
wetland vegetation and hydric soils that are contiguous with a great
pond and river; and have a surface elevation of below the water level
17
of the great pond or river during the period of normal high water.
"wetlands associated with great ponds or rivers" are considered to be
part of that great pond or river. PUT IN STANDARD FROM
DEFINITIONS
H. SHORELAND OVERLAY ZONE
1. General - The Shoreland Overlay Zone includes all land subject to
shoreland zoning, as required by 38 M.R.S.A., sections 435-448, and
applies to all land areas within 250 feet, horizontal distance, of the
normal high-water line of any GREAT POND, river or salt WATER
BODY; within 250 feet, horizontal distance, of the UPLAND EDGE of
a COASTAL or FRESHWATER WETLAND; and within 75 feet,
horizontal distance, of the normal high-water line of a STREAM. The
Shoreland Overlay Zone also applies to any STRUCTURE, such as a
dock, wharf or pier or other STRUCTURE extending beyond the
normal high-water line or within a WETLAND.
2. Relation to Underlying Districts - Within the Shoreland Overlay Zone,
all underlying district designations and regulations under this Land
Use Ordinance remain in effect and additional permitted use
standards and performance standards, also contained in this
Ordinance, are in effect.
3. Conflicts - Where there is a conflict between the standards of the
underlying district and the standards that apply in the Shoreland
Overlay Zone and/or the Resource Protection Overlay Zone, the more
restrictive standards shall apply.
4. Parts of West Bath included in the shoreland Overlay Zone
a. Oceanfront and Riverfront Areas - Land adjacent to tidal waters as
described in paragraph 1 of this subsection, including the tidal
POND east of the Berrys Mill Road crossing of Mill Cove;
b. WETLANDS - The Shoreland Overlay Zone surrounds the
following WETLANDS, as defined in Article VII of this Ordinance. Its
width, measured horizontally from the UPLAND EDGE of these
WETLANDS, is 250 feet.
c. The FRESHWATER WETLAND located in the eastern-most
portion of the Town, east of Berrys Mill Road, north of Campbells
Pond Road, southeast of the Lily Pond, and intersected by the
eastern end of the straight section of east-west- oriented Town
boundary line;
18
d. The FRESHWATER WETLAND east of Fosters Point Road and
adjacent to the STREAM flowing into Back Cove for most of its
length between State Road (Old Route 1) and Hill Road;
e. The FRESHWATER WETLAND adjacent to the STREAM that runs
along the eastern Town boundary south of State Road (Old Route
1), east of Berrys Mill Road, and north of the western end of the
straight section of east-west-oriented Town boundary line;
f. The Mill POND and adjacent WETLAND south of the crossing of
the Old Bath Road and the railroad tracks in the northeastern-most
portion of the Town;
g. The FRESHWATER WETLAND adjacent to the Lily POND
h. The FRESHWATER WETLAND on both sides of Back Cove Creek
extending from its northern end just south of the State Road to its
southern end north of the Hill Road;
The COASTAL WETLAND at the north end of Berrys Mill Pond.
i. STREAMS - The Shoreland Overlay Zone includes the land on both
sides of the following STREAM, as the term is defined in Article IX of
this Ordinance. Its width is 75 feet measured horizontally, from the
normal high water line of the STREAM on each side of the
STREAM:The STREAM flowing from Campbells Pond to Dam Cove;
i. GREAT PONDS - The Shoreland Overland Zone includes the land
surrounding the following GREAT PONDS classified GPA. Its width,
measured horizontally from normal high-water line, is 250 feet.
i.
Campbells Pond and the adjacent WETLAND at its
northern end;
ii.
Winnegance Pond and its adjacent WETLANDS.
j. All other areas which fall within the description contained at 38
M.R.S.A. § 435 as amended.
I.
SPECIAL INDUSTRIAL AND TRANSPORTATION OVERLAY ZONE
This overlay zone is for Special Industrial and Transportation Uses requiring
special provisions governing isolation and screening for reasons of safety
and/or inconsistency with other uses. This overlay zone shall include the
following areas in the Business & Commercial District:
19
1. New Meadows Road - Beginning at the northwest corner of New
Meadows Road and the State Road; thence northerly along the west
side of New Meadows Road to the south side of Route 1; thence
westerly along the south side of Route 1 to a point 250 feet from New
Meadows Lake; thence southerly paralleling said lake to the north side
of the State Road; thence easterly to the point of beginning.
2. Fosters Point Road - The portions within District 4. Business &
Commercial of map U-11 LOTS 1 and 35 and map U-12 LOTS 9, 10,
10A, 10B, 11, 11A, 11B, 16, and 16A
3. State Road - Map U-7 LOT 9A on the north side of the State Road
and map U-11 LOT 19 on the opposite side of said road.
4. Arthur J. Reno Sr. Road - The portions of lots within District 4.
Business & Commercial that are also within 500' of the Arthur J. Reno
Sr. Road and Wood Lot Road but are more than 500' from the State
ROAD.
Special Industrial and Transportation Use facilities legally existing as
of June 7, 2003, are not subject to the new standards, however any
change or expansion of a facility would be subject to the new
standards.
J. UNCERAINTY OF DISTRICT BOUNDARIES
When the Code Enforcement Officer cannot determine the location of a district
boundary, the Code Enforcement Officer may refuse action, and the Board of
Appeals, upon request, shall interpret the location of the district boundary with
reference to the scale of the Land Use Map and the purposes set forth in all
relevant provisions of this Ordinance.
2.2
USE REGULATIONS AND REQUIREMENTS
A. Table of Uses
No Building, STRUCTURE, or land shall be used or occupied except for the
purposes permitted in the district or overlay zone as set forth in the
accompanying Table of Use regulations or as provided for elsewhere in this
Ordinance.
All uses listed in this section are Major Developments, as defined under Site
20
Plan Review, that require site plan reviews for approval.
For Minor Developments, as defined under Site Plan Review, structures
changing the use or having an addition to a non-residential use are only
permitted if the corresponding use is permitted in the Table below regardless
of the municipal permitting authority. If the Minor Development is proposing
a changed use to something that the Table lists as "PB", the site plan review
is done through the Code Enforcement Officer unless they request a public
hearing through the Planning Board, as noted in the Minor Development
procedure.
A use listed in the Table of Use Regulations is permitted in any district or
overlay zone denoted by the following:
- Yes- No permit is required but still must comply with local and state
requirements if applicable.
- CEO- Permitted use which requires a site plan reviewed by the Code
Enforcement Officer
- PB- Permitted use which requires a site plan reviewed by the Planning
Board
- No- Use is not permitted
Name of District or Overlay Zone
Abbreviation in Table
Shoreland Overlay Zone
SOZ
Stream Protection Overlay Zone
SP
Resource Protection Overlay Zone
RP
High Density Coastal
HDC
Residential
R
Rural Residential
RR
Mobile Home Park
MHP
Business and Commercial
BC
Urban Development Park
UDP
Table 2.1: Land Use Matrix
A. RESIDENTIAL
Shoreland Zone
Land Use Districts
SOZ
SP
RP
HDC
R
RR
MHP
BC
UDP
21
1. Single-family
and duplex units
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
2. Accessory
Dwelling Unit
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
3. Accessory
additions such
as, but not
limited to,
garages, solar
systems for
personal use,
septic systems,
and wells,
swimming pools,
personal
storage.
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
4. New multi-family
housing between
3-4 units per
structure.
No
No
No
CEO
CEO
CEO
CEO
CEO
CEO
5. New multi-family
housing of 5 or
more units per
structure
No
No
No
No
No
No
No
CEO
No
6. Elderly housing
that includes
assisted living
services,
congregated
care services,
nursing home
services, or
hospice
services, without
restriction on the
number of
dwelling units
per structure.
No
No
No
No
No
No
PB
PB
PB
7. Group homes
and halfway
houses
No
No
No
No
No
No
No
PB
PB
8. Mobile Homes
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
9. Mobile Home
Parks
No
No
No
No
No
No
PB
No
No
22
10. Piers, wharves,
docks,
breakwaters,
causeways,
marinas,
bridges, and
uses projecting
into water
bodies.
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
11. Subdivisions and
Cluster
Subdivisions
PB
No
PB
PB
PB
PB
PB
PB
PB
B. INSTITUTIONAL,
RECREATIONAL,
EDUCATIONAL
Shoreland Zone
Land Use Districts
SOZ
SP
RP
HDC
R
RR
MHP
BC
UDP
1. Places of
Worship
No
No
No
No
PB
PB
PB
PB
PB
2. Schools
No
No
No
No
No
PB
No
PB
PB
3. Trade Schools
No
No
No
No
No
No
PB
PB
PB
4. Municipal and
county
governmental
buildings and
related or
supporting
facilities
including, but
not limited to,
libraries and
museums.
No
No
No
No
No
PB
PB
PB
PB
5. Cemeteries, other
than family burial
plots
No
No
No
No
PB
PB
PB
PB
PB
6. Publicly-owned
parks and
playgrounds.
No
No
No
No
CEO
CEO
CEO
CEO
CEO
7. Public Utilities,
PB
PB
PB
PB
PB
PB
PB
PB
PB
23
excluding utility
office
8. Private non-profit
community center
buildings, adult
education
centers, or other
similar facilities
No
No
No
No
No
No
PB
PB
PB
9. Child Care for up
to twelve (12)
attendees
No
No
No
CEO
CEO
CEO
CEO
CEO
CEO
5. Child Care with
no limits
No
No
No
PB
PB
PB
PB
PB
PB
6. Infirmaries and
Hospitals
No
No
No
No
No
No
PB
PB
PB
7. Child Care
No
No
No
No
No
No
CEO
CEO
CEO
8. Country clubs,
golf courses,
swimming pools,
tennis courts, or
other
recreational club
facilities
No
No
No
No
No
No
PB
PB
PB
9. Public and
private
recreation areas
involving
minimum
structural
development
(e.g. trails,
baseball fields)
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
CEO
10. Individual Private
Campsite for
non-commercial
use.
No
No
CEO
CEO
CEO
CEO
No
No
No
11. Public and
private
campgrounds for
commercial use
No
No
No
No
PB
PB
No
PB
PB
12. Small non-
residential
facilities for
scientific,
educational, or
nature
Yes
No
CEO
Yes
Yes
Yes
Yes
Yes
Yes
24
interpretation
purposes
13. Solid waste
transfer and
recycling
building and
facilities
No
No
No
No
No
No
No
PB
No
C. RESOURCE
UTILIZATION
Shoreland Zone
Land Use Districts
SOZ
SP
RP
HDC
R
RR
MHP
BC
UDP
1. Agriculture,
orchards, and
horticulture
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
2. Farms
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
3. Domesticated
chickens
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
4. Aquaculture
and landside
fish harvesting
operations
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
5. Harvesting of
wild crops
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
6. Forest
management,
silvi-culture,
Timber
Harvesting,
and temporary
on-site wood
processing.
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
7. Wildlife
management
practices
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
8. Extractive
industries,
mineral
explorations,
and quarries.
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
D. OFFICES,
LABORATORIES,
AND
COMMUNICATIONS
Shoreland Zone
Land Use Districts
SOZ
RP
HDC
R
RR
MHP
BC
UDP
25
SP
1. Business,
financial, or
professional
offices
No
No
No
No
No
No
PB
PB
PB
2. Medical,
psychiatric, or
other health
services for the
examination or
treatment of
persons as
outpatients.
This may
include
laboratories or
research
facilities.
No
No
No
No
No
PB
PB
PB
PB
3. Radio,
television, or
other wireless
communication
s buildings and
facilities. This
does not
include
communication
towers.
No
No
No
No
No
No
PB
PB
PB
4. Communication
Towers
No
No
No
No
No
No
PB
PB
PB
5. Home
Occupations
No
No
No
No
CEO
CEO
CEO
CEO
CEO
E. COMMERCIAL
AND
INDUSTRIAL
USES
Shoreland Zone
Land Use Districts
SOZ
SP
RP
HDC
R
RR
MHP
BC
UDP
26
1. Vehicle
services and
stores.
No
No
No
No
No
No
PB
PB
PB
2. Bank and other
financial
institutions
No
No
No
No
No
No
No
PB
PB
3. Retail and
wholesale
stores with no
manufacturing
or assembly on
the premises
No
No
No
No
No
No
PB
PB
PB
4. Commercial
studios for arts
and handcrafts
No
No
No
No
No
No
CEO
CEO
CEO
5. Service
businesses
such as, but
not limited to,
barber shops,
dry cleaning,
laundromats,
beauty parlors,
tailoring shops,
printing stores,
and caterers.
No
No
No
No
No
No
PB
PB
PB
6. Veterinary
Establishments
, kennels, pet
shop
No
No
No
No
No
PB
No
PB
PB
7. Places for
repair, sale,
rental, and/or
storage of
boats
No
No
No
No
No
No
PB
PB
PB
8. Indoor and
outdoor places
restaurants.
No
No
No
No
No
No
PB
PB
PB
9. Motels, Hotels,
and Inns
No
No
No
No
No
No
PB
PB
PB
10. Bed and
Breakfast
Establishments
No
No
No
No
No
No
CEO
CEO
CEO
11. Enclosed
storage facility
No
No
No
No
No
No
No
PB
PB
12. Flea Markets
No
No
No
No
No
No
No
No
PB
13. Industrial,
manufacturing,
and assembly
No
No
No
No
No
No
PB
No
PB
27
14. Wholesale
businesses
and storage
No
No
No
No
No
No
No
PB
PB
15. Trucking and
freight
terminals
No
No
No
No
No
No
No
PB
No
16. Bulk petroleum
and propane
facilities and
other
Hazardous
substances
No
No
No
No
No
No
No
PB
No
17. Large Solar
Energy
Systems
No
No
No
No
No
No
No
PB
PB
18. Small Wind
Energy
Systems
PB
No
No
PB
PB
PB
PB
PB
PB
19. Food Trucks
No
No
No
No
No
No
CEO
CEO
CEO
20. Junkyard
No
No
No
No
No
No
No
No
No
MINIMUM LOT STANDARDS
Notwithstanding any provisions in a local Ordinance to the contrary, all structures and
lots created after the adoption of this Ordinance shall meet the minimum lot standards
28
for the district in which they are located as shown in the following table. If a lot is legally
non-conforming, it is not required to meet the area or shore frontage of a legally
conforming lot.
Table 2.2. Minimum Lot Standards
District
Lot
Size
Road
Setback
Side &
Rear
Setback
Road
Frontage
Shore
Setback
Shore
Frontage
High Density
Coastal
(HDC)
1 Acre
56 ft
20 ft
137 ft
75 ft
125 ft
Residential
(R)
2 Acres
56 ft
20 ft
175 ft
75 ft
150 ft
Rural
Residential
(RR)
3 Acres
56 ft
20 ft
200 ft
75 ft
150 ft
Mobile Home
Park (MHP)
1 Acre
100 ft
35 ft
100 ft
75 ft
150 ft
Business and
Commercial
(BC)
1 Acre
56 ft
20 ft
150 ft
75 ft
150 ft
Urban
Development
Park (UDP)
1 Acre
50 ft
35 ft
100 ft
75 ft
150 ft
Notes associated with Dimensional Requirements
A. All setbacks are measured as the minimum horizontal distance irrespective of the
29
slope of the land, to the footprint of a structure or the vertical projection to ground
level of portions of the structure having usable volume or floor area, whichever
distance is smaller. Usable portions do not include eaves, decorative trim, flower
boxes, and trellises. Structures, which are only or principally roofs such as car ports,
shall have their setbacks measured from the vertical projection to ground of the
outermost portions of the structure. Road setbacks shall be measured from the
center of the traveled way. Setbacks apply to any structure with the exception of the
following: boundary fences and walls, shared driveways, right-of-way on boundary
lines, and small entities such as birdbaths and lampposts.
B. The minimum lot size requirement shall be met for each newly built dwelling unit
located on a parcel of land with the following exceptions:
1. Multiple units within a single structure in the Business Commercial (BC) or
Urban Development Park (UDP) shall be subject to the same minimum lot size
requirement as a single unit. By way of illustration, a new building in the BC or
UDP districts would require one (1) acre of land for each building that is
proposed; however, if multiple uses/units are proposed in the same building, the
lot hosting this structure will only need one (1) acre of land. All uses within the
structure are still subject to other local and state standards including access to
water and wastewater.
2. An Affordable Housing Development shall have a density of two and a half (2.5)
times the minimum lot size that is otherwise allowed in that location if it complies
with the standards found under Article V. This is not applicable to units in the
Shoreland Zone.
3. One (1) Accessory Dwelling Unit per lot shall be exempt from the minimum lot
size requirements with the exception of setback requirements. This is not
applicable to units in the Shoreland Zone.
30
ARTICLE III. SITE PLAN REVIEW
3.1.
Project Classes. The Code Enforcement Officer shall classify each
development as one of three classifications: Minimal Impact Development,
Minor Development, or Major development.
A. Minimal Impact Development. Minimal Impact Development shall include
those projects involving the single-family homes and change of ownership of
an existing development which does not involve exterior construction or
alterations excluding changes to signs. Minimal Impact Developments will not
require site plan review but will still be required to have an approved permit
issued by the CEO.
B. Minor Development. Minor Development shall include those projects
involving:
1. The construction of multi-unit residential buildings
2. The conversion from one use to another without enlargement of the
gross floor area, provided that the new use is allowable in the lot's
current district.
3. Exterior additions/alterations to non-residential use
4. Only the installation of outdoor impervious surfaces
Minor Developments will not require public hearing but will still be required
to have an approved permit issued by the CEO. However, applications may
be sent to the Planning Board for further review at the discretion of the
CEO.
C. Major Developments. Major Development shall include those projects
involving:
1. The construction of non-residential buildings
2. The conversion from one use to another that also enlarges the
gross floor area, provided that the new use is allowable in the
lot's current district as determined by the Land Use Matrix.
3. Projects involving the establishment of a campground,
communications tower, or other projects in the Land Use
31
Matrix not classified as a Minimal Impact or Minor
Development.
Major Developments will require site plan approval based on
Planning Board approval. All uses listed as "PB" in the Land Use
Matrix that are not a change of use, Minor Developments
designated by the CEO as needing review, or a proposal that
the CEO determines matches the category of 3.1(c) above shall
be deemed as a Major Development.
3.2.
Procedure: The following procedure shall govern the submission and
review of applications for site and building plans, other than subdivisions
3.2.1. Pre-Application Meeting
A. Prior to submitting an application for development, the developer or his
authorized agent should appear informally at a regular or special meeting
of the planning board to discuss the proposed development.
B. The Planning Board shall prepare an agenda for each regularly scheduled
meeting. Applicants shall request to be placed on the Planning Board's
agenda at least one week in advance of a regularly scheduled meeting by
contacting the Town Clerk. The Planning Board shall have up to 60 days
to review an application submitted to the Town Clerk. Applicants who
attend a meeting, but who are not on the Planning Board's agenda or
missed the deadline, may be heard but only after all agenda items have
been completed and if a majority of the Planning Board votes to amend
the agenda.
C. The developer shall present to the Planning Board, at this time, for
informal review and comment, a sketch plan of the proposed
development. The sketch plan shall consist of a rough outline of the
proposed development, and may be a free hand, penciled sketch of the
parcel, showing the proposed layout of buildings, roads, and other
features which may be of assistance to the Planning Board in making its
determinations.
D. The Planning Board may request that the developer arrange for an
inspection of the site with the Planning Board, or an individual appointed
by the Board Chair to act as the Board's representative.
E. No binding commitments shall be made between the developer and the
Planning Board at this stage. The purpose of the pre-application meeting
shall be to understand what is proposed, what is possible, and what is
32
acceptable.
3.2.2. Fees
A. All applications for Site Plan Review shall be accompanied by a non-
refundable application fee as listed in the Fees Schedule payable by check
to the Town.
3.2.3 Application
A. The application and fee shall be emailed or mailed to the West Bath Town
Clerk for the Planning Board to review fourteen days prior to a regularly
scheduled Planning board meeting. Within 30 days of the filing of an
application, the planning board shall notify the applicant in writing either that
the application is a complete application or, if the application is incomplete,
the specific additional material needed to make a complete application. After
the Planning Board has determined that a complete application has been
filed, it shall notify the applicant in writing and begin its review of the
proposed development.
B. The Planning Board may hold a public hearing within 14 days of the filing
of the completed application. The Town of West Bath, in addition to
notifying abutting landowners, shall publish the time, date and place of
hearing in two or more of the following ways at least seven days prior to
the meeting:
1. At least one publication in a newspaper of area-wide circulation;
2. Posted on the town-owned sign in front of the West Bath Fire
Department; or
3. Posted in the lobby of the West Bath Town Office.
C. Within 30 days of the public hearings or 60 days of receiving a completed
application, the Planning Board shall either approve, approve with
conditions, or disapprove the application. The time limit for review may be
extended by mutual agreement between the Planning Board and the
applicant.
D. Within fourteen (14) days of reaching their decision, the Planning Board
shall notify the applicant in writing of any action taken and the reason for
taking such action.
3.2.3. Final Approval
Approval shall expire one (1) year from the date of final approval unless the
33
applicant has started substantial construction. The Planning Board may extend
final approval for one (1) year. Applicants shall be required, as a condition of any
extension, to re-estimate improvement costs and to resubmit revised bonds or
letters of credit in accordance therewith.
3.2.4. Submissions
The Site Plan shall consist of one or more maps or drawings drawn to scale of
not more than 100 feet to the inch. Plans for developments containing more than
75 acres may be drawn at a scale not more than 200 feet to the inch. Plans shall
be no larger than 24 by 36 inches in size and shall have a margin of two (2)
inches of the borderline of the left side for binding and a one-inch margin outside
the border along the remaining sides. Space shall be reserved thereon for
endorsement by the Planning Board. One reproducible, stable based
transparent original to be recorded at the Registry of Deeds and three (3) copies
of the plan shall be submitted. In addition, one (1) copy of the Site Plan, reduced
to a size of 8 and 1/2 by 11 inches and all accompanying information shall be
mailed to the Planning Board no less than seven (7) days prior to the meeting.
The application for approval of the Site Plan shall include, as a minimum, the
following information: The Planning Board may waive any of the submission
requirements when it determines they would not be applicable or necessary, due
to the nature of a specific development proposal.
A. Plot plan(s) or map(s) including the following:
1. Name and address of any applicant, his authorized agent, and name
of proposed development and any land within 500 feet of the proposed
development in which the applicant has title or interest;
2. A copy of high intensity soils map
3. Town tax map and lot number and names and addresses of abutting
landowners and any others specified by the Planning Board;
4. Perimeter survey of the parcel made and certified by a registered land
surveyor relating to reference points, showing true north point, graphic
scale, corners of parcel and date of survey and total acreage. Areas
within 200 feet of the proposed development site shall be included;
5. Existing and proposed locations and dimensions of any utility lines,
sewer lines, water lines, easements, drainage ways and public or
private rights- of-way;
6. Location, ground floor area and elevations of buildings and other
structures on the site; including all existing and proposed setback
dimensions;
34
7. Location and dimensions of on-site pedestrian and vehicular access
ways, parking areas, loading and unloading facilities, design of ingress
and egress of vehicles to and from the site on to the public roads and
curb and sidewalk lines;
8. Landscape plan showing location, type and approximate size of
plantings and location and dimensions of all fencing and screening;
9. Topography by actual survey, indicating contours at five-foot intervals
for slopes averaging five percent or greater and at two-foot intervals
for land of lesser slope, in relation to mean sea level.
10. Location of aquifers and aquifer recharge areas, if mapped;
11. The size, location, and direction and intensity of illumination of all
major outdoor lighting apparatus and signs;
12. The type, size and location of all incineration devices;
13. The type, size and location of all machinery likely to generate
appreciable noise;
14. The location, type, and size of all existing and proposed catch basins,
storm drainage facilities, streams, and water courses, and all utilities,
both above and below ground. The amount and type of any raw,
finished or waste materials to be stored outside of roofed buildings,
including their physical and chemical properties, if appropriate.
B.
Written statement or statements including, as a minimum, the following:
1. Evidence by the applicant of the title and interest in the land that the
application covers;
2. A description of the proposed uses to be located on the site, including
quantity and type of residential unit, if any;
3. Total floor area and ground coverage of each proposed building and
structure and percentage of lot covered by each building or structure
4. Summary of existing and proposed easements, restrictions and
covenants placed on the property;
5. Method of solid waste disposal;
6. Erosion and sedimentation control plan;
35
7. Statement of financial capacity which should include the names and
sources of the financing parties, including banks, government
agencies, private corporations, partnerships and limited partnerships
and whether these sources of financing are for construction loans or
long-term mortgages or both;
8. A plan for fire protection as reviewed by the Fire Chief.
9. If public water and/or sewer are to be used, a statement from the water
and/or sewer district or utility as to the availability of public water and/or
sewer lines;
10. A statement from either the Town's Consulting Engineer, or Road
Commissioner that the proposed Road construction will meet Town
specifications and a statement of what impact will be on existing Town
Roads
11. An estimate of the date when construction will start and when the
development will be completed;
12. Any other information or data necessary for proper review and
conformance with all requirements set forth in the municipal
Subdivision and General Review Standards. Appropriate places for
the signatures of the Site Review Board.
See General Standards Article below for Additional Requirements.
3.3 General Performance Standards for Site Plan Review
3.3.1 Buffers and Screening Standards
A. Vegetative Buffer Strips. All lots, except for those in the Urban
Development Park District (UPD) shall have vegetative buffer strips with a
minimum depth of 20 feet along their road and side boundaries except for
designated access points along U.S. Route One where the vegetative
buffer strips shall be 100 feet in width measured from the edge of the right
of way (except at interchanges where the width shall be 40 feet).
B. Where side boundaries lie within a traveled way across private property,
the side buffer strip shall be set back from the side boundary of the lot, or
from the near edge of the traveled way's right-of-way when it is within the
applicant's property at least 8 feet. The Planning Board may require a
greater setback for the side buffer where it determines this is necessary to
accommodate the full buffer strip and the potential future development of
36
the traveled way as a road meeting Article III, section 3.10 of this
Ordinance.
C. Side boundary strips having natural vegetative screening shall not be
disturbed without Planning Board approval. When a natural screen does
not exist on a side boundary, a side buffer planting plan may need to be
submitted to the Planning Board for approval.
D. A vegetative buffer strip must retain existing, undisturbed predevelopment
vegetation to the maximum extent possible. Where the area has been
disturbed before or during construction, or where existing vegetation is
insufficient to provide a buffer, the Planning Board shall require plantings
as reasonably necessary to fulfill the function of the vegetative buffer strip.
E. The Planning Board may modify side buffer requirements to the extent
necessary to accommodate shared access and/or shared parking areas
and other common facilities.
F. The depth of a vegetative buffer strip alongside a road shall be measured
beginning at the edge of the right-of-way or at the outer edge of the road's
shoulder or drainage ditch, whichever is furthest from the center of the
traveled way.
G. Buffers in the form of fences, landscaping, berms and mounds shall be
required for all commercial and business uses abutting residential uses
and to minimize any adverse impacts or nuisance on the site or on
adjacent properties.
H. Buffers shall be considered in the following areas or for the following
purposes.
1. Along property lines, to shield various users from each other;
2. Along interior roads running parallel to roads exterior to the site, to
prevent confusion, particularly at night;
3. Parking areas, garbage collection areas, and loading and unloading
areas
4. To block prevailing wind patterns and to stop wind-borne debris from
leaving the site.
37
I. Buffers shall be sufficient to shield structures and uses from the view of
incompatible abutting properties and traveled ways, and to otherwise
prevent any nuisances.
J.
Exposed storage areas, service areas, exposed machinery installations,
and gravel extraction operations, truck loading areas, utility buildings and
structures, and areas used for the storage or collection of discarded
automobiles, auto parts, metals or any other articles of salvage or refuse,
and similar accessory areas and structures, shall have sufficient setbacks
and screening to provide an audio/visual buffer sufficient to minimize their
adverse impact on other land uses within the development site and
surrounding properties, such as stockade fence or a dense evergreen
hedge six (6) feet or more in height.
K. Where a potential safety hazard to children would be likely to arise,
physical screening sufficient to deter small children from entering the
premises shall be provided and shall be maintained in good condition.
L. Natural features shall be maintained wherever possible to provide an
audio/visual buffer sufficient to minimize their adverse impact on other
land uses within the development site and surrounding properties.
M. Where a potential safety hazard to children would be likely to arise,
physical screening sufficient to deter small children from entering the
premises shall be provided and shall be maintained in good condition.
N. Natural features shall be maintained wherever possible to provide a buffer
between the proposed development and incompatible abutting properties
and public roadways. When natural features such as topography, gullies,
stands of trees, shrubbery, rock outcrops do not exist or are insufficient to
provide a buffer, other kinds of buffers shall be considered.
O. Evergreens can be used as buffers, provided they are planted properly. An
evergreen buffer requires two (2) or three (3) rows of staggered plantings.
The rows should be five (5) feet apart and the evergreens planted four (4)
feet on center.
P. Fencing and screening shall be durable and properly maintained at all
times by the owner.
Q. Fencing and screening shall be so located within the property line to allow
access for building maintenance on both sides without intruding upon
abutting properties.
38
R. All buffer areas shall be maintained in a neat and sanitary condition by the
owner.
3.3.2. Setback Reduction Plan:
This section applies to new and expanded uses in all districts other than those in
the Urban Development Park District, where no buffers are required.
A. The purpose of the Setback Reduction Plan is to allow the Buffer and
Screening to be reduced if a plan for establishing a landscaped buffer is
agreed to by the applicant and approved by the Planning Board.
B.. The landscaped buffer, at a minimum, must meet the following criteria:
1. The buffer may include plant materials such as trees or shrubs, walls
or fences, and earthen berms, or a combination thereof.
2. The buffer must be sufficient in density and height so as to screen
noise, vibration, light, or other visual nuisances in a manner exceeding
that of the Setback or Yard Area required without a Setback Reduction
Plan.
3. The buffer must be visually pleasing and effective year-round.
4. The buffer must be maintained.
The burden of proving that these criteria are met is that of the applicant.
C. The Setback Reduction Plan will be reviewed by the Planning Board as
part of the Site Plan Review.
3.3.3. Refuse Disposal.
The applicant shall provide for the disposal of all solid and liquid wastes on a
timely basis and in an environmentally safe manner. The Planning Board shall
consider the impact of particular industrial or chemical wastes or byproducts
upon the Town sanitary landfill (in terms of volume, flammability, or toxicity) and
may require the applicant to dispose of such wastes elsewhere, in conformance
with all applicable State and Federal regulations.
Dumpsters may not be located in Yard Areas or parking spaces and must be
screened from abutting properties, public streets, and the New Meadows River.
The Planning Board may require the applicant to specify the amount and exact
nature of all industrial or chemical wastes to be generated by the proposed
operation.
3.3.4. Business and Commercial Signs
39
A. General Regulations: No sign may be erected, placed, established,
painted, created, or maintained in the town of West Bath except in
conformance with the standards, definitions, procedures, exemptions, and
other requirements of this Ordinance
B. Signs and Statuary. Any object including statuary and sculpture intended to
attract patrons shall be considered as signage for the purposes of this
Ordinance and shall be subject to the proceeding requirements.
C. Number and Size of Signs. A commercial lot with a single business can
have two (2) exterior signs, one (1) freestanding and one (1) building
mounted, each with a maximum area of twenty-five (25) square feet. The
freestanding sign can have lettering on both sides and shall have a
setback of at least ten (10) feet from paved road surfaces. Subsidiary
signs such as those indicating credit card acceptance or notices may be
directly attached to a freestanding sign but their area(s) plus that of the
freestanding sign must not exceed the maximum allowed area.
Businesses on corner lots at the intersection of two (2) major roads may
have two (2) freestanding signs, one (1) on each road, if it can be shown
that a single sign cannot be seen from the roads or might prove distracting
to drivers. The building mounted sign shall be single sided and mounted
on the primary building. For purposes of this Ordinance, banners, and
flags, other than those of the nation and state, shall be considered as
signs. Residential subdivisions with more than five (5) lots may have a
single sided sign with the name of the subdivision subject to architectural
review. Said sign shall not exceed twenty-five (25) square feet in area and
can incorporate lot identification and real estate contact information for a
period of one (1) year.
D. Sign Area and More Than One (1) Business Per lot. In the case where
there is more than one business on a single lot, the maximum area of the
freestanding sign is increased by five (5) square feet for each additional
individual business. The freestanding sign can be configured as a vertical
array with a separate sign of each business provided that the total allowed
area is not exceeded. Each business can have its own building mounted
single sided sign provided that it does not exceed twenty-five (25) square
feet in area.
E. Lighting of Signs. The lighting of permanent signs and exterior advertising
structures and features shall be limited to white floodlights directed at said
objects. Any lighting of permanent signs shall meet the standards of Article
3.3.7. of this Land Use Ordinance .
40
F. Directional Signs. Additional small signs required for the function of a
business, such as entrance and parking designators, may be allowed
subject to Planning Board approval.
G. Temporary Signs. All temporary signage on a property such as moveable
objects without lettering, banners, commercial flags, and notices shall not
have a combined area exceeding fifteen (15) square feet. Temporary
signage other than real estate signs may be displayed for not more than
half the daylight hours in a given thirty (30) day period and are subject to
fees scheduled by the Town of West Bath. One real estate sign per
property not exceeding eight (8) square feet in area including any riders
may be posted on the property or at the beginning of a private road
accessing said property. In the latter case if the property is not readily
visible or identifiable from the sign a secondary sign not exceeding two (2)
square feet in area is allowed at the property.
H. Signs and Sight Lines. No sign shall interfere with the road access sight
line distance as specified by the street design standards of Article III
section 3.10 of this Land Use Ordinance.
I. Maximum Height. No part of any sign shall exceed a height of thirty-five (35)
feet above the ground surface.
J. Gas Station Signs. Gas Station signs may have gasoline product pricing
attached to or incorporated in permitted freestanding signs. Said pricing
signage shall not exceed ten (10) square feet in area per sign surface and
shall be exempt from total sign area computations
3.3.5 Noise
A. This section applies to new or expanded non-residential uses.
B. The proposed development shall not increase noise levels to the extent that
abutting or nearby properties are adversely affected. To comply with this,
the development shall meet the following standards.
C. The maximum permissible sound-pressure level of any continuous, regular,
or frequent source of sound produced by any activity must be limited by
the period listed as follows. Sound levels will be measured at least 4 feet
aboveground at the lot line of the noise source (Sound-pressure-level
Limits are measured in dB scale)
41
7 a.m. - 8 p.m.: 60
8 p.m. - 7 a.m.: 50
D. The levels specified may be exceeded by 10 dBA for a single 15-minute
period per day. Noise will be measured by a meter set on the A-weighted
response scale, fast response. The meter must meet the American
National Standards Institute's (ANSI S1.4-1961) American Standards
Specifications for General Purpose Sound Level Meters.
E. The following uses and activities are exempt from this sound-pressure-level
regulation:
1. Noise created by building or facility construction, forestry, agricultural,
and temporary maintenance activities between 7:00 a.m. and 8:00 p.m.
2. The noises of safety signals, warning devices, emergency pressure-
relief valves, and any other emergency activity
3. Traffic noises on public streets
4. Noise from live entertainment within the provisions contained in Article
V, section 5.12.
3.3.6. Sanitary Provisions
A. Toilet Facilities for Workers: Suitable toilet facilities shall be provided and
maintained in a sanitary condition for the use of workers during
construction.
B. Subsurface Sewage Disposal Systems: All subsurface sewage disposal
systems shall be installed in conformance with the State of Maine
Subsurface Wastewater Disposal Rules and the following:
C. New Meadows River Discharges: Treated industrial waste discharges to the
New Meadows River shall be prohibited.
3.3.7. Lighting
A. The maximum height of free-standing lights shall be the same as the
principal building but not exceed 25 feet.
B. All lights shall be shielded to restrict the maximum apex angle of the cone of
illumination to 150 degrees.
C. Free-standing lights shall be so located and/or protected as to avoid being
damaged by vehicles.
42
D. Lighting should be located along streets, parking areas, at intersections and
crosswalks and where different circulation systems merge, intersect or
divide.
E. Stairways, sloping or rising paths, building entrances, and building exits
require illumination.
F. Display lighting and parking area lighting shall be shielded and located and
maintained so as not to create or constitute a hazard or nuisance to the
traveling public or to neighbors.
G. All exterior lighting shall be designed to not exceed 0.05 lumen within 10' of
neighboring residential properties.
H. All commercial, institutional and other similar activities shall provide
adequate exterior lighting for occupants, customers, and employees.
3.3.8 Parking and Entrance Design Standards:
A. Location on the Property
All business and commercial parking areas whether paved, coated, gravel,
dirt, grass or designated by plan, shall be located so as to be contained
behind the required vegetative buffer strips along the front and sides of the
property. The buffer strip shall be crossed by pavement only as necessary
to provide access to the property. Exterior vehicle display and/or storage
areas shall be considered as parking for purposes of this Ordinance. This
paragraph shall apply to all business and commercial parking areas,
including the expansion of existing parking, created after July 1, 1998.
B. Access. There shall be adequate provisions for ingress and egress to all
parking spaces. The width of access drives or driveways shall be
determined as part of Site Plan Review depending on use, topography,
and similar considerations.
C. Size of Aisles. The width of aisles providing direct access to individual
parking stalls shall be in accordance with the requirements set forth below.
Only one-way traffic shall be permitted in aisles serving single-row parking
spaces placed at an angle other than ninety (90) degrees.
Parking Angle
(degrees)
Description
Minimum
Aisle Width
(feet)
0°
Parallel parking
12
30°
degree parking
12
43
D. Sidewalk and Curbing. Sidewalks between parking areas and principal
structures along aisles and driveways and wherever pedestrian traffic shall
occur, shall be provided with a minimum width of four (4) feet of passable
area and shall be raised six (6) inches or more above the parking area
except where the sidewalks cross roads or driveways. Guardrails or wheel
stops, permanently anchored to the ground, shall be provided where
appropriate. Parked vehicles shall not overhang or extend over sidewalk
areas unless additional sidewalk width of two and one half (2 1/2) feet is
provided to accommodate such overhang.
E. Marking and Delineation of Parking Areas. Parking stalls, driveways, and
aisles shall be clearly marked and delineated. The Planning Board may
require that certain areas be maintained for firefighting, other emergency
purposes, or accessible access and that such areas be appropriately
designated.
3.3.9. Street Design Standards
A. Streets
1. These design standards shall be met by all STREETS within
SUBDIVISIONS, and shall control roadway, shoulders, curbs,
sidewalks, drainage systems, culverts, and other appurtenances.
2. Proposed STREETS shall conform, as far as practical, to such
COMPREHENSIVE PLAN or policy statement as may have been
adopted, in whole or in part, prior to the submission of a preliminary
plan.
3. All STREETS in the SUBDIVISIONS shall be designed so that, in the
opinion of the Board, they will provide safe vehicular travel while
discouraging movement of through traffic.
4. The arrangement, character, extent, width, grade, and location of all
STREETS shall be considered in their relation to existing or planned
45°
degree parking
13
60°
degree parking
18
90°
degree parking
30
44
STREETS, to topographical conditions, to public convenience and
safety, and their appropriate relation to the proposed use of the land
to be served by such STREETS. Grades of STREETS shall conform
as closely as possible to the original topography so that cut and fill are
minimized while maintaining the grade standards above.
5. Where a SUBDIVISION abuts or contains an existing or proposed
ARTERIAL STREET, the Board may require reverse frontage (that is,
frontage on a STREET other than the existing or proposed ARTERIAL
STREET) with screen planting contained in a non-access reservation
along the rear property line, or such other treatments as may be
necessary for adequate protection of residential properties and to
afford separation of through and local traffic.
6. The PLANNING BOARD may require that SUBDIVISIONS containing
fifteen (15) LOTS or more shall have at least two STREET connections
with existing public STREETS or STREETS shown on the official map
if such exists, or STREETS on an approved SUBDIVISION Plan for
which a bond has been filled.
7. Design and Construction Standards. All STREETS in a SUBDIVISION
shall be designed and constructed to meet the following standards for
STREETS according to their classification as determined by the
PLANNING BOARD:
Item
Minor
Streets
Private
Roads
1. Minimum right-of-way
50'
33'
2. Minimum width of travel surface
24'
16'
3. Maximum grade
10%
10%
4. Maximum grade within 50 feet of intersections
5%
--
5. Minimum intersection angle
60°
60°
6. Width of shoulders
5'
--
7. Road base (minimum), gravel
18"
18"
8. Surfacing (gravel)
4"
4"
9. Road crown (minimum)
¼" per 1'
¼" per 1'
10. Sidewalks - minimum width (where required)
5'
--
45
11. Dead-end or cul-de-sac streets - radius of turn-around at
enclosed end
65'
25'
8. The centerline of the roadway shall be the centerline of the right-of-
way.
9. Dead End STREET. In addition to the design standards above, dead-
end STREETS shall be constructed to provide a cul-de-sac around
with the following requirements for radii: Property line 65 feet; outer
edge of pavement 50 feet. The Board may require the reservation of
the 20-foot EASEMENT in line with the STREET to provide
continuation of pedestrian traffic or utilities to the next STREET. The
board may also require the reservation of a 50-foot EASEMENT in line
with the STREET to provide continuation of the ROAD where future
SUBDIVISION is possible.
10. STREET Names, Signs and Lighting. STREETS which join and are in
alignment with STREETS of abutting or neighboring properties shall
bear the same name. Names of new STREETS shall not duplicate,
nor bear phonetic resemblance to the names of existing STREETS
within the Municipality and shall be subject to the approval of the
Planning Board. The developer shall reimburse the Municipality for the
costs of installing STREET name, traffic safety and control signs.
B. Grades, Intersections, and Sight Distances
1. Grades of all STREETS shall conform in general to the terrain, and
shall not be more than 10 percent for minor STREETS and private
ROADS, but in no case more than 5 percent within 50 feet of any
intersection.
2. All changes in grade shall be connected by vertical curves of such
length and radius as meet with the approval of the Planning Board so
that clear visibility shall be provided for a distance of two hundred (200)
feet.
3. Intersections of STREETS shall be at angles as close to 90 degrees as
possible and in no case shall two (2) STREETS intersect at an angle
smaller than 60) degrees. To this end where one STREET approaches
another between 60 to 90 degrees the former STREET should be
curved approaching the intersection.
4. STREET surfaces at intersections shall be designed to provide for curb
radii of not less than 25 feet or 90-degree intersections and thirty (30)
feet for intersections less than 90 degrees.
46
5. STREET intersections and curves shall be so designed as to permit
adequate visibility for both pedestrian and vehicular traffic. That portion
of any corner LOT which is necessary to allow 25-foot sight lines
between intersection STREETS shall be cleared of all growth (except
isolated trees) and obstructions above the level three feet higher than
the center line of the STREET. If directed, ground shall be excavated
to achieve visibility.
6. Cross (four-cornered) STREET intersections shall be avoided insofar
as possible, except as shown on the COMPREHENSIVE PLAN or at
other important traffic intersections. A minimum distance of 200 feet
shall be maintained between centerlines of side STREETS.
C. Business and Commercial District Access Management Standards
These standards shall apply to the ROAD surfaces, public rights of way and
land areas adjacent to the ROADS, in the business and commercial and
urban business and commercial districts with the goal that all DRIVEWAYS
shall be located to afford maximum safety to traffic, minimizing conflict with
traffic flow and providing vehicles safe ingress and egress to properties in the
districts.
1. Sight Distances at Entrances and Exits
a. DRIVEWAY entrances and exits shall be located to achieve safe
sight distances from the driver's seat of a vehicle that is ten (10)
feet behind the curb (or edge of the shoulder) with the height of the
driver's view at three and a half (3 1/2) feet above the ROAD
surface and the height of the object viewed at four and a half (4 1/2)
feet.
b. The minimum sight distance will be one hundred (100) feet for every
ten (10) miles per hour of traffic speed based upon the posted
speed on the road.
c. In the event that insufficient frontage or other site constraints limit
the ability of a property owner to meet the standard of paragraph
c.1.b. above, the applicant must demonstrate to the PLANNING
BOARD that sight distances have been met to the maximum extent
possible. Should other portions of this Ordinance come into conflict
with sight distances, sight distances shall take precedence.
2. Minimum Distance Between DRIVEWAYS. The minimum distance
between DRIVEWAYS shall be measured from the centerlines-of the
47
DRIVEWAYS. The minimum spacing of DRIVEWAYS for any LOT
created after the effective date of this Ordinance shall be two hundred
(200) feet except on existing LOTS of record which cannot meet the
standard because of insufficient frontage. If frontage is insufficient, the
applicant must show the PLANNING BOARD the constraints of the
LOT and provide the best remedy possible, for the Board's review. The
minimum distance between DRIVEWAY entrances on LOTS with
insufficient frontage shall be one hundred (100) feet.
D. Number of DRIVEWAYS
1. One DRIVEWAY is allowed per LOT. Exceptions may be made on a
case-by-case basis subject to PLANNING BOARD approval. The need
for more than one DRIVEWAY must be substantiated by traffic volume
or other vehicular requirements consistent with Maine Department of
Transportation standards.
2. NON-CONFORMING LOTS of record which, as of the effective date of
this Ordinance, have STRUCTURES and multiple DRIVEWAYS are
prohibited from expanding or converting such STRUCTURES without
reducing their access to a single DRIVEWAY.
3. SHARED DRIVEWAYS are encouraged for adjacent sites. LOT size
and ROAD frontage requirements shall be eligible to be reduced by up
to a total of thirty (30) percent when the developer agrees to provide
common DRIVEWAYS and forty-five (45) percent when the common
DRIVEWAYS are on a STREET or ROAD other than an ARTERIAL;
provided that the buffer requirements and SETBACKS can still be met.
4. Where there is a SHARED DRIVEWAY located on or near a shared
property line, SETBACKS shall be measured from the property line in
common; not from the edges of the SHARED DRIVEWAY.
E. DRIVEWAY Design and Construction
1. Grade. DRIVEWAY width shall be no greater than thirty (30) feet unless
safety or volume concerns can be shown to require otherwise, subject
to PLANNING BOARD approval. DRIVEWAY grades shall not be more
than ten (10) percent over the entire length. The grade for the first fifty
(50) feet from the ROAD shall not be more than five (5) percent unless
otherwise approved by the PLANNING BOARD and the ROAD
commissioner.
2. Angle of Intersection. DRIVEWAYS shall intersect the ROAD at an
48
angle of as near ninety (90) degrees as site conditions permit, and in
no case shall be less than sixty (60) degrees. On properties with
access onto ARTERIALS, the applicant shall provide a turn-around
area to enable a vehicle to exit the property without backing into the
roadway.
F. Corner Clearances
The minimum distance between a DRIVEWAY served by an ARTERIAL
and an intersecting side STREET shall be two hundred (200) feet as
measured from the tangent point of the corner with the ARTERIAL. Where
the above cannot be met, and the possibility exists, access shall be limited
to a side STREET and the corner clearance standard shall be met to the
maximum practical extent as determined by the PLANNING BOARD.
Should neither of the above be possible, the corner clearance shall be
met to the maximum extent possible but shall not be less than one
hundred and fifty (150) feet, subject to approval by the PLANNING
BOARD.
G. Traffic Studies
Should a proposed development present apparent traffic safety or
capacity concerns in the vicinity of the development, the PLANNING
BOARD may require an access review and impose design standards
such as those found in the Maine Department of Transportation design
manuals. Designs and/or independent impact studies shall be conducted
at the expense of the applicant.
H. Street Construction Preparation
1. Before any clearing has started on the right-of-way, the center line and
side lines of the new ROAD shall be staked or flagged at 50-foot
intervals.
2. Before grading started, the entire right-of-way shall be cleared of all
stumps, roots, brush, and other objectionable material. All ledge, large
boulders, and tree stumps shall be removed from the right-of-way.
3. All organic materials shall be removed to a depth of two feet below the
sub-grade of the roadway. Rocks and boulders shall also be removed
to a depth of two feet below the sub-grade of the roadway. On soils
which have been identified by the Town ENGINEER as not suitable for
roadways, the subsoil shall be removed from the STREET site to a
depth of two feet below the sub-grade and replaced with material
meeting the specifications for gravel aggregate sub-based below.
49
4. Side slopes shall be no steeper than a slope of three feet horizontal to
one foot vertical, and shall be graded, limed, fertilized, and seeded
according to the specifications of the erosion and sedimentation control
plan.
3.3.10. Stormwater Management Design Standards
A. Adequate provision shall be made for disposal of all storm water generated
within the SUBDIVISION, and any drained ground water through a
management system of swales, culverts, under-drain, and storm drains.
The storm water management system shall be designed to conduct storm
water flows to existing watercourses or storm drains.
B. All components of the storm water management system shall be designed
to meet the criteria of a 25-year storm, based on rainfall data for Portland,
Maine. 2. The minimum pipe size for any storm drainage pipe shall be 12
inches. Maximum trench width at the pipe crown shall be outside diameter
of the pipe plus two feet. Pipe shall be bedded in a fine granular material,
containing no stones larger than three inches, lumps of clay, or organic
matter, reaching a minimum of six inches below the bottom of the pipe
extending to six inches above the top of the pipe.
C. The storm water management system shall be designed to accommodate
upstream drainage, considering existing conditions and approved or
planned developments not yet built and shall include a surplus design
capacity factor of 25% for potential increases in upstream runoff.
D. Downstream drainage requirements shall be studied to determine the
effect of the proposed SUBDIVISION. The storm drainage shall not
overload existing or future planned storm drainage systems downstream
from the SUBDIVISION. The subdivider shall be responsible for financing
any improvements to existing drainage systems required to handle the
increased storm flows.
E. Wherever the storm drainage system is not within the right-of-way of a
public STREET, perpetual EASEMENTS shall be provided to allow
maintenance and improvement of the system.
F. Where soils require a subsurface drainage system, the drain shall be
installed and maintained separately from the storm water drainage
system.
G. Erosion Control. The procedures outlined in the erosion and
sedimentation control plan shall be implemented during the site
preparation, construction, and clean-up stages.
50
H. Clean-up.
Following STREET construction, the developer or contractor shall
conduct a thorough clean-up of stumps and other debris from the entire
STREET right-of-way. If on-site disposal of the stumps and debris is
proposed, the site shall be indicated on the plan, and be suitably covered
with fill and topsoil, limed, fertilized and seeded.
I. Certification of Construction.
Upon completion of STREET construction and prior to a vote by the
Municipal Officers to submit a proposed public way to the legislative body,
a written certification signed by a professional ENGINEER registered in
the State of Maine shall be submitted to the Municipal Officers at the
expense of the applicant, certifying that the proposed way meets or
exceeds the design and construction requirements of these regulations.
"As built" plans shall be submitted to the Municipal Officers.
3.3.11. Dust, Fumes, Vapors, Gases, Odors, and Glare
A. Emission of dust, dirt, fly, ash, fumes, vapors, and gases which could
damage human health, animals, vegetation or property or which could soil
or stain persons or property, at any point beyond the lot line of the
commercial or industrial establishment creating that emission, shall be
prohibited.
B. No land use or establishment shall be permitted to produce offensive or
harmful odors beyond its lot lines, measured either at ground or habitable
elevation.
C. No land use or establishment shall be permitted to produce a strong,
dazzling light or reflection of that light beyond its lot lines onto neighboring
properties or onto any town way so as to impair the vision of the driver of
any vehicle in that town way.
3.3.12. Bulk Hazard Substance Uses
A. A Bulk Hazardous Substance Use is defined as any use that has a
principal part of its operation, the storage, shipping or sale of a substance
or substances in quantity whether liquid, solid, or gaseous, which are
hazardous because of their combustibility, toxicity or other danger to public
health and/or the environment. These uses are only permitted if they meet
51
the general requirements of this section, have been reviewed by the
Planning Board, and approved at the Annual Town Meeting.
B. Bulk Hazardous Substances are only permitted to be used for bulk
petroleum and propane uses.
C. Lot Size: All Bulk Hazardous Substance Uses shall be located on lots of at
least three (3) acres or on lots meeting the minimum size that requires
Maine Department of Environmental Protection approval under the Site
Location and Development Act, whichever is greater. No variances shall
be permitted.
D. Location: All Containment and Storage structures, Transfer Systems and
Vehicles containing Bulk Hazardous Substances which could leak or leach
into the ground shall not be located or parked closer than 300 feet from a
private well or 1,000 feet from a public well.
E. Outdoor Storage: Any aboveground outdoor storage facility for fuel,
chemicals, chemical industrial wastes and potentially harmful raw
materials shall be located on a reinforced concrete slab enclosed by an
impervious reinforced concrete dike, monolithically poured, which shall be
high enough to contain one hundred and ten (110) percent of the total
volume of material kept within the containment area plus the rain which
would fall into this area if it did not have a roof during a fifty (50) year
storm. However, all containment areas shall be covered by a permanent
roof with overhangs sufficient to prevent precipitation falling at an angle of
forty-five (45) degrees from entering the containment area. The installation
shall conform to all applicable Federal and State standards.
F. Highly Flammable Material: No highly flammable or explosive liquids, solids
or gases shall be stored in bulk above ground, unless they are stored in
compliance with the requirements of the National Fire Protection
Association (NFPA), Sections 30, 58, and 59- A.d.
G. Containment Areas
1. General: Any aboveground indoor and outdoor storage facility for bulk
hazardous liquids and solids shall be located on a reinforced concrete
slab enclosed by an impervious reinforced concrete dike, monolithically
poured, which shall be high enough to contain 110 percent of the total
volume of material kept within the containment area. All containment
areas shall be covered by a permanent roof with overhangs sufficient
to prevent precipitation falling at an angle of 45 degrees from entering
the containment area. Provisions shall be made to direct any
52
precipitation which does enter a containment area to a tank for
monitoring and decontamination or removal as necessary.
2. Liquids: All stations for transferring hazardous liquids to or from a
vehicle, other than facilities for refueling vehicles, shall be located
above a containment well having a capacity equal to 110 percent of the
largest vehicular or storage tank that can be connected to the station.
All piping connecting storage tanks to transfer stations shall be
enclosed inside a secondary pipe when outside a containment area.
The exterior pipes shall serve to return any liquid leaking from a
primary pipe to a containment area
H. Regulatory Authorities: Installations shall conform to all applicable Federal,
State and industry standards, including but not limited to the following:
1. Federal:
a. DOT (Department of Transportation)
b. EPA (Environmental Protection Agency)
c. USCG (United States Coast Guard)
2. State
a. DEP (Department of Environmental Protection)
b. MDOT (Maine Department of Transportation)
c. OSFB (Oil and Solid Fuel Board)
d. SFMO (State Fire Marshall's Office)
3. Other:
a. NFPA (National Fire Protection Association)
I. Spill Prevention, Control, and Countermeasures Plans (SPCC Plans). An
SPCC plan that conforms to EPA standards shall be provided by the
operator even if it is not required by a federal or state regulatory body.
J. Monitoring and Inspection: The operator of any bulk hazardous substance
facility shall provide at their expense for continuous electronic fire, leak,
and security monitoring of said facility by an independent alarm service
and for regular inspections by an independent party acceptable to the
Planning Board at intervals not exceeding one (1) year with copies of all
reports provided to the Town's Code Enforcement Officer.
K. Substance Specific Requirements:
53
1. Petroleum:
a. Medium and Heavy Distillates (includes Fuel Oil). Any precipitation
runoff collection tanks shall be configured and function as oil/water
separation tanks
b. Light Distillates (includes Gasoline). Transfer stations for retail
substance sales shall be located on a concrete pad surrounded by
curbing or guards protecting any pumping or transfer valve unit,
such as a gasoline pump from vehicular impact.
2. Propane:
a. Propane tanks shall be installed in a manner such that leaking gas
shall activate a leak sensor.
3.3.13. Stormwater Management
A. Adequate provisions must be made for the collection and disposal of all
stormwater that runs off proposed streets, parking areas, roofs, and other
surfaces, through a stormwater drainage system and maintenance plan,
which must not have adverse impacts on abutting or downstream
properties. The stormwater drainage system and maintenance plan shall
conform to one of the following options:
B. The stormwater management plan shall be prepared in accordance with
the latest edition of the Maine DEP "Stormwater Management for Maine:
Best Management Practices". The stormwater plan must be designed so
that the post-development stormwater runoff does not exceed the pre-
development stormwater runoff for the 24-hour duration, 2-year, 10-year,
and 25-year frequency storm events.
C. A stormwater plan developed in accordance with the Low Impact
Development (LID) practices contained in the latest edition of the Maine
LID Guidance Manual. This option is available for all single-family
residential dwellings and non-residential and multi-family developments.
(Non-residential and multi-family uses are smaller developments that do
not require review under Chapter 500 of the Code of Maine Rules.)
1. To the extent possible, the plan must retain stormwater on the site using
the natural features of the site. 2. The applicant must demonstrate that
on- and off-site downstream channel or system capacity is sufficient to
carry the flow without adverse effects, including but not limited to
flooding and erosion of shoreland areas, or that he/she will be
54
responsible for whatever improvements are needed to provide the
required increase in capacity and/or mitigation.
2. All natural drainage ways must be preserved at their natural gradients
and must not be filled or converted to a closed system unless
approved as part of the site plan review.
3. design of the storm-water drainage system must provide for the
disposal of storm-water without damage to streets, adjacent properties,
downstream properties, soils, and vegetation.
4. The design of the storm drainage system shall be designed with
consideration of all upstream drainage that may affect the site and
shall ensure safe and adequate conveyance of runoff across the
property.
5. The biological and chemical properties of the receiving waters must not
be degraded by the storm-water runoff from the development site. The
use of oil and grease traps in manholes, the use of on-site vegetated
waterways, and vegetated buffer strips along waterways and drainage
swales, and the reduction in use of deicing salts and fertilizers may be
required, especially where the development of storm-water discharges
into a bedrock aquifer area, other water supply source, lake, or pond.
6. Stormwater management plans shall be consistent with the standards
of this subsection and, except where the standards of this subsection
are more restrictive, strategies contained in each stormwater
management plan shall be selected from a manual entitled,
"Stormwater Management for Maine: Best Management Practices",
published by the Maine Department of Environmental Protection in
their most latest version. This publication shall be available for public
inspection at the Town Office.
3.3.14. Erosion and Sedimentation Control
All building, site, and roadway designs and layouts must harmonize with existing
topography and conserve desirable natural surroundings to the fullest extent
possible such that filling, excavation and earth moving activity must be kept to a
minimum. Parking LOTS on sloped sites must be terraced to avoid undue cut
and fill, and/or the need for retaining walls. Natural vegetation must be preserved
and protected wherever possible.
Soil erosion and sedimentation of watercourses and water bodies will be
minimized by an erosion and sedimentation control prepared in accordance with
55
the Maine Erosion and Sedimentation Control Handbook for Construction: Best
Management Practices, published by the Cumberland County Soil and Water
Conservation District and the Maine Department of Environmental Protection,
March 1991.
3.3.15. Water Quality Protection
No activity shall locate, store, or permit the discharge of any untreated, or
inadequately treated liquid, gaseous, or solid materials of such nature,
obnoxiousness, toxicity, or temperature that run off or percolate into surface or
ground waters so as to contaminate or harm such waters or cause nuisances,
such as objectionable shore deposits, floating or submerged debris, oil or scum,
color, odor, taste, or unsightliness or be harmful to animal or plant life.
3.3.16. Soils
Land uses shall be located on soils in or upon proposed uses or structures that
can be established or maintained without causing adverse effects, including
severe erosion, mass soil movement, and water pollution, whether during or after
construction. Proposed uses requiring subsurface waste disposal, and
commercial or industrial development and other similar intensive land uses shall
be required to file a soils report prepared by a State certified soil scientist or
geologist based primarily on criteria employed in the National Cooperative Soil
Survey as modified by on-site factors such as depth of water table.
3.3.17. Archeological Sites
The Planning Board shall retain the option of requiring submission of any
proposed site plan to the Maine Historic Preservation Commission for review and
comment to the Planning Board. If any portion of the site has been identified as
containing archeological resources, the development must include measures for
protecting these resources, including but not limited to modification of the
proposed design of the site, timing of construction, and limiting the extent of
excavation.
3.3.18. Road Damage and Restoration
A. Responsibility. The developer, contractor, or subcontractor shall be fully
responsible for any damage to town-owned roads, ditches, culverts,
shoulders, or other public property damage resulting from construction
vehicles, equipment, or activities associated with construction
B. Restoration. All damage identified by the Town of West Bath shall be
repaired by the developer, contractor, or subcontractor at their sole
expense, to a condition equal to or better than that which existed prior to
commencement of construction. All restoration work shall be completed
56
in accordance with specifications and timeline approved by the Road
Commissioner.
C. Financial Assurance. The Town of West Bath may require a performance
guarantee, in an amount satisfactory to the Select Board or its designee,
to ensure completion of all required repairs.
D. Failure to Comply. If the developer, contractor, or subcontractor fails to
complete required repairs within the timeframe established by the Town
of West Bath, the Town may undertake such repairs and recover all costs
incurred, including administrative and inspection costs, from the
developer, contractor, or subcontractor. Recovery may be made from the
performance guarantee, through lien, or by other lawful means.
E. Inspections. The Town of West Bath may conduct inspections of road
conditions before, during, and after construction to determine the extent
of any damage attributable to the associated development. Prior to
construction, the developer, contractor, or subcontractor shall take a
dated photograph of the work location.
3.4
WAIVERS
A. Waivers of Non-Applicable Submission Requirements.
Where the Planning Board determines that a specific submission
requirement is not applicable to a proposed subdivision or a site plan
review it may waive said requirement. Preliminary intent to waive a
submission requirement as indicated on a submission checklist does not
constitute a waiver since submission requirements may be increased if
any need to do so is identified during the review process. Final approval
of any waiver is granted only when it is recorded at the same time the
proposed project is approved or denied.
B. Submissions
Where the Planning Board makes written findings of fact that
extraordinary and unnecessary hardships may result from such
compliance with these regulations, it may waive portions of the
submission requirements or the standards, unless otherwise indicated in
the regulations, to permit a more practical and economic development,
provided the public health, safety, and welfare are protected, and
provided the waivers do not have the effect of nullifying the intent and
purpose of the Comprehensive Plan, the Land Use Ordinance, or these
regulations.
C. Improvements.
Where the Planning Board makes written findings of fact that due to
special circumstances , the provision of certain required improvements is
not requisite to provide for the public health, safety or welfare, or are
57
inappropriate because of inadequate or lacking connection facilities
adjacent to or in proximity of the proposed subdivisions, it may waive the
requirement for such improvements, subject to appropriate conditions.
D. Waivers Subject to Conditions.
1. In granting waivers to any of these regulations, the Planning Board shall
require such conditions as will assure the objectives of these regulations
are met.
2. When the Planning Board grants a waiver to any of the improvements
required by these regulations, the final plan, to be recorded at the
Registry of Deeds, shall indicate the waivers granted and the date on
which they were granted.
58
ARTICLE IV: SUBDIVISIONS
4.1 Purpose: The purpose of this Article is to establish an orderly, equitable and
expeditious procedure for reviewing subdivisions.
4.2: Definitions: Small vs. Large Subdivisions
A. Small subdivisions, for purposes of this ordinance, shall be defined as:
1. Proposed subdivision of three or four lots or dwelling units with no
new or upgraded streets and with an aggregate driveway length not
to exceed 450 feet for a three-lot subdivision or 600 feet for a four-lot
subdivision
B. Large subdivisions, for the purpose of this ordinance, shall be defined as:
1. Prosed subdivision of five or more lots or dwelling units or a
subdivision with aggregate driveway length exceeding 600 feet.
4.3: Standards. Small and large subdivisions shall meet the following standards:
A. Existing wooded buffers shall be maintained whenever possible.
B. Wooded buffers shall be a minimum of 75 feet in width.
C. Non-wooded buffers shall be at least 125 feet in width.
D. All drainage from the proposed subdivision shall pass through the
proposed buffer or buffers shown on the plan.
E. Driveway and parking areas must be designated and constructed so that
runoff is quickly shed form these areas to protected buffer areas (to the
maximum extent reasonably feasible given lot limitations) and disruption
of natural drainage patterns is minimized. Best management practices
(BMPs) such as swales, water bars, road-based drainage dips, and
proper grading of gravel drives should be used to prevent runoff from
concentrating in the driveway and to get it into the buffer areas as quickly
as feasible. These requirements must be incorporated into the lot's deed
covenants and restrictions.
F. Road and roof runoff must be distributed over stable, well vegetated areas
59
or be infiltrated into the soil using dry wells or other infiltration systems.
These requirements must be incorporated into the Lot's Deed covenants
and restrictions.
G. Deed covenants and restrictions must prohibit the use of lawn fertilizers
containing phosphorus except during the establishment of new turf on
bare soil.
H. The septic system must meet the standards of the Maine State Plumbing
Code and shall incorporate a loam liner whenever appropriate.
I. A proposed small subdivision which creates lots which could be further
divided such that five or more lots may result shall be subject to the
phosphorus controls for larger subdivisions and subdivisions with new
roads in subsection 4.10.F.3 unless there are deed restrictions prohibiting
future divisions of the lots.
4.4. Pre-Application Procedure
4.4.1: Pre-Application: An individual may test the feasibility of a subdivision as
part of the pre-application conference described in Article III, as amended (Site
Plan Review Application Procedure). The purpose of this initial meeting and on-
site inspection is for the applicant to present general information regarding the
proposed subdivision to the Board and receive the Board's comments prior to
the expenditure of substantial sums of money on surveying, soils identification,
and engineering by the applicant. During this pre-application conference, there
shall be a question and answer period where the Board may make specific
suggestions to be incorporated by the applicant into subsequent submissions.
The on-site inspection will be scheduled at this conference.
A. Pre-Application Sketch Plan. The pre-application Sketch Plan shall show,
in simple sketch form, the proposed layout of streets, lots, and other
features in relation to existing conditions. The Sketch Plan, which may be
a free-hand penciled sketch, should be supplemented with a clarification
letter to describe or outline the existing conditions of the site and the
proposed development. It will be most helpful to both the applicant and the
Board for site conditions such as steep slopes, wet areas and vegetative
cover to be identified in a general manner. It is recommended that the
Sketch Plan be superimposed on or accompanied by a copy of the
Assessor's map(s) on which the land is located. The Sketch Plan shall be
accompanied by a copy of a portion of the U.S.G.S. topographical map of
the area showing the outline of the proposed subdivision, and provide a
copy of the County soil survey showing the outline of the proposed
subdivision.
60
B. The Clarification Letter shall describe, or the Sketch Plan shall indicate,
the natural features to be preserved using the cluster approach.
Ultimately, it will be the Developer's decision whether to apply for approval
of a standard, or cluster subdivision.
4.4.2 Contour Interval And On-Site Inspection.
Within 30 days of the on-site inspection of the property, the Board shall
determine and inform the applicant in writing of the required contour interval on
the Preliminary Plan.
4.4.3: Rights Not Vested.
The submittal or review of the Sketch Plan shall not be considered the initiation
of the review process for the purposes of bringing the plan under the
protection of Title 1, M.R.S.A. § 302.
4.5: Application Procedure
4.5.1: Within six months of the on-site inspection conducted by the Planning
Board, the applicant shall submit 3 copies of the Preliminary Plan for the
Planning Board's review. Failure to do so shall require resubmission of the
Sketch Plan to the Planning Board. Applications shall be submitted at least
twenty-two (22) days prior to a scheduled meeting of the Planning Board by mail,
e-mail, or delivered by hand to the Town Office. The applicant is responsible for
postage fees and for all printing prior to the Planning Board meeting.
4.5.2:The applications for preliminary subdivision approval shall be accompanied
by a non- refundable application fee in accordance with the Town of West Bath
Planning Board Fee Schedule. In addition, the applicant shall pay all fees
incurred by the Planning Board to hire independent consulting services to review
the application when necessary.
4.5.3: The applicant shall notify in writing all owners of property abutting the
proposed Subdivision, including property on the opposite side of the Road that
an application for Subdivision approval has been submitted. The notification
letter shall specify the location of the proposed Subdivision and include a general
description of the project. The applicant shall provide in his application the names
and addresses of all abutting property owners notified.
4.5.4: Upon receiving an application form and fee for a Preliminary Plan, the
Town Clerk shall issue a dated receipt. The Clerk shall forward the application to
61
the Code Enforcement Officer or his or her designee. The Planning Board shall
notify the applicant in writing (email) whether or not the application is complete,
and what, if any, additional items are required for a Complete Application.
4.5.5: Upon determination that a Complete Application has been submitted for
review, the Code Enforcement Officer or his or her designee will ask the Clerk to
add the applicant to the Planning Board meeting agenda and schedule a public
hearing. The Planning Board shall hold the hearing within thirty days of receipt
of a Complete Application, and shall publish notice of the date, time, and place
of the hearing in a newspaper of general circulation in the municipality at least
two times, the date of the first publication to be at least seven days prior to the
hearing. Abutters will be notified of the hearing in accordance with Land Use
Ordinance, Article I, Section 5.6.
4.5.6: The applicant, or his duly authorized representative, shall attend the
meeting of the Planning Board to discuss the Preliminary Plan. Failure to attend
the meeting to present the Preliminary Plan Application shall result in the Planning
Board inaction on the application until the next meeting that the applicant
attends.
4.5.7: Within fourteen days of the meeting at which a Preliminary Plan
Application for subdivision is initially presented, the Planning Board shall:
A. Make Findings of Fact on the Application and approve, approve with
conditions, or deny the Preliminary Plan. The Planning Board shall
specify in writing its Findings of Facts and reasons for any conditions or
denial.
B. Notify the clerk and the review authority of the neighboring municipalities
if any portion of the subdivision abuts or crosses the municipal
boundary.
4.5.8. When granting approval to a Preliminary Plan, the Planning Board shall
state and follow- up in writing (mail or email) the conditions of such approval, if
any, with respect to:
A. The specific changes which the Planning Board will require for the Final
Plan submission;
B. The character and extent of the required improvements for which waivers
may have been requested and which in the Planning Board's opinion may
be waived without jeopardy to the public health, safety, and general
welfare; and
62
C. The amount of all performance guarantees which it will require as
prerequisite to the approval of the Final Plan;
4.5.9: Approval of a Preliminary Plan shall not constitute approval of the Final
Plan or intent to approve the Final Plan, but rather it shall be deemed an
expression of approval of the design of the Preliminary Plan as a guide to the
preparation of the Final Plan. The Final Plan shall be submitted for approval of
the Planning Board upon fulfillment of the requirements of these Ordinances and
the conditions of preliminary approval, if any. Prior to the approval of the Final
Plan, the Planning Board may require additional changes as a result of the
further study of the subdivision or as a result of new information received.
4.6: Preliminary Plan Submissions
4.6.1: The Preliminary Plan shall consist of the following items:
A. Application Form and Checklists.
B. Location Map. The Preliminary Plan shall be accompanied by a Location
Map adequate to show the relationship of the proposed subdivision to the
adjacent properties, and to allow the Planning Board to locate the
subdivision within the municipality. The Location Map shall show:
1. All existing subdivisions and approximate tract lines of acreage
parcels together with the names of the record owners of all adjacent
parcels of land, namely, those directly abutting or directly across any
street adjoining the proposed subdivision.
2. Locations and names of existing and proposed streets, easements,
and rights of way.
3. Boundaries and designations of zoning districts and overlay zones.
4. An outline of the proposed subdivision and any remaining portion of
the owner's property if the Preliminary Plan submitted covers only a
portion of the owner's entire contiguous holding.
C. Preliminary Plan. The Preliminary Plan shall be submitted with all
dimensions shown in feet or decimals of a foot. The reproducible
transparencies shall include the seal of the individual responsible for
preparing the plan. The plan shall be drawn to a scale of not more than
one hundred (100) feet to the inch. The Planning Board may allow plans
for subdivisions containing more than seventy-five (75) acres to be drawn
at a scale of not more than two hundred (200) feet to the inch provided
all necessary detail can easily be read. Space shall be provided for
63
endorsement by the Board with five (5) signature lines.
The Preliminary Plan shall include the following information:
1. Proposed name of the subdivision, the name of the municipality in
which it is located and the Tax Assessor's Map and Lot numbers.
2. A field survey of the boundary lines of the tract, giving complete
descriptive data by bearings and distances, made and certified by a
licensed land surveyor. The corners of the tract shall be located on the
plan and shall indicate the type of surveyor monumentation per 30-A
M.R.S.A. § 4406(2) set or found at each lot corner.
3. Contour lines at intervals of not more than five (5) feet or at such
intervals as the Planning Board may require, based on United States
Geological Survey datum of existing grades where changes of existing
ground elevation will be five (5) feet or more.
4. The zoning district in which the proposed subdivision is located and the
location of any zoning boundaries affecting the subdivision.
5. The number of acres within the proposed subdivision, location of
property lines, existing Buildings, watercourses, and other essential
existing physical features.
6. The date the plan was prepared, magnetic north point, graphic map
scale, names and addresses of the record owners, sub-divider, and
individual or company who prepared the plan.
7. The location and size of existing and proposed sewers, water mains,
culverts, and drainage ways on or adjacent to the property to be
subdivided.
8. The location of all rivers, streams, and brooks within or adjacent to the
proposed subdivision.
9. If any portion of the proposed subdivision is located within the
watershed of Campbells Pond or Winnegance Pond, the preliminary
plan shall show the corresponding watershed boundary location.1 The
1 Where there is a dispute as to exact location of a watershed boundary, the Planning Board or its designee and the applicant
shall conduct an on-site investigation to determine where the drainage divide lies. If the Planning Board and the applicant cannot
64
plan shall also show preliminary locations of proposed phosphorous
controls as required under 4.10.F.
10. The location, names, and present widths of existing and proposed
streets, highways, easements, building lines, parks and other open
spaces on or adjacent to the subdivision. The plan shall contain
sufficient data to allow the location, bearing and length of every street
line, lot line, and boundary line to be readily determined and be
reproduced upon the ground. These lines shall be tied to reference
points previously established.
11. The proposed lot lines with approximated dimensions and lot areas.
12. All parcels of land proposed to be dedicated to public use. The
conditions of such dedication should be represented in support
documents.
13. The location of any open space to be preserved and an indication of
its improvement and management.
14. All activities which involve filling, grading, excavation or other similar
activities which result in un-stabilized soil conditions and which require
a permit shall require a written soil erosion and sedimentation control
plan. The plan shall be submitted to the permitting authority for
approval and shall include, where applicable, provisions for:
a. Mulching, Revegetation Mulching and revegetation of disturbed soil.
b. Runoff Controls Temporary runoff control features such as hay
bales, silt fencing or diversion ditches.
c. Stabilization Structures. Permanent stabilization structures such as
retaining walls or rip-rap.
d. Topography and Soils. In order to create the least potential for
erosion, development shall be designed to fit with the topography
and soils of the site. Areas of steep slopes where high cuts and fills
may be required shall be avoided wherever possible, and natural
contours shall be followed as closely as possible.
e. Erosion Controls. Erosion and sedimentation control measures
shall apply to all aspects of the proposed project involving land
disturbance and shall be in operation during all stages of the
agree on the location of the drainage divide based on the on-site investigation, the burden of proof shall lie with the applicant to
provide the Planning Board with information from a registered land surveyor showing where the drainage divide lies.
65
activity. The amount of exposed soil at every phase of construction
shall be minimized to reduce the potential for erosion.
f. Exposed Ground Area. Any exposed ground area shall be
temporarily or permanently stabilized within one (1) week from the
time it was last actively worked, by use of rip-rap, sod, seed, and
mulch, or other effective measures. In all cases permanent
stabilization shall occur within nine (9) months of the initial date of
exposure. In addition:
g. Mulch. Where mulch is used, it shall be applied at a rate of at least
one (1) bale per five hundred (500) square feet and shall be
maintained until a catch of vegetation is established.
h. Anchoring. Anchoring the mulch with netting, pegs and twine, or
other suitable method may be required to maintain the mulch
cover.
i. Siltation Measures. Additional measures shall be taken where
necessary in order to avoid siltation into the water. Such measures
may include the use of staked hay bales and/or silt fences.
j. Protection of Drainage Ways. Natural and man-made drainage ways
and drainage outlets shall be protected from erosion from water
flowing through them. Drainage ways shall be designed and
constructed in order to carry water from a twenty-five (25) year
storm or greater and shall be stabilized with vegetation or lined with
rip-rap.
k. A Draft Storm Water Management Plan showing the disposal of
surface drainage waters, prepared by a Registered Professional
Engineer. The Storm Water Management Plan must conform to
one of the options for stormwater plans in Article III, section 3.11 of
this ordinance (The location, type, and size of all existing and
proposed catch basins, storm drainage facilities, streams, and
water courses, and all utilities, both above and below ground)
l. If any portion of the subdivision is in a flood-prone area, as
depicted on the municipality's Flood Insurance Rate Map, the
boundaries of any flood hazard areas, and the one hundred (100)
year flood elevation, shall be delineated on the plan.
m. Building envelopes for each proposed lot within the subdivision
shall be shown. They shall represent front, rear and side setbacks
66
along with any additional setbacks required from easements,
shoreland or wetland areas.
n. Areas with sustained slopes greater than 25% covering more than
one acre shall be delineated.
4.6.2. Supporting Documentation
A. Verification of right, title or interest in the property.
B. A copy of the deed from which the survey was based. A copy of all
covenants or deed restrictions, easements, right-of-way, or other
encumbrances currently affecting the property.
C. A draft copy of any covenants or deed restrictions intended to cover all or
part of the lots in the subdivision.
D. Indication of the type of sewage disposal to be used in the subdivision.
1. When sewage disposal is to be accomplished by connection to the
public sewer a letter from the Sewer District indicating there is
adequate capacity within the District's system to transport and treat
the sewage shall be submitted.
2. When sewage disposal is to be accomplished by subsurface sewage
disposal systems, test pit analyses prepared by a Licensed Site
Evaluator shall be provided. A map showing the location of all test pits
dug on the sites shall be submitted.
E. Indication of the type of water supply system(s) to be used in the subdivision.
1. When water is to be supplied by public water supply, a letter from the
servicing water district shall be submitted, indicating there is adequate
supply and pressure for the subdivision and that the district approves
the plans for extensions where necessary. Where the district's supply
line is to be extended, a written statement from the Fire Chief stating
approvals of the location of fire hydrants, and a written statement from
the district approving the design of the extension shall be submitted.
2. When water is to be supplied by private wells, either a well driller or a
hydrogeologist familiar with the area shall provide evidence of
adequate water supply and quality.
E. The names and addresses of owners of record of adjacent property, including
any property directly across an existing public street from the subdivision.
67
G. A copy of the County Soil Survey showing the subdivision outline. When
the medium intensity soil survey shows soils which are generally
unsuitable for the uses proposed, the Board may require the submittal of
a report by a Registered Soil Scientist, indicating the suitability of soil
conditions for those uses. The intensity of this study may be required to
identify changes in soil conditions down to one-tenth (1/10) acre.
H. Method of solid waste disposal.
I. At the discretion of the planning board, a hydrogeological assessment
prepared by a Maine-Certified Professional Hydrogeologist
describing the proposed development's impacts on groundwater may
be required. A hydrogeological assessment shall be a required
submission.
J. Wetland areas, regardless of size, shall be identified by a Certified Soil
Scientist or Wetland Scientist, and their locations show on the plan.
K. If the proposed subdivision is in the Campbells Pond watershed, include a
Long- Term Maintenance Plan for all phosphorous control measures,
including deed restrictions and/or conservation easements.
L. A copy of any access management driveway and/or entrance permit(s)
required for the proposed subdivision under 17-229 Maine Administrative
Rules, Chapter 299.
M. Copies of any other federal, state, or local permits required for the
proposed subdivision.
N. If the record owner or sub-divider is a corporation, the principles of such
corporation, LLC, or partnership shall be listed with officers so designated
and documentation showing that the organization is in good standing with
appropriate registration agencies shall be provided.
O. The Planning Board may require additional information to be submitted,
where it finds necessary, in order to determine whether the criteria of Title
68
30-A M.R.S.A. § 4404 and this Ordinance are met.
4.7: Final Plan Submission
4.7.1. Procedure for Final Plan Submission
A. No later than six (6) months after the approval of the Preliminary Plan, the
applicant shall submit 3 copies of the Final Plan Application for approval
to the Planning Board. Applications shall be submitted at least twenty-
two (22) days prior to a scheduled meeting of the Planning Board by
mail, e-mail to the town clerk, or delivered by hand to the Town Office. If
the application for the Final Plan is not submitted within six (6) months of
Preliminary Plan approval, the Planning Board shall require the Applicant
to resubmit the Preliminary Plan, unless the Planning Board approves an
extension consistent with this Section. If for any reason the applicant
cannot submit the Final Plan within six (6) months after approval of the
Preliminary Plan, the applicant may request an extension. Such a request
for an extension to the filing deadline shall be filed in writing with the
Planning Board prior to the expiration of the six (6) month filing deadline. In
considering the request for an extension the Planning Board must
determine (and may only grant an extension if it finds) that the applicant has
made due progress in preparation of the Final Plan and submission of the
same to other regulatory agencies.
B. The applications for Final Subdivision Approval shall be accompanied by
a non- refundable application fee in accordance with the Town of West
Bath Planning Board Fee Schedule, payable by check to the Town of West
Bath. In addition, the applicant shall pay all fees incurred by the Planning
Board to hire independent consulting services to review the application
when necessary.
C. Prior to submittal of the Final Plan Application, the following approvals
shall be obtained in writing, where appropriate:
1. Maine Department of Environmental Protection under the Site
Location of Development Act, and Natural Resources Protection Act or
if a Wastewater Discharge License is needed.
2. Written approval from all connecting utility districts (sewer and water) that
state their capacity to handle the new subdivision.
3. Maine Department of Human Services if a sub-divider proposes to
provide a central water supply system.
69
4. Maine Department of Human Services, if a centralized or shared
subsurface sewage disposal system(s) is to be utilized.
5. U.S. Army Corps of Engineers, if a permit under Section 404 of the
Clean Water Act is required.
D. Upon receiving an application form and fee for a Final Plan, the Town Clerk
shall issue a dated receipt. The Clerk shall forward the application to the
Code Enforcement Officer or his or her designee for review to determine
submission requirements have been met. The Planning Board shall notify
the applicant in writing (email) whether or not the application is complete
and what, if any, additional items are required for a complete application.
E. Upon determination that a Complete Application has been submitted for
review, the Code Enforcement Officer or his or her designee will ask the
Clerk to add the applicant to the meeting agenda. The Planning Board
shall determine to hold a public hearing on the Final Plan Application
following same guidelines as outlined in the Preliminary Plan Submission
for public hearings.
F. The applicant, or their duly authorized representative, shall attend the
meeting of the Planning Board to discuss the Final Plan.
Failure to attend the meeting to present the final plan application shall
result in the Planning Board not acting on the application until the next
meeting which the applicant attends.
G. Before the Planning Board grants approval of the Final Plan, the
subdivider shall meet the performance guarantee requirements contained
in Article XII as amended.
H. The Planning Board, within thirty (30) days from the public hearing or within
sixty (60) days of receiving a Complete Application, if no hearing is held, or
within such other time limit as may be otherwise mutually agreed to by the
Planning Board and the developer, shall make findings of fact, and
conclusions relative to the standards contained in Title 30-A M.R.S.A.
Section 4404 and in these regulations. If the Planning Board finds that all
standards of the Statute and these regulations have been met, they shall
approve the Final Plan. If the Planning Board finds that any of the standards
of the Statute and these regulations have not been met, the Planning Board
shall either deny the application or approve the application with conditions
to ensure all of the standards will be met by the subdivision. The reasons for
any conditions shall be stated in the records of the Planning Board.
I. Within 30 days of Final Approval, all lot corners must be marked on the
ground as shown on the plan. No lot may be sold without the required
70
monumentation.
4.7.2: The Final Plan Application shall consist of the following items:
A. Application Form and Checklist
B. Location Map on Plan Location will show the relationship of the proposed
subdivision to the adjacent properties and to also show the location in the
municipality.
C. Final Plan. The Final Plan shall be submitted as drawings drawn to a scale
of not more than one hundred (100) feet to the inch. Plans for subdivisions
containing more than seventy-five (75) acres may be drawn at a scale of
not more than two hundred (200) feet to the inch. Plans shall be no larger
than twenty-four (24) by thirty- six (36) inches in size and shall have a
margin of one and a half (1 ½) inches outside of the border line on the left
side for binding and a one half (1/2) inch margin outside the border along
the remaining sides. Space shall be reserved thereon with at least five (5)
lines for endorsement by the Planning Board. The applicant should
provide at least two (2) copies of the plan for the Town to retain.
As required by Title 33 M.R.S.A., Section 652, any plan to be recorded at
the registry of deeds must:
1. Be embossed with the seal of an architect, Professional Engineer or
Registered Land Surveyor;
2. Contain the signature and address of the person who prepared the plan;
3. Provide a space for recording the county, date, time, plan book and
page or file number and register's attest; and
4. Provide a title block containing the name of the plan, the record
owner's name and address, the location by street and town and date
of the plan.
The Final Plan shall include all the information required for a Preliminary
Plan plus the following information:
a. Street Information: The length of all straight lines, the deflection angles
radii length of curves and central angles of curves, tangent distances
and tangent bearings for each street shall be included.
71
b. Where the subdivision streets are to remain private roads, the following
language shall appear on the recorded plan: "All roads in this
subdivision shall remain private roads to be maintained by the
developer or lot owners."
D. Supporting Documentation:
1. Written offers of cession to the municipality of all public open spaces
shown on the plan, and copies of the agreements or other documents
showing the manner in which open spaces to be retained by the
developer or lot owners are to be maintained shall be submitted. If
open spaces or other land is to be offered to the municipality, written
evidence that the Municipal Officers are satisfied with the legal
sufficiency of the written offer of cession shall be included.
2. If the subdivision is in a public water supply area, a written statement
shall be submitted from the Fire Chief or their designee approving all
hydrant locations or other fire protection measures deemed necessary.
3. A list of construction items with cost estimates that will be completed
by the developer prior to the sale of lots.
4. A copy of the final covenants and/or deed restriction intended to cover
all or part of the lots in the subdivision.
5. A Final Storm Water Management Plan, in accordance with the
Stormwater Management for Maine: Best Management Practices,
published by the Maine Department of Environmental Protection
(1995). The Planning Board may waive submission of the storm water
management plan only if the subdivision is not in the watershed of a
great pond, the proposed subdivision will not involve grading which
changes drainage patters, and the addition of impervious surfaces
such as roofs and driveways is less than five (5) percent of the area
of the subdivision.
6. A Final Erosion and Sedimentation Control Plan prepared in
accordance with the Maine Erosion and Sedimentation Control
Handbook for Construction: Best Management Practices, published by
the Cumberland County Soil and Water Conservation District and the
Maine Department of Environmental Protection, March 1991. The
Planning Board may waive submission of the Erosion and
Sedimentation Control Plan only if the subdivision is not in the
watershed of a great pond, the proposed subdivisions will not involve
grading which changes drainage patters, and the addition of
impervious surfaces such as roofs and driveways is less than five (5)
percent of the area of the subdivision.
72
7. If any portion of the proposed subdivision is in the watershed of
Campbells POND, the following shall be submitted or indicated on the
plan:
a. A Phosphorous Impact Analysis and Control Plan conducted using
the procedures set forth in Phosphorous Control in Lake
Watersheds: A Technical Guide for Evaluating New Development,
published by the Maine Department of Environmental Protection,
revised September 1992. The analysis and control plan shall
include all worksheets, engineering calculations, and construction
specifications and diagrams for control measures, as required by
the Technical Guide.
b. A Long-Term Maintenance Plan for all phosphorous control
measures.
c. The contour lines shown on the plan shall be at an interval of five or
fewer feet.
4.8: Final Approval and Filing
A. No plan shall be approved by the Planning Board if the sub-divider is in
violation of the provisions of a previously approved plan within the Town
of West Bath.
B. Upon findings of fact and determination that standards in Title 30-A,
M.R.S.A. Section 4404, and the regulations within this ordinance have
been met, and upon voting to approve the subdivision, a majority of the
voting members of the Planning Board shall sign the Final Plan. The
Planning Board shall specify in writing its findings of fact and reasons for
any conditions or denial. Three (3) paper copies of the signed plan shall
be retained by the Planning Board as part of its permanent records. One
(1) copy of the signed plan shall be forwarded to the Select Board and
another copy shall be forwarded to the Code Enforcement Officer. Any
subdivision not recorded in the Registry of Deeds within ninety (90) days
of the date upon which the plan is approved and signed by the Planning
Board shall render the approval and subdivision null and void.
C. No changes, erasures, modification, or revisions shall be made in any Final
Plan after approval has been given by the Planning Board and endorsed
in writing on the plan, unless the revised Final Plan is first submitted and
the Planning Board approves any modifications, except in accordance
with The Planning Board shall make findings that the revised plan meets
73
the standards of Title 30-A, M.R.S.A. Section 4404, and these regulations.
If a plan is recorded without complying with this requirement, it shall be
considered null and void, and the Planning Board shall institute
proceedings to have the plan stricken from the records of the Registry of
Deeds.
D. The approval by the Planning Board of a subdivision Plan shall not be
deemed to constitute or be evidence of any acceptance by the Town of any
street, easement, or other open space shown on such plan. When a park,
playground, or other recreation area shall have been shown on the plan
to be dedicated to the municipality, approval of the plan shall not constitute
acceptance by the municipality of such areas. The Planning Board shall
require the plan contain appropriate notes to this effect. The Planning
Board may also require the filing of a written agreement between the
applicant and the Municipal Officers covering the future deed and title,
dedication, and provision for the cost of grading, development,
equipment, and maintenance of any such dedicated area.
E. Failure to commence substantial construction of the subdivision within two
(2) years of the date of approval and signing of the plan shall render the
plan null and void. Upon determining that a subdivision's approval has
expired under this paragraph, the Planning Board shall have a notice
placed in the Registry of Deeds to that effect. Failure of the Planning Board
to record a notice regarding the nullity of the approval shall not operate to
continue to permit said approval.
F. Building Permits will not be issued on subdivision lots unless the
subdivision road has been inspected and determined to be built to town
specifications by the Road Commissioner and Code Enforcement Officer.
4.9: Revisions to Approved Plans
4.9.1. Procedure
An applicant for a revision to a previously approved plan shall, at least ten (10)
days prior to a scheduled meeting of the Planning Board, request to be placed
on the Planning Board's agenda. If the revision involves the creation of one (1)
or more additional lots, dwelling units, or business units, the procedures for
Preliminary and Final Plan approval shall be followed. If the revision involves
only modifications of the Approved Plan, without the creation of additional lots or
dwelling units, the procedures for Final Plan Approval shall be followed.
4.9.2. Revision Submissions
The applicant shall submit a copy of the approved plan as well as three (3) copies
of the proposed revisions. The application shall also include enough supporting
information to allow the Planning Board to make a determination that the
74
proposed revisions meet the standards of this Ordinance. The revised plan shall
indicate that it is the revision of a previously approved and recorded plan and
shall show the title of the subdivision and the book and page or cabinet and sheet
on which the original plan is recorded at the Registry of Deeds.
4.9.3. Scope of Review
The Planning Board's scope of review shall be limited to those portions of the
plan which are proposed to be changed.
4.10. General Standards
In reviewing applications for a subdivision, the Planning Board shall consider the
following general standards and make findings that each has been met prior to
the approval of a Final Plan. In all instances, the burden of proof shall be upon
the applicant.
4.10.1. Conformance With Comprehensive Plan.
All proposed subdivisions shall be in conformity with the Comprehensive Plan
and with the provisions of all State and local codes and Ordinances.
4.10.2. Landscape Plan.
The Planning Board may require that the development plans include a landscape
plan that will show the location, type and approximate size of plantings and
location and dimensions of all fencing and screening, the preservation of any
existing trees larger than eighteen (18) inches diameter breast height, the
replacement of trees and vegetation, graded contours, streams, and the
preservation of scenic, historic or environmentally significant areas. Cutting of
trees on the northerly borders of lots should be avoided as far as possible to retain
a natural wind buffer.
4.10.3. Land Not Suitable For Development.
The following lands shall not be included in calculation of net residential acreage,
for purposes of determining the number of lots allowed in a subdivision:
A. Land which is situated below the normal high-water mark of any water body.
B. Land which is located within the 100-year frequency flood plain as identified
by the Federal Emergency Management Agency or the Department of
Housing and Urban Development, Flood Insurance Administration, unless
the sub-divider shows proof through the submittal of materials prepared by
a Registered Land Surveyor which show that the property in question lies
at least two (2) feet above the 100 year flood level. The elevation of filled or
made land shall not be considered.
75
C. Land which is part of a right-of-way, or easements, including utility
easements.
D. Wetland or land that has been created by filling or draining a pond or
wetland.
E. Land in the Resource Protection Overlay Zone.
4.10.4. Lots
A. All lots shall meet the minimum requirements of the Land Use Ordinance
for the district in which they are located, except as follows:
1. In a standard (non-cluster) subdivision all residential lots except those
in the Rural Residential District shall have minimum acreage as
outlined under the Minimum Lot Standards of this Ordinance.
minimum area of two (2) acres per dwelling unit and the deeds shall
contain a covenant prohibiting further division.
2. Special standards apply allowing cluster subdivisions in the residential
and Urban Development districts.
3. The number of lots allowed in any residential subdivision, in any
district, whether it is a cluster subdivision or standard subdivision, shall
be calculated by dividing the net residential acreage by the minimum
lot size applicable to the district in which the subdivision is proposed.
Any fractional portion of the result of this calculation shall not count for
an additional lot. Net Residential Acreage shall be calculated as
provided for in Section 4.10.3 which is entitled "Land Not Suitable for
Development".
B. Lot configuration and area shall be designed to provide for adequate off-
street parking and service facilities based upon the type of development
contemplated.
C. Lots with multiple frontages shall be avoided wherever possible. When
lots do have frontage on two or more roads, the plan and deed restrictions
shall indicate vehicular access shall be located only on the less traveled
way unless such access is prohibited by topography. A planting screen
easement of at least ten (10) feet, across which there shall be no right of
access, shall be provided along the line of lots abutting such a traffic
artery or other disadvantageous use.
D. Wherever possible, side lot lines shall be perpendicular to the street.
76
E. Where public utilities could be extended to the subdivision in the
foreseeable future, the subdivision shall be designed to accommodate the
extensions of utilities.
F. If a lot on one side of a stream, tidal water, road or other similar barrier fails
to meet the minimum requirements for lot size, it may not be combined
with a lot on the other side of the stream, tidal water, or road to meet the
minimum lot size.
G. The lot size, width, depth, shape and orientation and the minimum
building setback lines shall be appropriate for the location of the
subdivision and for the type of development and use contemplated.
H. Except as provided for in subsection 4.10.8 of this article, the subdividing
of the land shall be such as to provide that all lots shall have the
minimum horizontal frontage required by this ordinance on a private or
public street in the district(s) in which the subdivision is located.
4.10.5. Additional Requirements
A. Street trees, esplanades, and open spaces may be required at the
discretion of the Planning Board. Where such improvements are required,
they shall be incorporated in the Final Plan and executed by the sub-
divider as construction of the subdivision progresses.
B. The subdivision design shall minimize the possibility of noise pollution
either from within or without the development (from highway or industrial
sources) by providing and maintaining a green strip at least twenty (20)
feet wide between abutting properties that are so endangered.
4.10.6 Required Improvements
The following improvements are required for all subdivisions unless waived by the
Board in accordance with provisions of these regulations:
A. Monuments. All subdivision boundary corners and angle points, as well as all
lot boundary corners and angle points shall be marked by suitable
monumentation.
B. Water Supply.
1. Individually drilled wells shall be designed and installed on lots less than
four
(4) acres in accordance with requirements of the Maine Department of
Health and Human Services. The location of the wells shall be drawn
77
on the plot plan.
2. When a subdivision is to be served by a public water system, the
complete supply system, including fire hydrants, shall be installed at
the expense of the sub-divider.
3. If a central water supply is provided by the sub-divider, the location
and protection of the source, and the design, construction and
operation of the system shall conform to the standards of the Maine
Rules Relating to Drinking Water (10-144 A.C.M.R. 231).
4. In a subdivision having more than four (4) lots which are greater than
a 1,000 foot hose length from a public water system hydrant, the sub-
divider shall construct ponds and dry hydrants to provide for adequate
water storage for fire-fighting purposes. An easement shall be granted
to the Town granting access to the dry hydrants and ponds when
necessary. The Planning Board may waive the requirement for fire
ponds only upon submittal of evidence that the soil types in the
subdivision will not permit their construction.
C. Sewage Disposal
1. Private Systems.
a. The location of the designed system shall be laid out on the Plan.
b. In no instance shall a disposal area be permitted on soils or on a lot
which requires a New System Variance from Subsurface
Wastewater Disposal Rules.
2. Systems for Commercial or Industrial Uses
a. Holding tanks shall be permitted if they comply with the applicable
standards of the Maine Subsurface Wastewater Disposal Rules.
b. Public restroom facilities shall be provided in all commercial
subdivisions.
3. Multi-User Wastewater Disposal Systems. Multi-user wastewater
disposal systems designed to serve three or more separately owned
dwelling units and/or non-residential uses shall be permitted if approved
in writing by the Maine Department of Human Services as required
under the Maine State Plumbing Code, and provided the following
standards are met. Multi-user wastewater disposal systems serving
condominiums are also subject to this section.
a. Multi-user wastewater disposal systems shall be permitted only
when all other options for serving the wastewater needs of the users
78
included in the design have been found to be physically or legally
infeasible by a licensed site evaluator. The number of users on any
proposed multi-user system shall be limited to those without any
individual system alternative, on-site or off-site, except a multi-user
system.
b. All parts of the multi-user wastewater disposal system beyond the
building sewer shall be owned in common by the homeowner's
association or other association made up of lot or unit owners in the
development. In any development or group of homes or businesses
served by a multi-user wastewater disposal system, the association
shall be mandatory and membership in it by all owners that are users
of the system, including absentee owners, shall also be required.
c. The owner's association shall be an independent entity, legally
established under Maine Law. It shall be liable for the operation,
maintenance, repair or replacement of all parts of the multi-user
system beyond the individual building sewers. It shall keep the
system free of any nuisance or threat to the public health or
contamination of the environment.
d. The owner's association shall charge a maintenance fee and other
fees adequate to assure sufficient capitalization to meet its
responsibility to maintain and to replace all parts of the commonly
owned multi-user system.
e. The owner's association shall acquire all necessary rights of entry
and across property for purposes of accessing elements of the
multi-user system for evaluation, maintenance, or replacement.
These shall include access to a suitable site for replacement of the
leach-field.
f. Before a multi-user system can be approved by the Town, the
applicants for a multi-user system permit shall submit.
i.
A hydrogeological assessment prepared by a Maine-certified
hydrogeologist evaluating groundwater impacts of the
proposed system and whether they will be consistent with
standards contained in Subsection D.3 of this section.
ii.
A letter of approval for the proposed system from the Maine
Department of Human Services including any applicable
conditions of approval imposed by the department.
D. Impacts on Groundwater Quality or Quantity
79
1. When a hydrogeological assessment is submitted, the assessment
shall contain at least the following information:
a. A map showing the basic soil types.
b. The depth to the water table at representative points throughout
the subdivision.
c. Drainage conditions throughout the subdivision.
d. Data on the existing ground water quality, either from test wells in
the subdivision or from existing wells on nearby neighboring
properties.
e. An analysis and evaluation of the effect of the subdivision on
ground water resources. In the case of residential developments,
the evaluation shall, at a minimum, include a projection of post
development nitrate and nitrogen concentrations at any wells
within the subdivision, or at the subdivision boundaries; or at a
distance of one thousand (1,000) feet from potential contaminant
sources, whichever is the shortest distance.
f. A map showing the location of any subsurface wastewater disposal
systems and drinking water wells within the subdivision and within
two hundred (200) feet outside of the subdivision boundaries.
2. Projections of ground water quality shall assume of drought conditions
(60% of annual average precipitation).
3. A subdivision may not increase any groundwater contaminant
concentration by more than 50% of the applicable federal Primary
Drinking Water Standard, and in no case may it raise any contaminant
concentration above 80% of that standard. In addition, no subdivision
may increase any groundwater contaminant concentration above the
federal Secondary Drinking Water Standards.
4. If ground water contains contaminants are greater than the primary
standards, and the subdivision is to be served by on-site ground water
supplies, the applicant shall demonstrate how water quality will be
improved or treated.
5. If ground water contains contaminants greater than the secondary
standards, the subdivision shall not cause the concentration of the
parameters in question to exceed 150% of the ambient
80
concentration.
6. Subsurface wastewater disposal systems and drinking water wells
shall be constructed as shown on the map submitted with the
assessment. If construction standards for drinking water wells or other
measures to reduce groundwater contamination and protect drinking
water supplies are recommended in the assessment, those standards
shall be included as a note on the Final Plan, and as restrictions in the
deeds to the affected lots.
E. Surface Drainage. This section shall pertain to subdivisions traversed by
streams, rivers, a surface water drainage-way, or where the Planning Board
feels that surface water runoff to be created by the subdivision should be
controlled.
1. There shall be provided easements or drainage rights-of-way with
swales, culverts, catch basins or other means of channeling surface
water within the subdivision and over other properties. This storm-
water management system shall be designated by a Registered
Professional Engineer.
2. Drainage Easements for existing water-courses or proposed drainage
ways shall be provided and indicated on the plan at least thirty (30)
feet wide, conforming substantially with the lines of existing natural
drainage.
3. The developer shall provide a statement from the designing engineer
that the proposed subdivision will not create erosion, drainage or
runoff problems either in the subdivision or in other properties. Where
the peak runoff from the subdivision onto other properties is increased
either in volume or duration, easements from the abutting property
owners, allowing such additional discharge shall be obtained.
4. A Storm Water Drainage Plan, showing ditching, culverts, storm drains,
easements, and other proposed improvements, meeting the
standards of Article 3.11.P shall be submitted.
F. Phosphorus Impacts on Great Ponds.
1. Phosphorus Export.
a. Any subdivision within the watershed of a great pond shall limit its post-
development phosphorus export to the standards contained in Table
4.1 below.
81
2. Phosphorus Controls for subdivisions as defined in section 4.2.1 of this
ordinance shall meet the following standards:
a. Existing wooded buffers shall be provided whenever possible.
b. Wooded buffers shall be a minimum of 75 feet in width.
c. Non-wooded buffers shall be at least 125 feet in width.
d. All drainage from the proposed subdivision shall pass through the
proposed buffer or buffers shown on the plan.
e. Driveways and parking areas must be designated and constructed so
that runoff is quickly shed form these areas to protected buffer areas
(to the maximum extent reasonably feasible given lot limitations) and
disruption of natural drainage patterns is minimized. Best
management practices (BMPs) such as swales, water bars, road-
based drainage dips, and proper grading of gravel drives should be
used to prevent runoff from concentrating in the driveway and to get
it into the buffer areas as quickly as feasible. These requirements
must be incorporated into the lot's deed covenants and restrictions.
f. Road and roof runoff must be distributed over stable, well vegetated
areas or be infiltrated into the soil using dry wells or other infiltration
systems. These requirements must be incorporated into the Lot's
Deed covenants and restrictions.
g. Deed covenants and restrictions must prohibit the use of lawn
fertilizers containing phosphorus except during the establishment of
new turf on bare soil.
Table 4.1
Phosphorus Export Limits in Great Pond Watersheds
Great Pond Watershed
Per Acre Phosphorus Export Limitation
Campbells Pond
0.42 pounds per acre per year
82
h. The septic system must meet the standards of the Maine State
Plumbing Code and shall incorporate a loam liner whenever
appropriate.
i. A proposed small subdivision that creates lots capable of being
further divided into five or more total lots is subject to the phosphorus
control standards for larger subdivisions and subdivisions with new
roads, as described in subsection 3 below, unless deed restrictions
prohibit any future lot division.
3. Phosphorus Controls for Larger subdivisions and subdivisions with
New Roads.
a. This subsection shall apply to all proposed subdivisions other than
small subdivisions as defined in section 4.2.1 of this ordinance.
b. Phosphorus export from a proposed development shall be
calculated according to the procedures in Phosphorus Control in
Lake Watersheds: A Technical Guide for Evaluating New
Development,
published
by
the
Maine
Department
of
Environmental Protection, revised September 1992. When a
proposed subdivision creates lots which are more than twice the
required minimum lot size and there are no deed restrictions
proposed to prohibit future divisions, the applicant shall either
calculate phosphorus loading based on the maximum feasible
number of lots and shall design controls adequate to limit the
resulting phosphorus loading, or shall reserve a portion of the
permitted phosphorus export for future divisions.
c. Maintenance and Use Restrictions for Phosphorus Control
Measures.
1. Written
provisions
for
monitoring,
inspections,
and
maintenance of phosphorus control measures shall be included
in the application.
G. Vegetative Buffer Strips.
The locations of wooded buffers and non-wooded buffers shall be clearly
designated on the plan. Requirements for maintenance of buffers
shall be included in deed restrictions and/or conservation easements,
and as notes upon the plan. Copies of the plan showing the
83
phosphorus control buffers shall be provided by the developer to the
purchasers of lots in the subdivision at the time of sale.
H. Infiltration Systems.
Individual lot owners shall be responsible for maintenance of individual
infiltration systems according to the standards specified in Phosphorus
Control in Lake Watersheds: A Technical Guide for Evaluating New
Development, published by the Maine Department of Environmental
Protection, revised September 1992. Requirements for maintenance shall be
included in deed restrictions and as notes up the plan. As an alternative to
maintenance by individual LOT owners, the applicant may designate some
other entity to be contracted to take the responsibility and shall include the
above referenced maintenance provisions in any contractual agreement.
Where infiltration systems serve more than one lot, a lot owners' association
shall be established, and the above referenced maintenance provisions shall
be referenced in the documentation establishing the association.
I. Wet Ponds.
Lot owners' association shall be established to maintain wet ponds, unless the
municipality or some other public entity agrees to assume inspection and
maintenance
duties.
Documentation
establishing
the
association
or
establishing an agreement with a public entity shall include the maintenance
standards specified in the manual Phosphorus Control in Lake Watersheds: A
Technical Guide for Evaluating New Development, published by the Maine
Department of Environmental Protection, revised September 1992.
4.10.7. Land Features
A. Topsoil shall be considered part of the subdivision and shall not be
removed from the site except for surplus topsoil from roads, parking
areas, and building excavations.
B. Except for normal thinning, landscaping, and cutting trees to provide
access to direct sunlight, existing vegetation shall be left intact to prevent
soil erosion in the proposed subdivision.
C. Clearing of trees and conversion of other vegetation is permitted for
approved construction and landscaping. Where natural vegetation is
removed, it shall be replaced with other vegetation that is equally effective
in retarding erosion and preserving natural beauty.
84
4.10.8. Cluster Subdivisions
A. Purpose
The purpose of these provisions is to allow for new concepts of housing
development where maximum variation of design may be allowed, to
maintain the low density character of the town, and to encourage open
space preservation, including open spaces which are scenic or historic or
provide habitat for critical natural resources, provided that the net
residential density shall not be greater than is permitted in the District in
which the development is proposed.
Cluster developments shall be permitted only in the Residential and
Urban Development Districts. They shall meet all the following criteria:
B. Basic Requirements
1. All cluster developments shall meet all requirements for a residential
subdivision, except where specifically modified by this section. Each
building site shall be shown on an Overall Plan for Site Development.
The application shall illustrate the placement of buildings and the
treatment of spaces, paths, roads, service and parking.
2. The minimum area of land in a cluster development shall be 10 acres.
There shall be no approval of any proposed development which
exceeds the number of lots permitted in the district in which it is
located.
3. Any lot abutting an existing public road shall have a frontage and area
no less than that normally required in the District. For lots on internal
subdivision roads, lot area and road frontage may be reduced by up to
fifty (50) percent of the District requirements, provided that:
a. No building lot shall have an area of less than what is allowed by this
Ordinance or state law.
b. All lots except those abutting a circular turn-around shall have a
minimum frontage of 75 feet.
c. Average lot width shall be no less than the road frontage
requirement for the District in which the development is proposed.
d. Except for the common land, lots in a cluster subdivision shall be no
larger than the minimum lot size for the land use district in which the
subdivision is proposed.
85
4. In no case shall shore frontage be reduced below the minimum shore
frontage normally required in the District.
5. Lots in a cluster development shall meet all other dimensional
requirements for the District in which they are located.
6. The total area of common land within the development shall equal or
exceed the sum of the areas by which any building lots are reduced
below the minimum lot area normally required in the District.
7. Multi-family dwellings, not to exceed four units, will be permitted on a
separate lot.
8. All common land for recreational or conservation purposes only shall
be owned jointly or in common by the owners of the building lot, or by
a land trust with a principal purpose of conservation or preservation
of land in its natural condition.
9. Further subdivision of common land or its use for other than non-
commercial recreation or conservation, except for easements for
underground utilities, shall be prohibited. Structures and buildings
accessory to non-commercial recreational or conservation uses may
be erected on the common land.
10. Where a cluster development abuts a waterbody, a portion of the
shoreline, as well as reasonable access to it, shall be part of the
common land.
11. Unless the developer clearly demonstrates to the Planning Board that
it is not feasible, all dwelling units in the development shall be
connected to individual water supply wells. Where a common water
supply well(s) and distribution system, either public or private, are
necessary, the developer shall clearly demonstrate to the Planning
Board that such a system is feasible:
a. That the cost of providing a common water supply and distribution
system is prohibitive;
b. That adequate water is available to serve all locations proposed
for individual or common water systems; and
c.
That the ground water source(s) proposed for individual water
systems is safe from both on-site and off-site contamination.
86
12. All structures with required plumbing in the development shall be
connected to individual subsurface wastewater disposal systems in
accordance with minimum standards set forth in the State of Maine
Plumbing Code, unless the developer shall clearly demonstrate to the
Planning Board that a multi-user wastewater disposal system is
necessary to serve all or some of the units proposed.
13. Covenants for mandatory membership in the homeowner's association
setting forth the developer's and each lot or unit owner's rights and
interest and privileges in the association and the common land, shall
be reviewed by the Planning Board and included in the deed for each
lot.
14. The association shall levy annual charges against all property owners
to defray the expenses connected with the maintenance of open
space, neighborhood recreational facilities, property taxes and other
association assessments.
15. The developer or sub-divider shall maintain control of such open
space(s) and be responsible for their maintenance until development
sufficient to support the association has taken place or, alternatively,
the objectives of clustering have been met. Such determination shall
be made by the Planning Board upon request of the neighborhood
association or the developer or sub-divider.
16. The total area of reserved open space within the development shall
be at least equal to the total amount by which and BUILIDNG LOTS
are reduced below the minimum lot area required by the Zoning
Ordinance. No more than 50% of the reserved open space may
consist of land unsuitable for development as defined in Section
4.10.3 of this Ordinance (Land not suitable for development). Every lot
in the subdivision shall have access by road or path to the commonly
owned open space.
17. Every building lot that is reduced in area below the amount normally
required shall be within 1,000 feet of the nearest boundary of
commonly owned open space within the subdivision.
18. Individual lots or dwelling units shall have direct vehicular access only
87
onto internal roads within the subdivision.
4.10.9. Dedication and Maintenance of Common Land and Facilities
This section shall apply to all commonly owned open space and facilities,
whether located in cluster subdivisions or standard subdivisions, or other
developments.
A. All common land shall be owned jointly or in common by the owners of
the dwelling units by means of a homeowners' association, or by a land
trust which has as its principal purpose the conservation or preservation
of land in essentially its natural condition.
B. Further subdivision of the common land or its use for other than non-
commercial recreation or conservation purposes, except for easements
for underground utilities, shall be prohibited. Structures and buildings
accessory to non-commercial recreational or conservation uses may be
erected on the common land.
C. The common open space shall be shown on the Final Plan with an
appropriate notion on the plan to indicate that:
1. It shall not be used for future building lots.
2. It shall be reserved as common open space.
D. If any or all of the common open space and facilities are to be reserved for
use by the residents, the by-laws of the proposed homeowners'
association shall specify maintenance responsibilities and shall be
submitted to the planning board prior to Final Plan approval.
E. Covenants for mandatory membership in the homeowners' association
setting forth the owners' rights, interests, and privileges in the
association and the common property, shall be reviewed by the Planning
Board and included in the deed for each lot or dwelling.
F. The homeowners' association shall have the responsibility of maintaining
the common property. Draft articles of incorporation for the proposed
homeowners' or lot owners' association as a not-for-profit corporation
shall be submitted for review by the Planning Board .
G. Draft by-laws of the proposed homeowners' or lot owners' association
specifying the responsibilities and authority of the association, the
operating procedures of the association and providing for the proper
capitalization of the association to cover costs of repairs, maintenance
and replacement of common facilities shall also be submitted for review
88
by the Planning Board. The scope of Planning Board review authority for
these documents shall be limited to provisions affecting the association's
capacity to meet this Ordinance's standards for multi- user wastewater
disposal systems and for common land.
H. The association shall levy annual charges against all owners of dwelling
units to defray the expenses connected with the maintenance of common
property and tax assessments.
I. The developer or sub-divider shall maintain control of the common
property, and be responsible for its maintenance until development
sufficient to support the association has taken place.
4.11. Performance Guarantees
4.11.1 Types of Guarantees.
With submittal of the application for Final Plan Approval, the sub-divider shall
provide one of the following performance guarantees for an amount adequate to
cover the total construction costs of all required improvements, taking into
account the time-span of the construction schedule and inflation rate of
construction costs:
A. Either a certified check, payable to the Town, or a savings account or
certificate of deposit naming the Town as owner, for the establishment of
an escrow account;
B. A performance bond payable to the Town issued by a surety company,
approved by the Municipal Officers;
C. An irrevocable letter of credit from a financial institution establishing
funding for the construction of the SUBDIVISION, from which the Town
may draw if construction is inadequate, approved by the Municipal
Officers. The conditions and amount of the performance guarantee shall
be determined by the Planning Board with the advice of the Road
Commissioner and/or Municipal Officers.
4.11.2 Contents of Guarantee.
The performance guarantee shall contain a construction schedule, cost
estimates for each major phase of construction, provisions for the release of the
performance guarantee to the developer, and a date after which the developer
89
will be in default and the Town shall have access to the funds to finish the
construction.
4.11.3. Escrow Account.
A cash contribution to the establishment of an escrow account shall be made by
either a certified check made out to the municipality, the direct deposit into a
savings account, or the purchase of the certificate of deposit. For any account
opened by the sub-divider, the municipality shall be names as owner or co-
owner, and the consent of the municipality shall be required for a withdrawal.
Any interest earned on the escrow account shall be returned to the sub-divider
unless the municipality has found it necessary to draw on the account, in which
case the interest earned shall be proportionately divided between the amount
returned to the sub-divider and the amount withdrawn to complete the required
improvements.
4.11.4. Performance Bond.
A performance bond shall detail the conditions of the bond, the method for
release of the bond or portions of the bond to the sub-divider, and the procedures
for collection by the municipality. The bond documents shall specifically
reference the SUBDIVISION for which approval is sought.
4.11.5 Letter of Credit.
An irrevocable letter of credit from a bank or other lending institution shall
indicate that funds have been set aside for the construction of the SUBDIVISION
and may not be used for any other project or loan.
4.11.6 Release of Guarantee.
Prior to the release of the performance guarantee, the PLANNING BOARD shall
determine to its satisfaction, in part upon the report of the Code Enforcement
Officer and whatever other agencies and departments may be involved, that the
proposed improvements meet or exceed the design and construction
requirements.
4.11.7 Default.
If, upon inspection, the Code Enforcement Officer finds that any of the required
improvements have not been constructed in accordance with the plans and
specifications filed as part of the application, he shall so report in writing to the
Municipal Officers, the PLANNING BOARD, and the sub-divider or builder. The
Municipal Officers shall take any steps necessary to preserve the Town's rights.
90
4.11.8 Improvements Guaranteed.
Performance guarantees shall be tendered for all improvements for which the
PLANNING BOARD requires them.
ARTICLE V. SPECIFIC STANDARDS
Uses listed under this Chapter shall be required to address both the specific standards
of the corresponding Use, as well as all standards listed under the 'General Standards'
section, unless granted a waiver by the municipal reviewing authority.
5.1. Accessory Dwelling Unit (ADU)
A. The owner of an Accessory Dwelling Unit or regular Dwelling Unit must
provide written verification to the municipality that each unit is
connected
to
adequate
water
and wastewater services prior
to certification of occupancy or similar type of approval. Written verification
may include the following:
1. If connected to the City of Bath sewer, or a comparable sewer system
as defined in this Ordinance, proof of adequate service to support any
additional flow created by the unit and proof of payment for the
connection to the sewer system.
2. If connected to a private septic system, proof of adequate sewage
disposal for subsurface wastewater. The septic system must be
verified as adequate by a local plumbing inspector pursuant to 30-A
MRS 4221. Plans for a subsurface wastewater disposal must be
prepared by a licensed site evaluator in accordance with 10-144 CMR
Ch.241, Subsurface Wastewater Disposal Rules.
3. If connected to the City of Bath Water District, or a centrally managed
water system as defined in this Ordinance, proof of adequate service to
support any additional flow created by the unit, proof of payment for the
connection, and the volume and supply of water required for the unit.
4. If connected to a private well, proof of access to potable water,
including the standards outlined in 01-672 CMR. C.10 Section
10.25(J), Land Use District and Standards. Any test of an existing well
or proposed well must include that the water supply is potable and
acceptable for domestic use.
B. Only one (1) Accessory Dwelling Unit may be constructed on each lot that has
an existing single-family or duplex on the lot. The Accessory Dwelling Unit
91
may be within an existing dwelling unit, attached to an existing dwelling
unit, or detached from an existing dwelling unit. Accessory Dwelling Units
shall also:
1.
Be exempt from additional parking requirements. However, the
Accessory Dwelling Unit must have access to the existing single-
family or duplex driveway and parking spaces.
2. Be exempt from minimum lot size. Accessory Dwelling Units shall still
meet all other dimensional standards under Article III.A (Minimum
Lot Standards), such as the setback requirements.
3. Have access to adequate water and wastewater as described
under B.14 of this Article.
4.
Be permitted on non-conforming lots as long as the Accessory
Dwelling Unit does not make the lot and structures more non-
conforming.
5. Be required to meet Shoreland Zoning requirements. This includes
addressing all minimum lot size and parking requirements if the
Accessory Dwelling Unit is within a municipally designated Shoreland
Zone.
5.2. Affordable Housing Development
A. Affordable Housing Developments are only permitted in Districts that permit
multi-family dwelling units, except for Shoreland Zones, and are
Designated Growth Areas that can be cited in the most recent Town of West
Bath Comprehensive Plan. Affordable Housing Developments shall also:
1. Provide sufficient water and wastewater services as described
under B.14 of this Article.
2. Demonstrate the proposal can comply with the minimum lot size
requirements in accordance with Title 12 Chapter 423-A. The dwelling
unit density shall be 2.5 times the base density that is otherwise
allowed in that location. If fractional results occur when calculating the
density bonus, the number of units is rounded down to the nearest
whole number. For the purposes of illustration, a typical multi-family
housing project of five (5) units would need at least five (5) acres
in the Business and Commercial District for approval. If the Affordable
Housing Development can satisfy all standards in this Ordinance, a
92
proposed development of five (5) units would need at least two (2)
acres.
3. Provide at least two (2) off-street parking spaces for every three (3)
affordable units as determined by this Ordinance. Applicants shall
demonstrate and enforce their tenants not parking on a public right-
of-way.
4. Execute a restrictive covenant, recorded in the Sagadahoc County
Registry of Deeds, enforceable by a party acceptable to the Planning
Board, to ensure that at least thirty (30) years after completion of
construction:
a. For rental housing, occupancy of all the units designated
affordable in the development will remain limited to households
at or below 80% of the local area median income at the time of
initial occupancy; and
b.
For owned housing, occupancy of all the units designated
affordable in the development will remain limited to households at
or below 120% of the local area median income at the time of initial
occupancy.
5.3
Business and Commercial Development
A. The median height of BUILDINGS or other STRUCTURES with the
exception of telecommunication, utility and water towers and poles shall not
exceed 35 feet except in District 4. Business & Commercial and District
5. Urban Development Park where BUILDINGS more than 75 feet from
the boundaries of other districts can exceed 35 feet by up to 20 feet subject
to architectural review and screening if the following conditions are met:
1. A functional need can be demonstrated
2. Any exterior or stair tower access to the uppermost floor does not
exceed 45 feet above grade.
3. A sprinkler system is installed if required by the Fire Department
and/or State Authority to meet NFP 101 or other applicable state or
national code.
93
4. Any firefighting plan including access for firefighting vehicles
required by the Fire Department is on file with said department.
B. In the Business and Commercial District, in order to help preserve existing
vegetation for meeting the buffer requirements associated with future
development, PLANNING BOARD approval is required prior to the
clearing of any more vegetation beyond that which is necessary to provide
one vehicular access to the front of the property, even if no development
is proposed at the time of the proposed clearing. Clearing for the one
vehicular access shall not exceed 40 feet in width.
1. Prior to clearing of more vegetation than is needed for a vehicular
access, the owner of the property shall prepare and submit to the
PLANNING BOARD a clearing plan that demonstrates on a plan of
the property:
2. How the owner plans to comply with the DRIVEWAY maximum width
requirement and other locational requirements for DRIVEWAYS
contained in Article III, Section 3.10 of this Ordinance.
3. How the owner plans to comply with the vegetative buffer requirements
applicable to properties in the Business and Commercial District that
are contained in Article III, Section 3.1 of this Ordinance.
C. The clearing plan shall indicate that cleared vegetation in excess of that
needed to provide one access to the property shall be replanted within
the buffer-strip areas required if and when the LOT is developed or
redeveloped and show the location of these buffer strip areas.
The
clearing plan shall also state that any areas planned for clearing, whether
or not they are now part of a required buffer area shall be replanted if they
fall within the buffer strip area on a LOT that is part of a future
SUBDIVISION of the property.
D. The owner of the property shall obtain PLANNING BOARD approval of
the Clearing Plan before clearing more vegetation than is necessary to
create a single 40-foot-wide access to the property.
E. The above line 5.3.C shall apply to TIMBER HARVESTING as well as
clearing of vegetation.
F. Any non-residential use shall be set back from the boundaries of
districts or overlay zones where it is not allowed by at least the side/rear
SETBACK of the district in which it is located, whichever is greater.
94
G. Substance abuse medical treatment facilities shall be connected to
public water and sewer and must have a vault for the storage of scheduled
drugs and dangerous materials or objects and monitored by a 24-hour
security service.
H. No commercial use may be made of vegetative boundary strips other
than for free-standing signs and walkways which may be located in
roadside vegetative boundary strips. For purposes of this subsection
vegetative boundary strips as delineated in this Land Use Ordinance are
presumed to exist whether or not any vegetation is present.
5.4. Mineral Exploration and Extraction
A.. Mineral exploration to determine the nature or extent of mineral
resources shall be accomplished by hand sampling, test boring, or other
methods which create minimal disturbance. Mineral exploration or
extraction shall be prohibited in the Shoreland Overlay Zone.
5.5 Mobile Homes
A.. No MOBILE HOME, new or existing, shall be placed on a BUILDING site
until a full foundation with footings extending at least 4 feet below grade or
alternatively for a MOBILE HOME a 6 inch thick reinforced concrete slab
with provisions for tie-downs on a gravel or crushed stone bed and a
sewage system that meets State Plumbing Code has been constructed
and approved by the Code Enforcement Officer and/or Local Plumbing
Inspector and the respective permits issued unless waived by the Code
Enforcement Officer due to unusual circumstances.
B. One MOBILE HOME, house trailer or recreational vehicle may be
occupied as a dwelling temporarily on the same LOT during the
construction of a permitted dwelling for a period of not more than 60 days,
except upon application(s) for additional 30 day periods. A temporary
occupation fee must be paid for each 60 & 30 day period. The unit must
meet sewage disposal standards under the State of Maine Plumbing
Code.
C. MOBILE HOMES located outside mobile home parks shall be defined and
treated as single family dwellings and shall comply with the applicable
provisions of all ordinances of the Town of West Bath. A BUILDING permit
for a MOBILE HOME shall not be issued unless it meets the following
requirements and standards:
1. A minimum width of feet and a minimum FLOOR AREA of 750
square feet.
2. A roof pitch of 2 or more vertical units for every 12 horizontal units
3. Exterior siding that is residential in appearance.
95
4. It will be placed upon and anchored to a permanent foundation.
5. Proof of payment of sales tax is presented to the Code Enforcement
Officer.
6. Unit was built after June 14, 1976 and is certified by the US Department
of Housing and Urban Development.
5.6. Mobile Home Park Standards
A. Individual LOT size:
1. LOTS served by a public sewer system shall be at least 6,500 square
feet.
2.
LOTS served by a central on-site subsurface wastewater disposal
system approved by the Department of Human Services shall be at least
12,000 square feet, provided that the overall density of the mobile home
park shall be at least 20,000 square feet for every home.
3. LOTS with on-site subsurface wastewater disposal shall be at least
20,000 square feet.
B. Park size shall include the sum of the individual LOTS plus the following:
1. Area required for ROAD rights of way.
2. Area required for buffer strips.
3. Area set aside for open space, storage or recreation.
C. MOBILE HOMES on LOTS adjacent to a public ROAD shall be set back
one hundred (100) feet from the center of the right of way and each LOT
shall have one hundred (100) feet of frontage.
D. Privately owned ROADS within a mobile home park shall:
1. Be built according to acceptable engineering standards and with
a professional ENGINEER's seal as required by the Manufactured
Housing Board.
2. Have a right of way at least twenty-three (23) feet in width, twenty (20
feet of which is paved.
3. Conform to reasonable safety standards applicable to intersections
with public way adjacent to the mobile home park. Approval of
intersections is required from the Town ROAD Commissioner.
E.
A buffer strip fifty (50) feet wide, including LOT SETBACKS, shall be
provided along any mobile home park boundary which abuts land used for
96
residential use if the per acre density of homes within the park is at least
two times greater than the allowed density of residential development on
adjacent parcels of land. Natural screening requirements within the first
twenty-five (25) feet of the buffer strip shall conform to the standards found
in Article III, Section 3.1.
F. Dimensional requirements:
1.
Individual LOTS shall have fifty (50) feet of frontage on private
ROADS within the park. Homes shall be set back fifteen (15) feet from
any LOT line and forty (40) feet from the center of the interior ROAD.
G. For mobile home parks served by a public sewer an area equal to ten (10)
percent of the combined area of the individual LOTS shall be set aside
for open space, storage or recreations.
5.7. Home Occupation Standards
A Home Occupation use may be approved by the Code Enforcement Officer if
the applicable municipal and state approvals are obtained and the following
standards are met:
A. The existence of the business shall not be discernable from outside the
BUILDING.
B. The FLOOR AREA used for the business whether located in the dwelling
or an outbuilding shall not exceed 25 percent of the total FLOOR AREA
of the dwelling except for a Bed and Breakfast which is exempt.
C. Signage shall be limited to the name of the business on a standard
size mailbox and a sign not exceeding three (3) square feet in area for
the business entrance.
D. The business shall be conducted by resident(s) of the household and no
more than two full-time, or equivalent, persons that are not living on the
premises.
E. There shall be no retail sales other than incidental sales related to the
service provided.
F. Business uses must comply with all State requirements for that use.
G. Home occupation may not produce any odors, fumes, dust, smoke, vibrations,
glare, noise, or electrical interference in excess of that produced by normal
residential use. Failure to address a complaint issued by the Code
Enforcement Office within thirty (30) days of notice may result in the removal
of the Home Occupation permit.
97
H. Home Occupation shall be conducted wholly within the principal building or
within an accessory building on the property. Any storage outside the
buildings must be screened to minimize visual impact from public right of
ways or abutting properties.
5.8. Setback Reduction Plan - UDP District
A. Applies to new and expanded uses in UDP District.
B. The purpose of the SETBACK Reduction Plan is to allow the SETBACK
distance to be reduced if a plan for establishing a landscaped buffer is
agreed to by the applicant and approved by the PLANNING BOARD.
C. The landscaped buffer must meet the following criteria:
1. The plan must be prepared by a landscape architect registered in the
State of Maine.
2. The buffer may include plant materials such as trees or shrubs, walls
or fences, and earthen berms, or a combination thereof (but may not
consist of only a fence).
3. The buffer must be sufficient in density and height so as to screen
noise, light or other visual nuisances.
a. The buffer must be visually pleasing and effective year-round.
b. The buffer must be maintained.
c. The burden of proving that these criteria are met is that of the
applicant.
D. The SETBACK Reduction Plan will be reviewed by the PLANNING BOARD
as part of the Site Plan Review.
5.9. Small Wind Energy Conversion Systems
A. Purpose
The purpose of this Ordinance is to regulate the placement and
construction of and to provide standards for small wind energy
98
conversion systems that are used to produce electrical power primarily
for on-site consumption, in order to promote their safe and efficient
use and to minimize the visual, environmental, and operational impacts
of these systems.
B. Approval Required
No small wind energy conversion system may be sited, constructed or
operated without approval from the West Bath PLANNING BOARD in
accordance with the provisions of this Ordinance and applicable provisions
of the Town of West Bath Site Plan Review Ordinance.
C. Location
Small wind energy conversion systems are permitted as an accessory
use in all Districts within the Town except the Resource Protection Zone.
D. Submission Requirements
1. Applicant: Identification of the property owner and agent or
representative if applicable, including all contact information. If the
property owner is represented by agent, the agent must supply
documentation with the original signature of the owner authorizing the
agent or representative to represent the property owner during the
application process.
2. Location Map: A location map that will generally show the location of
the site within the Town where the small wind energy conversion
system is proposed, together with the street address, map and lot
number of the property, the book and page reference of the property's
deed evidencing title to the site.
3. Site Map: A site plan showing the planned location of the small
wind energy conversion system on the property, showing all property
lines and SETBACK lines. Map shall also show all existing
STRUCTURES, fencing, access ROADS and drives, rights-of-way,
turnout locations, electric cabling from the system to the utility,
accessory equipment, within one hundred (100) feet of the system's
Safety Zone. The PLANNING BOARD may require the showing of
additional physical features of the property and/or a topographical
contour map of the area adjacent to the system location.
4. System Definition: Specifications, schematics and drawings
prepared by the manufacturer or a professional ENGINEER of the
proposed system together with its tower and base or foundation. If
an attachment to an existing STRUCTURE is proposed, a
99
description of, or a drawing acceptable to the PLANNING BOARD,
shall be submitted. This submission shall also include the power
generating capacity of the generator, hub weight, rotor diameter, the
total height of the STRUCTURE and its specified noise level
measured in dBA, and that noise levels will be in compliance with the
development standards in Subsection 7(c) below.
5. Description of the Use: A description of the uses on site that the
system is accessory to.
6. Visual Study: A visual representation of the small wind energy
conversion system as proposed which may be drawings and/or a
computerized photographic overlay. The visual study shall also
indicate the color treatment of the system's components and any
visual screening incorporated into the site that is intended to lessen the
system's visual prominence.
7. Notice to Utility: If connection to the publicly regulated utility grid is
proposed, a copy of the contract between the applicant and Utility is
required, verifying the proposed connection is acceptable or such
other evidence that the Utility is aware of and will accept the proposed
connection.
8. Clearing: If any clearing/tree cutting is proposed for development of the
site, a clearing plan shall be submitted. Within the shoreland zone, tree
and other vegetation removal for the development or construction of a
small wind energy conversion system shall fully comply with the
standards in Article IV, Section 4.10.7.
9. Site Plan Requirements: Such other submissions and information as
may be required by the PLANNING BOARD in order to meet site
plan review requirements, as determined by the PLANNING BOARD.
10. Property Owners: List of property owners, with their mailing
addresses, whose properties are within 200 feet of the boundaries of
the proposed parcel.
E. Siting and Dimensional Requirements
1. LOT Size: The minimum LOT size for a small wind energy conversion
system shall be one (1) acre.
2. Limit Per LOT: There shall be no more than one (1) small wind
energy conversion system per LOT.
100
3. Safety Zone: All small wind energy conversion systems shall be
SETBACK a minimum horizontal distance of 1.25 times the total height
of the system from the property lines, ROADS, EASEMENTS and
STRUCTURES. New STRUCTURES shall not be constructed
within the SETBACK area after a small wind energy conversion system
is constructed and operation.
4. Height: The total height of a small wind energy conversion system
shall not exceed 150 feet.
5. Tree Clearing: No clear cutting on a ridge line in excess of a fifty by
fifty (50 x 50) foot area is allowed.
F. Development Standards
1. On-Site Construction: It shall be the primary purpose of a small
wind energy conversion system to produce electrical power for on-
site consumption to service a use on that LOT.
2. Maximum Power: The maximum power output for each small wind
energy conversion system shall be fifty (50) kilowatts.
3. Noise: Audible noise generated by the small wind energy conversion
system at the property boundary line of the proposed site shall not
exceed forty-five (45) dBA. Excluded from these noise levels limits
are short term events such as severe windstorms.
4. Non-Reflective Color Scheme: The system's tower, hub and rotor
shall be a non-reflective color that blends the system and its
components into the background to the greatest extent possible.
Visual Impacts: The system shall be designed and located in such
a manner to minimize negative visual impacts.
5. Exterior Lighting Prohibited: Exterior lighting on any tower or turbine
associated with the small wind energy conversion system shall not be
allowed unless required by the FAA.
6. Underground Wiring: All on-site electrical wires associated with the
systems shall be installed underground except for "tie-ins" to a public
utility company transmission poles, towers, and lines. This standard
may be modified by the PLANNING BOARD if the project terrain is
determined to be unsuitable due to reasons of the need for
excessive site work such as blasting.
7. Electromagnetic Interferences: The system shall be operated and
located such that no disruptive electromagnetic interference with signal
transmission or reception or off-site communications, surveillance, or
101
other similar systems, is caused beyond the site. If it has been
demonstrated that the system is causing disruptive interference beyond
the site, the
owner shall promptly eliminate the
disruptive
interference or cease operation of the system.
8. Signage: At least two signs shall be posted on the tower at a height of
five feet warning of electrical shock or high voltage and harm from
revolving machinery.
9.
Access Control: Towers shall be constructed to provide one of the
following means of access control or another appropriate method of
access control as approved by the PLANNING BOARD:
a. Tower climbing apparatus located no closer than twelve (12) feet
from the ground.
b. A locked anti-climb device installed on the tower.
c. A locked, protective fence surrounding the tower at least six (6)
feet in height and at all points at least six (6) feet from the tower
and any base STRUCTURES.
10. Anchor Points: Anchor points for any guy wires for a system tower
shall be located within the site and such that the guy wires do not
pass over or under any above-ground electrical transmission lines.
The point of attachment for the guy wires shall be enclosed by a
fence or sheathed in bright orange or yellow covering from three (3) to
eight (8) feet above the ground.
11.
Rotor Design and Over-Speed Control: The conformance of
rotor
design
and fabrication and over-speed control with good
engineering practices shall be certified by the manufacturer.
12. Site Plan Review Standards: Standards in the Town's Ordinances
applicable to the siting, construction and operation of the system shall
be met unless they are in conflict with this section.
13. Abandonment
A small wind energy system which is not used for eighteen (18)
consecutive months shall be deemed abandoned and shall be
dismantled and removed from the property at the expense of the
property owner.
5.10 Domesticated Chickens
102
A . Purpose
The purpose of this Ordinance is to provide standards for the keeping of
domesticated chickens. The Ordinance is intended to enable residents to
keep a small number of chickens while limiting the potential adverse impacts
on the surrounding neighborhood.
B. Domesticated Chickens will only be allowed on lots of at least one (acre
and must meet the following requirements:
1. Enclosures shall be SETBACK seventy-five (75) feet from any
abutting property line, WATER BODY, TRIBUTARY or WETLAND.
2. Chickens shall be kept for personal use only.
3. Chickens shall be secured within the enclosure during non-daylight
hours.
4. Enclosures must be clean, dry and odor free, kept in neat and sanitary
condition at all times, in a manner that will not disturb the use or
enjoyment of abutters due to noise, odor or other adverse impact.
5. Excessive noise from chickens shall not be a disturbance to abutters.
C. Penalties
1. Violation of any provision of this article shall be a civil violation and a
fine not to exceed one-hundred dollars ($100), may be imposed. Each
day a violation continues will be treated as a separate offense.
D. Removal of Chickens
1. Any violation of the provisions of this article shall be grounds for an
order from the Code Enforcement Officer to remove the chickens
and/or the chicken-related STRUCTURES. The Animal Control
Officer may also order the removal of the chickens and/or the
chicken-related STRUCTURES.
5.11. Solar Energy Systems
A. Purpose
103
The purpose of this section is to regulate the placement and construction of and
to provide standards for small and large solar energy systems that are
used to produce electrical power, in order to promote their safe and
efficient use and to minimize the visual, environmental, and operational
impacts of these systems.
B. Location
1. Small Solar Energy Systems are permitted as an accessory use in
all land districts within the Town.
2. Large Solar Energy Systems are permitted as a principal use in
the Business & Commercial and Urban Development Park land use
districts.
C. Approval Required
1. No Small Solar Energy Systems may be sited, constructed, or
operated without approval from the Code Enforcement Officer, and
must meet the following criteria:
a.
The layout, design and installation shall meet and conform to
industry standards, including but not limited to the standards of
ANSI, UL, ASTM, or other certifying organizations.
b. The Small Solar Energy System shall comply with the
requirements of all applicable building codes and life safety
codes.
c. The Small Solar Energy System shall be designed to minimize
reflective glare toward adjacent properties, roadways, and rights
of way.
d If the Small Solar Energy System is a ground-mounted system, it
shall be set back twice the applicable SETBACK requirement,
measured from the point on the device closest to the abutting
property line.
e. If the Small Solar Energy System is a rooftop mounted system, it
shall not exceed a maximum height of thirty-five (35) feet above
grade.
f. If the Small Solar Energy System is a ground mounted system, it
shall not exceed fifteen (15) feet in height.
g. All onsite utility and transmission lines extending to and from a Small
104
Solar Energy System that is not attached to the principal structure on
the property shall be placed underground, unless the applicant
demonstrates good cause for the Planning Board to waive this
requirement.
h. No Large Solar Energy Systems may be sited, constructed or
operated without approval from the Planning Board, and must
meet the following criteria:
i. The layout, design and installation shall meet and conform to
industry standards, including but not limited to the standards
of ANSI, UL, ASTM, or other certifying organizations.
ii. The layout, design, and installation shall comply with all
building code and applicable life safety requirements.
iii.
All onsite utility and transmission lines shall be placed
underground, unless the applicant
demonstrates
good
cause for the Planning Board to waive this requirement.
iv. The Large Solar Energy System shall be designed and
located to minimize reflective glare toward adjacent
properties, roadways, and rights of way.
v. If the Large Solar Energy System is mounted on a building, it
shall not exceed a maximum height of thirty-five (35) feet above
grade, unless the system is located in the Urban Development
Park District and meets the height exceptions contained in
Article V, Section 4 of this Ordinance.
vi. Clearly visible warning signage concerning voltage shall be
placed on all ground mounted devices and substations.
vii. Clearly visible signage identifying the owner of the facility with
contact information shall be mounted on the security fence.
viii. An eight (8) foot high security fence shall be erected
around the entire ground mounted system with a self-locking
gate. A method of access, that is deemed acceptable to the
West Bath Fire Chief, shall be available to the West Bath Fire
Department in the event of an emergency.
ix.
In the event the owner ceases to operate the Large Solar
Energy System, the owner shall notify the Town immediately
and shall dismantle and remove all solar system components
105
from the property within twelve (12) months of the last day
that the system was operational.
x. The Planning Board, in its sole discretion, may hire a
consultant to review the design of the Large Solar Energy
System, including any technical aspects and/or safety issues
related to the site or the design. Any required consultant fees
incurred by the Town shall be paid by the applicant.
xi. Proposed developments of three (3) or more acres must provide
a decommissioning plan and financial assurances that has been
reviewed by the Maine Department of Environmental Protection
Agency. Decommissioning plans and financial assurances must
include removal of all equipment up to twenty-four (24) inches
below surface level.
5.12. Communication Towers
A. Purpose
The purpose of this section is to provide standards for the construction,
maintenance, and removal of Communications Towers such as cellular,
radio, television, pager services, and other wireless telecommunication facilities.
B. Applicability
This Section applies to the construction, expansion, removal of, and/or the co-
location on any Communications Tower except:
1. An antenna that is an accessory use to a residential dwelling unit.
2. An amateur (ham) radio station licensed by the FCC.
3. A parabolic antenna less than seven (7) feet in diameter that is an
accessory use of a residential dwelling unit.
4.
The maintenance, repair, or reconstruction of a Commercial
Communications Tower and related equipment, provided that there is
no change in the tower height or other dimension of the facility.
5.
A temporary Communications Tower erected for emergency
communications by public officials that is in operation for less than
ninety (90) days and then promptly removed.
106
C. Approval Required
No Communications Tower may be sited, constructed, or operated without
approval of the PLANNING BOARD in accordance with the provisions of this
Ordinance and the Town of West Bath Land Use Ordinance.
Notwithstanding the foregoing provision, the Code Enforcement Officer shall
approve, approve with conditions, or deny any eligible facilities request under
Section 6409(a) of the Spectrum Act, 47 U.S.C. § 1455(a), for modification of an
existing Communications Tower that does not substantially change the physical
dimensions of such tower or base station, as those terms are defined under the
Spectrum Act.
D. Notification of Abutters and Public Hearing
The PLANNING BOARD shall hold a public hearing within thirty (30) days of the
filing of a completed application for a new Communications Tower. The
PLANNING BOARD shall publish the time, date, and place of hearing at least
twice in a newspaper of area-wide circulation, the date of the first publication to
be at least seven (7) days prior to the public hearing. The abutting landowners
within 1,000 feet of the proposed Communications Tower shall be notified of
the hearing in accordance with LAND USE ORDINANCE, Article I, Section 5.6.
Public hearings by the PLANNING BOARD shall be conducted according to the
procedures outlined in Title 30-A, M.R.S.A. § 2691(3)(a)-(e).
Notwithstanding any other provision of this Ordinance to the contrary, the
PLANNING BOARD may expedite the application review process set forth in this
Section in order to comply with the Federal Telecommunications Act of 1996, 47
U.S.C. § 332(c)(7), and its accompanying rules and regulations, as may be
amended from time to time, or any other federal or State law that imposes
specific time periods for completion of review of completed PLANNING
BOARD applications.
E. Application for Proposed Communications Tower
In addition to the requirements set forth in Article III, section 3.2,
an
application for a Communications Tower shall include the following:
1. A survey plan delineating fall zones, SETBACKS, proposed
structures, and all other details of the proposed Communications
Tower as are required herein.
107
2. A proposed landscaping and driveway access plan showing size and
type of plantings in order to create an adequate vegetative buffer
to
reduce
the
impact
of
the
Communications
Tower and associated facilities on adjacent properties to the greatest
extent possible.
3. At least three (3) simulated depictions of the Communications Tower
from locations as requested by the Planning Board, including views
from nearby roadways and elevations within a two (2) mile radius of
the proposed site.
F. Co-Location; Speculative Towers
As a prerequisite for obtaining approval for the construction of a new
Communications Tower, the applicant shall demonstrate to the PLANNING
BOARD that co-location or shared use of an existing tower or structure
within one and a half (1.5) miles of the proposed site is impossible or
unfeasible. The application for a new Communication Tower must include
evidence of an existing contract with a carrier for the future use of the tower.
The applicant shall further demonstrate that the Communications Tower would
be suitable and available for co-location of other future wireless providers.
No Speculative Towers are allowed.
G. Location
Communications Towers are permitted in the following land use districts:
1. Business & Commercial District.
2. Rural Residential District, provided that the tower is a camouflaged
monopine tower or is co-located on an allowed building or structure,
such as a church steeple. All tower SETBACK and height restrictions
apply.
3.
Urban Development Park District, provided that the tower is a
camouflaged monopine tower or is co-located on an allowed building
or structure, such as a church steeple. All tower SETBACK and height
restrictions apply.
H. Safety and conformance with existing standards
A Communications Tower and all appurtenant facilities shall conform
with and be constructed to all applicable American National Standards
Institute (ANSI) technical and structural codes and
shall comply with
the current Electronic Industries Association/Telecommunications Industries
Association (EIA/TIA) 222 Revision Standard entitled "Structural Standards
for Steel Antenna Towers and Antenna Supporting Structures."
I.Height limits
A Communications Tower may not exceed a tower height of 150 feet
108
above finished grade, including antennas or other structures attached to the
tower; provided, however, that no height limitation shall apply to a
Communications Tower whose owner or principal lessee is a municipality,
county, or other quasi-governmental entity, as determined by the Planning
Board.
J.Fall Zone, SETBACKS
A Communications Tower shall have a "fall zone" SETBACK from all property
boundary lines equal to a distance of one hundred and twenty-five (125)
percent or more of the tower height, or two times the applicable SETBACK
requirement for the land use district, whichever is greater. Accessory
buildings, guy wires, and other facilities must meet all applicable SETBACK
requirements for the land use district.
K.Access, noise, and lights
The Communications Tower and associated building(s) and facilities shall be
enclosed with an eight-foot-high fence and locked gate in order to
discourage trespassing on the property and climbing on the tower or other
structures. The property shall have signage warning of the dangers at the
facility including "Keep Out" and "No Trespassing" signs.
Noise levels shall not exceed 45 dBA Sound Pressure Level, measured at
the property boundary line of the proposed site, except that noise associated
with an emergency backup generator is exempt from this standard if running
during an emergency. In addition, the emergency backup generator may be
tested for short durations sufficient to test reliability and for maintenance
between the hours of 9:00 a.m. and 5:00 p.m. local time, Monday through
Friday.
LNo lights or security lights are allowed which will illuminate an abutting
property. Any lighting that is required by FCC or FAA regulations are exempt
from this standard but must avoid illuminating an abutting property as much as
practical.14.No inference with existing towers, antennas, and microwave
paths. The applicant shall demonstrate through an engineering study that the
Communications Tower will not create any interference with any existing
towers, antennas, wireless signals, microwave pats, and/or existing wind
generation facilities, and shall provide proof of all required FCC and FAA
approvals for the Communications Tower.
M.No applicability to small wind energy conversion systems
This Section applies only to Communications Towers as defined herein and
not to towers related to all wind energy conversion systems regulated under
Article V, Section 5.8 of this Land Use Ordinance.
N.Abandonment
A Communications Tower that is not operated for a continuous period of
twelve (12) months shall be considered abandoned. It is the Tower Owner's
109
responsibility to notify the Town when the tower is no longer needed and that
its use will be discontinued. If the Town discovers the tower has been
abandoned the Code Enforcement Officer shall notify the owner of the
abandoned facility in writing and order the removal of the facility within ninety
(90) days of the owner's receipt of the Code Enforcement Officer written
notice.
The owner of the facility shall have thirty (30) days from the receipt of the
notice to demonstrate to the Code Enforcement Officer that the facility has
not been abandoned. If the owner fails to show that the facility is in active
operation, the owner shall have sixty (60) days to remove the facility. If the
facility is not removed within this time period, the Town may remove the
facility at the owner's expense. The owner of the facility shall pay all site
reclamation costs deemed necessary and reasonable to return the site to
its preconstruction
condition, including
the
removal
of roads and
reestablishment of vegetation.
O.Removal Bond
Prior to the commencement of the construction of any Communications
Tower, the applicant shall provide the Town with a performance bond or letter
of credit in an amount sufficient to cover the cost of removal of the facility if it is
abandoned as set forth above, including all site reclamation costs deemed
necessary to return the site to its pre-construction condition, such as the
removal of any road and reestablishment of vegetation. In order to
determine the initial cost of removal of the facility and site reclamation
costs, the applicant shall provide an estimate from an independent
professional engineer. The applicant shall maintain such bond or replacement
bond/letter of credit in place throughout the time period that the
Communications Tower is in existence. The performance bond or letter of
credit or any replacement performance bond/letter of credit shall be subject to
the prior approval of the Town Attorney. The amount of the performance
bond or letter of credit or any replacement performance bond/letter of credit
shall be increased by fifteen (15) percent on the first of January every five (5)
years. The owner of the facility may apply to the PLANNING BOARD for
release of the surety when the facility and related equipment are removed to
the satisfaction of the PLANNING BOARD.
5.13. Indoor and Outdoor Places for Eating and Drinking; Live
Entertainment
110
A. Purpose. The purpose of this section is to permit indoor and
outdoor places for eating and drinking, as defined in this Ordinance, to
provide live entertainment for the benefit of patrons, subject to the
requirements of this section.
B. Standards.
1. Indoor live entertainment is permitted at any time in any district.
2. Outdoor live entertainment is permitted only in the Business
Commercial District until 11:00 p.m on Fridays and Saturdays. This
activity is exempt from noise limitations in this Land Use Ordinance.
5.13.1 Food Trucks
A. Proposed food trucks must contain all equipment needed for the
preparation of food within the unit, including trash and recycling
receptacles for the kitchen.
B. The operator must provide adequate trash and recycling receptacles
within a radius of thirty feet of the food truck location for public use. The
receptacles shall be removed each evening or when the food truck is not
present.
C. Food trucks, and any associated equipment, must be operating in a
manner which minimizes noise, exhaust and odors impacting the public
and surrounding public and private properties so as not to create a
nuisance. Permits for food trucks may be revoked by the Town of West
Bath if operator fails to address complaints outlined by the Code
Enforcement Officer within a thirty (30) day period.
D. Food truck must be registered by the Maine Department of Motor Vehicles
and licensed by the Maine Department of Health and Human Services
prior to operation. If the food truck is located on a parcel owned by a
different individual/organization, the operator of the food truck must
provide a signed document verifying the owner's permission to use the
site.
5.14 Agriculture
A. Manure piles must be located at least 75 ft. from all abutting property,
unless a waiver is permitted by the Planning Board.
111
5.15 Campgrounds not in the Shoreland Zone
A. Standards.
1. All campgrounds located outside of the shoreland zone must adhere to
standards located in the shoreland zone.
2. Bathrooms must be interior and located greater than 50 ft. from any
abutting property line.
3. 35 ft. vegetative buffers must be maintained at all abutting property
lines.
5.16 Kennels and animal accommodations
A. In the rural residential district, all kennels and animal accommodations
must be placed on a minimum of a 2-acre lot.
5.17 Bed & Breakfasts
A. Bed and Breakfast uses must maintain one parking space per unit of
lodging offered. The parking space must adhere to the parking space
standards in Article III of this ordinance.
5.18 General Industrial/Manufacturing uses
A. A vegetative buffer is required for all general industrial/manufacturing
uses. Buffers must adhere to the standards in article 3.11.a of this
Ordinance.
B. Fences may be permitted in lieu of a vegetative buffer if the Planning
Board permits.
5.19 Junkyards
A. Junkyards are not permitted in West Bath.
112
5.20 Daycares
A. Applicants proposing day care establishments must present a certified
Maine State license to operate a day care to the Planning Board as soon as
reasonably possible.
5.21 Change of Use
A. Proposed use shall only alter the use of the structure from one permitted use
to another as outlined in the Land Use Matrix.
B. No Alterations to the footprint of the structure, with the exception of changes
that are necessary for accessibility, shall be proposed with this proposed
use.
C. If both 5.21 A and 5.21 B are met, the proposed use may be subject to site
plan review by the Code Enforcement Officer instead of the Planning
Board. The Code Enforcement Officer shall notify the members of the
Planning Board and emergency services of the proposed application. At
the Code Enforcement Officer's discretion, the proposed use may be sent
to the Planning Board for a site plan review if the Code Enforcement
Officer believes the proposed use could have an off-site impact.
113
ARTICLE VI. NON-CONFORMANCE
A. PURPOSE: It is the intent of this Ordinance to promote land use
conformities, except that the nonconforming conditions which existed
before the effective date of this Ordinance shall generally be allowed to
continue, subject to the requirements set forth herein. Except as
otherwise provided in this Ordinance, a non-conforming condition shall
not be permitted to become more non-conforming. In a situation of
abutting non-conforming properties in common ownership, one or more
may become more non-conforming provided the non-conformity of the
additional lot(s) is lessened.
B. DEFINITION: Any lawful use, BUILDING, STRUCTURES, premises,
land, or parts thereof existing on May 4, 2026 and not in conformance
with the provisions of this Ordinance, shall be considered to be non-
conforming.
C. NON-CONFORMING USES: Any non-conforming use in existence prior to
May 4, 2026 may continue and may be maintained, repaired, and
improved. No such non-conforming use may be expanded, changed to
another non-conforming use, or renewed after it has been discontinued for
a period of twelve (12) calendar months or more. In the Shoreland Overlay
Zone, this provision shall not apply to the resumption of a use of a
residential STRUCTURE provided that the STRUCTURE has been used
or maintained for residential purposes during the preceding five (5) year
period. Once a non-conforming use has been replaced by a conforming
use, it cannot subsequently be replaced by any non-conforming use.
D. NON-CONFORMING LOTS:
1. Contiguous Built LOTS: If two (2) or more CONTIGUOUS LOTS or
parcels are in a single or joint ownership of record at the time of
adoption of this Ordinance, if all or part of the LOTS do not meet the
dimensional requirements of this Ordinance, and if a principal use or
STRUCTURE exists on each LOT, the NON-CONFORMING LOTS
may be conveyed separately or together, provided that the State
Minimum LOT Size Law and Subsurface Wastewater Disposal Rules
are complied with.
If two (2) or more principal uses or STRUCTURES existed on a single
114
LOT of record on the effective date of this Ordinance, each may be sold
on a separate LOT provided that the above referenced law and rules
are complied with. When such LOTS are divided each LOT thus
created must be as conforming as possible to the dimensional
requirements of this Ordinance.
2. CONTIGUOUS LOTS - Vacant or Partially Built: If two (2) or more
CONTIGUOUS LOTS or parcels are in single or joint ownership of
record at the time of or since adoption or amendment of this
Ordinance, if any of these LOTS do not individually meet the
dimensional requirements of this Ordinance or subsequent
amendments, and if a principle use or STRUCTURE exists on one (1)
LOT and if one (1) or more of the LOTS are vacant or contain no
principal STRUCTURE, the LOTS shall be combined to the extent
necessary to meet the dimensional requirement.
This paragraph is intended to apply to all LOTS, whether shown on an
approved recorded plan or not.
3. If a LOT is non-conforming by virtue of having more individual uses
than would be permitted in terms of having the required LOT area for
the number of uses thereon, the discontinuance of any use,
conforming or non-conforming, for a period of twelve (12) calendar
months or more shall not allow said use to be resumed.
E. NON-CONFORMING STRUCTURES:
A non-conforming STRUCTURE is a BUILDING or other STRUCTURE
that fails to meet one or more of the minimum SETBACK and LOT
coverage standards in Article II section 2.1 of this Ordinance.
F. RECONSTRUCTION/REPLACEMENT:
Any non-conforming STRUCTURE which is located less than the required road
setback, side & rear setback, and/or setback from the normal high-water line of a water
body, tributary stream, or upland edge of a wetland and which is removed, damaged
or destroyed, regardless of the cause, by more than 50% of the market
value of the STRUCTURE before such damage, destruction or removal
may be reconstructed, replaced, or relocated provided an approval from
the Planning Board and a building permit from the Code Enforcement
Officer are obtained within twelve months of the date of said damage,
destruction, or removal, provided that such reconstruction, relocation or
replacement is in compliance with all water SETBACK requirements to
the greatest practical extent. Greatest practical extent will be determined
by the PLANNING BOARD in accordance with the purpose of this
Ordinance, the criteria specified below, and Article VI, section 3. In no
115
case shall a STRUCTURE be reconstructed, relocated, or replaced so as
to increase its non-conformity.
If the reconstructed, relocated, or replacement structure is less than the
required SETBACK, it shall not be any larger than the original structure,
except as allowed pursuant to Article VI, Section 7 below as determined
by the non-conforming footprint of the reconstructed, relocated, or
replaced structure at its new location. If the total footprint of the original
structure can be relocated, reconstructed, or replaced beyond the
required SETBACK, no portion of the relocated, replaced, or
reconstructed structure shall be replaced, relocated or constructed at less
than the setback requirement for a new structure. When it is necessary to
remove vegetation to replace or reconstruct a structure, vegetation shall
be planted in accordance with Section 8 below.
A building permit for reconstruction, replacement, or relocation shall be
renewable for a total of only twelve months its original date of issue if no
substantial start of construction has been made.
If a permit is not obtained within twelve months of said damage or
destruction, repair or reconstruction of any such STRUCTURE shall
require an approval and/or permit from the same authorities as that for a
new such STRUCTURE. Whenever a new, enlarged, or replacement
foundation is constructed under a non-conforming structure in the
shoreland zone, the structure and new foundation must be placed such
that the setback requirement is met to the greatest practical extent as
determined by the Planning Board or its designee, basing its decision on
the criteria specified in Article VI, Section 8 below. If the completed
foundation does not extend beyond the exterior dimensions of the
structure, except for expansion in conformity with Article VI, Section 7
below, and the foundation does not cause the structure to be elevated by
more than three (3) additional feet, as measured from the uphill side of
the structure (from original ground level to the bottom of the first floor sill),
it shall not be considered to be expansion of the structure.
G. EXPANSIONS:
A non-conforming structure may be added to or expanded after obtaining a
permit from the same permitting authority as that for a new structure, if such
addition or expansion does not increase the non-conformity of the structure
and, if it is in the Shoreland Zone, is in accordance with paragraphs (a) and
(b) below.
1.Expansion of any portion of a structure within 25 feet of the normal high-
water line of a water body, tributary stream, or upland edge of a
wetland is prohibited, even if the expansion will not increase
116
nonconformity with the water body, tributary stream or wetland setback
requirement. Expansion of an accessory structure that is located closer
to the normal high-water line of a water body, tributary stream, or
upland edge of a wetland than the principal structure is prohibited,
even if the expansion will not increase nonconformity with the water
body, tributary stream, or wetland setback requirement.
2. Notwithstanding paragraph (a), above, if a legally existing
nonconforming principal structure is entirely located less than 25 feet
from the normal high-water line of a water body, tributary stream, or
upland edge of a wetland, that structure may be expanded as follows,
as long as all other applicable municipal land use standards are met
and the expansion is not prohibited by Section 7 (Expansions).
a. The maximum total footprint for the principal structure may not be
expanded to a size greater than 800 square feet or 30% larger than
the footprint that existed on January 1, 1989, whichever is greater.
The maximum height of any structure may not be made greater
than 15 feet or the height of the existing structure, whichever is
greater.
3. All other legally existing nonconforming principal and accessory
structures that do not meet the water body, tributary stream, or wetland
setback requirements may be expanded or altered as follows, as long
as other applicable municipal land use standards are met and the
expansion is not prohibited by Section 7(b) (i) above.
a. For structures located less than 75 feet from the normal high-water
line of a water body, tributary stream, or upland edge of a wetland,
the maximum combined total footprint for all structures may not be
expanded to a size greater than 1,000 square feet or 30% larger
than the footprint that existed on January 1, 1989, whichever is
greater. The maximum height of any structure may not be made
greater than 20 feet or the height of the existing structure,
whichever is greater.
b. For structures located less than 100 feet from the normal high-water
line of a great pond classified as GPA or a river flowing to a great
pond classified as GPA, the maximum combined total footprint for
all structures may not be expanded to a size greater than 1,500
117
square feet or 30% larger than the footprint that existed on January
1,1989, whichever is greater. The maximum height of any structure
may not be made greater than 25 feet or the height of the existing
structure, whichever is greater. Any portion of those structures
located less than 75 feet from the normal high-water line of a water
body, tributary stream, or upland edge of a wetland must meet the
footprint and height limits in Section 7(C)(ii) and Section 7(b) (i),
above.
4. In addition to the limitations in subparagraphs 7a, 7b, and 7c above,
for structures that are legally nonconforming due to their location
within the Resource Protection District when located at less than 250
feet from the normal high-water line of a water body or the upland
edge of a wetland, the maximum combined total footprint for all
structures may not be expanded to a size greater than 1,500 square
feet or 30% larger than the footprint that existed at the time the
Resource Protection District was established on the lot, whichever is
greater. The maximum height of any structure may not be made
greater than 25 feet or the height of the existing structure, whichever
is greater, except that any portion of those structures located less
than 75 feet from the normal high-water line of a water body, tributary
stream, or upland edge of a wetland must meet the footprint and
height limits in Section 7.
Table 6.1: Expansion Requirements
Distance from
water/wetland
Maximum structure
allowed (whichever is
greater) *
Maximum structure
height allowed**
< 25 feet
800 Square Feet or 30%
larger
15 feet
< 75 feet
1,000 Square feet or
30% larger
20 feet
< 100 feet
1,500 Square feet or
30% larger
20 feet
Additional total limit of all structures combined
118
0 to 250 feet
1,5000 or 30% larger
25 feet
*The increases are permitted from the building's footprint as it stood on January 1, 1989
**Unless height of original structure as it stood on January 1, 1989 exceeds listed values
H. GREATEST PRACTICAL EXTENT CRITERIA
In determining whether the building relocation meets the setback to the
greatest practical extent, the Planning Board, or its designee, shall consider:
1. the size of the lot;
2. the slope of the land;
3. the potential for soil erosion;
4. the location of other structures on the property and on adjacent
properties;
5. the location of the septic system and other on-site soils suitable for
septic systems; and
6. the type and amount of vegetation to be removed to accomplish the
relocation.
When it is necessary to remove vegetation within the water or wetland setback
area to relocate a structure, the Planning Board shall require replanting of native
vegetation to compensate for the destroyed vegetation. In addition, the area from
which the relocated structure was removed must be replanted with vegetation.
Replanting shall be required as follows:
Trees removed to relocate a structure must be replanted with at least one
native tree, three (3) feet in height, for every tree removed. If more than five
trees are planted, no one species of tree shall make up more than 50% of the
number of trees planted. Replacement trees must be planted no further from
the water or wetland than the trees that were removed.
Other woody and herbaceous vegetation and ground cover that are removed
or destroyed to relocate a structure must be re-established. An area at least
the same size as the area where vegetation and/or ground cover was
disturbed, damaged, or removed must be re-established within the setback
area. The replacement vegetation and/or ground cover must consist of native
vegetation and/or ground cover like that which was disturbed, destroyed or
removed.
Where feasible, when a structure is relocated on a parcel, the original location
of the structure shall be replanted with vegetation, which may consist of
119
grasses, shrubs, trees, or a combination thereof
ARTICLE VII - APPEALS
7.1
Composition, Appointments, Qualifications, and Terms
The Town of West Bath shall have a Board of Appeals consisting of five (5)
members and one (1) associate member, all of whom shall be appointed by the
Select Board. All members of the Board of Appeals shall be residents of the Town
of West Bath and registered voters thereof. Members of the Select Board, their
spouses, and members of the Planning Board shall not be eligible to serve on
the Board of Appeals. Members of the Board of Appeals shall serve staggered
three-year terms. If a vacancy occurs, the term of the PERSON appointed to fill
the vacancy shall be for the period of the unexpired term. The terms of the
members shall expire on June 30th unless a replacement has not been
appointed, in which case the term of the expiring member shall be extended until
a replacement is named.
7.2
Organization and Meetings
A. The Planning Board of Appeals shall annually elect a Chair, Vice Chair,
and Secretary and other such officials as it chooses from its membership.
The election of officials shall occur at the first meeting of the Board after
June 30 of each year.
B. The Chair's duties shall consist of calling of the meetings, establishing
agendas for the meeting, presiding at meetings, and for representing the
Board before other bodies. The Vice Chair shall be responsible for
carrying out the duties of the Chair in his or her absence or incapacity.
The Secretary shall be responsible for keeping minutes of the proceedings
of the Board of Appeals, and for making these minutes available to the
public.
C. The Board of Appeals shall meet monthly, provided there is business for
the Board to address. The Chair shall also call such other meetings as
are necessary, or a meeting may be called upon a written request of three
members of the Board.
D. All meetings of the Board of Appeals shall be announced to the general
public in accordance with State law. Meetings of the Board shall be
opened to the public, and shall be conducted in accordance with such
120
rules of procedure as the Board may determine, in compliance with
applicable State and local laws.
E. A quorum shall consist of three members of the Board. If one or more
regular members are absent, then the associate member shall participate
as a regular member if he or she is present.
F. All members present and not excused from voting shall vote on each item
The Secretary shall record results of all votes, and the vote of a majority
of those members present and voting shall be required for the passage
of any item of the Board's business.
7.3
Conflict of Interest
No member of the Planning Board shall vote on or participate in any matter in
which he/she has a bias or conflict of interest, including, but not limited to, a
direct or indirect financial or personal interest. Any question of whether a
particular issue involves a bias or conflict of interest sufficient to disqualify a
member from voting thereon shall be decided by a majority vote of the members,
except the member who is being challenged. No member of the Board shall
represent any third party in matters coming before the Board.
7.4
Powers and Duties
The Board of Appeals shall have the following powers and duties:
A.
Variance Appeals - The Board shall hear and decide requests for a
variance from the strict enforcement of the provisions of this Land Use
Ordinance adopted in accordance with 30-A M.R.S.A. § 4353 as follows:
1. Undue hardship zoning variance pursuant to 30-A M.R.S.A. §
4353(4) shall meet section 5A standards of review.
2. Disability Variance pursuant to 30-A M.R.S.A. § 4353(4-A) shall
meet section 5B standards of review.
3. Set-back variance for single-family dwellings pursuant to 30-A
M.R.S.A. § 4353(4-B) shall meet section 5C standards for review.
4. Variance from dimensional standards relating to practical difficulty
pursuant to 30-A M.R.S.A. § 4353(4-C) shall meet section 5D standards
of review. A practical difficulty variance may not be granted to allow an
increase in either volume or FLOOR AREA, or to permit the location of
a STRUCTURE to be situated on a LOT in a way which is contrary to
the provisions of the West Bath Land Use Ordinance.
121
B.
Administrative Appeals - The Board shall hear and decide administrative
appeals that are referred to it regarding decisions of the Planning Board,
or the Code Enforcement Officer, with regard to the provisions of this Land
Use Ordinance. The Board's role in these matters is strictly appellate
review and in no case will the Board conduct a de novo review.
Enforcement decisions by the Code Enforcement Officer may not be
appealed to the Board. Application for an administrative appeal shall be
made to the Board of Appeals on a form provided for that purpose.
The application shall be accompanied by the filing fee, which will be
determined by the Select Board on an annual basis. The applicant shall
also pay all advertising fees that are required to meet legal notice
requirements. Notwithstanding any other provision of this Ordinance to
the contrary, the Board may expedite the application/appeal review
process set forth in this Section in order to comply with the federal
Telecommunications Act of 1996, 47 U.S.C. § 332 (c) (7), and its
accompanying rules and regulations, as may be amended from time to
time, or any other federal or State law that imposes specific time periods
for
completion
of
review
of
completed
Board
of
Appeals
application/appeals.
7.5
Variances
A. Variance Defined - Variance is the relaxation of the terms of this
Ordinance where such a variance would not be contrary to the public
interest, and where, owing to conditions peculiar to the property and not
the result of actions of the applicant, a literal enforcement of this Ordinance
would result in unnecessary or undue hardship.
1. Undue hardship relates to a problem created by some feature of the
land, not a personal problem of the applicant.
2. Practical difficulty means that the strict application of the Ordinance to
the property precludes the ability of the petitioner to pursue a use
permitted in the zoning district in which the property is located and
results in significant economic injury to the petitioner.
3. Dimensional Standards means and is limited to Ordinance provisions
relating to LOT area, LOT coverage, frontage, and SETBACK
requirements.
4. An undesirable change in the neighborhood as it relates to the
"practical difficult" variance is defined so that the STRUCTURE can be
no larger or closer to the ROAD or property lines than the majority of
STRUCTURES within that neighborhood or would not result in a
percentage of LOT coverage which was greater than the majority of
LOTS in that neighborhood.
122
5. Unreasonable detrimental effect is defined so that a variance for the
subject property will not block an established view, pose a fire safety
hazard, or reduce the appraised value of the adjoining LOT.
B. Items for which a variance may be granted - As used in this Code, a
variance may be authorized for only the following items:
1. Minimum LOT area except for Bulk Hazardous Substance Uses
2. SETBACKS except for distance from normal high water mark or
UPLAND EDGE of a WETLAND.
3. LOT frontage, ROAD frontage, shore frontage
4. Percentage of a LOT coverage
5. Temporary disability access
6. DRIVEWAY or ROAD grade within fifty (50) feet of an intersection with
a Town Road, State Aid Road, or State Road. Establishment of a use
otherwise prohibited shall not be allowed by variance.
7.6
Application - Application for a variance shall be made to the Code
Enforcement Officer on forms provided for that purpose. The application shall
be accompanied by the filing fee, which will be determined by the Select Board
on an annual basis. The applicant shall also pay all advertising fees required by
state or local Ordinances to meet legal notice requirements.
7.7
Procedure - The Code Enforcement Officer shall forward the
application for variance to the Board of Appeals. Upon receipt of the
application, the Board shall set the matter for hearing at its next scheduled
meeting. The time, date, and place of the public hearing on the application shall
be advertised in a newspaper having general circulation in the Town of West
Bath at least seven days prior to the date of the hearing. The Board shall notify
all abutters in writing of the pendency of the application in accordance with
LAND USE ORDINANCE, ARTICLE III Section 5.6. Said notice to indicate the
nature of the application, and the time, date, and place of hearing. The Board
shall act on the application within 45 (forty-five) days of the date of the first
consideration.
7.8
Standards of Review - Prior to allowance for variance, the Board of
123
Appeals shall make specific findings that all of the standards for the type of
variance being sought have been met and that the requirements of this Code
applicable to an item for which a variance may be granted will impose an undue
hardship on the property of the owner. No variance shall be granted solely on
economic considerations.
A. Undue Hardship Variance:
1. That the relief sought would not adversely affect adjoining property or
property in the same neighborhood, or in the same zoning district and
would not endanger the public health, safety, or convenience of the
inhabitants of the Town of West Bath, nor would it impair the integrity
of the Ordinance and COMPREHENSIVE PLAN of the Town of West
Bath.
2. That the hardship is not the result of action taken by the applicant or
by a previous owner.
3. That the need for variance is due to unique circumstances of the
property and not to the general conditions of the neighborhood.
4. That all other requirements of the Land Use Ordinance have been met
or will be met.
5. That the land in question cannot yield a reasonable return unless a
variance is granted.
6. That the granting of a variance will not alter the essential character of
the locality.
B. Disability Variance - The Board may grant a variance to an owner of a
dwelling for the purpose of making that dwelling accessible to a PERSON
with a disability who resides in or regularly uses that dwelling. The Board
shall restrict any variance granted under this subsection solely to the
installation of equipment or the construction of STRUCTURES
necessary for access to or egress from the dwelling by the PERSON with
the disability. The Board may impose conditions on the variance, including
limiting the variance to the duration of the disability or to the time that the
PERSON with the disability lives in the dwelling. For the purposes of this
subsection, a disability has the same meaning as a physical or mental
handicap under Title 5 § 4553 and the term "STRUCTURES necessary for
access to or egress from the dwelling" is defined to include railing, wall or
roof systems necessary for the safety or effectiveness of the STRUCTURE.
124
C. SETBACK Variance for single-family dwellings - A variance may be
granted from a set-back requirement only when strict application of the
zoning Ordinance to the petitioner and the petitioner's property would
cause undue hardship. The Board may attach reasonable conditions,
which it finds necessary to protect the privacy of abutting property owners
and neighbors. These conditions are limited to specifications for
landscaping, fencing and parking. The term "undue hardship" as used in
this subsection means:
1. The need for a variance is due to the unique circumstances of the
property and not the general conditions in the neighborhood;
2. The granting of a variance will not alter the essential character of the
locality;
3. The hardship is not the result of action taken by the applicant or a prior
owner;
4. The granting of the variance will not substantially reduce or impair the
use of abutting property; and
5. That the granting of a variance is based upon demonstrated need, not
convenience, and no other feasible alternative is available.
A variance granted under this subsection is strictly limited to permitting
a variance from a set-back requirement for a single-family dwelling that
is the primary year-round residence of the petitioner. A variance under
this subsection may not exceed 20% of a SETBACK requirement and
may not be granted if the variance would cause the area of the
dwelling to exceed the maximum permissible LOT coverage.
D.
Practical difficulty/dimensional standards variance - The Board may grant
a variance from the dimensional standards of a zoning Ordinance when
strict application of the Ordinance to the petitioner and the petitioner's
property would cause a practical difficulty and when the following
conditions exist:
1. The need for a variance is due to the unique circumstances of the
property and not the general condition of the neighborhood;
2. The granting of a variance will not produce an undesirable change in
the character of the neighborhood and will not unreasonably
detrimentally affect the use or market value of abutting properties;
3. The practical difficulty is not the result of action taken by the petitioner
or a prior owner;
125
4. No other feasible alternative to a variance is available to the
petitioner or a prior owner;
5. The granting of a variance will not unreasonably adversely affect
the natural environment; and
6. The property is not located in whole or in part within shoreland areas
as described in Title 38 § 435.
7.9
Conditions of Approval - The Board of Appeals is empowered to
impose such conditions on the property owner as are necessary and
appropriate to protect abutting property owners or the Town as a whole from
any adverse impact resulting from the granting of such a variance. Any
violation of such condition imposed by the Board of Appeals shall result in
revocation of approval by the Board. The Board of Appeals shall limit any
variances granted as strictly as possible in order to ensure conformance with
the purposes and provisions of this Ordinance to the greatest extent possible,
and in doing so may impose such conditions to a variance as it deems
necessary. The party receiving the variance shall comply with any conditions
imposed.
7.10. Expiration - The variance granted by the Board of Appeals shall expire if
the construction or change involved is not commenced within one (1) year of the
date on which the variance is granted, or if the work or change is not substantially
completed within two (2) years from the date of approval, unless either of these
time periods is extended by the Board. A temporary disability access variance
shall expire when the disability disappears or the disabled individual is no longer
a resident.
7.11 Re-application - If the Board of Appeals shall deny a variance, a second
request of similar nature shall not be brought before the Board within one (1)
year of the date of denial of the first request, unless in the opinion of the
majority of the Board, substantial new evidence can be brought forward, or
unless the Board finds in its own exclusive judgment that an error of law or a
misunderstanding of facts has been made.
7.12 Misrepresentation - The Board of Appeals shall retain the right to
vacate any approval of a variance if further information or additional
investigation reveals that there has been a misrepresentation of information
presented to the Board.
7.13 Prior Work - Any construction activity commenced prior to the granting
of a required variance shall be a violation of this Code and shall be subject to
the penalties stated herein.
7.14 Notice to Department of Environmental Protection - A copy of each
variance request, including the application and all supporting information
supplied by the applicant, shall be forwarded by the municipal officials to the
126
Commissioner of the Department of Environmental Protection at least twenty (20)
days prior to action by the Board of Appeals. Any comments received from the
Commissioner prior to action by the Board of Appeals shall be made part of the
record and shall be taken into consideration by the Board of Appeals. A copy of
all variances granted by the Board of Appeals shall be submitted to the
Department of Environmental Protection within fourteen (14) days of the
decision.
ARTICLE VIII. SHORELAND ZONE
SECTION 1 SHORELAND ZONE OVERLAY DISTRICT (SZO)
1.1 Purpose
The purposes of the SZO District are to further the maintenance of safe and
healthful conditions; to prevent and control water pollution; to protect fish
spawning grounds, aquatic life, bird and other wildlife habitat; to protect
buildings and lands from flooding and accelerated erosion; to protect
archaeological and historic resources; to protect commercial fishing and
maritime industries; to protect freshwater coastal wetlands; to control building
sites, placement of structures, and land uses; to conserve shore cover, and
visual as well as actual points of access to inland and coastal waters; to
conserve natural beauty and open space; and to anticipate and respond to the
impacts of development in shoreland areas.
1.1.1 Permissible Uses
Land uses in the SZO shall be governed by the Table 2.1. All proposed
uses must also align with a permitted use allowed in the underlying
district.
1.2
SZO District Applicability
1.2.1 All lands within 250 feet, horizontal distance, of the:
1.2.1.1
Normal high-water line of any great pond or river;
1.2.1.2
Upland edge of a coastal wetland, including all areas affected by
tidal action during the highest annual tide, or;
1.2.1.3
Upland edge of a freshwater wetland
1.2.1.4
Any structure build on, over or abutting a dock, wharf, pier, or other
structure extending or located below the normal high-water line of a
water body or within a wetland.
1.3
The SZO Stream Protection Sub-District (SZO-SP) includes all land areas
within 75 feet, horizontal distance, of the edge of a stream, exclusive of
those areas within 250 feet, horizontal distance, of the normal high-water
line of a great pond or river, or upland edge of a freshwater or coastal
wetland. Where a stream and its associated shoreland area are located
within 250 feet, horizontal distance, of the above water bodies or wetlands,
that land area shall be regulated under the terms of the Shoreland District
associated with that water body or wetland.
127
1.4
The SZO Resource Protection Sub-District (SZO-RP) includes the
following areas in which development would adversely affect water quality,
productive habitat, biological ecosystems, or scenic and natural values.
This sub-district shall include the following areas when they occur within
the limits of the SZO, exclusive of the SZO-SP.
1.4.1 Floodplains along rivers and floodplains along artificially formed great
ponds along rivers, defined by the 100-year floodplain as designated on the
Federal Emergency Management Agency's (FEMA) Flood Insurance Rate
Maps or Flood Hazard Boundary Maps, or the flood of record, or in the
absence of these, by soil types identified as recent floodplain soils. This
district shall also include 100-year floodplains adjacent to tidal waters as
shown on FEMA's Flood Insurance Rate Maps or Flood Hazard Boundary
Maps.
1.4.2 Areas of two (2) or more contiguous acres with sustained slopes of 20% or
greater.
1.4.3 Areas of two (2) or more contiguous acres supporting wetland vegetation
and hydric soils, which are not part of a freshwater or coastal wetland as
defined, and which are not surficially connected to a water body during the
period of normal high water.
1.4.4 Areas within 250 feet, horizontal distance, of the upland edge of
freshwater and/or coastal wetlands, which are rated "moderate" or "high"
value waterfowl and wading bird habitat, including nesting and feeding
areas, by the Maine Department of Inland Fisheries and Wildlife
(MDIF&W).
1.4.5
Areas within 250 feet, horizontal distance, of the upland edge of
freshwater and/or coastal wetlands, which are rated "rare" value for
endangered plants as indicated by Maine Natural Areas Program.
1.4.6 Land areas along rivers subject to severe bank erosion,
undercutting, or river bed movement, and lands adjacent to tidal
waters which are subject to severe erosion or mass movement,
such as steep coastal bluffs.
1.4.7
SZO District and Sub-District boundaries are delineated on the West
Bath Zoning Map.
1.5 Additional Requirements for the SZO District
The requirements in this subsection shall apply to all development within the SZO
District and their subcategories.
128
1.5.1
Setbacks of Structures from Water Bodies and Wetlands
1.5.1.1
All new principal and accessory structures, excluding functionally
water-dependent uses, shall be located outside of any SZO
Resource Protection Sub-District (SZO-RP) and SZO Stream
Protection Sub-District (SZO-SP) unless a variance is granted by the
Planning Board.
1.5.1.2
All new principal and accessory structures, outside the SZO-RP,
SZO-SP, shall be setback at a minimum horizontal distance of at
least:
1.5.1.2.1
75 feet from the edge of the normal high-water line of a stream
or tributary stream or upland edge of a coastal or freshwater
wetland;
1.5.1.2.2
100 feet from the normal high-water line of great ponds
classified GPA and rivers that flow to Great Ponds GPA
1.5.1.2.3
Commercially Functionally Water-Dependent uses shall have
no minimum setback if not located in the Resource Protection
and Stream Protection Sub-Districts. (Note: Those that
require, for their primary purpose, location on submerged
lands that require direct access to, or location in, coastal or
inland waters and that cannot be located away from these
waters...Recreational boat storage buildings are not
considered to be functionally water-dependent use.)
1.5.1.3
Notwithstanding the requirements of this Subsection 1.5.1 (Setbacks
of Structures from Water Bodies and Wetlands), stairways or similar
structures may be permitted with a Building Permit approved by the
Code Enforcement Officer, to provide shoreline access in areas of
steep slope or unstable soils, provided that: the structure is limited to
a maximum of four (4) feet in width; that the structure does not extend
below or over the normal high-water line of a water body or upland
edge of a wetland (unless permitted by the Maine Department of
Environmental Protection pursuant to the Natural Resources
Protection Act, 38 M.R.S §480-C, as amended); and that the
applicant demonstrates that no reasonable alternative for access
exists on the property.
129
1.5.2 Lot Size and Shore Frontage
Category
Location / Description
Minimum
Lot Area
(sq ft)
Minimum Shore
Frontage (ft)
1. Residential (per dwelling
unit)
Within the Shoreland
Zone Adjacent to Tidal
Areas
30,000
150
Within the Shoreland
Zone Adjacent to
Non-Tidal Areas
40,000
200
2. Governmental, Institutional,
Commercial, or Industrial
(per principal structure)
Within the Shoreland
Zone Adjacent to Tidal
Areas
40,000
200
Within the Shoreland
Zone Adjacent to
Non-Tidal Areas
60,000
300
3. Public & Private
Recreational Facilities
Within the Shoreland
Zone Adjacent to Tidal
and Non-Tidal Areas
40,000
200
1.5.2.1 Unless otherwise required by state law the following dimensional requirements
shall apply within the SZO.
1.5.2.2 Land below the normal high-water line of a water body or upland edge of a
wetland and land beneath roads serving more than two (2) lots shall not be
included toward calculating minimum lot area.
1.5.2.3 Lots located on opposite sides of a public or private road shall be considered
each a separate tract or parcel of land unless such road was established by
the owner of land on both sides thereof after September 22, 1971.
1.5.2.4
The minimum width of any portion of any lot within one hundred (100) feet,
horizontal distance, of the normal high-water line of a water body or upland edge
of a wetland shall be equal to or greater than the shore frontage requirement for
a lot with the proposed use.
1.5.2.5 If more than one residential dwelling unit, principal governmental,
institutional, commercial or industrial structure or use, or combination thereof, is
constructed or established on a single parcel, all dimensional requirements shall
be met for each additional dwelling unit, principal structure, or use.
130
1.6
Piers, Docks, Wharves, Bridges and Other Structures and Uses
Extending Over or Below the Normal High-Water Line of a Water Body
or Within a Wetland, and Shoreline Stabilization
1.6.1 No more than one pier, dock, wharf or similar structure extending
or located below the normal high-water line of a water body or
within a wetland is allowed on a single lot; except that when a
single lot contains at least twice the minimum shore frontage as
specified in this Article a second structure may be allowed and
may remain as long as the lot is not further divided.
1.6.2 Access from shore shall be developed on soils appropriate
for such use and constructed so as to control erosion.
1.6.3 The location shall not interfere with existing developed or natural
beach areas.
1.6.4 The facility shall be located so as to minimize adverse effects on
fisheries.
1.6.5 The facility shall be no larger in dimension than necessary to
carry on the activity and be consistent with the surrounding
character and uses of the area. A temporary pier, dock or
wharf in non-tidal waters shall not be wider than six feet for non-
commercial uses.
1.6.6 No new structure shall be built on, over or abutting a pier,
wharf, dock or other structure extending beyond the normal high-
water line of a water body or within a wetland unless the structure
requires direct access to the water body or wetland as an
operational necessity.
1.6.7 New permanent piers and docks on non-tidal waters shall not be
permitted unless it is clearly demonstrated to the Planning
Board that a temporary pier or dock is not feasible, and a permit
has been obtained from the Department of Environmental
Protection, pursuant to the Natural Resources Protection Act
1.6.8 No existing structures built on, over or abutting a pier,
dock, wharf or other structure extending beyond the normal high-
water line of a water body or within a wetland shall be converted
to residential dwelling units in any district
1.6.9 Structures built on, over or abutting a pier, wharf, dock or other
structure extending beyond the normal high-water line of a water
body or within a wetland shall not exceed twenty (20) feet in
height above the pier, wharf, dock or other structure.
131
1.7
Shoreland Zone Overlay Permit Requirements and Exceptions
Development and other land use activity within the Shoreland Zone Overlay
Zone may be permitted in accordance with this Section.
1.7.1 Commercial and Industrial Uses
1.7.1.1
The following commercial and industrial uses are prohibited
within the SZO adjacent to great ponds classified GPA, and
rivers and streams which flow to such ponds:
1.7.1.1.1
Auto washing facilities;
1.7.1.1.2
Auto or other vehicle service and/or repair operations,
including body shops;
1.7.1.1.3
Chemical and bacteriological laboratories;
1.7.1.1.4
Storage of chemicals, including herbicides, pesticides or
fertilizers, other than amounts normally associated with
individual households or farms;
1.7.1.1.5
Commercial painting, wood preserving, and furniture
stripping
1.7.1.1.6
Dry cleaning establishments;
1.7.1.1.7
Electronic circuit assembly;
1.7.1.1.8
Laundromats, unless connected to a sanitary sewer;
1.7.1.1.9
Metal plating, finishing, or polishing;
1.7.1.1.10
Petroleum or petroleum product storage and/or sale
except storage on same property as use occurs and
except for storage and sales associated with marinas;
1.7.1.1.11
Photographic processing;
1.7.1.1.12
Printing
1.7.2
Agriculture
1.7.2.1
All spreading of manure must be accomplished in
conformance with the Manure Utilization Guidelines published
by the Maine Department of Agriculture on November 1, 2001,
and the Nutrient Management Law (7 M.R.S.A sections 4201-
4209).
1.7.2.2
Storage or stockpiling of manure shall be set back a minimum
horizontal distance of:
1.7.2.2.1 75 feet of the normal high-water line of a stream or tributary
stream;
1.7.2.2.2 150 feet from the normal high-water line of Great Ponds, rivers
that flow to Great Ponds, saltwater bodies, or the upland edge
of a coastal wetland.
132
1.7.2.3
All manure storage areas within the Shoreland Zone must be
constructed or modified such that the facility produces no
discharge of effluent or contaminated storm water.
1.7.2.4
Agricultural activities involving tillage of soil greater than
40,000 square feet in surface area within the Shoreland Zone
are required to file a Conservation Plan with the Code
Enforcement Officer or their designee.
Non-conformance with the provisions of said plan is
considered a violation of this Ordinance. Assistance in
preparing a soil and water conservation plan may be available
through the Androscoggin Valley Soil and Water Conservation
District Office.
1.7.2.5
Newly established fields that require tilling of soil shall not be
permitted within 75 feet, horizontal distance, from the normal
high-water line of any river or coastal wetlands; nor within 25
feet, horizontal distance, of tributary streams and freshwater
wetlands.
1.7.2.6
Operations in existence on May 16, 2001 and not in
conformance with this provision may be maintained.
1.7.2.7
Newly established livestock grazing areas may not be
permitted within 75 feet, horizontal distance, of any river or
coastal wetlands, nor; within 25 feet, horizontal distance, of
tributary streams and freshwater wetlands. Livestock grazing
associated with ongoing farm activities, and which are not in
conformance with these setback provisions may continue,
provided that such grazing is conducted in accordance with a
Conservation Plan that has been filed with the Town of West
Bath.
1.7.3 Aquaculture
Aquaculture land use activities extending over or below the normal
high-water line or within the wetland located in the SZO-SP and the
SZO-RP District shall require Planning Board approval in
accordance with permit standards in Section 1.8 (Shoreland Zone
Administration).
1.7.4 Timber Harvesting
Timber Harvesting in the SZO District is subject to and shall comply
with the Maine Forest Service's Statewide Standards for Timber
Harvesting Activities in Shoreland Areas (04-058 C.M.R. Ch.21) and
the Maine Bureau of Forestry's Forest Regeneration and
Clearcutting Standards (01-669 C.M.R. Ch.20) as amended.
133
1.7.5
Hazard Trees, Storm-Damaged Trees, and Dead Tree
Removal
Hazard trees in the Shoreland Protection Overlay may be removed
without a permit after consultation with the Code Enforcement Officer
if the following requirements are met:
1.7.5.1 Within the Shoreland Zoning Overlay buffer strip as described
within Section 1.2 (SZO District Applicability), if the removal of
a hazard tree results in a cleared opening in the tree canopy
greater than 250 square feet, replacement with native tree
species is required, unless there is new tree growth already
present. New tree growth must be as near as practicable to
where the hazard tree was removed and be at least two (2)
inches in diameter, measured at four and one half (4.5) feet
above the ground level. If new growth is not present, then
replacement trees shall consist of native species and be at
least four (4) feet in height, and be no less than two (2) inches
in diameter. Stumps may not be removed.
1.7.5.2
Outside of the Shoreland Zoning Overlay buffer strip as
described within Section 1.2 (SZO District Applicability), when
the removal of hazard trees exceeds 40 percent of the volume
of trees four (4) inches or more in diameter, measured at four
and one half (4.5) feet above ground level in any ten (10) year
period, and/or results in cleared openings exceeding 25
percent of the lot area within the Shoreland Zoning Overlay,
or 10,000 square feet, whichever is greater, replacement with
native tree species is required, unless there is new tree growth
already present. New tree growth must be as near as
practicable to where the hazard tree was removed and be at
least two (2) inches in diameter, measured at four and one
half (4.5) feet above the ground level. If new growth is not
present, then replacement trees shall consist of native
species and be at least two (2) inches in diameter, measured
at four and one half (4.5) feet above the ground level.
1.7.5.3
The removal of standing dead trees, resulting from
natural causes, is permissible without the need for replanting
or a permit, as long as the removal does not result in the
creation of new lawn areas, or other permanently cleared
areas, and stumps are not removed. For the purposes of this
provision dead trees are those trees that contain no foliage
during the growing season.
1.7.5.4
The Code Enforcement Officer may require the
property owner to submit an evaluation from a licensed
forester or arborist before any hazard tree can be removed
within the Shoreland Protection Overlay.
134
1.7.5.5
The Code Enforcement Officer may require more than
a one-for-one replacement for hazard trees removed that
exceed eight (8) inches in diameter measured at four and one
half (4.5) feet above the ground level.
1.7.5.6
Storm-damaged trees in the Shoreland Zoning Overlay
may be removed without a permit after consultation with the
Code Enforcement Officer if the following requirements are
met:
1.7.5.6.1 Within the Shoreland Zoning Overlay buffer strip as
described within Section 1.2 (SZO District Applicability),
when the removal of storm-damaged trees results in a
cleared opening in the tree canopy greater than 250 square
feet, replanting is not required, but the area shall be required
to naturally revegetate, and the following requirements must
be met:
1.7.5.6.1.1
The area from which a storm-damaged tree is
removed does not result in new lawn areas, or
other permanently cleared areas;
1.7.5.6.1.2
Stumps from the storm-damaged trees may not
be removed;
1.7.5.6.1.3
Limbs damaged from a storm event may be
pruned even if they extend beyond the bottom
one-third (1/3) of the tree; and
1.7.5.7
If after one (1) growing season, no natural regeneration or
regrowth is present, replanting of native tree seedlings or saplings is
required at a density of one seedling per every 80 square feet of lost
canopy. Outside of the Shoreland Zoning Overlay buffer strip as
described within Section 1.2 (SZO District Applicability) if the removal
of storm damaged trees exceeds 40 percent of the volume of trees
four (4) inches or more in diameter, measured at four and one half
(4.5) feet above the ground level in any ten (10) year period, or
results, in the aggregate, in cleared openings exceeding 25 percent
of the lot area within the Shoreland Protection Overlay or 10,000
square feet, whichever is greater, and no natural regeneration occurs
within one growing season, then native tree seedlings or saplings
shall be replanted on a one-for-one basis.
135
1.7.6
Exemptions to Clearing and Vegetation Removal Requirements
The following activities are exempt from the clearing and vegetation removal
standards set forth in Section 1.8.8 (Clearing or Removal of Vegetation for
Activities Other than Timber Harvesting), provided that all other applicable
requirements of this chapter are complied with, and the removal of
vegetation is limited to that which is necessary:
1.7.6.1
The removal of vegetation that occurs at least once every two
(2) years for the maintenance of legally existing areas that do not
comply with the vegetation standards in this chapter, such as but not
limited to cleared openings in the canopy or fields. Such areas shall
not be enlarged, except as allowed by this section. If any of these
areas, due to lack of removal of vegetation every two (2) years,
reverts back to primarily woody vegetation, the requirements of
Section 1.8.8 (Clearing or Removal of Vegetation for Activities Other
than Timber Harvesting) shall apply;
1.7.6.2
The removal of vegetation from the location of allowed
structures or allowed uses, when the shoreline setback requirements
of Section 1.5.1 (Setbacks of Structures from Water Bodies and
Wetlands) are not applicable;
1.7.6.3
The removal of vegetation from the location of public
swimming areas associated with an allowed public recreational
facility;
1.7.6.4
The removal of vegetation associated with allowed
agricultural uses, provided best management practices are utilized,
and provided all requirements of Section 1.8.2 (Agriculture) are
complied with;
1.7.6.5
The removal of vegetation associated with brownfields or
voluntary response action program (VRAP) projects provided that
the removal of vegetation is necessary for remediation activities to
clean-up contamination on a site within the SZO that is part of a state
or federal brownfields program or a voluntary response action
program pursuant 38 M.R.S. Section 343-E, as amended, and that
is located along:
1.7.6.5.1
A coastal wetland; or
1.7.6.5.2
A river that does not flow to a great pond classified as GA.
(Class GPA shall be the sole classification of great ponds and
lakes less than ten (10) acres in size [30 M.R.S. Section 465-
A(1)(B), as amended].
1.7.6.6
The removal of non-native invasive vegetation species,
provided the following minimum requirements are met:
1.7.6.6.1
If removal of vegetation occurs via wheeled or tracked
motorized equipment, the wheeled or tracked motorized
equipment is operated and stored at least 25 feet, horizontal
distance, from the shoreline, except that wheeled or tracked
equipment may be operated or stored on existing structural
surfaces, such as pavement or gravel;
136
1.7.6.6.2
Removal of vegetation within 25 feet, horizontal distance,
from the shoreline occurs via hand tools; and
1.7.6.6.3
If applicable, clearing and vegetation removal standards are
exceeded due to the removal of non-native invasive species
vegetation, the area shall be revegetated with native species
to achieve compliance.
1.7.6.6.4
The removal of vegetation associated with emergency
response activities conducted by the Department, the U.S.
Environmental Protection Agency, the U.S. Coast Guard, and
their agents.
1.7.7 Revegetation Requirements
1.7.7.1
When revegetation is required in response to violations of the
vegetation standards set forth in Section 1.8.8 (Clearing or
Removal of Vegetation for Activities Other than Timber
Harvesting) to address the removal of non-native invasive
species of vegetation, or as a mechanism to allow for
development that may otherwise not be permissible due to the
vegetation standards, including removal of vegetation in
conjunction with a shoreline stabilization project, the revegetation
must comply with the following requirements:
1.7.7.1.1 The property owner must submit a revegetation plan, prepared
with and signed by a qualified professional that describes
revegetation activities and maintenance. The plan must include a
scaled site plan, depicting where vegetation was, or is to be
removed, where existing vegetation is to remain, and where
vegetation is to be planted, including a list of all vegetation to be
planted.
1.7.7.1.2 Revegetation must occur along the same segment of shoreline
and in the same area where vegetation was removed and at a
density comparable to the pre-existing vegetation, except where
a shoreline stabilization activity does not allow revegetation to
occur in the same area and at a density comparable to the pre-
existing vegetation, in which case revegetation must occur along
the same segment of shoreline and as close as possible to the
area where vegetation was removed:
1.7.7.1.3 If part of a permitted activity, revegetation shall occur before the
expiration of the permit. If the activity or revegetation is not
completed before the expiration of the permit, a new revegetation
plan shall be submitted with any renewal or new permit
application.
137
1.7.7.1.4 Revegetation activities must meet the following requirements for
trees and saplings:
1.7.7.1.4.1
All trees and saplings removed must be replaced with
native noninvasive species;
1.7.7.1.4.2
Replacement vegetation must at a minimum consist of
saplings;
1.7.7.1.4.3
If more than three (3) trees or saplings are planted, then
at least three (3) different species shall be used;
1.7.7.1.4.4
No one species shall make up 50 percent or more of the
number of trees and saplings planted;
1.7.7.1.4.5
If revegetation is required for a shoreline stabilization
project, and it is not possible to plant trees and saplings in
the same area where trees or saplings were removed, then
trees or sapling must be planted in a location that
effectively reestablishes the screening between the
shoreline and structures; and
1.7.7.1.4.6
A survival rate of at least 80 percent of planted trees or
saplings is required for a minimum five (5) years period.
1.7.7.1.5 Revegetation activities must meet the following requirements for
woody vegetation and other vegetation under three (3) feet in
height:
1.7.7.1.5.1
All woody vegetation and vegetation under three (3) feet
in height must be replaced with native noninvasive species
of woody vegetation and vegetation under three (3) feet in
height as applicable;
1.7.7.1.5.2
Woody vegetation and vegetation under three (3) feet in
height shall be planted in quantities and variety sufficient
to prevent erosion and provide for effective infiltration of
stormwater;
1.7.7.1.5.3
If more than three (3) woody vegetation plants are to be
planted, then at least three (3) different species shall be
planted;
1.7.7.1.5.4
No one (1) species shall make up 50 percent or more of
the number of planted woody vegetation plants; and
1.7.7.1.5.5
Survival of planted woody vegetation and vegetation under
three (3) feet in height must be sufficient to remain in
compliance with the standards contained within this
chapter for minimum of five (5) years.
138
1.7.7.1.6 Revegetation activities must meet the following requirements for
ground vegetation and ground cover:
1.7.7.1.6.1
All ground vegetation and ground cover removed must be
replaced with native herbaceous vegetation, in quantities
and variety sufficient to prevent erosion and provide or the
effective infiltration of stormwater;
1.7.7.1.6.2
Where necessary due to a lack of sufficient ground cover,
an area must be supplemented with a minimum four (4)
inch depth of leaf mulch and/or bark mulch to prevent
erosion and provide for effective infiltration of stormwater;
and
1.7.7.1.6.3
Survival and functionality of ground vegetation and ground
cover must be sufficient to remain in compliance with the
standards contained within this Section for a minimum of
five (5) years.
1.7.8 Clearing or Removal of Vegetation for Activities Other than Timber
Harvesting
1.7.8.1.1 In SZO-RP, the cutting or removal of vegetation is limited to that
which is necessary for uses expressly authorized in that sub-
district.
1.7.8.1.2 Except in SZO-RP, and except to allow for the development of
permitted uses, within a strip of land extending 75 feet, horizontal
distance, inland from the normal high-water line of any river,
tributary stream, or the upland edge of a wetland, a buffer strip of
vegetation must be preserved as follows:
1.7.8.1.2.1
There may be no cleared opening greater than 250 square
feet in the forest canopy (or other existing woody
vegetation if a forested canopy is not present) as
measured from the outer limits of the tree or shrub crown.
However, a footpath not to exceed 6 feet in width as
measured between tree trunks and/or shrub stems is
allowed provided that a cleared line of sight to the water
through the buffer strip is not created.
1.7.8.1.2.2
Selective cutting of trees within the buffer strip is allowed
provided that a well-distributed stand of trees and other
natural vegetation is maintained. For the purposes of this
requirement a "well-distributed stand of trees" is defined
as maintaining a minimum rating score of 16 per 25-foot
by 50-foot rectangular area as determined by the following
rating system and criteria (a) through (e).
139
Diameter of Tree at 4-1/2
feet Above Ground Level
(inches)
Points
2- <4 inches
1
4- <8 inches
2
8- <12 inches
4
12 inches or greater
8
1.7.8.1.2.2.1 The 25-foot by 50-foot rectangular plots must be
established where the landowner or lessee proposes
clearing within the required buffer;
1.7.8.1.2.2.2 Each successive plot must be adjacent to, but may not
overlap a previous plot;
1.7.8.1.2.2.3 Any plot not containing the required points may have no
vegetation removed except as otherwise allowed by this
Code;
1.7.8.1.2.2.4 Any plot containing the required points may have
vegetations removed down to the minimum points required
or as otherwise allowed by this Code;
1.7.8.1.2.2.5 Where conditions permit, no more than 50 percent of the
points on any 25-foot by 50-foot rectangular area may
consist of trees greater than 12 inches in diameter.
1.7.9 Erosion and Sedimentation Control
1.7.9.1 Activities requiring Development Review that involve filling,
grading, excavation or other similar activities resulting in
unstabilized soil conditions shall require a written soil erosion and
sedimentation control plan. The plan shall be submitted to the
Review Authority for approval and shall include, where
applicable, provisions for
1.7.9.1.1 Mulching and revegetation of disturbed soil;
1.7.9.1.2 Temporary runoff control features such as hay bales, silt fencing,
or diversion ditches; and
1.7.9.1.3 Permanent stabilization such as retaining walls or rip rap.
1.7.9.2
To create the least potential for erosion, development shall be
designed to fit with the site topography and soils. Areas of steep
slopes where high cuts and fills may be required shall be avoided
wherever possible, and natural contours shall be followed as
closely as possible.
1.7.9.3 Erosion and sedimentation control measures shall apply to all
aspects of the proposed project involving land disturbance, and
shall be in operation during all stages of activity. The amount of
exposed soil at every phase of construction shall be minimized to
reduce the potential for erosion.
140
1.7.9.4
Any exposed ground area shall be temporarily or permanently
stabilized within one (1) week from the time it was last actively
worked by use of riprap, sod, seed, mulch, or other effective
measures. In all cases, permanent stabilization shall occur within
nine (9) months of the initial date of exposure. In addition:
1.7.9.4.1
Where mulch is used, it shall be applied at a rate of at least one
(1) bale per 500 square feet and shall be maintained until a catch
of vegetation is established.
1.7.9.4.2
Anchoring the mulch with netting, peg and twine, or other suitable
method may be required to maintain the mulch cover.
1.7.9.4.3
Additional measures shall be taken where necessary to avoid
siltation into the water. Such measures may include the use of
staked hay bales and/or silt fences.
1.7.9.5
Natural and artificial drainage ways and drainage outlets shall be
protected from erosion caused by water flow. Drainage ways shall
be designed and constructed to carry water from a 25-year storm or
greater, and shall be stabilized with vegetation or rip-rap.
1.7.9.6
When an excavation contractor will perform an activity that requires
or results in more than one (1) cubic yard of soil disturbance, the
person responsible for management of erosion and sedimentation
control practices at the site must be certified in erosion control
practices by the Maine Department of Environmental Protection. This
person must inspect the site each week earthmoving activity occurs
for a duration that is sufficient to ensure that proper erosion and
sedimentation control practices are followed. This is required until
erosion and sedimentation control measures have been installed,
which will either stay in place permanently or stay in place until the
area is sufficiently covered with vegetation necessary to prevent soil
erosion. The name and certification number of the person who will
oversee the activity causing or resulting in soil disturbance shall be
included on the permit application. This requirement does not apply
to a person or firm engaged in agriculture or timber harvesting if best
management practices for erosion and sedimentation control are
used; and municipal, state and federal employees engaged in
projects associated with that employment.
141
1.7.10
Mineral Exploration and Extraction
1.7.10.1 Mineral exploration or extraction shall be prohibited in the Shoreland
Overlay Zone
1.7.10.2 Structures and Other Activities Extending Over or Below a Water
Body or Within a Wetland or Shoreline Stabilization Area
The following requirements apply to piers, docks, wharves, bridges,
and other structures and activities extending over or below the
normal high-water line of a water body, or within a wetland or
shoreline stabilization area. (Note: New permanent structures, and
expansions thereof, projecting into or over water bodies require a
permit from the Maine Department of Environmental Protection
pursuant to the Natural Resources Protection Act, Title 38 M.R.S., §
480-C, as amended. Permits may also be required from the U.S.
Army Corps of Engineers if located in navigable waters.)
1.7.10.3 No more than one (1) pier, dock, wharf, or similar structure extending
over or located below the normal high-water line of a water body, or
within a wetland or shoreline stabilization area is permitted on a
single lot; except on single lots having a lot width at least twice the
required lot width of the base zoning district and at least twice the
minimum shore frontage as specified in Table 2.2, Minimum Lot
Standards. A second structure may be permitted and may remain as
long as the lot is not further divided.
1.7.10.3.1
The minimum distance from any portion of a dock including its
float, shall not be less than twenty-five (25) feet or the minimum
side setback requirement for the district in which it is located,
whichever is greater, to any portion of another float or dock.
1.7.10.3.2
Reduction of the minimum setback between docks is available
through variance, provided that the applicant can demonstrate
that:
1.7.10.3.2.1 No alternative design is practical;
1.7.10.3.2.2 The inability to meet the requirement is due to the location
characteristics and/or design of the abutter's existing dock;
and
1.7.10.3.2.3 All other standards in the Shoreland Overlay Zone are met.
1.7.10.4 Access from shore shall be developed on soils appropriate for such
use and constructed so as to control erosion.
1.7.10.5 The location shall not interfere with existing developed or natural
beach areas.
1.7.10.6 The structure or activity shall be located so as to minimize adverse
effects on fisheries as determined by the Code Enforcement Officer
or designee.
142
1.7.10.7 The structure shall be no larger in dimension than necessary to carry
on the activity and be consistent with the surrounding character and
uses of the area. A temporary pier, dock, or wharf shall not be wider
than six (6) feet for noncommercial uses.
1.7.10.8 No new structure shall be built on, or abutting a pier, wharf, dock, or
other structure extending beyond the normal high-water line of a
water body or within a wetland or shoreline stabilization area unless
the structure requires direct access to the water body or wetland or
shoreline stabilization area as an operational necessity.
1.7.10.9 New permanent piers and docks on non-tidal waters shall not be
permitted unless it is clearly demonstrated to the Code Enforcement
Officer that a temporary pier or dock is not feasible, and a permit has
been obtained from the Maine Department of Environmental
Protection pursuant to the Natural Resources Protection Act, Title 38
M.R.S., §480-C, as amended.
1.7.10.10 Except Commercially Functionally Water Dependent Uses outside
the Resource Protection and Stream Protection Sub-Districts,
structures built on, over or abutting a pier, wharf, dock or other
structure extending beyond the normal high-water line of a water
body or within a wetland may not exceed 20 feet in height above the
pier, wharf, dock or other structure.
1.7.10.11 No existing structures built on, over or abutting a pier, dock, wharf,
or other structure extending beyond the normal high-water line of a
water body or within a wetland shall be converted to residential
dwelling units in any sub-district.
1.7.10.12 Vegetation may be removed in excess of the standards in Section
1.8.8 (Clearing or Removal of Vegetation for Activities Other than
Timber Harvesting) of this ordinance in order to conduct shoreline
stabilization of an eroding shoreline, provided that a permit is
obtained from the Code Enforcement Officer.
1.7.10.13 When necessary, the removal of trees and other vegetation to allow
for construction equipment access to the stabilization site via land
must be limited to no more than 12 feet in width. When the
stabilization project is complete the construction equipment
accessway must be restored.
1.7.10.14 Revegetation must occur in accordance with Section 1.7.6
(Revegetation Requirements).
1.7.11
Roads and Driveways
The following standards shall apply to the construction of newly constructed
roads and/or driveways and drainage systems, culverts, and other related
features.
1.7.11.1 Unless the Code Enforcement Officer or their designee
determines that no reasonable alternative exists, roads and
driveways shall be set back a minimum horizontal distance of:
1.7.11.1.1
75 feet from the edge of a stream or tributary stream;
143
1.7.11.1.2
75 feet from the upland edge of a coastal or freshwater
wetland;
1.7.11.1.3
100 feet from the normal high-water line of a Great Pond
classified GPA.
1.7.11.2 On determining that no reasonable alternative exists to compliance
with a minimum road/driveway setback requirement in the Section
1.7.11.1 above, the Code Enforcement Officer or their designee may
reduce the minimum setback to no less than 50 feet upon clear
showing by the applicant that appropriate techniques will be used to
prevent sedimentation of the water body, tributary stream, or
wetland. Such techniques may include, but are not limited to, the
installation of settling basins and/or the effective use of additional
ditch relief culverts and turnouts placed so as to avoid sedimentation
of the water body, tributary stream, or wetland.
1.7.11.3 On slopes of greater than 20 percent, the minimum road/driveway
setbacks required in Section 1.7.11.1 above shall be increased by
ten (10) feet for each five (5) percent increase in slope above 20
percent.
1.7.11.4 The minimum road/driveway setbacks required in subsection a
above do not apply to approaches to water crossings to roads or
driveways that provide access to permitted structures and facilities
located nearer to the shoreline or tributary stream due to an
operational necessity excluding temporary docks for recreational
uses. Roads and driveways providing access to permitted structures
within the setback area shall comply fully with the requirements of
Subsection a above except for that portion of the road or driveway
necessary for direct access to the structure.
1.7.11.5 Existing public roads may be expanded within the legal road right-of-
way regardless of their setback from a water body, tributary stream
or wetland.
1.7.11.6 New roads and driveways are prohibited in the areas described in
Section 1.7 (Prohibited Locations of New Structures), except that the
Code Enforcement Officer or their designee may grant a permit to
construct a road or driveway to provide access to permitted uses
within those areas on finding that no reasonable alternative route or
location is available outside of those areas in which case the road
and/or driveway shall be set back as far as practicable from the water
body, tributary stream or upland edge of a wetland.
1.7.11.7 Road and driveway grades shall be no greater than ten (10) percent
except for driveway segments of less than 200 feet.
1.7.11.8 Road and driveway banks shall be no steeper than a slope of 2:1
horizontal to vertical, and shall be graded and stabilized in
accordance with the provisions for erosion and sedimentation control
contained in Section 1.7.8 (Erosion and Sedimentation Control).
144
1.7.11.9 To prevent road and driveway surface drainage from directly entering
a water body, tributary stream or wetland, roads and driveways shall
be designed, constructed, and maintained to empty onto an
unscarified buffer strip along a stream, tributary stream, river, tidal
waters, or wetlands:
1.7.11.9.1
The minimum horizontal width of an unscarified buffer strip along
the normal high water line of a stream or tributary stream shall be
25 feet.
1.7.11.9.2
The minimum width of an unscarified buffer strip along the normal
high water line of a river or tidal waters, or upland edge of a
coastal or freshwater wetland, shall equal 50 feet plus two (2)
times the average slope between the outflow point of the ditch or
culvert and the river, tidal waters, or wetlands.
1.7.11.10 Surface drainage directed to an unscarified buffer strip shall be
diffused or spread out to promote infiltration of the runoff and to
minimize channelized flow of the drainage through the buffer strip.
1.7.11.11 Ditch relief (cross drainage) culverts, drainage dips, and water
turnouts shall be installed in a manner effective in directing drainage
onto unscarified buffer strips before the flow gains sufficient volume
or head to erode the road, driveway or ditch. To accomplish this, the
following shall apply:
1.7.11.11.1 Ditch relief culverts, drainage dips. and associated water
turnouts shall be spaced along the road, or driveway at intervals
no greater than indicated in the following table:
Grade
Spacing
0-2%
250 feet
3-5%
200 - 135 feet
6-10%
100 - 80 feet
11-15%
80 - 60 feet
16-20%
60 - 45 feet
21%+
40 feet
1.7.11.11.2 Drainage dips may be used in place of ditch relief culverts only
where the grade is ten (10) percent or less.
1.7.11.11.3 On sections having slopes greater than ten (10) percent, ditch
relief culverts shall be placed at approximately a 30 degree angle
downslope from a line perpendicular to the centerline of the road
or driveway.
1.7.11.11.4 Ditch relief shall be sufficiently sized and properly installed in
order to allow for effective functioning and their inlet and outlet
ends shall be stabilized with appropriate materials.
1.7.11.12 Ditches, culverts, bridges, dips, water turnouts, and other storm
water runoff control installations associated with roads and
driveways shall be maintained on a regular basis to assure effective
functioning.
145
1.7.12
Campgrounds
Campgrounds shall conform to the minimum requirements imposed under
State licensing and permitting procedures and the following:
1.7.12.1 The areas intended for placement of a recreational vehicle, tent or
shelter, and utility and service buildings shall be set back a minimum
horizontal distance of:
1.7.12.1.1 75 feet from the edge of a stream or tributary stream;
1.7.12.1.2 75 feet from the upland edge of a coastal or freshwater
wetland;
1.7.12.2 Campgrounds shall contain a minimum of 5,000 square feet of land
for each camp site. Land containing roads and driveways, lands
supporting wetland vegetation, and land below the normal high water
line of a water body shall not be included in calculating land per camp
site.
1.7.12.3 All campgrounds are subject to Site Plan Review and approval by
the Maine Department of Health and Human Services.
1.7.13
Individual Private Campsites
Individual private campsites not associated with campgrounds are allowed
provide the following conditions are met:
1.7.13.1 One (1) campsite may be placed on 30,000 square feet of lot area
within the SZO, or shall be placed on a lot existing on the effective
date of this Ordinance, whichever is less, may be permitted.
1.7.13.2 Campsite placement on any lot, including the area intended for a
recreational vehicle or tent platform, shall be set back a minimum
horizontal distance of:
1.7.13.2.1
75 feet from the normal high-water line edge of a stream or
tributary stream;
1.7.13.2.2
75 feet from the normal high-water line upland edge of a
coastal or freshwater wetland;
1.7.13.3 When an individual private campsite is proposed on a lot that
contains another principal use and/or structure, the lot must contain
the minimum lot dimensional requirements for the principal structure
and/or use, and the individual private campsite separately.
1.7.13.4 Only one (1) recreational vehicle shall be allowed on a campsite. The
recreational vehicles shall not be located on any type of permanent
foundation and no structure(s) except canopies shall be attached to
the recreation vehicle.
1.7.13.5 The clearing of vegetation for the siting of the recreational vehicle,
tent, or similar shelter shall be limited to an area of 1,000 square feet.
1.7.13.6 A written sewage disposal plan describing the proposed method and
location of sewage disposal shall be required for each campsite and
shall be approved by the Local Plumbing Inspector. Where disposal
is off-site, written authorization from the receiving facility or land
owner is required.
146
1.7.13.7 No recreational vehicles, tent, or similar shelter shall be placed on-
site for more than 120 days per year.
1.7.14
Sanitary Standards
As well as meeting all requirements of the State of Maine Subsurface
Wastewater Disposal Rules, all on-site septic systems located within the SZO
District shall meet the following additional standards:
1.7.14.1 All parts of all types of subsurface wastewater disposal systems shall
be set back a minimum horizontal distance of:
1.7.14.1.1
75 feet from the edge of a stream or tributary stream;
1.7.14.1.2
75 feet from the upland edge of a coastal or freshwater
wetland;
1.7.14.2 No clearing or removal of woody vegetation necessary to site a new
system and any associated fill extensions shall occur within a
minimum horizontal distance of:
1.7.14.2.1
75 feet from the edge of a stream or tributary stream;
1.7.14.2.2
75 feet from the upland edge of a coastal or freshwater
wetland;
1.7.14.3 A holding tank is not allowed for a first-time residential use.
1.7.14.4 The Local Plumbing Inspector may consider and grant a request to
reduce this setback for a replacement subsurface wastewater
disposal system if a report prepared by a soils scientist or site
evaluator registered in the State of Maine is submitted and accepted,
and the report states that:
1.7.14.4.1
The existing system is failing;
1.7.14.4.2
No suitable location exists outside the setback; and
1.7.14.4.3
The proposed location meets the required setbacks to the
greatest extent practicable.
1.7.14.5 Setbacks for new subsurface wastewater disposal facilities cannot
be reduced by Variance.
1.7.15
Overboard Discharge Systems
Overboard discharge from a sewage disposal system, in which sewage
(chlorinated or otherwise) flows into a protected resource, is prohibited.
Systems licensed prior to June 6, 1994, may continue as long as they are
in compliance with all appropriate State laws and do not involve expansion
of the existing system.
1.7.16
Water Quality
No activity shall deposit on or into the ground, or discharge to the waters of the
State, any pollutant that, by itself, or in combination with other activities or
substances, will impair designated uses or the water classification of the water
body or wetland.
147
1.7.16.1 A person or activity may not locate, store, discharge, or permit the
discharge of any treated, untreated, or inadequately treated liquid,
gaseous, or solid materials of such nature, quantity, obnoxiousness,
toxicity, or temperature that may run off, seep, percolate, or wash into
surface water or groundwater so as to contaminate, pollute, or harm
such waters or cause nuisances such as objectionable shore deposits,
floating or submerged debris, oil or scum, color, odor, taste, or
unsightliness, or be harmful to human, animal, plant, or aquatic life.
1.7.16.2 All storage facilities for fuel, chemicals, chemical or industrial wastes,
and biodegradable raw materials must meet the standards of the
MEDEP and the State Fire Marshall's Office.
1.7.17
Soils
All land uses shall be located on soils in or upon which the proposed uses or
structures can be established or maintained without causing adverse
environmental impacts, including severe erosion, mass soil movement,
improper drainage, and water pollution, whether during or after construction.
Proposed uses requiring subsurface waste disposal, and commercial or
industrial development and other similar intensive land uses, shall require a
soils report based on an on-site investigation and be prepared by state-certified
professionals. Certified persons may include Maine Certified Soil Scientists,
Maine Registered Professional Engineers, Maine State Certified Geologists
and other persons who have training and experience in the recognition and
evaluation of soil properties. The report shall be based upon the analysis of the
characteristics of the soil and surrounding land and water areas, maximum
ground water elevation, presence of ledge, drainage conditions, and other
pertinent data which the evaluator deems appropriate. The soils report shall
include recommendations for a proposed use to counteract soil limitations
where they exist.
1.7.18
Historic and Archeological Resources
Any proposed land use activity involving structural development or soil
disturbance on or adjacent to sites listed on, or eligible to be listed on the
National Register of Historic Places, as determined by the permitting authority,
shall be submitted by the applicant to the Maine Historic Preservation
Commission for review and comment, at least twenty (20) days prior to action
being taken by the permitting authority. The permitting authority shall consider
comments received from the Commission prior to rendering a decision on the
application.
1.7.19
Parking Areas
1.7.19.1 Parking areas shall meet the minimum water body and wetland
setback requirements for principal and accessory structures in
Section 1.6.1 (Setbacks of Structures from Water Bodies and
Wetlands).
148
On finding that no reasonable alternative to compliance with a
required minimum setback exists, the Code Enforcement Officer or
their designee may reduce the minimum setback for parking areas
serving a public or private boat launching facility to no less than 50
feet from the normal high water line of a stream, tributary stream,
river, or tidal waters, and the upland edge of a coastal or freshwater
wetland.
1.7.19.2 Parking areas shall be designed to prevent stormwater runoff from
flowing directly into a water body, tributary stream or wetland, and
where feasible, to retain all runoff on-site.
1.7.19.3 Unless provided below, parking areas shall conform to the design
standards in Article III, section 3.9 of this Ordinance. In addition,
parking spaces for vehicles with boat trailers shall be at least 40 feet
in length.
1.7.19.3.1
Typical parking space: Approximately ten (10) feet wide and
twenty (20) feet long, except that parking spaces for a
vehicle and boat trailer shall be forty (40) feet long.
1.7.19.3.2
Internal travel aisles: Approximately twenty (20) feet wide.
1.7.20
Stormwater Runoff
1.7.20.1 All new construction and development shall be designed to minimize
storm water runoff from the site in excess of the natural
predevelopment conditions. Where possible, existing natural runoff
control features, such as berms, swales, terraces and wooded areas,
shall be retained in order to reduce runoff and encourage infiltration
of stormwaters.
1.7.20.2 Storm water runoff control systems shall be maintained as necessary
to ensure proper functioning.
1.7.20.3 Direct discharge of stormwater into any water body shall be avoided.
1.7.21
Essential Services
1.7.21.1 Where feasible, the installation of essential services shall be limited
to existing public rights-of-way and existing service corridors.
1.7.21.2 The installation of essential services, other than roadside distribution
lines, is not allowed in a Resource Protection (SZO-RP) or a Stream
Protection (SZO-SP) Sub-District, except to provide services to a
permitted use within said District, or except where the applicant
demonstrates that no reasonable alternative exists. Where allowed,
such structures and facilities shall be located so as to minimize any
adverse impacts on surrounding uses and resources, including, but
not limited to, visual impacts.
1.7.21.3 Damaged or destroyed utility transmission and distribution lines,
towers and related equipment may be replaced or reconstructed
without a Shoreland Zone Permit.
149
1.7.22 Minor Utilities
1.7.22.1 Where feasible, the installation of minor utilities shall be limited to
existing public ways and existing service corridors.
1.7.22.2 The installation of minor utilities other than road-side distribution
lines is not allowed in the SZO District except to provide services to
a permitted use within the District, or except where the applicant
demonstrates that no reasonable alternative exists. Where allowed,
such structures and facilities shall be located so as to minimize any
adverse impacts on surrounding uses and resources, including
visual impacts.
1.7.22.3 Damaged or destroyed public utility transmission and distribution
lines, towers, and related equipment may be replaced or
reconstructed without a Shoreland Zone Permit.
1.7.23 Signs
1.7.23.1 The following provisions shall govern the use of signs in the SZO:
1.7.23.1.1 Signs relating to goods and services sold on the premises shall
be allowed, provided that such signs shall not exceed six (6)
square feet in area and shall not exceed two (2) signs per
premises. In the Limited Commercial District, however, such
signs shall not exceed sixteen (16) square feet in area. Signs
relating to goods or services not sold or rendered on the
premises shall be prohibited.
1.7.23.1.2 Name signs are allowed, provided such signs shall not exceed
two (2) signs per premises, and shall not exceed twelve (12)
square feet in the aggregate.
1.7.23.1.3 Residential users may display a single sign not over three (3)
square feet in area relating to the sale, rental, or lease of the
premises.
1.7.23.1.4 Signs relating to trespassing and hunting shall be allowed
without restriction as to number provided that no such sign shall
exceed two (2) square feet in area.
1.7.23.1.5 Signs relating to public safety shall be allowed without restriction
1.7.23.1.6 No sign shall extend higher than twenty (20) feet above the
ground
1.7.23.1.7 Signs may be illuminated only by shielded, non-flashing lights.
1.7.24 Public Utility Service
No utility of any kind may install services to any new structure located in the
Shoreland Zone unless written authorization attesting to the validity and
currently of all local permits required under this Section, or any previous
Section, has been issued by the Code Enforcement Officer, or other written
arrangements have been made between the municipal officials and the
utility.
150
1.8
Shoreland Zone Administration
1.8.1
Permit Required
All development or other land use activity within the Shoreland Zone Overlay
District shall require a Shoreland Zoning Permit from the applicable Review
Authority in accordance with Development Review thresholds as stated in
Table 2.2, Land Use Matrix and the following review criteria, unless the Table
indicates a permit is not required. This permit shall be in addition to any other
permit or plan approvals which may be required by this Ordinance. The
applicant shall have the burden of proving that the proposed land use activity
is in conformity with the purposes and provisions of this Ordinance. In
accordance with 38 M.R.S §439-A(10) Shoreland Zoning Overlay permit
applicants must provide preconstruction photographs with their application
and, no later than 20 days after completion of the development,
postconstruction photographs of the Shoreline vegetation and development
site.
1.8.2
A permit is not required for the replacement of an existing road culvert as
long as:
1.8.2.1
The replacement culvert is not more than 25% longer than the culvert
being replaced;
1.8.2.2
The replacement culver is not longer than 75 feet; and
1.8.2.3
Adequate erosion control measures are taken to prevent
sedimentation of the water, and the crossing does not block fish
passage in the waterstone.
1.8.3
A permit is not required for an archaeological excavation as long as
the excavation is conducted by an archaeologist listed on the State
Historic Preservation Officer's approved list, and unreasonable
erosion and sedimentation is prevented by means of adequate and
timely temporary and permanent stabilization measures.
1.8.4
Any permit required by this Ordinance shall be in addition to any
other permit required by other law or ordinance.
1.8.5
Permit Review Criteria
After the submission of a complete application to the Planning Board or Code
Enforcement Officer, the Review Authority shall take action on an application
based on the following review criteria:
1.8.5.1
The development or other land use activity will maintain safe and
healthful conditions;
1.8.5.2
The development or other land use activity will not result in water
pollution, erosion, or sedimentation to surface waters;
1.8.5.3
Will adequately provide for the disposal of all wastewater;
1.8.5.4
Will not have an adverse impact on spawning grounds, fish, aquatic
life, bird or other wildlife habitat;
1.8.5.5
Will conserve shore cover and visual, as well as actual, points of
access to inland and coastal waters;
151
1.8.5.6
Will protect archaeological and historic resources as designated in
the Comprehensive Plan;
1.8.5.7
Will not adversely affect existing commercial fishing or maritime
activities in the SZO;
1.8.5.8
Will avoid problems associated with floodplain development and use;
and
1.8.5.9
Is in conformance with the provisions of this Ordinance.
If a permit is either denied or approved with conditions, the reasons as well as
conditions shall be stated in writing. No approval shall be granted for an
application involving a structure if the structure would be located in an
unapproved subdivision or would violate any other local ordinance, or
regulation or statute administered by the Town of West Bath.
1.8.6
Application Fees
All applications shall be accompanied by an application fee paid to the Town
of West Bath.
1.8.7
Procedure
Projects requiring approval from the Code Enforcement Officer or Planning
Board shall be subject to the following provisions:
1.8.7.1
Every applicant for approval shall submit a written application,
including a scaled site plan, on a form provided by the Code
Enforcement Officer
1.8.7.2
All applications shall be signed by the owner or individual who can
show evidence of right, title, or interest in the property or by an agent,
representative, tenant, or contractor of the owner with authorization
from the owner to apply for a permit hereunder, certifying that the
information in the application is complete and correct.
1.8.7.3
All applications shall be dated, and the Code Enforcement Officer
shall note upon each application the date and time of its receipt.
1.8.7.4
If the property is not served by the City of Bath sewer system, the
applicant shall submit a valid septic system permit or a completed
application for a septic system permit, including the site evaluation
approved by the plumbing inspector, whenever the nature of the
proposed structure would require the installation of a subsurface
disposal system.
152
1.8.7.5
If applicable when an excavation contractor will perform an activity
that requires or results in more than one (1) cubic yard of soil
disturbance, the person responsible for management of erosion and
sedimentation control practices at the site must be certified in
erosion control practices by the Maine Department of Environmental
Protection. This
person must be
present
at
the
site
each day earthmoving activity occurs for a duration that is sufficient
to ensure that proper erosion and sedimentation control practices are
followed. This is required until erosion and sedimentation control
measures have been installed, which will either stay in place
permanently or stay in place until the area is sufficiently covered with
vegetation necessary to prevent soil erosion. The name and
certification number of the person who will oversee the activity
causing or resulting in soil disturbance shall be included on the
permit application. This requirement does not apply to a person or
firm engaged in agriculture or timber harvesting if best management
practices for erosion and sedimentation control are used;
and municipal, state and federal employees engaged in projects
associated with that employment.
1.8.7.6
Within thirty-five days of the date of receiving a written application,
the Code Enforcement Officer shall notify the applicant in writing
either that the application is complete or, if the application is
incomplete, that additional material is needed to make the
application complete. The application shall either be approved,
approved with conditions, or denied in writing within thirty-five days
of receiving a completed application, or within thirty-five days of the
public hearing, if one is held.
1.8.7.7
The applicant shall have the burden of proving that the proposed land
use activity is in conformity with the purposes and provisions of this
Ordinance.
1.8.7.8
All applicants receiving approval for projects located in the Shoreland
Zone Overlay District must provide the Code Enforcement Officer
with pre-construction photographs and, no later than twenty days
after completion of the development, post-construction photographs
of the shoreline vegetation and development site.
1.8.8 If a permit is either denied or approved with conditions, the
reasons and conditions shall be stated in writing. No approval
shall be granted for an application involving a structure if the
structure would be located in an unapproved subdivision or would
violate this Ordinance or any regulation or any State law in which
the municipality is responsible for enforcing.
1.8.9 Permits granted under this section may be subject to reasonable
conditions to ensure conformity with the purpose and provisions
of this Ordinance.
153
1.8.10 Permits shall expire one year from the date of issuance if a
substantial start is not made in construction or in the use of the
property during that period. If a substantial start is made within
one year of the issuance of the permit, the applicant shall have
one additional year to complete the project, at which time the
permit shall expire.
1.9 Special Exceptions for Development within the Resource Protection.
In addition to the criteria specified in Section 1.8.5 (Permit Review Criteria)
above, excepting structure setback requirements, the Planning Board may
approve a permit for a single family residential structure in a Resource
Protection Sub-District provided that the applicant demonstrates that all of the
following condition are met:
1.9.1
There is no location on the property, other than a location within the
Resource Protection Sub-District, where the structure can be built.
1.9.2
The lot on which the structure is proposed is undeveloped and was
established and recorded in the Sagadahoc County Registry of
Deeds.
1.9.3
All proposed buildings, sewage disposal systems and other
improvements are:
1.9.3.1
Located on natural ground slopes of less than 20%; and
1.9.3.2
Located outside the floodway of the 100-year floodplain along rivers
and artificially formed great ponds along rivers and outside the
velocity zone in areas subject to tides based on detailed flood
insurance studies and as delineated on the Federal Emergency
Management Agency's Flood Boundary and Floodway Maps and
Flood Insurance Rate Maps; all buildings, including basements, are
elevated at lest one foot above the 100-year floodplain elevation; and
the development is otherwise in compliance with the City of Bath's
floodplain ordinance.
If the floodway is not shown on the Federal Emergency Management
Agency Maps, it is deemed to be ½ the width of the 100-year
floodplain.
1.9.4
The total footprint, including cantilevered or similar overhanging
extensions, of all principal and accessory structures is limited to a
maximum of 1,500 square feet. This limitation shall not be altered by
variance.
154
1.9.5
All structures, except functionally water-dependent structures, are
set back from the normal high-water line of a water body, tributary
stream or upland edge of a wetland to the greatest practical extent,
but not less than 75 feet, horizontal distance. In determining the
greatest practical extent, the Planning Board shall consider the depth
of the lot, the slope of the land, the potential for soil erosion, the type
and amount of vegetation to be removed, the proposed building site's
elevation in regard to the floodplain, and its proximity to moderate-
value and high-value wetlands.
155
ARTICLE IX - ENFORCEMENT AND PENALTIES
A. The Select Board is hereby given the power and authority to enforce the
provisions of this Ordinance. The Code Enforcement Officer shall be
delegated the authority to enforce the provisions of this Ordinance on
behalf of the Select Board
B. It shall be the duty of the Code Enforcement Officer to enforce the
provisions of this Land Use Ordinance. If any provision of this Ordinance
is being violated, the Code Enforcement Officer shall notify in writing the
person or entity responsible for such violations, indicating the nature of
the violation and ordering the action necessary to correct it, including
discontinuance of illegal use of land, buildings, or structures, or work
being done, removal of illegal buildings or structures, and abatement of
nuisance conditions.
C. The Code Enforcement Officer, upon being informed in writing of a
possible violation of this Ordinance, or on his own initiative, shall make or
cause to be made an investigation of facts and an inspection of the
premises where such violation may exist. After investigation, on evidence
of any violation, the Code Enforcement Officer shall give written notice of
such violation to the owner and to the occupant of such premises. The
Code Enforcement Officer shall demand in such notice that such violation
be abated within some designated reasonable time.
D. Legal Actions - When the above action does not result in the correction
or abatement of the violation or nuisance condition, the Municipal Officers
or the Code Enforcement Officer are hereby authorized and directed to
institute and all actions and proceedings, either legal or equitable,
including seeking injunctions of violations and the imposition of fines, that
may be appropriate or necessary to enforce the provisions of this
Ordinance in the name of the municipality.
E. Fines - Any person who continues to violate any provision of this
Ordinance after receiving notice of such violation shall be guilty of a
misdemeanor subject to a fine consistent with the provisions of 30-A
M.R.S. § 4452 as amended. Each day such violation is continued a
separate offense is considered.
F. If any conflict exists between this Ordinance and any other Ordinances, the
stricter Ordinance will prevail.
156
ARTICLE X: DEFINITIONS
In general, words and terms used in these regulations shall have their customary
dictionary meanings. More specifically, certain words and terms used herein are
defined as follows:
ACCESSORY DWELLING UNIT (ADU): A self-contained dwelling unit located within,
attached or detached from a single-family dwelling unit or duplex located on the same
parcel. An Accessory Dwelling Unit shall:
A. Be a minimum of 190 square feet
B. Be no larger than 1,000 square feet or 50% of the principal structure footprint,
whichever is less.
ADDITION: Any construction which increases the area or the height of any portion of
the building or structure
AFFORDABLE HOUSING DEVELOPMENT:
A.
For rental housing, a development in which a household whose income does
not exceed 80% of the median income for the area as defined by the United
States Department of Housing and Urban Development under the United
States Housing Act of 1937, Public Law 75-412, 50 Stat 888, Section 8, as
amended can afford a majority of the units that the development designates
as affordable without spending more than 30% of the household's monthly
income on housing costs; and
B. For owned housing, a development in which a household whose income
does not exceed 120% of the median income for the area as defined by the
United States Department of Housing and Urban Development under the
United States Housing Act of 1937, Public Law 75-412, 50 Stat. 888, Section
8, as amended, can afford a majority of the units that the developer
designates as affordable without spending more than 30% of the
household's monthly income on housing costs.
C.
For purposes of this definition, "majority" means more than half of proposed
and existing units of the same lot.
D.
For purposes of this definition, "housing costs" include, but are not limited to:
1. For a rental unit, the cost of rent and any utilities (electric, heat, water,
sewer, and/or trash) that the household pays separately from the rent;
and
2. For an ownership unit, the cost of mortgage principal and interest, real
estate taxes (including assessments), private mortgage insurance,
homeowner's insurance, condominium fees, and homeowners'
association fees.
157
AGRICULTURE: The production, keeping or maintenance for sale or lease, of plants
and/or animals, including but not limited to: Forages and sod crops; grains and seed
crops; dairy animals and dairy products; poultry and poultry products; livestock; fruits
and vegetables; and ornamental and greenhouse products. Agriculture does not
include forest management and timber harvesting activities.
AGGRIEVED PARTY: A person whose land is directly or indirectly affected by the
grant or the denial of a permit or variance under this Ordinance; a person whose land
abuts land which
a permit or variance has been granted; a group of five (5) or more citizens of the
municipality who represent an interest adverse to the grant or denial of such permit
or variance.
ALTERATION: Any changes or modification in construction, existing facilities, or
permanent fixtures or equipment which does not include an addition to the building or
structure.
AREA MEDIAN INCOME: The midpoint of a region's (Sagadahoc County) income
distribution calculated on an annual basis by the US Department of Housing & Urban
Development
ARTERIAL: A roadway which serves long distance through-traffic and also allows
access to abutting land.
ATTACHED: Connected by a shared wall to the principal structure or having
physically connected finished spaces.
BASE DENSITY: The maximum number of units allowed on a lot not used for
affordable housing based on dimensional requirements in a local land use or zoning
ordinance. This does not include local density bonuses, transferable development
rights, or other similar means that could increase the density of lots not used for
affordable housing.
BUILDING: A combination of materials to form a construction that is safe and stable,
and adapted to permanent or continuous occupancy for assembly, business,
educational, high hazard, industrial, institutional, mercantile, residential, or storage
purposes.
BUFFER AREA: A part of a property or an entire property, which is not built upon and
is specifically designed to separate and thus minimize the effects of a land use activity
(e.g. noise, dust, visibility, glare, etc.) on adjacent properties or on sensitive natural
resources.
BUSINESS UNIT: A distinct commercial use occupying a building or portion thereof
and/or a lot or portion thereof that has a distinct identity by virtue of legal status, stated
158
name or signage.
CAMPGROUND: In addition to the generally accepted definitions, camping areas,
glamping (a form of camping involving accommodation and facilities more luxurious
than traditional camping) areas, recreational vehicle parks, picnic and lunch grounds
or other premises where tents, recreational vehicles, rental cabins, and cottages are
permitted on five (5) or more sites for commercial or non-commercial purposes.
Campground includes but is not limited to, sites intended for recreational purposes
rather than temporary residency.
CENTRALLY MANAGED WATER SYSTEM: A water system that provides water for
human consumption through pipes or other constructed conveyances to at least
fifteen (15) service connections or serves an average of at least twenty-five (25)
people for at least sixty (60) days a year as regulated by 10-144 C.M.R. Ch.231,
Rules Relating to Drinking Water. This water system may be privately owned.
CERTIFICATE OF OCCUPANCY: The municipal approval for occupancy granted
pursuant to 25 M.R.S. §2357-A or the Maine Uniform Building and Energy Code
(MUBEC) adopted pursuant to Title 10 Chapter 1103. Certificate of Occupancy may
also be referred to as issuance of certificate of occupancy or other terms with a similar
intent.
CLUSTER SUBDIVISION: A subdivision in which the lot sizes and road frontages
may be reduced below those normally required in the zoning district in which the
development is located in return for the provision of permanent open space owned
in common by lot/unit
owners, or land trust. Clustering shall not increase the number of allowable lots in a
subdivision.
COASTAL FLOODPLAIN: The elevation of the one hundred (100) year flood is set
at nine (9) feet above, vertical distance, mean sea level for the Town of West Bath.
COASTAL WETLAND: Any swamp, marsh, bog, beach, flat, or other land which is
subject to tidal action above extreme low water and below its upland edge, which is
defined as the maximum spring tide as identified in tide tables published by the
National Ocean Service.
COMPARABLE SEWER SYSTEM: Any subsurface wastewater disposal system that
discharges over 2,000 gallons of wastewater per day as regulated by 10-144 C.M.R.
Ch.241, Subsurface Wastewater Disposal Rules.
COMPLETE APPLICATION: An application shall be considered complete upon
submission of the required fee and all information required by these regulations for a
Final Plan, or by a vote by the Board to waive the submission of required information.
The Board shall issue a receipt to the applicant upon its determination that an
application is complete.
159
COMPREHENSIVE PLAN: A document consistent with 30-A M.R.S §4326(1)-(4),
including the strategies for an implementation program that are consistent with the
goals and guidelines established pursuant to Title 30-A Chapter 187
CONTIGUOUS LOTS: Lots which adjoin at any line or point, or are separated at any
point by a body of water less than fifteen feet wide.
DENSITY REQUIREMENTS: Maximum number of dwelling units allowed on a lot,
subject to dimensional requirements.
DESIGNATED GROWTH AREA: An area that is designated in Union's
Comprehensive Plan as suitable for orderly residential, commercial, or industrial
development, or any combination of those types of development, and into which most
development projected over ten (10) years is directed. Designated Growth Areas may
also be referred to as priority development zones or other terms with a similar intent.
DIMENSIONAL REQUIREMENTS: Requirements which govern the size and
placement of structures including, but not limited to, the following requirements:
building height, lot area, minimum frontage, and lot depth.
DRIVEWAY:A traveled way that provides vehicular access to a single lot, located
wholly or partially on that lot or within an easement granting access to the lot..
DRIVEWAY: An entrance or exit used by vehicular traffic entering or exiting property
abutting a highway or public road. This term includes private residential driveways as
well as commercial and other nonresidential dwelling units.
DUPLEX: Two (2) dwelling units within a single structure.
DWELLING UNIT: A room or group of rooms designed and equipped exclusively for
use as permanent, seasonal, or temporary living quarters for only one (1) family
at a time, and
containing cooking, sleeping and toilet facilities. The term shall include mobile homes
and rental units that contain cooking, sleeping and toilet facilities regardless of the
time-period rented. Recreational vehicles are not residential dwelling units.
EASEMENT: The authorization of a property owner for the use by another, and for a
specified purpose, or any designated part of his or her property.
ENGINEER: Municipal Engineer or consulting engineer licensed by the State of Maine.
EXISTING DWELLING UNIT: A residential unit in existence on a lot at the time of
submission of a permit application to build additional units on that lot. If a municipality
does not have a permitting process, the dwelling unit on a lot must be in existence at
the time construction begins for additional units on a lot.
160
FINAL PLAN: The final drawings on which the applicant's subdivision plan is
presented to the Board for approval and which, if approved, may be recorded at the
Registry of Deeds.
FLOOR AREA: The sum of the nominal areas of each floor of a structure calculated
as the projected areas extended to the exterior faces of the surrounding walls, plus
the areas of any unenclosed portions of the structure such as porches and decks,
plus the area of an enclosed basement having a flat floor and ceiling height of at least
six (6') feet. If a floor level is completely discontinuous, such as in the way of a
cathedral ceiling, it shall not be projected through such a space. Minor discontinuities
such as stairwells are not excluded from the calculation.
FOREST MANAGEMENT ACTIVITIES: Timber cruising and other forest resources
evaluation activities, management planning activities, insect and disease control,
timber stand improvement, pruning, timber harvesting and other forest harvesting,
regeneration of forest stands, and other similar associated activities, but not the
construction of ROADS. Nevertheless, no timber shall be harvested within 150 feet
of normal high water mark.
FORESTED WETLAND: A freshwater wetland dominated by woody vegetation that
is twenty (20) feet tall or taller.
FRESHWATER WETLAND: Freshwater swamps, marshes, bogs and similar areas,
other than forested wetlands, which are:
A. Of ten or more contiguous acres; or of less than ten (10) contiguous acres and
adjacent to a surface water body, excluding any river, streamor brook, such that
in a natural state, the combined surface area is in excess of 10 acres; and
B. Inundated or saturated by surface or ground water at a frequency and for a
duration sufficient to support, and which under normal circumstances do
support, a prevalence of wetland vegetation typically adapted for life in
saturated soils.
Freshwater wetlands may contain small stream channels or inclusions of land
that do not conform to the criteria of this definition.
GREAT POND CLASSIFICATION GPA: Any great pond classified GPA, pursuant
to Title 38 Article 4-A Section 465-A.
HEIGHT OF A STRUCTURE: The vertical distance between the lowest point of the
structure at finished grade and the highest point of the structure excluding chimneys,
steeples, antennas, and similar appurtenances which are incidental to the principal
function of the structure. See also Median Height of a STRUCTURE.
HIGH INTENSITY SOIL SURVEY: A soil survey conducted by a Certified Soil
Scientist, meeting the standards of the National Cooperative Soil Survey, which
161
identifies soil types down to 1/10 acre or less at a scale equivalent to the subdivision
plan submitted. The mapping units shall be the soil series. Single soil test pits and
their evaluation shall not be considered to constitute high intensity soil surveys.
HOUSING: Any part of a structure which, through sale or lease, is intended for human
habitation, including single-family and multifamily housing, condominiums, time-
share units, and apartments. For purposes of this rule, this does not include
dormitories, boarding housing, or other similar types of housing units. This also does
not include transient housing or short-term rentals.
INDIVIDUAL PRIVATE CAMPSITE: An area of land which is not associated with a
campground, but which is developed for repeated camping by only one group not to
exceed ten (10) individuals and which involves site improvements which may include
but not be limited to gravel pads, parking areas, fire places, or tent platforms.
INDUSTRIAL PARK OR DEVELOPMENT: A subdivision in an area zoned for
industrial uses or a subdivision planned for industrial uses and developed and
managed as a unit, usually with provision for common services for the users.
INLAND WETLAND: Areas of two (2) or more acres enclosed by the normal high
water mark of inland waters and areas otherwise identified on the basis of soils,
vegetation, or other criteria as inland wetlands, including but not limited to swamps,
marshes, or bogs.
JUNKYARD: A yard, field or other area used as a place of storage, for: discarded,
worn-out or junked plumbing, heating supplies, household appliances and furniture;
discarded, scrap and junked lumber; old or scrap copper, brass, ropes, rags,
batteries, motor vehicle parts, paper trash, rubber or plastic debris, waste and all
scrap iron, steel and other scrap ferrous or non-ferrous material; garbage dumps,
waste dumps, and private sanitary landfills; automobile graveyards.
LAND USE ORDINANCE: The local ordinance of general application adopted by the
Union legislative body which controls, directs, or delineates allowed uses of land and
standards for those uses.
LOT: A single parcel of developed or undeveloped land.
LOT COVERAGE: The portion of a lot covered by structures, other impermeable
surfaces, and dedicated permeable surfaces such as parking lots or exterior storage
areas identified on the site plan of the lot.
MAJOR ROADS: The State Road (old Route 1), Berry's Mill Road, Campbells Pond
Road, Old Brunswick Road, New Meadows Road, Foster's Point Road, and Bull Rock
Road (between the State Road and Foster's Point Road).
MEDIAN HEIGHT OF A STRUCTURE: The vertical distance between the average of
162
the highest and the lowest points of a structure at finished grade and the highest
point of a structure excluding chimneys, steeples, antennas and similar
appurtenances which are incidental to the principal function of the structure . [Note:
Defining a height measurement for assessing the heights of structures on sloping
ground.]
MEDICAL OFFICE: Room or rooms whose principal use is as a space for a person
or persons offering a service which requires specialized knowledge such as dentist,
doctor or other medical professional and where no merchandise is sold.
MOBILE HOME: A moveable or portable dwelling built on a chassis, connectable to
utilities.
MULTIFAMILY DWELLING: A structure containing three (3) or more dwelling units.
West Bath does not permit a multi-family dwelling structure that exceeds eight (8)
dwelling units.
NON-CONFORMING LOT: A single LOT of record which, at the effective date of
adoption or amendment of this Ordinance, does not meet the area, frontage, or width
requirements of the district in which it is located.
NET RESIDENTIAL ACREAGE: The total acreage of the subdivision, as shown on
the proposed subdivision plan, minus the area for streets or access and the areas
which are unsuitable for development as specified in Section 4.10.3.
NORMAL HIGH WATER MARK OF COASTAL WATERS: The line on the shore of
tidal waters reached by the shoreward limit of the rise of the tide between the spring
and the neap.
NORMAL HIGH WATER ELEVATION OF COASTAL WATERS: The elevations at
which vegetation changes from predominantly salt tolerant to predominantly non-salt
tolerant. By way of illustration, salt tolerant lavender, silverweed, salt marsh bulrush,
seaside plantain, salt marsh sedge, salt marsh aster. In places where vegetation is not
present, the high water elevation shall be the identifiable debris line left by non-storm
tidal action. On a sand dune, the high-water elevation shall be the mean seaward
limit of salt tolerant vegetation.
NORMAL HIGH-WATER MARK OF INLAND WATERS: The line of the shore and
banks of non- tidal waters which is apparent because of the contiguous different
character of the soil or the vegetation due to the prolonged action of the water.
Relative to vegetation, it is the line where the vegetation changes from predominantly
aquatic to predominantly terrestrial. In places where the shore is of such character that
the high-water mark cannot easily be determined (rockslides, ledges, rapidly eroding
or slumping banks), the normal high water mark shall be determined from the places
where it can be determined, by the above method. Areas contiguous with rivers and
great ponds that support non-forested wetland vegetation and hydric soils and that
are at the same or lower elevation as the water level of the river or great pond during
163
the period of normal high-water are considered part of the river or great pond.
NORMAL HIGH-WATER ELEVATION OF INLAND WATERS: The line on the
shores of banks on non-tidal waters which is apparent because of the contiguous
different character of the solid or the vegetation due to the prolonged action of the
water. Relative to vegetation, it is that line where the vegetation changes from
predominantly aquatic to predominantly terrestrial (by way of illustration, aquatic
vegetation includes but is not limited to the following plants and plant groups: water
lily, pond lily, pickerelweed, cattail, wild rice, sedges, rushes and marsh grasses; and
terrestrial vegetation includes but is not limited to the following plants and plant
groups: upland grasses, aster, lady slipper, wintergreen, partridgeberry, sarsaparilla,
pines, cedars, oaks, ashes, alders, elms, and maples). In places where the shore or
bank is of such character that the high-water mark cannot be easily determined,
(rockslides, ledges, rapidly eroding or slumping banks) the normal high water
elevation shall be estimated from places where it can be determined by the above
method.
OFFICIAL SUBMITTAL DATE: The date upon which the Planning Board issues a
receipt indicating a complete application has been submitted.
PERSON: Includes a firm, association, organization, partnership, trust, company, or
corporation, as well as an individual.
PLANNING BOARD: The Planning Board of the Town of West Bath.
POND: Any inland body of water which has a surface area in excess of ten (10) acres,
except where such body of water is manmade and in addition is surrounded by land
held by a single owner, and except those privately owned ponds which are held
primarily as waterfowl and fish breeding areas for hunting and fishing.
POTABLE: Safe for drinking as defined by the US Environmental Protection
Agency's (EPA) Drinking Water Standards and Health Advisories Table and Maine's
interim drinking water standards for six different perfluoroalkyl and polyfluoroalkyl
substances (PFAS). Resolve 2021 Chater 82, Resolve, To Protect Consumers of
Public Drinking Water by Establishing Maximum Contaminant Level for Certain
Substances and Contaminants.
PRELIMINARY SUBDVISION PLAN: The preliminary drawings indicate the proposed
layout of the subdivision to be submitted to the Board for its consideration.
PRIMARY STRUCTURE: Shoreline structures such as piers, docks, wharves,
breakwaters, causeways, marinas, bridges, or similar structures extending below the
normal high water line into or over a waterbody.
PRINCIPAL STRUCTURE: A structure in which the main or primary use of the
structure is conducted. For purposes of this rule, principal structure does not include
commercial buildings.
164
PROFESSIONAL OFFICE: Room or rooms whose principal use is as a space for a
person or persons offering a service which requires specialized knowledge such as
an architect, engineer, insurance agent, lawyer, realtor, or similar occupation and
where no merchandise is sold.
RE-SUBDIVISION: The division of an existing subdivision or any change in the plan
for an approved subdivision which affects the lot lines, including land transactions by
the sub- divider not indicated on the approved land.
RESTRICTIVE COVENANT: A provision in a deed, or other covenant conveying real
property, restricting the use of the land.
ROAD: A route or track consisting of a bed of exposed mineral soil, gravel, asphalt,
or other surfacing material constructed for or created by the repeated passage of
motorized vehicles.
Private ROADS. Privately built and maintained right-of-way providing access to
two (2) or more properties.
SECONDARY STRUCTURE: Any structure located on a primary structure.
SETBACK: The minimum horizontal distance between a structure or other applicable
entity and a boundary, road centerline, body of water or wetland.
SETBACK REQUIREMENTS: The minimum horizontal distance from a lot line,
shoreline, or road to the nearest part of a structure, or other regulated object or area
as defined in local ordinance.
SHARED DRIVEWAY: A traveled way providing access to two (2) abutting lots from
a private or public road -- the shared portion of which is located at the boundary
between the lots.
SHORE FRONTAGE: The length of a lot bordering on a water body or wetland
measured in a straight line between the intersections of the lot lines with the shoreline.
SHORE SETBACK: The nearest horizontal distance from the normal high-water line
of a water body or tributary stream, or upland edge of a wetland, to the nearest part
of a structure,, road,, parking space or other regulated object or area.
SINGLE-FAMILY DWELLING UNIT: A structure containing one (1) dwelling unit
SPECIAL INDUSTRIAL AND TRANSPORTATION USES: Industrial manufacturing
and construction process and service uses and transportation and distribution service
uses requiring special ordinance provisions governing isolation and screening for
reasons of safety and/or inconsistency with other uses and restriction to an overlay
zone. Such uses may involve bulk hazardous substances, other hazardous
165
substances, significant exterior structures, processing, storage, and parking and also
frequent or heavy truck or rail service. Bulk Hazardous Substance Uses, as defined
and listed in Article III, section 3.13 of this Land Use Ordinance and trucking terminals
are examples of Special Industrial and Transportation Uses.
STREAM: In the Shoreland Overlay Zone, a free-flowing body of water from the outlet
of a great pond or the confluence of two (2) perennial streams as depicted on the most
recent edition of a United States Geological Survey 7.5 minute series topographical
map, or if not available, a 15-minute series topographic map, to the point where the
body of water becomes a river or flows to another water body or wetland within the
Shoreland Overlay Zone.
STREET: Public and private ways such as highways, roads, and other rights-of-way,
as well as areas on subdivision plans design as rights-of-way.
Major STREETS. The term "Major STREETS" includes ARTERIAL STREETS
which serve primarily as major traffic ways for travel between and through towns;
and Collector STREETS, which serve as feeders to ARTERIAL STREETS, as
collectors of traffic from minor STREETS and for circulation and access in
commercial and industrial areas.
Minor STREETS. Local STREETS which are used primarily for access to
abutting residential, commercial or industrial properties.
STRUCTURE: Anything temporarily or permanently located, built, constructed or
erected for the support, shelter or enclosure of persons as defined in 38 M.R.S. §436-
A(12).
STRUCTURE HAVING NEGLIGIBLE VOLUME: A structure or portion thereof,
principally two dimensional in nature, whose use does not utilize any of its volume,
such as exterior stairs, a deck supported by an open framework, or an impermeable
slab on the ground.
STRUCTURE HAVING OPEN VOLUME: A structure or portion thereof whose use
utilizes the volume bounded by its structure, but which is always open to the weather,
such as a screened porch.
STRUCTURE HAVING ENCLOSED VOLUME: A structure or a portion thereof
whose use utilizes the volume bounded by its structure, but which can be closed to
the weather, such as a room.
SUBDIVISION: The division of a tract or parcel of land into three (3) or more lots
within any five (5) year period, which period begins on or after September 23, 1972,
whether accomplished by sale, lease, development, buildings,, or otherwise. The term
"subdivision"" also includes the division of a new structure or structures on a tract or
parcel of land into five (5) or more DWELLING UNITS within a five (5) year period,
the construction or placement of five (5) or more dwelling units on a single tract or
166
parcel of land and the division of any existing structure or structures previously used
for commercial or industrial use into five (5) or more dwelling units within a five (5)
year period. Leased dwelling units as well as owner-occupied dwelling units, including
condominium units shall be counted as lots
A.
In determining whether a tract or parcel of land is divided into three (3) or
more lots, the first dividing of the tract or parcel is considered to create the first
two (2) lots and the next dividing of either of the first two (2) lots, by whomever
accomplished, is considered to create a third (3rd) lot, unless:
1. Both dividings are accomplished by a sub-divider who has retained
one (1) of the lots for the sub-divider's own use as a single-family
residence that has been the sub-divider's principal residence for a
period of at least five (5) years immediately preceding the second (2nd)
division; or
2. The division of the tract or parcel is otherwise exempt from this
ordinance.
B. The dividing of a tract or parcel of land and the lot or lots so made, which
dividing or lots when made are not subject to this ordinance, do not become
subject to this ordinance by the subsequent dividing of that tract or parcel of
land or any portion of that tract or parcel. The Planning Board shall consider
the existence of the previously created lot or lots in reviewing a proposed
subdivision created by a subsequent dividing.
C. A lot of 40 or more acres shall be counted as a lot, whether or not all or part of
the parcel of land being divided is located within any shoreland area as defined
in Title 38, Section 435, or the Town's shoreland zoning.
1. A division accomplished by devise does not create a lot or lots for the
purpose of this definition, unless the intent of the transferor is to avoid
the objectives of this ordinance or the Title 30-A M.R.S.A. Section 4401
et seq.
. 2. A division accomplished by condemnation does not create a lot or lots
for the purposes of this definition, unless the intent of the transferor is
to avoid the objectives of this ordinance or the Title 30-A M.R.S.A.,
Section 4401 et seq.
. 3. A division accomplished by order of court does not create a lot or lots
for the purposes of this definition, unless the intent of the transferor is
to avoid the objectives of this Ordinance or the Title 30-A M.R.S.A.,
Section 4401 et seq.
4. A division accomplished by gift to a person related to the donor of an
167
interest in property held by the donor for a continuous period of five (5)
years prior to the division by gift does not create a lot or lots for the
purposes of this definition, unless the intent of the transferor is to avoid
the objectives of this Ordinance or the Title 30-A M.R.S.A. Section
4401 et seq. If the real estate exempt under this paragraph is
transferred within 5 years to another person not related to the donor of
the exempt real estate as provided in this paragraph, then the
previously exempt division creates a LOT or LOTS for the purposes of
this subsection. "PERSON related to the donor" means a spouse,
parent, grandparent, brother, sister, child, or grandchild related by
blood, marriage or adoption. A gift under this paragraph cannot be
given for consideration that is more than 1/2 the assessed value of the
real estate.
5. A division accomplished by a gift to a municipality if that municipality
accepts the gift does not create a lot or lots for the purposes of this
definition, unless the intent of the transferor is to avoid the objectives
of this Ordinance or the Title 30-A M.R.S.A., Section 4401 et seq.
6. A division accomplished by the transfer of any interest in land to the
owners of abutting land that does not create a separate lot shall not
be considered to create a lot or lots for the purposes of this definition,
unless the intent of the transferor is to avoid the objectives of this
Ordinance or the Title 30-A M.R.S.A., Section 4401 et seq. If the real
estate exempt under this paragraph is transferred within 5 years to
another PERSON without all of the merged land, then the previously
exempt division shall be deemed to create a a lot or lots for the
purpose of this subsection.
D.
The division of a tract or parcel of land into 3 or more lots and upon each
of which lots permanent dwelling structures legally existed before
September 23, 1971 is not a subdvision.
E. In determining the number of dwelling units in a structure, the provisions
regarding the determination of the number of lots shall apply including
exemptions from the definition of a subdivision of land.
F. Notwithstanding the provisions of this subsection, leased dwelling units
are not subject to subdivision review if the Planning Board has determined
that the units are otherwise subject to Town review at least as stringent as that
required under this ordinance.
G. The grant of a bona fide security interest in an entire lot that has been
exempted from the definition of subdivision under paragraphs C.1. to C.6., or
subsequent transfer of that entire lot by the original holder of the security
interest or that person's successor in interest, does not create a lot for the
168
purposes of this definition, unless the intent of the transferor is to avoid the
objectives of this Ordinance or the Title 30-A M.R.S.A. Section 4401 et seq.
For the purposes of the definition of a subdivision, a tract or parcel of land is
defined as all contiguous land in the same ownership, as defined below,
provided that lands located on opposite sides of a public or private road shall
be considered each a separate tract or parcel of land unless such road was
established by the owner of land on both sides thereof.
H.
The division of a structure into three (3) or more units, whether they are
commercial, industrial or dwelling units, or any combination thereof, within
a five (5) year period shall constitute a subdvision.
TEMPORARY ACCESSORY RESIDENTIAL UNIT: Secondary living quarters
contained within and subordinate to a single-family detached dwelling or accessory
structure on a lot that does not meet the minimum lot size requirement for more than
one dwelling unit, and occupied by the owner's relative (by blood, marriage, or
adoption), the owner's caregiver, or any other person who provides day-to-day
assistance to the owner.
TERRESTRIAL VEGETATION: Plants that grow along streams and wetland areas.
TIMBER HARVESTING: The cutting and removal of trees from their growing
site, and the attendant operation of cutting and skidding machinery. Timber
Harvesting does not include the clearing of land for approved construction or the
construction or creation of roads.
TRACT, LOT, OR PARCEL OF LAND: All contiguous land in the same ownership,
whether or not the tract is separated at any point by: an intermittent or non-navigable
stream, tidal waters where there is no flow at low tide, or a private road established
by the abutting land owners.
TRAVELED WAY: The portion of a right-of-way having a surface, paved or
otherwise, for vehicular traffic.
TRIBUTARY STREAM: A channel between defined banks created by the action of
surface water, which is characterized by the lack of terrestrial vegetation or by the
presence of a bed devoid of topsoil containing waterborne deposits on exposed soil,
parent material or bedrock, and which is connected hydrologically with other water
bodies. This definition does not include the term "stream" as defined elsewhere in this
Ordinance, and only applies to that portion of the tributary stream located within the
Shoreland Overlay Zone of the receiving water body or wetland. Note: Water setback
requirements apply to tributary streams within the shoreland zone.
UNDERSIZED LOT: A lot created that is smaller in size than the minimum at the time
of the lot's creation as given in the Minimum Lot Standards Table for the district in
which the lot is located, that does not or will not have any business unit or dwelling
169
unit located thereon and for which there is an annotated plot plan listing the approved
use of the lot and any Planning Board conditions recorded at the Registry of Deeds.
No variances may be granted for an Undersized Lot.
UPLAND EDGE: The boundary between upland and wetland.
VEHICULAR RIGHT-OF-WAY: The land, defined by metes and bounds or
otherwise so designated, within which a traveled way is located.
VOLUME OF A STRUCTURE: The total volume of a structure enclosed by roofs,
decks and fixed exterior walls as measured to the exterior faces of the latter or
projections thereof. The volumes of eves and other minor protuberances are excluded
from the calculation. Only account for the volume of an enclosed foundation,
basement or lowest floor that has a minimum floor to ceiling height of 6' feet. The
volume of said floor area shall be calculated by multiplying only the floor area which
has a minimum 6' feet height by its height, or average height if the heights vary.
WATER BODY: Any Great Pond, river, stream, tributary stream, or tidal area.
WATER CROSSING: Any project extending from one bank to the opposite bank of a
river or stream, whether under, through or over the water course. Such projects
include but may not be limited to roads,, fords, bridges, culverts, water lines, sewer
lines, and cables as well as maintenance work on these crossings.
WATERSHED OF A GREAT POND: For the purposes of these regulations, Great
Pond watershed boundaries shall be as delineated on the Town of West Bath Land
Use District and Overlay zone Map. Due to the scale of this map, there may be small
inaccuracies in the delineation of the watershed boundary.
WETLAND: A freshwater or coastal wetland.
WETLANDS ASSOCIATED WITH GREAT PONDS AND RIVERS: Wetlands
contiguous with or adjacent to a Great Pond or river, and which during normal high
water, are connected by surface water to the Great Pond or river. Also included are
wetlands, which are separated from the great pond or river by a berm, causeway, or
similar feature less than 100 feet in width, and which have a surface elevation at or
below the normal high water line of the Great Pond or river. Wetlands associated with
Great Ponds or rivers are considered to be part of that Great Pond or river.
ZONING ORDINANCE: A type of ordinance that divides a municipality into districts
and that prescribes and reasonably applies different regulations in each district.