Shoreland Zoning Rules
Activities in the shoreland zone in Whitefield is regulated by rules of the State of Maine,
Department of Environmental Protection. The Town does administer the rules.
A copy of the rule as is relevant to Whitefield is available for viewing at the Town Office, The
rule is dated August 7, 1994.
For a general information only a more recent copy of the shoreland zoning rule is available
online as the URL below. However, please be aware this version of the rule has been further
amended and the August 7, 1994 version is still applicable to activities in Whitefield.
STATE OF MAINE
GUIDELINES FOR MUNICIPAL .
~ SHORELAND ZONING
ORDINANCES .
06-096 Department of Environmental Protection |
Chapter 1000
- \IROW
= OI
ee : m
= Sine ~
S \3 3
"ATE ge ww
1] Adopted by the Board of Environmental Protection
Pursuant to 38 M.R.S.A. Section 438-A(1)
_ EFFECTIVE DATE: MARCH 24, 1990
AMENDED: JULY 14, 1992
AUGUST 7, 1994
PREFACE
The Mandatory Shoreland Zoning Act, 38 M.R.S.A., Section 435-449, requires all
municipalities to adopt, administer, and enforce ordinances which regulate land use activities
within 250 feet of great ponds, rivers, freshwater and coastal wetlands, and tidal waters;
and within 75 feet of streams as defined. The Act also requires the Board of Environmental
Protection to establish minimum guidelines for such ordinances. This document, adopted by
the Board on February 14, 1990 and amended July 14, 1992 and August 7, 1994, contains
those guidelines for municipal shoreland ordinances. The Act requires that municipalities
adopt shoreland zoning ordinances consistent with, or no less stringent than, those
minimum guidelines.
Municipalities need not adopt this guideline ordinance word for word. In fact, the
Department encourages municipalities to consider local planning documents and other
special local considerations, and to modify this ordinance into one that meets the needs of
the particular community. Municipalities may wish to adopt more stringent ordinances, or
ordinances which are completely different from the guidelines, provided that such
ordinances, are equally or more effective in achieving the purposes of the Act. In addition,
coastal communities must address the coastal management policies cited in 38 M.R.S.A.,
Section 1801.
When a municipality determines that special local conditions within portions of the shoreland
= zone require a different set of standards from those in the minimum guidelines, the
municipality shall document the special conditions and submit them, together with its
proposed ordinance provisions, to the Board for review and approval. No amendment to an
ordinance which effects the shoreland zone is valid without the approval of the
Commissioner of the Department.
Neither this "Preface" nor the "Notes" contained in this model ordinance are official parts of
the ordinance and should not be incorporated into a municipality's locally adopted ordinance.
The Preface and Notes are provided for explanatory purpose only.
Municipalities must be aware that in addition to the requirements of the Mandatory
Shoreland Zoning Act, the requirements of the Comprehensive Planning and Land Use
Regulation Act (30-A M.R.S.A., Chapter 1878, Sections 4312-4349 will be an integral part
of a municipality's overall strategy for managing future development. For example, parts of
a municipality's shoreland area may be designated as an area for growth while others will be
designated as rural or slow growth areas.
in many situations, the shoreland zoning ordinance will be an effective tool for implementing
the goals and policies of a municipality's comprehensive plan. A municipality may choose to
integrate the shoreland zoning requirements into a town-wide zoning ordinance or choose to
have a separate shoreland zoning ordinance. Regardless, the shoreland zoning provisions
should form an integrated approach to managing growth as well as fulfilling the
requirements of the Mandatory Shoreland Zoning Act.
For more information on the Growth Management Program, please contact your regional
- council or the Office of Comprehensive Planning, State House Station #130, Augusta, Maine
'04333.
For more information on the shoreland zoning law, please contact the Department of
Environmental Protection's Shoreland Zoning Unit, State House Station #17, Augusta,
« Maine 04333.
. TABLE OF CONTENTS
PAGE
Section 1. PUIPOSES........ccceccccceccccesseeeescetecsuacneeeeeesaseeseeeecnessessctsercseseneenees 1
Section 2. AUtNOT RY. ec ccc ecenstecee esses eeesensncnaeseneccueseseuareseasesaeeesesaes 1
Section 3. Applicability ...........0..0...2cceccecesceeeeccecececccnererececaceeneeseessentenseneneeees 1
: Section 4. Effective Date and Repeal of Formerly Adopted Ordinance.......... 1
Section 5. Availability................. .casssassssnessinaneossuasaaneecsncenanbcesnanniseastaoneonants 2
Section 6. SOVOraD ity... ce. cccennsoennndtensuaa suciaastastuccrtedtalsossecestiauxasooancssnaiats 2
Section 7. Conflicts with Other Ordinances. ............cccccecccsceceeceeeseeenerecteensens 2
Section 8. AMONAMEMS.............ccesccesecseecceesserceseressueeceseenesecenececescsecenseensess 2
Section 9. Districts and Zoning Mab..................::cccscseeescereeeseseeeeeeeeeeneneeeeneess 2
A. Official Shoreland Zoning Map.............c:::.:scceseceeceeeeeeeeeeeeseeteeeeeceees 2
B. Scale Of Map... cee eeeceecseresssececseseecaceseaseaseneressenerseseraressess 3
C. Certification of Official Shoreland Zoning Map.................-:cseeeseeee 3
D. Changes to the Official Shoreland Zoning Map...............22.:1ceecee 3
Section 10. Interpretation of District Boundaries. ...............:.cccceeccecesseseeceseseeeees 3
Section 11. Land Use Requirements....................:cccccesccececsesecsneeeseeeseeeseeteaeees 3
Section 12. Non-Conformance. ................eeececeeeceeeeceeseneree sie Dulesscounueenetiidenieeeay' +
A. PUIPOSE. ........seceeeeceeenececeeeeetsceeescereeeeeaceenetsescesaseesseseneseneesersereates 4
B. GON CL Al aszccaccanvesseseweneracosavenseristesnncasnncaseausesteosesussontenecseserrenvenstes 4
C. Non-conforming Structures...........-..ccccccseseseecesseesseeeseeeseeeserereneeeess 4
, D. Non-conforming USGS. ...........:ccscccceseeecesssseseeeessensceneeesesesseetaeseeese 6
E. Non-conforming Lots...............:.::csccsssesececessesseceesseceeceeeeseeeeeeeeseees 6
Section 13. Establishment of Districts.........000......ccccccceccceeeeeeeneeteeeeeeeaeeeeceees 7
A. Resource Protection District..............cccecceeeeseeeeeereeeeneeteeeeaeenee 7
B. Limited Residential District... ccc ceeccceeeeestesenteneeeeeeeees 8
CG. Limited Commercial District................cccsccssscesssssesseeeceseeeerneeeteneees 8
D. General Development District........0.......ceccccccsecseeeneceesereneeeeeeeeneee 9
E. Commercial Fisheries/Maritime Activities District...............-.---:-+- 9
F. Stream Protection District..................c.ccccsecscscsceceeeececeeseceensseenreeees 10
Section 14. Table of Land US@S.. sccssiisssiascaecsicascensaavecesancessssaeecanascess sentventtien 10
Section 15 Land Use Standards...............::c:ccccsecescceeneceeceeceessercesaeeesenseceasees 13
A. Minimum Lot Standards. ............-...:cccsssscsecensceesenceeeeeeereeseseneenerees 13
B. Principal and Accessory Structures. ...............eeccceceeeeesseeereceeeeeeees 14
C. Piers, Docks, Wharves, Bridges and Other Structures and Uses
Extending Over or Beyond the Normal High-Water Line of a
Waterbody or Within a Wetland... ......222...2...0.ccecccceee settee eeeeeeeee 15
D. CAMPQFOUNs. ........... ee ceeeaceeeceeeeeeeeeecneseetenveseecseeenseeseseesseeesseeentees 16
E. Individual Private Campsites.................-.c:ses:ecsseceeceeseseseseaeesesneneers 16
F, Commercial and Industrial Uses..........2........2-:-ecsseceeeeeeeeeeeeseeeneees 17
G. Parking APr@as..........:cccccsesscssesssceeeceeseceeesseeeneceneaersrereeeeeeecerersearess 17
H. Roads and DrivewayS. .............:cccscceeceeseeseeeesescesneneeeeeseneeeseeeeeees 17
J. Storm Water Runoff....................22ccccecceeccnseeesecneeeeseeeceeeeceeeneeeeeeess 20
K. Septic Waste Disposall.................cccccsccesccesceeseeeeeceseseeeeseeeeeeeeaeenentes 20
L. Essential Services.............c.cecceseeececeeseesneseessenerenseeeeeesteeseeeeeeensecee 20
7 M. Mineral Exploration and Extraction. ...............:.c:cccceecceeeseseteseeeeeeeenee 21
N. AQTICUILLIIE......-accoreencerrerssesennerensnensnecerenenaneseceqacssssonssossssuatinessousiie 22
O. Timber Harvesting. ...........-..ss.ccceseceeesesseereeseneeereseeeeeecoatersntersnnnenss 22
P. Clearing of Vegetation for Development............---.-..1--:ssceerreereree 24
Q, Erosion and Sedimentation Comntrol.............-ccccsscsecesnneteeeeeseeeenenneees 26
R. SOI S secceswccassssdansarewacsaxscecscccananapaustrwedeneonseapecensievsesscomme oes s mmayaeess 27
S. Water Quality... ee eesseestenneeesecnseeeetecessteasetsaenenansinenees 27 .
T. Archaeological Sites... .ccececccceseeceeeneceeeessecesceeeseeeeceseeestnees 27
Section 16. Administration. ............cccccccccsessscsseececceceseessteneceeeeneceeeesssesenseeseoeers 27
A. Administering Bodies and Agemts................-:--:ssereceseneeeeesereeeresees 27
B. Permits! REQUIPEC -<rsnsnssnnesmencconmasemueenvessmensenasmeennemeeaenens 28
C. Permit Application. sssssssssssssveceecaceassenszecsrmsnmencaverseaneesavsennareeersees 28
D. Procedure for Administering Permits. ..............:.::::-scesseeeeeseeneeeeees 28
E. Special Exceptions. scasisscssvscstotesswersscvessinesssctatnoeacacvresnssannestarenss 29
F. Expiration Of Perimiit....rssccoscsscsanssesaspdsvssucegacoanssasceapsdsesesacestacetaes 30.--C
G. Installation of Public Utility Service..............-.--:-csccceeeeeeereeereeeeeeees 30
H. ADDGAIGS............0..00+000++2.28ye eta onnansanenenentenisnconeteennenmesrmummercopiersss 30
I. Enforcemennt........... ..wiacssadccsesancasasswarcenisessesacssanovanscncasesensannsneenss 33
Section 17. DetiNiIONS....0.....0........00..cascscawaseonswansasnaascenstcersenssnscnaseceasisdstcasnees 34
NOTE: The Board of Environmental Protection recognizes that many municipalities have
developed and adopted comprehensive land use ordinances for all land areas
within their respective communities. Those ordinances may or may not follow a
similar format to this guideline ordinance. it is not the intent of the Board to
impose this guideline ordinance on a municipality which, within its land use
codes, has otherwise met the intent and purposes of the Mandatory Shoreland
Zoning Act and this guideline ordinance.
Whether or not municipalities choose to integrate their shoreland zoning
requirements into a townwide zoning ordinance, it is important to develop a
comprehensive and coordinated strategy for managing and guiding growth in the
shoreland area.
L&W/RBPRETA
Shoreland Zoning Ordinance for the Municipality of
Section 1. Purposes
The purposes of this Ordinance are to further the maintenance of safe and healthful conditions; to
prevent and control water pollution; to protect fish spawning grounds, aquatic life, bird and other
wildlife habitat; to protect buildings and lands from flooding and accelerated erosion; to protect
archaeological and historic resources; to protect commercial fishing and maritime industries; to protect
freshwater and coastal wetlands; to control building sites, placement of structures and land uses; to
conserve shore cover, and visual as well as actual points of access to inland and coastal waters; to
conserve natural beauty and open space; and to anticipate and respond to the impacts of development
in shoreland areas.
Section 2. Authority
This Ordinance has been prepared in accordance with the provisions of Title 38 Sections 435-449 of
the Maine Revised Statutes Annotated (M.R.S.A.).
Section 3. Applicability
This Ordinance applies to all land areas within 250 feet, horizontal distance, of the normal high-water
line of any great pond, river or saltwater body; within 250 feet, horizontal distance, of the upland
edge of a coastal or freshwater wetland; and within 75 feet, horizontal distance, of the normal
high-water line of a stream. This Ordinance also applies to any structure built on, over or abutting a
dock, wharf or pier, or other structure extending or located beyond the normal high-water line of a
water body or within a wetland.
NOTE: Municipalities may choose not to regulate structures built on, over or abutting a dock, wharf,
pier or other structure extending beyond the normal high-water line of a water body or within
a wetland.
NOTE: Pursuant to Title 38, Section 440, municipalities may extend or adopt zoning controls beyond
the limits established in this section in order to protect the public health, safety, and welfare
' and to avoid problems associated with flood plain development.
Section 4. Effective Date and Repeal of Formerly Adopted Ordinance
This Ordinance, which was adopted by the municipal legislative body on
, shall not be effective unless approved by the Commissioner of the
Department of Environmental Protection. A certified copy of the Ordinance, attested and signed by _
the Municipal Clerk, shall be forwarded to the Commissioner for approval. If the Commissioner fails
to act on this Ordinance within forty-five (45) days of his/her receipt of the Ordinance, it shall be
automatically approved. Upon approval of this Ordinance, the shoreland zoning ordinance previously
adopted on is hereby repealed.
Any application for a permit submitted to the municipality within the forty-five (45) day period shall
be governed by the terms of this Ordinance if the Ordinance is approved by the Commissioner.
4
Section 5. Availability
A certified copy of this Ordinance shall be filed with the Municipal Clerk and shall be accessible to
any member of the public. Copies shall be made available to the public at reasonable cost at the
expense of the person making the request. Notice of availability of this Ordinance shall be posted.
. Section 6. Severability
Should any section or provision of this Ordinance be declared by the courts to be invalid, such
decision shall not invalidate any other section or provision of the Ordinance.
Section 7. Conflicts with Other Ordinances
Whenever a provision of this Ordinance conflicts with or is inconsistent with another provision of this
Ordinance or of any other ordinance, regulation or statute, the more restrictive provision shall
control.
Section 8. Amendments
This Ordinance may be amended by majority vote of the legislative body. Copies of amendments,
attested and signed by the Municipal Clerk, shall be submitted to the Commissioner of the Department
of Environmental Protection following adoption by the municipal legislative body and shall not be
effective unless approved by the Commissioner. If the Commissioner fails to act on any amendmen'
within forty-five (45) days of his/her receipt of the amendment, the amendment is automatically
approved. Any application for a permit submitted to the municipality within the forty-five (45) day
period shall be governed by the terms of the amendment, if such amendment is approved by the
Commissioner.
Section 9. Districts and Zoning Map
A. Official Shoreland Zoning Map
The areas to which this Ordinance is applicable are hereby divided into the following districts as
shown on the Official Shoreland Zoning Map(s) which is (are) made a part of this Ordinance:
1. Resource Protection
2. Limited Residential
, 3. Limited Commercial
4. General Development *
5. Commercial Fisheries/Maritime Activities
' 6. Stream Protection
"NOTE: The development of a waterfront management strategy can be a complex process. There are
many different techniques that can be used to tailor an ordinance to reflect local goals and
resources. The Commercial Fisheries/Maritime Activities (CFMA) District included in these
; Guidelines is one approach which is based on allowing as permitted uses only those uses
which are functionally water-dependent. But other zoning variations are also possible which
may be much more specific about what types of functionally water dependent uses should be
« permitted, make use of more than one type of waterfront district, may include standards for
2
assessing the impact of proposed development on water dependent uses, and may include
specific provisions to encourage certain types of public benefits.
The Department of Environmental Protection has developed one example of a more elaborate
ordinance, which is available as a technical supplement to this model ordinance. There are
many other sources of information available to assist with the design of this type of
ordinance. The Maine Department of Economic and Community Development's Office of
Comprehensive Planning and your regional planning council should be consulted for
additional assistance.
B. Scale of Map
The Official Shoreland Zoning Map shall be drawn at a scale of not less than: 1 inch = 2000 feet.
District boundaries shall be clearly delineated and a legend indicating the symbols for each district
shall be placed on the map.
NOTE: Because of map scale or other reason, a municipality may have a series of maps depicting its
shoreland zone.
C. Certification of Official Shoreland Zoning Map
The Official Shoreland Zoning Map shall be certified by the attested signature of the Municipal Clerk
and shall be located in the municipal office. In the event the municipality does not have a municipal
office, the Municipal Clerk shal] be the custodian of the map.
D. Changes to the Official Shoreland Zoning Map
If amendments, in accordance with Section 8, are made in the district boundaries or other matter
portrayed on the Official Shoreland Zoning Map, such changes shall be made on the Official
Shoreland Zoning Map within thirty (30) days after the amendment has been approved by the
Commissioner of the Department of Environmental Protection.
Section 10. Interpretation of District Boundaries
Unless otherwise set forth on the Official Shoreland Zoning Map, district boundary lines are property
__ lines, the centerlines of streets, roads and rights of way, and the boundaries of the shoreland area as
defined herein. Where uncertainty exists as to the exact location of district boundary lines, the Board
of Appeals shall be the final authority as to location.
NOTE: Municipalities are encouraged to incorporate specific written descriptions of district
boundaries into the Ordinance so that disputes over district boundaries are minimized.
Section 11. Land Use Requirements
Except as hereinafter specified, no building, structure or land shall hereafter be used or occupied, and
no building or structure or part thereof shall hereafter be erected, constructed, expanded, moved, or
altered and no new lot shall be created except in conformity with all of the regulations herein specified
« for the district in which it is located, unless a variance is granted.
3
Section 12. Non-conformance
A. Purpose
It is the intent of this Ordinance to promote land use conformities, except that non-conforming
conditions that existed before the effective date of this Ordinance shall be allowed to continue, subject
to the requirements set forth in this section.
B. General
1. Transfer of Ownership: Non-conforming structures, lots, and uses may be transferred, and
the new owner may continue the non-conforming use or continue to use the
non-conforming structure or lot, subject to the provisions of this Ordinance.
2. Repair and Maintenance: This Ordinance allows, without a permit, the normal upkeep and
maintenance of non-conforming uses and structures including repairs or renovations which
do not involve expansion of the non-conforming use or structure, and such other changes in
a non-conforming use or structure as federal, state, or local building and safety codes may
require.
NOTE: See Section 17 for the definitions of non-conforming structures, non-conforming uses and
non-conforming lots.
C. Non-conforming Structures
1. Expansions: A non-conforming structure may be added to or expanded after obtaining a
permit from the same permitting authority as that for a new structure, if such addition or
expansion does not increase the non-conformity of the. structure.
Further Limitations:
a. After January 1, 1989 if any portion of a structure is less than the required setback from
the normal high-water line of a water body or upland edge of a wetland, that portion of
the structure shall not be expanded in floor area or volume, by 30% or more, during the
lifetime of the structure.
b. Construction or enlargement of a foundation beneath the existing structure shall not be
considered an expansion of the structure provided; that the structure and new foundation
are placed such that the setback requirement is met to the greatest practical extent as
determined by the Planning Board, basing its decision on the criteria specified in
subsection 2. Relocation, below; that the completed foundation does not extend beyond
the exterior dimensions of the structure; and that the foundation does not cause the
structure to be elevated by more than three (3) additional feet.
c. No structure which is less than the required setback from the normal high-water line of a
water body, tributary stream, or upland edge of a wetland shall be expanded toward the
¢ water body, tributary stream, or wetland.
4
2. Relocation: A non-conforming structure may be relocated within the boundaries of the parcel
on which the structure is located provided that the site of relocation conforms to all setback
requirements to the greatest practical extent as determined by the Planning Board, and
provided that the applicant demonstrates that the present subsurface sewage disposal system
meets the requirements of State law and the State of Maine Subsurface Wastewater Disposal
Rules (Rules), or that a new system can be installed in compliance with the law and said
Rules. In no case shall a structure be relocated in a manner that causes the structure to be
more non-conforming.
In determining whether the building relocation meets the setback to the greatest practical
extent, the Planning Board shall consider the size of the lot, the slope of the land, the
potential for soil erosion, the location of other structures on the property and on adjacent
properties, the location of the septic system and other on-site soils suitable for septic systems,
and the type and amount of vegetation to be removed to accomplish the relocation.
3. Reconstruction or Replacement: Any non-conforming structure which is located less than the
required setback from the normal high-water line of a water body, tributary stream, or
upland edge of a wetland and which is removed, or damaged or destroyed by more than 50%
of the market value of the structure before such damage, destruction or removal, may be
reconstructed or replaced provided that a permit is obtained within one year of the date of
said damage, destruction, or removal, and provided that such reconstruction or replacement
- is in compliance with the water setback requirement to the greatest practical extent as
determined by the Planning Board in accordance with the purposes of this Ordinance. In no
case shall a structure be reconstructed or replaced so as to increase its non-conformity.
Any non-conforming structure which is damaged or destroyed by 50% or less of the market
value of the structure, excluding normal maintenance and repair, may be reconstructed in
place with a permit, from the code enforcement officer.
In determining whether the building reconstruction or replacement meets the water setback to
the greatest practical extent the Planning Board shall consider in addition to the criteria in
paragraph 2 above, the physical condition and type of foundation present, if any.
4. Change of Use of a Non-conforming Structure
The use of a non-conforming structure may not be changed to another use unless the Planning
Board after receiving a written application determines that the new use will have no greater
adverse impact on the water body or wetland, or on the subject or adjacent properties and
resources than the existing use.
In determining that no greater adverse impact will occur, the Planriing Board shall require
written documentation from the applicant, regarding the probable effects on public health and
safety, erosion and sedimentation, water quality, fish and wildlife habitat, vegetative cover,
visual and actual points of public access to waters, natural beauty, flood plain management,
archaeological and historic resources, and commercial fishing and maritime activities, and
other functionally water-dependent uses.
«
5
D. Non-conforming Uses
1. Expansions: Expansions of non-conforming uses are prohibited, except that non-conforming
residential uses may, after obtaining a permit from the Planning Board, be expanded within
existing residential structures or within expansions of such structures as permitted in Section
12(C)(1)(a) above.
2. Resumption Prohibited: A lot, building or structure in or on which a non-conforming use is
discontinued for a period exceeding one year, or which is superseded by a conforming use,
may not again be devoted to a non-conforming use except that the Planning Board may, for
good cause shown by the applicant, grant up to a one year extension to that time period.
This provision shall not apply to the resumption of a use of a residential structure provided
that the structure has been used or maintained for residential purposes during the preceding
five (5) year period. ,
3. Change of Use: An existing non-conforming use may be changed to another non-conforming
use provided that the proposed use has no greater adverse impact on the subject and adjacent
properties and resources, including water dependent uses in the CFMA district, than the
former use, as determined by the Planning Board. The determination of no greater adverse
. impact shall be made according to criteria listed in Section 12 (C) (4) above.
E. Non-conforming Lots
1. Non-conforming Lots: A non-conforming lot of record as of the effective date of this
Ordinance or amendment thereto may be built upon, without the need for a variance,
provided that such lot is in separate ownership and not contiguous with any other lot in the
same ownership, and that all provisions of this Ordinance except lot size and frontage can be
met. Variances relating to setback or other requirements not involving lot size or. frontage
shall be obtained by action of the Board of Appeals.
2. Contiguous Built Lots: If two or more contiguous lots or parcels are in a single or joint
ownership of record at the time of adoption of this Ordinance, if all or part of the lots do not
meet the dimensional requirements of this Ordinance, and if a principal use or structure exists
on each lot, the non-conforming lots may be conveyed separately or together, provided that
the State Minimum Lot Size Law and Subsurface Wastewater Disposal Rules are complied
'with.
If two or more principal uses or structures existed on'a single lot of record on the effective
date of this ordinance, each may be sold on a separate lot provided that the above referenced
law and rules are complied with. When such lots are divided each lot thus created must be as
conforming as possible to the dimensional requirements of this Ordinance.
3. Contiguous Lots - Vacant or Partially Built: If two or more contiguous lots or parcels are in
single or joint ownership of record at the time of or since adoption or amendment of this
Ordinance, if any of these lots do not individually meet the dimensional requirements of this
( Ordinance or subsequent amendments, and if one or more of the lots are vacant or contain no
= principal structure the lots shall be combined to the extent necessary to meet the dimensional
requirements. .
6
This provision shall not apply to 2 or more contiguous lots, at least one of which is
nonconforming, owned by the same person or persons on the effective date of this Ordinance
and recorded in the registry of deeds if the lot is served by a public sewer or can |
accommodate a subsurface sewage disposal system in conformance with the State of Maine
Subsurface Wastewater Disposal Rules, and:
a. Each lot contains at least 100 feet of shore frontage and at least 20,000 square feet of lot
area; or
b. Any lots that do not meet the frontage and lot size requirements of subparagraph a. are
reconfigured or combined so that each new lot contains at least 100 feet of shore
frontage and 20,000 square feet of Jot area.
Section 13. Establishment of Districts
A. Resource Protection District
The Resource Protection District includes areas in which development would adversely affect water
quality, productive habitat, biological ecosystems, or scenic and natural values. This district shall
include the following areas when they occur within the limits of the shoreland zone, exclusive of the
Stream Protection District, except that areas which are currently developed and areas which meet the
criteria for the Limited Commercial, General Development, or Commercial Fisheries/Maritime
Activities Districts need not be included within the Resource Protection District.
1. Areas within 250 feet, horizontal distance, of the upland edge of freshwater wetlands, salt
marshes and salt meadows, and wetlands associated with great ponds and rivers, which are
rated "moderate" or "high" value by the Maine Department of Inland Fisheries and Wildlife
(MDIF&W) as of January 1, 1973.
NOTE: The Natural Resources Protection Act, Title 38 Sections 480-A through 480-S, requires the
Department of Environmental Protection to designate areas of "significant wildlife habitat".
Significant wildlife habitat includes: .
Habitat for species appearing on the official state or federal lists of endangered or threatened
species; high and moderate value deer wintering areas and travel corridors as defined by the
Department of Inland Fisheries and Wildlife; high and moderate value waterfowl] and wading
bird habitats, including nesting and feeding areas as defined by the Department of Inland
Fisheries and Wildlife; critical spawning and nursery areas for Atlantic sea run salmon as
defined by the Atlantic Sea Run Salmon Commission; and shorebird nesting, feeding and
staging areas and seabird nesting islands as defined by the Department of Inland Fisheries
and Wildlife.
As these areas are mapped and development standards are established, municipalities should
incorporate such areas and standards into their locally adopted ordinances.
«
7
2. Flood plains along rivers and flood plains along artificially formed great ponds along rivers,
defined by the 100 year flood plain as designated on the Federal Emergency Management
Agency's (FEMA) Flood Insurance Rate Maps or Flood Hazard Boundary Maps, or the
flood of record, or in the absence of these, by soil types identified as recent flood plain
soils. This district shall also include 100 year flood plains adjacent to tidal waters as shown
on FEMA's Flood Insurance Rate Maps or Flood Hazard Boundary Maps.
3. Areas of two or more contiguous acres with sustained slopes of 20% or greater.
4, Areas of two (2) or more contiguous acres supporting wetland vegetation and hydric soils,
which are not part of a freshwater or coastal wetland as defined, and which are not
surficially connected to a water body during normal spring high water.
5. Land areas along rivers subject to severe bank erosion, undercutting, or river bed movement
and lands adjacent to tidal waters which are subject to severe erosion or mass movement,
such as steep coastal bluffs.
NOTE: Municipalities may also include the following other areas which have been recommended for
protection in the comprehensive plan of the municipality such as:
A. Other important wildlife habitat;
B. Natural sites of significant scenic or esthetic value;
C. Areas designated by federal, state or municipal governments as natural areas of
significance to be protected from development; and
D. Other significant areas which should be included in this district to fulfill the purposes of
this Ordinance, such as, but not limited to, existing public access areas and certain
significant archaeological and historic sites deserving of long-term protection as
determined by the municipality after consultation with the Maine Historic Preservation
Commission.
B. Limited Residential District
The Limited Residential District includes those areas suitable for residential and recreational
development. It includes areas other than those in the Resource Protection District, or Stream
Protection District, and areas which are used less intensively than those in the Limited
Commercial District, the General: Development District, or the Commercial Fisheries/Maritime
Activities District.
C. Limited Commercial District
The Limited Commercial District includes areas of mixed, light commercial and residential uses,
exclusive of the Stream Protection District, which should not be developed as intensively as the
General Development District. This district includes areas of two or more contiguous acres in
( size devoted to a mix of residential and low intensity business and commercial uses. Industrial
: uses are prohibited. .
8
D. General Development District
The General Development District includes the following types of areas:
1. Areas of two or more contiguous acres devoted to commercial, industrial or intensive
recreational activities, or a mix of such activities, including but not limited to the following:
a. Areas devoted to manufacturing, fabricating or
other industrial activities;
b. Areas devoted to wholesaling, warehousing, retail ;
trade and service activities, or other commercial
activities; and
c. Areas devoted to intensive recreational development .
and activities, such as, but not limited to
amusement parks, race tracks and fairgrounds.
2. Areas otherwise discernable as having patterns of intensive commercial, industrial or
recreational uses.
Portions of the General Development District may also include residential development.
However, no area shall be designated as a General Development District based solely on
residential use.
In areas adjacent to great ponds classified GPA and adjacent to rivers flowing to great ponds
classified GPA, the designation of an area as a General Development District shall be based
upon uses existing at the time of adoption of this Ordinance. There shall be no newly
established General Development Districts or expansions in area of existing General
Development Districts adjacent to great ponds classified GPA, and adjacent to rivers which
_ flow to great ponds classified GPA.
NOTE: _ See definition of "great pond classified GPA" in Section 17.
'E. Commercial Fisheries/Maritime Activities District
The Commercial Fisheries/Maritime Activities District includes areas where the existing
predominant pattern of development is consistent with the allowed uses for this district as
indicated in the Table of Land Uses, Section 14, and other areas which are suitable for
functionally water-dependent uses, taking into consideration such factors as:
1. Shelter from prevailing winds and waves;
2. Slope of the land within 250 feet, horizontal distance, of the normal high-water line;
3. Depth of the water within 150 feet, horizontal distance, of the shoreline;
( 4. Available support facilities including utilities and transportation facilities; and
x 5. Compatibility with adjacent upland uses.
9
NOTE: A municipality may opt to identify one or more CFMA Districts, each of which may be as small
as a single parcel, provided that the municipality includes in this district or combination of
CFMA districts, all land currently occupied by or suitable for active water dependent uses,
taking into consideration the above-listed factors.
F. Stream Protection District
The Stream Protection District includes all land areas within seventy-five (75) feet, horizontal
distance, of the normal high-water line of a stream, exclusive of those areas within two-hundred
and fifty (250) feet, horizontal distance, of the normal high-water line of a great pond, river or
saltwater body, or within two hundred and fifty (250) feet, horizontal distance, of the upland
edge of a freshwater or coastal wetland. Where a stream and its associated shoreland area is
located within two-hundred and fifty (250) feet, horizontal distance, of the above water bodies or
wetlands, that land area shall be regulated under the terms of the shoreland district associated
with that water body or wetland.
Section 14. Table of Land Uses
All land use activities, as indicated in Table 1, Land Uses in the Shoreland Zone, shall conform with
all of the applicable land use standards in Section 15. The district designation for a particular site
shall be determined from the Official Shoreland Zoning Map.
Key to Table 1:
Yes - Allowed (no permit required but the use must comply with
all applicable land use standards.)
No - Prohibited
PB - Requires permit issued by the Planning Board
CEO - Requires permit issued by the Code Enforcement Officer
LPI - Requires permit issued by the Local Plumbing Inspector
Abbreviations:
RP - Resource Protection
LR - Limited Residential
LC - Limited Commercial
GD - General Development
"os CFMA - Commercial Fisheries/Maritime Activities
SP - Stream Protection
(
10
. The following notes are applicable to the Land Uses Table on the following page:
NOTE: The term "functionally water-dependent use" as defined, includes a very diverse group of
uses ranging from large, industrial facilities that receive shipments by water or use water for
cooling, to traditional commercial fishing enterprises, and public shorefront parks.
Communities are encouraged to define the functionally water-dependent uses which are to be
permitted and which are prohibited in each CFMA district, based on considerations of
prevailing existing uses, desired future uses, available support facilities, site suitability and
compatibility with adjacent uses. A municipality can narrow the range of permitted uses by
precluding certain functionally water-dependent uses, or by adopting conditional uses for
certain functionally water-dependent uses that it determines would only be compatible with its
plan for the waterfront under certain conditions.
NOTE: Recreational water-dependent uses such as marinas and excursion vessels may in some
communities displace or threaten to displace traditional commercial fisheries and maritime
activities. Therefore communities may wish to preclude or further limit these types of uses
in this district in order to protect berthing space and onshore staging areas for commercial
fishing enterprises.
«
ay
TABLE 1. LAND USES IN THE SHORELAND ZONE
LAND USES DISTRICT
SP RP tk soLe GD Crew
1. Non-intensive recreational uses not requiring structures such as
hunting, fishing and hiking yes yes yes yes yes yes
2. Motorized vehicular traftic on existing roads and trails yes yes yes yes yes yes
3._ Forest management activities except for timber harvesting yes yes yes yes yes yes
4, Timber harvesting yes CEO yes yes yes yes
5._Clearing of vegetation for approved construction and other allowed uses CEO CEO yes yes yes yes
6. Fire prevention activities yes yes yes yes yes yes
7._Wildlife management practices yes yes yes yes yes yes
8. Soil and Water conservation practices yes yes yes yes yes yes
9. Mineral exploration no yes yes yes yes yes
10. Mineral extraction including sand and gravel extraction no PB PB PB PB PB
11. Surveying and resource analysis yes yes yes yes yes yes
12. Emergency Operations yes yes yes yes yes yes
13. Agriculture yes PB yes yes yes yes
14. Aquaculture PB PB PB yes yes yes
15. Principal structures and uses
A._One and two family residential ppt _ pp? CEO _CEO _CEO___no
B. Multi-unit residential no no PB PB PB no
Cc. Commercial no no no PB PB PB"
D. Industrial no no no no PB PB>
E. Govermmental and Institutional no no no PB PB PB?
F. Small non-residential facilities for educational, scientific, or nature interpretation pp PB CEO CEO CEO PB?
16. Structures accessory to allowed uses PBa PB CEO CEO yes yes
17. Piers, docks, wharfs, bridges and other structures and uses extending over or below
the normal high-water line or within a wetland
a Temporary CEO CEO CEO CEO CEO CEO
b. Permanent PB PB PB PB PB ro
18. Conversions of seasonal residences to year-round residences LPI LPI LPI LPI LPi KR
*9. Home occupations PB no PB CEO yes yes
1. Private sewage disposal systems for allowed uses LPI LPI LPI LPI LPI LPI
21. Essential services PB PB PB PB PB PB
22. Service drops, as defined, to allowed uses yes yes yes yes yes ves
23. Public and private recreational areas involving minimal structural development PB PB PB CEO CEO CE
24. Individual, private campsites CEO CEO CEO CEO CEO CEO
25, Campgrounds no no PB PB PB no
26. Road & driveway construction PB no PB PB PB PB
27. Parking facilities no no PB PB PB PB
28. Marinas PB no PB PB PB PB
29. Filling and earth moving of <10 cubic yards CEO CEO yes yes yes yes
30. Filling and earth moving of >10 cubic yards . PB PB CEO CEO CEO CEO
31, Signs yes yes yes yes yes yes
32. Uses similar to allowed uses CEO CEO CEO CEO CEO CEO
33, Uses similar to uses requiring a CEO permit CEO CEO CEO CEO CEO CEO
34. Uses similar to uses requiring a PB permit PB PB PB PB PB PB
Mn RP not permitted within 75 feet of the normal high-water line of great ponds, except to remove safety hazards.
*Requires permit from the Code Enforcement Officer if more than 100 square feet of surface area, In total, Is disturbed.
3in RP not permitted In areas so designated because of wildilie value, . .
'provided that a variance trom the setback requirament Is abtalned from the Board of Appeals.
Sunctionally water-dependent uses and uses accessory to such water dependent uses only (See note an previous page).
5See turther restrictions In Section 15(L)(2) on page 20.
TExcept when area is zoned for resource protection duc to flood plain criteria in which case a permit is required from the PB.
Sexcept to provide access to permitted uses within the district, or where no reasonable alternative route or location is available outside the RP
area, in which case a permit is required from the PB.
Ssingle family residential structures may be allowed by special exception only according to the provisions of Section 16E, Special Exceptions.
Two-family residential structures are prohibited.
NOTE: A person performing any of the following activities shall require a permit from the Department of Environmental Protection, pursuant to
Title 38 M.RS.A,, Section 480-C, if the activity occurs in, on, over or adjacent to any freshwater or coastal wetland, great pond, river, stream or
.>rook and operates in such a manner that material or soil may be washed into them:
« )A. Dredging. bulldozing. removing or displacing soil, sand, vegetation or other materials;
-- B. Draining or otherwise dewatering;
. © Filling, including adding sand or other material to a sand dune; or
D. Any construction or alteration of any permanent structure.
LRBZONE
12
vection 15.° Land Use Standards
NOTE: Municipalities should review the land use standards contained herein to determine
whether they will result in a scale of development that is compatible with existing
development or with the future desired scale of development. If not, more restrictive
land use standards may be adopted by the municipality.
All land use activities within the shoreland zone shall conform with the following provisions, if
applicable.
A. Minimum Lot Standards
1.
Minimum Lot Area Minimum Shore
(sq. ft.) Frontage (ft.)
Residential per dwelling unit
a. Within the Shoreland Zone .
Adjacent to Tidal Areas 30,000 150
Within the Shoreland Zone
Adjacent to Non-Tidal Areas 40,000 200
Governmental, Institutional, Commercial or Industrial per principal structure
a. Within the Shoreland Zone
Adjacent to Tidal Areas Exclusive
of Those Areas Zoned for
Commercial Fisheries and Maritime
Activities 40,000 200
b. Within the Shoreland Zone Adjacent to
Tidal Areas Zoned for Commercial Fisheries
~ and Maritime Activities NONE NONE
Cc. Within the Shoreland Zone Adjacent to
Non-tidal Areas : 60,000 300
Public and Private Recreational Facilities
a. Within the Shoreland Zone Adjacent to
Tidal and Non-Tidal Areas 40,000 200
13
2. Land below the normal high-water line of a water body or upland edge of a wetland and lar
beneath roads serving more than two (2) lots shall not be included toward calculating minimw
lot area.
3. Lots located on opposite sides of a public or private road shall be considered each a separate trac
° or parcel of land unless such road was established by the owner of land on both sides thereo:
after September 22, 1971.
4. The minimum width of any portion of any lot within one hundred (100) feet, horizontal distance,
of the normal high-water line of a water body or upland edge of a wetland shall be equal to or
greater than the shore frontage requirement for a lot with the proposed use.
5. If more than one residential dwelling unit or more than one principal commercial or industrial
structure is constructed on a single parcel, all dimensional requirements shall be met for each
additional dwelling unit or principal structure.
NOTE: Municipalities may include provisions for clustered housing within the shoreland zone provided
that the overall dimensional requirements, including frontage and lot area per dwelling unit are
met. When determining whether dimensional requirements are met, only land area within the
shoreland zone shall be considered.
B. Principal and Accessory Structures
1. All new principal and accessory structures shall be set back at least one hundred (100) feet from
the normal high-water line of great ponds classified GPA and rivers that flow to great ponds
classified GPA, and seventy-five (75) feet from the normal high-water line of other water bodies,
tributary streams, or the upland edge of a wetland, except that in the General Development
District the setback from the normal high-water line shall be at least twenty-five (25) feet, and in
the Commercial Fisheries/Maritime Activities District there shall be no minimum setback.
In addition:
a. The water body or wetland setback provision shall neither apply to structures which require
direct access to the water as an operational necessity, such as piers, docks and retaining
walls, nor to other functionally water-dependent uses.
b. All principal structures along Significant River Segments as listed in Title 38 M.R.S.A.,
-.- Section 437, shall be set back a minimum of one hundred and twenty-five (125) feet from the
normal high-water line and shall be screened from the river by existing vegetation. This
provision does not apply to structures related to hydropower facilities.
*NOTE: A municipality may within its ordinance, authorize the Planning Board.to increase the required
setback of a proposed structure, as a condition to permit approval, if necessary to accomplish the
purposes of this ordinance. Instances where a greater setback may be appropriate include, but
not be limited to, areas of steep slope; shallow or erodible soils; or where an adequate vegetative
buffer does not exist.
14
2. Principal or accessory structures and expansions of existing structures which are permitted in the
Resource Protection, Limited Residential, Limited Commercial, and Stream Protection Districts,
Shall not exceed thirty-five (35) feet in height. This provision shall not apply to structures such
as transmission towers, windmills, antennas, and similar structures having no floor area.
3. The first floor elevation or openings of all buildings and structures including basements shall be
elevated at least one foot above the elevation of the 100 year flood, the flood of record, or in the
absence of these, the flood as defined by soil types identified as recent flood plain soils.
4. The total area of all structures, parking lots and other non-vegetated surfaces, within the
shoreland zone shall not exceed twenty (20) percent of the lot or a portion there of, located
within the shoreland zone, including land area previously developed, except in the General
Development District adjacent to tidal waters and rivers which do not flow to great ponds
classified GPA, and in the Commercial Fisheries/Maritime Activities District, where lot coverage
shall not exceed seventy (70) percent.
5. Notwithstanding the requirements stated above, stairways or similar structures may be allowed .
with a permit from the Code Enforcement Officer, to provide shoreline access in areas of steep
slopes or unstable soils provided; that the structure is limited to a maximum of four (4) feet in
width; that the structure does not extend below or over the normal high-water line of a water
body or upland edge of a wetland, (unless permitted by the Department of Environmental
Protection pursuant to the Natural Resources Protection Act, Title 38, Section 480-C); and that
_ the applicant demonstrates that no reasonable access alternative exists on the property.
C. Piers, Docks, Wharfs, Bridges and Other Structures and Uses Extending Over or Beyond the Normal
High-Water Line of a Water Body or Within a Wetland.
1. Access from shore shal] be developed on soils appropriate for such use and constructed so as
to control erosion.
2. The location shall not interfere with existing developed or natural beach areas.
3. The facility shall be located so as to minimize adverse effects on fisheries.
4. The facility shall be no larger in dimension than necessary to carry on the activity and be
consistent with existing conditions, use, and character of the area.
5. No new structure shall be built on, over or abutting a pier, wharf, dock or other structure
extending beyond the normal high-water line of a water body or within a wetland unless the
structure requires direct access to the water as an operational necessity.
6. No existing structures built on, over or abutting a pier, dock, wharf or other structure
extending beyond the normal high-water line of a water body or within a wetland shall be
converted to residential dwelling units in any district.
7. Except in the General Development District and Commercial Fisheries/Maritime Activities
District, structures built on, over or abutting a pier, wharf, dock or other structure extending
( beyond the normal high-water line of a water body or within a wetland shall not exceed
twenty (20) feet in height above the pier, wharf, dock or other structure.
15
NOTE: Permanent structures projecting into or over water bodies shall require a permit from the
Department of Environmental Protection pursuant to the Natural Resources Protection Act, Title
38 M.R.S.A., Section 480-C.
D. Campgrounds
Campgrounds shall conform to the minimum requirements imposed under State licensing procedures
and the following:
1. Campgrounds shall contain a minimum of five thousand (5,000) square feet of land, not including
roads and driveways, for each site. Land supporting wetland vegetation, and land below the
normal high-water line of a water body shall not be included in calculating land area per Site.
2. The areas intended for placement of a recreational vehicle, tent or shelter, and utility and service
buildings shall be set back a minimum of one hundred (100) feet from the normal high-water
line of a great pond classified GPA or a river flowing to a great pond classified GPA, and
seventy-five (75) feet from the normal high-water line of other water bodies, tributary streams,
or the upland edge of a wetland.
E. Individual Private Campsites
Individual, private campsites not associated with campgrounds are permitted provided the following
conditions are met:
1. One campsite per lot existing on the effective date of this Ordinance, or thirty thousand (30,000)
square feet of lot area within the shoreland zone, whichever is less, may be permitted.
2. Campsite placement on any lot, including the area intended for a recreational vehicle or tent
platform, shall be set back one hundred (100) feet from the normal high-water line of a great
pond classified GPA or river flowing to a great pond classified GPA, and seventy-five (75) feet
from the normal high-water line of other water bodies, tributary streams, or the upland edge of a
_ wetland. :
3. Recreational vehicles shall not be located on any type of permanent foundation except for a
gravel pad, and no structure(s) except canopies shall be attached to the recreational vehicle.
4. The clearing of vegetation for the siting of the recreational vehicle, tent or similar shelter in a
Resource Protection District shall be limited to one thousand (1000) square feet.
5. A written sewage disposal plan describing the proposed method and location of sewage disposal
shall be required for each campsite and shall be approved by the Local Plumbing Inspector.
Where disposal is off-site, written authorization from the receiving facility or land owner is
required.
6. When a recreational vehicle, tent or similar shelter is placed on-site for more than one hundred
f and twenty (120) days per year, all requirements for residential structures shall be met, including
: the installation of a subsurface sewage disposal system in compliance with the State of Maine
Subsurface Wastewater Disposal Rules unless served by public sewage facilities.
16
Commercial and Industrial Uses
The following new commercial and industrial uses are prohibited within the shoreland zone adjacent
to great ponds classified GPA, and rivers and streams which flow to great ponds classified GPA:
a. Auto washing facilities
b. Auto or other vehicle service and/or repair operations, including body shops
c. Chemical and bacteriological laboratories
d. Storage of chemicals, including herbicides, pesticides or fertilizers other than amounts normally
associated with individual households or farms
e. Commercial painting, wood preserving, and furniture stripping
f. Dry cleaning establishments
g. Electronic circuit assembly
h. Laundromats, unless connected to a sanitary sewer
i. Metal plating, finishing, or polishing
j- Petroleum or petroleum product storage and/or sale except storage on same property as use occurs
and except for storage and sales associated with marinas
k. Photographic processing
1. Printing
G. Parking Areas
1. Parking areas shall meet the shoreline setback requirements for structures for the district in which
such areas are located, except that in the Commercial Fisheries/Maritime Activities District
parking areas shall be set back at least twenty-five (25) feet from the normal high-water line or
the upland edge of a wetland. The setback requirement for parking areas serving public boat
launching facilities, in Districts other than the General Development and Commercial
Fisheries/Maritime Activities Districts may be reduced to no less than fifty (50) feet from the
normal high-water line or upland edge of a wetland if the Planning Board finds that no other
reasonable alternative exists.
_2. Parking areas shall be adequately sized for the proposed use and shall be designed to prevent
stormwater runoff from flowing directly into a water body, and where feasible, to retain all
runoff on-site.
3. In determining the appropriate size of proposed parking facilities, the following shall apply:
a. Typical parking space: Approximately ten (10) feet wide and twenty (20) feet long, except
that parking spaces for a vehicle and boat trailer shall be forty (40) feet long.
b. Internal travel aisles: Approximately twenty (20) feet wide.
H. Roads and Driveways
The following standards shall apply to the construction of roads and/or driveways and drainage
( systems, culverts and other related features.
: 1. Roads and driveways shall be set back at least one-hundred (100) feet from the normal high-water
17
line of a great pond classified GPA or a river that flows to a great pond classified GPA, and
seventy-five (75) feet from the normal high-water line of other water bodies, tributary steams, or
the upland edge of a wetland unless no reasonable alternative exists as determined by the
Planning Board. If no other reasonable alternative exists, the Planning Board may reduce the
road and/or driveway setback requirement to no less than fifty (50) feet upon clear showing by
the applicant that appropriate techniques will be used to prevent sedimentation of the water body.
Such techniques may include, but are not limited to, the installation of settling basins, and/or the
effective use of additional ditch relief culverts and turnouts placed so as to avoid sedimentation of
the water body, tributary stream, or wetland.
On slopes of greater than twenty (20) percent the road and/or driveway setback shall be increased
by ten (10) feet for each five (5) percent increase in slope above twenty (20) percent.
This paragraph shall neither apply to approaches to water crossings nor to roads or driveways
that provide access to permitted structures, and facilities located nearer to the shoreline due to an
operational necessity.
2. Existing public roads may be expanded within the legal road right-of-way regardless of its
setback from a water body.
3. New permanent roads are not permitted within the shoreland zone along Significant River
Segments except:
a. To provide access to structures or facilities within the zone; or
b. The applicant demonstrates that no reasonable alternative route exists outside the shoreland
zone. When roads must be located within the shoreland zone they shall be set back as far as
practicable from the normal high-water line and screened from the river by existing
vegetation.
4. New roads and driveways are prohibited in a Resource Protection District except to provide
access to permitted uses within the district, or as approved by the Planning Board upon a finding
that no reasonable alternative route or location is available outside the district, in which case the
road and/or driveway shall be set back as far as practicable from the normal high-water line of a
. water body, tributary stream, or upland edge of a wetland.
5. Road banks shall be no steeper than a slope of two (2) horizontal to one (1) vertical, and shall be
graded and stabilized in accordance with the provisions for erosion and sedimentation control
contained in subsection Q.
6. Road grades shall be no greater than ten (10) percent except for short segments of less than two
hundred (200) feet.
7. In order to prevent road surface drainage from directly entering water bodies, roads shall be
designed, constructed, and maintained to empty onto an unscarified buffer strip at least (50) feet
plus two times the average slope, in width between the outflow point of the ditch or culvert and
( the normal high-water line of a water body, tributary stream, or upland edge of a wetland. Road
surface drainage which is directed to an unscarified buffer strip shall be diffused or spread out to
18
promote infiltration of the runoff and to minimize channelized flow of the drainage through the
buffer strip.
8. Ditch relief (cross drainage) culverts, drainage dips and water turnouts shal] be installed in a
manner effective in directing drainage onto unscarified buffer strips before the flow in the road or
ditches gains sufficient volume or head to erode the road or ditch. To accomplish this, the
following shall apply:
a. Ditch relief culverts, drainage dips and associated water turnouts shall be spaced along the
road at intervals no greater than indicated in the following table:
Road Grade Spacing
(Percent) (Feet)
0-2 250
3-5 200-135
6-10 100-80
11-15 80-60
16-20 60-45
21+ 40
b. Drainage dips may be used in place of ditch relief culverts only where the road grade is ten
(10) percent or less.
c. Onroad sections having slopes greater than ten (10) percent, ditch relief culverts shall be
placed across the road at approximately a thirty (30) degree angle downslope from a line
perpendicular to the centerline of the road. "
d. Ditch relief culverts shall be sufficiently sized and properly installed in order to allow for
effective functioning, and their. inlet and outlet.ends shall be stabilized with appropriate
materials.
9. Ditches, culverts, bridges, dips, water turnouts and other storm water runoff control installations
associated with roads shall be maintained on a regular basis to assure effective functioning.
The following provisions shall govern the use of signs in the Resource Protection, Stream Protection,
Limited Residential and Limited Commercial Districts:
1. Signs and billboards relating to goods and services sold on the premises shall be permitted,
.provided that such signs shall not exceed six (6) square feet in area and shall not exceed two (2)
signs per premises. Billboards and signs relating to goods or services not sold or rendered on
"the premises shall be prohibited.
2. Name signs shall be permitted, provided such signs shall not exceed two (2) signs per premises.
19
3. Residential users may display a single sign not over three (3) square feet in area relating to the
sale, rental, or lease of the premises.
4, Signs relating to trespassing and hunting shall be permitted without restriction as to number
provided that no such sign shall exceed two (2) square feet in area.
5. Signs relating to public safety shall be permitted without restriction.
6. No sign shall extend higher than twenty (20) feet above the ground.
7, Signs may be illuminated only by shielded, non-flashing lights.
J. Storm Water Runoff
1. All new construction and development shall be designed to minimize storm water runoff from the
site in excess of the natural predevelopment conditions. Where possible, existing natural runoff
control features, such as berms, swales, terraces and wooded areas shall be retained in order to
reduce runoff and encourage infiltration of stormwaters.
2. Storm water runoff control systems shall be maintained as necessary to ensure proper
functioning.
K. Septic Waste Disposal
1. All subsurface sewage disposal systems shall be installed in conformance with the State of Maine
Subsurface Wastewater Disposal Rules (Rules).
NOTE: The Rules, among other requirements, include:
a. The minimum setback for new subsurface sewage disposal systems, shall be no less than one
hundred (100) horizontal feet from the normal high-water line of a perennial water body.
The minimum setback distances from water bodies for new subsurface sewage disposal
systems shall not be reduced by variance.
b. Replacement systems shall meet the standards for replacement systems as contained in the
Rules.
L. Essential Services
1.. Where feasible, the installation of essential services shall be limited to existing public ways and
. existing service corridors.
2. The installation of essential services is not permitted in a Resource Protection or Stream
Protection District, except to provide services to a permitted use within said district, or except
where the applicant demonstrates that no reasonable alternative exists. Where permitted, such
structures and facilities shall be located so as to minimize any adverse impacts on surrounding
uses and resources, including visual impacts.
20
4. Mineral Exploration and Extraction
Mineral exploration to determine the nature or extent of mineral resources shall be accomplished by
hand sampling, test boring, or other methods which create minimal disturbance of less than one
hundred (100) square feet of ground surface. A permit from the Code Enforcement Officer shall be
required for mineral exploration which exceeds the above limitation. All excavations, including test
pits and holes shall be immediately capped, filled or secured by other equally effective measures, so as
to restore disturbed areas and to protect the public health and safety.
Mineral extraction may be permitted under the following conditions:
1. A reclamation plan shall be filed with, and approved by the Planning Board before a permit is
granted. Such plan shall describe in detail procedures to be undertaken to fulfill the requirements
of paragraph 4 below.
2. Unless authorized pursuant to the Natural Resources Protection Act, Title 38, M.R.S.A, Section
480-C no part of any extraction operation, including drainage and runoff control features shall be
permitted within one hundred (100) feet of the normal high-water line of a great pond classified
GPA or a river flowing to a great pond classified GPA, and within seventy-five (75) feet of the
normal high-water line of any other water body, tributary stream, or the upland edge of a
wetland. Extraction operations shall not be permitted within seventy-five (75) feet of any
property line, without written permission of the owner of such adjacent property.
3. Developers of new gravel pits along Significant River Segments shall demonstrate that no
reasonable mining site outside the shoreland zone exists. When gravel pits must be located
within the zone, they shall be set back as far as practicable from the normal high-water line and
no less than seventy-five (75) feet and screened from the river by existing vegetation.
4. Within twelve (12) months following the completion of extraction operations at any extraction
site, which operations shall be deemed complete when less than one hundred (100) cubic yards of
materials are removed in any consecutive twelve (12) month period, ground levels and grades
shall be established in accordance with the following:
a. All debris, stumps, and similar material shall be removed for disposal in an approved
location, or shall be buried on-site. Only materials generated on-site may be buried or
covered on-site.
NOTE: The State of Maine Solid Waste Laws, Title 38, Maine Revised Statutes Annotated, Section 1310
and Chapter 404-of the Department of Environmental Protection's regulations may contain other
applicable provisions regarding disposal of such materials.
b. The final graded slope shall be two to one (2:1) slope or flatter.
c. Top soil or loam shall be retained to cover all disturbed land areas, which shall be reseeded
and stabilized with vegetation native to the area. Additional topsoil or loam shall be
obtained from off-site sources if necessary to complete the stabilization project.
( 5. In keeping with the purposes of this Ordinance, the Planning Board may impose such conditions
as are necessary to minimize the adverse impacts associated with mineral extraction operations on
21
surrounding uses and resources.
N. Agriculture
1. All spreading or disposal of manure shall be accomplished in conformance with the Maine
Guidelines for Manure and Manure Sludge Disposal on Land published by the University of
Maine Soil and Water Conservation Commission in July, 1972.
2. Manure shall not be stored or stockpiled within one hundred (100) feet, horizontal distance, of a
great pond classified GPA or a river flowing to a great pond, classified GPA, or within
seventy-five (75) feet horizontal distance, of other water bodies, tributary streams, or wetlands.
Within five (5) years of the effective date of this ordinance all manure storage areas within the
shoreland zone must be constructed or modified such that the facility produces no discharge of
effluent or contaminated storm water. [Existing facilities which do not meet the setback
requirement may remain, but must meet the no discharge provision within the above five (5S) year
period. .
3. Agricultural activities involving tillage of soil greater than forty thousand (40,000) square feet in
surface area, or the spreading, disposal or storage of manure within the shoreland zone shall
require a Soil and Water Conservation Plan to be filed with the Planning Board.
Non-conformance with the provisions of said plan shall be considered to be a violation of this
Ordinance.
NOTE: Assistance in preparing a soil and water conservation plan may be available through the local
Soil and Water Conservation District office.
4. There shall be no new tilling of soil within one-hundred (100) feet, horizontal distance, of the
normal high-water line of a great pond classified GPA; within seventy-five (75) feet, horizontal
distance, from other water bodies; nor within twenty-five feet, horizontal distance, of tributary
streams, and wetlands. Operations in existence on the effective date of this ordinance and not in
conformance with this provision may be maintained.
5. After the effective date of this Ordinance, newly established livestock grazing areas shall not be
permitted within one hundred (100) feet, horizontal distance, of the normal high-water line of a
great pond classified GPA; within seventy-five (75) feet, horizontal distance of other water
bodies, nor; within twenty-five (25) feet, horizontal distance, of tributary streams, and wetlands.
Livestock grazing associated with ongoing farm activities, and which are not in conformance
with the above setback provisions may continue, provided that such grazing is conducted in
accordance with a Soil and Water Conservation Plan.
O. Timber Harvesting
1. Inashoreland area zoned for resource protection abutting a great pond, timber harvesting shall
be limited to the following: :
a. Within the strip of land extending 75 feet inland from the normal high-water line there shall
r be no timber harvesting, except to remove safety hazards.
22
b. Beyond the 75 foot "no-harvest" strip referred to in paragraph a. above, timber harvesting is
permitted in accordance with paragraph 2 below except that in no case shall the average
residual basal area of trees over 1 inch in diameter at 4 1/2 feet above ground level be
reduced to less than 30 square feet per acre.
2. Except in areas as described in Paragraph 1 above, timber harvesting shall conform with the
following provisions:
a. Selective cutting of no more than forty (40) percent of the total volume of trees four (4)
inches or more in diameter measured at 4 1/2 feet above ground level on any lot in any ten
(10) year period is permitted. In addition: ;
i. Within one-hundred (100) feet, horizontal distance of the normal high-water line of a
great pond classified GPA or a river flowing to a great pond classified GPA, and
within seventy-five (75) feet, horizontal distance, of the normal high-water line of other
water bodies, tributary streams, or the upland edge of a wetland, there shall be no
clearcut openings and a well-distributed stand of trees and other vegetation, including
existing ground cover, shall be maintained.
ii. At distances greater than one-hundred (100) feet, horizontal distance, of a great pond
classified GPA or a river flowing to a great pond classified GPA, and greater than
seventy-five (75) feet, horizontal distance, of the normal high-water line of other water
bodies or the upland edge of a wetland, harvesting operations shall not create single
clearcut openings greater than ten-thousand (10,000) square feet in the forest canopy.
Where such openings exceed five-thousand (5000) square feet they shall be at least one
hundred (100) feet apart. Such clearcut openings shall be included in the calculation of
total volume removal. For the purposes of these standards volume may be considered
to be equivalent to basal area.
b. Timber harvesting operations exceeding the 40% limitation in paragraph a. above, may be
allowed by the planning board upon a clear showing, including a forest management plan
signed by a Maine licensed professional forester, that such an exception is necessary for
_ good forest management and will be carried out in accordance with the purposes of this
Ordinance. The planning board shall notify the Commissioner of the Department of
Environmental Protection of each exception allowed, within fourteen (14) days of the
planning board's decision.
| c. No accumulation of slash shall be left within fifty (50) feet of the normal high-water line of
a water body. In all other areas.slash shall. either be removed or disposed of in such a
manner that it lies on the ground and no part thereof extends more than four (4) feet above
the ground. Any debris that falls below the normal high-water line of a water body shall
be removed.
d. Timber harvesting equipment shall not use stream channels as travel routes except when:
i. Surface waters are frozen; and
y ii. The activity will not result in any ground disturbance.
23
e. All crossings of flowing water shall require a bridge or culvert, except in areas with low
banks and channel beds which are composed of gravel, rock or similar hard surface which
would not be eroded or otherwise damaged.
f. Skid trail approaches to water crossings shall be located and designed so as to prevent
water runoff from directly entering the water body or tributary stream. Upon completion
of timber harvesting, temporary bridges and culverts shall be removed and areas of
exposed soil revegetated.
g. Except for water crossings, skid trails and other sites where the operation of machinery
used in timber harvesting results in the exposure of mineral soil shall be located such that
an unscarified strip of vegetation of at least seventy-five (75) feet in width for slopes up to
ten (10) percent shall be retained between the exposed mineral soil and: the normal
high-water line of a water body or upland edge of a wetland. For each ten (10) percent
increase in slope, the unscarified strip shall be increased by twenty (20) feet. The
provisions of this paragraph apply only to a face sloping toward the water body or wetland,
provided, however, that no portion of such exposed mineral soil on a back face shall be
closer than twenty five (25) feet from the normal high-water line of a water body or upland
edge of a wetland.
P. Clearing of Vegetation for Development
1. Within a shoreland area zoned for Resource Protection abutting a great pond, there shall be no
cutting of vegetation within the strip of land extending 75 feet, horizontal distance, inland from
the normal high-water line, except to remove safety hazards.
Elsewhere, in any Resource Protection District the clearing of vegetation shall be limited to that
. which is necessary for uses expressly authorized in that district.
2. Except in areas as described in Paragraph 1, above, and except to allow for the development of
permitted uses, within a strip of land extending one-hundred (100) feet, horizontal distance,
inland from the normal high-water line of a great pond classified GPA or a river flowing to a
great pond classified GPA, and seventy-five (75) feet, horizontal distance, from any other water
body, tributary stream, or the upland edge of a wetland, a buffer strip of vegetation shall be
preserved as follows:
a. There shall be no cleared opening greater than 250 square feet in the forest canopy as
measured from the outer limits of the tree crown. However, a footpath not to exceed ten
(10) feet in width as measured between tree trunks is permitted provided that a cleared line
of sight to the water through the buffer strip is not created. Adjacent to a great pond
classified GPA, or stream or river flowing to a great pond classified GPA, the width of the
foot path shall be limited to six (6) feet.
b. Selective cutting of trees within the buffer strip is permitted provided that a well distributed
stand of trees and other vegetation is maintained. For the purposes of this section a
"well-distributed stand of trees and other vegetation" adjacent to a great pond classified
GPA or a river or stream flowing to a great pond classified GPA, shall be defined as -
6 maintaining a rating score of 12 or more in any 25-foot by 25-foot square (625 square feet)
area as determined by the following rating system.
24
Diameter of Tree at 4-1/2 feet Above Ground Level (inches) Points
2-4 in. ]
>4 - 12 in. 2
> 12 in. 4
Adjacent to other water bodies, tributary streams, and wetlands, a "well-distributed stand of trees and
. other vegetation" is defined as maintaining a minimum rating score of 8 per 25-foot square area.
Note: As an example, adjacent to a great pond, if a 25-foot x 25-foot plot contains three (3) trees
between 2 and 4 inches in diameter, three trees between 4 and 12 inches in diameter, and
three trees over 12 inches in diameter, the rating score is:
(3x1) + (3x2) + x4) = 21 points
Thus, the 25-foot by 25-foot plot contains trees worth 21 points. Trees totaling 9 points
(21 - 12 = 9) may be removed from the plot provided that no cleared openings are
created.
Notwithstanding the above provisions, no more than 40% of the total volume of trees four (4) inches or
more in diameter, measured at 4 1/2 feet above ground level may be removed in any ten (10) year
period.
c. In order to protect water quality and wildlife habitat, adjacent to great ponds classified GPA, and
streams and rivers which flow to great ponds classified GPA, existing vegetation under three (3)
feet in height and other ground cover shall not be removed, except to provide for a footpath or
other permitted uses as described in paragraphs 2 and 2a. above.
d. Pruning of tree branches, on the bottom 1/3 of the tree is permitted.
e. In order to maintain a buffer strip of vegetation, when the removal of storm-damaged, diseased,
unsafe, or dead trees results in the creation of cleared openings, these openings shall be replanted
with native tree species unless existing new tree growth is present.
The provisions contained in paragraph 2 above shall not apply to those portions of public recreational
facilities adjacent to public swimming areas. Cleared areas, however, shall be limited to the minimum
area necessary.
« 33 At distances greater than one hundred (100) feet, horizontal distance, from a great pond
classified GPA or a river flowing to a great pond classified. GPA, and seventy-five (75) feet,
horizontal distance, from the normal high-water line of any other water body, tributary stream,
or the upland edge of a wetland, except to allow for the development of permitted uses, there
shall be permitted on any lot, in any ten (10) year period, selective cutting of not more than
forty (40) percent of the volume of trees four (4) inches or more in diameter, measured 4 1/2
feet above ground level. Tree removal in conjunction with the development of permitted uses
shall be included in the forty (40) percent calculation. For the purposes of these standards
volume may be considered to be equivalent to basal area.
In no event shall cleared openings for development, including but not limited to, principal and
r accessory structures, driveways and sewage disposal areas, exceed in the aggregate, 25% of the
25
lot area or ten thousand (10,000) square feet, whichever is greater, including land previously
developed. This provision shall not apply to the General Development or Commercial
Fisheries/Maritime Activities District.
4. Cleared openings legally in existence on the effective date of this Ordinance may be maintained,
but shall not be enlarged, except as permitted by this Ordinance.
5. Fields which have reverted to primarily shrubs, trees, or other woody vegetation shall be
regulated under the provisions of this section.
Q. Erosion and Sedimentation Control
1. Ail activities which involve filling, grading, excavation or other similar activities which result in
unstabilized soil conditions and which require a permit shall require a written soil erosion and
sedimentation control plan. The plan shall be submitted to the permitting authority for approval
and shail include, where applicable, provisions for:
a. Mulching and revegetation of disturbed soil.
b. Temporary runoff control features such as hay bales, silt fencing or diversion ditches.
c. Permanent stabilization structures such as retaining walls or riprap.
2. In order to create the least potential for erosion, development shall be designed to fit with the
topography and soils of the site. Areas of steep slopes where high cuts and fills may be required
shall be avoided wherever possible, and natural contours shall be followed as closely as possible.
3. Erosion and sedimentation control measures shall apply to all aspects of the proposed project
involving land disturbance, and shall be in operation during all stages of the activity. The
- amount of exposed soil at every phase of construction shall be minimized to reduce the potential
for erosion.
4. Any exposed ground area shall be temporarily or permanently stabilized within one (1) week
from the time it was last actively worked, by use of riprap, sod, seed, and mulch, or other
effective measures. In all cases permanent stabilization shall occur within nine (9) months of the
initial date of exposure. In addition:
. a. Where mulch is used, it shall be applied at a rate of at least one (1) bale per five hundred
(500) square feet and shall be maintained until a catch of vegetation is established.
b. Anchoring the mulch with netting, peg and twine or other suitable method may be required to
maintain the mulch cover.
. c. Additional measures shall be taken where necessary in order to avoid siltation into the water.
Such measures may include the use of staked hay bales and/or silt fences.
5. Natural and man-made drainage ways and drainage outlets shall be protected from erosion from +
water flowing through them. Drainageways shall be designed and constructed in order to carry
( water from a twenty five (25) year storm or greater, and shall be stabilized with vegetation or
26
lined with rip-rap.
R. Soils
All land uses shall be located on soils in or upon which the proposed uses or structures can be
established or maintained without causing adverse environmental impacts, including severe erosion,
mass soil movement, improper drainage, and water pollution, whether during or after construction.
Proposed uses requiring subsurface waste disposal, and commercial or industrial development and
other similar intensive land uses, shall require a soils report based on an on-site investigation and be
; prepared by state-certified professionals. Certified persons may include Maine Certified Soil
Scientists, Maine Registered Professional Engineers, Maine State Certified Geologists and other
persons who have training and experience in the recognition and evaluation of soil properties. The
report shall be based upon the analysis of the characteristics of the soil and surrounding land and
water areas, maximum ground water elevation, presence of ledge, drainage conditions, and other
pertinent data which the evaluator deems appropriate. The soils report shall include recommendations
for a proposed use to counteract soil limitations where they exist.
S. Water Quality
No activity shall deposit on or into the ground or discharge to the waters of the State any pollutant
that, by itself or in combination with other activities or substances will impair designated uses or the
water Classification of the water body.
T. Archaeological Sites
Any proposed land use activity involving structural development or soil disturbance on or adjacent to
sites listed on, or eligible to be listed on the National Register of Historic Places, as determined by the
permitting authority shall be submitted by the applicant to the Maine Historic Preservation
Commission for review and comment, at least twenty (20) days prior to action being taken by the
permitting authority. The permitting authority shall consider comments received from the
Commission prior to rendering a decision on the application.
Note: Municipal officials should contact the Maine Historic Preservation Commission for the listing
and location of Historic Places in their community.
Section 16. Administration
A. Administering Bodies and Agents
1. Code Enforcement Officer
A Code Enforcement Officer shall be appointed or reappointed annually by July ist.
2. Board of Appeals
A Board of Appeals shall be created in accordance with the provisions of Title 30-A Section
2691. °
27
3. Planning Board
A Planning Board shall be created in accordance with the provisions of State law.
B. Permits Required
After the effective date of this Ordinance no person shall, without first obtaining a permit,
engage in any activity or use of land or structure requiring a permit in the district in which such
activity or use would occur; or expand, change, or replace an existing use or structure; or renew
a discontinued nonconforming use.
A permit is not required for the replacement of an existing road culvert as long as:
1. The replacement culvert is not more than 25% longer than the culvert being replaced;
2. The replacement culvert is not longer than 75 feet; and
3. Adequate erosion control measures are taken to prevent sedimentation of the water, and the
crossing does not block fish passage in the water course.
C. Permit Application
1. Every applicant for a permit shall submit a written application, including a scaled site plan,
on a form provided by the municipality, to the appropriate official as indicated in Section 14.
2. All applications shall be signed by the owner or owners of the property or other person
authorizing the work, certifying 'that the information in the application is complete and
correct. If the person signing the application is not the owner or lessee of the property then
that person shall submit a letter of authorization from the owner or lessee.
3. All applications shall be dated, and the Code Enforcement Officer or Planning Board, as
appropriate, shall note upon each application the date and time of its receipt.
4. Ifthe property is not served by a public sewer, a valid plumbing permit or a completed
application for a plumbing permit, including the site evaluation approved by the Plumbing
Inspector, shall be submitted whenever the nature of the proposed structure would require the
installation of a subsurface sewage disposal system.
D. Procedure for Administering Permits
Within 35 days of the date of receiving written application, the Planning board or Code enforcement
Officer, as indicated in Section 14, shall notify the applicant in writing either that the application is a
complete application, or, if the application is incomplete, that specified additional material is needed
to make the application complete. The Planning Board or the Code Enforcement Officer, as
appropriate shall approve, approve with conditions, or deny all permit applications in writing within
35 days of receiving a completed application. However, if the Planning board has a waiting list of
applications, a decision on the application shall occur within 35 days after the first available date on
the Planning Board's agenda following receipt of the completed application, or within 35 days of the
( public hearing, if the proposed use or structure is found to be in conformance with the purposes and
28
provisions of this Ordinance.
The applicant shall have the burden of proving that the proposed land use activity is in conformity
with the purposes and provisions of this Ordinance.
After the submission of a complete application to the Planning Board, the Board shall approve an
application or approve it with conditions if it makes a positive finding based on the information
presented that the proposed use:
1. Will maintain safe and healthful conditions;
2. Will not result in water pollution, erosion, or sedimentation to surface waters;
3. Will adequately provide for the disposal of all wastewater;
4. Will not have an adverse impact on spawning grounds, fish, aquatic life, bird or other
wildlife habitat;
5. Will conserve shore cover and visual, as well as actual, points of access to inland and
coastal waters;
6. Will protect archaeological and historic resources as designated in the comprehensive plan;
7. Will not adversely affect existing commercial fishing or maritime activities in a Commercial
Fisheries/Maritime Activities district;
8. Will avoid problems associated with flood plain development and use; and
9. Is in conformance with the provisions of Section 15, Land Use Standards.
If a permit is either denied or approved with conditions, the reasons as well as conditions shall be
stated in writing. No approval shall be granted for an application involving a structure if the structure
would be located in an unapproved subdivision or would violate any other local ordinance or
regulation or any State law which the municipality is responsible for enforcing.
E. Special Exceptions
In addition to the criteria specified in Section 16.D. above, the Planning Board may approve a permit
for a single family residential structure in a Resource Protection District provided that the applicant
demonstrates that all of the following conditions are met:
1. There is no location on the property, other than a location within the Resource Protection
District, where the structure can be built.
. 2. The lot on which the structure is proposed is undeveloped and was established and
recorded in the registry of deeds of the county in which the lot is located before the
adoption of the Resource Protection District.
3. The proposed location of all buildings, sewage disposal systems and other improvements
are:
a. Located on natural ground slopes of less than 20%; and
b. Located outside the floodway of the 100-year floodplain along rivers and
artificially formed great ponds along rivers and outside the velocity zone in
areas subject to tides, based on detailed flood insurance studies and as
( delineated on the Federal Emergency Management Agency's Flood Boundary
29
and Floodway Maps and Flood Insurance Rate Maps; all buildings, including
basements, are elevated at least one foot above the 100-year floodplain
elevation; and the development is otherwise in compliance with any applicable
municipal floodplain ordinance.
If the floodway is not shown on the Federal Emergency Management Agency
Maps, it is deemed to be 1/2 the width of the 100-year floodplain.
4. The total ground-floor area of all principal and accessory structures is limited to a
maximum of 1,500 square feet.
5. All structures, except functionally water-dependent structures, are set back from the
normal high-water line or upland edge of a wetland to the greatest practical extent, but not
less than 75 feet. In determining the greatest practical extent, the planning board shall
consider the depth of the lot, the slope of the land, the potential for soil erosion, the type
and amount of vegetation to be removed, the proposed building site's elevation in regard to
the floodplain, and its proximity to moderate-value and high-value wetlands.
F. Expiration of Permit
Following the issuance of a permit, if no substantial start is made in construction or in the use of the
property within one year of the date of the permit, the permit shall lapse and become void.
G. Installation of Public Utility Service
No public utility, water district, sanitary district or any utility company of any kind may install
services to any new structure located in the shoreland zone unless written authorization attesting to the
validity and currency of all local permits required under this or any previous Ordinance, has been
issued by the appropriate municipal officials. Following installation of service, the company or
district shall forward the written authorization to the municipal officials, indicating that installation
has been completed.
H. Appeals
1. Powers and Duties of the Board of Appeals
The Board of Appeals shall have the following powers:
a. Administrative Appeals: To hear and decide appeals where it is alleged that there is an
error in any order, requirement, decision, or determination made by, or failure to act by,
the Code Enforcement Officer or Planning Board in the administration of this Ordinance.
b. Variance Appeals: To authorize variances upon appeal, within the limitations set forth in
this Ordinance.
2. Variance Appeals
é Variances may be permitted only under the following conditions:
30
a. Variances may be granted only from dimensional requirements including but not limited
to, lot width, structure height, percent of lot coverage, and setback requirements.
b. Variances shall not be granted for establishment of any uses otherwise prohibited by this
Ordinance.
c. The Board shall not grant a variance unless it finds that:
(1)The proposed structure or use would meet the provisions of Section 15 except for
the specific provision which has created the non-conformity and from which relief is
sought; and
(2)The strict application of the terms of this Ordinance would result in undue hardship.
The term "undue hardship" shall mean:
(i) That the land in question cannot yield a reasonable return unless a variance is
granted;
(ii) That the need for a variance is due to the unique circumstances of the property
and not to the general conditions in the neighborhood;
(iii) That the granting of a variance will not alter the essential character of the
locality; and
(iv) That the hardship is not the result of action taken by the applicant or a prior
owner.
d. The Board of Appeals may grant a variance to a property owner for the purpose of making that
property accessible to a person with a disability who is living on the property. The board shall
restrict any variance granted under this subsection solely to the installation of equipment or the
construction of structures necessary for access to or egress from the property by the person with
the disability. The board may impose conditions on the variance, including limiting the
variance to the duration of the disability or to the time that the person with the disability lives
on the property. The term "structures necessary for access to or egress from the property" shall
include railing, wall or roof systems necessary for the safety or effectiveness of the structure.
'@. The Board of Appeals shall limit any variances granted as strictly as possible in order to insure
conformance with the purposes and provisions of this Ordinance to the greatest extent possible,
and in doing so may impose such conditions to a variance as it deems necessary. The party
receiving the variance shall comply with any conditions imposed.
f. Acopy of all variances granted by the Board of Appeals shall be submitted to the Department of
Environmental Protection within fourteen (14) days of the decision.
(
31
3. Appeal Procedure
a. Making an Appeal
(1) An administrative or variance appeal may be taken to the Board of Appeals by an aggrieved
; party from any decision of the Code Enforcement Officer or the Planning Board. Such
appeal shall be taken within thirty GQ) days of the date of the decision appealed from, and
not otherwise, except that the Board, upon a showing of good cause, may waive the thirty
(30) day requirement.
(2) Such appeal shall be made by filing with the Board of Appeals a written notice of appeal
which includes:
Gi) A concise written statement indicating what relief is requested and why it should be granted.
(ii) A sketch drawn to scale showing lot lines, location of existing buildings and structures and
other physical features of the lot pertinent to the relief sought.
(3) Upon being notified of an appeal, the Code Enforcement Officer or Planning Board, as
appropriate, shall transmit to the Board of Appeals all of the papers constituting the record of
the decision appealed from.
(4) The Board of Appeals shall hold a public hearing on the appeal within thirty-five (35) days of
its receipt of an appeal request.
b. Decision by Board of Appeals
(1) A majority of the board shall constitute a quorum for the purpose of deciding an appeal. A
member who abstains shall not be counted in determining whether a quorum exists.
(2) The concurring vote of a majority of the members of the Board of Appeals present and voting
Shall be necessary to reverse an order, requirement, decision, or determination of the Code
Enforcement Officer or Planning Board, or to decide in favor of the applicant on any matter
on which it is required to decide under this Ordinance, or to affect any variation in the
application of this Ordinance from its stated terms. The board may reverse the decision, or
failure to act, of the Code Enforcement Officer or Planning Board only upon a finding that
the decision, or failure to act, was clearly contrary to specific provisions of this Ordinance.
(3) The person filing the appeal shall have the burden of proof.
(4) The Board shall decide all appeals within thirty five (35) days after the close of the
hearing, and shall issue a written decision on all appeals.
(5) All decisions shall become a part of the record and shall include a statement of findings and
conclusions as well as the reasons or basis therefor, and the appropriate order, relief or
denial thereof.
| 32
4. Appeal to Superior Court
Any aggrieved party who participated as a party during the proceedings before the Board of
Appeals may take an appeal to Superior Court in accordance with State laws within forty-five
(45) days from the date of any decision of the Board of Appeals.
5. Reconsideration
The Board of Appeals may reconsider any decision within thirty (30) days of its prior decision.
The Board may conduct additional hearings and receive additional evidence and testimony.
L Enforcement
1. Nuisances
Any violation of this Ordinance shall be deemed to be a nuisance.
2. Code Enforcement Officer
a. It shall be the duty of the Code Enforcement Officer to enforce the provisions of this
Ordinance. If the Code Enforcement Officer shall find that any provision of this Ordinance
is being violated, he or she shall notify in writing the person responsible for such violation,
indicating the nature of the violation and ordering the action necessary to correct it, including
discontinuance of illegal use of land, buildings or structures, or work being done, removal of
illegal buildings or structures, and abatement of nuisance conditions. A copy of such notices
shall be submitted to the municipal officers and be maintained as a permanent record.
b. The Code Enforcement Officer shall conduct on-site inspections to insure compliance with all
applicable laws and conditions attached to permit approvals. The Code Enforcement Officer
shall also investigate all complaints of alleged violations of this Ordinance.
c. The Code Enforcement Officer shall keep a complete record of all essential transactions of
the office, including applications submitted, permits granted or denied, variances granted or
denied, revocation actions, revocation of permits, appeals, court actions, violations
investigated, violations found, and fees collected. On a biennial basis, a summary of this
record shall be submitted to the Director of the Bureau of Land Quality Control within the
Department of Environmental Protection.
3. Legal Actions
When the above action does not result in the correction or abatement of the violation or nuisance
condition, the Municipal Officers, upon notice from the Code Enforcement Officer, are hereby
directed to institute any and all actions and proceedings, either legal or equitable, including
seeking injunctions of violations and the imposition of fines, that may be appropriate or
necessary to enforce the provisions of this Ordinance in the name of the municipality. The
municipal officers, or their authorized agent, are hereby authorized to enter into administrative
consent agreements for the purpose of eliminating violations of this Ordinance and recovering
fines without Court action. Such agreements shall not allow an illegal structure or use to
33
continue unless there is clear and convincing evidence that the illegal structure or use was
constructed or conducted as a direct result of erroneous advice given by an authorized municipal
official and there is no evidence that the owner acted in bad faith, or unless the removal of the
structure or use will result in a threat or hazard to public health and safety or will result in
substantial environmental damage.
4. Fines
Any person, including but not limited to a landowner, a landowner's agent or a contractor, who
orders or conducts any activity in violation of this Ordinance shall be penalized in accordance
with Title 30-A, Maine Revised Statutes Annotated, Subsection 4452.
NOTE: Current penalties include fines of not less than $100 nor more than $2500 per violation for each
day that the violation continues.
Section 17. Definitions
Accessory structure or use - a use or structure which is incidental and subordinate to the principal use or
structure. Accessory uses, when aggregated shall not subordinate the principal use of the lot. A deck
or similar extension of the principal structure or a garage attached to the principal structure by a roof
or a common wall is considered part of the principal structure.
Agriculture - the production, keeping or maintenance for sale or lease, of plants and/or animals, including
but not limited to: forages and sod crops; grains and seed crops; dairy animals and dairy products;
poultry and poultry products; livestock; fruits and vegetables; and ornamental and green house
products. Agriculture does not include forest management and timber harvesting activities.
Aggrieved party - an owner of land whose property is directly or indirectly affected by the granting or
denial of a permit or variance under this Ordinance; a person whose land abuts land for which a
permit or variance has been granted; or any other person or group of persons who have suffered
partticularized injury as a result of the granting or denial of such permit or variance.
Aquaculture - the growing or propagation of harvestable freshwater, estuarine, or marine plant or animal
species.
Basal Area - the area of cross-section of a tree stem at 4 1/2 feet above ground level and inclusive of bark.
Boat Launching Facility - a facility designed primarily for the launching and landing of watercraft, and
which may include an access ramp, docking area, and parking spaces for vehicles and trailers.
'Campground - any area or tract of land to accommodate two (2) or more parties in temporary living
quarters, including, but not limited to tents, recreational vehicles or other shelters.
Coastal wetland - all tidal and subtidal lands; all lands below any identifiable debris line left by tidal
action; all lands with vegetation present that is tolerant of salt water and occurs primarily in a salt
water or estuarine habitat; and any swamp, marsh, bog, beach, flat or other contiguous low land
which is subject to tidal action during the maximum spring tide level as identified in tide tables
f published by the National Ocean Service. Coastal wetlands may include portions of coastal sand
dunes. .
34
Commercial use - the use of lands, buildings, or structures, other than a "home occupation," defined
below, the intent and result of which activity is the production of income from the buying and selling
of goods and/or services, exclusive of rental of residential buildings and/or dwelling units.
Dimensional requirements - numerical standards relating to spatial relationships including but not limited
to setback, lot area, shore frontage and height.
Disability - any disability, infirmity, malformation, disfigurement, congenital defect or mental condition
caused by bodily injury, accident, disease, birth defect, environmental conditions or illness; and also
includes the physical or mental condition of a person which constitutes a substantial handicap as
determined by a physician or in the case of mental handicap, by a psychiatrist or psychologist, as well
as any other health or sensory impairment which requires special education, vocational rehabilitation
or related services.
| Driveway - a vehicular access-way less than five hundred (500) feet in length serving two lots or less.
Emergency operations - operations conducted for the public health, safety or general welfare, such as
protection of resources from immediate destruction or loss, law enforcement, and operations to rescue
human beings, property and livestock from the threat of destruction or injury.
Essential services - gas, electrical or communication facilities; steam, fuel, electric power or water
transmission or distribution lines, towers and related equipment; telephone cables or lines, poles and
related equipment; gas, oil, water, slurry or other similar pipelines; municipal sewage lines, collection
or supply systems; and associated storage tanks. Such systems may include towers, poles, wires,
mains, drains, pipes, conduits, cables, fire alarms and police call boxes, traffic signals, hydrants and
} similar accessories, but shall not include service drops or buildings which are necessary for the
furnishing of such services.
Expansion of a structure - an increase in the floor area or volume of a structure, including all extensions
such as, but not limited to attached: decks, garages, porches and greenhouses.
Expansion of use - the addition of one or more months to a use's operating season; or the use of more floor
area or ground area devoted to a particular use.
Family - one or more persons occupying a premises and living as a single housekeeping unit.
Floodway - the channel of a river or other watercourse and adjacent land areas that must be reserved in
order to discharge the 100-year flood without cumulatively increasing the water surface elevation by
more than one foot in height.
Floor area - the sum of the horizontal areas of the floor(s) of a structure enclosed by exterior walls, plus
the horizontal area of any unenclosed portions of a structure such as porches and decks.
Forest management activities - timber cruising and other forest resource evaluation activities, pesticide or
fertilizer application, management planning activities, timber stand improvement, pruning,
regeneration of forest stands, and other similar or associated activities, exclusive of timber harvesting
and the construction, creation or maintenance of roads.
( Forested wetland - a freshwater wetland dominated by woody vegetation that is six (6) meters tall or taller.
35
Foundation - the supporting substructure of a building or other structure including but not limited to
basements, slabs, sills, posts or frostwalls.
Freshwater wetland - freshwater swamps, marshes, bogs and similar areas, other than forested wetlands,
which are:
1. Of ten or more contiguous acres; or of less than 10 contiguous acres and adjacent to a surface
water body, excluding any river, stream or brook, such that in a natural state, the combined surface
area is in excess of 10 acres; and
2. Inundated or saturated by surface or ground water at a frequency and for a duration sufficient to
support, and which under normal circumstances do support, a prevalence of wetland vegetation
typically adapted for life in saturated soils.
Freshwater wetlands may contain small stream channels or inclusions of land that do not conform to
the criteria of this definition.
Functionally water-dependent uses - those uses that require, for their primary purpose, location on
submerged lands or that require direct access to, or location in, coastal and inland waters and which
cannot be located away from these waters. The uses include, but are not limited to commercial and
recreational fishing and boating facilities, finfish and shellfish processing, fish storage and retail and
wholesale fish marketing facilities, waterfront dock and port facilities, shipyards and boat building
facilities, marinas, navigation aides, basins and channels, industrial uses dependent upon water-borne
transportation or requiring large volumes of cooling or processing water and which cannot reasonably
be located or operated at an inland site, and uses which primarily provide general public access to
marine or tidal waters.
Great pond - any inland body of water which in a natural state has a surface area in excess of ten acres, and
any inland body of water artificially formed or increased which has a surface area in excess of thirty
(30) acres except for the purposes of this Ordinance, where the artificially formed or increased inland
body of water is completely surrounded by land held by a single owner.
Great pond classified GPA - any great pond classified GPA, pursuant to Title 38 Article 4-A Section
465-A. This classification includes some, but not all impoundments of rivers that are defined as great
ponds.
_ Height of a structure - the vertical distance between the mean original grade at the downhill side of the
structure and the highest point of the structure, excluding chimneys, steeples, antennas, and similar
appurtenances which have no floor area.
Home occupation - an occupation or profession which is customarily conducted on or in a residential
structure or property and which is 1) clearly incidental to and compatible with the residential use of
the property and surrounding residential uses; and 2) which employs no more than two (2) persons
other than family members residing in the home.
Individual private campsite - an area of land which is not associated with a campground, but which is
developed for repeated camping by only one group not to exceed ten (10) individuals and which
' involves site improvements which may include but not be limited to gravel pads, parking areas, fire
¢ places, or tent platforms.
36
'dustrial - The assembling, fabrication, finishing, manufacturing, packaging or processing of goods, or the
extraction of minerals.
Lot area - The area of land enclosed within the boundary lines of a lot, minus land below the normal
. high-water line of a water body or upland edge of a wetland and areas beneath roads serving more
than two lots.
Marina - a business establishment having frontage on navigable water and, as its principal use, providing
for hire offshore moorings or docking facilities for boats, and which may also provide accessory
services such as boat and'related sales, boat repair and construction, indoor and outdoor storage of
boats and marine equipment, boat and tackle shops and marine fuel service facilities.
Market value - the estimated price a property will bring in the open market and under prevailing market
conditions in a sale between a willing seller and a willing buyer, both conversant with the property
and with prevailing general price levels.
Minimum lot width - the closest distance between the side lot lines of a lot.
Mineral exploration - hand sampling, test boring, or other methods of determining the nature or extent of
mineral resources which create minimal disturbance to the land and which include reasonable
measures to restore the land to its original condition.
Mineral extraction - any operation within any twelve (12) month period which removes more than one
hundred (100) cubic yards of soil, topsoil, loam, sand, gravel, clay, rock, peat, or other like material
from its natural location and to transport the product removed, away from the extraction site.
Multi-unit residential - a residential structure containing three (3) or more residential dwelling units.
Non-conforming lot - a single lot of record which, at the effective date of adoption or amendment of this
Ordinance, does not meet the area, frontage, or width requirements of the district in which it is
Non-conforming structure - a structure which does not meet any one or more of the following dimensional
requirements; setback, height, or lot coverage, but which is allowed solely because it was in lawful
existence at the time this Ordinance or subsequent amendments took effect.
Non-conforming use - use of buildings, structures, premises, land or parts thereof which is not permitted in
the district in which it is situated, but which is allowed to remain solely because it was in lawful
existence at the time this Ordinance or subsequent amendments took effect.
Normal high-water line - that line which is apparent from visible markings, changes in the character of
soils due to prolonged action of the water or changes in vegetation, and which distinguishes between
predominantly aquatic and predominantly terrestrial land. In the case of wetlands adjacent to rivers
and great ponds, the normal high-water line is the upland edge of the wetland, and not the edge of the
open water.
37
-_ Riprap - rocks, irregularly shaped, and at least six (6) inches in diameter, used for erosion control and soil
stabilization, typically used on ground slopes of two (2) units horizontal to one (1) unit vertical or
less.
River - a free-flowing body of water including its associated flood plain wetlands from that point at which it
provides drainage for a watershed of twenty five (25) square miles to its mouth.
Road - a route or track consisting of a bed of exposed mineral soil, gravel, asphalt, or other surfacing
material constructed for or created by the repeated passage of motorized vehicles.
Salt marsh - Areas along coastal waters (most often along coastal bays) which support salt tolerant species,
and where at average high tide during the growing season, the soil is regularly inundated by tidal
waters. The predominant species is saltmarsh cordgrass (Spartina alterniflora). More open areas
often support widgeon grass, eelgrass, and Sago pondweed.
Salt meadow - Areas which support salt tolerant plant species bordering the landward side of salt marshes |
or open coastal water, where the soil is saturated during the growing season but which is rarely
inundated by tidal water. Indigenous plant species include salt meadow cordgrass (Spartina patens)
and black rush; common threesquare occurs in fresher areas.
Service drop ~ any utility line extension which does not cross or run beneath any portion of a water body
provided that:
1. in the case of electric service
a. the placement of wires and/or the installation of utility poles is located entirely upon the
premises of the customer requesting service or upon a roadway right-of-way; and
b. the total length of the extension is less than one thousand (1,000) feet.
2. in the case of telephone service
a. the extension, regardless of length, will be made by the installation of telephone wires to
existing utility poles, or , ,
b. the extension requiring the installation of new utility poles or placement underground is less
than one thousand (1,000) feet in length.
Setback - the nearest horizontal distance from the normal high-water line to the nearest part of a structure,
road, parking space or other regulated object or area.
Shore frontage - the length of a lot bordering on a water body measured in a straight line between the
intersections of the lot lines with the shoreline at normal high-water elevation.
Shoreland zone - the land area located within two hundred and fifty (250) feet, horizontal distance, of the |
normal high-water line of any great pond, river, or saltwater body; within 250 feet of the upland edge
of a coastal or freshwater wetland; or within seventy-five (75) feet of the normal high-water line of a
stream.
39
Person - an individual, corporation, governmental agency, municipality, trust, estate, partnership,
association, two or more individuals having a joint or common interest, or other legal entity.
Piers, docks, wharfs, bridges and other structures and uses extending over or beyond the normal
high-water line or within a wetland-
Temporary: Structures which remain in or over the water for less than seven (7) months in any period of
twelve (12) consecutive months.
Permanent: Structures which remain in or over the water for seven (7) months or more in any period of
twelve (12) consecutive months.
Principal structure - a building other than one which is used for purposes wholly incidental or accessory
to the use of another building or use on the same premises.
Principal use - a use other than one which is wholly incidental or accessory to another use on the same
premises.
Public facility - any facility, including, but not limited to, buildings, property, recreation areas, and roads,
which are owned, leased, or otherwise operated, or funded by a governmental body or public entity.
Recent flood plain soils - the following soil series as described and identified by the National Cooperative
Soil Survey:
Fryeburg Hadley Limerick
Lovewell Medomak Ondawa
Alluvial Cornish Charles
Podunk Rumney Saco
Suncook Sunday Winooski
Recreational facility - a place designed and equipped for the conduct of sports, leisure time activities, and
other customary and usual recreational activities, excluding boat launching facilities.
Recreational vehicle - a vehicle or an attachment to a vehicle designed to be towed, and designed for
temporary sleeping or living quarters for one or more persons, and which may include a pick-up
camper, travel trailer, tent trailer, camp trailer, and motor home. In order to be considered as a
vehicle and not as a structure, the unit must remain with its tires on the ground, and must be
registered with the State Division of Motor Vehicles.
Replacement system - a system intended to replace: 1.) an existing system which is either malfunctioning
or being upgraded with no significant change of design flow or use of the structure, or 2.) any
existing overboard wastewater discharge.
Residual basal area - the sum of the basal area of trees remaining on a harvested site.
Residential dwelling unit - a room or group of rooms designed and equipped exclusively for use as |
permanent, seasonal, or temporary living quarters for only one family. The term shall include mobile |
homes, but not recreational vehicles. |
38
Riprap - rocks, irregularly shaped, and at least six (6) inches in diameter, used for erosion control and soil
stabilization, typically used on ground slopes of two (2) units Horizontal to one (1) unit vertical or
less.
River - a free-flowing body of water including its associated flood plain wetlands from that point at which it
provides drainage for a watershed of twenty five (25) square miles to its mouth. :
Road - a route or track consisting of a bed of exposed mineral soil, gravel, asphalt, or other surfacing
material constructed for or created by the repeated passage of motorized vehicles.
Salt marsh - Areas along coastal waters (most often along coastal bays) which support salt tolerant species,
and where at average high tide during the growing season, the soil is regularly inundated by tidal
waters. The predominant species is saltmarsh cordgrass (Spartina alterniflora). More open areas
often support widgeon grass, eelgrass, and Sago pondweed.
Salt meadow - Areas which support salt tolerant plant species bordering the landward side of salt marshes .
or open coastal water, where the soil is saturated during the growing season but which is rarely
inundated by tidal water. Indigenous plant species include salt meadow cordgrass (Spartina patens)
and black rush; common threesquare occurs in fresher areas.
Service drop - any utility line extension which does not cross or run beneath any portion of a water body
provided that:
1. im the case of electric service
a. the placement of wires and/or the installation of utility poles is located entirely upon the
premises of the customer requesting service or upon a roadway right-of-way; and
b. the total length of the extension is less than one thousand (1,000) feet.
2. in the case of telephone service
a. the extension, regardless of length, will be made by the installation of telephone wires to
existing utility poles, or ; :
b. the extension requiring the installation of new utility poles or placement underground is less
than one thousand (1,000) feet in length.
Setback - the nearest horizontal distance from the normal high-water line to the nearest part of a structure,
road, parking space or other regulated object or area.
Shore frontage - the length of a lot bordering on a water body measured in a straight line between the
intersections of the lot lines with the shoreline at normal high-water elevation.
Shoreland zone - the land area located within two hundred and fifty (250) feet, horizontal distance, of the
normal high-water line of any great pond, river, or saltwater body; within 250 feet of the upland edge
of a coastal or freshwater wetland; or within seventy-five (75) feet of the normal high-water line of a
stream.
39
Significant River Segments - See Title 38 MRSA Sec. 437.
Stream - a free-flowing body of water from the outlet of a great pond or the confluence of two (2) perennial
streams as depicted on the most recent edition of a United States Geological Survey 7.5 minute series
topographic map, or if not available, a 15-minute series topographic map, to the point where the body
of water becomes a river or flows to another water body or wetland within the shoreland area.
Structure - anything built for the support, shelter or enclosure of persons, animals, goods or property of
any kind, together with anything constructed or erected with a fixed location on or in the ground,
exclusive of fences. The term includes structures temporarily or permanently located, such as decks
and satellite dishes.
Substantial start - completion of thirty (30) percent of a permitted structure or use measured as a
percentage of estimated total cost.
Subsurface sewage disposal system - a collection of treatment tank(s), disposal area(s), holding tank(s) and
pond(s), surface spray system(s), cesspool(s), well(s), surface ditch(es), alternative toilet(s), or other
devices and associated piping designed to function as a unit for the purpose of disposing of wastes or
wastewater on or beneath the surface of the earth. The term shall not include any wastewater
discharge system licensed under 38 MRSA Section 414, any surface wastewater disposal system
licensed under 38 MRSA Section 413 Subsection 1-A, or any public sewer. The term shall not
include a wastewater disposal system designed to treat wastewater which is in whole or in part
hazardous waste as defined in 38 MRSA Chapter 13, subchapter 1. :
Sustained slope - a change in elevation where the referenced percent grade is substantially maintained or
exceeded throughout the measured area.
Timber harvesting - the cutting and removal of trees from their growing site, and the attendant operation of
cutting and skidding machinery but not the construction or creation of roads. Timber harvesting does
not include the clearing of land for approved construction.
Tributary stream - a channel between defined banks created by the action of surface water, whether
intermittent or perennial, and which is characterized by the lack of upland vegetation or presence of
aquatic vegetation and by the presence of a bed devoid of topsoil containing waterborne deposits on
exposed soil, parent material or bedrock, and which flows to a water body or wetland as defined.
This definition does not include the term "stream" as defined elsewhere in this Ordinance, and only
applies to that portion of the tributary stream located within the shoreland zone of the receiving water
body or wetland.
Upland edge - the boundary between upland and wetland.
Vegetation - all live trees, shrubs, ground cover, and other plants including without limitation, trees both
over and under 4 inches in diameter, measured at 4 1/2 above ground level.
Velocity zone - an area of special flood hazard extending from offshore to the inland limit of the primary
é frontal dune along an open coast and any other area subject to high velocity wave action from storms
or seismic sources.
40
Volume of a structure - the volume of all portions of a structure enclosed by roof and fixed exterior walls
as measured from the exterior faces of these walls and roof.
Water body - any great pond, river, stream or tidal area.
Water crossing - any project extending from one bank to the opposite bank of a river or stream, whether
under, through, or over the water course. Such projects include but may not be limited to roads,
fords, bridges, culverts, water lines, sewer lines, and cables as well as maintenance work on these
crossings.
Wetland - a freshwater or coastal wetland.
Wetlands associated with great ponds and rivers - wetlands contiguous with or adjacent to a great pond or
river, and which during normal high water, are connected by surface water to the great pond or river.
Also included are wetlands which are separated from the great pond or river by a berm, causeway, or
similar feature less than 100 feet in width, and which have a surface elevation at or below the normal
, high water line of the great pond or river. Wetlands associated with great ponds or rivers are
considered to be part of that great pond or river.
41