| single detached charge |
$17,747 per dwelling unit/lot (Nov 3, 2025) |
DCC rates table: "Single Family Units... $17,747... per dwelling unit/lot"; "new DCC rates came into effect November 3, 2025" |
| apartment charge |
Apartment 5+ storeys: $10,304; other apartments (<5 storeys, suites, small-scale): $12,593 per dwelling unit (Nov 3, 2025) |
DCC rates table: "Single Family Units... $17,747... per dwelling unit/lot"; "new DCC rates came into effect November 3, 2025" |
| non residential charge |
Commercial: $148.26/m2 gross floor area; Industrial: $110.37/m2 gross floor area; Not-for-Profit Rental: no charges (Nov 3, 2025) |
DCC rates table: "Commercial... $148.26... Industrial... $110.37... Not-for-Profit Rental... no charges... per m2 gross floor area" |
| services covered |
Transportation, parks/parkland acquisition and improvement, fire services, water, sanitary sewers, storm drainage, solid waste & recycling |
"What services do DCCs help pay for?" section listing Transportation, Parks, Protection Services, Water, Sanitary Sewers, Storm Drainage, Solid Waste & Recycling |
| exemptions |
Not-for-Profit Rental: no charges; 'several projects that are exempt from paying DCCs, along with other exemptions required under the Local Government Act' |
DCC rates table: "Not-for-Profit Rental... no charges"; "several projects that are exempt from paying DCCs, along with other exemptions required under the Local Government Act" |
| payment timing |
At building permit issuance or subdivision approval; installment option (effective Jan 1, 2026): 25% due at permit/subdivision approval, 75% deferred until 4 years after permit or 15 business days after all occupancy permits issued (whichever first); security (irrevocable letter of credit or on-demand surety bond) required for deferral |
"DCCs are fees collected from developers at the time a building permit is issued or a subdivision is approved"; "New Rules for Paying DCCs in Installments" section |