In the Township of Oro-Medonte, Ontario, building permit rules are set by Oro-Medonte Fees and Charges By-law 2025-129, verified 2026-10-26. Permit required for: construction or demolition of a building. Permit fees: Permit Fee = Service Index (SI) x Total gross floor area (A); minimum fee per current-year rate unless flat rate. Administered by: Chief Building Official.

Oro-Medonte Fees and Charges By-law 2025-129 adopted bylaw
permit required for construction or demolition of a building Schedule "B", s. 5.2
fee basis Permit Fee = Service Index (SI) x Total gross floor area (A); minimum fee per current-year rate unless flat rate Schedule "B", s. 1
authority Chief Building Official Schedule "B", s. 1
fine range $25.00 administrative penalty s. 7
scout note

Oro-Medonte's Fees and Charges By-law 2025-129, Schedule B: building permit fee = service index per ft2 x gross floor area (Table 2.1, yearly rates 2025-2031, e.g. plumbing 0-6 fixtures $108.11 in 2026). Work begun without a permit pays double. Fees rise 2.5% each January; amendments 2026-029 and 2026-049 may change Schedule B; check current schedule.

Building By-law

Township's Building By-law under the Building Code Act, 1992, linked as 'Building By-law' from the Building and Renovating page. Hosted in a JS-rendered Laserfiche Cloud WebLink portal; automated fetch returns only an app shell, so permit classes/fees/date could not be confirmed.

Fees and Charges By-law No. 2024-134 (Office Consolidation Aug 22, 2025)

Superseded 2024-134 fee schedule, retained for provenance only. By-law 2025-129 expressly repeals it.