In the Municipality of North Perth, Ontario, development charges & levies rules are set by 2026 Development Charges information sheet (By-laws 53-2024 & 74-2024) and 2 other bylaws, verified 2026-10-23. Charge per single-detached home: $23,724 per dwelling unit (Municipal Wide Total, Jan 1–Dec 31 2026); additional Urban Area-Specific and NEMP Area-Specific charges may apply. Non-residential charge: $48.44/m² (Municipal Wide Total, Jan 1–Dec 31 2026); Non-Residential NEMP Area-Specific Total: $159.43/m²; based on Gross Floor Area. Exemptions: Municipality, County of Perth or local board; board of education; place of worship; public hospitals; full list per Development Charges Act and by-law.

2026 Development Charges information sheet (By-laws 53-2024 & 74-2024) adopted bylaw
single detached charge $23,724 per dwelling unit (Municipal Wide Total, Jan 1–Dec 31 2026); additional Urban Area-Specific and NEMP Area-Specific charges may apply "Effective January 1, 2026 to December 31, 2026" / "Municipal Wide Total" row, Residential 2026 DC Rates table
apartment charge Apartments with 2+ bedrooms: $13,699/unit; Apartments with 1 & less bedrooms: $9,184/unit (Municipal Wide Total, Jan 1–Dec 31 2026); additional area-specific and utility charges may apply "Effective January 1, 2026 to December 31, 2026" / "Municipal Wide Total" row, Residential 2026 DC Rates table
non residential charge $48.44/m² (Municipal Wide Total, Jan 1–Dec 31 2026); Non-Residential NEMP Area-Specific Total: $159.43/m²; based on Gross Floor Area "Effective January 1, 2026 to December 31, 2026" / "Municipal Wide Total" and "Area Specific Total" rows, Non-Residential 2026 DC Rates table; "Non-Residential development charge rates are based on Gross Floor Area space ($/m2)"
services covered Library, Parks & Rec, Child Care Services, Administration, Fire Protection, Police, Public Works, Roads & Related, Stormwater, Water, Wastewater Services Component column headings, Residential and Non-Residential 2026 DC Rates tables
exemptions Municipality, County of Perth or local board; board of education; place of worship; public hospitals; full list per Development Charges Act and by-law "Exemptions provided in the By-law and/or the Act include:" — Exemptions and Incentives section
payment timing All residential and certain institutional: collected post first building permit issuance per s. 26.1 of the Development Charges Act. All other types: collected on date first building permit is issued. For Site Plan/Zoning By-law amendment developments: DCs calculated at complete application receipt, frozen for up to 18 months from approval; lower of frozen rate or current rate applies if permit issued within frozen period "DCs are collected post first building permit issuance in accordance with section 26.1 of the Development Charges Act" / "DCs are calculated on the date the first building permit is issued" / "frozen from the date of application approval for a period of up to eighteen months"
indexing expiry Indexed annually commencing January 1, 2025 without amendment to the by-laws, in accordance with the prescribed index in the Act; no expiry date stated "indexed annually commencing January 1, 2025, without amendment to the by-laws, in accordance with the prescribed index in the Act"
scout note

rates page: 2026. 2026: municipal-wide total $23,724 per single/semi-detached; $13,699 per apartment 2+ bedrooms; $9,184 apartment 1 bedroom or less; urban water $2,392 and wastewater $6,428 extra per single where available. Effective Jan 1-Dec 31 2026.

Development Charges By-law No. 53-2024 (North East Master Plan Area) adopted bylaw
services covered Northeast Master Plan Area: water services, wastewater services, storm water drainage and control, and services related to a highway. s. 2.1
exemptions Additional residential units; affordable/non-profit housing; industrial expansion; agricultural uses/farm buildings; places of worship/cemeteries; public hospitals; temporary buildings; wind turbines; rental housing bedroom-based reductions. ss. 3.5–3.7; s. 3.10
payment timing Calculated, payable, and collected upon issuance of a building permit; agreements may provide for payment before or after. s. 3.12; s. 3.14
indexing expiry Adjusted annually commencing Jan 1, 2025 per prescribed index; expires Aug 26, 2034 unless repealed earlier. s. 5.1; s. 10.1
scout note

Area-specific DC by-law for the North East Master Plan Area, passed Aug 26, 2024 (expires 2034), charged on top of municipal-wide DCs. 2026 rate: $26,648 per single/semi-detached; $159.43/m2 non-residential.

Development Charges By-law No. 74-2024 (Municipality of North Perth) adopted bylaw

Municipal-wide DC by-law repealing 78-2019; confirmed North Perth text. Rates indexed annually (see 2026 information sheet).

DC Background Study (Hemson, Oct 2024)

Background study supporting the 2024 DC by-laws.

North Perth Development Charges page

Municipality's DC page pointing to by-laws, background study and information sheets.

Machine-readable: development-charges.json · Official website: http://www.northperth.ca/ · Last verified 2026-10-23 · Development charges & levies across Ontario · Development charges & levies in other municipalities